Prior art keywords
work
time
unmanaged
actual
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018536658A
Other languages
Japanese (ja)
Other versions
JPWO2018042646A1 (en
Inventor
大知 尾白
正裕 本林
淳一 平山
高志 渡邊
崇治 櫻田
泰毅 嶋津
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Transport System Ltd
Original Assignee
Hitachi Transport System Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Transport System Ltd filed Critical Hitachi Transport System Ltd
Publication of JPWO2018042646A1 publication Critical patent/JPWO2018042646A1/en
Application granted granted Critical
Publication of JP6594555B2 publication Critical patent/JP6594555B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Human Resources & Organizations (AREA)
  • Operations Research (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Data Mining & Analysis (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

本発明は、作業を分析する分析システムに関する。   The present invention relates to an analysis system for analyzing work.

工場や倉庫等、複数人の作業者が連携して様々な作業を行っている作業環境では、作業者が手待ちになり無駄な時間が発生している場合がある。そのため、作業内容や作業者の状態を管理し、誰が、いつ、何の作業を行っているかの把握が重要である。   In a work environment such as a factory or a warehouse where a plurality of workers cooperate to perform various tasks, there is a case where a worker is waiting and wasteful time occurs. For this reason, it is important to manage the work content and the worker's state, and to understand who is doing what and when.

本技術分野の背景技術として、以下の先行技術がある。特許文献1(米国特許第8972276号明細書)には、作業負荷を評価する手法の過程で、誰が、いつ、何の作業を行っているかの情報を取得している。   There are the following prior arts as background art of this technical field. In Patent Document 1 (US Pat. No. 8,972,276), information on who is doing what and when is obtained in the course of a method for evaluating workload.

米国特許第8972276号明細書US Pat. No. 8,972,276

作業には直接的に成果を生じる作業(直接作業)と、直接的には成果を生じないが必要な作業(間接作業)の2種類に大別できる。多くの場合、直接作業の実績データは収集され、管理されているが、間接作業のデータを収集し管理するケースは少ない。また、間接作業は種類が多く、かつ計画外に発生する場合があるため、予め全ての間接作業を想定し、間接作業の実績データの収集は困難である。   There are two types of work: work that produces results directly (direct work) and work that does not produce results directly but is necessary (indirect work). In many cases, performance data of direct work is collected and managed, but there are few cases of collecting and managing data of indirect work. Moreover, since there are many types of indirect work and may occur outside the plan, it is difficult to collect indirect work performance data assuming all indirect work in advance.

作業実績データを分析することによって、実績が残されている直接作業は把握できる。一方、実績が残されていない間接作業については作業者の状態が不明な時間帯がある。また、センサやカメラを導入しても、データの解釈に人手を要するため、作業者の実態の自動的な把握は困難である。   By analyzing the work performance data, it is possible to grasp the direct work where the results are left. On the other hand, there is a time zone in which the state of the worker is unknown for the indirect work in which no record is left. Even if a sensor or a camera is introduced, it is difficult to automatically grasp the actual situation of the worker because it requires manpower to interpret the data.

しかし、前述した特許文献1に記載された技術では、評価対象の作業は全ての実績データが揃っている必要がある。   However, in the technique described in Patent Document 1 described above, it is necessary that all performance data is prepared for the work to be evaluated.

そこで、本発明では、作業実績データ等を用いて、作業実績が記録されていない時間帯の作業内容を推定する。   Therefore, in the present invention, work contents in a time zone in which work results are not recorded are estimated using work result data and the like.

本願において開示される発明の代表的な一例を示せば以下の通りである。すなわち、分析システムであって、プログラムを実行するプロセッサと、前記プロセッサがアクセスする記憶装置とを備え、分析対象の作業実績を含む第一の作業実績データを取得する取得部と、作業実績が記録されていない実績未管理時間を、前記第一の作業実績データから抽出し、前記抽出された実績未管理時間の属性情報を取得する算出部と、前記取得した属性情報を用いて、前記実績未管理時間を分類するための実績未管理時間分類属性を生成する分類部と、分析対象でない作業実績を含む第二の作業実績データを取得し、前記生成された実績未管理時間分類属性に従って前記第二の作業実績データを分類し、実績未管理時間分類属性ごとに作業を推定するための確率モデルを生成するモデル生成部と、を有し、前記分類部は、前記生成された確率モデルを用いて前記第一の作業実績データを分析し、前記第一の作業実績データに含まれる実績未管理時間における作業を推定する。   A typical example of the invention disclosed in the present application is as follows. That is, the analysis system includes a processor that executes a program and a storage device that is accessed by the processor, an acquisition unit that acquires first work performance data including the work performance to be analyzed, and the work performance is recorded. The result unmanaged time that has not been extracted is extracted from the first work result data, the attribute information of the extracted result unmanaged time is obtained, and the obtained attribute information is used to obtain the result unmanaged A classifying unit that generates an actual unmanaged time classification attribute for classifying the management time, and second work performance data including a work actual that is not an analysis target are acquired, and the second data is acquired according to the generated actual unmanaged time classification attribute. A model generation unit that classifies the second work performance data and generates a probability model for estimating work for each performance unmanaged time classification attribute, the classification unit, Using made probability model to analyze the first work record data, to estimate the work in actual unmanaged time included in the first work record data.

本発明の一態様によれば、作業実績データとして記録されていない作業を推定できる。前述した以外の課題、構成及び効果は、以下の実施例の説明により明らかにされる。   According to one aspect of the present invention, work that is not recorded as work performance data can be estimated. Problems, configurations, and effects other than those described above will become apparent from the description of the following embodiments.

第一の実施例のシステムの構成を示す図である。It is a figure which shows the structure of the system of a 1st Example. 第一の実施例のシステムを構成するサーバの物理的な構成を示すブロック図である。It is a block diagram which shows the physical structure of the server which comprises the system of a 1st Example. 作業実績データベースの構成例を示す図である。It is a figure which shows the structural example of a work performance database. 作業関連データベースの構成例を示す図である。It is a figure which shows the structural example of a work related database. 拠点情報データベースの構成例を示す図である。It is a figure which shows the structural example of a base information database. 第一の実施例の処理手順のフローチャートである。It is a flowchart of the process sequence of a 1st Example. 第一の実施例の実績未管理時間属性データの構成例を示す図である。It is a figure which shows the structural example of the performance unmanaged time attribute data of a 1st Example. 第一の実施例の作業推定確率モデル生成処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the work estimation probability model production | generation process of a 1st Example. 第一の実施例の実績未管理時間分類結果の構成例を示す図である。It is a figure which shows the structural example of the performance unmanaged time classification | category result of a 1st Example. 第一の実施例の実績未管理時間分類属性の構成例を示す図である。It is a figure which shows the structural example of the performance unmanaged time classification | category attribute of a 1st Example. 第一の実施例の作業推定確率モデルの構成例を示す図である。It is a figure which shows the structural example of the work estimation probability model of a 1st Example. 作業の推定結果を出力する画面の例を示す図である。It is a figure which shows the example of the screen which outputs the estimation result of an operation | work. 作業の推定結果を出力する画面の例を示す図である。It is a figure which shows the example of the screen which outputs the estimation result of an operation | work. 作業の推定結果を出力する画面の例を示す図である。It is a figure which shows the example of the screen which outputs the estimation result of an operation | work. 作業の推定結果を出力する画面の例を示す図である。It is a figure which shows the example of the screen which outputs the estimation result of an operation | work. 第二の実施例の作業推定確率モデル生成処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the work estimation probability model production | generation process of a 2nd Example. 第二の実施例の実績未管理時間分類属性の構成例を示す図である。It is a figure which shows the structural example of the performance unmanaged time classification | category attribute of a 2nd Example. 第二の実施例の作業推定確率モデルの構成例を示す図である。It is a figure which shows the structural example of the work estimation probability model of a 2nd Example. 第三の実施例の作業推定確率モデル生成処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the work estimation probability model production | generation process of a 3rd Example. 第三の実施例の実績未管理時間分類属性の構成例を示す図である。It is a figure which shows the structural example of the performance unmanaged time classification | category attribute of a 3rd Example. 第三の実施例の作業推定確率モデルの構成例を示す図である。It is a figure which shows the structural example of the work estimation probability model of a 3rd Example. 第四の実施例の作業推定確率モデル生成処理の詳細を示すフローチャートである。It is a flowchart which shows the detail of the work estimation probability model production | generation process of a 4th Example. 第四の実施例の作業推定確率モデルの構成例を示す図である。It is a figure which shows the structural example of the work estimation probability model of a 4th Example. 第五の実施例の処理手順のフローチャートである。It is a flowchart of the process sequence of a 5th Example.

<第一の実施例>
本発明の第一の実施例では、利用者のリクエストに応じて、ある拠点及び期間における全作業者の実績未管理時間の作業を各実績未管理時間の前後の作業内容から推定する処理を説明する。第一の実施例では、例えば、前後の作業が異なる場合に行われる段取り作業や切替え作業など、前後作業が特徴的な作業を推定できる。
<First embodiment>
In the first embodiment of the present invention, in accordance with a user's request, a process for estimating the work of the actual unmanaged time of all workers at a certain base and period from the work contents before and after each actual unmanaged time is explained. To do. In the first embodiment, for example, it is possible to estimate a work having a characteristic before and after work such as a setup work or a switching work performed when the work before and after is different.

図1Aは、第一の実施例のシステムの構成を示す図である。   FIG. 1A is a diagram illustrating a configuration of a system according to the first embodiment.

第一の実施例のシステムの構成は、情報管理サーバ1100と、計算サーバ1200と、計算機1300とで構成される。計算サーバ1200と情報管理サーバ1100と計算機1300とはネットワーク1400を介して接続される。計算サーバ1200は、実績が記録されていない時間帯の作業及び状態を推定するための計算処理を実行する。情報管理サーバ1100は、計算サーバ1200での処理に必要なデータを管理する。計算機1300は、利用者が分析・可視化結果を閲覧したり入力するためのユーザインタフェースを提供する。なお、情報管理サーバ1100及び計算サーバ1200は一つのサーバで構成してもよい。   The system configuration of the first embodiment includes an information management server 1100, a calculation server 1200, and a computer 1300. The calculation server 1200, the information management server 1100, and the computer 1300 are connected via a network 1400. The calculation server 1200 executes a calculation process for estimating work and a state in a time zone in which no record is recorded. The information management server 1100 manages data necessary for processing in the calculation server 1200. The computer 1300 provides a user interface for the user to browse and input analysis / visualization results. Note that the information management server 1100 and the calculation server 1200 may be configured as a single server.

情報管理サーバ1100は、作業実績データベース1101と、作業関連データベース1102と、拠点情報データベース1103とを有する。情報管理サーバ1100は、図1Bで後述するように、補助記憶装置3を有し、各データベースを補助記憶装置3に格納する。情報管理サーバ1100が格納するデータは、計算機1300から入力されたものでも、他のシステムから取得したものでもよい。   The information management server 1100 includes a work performance database 1101, a work related database 1102, and a base information database 1103. As will be described later with reference to FIG. 1B, the information management server 1100 includes the auxiliary storage device 3 and stores each database in the auxiliary storage device 3. Data stored in the information management server 1100 may be input from the computer 1300 or acquired from another system.

