JP6987624B2 - Pile construction method and pile construction management system - Google Patents

Pile construction method and pile construction management system Download PDF

Info

Publication number
JP6987624B2
JP6987624B2 JP2017231959A JP2017231959A JP6987624B2 JP 6987624 B2 JP6987624 B2 JP 6987624B2 JP 2017231959 A JP2017231959 A JP 2017231959A JP 2017231959 A JP2017231959 A JP 2017231959A JP 6987624 B2 JP6987624 B2 JP 6987624B2
Authority
JP
Japan
Prior art keywords
pile
support layer
length
layer data
pile length
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017231959A
Other languages
Japanese (ja)
Other versions
JP2019100082A (en
Inventor
瑞樹 林
悟 安藤
直宏 大西
宰 伊藤
謙司 杉浦
聡 尾本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2017231959A priority Critical patent/JP6987624B2/en
Publication of JP2019100082A publication Critical patent/JP2019100082A/en
Application granted granted Critical
Publication of JP6987624B2 publication Critical patent/JP6987624B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

本発明は、杭打ち対象地にて杭を建て込む杭打ち作業を行う杭施工方法及び杭施工管理システムに関する。 The present invention relates to a pile construction method and a pile construction management system for performing pile driving work for building piles at a pile driving target site.

上記の杭施工方法では、事前に、杭打ち対象地に対してボーリング調査等の地盤調査を実施し、その地盤調査で得られた多数の地盤調査地点の支持層深度情報から杭打ち対象地で想定される支持層の全貌を示す支持層データを作成し(例えば特許文献1参照)、その支持層データに基づいて杭打ち地点毎に杭長を設定している。そして、設定された杭長の杭を準備して杭打ち地点毎に建て込む杭打ち作業を行っている。 In the above pile construction method, a ground survey such as a boring survey is conducted in advance on the pile driving target site, and the support layer depth information of many ground survey points obtained by the ground survey is used to determine the pile driving target site. Support layer data showing the entire picture of the assumed support layer is created (see, for example, Patent Document 1), and the pile length is set for each pile driving point based on the support layer data. Then, piles with a set pile length are prepared and pile driving work is performed to build them at each pile driving point.

特開2012−37427号公報Japanese Unexamined Patent Publication No. 2012-37427

ところが、大規模な敷地に大量の杭を施工する場合等では、精度の高い支持層データを作成するために必要となる地盤調査地点数が多くなる。そのため、杭打ち作業前の地盤調査に要する期間や費用が嵩み、全体工期の長期化や高コスト化を招く不都合がある。 However, when a large number of piles are constructed on a large-scale site, the number of ground survey points required to create highly accurate support layer data increases. Therefore, the period and cost required for the ground survey before the pile driving work are increased, and there is an inconvenience that the entire construction period is lengthened and the cost is increased.

この実情に鑑み、本発明の主たる課題は、大規模な敷地に大量の杭を施工する場合等でも、地盤調査に要する期間や費用を抑えながら杭の施工を適切に行える杭施工方法及び杭施工管理システムを提供する点にある。 In view of this situation, the main problem of the present invention is a pile construction method and pile construction that can appropriately construct piles while suppressing the period and cost required for ground investigation even when a large number of piles are constructed on a large-scale site. The point is to provide a management system.

本発明の第1特徴構成は、地盤調査地点の支持層深度情報から杭打ち対象地で想定される支持層の全貌を示す支持層データを作成する支持層データ作成ステップと、
前記支持層データ作成ステップにて作成された前記支持層データに基づいて杭打ち地点毎に杭長を設定する杭長設定ステップと、
杭打ち作業にて逐次取得される杭打ち地点毎の杭の支持層到達深度情報を前記支持層深度情報として追加して前記支持層データを更新する支持層データ更新ステップと、
前記支持層データ更新ステップにて更新された前記支持層データに基づいて杭長を設定変更する杭長変更ステップとを備える点にある。
The first characteristic configuration of the present invention includes a support layer data creation step for creating support layer data showing the entire picture of the support layer assumed at the pile driving target site from the support layer depth information at the ground survey point.
A pile length setting step for setting a pile length for each pile driving point based on the support layer data created in the support layer data creation step, and a pile length setting step.
A support layer data update step for updating the support layer data by adding the support layer reach depth information of the pile for each pile driving point sequentially acquired in the pile driving operation as the support layer depth information , and
The point is to include a pile length changing step in which the pile length is set and changed based on the support layer data updated in the support layer data update step.

本構成によれば、支持層データ作成ステップにて地盤調査地点の支持層深度情報から支持層データを作成し、杭長設定ステップにて支持層データに基づいて杭打ち地点毎の杭長を設定して杭打ち作業を行うが、支持層データ更新ステップにて杭打ち作業にて逐次取得される支持層到達深度情報を支持層深度情報として追加して支持層データを更新する。
そのため、事前の地盤調査地点数が少なくて当初の支持層データの精度があまり高くなくても、杭打ち作業の進捗に連れて支持層データの精度を高めることができ、その精度を高めた支持層データに基づいて後続の杭打ち作業を行うことができる。
よって、大規模な敷地に大量の杭を施工する場合等でも、地盤調査地点数を極力少なくして地盤調査に要する期間や費用を抑えながら杭の施工を適切に行うことができる。
According to this configuration, the support layer data is created from the support layer depth information of the ground survey point in the support layer data creation step, and the pile length for each pile driving point is set based on the support layer data in the pile length setting step. Then, the pile driving work is performed, and the support layer data is updated by adding the support layer reach depth information sequentially acquired in the pile driving work in the support layer data update step as the support layer depth information.
Therefore, even if the number of ground survey points in advance is small and the accuracy of the initial support layer data is not very high, the accuracy of the support layer data can be improved as the pile driving work progresses, and the support with improved accuracy. Subsequent pile driving work can be performed based on the layer data.
Therefore, even when a large number of piles are to be constructed on a large-scale site, the number of ground survey points can be reduced as much as possible to appropriately construct the piles while suppressing the period and cost required for the ground survey.

更に、本構成によれば、支持層データ更新ステップにて更新された支持層データに基づいて杭打ち作業の途中で杭長を設定変更するので、その設定変更された杭長の杭を後続の杭打ち作業で使用し、後続の杭打ち作業の適切な実施を簡単・確実に行うことができる。 Further, according to this configuration, the pile length is set and changed during the pile driving operation based on the support layer data updated in the support layer data update step. It can be used in pile driving work, and the subsequent pile driving work can be carried out properly and reliably.

本発明の第特徴構成は、前記支持層データ更新ステップにて更新された前記支持層データに基づき、前記杭長設定ステップにて設定されている杭打ち地点毎の杭長の過不足状態を判定する杭長判定ステップを備え、
前記杭長変更ステップでは、前記杭長判定ステップでの判定結果に基づいて杭長を設定変更する点にある。
The second characteristic configuration of the present invention is based on the support layer data updated in the support layer data update step, and the excess / deficiency state of the pile length for each pile driving point set in the pile length setting step is set. Equipped with a pile length determination step to determine
In the pile length change step, the pile length is set and changed based on the determination result in the pile length determination step.

本構成によれば、支持層データ更新ステップにて更新された最新の精度の高い支持層データに基づき、杭長判定ステップにて現在設定されている杭打ち地点毎の杭長の過不足状態を適切に判定することができる。そして、その杭長判定ステップでの適切な判定結果に基づき、杭長変更ステップにて杭長を適切に設定変更することができる。 According to this configuration, based on the latest highly accurate support layer data updated in the support layer data update step, the excess / deficiency state of the pile length for each pile driving point currently set in the pile length determination step can be determined. It can be judged appropriately. Then, based on the appropriate determination result in the pile length determination step, the pile length can be appropriately set and changed in the pile length change step.

