JP6678806B1 - Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage - Google Patents

Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage Download PDF

Info

Publication number
JP6678806B1
JP6678806B1 JP2019205945A JP2019205945A JP6678806B1 JP 6678806 B1 JP6678806 B1 JP 6678806B1 JP 2019205945 A JP2019205945 A JP 2019205945A JP 2019205945 A JP2019205945 A JP 2019205945A JP 6678806 B1 JP6678806 B1 JP 6678806B1
Authority
JP
Japan
Prior art keywords
reinforcing
ring
suspension
cage
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019205945A
Other languages
Japanese (ja)
Other versions
JP2021080630A (en
Inventor
祐司 勝本
祐司 勝本
Original Assignee
株式会社 Cup商会
株式会社 Cup商会
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社 Cup商会, 株式会社 Cup商会 filed Critical 株式会社 Cup商会
Priority to JP2019205945A priority Critical patent/JP6678806B1/en
Application granted granted Critical
Publication of JP6678806B1 publication Critical patent/JP6678806B1/en
Publication of JP2021080630A publication Critical patent/JP2021080630A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

【課題】無溶接工法で用いられる鉄筋固定用金具の負担荷重を減らすことができ、建て込み作業時における撓みや変形が防止でき、施工安全性が確保された鉄筋籠を構築することができる特殊吊補強リングを提供すること。【解決手段】場所打ち杭用の鉄筋籠を構成する複数の主筋2と直交させて配設され、複数の主筋2との交差部に鉄筋固定用金具(第1金具20)が取り付けられるとともに、鉄筋籠の建て込み時に吊り具6が取り付けられる特殊吊補強リング4であって、鉄筋籠の中心軸方向に所定間隔を設けて配置される2以上のリング部11と、隣り合うリング部11どうしを連結する2以上の連結部12とを装備する。【選択図】図2PROBLEM TO BE SOLVED: To construct a rebar cage which can reduce the burden load of a metal fitting for fixing a rebar used in a non-welding method, prevent bending and deformation at the time of building work, and ensure construction safety. Providing suspension reinforcement rings. SOLUTION: The reinforcing bar is arranged so as to be orthogonal to a plurality of main bars 2 constituting a reinforcing bar cage for cast-in-place piles, and a reinforcing bar fixing metal fitting (first metal fitting 20) is attached to an intersection of the plurality of main reinforcing bars 2. A special suspension reinforcement ring 4 to which a hanger 6 is attached when a reinforcing bar cage is built up, and two or more ring portions 11 arranged at a predetermined interval in the central axis direction of the reinforcing bar cage, and adjacent ring portions 11 to each other. And two or more connecting parts 12 for connecting [Selection diagram] FIG.

Description

本発明は特殊吊補強リング、鉄筋籠、及び鉄筋籠の設計方法に関し、より詳細には、施工安全性が確保された鉄筋籠を構築することができる特殊吊補強リング、該特殊吊補強リングを備えた鉄筋籠、及び鉄筋籠の設計方法に関する。   The present invention relates to a special hanging reinforcement ring, a reinforcing cage, and a method of designing a reinforcing cage, and more particularly, to a special hanging reinforcing ring capable of constructing a reinforcing cage with secured construction safety, and a special hanging reinforcing ring. The present invention relates to a reinforced cage provided and a method of designing a reinforced cage.

構造物の建設現場では、構造物の耐震強度等を高めるために、地盤に杭を打ち込み、構造物を支える杭基礎を形成する工法が一般に採用されている。杭基礎の施工法の一つに場所打ち杭による施工法がある。場所打ち杭とは、筒状に組み立てられた鉄筋籠を掘削した杭孔内に建て込み、建て込み後にコンクリートを杭孔内に打ち込み、固めて形成したものである。場所打ち杭による施工法には、地面を掘削する方法等の違いにより、オールケーシング工法、アースドリル工法、リバース工法などのいくつかの工法が知られている。   2. Description of the Related Art In a construction site of a structure, a method of driving a pile into the ground and forming a pile foundation for supporting the structure is generally adopted in order to enhance the seismic strength of the structure. One of the construction methods for pile foundations is a construction method using cast-in-place piles. The cast-in-place pile is formed by building a cylindrically assembled reinforced cage into an excavated pile hole, driving the concrete into the pile hole after setting, and solidifying the concrete. Several construction methods, such as an all casing method, an earth drill method, and a reverse method, are known as a construction method using a cast-in-place pile due to a difference in a method of excavating the ground.

場所打ち杭を構築するために必要となる鉄筋籠の組み立てについては、従来、溶接による仮止めが行われることが多かった。しかしながら、2012年3月に「道路橋示方書・同解説」(社団法人 日本道路協会)が改訂され、「19.8 鉄筋かごの製作及び建込み」の(1)のただし書きには、「…ただし、鉄筋の組立においては、組立上の形状保持などのための溶接を行ってはならない。」と記載され、また、その解説には、「…、溶接による…施工品質の確保が困難であり鉄筋の断面減少等の欠陥が生じるおそれがあるため、…」と記載され、鉄筋籠の主要構成部材である主筋に直接の溶接を用いてはならないように規定されている。このため、現在では、溶接を行わない無溶接工法が採用されている。このような無溶接工法で製作された鉄筋籠については、下記の特許文献1に開示されている。   Conventionally, as for assembling a steel cage required for constructing a cast-in-place pile, temporary fixing by welding has been often performed. However, in March 2012, the "Road Bridge Specification and Commentary" (Japan Highway Association) was revised, and the proviso to (1) of "19.8 Reinforced Basket Production and Construction" states that "... However, in assembling the rebar, welding to maintain the shape during assembly, etc. must not be performed. "In addition, the commentary states," ..., it is difficult to secure the construction quality by welding. " Since there is a possibility that a defect such as a decrease in the cross section of the reinforcing bar may occur, "..." is specified, and it is stipulated that direct welding should not be used for the main bar, which is a main component of the reinforcing bar cage. For this reason, a welding-free construction method that does not perform welding is currently employed. A steel cage manufactured by such a welding-free method is disclosed in Patent Document 1 below.

特許文献1には、分割鉄筋籠が連結接続された連結鉄筋籠が記載されている。連結鉄筋籠を構成する分割鉄筋籠は、主筋と補強枠が格子状にそれぞれ交差するように配置され、環状の補強枠の内側に主筋が縦方向に所定本数格子状に配置されると共に、Uボルト形状の取り付け金具で補強枠が主筋に取付け保持固定され、その保持固定された補強枠間にフープ筋が多数並列されて、格子状に配置されると共に結束線又は取付金具で取付け保持固定されている。   Patent Literature 1 describes a connected rebar basket in which divided rebar baskets are connected and connected. The split reinforcing bars forming the connecting reinforcing bars are arranged such that the main reinforcing bars and the reinforcing frames cross each other in a lattice shape, and the main reinforcing bars are arranged inside the annular reinforcing frame in a predetermined number of grids in the vertical direction. The reinforcing frame is attached and held and fixed to the main reinforcing bar by the bolt-shaped mounting bracket, a large number of hoop bars are arranged in parallel between the held and fixed reinforcing frames, arranged in a lattice shape, and mounted and held and fixed by a binding wire or a mounting bracket. ing.

このような無溶接工法で製作される鉄筋籠については、「一般社団法人 日本基礎協会」が発刊している「場所打ちコンクリート杭の鉄筋かご無溶接工法 設計・施工に関するガイドライン」に則って、鉄筋籠の形状保持と建て込み時の安全性を確保するための検討を行うことが推奨されている。   Reinforcing bars manufactured by such a non-welding method are reinforced in accordance with the “Guidelines for the Design and Construction of Reinforced Baskets for Cast-in-Place Concrete Piles”, published by the Japan Foundation Association. It is recommended that consideration be given to maintaining the shape of the basket and ensuring safety during installation.

無溶接工法で製作される鉄筋籠は、主筋と、組立用鉄筋である補強枠(補強リングともいう)との各交点が取付金具(無溶接金具)で固定されるため、これら取付金具が取り付けられる補強リングが、鉄筋籠の形状保持、及び建て込み時の安全性確保に重要な役割を果たしている。上記道路橋示方書によれば、「組立用鉄筋の径及びその配置は、鉄筋かごの大きさや重量等によって異なるが、一般的に直径22mm程度の鉄筋を2〜3mの間隔に配置するのがよい。」と記載されている。   Since the intersections of the main reinforcing bars and the reinforcing frame (also referred to as a reinforcing ring), which is the reinforcing bar for assembly, are fixed with mounting brackets (no welding brackets), these mounting brackets are attached to the reinforcing bar cages manufactured by the non-welding method. The reinforcing ring plays an important role in maintaining the shape of the reinforced cage and ensuring safety during installation. According to the above-mentioned road bridge specification, "the diameter of the reinforcing steel bars and their arrangement vary depending on the size and weight of the reinforcing steel cage, but generally, reinforcing steel bars having a diameter of about 22 mm are arranged at intervals of 2 to 3 m. Good. "

[発明が解決しようとする課題]
阪神淡路の震災以降、年々、杭頭の鉄筋籠配筋の太径/多本数化が著しくなっており、杭頭の過大な荷重を従来同様の脚部主筋(すなわち、杭頭の鉄筋籠と比べて、細径/低本数の主筋からなる鉄筋籠)が支えるという配筋になってきている。また、従来滅多に使用されることのなかったD51等の極太径主筋、D32やD35などの太径の帯筋が使用され、また、杭長も中間支持層までだったものが、より深い支持層へ到達させるようになるなど、従来の溶接工法時代とは、全く異なる困難な施工条件になってきている。
[Problems to be solved by the invention]
Since the Hanshin-Awaji Earthquake, the diameter and the number of reinforcing bars in the pile head have been remarkably increasing year by year, and the excessive load on the pile head has been reduced by the same method as before. Reinforcement cages, which are made up of small diameter / low number of main reinforcements, have become supported. In addition, very large diameter main bars such as D51, which are rarely used in the past, and large-diameter band bars such as D32 and D35 are used, and the pile length is also up to the intermediate support layer. It has become a completely different and difficult construction condition from the era of the conventional welding method, such as reaching the layer.

このように数年前の鉄筋籠の配筋と比較して、現在の鉄筋籠の配筋は、主筋の径や本数等が前例のないものとなってきており、鉄筋籠の大重量化、大径化が進み、過去の経験が全く役に立たないほど、施工の難易度が高くなってきている。また、鉄筋籠の大重量化、大径化が進むにつれて、鉄筋籠の建て込み作業時に補強リングの撓みや変形を防止するために、吊り具が取り付けられる補強リングの大径化、板厚(断面積)の増大化が進んできている。   In this way, compared to several years ago, the reinforcing bars of the current reinforcing bars have become unprecedented in the diameter and number of main bars, and the weight of the reinforcing bars has been increased. As the diameter increases, the difficulty of construction is increasing so that past experience is of no use at all. In addition, as the weight and diameter of the reinforcing cage increase, the reinforcing ring to which the suspending device is attached is increased in diameter and plate thickness (in order to prevent bending and deformation of the reinforcing ring during the work of building the reinforcing cage. (Cross-sectional area) is increasing.

しかしながら、補強リングの板厚(断面積)が大きくなると、主筋と補強リングとの交点(交差部)に取付金具を強固に取り付けにくくなり、また、取付金具の負担荷重も増大し、鉄筋下がりなどの固定位置のずれが生じやすくなるという課題があった。
さらに、近年では、鉄筋籠の建て込み作業時における吊荷重(鉄筋籠総重量)が50tを優に超える場合もあり、かかる場合、特許文献1に記載されているような従来の補強リングでは、建て込み作業時に撓みや変形が生じる虞が高くなるという課題があった。
However, when the plate thickness (cross-sectional area) of the reinforcing ring is increased, it becomes difficult to firmly attach the mounting bracket to the intersection (intersection) between the main reinforcing bar and the reinforcing ring, and the load on the mounting bracket increases, and the reinforcing bar falls. However, there has been a problem that the fixing position tends to shift.
Furthermore, in recent years, the hanging load (total weight of the reinforcing bar cage) during the work of setting up the reinforcing bar cage may well exceed 50 t, and in such a case, the conventional reinforcing ring as described in Patent Literature 1 requires: There was a problem that the possibility of bending or deformation occurring during the erection work increased.

特許第5382394号公報Japanese Patent No. 5382394

課題を解決するための手段及びその効果Means for solving the problem and its effects

本発明は上記課題に鑑みなされたものであって、無溶接工法で用いられる鉄筋固定用金具が負担する荷重を減らすことができ、また、建て込み作業時における撓みや変形を防止でき、施工安全性が確保された鉄筋籠を構築することができる特殊吊補強リング、該特殊吊補強リングを備えた鉄筋籠、及び鉄筋籠の設計方法を提供することを目的としている。   The present invention has been made in view of the above problems, and can reduce a load borne by a reinforcing bar fixing metal used in a welding-free method, and can prevent bending and deformation at the time of a erection work, thereby ensuring construction safety. An object of the present invention is to provide a special hanging reinforcement ring capable of constructing a reinforcing cage having ensured properties, a reinforcing cage provided with the special hanging reinforcing ring, and a method of designing a reinforcing cage.

上記目的を達成するために本発明に係る特殊吊補強リング(1)は、場所打ち杭用の鉄筋籠を構成する複数の主筋と直交させて配設され、前記複数の主筋との交差部に鉄筋固定用金具が取り付けられるとともに、前記鉄筋籠の建て込み時に吊り具が取り付けられる特殊吊補強リングであって、
当該特殊補強リングが、
前記鉄筋籠の中心軸方向に所定間隔を設けて配置される2以上のリング部と、
前記所定間隔を設けて配置される隣り合う前記リング部の内側面どうしを連結する2以上の連結部とを備えていることを特徴としている。
In order to achieve the above object, a special suspension reinforcing ring (1) according to the present invention is disposed orthogonally to a plurality of main bars constituting a steel cage for a cast-in-place pile, and at an intersection with the plurality of main bars. Reinforcing metal fittings are attached, a special hanging reinforcement ring to which a hanging tool is attached when the reinforcing bar is built,
The special reinforcing ring is
Two or more ring portions arranged at predetermined intervals in the center axis direction of the reinforcing bar,
And two or more connecting portions for connecting the inner surfaces of the adjacent ring portions arranged at the predetermined interval .

上記特殊吊補強リング(1)によれば、2以上の前記リング部と、前記所定間隔を設けて配置される隣り合う前記リング部の内側面どうしを連結する2以上の連結部とを備えているので、前記鉄筋籠の建て込み時の吊荷重(鉄筋籠総重量)を2以上の前記リング部に均等分散させることができ、前記リング部の撓みや変形を防止できるとともに、前記鉄筋固定用金具が負担する荷重を減らすことができる。これにより、前記鉄筋籠の建て込み作業の安全性を高めることができ、施工安全性の向上を図ることができる。 According to the above-mentioned special suspension reinforcing ring (1), it is provided with two or more of the ring portions and two or more connecting portions for connecting inner surfaces of adjacent ring portions arranged at the predetermined interval. As a result, the hanging load (total weight of the reinforcing bar) when the reinforcing bar is built can be evenly distributed to two or more of the ring portions, so that bending and deformation of the ring portion can be prevented, and the reinforcing bars can be fixed. The load borne by the fitting can be reduced. Thereby, the safety of the work of laying the reinforcing bar can be enhanced, and the construction safety can be improved.

また本発明に係る特殊吊補強リング(2)は、上記特殊吊補強リング(1)において、
前記連結部が、隣り合う前記リング部の内側面に固定されて、該内側面より内側方向へ張り出した形状を有し
前記主筋と前記連結部との間に、前記張り出した形状分のスペースが確保されていることを特徴としている。
The special suspension reinforcing ring (2) according to the present invention is the special suspension reinforcement ring (1),
The connecting portion is fixed to an inner surface of the adjacent ring portion, and has a shape projecting inward from the inner surface ,
A space for the protruding shape is secured between the main reinforcement and the connecting portion .

