JP6937627B2 - Offshore wind power generation equipment and its construction method - Google Patents

Offshore wind power generation equipment and its construction method Download PDF

Info

Publication number
JP6937627B2
JP6937627B2 JP2017136733A JP2017136733A JP6937627B2 JP 6937627 B2 JP6937627 B2 JP 6937627B2 JP 2017136733 A JP2017136733 A JP 2017136733A JP 2017136733 A JP2017136733 A JP 2017136733A JP 6937627 B2 JP6937627 B2 JP 6937627B2
Authority
JP
Japan
Prior art keywords
tower
floating body
power generation
wind power
shaft structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017136733A
Other languages
Japanese (ja)
Other versions
JP2018016302A (en
Inventor
小林 修
修 小林
郁 佐藤
郁 佐藤
桂司 西山
桂司 西山
和聴 杉本
和聴 杉本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toda Corp
Original Assignee
Toda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toda Corp filed Critical Toda Corp
Publication of JP2018016302A publication Critical patent/JP2018016302A/en
Application granted granted Critical
Publication of JP6937627B2 publication Critical patent/JP6937627B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Wind Motors (AREA)

Description

本発明は、浮体内部にタワーが収容され、海上での施工時にタワー昇降設備によってタワーを引上げ、固定するようにしたスパー型の洋上風力発電設備及びその施工方法に関する。 The present invention relates to a spar-type offshore wind power generation facility in which a tower is housed inside a floating body and the tower is pulled up and fixed by a tower elevating facility during construction at sea, and a construction method thereof.

従来より、主として水力、火力及び原子力発電等の発電方式が採用されてきたが、近年は環境や自然エネルギーの有効活用の点から自然風を利用して発電を行う風力発電が注目されている。この風力発電設備には、陸上設置式と、水上(主として海上)設置式とがあるが、沿岸域から後背に山岳地形をかかえる我が国の場合は、沿岸域に安定した風が見込める平野が少ない状況にある。一方、日本は四方を海で囲まれており、海上は発電に適した風が容易に得られるとともに、設置の制約が少ないなどの利点を有する。そこで、近年は洋上風力発電設備が多く提案されている。 Conventionally, power generation methods such as hydropower, thermal power, and nuclear power generation have been mainly adopted, but in recent years, wind power generation that uses natural wind to generate power has attracted attention from the viewpoint of effective utilization of the environment and natural energy. There are two types of wind power generation facilities, one is installed on land and the other is installed on water (mainly on the sea). In Japan, which has mountainous terrain behind the coastal area, there are few plains where stable wind can be expected in the coastal area. It is in. On the other hand, Japan is surrounded on all sides by the sea, and has the advantages of being able to easily obtain wind suitable for power generation on the sea and having few restrictions on installation. Therefore, in recent years, many offshore wind power generation facilities have been proposed.

本出願人においても、下記特許文献1において、スパー型の洋上風力発電設備及びその施工方法を提案した。具体的には、浮体はコンクリート製のプレキャスト筒状体を高さ方向に複数段積み上げ、各プレキャスト筒状体をPC鋼材により緊結し一体化を図った下側コンクリート製浮体構造部と、この下側コンクリート浮体構造部の上側に連設された上側鋼製浮体構造部とからなるとともに、上端部を開口させた有底中空部を有するスパー型の浮体構造とし、少なくとも施工時に前記タワーは前記デッキ上に設けたタワー昇降設備によって昇降自在とされ、前記浮体内部に収容可能とされる洋上風力発電設備を提案した。また、その施工方法として、浮体内部にタワーを収容させた状態で海上に横向きで浮かべ、洋上設置場所まで曳航する第1手順と、洋上設置場所において、バラストを投入することによって浮体を直立状態に起立させる第2手順と、前記タワー昇降設備によってタワーを任意の高さ位置まで引き上げた状態で、前記ナセルを設置するとともに、風車ブレードを設置する第3手順と、タワーを正規の高さ位置まで引き上げ固定する第4手順とからなる洋上風力発電設備の施工方法を提案した。 The applicant also proposed a spar-type offshore wind power generation facility and a construction method thereof in Patent Document 1 below. Specifically, the floating body is a lower concrete floating body structure part in which concrete precast tubular bodies are stacked in multiple stages in the height direction, and each precast tubular body is tied together with a PC steel material to integrate them, and below this. A spar-type floating structure consisting of an upper steel floating structure connected to the upper side of the side concrete floating structure and having a bottomed hollow portion with an open upper end, and the tower is at least during construction. We have proposed an offshore wind power generation facility that can be lifted and lowered by the tower lifting facility provided above and can be accommodated inside the floating body. In addition, as the construction method, the first procedure of floating the tower sideways on the sea with the tower housed inside the floating body and towing it to the offshore installation location, and at the offshore installation location, the floating body is put upright by throwing a ballast. The second step of standing up, the third step of installing the nacelle and the wind turbine blade while the tower is pulled up to an arbitrary height position by the tower lifting equipment, and the tower to the regular height position. We proposed a construction method for offshore wind power generation facilities, which consists of the fourth procedure of pulling up and fixing.

特開2010−223114号公報Japanese Unexamined Patent Publication No. 2010-223114

前記特許文献1に係る洋上風力発電設備では、タワーを下降させた状態でナセルや風車ブレードの取付けができるようになり高所作業が減って安全に施工できるようになる。また、供用後のメンテナンス時にタワーを下降させることにより安全に作業が行えるようになるとともに、強風や波浪時にも、タワーを下降させることにより安定性が増し損傷のおそれも少なくなるなどの効果が期待できるようになる。 In the offshore wind power generation facility according to Patent Document 1, nacelles and wind turbine blades can be attached in a state where the tower is lowered, so that work at heights can be reduced and safe construction can be performed. In addition, it will be possible to work safely by lowering the tower during maintenance after operation, and it is expected that lowering the tower will increase stability and reduce the risk of damage even in strong winds and waves. become able to.

しかしながら、前記特許文献1記載の発明では、タワーの下端に直接PC鋼材を取付け、浮体上部までジャッキアップする機構であるため、タワーの引上げが不安定になり易いなどの問題があるとともに、タワーを浮体から完全に引き上げた状態で、タワーを浮体に固定用金具を用いて固定するものであるため、波で揺れる浮体上でのタワーの固定作業が危険を伴う作業となるなどの問題があった。更に、大規模修繕や強風・波浪時などにタワーを下降させる際にも、波で揺れる浮体上でのタワーの固定解除や下降作業が危険を伴う作業となるなどの問題もあった。 However, in the invention described in Patent Document 1, since the PC steel material is directly attached to the lower end of the tower and the mechanism is jacked up to the upper part of the floating body, there is a problem that the pulling up of the tower tends to be unstable, and the tower is raised. Since the tower is fixed to the floating body by using fixing brackets while it is completely pulled up from the floating body, there is a problem that the work of fixing the tower on the floating body swaying by waves becomes a dangerous work. .. Further, when lowering the tower during large-scale repairs or strong winds or waves, there is a problem that the defixation and lowering work of the tower on the floating body swaying by the waves becomes a dangerous work.

そこで本発明の主たる課題は、浮体内部にタワーが収容され、海上での施工時にタワー昇降設備によってタワーを引上げ、固定するようにしたスパー型洋上風力発電設備において、前記タワーの引上げ及び固定作業や前記タワーの固定解除及び下降作業を容易かつ安全に行えるようにしたスパー型洋上風力発電設備及びその施工方法を提供することにある。 Therefore, the main problem of the present invention is to lift and fix the tower in a spar-type offshore wind power generation facility in which the tower is housed inside the floating body and the tower is pulled up and fixed by the tower elevating facility at the time of construction at sea. It is an object of the present invention to provide a spar-type offshore wind power generation facility capable of easily and safely performing defixation and lowering work of the tower, and a construction method thereof.