作業実績データベース1101は、工場や倉庫等の作業実績データを格納する。作業関連データベース1102は、作業者の動きや位置などの作業実績データ以外で作業の過程で生成される作業関連データを格納する。拠点情報データベース1103は、工場や倉庫等の設備や、業務内容や、取扱い製品や商品や、作業者など拠点情報データを格納する。なお、本実施例において、作業を行う主体は作業者として説明するが、複数種類の作業を行う機械(例えば、ロボット)でもよい。また、作業は、倉庫で行われるピッキング作業や、工場で行われる製造作業を主とするが、オフィスで行われる事務作業でもよい。   The work record database 1101 stores work record data such as factories and warehouses. The work-related database 1102 stores work-related data generated in the course of work other than work performance data such as worker movement and position. The base information database 1103 stores base information data such as facilities such as factories and warehouses, business contents, handled products and products, and workers. In the present embodiment, the subject performing the work is described as an operator, but may be a machine (for example, a robot) that performs a plurality of types of work. The work mainly includes picking work performed in a warehouse and manufacturing work performed in a factory, but may be office work performed in an office.

計算サーバ1200は、実績情報取得部1201と、実績未管理時間算出部1202と、実績未管理時間分類部1203と、作業推定確率モデル生成部1204と、分析・可視化結果出力部1205を有する。計算サーバ1200は、図1Bで後述するように、プログラムを実行するプロセッサ1を有し、プロセッサが所定のプログラムを実行することによって各部が機能する。   The calculation server 1200 includes a result information acquisition unit 1201, a result unmanaged time calculation unit 1202, a result unmanaged time classification unit 1203, a work estimation probability model generation unit 1204, and an analysis / visualization result output unit 1205. As will be described later with reference to FIG. 1B, the calculation server 1200 includes a processor 1 that executes a program, and each unit functions when the processor executes a predetermined program.

実績情報取得部1201は、情報管理サーバ1100から特定の拠点の作業実績である第一の作業実績データを取得する。実績未管理時間算出部1202は、第一の作業実績データから各作業者の実績がなく未管理となっている実績未管理時間と、前記実績未管理時間の時間帯や作業者の役割や位置等の実績未管理時間属性とを取得する。実績未管理時間分類部1203は、取得した実績未管理時間属性から実績未管理時間を分類するための実績未管理時間分類属性を生成して、実績未管理時間を分類する。作業推定確率モデル生成部1204は、情報管理サーバ1100から実績未管理時間分類属性が一致する、他拠点を含めた、作業実績である第二の作業実績データを取得し、第二の作業実績データから実績未管理時間分類属性ごとに作業を推定する作業推定確率モデルを生成する。分析・可視化結果出力部1205は、第一の作業実績データと作業推定確率モデルとを用いて作業を推定し、実績未管理時間のデータを分析し、その結果を可視化する。   The record information acquisition unit 1201 acquires first work record data that is a work record of a specific base from the information management server 1100. The actual unmanaged time calculation unit 1202 includes an actual unmanaged time in which there is no actual record of each worker from the first work actual data, the time zone of the actual unmanaged time, the role and position of the worker Acquire track record unmanaged time attribute. The actual unmanaged time classification unit 1203 generates an actual unmanaged time classification attribute for classifying the actual unmanaged time from the acquired actual unmanaged time attribute, and classifies the actual unmanaged time. The work estimation probability model generation unit 1204 acquires second work result data that is work results including other bases that have the same result unmanaged time classification attribute from the information management server 1100, and obtains second work result data. A work estimation probability model that estimates work for each unmanaged time classification attribute is generated. The analysis / visualization result output unit 1205 estimates the work using the first work result data and the work estimation probability model, analyzes the data of the result unmanaged time, and visualizes the result.

計算機1300は、利用者へ情報を提示したり、利用者がリクエスト等を入力する。計算機1300は、プログラムを実行するプロセッサ(CPU)、プログラムやデータを格納する記憶装置、ユーザインタフェース(キーボード、マウス、タッチパネル,ディスプレイ、プリンタなど)及び通信インタフェースを有する計算機によって構成される。計算機1300では、ユーザインタフェースを提供するウェブブラウザが動作しても、専用プログラムが動作してもよい。   The computer 1300 presents information to the user, or the user inputs a request or the like. The computer 1300 includes a processor (CPU) that executes a program, a storage device that stores programs and data, a user interface (keyboard, mouse, touch panel, display, printer, etc.), and a computer having a communication interface. The computer 1300 may operate a web browser that provides a user interface or a dedicated program.

図1Bは、第一の実施例のシステムを構成するサーバの物理的な構成を示すブロック図である。なお、図1Bでは、計算サーバ1200について説明するが、情報管理サーバ1100も同じ構成でよい。   FIG. 1B is a block diagram illustrating a physical configuration of a server configuring the system of the first embodiment. 1B illustrates the calculation server 1200, the information management server 1100 may have the same configuration.

本実施例の計算サーバ1200は、プロセッサ(CPU)1、メモリ2、補助記憶装置3及び通信インタフェース4を有する計算機によって構成される。   The calculation server 1200 of this embodiment is configured by a computer having a processor (CPU) 1, a memory 2, an auxiliary storage device 3, and a communication interface 4.

プロセッサ1は、メモリ2に格納されたプログラムを実行する。メモリ2は、不揮発性の記憶デバイスであるROM及び揮発性の記憶デバイスであるRAMを含む。ROMは、不変のプログラム(例えば、BIOS)などを格納する。RAMは、DRAM(Dynamic Random Access Memory)のような高速かつ揮発性の記憶デバイスであり、プロセッサ1が実行するプログラム及びプログラムの実行時に使用されるデータを一時的に格納する。   The processor 1 executes a program stored in the memory 2. The memory 2 includes a ROM that is a nonvolatile storage device and a RAM that is a volatile storage device. The ROM stores an immutable program (for example, BIOS). The RAM is a high-speed and volatile storage device such as a dynamic random access memory (DRAM), and temporarily stores a program executed by the processor 1 and data used when the program is executed.

補助記憶装置3は、例えば、磁気記憶装置(HDD)、フラッシュメモリ(SSD)等の大容量かつ不揮発性の記憶デバイスによって構成され、プロセッサ1が実行するプログラム及びプログラムの実行時に使用されるデータを格納する。すなわち、プログラムは、補助記憶装置3から読み出されて、メモリ2にロードされて、プロセッサ1によって実行される。   The auxiliary storage device 3 is configured by a large-capacity and non-volatile storage device such as a magnetic storage device (HDD) or a flash memory (SSD), for example, and stores a program executed by the processor 1 and data used when the program is executed. Store. That is, the program is read from the auxiliary storage device 3, loaded into the memory 2, and executed by the processor 1.

通信インタフェース4は、所定のプロトコルに従って、他の装置(計算機102など)との通信を制御するネットワークインタフェース装置である。   The communication interface 4 is a network interface device that controls communication with other devices (such as the computer 102) according to a predetermined protocol.

計算サーバ1200は、入力インタフェース5及び出力インタフェース8を有してもよい。入力インタフェース5は、キーボード6やマウス7などが接続され、管理者からの入力を受けるインタフェースである。出力インタフェース8は、ディスプレイ装置9やプリンタなどが接続され、計算サーバ1200の状態やプログラムの実行結果を管理者が視認可能な形式で出力するインタフェースである。   The calculation server 1200 may have an input interface 5 and an output interface 8. The input interface 5 is an interface to which a keyboard 6 and a mouse 7 are connected and receives an input from an administrator. The output interface 8 is an interface to which a display device 9 or a printer is connected, and outputs the state of the calculation server 1200 and the execution result of the program in a format that can be viewed by the administrator.

プロセッサ1が実行するプログラムは、リムーバブルメディア(CD−ROM、フラッシュメモリなど)又はネットワークを介して計算サーバ1200に提供され、非一時的記憶媒体である不揮発性の補助記憶装置3に格納される。このため、計算サーバ1200は、リムーバブルメディアからデータを読み込むインタフェースを有するとよい。   The program executed by the processor 1 is provided to the calculation server 1200 via a removable medium (CD-ROM, flash memory, etc.) or a network, and is stored in the nonvolatile auxiliary storage device 3 that is a non-temporary storage medium. For this reason, the calculation server 1200 may have an interface for reading data from a removable medium.

計算サーバ1200は、物理的に一つの計算機上で、又は、論理的又は物理的に構成された複数の計算機上で構成される計算機システムであり、複数の物理的計算機資源上に構築された仮想計算機上で動作してもよい。また、計算サーバ1200上で実行されるプログラムは、同一の計算機上で別個のスレッドで動作してもよい。   The calculation server 1200 is a computer system configured on a plurality of computers that are physically configured on a single computer or logically or physically, and is a virtual system constructed on a plurality of physical computer resources. It may operate on a computer. A program executed on the calculation server 1200 may operate on a separate thread on the same computer.

また、計算サーバ1200において、プログラムによって実装される機能ブロックの全部又は一部は、物理的な集積回路(例えば、Field-Programmable Gate Array)等によって構成されてもよい。   In the calculation server 1200, all or part of the functional blocks implemented by the program may be configured by a physical integrated circuit (for example, Field-Programmable Gate Array).

図2は、作業実績データベース1101の構成例を示す図である。   FIG. 2 is a diagram illustrating a configuration example of the work performance database 1101.

作業実績データベース1101が格納する作業実績データは、作業者、前作業、作業内容、後作業、作業時刻、作業が行われた拠点の番号、作業の対象である取扱品、当該取扱品の数量などの情報を記録したデータで、現場管理者が作業進捗を把握したり、作業の証拠として取引先や顧客に提示するために記録される。作業内容は、作業者が行った作業の内容であるが、昼休み、朝礼などの複数の作業者が同時に行う行為や、作業を行っていないこと(作業無し)も含む。作業時刻は、作業終了時刻でも、作業開始時刻でも、作業開始時刻と作業終了時刻との両方でも、作業中の任意の時刻でもよい。取扱品及び数量は、例えば、倉庫内の作業であれば、移動した物品の品番及び数量であり、工場内の作業であれば、加工した物品の品番及び数量である。なお、作業実績データベース1101では、最低限、作業者、作業内容及び作業時刻が記録されていればよい。   The work record data stored in the work record database 1101 includes the worker, the previous work, the work content, the subsequent work, the work time, the number of the base where the work was performed, the handled product, the quantity of the handled product, and the like. This data is recorded so that the site manager can grasp the progress of the work and present it to the business partners and customers as evidence of the work. The work content is the content of the work performed by the worker, but includes actions that a plurality of workers perform at the same time, such as a lunch break and a morning meeting, and that no work is performed (no work). The work time may be the work end time, the work start time, both the work start time and the work end time, or any time during the work. The handling item and quantity are, for example, the article number and quantity of the moved article if the work is in a warehouse, and the article number and quantity of the processed article if the work is in a factory. In the work record database 1101, the worker, the work content, and the work time may be recorded at least.

図3は、作業関連データベース1102の構成例を示す図である。   FIG. 3 is a diagram illustrating a configuration example of the work-related database 1102.