本発明の第特徴構成は、第特徴構成に記載の杭施工方法に用いられる杭施工管理システムであって、
前記支持層データ作成ステップにて作成された前記支持層データに基づいて杭打ち地点毎に杭長を自動設定する杭長設定部と、
杭打ち作業にて逐次取得される前記支持層到達深度情報が前記支持層深度情報として追加された場合に、前記支持層データを自動更新する支持層データ更新部と、
前記支持層データ更新部にて前記支持層データが更新された場合に、前記杭長設定部にて設定された杭打ち地点毎の杭長の過不足状態を自動判定する杭長判定部と、を備える点にある。
The third feature configuration of the present invention is a pile construction management system used in the pile construction method described in the second feature configuration.
A pile length setting unit that automatically sets the pile length for each pile driving point based on the support layer data created in the support layer data creation step, and a pile length setting unit.
A support layer data update unit that automatically updates the support layer data when the support layer reach depth information sequentially acquired in the pile driving operation is added as the support layer depth information.
When the support layer data is updated by the support layer data update unit, a pile length determination unit that automatically determines an excess or deficiency state of the pile length for each pile driving point set by the pile length setting unit, and a pile length determination unit. It is in the point of having.

本構成によれば、杭長設定ステップにおける杭長の設定、及び、支持層データ更新ステップにおける支持層データの更新、並びに、杭長判定ステップにおける杭長の判定を自動的に行うことができ、前述した杭施工方法による杭の施工を少ない手間で効率良く行うことができる。 According to this configuration, it is possible to automatically set the pile length in the pile length setting step, update the support layer data in the support layer data update step, and determine the pile length in the pile length determination step. It is possible to efficiently carry out pile construction by the above-mentioned pile construction method with little labor.

本発明の第特徴構成は、前記支持層データが、杭打ち対象地の支持層の全貌を表示部に三次元的に表示した支持層モデルである点にある。 The fourth characteristic configuration of the present invention is that the support layer data is a support layer model in which the entire support layer of the pile driving target site is three-dimensionally displayed on the display unit.

本構成によれば、支持層データ作成ステップにて作成された支持層データや支持層データ更新ステップにて更新された支持層データが支持層モデルとして表示部に表示されるので、支持層の状態を立体的に把握することができ、その立体的な支持層の把握に基づいて前述した杭施工方法による杭の施工を適切に行うことができる。 According to this configuration, the support layer data created in the support layer data creation step and the support layer data updated in the support layer data update step are displayed on the display unit as a support layer model, and thus the state of the support layer. Can be grasped three-dimensionally, and pile construction by the above-mentioned pile construction method can be appropriately performed based on the grasp of the three-dimensional support layer.

本発明の第特徴構成は、前記杭長判定部は、杭長の過不足状態の判定結果を杭打ち地点毎に前記支持層モデル上の該当する杭打ち地点に対応する位置に表示する点にある。 The fifth characteristic configuration of the present invention is that the pile length determination unit displays the determination result of the excess / deficiency state of the pile length at each pile driving point at a position corresponding to the corresponding pile driving point on the support layer model. It is in.

本構成によれば、杭長判定ステップの後に行う杭長変更ステップにて、杭長が過剰な杭や杭長が不足する杭を支持層モデル上で杭打ち地点を特定しながら正確に把握しながら杭長の設定変更を一層適切に行うことができ、前述した杭施工方法による杭の施工を更に適切に行うことができる。 According to this configuration, in the pile length change step performed after the pile length determination step, piles with excessive pile length or piles with insufficient pile length are accurately grasped while specifying the pile driving point on the support layer model. However, the setting of the pile length can be changed more appropriately, and the pile construction by the above-mentioned pile construction method can be performed more appropriately.

杭施工方法のフローを示す図Diagram showing the flow of pile construction method 杭施工管理システムの構成図Configuration diagram of pile construction management system 支持層モデルを示す図Diagram showing the support layer model 杭施工管理モデルを示す図Figure showing pile construction management model 杭施工管理モデルを示す図Figure showing pile construction management model 杭施工管理モデルの変化状態を示す図Figure showing change state of pile construction management model 杭施工管理モデルの別実施形態を示す図The figure which shows another embodiment of the pile construction management model 杭施工管理モデルの別実施形態を示す図The figure which shows another embodiment of the pile construction management model

本発明の杭施工方法及び杭施工管理システムの実施形態の一例を図面に基づいて説明する。
図1は本発明の杭施工方法のフローを示している。同図1に示すように、この杭施工方法は、杭打ち対象地の地中の支持層の全貌を示す支持層モデルMs(支持層データの一例、図3参照)を作成する支持層データ作成ステップ♯1、支持層モデルMsに基づいて杭打ち地点毎に杭長(杭の長さ)を設定する杭長設定ステップ♯2、杭打ち地点の位置と設定された杭長とを関連付けて示した杭伏図を作成する杭伏図作成ステップ♯3、杭伏図に基づいて杭打ち作業を行う杭施工ステップ♯4を順番に実施して杭の施工を行う。
An example of the pile construction method and the embodiment of the pile construction management system of the present invention will be described with reference to the drawings.
FIG. 1 shows the flow of the pile construction method of the present invention. As shown in FIG. 1, this pile construction method creates support layer data Ms (an example of support layer data, see FIG. 3) showing the entire picture of the support layer in the ground of the pile driving target site. Step # 1, pile length setting step # 2, in which the pile length (pile length) is set for each pile driving point based on the support layer model Ms, the position of the pile driving point is shown in association with the set pile length. Pile construction is carried out by sequentially performing the pile plan creation step # 3 for creating the pile plan and the pile construction step # 4 for performing the pile driving work based on the pile plan.

更に、この杭施工方法は、杭施工ステップ♯4の杭打ち作業にて逐次得られる杭の支持層到達深度情報に基づいて支持層モデルMsを更新する支持層データ更新ステップ♯5、更新した支持層モデルMsに基づいて杭長の過不足状態を判定する杭長判定ステップ♯6、その判定結果に基づいて杭長を設定変更する杭長変更ステップ♯7を順番に実施して後続の杭の杭長を適切なものに設定変更し、杭施工ステップ♯4に戻って後続の杭の施工を行う。
このように、杭施工ステップ♯4〜杭長変更ステップ♯7を繰り返すことで、杭工事の進捗に連れて支持層モデルMsの精度を高め、それに伴って杭長を適切なものに見直しながら、大規模な敷地に対する多量の杭の施工を適切に行うことができる。
Further, in this pile construction method, the support layer data update step # 5 for updating the support layer model Ms based on the support layer reach depth information of the piles sequentially obtained in the pile driving operation of the pile construction step # 4, and the updated support. The pile length determination step # 6 for determining the excess / deficiency state of the pile length based on the layer model Ms and the pile length change step # 7 for changing the setting of the pile length based on the determination result are sequentially performed for the subsequent piles. Change the setting of the pile length to an appropriate one, and return to the pile construction step # 4 to construct the subsequent piles.
In this way, by repeating the pile construction step # 4 to the pile length change step # 7, the accuracy of the support layer model Ms is improved as the pile construction progresses, and the pile length is reviewed to be appropriate accordingly. A large number of piles can be properly constructed on a large site.