上記課題を解決するために請求項1に係る本発明として、浮体と、係留索と、タワーと、タワーの頂部に設備されるナセル及び複数の風車ブレードとからなり、前記浮体は、上端部を開口させた有底中空部を有するスパー型の浮体構造とし、前記タワーは全部又は下端側の大部分が前記浮体内部に収容可能とされるとともに、前記タワーがタワー昇降設備によって昇降自在とされた洋上風力発電設備において、
前記タワーの下端に連続してシャフト構造体を一体的に備えるとともに、前記シャフト構造体は、浮体内部に設けられたガイド部材によって鉛直方向の移動が案内され
前記タワーの下端と前記浮体の上端との接合部は、周方向に分割可能とされたリング状部材によって接合されていることを特徴とする洋上風力発電設備が提供される。
In order to solve the above-mentioned problems, the present invention according to claim 1 comprises a floating body, a mooring line, a tower, a nacelle installed at the top of the tower, and a plurality of wind turbine blades. It has a spar-type floating structure having an open bottomed hollow portion, and the tower can be accommodated in all or most of the lower end side inside the floating body, and the tower can be raised and lowered by a tower elevating facility. In offshore wind power generation equipment
A shaft structure is integrally provided at the lower end of the tower, and the shaft structure is guided to move in the vertical direction by a guide member provided inside the floating body .
An offshore wind power generation facility is provided in which the lower end of the tower and the upper end of the floating body are joined by a ring-shaped member that can be divided in the circumferential direction.

上記請求項1記載の発明では、前記タワーの下端に連続してシャフト構造体を一体的に備えるとともに、前記シャフト構造体は、浮体内部に設けられたガイド部材によって鉛直方向の移動が案内されている構造としている。 In the invention according to claim 1, the shaft structure is integrally provided at the lower end of the tower, and the shaft structure is guided to move in the vertical direction by a guide member provided inside the floating body. It has a structure that is

従って、タワーの下端から連続して設けられたシャフト構造体の鉛直方向の移動がガイド部材によってしっかりと案内されていることにより、タワーを昇降設備によって引き上げる際、安定的に引き上げることができる。また、引上げ後に、タワーの下端を浮体の上部と連結する際にも、タワー下端から延びたシャフト構造体の鉛直方向の移動が浮体の内部に安定的に案内されていることにより、波に揺れる洋上であっても、タワーの挙動と浮体の挙動とが一体的となるため、タワーの固定作業が容易かつ安全に行えるようになる。更に、大規模修繕や強風・波浪時等にタワーを下降させる場合も、タワー下端から延びたシャフト構造体の鉛直方向の移動が浮体の内部に安定的に案内されていることにより、タワーの固定解除及び下降作業を容易かつ安全に行えるようになる。 Therefore, since the vertical movement of the shaft structure continuously provided from the lower end of the tower is firmly guided by the guide member, the tower can be stably pulled up when it is pulled up by the elevating equipment. Also, when connecting the lower end of the tower to the upper part of the floating body after pulling up, the vertical movement of the shaft structure extending from the lower end of the tower is stably guided inside the floating body, so that it sways in the waves. Even at sea, the behavior of the tower and the behavior of the floating body are integrated, so the tower fixing work can be performed easily and safely. Furthermore, even when the tower is lowered during large-scale repairs, strong winds, waves, etc., the vertical movement of the shaft structure extending from the lower end of the tower is stably guided inside the floating body, so that the tower is fixed. The release and descent work can be performed easily and safely.

本発明ではタワーは浮体内に収納可能とされるため、タワーの下端外径は前記浮体の上端内径よりも小さくなる。従って、タワーの下端と前記浮体の上端との間にリング状部材を介在させることによって両者を接合するようにしている。前記リング状部材を設けることにより、タワーに作用した外力は前記シャフト構造体に伝達されるのではなく、前記浮体に直接的に伝達されるようになる。 In the present invention, since the tower can be housed in the floating body, the outer diameter of the lower end of the tower is smaller than the inner diameter of the upper end of the floating body. Therefore, a ring-shaped member is interposed between the lower end of the tower and the upper end of the floating body to join the two. By providing the ring-shaped member, the external force acting on the tower is not transmitted to the shaft structure, but is directly transmitted to the floating body.

前記リング状部材としては、周方向に分割可能としたものを用いるようにしている。前記タワーの下端から連続してシャフト構造体が設けられているため、前記リング状部材を周方向に分割可能とした部材を用いることによりシャフト構造体があっても支障なくリング状部材をタワーと浮体との間に設置することが可能となる。 As the ring-shaped member, a member that can be divided in the circumferential direction is used. Since the shaft structure is continuously provided from the lower end of the tower, by using a member capable of dividing the ring-shaped member in the circumferential direction, the ring-shaped member can be used as the tower without any problem even if there is a shaft structure. It can be installed between the floating body.

請求項2に係る本発明として、前記シャフト構造体は、骨組構造体又は管状構造体からなる請求項1記載の洋上風力発電設備が提供される。 According to the second aspect of the present invention, the offshore wind power generation facility according to claim 1, wherein the shaft structure is composed of a skeleton structure or a tubular structure.

上記請求項2記載の発明は、前記シャフト構造体の具体的構造例を示したものである。前記シャフト構造体としては、骨組構造体又は管状構造体とするのが望ましい。重量を軽減できる点では、骨組構造体とするのが望ましい。 The invention according to claim 2 shows a specific structural example of the shaft structure. The shaft structure is preferably a skeleton structure or a tubular structure. It is desirable to use a skeleton structure in terms of reducing weight.

請求項に係る本発明として、前記浮体内部に電気設備を備えるとともに、前記電気設備は前記タワー及びシャフト構造体が配置される中央部を避けて周囲に配置されている請求項1、2いずれかに記載の洋上風力発電設備が提供される。 As the present invention according to claim 3, provided with a electrical equipment inside the floating body, the electrical equipment is either the tower and in the claims which are disposed around while avoiding the central portion of the shaft structure is arranged 1, 2 Offshore wind farms listed in Crab are provided.

上記請求項記載の発明では、通常、浮体内部に配設される電気設備をタワーとシャフト構造体が中央部を通過できるように、中央部を避けて周囲に配置するようにしている。また、従来は浮体の上部に電気設備を設置していたが、浮体内部に配置することにより、浮体の重心を下げることができ、浮体の安定度は増すようになる。 In the invention according to claim 3 , usually, the electrical equipment arranged inside the floating body is arranged around the central portion so as to allow the tower and the shaft structure to pass through the central portion. Further, conventionally, the electric equipment is installed on the upper part of the floating body, but by arranging it inside the floating body, the center of gravity of the floating body can be lowered and the stability of the floating body is increased.

請求項に係る本発明として、前記タワー昇降設備は、浮体上部に設けられたデッキ上に、周方向に均等配置された複数のジャッキと、前記シャフト構造体の下端に一端が連結され、他端が前記ジャッキに接続されたPCケーブルとからなる請求項1〜いずれかに記載の洋上風力発電設備が提供される。 According to the fourth aspect of the present invention, the tower elevating equipment has a plurality of jacks evenly arranged in the circumferential direction on a deck provided on the upper part of the floating body, and one end thereof is connected to the lower end of the shaft structure. The offshore wind power generation facility according to any one of claims 1 to 3 is provided, which comprises a PC cable whose end is connected to the jack.

上記請求項記載の発明は、タワー昇降設備の具体的構造例を示したものである。タワー昇降設備としては、浮体上部に設けられたデッキ上に、周方向に均等配置された複数のジャッキと、前記シャフト構造体の下端に一端が連結され、他端が前記ジャッキに接続されたPCケーブルとから構成するのが望ましい。前記PCケーブルの一端をシャフト構造体の下端に連結することにより、タワーの構造をシンプルにできる。 The invention according to claim 4 shows a specific structural example of the tower elevating equipment. As the tower elevating equipment, a plurality of jacks evenly arranged in the circumferential direction on a deck provided on the upper part of the floating body, and a PC having one end connected to the lower end of the shaft structure and the other end connected to the jack. It is desirable to configure it with a cable. By connecting one end of the PC cable to the lower end of the shaft structure, the structure of the tower can be simplified.

請求項に係る本発明として、請求項1〜いずれかに記載の洋上風力発電設備を洋上に設置するための施工方法であって、
洋上にて、浮体を直立に起立させた状態とし、浮体内部に前記シャフト構造体を収容するとともに、このシャフト構造体の上部に前記タワーを連結し、かつ該タワーの上部を前記浮体の上端よりも突出させた状態とする第1手順と、
起重機船により前記タワーの頂部に少なくともナセルを設置する第2手順と、
前記タワー昇降設備によって前記タワーを正規の高さ位置まで引き上げ、タワーの下端と前記浮体の上端とを結合する第3手順とを含むことを特徴とする洋上風力発電設備の施工方法が提供される。
The present invention according to claim 5 is a construction method for installing the offshore wind power generation facility according to any one of claims 1 to 4 at sea.
At sea, the floating body is set to stand upright, the shaft structure is housed inside the floating body, the tower is connected to the upper part of the shaft structure, and the upper part of the tower is connected to the upper end of the floating body. The first step to make it protrude
The second step of installing at least a nacelle on the top of the tower by a crane vessel, and
Provided is a method for constructing an offshore wind power generation facility, which comprises a third step of pulling the tower up to a regular height position by the tower elevating facility and connecting the lower end of the tower and the upper end of the floating body. ..