作業関連データベース1102が格納する作業関連データは、作業実績データとして管理されないが作業の過程で生成されるデータ等の作業に関連するデータである。例えば図3では、作業における位置や動作などのセンシングデータを例示する。例えば、位置のセンシングデータは作業者の倉庫、工場内の位置データであり、動作のセンシングデータは加速度データであり、作業中の作業者の動き(行動)を記録する。この他に、作業関連データは、設備のログデータ(例えば、加工機の稼働状況)等も含んでもよい。   The work-related data stored in the work-related database 1102 is data related to work such as data that is not managed as work performance data but is generated in the course of work. For example, FIG. 3 illustrates sensing data such as a position and an operation in the work. For example, the position sensing data is position data in the warehouse and factory of the worker, and the motion sensing data is acceleration data, and records the movement (action) of the worker during the work. In addition to this, the work-related data may include equipment log data (for example, the operating status of the processing machine).

なお、作業実績データを作業関連データとは、厳密に区別できるものではなく、本システムで記録される作業において、作業実績として把握すべきデータが作業実績データベース1101に格納される。   Note that the work performance data is not strictly distinguishable from the work-related data, and data to be grasped as work performance is stored in the work performance database 1101 in the work recorded by this system.

図4は、拠点情報データベース1103の構成例を示す図である。   FIG. 4 is a diagram illustrating a configuration example of the base information database 1103.

拠点情報データベース1103が格納する拠点情報は、各拠点で取り扱う商品・製品の種類や導入されている設備など、拠点ごとの特徴や基本的な属性情報を記録しているデータである。拠点データは、例えば、当該作業の対象である取扱品、及び当該拠点に設置され稼動している設備のデータを含み、拠点の類似度を判定するために使用される。   The base information stored in the base information database 1103 is data that records the characteristics and basic attribute information for each base, such as the types of products and products handled at each base and the installed equipment. The base data includes, for example, data on handling items that are the objects of the work and equipment installed and operating at the base, and is used to determine the similarity of the bases.

取扱品は、取り扱いに特に注意を要する物品(例えば、衝撃を与えてはならない化学品、処方の誤りが重大な影響を生じる医薬品など)を区別するために記録される。これらの特に注意を要する物品は、通常の物品より作業の時間が長くなる。設備は、当該設備が当該拠点に設置されており、稼動しているかを示し、例えば仕分け作業の自動化設備が導入されているかが分かる。   Handled items are recorded to distinguish items that require special handling (eg, chemicals that should not be impacted, pharmaceuticals where prescription errors have a significant impact). These particularly sensitive items require longer work time than normal items. The facility indicates whether the facility is installed at the base and is operating, and for example, it can be seen whether an automated facility for sorting work is installed.

拠点情報は、拠点(例えば、倉庫)同士の作業を比較する際に使用され、拠点の属性情報の一致又は類似によって比較対象の拠点が決定される。   The base information is used when the operations of the bases (for example, warehouses) are compared, and the base for comparison is determined based on the match or similarity of the base attribute information.

また、図示を省略するが、情報管理サーバ1100が、作業者の情報(実施可能な作業、操作可能な装置、主担当作業)を含む作業者データベースを格納してもよい。   Although not shown, the information management server 1100 may store a worker database including worker information (work that can be performed, devices that can be operated, main work in charge).

図5は、第一の実施例の処理手順のフローチャートである。図5に示す処理は、計算サーバ1200のプロセッサ1が実行する。   FIG. 5 is a flowchart of the processing procedure of the first embodiment. The processing shown in FIG. 5 is executed by the processor 1 of the calculation server 1200.

まず、実績情報取得部1201は、利用者による分析リクエストと分析の条件(対象拠点・期間等)を受信する(5001)。実績情報取得部1201が受信する分析リクエストは、分析の条件(例えば、拠点、期間、作業者など)を含む。分析リクエストは、全データを対象とするものでもよい。   First, the record information acquisition unit 1201 receives an analysis request and analysis conditions (target base / period, etc.) by the user (5001). The analysis request received by the record information acquisition unit 1201 includes analysis conditions (for example, a base, a period, a worker, etc.). The analysis request may be for all data.

次に、実績情報取得部1201は、受信した分析リクエストに含まれる分析の条件に応じて、情報管理サーバ1100の作業実績データベース1101から作業実績データを、作業関連データベース1102から作業関連データを、拠点情報データベース1103から拠点情報データを取得する(5002)。   Next, the result information acquisition unit 1201 receives work result data from the work result database 1101 of the information management server 1100, work related data from the work related database 1102, and bases according to the analysis conditions included in the received analysis request. The base information data is acquired from the information database 1103 (5002).

そして、実績未管理時間算出部1202は、取得した作業実績データから、各作業者において就業時間内で一定時間以上実績が記録されていない実績未管理時間を算出し、実績未管理時間に関する属性である実績未管理時間属性を取得する(5003)。   The actual unmanaged time calculation unit 1202 calculates an actual unmanaged time in which no actual result is recorded within a certain working time in each worker from the acquired work actual data. A certain result unmanaged time attribute is acquired (5003).

図6は、実績未管理時間属性データの構成例を示す図である。なお、図6に示す実績未管理時間属性データは例示であって、実績未管理時間属性データが、図示した項目以外を含んでもよい。また、実績未管理時間属性データは、時間帯を特定するデータと作業者情報を含めば、図示した項目の一部を含まなくてもよい。   FIG. 6 is a diagram illustrating a configuration example of the actual unmanaged time attribute data. The actual unmanaged time attribute data illustrated in FIG. 6 is an example, and the actual unmanaged time attribute data may include items other than those illustrated. Further, the result unmanaged time attribute data may not include some of the illustrated items as long as the data specifying the time zone and the worker information are included.

実績未管理時間属性は、例えば、実績未管理時間の時間帯を特定する開始時刻及び終了時刻、作業者情報、当該作業者が実績未管理時間の前及び後に行った作業実績データに記録されている作業の情報、実績未管理時間における作業関連データ(作業エリア内の位置データ、作業者の動作)の情報、拠点情報データに記載されている拠点での取扱商品や設備情報等である。なお、役割として、当該作業者の主担当作業を前述した作業者データベースから取得してもよい。   The actual unmanaged time attribute is recorded in, for example, the start time and end time for specifying the time zone of the actual unmanaged time, the worker information, and the actual work data performed by the worker before and after the actual unmanaged time. Information on the work being performed, information on work related data (position data in the work area, operation of the worker) during actual unmanaged time, information on products handled at the base described in the base information data, equipment information, and the like. In addition, as a role, you may acquire the main charge work of the said worker from the worker database mentioned above.

そして、作業推定確率モデル生成部1204は、実績未管理時間分類属性を設定し、実績未管理時間分類属性と一致する属性を有する作業実績データから作業推定確率モデルを生成する(5004)。   Then, the work estimation probability model generation unit 1204 sets a performance unmanaged time classification attribute, and generates a work estimation probability model from work performance data having an attribute that matches the performance unmanaged time classification attribute (5004).

図7は、作業推定確率モデル生成処理の詳細を示すフローチャートである。   FIG. 7 is a flowchart showing details of the work estimation probability model generation process.

まず、作業推定確率モデル生成部1204は、実績未管理時間分類属性を設定し、実績未管理時間分類結果を生成する(7001)。   First, the work estimation probability model generation unit 1204 sets an actual unmanaged time classification attribute, and generates an actual unmanaged time classification result (7001).

ここで、前作業及び後作業を実績未管理時間分類属性に設定した例を説明する。例えば、まず、図9に例示するように、前作業及び後作業が実績未管理時間分類属性に設定された実績未管理時間分類属性データを生成する。具体的には、実績未管理時間分類属性に設定された前作業と後作業の組について、作業実績データベース1101から全ての組み合わせを抽出し、実績未管理時間分類属性データに記録する。なお、実績未管理時間分類属性は、本システムの利用者が入力した定義を記録してもよい。なお、図9に示す実績未管理時間分類属性データの3番目のレコードは、前作業が作業Bであることが規定されているが、後作業は何でもよいことを示す。   Here, an example will be described in which the previous work and the subsequent work are set as the actual unmanaged time classification attribute. For example, first, as illustrated in FIG. 9, actual unmanaged time classification attribute data in which the previous work and the subsequent work are set to the actual unmanaged time classification attribute is generated. More specifically, all combinations are extracted from the work performance database 1101 for the set of the previous work and the subsequent work set in the performance unmanaged time classification attribute and recorded in the performance unmanaged time classification attribute data. Note that the definition input by the user of this system may be recorded in the performance unmanaged time classification attribute. Note that the third record of the actual unmanaged time classification attribute data shown in FIG. 9 specifies that the previous work is the work B, but indicates that the subsequent work may be anything.

そして、図8に例示するように、実績未管理時間分類結果を生成する。具体的には、実績未管理時間属性データの各レコードについて、実績未管理時間分類属性(前作業、後作業)と実績未管理時間属性データの当該項目とを比較し、各実績未管理時間に実績未管理時間分類属性で定義された分類を割り当てる。   Then, as illustrated in FIG. 8, a result unmanaged time classification result is generated. Specifically, for each record of the actual unmanaged time attribute data, the actual unmanaged time classification attribute (previous work, subsequent work) and the corresponding item of the actual unmanaged time attribute data are compared, and each actual unmanaged time Assigns the class defined by the actual unmanaged time class attribute.

ステップ7001によって、実績未管理時間の前後で作業者が行っていた作業をキーにして実績未管理を分類できる。   By step 7001, performance unmanaged can be classified using the work performed by the worker before and after the performance unmanaged time as a key.

次に、作業推定確率モデル生成部1204は、実績未管理時間分類属性と属性が一致する、全ての拠点の作業実績データ及び当該作業実績データに関連する作業関連データ及び拠点データを取得する。そして、取得した作業実績データから実績未管理時間分類属性ごとに作業を推定する作業推定確率モデルを生成する(7002)。   Next, the work estimation probability model generation unit 1204 acquires work performance data of all bases, work-related data and base data related to the work performance data whose attributes match the actual unmanaged time classification attribute. Then, a work estimation probability model for estimating work for each performance unmanaged time classification attribute is generated from the acquired work performance data (7002).

作業推定確率モデルは、図10に例示するように、実績未管理時間分類属性の組み合わせに対応して、推定される作業及び推定される確率が定められる。具体的には、実績未管理時間分類結果の分類ごとに、当該前作業と当該後作業との間で行われていた中間作業を抽出し、作業推定確率モデルに推定作業を記録する。さらに、分類属性及び推定される作業の組み合わせごとに抽出された数を集計して、抽出された全推定作業の数で除した値を、当該中間作業である推定確率として記録する。   In the work estimation probability model, as illustrated in FIG. 10, the estimated work and the estimated probability are determined corresponding to the combination of the actual unmanaged time classification attributes. Specifically, for each classification of the result unmanaged time classification result, an intermediate work performed between the previous work and the subsequent work is extracted, and the estimated work is recorded in the work estimation probability model. Further, the number extracted for each combination of the classification attribute and the estimated work is totaled, and the value divided by the number of all the estimated work extracted is recorded as the estimated probability that is the intermediate work.

なお、前作業との間の時間が所定値(例えば10分)を超える作業実績データを除外し、後作業との間の時間が所定値(例えば10分)を超える作業実績データを除外するフィルタリングをしたデータを取得してもよい。これは、記録されている作業と前作業との間の時間や後作業との間の時間が長い場合、当該時間は未管理時間であり、別の作業が行われている可能性があるからである。   Filtering that excludes work performance data whose time between the previous work exceeds a predetermined value (for example, 10 minutes) and excludes work performance data whose time between the previous work exceeds a predetermined value (for example, 10 minutes). You may acquire the data which did. This is because if the time between the recorded work and the previous work or the time after the work is long, the time is an unmanaged time and another work may be performed. It is.