また、この杭施工方法は、上述した一連のステップ♯1〜♯7の少なくとも一部を自動的に実施する杭施工管理システム1を用いることで、大規模な敷地に対する多量の杭の施工を少ない手間で効率良く行えるとともに、多量の杭の施工を適切に管理することができる。
図2は杭施工管理システム1の概略構成を示している。この杭施工管理システム1は、例えば、1台又は複数台のコンピュータ等から構成され、図2に示すように、CPUやメモリやハードディスク等を備えて各種の情報の演算や送受信が可能な制御部2と、各種の情報や画像を表示可能なモニタ等の表示部3等が備えられている。制御部2には、記憶部27の他、機能部として、例えば、支持層データ作成部21、杭長設定部22、杭伏図作成部23、支持層データ更新部24、杭長判定部25、杭長変更部26等が備えられ、詳細は後述するが、杭工事前と杭工事中の夫々のタイミングで所定の情報の入力を受けながら、杭施工ステップ♯4を除くステップ♯1〜♯3,♯5〜♯7の夫々を自動的に実施可能に構成されている。
以下、杭施工方法の各ステップ♯1〜♯7の具体的構成の一例について説明を加える。
Further, this pile construction method uses a pile construction management system 1 that automatically implements at least a part of the series of steps # 1 to # 7 described above, so that the construction of a large amount of piles on a large-scale site is small. It can be done efficiently with time and effort, and the construction of a large number of piles can be managed appropriately.
FIG. 2 shows a schematic configuration of the pile construction management system 1. The pile construction management system 1 is composed of, for example, one or a plurality of computers, and as shown in FIG. 2, is equipped with a CPU, a memory, a hard disk, and the like, and is a control unit capable of calculating and transmitting various information. 2 and a display unit 3 such as a monitor capable of displaying various information and images are provided. In addition to the storage unit 27, the control unit 2 has, as functional units, for example, a support layer data creation unit 21, a pile length setting unit 22, a pile plan creation unit 23, a support layer data update unit 24, and a pile length determination unit 25. , Pile length changing section 26, etc. are provided, and details will be described later, but steps # 1 to # excluding pile construction step # 4 while receiving predetermined information at each timing before and during pile construction. It is configured so that each of 3, # 5 and # 7 can be automatically carried out.
Hereinafter, an example of a specific configuration of each step # 1 to # 7 of the pile construction method will be described.

(支持層データ作成ステップ♯1)
支持層データ作成ステップ♯1では、杭打ち対象地に対するボーリング調査(地盤調査の一例)で得られた多数の地盤調査地点の支持層深度情報から杭打ち対象地で想定される支持層の全貌を立体的に表現した支持層モデルMsを作成する。
支持層モデルMsは、各種の表現方法を採用できるが、図3に示す例では、地中における支持層の上面レベルの深度(深さ位置)の全貌を多数の等高線Cで表現し、更に、深度範囲毎に異なる色調や濃淡で表現したモデルとなっている。なお、支持層モデルMsは、図示は省略するが、例えば、支持層の傾斜角度が急なほど濃く表現するなど、更に支持層の傾斜角度を表現するようにしてもよい。
(Support layer data creation step # 1)
In the support layer data creation step # 1, the entire picture of the support layer assumed at the pile driving target site is obtained from the support layer depth information of many ground survey points obtained by the boring survey (an example of the ground survey) for the pile driving target site. Create a support layer model Ms expressed in three dimensions.
The support layer model Ms can adopt various expression methods, but in the example shown in FIG. 3, the entire picture of the depth (depth position) of the upper surface level of the support layer in the ground is expressed by a large number of contour lines C, and further. It is a model that expresses different colors and shades for each depth range. Although not shown, the support layer model Ms may further express the inclination angle of the support layer, for example, the steeper the inclination angle of the support layer, the darker the expression.

本実施形態では、杭施工管理システム1にて支持層モデルMsを自動作成するように構成されている。具体的には、まず、設計者等が、ボーリング調査で得られた多数の地盤調査地点の支持層深度情報(位置情報に関連づけた支持層深度情報)に基づき、例えば、隣接する地盤調査地点の中間地点の支持層深度を隣接する調査地点の支持層深度の中間値とする等の算出形態により、地盤調査地点を含む設定面積毎等の多数の設定地点の支持層の三次元座標を示した支持層XYZ座標リストを作成し、その支持層XYZ座標リストを杭施工管理システム1に入力する。 In this embodiment, the pile construction management system 1 is configured to automatically create support layer models Ms. Specifically, first, the designers, etc., based on the support layer depth information (support layer depth information associated with the position information) of many ground survey points obtained by the boring survey, for example, at the adjacent ground survey points. The three-dimensional coordinates of the support layer of many set points such as for each set area including the ground survey point are shown by the calculation form such as setting the support layer depth of the intermediate point as the intermediate value of the support layer depth of the adjacent survey point. A support layer XYZ coordinate list is created, and the support layer XYZ coordinate list is input to the pile construction management system 1.

図2に示すように、杭施工管理システム1は、支持層XYZ座標リストが入力されると、記憶部27に支持層XYZ座標リストを記憶するとともに、支持層データ作成部21にて、例えば、隣接する設定地点のXYZ座標を3次元的に結ぶ等の演算形態で支持層モデルMsを自動作成する。そして、その支持層モデルMsを記憶部27に格納するとともに表示部3に表示する。
なお、杭施工管理システム1は、多数の設定地点のXYZ座標のうち、地盤調査地点のXYZ座標は、支持層モデルMsの作成のための確度の高い基本情報(固定情報)として他の設定地点のXYZ座標と識別可能に記憶することができる。つまり、この基本情報は、支持層データ更新ステップ♯5でも変更されない固定情報となる。
As shown in FIG. 2, when the support layer XYZ coordinate list is input, the pile construction management system 1 stores the support layer XYZ coordinate list in the storage unit 27 and, for example, in the support layer data creation unit 21. The support layer model Ms is automatically created in a calculation form such as three-dimensionally connecting the XYZ coordinates of adjacent set points. Then, the support layer model Ms is stored in the storage unit 27 and displayed on the display unit 3.
In the pile construction management system 1, among the XYZ coordinates of many setting points, the XYZ coordinates of the ground survey point are other setting points as highly accurate basic information (fixed information) for creating the support layer model Ms. It can be stored so as to be distinguishable from the XYZ coordinates of. That is, this basic information is fixed information that is not changed even in the support layer data update step # 5.

(杭長設定ステップ♯2)
杭長設定ステップ♯2では、支持層データ作成ステップ♯1にて作成された支持層モデルMsに基づいて杭打ち地点毎に杭長を設定する。また、支持層モデルMsに対して杭の位置や杭長を追加表現した杭施工管理モデルMk(杭施工管理データの一例)を作成する。
(Pile length setting step # 2)
In the pile length setting step # 2, the pile length is set for each pile driving point based on the support layer model Ms created in the support layer data creation step # 1. In addition, a pile construction management model Mk (an example of pile construction management data) that additionally expresses the position and length of the pile with respect to the support layer model Ms is created.

杭長の設定は、各種の方法を採用可能であるが、例えば、支持層XYZ座標リスト中の多数の設定地点とは関係なく、杭打ち地点の平面的な位置を示した杭位置図等の杭位置情報から支持層モデルMs上での杭打ち地点の平面的な位置を特定し、各杭打ち地点における床付け面から支持層までの深さ(長さ)に対して杭先端の所定の貫入量を加算する等の算出形態で杭長を算出して設定することができる。 Various methods can be adopted for setting the pile length, but for example, a pile position map showing the planar position of the pile driving point regardless of a large number of setting points in the support layer XYZ coordinate list, etc. The planar position of the pile driving point on the support layer model Ms is specified from the pile position information, and the predetermined depth (length) from the flooring surface to the support layer at each pile driving point is determined. The pile length can be calculated and set by a calculation form such as adding the penetration amount.

杭施工管理モデルMkは、図4に示す例では、支持層モデルMsにおける各杭打ち地点に対応する位置に杭打ち地点を示す縦姿勢の直線状の杭表示体Kを重ねて表示したモデルとなっている。杭表示体Kの長さは、設定杭長に応じた長さとなっており、図示は省略するが、杭表示体Kの近傍に杭長を示す文字が表示される。なお、図4〜図7に示す杭施工管理モデルMkにおいて、支持層モデルMsに表現された色調や濃淡等は省略している。 In the example shown in FIG. 4, the pile construction management model Mk is a model in which a linear pile display body K in a vertical posture indicating a pile driving point is superimposed and displayed at a position corresponding to each pile driving point in the support layer model Ms. It has become. The length of the pile display body K is a length corresponding to the set pile length, and although not shown, characters indicating the pile length are displayed in the vicinity of the pile display body K. In the pile construction management model Mk shown in FIGS. 4 to 7, the color tone, shading, etc. expressed in the support layer model Ms are omitted.