上記請求項記載の発明は、本洋上風力発電設備の施工方法を示したものである。タワーを下降させた状態でナセルや風車ブレードの取付けができるようになり、高所作業が減って安全に作業ができるようになる。 The invention according to claim 5 shows a method of constructing an offshore wind power generation facility. Nacelles and wind turbine blades can be installed with the tower lowered, reducing work at heights and enabling safe work.

請求項に係る本発明として、風車ブレードの取付けは、前記第2手順から前記第3手順を終えた後までの期間内に段階的又は一括で行うようにする請求項記載の洋上風力発電設備の施工方法が提供される。 According to the sixth aspect of the present invention, the offshore wind power generation according to claim 5 , wherein the wind turbine blades are attached stepwise or collectively within the period from the second procedure to the completion of the third procedure. Equipment construction methods are provided.

上記請求項記載の発明は、風車ブレードの取付け時期について規定したものである。風車ブレードは、具体的には前記第2手順から前記第3手順を終えた後までの期間内に段階的又は一括で行うようすることができる。すなわち、施工手順や施工条件などに合わせて、風車ブレードの取付けは所定の期間内に段階的又は一括で行うようにすればよい。 The invention according to claim 6 defines the mounting timing of the wind turbine blade. Specifically, the wind turbine blades can be operated stepwise or collectively within the period from the second procedure to the completion of the third procedure. That is, the wind turbine blades may be attached stepwise or collectively within a predetermined period according to the construction procedure, construction conditions, and the like.

以上詳説のとおり本発明によれば、浮体内部にタワーが収容され、海上での施工時にタワー昇降設備によってタワーを引上げ、固定するようにしたスパー型洋上風力発電設備において、前記タワーの引上げ作業及び固定作業や前記タワーの固定解除及び下降作業を容易かつ安全に設置が行えるようになる。 As described in detail above, according to the present invention, in a spar-type offshore wind power generation facility in which a tower is housed inside a floating body and the tower is pulled up and fixed by a tower elevating facility during construction at sea, the tower pulling work and It will be possible to easily and safely install the fixing work, the fixing release of the tower, and the lowering work.

本発明に係る洋上風力発電設備1の全体概略図である。It is an overall schematic view of the offshore wind power generation facility 1 which concerns on this invention. プレキャスト筒状体12(13)を示す、(A)は縦断面図、(B)は平面図(B-B線矢視図)、(C)は底面図(C-C線矢視図)である。The precast cylindrical body 12 (13) is shown, (A) is a vertical cross-sectional view, (B) is a plan view (B-B line arrow view), and (C) is a bottom view (C-C line arrow view). プレキャスト筒状体12(13)同士の緊結要領図(A)(B)である。It is a binding procedure diagram (A) (B) between the precast tubular bodies 12 (13). 上側鋼製浮体構造部を示す縦断面図である。It is a vertical cross-sectional view which shows the floating body structure part made of upper steel. 洋上風力発電設備1の要部拡大縦断面図である。It is an enlarged vertical sectional view of the main part of the offshore wind power generation facility 1. 更にその拡大縦断面図である。Further, it is an enlarged vertical sectional view thereof. デッキ部3の平面図(図6のVII−VII線矢視図)である。It is a top view of the deck part 3 (the VII-VII line arrow view of FIG. 6). 浮体2の横断面図(図6のVIII−VIII線矢視図)である。It is a cross-sectional view of a floating body 2 (a view taken along the line VIII-VIII of FIG. 6). 洋上風力発電設備1の施工手順図(その1)である。It is a construction procedure diagram (No. 1) of the offshore wind power generation facility 1. 洋上風力発電設備1の施工手順図(その2)である。It is a construction procedure diagram (No. 2) of the offshore wind power generation facility 1. 洋上風力発電設備1の施工手順図(その3)である。It is a construction procedure diagram (No. 3) of the offshore wind power generation facility 1. 洋上風力発電設備1の施工手順図(その4)である。It is a construction procedure diagram (No. 4) of the offshore wind power generation facility 1. 洋上風力発電設備1の施工手順図(その5)である。It is a construction procedure diagram (No. 5) of the offshore wind power generation facility 1. 洋上風力発電設備1の施工手順図(その6)である。It is a construction procedure diagram (No. 6) of the offshore wind power generation facility 1. タワー5の下端と浮体2の上端との接合要領を示す要部拡大図である。It is an enlarged view of the main part which shows the joining procedure of the lower end of a tower 5 and the upper end of a floating body 2.

以下、本発明の実施の形態について図面を参照しながら詳述する。 Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.

図1に示されるように、洋上風力発電設備1は、浮体2と、この浮体2の上部に設置されたデッキ3と、前記浮体2に繋がれた係留索4、4…と、前記浮体2の上端部に立設されたタワー5と、このタワー5の頂部に設備されたナセル6及び複数の風車ブレード7,7…とからなるものであり、本発明では特に、前記タワー5の下端に連続してシャフト構造体8を一体的に備えるとともに、前記シャフト構造体8は、浮体2内部に設けられたガイド部材によって鉛直方向の移動が案内されているものである。 As shown in FIG. 1, the offshore wind power generation facility 1 includes a floating body 2, a deck 3 installed on the floating body 2, mooring lines 4, 4, ... Connected to the floating body 2, and the floating body 2. It is composed of a tower 5 erected at the upper end of the tower 5, a nacelle 6 installed at the top of the tower 5, and a plurality of wind turbine blades 7, 7 ... The shaft structure 8 is continuously provided integrally, and the shaft structure 8 is guided to move in the vertical direction by a guide member provided inside the floating body 2.

以下、更に具体的に詳述する。 Hereinafter, the details will be described in more detail.

前記浮体2は、上端部を開口させた有底中空部を有するスパー型の浮体構造とし、コンクリート製のプレキャスト筒状体12〜13を高さ方向に複数段積み上げ、各プレキャスト筒状体12〜13をPC鋼材により緊結し一体化を図った下側コンクリート製浮体構造部2Aと、この下側コンクリート浮体構造部2Aの上側に連設された上側鋼製浮体構造部2Bとからなるとともに、下側コンクリート浮体構造部2Aと上側鋼製浮体構造部2Bとの境界部に合成プレキャスト部材13が介在され、両者が接合されている。前記上側鋼製浮体構造部2Bは、高さ方向に段階的に外径寸法が縮小される変断面形状としてある。 The floating body 2 has a spar-type floating body structure having a bottomed hollow portion with an open upper end, and concrete precast tubular bodies 12 to 13 are stacked in a plurality of stages in the height direction, and each precast tubular body 12 to 12 to It is composed of a lower concrete floating structure part 2A in which 13 is tightly connected by a PC steel material and integrated, and an upper steel floating structure part 2B connected to the upper side of the lower concrete floating structure part 2A, and below. A synthetic precast member 13 is interposed at the boundary between the side concrete floating structure portion 2A and the upper steel floating structure portion 2B, and both are joined. The upper steel floating structure portion 2B has a modified cross-sectional shape in which the outer diameter dimension is gradually reduced in the height direction.

前記下側コンクリート浮体構造部2Aは、コンクリート製のプレキャスト筒状体12…と、前記合成プレキャスト部材13の下半部分とで構成されている。前記プレキャスト筒状体12は、図2に示されるように、軸方向に同一断面とされる円形筒状のプレキャスト部材であり、それぞれが同一の型枠を用いて製作されるか、遠心成形により製造された中空プレキャスト部材が用いられる。 The lower concrete floating structure portion 2A is composed of a concrete precast tubular body 12 ... And a lower half portion of the synthetic precast member 13. As shown in FIG. 2, the precast tubular body 12 is a circular tubular precast member having the same cross section in the axial direction, and each is manufactured using the same mold or by centrifugation. The manufactured hollow precast member is used.

壁面内には鉄筋20の他、周方向に適宜の間隔でPC鋼棒19を挿通するためのシース21、21…が埋設されている。このシース21、21…の下端部にはPC鋼棒19同士を連結するためのカップラーを挿入可能とするためにシース拡径部21aが形成されているとともに、上部には定着用アンカープレートを嵌設するための箱抜き部22が形成されている。また、上面には吊り金具23が複数設けられている。 In addition to the reinforcing bars 20, sheaths 21, 21, ... For inserting the PC steel rods 19 at appropriate intervals in the circumferential direction are embedded in the wall surface. A sheath diameter-expanded portion 21a is formed at the lower ends of the sheaths 21, 21 ... To allow a coupler for connecting the PC steel rods 19 to be inserted, and a fixing anchor plate is fitted at the upper portion. A box punching portion 22 for installation is formed. Further, a plurality of hanging metal fittings 23 are provided on the upper surface.