また、全ての拠点の作業実績データの代わりに、全ての作業を含むモデル拠点のデータを取得してもよい。モデル拠点は、現実に作業者が作業を行っている拠点でも、作業がシミュレーションされた仮想の拠点でもよい。   Further, instead of the work result data of all the bases, data of the model bases including all the work may be acquired. The model base may be a base where the worker is actually working, or a virtual base where the work is simulated.

なお、作業実績データベース1101が作業時間(又は、開始時刻と終了時刻)を記録している場合、実績未管理時間の時間幅と作業実績データの作業時間とを照合して、推定作業及び推定確率を決定してもよい。   When the work performance database 1101 records the work time (or start time and end time), the time width of the actual unmanaged time and the work time of the work performance data are collated, and the estimated work and the estimated probability May be determined.

次に、作業推定確率モデル生成部1204は、作成した作業推定確率モデルに問題があるかを判定する(7003)。作成した作業推定確率モデルに問題がある場合、不適切な実績未管理時間分類属性を用いて実績未管理時間を分類したので、実績未管理時間分類属性を再設定し(7004)、ステップ7002に戻る。   Next, the work estimation probability model generation unit 1204 determines whether there is a problem in the created work estimation probability model (7003). If there is a problem with the created work estimation probability model, the actual unmanaged time classification attribute is used to classify the actual unmanaged time, so the actual unmanaged time classification attribute is reset (7004). Return.

例えば、属性の指定が大まかである場合は、一つの実績未管理時間分類属性に対応する作業実績データの種類が多くなり、作業推定確率モデルの各推定結果の推定確率が大きくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を増やすとよい(例えば、前作業と後作業を属性に設定していた場合、さらに作業者の役割や期間を追加する等)。一方、属性の指定が細かい場合は、一つの実績未管理時間分類属性に対応する作業実績データが少なくなり(又は、存在しない)、作業推定確率モデルの各推定結果の推定確率が小さくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を減らすとよい。   For example, when the designation of the attribute is rough, the types of work performance data corresponding to one performance unmanaged time classification attribute increase, and the estimation probability of each estimation result of the work estimation probability model increases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute may be increased (for example, the previous work and the subsequent work are attributed). If it is set to, add the role and period of the worker, etc.). On the other hand, when the designation of the attribute is fine, the work result data corresponding to one result unmanaged time classification attribute decreases (or does not exist), and the estimation probability of each estimation result of the work estimation probability model decreases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute may be reduced.

なお、所定回数試行しても作業推定確率モデルに問題があると判定される場合、有用な作業推定確率モデルが生成できなかったエラーを利用者に通知して、処理を終了してもよい。   If it is determined that there is a problem with the work estimation probability model after a predetermined number of trials, the user may be notified of an error that a useful work estimation probability model could not be generated, and the process may be terminated.

このように、作業推定確率モデルを評価し、作業推定確率モデルが不適切な場合は、再作成するので、作業実績データとして記録されていない作業を高精度で推定できる。   As described above, the work estimation probability model is evaluated, and if the work estimation probability model is inappropriate, the work estimation probability model is re-created. Therefore, the work not recorded as work performance data can be estimated with high accuracy.

一方、作成した作業推定確率モデルに問題がない場合、作業推定確率モデル生成処理を終了し、図5のステップ5005へ進む。   On the other hand, if there is no problem in the created work estimation probability model, the work estimation probability model generation process is terminated, and the process proceeds to step 5005 in FIG.

ステップ5005では、実績未管理時間分類部1203は、作成した作業推定確率モデルを用いて各実績未管理時間に作業を推定し、推定された作業(推定作業)を各実績未管理時間に関連付ける。例えば、前作業及び後作業が同じ作業のうち推定確率が最も高い推定作業を、当該実績未管理時間に行われていた作業であると推定する。   In step 5005, the actual unmanaged time classifying unit 1203 estimates the work at each actual unmanaged time using the created work estimated probability model, and associates the estimated work (estimated work) with each actual unmanaged time. For example, it is estimated that the estimated work having the highest estimated probability among the work with the same previous work and the subsequent work is the work performed during the actual unmanaged time.

分析・可視化結果出力部1205は、ステップ5002で取得した第一の作業実績データと、推定作業が関連付けられた実績未管理時間の情報に基づいて、実績未管理時間の情報に基づいて、分析結果を可視化するためのデータを生成し、生成したデータを計算機1300に出力する(5006)。   The analysis / visualization result output unit 1205 analyzes the analysis result based on the information on the actual unmanaged time based on the first work performance data acquired in Step 5002 and the information on the actual unmanaged time associated with the estimated work. Is generated, and the generated data is output to the computer 1300 (5006).

図11から図14は、作業の推定結果を出力する画面の例を示す図である。図11に例示するように、作業者と作業内容を対応付けて時系列に表示してもよい。この画面によると、誰が、何時、何の作業を行っていたかを可視化できる。図11に示す画面において、実績未管理時間に行われていたと推定される作業を一つ表示してもよく、複数の候補を推定確率と共に表示してもよい。また、実績未管理時間を表示するために複数の態様(色や模様)を準備して、複数の態様の各々を推定された作業内容に割り当てて、推定作業を可視化してもよい。   FIG. 11 to FIG. 14 are diagrams showing examples of screens for outputting work estimation results. As illustrated in FIG. 11, the worker and the work content may be associated with each other and displayed in time series. This screen makes it possible to visualize who is doing what, when and what. In the screen shown in FIG. 11, one task that is estimated to have been performed during the actual unmanaged time may be displayed, or a plurality of candidates may be displayed together with the estimated probability. In addition, a plurality of modes (colors and patterns) may be prepared to display the actual unmanaged time, and each of the plurality of modes may be assigned to the estimated work content to visualize the estimated work.

また、図12に例示するように、時間帯ごとに各作業(推定作業を含めてもよい)に要した時間を集計して時系列に表示してもよい。表示される作業は一人の分でも、特定のグループの分でも、全員の分でもよい。この画面によると、各時間帯で行われていた作業の割合を可視化でき、主に行われていた作業を知ることができる。   Moreover, as illustrated in FIG. 12, the time required for each work (may include the estimation work) may be aggregated and displayed in time series for each time zone. The work displayed can be for one person, for a specific group, or for all. According to this screen, it is possible to visualize the ratio of work performed in each time zone, and to know the work performed mainly.

また、図13に例示するように、作業が推定される確率と実績未管理時間の量を表示してもよい。この画面において、横軸は、実績未管理時間分類属性ごとの合計時間である。この画面によると、各作業が推定される確率を可視化できる。   Further, as illustrated in FIG. 13, the probability that the work is estimated and the amount of actual unmanaged time may be displayed. In this screen, the horizontal axis represents the total time for each performance unmanaged time classification attribute. According to this screen, the probability that each work is estimated can be visualized.

さらに、図14に例示するように、推定結果を修正するインタフェースを設けてもよい。例えば、各作業の時間帯を指定して、推定が正しいか誤っているかを選択する。誤っている場合は、正しい作業内容を入力できる入力欄が設けられている。このインタフェースは推定結果の修正や、作業が推定できなかった場合に、利用者が作業内容を入力できる。   Further, as illustrated in FIG. 14, an interface for correcting the estimation result may be provided. For example, the time zone of each work is designated and whether the estimation is correct or incorrect is selected. If it is incorrect, an input field is provided for inputting correct work contents. This interface allows the user to input the work content when the estimation result is corrected or the work cannot be estimated.

図14に示すインタフェースに利用者が入力すると、分析・可視化結果出力部1205が、利用者の入力を受信する(5007)。   When the user inputs to the interface shown in FIG. 14, the analysis / visualization result output unit 1205 receives the user's input (5007).

その後、実績未管理時間分類部1203は、受信した入力データを用いて実績未管理時間の作業実績データを修正及び生成し、所定の形式に変換して、作業実績データベース1101に格納する(5008)。このため、誤った作業実績データを修正でき、正しい作業実績を作業実績データベース1101に格納できる。   Thereafter, the result unmanaged time classifying unit 1203 corrects and generates work result data of the result unmanaged time using the received input data, converts it into a predetermined format, and stores it in the work result database 1101 (5008). . For this reason, incorrect work performance data can be corrected, and the correct work performance data can be stored in the work performance database 1101.

以上に説明したように、本発明の第一の実施例では、作業実績データとして記録されていない作業を推定できる。   As described above, in the first embodiment of the present invention, work that is not recorded as work performance data can be estimated.

<第二の実施例>
本発明の第二の実施例では、利用者のリクエストに応じて、ある拠点及び期間における全作業者の実績未管理時間の作業を同時刻の作業実績から推定する。これによって実績未管理時間の作業や状態として、例えば、設備不良や申告漏れ等によって、欠落している作業実績を推定できる。
<Second Example>
In the second embodiment of the present invention, in response to a user's request, the work of the actual unmanaged time of all workers at a certain base and period is estimated from the work results at the same time. As a result, it is possible to estimate a missing work record due to, for example, equipment failure or missing report as the work or state in the record unmanaged time.

なお、第二の実施例では、第一の実施例と同じ構成及び機能には同じ符号を付し、それらの説明は省略する。例えば、第二の実施例のシステムは、図1Aに示す第一の実施例のシステムと同じでよい。   In the second embodiment, the same components and functions as those in the first embodiment are denoted by the same reference numerals, and the description thereof is omitted. For example, the system of the second embodiment may be the same as the system of the first embodiment shown in FIG. 1A.

また、第二の実施例の処理手順は、図5に示す第一の実施例と同様であるが、作業推定確率モデル生成処理(5004)が第一の実施例と異なる。図15を参照して、第二の実施例の作業推定確率モデル生成処理を説明する。   The processing procedure of the second embodiment is the same as that of the first embodiment shown in FIG. 5, but the work estimation probability model generation processing (5004) is different from that of the first embodiment. With reference to FIG. 15, the work estimation probability model generation processing of the second embodiment will be described.

まず、作業推定確率モデル生成部1204は、実績未管理時間の発生時刻を実績未管理時間分類属性に設定する(15001)。なお、実績未管理時間の発生時刻は、5分、10分、30分、1時間等の単位で抽象化して、時間帯に分類してもよい。   First, the work estimation probability model generation unit 1204 sets the generation time of the actual unmanaged time as the actual unmanaged time classification attribute (15001). The generation time of the actual unmanaged time may be abstracted in units of 5 minutes, 10 minutes, 30 minutes, 1 hour, and classified into time zones.

次に、作業推定確率モデル生成部1204は、他の実績未管理時間属性を実績未管理時間分類属性に設定し、実績未管理時間分類結果を生成する(15002)。ステップ15002で設定される実績未管理時間分類属性は、処理15001で設定された実績未管理時間分類属性の他、作業者の役割、作業拠点における位置などである。   Next, the work estimation probability model generation unit 1204 sets another actual unmanaged time attribute as an actual unmanaged time classification attribute, and generates an actual unmanaged time classification result (15002). The actual unmanaged time category attribute set in step 15002 includes the role of the worker, the position at the work site, etc., in addition to the actual unmanaged time category attribute set in step 15001.