上記特殊吊補強リング(2)によれば、前記連結部が、隣り合う前記リング部の内側面に固定されて、該内側面より内側方向へ張り出した形状を有し、前記主筋と前記連結部との間に、前記張り出した形状分のスペースが確保されているので、前記リング部周上に配置される前記複数の主筋と、前記連結部との間に前記張り出した形状分のスペースを確保することができる。したがって、杭孔への建て込み後にコンクリートが十分に回り込むように、コンクリートの打設を適切に行うことができる。 According to the special suspension reinforcing ring (2), the connecting portion is fixed to an inner surface of the adjacent ring portion and has a shape projecting inward from the inner surface , and the main reinforcement and the connecting portion are provided. Between the plurality of main bars arranged on the circumference of the ring portion and the connecting portion, a space corresponding to the overhanging shape is secured. can do. Therefore, it is possible to appropriately cast the concrete so that the concrete sufficiently wraps around the pile hole.

また本発明に係る特殊吊補強リング(3)は、上記特殊吊補強リング(1)において、
前記連結部が、ワイヤーロープを含んで構成され、
前記リング部の内側面に、前記ワイヤーロープを取り付けるための2以上の取付部が設けられていることを特徴としている。
The special suspension reinforcing ring (3) according to the present invention is the above-mentioned special suspension reinforcement ring (1),
The connecting portion is configured to include a wire rope,
Two or more attachment portions for attaching the wire rope are provided on the inner surface of the ring portion.

上記特殊吊補強リング(3)によれば、前記連結部が、前記ワイヤーロープを含んで構成され、前記リング部の内側面に、前記ワイヤーロープを取り付けるための2以上の前記取付部が設けられているので、上記特殊吊補強リング(2)と同様の効果が得られるとともに、嵩張らない形態にすることができ、運搬時の省スペース化とともに運搬効率の向上を図ることができる。   According to the special hanging reinforcement ring (3), the connection portion includes the wire rope, and two or more attachment portions for attaching the wire rope are provided on an inner surface of the ring portion. Therefore, the same effect as the above-mentioned special suspension reinforcing ring (2) can be obtained, and it can be made not bulky, so that it is possible to save space during transportation and improve transportation efficiency.

また、前記ワイヤーロープは、長さが異なる複数種類のものを含んで構成されてもよく、かかる構成によれば、隣り合う前記リング部の間隔調整や間隔変更に容易に対応することができる。また、2以上の前記取付部は、前記リング部の内側面より内側方向へ張り出した形状としてもよい。   Further, the wire rope may include a plurality of types having different lengths, and according to such a configuration, it is possible to easily cope with an interval adjustment or an interval change between the adjacent ring portions. Further, the two or more attachment portions may have a shape projecting inward from the inner surface of the ring portion.

また本発明に係る特殊吊補強リング(4)は、上記特殊吊補強リング(3)において、
前記連結部が、連結棒を含んで構成され、
前記リング部の内側面に、前記連結棒を取り付けるための2以上の取付部が設けられていることを特徴としている。
The special suspension reinforcing ring (4) according to the present invention is the special suspension reinforcement ring (3),
The connecting portion is configured to include a connecting rod,
Two or more attachment portions for attaching the connecting rod are provided on an inner surface of the ring portion.

上記特殊吊補強リング(4)によれば、前記連結部が、前記連結棒を含んで構成され、前記リング部の内側面に、前記連結棒を取り付けるための2以上の前記取付部が設けられているので、上記特殊吊補強リング(2)と同様の効果が得られるとともに、上記特殊吊補強リング(3)と同様に、嵩張らない形態にすることができ、運搬時の省スペース化とともに運搬効率の向上を図ることができる。   According to the special suspension reinforcing ring (4), the connecting portion is configured to include the connecting bar, and two or more of the mounting portions for mounting the connecting bar are provided on an inner surface of the ring portion. As a result, the same effect as that of the special suspension reinforcing ring (2) can be obtained, and in the same manner as the special suspension reinforcement ring (3), it can be made not bulky. Efficiency can be improved.

前記連結棒は、ネジ棒鋼でもよいし、異形棒鋼でのよいし、少なくとも両端部分にネジ加工が施された異形棒鋼でもよいし、その他の棒鋼であってもよい。
また、2以上の前記取付部に前記連結棒を取り付ける形態は、特に限定されない。例えば、前記連結棒の両端部分に取り付け可能な締結・連結具などを用いて、前記取付部に前記連結棒を取り付けもよいし、他の取り付け方法であってもよい。
The connection rod may be a threaded steel bar, a deformed steel bar, a deformed steel bar having at least both ends threaded, or another steel bar.
The form in which the connecting rod is attached to the two or more attachment portions is not particularly limited. For example, the connecting rod may be attached to the attaching portion using a fastening / connecting tool that can be attached to both end portions of the connecting rod, or another attaching method may be used.

また、前記連結棒は、長さが異なる複数種類のものを含んで構成されてもよいし、前記取付部に取り付ける位置調整が可能な構成でもよい。かかる構成によれば、隣り合う前記リング部の間隔調整や間隔変更に容易に対応することが可能となる。   Further, the connecting rod may include a plurality of types having different lengths, or may be configured to be capable of adjusting a position where the connecting rod is attached to the attaching portion. According to such a configuration, it is possible to easily cope with the adjustment of the interval between adjacent ring portions or the change of the interval.

また本発明に係る特殊吊補強リング(5)は、上記特殊吊補強リング(1)〜(4)のいずれかにおいて、
2以上の前記リング部のうち少なくとも最上段リング部が、前記交差部において、前記鉄筋固定用金具を上下2箇所に取り付け可能な縦幅を備えていることを特徴としている。
Further, the special suspension reinforcing ring (5) according to the present invention is the special suspension reinforcement ring (1) to (4),
At least the uppermost ring portion of the two or more ring portions has a vertical width at the intersection where the reinforcing metal fixing bracket can be attached to two upper and lower locations.

上記特殊吊補強リング(5)によれば、2以上の前記リング部のうち少なくとも前記最上段リング部の前記交差部において、前記鉄筋固定用金具を上下2箇所に取り付けることが可能となる。これにより、前記交差部において前記鉄筋固定用金具が負担する荷重を分散させて、前記鉄筋固定用金具1個当たりにかかる荷重を減らす効果を高めることができ、前記主筋の固定位置のずれ防止効果を高め、施工安全性を一層向上させることができる。   According to the special suspension reinforcing ring (5), it is possible to attach the reinforcing bar fixing bracket to two upper and lower portions at least at the intersection of the uppermost ring portion of the two or more ring portions. This makes it possible to increase the effect of dispersing the load borne by the reinforcing-bar fixing metal at the intersection, thereby reducing the load applied to each reinforcing-bar fixing metal, and to prevent the main bar from being displaced in the fixing position. And the construction safety can be further improved.

また本発明に係る場所打ち杭用の鉄筋籠(1)は、上記特殊吊補強リング(1)〜(5)のいずれかを備え、該特殊吊補強リングの周上に複数の主筋が鉄筋固定用金具により取り付けられていることを特徴としている。   Further, the steel cage for cast-in-place pile according to the present invention includes any one of the special hanging reinforcing rings (1) to (5), and a plurality of main reinforcing bars are fixed on the periphery of the special hanging reinforcing ring. It is characterized by being attached by metal fittings.

上記場所打ち杭用の鉄筋籠(1)によれば、上記特殊吊補強リング(1)〜(5)のいずれかを備え、該特殊吊補強リングの周上に複数の主筋が鉄筋固定用金具により取り付けられているので、鉄筋籠の建て込み作業をより安全に実施することが可能となり、施工安全性の向上を図ることができる。   According to the steel cage for cast-in-place pile (1), any one of the special suspension reinforcing rings (1) to (5) is provided, and a plurality of main reinforcing bars are provided around the special suspension reinforcement ring. As a result, it is possible to carry out the work of building the reinforcing bar more safely, and to improve the construction safety.

また本発明に係る鉄筋籠の設計方法(1)は、鉄筋固定用金具を用いた無溶接工法により組み立てられる場所打ち杭用の鉄筋籠の設計方法であって、
前記鉄筋籠の建て込み時に吊り具が取り付けられる吊補強リング周上の主筋間における剪断応力度と曲げ応力度とが所定条件を満たすように、前記吊補強リングの仕様と前記吊り具を取り付ける吊箇所数とを決定する第1工程と、
前記鉄筋籠の建て込み時の吊荷重を前記吊補強リング周上の前記主筋による分割数で除算して、前記吊補強リング周上における前記主筋との交差部にかかる荷重(以下、分散荷重という)を算出する第2工程と、
前記分散荷重と、前記交差部に取り付けられる前記鉄筋固定用金具の許容支持力、又は該許容支持力に所定の安全率を考慮して決定された許容安全支持力とを比較する第3工程と、
前記分散荷重が前記許容支持力又は前記許容安全支持力より大きい場合、前記鉄筋籠の建て込み時に、前記交差部に取り付けられる前記鉄筋固定用金具1個当たりの負担荷重が前記許容安全支持力以下となるように、前記吊補強リングへの前記鉄筋固定用金具の取付個数を決定する第4工程とを含み、
前記分散荷重が、前記許容支持力又は前記許容安全支持力より大きい所定値以上となる場合、又は前記鉄筋固定用金具の取付個数が、前記分割数の2倍より大きな値となる場合に、前記吊補強リングに、上記特殊吊補強リング(1)〜(5)のいずれかを用いるようにすることを特徴としている。
The method (1) for designing a reinforcing cage according to the present invention is a method for designing a reinforcing cage for a cast-in-place pile assembled by a welding-free method using a reinforcing-bar fixing metal,
The specifications of the suspension reinforcing ring and the suspension for mounting the suspension are so set that the degree of shear stress and the degree of bending stress between the main reinforcements on the periphery of the suspension reinforcement ring to which the suspension is attached when the reinforcing cage is installed satisfy predetermined conditions. A first step of determining the number of locations;
The load applied to the intersection with the main reinforcement on the circumference of the suspension reinforcement ring is divided by the suspension load at the time of building the reinforcing cage and divided by the number of divisions of the main reinforcement on the periphery of the suspension reinforcement ring (hereinafter referred to as a dispersed load). ), And
A third step of comparing the distributed load with an allowable supporting force of the reinforcing metal fixing bracket attached to the intersection, or an allowable safety supporting force determined in consideration of a predetermined safety factor for the allowable supporting force; and ,
When the distributed load is greater than the allowable supporting force or the allowable safety supporting force, when the reinforcing bar is erected, a load per one reinforcing bar fixing bracket attached to the intersection is equal to or less than the allowable safety supporting force. A fourth step of determining the number of the metal reinforcing bars to be attached to the suspension reinforcing ring,
When the distributed load is equal to or more than a predetermined value larger than the allowable supporting force or the allowable safety supporting force, or when the number of the reinforcing bar fixing brackets is a value larger than twice the number of divisions, The present invention is characterized in that any one of the special hanging reinforcing rings (1) to (5) is used as the hanging reinforcing ring.

上記鉄筋籠の設計方法(1)によれば、前記第1工程により、前記吊補強リングに撓み又は変形を生じさせないように、前記吊補強リングにかかる荷重を均等分散させるための前記吊補強リングの仕様と前記吊箇所数とが決定され、前記第2工程により、前記分散荷重が算出される。
また、前記第3工程により、前記分散荷重と、前記鉄筋固定用金具の許容支持力、又は前記許容安全支持力とが比較されて、前記第4工程により、前記鉄筋固定用金具1個当たりの負担荷重が、前記許容安全支持力以下となるように、前記吊補強リングへの前記鉄筋固定用金具の取付個数が決定される。
According to the reinforcing cage design method (1), in the first step, the suspension reinforcement ring for evenly distributing a load applied to the suspension reinforcement ring so that the suspension reinforcement ring does not bend or deform. Are determined and the number of suspension points is determined, and the dispersion load is calculated in the second step.
In addition, in the third step, the distributed load is compared with the allowable supporting force of the reinforcing bar fixing metal or the allowable safety supporting force, and in the fourth step, the per-reinforcing metal fitting is determined. The number of the reinforcing bar fixing brackets to be attached to the suspension reinforcing ring is determined so that the burden load is equal to or less than the allowable safety supporting force.

また、前記分散荷重が、前記許容支持力又は前記許容安全支持力より大きい所定値以上となる場合、又は前記鉄筋固定用金具の取付個数が、前記分割数の2倍より大きな値となる場合に、前記吊補強リングとして、上記特殊吊補強リング(1)〜(5)のいずれかを用いるように設計される。したがって、前記鉄筋籠の建て込み時の吊荷重(鉄筋籠総重量)を前記吊補強リング又は前記特殊吊補強リングに均等分散させることができ、また、前記鉄筋固定用金具が負担する荷重を減らすことができる。   Further, when the distributed load is equal to or more than a predetermined value larger than the allowable supporting force or the allowable safety supporting force, or when the number of the reinforcing bar fixing brackets is a value larger than twice the number of divisions. It is designed to use any one of the special hanging reinforcing rings (1) to (5) as the hanging reinforcing ring. Therefore, the hanging load (total weight of the reinforcing cage) at the time of setting the reinforcing cage can be evenly distributed to the reinforcing reinforcing ring or the special reinforcing reinforcing ring, and the load that the reinforcing metal fixing bracket bears can be reduced. be able to.

これにより、前記鉄筋固定用金具を用いた無溶接工法で、太径や極太径の前記主筋を用いて、大重量の前記鉄筋籠を設計する際に、鉄筋籠の建て込み時に前記吊補強リングの撓み若しくは変形、又は主筋の位置ずれ(許容値以上の位置ずれ)が起きないようにするための前記吊補強リングの仕様や種類、吊箇所数、金具数を、熟練作業者の経験や勘に頼ることなく、簡単に決定することができる。したがって、前記鉄筋固定用金具を用いた施工安全性の高い、より信頼性の高い無溶接工法を様々な施工現場に広めることができる。   With this, when designing the heavy-weight reinforcing bar using the large-diameter or extra-large-diameter main reinforcing bar by the non-welding method using the reinforcing-bar fixing metal, the suspension reinforcing ring is used when the reinforcing-bar cage is installed. In order to prevent the bending or deformation of the main reinforcement, or the displacement of the main reinforcement (displacement exceeding the allowable value), the specifications and types of the suspension reinforcing ring, the number of suspension points, and the number of brackets are determined by the experience and intuition of the skilled worker. Can be easily determined without resorting to Therefore, a highly reliable welding-free construction method using the metal fittings for reinforcing bars can be spread to various construction sites.

また本発明に係る鉄筋籠の設計方法(2)は、上記鉄筋籠の設計方法(1)において、
前記第4工程では、
前記交差部の数に相当する個数の前記鉄筋固定用金具の許容支持力には、第1の評価係数を乗じた値を用い、
前記交差部の数を超えた残りの個数の前記鉄筋固定用金具の許容支持力には、前記第1の評価係数よりも低い第2の評価係数を乗じた値を用いて、
前記鉄筋固定用金具1個当たりの負担荷重を求めることを特徴としている。
In addition, the method (2) for designing a reinforcing bar cage according to the present invention is the method for designing a reinforcing bar cage (1) described above.
In the fourth step,
A value obtained by multiplying the first evaluation coefficient is used for the allowable bearing force of the reinforcing bar fixing pieces in a number corresponding to the number of the intersections,
The allowable supporting force of the remaining number of the reinforcing bar fixing members exceeding the number of the intersections, using a value multiplied by a second evaluation coefficient lower than the first evaluation coefficient,
The present invention is characterized in that a burden load per one of the reinforcing bar fixing brackets is obtained.