本実施形態では、杭施工管理システム1にて、杭打ち地点毎の杭長を自動設定するとともに、杭施工管理モデルMkを自動作成するように構成されている。
具体的には、設計者側の設計システム等から平面的な杭打ち地点の位置(平面配置)を示す杭位置図(杭位置情報の一例)を杭施工管理システム1に入力する。
図2に示すように、杭施工管理システム1は、杭位置図が入力されると、杭長設定部22にて、例えば、杭位置図に基づいて支持層モデルMs上での杭打ち地点の平面的な位置を特定し、各杭打ち地点における床付け面から支持層までの深さ(長さ)に対して杭先端の所定の貫入量を加算する等の演算形態で杭長を算出して自動設定する。更に、杭長設定部22は、上述した杭施工管理モデルMkを自動作成し、その杭施工管理モデルMkを記憶部27に格納するとともに表示部3に表示する。
In this embodiment, the pile construction management system 1 is configured to automatically set the pile length for each pile driving point and automatically create the pile construction management model Mk.
Specifically, a pile position diagram (an example of pile position information) showing the position (planar arrangement) of a flat pile driving point is input to the pile construction management system 1 from the design system on the designer side.
As shown in FIG. 2, when the pile position map is input, the pile construction management system 1 has the pile length setting unit 22, for example, the pile driving point on the support layer model Ms based on the pile position map. The pile length is calculated by specifying a planar position and adding a predetermined penetration amount of the pile tip to the depth (length) from the flooring surface to the support layer at each pile driving point. Automatically set. Further, the pile length setting unit 22 automatically creates the above-mentioned pile construction management model Mk, stores the pile construction management model Mk in the storage unit 27, and displays the pile construction management model Mk on the display unit 3.

(杭伏図作成ステップ♯3)
杭伏図作成ステップ♯3では、図示は省略するが、前述した杭位置図上に各杭打ち地点の杭長を表示した杭伏図(構造図や施工図の一例)を作成する。
この杭伏図は、例えば、杭位置図上の各杭打ち地点の直上又は近傍に当該杭打ち地点に設定された杭長を表示した図とすることができる。
(Pile plan creation step # 3)
In step # 3 for creating a pile plan, although not shown, a pile plan (an example of a structural drawing or a construction drawing) showing the pile length at each pile driving point is created on the above-mentioned pile position map.
This pile plan may be, for example, a diagram displaying the pile length set at the pile driving point directly above or near each pile driving point on the pile position map.

本実施形態では、杭施工管理システム1にて杭伏図を自動作成するように構成されている。具体的には、杭施工管理システム1は、設計者等により杭伏図の作成が指令されると、既に入力されて記憶部27に格納されている杭位置図上に杭長設定ステップ♯2にて設定した杭長を追加表示する演算形態で杭伏図を自動作成し、その杭伏図を記憶部27に格納するとともに表示部3に表示する。 In this embodiment, the pile construction management system 1 is configured to automatically create a pile plan. Specifically, when the designer or the like instructs the pile construction management system 1 to create a pile plan, the pile length setting step # 2 is already input and stored on the pile position map stored in the storage unit 27. A pile plan is automatically created in a calculation mode in which the pile length set in is additionally displayed, and the pile plan is stored in the storage unit 27 and displayed on the display unit 3.

(杭施工ステップ♯4)
杭施工ステップ♯4では、杭施工業者等が、杭打ち対象地における杭伏図等にて特定される位置に対して、杭伏図にて特定される杭長を有した既成杭等の杭を建て込む杭打ち作業を行う。また、その際、杭打ち地点毎に杭の支持層到達深度情報(杭打ち地点に関連付けられた支持層到達深度情報)を含む杭施工管理情報を取得し、例えば、タブレット等の端末機を操作して管理用サーバ等の施工管理情報データベース等に登録する。なお、杭は、既成杭に限らず、場所打ち杭等であってもよく、各種の構造の杭を適用することができる。
(Pile construction step # 4)
In the pile construction step # 4, a pile contractor or the like has a pile such as a ready-made pile having a pile length specified by the pile plan at a position specified by the pile plan or the like in the pile driving target site. Perform pile driving work to build. At that time, pile construction management information including pile support layer reach depth information (support layer reach depth information associated with the pile driving point) is acquired for each pile driving point, and a terminal such as a tablet is operated, for example. And register it in the construction management information database etc. of the management server etc. The pile is not limited to a ready-made pile, but may be a cast-in-place pile or the like, and piles having various structures can be applied.

(支持層モデル更新ステップ♯5)
支持層モデル更新ステップ♯5では、杭施工ステップ♯4の杭打ち作業にて逐次取得される杭打ち地点毎の杭の支持層到達深度情報を支持層深度情報として追加して支持層モデルMsを更新する。
(Support layer model update step # 5)
In the support layer model update step # 5, the support layer model Ms is added by adding the support layer reach depth information of the piles for each pile driving point sequentially acquired in the pile driving operation of the pile construction step # 4 as the support layer depth information. Update.

本実施形態では、杭施工管理システム1にて支持層モデルを自動更新するように構成されている。具体的には、前述した施工管理情報データベース等から杭打ち作業にて逐次取得される杭打ち地点毎の支持層到達深度情報を杭施工管理システム1に入力する。
図2に示すように、杭施工管理システム1は、杭打ち地点毎の支持層到達深度情報が入力されると、例えば、記憶部27に記憶されている支持層XYZ座標リスト対して、支持層到達深度情報としての支持層到達位置のXYZ座標を確度の高い基本情報として追加する。そして、その基本情報の追加により当初よりも基本情報が増えた支持層XYZ座標リスト中の各XYZ座標を3次元的に結ぶ等の演算形態で支持層モデルMsを自動更新(再構築)する。また、更新後の支持層モデルMsを記憶部27に格納するとともに表示部3に表示する。
In this embodiment, the pile construction management system 1 is configured to automatically update the support layer model. Specifically, the support layer reach depth information for each pile driving point, which is sequentially acquired from the above-mentioned construction management information database or the like in the pile driving work, is input to the pile construction management system 1.
As shown in FIG. 2, in the pile construction management system 1, when the support layer reach depth information for each pile driving point is input, for example, the support layer with respect to the support layer XYZ coordinate list stored in the storage unit 27. The XYZ coordinates of the support layer arrival position as the arrival depth information are added as highly accurate basic information. Then, the support layer model Ms is automatically updated (reconstructed) in a calculation form such as three-dimensionally connecting each XYZ coordinate in the support layer XYZ coordinate list whose basic information has increased from the beginning due to the addition of the basic information. Further, the updated support layer model Ms is stored in the storage unit 27 and displayed on the display unit 3.

この支持層モデル更新ステップ♯5では、支持層XYZ座標リスト中における確度の高い基本情報(ボーリング調査の支持層深度情報、及び、杭の支持層到達深度情報)を増やす形態で支持層モデルMsを更新することで、支持層モデルMsの精度を高めることができる。なお、支持層モデル更新ステップ♯5において、支持層XYZ座標リスト中における基本情報を増やした場合に、その時点で取得している全ての基本情報に基づいて支持層XYZ座標リスト中の他の設定地点を再算出する形態で支持層XYZ座標リストを全体的に再構築し、その再構築した支持層XYZ座標に基づいて支持層モデルMsを自動更新するようにしてもよい。 In this support layer model update step # 5, the support layer model Ms is generated in a form of increasing the basic information with high accuracy (support layer depth information of the boring survey and support layer reach depth information of the pile) in the support layer XYZ coordinate list. By updating, the accuracy of the support layer model Ms can be improved. When the basic information in the support layer XYZ coordinate list is increased in the support layer model update step # 5, other settings in the support layer XYZ coordinate list are set based on all the basic information acquired at that time. The support layer XYZ coordinate list may be reconstructed as a whole in the form of recalculating the points, and the support layer model Ms may be automatically updated based on the reconstructed support layer XYZ coordinates.