ここで、実績未管理時間が発生した時間帯及び作業者の役割を実績未管理時間分類属性に設定した例を説明する。例えば、図16に例示するように、実績未管理時間発生時間帯及び作業者の役割が実績未管理時間分類属性に設定された実績未管理時間分類属性データを生成する。具体的には、実績未管理時間分類属性に設定された時間帯と役割の組について、作業実績データベース1101から全ての組み合わせを抽出し、実績未管理時間分類属性データに記録する。なお、実績未管理時間分類属性は、本システムの利用者が入力した定義を記録してもよい。   Here, an example in which the time zone in which the actual unmanaged time has occurred and the role of the worker is set as the actual unmanaged time classification attribute will be described. For example, as illustrated in FIG. 16, actual unmanaged time classification attribute data in which the actual unmanaged time generation time zone and the role of the worker are set in the actual unmanaged time classification attribute is generated. Specifically, for the combination of time zone and role set in the performance unmanaged time classification attribute, all combinations are extracted from the work performance database 1101 and recorded in the performance unmanaged time classification attribute data. Note that the definition input by the user of this system may be recorded in the performance unmanaged time classification attribute.

そして、実績未管理時間分類結果(図示省略)を生成する。具体的には、実績未管理時間属性データの各レコードについて、実績未管理時間分類属性(時間帯、役割)と実績未管理時間属性データの当該項目とを比較し、各実績未管理時間に実績未管理時間分類属性で定義された分類を割り当てる。   Then, a result unmanaged time classification result (not shown) is generated. Specifically, for each record of the actual unmanaged time attribute data, the actual unmanaged time classification attribute (time zone, role) and the corresponding item of the actual unmanaged time attribute data are compared, and the actual results are recorded at each actual unmanaged time. Assigns a classification defined with the unmanaged time classification attribute.

その後、作業推定確率モデル生成部1204は、実績未管理時間分類属性と属性が一致する、同じ拠点の作業実績データ及び当該作業実績データに関連する作業関連データ及び拠点データを取得する。そして、取得した作業実績データから実績未管理時間分類属性ごとに作業を推定する作業推定確率モデルを生成する(15003)。   Thereafter, the work estimation probability model generation unit 1204 obtains work performance data of the same base, work-related data related to the work performance data, and base data that have the same attribute as the unmanaged time classification attribute. Then, a work estimation probability model for estimating a work for each performance unmanaged time classification attribute is generated from the acquired work performance data (15003).

作業推定確率モデルでは、図17に例示するように、実績未管理時間分類属性の組み合わせに対応して、推定される作業及び推定される確率が定められる。具体的には、実績未管理時間分類結果の分類ごとに、当該時間帯において当該役割を有する作業者が行っている作業を抽出し、作業推定確率モデルに推定作業を記録する。さらに、分類属性及び推定される作業の組み合わせごとに抽出された数を集計して、抽出された全推定作業の数で除した値を、当該作業の推定確率として記録する。   In the work estimation probability model, as illustrated in FIG. 17, the estimated work and the estimated probability are determined corresponding to the combination of the actual unmanaged time classification attributes. Specifically, for each classification of the result unmanaged time classification result, the work performed by the worker having the role in the time zone is extracted, and the estimated work is recorded in the work estimation probability model. Further, the number extracted for each combination of the classification attribute and the estimated work is totaled, and the value divided by the number of all the estimated work extracted is recorded as the estimated probability of the work.

なお、同じ拠点の作業実績データに加えて、他の拠点のデータを取得してもよい。他の拠点は、分析対象の拠点と類似している拠点(特に、時間帯による作業が類似している拠点)が望ましい。   In addition to work performance data at the same base, data at other bases may be acquired. The other bases are preferably bases that are similar to the base to be analyzed (particularly, bases that have similar work in time zones).

次に、作業推定確率モデル生成部1204は、作成した作業推定確率モデルに問題があるかを判定する(15004)。作成した作業推定確率モデルに問題がある場合、不適切な実績未管理時間分類属性を用いて実績未管理時間を分類したので、実績未管理時間分類属性を再設定し(15005)、ステップ15003に戻る。   Next, the work estimation probability model generation unit 1204 determines whether there is a problem with the created work estimation probability model (15004). If there is a problem with the created work estimation probability model, since the actual unmanaged time is classified using an inappropriate actual unmanaged time classification attribute, the actual unmanaged time classification attribute is reset (15005). Return.

例えば、属性の指定が大まかである場合は、一つの実績未管理時間分類属性データに対応する作業実績データが多くなり、作業推定確率モデルの各推定結果の推定確率が大きくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を増やすとよい(例えば、時間帯のみを属性に設定していた場合、さらに作業者の役割を追加する等)。一方、属性の指定が細かい場合は、一つの実績未管理時間分類属性に対応する作業実績データが少なくなり(又は、存在しない)、作業推定確率モデルの各推定結果の推定確率が小さくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を減らすとよい。   For example, when the designation of the attribute is rough, the work result data corresponding to one result unmanaged time classification attribute data increases, and the estimation probability of each estimation result of the work estimation probability model increases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute should be increased (for example, only the time zone is set as the attribute) If so, add more worker roles). On the other hand, when the designation of the attribute is fine, the work result data corresponding to one result unmanaged time classification attribute decreases (or does not exist), and the estimation probability of each estimation result of the work estimation probability model decreases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute may be reduced.

なお、所定回数試行しても作業推定確率モデルに問題があると判定される場合、有用な作業推定確率モデルが生成できなかったエラーを利用者に通知して、処理を終了してもよい。   If it is determined that there is a problem with the work estimation probability model after a predetermined number of trials, the user may be notified of an error that a useful work estimation probability model could not be generated, and the process may be terminated.

一方、作成した作業推定確率モデルに問題がない場合、作業推定確率モデル生成処理を終了し、図5のステップ5005へ進む。ステップ5004以外の処理は、前述した第一の実施例と同じである。   On the other hand, if there is no problem in the created work estimation probability model, the work estimation probability model generation process is terminated, and the process proceeds to step 5005 in FIG. Processing other than step 5004 is the same as that in the first embodiment described above.

以上に説明したように、本発明の第二の実施例では、実績未管理時間において欠落している作業実績を推定できる。特に、複数の作業者が同じ時間帯に同じ作業を行っている拠点において、他の作業者の作業実績から、記録されなかった作業を適切に推定できる。   As described above, in the second embodiment of the present invention, it is possible to estimate the work results that are missing in the result unmanaged time. In particular, at a base where a plurality of workers are performing the same task in the same time zone, a task that has not been recorded can be appropriately estimated from the work results of other workers.

<第三の実施例>
本発明の第三の実施例では、利用者のリクエストに応じて、ある拠点及び期間における全作業者の実績未管理時間の作業を同時刻における他の実績未管理時間の発生傾向から推定する。これによって実績未管理時間の作業や状態として、例えば、複数人が同時に行う作業(昼休み、朝礼など)を推定できる。
<Third embodiment>
In the third embodiment of the present invention, according to a user's request, the work of the actual unmanaged time of all workers at a certain base and period is estimated from the tendency of the other unmanaged time to occur at the same time. As a result, for example, work (lunch break, morning gathering, etc.) performed by a plurality of persons can be estimated as work or status in the unmanaged time.

なお、第三の実施例では、第一の実施例と同じ構成及び機能には同じ符号を付し、それらの説明は省略する。例えば、第三の実施例のシステムは、図1Aに示す第一の実施例のシステムと同じでよい。   In the third embodiment, the same components and functions as those in the first embodiment are denoted by the same reference numerals, and description thereof is omitted. For example, the system of the third embodiment may be the same as the system of the first embodiment shown in FIG. 1A.

また、第三の実施例の処理手順は、図5に示す第一の実施例と同様であるが、作業推定確率モデル生成処理(5004)が第一の実施例と異なる。図18を参照して、第三の実施例の作業推定確率モデル生成処理を説明する。   The processing procedure of the third embodiment is the same as that of the first embodiment shown in FIG. 5, but the work estimation probability model generation processing (5004) is different from that of the first embodiment. With reference to FIG. 18, the work estimation probability model generation processing of the third embodiment will be described.

まず、作業推定確率モデル生成部1204は、実績未管理時間の発生時刻を比較し、同時間帯に発生している実績未管理時間を纏めて実績未管理時間分類結果を生成する。当該実績未管理時間分類結果では、共起性及び発生時間帯を実績未管理時間分類属性に設定する(18001)。なお、発生時刻は5分、10分、30分、1時間等の単位で抽象化して、時間帯に分類してもよい。なお、時間帯の他に作業者の役割や作業拠点における位置などを実績未管理時間分類属性に設定してもよい。作業者の役割や拠点内の配置場所によって共起する作業が異なる場合に有効である。   First, the work estimation probability model generation unit 1204 compares the occurrence times of the actual unmanaged time, and generates the actual unmanaged time classification result by collecting the actual unmanaged times occurring in the same time zone. In the actual unmanaged time classification result, the co-occurrence and occurrence time zone are set as the actual unmanaged time classification attribute (18001). The generation time may be abstracted in units of 5 minutes, 10 minutes, 30 minutes, 1 hour, etc., and classified into time zones. In addition to the time zone, the role of the worker, the position at the work base, and the like may be set as the performance unmanaged time classification attribute. This is effective when the co-occurring work differs depending on the role of the worker and the location in the base.

また、時間帯を使用せず、共起情報だけを実績未管理時間分類属性に設定してもよい。例えば、時間帯によらず、共起する作業が同じである場合(例えば、休憩時間)、実績未管理時間分類属性を減らして処理を簡素化できる。一方、時間帯及び共起情報を実績未管理時間分類属性に設定すると、時間帯によって共起する作業が異なる場合(例えば、非理休み、朝礼)、実績未管理時間の作業内容を正確に推定できる。   Further, only the co-occurrence information may be set as the result unmanaged time classification attribute without using the time zone. For example, when the co-occurring work is the same regardless of the time zone (for example, break time), the processing can be simplified by reducing the actual unmanaged time classification attribute. On the other hand, when the time zone and co-occurrence information are set as the actual unmanaged time classification attribute, the work contents of the actual unmanaged time can be accurately estimated when the co-occurring work differs depending on the time zone (for example, irrational leave, morning meeting). .

実績未管理時間分類属性として、例えば、図19に例示するように、実績未管理時間発生時間帯及び共起情報が実績未管理時間分類属性に設定された実績未管理時間分類属性データを生成する。具体的には、実績未管理時間分類属性に設定された時間帯を作業実績データベース1101から抽出し、実績未管理時間分類属性データに記録する。なお、実績未管理時間分類属性は、本システムの利用者が入力した定義を記録してもよい。   As the actual unmanaged time classification attribute, for example, as illustrated in FIG. 19, actual unmanaged time classification attribute data in which the actual unmanaged time occurrence time zone and the co-occurrence information are set in the actual unmanaged time classification attribute is generated. . Specifically, the time zone set in the performance unmanaged time classification attribute is extracted from the work performance database 1101 and recorded in the performance unmanaged time classification attribute data. Note that the definition input by the user of this system may be recorded in the performance unmanaged time classification attribute.

共起情報は、例えば、実績未管理時間が複数の作業者に共起しているかの情報(共起している場合は1、共起していない場合は0)であるが、実績未管理時間が共起している作業者の数でもよい。共起情報として複数の作業者に共起しているかを記録する場合、共起有りと判定する作業者の数の閾値を予め設定しておくとよい。   The co-occurrence information is, for example, information on whether or not the result unmanaged time co-occurs with a plurality of workers (1 if co-occurs, 0 if not co-occurrence), but results unmanaged It may be the number of workers with whom time co-occurs. When recording whether co-occurrence occurs with a plurality of workers as co-occurrence information, a threshold value for the number of workers determined to have co-occurrence may be set in advance.

