JP6852753B2 - Elevator device - Google Patents

Elevator device Download PDF

Info

Publication number
JP6852753B2
JP6852753B2 JP2019102756A JP2019102756A JP6852753B2 JP 6852753 B2 JP6852753 B2 JP 6852753B2 JP 2019102756 A JP2019102756 A JP 2019102756A JP 2019102756 A JP2019102756 A JP 2019102756A JP 6852753 B2 JP6852753 B2 JP 6852753B2
Authority
JP
Japan
Prior art keywords
hoistway
hoistway wall
plate
scaffolding
car
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019102756A
Other languages
Japanese (ja)
Other versions
JP2020196564A (en
Inventor
義和 杉山
義和 杉山
武史 堀
武史 堀
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Electric Building Techno-Service Co Ltd
Original Assignee
Mitsubishi Electric Building Techno-Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Electric Building Techno-Service Co Ltd filed Critical Mitsubishi Electric Building Techno-Service Co Ltd
Priority to JP2019102756A priority Critical patent/JP6852753B2/en
Priority to CN202010428681.7A priority patent/CN112010128A/en
Publication of JP2020196564A publication Critical patent/JP2020196564A/en
Application granted granted Critical
Publication of JP6852753B2 publication Critical patent/JP6852753B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B5/00Applications of checking, fault-correcting, or safety devices in elevators
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B9/00Kinds or types of lifts in, or associated with, buildings or other structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F17/00Vertical ducts; Channels, e.g. for drainage
    • E04F17/005Lift shafts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/04Means for fastening, supporting, or bracing scaffolds on or against building constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/08Scaffold boards or planks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Maintenance And Inspection Apparatuses For Elevators (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
  • Cage And Drive Apparatuses For Elevators (AREA)

Description

この発明は、エレベーター装置に関する。 The present invention relates to an elevator device.

特許文献1に、昇降路に設置された機器を点検する際に使用される作業台が記載されている。特許文献1に記載された作業台は、制御盤の下方に収納される。エレベーターの保守員は、作業台を組み立てて作業台に上り、制御盤の点検を行う。 Patent Document 1 describes a workbench used when inspecting equipment installed in a hoistway. The workbench described in Patent Document 1 is housed below the control panel. Elevator maintenance personnel assemble the workbench, go up to the workbench, and inspect the control panel.

特開2013−18618号公報Japanese Unexamined Patent Publication No. 2013-18618

エレベーター装置では、昇降路に種々の機器が設置される。特許文献1に記載されたエレベーター装置では、作業台を制御盤の点検のためにしか使用することができない。例えば、制御盤から離れた位置に他の機器が設置されている場合は、もう一つの作業台が必要になる。機器ごとに作業台を組み立てる必要があり、機器の点検に時間と手間とが掛かるといった問題があった。 In the elevator device, various devices are installed in the hoistway. In the elevator device described in Patent Document 1, the workbench can be used only for inspection of the control panel. For example, if other equipment is installed away from the control panel, another workbench is required. It is necessary to assemble a workbench for each device, and there is a problem that it takes time and effort to inspect the device.

この発明は、上述のような課題を解決するためになされた。この発明の目的は、昇降路に設置された機器の点検を効率良く行うことができるエレベーター装置を提供することである。 The present invention has been made to solve the above-mentioned problems. An object of the present invention is to provide an elevator device capable of efficiently inspecting equipment installed in a hoistway.

この発明に係るエレベーター装置は、エレベーターの昇降路に設けられ、つり合いおもりの移動を案内するガイドレールと、昇降路のピットに設けられ、ガイドレール及び第1昇降路壁の間に配置された巻上機と、ピットに設けられ、第1昇降路壁に対向する第2昇降路壁に隣接するように配置された制御装置と、第2昇降路壁に設けられ、制御装置の下方に配置された受け金と、作業足場と、を備える。つり合いおもりと巻上機とは、平面視において、第1昇降路壁と第2昇降路壁との間に形成された第3昇降路壁に沿うように並んで配置される。作業足場は、第1端部が受け金に着脱可能な足場板と、足場板の第2端部に設けられた脚と、を備える。足場板は、第1端部が受け金に取り付けられると、ガイドレールと第1昇降路壁との距離より第2端部と第1昇降路壁との距離の方が短くなるように、第2昇降路壁から突出するように配置される。 The elevator device according to the present invention is provided in a hoistway of an elevator and is provided in a guide rail for guiding the movement of a balanced weight, and a winding is provided in a pit of the hoistway and is arranged between the guide rail and the first hoistway wall. The upper machine, the control device provided in the pit and arranged so as to be adjacent to the second hoistway wall facing the first hoistway wall, and the control device provided on the second hoistway wall and arranged below the control device. It is equipped with a receipt and a work scaffold. The balance weight and the hoisting machine are arranged side by side along the third hoistway wall formed between the first hoistway wall and the second hoistway wall in a plan view. The work scaffold includes a scaffold plate whose first end can be attached to and detached from a receiver, and legs provided at the second end of the scaffold plate. The scaffolding plate is provided so that when the first end is attached to the receiver, the distance between the second end and the first hoistway wall is shorter than the distance between the guide rail and the first hoistway wall. 2 Arranged so as to protrude from the hoistway wall.

