JP6801910B1 - How to build a wall structure - Google Patents

How to build a wall structure Download PDF

Info

Publication number
JP6801910B1
JP6801910B1 JP2020087915A JP2020087915A JP6801910B1 JP 6801910 B1 JP6801910 B1 JP 6801910B1 JP 2020087915 A JP2020087915 A JP 2020087915A JP 2020087915 A JP2020087915 A JP 2020087915A JP 6801910 B1 JP6801910 B1 JP 6801910B1
Authority
JP
Japan
Prior art keywords
wall
filling material
constructing
wall structure
structure according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2020087915A
Other languages
Japanese (ja)
Other versions
JP2021181722A (en
Inventor
佐藤 光一
光一 佐藤
Original Assignee
株式会社第一基礎
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社第一基礎 filed Critical 株式会社第一基礎
Priority to JP2020087915A priority Critical patent/JP6801910B1/en
Application granted granted Critical
Publication of JP6801910B1 publication Critical patent/JP6801910B1/en
Publication of JP2021181722A publication Critical patent/JP2021181722A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

【課題】壁体構造物の効率的な施工を可能にする構築方法を提供する。【解決手段】壁体構造物を構築しようとする地盤に盛土を築堤する工程と、盛土が築堤された地盤に、互いに嵌合された多数の壁体構成部材によって形成される壁体を所定間隔隔てた対向位置に2列をなすように所定手段で埋設する工程と、2列の壁体によって形成される空間内の盛土を第1中詰材とする工程と、第1中詰材の表面よりも上方の個所における壁体の所定部位において、連結材によって壁体同士を連結する工程と、第1中詰材の表面より上方の空間に充填材を充填して少なくとも1層の第2中詰材とする工程とを含むことを特徴とする構築方法が提供される。【選択図】図2PROBLEM TO BE SOLVED: To provide a construction method capable of efficient construction of a wall structure. SOLUTION: A step of embankment on the ground for constructing a wall structure and a wall body formed by a large number of wall body constituent members fitted to each other are spaced apart from each other on the ground on which the embankment is embanked. A step of burying by a predetermined means so as to form two rows at separated facing positions, a step of using the embankment in the space formed by the two rows of walls as the first filling material, and the surface of the first filling material. A step of connecting the wall bodies with a connecting material at a predetermined part of the wall body at a position above the surface, and a filling material is filled in the space above the surface of the first filling material to fill at least one layer in the second middle layer. A construction method characterized by including a step of filling material is provided. [Selection diagram] Fig. 2

Description

本発明は一般に、壁体構造物の構築方法に関する。より詳細には、本発明は、二重鋼矢板式構造物のような壁体構造物の効率的な施工を可能にする、壁体構造物の構築方法に関する。 The present invention generally relates to a method of constructing a wall structure. More specifically, the present invention relates to a method for constructing a wall structure, which enables efficient construction of a wall structure such as a double steel sheet pile structure.

鋼矢板を所定間隔隔てて2列に基礎地盤に埋設させることによって形成される二重鋼矢板式構造物が知られている。従来、このような二重鋼矢板式構造物の施工では、基礎地盤に埋設された2列の鋼矢板壁の上方部同士をタイロッド等の連結材で連結した後、鋼矢板壁の間の空間に中詰土を複数回に分けて充填し、所要の設計品質が確保されるように、充填した中詰土をその都度締め固める作業が行われている。 A double steel sheet pile type structure formed by burying steel sheet piles in two rows at a predetermined interval in the foundation ground is known. Conventionally, in the construction of such a double steel sheet pile type structure, after connecting the upper parts of the two rows of steel sheet pile walls buried in the foundation ground with a connecting material such as a tie rod, the space between the steel sheet pile walls is used. The filling soil is filled in multiple times, and the filled filling soil is compacted each time so as to ensure the required design quality.

しかしながら、中詰材の充填作業では、ローラーやダンパー等の締固め機械を中詰材の上面に載置する必要があるが、従来の方法では、締固め作業の時点で中詰材の上方に連結材が設置されているため、締固め作業の能率が極めて悪いうえ、中詰材の上面と連結材との間の空間に出し入れ可能な大きさの締固め機械しか使用できない、という課題がある。 However, in the filling work of the filling material, it is necessary to place a compaction machine such as a roller or a damper on the upper surface of the filling material, but in the conventional method, it is above the filling material at the time of the compacting work. Since the connecting material is installed, the efficiency of the compaction work is extremely low, and there is a problem that only a compacting machine of a size that can be taken in and out of the space between the upper surface of the filling material and the connecting material can be used. ..

本発明は、このような状況に鑑みて開発されたものであって、二重鋼矢板式構造物のような壁体構造物の効率的な施工を可能にする、壁体構造物の構築方法を提供することを目的としている。 The present invention has been developed in view of such a situation, and is a method for constructing a wall structure that enables efficient construction of a wall structure such as a double steel sheet pile type structure. Is intended to provide.

本願請求項1に記載された壁体構造物の構築方法は、前記壁体構造物を構築しようとする地盤に盛土を築堤する工程と、前記盛土が築堤された地盤に、互いに嵌合された多数の壁体構成部材によって形成される壁体を所定間隔隔てた対向位置に2列をなすように所定手段で埋設する工程と、2列の前記壁体によって形成される空間内の前記盛土を第1中詰材とする工程と、前記第1中詰材の表面よりも上方の個所における前記壁体の所定部位において、連結材によって前記壁体同士を連結する工程と、前記第1中詰材の表面より上方の空間に充填材を充填して少なくとも1層の第2中詰材とする工程とを含むことを特徴とするものである。 The method for constructing a wall structure according to claim 1 of the present application is a step of embankment on the ground on which the wall structure is to be constructed and a step of embankment on the ground on which the embankment is embanked. The step of burying the wall bodies formed by a large number of wall body constituent members by a predetermined means so as to form two rows at opposite positions separated by a predetermined interval, and the embankment in the space formed by the two rows of the wall bodies. A step of using the first filling material, a step of connecting the wall bodies to each other by a connecting material at a predetermined portion of the wall body at a position above the surface of the first filling material, and the first filling material. It is characterized by including a step of filling a space above the surface of the material with a filler to form at least one layer of a second filling material.

本願請求項2に記載された壁体構造物の構築方法は、前記請求項1の構築方法において、前記第1中詰材が、前記盛土の一部であることを特徴とするものである。 The method for constructing a wall structure according to claim 2 of the present application is characterized in that, in the method for constructing claim 1, the first filling material is a part of the embankment.

本願請求項3に記載された壁体構造物の構築方法は、前記請求項1又は2の構築方法において、前記第2中詰材が、前記壁体の外側に位置する前記盛土の一部を流用したものであることを特徴とするものである。 The method for constructing a wall structure according to claim 3 of the present application is that in the method for constructing claim 1 or 2, the second filling material forms a part of the embankment located outside the wall. It is characterized by being diverted.