そして、実績未管理時間分類結果(図示省略)を生成する。具体的には、実績未管理時間属性データの各レコードについて、実績未管理時間分類属性(時間帯)と実績未管理時間属性データの当該項目とを比較し、各実績未管理時間に実績未管理時間分類属性で定義された分類を割り当てる。   Then, a result unmanaged time classification result (not shown) is generated. Specifically, for each record of the actual unmanaged time attribute data, the actual unmanaged time classification attribute (time zone) is compared with the corresponding item of the actual unmanaged time attribute data, and the actual unmanaged time is recorded at each actual unmanaged time. Assign the classification defined by the time classification attribute.

その後、作業推定確率モデル生成部1204は、実績未管理時間分類属性と属性が一致する、全ての拠点の作業実績データ及び当該作業実績データに関連する作業関連データ及び拠点データを取得する。そして、取得した作業実績データから実績未管理時間分類属性ごとに作業を推定する作業推定確率モデルを生成する(18002)。   Thereafter, the work estimation probability model generation unit 1204 acquires work performance data of all bases, work-related data and base data related to the work performance data, whose attributes match the actual unmanaged time classification attribute. Then, a work estimation probability model for estimating work for each performance unmanaged time classification attribute is generated from the acquired work performance data (18002).

作業推定確率モデルでは、図20に例示するように、実績未管理時間分類属性(時間帯)に対応して推定される作業及び推定される確率が定められる。具体的には、実績未管理時間分類結果の分類ごとに、実績未管理時間発生時間帯に行われていた作業を抽出し、共起情報によって分類して、作業推定確率モデルに推定作業を記録する。さらに、分類属性及び推定される作業の組み合わせごとに抽出された数を集計して、抽出された全推定作業の数で除した値を、当該作業の推定確率として記録する。   In the work estimation probability model, as illustrated in FIG. 20, the work to be estimated and the probability to be estimated are determined corresponding to the actual unmanaged time classification attribute (time zone). Specifically, for each classification of the actual unmanaged time classification result, the work that was performed during the actual unmanaged time generation time zone is extracted, classified by co-occurrence information, and the estimated work is recorded in the work estimation probability model To do. Further, the number extracted for each combination of the classification attribute and the estimated work is totaled, and the value divided by the number of all the estimated work extracted is recorded as the estimated probability of the work.

なお、全ての拠点の作業実績データではなく、分析対象の拠点と類似している拠点(特に、時間帯による作業が類似している拠点)のデータを取得してもよい。   It should be noted that, instead of the work performance data of all the bases, data on bases similar to the bases to be analyzed (particularly bases having similar work in time zones) may be acquired.

次に、作業推定確率モデル生成部1204は、作成した作業推定確率モデルに問題があるかを判定する(18003)。作成した作業推定確率モデルに問題がある場合、不適切な実績未管理時間分類属性を用いて実績未管理時間を分類したので、実績未管理時間分類属性を再設定し(18004)、ステップ18002に戻る。   Next, the work estimation probability model generation unit 1204 determines whether there is a problem with the created work estimation probability model (18003). If there is a problem with the created work estimation probability model, the actual unmanaged time is classified using an inappropriate actual unmanaged time classification attribute, so the actual unmanaged time classification attribute is reset (18004). Return.

例えば、属性の指定が大まかである場合は、一つの実績未管理時間分類属性データに対応する作業実績データが多くなり、作業推定確率モデルの各推定結果の推定確率が大きくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を増やすとよい(例えば、時間帯のみを属性に設定していた場合、さらに作業者の役割を追加する等)。一方、属性の指定が細かい場合は、一つの実績未管理時間分類属性に対応する作業実績データが少なくなり(又は、存在しない)、作業推定確率モデルの各推定結果の推定確率が小さくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を減らすとよい。   For example, when the designation of the attribute is rough, the work result data corresponding to one result unmanaged time classification attribute data increases, and the estimation probability of each estimation result of the work estimation probability model increases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute should be increased (for example, only the time zone is set as the attribute) If so, add more worker roles). On the other hand, when the designation of the attribute is fine, the work result data corresponding to one result unmanaged time classification attribute decreases (or does not exist), and the estimation probability of each estimation result of the work estimation probability model decreases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute may be reduced.

なお、所定回数試行しても作業推定確率モデルに問題があると判定される場合、有用な作業推定確率モデルが生成できなかったエラーを利用者に通知して、処理を終了してもよい。   If it is determined that there is a problem with the work estimation probability model after a predetermined number of trials, the user may be notified of an error that a useful work estimation probability model could not be generated, and the process may be terminated.

一方、作成した作業推定確率モデルに問題がない場合、作業推定確率モデル生成処理を終了し、図5のステップ5005へ進む。ステップ5004以外の処理は、前述した第一の実施例と同じである。   On the other hand, if there is no problem in the created work estimation probability model, the work estimation probability model generation process is terminated, and the process proceeds to step 5005 in FIG. Processing other than step 5004 is the same as that in the first embodiment described above.

以上に説明したように、本発明の第三の実施例では、実績未管理時間において欠落している作業実績を推定できる。特に、ある拠点及び期間において複数人が同時に行う作業(昼休み、朝礼など)を推定できる。   As described above, in the third embodiment of the present invention, it is possible to estimate the work results that are missing in the result unmanaged time. In particular, it is possible to estimate the work (lunch break, morning meeting, etc.) performed by a plurality of people at a certain base and period.

<第四の実施例>
本発明の第四の実施例では、利用者のリクエストに応じて、ある拠点及び期間における全作業者の実績未管理時間の作業を実績未管理時間の発生パターンから推定する。これによって作業の発生パターン(作業者人数、時系列などの特徴)に特徴がある作業を推定できる。
<Fourth embodiment>
In the fourth embodiment of the present invention, in response to a user's request, the work of the actual unmanaged time of all workers at a certain base and period is estimated from the occurrence pattern of the actual unmanaged time. As a result, it is possible to estimate a work having a feature in a work generation pattern (features such as the number of workers and time series).

なお、第四の実施例では、第一の実施例と同じ構成及び機能には同じ符号を付し、それらの説明は省略する。例えば、第四の実施例のシステムは、図1Aに示す第一の実施例のシステムと同じでよい。   Note that in the fourth embodiment, the same reference numerals are given to the same configurations and functions as those in the first embodiment, and description thereof will be omitted. For example, the system of the fourth embodiment may be the same as the system of the first embodiment shown in FIG. 1A.

また、第四の実施例の処理手順は、図5に示す第一の実施例と同様であるが、作業推定確率モデル生成処理(5004)が第一の実施例と異なる。図21を参照して、第四の実施例の作業推定確率モデル生成処理を説明する。   The processing procedure of the fourth embodiment is the same as that of the first embodiment shown in FIG. 5, but the work estimation probability model generation process (5004) is different from that of the first embodiment. With reference to FIG. 21, the work estimation probability model generation processing of the fourth embodiment will be described.

まず、作業推定確率モデル生成部1204は、実績未管理時間属性から一つ以上の属性データを選択し、実績未管理時間分類属性に設定する。そして、設定された実績未管理時間分類属性に基づいて各実績未管理時間を分類し、属性が共通するグループを作成する(21001)。   First, the work estimation probability model generation unit 1204 selects one or more attribute data from the actual unmanaged time attribute and sets it as the actual unmanaged time classification attribute. Then, each actual unmanaged time is classified based on the set actual unmanaged time classification attribute, and a group having a common attribute is created (21001).

次に、作業推定確率モデル生成部1204は、グループの発生パターンAを生成する(21002)。発生パターンAは、一人又は複数の作業者において時系列上で実績未管理時間が発生する特徴を指し、例えば、ある一定の時間間隔で繰り返し実績未管理時間が発生している場合や、複数人の作業者で時刻をずらして交代で実績未管理時間が発生している場合等である。複数の発生パターンAを生成してもよい。   Next, the work estimation probability model generation unit 1204 generates a group generation pattern A (21002). Occurrence pattern A refers to the characteristic that actual unmanaged time occurs on a time series in one or a plurality of workers. For example, when there is repeated actual unmanaged time at a certain time interval, This is a case where the actual unmanaged time is generated by changing the time by shifting the time. A plurality of generation patterns A may be generated.

そして、実績未管理時間分類属性と属性が一致する、全ての拠点の作業実績データ及び当該作業実績データに関連する作業関連データ及び拠点データを取得する。そして、取得した作業実績データから各作業の発生パターンBを生成する(21003)。発生パターンBは発生パターンAと同様に、一人又は複数作業者において時系列上で実績未管理時間が発生する特徴を指す。複数の発生パターンBを生成してもよい。   And the work related data and base data relevant to the work performance data of all bases and the said work performance data whose attributes and attributes match the actual unmanaged time classification attribute are acquired. Then, an occurrence pattern B of each work is generated from the acquired work performance data (21003). Similar to the occurrence pattern A, the occurrence pattern B refers to a feature in which an actual unmanaged time occurs on a time series in one or a plurality of workers. A plurality of generation patterns B may be generated.

その後、発生パターンAと発生パターンBとを照合し、作業推定確率モデルを生成する(21004)。   Thereafter, the occurrence pattern A and the occurrence pattern B are collated to generate a work estimation probability model (21004).

作業推定確率モデルでは、図22に例示するように、実績未管理時間分類属性(時間帯、共起情報)に対応して、発生パターンごとに推定される作業及び推定される確率が定められる。具体的には、実績未管理時間分類結果の分類ごとに、実績未管理時間発生時間帯に行われていた作業を抽出し、共起情報によって分類して、作業推定確率モデルに推定作業を記録する。さらに、分類属性及び推定される作業の組み合わせごとに抽出された数を集計して、抽出された全推定作業の数で除した値を、当該作業の推定確率として記録する。   In the work estimation probability model, as illustrated in FIG. 22, the work to be estimated and the probability to be estimated are determined for each occurrence pattern corresponding to the actual unmanaged time classification attribute (time zone, co-occurrence information). Specifically, for each classification of the actual unmanaged time classification result, the work that was performed during the actual unmanaged time generation time zone is extracted, classified by co-occurrence information, and the estimated work is recorded in the work estimation probability model To do. Further, the number extracted for each combination of the classification attribute and the estimated work is totaled, and the value divided by the number of all the estimated work extracted is recorded as the estimated probability of the work.

なお、全ての拠点の作業実績データではなく、分析対象の拠点と類似している拠点(特に、時系列上での作業順序が類似している拠点)のデータを取得してもよく、全ての作業を含むモデル拠点のデータを取得してもよい。モデル拠点は、現実に作業者が作業を行っている拠点でも、作業がシミュレーションされた仮想の拠点でもよい。   In addition, it is possible to obtain the data of the bases that are similar to the bases to be analyzed (especially the bases that have similar work order in time series) instead of the actual work data of all bases. You may acquire the data of the model base including work. The model base may be a base where the worker is actually working, or a virtual base where the work is simulated.