支持層モデルMsの更新例としては、例えば、図3,4に示す支持層モデルMsが、等高線Cが一層密に表示された図5に示す支持層モデルMsに更新される例を挙げることができる。
また、例えば、図6(a)に示す支持層モデルMsが、主として支持層到達深度情報を取得した杭打ち地点の周辺エリアPで等高線Cが変更(更新)された図6(b)に示す支持層モデルMsに更新される例等を挙げることができる。
As an example of updating the support layer model Ms, for example, the support layer model Ms shown in FIGS. 3 and 4 may be updated to the support layer model Ms shown in FIG. 5 in which the contour lines C are displayed more densely. can.
Further, for example, the support layer model Ms shown in FIG. 6 (a) is shown in FIG. 6 (b) in which the contour lines C are changed (updated) mainly in the peripheral area P of the pile driving point where the support layer reach depth information is acquired. An example of being updated to the support layer model Ms can be given.

(杭長判定ステップ♯6)
杭長判定ステップ♯6では、支持層データ更新ステップ♯5にて更新された支持層モデルMsに基づき、杭長設定ステップ♯3にて設定されている杭打ち地点毎の杭長(その時点で設定されている現在杭長)の過不足状態を判定する。
(Pile length determination step # 6)
In the pile length determination step # 6, based on the support layer model Ms updated in the support layer data update step # 5, the pile length for each pile driving point set in the pile length setting step # 3 (at that time). Judge the excess / deficiency state of the set current pile length).

本実施形態では、支持層モデルMsが更新された場合に、杭施工管理システム1にて杭打ち地点毎の現在杭長の過不足状態を自動判定するように構成されている。
具体的には、杭施工管理システム1は、支持層データ更新ステップ♯5にて支持層モデルMsが更新されると、杭長判定部25にて、更新された支持層モデルMs上の支持層に対する杭打ち地点毎の現在杭長での根入れ深さを演算し、その根入れ深さに基づいて杭打ち地点毎の現在杭長の過不足状態を判定する。
In this embodiment, when the support layer model Ms is updated, the pile construction management system 1 is configured to automatically determine the excess / deficiency state of the current pile length at each pile driving point.
Specifically, in the pile construction management system 1, when the support layer model Ms is updated in the support layer data update step # 5, the pile length determination unit 25 determines the updated support layer on the support layer model Ms. The depth of the current pile at the current pile length for each pile driving point is calculated, and the excess / deficiency state of the current pile length at each pile driving point is determined based on the depth of the pile.

例えば、杭長判定部25は、杭長の過不足状態として、現在杭長の根入深さが杭径の2倍未満である場合は「余長が少ない」と判定し、現在杭長の根入深さが杭径の1倍未満である場合は「余長不足」と判定し、現在杭長の根入れ深さが杭径の5倍を超える場合は「余長過剰」と判定し、現在杭長の根入れ深さが杭径の2倍以上且つ杭径の5倍未満である場合は「余長適正」と判定する。 For example, the pile length determination unit 25 determines that the pile length is in excess or deficiency, and if the current depth of the pile length is less than twice the pile diameter, the pile length determination unit 25 determines that the extra length is small, and the current pile length If the penetration depth is less than 1 times the pile diameter, it is judged as "insufficient extra length", and if the penetration depth of the current pile length exceeds 5 times the pile diameter, it is judged as "excessive extra length". If the depth of the pile length is more than twice the pile diameter and less than five times the pile diameter, it is judged as "appropriate extra length".

そして、杭施工管理システム1の杭長判定部25は、図5に示すように、杭施工管理モデルMkにおいて杭の過不足状態の判定結果を線種や色を異ならせる等により識別可能に表現し、その杭施工管理モデルMkを記憶部27に格納するとともに表示部3に表示する。 Then, as shown in FIG. 5, the pile length determination unit 25 of the pile construction management system 1 can clearly express the determination result of the excess / deficiency state of the piles in the pile construction management model Mk by different line types and colors. Then, the pile construction management model Mk is stored in the storage unit 27 and displayed on the display unit 3.

例えば、図5に示す杭施工管理モデルMkの例では、杭打ち地点を示す杭表示体Kのうち、「余長が少ない」と判定した杭打ち地点に相当する杭表示体K2を太点線で表示し、「余長不足」と判定した杭打ち地点に相当する杭表示体K3を太実線で表示している。また、「余長過剰」と判定した杭打ち地点に相当する杭表示体K4を太一点鎖線で表示し、「余長適正」と判定した杭打ち地点に相当する杭表示体K1を細実線で表示している。なお、これに代え、杭表示体K1〜K4を夫々異なる色で表示してもよい。 For example, in the example of the pile construction management model Mk shown in FIG. 5, among the pile display bodies K indicating the pile driving points, the pile display body K2 corresponding to the pile driving point determined to have "small extra length" is shown by a thick dotted line. The pile display body K3 corresponding to the pile driving point determined to be "insufficient extra length" is displayed by a thick solid line. In addition, the pile display body K4 corresponding to the pile driving point determined to be "excessive extra length" is displayed by a large one-dot chain line, and the pile display body K1 corresponding to the pile driving point determined to be "appropriate extra length" is indicated by a fine solid line. it's shown. Instead of this, the pile display bodies K1 to K4 may be displayed in different colors.

図5に示す杭施工管理モデルMkは、図3,4に示す支持層モデルMsから等高線Cが一層密に表示された図5に示す支持層モデルMsに更新された場合に、一部の杭表示体Kが、「余長適正」を示す杭表示体K1から「余長が少ない」や「余長不足」や「余長過剰」を示す杭表示体K2〜K4に変更された場合を例示している。 The pile construction management model Mk shown in FIG. 5 is a part of the piles when the support layer model Ms shown in FIGS. 3 and 4 is updated to the support layer model Ms shown in FIG. 5 in which the contour lines C are displayed more densely. An example is the case where the display body K is changed from the pile display body K1 indicating "appropriate extra length" to the pile display bodies K2 to K4 indicating "small extra length", "insufficient extra length", or "excessive extra length". is doing.

また、図6(b)に示す杭施工管理モデルMkは、図6(a)に示す支持層モデルMsから新たに支持層到達深度情報を取得した杭打ち地点の周辺エリアPの等高線Cが深くなる側に変更された図6(b)に示す支持層モデルMsに更新された場合に、当該周辺エリアPに位置する杭表示体Kが、「余長適正」を示す杭表示体K1から「余長が少ない」や「余長不足」を示す杭表示体K2,K3に変更された場合を例示している。 Further, in the pile construction management model Mk shown in FIG. 6 (b), the contour line C of the peripheral area P of the pile driving point where the support layer reach depth information is newly acquired from the support layer model Ms shown in FIG. 6 (a) is deep. When updated to the support layer model Ms shown in FIG. 6 (b) changed to the side, the pile display body K located in the peripheral area P is changed from the pile display body K1 indicating "appropriate extra length" to ". The case where the pile display bodies K2 and K3 are changed to indicate "the extra length is small" or "the extra length is insufficient" is illustrated.

(杭長変更ステップ♯7)
杭長変更ステップ♯7では、支持層データ更新ステップ♯5にて更新された支持層モデルMsに基づく杭長判定ステップ♯6での判定結果に基づいて杭打ち地点毎の杭長を設定変更する。このように、支持層モデルMsが更新される毎に、杭長判定ステップ♯6での判定結果に基づいて杭長を設定変更することで、後続の杭打ち作業を適切且つ効率的に行うことができる。
(Pile length change step # 7)
In the pile length change step # 7, the pile length for each pile driving point is changed based on the judgment result in the pile length determination step # 6 based on the support layer model Ms updated in the support layer data update step # 5. .. In this way, every time the support layer model Ms is updated, the pile length is set and changed based on the determination result in the pile length determination step # 6, so that the subsequent pile driving work can be performed appropriately and efficiently. Can be done.