本願請求項4に記載された壁体構造物の構築方法は、前記請求項1から請求項3のうちいずれか1項の構築方法において、前記盛土を形成する材料が、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料であることを特徴とするものである。 In the method for constructing a wall structure according to claim 4, in the method for constructing any one of claims 1 to 3, the material forming the embankment is earth and sand, improved soil, and slag. , Or at least one of the time-curable materials.

本願請求項5に記載された壁体構造物の構築方法は、前記壁体構造物を構築しようとする地盤に、互いに嵌合された多数の壁体構成部材によって形成される壁体を所定間隔隔てた対向位置に2列をなすように所定手段で埋設する工程と、2列の前記壁体によって形成される空間内に充填材を充填して第1中詰材とする工程と、前記第1中詰材の表面よりも上方の個所における前記壁体の所定部位において、連結材によって前記壁体同士を連結する工程と、前記第1中詰材の表面より上方の空間に充填材を充填して少なくとも1層の第2中詰材とする工程とを含むことを特徴とするものである。 The method for constructing a wall structure according to claim 5 of the present application is to place walls formed by a large number of wall body constituent members fitted to each other at predetermined intervals on the ground on which the wall structure is to be constructed. A step of burying by a predetermined means so as to form two rows at separated facing positions, a step of filling the space formed by the two rows of the wall bodies with a filler to form a first filling material, and the first step. 1 A step of connecting the walls with a connecting material at a predetermined portion of the wall body above the surface of the filling material, and filling a space above the surface of the first filling material with the filling material. It is characterized by including a step of forming at least one layer of the second filling material.

本願請求項6に記載された壁体構造物の構築方法は、前記請求項1から請求項5のうちいずれか1項の構築方法において、前記所定手段が、バイブロハンマを用いた振動打設、又は油圧圧入装置による圧入であることを特徴とするものである。 The method for constructing a wall structure according to claim 6 of the present application is the method for constructing a wall structure according to any one of claims 1 to 5, wherein the predetermined means is vibration driving using a vibro hammer. It is characterized by being press-fitted by a hydraulic press-fitting device.

本願請求項7に記載された壁体構造物の構築方法は、前記請求項1から請求項6のうちいずれか1項の構築方法において、前記充填材が、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料であることを特徴とするものである。 The method for constructing a wall structure according to claim 7 of the present application is the method for constructing a wall structure according to any one of claims 1 to 6, wherein the filler is earth and sand, improved soil, slag, or aging. It is characterized in that it is at least one kind of curable material.

本願請求項8に記載された壁体構造物の構築方法は、前記請求項1から請求項7のうちいずれか1項の構築方法において、前記第1中詰材とする工程と前記壁体同士を連結する工程との間に、前記壁体構成部材の所定部位に腹起を設置する工程をさらに含むことを特徴とするものである。 The method for constructing a wall structure according to claim 8 of the present application is the step of using the first filling material and the wall bodies in the construction method according to any one of claims 1 to 7. It is characterized by further including a step of installing an abdomen at a predetermined portion of the wall body constituent member between the step of connecting the two.

本願請求項9に記載された壁体構造物の構築方法は、前記請求項1から請求項8のうちいずれか1項の構築方法において、前記連結材が、抗張力部材であることを特徴とするものである。 The method for constructing a wall structure according to claim 9 of the present application is characterized in that, in the method for constructing any one of claims 1 to 8, the connecting member is a tensile strength member. It is a thing.

本願請求項10に記載された壁体構造物の構築方法は、前記請求項1から請求項9のうちいずれか1項の構築方法において、前記壁体のうち一方の壁体の頭部に、前記一方の壁体の延長方向に延びるように第1頭部連結材を設置し、前記壁体のうち他方の壁体の頭部に、前記他方の壁体の延長方向に延びるように第2頭部連結材を設置することを特徴とするものである。 The method for constructing a wall structure according to claim 10 of the present application is the method for constructing a wall structure according to any one of claims 1 to 9, wherein the head of one of the walls is used. The first head connecting member is installed so as to extend in the extension direction of the one wall body, and the second head connecting member extends to the head of the other wall body of the wall body in the extension direction of the other wall body. It is characterized by installing a head connecting material.

本願請求項11に記載された壁体構造物の構築方法は、前記請求項10の構築方法において、複数本の断面方向連結材によって前記第1頭部連結材と前記第2頭部連結材を連結することを特徴とするものである。 The method for constructing a wall structure according to claim 11 of the present application is the method for constructing the wall structure according to claim 10, wherein the first head connecting material and the second head connecting material are connected by a plurality of cross-sectional direction connecting materials. It is characterized by being connected.

本願請求項12に記載された壁体構造物の構築方法は、前記請求項1から請求項11のうちいずれか1項の構築方法において、前記第2中詰材の表面を被覆するように保護工を施すことを特徴とするものである。 The method for constructing a wall structure according to claim 12 of the present application protects the surface of the second filling material in the construction method according to any one of claims 1 to 11. It is characterized by performing work.

本願請求項13に記載された壁体構造物の構築方法は、前記請求項12の構築方法において、前記保護工が、現場施工コンクリート、プレキャストコンクリート版、又は鋼板であることを特徴とするものである。 The method for constructing a wall structure according to claim 13 of the present application is characterized in that, in the method for constructing claim 12, the protective work is on-site construction concrete, precast concrete slab, or steel plate. is there.

本願請求項14に記載された壁体構造物の構築方法は、前記請求項12又は13の構築方法において、前記壁体構成部材に、前記保護工の沈下を抑止するための抑止部材を設置することを特徴とするものである。
本願請求項15に記載された壁体構造物の構築方法は、前記請求項10の構築方法において、前記第1頭部連結材及び/又は前記第2頭部連結材に、前記第2中詰材の表面を被覆するように施された保護工の沈下を抑止するための抑止部材を設置することを特徴とするものである。
本願請求項16に記載された壁体構造物の構築方法は、前記請求項11の構築方法において、前記断面方向連結材に、前記第2中詰材の表面を被覆するように施された保護工の沈下を抑止するための抑止部材を設置することを特徴とするものである。
The method for constructing a wall structure according to claim 14 of the present application is to install a deterrent member for suppressing subsidence of the protective work on the wall body constituent member in the method for constructing the wall structure according to claim 12 or 13. It is characterized by that.
The method for constructing a wall structure according to claim 15 of the present application is the method for constructing a wall structure according to claim 10, wherein the first head connecting material and / or the second head connecting material is filled with the second filling. It is characterized by installing a deterrent member for suppressing the sinking of the protective work applied so as to cover the surface of the material.
The method for constructing a wall structure according to claim 16 of the present application is the protection provided to the cross-sectional direction connecting material so as to cover the surface of the second filling material in the method for constructing the wall structure according to claim 11. It is characterized by installing a deterrent member to prevent the sinking of the work.

