JP6510690B1 - Construction method of underground structure - Google Patents

Construction method of underground structure Download PDF

Info

Publication number
JP6510690B1
JP6510690B1 JP2018028410A JP2018028410A JP6510690B1 JP 6510690 B1 JP6510690 B1 JP 6510690B1 JP 2018028410 A JP2018028410 A JP 2018028410A JP 2018028410 A JP2018028410 A JP 2018028410A JP 6510690 B1 JP6510690 B1 JP 6510690B1
Authority
JP
Japan
Prior art keywords
box
pit
roof
construction method
underground structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018028410A
Other languages
Japanese (ja)
Other versions
JP2019143362A (en
Inventor
植村 誠
誠 植村
賢治郎 植村
賢治郎 植村
丸田 新市
新市 丸田
智哉 中村
智哉 中村
Original Assignee
植村 誠
誠 植村
賢治郎 植村
賢治郎 植村
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 植村 誠, 誠 植村, 賢治郎 植村, 賢治郎 植村 filed Critical 植村 誠
Priority to JP2018028410A priority Critical patent/JP6510690B1/en
Application granted granted Critical
Publication of JP6510690B1 publication Critical patent/JP6510690B1/en
Publication of JP2019143362A publication Critical patent/JP2019143362A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

【課題】発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱形ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、到達坑を極力小さいものとする地下構造物の施工方法を提供する。【解決手段】函体を発進坑3に設置する前に、箱形ルーフ6を組み配置した内部の土砂の中を、管体23を発進坑と到達坑4側間に貫通させ、発進坑に設置した函体の推進とともに箱形ルーフ、その内部の土砂および管体を到達側に押し出すとともに、これら到達坑側に押し出す前記箱形ルーフ、土砂、管体は順次解体して、この解体物は管体および函体の内部を発進坑へと搬送し、発進坑から地上に搬出する。【選択図】図7To assemble a box-shaped roof so as to correspond to the outer shape of a box to be propelled from a starting pit to a reaching pit and press-in the ground from the starting pit or the reaching pit, and then the box-shaped roof In the construction method of the underground structure which arranges the box body at the end and pushes the earth and sand inside the box roof assembled together with the box roof with the promotion of the box, the underground structure which makes the reaching pit as small as possible Provide the construction method of the object. SOLUTION: Before installing a box in the start pit 3, the pipe body 23 is penetrated between the start pit and the reach pit 4 in the inside of the earth and sand in which the boxed roof 6 is arranged, The boxed roof, the earth and sand and the pipe inside thereof are pushed out to the arrival side with the promotion of the installed box body, and the boxed roof, the earth and sand, the pipe pushed out to the arrival pit side are disassembled one by one. Transport the inside of the tube and box to the start pit and carry it out from the start pit to the ground. [Selected figure] Figure 7

Description

本発明は、鉄道、道路などの下部地中に大幅員の地下構造物を横断方向に掘進建設する際に上部交通に支障を与えることなく施工することができる地下構造物の施工法に関するものである。   The present invention relates to a construction method of an underground structure which can be constructed without obstructing the upper traffic when a large member of the underground structure is constructed in a cross direction in a lower ground such as a railway or a road. is there.

鉄道、道路などの下部地中に大幅員の地下構造物を横断方向に掘進させるには、上部交通を支承するための防護工が必要となり、管体等を水平に並列させるパイプルーフを設けることなどがあげられる。   In order to extend a large member underground structure transversely into the lower ground such as railways and roads, a protective structure is required to support upper traffic, and a pipe roof should be provided to horizontally align pipes etc. Etc.

しかし、先に別工事としてパイプルーフを形成し、その下や中を掘削して地下構造物を構築し、また地下構造物をパイプルーフ下に掘進させるようにしたのでは、このパイプルーフが存在する分だけ土被りが厚くなる。しかも、パイプルーフ施工の防護工が地下構造物埋設の本工事と別工事となり、工費、工期が大である。   However, if a pipe roof was first formed as a separate construction, and the underground structure was constructed by excavating under and inside the pipe roof, and this underground structure would be excavated under the pipe roof, this pipe roof exists The amount of soiling increases by the amount of Moreover, the protection work of the pipe roof construction is a separate work from the main construction of underground structure burial, and the construction cost and construction period are large.