本実施形態では、杭施工管理システム1にて、杭長の設定変更を自動的に行うように構成されている。具体的には、杭施工管理システム1は、設計者等から杭長の設定変更が指令されると、杭長変更部26にて、例えば、「余長が少ない」や「余長不足」や「余長過剰」と判定した杭打ち地点の杭長を、「余長適正」と判定される範囲(根入深さが杭径の2倍以上且つ杭径の5倍未満となる範囲)で設定された設定杭長に自動的に設定変更する。 In this embodiment, the pile construction management system 1 is configured to automatically change the setting of the pile length. Specifically, in the pile construction management system 1, when a designer or the like instructs to change the setting of the pile length, the pile length changing unit 26, for example, "small extra length" or "insufficient extra length". The pile length at the pile driving point judged to be "excessive extra length" is within the range judged to be "appropriate extra length" (the range where the penetration depth is at least twice the pile diameter and less than five times the pile diameter). The setting is automatically changed to the set pile length.

なお、「余長が少ない」や「余長不足」や「余長過剰」と判定した杭打ち地点の杭長のうちで「余長不足」や「余長過剰」等の重要性の高い特定の一部の判定結果がなされた杭打ち地点の杭長のみを自動的に設定変更するように構成してもよい。
また、杭長の設定変更を人為的に行うようにしてもよく、その場合、例えば、設計者や施工管理者等が、杭施工管理モデルMkにて杭長の過不足状態の判定結果を確認して杭打ち地点毎に杭長の設定変更の要否を判断し、必要と判断した杭打ち地点の杭長を杭施工管理システム1に入力する等により杭長の設定変更を行うことができる。
Of the pile lengths at the pile driving points that were judged to be "small extra length", "insufficient extra length", or "excessive extra length", "insufficient extra length", "excessive extra length", etc. are highly important. It may be configured to automatically change the setting of only the pile length at the pile driving point where a part of the determination results of the above is made.
Further, the setting of the pile length may be changed artificially. In that case, for example, the designer, the construction manager, etc. confirm the judgment result of the excess / deficiency state of the pile length with the pile construction management model Mk. Then, it is possible to determine the necessity of changing the pile length setting for each pile driving point, and input the pile length of the pile driving point determined to be necessary into the pile construction management system 1 to change the pile length setting. ..

以上説明したように、本発明の杭施工方法によれば、杭工事の進捗に連れて支持層モデルMsの精度を高め、それに伴って杭長を適切なものに見直しながら、大規模な敷地に対する多量の杭の施工を適切に行うことができる。しかも、上述した杭施工管理システム1を用いることで、大規模な敷地に対する多量の杭の施工を少ない手間で効率良く行うことができ、更に、多量の杭の施工を適切に管理することができる。 As described above, according to the pile construction method of the present invention, the accuracy of the support layer model Ms is improved as the pile construction progresses, and the pile length is reviewed to be appropriate accordingly for a large-scale site. It is possible to properly construct a large number of piles. Moreover, by using the above-mentioned pile construction management system 1, it is possible to efficiently construct a large number of piles on a large-scale site with little effort, and further, it is possible to appropriately manage the construction of a large number of piles. ..

〔別実施形態〕
本発明の他の実施形態について説明する。なお、以下に説明する各実施形態の構成は、それぞれ単独で適用するものに限られず、他の実施形態の構成と組み合わせて適用することも可能である。
[Another Embodiment]
Other embodiments of the present invention will be described. The configuration of each embodiment described below is not limited to the one applied independently, and can be applied in combination with the configuration of other embodiments.

(1)杭施工管理モデル(杭施工管理データ)Mkは、前述の実施形態で示した構成に限らず、種々の構成変更が可能である。
図7は、杭施工管理モデルMkの別実施形態を示している。図7では、平面的な表示状態を示しているが、視点の変更指令等により立体的な表示状態に変更可能なものとなっている。また、杭施工管理モデルMk中の支持層モデルMsに表現された色調や濃淡等は省略している。
この杭施工管理モデルMkは、前述の実施形態でも識別可能に表示されていた「余長が少ない」、「余長不足」、「余長過剰」に加えて、直近の施工日に杭の施工が完了した「杭施工済み(直近の施工日)」や直近の施工日より前に杭の施工が完了した「杭施工済み(直近の施工日より前)」も識別可能に表示され、更に、「地盤調査地点」も識別可能に表示されるように構成されている。
(1) The pile construction management model (pile construction management data) Mk is not limited to the configuration shown in the above-described embodiment, and various configuration changes are possible.
FIG. 7 shows another embodiment of the pile construction management model Mk. Although FIG. 7 shows a two-dimensional display state, it can be changed to a three-dimensional display state by a viewpoint change command or the like. In addition, the color tone and shading expressed in the support layer model Ms in the pile construction management model Mk are omitted.
In this pile construction management model Mk, in addition to "small extra length", "insufficient extra length", and "excessive extra length" that are identifiablely displayed in the above-described embodiment, pile construction is performed on the latest construction day. "Pile construction completed (latest construction date)" and "Pile construction completed (prior to the latest construction date)" for which pile construction was completed before the latest construction date are also displayed in an identifiable manner. The "ground survey point" is also configured to be displayed in an identifiable manner.

ちなみに、図示の例では、杭打ち地点を示す円形の杭表示体Kのうち、「余長が少ない」と判定した杭打ち地点に相当する杭表示体K2は円形の内部をグレーで塗り潰して表示し、「余長不足」と判定した杭打ち地点に相当する杭表示体K3は円形の内部を黒で塗り潰して表示している。「余長過剰」と判定した杭に相当する杭表示体K4は円形の内部に斜めハッチングを施して表示し、「余長適正」と判定した杭打ち地点に相当する杭表示体K1は円形の内部を白抜きにして表示している。
更に、「杭施工済み(直近の施工日)」に該当する杭打ち地点は、円形の杭表示体Kの外側に点線の円Dtを表示し、「杭施工済み(直近の施工日より前)」に該当する杭打ち地点は、円形の杭表示体Kの外側に実線の円Dbを表示している。また、「地盤調査地点」は×印Bを表示している。
By the way, in the illustrated example, among the circular pile display bodies K indicating the pile driving points, the pile display body K2 corresponding to the pile driving points determined to have "small extra length" is displayed by painting the inside of the circle with gray. However, the pile display body K3 corresponding to the pile driving point determined to be "insufficient extra length" is displayed by filling the inside of the circle with black. The pile display body K4 corresponding to the pile judged to be "excessive extra length" is displayed by diagonally hatching the inside of the circle, and the pile display body K1 corresponding to the pile driving point judged to be "appropriate extra length" is circular. The inside is shown in white.
Furthermore, for the pile driving points corresponding to "Pile construction completed (most recent construction date)", a dotted circle Dt is displayed on the outside of the circular pile display body K, and "Pile construction completed (before the latest construction date)" is displayed. A solid circle Db is displayed on the outside of the circular pile display body K at the pile driving point corresponding to the above. In addition, the "ground survey point" is indicated by a cross mark B.

更に、この杭施工管理モデルMkは、図8に示すように、表示変更指令等により、杭表示体Kの近傍に当該杭打ち地点における「杭天端の高さ」や「杭長」、「支持層深度」、「余長」に関する設計時の情報と工事計画時の情報と実施時の情報とを並べて表示することができる。 Further, as shown in FIG. 8, this pile construction management model Mk has "height of pile top end", "pile length", and "support layer" at the pile driving point in the vicinity of the pile display body K by a display change command or the like. Information at the time of design, information at the time of construction planning, and information at the time of implementation regarding "depth" and "extra length" can be displayed side by side.