プレキャスト筒状体12同士の緊結は、図3(A)に示されるように、下段側プレキャスト筒状体12から上方に延長されたPC鋼棒19、19…をシース21、21…に挿通させながらプレキャスト筒状体12,12を積み重ねたならば、アンカープレート24を箱抜き部22に嵌設し、ナット部材25によりPC鋼棒19に張力を導入し一体化を図る。また、グラウト注入孔27からグラウト材をシース21内に注入する。なお、前記アンカープレート24に形成された孔24aはグラウト注入確認孔であり、該確認孔からグラウト材が吐出されたことをもってグラウト材の充填を終了する。 As shown in FIG. 3A, the precast tubular bodies 12 are tightly connected by inserting PC steel rods 19, 19 ... Extending upward from the lower precast tubular body 12 into the sheaths 21, 21 ... However, when the precast cylindrical bodies 12 and 12 are stacked, the anchor plate 24 is fitted into the box punching portion 22, and tension is introduced into the PC steel rod 19 by the nut member 25 to integrate them. Further, the grout material is injected into the sheath 21 through the grout injection hole 27. The hole 24a formed in the anchor plate 24 is a grout injection confirmation hole, and filling of the grout material is completed when the grout material is discharged from the confirmation hole.

次に、図3(B)に示されるように、PC鋼棒19の突出部に対してカップラー26を螺合し、上段側のPC鋼棒19、19…を連結したならば、上段となるプレキャスト筒状体12のシース21、21…に前記PC鋼棒19、19…を挿通させながら積み重ね、前記要領によりPC鋼棒19の定着を図る手順を順次繰り返すことにより高さ方向に積み上げられる。この際、下段側プレキャスト筒状体12と上段側プレキャスト筒状体12との接合面には止水性確保及び合わせ面の接合のためにエポキシ樹脂系などの接着剤28やシール材が塗布される。 Next, as shown in FIG. 3B, if the coupler 26 is screwed into the protruding portion of the PC steel rod 19 and the PC steel rods 19, 19 ... On the upper stage side are connected, the upper stage is obtained. The PC steel rods 19, 19 ... Are stacked while being inserted into the sheaths 21, 21 ... Of the precast cylindrical body 12, and the PC steel rods 19 are stacked in the height direction by sequentially repeating the procedure for fixing the PC steel rods 19 according to the above procedure. At this time, an adhesive 28 such as an epoxy resin or a sealing material is applied to the joint surface between the lower precast tubular body 12 and the upper precast tubular body 12 in order to ensure water stoppage and join the mating surfaces. ..

次いで、前記合成プレキャスト部材13は、図4に示されるように、コンクリート製のプレキャスト筒状体16と鋼製筒状体17との合成構造である。これらは一体的に製作される。前記プレキャスト筒状体16は、前記鋼製筒状体17の肉厚分の厚さを減じた外径寸法とされ、この外周に前記鋼製筒状体17の下半部分が外嵌された構造とし、前記プレキャスト筒状体16の上端面がPC鋼棒19の締結面とされる。 Next, as shown in FIG. 4, the synthetic precast member 13 has a composite structure of a concrete precast tubular body 16 and a steel tubular body 17. These are manufactured integrally. The precast tubular body 16 has an outer diameter dimension obtained by subtracting the thickness of the steel tubular body 17 by the wall thickness, and the lower half portion of the steel tubular body 17 is fitted on the outer periphery thereof. The structure is such that the upper end surface of the precast tubular body 16 is the fastening surface of the PC steel rod 19.

前記上側鋼製浮体構造部2Bは、同図4に示されるように、前記合成プレキャスト部材13の上半部分と、鋼製筒状体14,15とで構成されている。下段側の鋼製筒状体14は、合成プレキャスト部材13と同一の外径寸法とされ、合成プレキャスト部材13に対して、ボルト又は溶接等(図示例はボルト締結)によって連結される。上段側の鋼製筒状体15は、前記下段側の鋼製筒状体14よりも外径寸法が縮小され、変断面形状とされ、下段側の鋼製筒状体14に対してボルト又は溶接等によって連結される。前記上段側鋼製筒状体15の上端は開口のままとされるとともに、前記上段側鋼製筒状体15及び下段側鋼製筒状体14との境界部及び下段側鋼製筒状体14と鋼製筒状体17との境界部は空間が仕切られておらず、浮体2内部にはタワー5を収容するための中空部が形成されている。 As shown in FIG. 4, the upper steel floating structure portion 2B is composed of an upper half portion of the synthetic precast member 13 and steel tubular bodies 14 and 15. The steel tubular body 14 on the lower stage side has the same outer diameter as the synthetic precast member 13, and is connected to the synthetic precast member 13 by bolts, welding, or the like (bolt fastening in the illustrated example). The steel tubular body 15 on the upper stage side has an outer diameter smaller than that of the steel tubular body 14 on the lower stage side and has a modified cross-sectional shape. It is connected by welding or the like. The upper end of the upper steel tubular body 15 is left open, and the boundary between the upper steel tubular body 15 and the lower steel tubular body 14 and the lower steel tubular body 14 are left open. The boundary between the 14 and the steel tubular body 17 is not partitioned, and a hollow portion for accommodating the tower 5 is formed inside the floating body 2.

一方、前記タワー5は少なくとも施工時(洋上での組立時)に前記デッキ3上に設けたタワー昇降設備9,9…によって昇降自在とされ、全部又は下端側の大部分が前記浮体2内部に収容可能となっている。前記浮体2の吃水Lは、例えば2MW級発電設備の場合、概ね60m以上に設定される。 On the other hand, the tower 5 is made movable at least by the tower elevating facilities 9, 9 ... Provided on the deck 3 at the time of construction (when assembled at sea), and all or most of the lower end side is inside the floating body 2. It can be accommodated. The draft L of the floating body 2 is set to approximately 60 m or more in the case of, for example, a 2 MW class power generation facility.

前記タワー5の全部が浮体2内部に収容可能とは、予め浮体2の内部にタワー5を収容して曳航する場合を想定するものであり、前記タワー5の下端側の大部分が浮体2内部に収容可能とは、後述のように、浮体2の起立場所でタワー5を浮体2の上端開口から挿入設置する場合を想定するものである。 The fact that all of the tower 5 can be accommodated inside the floating body 2 is based on the assumption that the tower 5 is accommodated inside the floating body 2 in advance and towed, and most of the lower end side of the tower 5 is inside the floating body 2. As will be described later, it is assumed that the tower 5 is inserted and installed from the upper end opening of the floating body 2 at the standing position of the floating body 2.

前記タワー5は、鋼材、コンクリート又はPRC(プレストレスト鉄筋コンクリート)から構成されるものが使用されるが、好ましいのは総重量が小さくなるように鋼材によって製作されたものを用いるのが望ましい。また、前記ナセル6は、風車の回転を電気に変換する発電機やブレードの角度を自動的に変えることができる制御器などが搭載された装置である。 The tower 5 is made of steel, concrete or PRC (prestressed reinforced concrete), but it is preferable to use one made of steel so that the total weight is small. Further, the nacelle 6 is a device equipped with a generator that converts the rotation of the wind turbine into electricity, a controller that can automatically change the angle of the blade, and the like.

前記シャフト構造体8は、詳細には図5及び図6に示されるように、軽量化を図るために、H形鋼や角型形鋼などの形材を組み合わせて構成された骨組構造体とされている。図示例のシャフト構造体8は、図8の横断面図に示されるように、平面視が正六角形状を成す複数のフレーム体8A、8A…を、各隅部に配設された鉛直方向材8B、8B…によって鉛直方向に所定の間隔で連結した構造とされている。前記シャフト構造体8は、供用後も残置されるものであり、かつタワー5の下端位置、すなわち水面近傍ないしそれから数十mの範囲に存在するものであり、浮体2を合わせた全体構造の中では中間乃至それよりも上部側に位置するため、浮体2とタワー5と合わせた構造体の重心を上側に移行させるため、出来る限り軽量化を図り、重心が上側に移動するのを防止するのが望ましい。 As shown in FIGS. 5 and 6 in detail, the shaft structure 8 is a frame structure formed by combining shaped members such as H-shaped steel and square-shaped steel in order to reduce the weight. Has been done. As shown in the cross-sectional view of FIG. 8, the shaft structure 8 of the illustrated example is a vertical member in which a plurality of frame bodies 8A, 8A ... It has a structure in which 8B, 8B ... Are connected in the vertical direction at predetermined intervals. The shaft structure 8 is left behind even after operation, and exists at the lower end position of the tower 5, that is, near the water surface or within a range of several tens of meters from the water surface, and is included in the overall structure including the floating body 2. Then, since it is located in the middle or above it, the center of gravity of the structure including the floating body 2 and the tower 5 is shifted to the upper side, so that the weight is reduced as much as possible and the center of gravity is prevented from moving to the upper side. Is desirable.

