JP6470159B2 - Hydraulic operating device and inspection method thereof - Google Patents

Hydraulic operating device and inspection method thereof Download PDF

Info

Publication number
JP6470159B2
JP6470159B2 JP2015195367A JP2015195367A JP6470159B2 JP 6470159 B2 JP6470159 B2 JP 6470159B2 JP 2015195367 A JP2015195367 A JP 2015195367A JP 2015195367 A JP2015195367 A JP 2015195367A JP 6470159 B2 JP6470159 B2 JP 6470159B2
Authority
JP
Japan
Prior art keywords
port
valve
pressure
closing
liquid supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2015195367A
Other languages
Japanese (ja)
Other versions
JP2017069112A (en
Inventor
正志 岩澤
正志 岩澤
武彦 別所
武彦 別所
高木 弘和
弘和 高木
文雄 中嶋
文雄 中嶋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Toshiba Energy Systems and Solutions Corp
Original Assignee
Toshiba Corp
Toshiba Energy Systems and Solutions Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Toshiba Energy Systems and Solutions Corp filed Critical Toshiba Corp
Priority to JP2015195367A priority Critical patent/JP6470159B2/en
Publication of JP2017069112A publication Critical patent/JP2017069112A/en
Application granted granted Critical
Publication of JP6470159B2 publication Critical patent/JP6470159B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Driving Mechanisms And Operating Circuits Of Arc-Extinguishing High-Tension Switches (AREA)
  • Fluid-Pressure Circuits (AREA)
  • Arc-Extinguishing Devices That Are Switches (AREA)

Description

本発明の実施形態は、液圧操作装置及びその検査方法に関する。   Embodiments described herein relate generally to a hydraulic operating device and an inspection method thereof.

一般に、SF6ガスを消弧用の絶縁媒体として用いるガス遮断器は、電路を開閉操作させる操作方式として、空気操作方式、油圧操作方式、電動ばね操作方式などを適用している。空気操作方式を適用する操作装置は、圧縮空気を発生させるコンプレッサを頻繁に点検する作業の煩雑さや、稼働時の騒音などが課題となっており、需要が減少傾向にある。 In general, a gas circuit breaker using SF 6 gas as an arc-extinguishing insulating medium employs an air operation method, a hydraulic operation method, an electric spring operation method, or the like as an operation method for opening and closing an electric circuit. The operating device to which the air operating method is applied has problems such as troublesome work of frequently checking a compressor that generates compressed air, noise during operation, and the like, and the demand is decreasing.

一方、電動ばね操作方式を適用する操作装置は、その保守性の良さから、近年では、需要が広がりつつある。しかしながら、主に大電流及び高電圧の電力を扱うガス遮断器は、開閉操作の際に大きな操作出力が必要になる。このため、電動ばね操作方式を採る操作装置は、ガス遮断器を開閉操作するための操作出力が十分に得られない場合がある。   On the other hand, the operating device to which the electric spring operating method is applied has recently been increasing in demand due to its maintainability. However, a gas circuit breaker that mainly handles large current and high voltage power requires a large operation output during opening and closing operations. For this reason, the operation device employing the electric spring operation method may not obtain a sufficient operation output for opening and closing the gas circuit breaker.

つまり、ガス遮断器の開閉操作に大きな操作出力が要求される場合には、依然として、油圧操作方式を適用する液圧(油圧)操作装置のニーズが高くなっている。今日では、このような液圧操作装置に対しては、これまで以上にコンパクト化が求められ、さらにはメンテナンス性の改善も要請されている。   That is, when a large operation output is required for the opening / closing operation of the gas circuit breaker, there is still a growing need for a hydraulic (hydraulic) operation device that applies a hydraulic operation method. Nowadays, such a hydraulic operation device is required to be more compact than ever, and further to improve maintenance.

特開2001−345032号公報JP 2001-345032 A 特公昭64−773号公報Japanese Patent Publication No. 64-773

そこで、本発明が解決しようとする課題は、保守性の向上及び小型化を図れる液圧操作装置及びその検査方法を提供することである。   Therefore, the problem to be solved by the present invention is to provide a hydraulic operating device and an inspection method thereof that can improve maintainability and reduce the size.