(2)前述の実施形態では、杭長設定ステップ♯2において、各杭打ち地点における床付け面から支持層までの深さ(長さ)に対して杭先端の所定の貫入量を加算する等の算出形態等で各杭打ち地点の杭長を算出して設定する場合を例に示したが、例えば、このように算出形態等で算出した杭長に対して支持層深度が想定と異なるリスクを考慮した補正値を加えて設定することもできる。 (2) In the above-described embodiment, in the pile length setting step # 2, a predetermined penetration amount of the pile tip is added to the depth (length) from the flooring surface to the support layer at each pile driving point. The case where the pile length at each pile driving point is calculated and set by the calculation form of is shown as an example, but for example, there is a risk that the support layer depth is different from the assumption with respect to the pile length calculated by the calculation form etc. in this way. It is also possible to add a correction value in consideration of.

この場合、支持層深度が想定と異なるリスクの変化要因としては、杭打ち地点における杭芯位置の支持層の傾斜角度が考えられるので、例えば、杭打ち地点における杭芯位置の支持層の傾斜角度をθとして、設定値にsinθを乗じて得られた値等を補正値として杭長に加えるようにしてもよい。
また、これに代えて、又は、これに加えて、支持層深度が想定と異なるリスクの変化要因として、杭打ち地点における杭芯位置と最も近い地盤調査地点の距離が考えられるので、例えば、その距離をLとして、Lを設定値で除して得られた値等を補正値として杭長に加えるようにしてもよい。
In this case, the tilt angle of the support layer at the pile core position at the pile driving point can be considered as a factor that changes the risk that the support layer depth is different from the assumption. For example, the tilt angle of the support layer at the pile core position at the pile driving point. May be θ, and a value obtained by multiplying the set value by sin θ or the like may be added to the pile length as a correction value.
In addition to this, or in addition to this, the distance between the pile core position at the pile driving point and the nearest ground survey point can be considered as a factor for changing the risk that the depth of the support layer is different from the assumption. The distance may be L, and the value obtained by dividing L by the set value may be added to the pile length as a correction value.

なお、このように算出した補正値の大小は、支持層深度が想定と異なるリスクの大小を示すものとなるので、例えば、この補正値の大小を杭施工管理モデルMk等に表示し、ボーリング調査の追加の要否等の検討資料とすることもできる。 The magnitude of the correction value calculated in this way indicates the magnitude of the risk that the depth of the support layer is different from the assumption. Therefore, for example, the magnitude of this correction value is displayed on the pile construction management model Mk or the like for a boring survey. It can also be used as a study material such as the necessity of additional addition.

(3)前述の実施形態では、支持層データ作成ステップ♯1において、一部の作業を杭施工管理システム1を用いずに人為的に実施し、他部の作業を杭施工管理システム1にて自動的に実施する場合を例に示したが、全ての作業を人為的に実施したり、杭施工管理システム1にて自動的に実施したりしてもよい。 (3) In the above-described embodiment, in the support layer data creation step # 1, some work is artificially performed without using the pile construction management system 1, and the work of the other part is performed by the pile construction management system 1. Although the case of automatic implementation is shown as an example, all the operations may be performed artificially or may be automatically performed by the pile construction management system 1.

(4)前述の実施形態では、杭長設定ステップ♯2、杭伏図作成ステップ♯3、支持層データ更新ステップ♯5、杭長判定ステップ♯6、杭長変更ステップ♯7の夫々において、全ての作業を杭施工管理システム1にて自動的に実施する場合を例に示したが、各ステップ♯2,♯3,♯5,♯6,♯7の夫々において、全ての作業を人為的に実施したり、一部の作業を人為的に実施し、他部の作業を杭施工管理システム1にて自動的に実施したりしてもよい。 (4) In the above-described embodiment, all of the pile length setting step # 2, the pile plan creation step # 3, the support layer data update step # 5, the pile length determination step # 6, and the pile length change step # 7 are all performed. Although the case where the above work is automatically performed by the pile construction management system 1 is shown as an example, all the work is artificially performed in each of steps # 2, # 3, # 5, # 6, and # 7. It may be carried out, or some work may be carried out artificially, and the work of other parts may be carried out automatically by the pile construction management system 1.

(5)前述の実施形態では、支持層の全貌を示す支持層データとして支持層の全貌を立体的に表現した支持層モデルMsを例に示したが、支持層データは、支持層の全貌に関する情報を表形式等で表現したリスト等であってもよい。 (5) In the above-described embodiment, the support layer model Ms that three-dimensionally expresses the entire image of the support layer is shown as an example of the support layer data showing the entire image of the support layer, but the support layer data relates to the entire image of the support layer. It may be a list or the like expressing information in a tabular format or the like.

(6)同様に、前述の実施形態では、杭施工管理データとして杭施工管理モデルMkを例に示したが、杭施工管理データは各種情報が表形式等で表示されたリスト等であってもよい。 (6) Similarly, in the above-described embodiment, the pile construction management model Mk is shown as an example of the pile construction management data, but the pile construction management data may be a list or the like in which various information is displayed in a tabular format or the like. good.

以上、本発明の実施形態について説明したが、本発明はこうした実施形態に何等限定されるものでなく、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。 Although the embodiments of the present invention have been described above, the present invention is not limited to these embodiments, and it is needless to say that the present invention can be carried out in various embodiments without departing from the gist of the present invention.

1 杭施工管理システム
2 制御部
3 表示部
21 支持層データ作成部
22 杭長設定部
23 杭伏図作成部
24 支持層データ更新部
25 杭長判定部
26 杭長変更部
27 記憶部
Ms 支持層モデル(支持層データ)
Mk 杭施工管理モデル(杭施工管理データ)
P 杭打ち地点の周辺エリア
K 杭表示体
K1 杭表示体(余長適正)
K2 杭表示体(余長が少ない)
K3 杭表示体(余長不足)
K4 杭表示体(余長過剰)
C 等高線
Dt 杭施工済み(直近の施工日)
Db 杭施工済み(直近の施工日より前)
B 地盤調査地点
1 Pile construction management system 2 Control unit 3 Display unit 21 Support layer data creation unit 22 Pile length setting unit 23 Pile plan creation unit 24 Support layer data update unit 25 Pile length determination unit 26 Pile length change unit 27 Storage unit Ms Support layer Model (support layer data)
Mk pile construction management model (pile construction management data)
P Area around the pile driving point K Pile display body K1 Pile display body (appropriate extra length)
K2 pile display body (less extra length)
K3 pile display (insufficient extra length)
K4 pile display (excessive extra length)
C contour line Dt pile construction completed (latest construction date)
Db pile construction completed (before the latest construction date)
B Geotechnical investigation point

Claims (5)