この発明に係るエレベーター装置であれば、昇降路に設置された機器の点検を効率良く行うことができる。 With the elevator device according to the present invention, it is possible to efficiently inspect the equipment installed in the hoistway.

実施の形態1におけるエレベーター装置の例を示す図である。It is a figure which shows the example of the elevator apparatus in Embodiment 1. FIG. 図1のA−A断面を示す図である。It is a figure which shows the AA cross section of FIG. 図2のB−B断面を示す図である。It is a figure which shows the BB cross section of FIG. 受け金の例を示す斜視図である。It is a perspective view which shows the example of the receipt. 図3のC−C断面を示す図である。It is a figure which shows the CC cross section of FIG. 実施の形態1におけるエレベーター装置の他の例を示す図である。It is a figure which shows another example of the elevator apparatus in Embodiment 1. FIG.

添付の図面を参照し、本発明を説明する。重複する説明は、適宜簡略化或いは省略する。各図において、同一の符号は同一の部分又は相当する部分を示す。 The present invention will be described with reference to the accompanying drawings. Overlapping description will be simplified or omitted as appropriate. In each figure, the same reference numerals indicate the same parts or corresponding parts.

実施の形態1.
図1は、実施の形態1におけるエレベーター装置の例を示す図である。図2は、図1のA−A断面を示す図である。図3は、図2のB−B断面を示す図である。
Embodiment 1.
FIG. 1 is a diagram showing an example of an elevator device according to the first embodiment. FIG. 2 is a diagram showing a cross section taken along the line AA of FIG. FIG. 3 is a diagram showing a BB cross section of FIG.

エレベーター装置は、かご1及びつり合いおもり2を備える。かご1は、昇降路3を上下に移動する。かご1及びつり合いおもり2は、主ロープ4によって昇降路3に吊り下げられる。つり合いおもり2は、かご1が移動する方向とは反対の方向に昇降路3を移動する。 The elevator device includes a basket 1 and a balance weight 2. The car 1 moves up and down in the hoistway 3. The car 1 and the balance weight 2 are suspended from the hoistway 3 by the main rope 4. The balance weight 2 moves in the hoistway 3 in the direction opposite to the direction in which the car 1 moves.

かご1の移動は、一対のガイドレール5によって案内される。ガイドレール5は、昇降路3に鉛直に設けられる。平面視において、かご1は、ガイドレール5の間に配置される。ガイドレール5は、昇降路3のピット3aから昇降路3の頂部に亘って配置される。つり合いおもり2は、一対のガイドレール6によって案内される。ガイドレール6は、昇降路3に鉛直に設けられる。平面視において、つり合いおもり2は、ガイドレール6の間に配置される。ガイドレール6は、昇降路3のピット3aから昇降路3の頂部に亘って配置される。 The movement of the car 1 is guided by a pair of guide rails 5. The guide rail 5 is provided vertically on the hoistway 3. In plan view, the car 1 is arranged between the guide rails 5. The guide rail 5 is arranged from the pit 3a of the hoistway 3 to the top of the hoistway 3. The balance weight 2 is guided by a pair of guide rails 6. The guide rail 6 is provided vertically on the hoistway 3. In plan view, the counterweight 2 is arranged between the guide rails 6. The guide rail 6 is arranged from the pit 3a of the hoistway 3 to the top of the hoistway 3.

図2に示すように、昇降路3のピット3aは、昇降路壁7〜10に四方が囲まれる。エレベーターの乗場の出入口は、昇降路壁7に形成される。昇降路壁8は、乗場から見て奥側の壁である。昇降路壁8は、昇降路壁7に対向する。昇降路壁8は、昇降路壁9及び10の間に形成される。昇降路壁9は、乗場から見て左側の壁である。昇降路壁10は、乗場から見て右側の壁である。昇降路壁9及び10は、互いに対向する。 As shown in FIG. 2, the pit 3a of the hoistway 3 is surrounded on all sides by the hoistway walls 7 to 10. The entrance / exit of the elevator platform is formed on the hoistway wall 7. The hoistway wall 8 is a wall on the back side when viewed from the landing. The hoistway wall 8 faces the hoistway wall 7. The hoistway wall 8 is formed between the hoistway walls 9 and 10. The hoistway wall 9 is a wall on the left side when viewed from the landing. The hoistway wall 10 is a wall on the right side when viewed from the landing. The hoistway walls 9 and 10 face each other.