前記タワー5との連結は、図6に示されるように、タワー5の本体5Aの下端に連続して鋼製リング状のタワー側接続部材5aが設けられ、前記シャフト構造体8の最上部のフレーム体8A及び上端に設けられた延出部材8aが前記継手部材5aの内面に溶接又はボルト・ナットなどの連結手段により連結され一体化されている。 In connection with the tower 5, as shown in FIG. 6, a steel ring-shaped tower-side connecting member 5a is continuously provided at the lower end of the main body 5A of the tower 5, and the uppermost portion of the shaft structure 8 is connected. The frame body 8A and the extension member 8a provided at the upper end are connected and integrated with the inner surface of the joint member 5a by welding or connecting means such as bolts and nuts.

前記シャフト構造体8は、浮体2の内部に設けられたガイド部材によって鉛直方向の移動が案内されている。具体的には、図6に示されるように、浮体2内部に鉛直方向に沿って複数本の、図示例では3本のガイドレール30が配設されている。これらのガイドレール30、30…は、タワー5の内面に高さ方向に適宜の間隔で周方向に沿って設けられた横T字断面の周方向補強材39によって支持されている。 The shaft structure 8 is guided to move in the vertical direction by a guide member provided inside the floating body 2. Specifically, as shown in FIG. 6, a plurality of guide rails 30 are arranged inside the floating body 2 along the vertical direction, and in the illustrated example, three guide rails 30 are arranged. These guide rails 30, 30 ... Are supported by a circumferential reinforcing member 39 having a lateral T-shaped cross section provided on the inner surface of the tower 5 along the circumferential direction at appropriate intervals in the height direction.

そして、前記シャフト構造体8の角部から水平方向に突出して設けられたブラケット31の先端部が前記ガイドレール30に沿って摺動することにより、シャフト構造体8の鉛直方向の移動が横ブレすることなく円滑に行われるように案内されている。 Then, the tip of the bracket 31 provided so as to project horizontally from the corner of the shaft structure 8 slides along the guide rail 30, so that the vertical movement of the shaft structure 8 is laterally shaken. It is guided so that it can be done smoothly without doing anything.

なお、本形態例では、前記シャフト構造体8を骨組構造により構成したが、鋼管などによって構成された管状構造体とすることも可能である。 In the example of this embodiment, the shaft structure 8 is composed of a skeleton structure, but it is also possible to use a tubular structure composed of a steel pipe or the like.

前記タワー昇降設備9は、図7に示されるように、前記デッキ3上に、周方向に均等配置された複数のセンターホールジャッキ32,32と、前記シャフト構造体8の下端に一端が連結され、他端が前記センターホールジャッキ32に接続されたPCケーブル33とからなる。前記デッキ3上には、センターホールジャッキを駆動するための電動ポンプユニット34が複数配置されている。なお、前記センターホールジャッキに代えてダブルツインジャッキ等を用いてもよい。 As shown in FIG. 7, the tower elevating equipment 9 is connected to a plurality of center hole jacks 32, 32 evenly arranged in the circumferential direction on the deck 3 and one end to the lower end of the shaft structure 8. The other end is a PC cable 33 connected to the center hole jack 32. A plurality of electric pump units 34 for driving the center hole jack are arranged on the deck 3. A double twin jack or the like may be used instead of the center hole jack.

本洋上風力発電設備1では、前記PCケーブル33の一端をタワー5に連結するのではなく、前記シャフト構造体8に連結するため、タワー構造をシンプルな構造とすることができる。 In the offshore wind power generation facility 1, one end of the PC cable 33 is not connected to the tower 5, but is connected to the shaft structure 8, so that the tower structure can be made simple.

また、浮体2には、種々の電気設備35が配設されるが、本発明では、浮体2内部にタワー5及びシャフト構造体8が収容され、鉛直方向に移動可能とされているため、前記電気設備35は、図5に示されるように、前記タワー5及びシャフト構造体8が配置される中央部を避けて周囲に配置されている。すなわち、前記上側鋼製浮体構造部2Bは、高さ方向に段階的に外径寸法が縮小される変断面形状としてあり、前記電気設備35は、相対的に外径寸法の大きな部位であって、前記シャフト構造体8が通過する中央範囲を避けた空間内に収まる寸法とし、周方向に分散して配置されている。 Further, various electric facilities 35 are arranged in the floating body 2, but in the present invention, the tower 5 and the shaft structure 8 are housed inside the floating body 2 and can be moved in the vertical direction. As shown in FIG. 5, the electrical equipment 35 is arranged around the tower 5 and the shaft structure 8 so as to avoid the central portion where the tower 5 and the shaft structure 8 are arranged. That is, the upper steel floating structure portion 2B has a variable cross-sectional shape in which the outer diameter dimension is gradually reduced in the height direction, and the electrical equipment 35 is a portion having a relatively large outer diameter dimension. The dimensions are such that the shaft structure 8 fits in a space avoiding the central range through which the shaft structure 8 passes, and the shaft structures 8 are arranged dispersed in the circumferential direction.

一方、前記タワー5の下端と、浮体2の上部との接合部は、図6に示されるように、上端部の直径が下端部の直径よりも小さい截頭円錐形状のリング状部材であって周方向に分割可能とされた接合部材36によって接合されている。すなわち、タワー5の下端に設けられたタワー側接続部材5aの外径は、浮体2の内部に収容されるため、浮体2の上端部の内径よりも小さく構成されている。そのため、前記接合部材36は、上端部の直径が下端部の直径よりも小さい截頭円錐形状のリング状部材とされている。また、タワー5を引き上げた状態で、浮体2の上部との接合を可能とするため、前記接合部材36は、周方向に分割可能、好ましくは図示例のように、周方向に2分割構造とされている。従って、後述するように、タワー5を引き上げた状態とし、側方から2分割構造の接合部材36をそれぞれ嵌め込んで、周方向に連結するとともに、タワー5の下端とボルト接合し、かつ浮体2の上端とボルト接合する構造となっている。図示例では、前記接合部材36と、タワー5及び浮体2との接続は、内側に向けたフランジ継手が採用されている。前記接合部材36を設けることにより、タワー5に作用した外力は前記シャフト構造体8に伝達されるのではなく、前記浮体2に直接的に伝達されるようになる。 On the other hand, the joint portion between the lower end of the tower 5 and the upper portion of the floating body 2 is a cone-shaped ring-shaped member having a diameter of the upper end portion smaller than the diameter of the lower end portion, as shown in FIG. It is joined by a joining member 36 that can be divided in the circumferential direction. That is, the outer diameter of the tower-side connecting member 5a provided at the lower end of the tower 5 is accommodated inside the floating body 2, so that the outer diameter is smaller than the inner diameter of the upper end portion of the floating body 2. Therefore, the joining member 36 is a ring-shaped member having a cone shape in which the diameter of the upper end portion is smaller than the diameter of the lower end portion. Further, in order to enable joining with the upper part of the floating body 2 with the tower 5 pulled up, the joining member 36 can be divided in the circumferential direction, preferably having a structure divided into two in the circumferential direction as shown in the illustrated example. Has been done. Therefore, as will be described later, the tower 5 is in a pulled-up state, and the joining members 36 having a two-part structure are fitted from the sides, connected in the circumferential direction, bolted to the lower end of the tower 5, and the floating body 2. It has a structure that is bolted to the upper end of the tower. In the illustrated example, a flange joint facing inward is adopted for the connection between the joining member 36 and the tower 5 and the floating body 2. By providing the joining member 36, the external force acting on the tower 5 is not transmitted to the shaft structure 8 but is directly transmitted to the floating body 2.