かかる不都合を解消するものとして、本発明者等は、下記特許文献に示すように箱形ルーフを圧入後、コンクリート函体を推進させる場合、函体の推進とともに切羽部の土砂を箱形ルーフと一緒に押し出すので、切羽部を掘削する作業を別途必要とせず、コスト削減と工期短縮を図ることができ、また、危険を伴う切羽部の掘削作業を省くことで安全性も向上でき、しかも、函体を推進するための反力抵抗を分散することで、大掛かりな設備を必要としない地下構造物の施工法を出願し、特許権を取得した。
日本国 特許第4134089号公報 日本国 特許第4317843号公報 日本国 特許第3887383号公報
In order to eliminate this disadvantage, the inventors of the present invention, as described in the following patent document, press-in the box-shaped roof and then promote the concrete box, the soil in the face portion of the cutting face is Since it is extruded together, it is possible to reduce costs and shorten the construction period without separately needing a drilling operation for the face portion, and also to improve the safety by omitting the drilling operation for the face portion with danger, By distributing reaction force resistance for propelling a box, we applied for the construction method of the underground structure which does not need a large-scale equipment, and obtained the patent right.
Japan Patent No. 4134089 Japan Patent No. 4317843 Japan Patent No. 3887 383

この工法はSFT工法と名付けられ、下記非特許文献1にも掲載されている。なお、SFT工法は、(Simple and Face-Less Method of Construction of Tunnel)は、「シンプルで切羽の無いトンネルの構築工法」の略称である。
インターネットウエブサイトの植村技研工業株式会社のホームページ http://www.uemuragiken.co.jp/tech/sft.html
This method is named as the SFT method and is also described in the following Non-Patent Document 1. In addition, SFT method (Simple and Face-Less Method of Construction of Tunnel) is an abbreviation of "construction method of a simple and faceless tunnel".
The website of Uemura Giken Kogyo Co., Ltd. on the Internet website http://www.uemuragiken.co.jp/tech/sft.html

SFT工法は、第1工程として図20に示すように鉄道などの上部交通(図示は省略した)の脇に土留鋼矢板2を打設して、発進坑3と到達坑4を築造し、前記発進坑3内に推進機5を設置してこれでルーフ用筒体である箱形ルーフ6を到達坑4に向けて圧入させる。箱形ルーフ6の上面にはフリクションカッタープレート7を載せて置き、箱形ルーフ6とともに押出す。   In the SFT method, as shown in FIG. 20 as the first step, the retaining steel sheet pile 2 is placed beside the upper traffic (not shown) such as a railway to build the start pit 3 and the reach pit 4 The propulsion unit 5 is installed in the start pit 3, and the box-shaped roof 6, which is a roof cylinder, is then pressed into the arrival pit 4. The friction cutter plate 7 is placed on the upper surface of the box-shaped roof 6 and extruded together with the box-shaped roof 6.

箱形ルーフ6は、図24に示すように矩形断面の箱形筒体であり、側面に鉤状または平板状の継手6a,6bを長手方向に連続して形成し、また、上面に平板からなるフリクションカッタープレート7を取り付けている。箱形ルーフ6は前後端にボルト接合用のフランジを形成して、長さ方向に順次接続して必要長を埋設することができ、さらに継手6a,6bを介して縦横方向に連続しながら並列させる。   The box-like roof 6 is a box-like cylinder having a rectangular cross section as shown in FIG. 24. The wedge-like or flat joints 6a and 6b are continuously formed on the side in the longitudinal direction, and The friction cutter plate 7 is attached. The box-like roof 6 is formed with flanges for bolt connection at the front and rear ends, and can be sequentially connected in the length direction to embed the required length, and further parallel connection is continued in the vertical and horizontal directions via the joints 6a and 6b Let

推進機5の詳細図示は省略するが、土砂排土管を押出し体として元押しジャッキで押し出すことにより箱形ルーフ6を掘進させるもので、箱形ルーフ6の先端切羽の掘削は、人力掘削刃口を設けて行なう場合の他、オーガスクリューなどの掘削機構を設けて行なう場合などがある。   Although the detailed illustration of the propulsion unit 5 is omitted, the earth-and-sand discharge pipe is pushed out with a pushing jack as an extrusion body and the box-shaped roof 6 is excavated. There is a case where an excavating mechanism such as an auger screw is provided, in addition to the case of providing the

箱形ルーフ6は推進させようとするコンクリート函体9の外形に対応するように四角形状に配列設置し、箱形ルーフ6の配列で囲まれた切羽部には土留部材19を配設する。   The box-like roof 6 is arranged in a rectangular shape so as to correspond to the outer shape of the concrete box 9 to be promoted, and the earth retaining member 19 is arranged in the face portion surrounded by the arrangement of the box-like roof 6.

図中17は腹起こし材、発進坑3側の土留鋼矢板2と到達坑4側の土留鋼矢板2を結合するタイロット材28で固定する。20は発進台を示す。   In the figure, 17 is fixed by a tie-lot material 28 which connects the uplifting material, the retained steel sheet pile 2 on the side of the starting pit 3 and the retained steel sheet pile 2 on the side of the reaching pit 4. 20 shows a starting platform.