地盤調査地点の支持層深度情報から杭打ち対象地で想定される支持層の全貌を示す支持層データを作成する支持層データ作成ステップと、
前記支持層データ作成ステップにて作成された前記支持層データに基づいて杭打ち地点毎に杭長を設定する杭長設定ステップと、
杭打ち作業にて逐次取得される杭打ち地点毎の杭の支持層到達深度情報を前記支持層深度情報として追加して前記支持層データを更新する支持層データ更新ステップと、
前記支持層データ更新ステップにて更新された前記支持層データに基づいて杭長を設定変更する杭長変更ステップとを備える杭施工方法。
Support layer data creation step to create support layer data showing the whole picture of the support layer assumed at the pile driving target site from the support layer depth information at the ground survey point,
A pile length setting step for setting a pile length for each pile driving point based on the support layer data created in the support layer data creation step, and a pile length setting step.
A support layer data update step for updating the support layer data by adding the support layer reach depth information of the pile for each pile driving point sequentially acquired in the pile driving operation as the support layer depth information , and
A pile construction method including a pile length change step for setting and changing a pile length based on the support layer data updated in the support layer data update step.
前記支持層データ更新ステップにて更新された前記支持層データに基づき、前記杭長設定ステップにて設定されている杭打ち地点毎の杭長の過不足状態を判定する杭長判定ステップを備え、
前記杭長変更ステップでは、前記杭長判定ステップでの判定結果に基づいて杭長を設定変更する請求項記載の杭施工方法。
Based on the support layer data updated in the support layer data update step, a pile length determination step for determining an excess / deficiency state of the pile length for each pile driving point set in the pile length setting step is provided.
Wherein the pile length changing step, pile construction method of claim 1, wherein the setting change pile length based on the determination result in the pile length determination step.
請求項記載の杭施工方法に用いられる杭施工管理システムであって、
前記支持層データ作成ステップにて作成された前記支持層データに基づいて杭打ち地点毎に杭長を自動設定する杭長設定部と、
杭打ち作業にて逐次取得される前記支持層到達深度情報が前記支持層深度情報として追加された場合に、前記支持層データを自動更新する支持層データ更新部と、
前記支持層データ更新部にて前記支持層データが更新された場合に、前記杭長設定部にて設定された杭打ち地点毎の杭長の過不足状態を自動判定する杭長判定部と、を備える杭施工管理システム。
A pile construction management system used in the pile construction method according to claim 2.
A pile length setting unit that automatically sets the pile length for each pile driving point based on the support layer data created in the support layer data creation step, and a pile length setting unit.
A support layer data update unit that automatically updates the support layer data when the support layer reach depth information sequentially acquired in the pile driving operation is added as the support layer depth information.
When the support layer data is updated by the support layer data update unit, a pile length determination unit that automatically determines an excess or deficiency state of the pile length for each pile driving point set by the pile length setting unit, and a pile length determination unit. Pile construction management system equipped with.
前記支持層データが、杭打ち対象地の支持層の全貌を表示部に三次元的に表示した支持層モデルである請求項記載の杭施工管理システム。 The pile construction management system according to claim 3 , wherein the support layer data is a support layer model in which the entire support layer of the pile driving target site is three-dimensionally displayed on the display unit. 前記杭長判定部は、杭長の過不足状態の判定結果を杭打ち地点毎に前記支持層モデル上の該当する杭打ち地点に対応する位置に表示する請求項又は記載の杭施工管理システム。 The pile construction management according to claim 3 or 4, wherein the pile length determination unit displays the determination result of the excess / deficiency state of the pile length at the position corresponding to the corresponding pile driving point on the support layer model for each pile driving point. system.
JP2017231959A 2017-12-01 2017-12-01 Pile construction method and pile construction management system Active JP6987624B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017231959A JP6987624B2 (en) 2017-12-01 2017-12-01 Pile construction method and pile construction management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017231959A JP6987624B2 (en) 2017-12-01 2017-12-01 Pile construction method and pile construction management system

Publications (2)

Publication Number Publication Date
JP2019100082A JP2019100082A (en) 2019-06-24
JP6987624B2 true JP6987624B2 (en) 2022-01-05

Family

ID=66976328

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017231959A Active JP6987624B2 (en) 2017-12-01 2017-12-01 Pile construction method and pile construction management system

Country Status (1)

Country Link
JP (1) JP6987624B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7397481B2 (en) 2020-04-10 2023-12-13 株式会社オムテック Ground liquefaction depth estimation device and method
CN111506954A (en) * 2020-05-13 2020-08-07 中建三局第三建设工程有限责任公司 Pile length estimation method based on BIM model
JP7405694B2 (en) * 2020-05-22 2023-12-26 東洋建設株式会社 Base layer depth prediction method and base layer depth prediction system
CN113360963B (en) * 2021-06-03 2023-11-21 中国建筑第八工程局有限公司 Engineering pile length batch pre-judging method based on BIM technology

Family Cites Families (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07189237A (en) * 1993-12-27 1995-07-28 Takenaka Komuten Co Ltd Simplifying method of lamination
JPH11148127A (en) * 1997-11-17 1999-06-02 Chubu Electric Power Co Inc Optimum arrangement method for investigation boring for level estimation of foundation ground, and record media for the method
JP5215649B2 (en) * 2007-05-21 2013-06-19 積水化学工業株式会社 Unit building structural analysis system, structural decision support system, and seismic performance evaluation system
JP2008297870A (en) * 2007-06-04 2008-12-11 Shimizu Corp Underground construction management system and underground construction management method
JP5071858B2 (en) * 2008-03-31 2012-11-14 日本ヒューム株式会社 Ready-made pile construction management equipment
KR101017567B1 (en) * 2009-01-16 2011-02-28 삼성물산 주식회사 Design and construction method of Cast in place piles
JP5435620B2 (en) * 2009-03-17 2014-03-05 有限会社探査環境技術事務所 Sensitivity-compatible inverse analysis method in numerical analysis of resistivity method
JP5516211B2 (en) * 2010-08-09 2014-06-11 株式会社大林組 Ground estimation method and ground estimation system
JP2013028923A (en) * 2011-07-27 2013-02-07 Daiwa Kiko Kk Control device of ground improvement machine
JP5985672B2 (en) * 2015-01-15 2016-09-06 日研高圧平和キドウ株式会社 Concrete foundation pile construction method
JP6201059B2 (en) * 2015-03-03 2017-09-20 株式会社岩崎 Ground shape estimation program, ground shape estimation device, and ground shape estimation method
JP2017123061A (en) * 2016-01-07 2017-07-13 オフィスケイワン株式会社 Visualization system of finished shape and visualization data generation program of finished shape
JP2017128878A (en) * 2016-01-19 2017-07-27 株式会社トーヨーアサノ Construction method of precast pile
JP6702730B2 (en) * 2016-01-19 2020-06-03 株式会社トーヨーアサノ Ready-made pile construction method

Also Published As

Publication number Publication date
JP2019100082A (en) 2019-06-24

Similar Documents

Publication Publication Date Title
JP6987624B2 (en) Pile construction method and pile construction management system
US8392014B2 (en) Designing drilling pattern for excavating rock cavern
CN108475399B (en) Simulation system and simulation method
AU2019203748A1 (en) Construction management system and construction management method
CN108951750A (en) A kind of excavator construction operation method, system and excavator
JP6468962B2 (en) Crane interference check system, bridge erection simulation system, and 3D construction planning system equipped with them
CN111226007B (en) Construction management device, display device, and construction management method
US11414839B2 (en) Display control device and method for generating target line or control line of work machine
JP2010539363A (en) Drilling pattern design method and software product for rock cavity rock drilling
JP5725908B2 (en) Map data generation system
JP5878664B1 (en) Ground surveying device, ground surveying system, ground surveying program, and ground surveying method
JP2005083893A (en) Method for displaying cross section measurement result and its program
US11761173B2 (en) Systems and methods for building a pad
JP7317926B2 (en) Construction management device, display device and construction management method
JP6626475B2 (en) Civil engineering method and civil engineering program
CN114892688B (en) Three-dimensional design method and system for side slope anchor rod frame beam
CN110851900A (en) Method, device, storage medium and equipment for reinforcing ribs of geometric shapes and automatically updating geometric shapes
KR101075256B1 (en) Error compensation method digital map using matching with output draft
CN112648974B (en) Engineering quantity calculation method based on aerial three-dimensional image data
CN115408750A (en) Power transmission line measurement finished product diagram generation method, device, equipment and storage medium
CN114996798A (en) Automatic dredging construction drawing creating method and system based on Civil3D
JP7107792B2 (en) construction machinery
JP7138018B2 (en) Scaffold design device and scaffold design method
KR101075254B1 (en) Error compensation apparatus digital map using matching with output draft and method of the same
JP3867011B2 (en) Tunnel development plan and how to create it

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200924

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210721

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210804

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210921

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211109

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211201

R150 Certificate of patent or registration of utility model

Ref document number: 6987624

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150