また、浮体2の海面上には、接舷施設37及び通路デッキ38が設けられ、施工時やメンテナンス時に作業員等が洋上風力発電設備1へ乗り入れできるようになっている。 Further, a side facility 37 and a passage deck 38 are provided on the sea surface of the floating body 2 so that a worker or the like can enter the offshore wind power generation facility 1 at the time of construction or maintenance.

〔施工手順〕
以下、図9〜図15に基づいて、前記洋上風力発電設備1の施工手順について詳述する。
[Construction procedure]
Hereinafter, the construction procedure of the offshore wind power generation facility 1 will be described in detail based on FIGS. 9 to 15.

(第1手順)
製作ヤードに隣接した洋上において、図9に示されるように、浮体2を海上に横向きで浮かべ、曳航船18により起立場所まで曳航する。前記浮体2の内部には予め、前記シャフト構造体8が収納されている。
(First step)
On the ocean adjacent to the production yard, as shown in FIG. 9, the floating body 2 is floated sideways on the sea and towed by a towing vessel 18 to a standing place. The shaft structure 8 is housed in the floating body 2 in advance.

浮体2の下側コンクリート浮体構造部2Aと、上側鋼製浮体構造部2Bとでは、下側コンクリート浮体構造部2A側の方が重いため、バランス調整用浮体42を浮かべるとともに、この浮体上に設置したウインチ43から繰り出されたワイヤの一端を下側コンクリート浮体構造部2Aの端部に連結し、浮体2が水平になるように調整することが望ましい。前記上段側鋼製筒状体15の上端開口は塞がれている。また、浮体2は、海上に横向きで浮かべた状態でバラスト水(水又は海水)を注水し、吃水を調整するようにしてもよい。前記起立場所とは、所定のバラストを投入し浮体2を起立状態とする洋上場所のことである。 Since the lower concrete floating structure 2A of the floating body 2 and the upper steel floating structure 2B are heavier on the lower concrete floating structure 2A side, the balance adjusting floating body 42 is floated and installed on the floating body. It is desirable to connect one end of the wire unwound from the winch 43 to the end of the lower concrete floating structure portion 2A and adjust the floating body 2 so as to be horizontal. The upper end opening of the upper steel tubular body 15 is closed. Further, the floating body 2 may be floated sideways on the sea and ballast water (water or seawater) may be injected to adjust the draft. The standing place is an offshore place where a predetermined ballast is thrown in and the floating body 2 is placed in an standing state.

前記曳航船18により曳航する方法に代えて、図示しないが、浮体2を台船に搭載して洋上設置場所まで運搬し、洋上設置場所にてクレーンで洋上に浮かべるようにしてもよい。この場合、浮体2内にはバラスト水やバラスト材を投入しないことが好ましい。 Instead of the method of towing by the towing vessel 18, although not shown, the floating body 2 may be mounted on a pontoon and transported to an offshore installation location, and floated on the offshore by a crane at the offshore installation location. In this case, it is preferable not to put ballast water or ballast material into the floating body 2.

図10に示されるように、起立場所に到着したならば、浮体2の内部にバラスト41(水又は海水、バラスト材)を投入するとともに、前記バランス調整用浮体42上のウインチ43からワイヤを徐々に繰り出すことにより、ゆっくりと浮体2を直立状態に起立させる。 As shown in FIG. 10, when arriving at the standing place, the ballast 41 (water or seawater, ballast material) is put into the floating body 2, and the wire is gradually drawn from the winch 43 on the balancing floating body 42. By feeding out to, the floating body 2 is slowly raised upright.

前記バラスト材としては、水より高比重である粉粒状のものが使用され、具体的には、砂、砂利、重晶石を含む鉱物類及び鉄、鉛等の金属粉、金属粒を含む金属類のうち一種または複数種の組み合わせからなるものとすることが好ましい。また、適宜モルタルを混合することもできる。 As the ballast material, a powder or granular material having a higher specific gravity than water is used. Specifically, minerals including sand, gravel and heavy crystal stone, metal powder such as iron and lead, and metal containing metal particles are used. It is preferable that it is composed of one or a combination of a plurality of types. In addition, mortar can be mixed as appropriate.

図11に示されるように、バラスト41を注入することによって浮体2を海底に着底させる。 As shown in FIG. 11, the floating body 2 is landed on the seabed by injecting the ballast 41.

前記デッキ3上にタワー昇降設備9を設置し、さらに起重機船44によってタワー5を浮体2内部に吊り降ろし、予め浮体2内部に収納されている前記シャフト構造体8と連結し、一体化を図る。この状態で、タワー5の上部は浮体2の上端より突出させた状態となっている。なお、前記タワー5の突出量は、前記デッキ3上にタワー昇降設備9等が設けられるため、後段の第2手順において、ナセル6の設置作業に支障が出ない程度とする。 The tower elevating equipment 9 is installed on the deck 3, and the tower 5 is further suspended inside the floating body 2 by the crane vessel 44, and is connected to the shaft structure 8 previously stored in the floating body 2 to be integrated. .. In this state, the upper part of the tower 5 is in a state of protruding from the upper end of the floating body 2. The amount of protrusion of the tower 5 is such that the installation work of the nacelle 6 is not hindered in the second procedure of the subsequent stage because the tower elevating equipment 9 and the like are provided on the deck 3.

以上、第1手順についての代表的例を示したが、種々の変更が可能である。具体的に述べると、
(1)上記第1手順では、浮体2を海上に横向きで浮かべ、曳航船18により起立場所まで曳航する際、前記浮体2の内部には前記シャフト構造体8のみを収納するようにしたが、タワー5も浮体2内部に収納して、曳航するようにしてもよい。
The typical example of the first procedure has been shown above, but various changes can be made. Specifically,
(1) In the first procedure, when the floating body 2 is floated sideways on the sea and towed by the towing vessel 18 to the upright position, only the shaft structure 8 is housed inside the floating body 2. The tower 5 may also be housed inside the floating body 2 and towed.

この場合、施工場所において、タワー昇降設備9によりタワー5の上部が浮体2の上端より突出させた状態となるまで引き上げるようにする。
(2)上記第1手順では、前記浮体2の内部に前記シャフト構造体8を収容した状態で起立場所まで曳航したが、シャフト構造体8は収容しない状態で前記浮体2のみを起立場所まで曳航し、起立させた後、別途輸送したシャフト構造体8を前記浮体2内部に挿入するとともに、このシャフト構造体8の上端部に前記タワー5の下端を連結するようにしてもよい。
(3)上記第1手順では、浮体2を着底させるようにしたが、洋上に浮かべたままで作業するようにすることも可能である。この場合は、前記浮体2に係留索4、4…を繋ぎ、浮体2の安定化を図るようにするのが望ましい。
In this case, at the construction site, the tower elevating equipment 9 is used to pull up the tower 5 until the upper part of the tower 5 protrudes from the upper end of the floating body 2.
(2) In the first procedure, the shaft structure 8 was towed to the standing place with the shaft structure 8 housed inside the floating body 2, but only the floating body 2 was towed to the standing place without the shaft structure 8 being housed. Then, after standing up, the separately transported shaft structure 8 may be inserted into the floating body 2 and the lower end of the tower 5 may be connected to the upper end of the shaft structure 8.
(3) In the first procedure described above, the floating body 2 is set to land on the ground, but it is also possible to work while floating on the ocean. In this case, it is desirable to connect the mooring lines 4, 4, ... To the floating body 2 so as to stabilize the floating body 2.

いずれにしても、第1手順では、洋上にて、着底の有無を問わず、浮体2を直立に起立させた状態とし、浮体2内部に前記シャフト構造体8を収容するとともに、このシャフト構造体8の上部に前記タワー5を連結し、かつ該タワー5の上部を前記浮体2の上端よりも突出させた状態とするまでの作業を行う。 In any case, in the first procedure, the floating body 2 is set to stand upright at sea regardless of whether or not it has landed, and the shaft structure 8 is housed inside the floating body 2 and the shaft structure is accommodated. The work is performed until the tower 5 is connected to the upper part of the body 8 and the upper part of the tower 5 is projected from the upper end of the floating body 2.

(第2手順)
次いで、図12に示されるように、起重機船により前記タワー5の頂部に少なくともナセル6を設置する。「少なくともナセル6を設置する」とは、風車ブレード7、7…の内の一部を同時に設置してもよいことを意味する。好ましくは、同図12に示したように、ナセル6とともに、ナセル6よりも上部側に位置させた状態の風車ブレード7(2枚)を含んで設置することが望ましい。
(Second step)
Then, as shown in FIG. 12, at least the nacelle 6 is installed on the top of the tower 5 by a crane vessel. “Installing at least the nacelle 6” means that a part of the wind turbine blades 7, 7, ... May be installed at the same time. Preferably, as shown in FIG. 12, it is desirable to include and install the wind turbine blades 7 (2 blades) in a state of being positioned above the nacelle 6 together with the nacelle 6.