前記鉄筋固定用金具で前記主筋を固定したときの支持力には、多少のバラつきが生じる。
上記鉄筋籠の設計方法(2)によれば、前記鉄筋固定用金具1個当たりの負担荷重を求めるにあたり、前記第1の評価係数と、前記第2の評価係数とを用いることにより、前記支持力のバラつきが考慮された値として前記負担荷重を求めることができる。
そして、前記負担荷重が前記許容安全支持力以下となるように前記取付個数を決定することにより、前記支持力にバラつきが生じた場合でも、前記主筋のずれを許容範囲に確実に抑えることができる、すなわち、施工安全性が確保された鉄筋籠の設計を行うことができる。
There is some variation in the supporting force when the main reinforcing bar is fixed by the reinforcing bar fixing metal.
According to the rebar cage design method (2), the support load is obtained by using the first evaluation coefficient and the second evaluation coefficient in calculating the load to be applied to each of the reinforcing bar fixing brackets. The burden load can be determined as a value in which the variation in force is considered.
Then, by determining the number of attachments so that the burden load is equal to or less than the allowable safety support force, even when the support force varies, the displacement of the main muscle can be reliably suppressed to an allowable range. That is, it is possible to design a reinforced cage in which construction safety is ensured.

また本発明に係る鉄筋籠の設計方法(3)は、上記鉄筋籠の設計方法(2)において、
前記第1の評価係数が、0.8以上1.0以下であり、
前記第2の評価係数が、0.2以上0.7以下であることを特徴としている。
Further, the method (3) for designing a reinforcing bar cage according to the present invention is the method for designing a reinforcing bar cage (2) described above.
The first evaluation coefficient is 0.8 or more and 1.0 or less,
The second evaluation coefficient is 0.2 or more and 0.7 or less.

上記鉄筋籠の設計方法(3)によれば、前記第1の評価係数を0.8以上1.0以下の所定値に設定し、前記第2の評価係数を0.2以上0.7以下の所定値に設定することにより、前記支持力のバラつきが十分に考慮された値として前記負担荷重を求めることができ、施工安全性がより確実に確保されるように前記取付個数を決定することができる。   According to the reinforcing cage design method (3), the first evaluation coefficient is set to a predetermined value of 0.8 to 1.0, and the second evaluation coefficient is set to 0.2 to 0.7. By setting to the predetermined value, it is possible to obtain the burden load as a value in which the variation in the supporting force is sufficiently considered, and to determine the number of attachments so that construction safety is more reliably ensured. Can be.

本発明の実施の形態に係る特殊吊補強リングを用いて構築される鉄筋籠の要部構成を示す模式図である。It is a mimetic diagram showing an important section composition of a rebar basket constructed using a special hanging reinforcement ring concerning an embodiment of the invention. 実施の形態に係る特殊吊補強リングの一例を示す斜視図である。It is a perspective view showing an example of the special hanging reinforcement ring concerning an embodiment. 別の実施の形態に係る特殊吊補強リングを示す斜視図である。It is a perspective view showing the special suspension reinforcement ring concerning another embodiment. さらに別の実施の形態に係る特殊吊補強リングを示す斜視図である。It is a perspective view which shows the special suspension reinforcement ring which concerns on another embodiment. 実施の形態に係る鉄筋籠に用いられる鉄筋固定用金具(第1金具)を示す図であり、(a)は正面図、(b)は底面図である。It is a figure which shows the metal fittings (1st metal fittings) for reinforcing bars used for the steel cage which concerns on embodiment, (a) is a front view, (b) is a bottom view. 実施の形態に係る鉄筋籠に用いられる別の鉄筋固定用金具(第2金具)を示す図であり、(a)は正面図、(b)は底面図である。It is a figure which shows the metal fittings (2nd metal fittings) for another reinforcing rod used for the reinforcing rod basket which concerns on embodiment, (a) is a front view, (b) is a bottom view. 実施の形態に係る鉄筋籠の設計方法を説明するための表であり、吊補強リングの仕様及び吊箇所数の設計評価内容の一例を示す表である。It is a table | surface for demonstrating the design method of the rebar cage which concerns on embodiment, and is a table | surface which shows an example of the design evaluation content of the specification of the suspension reinforcement ring, and the number of suspension points. 実施の形態に係る鉄筋籠の設計方法を説明するための表であり、鉄筋固定用金具数及び負担荷重の設計評価内容の一例を示す表である。It is a table | surface for demonstrating the design method of the rebar cage which concerns on embodiment, Comprising: It is a table | surface which shows an example of the design evaluation content of the number of metal fittings for reinforcing bars, and burden load. 実施の形態に係る鉄筋籠の設計方法の手順を示すフローチャートである。It is a flowchart which shows the procedure of the design method of the rebar cage which concerns on embodiment.

以下、本発明に係る特殊吊補強リング、鉄筋籠、及び鉄筋籠の設計方法の実施の形態を図面に基づいて説明する。なお、以下に述べる実施の形態は、本発明の好適な具体例であるから、技術的に好ましい種々の限定が付されているが、本発明の範囲は、以下の説明において特に本発明を限定する旨の記載がない限り、これらの形態に限られるものではない。   Hereinafter, embodiments of a special suspension reinforcing ring, a reinforcing rod cage, and a method of designing a reinforcing rod cage according to the present invention will be described with reference to the drawings. Note that the embodiments described below are preferred specific examples of the present invention, and therefore, various technically preferable limitations are added. However, the scope of the present invention particularly limits the present invention in the following description. It is not limited to these forms unless otherwise stated.

図1は、実施の形態に係る特殊吊補強リングを用いて構築される鉄筋籠の要部構成を示す模式図である。図1は、鉄筋籠の建て込み作業の状態を示している。
無溶接工法により作製される場所打ち杭用の鉄筋籠(連結鉄筋籠)10は、複数の鉄筋籠1、1A、…が連結されて構築されている。
鉄筋籠10を構成する各節の鉄筋籠1、1Aは、中心軸の周囲に該中心軸の方向とほぼ平行に配列された複数の主筋2と、中心軸とほぼ直交する円周方向に配設され、複数の主筋2と交差部を有する複数のフープ筋3と、複数の主筋2の内側に配設され、これら主筋2と交差部を有する特殊吊補強リング4及び通常補強リング5とを含んで構成されている。
FIG. 1 is a schematic diagram showing a configuration of a main part of a reinforcing bar cage constructed using the special suspension reinforcing ring according to the embodiment. FIG. 1 shows the state of the work of setting up the reinforcing bar cage.
A reinforced cage for connected cast-in-place piles (connected reinforced cage) 10 manufactured by a non-welding method is constructed by connecting a plurality of reinforced cages 1, 1A,.
The reinforcing bars 1 and 1A of each node constituting the reinforcing bar cage 10 are arranged around a central axis and a plurality of main reinforcing bars 2 arranged substantially in parallel to the direction of the central axis, and in a circumferential direction substantially orthogonal to the central axis. A plurality of hoop bars 3 having a plurality of main bars 2 and intersections, and a special suspension reinforcing ring 4 and a normal reinforcing ring 5 disposed inside the plurality of main bars 2 and having an intersection with the main bars 2. It is comprised including.

これら主筋2と特殊吊補強リング4との交差部、並びにこれら主筋2と通常補強リング5との交差部が、鉄筋固定用金具(無溶接金具)である第1金具20によって固定されている。また、主筋2とフープ筋3との交差部は、鉄線結束、クリップ金具等(図示せず)により固定されている。   The intersection between the main reinforcement 2 and the special suspension reinforcing ring 4 and the intersection between the main reinforcement 2 and the normal reinforcement ring 5 are fixed by a first metal fitting 20 which is a metal fixing metal (no welding metal fitting). The intersection between the main bar 2 and the hoop bar 3 is fixed by iron wire binding, clip fittings, or the like (not shown).

特殊吊補強リング4は、上下2つのリング部11と、隣り合うリング部11どうしを連結する2以上の連結部12とを含んで構成されている。特殊吊補強リング4については後述する。   The special suspension reinforcing ring 4 includes two upper and lower ring portions 11 and two or more connecting portions 12 that connect adjacent ring portions 11 to each other. The special suspension reinforcing ring 4 will be described later.

通常補強リング5は、図1に示すように主筋2の内側に配設されてもよいし、主筋2の外側に配設される形態であってもよい。また、通常補強リング5は、帯状鋼板(平鋼材)で構成されてもよいし、アングル型(L型)鋼材などで構成されてもよい。   Normally, the reinforcing ring 5 may be disposed inside the main reinforcement 2 as shown in FIG. 1, or may be disposed outside the main reinforcement 2. In addition, the normal reinforcing ring 5 may be made of a strip-shaped steel plate (flat steel material), or may be made of an angle type (L-type) steel material.

鉄筋籠1、1Aの大きさは、施工現場ごとに異なり、その直径が0.6m〜3m程度以上のものまであり、また、長さが1籠当たり12m〜14m程度に及ぶものもある。また、主筋2には、直径が19mm〜51mm程度の棒状筋が使用される。また、主筋2は、1本ずつ配置される場合の他、2本を束ねて配置される場合もある。場所打ち杭の施工現場では、このような鉄筋籠1、1A、…を連結しながら数十m以上(〜70m程度)の深さがある杭孔へ建て込む作業が行われる。   The size of the reinforced baskets 1 and 1A varies from construction site to construction site, with diameters ranging from about 0.6 m to 3 m or more, and lengths ranging from about 12 m to 14 m per basket. Further, as the main bar 2, a bar bar having a diameter of about 19 mm to 51 mm is used. The main bars 2 may be arranged one by one, or may be arranged in a bundle of two. At the construction site of the cast-in-place pile, work is performed in which such reinforcing cages 1, 1A,... Are connected and piled into a pile hole having a depth of several tens of meters or more (about 70 m).

図2は、本発明の実施の形態に係る特殊吊補強リングの一例を示す斜視図である。
特殊吊補強リング4は、図1に示したように、各節の鉄筋籠1、1Aを構成する複数の主筋2と直交させて配設され、複数の主筋2との交差部に第1金具(鉄筋固定用金具)20が取り付けられるとともに、鉄筋籠1、1Aの建て込み時に吊り具6が取り付けられる。なお、吊り具6は、例えば、鉄筋籠1、1Aを吊り上げるためのクレーン装置から吊り下げられたワイヤーロープ、シャックルなどを含んで構成される。
FIG. 2 is a perspective view showing an example of the special suspension reinforcing ring according to the embodiment of the present invention.
As shown in FIG. 1, the special suspension reinforcing ring 4 is disposed orthogonal to the plurality of main reinforcing bars 2 constituting the reinforcing bar cages 1 and 1A of each node, and a first metal fitting is provided at an intersection with the plurality of main reinforcing bars 2. (Reinforcing metal fittings) 20 are attached, and the hanging members 6 are attached when the reinforcing bars 1 and 1A are built. In addition, the suspending tool 6 is configured to include, for example, a wire rope, a shackle, and the like suspended from a crane device for lifting the reinforced baskets 1 and 1A.

特殊吊補強リング4は、鉄筋籠1、1Aの中心軸方向に所定間隔を設けて配置される2つのリング部11と、隣り合うリング部11どうしを連結する4つの連結部12とを含む、2連結リングで構成されている。隣り合うリング部11の間隔は、鉄筋籠1、A1の重量、直径などに応じて適宜設定され、例えば、数十cmから3m程度の範囲で設定され得る。   The special suspension reinforcing ring 4 includes two ring portions 11 arranged at predetermined intervals in the center axis direction of the reinforcing bar cages 1 and 1A, and four connecting portions 12 connecting adjacent ring portions 11 to each other. It is composed of two connecting rings. The interval between the adjacent ring portions 11 is appropriately set according to the weight, diameter, and the like of the rebar cage 1, A1, and may be set, for example, in the range of about several tens of cm to about 3 m.

特殊吊補強リング4は、円環状の2つのリング部11(2連結リング)で構成されているが、別の実施の形態では、特殊吊補強リング4は、3以上のリング部11(3連結リング以上)で構成されてもよい。また、特殊吊補強リング4は、4つの連結部12で構成されているが、別の実施の形態では、特殊吊補強リング4は、2つ、3つ、又は5つ以上の連結部12を含んで構成されてもよい。   The special suspension reinforcing ring 4 is formed of two annular ring portions 11 (two connection rings), but in another embodiment, the special suspension reinforcement ring 4 includes three or more ring portions 11 (three connection rings). Ring or more). In addition, the special hanging reinforcement ring 4 is configured by four connecting portions 12, but in another embodiment, the special hanging reinforcing ring 4 includes two, three, or five or more connecting portions 12. You may comprise including.

特殊吊補強リング4を構成するリング部11の個数と連結部12の個数は、上段の鉄筋籠1を下段の鉄筋籠1Aと連結して、杭孔に建て込む際の吊荷重(鉄筋籠総重量)、又は吊り具6が取り付けられる箇所数(吊箇所数)などを考慮して設定される。   The number of the ring portions 11 and the number of the connecting portions 12 constituting the special hanging reinforcing ring 4 are determined by the hanging load when the upper reinforcing cage 1 is connected to the lower reinforcing cage 1A and built into the pile hole (the reinforcing steel cage total). Weight) or the number of places where the hanging tool 6 is attached (the number of hanging places).

また、特殊吊補強リング4の2つのリング部11は、帯状鋼板(平鋼材)で構成され、主筋2との交差部において、図1に示すように、第1金具20を上下2箇所に取り付け可能な縦幅を備えている。なお、別の実施の形態では、2以上のリング部11のうち少なくとも最上段のリング部11が、鉄筋固定用金具を上下2箇所に取り付け可能な縦幅を備えている構成としてもよい。   The two ring portions 11 of the special suspension reinforcing ring 4 are made of a strip-shaped steel plate (flat steel material). At the intersection with the main reinforcing bar 2, the first metal fittings 20 are attached to two upper and lower portions as shown in FIG. It has a possible vertical width. In another embodiment, at least the uppermost ring portion 11 among the two or more ring portions 11 may have a vertical width in which the reinforcing bar fixing metal can be attached to two upper and lower locations.

また、特殊吊補強リング4では、2つのリング部11が、帯状鋼板(平鋼材)で構成されているが、別の実施の形態では、2つのリング部11が、アングル型(L型)鋼材で構成されてもよいし、帯状鋼板とアングル型鋼材とで構成されてもよい。例えば、最上段のリング部11が、帯状鋼板で構成され、他のリング部11が、アングル型鋼材で構成されてもよい。また、2つのリング部11の仕様(厚さ、縦幅など)は、同じ仕様にしてもよいし、異なる仕様にしてもよい。なお、異なる仕様にする場合は、最上段のリング部11の強度が、他のリング部11の強度より高くなるように設計することが好ましい。   Further, in the special suspension reinforcing ring 4, the two ring portions 11 are formed of a strip-shaped steel plate (flat steel material). In another embodiment, the two ring portions 11 are formed of an angle type (L-type) steel material. Or may be formed of a strip-shaped steel plate and an angle-type steel material. For example, the uppermost ring portion 11 may be formed of a strip-shaped steel plate, and the other ring portions 11 may be formed of an angle-type steel material. The specifications (thickness, vertical width, etc.) of the two ring portions 11 may be the same or different. When different specifications are used, it is preferable that the uppermost ring portion 11 is designed to have a higher strength than the other ring portions 11.

また、特殊吊補強リング4の4つの連結部12は、隣り合うリング部11の内側面に、溶接等により固定されて、該内側面より内側方向へ張り出した形状を有している。
連結部12の形状は、縦長の略コの字形状に限定されるものではなく、リング部11の内側面より内側方向へ張り出した形状であればよく、別の実施の形態では、連結部12の形状が、略くの字形状、又は円弧形状などであってもよい。
また、4つの連結部12は、平鋼材で構成されているが、別の実施の形態では、4つの連結部12が、棒鋼で構成されてもよいし、アングル型(L型)鋼材などで構成されてもよい。
Further, the four connecting portions 12 of the special suspension reinforcing ring 4 are fixed to the inner surface of the adjacent ring portion 11 by welding or the like, and have a shape projecting inward from the inner surface.
The shape of the connecting portion 12 is not limited to a vertically long substantially U-shape, and may be any shape as long as it protrudes inward from the inner side surface of the ring portion 11. In another embodiment, the connecting portion 12 May be a substantially rectangular shape or an arc shape.
Further, the four connecting portions 12 are made of a flat steel material, but in another embodiment, the four connecting portions 12 may be made of a bar steel, or may be made of an angle type (L-type) steel material. It may be configured.