本願請求項17に記載された壁体構造物の構築方法は、前記請求項1から請求項9のうちいずれか1項の構築方法において、2列の前記壁体の頭部を鉄筋コンクリート製の頂版で連結することを特徴とするものである。 The method for constructing a wall structure according to claim 17 of the present application is the construction method according to any one of claims 1 to 9, wherein the heads of the two rows of the wall structures are made of reinforced concrete. It is characterized by being connected by a plate.

本願請求項18に記載された壁体構造物の構築方法は、前記請求項1から請求項17のうちいずれか1項の構築方法において、前記第2中詰材の表面に上げ越しを施すことを特徴とするものである。 The method for constructing a wall structure according to claim 18 of the present application is that the surface of the second filling material is raised in the construction method according to any one of claims 1 to 17. It is characterized by.

本願請求項19に記載された壁体構造物の構築方法は、前記請求項1から請求項18のうちいずれか1項の構築方法において、前記壁体構成部材が、鋼矢板、鋼管矢板、軽量鋼矢板、箱型矢板、又はコンクリート矢板であって、嵌合継手を有するものであることを特徴とするものである。 In the method for constructing a wall structure according to claim 19 , in the construction method according to any one of claims 1 to 18 , the wall body constituent member is a steel sheet pile, a steel pipe sheet pile, or a lightweight steel sheet pile. It is a steel sheet pile, a box-shaped sheet pile, or a concrete sheet pile, and is characterized by having a fitting joint.

本発明によれば、連結材を設置する前に第1中詰材の充填・締固め作業が行われるので、効率的な締固め作業が可能になるとともに、締固め機械の選択も自由に行うことができる。また、第1中詰材の充填・締固め作業、連結材の設置作業、第2中詰材の充填・締固め作業の順に構築作業が行われるため、詳細には後述するように、壁体の壁高部分に最終的に発生する曲げモーメントがかなり小さくなる。また、連結材には、第1中詰材の充填・締固めに起因する張力の発生がないため、連結材に最終的に発生する張力もかなり小さくなる。このため、壁体構造物の安全性を高めることができる。従来の二重鋼矢板式構造物の施工手順で決定した壁体構成部材や連結材に対し、本発明に基づく施工手順で二重鋼矢板式構造物を構築すると、壁体構成部材や連結材に耐力的に余裕ができる場合が多い。逆に言うと、本発明に基づく施工手順、力学的挙動を反映した構造計算法で設計すると、経済的・合理的な二重鋼矢板式構造物を実現できる。さらに、盛土を築堤すれば、鋼矢板の自立安定性に寄与するとともに、作業足場等への利用が可能となる。 According to the present invention, since the filling and compaction work of the first filling material is performed before installing the connecting material, efficient compaction work is possible and the compaction machine can be freely selected. be able to. Further, since the construction work is performed in the order of the filling / compacting work of the first filling material, the installation work of the connecting material, and the filling / compacting work of the second filling material, the wall body is described in detail later. The bending moment that is finally generated at the height of the wall is considerably small. Further, since the connecting material does not generate tension due to filling and compaction of the first filling material, the tension finally generated in the connecting material is also considerably reduced. Therefore, the safety of the wall structure can be enhanced. When a double steel sheet pile type structure is constructed by the construction procedure based on the present invention with respect to the wall body constituent members and connecting materials determined by the construction procedure of the conventional double steel sheet pile type structure, the wall body constituent members and connecting materials are constructed. In many cases, there is a margin in terms of bearing capacity. To put it the other way around, an economical and rational double steel sheet pile type structure can be realized by designing with a construction procedure based on the present invention and a structural calculation method that reflects mechanical behavior. Furthermore, if an embankment is built, it will contribute to the self-sustaining stability of the steel sheet pile and can be used as a work scaffold.

本発明の好ましい実施形態に係る壁体構造物の構築方法を示した一連の図である。It is a series of figures which showed the construction method of the wall structure which concerns on a preferable embodiment of this invention. 図1に示した構築方法によって構築された壁体構造物を模式的に示した断面図である。It is sectional drawing which shows typically the wall structure constructed by the construction method shown in FIG. 図3(a)は、壁体を形成するハット形鋼矢板を示した平面図、図3(b)は、ハット形鋼矢板の嵌合個所を示した拡大図である。FIG. 3A is a plan view showing a hat-shaped steel sheet pile forming a wall body, and FIG. 3B is an enlarged view showing a fitting portion of the hat-shaped steel sheet pile. 第1中詰材の充填工程、連結材の設置工程、および第2中詰材の充填工程におけるハット形鋼矢板に作用する曲げモーメントの変化を説明するための一連の図である。It is a series of figures for demonstrating the change of the bending moment acting on the hat-shaped steel sheet pile in the 1st filling material filling process, the connecting material installation process, and the 2nd filling material filling process. 図1の構築方法の変形形態を示した一連の図である。It is a series of figures which showed the modified form of the construction method of FIG. 図6(a)は、第1及び第2頭部連結材を示した斜視図、図6(b)は、断面方向連結材を示した斜視図、図6(c)は、壁体構造物の頭部に形成される頂版を示した斜視図である。6 (a) is a perspective view showing the first and second head connecting members, FIG. 6 (b) is a perspective view showing the cross-sectional direction connecting members, and FIG. 6 (c) is a wall structure. It is a perspective view which showed the top plate formed on the head of.

次に図面を参照して、本発明の好ましい実施形態に係る壁体構造物の構築方法について説明する。図1は、本発明の好ましい実施形態に係る壁体構造物の構築方法を示した一連の図、図2は、図1に示した構築方法によって構築された壁体構造物10を模式的に示した断面図である。 Next, a method for constructing a wall structure according to a preferred embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a series of views showing a method for constructing a wall structure according to a preferred embodiment of the present invention, and FIG. 2 schematically shows a wall structure 10 constructed by the construction method shown in FIG. It is the cross-sectional view shown.

最初に、壁体構造物10を構築しようとする地盤に、盛土12を築堤する(図1(a)参照)。盛土12は、後述する壁体14の施工時における壁体14の自立安定性を確保するとともに、後述する第1中詰材18の一部となり、また後述する腹起20及び連結材22を設置する際の作業足場として利用される。なお、盛土12の天端(高さ)は、腹起20及び連結材22の設置を考慮して、腹起20及び連結材22の設置高さよりも下方とするのが好ましい。盛土12は、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料によって形成される。 First, an embankment 12 is laid on the ground on which the wall structure 10 is to be constructed (see FIG. 1 (a)). The embankment 12 secures the self-sustaining stability of the wall body 14 at the time of construction of the wall body 14 described later, becomes a part of the first filling material 18 described later, and also installs the abdominal raising 20 and the connecting material 22 described later. It is used as a work scaffold when doing work. The top end (height) of the embankment 12 is preferably lower than the installation height of the abdomen 20 and the connecting member 22 in consideration of the installation of the abdomen 20 and the connecting member 22. The embankment 12 is formed of at least one of earth and sand, improved soil, slag, and a time-curable material.