主ロープ4は、巻上機11の駆動綱車12に巻き掛けられる。かご1及びつり合いおもり2は、駆動綱車12の回転に応じて移動する。即ち、かご1は、巻上機11によって駆動される。巻上機11は、昇降路3のピット3aに設けられる。巻上機11は、例えば支持装置13の上に固定される。巻上機11は、支持装置13に支持されることにより、ピット3aの底面から一定の高さに配置される。 The main rope 4 is wound around the drive sheave 12 of the hoisting machine 11. The car 1 and the balance weight 2 move according to the rotation of the drive sheave 12. That is, the car 1 is driven by the hoisting machine 11. The hoisting machine 11 is provided in the pit 3a of the hoistway 3. The hoisting machine 11 is fixed on, for example, the support device 13. The hoisting machine 11 is arranged at a constant height from the bottom surface of the pit 3a by being supported by the support device 13.

巻上機11及びガイドレール6は、ピット3aにおいて、昇降路壁8に隣接するように配置される。例えば、平面視において、巻上機11及びつり合いおもり2は、奥側の昇降路壁8に沿うように並んで配置される。巻上機11は、昇降路壁10にも隣接するように配置される。巻上機11は、乗場から見てガイドレール6の右側に配置される。ガイドレール6の一方は、昇降路壁9にも隣接する。巻上機11は、ガイドレール6と昇降路壁10との間に配置される。つり合いおもり2は、平面視において、巻上機11と昇降路壁9との間に配置される。 The hoisting machine 11 and the guide rail 6 are arranged in the pit 3a so as to be adjacent to the hoistway wall 8. For example, in a plan view, the hoisting machine 11 and the balance weight 2 are arranged side by side along the hoistway wall 8 on the back side. The hoisting machine 11 is arranged so as to be adjacent to the hoistway wall 10. The hoisting machine 11 is arranged on the right side of the guide rail 6 when viewed from the landing. One of the guide rails 6 is also adjacent to the hoistway wall 9. The hoisting machine 11 is arranged between the guide rail 6 and the hoistway wall 10. The balance weight 2 is arranged between the hoisting machine 11 and the hoistway wall 9 in a plan view.

巻上機11は、制御装置14によって制御される。即ち、制御装置14は、かご1の移動を制御する。制御装置14は、昇降路3のピット3aに設けられる。例えば、昇降路壁9に近い一方のガイドレール5と一方のガイドレール6との間に支持装置(図示せず)が設けられる。制御装置14は、この支持装置に支持される。制御装置14は、支持装置に支持されることにより、ピット3aの底面から一定の高さに配置される。制御装置14は、昇降路壁9に隣接するように配置される。例えば、平面視において、制御装置14は、かご1と昇降路壁9との間に配置される。 The hoisting machine 11 is controlled by the control device 14. That is, the control device 14 controls the movement of the car 1. The control device 14 is provided in the pit 3a of the hoistway 3. For example, a support device (not shown) is provided between one guide rail 5 near the hoistway wall 9 and one guide rail 6. The control device 14 is supported by this support device. The control device 14 is arranged at a constant height from the bottom surface of the pit 3a by being supported by the support device. The control device 14 is arranged so as to be adjacent to the hoistway wall 9. For example, in a plan view, the control device 14 is arranged between the car 1 and the hoistway wall 9.

本実施の形態に示す例では、昇降路3のピット3aに、巻上機11と制御装置14とが設けられる。エレベーターの保守員は、昇降路3のピット3aにおいて、巻上機11及び制御装置14の点検を行う。このため、本実施の形態に示す例では、昇降路3のピット3aに、保守員が点検時に使用するための作業足場15が備えられる。 In the example shown in this embodiment, the hoisting machine 11 and the control device 14 are provided in the pit 3a of the hoistway 3. The elevator maintenance staff inspects the hoisting machine 11 and the control device 14 in the pit 3a of the hoistway 3. Therefore, in the example shown in the present embodiment, the pit 3a of the hoistway 3 is provided with a work scaffold 15 for use by maintenance personnel during inspection.

作業足場15は、保守員が使用する際に保守員によって取り付けられる。保守員は、点検が終了すると、作業足場15を取り外してピット3aに収納する。作業足場15は、例えば足場板16と脚17とを備える。また、作業足場15を取り付けるための受け金18が昇降路壁9に設けられる。 The work scaffold 15 is attached by the maintenance personnel when used by the maintenance personnel. When the inspection is completed, the maintenance staff removes the work scaffold 15 and stores it in the pit 3a. The work scaffold 15 includes, for example, a scaffold plate 16 and legs 17. Further, a receiver 18 for attaching the work scaffold 15 is provided on the hoistway wall 9.