次に、図13に示されるように、タワー昇降設備9により、所定の高さまで引き上げた後、起重機船44により残りの下側に位置させた状態の風車ブレード7を設置し、ナセル6及び風車ブレード7,7…の設置まで作業を完了させる。前記タワー昇降設備9によりタワー5を引き上げる際、本発明ではタワー5の下端から連続して設けられたシャフト構造体8の鉛直方向の移動がガイド部材によってしっかりと案内されていることにより、タワー5を安定的に引き上げることができる。 Next, as shown in FIG. 13, after being pulled up to a predetermined height by the tower elevating equipment 9, the wind turbine blade 7 in a state of being positioned on the remaining lower side by the crane vessel 44 is installed, and the nacelle 6 and the wind turbine are installed. The work is completed until the installation of the blades 7, 7 ... When the tower 5 is pulled up by the tower elevating facility 9, in the present invention, the vertical movement of the shaft structure 8 continuously provided from the lower end of the tower 5 is firmly guided by the guide member, so that the tower 5 is pulled up. Can be raised stably.

(第3手順)
図14に示されるように、前記タワー昇降設備9によって前記タワー5を正規の高さ位置まで引き上げ、タワー5の下端と前記浮体2の上端とを結合する。結合は、前述した接合部材36をタワー5の下端と前記浮体2の上端との間に介在させることにより、両者の結合を図る。具体的には、図15に示されるように、タワー5の下端と前記浮体2の上端との間に、接合部材36の高さ分の空間を空けた状態でタワー5を保持し、側方から2分割構造の接合部材36A、36Bをぞれぞれ嵌め込んで、周方向に連結するとともに、タワー5の下端とボルト接合し、かつ浮体2の上端とボルト接合する。本発明では、前記タワー5を浮体2に連結する際にも、前記タワー5の下端から延びたシャフト構造体8が浮体2の内部に安定的に支持されていることにより、波に揺れる洋上であっても、タワー5の挙動と浮体2の挙動とが一体的となるため、タワー5の固定作業が容易かつ安全に行えるようになる。
(Third step)
As shown in FIG. 14, the tower elevating equipment 9 raises the tower 5 to a regular height position and connects the lower end of the tower 5 and the upper end of the floating body 2. The connection is achieved by interposing the above-mentioned joining member 36 between the lower end of the tower 5 and the upper end of the floating body 2. Specifically, as shown in FIG. 15, the tower 5 is held sideways with a space corresponding to the height of the joining member 36 between the lower end of the tower 5 and the upper end of the floating body 2. The joining members 36A and 36B having a two-part structure are fitted into the joint members 36A and 36B, respectively, and connected in the circumferential direction, and are bolted to the lower end of the tower 5 and to the upper end of the floating body 2. In the present invention, even when the tower 5 is connected to the floating body 2, the shaft structure 8 extending from the lower end of the tower 5 is stably supported inside the floating body 2, so that the tower 5 is stably supported inside the floating body 2 and thus is swayed by waves at sea. Even if there is, since the behavior of the tower 5 and the behavior of the floating body 2 are integrated, the fixing work of the tower 5 can be easily and safely performed.

(第4手順)
バラスト水を浮体から抜いて、浮体2を浮かべたならば、浮体2に係留索4,4…を設置する(図1参照)。
(4th step)
After the ballast water is drained from the floating body and the floating body 2 is floated, mooring lines 4, 4 ... Are installed on the floating body 2 (see FIG. 1).

なお、浮体2を浮かべた状態とした後、設置場所まで曳航し、設置場所で浮体に係留索4,4…を設置するようにしてもよい。 After the floating body 2 is floated, it may be towed to the installation location and mooring lines 4, 4 ... May be installed on the floating body at the installation location.

前記タワー昇降設備9は、そのまま残置しても良いし、撤去してもよい。残置した場合は、将来のメンテナンス補修時等に、残置したタワー昇降設備9によってタワー5を下降させることにより、大規模修繕をより低コストで行うことが可能となる。この際、浮体2内部にはシャフト構造体8が存在しているため、タワー5の下降・上昇を容易かつ安全に行うことが可能である。なお、前記タワー昇降設備9を撤去した場合は、大規模修繕時に再度、前記タワー昇降設備9を設置するようにすればよい。 The tower elevating equipment 9 may be left as it is or may be removed. If the tower is left behind, the tower 5 can be lowered by the left-over tower elevating equipment 9 at the time of maintenance repair in the future, so that large-scale repair can be performed at a lower cost. At this time, since the shaft structure 8 exists inside the floating body 2, the tower 5 can be easily and safely lowered and raised. If the tower elevating equipment 9 is removed, the tower elevating equipment 9 may be installed again at the time of large-scale repair.

〔他の形態例〕
(1)上記形態例では、前記浮体2の構造を、下側コンクリート製浮体構造部2Aと上側鋼製浮体構造部2Bとからなるハイブリッド構造としたが、すべてがコンクリート製の浮体構造としても良いし、すべてが鋼製の浮体構造としてもよい。
[Other form examples]
(1) In the above embodiment, the structure of the floating body 2 is a hybrid structure including a lower concrete floating body structure 2A and an upper steel floating structure 2B, but all of them may be a concrete floating structure. However, it may be a floating structure made entirely of steel.

(2)上記形態例では、ナセル6及び風車ブレード7,7…の設置をタワー5の引上げる前と引き上げた後で段階的に行うようにしたが、最初にナセル6のみを取付け、タワー5を引き上げた後に3枚の風車ブレードを順に取り付けるようにしてもよいし、タワー5を引き上げた後に、ナセル6と風車ブレード7,7…とを一括で取り付けるようにしてもよい。 (2) In the above embodiment, the nacelle 6 and the wind turbine blades 7, 7 ... Are installed in stages before and after the tower 5 is pulled up, but only the nacelle 6 is installed first and the tower 5 is installed. The three wind turbine blades may be attached in order after the tower 5 is pulled up, or the nacelle 6 and the wind turbine blades 7, 7 ... May be attached at once after the tower 5 is pulled up.

(3)上記形態例では、タワー5の下端と前記浮体2の上端とを結合する第3手順の前に、残りの1枚の風車ブレード7,7…を取付け、すべての風車ブレード7の取付けを完了させるようにしたが、タワー5の下端と前記浮体2の上端とを結合する第3手順の後に、残りの1枚の風車ブレード7を取り付けるようにしてもよい。 (3) In the above embodiment, the remaining one wind turbine blades 7, 7 ... Are attached and all the wind turbine blades 7 are attached before the third step of connecting the lower end of the tower 5 and the upper end of the floating body 2. However, the remaining one wind turbine blade 7 may be attached after the third step of connecting the lower end of the tower 5 and the upper end of the floating body 2.

(4)前記形態例では、前記タワー5の下端と、浮体2の上部との接合部は、図6に示されるように、上端部の直径が下端部の直径よりも小さい截頭円錐形状のリング状部材であって周方向に分割可能とされた接合部材36によって接合するようにしたが、平板状のリング状部材によって両者を接合するようにしてもよい。これらのリング状部材は、シャフト構造体8を取り付けた状態のまま、接合部材36の取付けが出来るように周方向に分割可能な構造としたが、タワー5とシャフト構造体8とを分離させるとともに、両者を一旦仮受け支持した状態とし、タワー5と浮体2との間に周方向に連続したリング状部材を挿入し、タワー5と浮体2とを前記周方向に連続したリング状部材を介して接合するようにしてもよい。 (4) In the above embodiment, the joint portion between the lower end of the tower 5 and the upper portion of the floating body 2 has a head cone shape in which the diameter of the upper end portion is smaller than the diameter of the lower end portion, as shown in FIG. Although the ring-shaped member is joined by the joining member 36 which is divisible in the circumferential direction, the two may be joined by the flat plate-shaped ring-shaped member. These ring-shaped members have a structure that can be divided in the circumferential direction so that the joining member 36 can be attached while the shaft structure 8 is attached. However, the tower 5 and the shaft structure 8 are separated from each other. , Both are temporarily supported and supported, a ring-shaped member continuous in the circumferential direction is inserted between the tower 5 and the floating body 2, and the tower 5 and the floating body 2 are connected via the ring-shaped member continuous in the circumferential direction. May be joined.