次に第2工程の図21に示すようにコンクリート函体9を発進坑3に設置し、コンクリート函体9の後方の反力壁8との間に推進設備として元押しジャッキ10、ストラット16、井桁枠22を配設する。   Next, as shown in FIG. 21 of the second step, the concrete box 9 is installed in the start pit 3 and between the reaction wall 8 and the rear of the concrete box 9, the main push jack 10 and strut 16 The well frame 22 is disposed.

そして、止め部材14でフリクションカッタープレート7を発進坑3側に固定する。このフリクションカッタープレート7により箱形ルーフ6およびコンクリート函体9と周辺土砂との縁切りを行う。   Then, the friction cutter plate 7 is fixed to the start pit 3 side by the stop member 14. The friction cutter plate 7 cuts off the box roof 6 and the concrete box 9 from the surrounding soil.

次に先行して押出した箱形ルーフ6の後端にコンクリート函体9の先端を接合し、または当接させて、第3工程として図22に示すように元押しジャッキ10を伸長してコンクリート函体9を前方に押出す。   Next, the front end of the concrete box 9 is joined or abutted to the rear end of the box-shaped roof 6 that has been extruded in advance, and as shown in FIG. Push the box 9 forward.

コンクリート函体9の押出しと同時に箱形ルーフ6も押出し、さらに切羽部の掘削は行わず、箱形ルーフ6を押出すときに同時に箱形ルーフ6で囲まれた部分に配設した土留部材19を押出すことによりその前方の土砂も同時に押出す。この場合、前記のようにフリクションカッタープレート7により箱形ルーフ6およびコンクリート函体9と周辺土砂との縁切りがなされているから、箱形ルーフ6およびコンクリート函体9はスムーズに推進する。   A soil retaining member 19 disposed at the same time as extruding the box roof 6 at the same time as extruding the box roof 6 while extruding the box roof 6 simultaneously with the extrusion of the concrete box 9 The soil in front of it is also extruded simultaneously by extruding In this case, since the rim of the box-shaped roof 6 and the concrete box 9 and the surrounding earth and sand is made by the friction cutter plate 7 as described above, the box-shaped roof 6 and the concrete box 9 are smoothly propelled.

このようにして第4工程として図22に示すように箱形ルーフ6とこの箱形ルーフ6に囲まれて同時に押出された土砂が到達坑4に到達したならば、到達坑4で箱形ルーフ6を撤去すると同時に、土砂を掘削して排土する。   Thus, as shown in FIG. 22 as the fourth step, if the soil extruded simultaneously surrounded by the box-shaped roof 6 and the box-shaped roof 6 reaches the reaching pit 4, the box-shaped roof at the reaching pit 4 Remove the soil and excavate the soil at the same time as removing 6.

この撤去は図25に示すように到達坑4の内部において箱形ルーフ6を解体し、クレーン等で到達坑4の上方に引き上げるとともに、土砂もバックホー等のショベルで、到達坑4の上方に排出する。   As shown in FIG. 25, this removal dismantles the box-like roof 6 inside the reaching pit 4 and pulls it up above the reaching pit 4 with a crane etc., and also discharges the soil above the reaching pit 4 with a shovel such as a backhoe. Do.

そして、さらにコンクリート函体9の先端が到達坑4に達するまで推進してコンクリート函体9の全長の推進が完了する。(図26参照)   Then, the tip end of the concrete box 9 is further propelled until reaching the reaching pit 4 to complete the promotion of the full length of the concrete box 9. (See Figure 26)

前記SFT工法においては、到達坑4から箱形ルーフ6を撤去すると同時に、土砂を排土するものであり、到達坑4はそのための作業スペースの広さを確保する大きさを必要とする。   In the SFT method, the box roof 6 is removed from the reaching pit 4 and soil is removed at the same time, and the reaching pit 4 needs to have a size for securing a wide working space therefor.

これら箱形ルーフ6や土砂は、到達坑4の上方の開口から地上に引き上げられて撤去されるので、到達坑4は排出のための開口を備えた大きなものにならざるを得ない。   Since the boxed roof 6 and the soil are pulled up to the ground from the opening above the reaching pit 4 and removed, the reaching pit 4 must be a large one provided with an opening for discharge.

到達側に到達坑4の形成用の用地が充分確保できないときは、周辺環境・条件により到達側において排土ができない場合や到達坑4の長さに制限が生じ、重機が複数台設置できないことや施工ヤードが狭いか、もしくはないことになる。   When sufficient land for formation of the arrival pit 4 can not be secured on the arrival side, if the arrival side can not remove the soil due to the surrounding environment and conditions, or the length of the arrival pit 4 is limited, multiple heavy machinery can not be installed And the construction yard will be narrow or not.