図4は、受け金18の例を示す斜視図である。受け金18は、作業足場15を支持するための部材である。受け金18は、昇降路壁9に設けられる。受け金18は、制御装置14の下方に配置される。図4に示す例では、受け金18は、全体としてL字形状である。受け金18は、例えば板部19、及び板部20を備える。 FIG. 4 is a perspective view showing an example of the receiver 18. The receiver 18 is a member for supporting the work scaffold 15. The receiver 18 is provided on the hoistway wall 9. The receiver 18 is arranged below the control device 14. In the example shown in FIG. 4, the receiver 18 has an L-shape as a whole. The receiver 18 includes, for example, a plate portion 19 and a plate portion 20.

板部19は、昇降路壁9に沿うように配置される。例えば、昇降路壁9にアンカーボルト21が設けられる。アンカーボルト21は、制御装置14の下方に配置される。板部19は、アンカーボルト21を介して昇降路壁9に固定される。板部20は、板部19の下端部から昇降路壁10側に突出するように設けられる。板部20の上面にねじ孔20aが形成される。 The plate portion 19 is arranged along the hoistway wall 9. For example, an anchor bolt 21 is provided on the hoistway wall 9. The anchor bolt 21 is arranged below the control device 14. The plate portion 19 is fixed to the hoistway wall 9 via anchor bolts 21. The plate portion 20 is provided so as to project from the lower end portion of the plate portion 19 toward the hoistway wall 10. A screw hole 20a is formed on the upper surface of the plate portion 20.

作業足場15の足場板16は、一方の端部16aが受け金18に着脱可能である。図5は、図3のC−C断面を示す図である。図5は、足場板16の端部16aが受け金18に取り付けられた例を示す。例えば、足場板16の端部16aに貫通孔16cが形成される。足場板16は、端部16aが受け金18の板部20に載せられた状態で貫通孔16cを貫通したボルト22がねじ孔20aにねじ込まれることにより、受け金18に取り付けられる。ボルト22を緩めることにより、足場板16を受け金18から外すことができる。 The scaffolding plate 16 of the work scaffolding 15 has one end 16a attached to and detached from the receiver 18. FIG. 5 is a diagram showing a CC cross section of FIG. FIG. 5 shows an example in which the end portion 16a of the scaffolding plate 16 is attached to the receiver 18. For example, a through hole 16c is formed in the end portion 16a of the scaffolding plate 16. The scaffolding plate 16 is attached to the receiving metal 18 by screwing a bolt 22 penetrating the through hole 16c into the screw hole 20a with the end portion 16a placed on the plate portion 20 of the receiving metal 18. By loosening the bolt 22, the scaffolding plate 16 can be removed from the receiving metal 18.

脚17は、足場板16のもう一方の端部16bに設けられる。脚17は、足場板16に対して折り畳み可能である。足場板16の端部16aは、受け金18に支持される。足場板16の端部16bは、脚17に支持される。脚17は、図2に示すように梯子状であることが好ましい。保守員は、脚17から足場板16の上に移動することができる。 The legs 17 are provided at the other end 16b of the scaffolding plate 16. The legs 17 are foldable with respect to the scaffolding plate 16. The end portion 16a of the scaffolding plate 16 is supported by the receiver 18. The end portion 16b of the scaffolding plate 16 is supported by the legs 17. The legs 17 are preferably ladder-shaped as shown in FIG. The maintenance personnel can move from the legs 17 onto the scaffolding board 16.

足場板16は、端部16aが受け金18に取り付けられると、図2に示すように昇降路壁9から突出するように配置される。足場板16の端部16bは、ガイドレール6より昇降路壁10に近い位置に配置される。即ち、足場板16の端部16aが受け金18に取り付けられると、ガイドレール6と昇降路壁10との距離より、足場板16の端部16bと昇降路壁10との距離の方が短くなる。 The scaffolding plate 16 is arranged so as to protrude from the hoistway wall 9 as shown in FIG. 2 when the end portion 16a is attached to the receiver 18. The end portion 16b of the scaffolding plate 16 is arranged at a position closer to the hoistway wall 10 than the guide rail 6. That is, when the end portion 16a of the scaffolding plate 16 is attached to the receiver 18, the distance between the end portion 16b of the scaffolding plate 16 and the hoistway wall 10 is shorter than the distance between the guide rail 6 and the hoistway wall 10. Become.