次いで、盛土12が築堤された地盤に、互いに嵌合された多数の壁体構成部材16によって形成される壁体14を所定間隔隔てた対向位置に2列をなすように埋設する(図1(b)参照)。 Next, in the ground on which the embankment 12 is embanked, wall bodies 14 formed by a large number of wall body constituent members 16 fitted to each other are buried in two rows at opposite positions at predetermined intervals (FIG. 1 (FIG. 1). b) See).

壁体構成部材16としては、例えばハット形鋼矢板16が用いられる。ハット形鋼矢板16は、図3(a)に示されるように、土水圧等の荷重が作用した場合に主として曲げモーメントに抵抗するフランジ16a、アーム部16b及び継手部16cと、主としてせん断力に抵抗するウェブ16dとを有している。より詳細に説明すると、ハット形鋼矢板16では、フランジ16aの両縁部から外方に向かって拡がるように一対のウェブ16dがそれぞれ連続して配置され、各ウェブ16dにフランジ16aと略平行になるようにアーム部16bがそれぞれ連続して配置されており、各アーム部16bに継手部16cがそれぞれ連続して設けられている。 As the wall body component 16, for example, a hat-shaped steel sheet pile 16 is used. As shown in FIG. 3A, the hat-shaped steel sheet pile 16 mainly has a flange 16a, an arm portion 16b, and a joint portion 16c that resist bending moments when a load such as soil water pressure is applied, and mainly a shear force. It has a web 16d to resist. More specifically, in the hat-shaped steel sheet pile 16, a pair of webs 16d are continuously arranged so as to extend outward from both edges of the flange 16a, and each web 16d is substantially parallel to the flange 16a. The arm portions 16b are continuously arranged so as to be such, and the joint portion 16c is continuously provided on each arm portion 16b.

ハット形鋼矢板16の継手部16cの一方には上方開口爪16c1が形成され、継手部16cの他方には下方開口爪16c2が形成されている。上方開口爪16c1と下方開口爪16c2は、互いに相補する形状に形作られており、一方のハット形鋼矢板16の継手部16cの上方開口爪16c1に、隣接する他方のハット形鋼矢板16の継手部16cの下方開口爪16c2を嵌め込むことによって、或いは、一方のハット形鋼矢板16の継手部16cの下方開口爪16c2に、隣接する他方のハット形鋼矢板16の継手部16cの上方開口爪16c1を嵌め込むことによって、所望の枚数のハット形鋼矢板16を嵌合させることができる。図3(b)は、ハット形鋼矢板16の継手部の嵌合個所を示した拡大図である。 An upper opening claw 16c1 is formed on one of the joint portions 16c of the hat-shaped steel sheet pile 16, and a lower opening claw 16c2 is formed on the other side of the joint portion 16c. The upper opening claw 16c1 and the lower opening claw 16c2 are shaped to complement each other, and the joint portion 16c of the joint portion 16c of one hat-shaped steel sheet pile 16 is adjacent to the joint portion 16c1 of the other hat-shaped steel sheet pile 16. By fitting the lower opening claw 16c2 of the portion 16c, or by fitting the lower opening claw 16c2 of the joint portion 16c of one hat-shaped steel sheet pile 16, the upper opening claw of the joint portion 16c of the other hat-shaped steel sheet pile 16 adjacent to the lower opening claw 16c2. By fitting 16c1, a desired number of hat-shaped steel sheet piles 16 can be fitted. FIG. 3B is an enlarged view showing the fitting portion of the joint portion of the hat-shaped steel sheet pile 16.

壁体14の下端が埋設される地盤には、改良土によって形成される地盤も含まれる。壁体14の地盤への埋設は、バイブロハンマを用いた振動打設や油圧圧入装置による圧入によって行われる。 The ground in which the lower end of the wall body 14 is buried includes the ground formed by the improved soil. The wall body 14 is embedded in the ground by vibration driving using a vibro hammer or press fitting by a hydraulic press fitting device.

盛土12が築堤された地盤に2列の壁体14を埋設するため、2列の壁体14によって形成される空間内に、所定高さまで充填された盛土12が存在することになるが、この盛土が所定の密度に締め固められて、第1中詰材18になる。 Since the two rows of wall bodies 14 are buried in the ground on which the embankment 12 is embanked, the embankment 12 filled to a predetermined height exists in the space formed by the two rows of wall bodies 14. The embankment is compacted to a predetermined density to become the first filling material 18.

次いで、必要に応じて、ハット形鋼矢板の所定部位に腹起20を設置する。次いで、第1中詰材18の表面よりも上方の個所において、連結材(例えば、タイロッドやタイワイヤー等の抗張力部材)22によってハット形鋼矢板16同士を連結する(図1(c)参照)。腹起20及び連結材22を設置する際に、盛土12を足場として利用することができる。連結材22を設置する段階では、2列の壁体14は、第1中詰材18の充填の影響により外側に変形している。すなわち、連結材22の設置位置での2列の壁体14は、互いに外側に変位し、離間距離が大きくなっている。この変位を残留させたまま、連結材22を設置すると、連結材22に発生する張力は、連結材22の自重や施工管上導入する締め付け力の影響を除けば、実質的にゼロである。したがって、連結材22に発生する張力は、第2中詰材24を充填した以降の影響により発生する張力となり、従来の二重鋼矢板式構造物の構築方法と比べると、最終的に連結材22に発生する張力が小さくなる。 Next, if necessary, the abdominal ridge 20 is installed at a predetermined portion of the hat-shaped steel sheet pile. Next, the hat-shaped steel sheet piles 16 are connected to each other by a connecting material (for example, a tensile strength member such as a tie rod or a tie wire) 22 at a position above the surface of the first filling material 18 (see FIG. 1 (c)). .. The embankment 12 can be used as a scaffold when installing the abdominal ridge 20 and the connecting member 22. At the stage of installing the connecting member 22, the two rows of wall bodies 14 are deformed outward due to the influence of the filling of the first filling member 18. That is, the two rows of wall bodies 14 at the installation position of the connecting member 22 are displaced outward from each other, and the separation distance is increased. When the connecting member 22 is installed with this displacement remaining, the tension generated in the connecting member 22 is substantially zero except for the influence of the weight of the connecting member 22 and the tightening force introduced on the construction pipe. Therefore, the tension generated in the connecting material 22 becomes the tension generated due to the influence after filling the second filling material 24, and is finally compared with the conventional method for constructing a double steel sheet pile type structure. The tension generated in 22 becomes smaller.