図3は、別の実施の形態に係る特殊吊補強リング4Aを示す斜視図である。なお、図3では、ワイヤーロープ121の記載が一部省略されている。
特殊吊補強リング4Aは、各節の鉄筋籠1、1Aの中心軸方向に所定間隔を設けて配置される2つのリング部11Aと、隣り合うリング部11Aどうしを連結する4つの連結部12Aとを含む、2連結リングで構成されている。隣り合うリング部11Aの間隔は、鉄筋籠1、A1の重量、直径などに応じて適宜設定され、例えば、数十cmから3m程度の範囲で設定され得る。
FIG. 3 is a perspective view showing a special suspension reinforcing ring 4A according to another embodiment. Note that, in FIG. 3, the description of the wire rope 121 is partially omitted.
The special suspension reinforcing ring 4A includes two ring portions 11A arranged at predetermined intervals in the center axis direction of the reinforcing bar cages 1 and 1A of each node, and four connecting portions 12A connecting the adjacent ring portions 11A. And two connecting rings. The interval between the adjacent ring portions 11A is appropriately set according to the weight, diameter, and the like of the rebar basket 1, A1, and may be set, for example, in a range from several tens of cm to about 3 m.

特殊吊補強リング4Aは、円環状の2つのリング部11A(2連結リング)で構成されているが、別の実施の形態では、特殊吊補強リング4Aは、3以上のリング部11A(3連結リング以上)で構成されてもよい。また、特殊吊補強リング4Aは、4つの連結部12Aを含んで構成されているが、別の実施の形態では、特殊吊補強リング4Aは、2つ、3つ、又は5つ以上の連結部12Aを含んで構成されてもよい。   The special suspension reinforcing ring 4A is composed of two annular ring portions 11A (two connection rings). However, in another embodiment, the special suspension reinforcement ring 4A has three or more ring portions 11A (3 connection rings). Ring or more). Further, the special suspension reinforcing ring 4A includes four connecting portions 12A, but in another embodiment, the special hanging reinforcing ring 4A includes two, three, or five or more connecting portions. 12A.

特殊吊補強リング4Aを構成するリング部11Aの個数と連結部12Aの個数は、上段の鉄筋籠1を下段の鉄筋籠1Aと連結して、杭孔に建て込む際の吊荷重(鉄筋籠総重量)、又は吊り具6が取り付けられる箇所数(吊箇所数)などを考慮して設定される。   The number of the ring portions 11A and the number of the connecting portions 12A constituting the special hanging reinforcing ring 4A are determined by the lifting load when the upper reinforcing bar cage 1 is connected to the lower reinforcing bar cage 1A and built into the pile hole (the reinforcing steel cage total). Weight) or the number of places where the hanging tool 6 is attached (the number of hanging places).

また、特殊吊補強リング4Aの2つのリング部11Aは、帯状鋼板(平鋼材)で構成され、主筋2との交差部において、第1金具20を上下2箇所に取り付け可能な縦幅を備えてもよい。なお、別の実施の形態では、2以上のリング部11Aのうち少なくとも最上段のリング部11Aが、鉄筋固定用金具を上下2箇所に取り付け可能な縦幅を備えている構成としてもよい。   The two ring portions 11A of the special suspension reinforcing ring 4A are formed of a strip-shaped steel plate (flat steel material), and have a vertical width at which the first metal fitting 20 can be attached to the upper and lower two places at the intersection with the main reinforcement 2. Is also good. In another embodiment, at least the uppermost ring portion 11A of the two or more ring portions 11A may have a vertical width in which the reinforcing bar fixing metal can be attached to two upper and lower locations.

また、特殊吊補強リング4Aでは、2つのリング部11Aが、帯状鋼板(平鋼材)で構成されているが、別の実施の形態では、2つのリング部11Aが、アングル型(L型)鋼材で構成されてもよいし、帯状鋼板とアングル型鋼材とで構成されてもよい。例えば、最上段のリング部11Aが、帯状鋼板で構成され、他のリング部11Aが、アングル型鋼材で構成されてもよい。また、2つのリング部11Aの仕様(厚さ、縦幅など)は、同じ仕様にしてもよいし、異なる仕様にしてもよい。なお、異なる仕様にする場合は、最上段のリング部11Aの強度が、他のリング部11Aの強度より高くなるように設計することが好ましい。   Further, in the special suspension reinforcing ring 4A, the two ring portions 11A are formed of a strip-shaped steel plate (flat steel material), but in another embodiment, the two ring portions 11A are formed of an angle type (L-type) steel material. Or may be formed of a strip-shaped steel plate and an angle-type steel material. For example, the uppermost ring portion 11A may be made of a strip-shaped steel plate, and the other ring portions 11A may be made of an angle-type steel material. The specifications (thickness, vertical width, and the like) of the two ring portions 11A may be the same or different. In the case of different specifications, it is preferable to design the uppermost ring portion 11A so that the strength is higher than the strength of the other ring portions 11A.

また、特殊吊補強リング4Aの4つの連結部12Aは、ワイヤーロープ121と、ワイヤーロープ121の両端に取り付けられる吊り金具122とを含んで構成されている。吊り金具122は、例えば、シャックルなどで構成される。ワイヤーロープ121は、異なる所定の長さに設計されたものを予め複数種類備えてもよい。また、ワイヤーロープ121の種類(直径など)は、吊荷重(鉄筋籠総重量)などを考慮して適宜選択され得る。   In addition, the four connecting portions 12A of the special suspension reinforcing ring 4A are configured to include a wire rope 121 and suspension fittings 122 attached to both ends of the wire rope 121. The suspension fitting 122 is formed of, for example, a shackle. The wire rope 121 may be provided in advance with a plurality of types designed in different predetermined lengths. In addition, the type (diameter and the like) of the wire rope 121 can be appropriately selected in consideration of a hanging load (total weight of a reinforcing bar cage) and the like.

また、リング部11Aの内側面には、吊り金具122を介してワイヤーロープ121を取り付けるための4つの取付部111が等間隔で設けられている。4つの取付部111は、リング部11Aの内側面に、溶接等により固定されて、該内側面より内側方向へ張り出した形状を有している。取付部111は、例えば、平鋼材で構成され、吊り金具122を取り付けるための取付孔が形成されている。   In addition, four attachment portions 111 for attaching the wire rope 121 via the suspension fitting 122 are provided at equal intervals on the inner side surface of the ring portion 11A. The four mounting portions 111 are fixed to the inner surface of the ring portion 11A by welding or the like, and have a shape projecting inward from the inner surface. The mounting portion 111 is made of, for example, a flat steel material, and has a mounting hole for mounting the hanging bracket 122.

図4は、さらに別の実施の形態に係る特殊吊補強リング4Bを示す斜視図である。
特殊吊補強リング4Bは、各節の鉄筋籠1、1Aの中心軸方向に所定間隔を設けて配置される2つのリング部11Bと、隣り合うリング部11Bどうしを連結する4つの連結部12Bとを含む、2連結リングで構成されている。隣り合うリング部11Bの間隔は、鉄筋籠1、A1の重量、直径などに応じて適宜設定され、例えば、数十cmから3m程度の範囲で設定され得る。
FIG. 4 is a perspective view showing a special suspension reinforcing ring 4B according to still another embodiment.
The special suspension reinforcing ring 4B includes two ring portions 11B arranged at predetermined intervals in the central axis direction of the reinforcing bar cages 1 and 1A of each node, and four connecting portions 12B connecting adjacent ring portions 11B. And two connecting rings. The interval between the adjacent ring portions 11B is appropriately set according to the weight, the diameter, and the like of the rebar cage 1, A1, and may be set, for example, in a range from several tens of cm to about 3 m.

特殊吊補強リング4Bは、円環状の2つのリング部11B(2連結リング)で構成されているが、別の実施の形態では、特殊吊補強リング4Bは、3以上のリング部11B(3連結リング以上)で構成されてもよい。また、特殊吊補強リング4Bは、4つの連結部12Bを含んで構成されているが、別の実施の形態では、特殊吊補強リング4Bは、2つ、3つ、又は5つ以上の連結部12Bを含んで構成されてもよい。   The special suspension reinforcing ring 4B is composed of two annular ring portions 11B (two connection rings), but in another embodiment, the special suspension reinforcement ring 4B has three or more ring portions 11B (3 connection rings). Ring or more). Further, the special suspension reinforcing ring 4B includes four connecting portions 12B, but in another embodiment, the special hanging reinforcing ring 4B includes two, three, or five or more connecting portions. 12B.

特殊吊補強リング4Bを構成するリング部11Bの個数と連結部12Bの個数は、上段の鉄筋籠1を下段の鉄筋籠1Aと連結して、杭孔に建て込む際の吊荷重(鉄筋籠総重量)、又は吊り具6が取り付けられる箇所数(吊箇所数)などを考慮して設定され得る。   The number of ring portions 11B and the number of connecting portions 12B constituting the special suspension reinforcing ring 4B are determined by the suspension load (reinforcement cage total) when the upper reinforcing cage 1 is connected to the lower reinforcing cage 1A and built into the pile hole. Weight) or the number of places where the hanging tool 6 is attached (the number of hanging places).

特殊吊補強リング4Bの2つのリング部11Bは、帯状鋼板(平鋼材)で構成され、主筋2との交差部において、鉄筋固定用金具である第1金具20を上下2箇所に取り付け可能な縦幅を備えてもよい。なお、別の実施の形態では、2以上のリング部11Bのうち少なくとも最上段のリング部11Bが、鉄筋固定用金具を上下2箇所に取り付け可能な縦幅を備えている構成としてもよい。   The two ring portions 11B of the special suspension reinforcing ring 4B are made of a strip-shaped steel plate (flat steel material). At the intersection with the main reinforcing bar 2, the first metal fittings 20, which are metal fittings for fixing the reinforcing steel, can be attached vertically at two locations. A width may be provided. In another embodiment, at least the uppermost ring portion 11B of the two or more ring portions 11B may have a vertical width capable of mounting the reinforcing bar fixing metal at two upper and lower locations.

また、特殊吊補強リング4Bでは、2つのリング部11Bが、帯状鋼板(平鋼材)で構成されているが、別の実施の形態では、2つのリング部11Bが、アングル型(L型)鋼材で構成されてもよいし、帯状鋼板とアングル型鋼材とで構成されてもよい。例えば、最上段のリング部11Bが、帯状鋼板で構成され、他のリング部11Bが、アングル型鋼材で構成されてもよい。また、2つのリング部11Bの仕様(厚さ、縦幅など)は、同じ仕様にしてもよいし、異なる仕様にしてもよい。なお、異なる仕様にする場合は、最上段のリング部11Bの強度が、他のリング部11Bの強度より高くなるように設計することが好ましい。   Further, in the special suspension reinforcing ring 4B, the two ring portions 11B are formed of a strip-shaped steel plate (flat steel material), but in another embodiment, the two ring portions 11B are formed of an angle (L-type) steel material. Or may be formed of a strip-shaped steel plate and an angle-type steel material. For example, the uppermost ring portion 11B may be made of a strip-shaped steel plate, and the other ring portions 11B may be made of an angle-type steel material. The specifications (thickness, vertical width, etc.) of the two ring portions 11B may be the same or different. When different specifications are used, it is preferable to design the uppermost ring portion 11B so that the strength is higher than the strength of the other ring portions 11B.

また、特殊吊補強リング4Bの4つの連結部12Bは、連結棒123と、連結棒123の両端部に取り付けられる棒固定金具124とを含んで構成されている。連結棒123は、ネジ棒鋼でもよいし、異形棒鋼でもよいし、両端部にネジ加工がされた異形棒鋼でもよい。連結棒123は、異なる所定の長さに設計されたものを予め複数種類備えてもよいし、カプラーなどを用いて連結可能な構成としてもよい。棒固定金具124には、例えば、ナット、カプラーなどの締結・連結具が使用される。   Further, the four connecting portions 12B of the special suspension reinforcing ring 4B are configured to include a connecting rod 123 and rod fixing fittings 124 attached to both ends of the connecting rod 123. The connecting rod 123 may be a threaded steel bar, a deformed steel bar, or a deformed steel bar having both ends threaded. A plurality of types of connecting rods 123 designed to have different predetermined lengths may be provided in advance, or may be configured to be connectable using a coupler or the like. For the rod fixing fitting 124, for example, a fastening / connecting tool such as a nut or a coupler is used.

リング部11Bの内側面には、棒固定金具124を用いて連結棒123を取り付けるための4つの取付部112が等間隔で設けられている。4つの取付部112は、リング部11Aの内側面に、溶接等により固定されて、該内側面より内側方向へ張り出した形状を有している。取付部111は、例えば、肉厚の平鋼材、角鋼管などで構成され、連結棒123を取り付ける(挿通させる)ための取付孔が形成されている。   On the inner surface of the ring portion 11B, four attachment portions 112 for attaching the connecting rod 123 using the rod fixing fitting 124 are provided at equal intervals. The four mounting portions 112 are fixed to the inner surface of the ring portion 11A by welding or the like, and have a shape projecting inward from the inner surface. The attachment portion 111 is made of, for example, a thick flat steel material, a square steel pipe, or the like, and has an attachment hole for attaching (inserting) the connecting rod 123.

図5は、実施の形態に係る鉄筋籠の主筋と特殊吊補強リングとの交差部に取り付けられる第1金具20の一例を示す図であり、(a)は正面図、(b)は底面図である。   FIG. 5 is a diagram showing an example of the first metal fitting 20 attached to the intersection of the main reinforcing bar of the reinforcing bar cage and the special suspension reinforcing ring according to the embodiment, (a) is a front view, and (b) is a bottom view. It is.

第1金具20は、板状体がコ字状に折り返されてコ字状の折曲部21及び左右側片22を有する金具本体を備え、左右側片22のそれぞれの一側縁より補強リング挿入用の挿入溝23が形成され、折曲部21に固定用ボルト挿通用の挿通孔24が形成されている。折曲部21には、挿通孔24に連通するナット25が固着され、ナット25に固定用ボルト26が取り付けられている。   The first metal fitting 20 is provided with a metal fitting body having a U-shaped bent portion 21 and a left and right piece 22 formed by folding a plate-shaped body into a U shape, and a reinforcing ring from one side edge of each of the left and right pieces 22. An insertion groove 23 for insertion is formed, and an insertion hole 24 for inserting a fixing bolt is formed in the bent portion 21. A nut 25 communicating with the insertion hole 24 is fixed to the bent portion 21, and a fixing bolt 26 is attached to the nut 25.