本実施の形態に示す例であれば、エレベーターの保守員は、ピット3aにおいて、作業足場15の足場板16の上で制御装置14の点検を行うことができる。また、保守員は、足場板16の上を移動するだけで、巻上機11にアクセスできる。例えば、保守員は、足場板16の上から巻上機11の上部の蓋23を外すことによって、駆動綱車12に形成された溝の摩耗状態を点検する。保守員は、足場板16の上から正面カバー24を外すことによって、内部のブレーキ装置25及びエンコーダ26を点検する。 In the example shown in this embodiment, the elevator maintenance staff can inspect the control device 14 on the scaffolding plate 16 of the work scaffolding 15 in the pit 3a. Further, the maintenance staff can access the hoisting machine 11 only by moving on the scaffolding plate 16. For example, the maintenance staff checks the wear state of the groove formed in the drive sheave 12 by removing the lid 23 on the upper part of the hoisting machine 11 from the scaffolding plate 16. The maintenance staff inspects the internal brake device 25 and the encoder 26 by removing the front cover 24 from above the scaffolding plate 16.

巻上機11の点検を更に行い易くするため、足場板16は、端部16bが駆動綱車12の回転軸27より昇降路壁10に近い位置に配置されても良い。即ち、足場板16の端部16aが受け金18に取り付けられると、駆動綱車12の回転軸27と昇降路壁10との距離より、足場板16の端部16bと昇降路壁10との距離の方が短くなる。この例であれば、保守員は、足場板16の上で巻上機11の正面に立って巻上機11の点検を行うことができる。なお、駆動綱車12の回転軸27は、昇降路壁8に対して垂直に配置される。 In order to make the inspection of the hoisting machine 11 easier, the scaffolding plate 16 may be arranged at a position where the end portion 16b is closer to the hoistway wall 10 than the rotating shaft 27 of the drive sheave 12. That is, when the end portion 16a of the scaffolding plate 16 is attached to the receiver 18, the end portion 16b of the scaffolding plate 16 and the hoistway wall 10 come into contact with each other based on the distance between the rotating shaft 27 of the drive sheave 12 and the hoistway wall 10. The distance is shorter. In this example, the maintenance staff can inspect the hoisting machine 11 by standing in front of the hoisting machine 11 on the scaffolding plate 16. The rotating shaft 27 of the drive sheave 12 is arranged perpendicular to the hoistway wall 8.

足場板16は、複数の板部材を備えることによって伸縮自在であっても良い。例えば、足場板16は、端部16aが受け金18に取り付けられた後に手動で伸長されることにより、端部16bが駆動綱車12の回転軸27より昇降路壁10に近い位置に配置されても良い。 The scaffolding plate 16 may be stretchable by providing a plurality of plate members. For example, the scaffolding plate 16 is manually extended after the end portion 16a is attached to the receiver 18, so that the end portion 16b is arranged at a position closer to the hoistway wall 10 than the rotation shaft 27 of the drive sheave 12. You may.

保守員は、足場板16の上での点検が終了すると、ボルト22を緩めて足場板16を受け金18から外す。また、保守員は、脚17を折り畳んで作業足場15を昇降路3のピット3aに収納する。作業足場15の取り付け及び取り外しは狭いピット3aで行われるため、作業足場15は軽量であることが好ましい。作業足場15を軽量化するため、足場板16の幅を小さくしても良い。例えば、足場板16の幅w1は、制御装置14の幅w2より小さくても良い。制御装置14の点検は、基本的に制御装置14の正面から行われる。このため、足場板16の幅w1が制御装置14の幅w2より小さくても、点検時の作業性が極端に悪化することはない。この例によれば、足場板16の長さとして巻上機11及び制御装置14の双方の点検に必要な長さを確保した上で、作業足場15の重量を抑えることができる。 When the inspection on the scaffolding plate 16 is completed, the maintenance staff loosens the bolt 22 and removes the scaffolding plate 16 from the receiving metal 18. Further, the maintenance staff folds the legs 17 and stores the work scaffold 15 in the pit 3a of the hoistway 3. Since the work scaffold 15 is attached and detached in the narrow pit 3a, the work scaffold 15 is preferably lightweight. In order to reduce the weight of the work scaffold 15, the width of the scaffold plate 16 may be reduced. For example, the width w1 of the scaffolding plate 16 may be smaller than the width w2 of the control device 14. The inspection of the control device 14 is basically performed from the front of the control device 14. Therefore, even if the width w1 of the scaffolding plate 16 is smaller than the width w2 of the control device 14, the workability at the time of inspection is not extremely deteriorated. According to this example, the weight of the work scaffold 15 can be suppressed while ensuring the length of the scaffold plate 16 required for inspection of both the hoisting machine 11 and the control device 14.