次いで、第1中詰材20の表面より上方の空間に充填材を充填し締め固めて第2中詰材24とする(図1(d)参照)。充填材として、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料が用いられる。充填材として、ハット形鋼矢板16の外側の一方又は両方に位置する盛土12を利用してもよい。また、第2中詰材24の表面には、第2中詰材24の沈下対策として、上げ越しを施してもよい。なお、図1(d)では、第2中詰材24が単一の層として図示されているが、第2中詰材24を複数の層から構成してもよい。 Next, the space above the surface of the first filling material 20 is filled with the filler and compacted to obtain the second filling material 24 (see FIG. 1D). As the filler, at least one of earth and sand, improved soil, slag, and a time-curable material is used. As the filler, the embankment 12 located on one or both of the outer sides of the hat-shaped steel sheet pile 16 may be used. Further, the surface of the second filling material 24 may be raised as a countermeasure against the settlement of the second filling material 24. Although the second filling material 24 is shown as a single layer in FIG. 1D, the second filling material 24 may be composed of a plurality of layers.

図6(a)〜図6(c)は、壁体構造物10の上部構造の例を示した図である。すなわち、図6(a)に示される形態では、2列の壁体14のうち一方の壁体14の頭部に、壁体14の延長方向に延びるように第1頭部連結材25aを設置し、他方の壁体14の頭部に、壁体14の延長方向に延びるように第2頭部連結材25bを設置し、壁体構造物10の上部が補強されている。また、図6(b)に示される形態では、複数本の断面方向連結材25cによって、第1頭部連結材25aと第2頭部連結材25bが連結され、図6(a)の形態よりもさらに強固な剛結構造となっている。さらに、図6(c)に示される形態では、2列の壁体14の頭部が鉄筋コンクリート製の頂版25dで連結され、壁体構造物10の上部が補強されている。 6 (a) to 6 (c) are views showing an example of the superstructure of the wall structure 10. That is, in the form shown in FIG. 6A, the first head connecting member 25a is installed on the head of one of the two rows of wall bodies 14 so as to extend in the extension direction of the wall body 14. Then, a second head connecting member 25b is installed on the head of the other wall body 14 so as to extend in the extension direction of the wall body 14, and the upper portion of the wall body structure 10 is reinforced. Further, in the form shown in FIG. 6B, the first head connecting member 25a and the second head connecting member 25b are connected by a plurality of cross-sectional direction connecting members 25c, and the form shown in FIG. 6A shows. Has a stronger rigid structure. Further, in the form shown in FIG. 6C, the heads of the two rows of wall bodies 14 are connected by a top plate 25d made of reinforced concrete, and the upper portion of the wall structure 10 is reinforced.

図6(a)〜図6(c)に例示されるような上部構造を設ける代わりに又は図6(a)及び図6(b)に例示されるような上部構造に加えて、第2中詰材24の表面に、第2中詰材24を保護するための保護工26を設けてもよい(図1(e)参照)。保護工26としては、現場施工コンクリート、プレキャストコンクリート版、又は鋼板が用いられる。 Instead of providing the superstructure as illustrated in FIGS. 6 (a) to 6 (c) or in addition to the superstructure as exemplified in FIGS. 6 (a) and 6 (b), the second middle A protective work 26 for protecting the second filling material 24 may be provided on the surface of the filling material 24 (see FIG. 1 (e)). As the protective work 26, on-site construction concrete, precast concrete slab, or steel plate is used.

壁体14には、保護工26の沈下を抑止するための抑止部材28を設置するのが好ましい。抑止部材28としては、例えば、ハット形鋼矢板16、第1頭部連結材25a、第2頭部連結材25b、及び断面方向連結材25cのうち少なくとも1種以上の部材に、保護工26の下面を支持するようにこれらの部材に固定された鋼材、又は保護工26の内部に位置するようにこれらの部材に固定された鋼材が用いられる。 It is preferable to install a deterrent member 28 on the wall body 14 for deterring the sinking of the protective work 26. As the restraining member 28, for example, at least one of the hat-shaped steel sheet pile 16, the first head connecting member 25a, the second head connecting member 25b, and the cross-sectional direction connecting member 25c is provided with the protective work 26. Steel materials fixed to these members so as to support the lower surface, or steel materials fixed to these members so as to be located inside the protective work 26 are used.

壁体14の外側に位置する盛土12を一部又は全部撤去することにより、壁体構造物10が完成する。壁体14の外側に位置する盛土12を一部又は全部撤去する前に、当該盛土12を利用して保護工26を施工してもよい。なお、盛土12を残置することもありうる。盛土12の取り扱いは、計画設計条件に依存する。 The wall structure 10 is completed by removing part or all of the embankment 12 located outside the wall 14. Before removing a part or all of the embankment 12 located on the outside of the wall body 14, the embankment 12 may be used to construct the protective work 26. The embankment 12 may be left behind. The handling of the embankment 12 depends on the planning and design conditions.

図4は、第1中詰材18の充填工程、連結材22の設置工程、および第2中詰材24の充填工程におけるハット形鋼矢板16に作用する曲げモーメントの変化を説明するための一連の図である。第1中詰材18が締め固められ、ハット形鋼矢板16の外側に位置する盛土12が除去された状態(図4(a‐1))では、ハット形鋼矢板16には、図4(a‐2)に示されるような土圧が作用するが、その際にハット形鋼矢板16に作用する曲げモーメントは、図4(a‐3)に示される通りである。連結材22が設置される(図4(b‐1))と、連結材22の設置個所におけるハット形鋼矢板16の側方変位が拘束されるので、当該箇所に支点が設けられた構造モデル(図4(b‐2))と同等とみなされる。この状態で第2中詰材24が充填され締め固められる(図4(c‐1))と、ハット形鋼矢板16には、図4(c‐2)に示されるような土圧が作用する(図4(c‐2)においてハッチングは、図4(a‐2)における土圧を示す)が、その際にハット形鋼矢板16に作用する曲げモーメントは、図4(c‐3)に示される通りである。図4(a‐3)と図4(c‐3)を重ね合わせると、図4(d‐1)の状態においてハット形鋼矢板16に作用する曲げモーメントが得られる(図4(d‐2)参照)。 FIG. 4 is a series for explaining changes in the bending moment acting on the hat-shaped steel sheet pile 16 in the filling step of the first filling material 18, the installation step of the connecting member 22, and the filling step of the second filling material 24. It is a figure of. In a state where the first filling material 18 is compacted and the embankment 12 located outside the hat-shaped steel sheet pile 16 is removed (FIG. 4 (a-1)), the hat-shaped steel sheet pile 16 is shown in FIG. The earth pressure as shown in a-2) acts, and the bending moment acting on the hat-shaped steel sheet pile 16 at that time is as shown in FIG. 4 (a-3). When the connecting member 22 is installed (FIG. 4 (b-1)), the lateral displacement of the hat-shaped steel sheet pile 16 at the location where the connecting member 22 is installed is restricted, so that a structural model in which a fulcrum is provided at that location. (Fig. 4 (b-2)) is considered to be equivalent. When the second filling material 24 is filled and compacted in this state (FIG. 4 (c-1)), earth pressure as shown in FIG. 4 (c-2) acts on the hat-shaped steel sheet pile 16. (Hatching in FIG. 4 (c-2) indicates earth pressure in FIG. 4 (a-2)), but the bending moment acting on the hat-shaped steel sheet pile 16 at that time is shown in FIG. 4 (c-3). As shown in. By superimposing FIGS. 4 (a-3) and 4 (c-3), a bending moment acting on the hat-shaped steel sheet pile 16 in the state of FIG. 4 (d-1) can be obtained (FIG. 4 (d-2). )reference).