次に、作業推定確率モデル生成部1204は、作成した作業推定確率モデルに問題があるかを判定する(21005)。作成した作業推定確率モデルに問題がある場合、不適切な実績未管理時間分類属性を用いて実績未管理時間を分類したので、実績未管理時間分類属性を再設定し(21006)、ステップ21001に戻る。   Next, the work estimation probability model generation unit 1204 determines whether there is a problem with the created work estimation probability model (21005). If there is a problem with the created work estimation probability model, since the actual unmanaged time is classified using an inappropriate actual unmanaged time classification attribute, the actual unmanaged time classification attribute is reset (21006), and step 21001 is entered. Return.

例えば、属性の指定が大まかである場合は、発生パターンBに対応する(一致又は類似する)作業実績データが多くなり、作業推定確率モデルの各推定結果の推定確率が大きくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を増やすとよい(例えば、時間帯及び共起を属性に設定していた場合、さらに作業者の役割を追加する等)。一方、属性の指定が細かい場合は、発生パターンBに対応する(一致又は類似する)作業実績データが少なくなり(又は、存在しない)、作業推定確率モデルの各推定結果の推定確率が小さくなる。この場合、作業推定確率モデルの信頼性が低く、作業推定確率モデルに問題があると判定されるので、実績未管理時間分類属性の項目数を減らすとよい。   For example, when the designation of the attribute is rough, the work result data corresponding to (matching or similar to) the occurrence pattern B increases, and the estimation probability of each estimation result of the work estimation probability model increases. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, it is preferable to increase the number of items of the actual unmanaged time classification attribute (for example, attribute the time zone and co-occurrence to the attribute). If it was set to, add the role of the worker, etc.). On the other hand, when the attribute designation is fine, the work performance data corresponding to the occurrence pattern B (matching or similar) is reduced (or does not exist), and the estimation probability of each estimation result of the work estimation probability model is reduced. In this case, since the reliability of the work estimation probability model is low and it is determined that there is a problem with the work estimation probability model, the number of items of the actual unmanaged time classification attribute may be reduced.

なお、所定回数試行しても作業推定確率モデルに問題があると判定される場合、有用な作業推定確率モデルが生成できなかったエラーを利用者に通知して、処理を終了してもよい。   If it is determined that there is a problem with the work estimation probability model after a predetermined number of trials, the user may be notified of an error that a useful work estimation probability model could not be generated, and the process may be terminated.

一方、作成した作業推定確率モデルに問題がない場合、作業推定確率モデル生成処理を終了し、図5のステップ5005へ進む。ステップ5004以外の処理は、前述した第一の実施例と同じである。   On the other hand, if there is no problem in the created work estimation probability model, the work estimation probability model generation process is terminated, and the process proceeds to step 5005 in FIG. Processing other than step 5004 is the same as that in the first embodiment described above.

以上に説明したように、本発明の第四の実施例では、実績未管理時間において欠落している作業実績を推定できる。特に、特定のパターン(時系列や作業者人数などの特徴)で作業が発生する作業を的確に推定できる。   As described above, in the fourth embodiment of the present invention, it is possible to estimate the work results that are missing in the result unmanaged time. In particular, it is possible to accurately estimate the work that occurs in a specific pattern (characteristics such as time series and the number of workers).

<第五の実施例>
本発明の第五の実施例では、各拠点において行われた作業の実績が作業実績データベース1101に格納されると、各実施例の推定処理を逐次実行し、推定された実績未管理時間の作業を作業実績データベース1101に格納する。これにより実績未管理時間が発生した際にアラームを報知し、その場で現場管理者や作業者の記憶が薄れないうちに実績を入力させ、実績未管理時間を減少できる。
<Fifth embodiment>
In the fifth embodiment of the present invention, when the results of the work performed at each base are stored in the work performance database 1101, the estimation process of each embodiment is sequentially executed, and the work of the estimated actual unmanaged time is performed. Is stored in the work performance database 1101. As a result, an alarm is notified when the actual unmanaged time occurs, and the actual unmanaged time can be reduced by inputting the actual result before the memory of the site manager and the worker is not lost on the spot.

なお、第四の実施例では、第一の実施例と同じ構成及び機能には同じ符号を付し、それらの説明は省略する。例えば、第五の実施例のシステムは、図1Aに示す第一の実施例のシステムと同じでよい。   Note that in the fourth embodiment, the same reference numerals are given to the same configurations and functions as those in the first embodiment, and description thereof will be omitted. For example, the system of the fifth embodiment may be the same as the system of the first embodiment shown in FIG. 1A.

図23は、第五の実施例の処理手順のフローチャートである。図23に示す処理は、計算サーバ1200のプロセッサ1が実行する。   FIG. 23 is a flowchart of the processing procedure of the fifth embodiment. The processing illustrated in FIG. 23 is executed by the processor 1 of the calculation server 1200.

まず、実績情報取得部1201は、分析リクエストと分析の条件(対象拠点・期間等)を受信する(23001)。第五の実施例では、分析リクエストは、作業実績データが生成されたタイミングで生成される。作業実績データの生成タイミングごとに分析をすると、実績未管理時間の発生をリアルタイムで分析できる。また、分析リクエストは、予め定められたタイミング(例えば、所定の時間間隔)で繰り返し生成されてもよい。所定のタイミングで分析をすると、例えば、前1時間における実績未管理時間の発生を遅滞なく分析できる。また、分析リクエストに含まれる分析の条件は、分析対象の拠点、期間(例えば、前回分析した後の期間)、作業者などである。   First, the record information acquisition unit 1201 receives an analysis request and analysis conditions (target base / period, etc.) (23001). In the fifth embodiment, the analysis request is generated at the timing when the work result data is generated. If analysis is performed for each generation timing of work result data, it is possible to analyze the occurrence of unmanaged time in real time. The analysis request may be repeatedly generated at a predetermined timing (for example, a predetermined time interval). If the analysis is performed at a predetermined timing, for example, the occurrence of the actual unmanaged time in the previous hour can be analyzed without delay. Further, the analysis conditions included in the analysis request are a base to be analyzed, a period (for example, a period after the previous analysis), an operator, and the like.

ステップ23002〜23003の処理は、ステップ5002〜5003と同じなので、説明を省略する。   Since the processing in steps 23002 to 23003 is the same as that in steps 5002 to 5003, the description thereof is omitted.

その後、実績未管理時間算出部1202は、ステップ23003において実績未管理時間が算出されたかを判定する。実績未管理時間が算出されていない場合、実績未管理時間発生のアラームを報知する必要がないので、処理を終了する。一方、実績未管理時間が算出された場合、作業推定確率モデル生成部1204は、実績未管理時間分類属性を設定し、実績未管理時間分類属性と一致する属性を有する作業実績データから作業推定確率モデルを生成する(23005)。   Thereafter, the actual unmanaged time calculation unit 1202 determines whether the actual unmanaged time has been calculated in Step 23003. If the actual unmanaged time has not been calculated, it is not necessary to notify an alarm indicating that the actual unmanaged time has occurred, and thus the process ends. On the other hand, when the actual unmanaged time is calculated, the work estimated probability model generation unit 1204 sets the actual unmanaged time classification attribute, and the estimated work probability from the actual work data having an attribute that matches the actual unmanaged time classification attribute. A model is generated (23005).

ステップ23005〜23009の処理は、ステップ5004〜5008と同じなので、説明を省略する。また、作業推定確率モデル生成処理(23005)は、前述したいずれの実施例の処理でもよい。   Since the processing in steps 23005 to 23209 is the same as that in steps 5004 to 5008, description thereof will be omitted. Further, the work estimation probability model generation process (23005) may be the process of any of the embodiments described above.

以上に説明したように、本発明の第五の実施例では、実績未管理時間の作業を遅滞なく作業実績データベース1101に格納でき、実績未管理時間を減少できる。   As described above, in the fifth embodiment of the present invention, the work of the actual unmanaged time can be stored in the work actual result database 1101 without delay, and the actual unmanaged time can be reduced.

なお、以上に説明した各実施例において、実績未管理時間に複数の作業を推定してもよい。例えば、前作業と後作業との間の中間作業として、複数の作業の組を推定作業として含む作業推定確率モデルを作成するとよい。また、実績未管理時間に一つの作業を推定して、推定された作業の標準的な作業時間を当該実績未管理時間に当てはめても実績未管理時間がある場合、さらなる実績未管理時間に作業を推定してもよい。   In each of the embodiments described above, a plurality of operations may be estimated during the actual unmanaged time. For example, a work estimation probability model including a plurality of work sets as estimation work may be created as an intermediate work between the previous work and the back work. In addition, if one work is estimated at the actual unmanaged time and the standard work time of the estimated work is applied to the actual unmanaged time, but there is an actual unmanaged time, the work is performed at the further actual unmanaged time. May be estimated.

なお、本発明は前述した実施例に限定されるものではなく、添付した特許請求の範囲の趣旨内における様々な変形例及び同等の構成が含まれる。例えば、前述した実施例は本発明を分かりやすく説明するために詳細に説明したものであり、必ずしも説明した全ての構成を備えるものに本発明は限定されない。また、ある実施例の構成の一部を他の実施例の構成に置き換えてもよい。また、ある実施例の構成に他の実施例の構成を加えてもよい。また、各実施例の構成の一部について、他の構成の追加・削除・置換をしてもよい。   The present invention is not limited to the above-described embodiments, and includes various modifications and equivalent configurations within the scope of the appended claims. For example, the above-described embodiments have been described in detail for easy understanding of the present invention, and the present invention is not necessarily limited to those having all the configurations described. A part of the configuration of one embodiment may be replaced with the configuration of another embodiment. Moreover, you may add the structure of another Example to the structure of a certain Example. In addition, for a part of the configuration of each embodiment, another configuration may be added, deleted, or replaced.

また、前述した各構成、機能、処理部、処理手段等は、それらの一部又は全部を、例えば集積回路で設計する等により、ハードウェアで実現してもよく、プロセッサがそれぞれの機能を実現するプログラムを解釈し実行することにより、ソフトウェアで実現してもよい。   In addition, each of the above-described configurations, functions, processing units, processing means, etc. may be realized in hardware by designing a part or all of them, for example, with an integrated circuit, and the processor realizes each function. It may be realized by software by interpreting and executing the program to be executed.

各機能を実現するプログラム、テーブル、ファイル等の情報は、メモリ、ハードディスク、SSD(Solid State Drive)等の記憶装置、又は、ICカード、SDカード、DVD等の記録媒体に格納することができる。   Information such as programs, tables, and files that realize each function can be stored in a storage device such as a memory, a hard disk, and an SSD (Solid State Drive), or a recording medium such as an IC card, an SD card, and a DVD.

また、制御線や情報線は説明上必要と考えられるものを示しており、実装上必要な全ての制御線や情報線を示しているとは限らない。実際には、ほとんど全ての構成が相互に接続されていると考えてよい。   In addition, the control lines and the information lines indicate what is considered necessary for the explanation, and do not necessarily indicate all the control lines and information lines necessary for the mounting. In practice, it can be considered that almost all the components are connected to each other.