他の例として、受け金18の板部19に所謂ダルマ孔が形成されても良い。板部19にダルマ孔が形成されていれば、アンカーボルト21を使用した受け金18の固定を容易に行うことができる。また、受け金18の板部19に、受け金18の設置高さを調整可能にするための複数の貫通孔或いは複数のダルマ孔が形成されても良い。かかる場合、作業足場15の脚17は伸縮可能に構成される。 As another example, a so-called Dharma hole may be formed in the plate portion 19 of the receiver 18. If the plate portion 19 is formed with a Dharma hole, the receiver 18 can be easily fixed by using the anchor bolt 21. Further, a plurality of through holes or a plurality of Dharma holes for making the installation height of the receiver 18 adjustable may be formed in the plate portion 19 of the receiver 18. In such a case, the legs 17 of the work scaffold 15 are configured to be expandable and contractible.

本実施の形態では、保守員が足場板16の上で巻上機11と制御装置14の点検を行う例について説明した。これは一例である。図2に示すように、昇降路壁9から昇降路壁10側に延びる足場板16は、平面視においてつり合いおもり2の前を通過するように配置される。このため、保守員は、足場板16の上からつり合いおもり2の点検を行っても良い。 In the present embodiment, an example in which a maintenance worker inspects the hoisting machine 11 and the control device 14 on the scaffolding plate 16 has been described. This is just an example. As shown in FIG. 2, the scaffolding plate 16 extending from the hoistway wall 9 to the hoistway wall 10 side is arranged so as to pass in front of the balanced weight 2 in a plan view. Therefore, the maintenance staff may inspect the balance weight 2 from above the scaffolding plate 16.

図6は、実施の形態1におけるエレベーター装置の他の例を示す図である。図6は、かご1が乗場28と乗場28より上方の乗場29とにしか停止しない例を示す。図6に示されていない構成に関しては、上述した何れかの例と同様である。図6は、かご1に2つの出入口が形成される例を示す。かご1が乗場28に停止すると、かご1に備えられた一方のドア1aが開閉する。かご1が乗場29に停止すると、かご1に備えられたもう一方のドア1bが開閉する。例えば、ドア1bは、ドア1aに対向する位置に配置される。 FIG. 6 is a diagram showing another example of the elevator device according to the first embodiment. FIG. 6 shows an example in which the car 1 stops only at the landing 28 and the landing 29 above the landing 28. The configuration not shown in FIG. 6 is the same as any of the above examples. FIG. 6 shows an example in which two entrances and exits are formed in the car 1. When the car 1 stops at the landing 28, one of the doors 1a provided in the car 1 opens and closes. When the car 1 stops at the landing 29, the other door 1b provided in the car 1 opens and closes. For example, the door 1b is arranged at a position facing the door 1a.

図6に示す例では、かご1が上方の乗場29に停止した時のかご1の下端が、かご1が乗場28に停止した時のかご1の上端より下方に配置される。例えば、かご1が乗場28に停止した時のドア1bの上端は、乗場29に備えられたドア29aの下端より上方に配置される。 In the example shown in FIG. 6, the lower end of the car 1 when the car 1 stops at the upper landing 29 is arranged below the upper end of the car 1 when the car 1 stops at the landing 28. For example, the upper end of the door 1b when the car 1 stops at the landing 28 is arranged above the lower end of the door 29a provided in the landing 29.

一般に、つり合いおもり2の点検は、保守員がかご1を手動で動かす点検モードにおいて、かご1の上から行われる。点検モードでは、かご1の上にいる人の安全及びピット3aにいる人の安全を確保するため、かご1の可動範囲が狭い範囲に制限される。このため、図6に示すようなかご1の昇降行程が短いエレベーター装置では、点検モードにおいて、つり合いおもり2の点検位置に合わせてかご1を停止させることができない場合がある。即ち、図6に示す例では、つり合いおもり2の点検をかご1の上から行うことが難しい。したがって、このようなエレベーター装置に作業足場15が備えられていれば、足場板16の上からつり合いおもり2の点検を行うことができる。これにより、昇降路3に設置された機器の点検を更に効率良く行うことができる。 Generally, the inspection of the balance weight 2 is performed from above the car 1 in the inspection mode in which the maintenance staff manually moves the car 1. In the inspection mode, the movable range of the car 1 is limited to a narrow range in order to ensure the safety of the person above the car 1 and the safety of the person in the pit 3a. Therefore, in an elevator device having a short ascending / descending stroke of the car 1 as shown in FIG. 6, it may not be possible to stop the car 1 in accordance with the inspection position of the balance weight 2 in the inspection mode. That is, in the example shown in FIG. 6, it is difficult to inspect the balance weight 2 from above the car 1. Therefore, if such an elevator device is provided with the work scaffold 15, the balance weight 2 can be inspected from above the scaffold plate 16. As a result, the equipment installed in the hoistway 3 can be inspected more efficiently.