本発明の目的は前記従来例の不都合を解消し、発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱形ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、到達坑を極力小さいものとすることができる地下構造物の施工法を提供することにある。   The object of the present invention is to eliminate the disadvantages of the prior art and construct a box-shaped roof so as to correspond to the outer shape of a box to be propelled from the starting pit to the reaching pit, and After press-in to the ground, a box is placed at the end of the box-like roof, and the construction method of the underground structure which pushes out the earth and sand of the interior where the box-like roof is assembled and arranged together with the box-like roof An object of the present invention is to provide a construction method of an underground structure which can make the reaching pit as small as possible.

前記目的を達成するため請求項1記載の本発明は、発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱形ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、函体を発進坑に設置する前に、箱形ルーフを組み配置した内部の土砂の中に管体を発進坑と到達坑側間に貫通させ、発進坑に設置した函体の推進とともに箱形ルーフ、その内部の土砂および管体を到達側に押し出すとともに、これら到達坑側に押し出す前記箱形ルーフ、土砂、管体は順次解体して、この解体物は管体および函体の内部を発進坑へと搬送し、発進坑から地上に搬出することを要旨とするものである。   In order to achieve the above object, the present invention according to claim 1 is characterized in that the box roof is assembled and arranged to correspond to the outer shape of the box to be propelled from the starting pit to the reaching pit. After pressing into the ground from the ground, a box is placed at the end of this boxy roof, and the construction method of the underground structure that pushes out the earth and sand inside the boxy roof assembled and arranged with the boxy roof together with the promotion of box. Before installing the box in the start pit, the tube is penetrated between the start pit and the reaching pit side in the inner soil in which the box-shaped roof is arranged, and with the promotion of the box set in the start pit The box roof, the earth and sand and the tube inside thereof are pushed out to the arrival side, and the box roof, the earth and sand, and the pipe pushed out to the arrival pit side are dismantled sequentially, Are transported to the start pit and unloaded from the start pit to the ground It is an gist of Rukoto.

請求項1記載の本発明によれば、発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱形ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、到達坑側に押し出す箱形ルーフ、土砂、管体は順次解体して、この解体物は管体および函体の内部を発進坑へと搬送し、発進坑から地上に搬出するので、到達側立坑を小さくできる。   According to the present invention as set forth in claim 1, the box-shaped roof is assembled and arranged to correspond to the outer shape of the box to be propelled from the starting pit to the reaching pit, and from the starting pit or the reaching pit to the ground. After press-fitting, a box is placed at the end of the box-shaped roof, and the construction method of the underground structure in which the earth and sand inside the box-shaped roof are assembled and arranged together with the box-shaped roof is arranged. The boxed roof, soil, and pipe are pushed out to the side, dismantled in order, and the dismantled material is transferred from inside the pipe and the box to the starting pit and carried out from the starting pit to the ground. it can.

さらに、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す場合に、箱形ルーフの矩形配列内方の土砂は管体の推進断面分減少させられているので、多くの土砂を押し出す必要がないので、その分推進もしくはけん引設備を小型にでき、施工の大断面・長延長化にも対応できるものとなる。   Furthermore, when pushing out the earth and sand inside the box-shaped roof assembled and arranged with the box-shaped roof together with the promotion of the box, the earth and sand inside the rectangular array of the box-shaped roof is reduced by the pushing section of the pipe Therefore, since it is not necessary to push out a lot of earth and sand, it is possible to miniaturize the promotion or traction equipment, and to cope with the large cross section and long extension of the construction.

以上述べたように本発明の地下構造物の施工法は、発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱型ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、到達坑を極力小さいものとすることができ、また、押し出す切羽部の土砂を予め減少させることで、推進もしくはけん引設備を小型にでき、施工の大断面・長延長化にも対応できるものである。   As described above, according to the construction method of the underground structure of the present invention, the box roof is assembled and arranged to correspond to the outer shape of the box to be promoted from the starting pit to the reaching pit, and the starting pit or reaching is reached. After press-in from the pit into the ground, place a box at the end of this box-shaped roof, and construct the box-shaped roof with the promotion of the box. In the law, the reach pit can be made as small as possible, and by reducing the earth and sand of the pushing face in advance, the propulsion or traction equipment can be made smaller, and the construction can be coped with the large cross section and long extension. It is a thing.