Claims (14)

分析システムであって、
プログラムを実行するプロセッサと、前記プロセッサがアクセスする記憶装置とを備え、
分析対象の作業実績を含む第一の作業実績データを取得する取得部と、
作業実績が記録されていない実績未管理時間を、前記第一の作業実績データから抽出し、前記抽出された実績未管理時間の属性情報を取得する算出部と、
前記取得した属性情報を用いて、前記実績未管理時間を分類するための実績未管理時間分類属性を生成する分類部と、
分析対象でない作業実績を含む第二の作業実績データを取得し、前記生成された実績未管理時間分類属性に従って前記第二の作業実績データを分類し、実績未管理時間分類属性ごとに作業を推定するための確率モデルを生成するモデル生成部と、を有し、
前記分類部は、前記生成された確率モデルを用いて前記第一の作業実績データを分析し、前記第一の作業実績データに含まれる実績未管理時間における作業を推定することを特徴とする分析システム。
An analysis system,
A processor that executes a program; and a storage device that is accessed by the processor;
An acquisition unit for acquiring first work result data including work results to be analyzed;
A calculation unit that extracts the result unmanaged time in which the work result is not recorded from the first work result data, and acquires attribute information of the extracted result unmanaged time;
Using the acquired attribute information, a classification unit that generates an actual unmanaged time classification attribute for classifying the actual unmanaged time;
Acquire second work result data including work results that are not the subject of analysis, classify the second work result data according to the generated result unmanaged time classification attribute, and estimate work for each result unmanaged time classification attribute A model generation unit for generating a probability model for
The classification unit analyzes the first work performance data using the generated probability model, and estimates work in the actual unmanaged time included in the first work performance data system.
請求項1に記載の分析システムであって、
前記分類部は、作業実績が記録されていない時間の前後で作業者が行っていた作業に基づいて生成された確率モデルを用いて、実績未管理時間の作業を推定することを特徴とする分析システム。
The analysis system according to claim 1,
The classification unit estimates work in actual unmanaged time using a probabilistic model generated based on work performed by an operator before and after the time when no actual work is recorded. system.
請求項1に記載の分析システムであって、
前記分類部は、実績未管理時間を含む時間帯における他の作業実績データに基づいて生成された確率モデルを用いて、実績未管理時間の作業を推定することを特徴とする分析システム。
The analysis system according to claim 1,
The said classification | category part estimates the operation | work of performance unmanaged time using the probability model produced | generated based on the other work performance data in the time slot | zone including performance unmanaged time.
請求項1に記載の分析システムであって、
前記分類部は、実績未管理時間の出現パターンに基づいて生成された確率モデルを用いて、実績未管理時間の作業を推定することを特徴とする分析システム。
The analysis system according to claim 1,
The classification system estimates an operation of actual unmanaged time using a probability model generated based on an appearance pattern of actual unmanaged time.
請求項1に記載の分析システムであって、
作業実績データと実績未管理時間における推定された作業の情報とを用いて、作業者の作業内容を、作業実績データであるか推定された作業の情報であるかを区別可能に表示するためのデータを出力する可視化部を有することを特徴とする分析システム。
The analysis system according to claim 1,
Using the work performance data and information on the estimated work in the actual unmanaged time, the work content of the worker is displayed so that it can be distinguished whether it is work performance data or estimated work information. An analysis system comprising a visualization unit for outputting data.
請求項5に記載の分析システムであって、
前記可視化部は、前記推定された作業の情報を修正する入力欄を有する表示データを出力し、利用者が入力したデータを受け、
前記分類部は、前記利用者が入力したデータを用いて前記推定された作業の情報を修正することを特徴とする分析システム。
The analysis system according to claim 5,
The visualization unit outputs display data having an input field for correcting the estimated work information, receives data input by a user,
The classification system corrects information of the estimated work using data inputted by the user.
請求項1に記載の分析システムであって、
前記モデル生成部は、生成した確率モデルに問題がある場合、実績未管理時間分類属性を再設定して確率モデルを生成することを特徴とする分析システム。
The analysis system according to claim 1,
The model generation unit generates a probability model by resetting an actual unmanaged time classification attribute when there is a problem with the generated probability model.
計算機が実行する分析方法であって、
前記計算機は、プログラムを実行するプロセッサと、前記プロセッサがアクセスする記憶装置とを有し、
前記分析方法は、
前記プロセッサが、分析対象の作業実績を含む第一の作業実績データを取得する取得手順と、
前記プロセッサが、作業実績が記録されていない実績未管理時間を、前記第一の作業実績データから抽出し、前記抽出された実績未管理時間の属性情報を取得する算出手順と、
前記プロセッサが、前記取得した属性情報を用いて、前記実績未管理時間を分類するための実績未管理時間分類属性を生成する分類手順と、
前記プロセッサが、分析対象でない作業実績を含む第二の作業実績データを取得し、前記生成された実績未管理時間分類属性に従って前記第二の作業実績データを分類し、実績未管理時間分類属性ごとに作業を推定するための確率モデルを生成するモデル生成手順と、を含み、
前記分類手順では、前記プロセッサは、前記生成された確率モデルを用いて前記第一の作業実績データを分析し、前記第一の作業実績データに含まれる実績未管理時間における作業を推定することを特徴とする分析方法。
An analysis method executed by a computer,
The computer includes a processor that executes a program, and a storage device that is accessed by the processor.
The analysis method is:
An acquisition procedure in which the processor acquires first work result data including a work result to be analyzed;
The processor extracts a result unmanaged time in which no work record is recorded from the first work record data, and obtains attribute information of the extracted record unmanaged time,
A classification procedure in which the processor generates an actual unmanaged time classification attribute for classifying the actual unmanaged time using the acquired attribute information;
The processor acquires second work result data including work results that are not analyzed, classifies the second work result data according to the generated result unmanaged time classification attribute, and records each result unmanaged time classification attribute. A model generation procedure for generating a probabilistic model for estimating work,
In the classification procedure, the processor analyzes the first work performance data using the generated probability model, and estimates the work in the actual unmanaged time included in the first work performance data. Characteristic analysis method.
請求項8に記載の分析方法であって、
前記分類手順では、前記プロセッサは、作業実績が記録されていない時間の前後で作業者が行っていた作業に基づいて生成された確率モデルを用いて、実績未管理時間における作業を推定することを特徴とする分析方法。
The analysis method according to claim 8, comprising:
In the classification procedure, the processor estimates the work in the actual unmanaged time using a probability model generated based on the work performed by the worker before and after the time when the work performance is not recorded. Characteristic analysis method.
請求項8に記載の分析方法であって、
前記分類手順では、前記プロセッサは、実績未管理時間を含む時間帯における他の作業実績データに基づいて生成された確率モデルを用いて、実績未管理時間の作業を推定することを特徴とする分析方法。
The analysis method according to claim 8, comprising:
In the classification procedure, the processor estimates work in actual unmanaged time using a probability model generated based on other actual work data in a time zone including actual unmanaged time. Method.
請求項8に記載の分析方法であって、
前記分類手順では、前記プロセッサは、実績未管理時間の出現パターンに基づいて生成された確率モデルを用いて、実績未管理時間の作業を推定することを特徴とする分析方法。
The analysis method according to claim 8, comprising:
In the classification procedure, the processor estimates a work in actual unmanaged time using a probability model generated based on an appearance pattern of actual unmanaged time.
請求項8に記載の分析方法であって、
前記プロセッサが、作業実績データと実績未管理時間における推定された作業の情報とを用いて、作業者の作業内容を、作業実績データであるか推定された作業の情報であるかを区別可能に表示するためのデータを出力する可視化手順を含むことを特徴とする分析方法。
The analysis method according to claim 8, comprising:
The processor can distinguish whether the worker's work content is work result data or estimated work information by using work result data and information of the estimated work in the result unmanaged time. An analysis method comprising a visualization procedure for outputting data for display.
請求項12に記載の分析方法であって、
前記可視化手順では、前記プロセッサは、前記推定された作業の情報を修正する入力欄を有する表示データを出力し、利用者が入力したデータを受け、
前記分類手順では、前記プロセッサは、前記利用者が入力したデータを用いて前記推定された作業の情報を修正することを特徴とする分析方法。
The analysis method according to claim 12, comprising:
In the visualization procedure, the processor outputs display data having an input field for correcting the information of the estimated work, receives data input by a user,
In the classification procedure, the processor modifies the estimated work information using data input by the user.
請求項8に記載の分析方法であって、
前記モデル生成手順では、前記プロセッサは、生成した確率モデルに問題がある場合、実績未管理時間分類属性を再設定して確率モデルを生成することを特徴とする分析方法。
The analysis method according to claim 8, comprising:
In the model generation procedure, when there is a problem in the generated probability model, the processor generates a probability model by resetting an actual unmanaged time classification attribute.
JP2018536658A 2016-09-05 2016-09-05 Analysis system and analysis method Active JP6594555B2 (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/JP2016/075951 WO2018042646A1 (en) 2016-09-05 2016-09-05 Analysis system and analysis method

Publications (2)

Publication Number Publication Date
JPWO2018042646A1 JPWO2018042646A1 (en) 2018-11-15
JP6594555B2 true JP6594555B2 (en) 2019-10-23

Family

ID=61300428

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018536658A Active JP6594555B2 (en) 2016-09-05 2016-09-05 Analysis system and analysis method

Country Status (2)

Country Link
JP (1) JP6594555B2 (en)
WO (1) WO2018042646A1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7458300B2 (en) 2020-11-09 2024-03-29 ヤンマーホールディングス株式会社 Work information management system, work information management program, and work information management method
JP2022135135A (en) * 2021-03-04 2022-09-15 株式会社モノフル Method, program, device, and system
JPWO2022209082A1 (en) * 2021-04-02 2022-10-06

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5830780B2 (en) * 2011-12-02 2015-12-09 株式会社日立製作所 Business analysis apparatus, business analysis system, and business analysis method

Also Published As

Publication number Publication date
WO2018042646A1 (en) 2018-03-08
JPWO2018042646A1 (en) 2018-11-15

Similar Documents

Publication Publication Date Title
US10439922B2 (en) Service analyzer interface
US20190391863A1 (en) Artificial Creation Of Dominant Sequences That Are Representative Of Logged Events
US9448908B2 (en) System and method for model based session management
US20200233736A1 (en) Enabling symptom verification
US9424157B2 (en) Early detection of failing computers
US9904517B2 (en) System and method for automatic modeling of an application
WO2014143279A1 (en) Bottleneck detector for executing applications
US9870279B2 (en) Analysis apparatus and analysis method
JP6216873B2 (en) Search method and apparatus, and storage medium
EP2686771B1 (en) Usability testing
JP6594555B2 (en) Analysis system and analysis method
JP6995843B2 (en) Work management system and work management method
CN103069749A (en) Isolation of problems in a virtual environment
US11113137B2 (en) Error incident fingerprinting with unique static identifiers
US20080126283A1 (en) Method of capturing Problem Resolution for Subsequent Use in Managed Distributed Computer Systems
JP5312742B2 (en) Audit and track data and code changes in spreadsheets and other documents
JP7235110B2 (en) Operation log acquisition device, operation log acquisition method, and operation log acquisition program
WO2009136529A1 (en) Work process management device, work process management method, and work process management program
KR20210069215A (en) The user interface method for optimalizing bigdata analysis
JP5825915B2 (en) Work man-hour calculating device, work man-hour calculating method, and program
JP6845657B2 (en) Management server, management method and its program
JP2012108708A (en) Failure detection device, information processing method, and program
US9928152B2 (en) Computer implemented system and method to non-intrusive sensing and instrumentation of work process
JP2008191849A (en) Operation management device, information processor, control method for operation management device, control method for information processor and program
US20160378285A1 (en) Automatic Detection of Semantics

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180727

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190903

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190924

R150 Certificate of patent or registration of utility model

Ref document number: 6594555

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533