1 かご、 1a ドア、 1b ドア、 2 つり合いおもり、 3 昇降路、 3a ピット、 4 主ロープ、 5 ガイドレール、 6 ガイドレール、 7〜10 昇降路壁、 11 巻上機、 12 駆動綱車、 13 支持装置、 14 制御装置、 15 作業足場、 16 足場板、 16a 端部、 16b 端部、 16c 貫通孔、 17 脚、 18 受け金、 19 板部、 20 板部、 20a ねじ孔、 21 アンカーボルト、 22 ボルト、 23 蓋、 24 正面カバー、 25 ブレーキ装置、 26 エンコーダ、 27 回転軸、 28 乗場、 29 乗場、 29a ドア 1 car, 1a door, 1b door, 2 balance weight, 3 hoistway, 3a pit, 4 main rope, 5 guide rail, 6 guide rail, 7-10 hoistway wall, 11 hoisting machine, 12 drive sheave, 13 Support device, 14 control device, 15 work scaffolding, 16 scaffolding plate, 16a end, 16b end, 16c through hole, 17 legs, 18 receiver, 19 plate, 20 plate, 20a screw hole, 21 anchor bolt, 22 bolts, 23 lids, 24 front covers, 25 braking devices, 26 encoders, 27 rotating shafts, 28 landings, 29 landings, 29a doors

Claims (5)

エレベーターの昇降路に設けられ、つり合いおもりの移動を案内するガイドレールと、
前記昇降路のピットに設けられ、前記ガイドレール及び第1昇降路壁の間に配置された巻上機と、
前記ピットに設けられ、前記第1昇降路壁に対向する第2昇降路壁に隣接するように配置された制御装置と、
前記第2昇降路壁に設けられ、前記制御装置の下方に配置された受け金と、
作業足場と、
を備え、
前記つり合いおもりと前記巻上機とは、平面視において、前記第1昇降路壁と前記第2昇降路壁との間に形成された第3昇降路壁に沿うように並んで配置され、
前記作業足場は、
第1端部が前記受け金に着脱可能な足場板と、
前記足場板の第2端部に設けられた脚と、
を備え、
前記足場板は、前記第1端部が前記受け金に取り付けられると、前記ガイドレールと前記第1昇降路壁との距離より前記第2端部と前記第1昇降路壁との距離の方が短くなるように、前記第2昇降路壁から突出するように配置されるエレベーター装置。
A guide rail installed on the hoistway of the elevator to guide the movement of the balanced weight,
A hoisting machine provided in the pit of the hoistway and arranged between the guide rail and the first hoistway wall.
A control device provided in the pit and arranged so as to be adjacent to the second hoistway wall facing the first hoistway wall.
A receiver provided on the second hoistway wall and arranged below the control device,
Work scaffolding and
With
The balance weight and the hoisting machine are arranged side by side along a third hoistway wall formed between the first hoistway wall and the second hoistway wall in a plan view.
The work scaffolding
A scaffolding plate whose first end is removable from the receiver,
With the legs provided at the second end of the scaffolding board,
With
When the first end portion of the scaffolding plate is attached to the receiver, the distance between the second end portion and the first hoistway wall is greater than the distance between the guide rail and the first hoistway wall. An elevator device arranged so as to project from the second hoistway wall so as to shorten the distance.
前記足場板は、前記第1端部が前記受け金に取り付けられると、前記巻上機の駆動綱車の回転軸と前記第1昇降路壁との距離より前記第2端部と前記第1昇降路壁との距離の方が短くなる請求項1に記載のエレベーター装置。 When the first end portion of the scaffolding plate is attached to the receiver, the second end portion and the first hoistway plate are obtained from the distance between the rotation shaft of the drive sheave of the hoisting machine and the first hoistway wall. The elevator device according to claim 1, wherein the distance from the hoistway wall is shorter. 前記足場板の幅は、前記制御装置の幅より小さい請求項1又は請求項2に記載のエレベーター装置。 The elevator device according to claim 1 or 2, wherein the width of the scaffolding plate is smaller than the width of the control device. 前記受け金は、
前記第2昇降路壁にアンカーボルトを介して固定された第1板部と、
前記第1板部から前記第1昇降路壁側に突出するように設けられ、上面にねじ孔が形成された第2板部と、
を備え、
前記足場板の第1端部に貫通孔が形成され、
前記足場板は、前記貫通孔を貫通したボルトが前記ねじ孔にねじ込まれることによって前記受け金に取り付けられる請求項1から請求項3の何れか一項に記載のエレベーター装置。
The receipt is
The first plate portion fixed to the second hoistway wall via anchor bolts,
A second plate portion provided so as to project from the first plate portion toward the first hoistway wall side and having a screw hole formed on the upper surface, and a second plate portion.
With
A through hole is formed at the first end of the scaffolding plate, and a through hole is formed.
The elevator device according to any one of claims 1 to 3, wherein the scaffolding plate is attached to the receiver by screwing a bolt penetrating the through hole into the screw hole.
前記つり合いおもりを前記昇降路に吊り下げる主ロープと、
前記主ロープによって前記昇降路に吊り下げられるかごと、
を更に備え、
前記かごは、第1乗場と前記第1乗場より上方の第2乗場にのみ停止し、
前記かごが前記第2乗場に停止した時の前記かごの下端は、前記かごが前記第1乗場に停止した時の前記かごの上端より下方に配置される請求項1から請求項4の何れか一項に記載のエレベーター装置。
A main rope that suspends the balanced weight on the hoistway, and
A basket suspended from the hoistway by the main rope,
Further prepare
The car only stops at the first landing and the second landing above the first landing.
Any of claims 1 to 4, wherein the lower end of the car when the car stops at the second landing is arranged below the upper end of the car when the car stops at the first landing. The elevator device according to the first paragraph.
JP2019102756A 2019-05-31 2019-05-31 Elevator device Active JP6852753B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2019102756A JP6852753B2 (en) 2019-05-31 2019-05-31 Elevator device
CN202010428681.7A CN112010128A (en) 2019-05-31 2020-05-20 Elevator device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019102756A JP6852753B2 (en) 2019-05-31 2019-05-31 Elevator device