上記の構築方法の効果についてより詳細に説明すると、連結材22を設置する前に第1中詰材18の充填・締固め作業を行うため、第1中詰材18の締固め作業時には当該作業の障害となる連結材22が存在せず、効率的な締固め作業が可能になるとともに、締固め機械の選択も自由に行うことができる。第1中詰材18の充填・締固め作業が行われるときには、壁体14の上部には連結材22による支持がなく、いわゆる自立壁状態になっており、この状態に対応した応答(変形、曲げモーメント分布等)を呈している。連結材22が設置されると、第2中詰材24の充填・締固め作業が行われるが、この時点では、壁体14の上部は連結材22によって支持されている。そのため、第2中詰材24の充填・締固め作業においては、連結材22による支持がある状態に対応した応答(変形、曲げモーメント分布等)を呈することとなる。そして、自立壁状態時の応答と、連結材22による支持時の応答とを合成した応答が、最終的な壁体14の応答(変形、曲げモーメント分布等)となる。壁体14の壁高部分の殆どの範囲において、曲げモーメント分布の向きは、自立壁状態と連結材22による支持時の状態とでは異なるため、合成された曲げモーメントは、かなり小さなものとなる(図4(d‐2)参照)。また、連結材22には、第1中詰材18の充填・締固めに起因する張力の発生がないため、連結材22に最終的に発生する張力もかなり小さくなる。このため、壁体構造物10の安全性を高めることができる。 Explaining the effect of the above construction method in more detail, since the filling and compacting work of the first filling material 18 is performed before the connecting material 22 is installed, the work is performed during the compacting work of the first filling material 18. Since there is no connecting member 22 that obstructs the above, efficient compaction work can be performed, and the compaction machine can be freely selected. When the filling / compacting work of the first filling material 18 is performed, the upper part of the wall body 14 is not supported by the connecting material 22 and is in a so-called self-supporting wall state, and the response (deformation, deformation, corresponding to this state) Bending moment distribution, etc.). When the connecting member 22 is installed, the filling / compacting work of the second filling member 24 is performed. At this point, the upper portion of the wall body 14 is supported by the connecting member 22. Therefore, in the filling / compacting work of the second filling material 24, the response (deformation, bending moment distribution, etc.) corresponding to the state of being supported by the connecting material 22 is exhibited. Then, the response obtained by combining the response in the free-standing wall state and the response in the support by the connecting member 22 becomes the final response (deformation, bending moment distribution, etc.) of the wall body 14. In most of the wall height portion of the wall body 14, the direction of the bending moment distribution differs between the self-supporting wall state and the state when supported by the connecting member 22, so that the combined bending moment is considerably small ( See FIG. 4 (d-2)). Further, since the connecting material 22 does not generate tension due to filling and compaction of the first filling material 18, the tension finally generated in the connecting material 22 is also considerably reduced. Therefore, the safety of the wall structure 10 can be enhanced.

上述の実施形態では、壁体構造物10を構築しようとする地盤に盛土12が築堤されているが、盛土12を設けなくともよい。図5は、盛土12が設けられていない場合における壁体構造物10の構築方法を示した一連の図である。 In the above-described embodiment, the embankment 12 is laid on the ground on which the wall structure 10 is to be constructed, but the embankment 12 does not have to be provided. FIG. 5 is a series of views showing a method of constructing the wall structure 10 when the embankment 12 is not provided.

すなわち、互いに嵌合された多数の壁体構成部材16によって形成される壁体14を所定間隔隔てた対向位置に2列をなすように、地盤に埋設する(図5(a)参照)。次いで、2列の壁体14によって形成される空間内に、所定高さまで充填材を充填し締め固めて、第1中詰材18とする(図5(b)参照)。次いで、必要に応じて、ハット形鋼矢板の所定部位に腹起20を設置する。次いで、第1中詰材18の表面よりも上方の個所において、連結材(例えば、タイロッドやタイワイヤー等の抗張力部材)22によってハット形鋼矢板16同士を連結する(図5(b)参照)。次いで、第1中詰材20の表面より上方の空間に充填材を充填し締め固めて第2中詰材24とする(図5(c)参照)。最後に、任意的ではあるが、第2中詰材24の表面に、第2中詰材24を保護するための保護工26を設ける(図5(d)参照)。なお、盛土を設けない形態においても、盛土を設ける上記形態と同様に、第1頭部連結材25a、第2頭部連結材25b、断面方向連結材25c、鉄筋コンクリート製の頂版25d、及び抑止部材18を設置してもよい。 That is, the wall bodies 14 formed by a large number of wall body constituent members 16 fitted to each other are buried in the ground so as to form two rows at opposite positions separated by a predetermined interval (see FIG. 5A). Next, the space formed by the two rows of wall bodies 14 is filled with a filler to a predetermined height and compacted to form a first filling material 18 (see FIG. 5B). Next, if necessary, the abdominal ridge 20 is installed at a predetermined portion of the hat-shaped steel sheet pile. Next, the hat-shaped steel sheet piles 16 are connected to each other by a connecting material (for example, a tensile strength member such as a tie rod or a tie wire) 22 at a position above the surface of the first filling material 18 (see FIG. 5 (b)). .. Next, the space above the surface of the first filling material 20 is filled with the filling material and compacted to obtain the second filling material 24 (see FIG. 5C). Finally, although optional, a protective work 26 for protecting the second filling material 24 is provided on the surface of the second filling material 24 (see FIG. 5D). Even in the form in which the embankment is not provided, the first head connecting material 25a, the second head connecting material 25b, the cross-sectional direction connecting material 25c, the reinforced concrete top plate 25d, and the restraint are similarly provided. The member 18 may be installed.