なお、ナット25は、折曲部21の外側に固着してもよいし、折曲部21の内側に固着してもよい。また、ナット25を設けずに、折曲部21に、固定用ボルト用のネジ孔が形成されてもよい。板状体はコ字状の他、略U字状に折り返されてもよい。また、第1金具20は、主筋2を縦に2本束ねた縦束ね筋に適用できるように板状体の左右側片22を深めに構成してもよい。また、主筋2を横に2本束ねた横束ね筋に適用できるように板状体の折曲部21が幅広に構成されてもよい。また、図1に示すように、通常補強リング5に取り付けられる第1金具20の一部は、建て込み時(連結後)に鉄筋籠10から取り外して回収し、再利用することも可能である。また、金具本体の左右側片22には、掘削孔の壁面との間隔を確保するための鉄筋籠用スペーサ(図示せず)の軸部を挿通させるための軸受け(図示せず)が設けられてもよい。   The nut 25 may be fixed to the outside of the bent part 21 or may be fixed to the inside of the bent part 21. Further, a screw hole for a fixing bolt may be formed in the bent portion 21 without providing the nut 25. The plate-shaped body may be folded back into a substantially U-shape in addition to the U-shape. In addition, the first metal fitting 20 may be configured such that the left and right side pieces 22 of the plate-like body are deeper so that the first metal fitting 20 can be applied to a vertical bundle of two main bars 2 vertically. Further, the bent portion 21 of the plate-like body may be configured to be wide so as to be applicable to a horizontal bundle of two main bars 2 bundled horizontally. In addition, as shown in FIG. 1, a part of the first metal fitting 20 usually attached to the reinforcing ring 5 can be removed from the reinforced cage 10 at the time of building (after connection), collected, and reused. . Further, bearings (not shown) are provided on the left and right side pieces 22 of the metal fitting body for inserting the shaft portions of the reinforcing bar cage spacers (not shown) for securing an interval with the wall surface of the excavation hole. You may.

図6は、実施の形態に係る鉄筋籠の主筋と特殊吊補強リングとの交差部に取り付けられる別の鉄筋固定用金具(第2金具30)を示す図であり、(a)は正面図、(b)は底面図である。   FIG. 6 is a view showing another reinforcing-bar fixing metal fitting (second metal fitting 30) attached to the intersection of the main reinforcing bar of the reinforcing-bar cage and the special suspension reinforcing ring according to the embodiment, (a) is a front view, (B) is a bottom view.

第2金具30は、金具本体31と、押圧部材36とを含んで構成されている。
金具本体31は、2本の主筋2を跨ぐように板状体が略U字状に折り曲げられて、左右側板部32と主筋把持部33とが形成され、左右側板部32の先端側にそれぞれ係止片34が形成されたものである。金具本体31の左右側板部32の係止片34は、左右側板部32の一側縁を略凹形状に切り欠いた切欠き部35により形成されている。
The second fitting 30 includes a fitting main body 31 and a pressing member 36.
The bracket body 31 is formed by bending a plate-like body into a substantially U-shape so as to straddle the two main bars 2 to form left and right side plate portions 32 and main line gripping portions 33. The locking piece 34 is formed. The locking pieces 34 of the left and right side plate portions 32 of the metal fitting body 31 are formed by cutout portions 35 in which one side edges of the left and right side plate portions 32 are cut out in a substantially concave shape.

押圧部材36は、金具本体31の左右側板部32の係止片34間に跨設されるように肉厚短冊状の板体が略コの字形状に折り曲げられて、左右折片部37と連結板部38とが形成されている。連結板部38にボルト螺合用ネジ孔38aが形成され、ボルト螺合用ネジ孔38aに特殊吊補強リング4(4A、4B)のリング部11(11A、11B)、又は通常補強リング5を主筋2側に押圧するための押えボルト39が螺装される構成となっている。   The pressing member 36 is formed by bending a thick strip-shaped plate into a substantially U-shape so as to be straddled between the locking pieces 34 of the left and right side plate portions 32 of the metal fitting main body 31, A connecting plate portion 38 is formed. A screw hole 38a for bolt screwing is formed in the connecting plate portion 38, and the ring portion 11 (11A, 11B) of the special suspension reinforcing ring 4 (4A, 4B) or the normal reinforcing ring 5 is attached to the main reinforcement 2 in the screw hole 38a for bolt screwing. A pressing bolt 39 for pressing the pressing side is screwed.

なお、金具本体31の左右側板部32には、掘削孔の壁面との間隔を確保するための鉄筋籠用スペーサ(図示せず)の軸部を挿通させるための軸受け(図示せず)が設けられていてもよい。
また、図6に示した第2金具30は、縦束ね筋に対応したもの(2本の主筋を跨ぐように板状体が略U字状に折り曲げられている構成)となっているが、金具本体31が、一本の主筋2を跨ぐように左右側板部32を浅めに構成してもよい。
The left and right side plate portions 32 of the metal fitting body 31 are provided with bearings (not shown) for inserting the shaft portions of the reinforcing cage basket spacers (not shown) for securing the interval with the wall surface of the excavation hole. It may be.
Further, the second metal fitting 30 shown in FIG. 6 has a configuration corresponding to the vertical brace (a configuration in which a plate-like body is bent in a substantially U shape so as to straddle two main reinforcing bars). The left and right side plate portions 32 may be configured to be shallower so that the metal fitting body 31 straddles one main bar 2.

鉄筋固定用金具には、上記した第1金具20、又は第2金具30を使用することが好ましいが、必要な許容支持力を確保できる金具であれば、これら第1金具20、及び第2金具30に限定されない。例えば、特殊吊補強リング4(4A、4B)のリング部11(11A、11B)、又は通常補強リング5と、主筋2との交差部をUボルトで固定するタイプの金具、交差部の主筋2に引っ掛けてボルトで固定するタイプの金具、又は交差部の主筋2をボルトで直接締め付けるタイプの金具など、各種の無溶接金具を使用することができる。また、これら各種の無溶接金具を組み合わせて使用してもよい。なお、前記Uボルトを用いる場合には、リング部11(11A、11B)、又は通常補強リング5周上の主筋2を配設する位置には、Uボルトの端部を通して、ナットで固定するための挿通孔が形成される。   It is preferable to use the above-described first metal fittings 20 or second metal fittings 30 as the metal fittings for reinforcing bars, but if the metal fittings can secure a necessary allowable supporting force, these first metal fittings 20 and second metal fittings 20 are used. It is not limited to 30. For example, a metal fitting of a type in which an intersection between the ring portion 11 (11A, 11B) of the special suspension reinforcing ring 4 (4A, 4B) or the normal reinforcing ring 5 and the main reinforcement 2 is fixed with a U bolt, the main reinforcement 2 at the intersection Various types of non-weld metal fittings can be used, such as a metal fitting that is hooked on and fixed with a bolt, or a metal fitting that directly tightens the main bar 2 at the intersection with a bolt. Further, these various types of non-weld metal fittings may be used in combination. When the U-bolt is used, the nut is fixed to the ring portion 11 (11A, 11B) or the position where the main reinforcement 2 on the circumference of the normal reinforcing ring 5 is provided, through the end of the U-bolt. Is formed.

次に、本発明の実施の形態に係る鉄筋籠の設計方法について説明する。
なお、実施の形態に係る鉄筋籠の設計方法では、特に、鉄筋籠の建て込み作業の施工安全性を確保するために、鉄筋籠を吊り上げるための吊り具6が取り付けられる吊補強リングの仕様(鋼材種類、厚さ、幅など)と種類(特殊吊補強リング4又は通常補強リング5)、吊り具6が取り付けられる吊箇所数、及び吊補強リングに取り付けられる鉄筋固定用金具(第1金具20又は第2金具30)の取付個数を決定する。
Next, a method of designing a reinforcing rod cage according to an embodiment of the present invention will be described.
In addition, in the method of designing a reinforced cage according to the embodiment, in particular, in order to ensure the construction safety of the erection of the reinforced cage, the specifications of the hanging reinforcing ring to which the hanging tool 6 for lifting the reinforced cage is attached ( Steel material type, thickness, width, etc.) and type (special suspension reinforcing ring 4 or normal reinforcement ring 5), the number of suspension points to which suspension members 6 are attached, and reinforcing metal fixing brackets (first bracket 20) to be attached to suspension reinforcement rings Alternatively, the number of the second metal fittings 30) is determined.

実施の形態に係る鉄筋籠の設計方法は、第1工程、第2工程、第3工程、及び第4工程を含んでいる。なお、第1工程よりも前の工程において、場所打ち杭用の鉄筋籠10を構成する各節の鉄筋籠1、1Aの数(籠数)、直径、主筋2の仕様(本数、長さ、径など)、フープ筋3(帯筋)の仕様(本数、設置間隔、径など)などが設計されている。   The method for designing a reinforcing cage according to the embodiment includes a first step, a second step, a third step, and a fourth step. In addition, in the process before a 1st process, the number (the number of baskets), the diameter of the reinforcing bar basket 1, 1A of each node which comprises the reinforcing bar cage 10 for cast-in-place piles, the specification of the main bar 2 (number, length, The diameter (e.g., diameter) of the hoop 3 (band) is designed (number, installation interval, diameter, etc.).

第1工程は、鉄筋籠の建て込み時に吊り具6が取り付けられる吊補強リング(特殊吊補強リング4又は通常補強リング5)周上の主筋2間における剪断応力度と曲げ応力度とが所定条件(例えば、鋼材の短期許容応力度)を満たすように、吊補強リング(特殊吊補強リング4又は通常補強リング5)の仕様と吊り具6を取り付ける吊箇所数とを決定する。   In the first step, the shear stress and the bending stress between the main reinforcing bars 2 on the periphery of the suspension reinforcing ring (the special suspension reinforcing ring 4 or the normal reinforcing ring 5) to which the suspending tool 6 is attached when the reinforcing cage is built are determined under predetermined conditions. The specifications of the suspension reinforcing ring (special suspension reinforcing ring 4 or normal reinforcement ring 5) and the number of suspension points to which the suspender 6 is attached are determined so as to satisfy (for example, the short-term allowable stress of the steel material).

第2工程は、鉄筋籠の建て込み時の吊荷重を吊補強リング(特殊吊補強リング4又は通常補強リング5)周上の主筋2による分割数で除算して、吊補強リング周上における主筋2との交差部にかかる荷重(分散荷重)を算出する。   The second step is to divide the suspension load at the time of building the reinforcing cage by the number of divisions by the main reinforcement 2 on the periphery of the suspension reinforcement ring (special suspension reinforcement ring 4 or the normal reinforcement ring 5) to obtain the main reinforcement on the periphery of the suspension reinforcement ring. The load (dispersion load) applied to the intersection with 2 is calculated.

第3工程は、第2工程で算出した分散荷重と、前記交差部に取り付けられる鉄筋固定用金具(第1金具20又は第2金具30)の許容支持力、又は該許容支持力に所定の安全率を考慮して決定された許容安全支持力とを比較する。   In the third step, the dispersion load calculated in the second step and the allowable support force of the reinforcing bar fixing metal (the first metal fitting 20 or the second metal fitting 30) attached to the intersection or a predetermined safety value is determined. Compare with the allowable safety bearing capacity determined in consideration of the rate.

第4工程は、前記分散荷重が前記許容支持力又は前記許容安全支持力より大きい場合、鉄筋籠の建て込み時に、前記交差部に取り付けられる鉄筋固定用金具1個当たりの負担荷重が前記許容安全支持力以下となるように、吊補強リング(特殊吊補強リング4又は通常補強リング5)への鉄筋固定用金具の取付個数を決定する。   The fourth step is that, when the distributed load is larger than the allowable supporting force or the allowable safety supporting force, when the reinforcing bar cage is erected, the burden load per one reinforcing-bar fixing bracket attached to the intersection is the allowable safety force. The number of metal reinforcing bars to be attached to the suspension reinforcement ring (special suspension reinforcement ring 4 or normal reinforcement ring 5) is determined so as to be equal to or less than the supporting force.

次に実施の形態に係る鉄筋籠の設計方法の一例を図7、図8に基づいて説明する。
図7、図8は、最上節(杭頭側)の第1節から最下節(杭底側)の第9節までの鉄筋籠が連結されて構築される場所打ち杭用の鉄筋籠(連結鉄筋籠)の設計及び評価内容を示している。なお、鉄筋籠の連結、及び杭孔への建て込み作業は、最下節の鉄筋籠から順番に行われる。
Next, an example of a method of designing a reinforcing rod cage according to the embodiment will be described with reference to FIGS.
FIG. 7 and FIG. 8 show reinforcing bars for cast-in-place piles constructed by connecting reinforcing bars from the first section of the uppermost section (pile head side) to the ninth section of the lowermost section (pile bottom side). 3 shows the design and evaluation contents of a connected steel cage. In addition, the connection of the reinforcing rod cages and the work of building the piles into the pile holes are performed in order from the lowermost reinforcing rod cage.

図7は、実施の形態に係る鉄筋籠の設計方法を説明するための表であり、吊補強リングの仕様及び吊箇所数の設計評価内容の一例を示す表である。
図7に示す設計評価表において、「鉄筋籠」の欄は、連結される鉄筋籠の節数を示している。本例では、杭頭側最上節の第1節から最下節の第9節までの鉄筋籠が連結されて場所打ち杭用の鉄筋籠が構築される設計となっている。
FIG. 7 is a table for explaining a method of designing a reinforcing bar cage according to the embodiment, and is a table showing an example of the design evaluation contents of the specifications of the suspension reinforcing rings and the number of suspension points.
In the design evaluation table shown in FIG. 7, the column of “rebar basket” indicates the number of nodes of the rebar basket to be connected. In this example, the design is such that the rebar baskets from the first section at the top of the pile head to the ninth section at the bottom are connected to form a rebar basket for cast-in-place piles.

「吊位置」の欄は、鉄筋籠の建て込み作業時において、鉄筋籠を吊り上げるための吊り具6が取り付けられるリング(吊補強リング)に付された番号(No)を示している。リングNoは、第1節鉄筋籠の最上段リングから順番に付されている。本例では、各節の鉄筋籠に3つの補強リングが設けられている設計となっており(例えば、第1節鉄筋籠はNo.1〜3の補強リングが設けられている)、各節の鉄筋籠の最上段リングが吊補強リングとして吊位置に設定されている。   The column of “hanging position” indicates a number (No) assigned to a ring (suspension reinforcing ring) to which the hanging tool 6 for lifting the reinforcing bar cage is attached at the time of installing the reinforcing bar cage. Ring Nos. Are assigned in order from the uppermost ring of the first rebar basket. In this example, the design is such that three reinforcing rings are provided on the reinforcing bar cage of each section (for example, the first reinforcing bar basket has reinforcing rings Nos. 1 to 3). The uppermost ring of the reinforcing bar is set at a suspension position as a suspension reinforcement ring.

「吊荷重A」の欄は、各節の鉄筋籠を連結して、杭孔に建て込むときの鉄筋籠総重量を示している。例えば、第1節鉄筋籠の吊荷重「76.50t」は、第1節から第9節までの鉄筋籠が連結されたときの総重量を示している。   The column of "hanging load A" indicates the total weight of the reinforcing bar cage when the reinforcing bar cages of the respective nodes are connected and built into the pile holes. For example, the suspended load “76.50t” of the first rebar basket indicates the total weight when the rebar baskets of the first to ninth sections are connected.

「吊補強リング」の欄は、決定された吊補強リングの仕様(鋼材種類、厚さ、幅を含む)を示している。例えば、第1節鉄筋籠の吊補強リング「FB−25*150」は、「平鋼材−厚さ25mm*縦幅150mm」を示している。また、第8節鉄筋籠の吊補強リング「L−13*100*100」は、「L型鋼材−厚さ13mm*幅100mm*100mm」を示している。   The column of “suspension reinforcing ring” indicates the determined specifications of the suspension reinforcement ring (including the steel material type, thickness, and width). For example, the suspension reinforcing ring “FB-25 * 150” of the first rebar cage indicates “flat steel material—thickness 25 mm * length 150 mm”. Further, the suspension reinforcing ring “L-13 * 100 * 100” of the eighth bar reinforced cage indicates “L-shaped steel material—thickness 13 mm * width 100 mm * 100 mm”.