本発明の地下構造物の施工法の第1実施形態を示す第1工程の縦断側面図である。It is a vertical side view of the 1st process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第2工程の縦断側面図である。It is a vertical side view of the 2nd process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第3工程の縦断側面図である。It is a longitudinal side view of the 3rd process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第4工程の縦断側面図である。It is a longitudinal side view of the 4th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第5工程の縦断側面図である。It is a longitudinal side view of the 5th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第6工程の縦断側面図である。It is a longitudinal side view of the 6th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第7工程の縦断側面図である。It is a longitudinal side view of the 7th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第8工程の縦断側面図である。It is a longitudinal side view of the 8th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第9工程の縦断側面図である。It is a longitudinal side view of the 9th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第10工程の縦断側面図である。It is a longitudinal side view of the 10th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第11工程の縦断側面図である。It is a longitudinal side view of the 11th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第12工程の縦断側面図である。It is a longitudinal side view of the 12th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第13工程の縦断側面図である。It is a longitudinal side view of the 13th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第14工程の縦断側面図である。It is a longitudinal side view of the 14th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第15工程の縦断側面図である。It is a longitudinal side view of the 15th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第16工程の縦断側面図である。It is a longitudinal side view of the 16th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第17工程の縦断側面図である。It is a longitudinal side view of the 17th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 本発明の地下構造物の施工法の第1実施形態を示す第18工程の縦断側面図である。It is a longitudinal side view of the 18th process which shows 1st Embodiment of the construction method of the underground structure of this invention. 図3の第3工程に対応する縦断正面図である。It is a vertical front view corresponding to the 3rd process of FIG. 従来の地下構造物の施工法の第1工程を示す縦断側面図である。It is a vertical side view which shows the 1st process of the construction method of the conventional underground structure. 従来の地下構造物の施工法の第2工程を示す縦断側面図である。It is a vertical side view which shows the 2nd process of the construction method of the conventional underground structure. 従来の地下構造物の施工法の第3工程を示す縦断側面図である。It is a vertical side view which shows the 3rd process of the construction method of the conventional underground structure. 従来の地下構造物の施工法の第4工程を示す縦断側面図である。It is a vertical side view which shows the 4th process of the construction method of the conventional underground structure. 箱形ルーフの正面図である。It is a front view of a box shaped roof. 従来の地下構造物の施工法の第5工程を示す縦断側面図である。It is a vertical side view which shows the 5th process of the construction method of the conventional underground structure. 従来の地下構造物の施工法の第6工程を示す縦断側面図である。It is a vertical side view which shows the 6th process of the construction method of the conventional underground structure. 従来の地下構造物の施工法の第7工程を示す縦断側面図である。It is a vertical side view which shows the 7th process of the construction method of the conventional underground structure.

以下、図面について本発明の実施形態を詳細に説明する。図1〜図18は本発明の地下構造物の施工法の1実施形態を示す各工程の縦断側面図で、図19は第3工程の縦断正面図で、前記従来例を示す図20〜図27と同一構成要素には同一参照符号を付したものである。   Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. 1 to 18 are longitudinal side views of each step showing one embodiment of the construction method of the underground structure of the present invention, and FIG. 19 is a longitudinal sectional front view of the third step, and FIG. The same reference numerals as in FIG.

本発明も従来のSFT工法と同じように第1工程として図1に示すように鉄道などの上部交通(図示は省略した)の脇にシートパイル等の土留鋼矢板2からなる仮土留杭を打設して、発進坑3と到達坑4を築造し、図2に示すように発進坑3に捨石およびベースコンクリート打設による発進台20を形成し、推進機(図示せず、図20参照)を設置してこれで図2に示すようにルーフ用筒体である箱形ルーフ6を到達坑4に向けて圧入させる。   In the present invention, as in the conventional SFT method, as shown in FIG. 1 as a first step, a temporary earth retaining pile consisting of soil retained steel sheet piles 2 such as sheet piles is hit beside the upper traffic (not shown) The start pit 3 and the arrival pit 4 are built, and as shown in FIG. 2, the start pit 20 is formed by putting rubble and base concrete in the start pit 3 and a propulsion unit (not shown, see FIG. 20) The box-shaped roof 6 which is a roof cylinder is then pressed into the reaching pit 4 as shown in FIG.

到達坑4にも同じく捨石およびベースコンクリート打設による到達台21を形成してある。   The reach pit 4 is also formed with a reach 21 by rubbish and base concrete placement.

箱形ルーフ6は前記従来例と同じく図24に示すような矩形断面の箱形筒体で、前後端にボルト接合用のフランジを形成して(図示せず)、長さ方向に順次接続して必要長を埋設することができるものである。   The box-shaped roof 6 is a box-shaped cylindrical body having a rectangular cross section as shown in FIG. 24 as in the prior art, and flanges for bolt connection are formed at the front and rear ends (not shown). Necessary length can be buried.