盛土12を設けない形態では、第1中詰材18及び第2中詰材24の材料となる充填材として、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料が用いられる。 In the form in which the embankment 12 is not provided, at least one or more of earth and sand, improved soil, slag, and a time-curable material can be used as the filler to be the material of the first filling material 18 and the second filling material 24. Used.

盛土12を設けない形態においても、盛土12を設ける形態と同様に、効率的な締固め作業が可能になるとともに、締固め機械の選択も自由に行うことができるうえ、壁体構造物10の安全性を高めることができる。 Even in the form in which the embankment 12 is not provided, as in the form in which the embankment 12 is provided, efficient compaction work can be performed, the compaction machine can be freely selected, and the wall structure 10 can be used. Safety can be increased.

上述の実施形態では、壁体構成部材16としてハット形鋼矢板16が用いられているが、ハット形鋼矢板以外の鋼矢板(U形鋼矢板、Z形鋼矢板、BOX形鋼矢板など)、鋼管矢板(円形鋼管矢板、角形鋼管矢板)、軽量鋼矢板、箱型矢板、又はコンクリート矢板(溝形コンクリート矢板、波形コンクリート矢板)であって、嵌合継手を有するものを壁体構成部材16として用いてもよい。 In the above-described embodiment, the hat-shaped steel sheet pile 16 is used as the wall body component 16, but steel sheet piles other than the hat-shaped steel sheet pile (U-shaped steel sheet pile, Z-shaped steel sheet pile, BOX-shaped steel sheet pile, etc.), Steel pipe sheet piles (circular steel pipe sheet piles, square steel pipe sheet piles), lightweight steel sheet piles, box-shaped sheet piles, or concrete sheet piles (grooved concrete sheet piles, corrugated concrete sheet piles) having fitting joints as wall constituent members 16. You may use it.

本発明は、以上の発明の実施の形態に限定されることなく、特許請求の範囲に記載された発明の範囲内で、種々の変更が可能であり、それらも本発明の範囲内に包含されるものであることはいうまでもない。 The present invention is not limited to the embodiments of the above invention, and various modifications can be made within the scope of the invention described in the claims, and these are also included in the scope of the present invention. It goes without saying that it is a thing.

例えば、図示されている構成要素の細部は、単なる例示的なものにすぎず、これらの細部を修正してもよい。 For example, the details of the components shown are merely exemplary and may be modified.

10 壁体構造物
12 盛土
14 壁体
16 壁体構成部材(ハット形鋼矢板)
18 第1中詰材
20 腹起
22 連結材
24 第2中詰材
25a 第1頭部連結材
25b 第2頭部連結材
25c 断面方向連結材
25d 鉄筋コンクリート製の頂版
26 保護工
28 抑止部材
10 Wall structure 12 Filling 14 Wall 16 Wall components (hat-shaped steel sheet pile)
18 1st filling material 20 Abdominal raising 22 Connecting material 24 2nd filling material 25a 1st head connecting material 25b 2nd head connecting material 25c Cross-sectional direction connecting material 25d Reinforced concrete top plate 26 Protective work 28 Deterrent member

Claims (19)