「主筋径」の欄は、各節の鉄筋籠に使用される主筋の呼び径を示している。「D41」は、鉄筋の呼び名である。
「リング外径」の欄は、吊補強リングの外径(mm)を示している。
「分割数B」の欄は、吊補強リング周上の主筋による分割数を示している。本例では、吊補強リング周上を48分割するように主筋2が均等配置される設計となっている。
The column of "Main Bar Diameter" indicates the nominal diameter of the main bar used for the reinforcing bar cage of each node. “D41” is the name of the reinforcing bar.
The column “Ring outer diameter” indicates the outer diameter (mm) of the suspension reinforcing ring.
The column “Division number B” indicates the number of divisions by the main reinforcement on the periphery of the suspension reinforcing ring. In this example, the main reinforcement 2 is designed to be evenly arranged so as to divide the periphery of the suspension reinforcing ring into 48 parts.

「吊箇所数」の欄は、各節の鉄筋籠(連結された鉄筋籠)を杭孔に建て込む際に、吊り具6が吊補強リングに取り付けられる箇所数を示している。例えば、「4点吊」は、吊り具6が吊補強リングの4箇所に取り付けられる設計、「2点吊」は、吊り具6が吊補強リングの2箇所に取り付けられる設計となっている。   The column of "number of hanging points" indicates the number of places where the hanging tool 6 is attached to the hanging reinforcing ring when the reinforcing rod cage (connected reinforcing rod cage) of each node is built in the pile hole. For example, “four-point hanging” is a design in which the hanging tool 6 is attached to four places of the hanging reinforcing ring, and “two-point hanging” is a design in which the hanging tool 6 is attached to two places of the hanging reinforcing ring.

「剪断応力度(τ)」の欄は、各節の鉄筋籠(連結された鉄筋籠)を杭孔に建て込む際にかかる吊補強リングの剪断応力度(吊補強リング周上の主筋2間における剪断応力度)を示している。
「曲げ応力度(σ)」の欄は、各節の鉄筋籠(連結された鉄筋籠)を杭孔に建て込む際にかかる吊補強リングの曲げ応力度(吊補強リング周上の主筋2間における曲げ応力度)を示している。
The column of “shear stress (τ)” indicates the shear stress of the suspension reinforcing ring (when the reinforcing bars are connected to each other on the circumference of the suspension reinforcing ring) when the reinforcing bars of each node (connected reinforcing bars) are built into the pile holes. (Shear stress degree).
The column of “Bending stress (σ)” indicates the bending stress of the suspension reinforcing ring (when the reinforcing bars are connected to each other on the circumference of the suspension reinforcing ring) when the reinforcing bar cage (connected reinforcing bar cage) of each node is built into the pile hole. At the same time).

吊補強リングの剪断応力度、及び曲げ応力度の算出式の一例を以下に説明する。
吊補強リング周上の主筋2の間隔をL(mm)、L=D2×π/n、
吊り具6の吊箇所数をm、
鉄筋籠の建て込み時の吊重量(鉄筋籠総重量)をW(kN)、
吊補強リングの曲げモーメントをM(N・mm)、M=(W1×L)/4(両端固定)、
吊り具1箇所にかかる荷重W1=W/m(kN)
吊補強リングの直径をD2、
主筋の本数をn(本)、
吊補強リングの断面積をA(mm
吊補強リング(鋼材)の断面係数をZ(mm)とした場合、
剪断応力度(τ)は、式τ=W1/A(Nmm)により求められる。
また、曲げ応力度(σ)は、式σ=M/Z(N)により求められる。
An example of a calculation formula of the shear stress and the bending stress of the suspension reinforcing ring will be described below.
The interval between the main reinforcements 2 on the periphery of the suspension reinforcing ring is L (mm), L = D2 × π / n,
The number of hanging points of the hanging tool 6 is m,
W (kN) is the suspended weight (reinforcement basket total weight) when the reinforcing cage is built.
The bending moment of the suspension reinforcing ring is M (N · mm), M = (W1 × L) / 4 (fixed at both ends),
Load W1 applied to one hanging tool W1 = W / m (kN)
The diameter of the suspension reinforcing ring is D2,
The number of main bars is n (lines),
A (mm 2 )
When the section modulus of the suspension reinforcing ring (steel material) is Z (mm 3 ),
The degree of shear stress (τ) is determined by the equation τ = W1 / A (Nmm 2 ).
Further, the bending stress degree (σ) is obtained by the equation σ = M / Z (N).

「判定」の欄は、吊補強リングの剪断応力度(τ)及び曲げ応力度(σ)が所定条件を満たしているか否かの判定結果を示している。
本例では、剪断応力度(τ)が、鋼材(例えば、SS400)の短期許容剪断応力度(120Nmm2)未満であり、かつ曲げ応力度(σ)が、鋼材(例えば、SS400)の短期曲げ応力度(210N)未満であるか否かの判定結果を示している。この判定結果が「OK」となるように(前記所定条件を満たすように)、「吊補強リング」の仕様と、「吊箇所数」とが決定されるようになっている。
The column of “judgment” indicates the result of judging whether the shear stress (τ) and the bending stress (σ) of the suspension reinforcing ring satisfy predetermined conditions.
In this example, the shear stress (τ) is less than the short-term allowable shear stress (120 Nmm2) of the steel (eg, SS400), and the bending stress (σ) is short-term bending stress of the steel (eg, SS400). A result of determination as to whether or not the degree is less than (210N) is shown. The specification of the “suspension reinforcing ring” and the “number of suspension points” are determined so that this determination result is “OK” (to satisfy the predetermined condition).

「分散荷重」の欄は、各節の鉄筋籠の吊荷重Aを分割数Bで除算した値、すなわち、吊補強リング周上における主筋2との交差部にかかる荷重を示している。   The column of “dispersed load” indicates a value obtained by dividing the suspended load A of the reinforcing bar cage at each node by the number of divisions B, that is, the load applied to the intersection with the main reinforcement 2 on the periphery of the suspended reinforcing ring.

図8は、実施の形態に係る鉄筋籠の設計方法を説明するための表であり、鉄筋固定用金具数及び負担荷重の設計評価内容の一例を示す表である。
図8に示す設計評価表において、「鉄筋籠」の欄は、連結される鉄筋籠の節数を示している。「吊位置」の欄は、鉄筋籠の建て込み作業時において、鉄筋籠を吊り上げるための吊り具6が取り付けられるリング(吊補強リング)に付された番号(No)を示している。
FIG. 8 is a table for explaining a method of designing a reinforcing bar cage according to the embodiment, and is a table showing an example of the design evaluation contents of the number of reinforcing-bar fixing brackets and the burden load.
In the design evaluation table shown in FIG. 8, the column of “rebar basket” indicates the number of nodes of the rebar basket to be connected. The column of “hanging position” indicates a number (No) assigned to a ring (suspension reinforcing ring) to which the hanging tool 6 for lifting the reinforcing bar cage is attached at the time of installing the reinforcing bar cage.

「補強リング 固定方法」の欄は、吊補強リングの形態、該吊補強リングへの鉄筋固定用金具の固定方法を示している。
本例では、第1節から第3節の鉄筋籠の吊補強リングに2連結リング(特殊吊補強リング4)が用いられる設計となっている。
また、第4節から第6節の鉄筋籠の吊補強リングに通常補強リング5(1連リング)が用いられ、主筋2との交差部に鉄筋固定用金具(第1金具20又は第2金具30)が上下2箇所固定(上下固定)される設計となっている。
第7節から第9節の鉄筋籠の吊補強リングに通常補強リング5が用いられ、主筋2との交差部に鉄筋固定用金具(第1金具20又は第2金具30)が1箇所固定(通常固定)される設計となっている。
The column of “reinforcing ring fixing method” indicates the form of the suspension reinforcing ring and the method of fixing the metal reinforcing bar to the suspension reinforcing ring.
In this example, two connecting rings (special suspension reinforcing rings 4) are used as the suspension reinforcement rings of the reinforcing bars of the first to third sections.
In addition, a normal reinforcing ring 5 (single ring) is used as a suspension reinforcing ring of the reinforcing bar cage in the fourth to sixth sections, and a reinforcing bar fixing metal (the first metal fitting 20 or the second metal fitting) is provided at an intersection with the main reinforcing bar 2. 30) is designed to be fixed at two upper and lower locations (fixed vertically).
The reinforcing ring 5 is usually used as the suspension reinforcing ring of the reinforcing bar cage in the sections 7 to 9, and a reinforcing bar fixing metal (the first metal fitting 20 or the second metal fitting 30) is fixed at one place at the intersection with the main reinforcing bar 2 ( Usually fixed).

「鉄筋固定用金具数」の欄は、「吊補強リング」に取り付けられる鉄筋固定用金具の個数を示している。例えば、第1節鉄筋籠の2連結リングには、178個の金具(第1金具20又は第2金具30)が取り付けられる設計となっている。すなわち、2連結リング(例えば、特殊吊補強リング4)の上段のリング部11(リングNo.1)に96個(上下固定)、下段のリング部11(リングNo.2)に82個(上下固定)の金具(第1金具20又は第2金具30)が取り付けられる設計となっている。
また、第4節から第6節の鉄筋籠の吊補強リング(通常補強リング5)には、96個(上下固定)の金具が取り付けられる設計となっている。
また、第7節から第9節の鉄筋籠の吊補強リング(通常補強リング5)には、48個(通常固定)の金具が取り付けられる設計となっている。
The column of “number of reinforcing bar fixing brackets” indicates the number of reinforcing bar fixing brackets attached to the “suspension reinforcing ring”. For example, 178 metal fittings (the first metal fitting 20 or the second metal fitting 30) are designed to be attached to the two connection rings of the first rebar cage. That is, 96 (upper and lower fixed) are provided in the upper ring portion 11 (ring No. 1) of the two connecting rings (for example, the special suspension reinforcing ring 4), and 82 (upper and lower) are provided in the lower ring portion 11 (ring No. 2). (Fixed) metal fitting (first metal fitting 20 or second metal fitting 30).
In addition, 96 (upper and lower fixed) metal fittings are designed to be attached to the suspension reinforcing ring (normally the reinforcing ring 5) of the reinforcing bar cage in the fourth to sixth sections.
In addition, 48 (normally fixed) metal fittings are designed to be attached to the suspension reinforcing rings (normal reinforcing rings 5) of the reinforcing bars in the sections 7 to 9.

「100%評価個数」の欄、及び「50%評価個数」の欄は、「負担荷重」を求める際に使用される評価条件を示している。
100%評価個数とは、「負担荷重」を求める際に使用する鉄筋固定用金具の許容支持力に、第1の評価係数1.0(100%)を乗じる金具の個数を示している。
50%評価個数とは、「負担荷重」を求める際に使用する鉄筋固定用金具の許容支持力に、第2の評価係数0.5(50%)を乗じる金具の個数を示している。
The column of “100% evaluation number” and the column of “50% evaluation number” indicate evaluation conditions used when obtaining “burden load”.
The 100% evaluation number indicates the number of metal fittings obtained by multiplying the permissible support force of the metal fixing metal used for obtaining the “burden load” by the first evaluation coefficient 1.0 (100%).
The 50% evaluation number indicates the number of metal fittings obtained by multiplying the permissible support force of the reinforcing metal fixing metal used for obtaining the “burden load” by the second evaluation coefficient 0.5 (50%).

例えば、第1節鉄筋籠のリングNo.1の吊補強リング(特殊吊補強リング4)では、178個の鉄筋固定用金具のうち48個(すなわち、通常固定に相当する個数)は、100%の許容支持力が得られるものとして評価するようになっている。
一方、178個の鉄筋固定用金具のうち残りの130個は、金具固定力のバラつきなどの影響を考慮して、50%の許容支持力しか得られないものとして評価するようになっている。
For example, the ring no. With one suspension reinforcement ring (special suspension reinforcement ring 4), 48 (i.e., the number equivalent to the normal fixation) of the 178 reinforcing bar fixing brackets are evaluated as having a 100% allowable supporting force. It has become.
On the other hand, the remaining 130 of the 178 reinforcing bar fixing brackets are evaluated as having only an allowable bearing force of 50% in consideration of the influence of the variation in the fixing force of the brackets.

「負担荷重」の欄は、各節の鉄筋籠の吊補強リング(特殊吊補強リング4、又は通常補強リング5)に取り付けられる鉄筋固定用金具1個当たりの負担荷重であり、以下の式に基づいて算出される。
負担荷重(t/個)=吊荷重A÷(100%評価個数×第1の評価係数+50%評価個数×第2の評価係数)
例えば、第1節鉄筋籠のリングNo.1の吊補強リングに取り付けられる金具の負担荷重は、76.50t(吊荷重)÷(48個×1.0+130個×0.5)≒0.677t/個(約0.7t/個)となる。
The column of “Load” is the load per reinforcing metal fixing bracket attached to the suspension reinforcement ring (special suspension reinforcement ring 4 or normal reinforcement ring 5) of the reinforcement cage of each node. It is calculated based on:
Load (t / piece) = Hanging load A 荷重 (100% evaluation number × first evaluation coefficient + 50% evaluation number × second evaluation coefficient)
For example, the ring no. The load applied to the metal fittings attached to the suspension reinforcing ring 1 is 76.50 t (suspension load) ÷ (48 pieces × 1.0 + 130 pieces × 0.5) ≒ 0.677 t / piece (about 0.7 t / piece). Become.

なお、本例では、第1の評価係数が1.0(100%評価)、第2の評価係数が0.5(50%評価)に設定されているが、第1の評価係数、及び第2の評価係数は、これら値に限定されない。別の実施の形態では、第1の評価係数は、0.8以上1.0未満の値に設定してもよく、また第2の評価係数は、0.2以上0.7以下の値に設定してもよい。なお、第2の評価係数は、施工経験上、0.25以上0.5以下の値に設定することがより好ましい。また、これら評価係数の値は、吊重量、分割数、鉄筋固定用金具数、鉄筋固定用金具の種類など、鉄筋籠の仕様に応じて設定してもよい。   In this example, the first evaluation coefficient is set to 1.0 (100% evaluation), and the second evaluation coefficient is set to 0.5 (50% evaluation). The evaluation coefficient of 2 is not limited to these values. In another embodiment, the first evaluation coefficient may be set to a value of 0.8 or more and less than 1.0, and the second evaluation coefficient may be set to a value of 0.2 or more and 0.7 or less. May be set. Note that the second evaluation coefficient is more preferably set to a value of 0.25 or more and 0.5 or less from construction experience. Further, the values of these evaluation coefficients may be set according to the specifications of the reinforcing bar cage, such as the suspended weight, the number of divisions, the number of reinforcing bar fixing brackets, and the type of reinforcing bar fixing brackets.

「判定」欄は、「負担荷重」が、鉄筋固定用金具の許容安全支持力以下であるか否かを判定した結果を示している。
本実施の形態で用いられる鉄筋固定用金具(第1金具20、及び第2金具30)の許容支持力は、10kN(1t)である。この場合、許容安全支持力は、許容支持力に所定の安全率(例えば、1.5)を考慮して決定された値、すなわち、7kN(0.7t)となっている。この場合、「負担荷重」が、0.7(t/個)以下(許容安全支持力以下)となればOKと判定される。
図8に示す設計評価表では、第1節から第9節の鉄筋籠の吊補強リングに取り付けられる鉄筋固定用金具の負担荷重は、いずれも0.7t/個以下となっており、OKと判定されている。
The “judgment” column shows the result of judging whether or not the “burden load” is equal to or less than the allowable safety support force of the reinforcing bar fixing metal.
The permissible supporting force of the metal fittings (first metal fitting 20 and second metal fitting 30) used in the present embodiment is 10 kN (1t). In this case, the allowable safety support force is a value determined in consideration of a predetermined safety factor (for example, 1.5) for the allowable support force, that is, 7 kN (0.7 t). In this case, if the “burden load” is 0.7 (t / piece) or less (less than the allowable safety bearing force), it is determined to be OK.
In the design evaluation table shown in FIG. 8, the load imposed on the reinforcing bar fixing brackets attached to the hanging reinforcement rings of the reinforcing bars in the first to ninth sections is 0.7 t / piece or less. Has been determined.