なお、本発明で使用する箱形ルーフ6は側面に鉤状または平板状の継手6a,6bを長手方向に連続して形成し、また、上面に平板からなるフリクションカッタープレート7を取り付けているものの他、これら継手6a,6bがなく、また、フリクションカッタープレート7を取り付けていない、単なる矩形管体のものもある。   The box-like roof 6 used in the present invention is formed by continuously forming the wedge-like or flat plate-like joints 6a and 6b in the longitudinal direction on the side and attaching the friction cutter plate 7 consisting of a flat plate on the upper surface In addition, there is also a simple rectangular tube without these joints 6a and 6b and without the friction cutter plate 7 attached.

前記フリクションカッタープレート7は端部を箱形ルーフ6の端部に溶接して一体化しそれ以外は単に載せているだけのものであり、箱形ルーフ6が長さ方向に順次接続してなる場合は、フリクションカッタープレート7自体も相互に溶接などで接続して連続するものとする。   The friction cutter plate 7 is integrally integrated by welding the end to the end of the box-shaped roof 6 and the rest is simply mounted, and the box-shaped roof 6 is sequentially connected in the longitudinal direction. The friction cutter plate 7 itself is also connected to each other by welding or the like.

箱形ルーフ6は推進させようとするコンクリート函体9の外形に対応するように四角形状に配列設置した。この段階では箱形ルーフ6で囲まれた内部には土砂31が存在する。(図19参照)   The box-like roofs 6 were arranged in a square so as to correspond to the outer shape of the concrete box 9 to be promoted. At this stage, soil 31 exists inside the box-shaped roof 6. (See Figure 19)

次いで、コンクリート函体9を発進坑3に設置する前に、箱型ルーフ6を組み配置した内部の土砂の中を大径の管体23を順次継ぎ足しながら掘進して発進坑3と到達坑4間に貫通させる。管体23の内部は空洞となっている。   Next, before installing the concrete box 9 in the start pit 3, the large diameter pipe body 23 is sequentially added to the inside of the earth and sand in which the box-type roof 6 is arranged and excavated to start the start pit 3 and the reaching pit 4. Let it penetrate. The inside of the tube body 23 is hollow.

この管体23としては鋼管、ヒューム管などの使用が考えられるが、解体を考慮すると鋼管が好適である。また、円筒に限らず、角形なものでもよい。   As this pipe body 23, use of a steel pipe, a fume pipe, etc. can be considered, but in consideration of disassembly, a steel pipe is preferable. Moreover, not only a cylinder but a square thing may be used.

管体23の掘進は、管体23を3〜6m程度の単位体として順次接続しながら発進坑3に設置する推進機(図示せず)で推し進め、管体23の先頭を掘削部27として管体23の内部から手掘り、もしくは機械掘りで、土砂は管体23の内部から発進坑3へと導く。   The pipe 23 is pushed forward by a propulsion unit (not shown) installed in the start pit 3 while sequentially connecting the pipe 23 as a unit of about 3 to 6 m, and the head of the pipe 23 is taken as the excavating part 27 From the inside of the body 23 by hand digging or mechanical digging, the earth and sand are guided from the inside of the pipe body 23 to the start pit 3.

図4に示すようにコンクリート函体9を発進坑3に設置し、コンクリート函体9の後方の反力壁8との間に推進設備として元押しジャッキ10、ストラット16、井桁枠22を配設する。   As shown in FIG. 4, the concrete box 9 is installed in the start pit 3 and the main push jack 10, the struts 16 and the well girder frame 22 are arranged as a propulsion facility between the reaction wall 8 and the rear of the concrete box 9. Do.

そして、止め部材14でフリクションカッタープレート7を発進坑3側に固定する。このフリクションカッタープレート7により箱形ルーフ6およびコンクリート函体9と周辺土砂との縁切りを行う。   Then, the friction cutter plate 7 is fixed to the start pit 3 side by the stop member 14. The friction cutter plate 7 cuts off the box roof 6 and the concrete box 9 from the surrounding soil.

また、箱形ルーフ6および管体23を発進坑3と到達坑4間に貫通させるに際して発進坑3と到達坑4を構成する仮土留杭には箱形ルーフ6および管体23を貫通させるが、箱形ルーフ6で囲まれた内部の仮土留杭の部分はこれを土留部材19としてそのまま残しておく。   When the boxed roof 6 and the pipe body 23 are to be penetrated between the start pit 3 and the arrival pit 4, the box roof 6 and the pipe body 23 are made to penetrate through temporary earth retaining piles constituting the start pit 3 and the arrival pit 4. The portion of the temporary earth retaining pile surrounded by the box-shaped roof 6 is left as the earth retaining member 19 as it is.