Publications (2)

Publication Number Publication Date
JP2020196564A JP2020196564A (en) 2020-12-10
JP6852753B2 true JP6852753B2 (en) 2021-03-31

Family

ID=73506589

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019102756A Active JP6852753B2 (en) 2019-05-31 2019-05-31 Elevator device

Country Status (2)

Country Link
JP (1) JP6852753B2 (en)
CN (1) CN112010128A (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013018618A (en) * 2011-07-12 2013-01-31 Hitachi Building Systems Co Ltd Working platform device for inspection of equipment in hoistway
CN102363486A (en) * 2011-11-19 2012-02-29 希姆斯电梯(中国)有限公司 Underlying elevator without machine room
JP5827596B2 (en) * 2012-05-28 2015-12-02 株式会社日立ビルシステム Elevator hoisting machine inspection table and its assembly method
CN105246811A (en) * 2013-05-22 2016-01-13 三菱电机株式会社 Elevator pit scaffolding device
CN105438936B (en) * 2014-09-02 2018-08-21 株式会社日立制作所 Elevator without machine room
CN107531450B (en) * 2015-04-17 2019-06-14 三菱电机株式会社 Machine-roomless lift
CN207748687U (en) * 2017-12-05 2018-08-21 天津利福特电梯部件有限公司 A kind of cage top overhauling platform

Also Published As

Publication number Publication date
JP2020196564A (en) 2020-12-10
CN112010128A (en) 2020-12-01

Similar Documents

Publication Publication Date Title
KR20070037995A (en) Method of mounting a support means of a lift cage to a lift cage and to a lift shaft
FI125130B (en) Hardware for securing lift hoisting machinery and attachment arrangement
KR100499660B1 (en) Machine room-less elevator
KR20040052478A (en) Machine-room-less traction sheave elevator
JP2013095571A (en) Elevator device
WO2014189074A1 (en) Elevator pit scaffolding device
JP6422570B2 (en) Machine room-less elevator
JP6852753B2 (en) Elevator device
JP2007210703A (en) Device and method for installing hoist machine in machine-room-less elevator
CN108349693B (en) Elevator and operation method thereof
WO2015159319A1 (en) Pit entry/exit device for elevator
WO2016002042A1 (en) Machine room-less elevator
WO2014013600A1 (en) Elevator device
JP2005008335A (en) Elevator apparatus
JP5052110B2 (en) Automatic maintenance operation device of elevator
JP6965371B2 (en) Elevator work table and elevator
JP2011051736A (en) Elevator device
JP2002037564A (en) Elevator modifying method
KR20180101486A (en) Elevator device
JP6508438B1 (en) Lift frame assembly support apparatus for elevator and elevator frame assembly method
WO2003104130A1 (en) Elevator
JP2013086935A (en) Double deck elevator
JP7213362B2 (en) Elevator equipment for construction
JP7396099B2 (en) measuring device
WO2013004899A1 (en) Elevator, rope anchorage assembly for an elevator, and method for modernizing an elevator

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200108

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210121

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210209

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210222

R150 Certificate of patent or registration of utility model

Ref document number: 6852753

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250