図9は、上記した実施の形態に係る鉄筋籠の設計方法の手順を示すフローチャートである。
まず、ステップS1では、鉄筋籠の建て込み時に吊り具6が取り付けられる吊補強リング周上の主筋2間における剪断応力度(τ)と曲げ応力度(σ)とが所定条件(τ<120Nmm、且つσ<210N)を満たすように、第1節から第9節のそれぞれの鉄筋籠に使用する吊補強リングの仕様(鋼材種類、厚さ、幅を含む)と吊り具6が取り付けられる吊箇所数とを決定する(第1工程)。
FIG. 9 is a flowchart illustrating a procedure of a method of designing a reinforcing bar cage according to the above-described embodiment.
First, in step S1, the shear stresses between the main reinforcement 2 on hanging reinforcement ring circumference hanger 6 when like an anchor rebar cage is attached (tau) and bending stresses (sigma) and a predetermined condition (τ <120Nmm 2 And σ <210N), the specifications (including the type, thickness, and width of the steel material) of the suspension reinforcing ring used for each of the reinforcing bars in the first to ninth sections and the suspension to which the suspender 6 is attached. The number of locations is determined (first step).

次にステップS2では、第1節から第9節のそれぞれの鉄筋籠の建て込み時の吊荷重Aを吊補強リング周上の主筋2による分割数Bで除算して、前記吊補強リング周上における主筋2との交差部にかかる分散荷重(A/B)を算出する(第2工程)。   Next, in step S2, the hanging load A of each of the first to ninth sections at the time of building the reinforcing cage is divided by the number of divisions B by the main reinforcing bars 2 on the periphery of the suspension reinforcing ring, and the suspension load A Calculate the dispersion load (A / B) applied to the intersection with the main bar 2 in (2nd step).

次にステップS3では、ステップS2で算出した分散荷重(A/B)と、前記交差部に取り付けられる鉄筋固定用金具(第1金具20、又は第2金具30)の許容支持力(10kN≒1t)に所定の安全率を考慮して決定された許容安全支持力(7kN≒0.7t)とを比較する(第3工程)。例えば、第1節から第9節のそれぞれの前記分散荷重(A/B)が、前記許容安全支持力より大きいか否かを比較判定する。なお、第3工程において、第1節から第9節のそれぞれの前記分散荷重(A/B)と、前記許容支持力(10kN≒1t)とを比較してもよい。   Next, in step S3, the dispersion load (A / B) calculated in step S2 and the allowable supporting force (10 kN ≒ 1t) of the reinforcing bar fixing metal (the first metal 20 or the second metal 30) attached to the intersection. ) Is compared with an allowable safety bearing capacity (7 kN ≒ 0.7 t) determined in consideration of a predetermined safety factor (third step). For example, it is determined whether or not the distributed load (A / B) in each of the first to ninth sections is larger than the allowable safety bearing force. In the third step, the scattered load (A / B) of each of the first to ninth sections may be compared with the allowable supporting force (10 kN ≒ 1t).

ステップS3において、前記分散荷重(A/B)が、前記許容安全支持力より大きくない(換言すれば、前記許容安全支持力以下である)と判断すれば(図7に示す第7節から第9節の鉄筋籠の場合に該当する)、ステップS4に進む。   In step S3, if it is determined that the distributed load (A / B) is not larger than the allowable safety supporting force (in other words, it is equal to or less than the allowable safety supporting force) (from the seventh to the seventh sections shown in FIG. 7). This corresponds to the case of the reinforcing bar of section 9), and the process proceeds to step S4.

ステップS4では、前記交差部に取り付けられる鉄筋固定用金具1個当たりの負担荷重が前記許容安全支持力以下となるので、前記交差部1箇所につき、1個の金具を取り付けるように、鉄筋固定用金具の取付個数を決定し(すなわち、通常補強リング5に金具を通常固定する方法に決定し)、その後、処理を終える。例えば、図8に示す第7節から第9節の鉄筋籠の場合、吊補強リング(通常補強リング5)に取り付ける金具数が、48個に決定される。   In step S4, the load imposed on each reinforcing bar fixing metal attached to the intersection is equal to or less than the allowable safety supporting force. The number of metal fittings is determined (that is, the method of fixing the metal fittings to the normal reinforcing ring 5 is determined), and then the processing is finished. For example, in the case of the reinforcing bars of the seventh to ninth sections shown in FIG. 8, the number of metal fittings to be attached to the suspension reinforcing ring (normally the reinforcing ring 5) is determined to be 48 pieces.

一方ステップS3において、前記分散荷重(A/B)が、前記許容安全支持力より大きいと判断すれば(図7に示す第1節から第6節の鉄筋籠の場合に該当する)、ステップS5に進む。   On the other hand, if it is determined in step S3 that the scattered load (A / B) is larger than the allowable safety bearing capacity (corresponding to the case of the reinforcing bars of the first to sixth sections shown in FIG. 7), step S5 is performed. Proceed to.

ステップS5では、各節(第1節から第6節)の鉄筋籠の建て込み時に、前記交差部に取り付けられる鉄筋固定用金具1個当たりの負担荷重が前記許容安全支持力(7kN≒0.7t)以下となるように、吊補強リングへの鉄筋固定用金具の取付個数を決定し(第4工程)、その後ステップS6に進む。   In step S5, when the reinforcing bars of the respective sections (sections 1 to 6) are erected, the burden load per reinforcing metal fixing bracket attached to the intersection is the allowable safety supporting force (7 kN ≒ 0. 7t) The number of metal fittings for fixing reinforcing bars to the suspension reinforcing ring is determined so as to be less than or equal to 4t (fourth step), and thereafter, the process proceeds to step S6.

なお、前記負担荷重は、上記した次式により求めることが可能である。
負担荷重(t/個)=吊荷重A÷(100%評価個数(48)×第1の評価係数(1.0)+50%評価個数×第2の評価係数(0.5))
本例では、100%評価個数は48個に設定されるので、負担荷重が0.7t/個以下となるように50%評価個数を求めて、これらの合計を前記取付個数とする。
Note that the burden load can be obtained by the following equation.
Load (t / piece) = Hanging load A 荷重 (100% evaluation number (48) × first evaluation coefficient (1.0) + 50% evaluation number × second evaluation coefficient (0.5))
In this example, since the 100% evaluation number is set to 48 pieces, the 50% evaluation number is determined so that the burden load is 0.7 t / piece or less, and the total of them is defined as the number of attachments.

ステップS6では、ステップS5で求めた鉄筋固定用金具の取付個数が、分割数Bの2倍(本例では、分割数48×2=96)より大きな値であるか否かを判断し、鉄筋固定用金具の取付個数が、分割数Bの2倍より大きな値であると判断すれば(図8に示す第1節から第3節の鉄筋籠の場合に該当する)、ステップS7に進む。   In step S6, it is determined whether or not the number of the reinforcing bar fixing brackets obtained in step S5 is greater than twice the number of divisions B (in this example, the number of divisions 48 × 2 = 96). If it is determined that the number of fixing brackets attached is greater than twice the number of divisions B (corresponding to the case of the first to third sections shown in FIG. 8), the process proceeds to step S7.

なお、ステップS6の手順に代えて、例えば、分散荷重(A/B)が、前記許容支持力又は前記許容安全支持力より大きい所定値以上であるか否かを判断し、分散荷重(A/B)が、前記所定値以上であると判断すれば、ステップS7に進むようにしてもよい。   Instead of the procedure of step S6, for example, it is determined whether or not the distributed load (A / B) is equal to or larger than a predetermined value larger than the allowable supporting force or the allowable safety supporting force. If it is determined that B) is equal to or greater than the predetermined value, the process may proceed to step S7.

ステップS7では、使用する吊補強リングを特殊吊補強リング4に決定し、特殊吊補強リング4のリング部11に鉄筋固定用金具を上下固定する方法に決定し、その後処理を終える。なお、前記取付個数が、前記分割数の2倍より大きく、4倍以下の場合は、特殊吊補強リング4に2連結リングを用いる。また、前記取付個数が、分割数Bの4倍より大きく、6倍以下の場合は、特殊吊補強リング4に3連結リングを用いるようにしてもよい。   In step S7, the suspension reinforcement ring to be used is determined to be the special suspension reinforcement ring 4, and the method of vertically fixing the reinforcing bar fixing bracket to the ring portion 11 of the special suspension reinforcement ring 4 is determined, and the process is thereafter terminated. In the case where the number of attachments is larger than twice the number of divisions and equal to or smaller than four times, two connection rings are used for the special suspension reinforcing ring 4. When the number of attachments is more than four times the number of divisions B and six times or less, three connection rings may be used for the special suspension reinforcing ring 4.

一方、ステップS6において、前記鉄筋固定用金具の取付個数が、前記分割数の2倍より大きな値ではないと判断すれば(図8に示す第4節から第6節の鉄筋籠の場合に該当する)、ステップS8に進む。
ステップS8では、通常補強リング5に鉄筋固定用金具を上下固定する方法に決定し、その後処理を終える。
On the other hand, if it is determined in step S6 that the number of the reinforcing bar fixing brackets is not greater than twice the number of divisions (this corresponds to the case of the reinforcing bars of the fourth to sixth sections shown in FIG. 8). Yes), and proceed to step S8.
In step S8, a method for fixing the reinforcing metal fixing bracket up and down to the normal reinforcing ring 5 is determined, and the process is thereafter terminated.

なお、上記設計方法は、剪断応力度、曲げ応力度、金具の負担荷重などを求めるための計算(算出)式、鉄筋(鋼材)の断面性能(種類、重量、断面係数、断面積など)などの各種設計条件などがメモリに記憶されたコンピュータ装置を用い、該コンピュータ装置に、本設計方法のプログラムを実行させることにより実現する構成としてもよい。   In addition, the above-mentioned design method includes a calculation (calculation) formula for obtaining a shear stress degree, a bending stress degree, a burden load of a metal fitting, a cross-sectional performance (type, weight, cross-sectional modulus, cross-sectional area, etc.) of a reinforcing bar (steel material), and the like. It is also possible to use a computer in which various design conditions and the like are stored in a memory, and execute the program of the present design method on the computer to realize the design method.

上記実施の形態に係る特殊吊補強リング4によれば、2以上のリング部11と、隣り合うリング部11どうしを連結する2以上の連結部12とを備えているので、鉄筋籠の建て込み時の吊荷重を2以上のリング部11に均等分散させることができ、リング部11の撓みや変形を防止できるとともに、第1金具20又は第2金具30の負担荷重を減らすことができる。これにより、鉄筋籠の建て込み作業の安全性を高めることができ、施工安全性の向上を図ることができる。   According to the special suspension reinforcing ring 4 according to the above-described embodiment, since there are provided two or more ring portions 11 and two or more connecting portions 12 for connecting the adjacent ring portions 11, the reinforcing cage is installed. The hanging load at the time can be evenly distributed to the two or more ring portions 11, so that the bending and deformation of the ring portion 11 can be prevented, and the load imposed on the first metal fitting 20 or the second metal fitting 30 can be reduced. Thereby, the safety of the erection work of the reinforcing bar can be enhanced, and the construction safety can be improved.

また、上記特殊吊補強リング4によれば、連結部12が、隣り合うリング部11の内側面に固定されて、該内側面より内側方向へ張り出した略コの字形状を有しているので、リング部11周上に配置される複数の主筋2と、連結部12との間に前記張り出した形状分のスペースを確保することができる。したがって、杭孔への建て込み後にコンクリートが十分に回り込むように、コンクリートの打設を適切に行うことができる。   In addition, according to the special hanging reinforcement ring 4, the connecting portion 12 is fixed to the inner surface of the adjacent ring portion 11 and has a substantially U-shape protruding inward from the inner surface. In addition, a space corresponding to the protruding shape can be secured between the plurality of main reinforcing bars 2 arranged on the circumference of the ring portion 11 and the connecting portion 12. Therefore, it is possible to appropriately cast the concrete so that the concrete sufficiently wraps around the pile hole.

また、特殊吊補強リング4によれば、2以上のリング部11のうち少なくとも最上段のリング部が、前記交差部において、第1金具20を上下2箇所に取り付け可能な縦幅を備えているので、前記交差部において第1金具20が負担する荷重を分散させて、鉄筋固定用金具1個当たりにかかる荷重を減らす効果を高めることができ、主筋2の固定位置のずれ防止効果を高め、施工安全性を一層向上させることができる。   In addition, according to the special suspension reinforcing ring 4, at least the uppermost ring portion of the two or more ring portions 11 has a vertical width at which the first metal fitting 20 can be attached to two upper and lower locations at the intersection. Therefore, it is possible to increase the effect of reducing the load applied to each reinforcing bar fixing metal by dispersing the load borne by the first metal fittings 20 at the intersection, and to enhance the effect of preventing the main bar 2 from being displaced in the fixing position, Construction safety can be further improved.

また、図3に示す特殊吊補強リング4Aによれば、連結部12Aが、ワイヤーロープ121を含んで構成され、リング部11Aの内側面に、ワイヤーロープ121を取り付けるための2以上の取付部111が設けられているので、特殊吊補強リング4と同様の効果が得られるとともに、嵩張らない形態にすることができ、運搬時の省スペース化とともに運搬効率の向上を図ることができる。   According to the special suspension reinforcing ring 4A shown in FIG. 3, the connecting portion 12A includes the wire rope 121, and two or more mounting portions 111 for mounting the wire rope 121 on the inner surface of the ring portion 11A. Is provided, the same effect as that of the special suspension reinforcing ring 4 can be obtained, and it can be made not bulky, so that it is possible to save space during transportation and improve transportation efficiency.

また、図4に示す特殊吊補強リング4Bによれば、連結部12Bが、連結棒123、棒固定金具124を含んで構成され、リング部11Bの内側面に、連結棒123を取り付けるための2以上の取付部112が設けられているので、上記特殊吊補強リング4と同様の効果が得られるとともに、上記特殊吊補強リング4Aと同様に、嵩張らない形態にすることができ、運搬時の省スペース化とともに運搬効率の向上を図ることができる。   Further, according to the special suspension reinforcing ring 4B shown in FIG. 4, the connecting portion 12B includes the connecting rod 123 and the rod fixing member 124, and is used for attaching the connecting rod 123 to the inner surface of the ring portion 11B. Since the above-described mounting portion 112 is provided, the same effect as that of the special suspension reinforcing ring 4 can be obtained, and also, as in the case of the special suspension reinforcing ring 4A, a bulky form can be achieved. It is possible to improve the transportation efficiency as well as the space.

また、上記実施の形態に係る鉄筋籠10によれば、少なくとも最上節の鉄筋籠1に特殊吊補強リング4を備え、特殊吊補強リング4の周上に複数の主筋2が第1金具20により取り付けられているので、上記した特殊吊補強リング4の有する効果により、鉄筋籠の建て込み作業をより安全に実施することが可能となり、施工安全性の向上を図ることができる。   Further, according to the reinforcing bar cage 10 according to the above-described embodiment, at least the uppermost bar reinforcing bar cage 1 is provided with the special suspension reinforcing ring 4, and the plurality of main reinforcing bars 2 are formed on the periphery of the special suspension reinforcing ring 4 by the first metal fitting 20. Because of the attachment, the effect of the special suspension reinforcing ring 4 described above makes it possible to carry out the work of building the reinforcing cage more safely, and to improve the construction safety.