次に先行して押出した箱形ルーフ6の後端にコンクリート函体9の先端を接合し、または当接させて、第5工程として図5に示すように元押しジャッキ10を伸長してコンクリート函体9を前方に押出す。   Next, the front end of the concrete box 9 is joined to or brought into contact with the rear end of the box-shaped roof 6 that has been extruded in advance, and as shown in FIG. Push the box 9 forward.

コンクリート函体9の押出しと同時に箱形ルーフ6も押出し、さらに切羽部の掘削は行わず、箱形ルーフ6を押出すときに同時に箱形ルーフ6で囲まれた部分に配設した土留部材19を押出すことにより箱形ルーフ6で囲まれた内部の土砂31や管体23も同時に押出す。   A soil retaining member 19 disposed at the same time as extruding the box roof 6 at the same time as extruding the box roof 6 while extruding the box roof 6 simultaneously with the extrusion of the concrete box 9 By simultaneously extruding the inside soil 31 and the tube 23 surrounded by the box-shaped roof 6.

この場合、前記のようにフリクションカッタープレート7により箱形ルーフ6およびコンクリート函体9と周辺土砂との縁切りがなされているから、箱形ルーフ6およびコンクリート函体9はスムーズに推進する。   In this case, since the rim of the box-shaped roof 6 and the concrete box 9 and the surrounding earth and sand is made by the friction cutter plate 7 as described above, the box-shaped roof 6 and the concrete box 9 are smoothly propelled.

このようにして第6工程として図6に示すように箱形ルーフ6とこの箱形ルーフ6に囲まれて同時に押出された土砂31が到達坑4に到達したならば、到達坑4で箱形ルーフ6をピース毎に分解し、撤去すると同時に、土砂31を掘削して排土する。   Thus, as shown in FIG. 6 as the sixth step, if the soil 31 which is simultaneously and enclosed by the box-shaped roof 6 and the box-shaped roof 6 reaches the reaching pit 4, the box type of the reaching pit 4 is formed. The roof 6 is disassembled piece by piece and, at the same time, the earth and sand 31 is excavated and discharged.

また、押し出される管体23の先頭部も溶断等で小片に分断し、これも撤去する。   Further, the leading end of the extruded tubular body 23 is also divided into small pieces by melting and the like, and this is also removed.

前記土留部材19も撤去する。   The soil retaining member 19 is also removed.

図中32は到達坑4に設置したホイストであるが、ピース毎に分解した箱形ルーフ6や掘削した土砂31、分断した土留部材19や管体23はホイスト32で一時的に保持し、管体23の内部に導き、管体23の内部および函体9の内部を発進坑3へと搬送し、発進坑3から地上に搬出する。   In the figure, 32 is a hoist installed in the reaching pit 4, but the box-shaped roof 6 disassembled into pieces and excavated soil 31 and divided soil retaining members 19 and tubes 23 are temporarily held by the hoist 32 and pipes It is led to the inside of the body 23, and the inside of the tubular body 23 and the inside of the box 9 are transported to the start pit 3 and carried out of the start pit 3 to the ground.

図7に示すように、台車33を用いて搬送することができる。   As shown in FIG. 7, the carriage 33 can be used to carry.

以上のように到達坑4側に押し出す前記箱形ルーフ6、土砂31、管体23は順次解体して、この解体物は管体および函体の内部を発進坑へと搬送し、発進坑3から地上に搬出する。   As described above, the boxed roof 6, the soil 31, and the pipe 23 which are pushed to the reaching pit 4 side are dismantled in order, and the dismantled material is transported to the starting pit from the inside of the pipe and the box. Take it out to the ground.

して、さらにコンクリート函体9の先端が到達坑4に達するまで推進してコンクリート函体9の全長の推進が完了する。   Then, the propelling of the full length of the concrete box 9 is completed by propelling until the tip of the concrete box 9 reaches the reaching pit 4.