壁体構造物の構築方法であって、
前記壁体構造物を構築しようとする地盤に盛土を築堤する工程と、
前記盛土が築堤された地盤に、互いに嵌合された多数の壁体構成部材によって形成される壁体を所定間隔隔てた対向位置に2列をなすように所定手段で埋設する工程と、
2列の前記壁体によって形成される空間内の前記盛土を第1中詰材とする工程と、
前記第1中詰材の表面よりも上方の個所における前記壁体の所定部位において、連結材によって前記壁体同士を連結する工程と、
前記第1中詰材の表面より上方の空間に充填材を充填して少なくとも1層の第2中詰材とする工程と、
を含むことを特徴とする構築方法。
It is a method of constructing a wall structure,
The process of embankment on the ground where the wall structure is to be constructed, and
A step of burying a wall body formed of a large number of wall body constituent members fitted to each other in two rows at opposite positions separated by a predetermined distance in the ground on which the embankment is embanked by a predetermined means.
A step of using the embankment in the space formed by the two rows of walls as the first filling material, and
A step of connecting the wall bodies with a connecting material at a predetermined portion of the wall body at a position above the surface of the first filling material.
A step of filling a space above the surface of the first filling material with a filler to form at least one layer of the second filling material.
A construction method characterized by including.
前記第1中詰材が、前記盛土の一部であることを特徴とする請求項1に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to claim 1, wherein the first filling material is a part of the embankment. 前記第2中詰材が、前記壁体の外側に位置する前記盛土の一部を流用したものであることを特徴とする請求項1又は2に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to claim 1 or 2, wherein the second filling material is a part of the embankment located outside the wall. 前記盛土を形成する材料が、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料であることを特徴とする請求項1から請求項3までのいずれか1項に記載された壁体構造物の構築方法。 The method according to any one of claims 1 to 3, wherein the material forming the embankment is at least one of earth and sand, improved soil, slag, and a time-curable material. How to build a wall structure. 壁体構造物の構築方法であって、
前記壁体構造物を構築しようとする地盤に、互いに嵌合された多数の壁体構成部材によって形成される壁体を所定間隔隔てた対向位置に2列をなすように所定手段で埋設する工程と、
2列の前記壁体によって形成される空間内に充填材を充填して第1中詰材とする工程と、
前記第1中詰材の表面よりも上方の個所における前記壁体の所定部位において、連結材によって前記壁体同士を連結する工程と、
前記第1中詰材の表面より上方の空間に充填材を充填して少なくとも1層の第2中詰材とする工程と、
を含むことを特徴とする構築方法。
It is a method of constructing a wall structure,
A step of burying a wall body formed of a large number of wall body constituent members fitted to each other in two rows at opposite positions separated by a predetermined distance in the ground on which the wall body structure is to be constructed by a predetermined means. When,
A step of filling the space formed by the two rows of the wall bodies with a filler to form a first filling material, and
A step of connecting the wall bodies with a connecting material at a predetermined portion of the wall body at a position above the surface of the first filling material.
A step of filling a space above the surface of the first filling material with a filler to form at least one layer of the second filling material.
A construction method characterized by including.
前記所定手段が、バイブロハンマを用いた振動打設、又は油圧圧入装置による圧入であることを特徴とする請求項1から請求項5までのいずれか1項に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to any one of claims 1 to 5, wherein the predetermined means is vibration driving using a vibro hammer or press fitting by a hydraulic press-fitting device. .. 前記充填材が、土砂、改良土、スラグ、又は経時硬化性材料のうち少なくとも1種以上の材料であることを特徴とする請求項1から請求項6までのいずれか1項に記載された壁体構造物の構築方法。 The wall according to any one of claims 1 to 6, wherein the filler is at least one of earth and sand, improved soil, slag, and a time-curable material. How to build a body structure. 前記第1中詰材とする工程と前記壁体同士を連結する工程との間に、前記壁体構成部材の所定部位に腹起を設置する工程をさらに含むことを特徴とする請求項1から請求項7までのいずれか1項に記載された壁体構造物の構築方法。 According to claim 1, a step of installing an abdomen at a predetermined portion of the wall body constituent member is further included between the step of forming the first filling material and the step of connecting the wall bodies to each other. The method for constructing a wall structure according to any one of claims 7. 前記連結材が、抗張力部材であることを特徴とする請求項1から請求項8までのいずれか1項に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to any one of claims 1 to 8, wherein the connecting member is a tensile strength member. 前記壁体のうち一方の壁体の頭部に、前記一方の壁体の延長方向に延びるように第1頭部連結材を設置し、前記壁体のうち他方の壁体の頭部に、前記他方の壁体の延長方向に延びるように第2頭部連結材を設置することを特徴とする請求項1から請求項9までのいずれか1項に記載された壁体構造物の構築方法。 A first head connecting member is installed on the head of one of the walls so as to extend in the extension direction of the one wall, and on the head of the other wall of the walls, The method for constructing a wall structure according to any one of claims 1 to 9, wherein the second head connecting member is installed so as to extend in the extension direction of the other wall body. .. 複数本の断面方向連結材によって前記第1頭部連結材と前記第2頭部連結材を連結することを特徴とする請求項10に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to claim 10, wherein the first head connecting member and the second head connecting member are connected by a plurality of cross-sectional direction connecting members. 前記第2中詰材の表面を被覆するように保護工を施すことを特徴とする請求項1から請求項11までのいずれか1項に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to any one of claims 1 to 11, wherein a protective work is applied so as to cover the surface of the second filling material. 前記保護工が、現場施工コンクリート、プレキャストコンクリート版、又は鋼板であることを特徴とする請求項12に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to claim 12, wherein the protective work is on-site construction concrete, precast concrete slab, or steel plate. 前記壁体構成部材に、前記保護工の沈下を抑止するための抑止部材を設置することを特徴とする請求項12又は13に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to claim 12 or 13, wherein a deterrent member for suppressing the sinking of the protective work is installed on the wall component. 前記第1頭部連結材及び/又は前記第2頭部連結材に、前記第2中詰材の表面を被覆するように施された保護工の沈下を抑止するための抑止部材を設置することを特徴とする請求項10に記載された壁体構造物の構築方法 The first head connecting material and / or the second head connecting material shall be provided with a deterrent member for suppressing the sinking of the protective work provided so as to cover the surface of the second filling material. The method for constructing a wall structure according to claim 10 . 前記断面方向連結材に、前記第2中詰材の表面を被覆するように施された保護工の沈下を抑止するための抑止部材を設置することを特徴とする請求項11に記載された壁体構造物の構築方法 The wall according to claim 11, wherein a deterrent member for suppressing the sinking of the protective work provided so as to cover the surface of the second filling material is provided on the cross-sectional direction connecting member. How to build a body structure . 2列の前記壁体の頭部を鉄筋コンクリート製の頂版で連結することを特徴とする請求項1から請求項9までのいずれか1項に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to any one of claims 1 to 9, wherein the heads of the two rows of the wall bodies are connected by a top plate made of reinforced concrete. 前記第2中詰材の表面に上げ越しを施すことを特徴とする請求項1から請求項17までのいずれか1項に記載された壁体構造物の構築方法。 The method for constructing a wall structure according to any one of claims 1 to 17, wherein the surface of the second filling material is raised. 前記壁体構成部材が、鋼矢板、鋼管矢板、軽量鋼矢板、箱型矢板、又はコンクリート矢板であって、嵌合継手を有するものであることを特徴とする請求項1から請求項18までのいずれか1項に記載された構築方法。 Claims 1 to 18, wherein the wall body component is a steel sheet pile, a steel pipe sheet pile, a lightweight steel sheet pile, a box-shaped sheet pile, or a concrete sheet pile, and has a fitting joint. The construction method described in any one of the items.
JP2020087915A 2020-05-20 2020-05-20 How to build a wall structure Active JP6801910B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020087915A JP6801910B1 (en) 2020-05-20 2020-05-20 How to build a wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020087915A JP6801910B1 (en) 2020-05-20 2020-05-20 How to build a wall structure

Publications (2)

Publication Number Publication Date
JP6801910B1 true JP6801910B1 (en) 2020-12-16
JP2021181722A JP2021181722A (en) 2021-11-25

Family

ID=73741009

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020087915A Active JP6801910B1 (en) 2020-05-20 2020-05-20 How to build a wall structure

Country Status (1)

Country Link
JP (1) JP6801910B1 (en)

Also Published As

Publication number Publication date
JP2021181722A (en) 2021-11-25

Similar Documents

Publication Publication Date Title
JP2009516109A5 (en)
JP2007321452A (en) Construction method for bridge and bridge structure thereof
JP6812819B2 (en) Foundation reinforcement structure, reinforcement foundation structure and foundation reinforcement method
JP6834226B2 (en) Pile foundation and tower rebuilding method
JP4281567B2 (en) Reinforcement structure of existing pier foundation and reinforcement method of existing pier foundation
KR20090093556A (en) Panel , Wall Structure with panels and Construction Method using the Same
JP7017541B2 (en) Improvement structure and improvement method of existing sheet pile type quay
JP5041758B2 (en) Seismic isolation structure with artificial ground
JP2018003308A (en) Seismic reinforcement structure of pile foundation and construction method thereof
WO2007046142A1 (en) Retaining wall banking structure
JP2010203114A (en) Soil retaining construction method using large-sized sandbag and restraining pile together and soil retaining structure by the method
JP2021063404A (en) Improvement structure and improvement method of existing quay wall
JP4987652B2 (en) Reinforcement structure and method of embankment and linear embankment
JP6801910B1 (en) How to build a wall structure
JP2008223291A (en) Rigid frame bridge formed integrally with revetment and method of constructing same
JP2006316495A (en) Foundation structure of bridge pier and its construction method
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
JP5480744B2 (en) Foundation for structure and its construction method
JP2018003523A (en) Pile foundation structure, and reinforcement method for existing pile
JP2007197954A (en) Earth retaining wall construction method
JP6292028B2 (en) Embankment reinforcement structure
JP5065346B2 (en) Structure and construction method of reinforced earth embankment
JP6536895B2 (en) Concrete wall structure and construction method for reinforced embankment integrated bridge
JP2022176549A (en) flat slab structure
JP2022070388A (en) Wall body structure construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200520

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20200526

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20200929

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20201001

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20201027

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20201117

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20201118

R150 Certificate of patent or registration of utility model

Ref document number: 6801910

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250