また、上記実施の形態に係る鉄筋籠の設計方法によれば、第1金具20、第2金具30などを用いた無溶接工法で、太径、極太径の主筋2を用いて、大重量の鉄筋籠10を設計する際に、鉄筋籠の建て込み時に吊補強リング(特殊吊補強リング4や通常補強リング5)の撓み若しくは変形、又は主筋2の位置ずれ(許容値以上の位置ずれ)が起きないようにするための前記吊補強リングの仕様や種類、吊箇所数、鉄筋固定用金具数を、熟練作業者の経験や勘に頼ることなく、簡単に決定することができる。したがって、施工安全性の高い、より信頼性の高い無溶接工法を様々な施工現場に広めることができる。   Further, according to the method of designing a reinforcing rod cage according to the above-described embodiment, a large-diameter, extra-large-diameter main reinforcing bar 2 is used by a non-welding method using the first metal fitting 20, the second metal fitting 30, and the like. When designing the reinforcing bar cage 10, the bending or deformation of the suspension reinforcing ring (special suspension reinforcing ring 4 or the normal reinforcing ring 5) or the displacement of the main reinforcing bar 2 (the displacement more than the allowable value) when the reinforcing cage is built. The specifications and types of the suspension reinforcing ring, the number of suspension points, and the number of metal fittings for fixing the reinforcing bars for preventing the occurrence can be easily determined without depending on the experience and intuition of the skilled worker. Therefore, a more reliable welding-free construction method with high construction safety can be spread to various construction sites.

また、上記実施の形態に係る鉄筋籠の設計方法によれば、鉄筋固定用金具1個当たりの負担荷重を求めるにあたり、適切な値に設定された前記第1の評価係数と、前記第2の評価係数とを用いることにより、第1金具20や第2金具30で主筋2を固定したときの支持力のバラつきが考慮された値として前記負担荷重を求めることができる。そして、前記負担荷重が前記許容安全支持力以下となるように前記取付個数を決定することにより、前記支持力にバラつきが生じた場合でも、主筋2のずれを許容範囲に確実に抑えることができる、すなわち、施工安全性が確保された鉄筋籠の設計を行うことができる。   Further, according to the method for designing a reinforcing bar cage according to the above-described embodiment, the first evaluation coefficient set to an appropriate value and the second By using the evaluation coefficient, the burden load can be obtained as a value in which the variation in the supporting force when the main bar 2 is fixed with the first metal fitting 20 or the second metal fitting 30 is considered. Then, by determining the number of attachments so that the burden load is equal to or less than the allowable safety support force, even if the support force varies, the displacement of the main bar 2 can be reliably suppressed to an allowable range. That is, it is possible to design a reinforced cage in which construction safety is ensured.

1、1A 鉄筋籠
2 主筋
3 フープ筋
4、4A、4B 特殊吊補強リング
5 通常補強リング
6 吊り具
10 鉄筋籠(連結鉄筋籠)
11、11A、11B リング部
111、112 取付部
12、12A、12B 連結部
121 ワイヤーロープ
122 吊り金具
123 連結棒
124 棒固定金具
20 第1金具(鉄筋固定用金具)
21 折曲部
22 左右側片
23 挿入溝
24 挿通孔
25 ナット
26 固定用ボルト
30 第2金具(鉄筋固定用金具)
31 金具本体
32 左右側板部
33 主筋把持部
34 係止片
35 切欠き部
36 押圧部材
37 左右折片部
38 連結板部
39 押えボルト
1, 1A Reinforcing bar 2 Main bar 3 Hoop bar 4, 4A, 4B Special suspension reinforcing ring 5 Normal reinforcing ring 6 Hanging tool 10 Reinforcing cage (connecting rebar cage)
11, 11A, 11B Ring parts 111, 112 Attaching parts 12, 12A, 12B Connecting part 121 Wire rope 122 Suspension fitting 123 Connecting rod 124 Bar fixing fitting 20 First fitting (reinforcing metal fitting)
21 Folding part 22 Left and right piece 23 Insertion groove 24 Insertion hole 25 Nut 26 Fixing bolt 30 Second fitting (Reinforcing metal fitting)
31 Hardware main body 32 Left and right plate 33 Main bar gripping part 34 Locking piece 35 Notch 36 Pressing member 37 Left and right bent part 38 Connecting plate 39 Holding bolt

Claims (9)

場所打ち杭用の鉄筋籠を構成する複数の主筋と直交させて配設され、前記複数の主筋との交差部に鉄筋固定用金具が取り付けられるとともに、前記鉄筋籠の建て込み時に吊り具が取り付けられる特殊吊補強リングであって、
当該特殊吊補強リングが、
前記鉄筋籠の中心軸方向に所定間隔を設けて配置される2以上のリング部と、
前記所定間隔を設けて配置される隣り合う前記リング部の内側面どうしを連結する2以上の連結部とを備えていることを特徴とする特殊吊補強リング。
A plurality of main reinforcing bars constituting the cast-in-place pile are arranged perpendicularly to the main reinforcing bars.Reinforcing bars are attached at intersections with the plurality of main reinforcing bars, and hanging members are attached when the reinforcing bars are built. Special hanging reinforcement ring,
The special hanging reinforcement ring,
Two or more ring portions arranged at predetermined intervals in the center axis direction of the reinforcing bar,
A special suspension reinforcing ring comprising: two or more connecting portions for connecting inner surfaces of adjacent ring portions arranged at the predetermined interval .
前記連結部が、
隣り合う前記リング部の内側面に固定されて、該内側面より内側方向へ張り出した形状を有し
前記主筋と前記連結部との間に、前記張り出した形状分のスペースが確保されていることを特徴とする請求項1記載の特殊吊補強リング。
The connecting portion,
It has a shape that is fixed to the inner surface of the adjacent ring portion and protrudes inward from the inner surface ,
The special suspension reinforcing ring according to claim 1 , wherein a space corresponding to the protruding shape is secured between the main reinforcement and the connecting portion .
前記連結部が、ワイヤーロープを含んで構成され、
前記リング部の内側面に、前記ワイヤーロープを取り付けるための2以上の取付部が設けられていることを特徴とする請求項1記載の特殊吊補強リング。
The connecting portion is configured to include a wire rope,
2. The special suspension reinforcing ring according to claim 1, wherein two or more attachment portions for attaching the wire rope are provided on an inner surface of the ring portion. 3.
前記連結部が、連結棒を含んで構成され、
前記リング部の内側面に、前記連結棒を取り付けるための2以上の取付部が設けられていることを特徴とする請求項1記載の特殊吊補強リング。
The connecting portion is configured to include a connecting rod,
The special suspension reinforcing ring according to claim 1, wherein two or more attachment portions for attaching the connecting rod are provided on an inner surface of the ring portion.
2以上の前記リング部のうち少なくとも最上段リング部が、前記交差部において、前記鉄筋固定用金具を上下2箇所に取り付け可能な縦幅を備えていることを特徴とする請求項1〜4のいずれかの項に記載の特殊吊補強リング。   The at least uppermost ring portion of the two or more ring portions has a vertical width at the intersection where the reinforcing bar fixing bracket can be attached to two upper and lower locations. The special suspension reinforcing ring according to any of the above items. 請求項1〜5のいずれかの項に記載の特殊吊補強リングを備え、
該特殊吊補強リングの周上に複数の主筋が鉄筋固定用金具により取り付けられていることを特徴とする場所打ち杭用の鉄筋籠。
A special suspension reinforcing ring according to any one of claims 1 to 5,
A reinforcing rod cage for cast-in-place piles, wherein a plurality of main reinforcing bars are mounted on the periphery of the special suspension reinforcing ring by reinforcing metal fixing brackets.
鉄筋固定用金具を用いた無溶接工法により組み立てられる場所打ち杭用の鉄筋籠の設計方法であって、
前記鉄筋籠の建て込み時に吊り具が取り付けられる吊補強リング周上の主筋間における剪断応力度と曲げ応力度とが所定条件を満たすように、前記吊補強リングの仕様と前記吊り具を取り付ける吊箇所数とを決定する第1工程と、
前記鉄筋籠の建て込み時の吊荷重を前記吊補強リング周上の前記主筋による分割数で除算して、前記吊補強リング周上における前記主筋との交差部にかかる荷重(以下、分散荷重という)を算出する第2工程と、
前記分散荷重と、前記交差部に取り付けられる前記鉄筋固定用金具の許容支持力、又は該許容支持力に所定の安全率を考慮して決定された許容安全支持力とを比較する第3工程と、
前記分散荷重が前記許容支持力又は前記許容安全支持力より大きい場合、前記鉄筋籠の建て込み時に、前記交差部に取り付けられる前記鉄筋固定用金具1個当たりの負担荷重が前記許容安全支持力以下となるように、前記吊補強リングへの前記鉄筋固定用金具の取付個数を決定する第4工程とを含み、
前記分散荷重が、前記許容支持力又は前記許容安全支持力より大きい所定値以上となる場合、又は前記鉄筋固定用金具の取付個数が、前記分割数の2倍より大きな値となる場合に、前記吊補強リングに、請求項1〜5のいずれかの項に記載の特殊吊補強リングを用いるようにすることを特徴とする鉄筋籠の設計方法。
A method of designing a steel cage for a cast-in-place pile assembled by a welding-free method using metal fittings for reinforcing steel,
The specifications of the suspension reinforcing ring and the suspension for mounting the suspension are so set that the degree of shear stress and the degree of bending stress between the main reinforcements on the periphery of the suspension reinforcement ring to which the suspension is attached when the reinforcing cage is installed satisfy predetermined conditions. A first step of determining the number of locations;
The load applied to the intersection with the main reinforcement on the circumference of the suspension reinforcement ring is divided by the suspension load at the time of building the reinforcing cage and divided by the number of divisions of the main reinforcement on the periphery of the suspension reinforcement ring (hereinafter referred to as a dispersed load). ), And
A third step of comparing the distributed load with an allowable supporting force of the reinforcing metal fixing bracket attached to the intersection, or an allowable safety supporting force determined in consideration of a predetermined safety factor for the allowable supporting force; and ,
When the distributed load is larger than the permissible supporting force or the permissible safety supporting force, when the reinforcing bar is erected, the load per one reinforcing bar fixing bracket attached to the intersection is equal to or less than the permissible safety supporting force. A fourth step of determining the number of the metal reinforcing bars to be attached to the suspension reinforcing ring,
When the distributed load is equal to or more than a predetermined value larger than the allowable supporting force or the allowable safety supporting force, or when the number of the reinforcing bar fixing brackets is a value larger than twice the number of divisions, A method for designing a reinforcing bar cage, wherein the special reinforcing ring according to any one of claims 1 to 5 is used as the hanging reinforcing ring.
前記第4工程では、
前記交差部の数に相当する個数の前記鉄筋固定用金具の許容支持力には、第1の評価係数を乗じた値を用い、
前記交差部の数を超えた残りの個数の前記鉄筋固定用金具の許容支持力には、前記第1の評価係数よりも低い第2の評価係数を乗じた値を用いて、
前記鉄筋固定用金具1個当たりの負担荷重を求めることを特徴とする請求項7記載の鉄筋籠の設計方法。
In the fourth step,
A value obtained by multiplying the first evaluation coefficient is used for the allowable bearing force of the reinforcing bar fixing pieces in a number corresponding to the number of the intersections,
The allowable supporting force of the remaining number of the reinforcing bar fixing members exceeding the number of the intersections, using a value multiplied by a second evaluation coefficient lower than the first evaluation coefficient,
The method for designing a reinforcing bar cage according to claim 7, wherein a burden load per said reinforcing bar fixing bracket is obtained.
前記第1の評価係数が、0.8以上1.0以下であり、
前記第2の評価係数が、0.2以上0.7以下であることを特徴とする請求項8記載の鉄筋籠の設計方法。
The first evaluation coefficient is 0.8 or more and 1.0 or less,
9. The method according to claim 8, wherein the second evaluation coefficient is not less than 0.2 and not more than 0.7.
JP2019205945A 2019-11-14 2019-11-14 Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage Active JP6678806B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019205945A JP6678806B1 (en) 2019-11-14 2019-11-14 Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019205945A JP6678806B1 (en) 2019-11-14 2019-11-14 Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage

Publications (2)

Publication Number Publication Date
JP6678806B1 true JP6678806B1 (en) 2020-04-08
JP2021080630A JP2021080630A (en) 2021-05-27

Family

ID=70057955

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019205945A Active JP6678806B1 (en) 2019-11-14 2019-11-14 Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage

Country Status (1)

Country Link
JP (1) JP6678806B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703887A (en) * 2022-04-29 2022-07-05 中国十九冶集团有限公司 Construction method of high-pile bearing platform tower crane foundation
CN117380876A (en) * 2023-11-17 2024-01-12 南京工业大学 Reinforced concrete frame consolidates welded fastening device

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001020454A (en) * 1999-07-12 2001-01-23 Housing & Urban Development Corp Reinforcing bar cage without welding for structure such as foundation pillar and manufacture thereof
JP4858888B1 (en) * 2011-08-12 2012-01-18 株式会社恵信工業 On-site non-welded assembly method for reinforcing bar and its reinforcing frame with auxiliary bars.
JP5584744B2 (en) * 2012-10-05 2014-09-03 株式会社 Cup商会 Lifting device, rebar top edge positioning jig, rebar lifting method, and rebar erection method
GB201418298D0 (en) * 2014-10-15 2014-11-26 Reinforcement Consultants Ltd Device for splicing reinforcement cages
JP2017150265A (en) * 2016-02-26 2017-08-31 三井住友建設株式会社 Reinforcement cage and assembly method of this reinforcement cage

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114703887A (en) * 2022-04-29 2022-07-05 中国十九冶集团有限公司 Construction method of high-pile bearing platform tower crane foundation
CN117380876A (en) * 2023-11-17 2024-01-12 南京工业大学 Reinforced concrete frame consolidates welded fastening device
CN117380876B (en) * 2023-11-17 2024-05-10 南京工业大学 Reinforced concrete frame consolidates welded fastening device

Also Published As

Publication number Publication date
JP2021080630A (en) 2021-05-27

Similar Documents

Publication Publication Date Title
JP5584744B2 (en) Lifting device, rebar top edge positioning jig, rebar lifting method, and rebar erection method
JP5074469B2 (en) Compression buckling strength reinforcement mechanism and fastening method thereof
JP6678806B1 (en) Special hanging reinforcement ring, reinforced cage, and design method of reinforced cage
JP4858888B1 (en) On-site non-welded assembly method for reinforcing bar and its reinforcing frame with auxiliary bars.
JP2016118027A (en) Anti-lifting assembly of rebar cage, rebar cage and construction method of cast-in-place pile
WO2014193323A1 (en) Shear and bending reinforcements of coupling beams of coupled shear walls
JP2004176482A (en) Construction method for non-buried column leg and structure of non-buried column leg
JP6796335B2 (en) Reinforcing support member for reinforcing bar cage, reinforcing bar cage using this, and structure of reinforcing bar cage
JP2012202032A (en) Earthquake-resistant structure of suspended ceiling
JP7128108B2 (en) Design method of interlocking reinforcing bar cage
JP6362141B2 (en) Reinforcing bar reinforced frame, hoop, and reinforcing bar
JP5925098B2 (en) Seismic ceiling structure
JP5036065B2 (en) Pile head joint structure
JP2004003236A (en) Structure of joint between steel-concrete composite structure and reinforced concrete structure
JP2019108701A (en) Fence for safety measures of reinforced soil wall construction
JP6461690B2 (en) Foundation structure and foundation construction method
JP2012188923A (en) Earth retaining wall reinforcing structure and method
KR20210054239A (en) Anchor bolt fixture
JP2020094478A (en) Earthquake proof repair method of existing structure
JP5130129B2 (en) A computer program that supports the calculation of allowable stress levels for wooden framed houses.
TW495576B (en) Structure and method for mounting viscous quake damping wall
JP7344702B2 (en) Main reinforcing bar member for reinforcing bar cage, hoop bar, reinforcing bar cage including these, and assembly method of reinforcing bar cage
KR102438445B1 (en) Reinforcing material with enlarged head and the reinforcing method using the same
KR102553850B1 (en) Non-supporting formwork system
CN215367854U (en) Connecting joint of steel beam and concrete filled steel tube bundle shear wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20191114

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20191114

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20191127

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191217

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200130

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20200130

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200310

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200317

R150 Certificate of patent or registration of utility model

Ref document number: 6678806

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250