2 土留鋼矢板
3 発進坑 4 到達坑
5 推進機 6 箱形ルーフ
6a,6b 平板状の継手 7 フリクションカッタープレート
8 反力壁 9 コンクリート函体
10 元押しジャッキ 11 刃口
12 小ジャッキ 13 支持材
14 止め部材 15 受台
16 ストラット 17 腹起こし材
18 函体接続工 19 土留部材
20 発進台 21 到達台
22 井桁枠 23 管体
24 土砂 25 土留部材
26 発進台 27 掘削部
28 タイロット材 29 リフター
30 押角 31 土砂
32 ホイスト 33 台車
DESCRIPTION OF SYMBOLS 2 Soil retaining steel sheet pile 3 Starting pit 4 Reaching pit 5 Propulsion machine 6 Box-shaped roof 6a, 6b Flat joint 7 Friction cutter plate 8 Reaction wall 9 Concrete box 10 Original push jack 11 Cutting edge 12 Small jack 13 Support 14 Retaining members 15 pedestals 16 struts 17 uplifting members 18 box connection work 19 soil retention members 20 starting platforms 21 arrival platforms 22 well girder frames 23 pipes 24 sediments 25 soil retaining members 26 launch platforms 27 excavating sections 28 tie-lot materials 29 lifters 30 pushing angle 31 Earth and sand 32 Hoist 33 Bogie

Claims (1)

発進坑から到達坑にむけて推進しようとする函体の外形に対応するように箱形ルーフを組み配置して、発進坑もしくは到達坑から地中に圧入した後、この箱形ルーフ端部に函体を配置し、函体の推進とともに箱形ルーフを組み配置した内部の土砂を箱形ルーフといっしょに押し出す地下構造物の施工法において、
函体を発進坑に設置する前に、箱形ルーフを組み配置した内部土砂の中に管体を発進坑と到達坑側間に貫通させ、発進坑に設置した函体の推進とともに箱形ルーフ、その内部の土砂および管体を到達側に押し出すとともに、これら到達坑側に押し出す前記箱形ルーフ、土砂、管体は順次解体して、この解体物は管体および函体の内部を発進坑へと搬送し、発進坑から地上に搬出することを特徴とした地下構造物の施工法。
The boxed roof is assembled so as to correspond to the outer shape of the box to be propelled from the starting pit to the reaching pit, and pressed into the ground from the starting pit or the reaching pit, In the construction method of the underground structure which arranges the box body and pushes out the earth and sand inside the box roof assembled and arranged with the box roof together with the promotion of the box,
Before installing the box in the start pit, the tube is penetrated between the start pit and the arrival pit side in the inside soil where the box roof is assembled and arranged, and the box roof is promoted along with the promotion of the box placed in the start pit While pushing out the earth and sand and the tube inside of the box roof, the earth and sand, and the tube pushing out to the reaching side, dismantling products are dismantled in order, and the dismantling material starts the inside of the tube and box. Underground construction method characterized by carrying to the ground and carrying it out from the starting pit to the ground.
JP2018028410A 2018-02-21 2018-02-21 Construction method of underground structure Active JP6510690B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018028410A JP6510690B1 (en) 2018-02-21 2018-02-21 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018028410A JP6510690B1 (en) 2018-02-21 2018-02-21 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JP6510690B1 true JP6510690B1 (en) 2019-05-08
JP2019143362A JP2019143362A (en) 2019-08-29

Family

ID=66429954

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018028410A Active JP6510690B1 (en) 2018-02-21 2018-02-21 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JP6510690B1 (en)

Also Published As

Publication number Publication date
JP2019143362A (en) 2019-08-29

Similar Documents

Publication Publication Date Title
JP4317843B2 (en) Construction method for underground structures
JP2010090608A (en) Method for constructing underground space and structure of the underground space
JP2008223397A (en) Construction method for underground structure
JP6510690B1 (en) Construction method of underground structure
JP6510620B1 (en) Construction method of underground structure and push-in jack used therefor
JP7177233B2 (en) Start Reaction Force Structure and Method for Concrete Box or Open Shield Machine
JP4134089B2 (en) Construction method for underground structures
JP3382183B2 (en) Construction method for underground structure and roof cylinder used therefor
JP3887383B2 (en) Construction method for underground structures
JP6714060B2 (en) Construction method of underground structure
JP6510432B2 (en) Construction method of underground structure
JP6982603B2 (en) Box-shaped roof construction method
JP5885229B2 (en) Reaction force device
JP5054164B2 (en) Construction method for underground structures
JP6445478B2 (en) Construction method for underground structures
JP6441871B2 (en) Box roof deflection reduction method for box roof method
JP4647562B2 (en) Pipe roof construction method
JP6212087B2 (en) Construction method for underground structures
CN110359916B (en) Construction method for underground structure
JP6139613B2 (en) Construction method for underground structures
JP5342571B2 (en) How to build an underpass
JP2019183513A (en) Non-earth-removal auger excavation tool
JPH06229187A (en) Constructing method of subsurface structure
KR100725952B1 (en) It establishes the tunnel formation tunnel structure the Maine pipe construction method
JP5394454B2 (en) Open shield method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180328

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20190402

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190404

R150 Certificate of patent or registration of utility model

Ref document number: 6510690

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250