1…洋上風力発電設備、2…浮体、3…デッキ、4…係留索、5…タワー、6…ナセル、7…風車ブレード、8…シャフト構造体、9…タワー昇降設備、30…ガイドレール、31…ブラケット、32…センターホールジャッキ、33…PCケーブル、34…電動ポンプユニット 1 ... Offshore wind power generation equipment, 2 ... Floating body, 3 ... Deck, 4 ... Mooring line, 5 ... Tower, 6 ... Nacelle, 7 ... Wind turbine blade, 8 ... Shaft structure, 9 ... Tower lifting equipment, 30 ... Guide rail, 31 ... Bracket, 32 ... Center hole jack, 33 ... PC cable, 34 ... Electric pump unit

Claims (6)

浮体と、係留索と、タワーと、タワーの頂部に設備されるナセル及び複数の風車ブレードとからなり、前記浮体は、上端部を開口させた有底中空部を有するスパー型の浮体構造とし、前記タワーは全部又は下端側の大部分が前記浮体内部に収容可能とされるとともに、前記タワーがタワー昇降設備によって昇降自在とされた洋上風力発電設備において、
前記タワーの下端に連続してシャフト構造体を一体的に備えるとともに、前記シャフト構造体は、浮体内部に設けられたガイド部材によって鉛直方向の移動が案内され
前記タワーの下端と前記浮体の上端との接合部は、周方向に分割可能とされたリング状部材によって接合されていることを特徴とする洋上風力発電設備。
It consists of a floating body, a mooring line, a tower, a nacelle installed at the top of the tower, and a plurality of wind turbine blades. In an offshore wind power generation facility in which all or most of the lower end side of the tower can be accommodated inside the floating body and the tower can be raised and lowered by the tower raising and lowering facility.
A shaft structure is integrally provided at the lower end of the tower, and the shaft structure is guided to move in the vertical direction by a guide member provided inside the floating body .
An offshore wind power generation facility characterized in that a joint portion between the lower end of the tower and the upper end of the floating body is joined by a ring-shaped member that can be divided in the circumferential direction.
前記シャフト構造体は、骨組構造体又は管状構造体からなる請求項1記載の洋上風力発電設備。 The offshore wind power generation facility according to claim 1, wherein the shaft structure is composed of a skeleton structure or a tubular structure. 前記浮体内部に電気設備を備えるとともに、前記電気設備は前記タワー及びシャフト構造体が配置される中央部を避けて周囲に配置されている請求項1、2いずれかに記載の洋上風力発電設備。 The offshore wind power generation facility according to any one of claims 1 and 2 , wherein an electric facility is provided inside the floating body, and the electric facility is arranged around the tower and a shaft structure so as to avoid a central portion where the tower and the shaft structure are arranged. 前記タワー昇降設備は、浮体上部に設けられたデッキ上に、周方向に均等配置された複数のジャッキと、前記シャフト構造体の下端に一端が連結され、他端が前記ジャッキに接続されたPCケーブルとからなる請求項1〜いずれかに記載の洋上風力発電設備。 The tower elevating equipment is a PC having a plurality of jacks evenly arranged in the circumferential direction on a deck provided on the upper part of the floating body, one end connected to the lower end of the shaft structure, and the other end connected to the jack. The offshore wind power generation facility according to any one of claims 1 to 3, which comprises a cable. 請求項1〜いずれかに記載の洋上風力発電設備を洋上に設置するための施工方法であって、
洋上にて、浮体を直立に起立させた状態とし、浮体内部に前記シャフト構造体を収容するとともに、このシャフト構造体の上部に前記タワーを連結し、かつ該タワーの上部を前記浮体の上端よりも突出させた状態とする第1手順と、
起重機船により前記タワーの頂部に少なくともナセルを設置する第2手順と、
前記タワー昇降設備によって前記タワーを正規の高さ位置まで引き上げ、タワーの下端と前記浮体の上端とを結合する第3手順とを含むことを特徴とする洋上風力発電設備の施工方法。
A construction method for installing the offshore wind power generation facility according to any one of claims 1 to 4 at sea.
At sea, the floating body is set to stand upright, the shaft structure is housed inside the floating body, the tower is connected to the upper part of the shaft structure, and the upper part of the tower is connected to the upper end of the floating body. The first step to make it protrude
The second step of installing at least a nacelle on the top of the tower by a crane vessel, and
A method for constructing an offshore wind power generation facility, which comprises a third step of pulling the tower up to a regular height position by the tower elevating facility and connecting the lower end of the tower and the upper end of the floating body.
風車ブレードの取付けは、前記第2手順から前記第3手順を終えた後までの期間内に段階的又は一括で行うようにする請求項記載の洋上風力発電設備の施工方法。 The method for constructing an offshore wind power generation facility according to claim 5 , wherein the wind turbine blades are attached stepwise or collectively within the period from the second procedure to the completion of the third procedure.
JP2017136733A 2016-07-13 2017-07-13 Offshore wind power generation equipment and its construction method Active JP6937627B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2016138282 2016-07-13
JP2016138282 2016-07-13

Publications (2)

Publication Number Publication Date
JP2018016302A JP2018016302A (en) 2018-02-01
JP6937627B2 true JP6937627B2 (en) 2021-09-22

Family

ID=61075826

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017136733A Active JP6937627B2 (en) 2016-07-13 2017-07-13 Offshore wind power generation equipment and its construction method

Country Status (1)

Country Link
JP (1) JP6937627B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7474669B2 (en) 2020-09-29 2024-04-25 戸田建設株式会社 How to mount a wind turbine on an offshore wind power generation facility

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0645977B2 (en) * 1988-01-27 1994-06-15 株式会社大林組 Lift up or down construction method
JP3648146B2 (en) * 2000-10-16 2005-05-18 株式会社ピーエス三菱 Wind power tower
JP4701047B2 (en) * 2005-09-07 2011-06-15 株式会社竹中工務店 Wind power tower construction method
JP5330048B2 (en) * 2009-03-24 2013-10-30 戸田建設株式会社 Installation method of offshore wind power generation equipment
JP5274329B2 (en) * 2009-03-24 2013-08-28 戸田建設株式会社 Offshore wind power generation facility and its construction method
US8919074B2 (en) * 2009-07-13 2014-12-30 Vsl International Ag Telescopic tower assembly and method
DK2374966T3 (en) * 2010-04-06 2016-11-07 Soletanche Freyssinet A method of building a hybrid tower for a wind turbine

Also Published As

Publication number Publication date
JP2018016302A (en) 2018-02-01

Similar Documents

Publication Publication Date Title
JP5274329B2 (en) Offshore wind power generation facility and its construction method
JP5330048B2 (en) Installation method of offshore wind power generation equipment
JP6108445B2 (en) Floating offshore wind power generation facility
US10934735B2 (en) Tower erecting systems and methods
JP2010223114A5 (en)
EP3102822B1 (en) Method of assembling a floating wind turbine platform
JP5738644B2 (en) Installation method of offshore wind power generation equipment
CN102767303B (en) Precast concrete tower and construction method thereof
US10107265B2 (en) Foundation for a wind turbine and method of making same
US20180030962A1 (en) Offshore deployable floating wind turbine system and method
JP6270527B2 (en) Installation method of offshore wind power generation equipment
EP3130796A1 (en) Wind turbine assembly system and related method
US20180030961A1 (en) Offshore deployable wind turbine system and method with a gravity base
JP5738643B2 (en) Installation method of offshore wind power generation equipment
WO2018018103A1 (en) Offshore deployable wind turbine system and method with a gravity base
JP6937627B2 (en) Offshore wind power generation equipment and its construction method
JP5738642B2 (en) Installation method of offshore wind power generation equipment
WO2018018104A1 (en) Offshore deployable floating wind turbine system and method
WO2023095335A1 (en) Method for mounting windmill on offshore wind power generation facility
JP7474669B2 (en) How to mount a wind turbine on an offshore wind power generation facility
JP2018173011A (en) Method for constructing floating body of floating offshore wind power generation facility
CN205653811U (en) Marine fan gravity type foundation and basic system
GB2534851A (en) Turbine support structure
DE102011102371A1 (en) Lifting unit for construction, maintenance and demounting of wind energy plants, has tower structure, such that outer side of tower structure is moved freely up and down, where tower shaft is trained for free movability of lifting unit

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200708

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210520

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210531

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210726

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210817

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210831

R150 Certificate of patent or registration of utility model

Ref document number: 6937627

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150