実施の形態の液圧操作装置は、アキュムレータ、低圧タンク、電極駆動ユニット、切換弁ユニット、給排液弁ユニット、及び閉止弁を備えている。アキュムレータは、昇圧された作動液を第1の給液ポート側に向けて給液する。低圧タンクは、第1の排液ポートを介して作動液を回収する。電極駆動ユニットは、第1の制御ポートを介して作動液が出入りする第1の液室内の圧力に応じて、遮断器の可動電極が、前記遮断器の固定電極から離間する第1の開路位置と前記固定電極に接触する第1の閉路位置との間で、前記可動電極を移動させる電極移動機構を含む。切換弁ユニットは、第2の排液ポートと第2の制御ポートとを接続する第2の開路位置と、前記第1の給液ポートにつながる第2の給液ポートと前記第2の制御ポートとを接続する第2の閉路位置と、の間で移動する切換弁を含む。給排液弁ユニットは、前記第2の制御ポートを介して作動液が出入りする第2の液室内の圧力に応じて、第3の開路位置と第3の閉路位置との間を移動し、前記第3の閉路位置に移動したときに、前記第1の制御ポートと前記第1の給液ポートとの間を接続する給液弁と、前記第2の液室内の圧力に応じて、前記給液弁と一体となって第4の開路位置と第4の閉路位置との間を移動し、前記第4の開路位置に移動したときに、前記第1の制御ポートと前記第1の排液ポートとの間を接続する排液弁と、を含む。閉止弁は、前記第1の給液ポート、前記第1の排液ポート及び前記第1の制御ポートを含むポート組と、前記第2の給液ポート、前記第2の排液ポート及び前記第2の制御ポートを含むポート組と、のうちの少なくとも一方のポート組の各ポート上にそれぞれ設けられている。   The fluid pressure operating device according to the embodiment includes an accumulator, a low pressure tank, an electrode driving unit, a switching valve unit, a supply / drain liquid valve unit, and a closing valve. The accumulator supplies the pressurized hydraulic fluid toward the first liquid supply port. The low pressure tank collects the working fluid through the first drain port. The electrode drive unit has a first open position in which the movable electrode of the circuit breaker is separated from the fixed electrode of the circuit breaker according to the pressure in the first liquid chamber through which the working fluid enters and exits through the first control port. And an electrode moving mechanism for moving the movable electrode between the first closed position contacting the fixed electrode. The switching valve unit includes a second open position that connects the second drainage port and the second control port, a second liquid supply port that connects to the first liquid supply port, and the second control port. And a second closed position connecting the two and a switching valve that moves between them. The supply / drainage valve unit moves between a third open position and a third closed position according to the pressure in the second liquid chamber through which the hydraulic fluid enters and exits via the second control port, When moved to the third closed position, the liquid supply valve connecting between the first control port and the first liquid supply port, and the pressure in the second liquid chamber, The first control port and the first discharge port are moved together between the fourth open position and the fourth closed position integrally with the liquid supply valve and moved to the fourth open position. A drainage valve connected to the fluid port. The shut-off valve includes a port set including the first liquid supply port, the first liquid discharge port, and the first control port, the second liquid supply port, the second liquid discharge port, and the first liquid discharge port. And a port set including two control ports, and at least one of the port sets.

第1の実施形態に係る液圧操作装置の開路状態を示す断面図。Sectional drawing which shows the open circuit state of the hydraulic operation apparatus which concerns on 1st Embodiment. 図1の液圧操作装置の閉路状態へ向う過渡期の状態を示す断面図。Sectional drawing which shows the state of the transition period which goes to the closed circuit state of the hydraulic-pressure operation apparatus of FIG. 図1の液圧操作装置の閉路状態を示す断面図。Sectional drawing which shows the closed circuit state of the hydraulic-pressure operation apparatus of FIG. 図1の液圧操作装置の開路状態へ向う過渡期の状態を示す断面図。Sectional drawing which shows the state of the transition period which goes to the open circuit state of the hydraulic operation apparatus of FIG. 図1の液圧操作装置の全体の構成を説明するための代表的なレイアウト図。The typical layout figure for demonstrating the whole structure of the hydraulic-pressure operation apparatus of FIG. 図1の液圧操作装置が備える各ユニットを取り外した状態を示す断面図。Sectional drawing which shows the state which removed each unit with which the hydraulic operation apparatus of FIG. 1 is provided. 第2の実施形態に係る液圧操作装置が備える各ユニットを取り外した状態を示す断面図。Sectional drawing which shows the state which removed each unit with which the hydraulic operation apparatus which concerns on 2nd Embodiment is provided. 第3の実施形態に係る液圧操作装置が備える圧力スイッチユニットの周辺の構成を示す断面図。Sectional drawing which shows the structure of the periphery of the pressure switch unit with which the hydraulic-pressure operating device which concerns on 3rd Embodiment is provided. 図8の圧力スイッチユニットを取り外した状態を示す断面図。Sectional drawing which shows the state which removed the pressure switch unit of FIG. 第4の実施形態に係る液圧操作装置が備える圧力スイッチユニットの周辺の構成を示す断面図。Sectional drawing which shows the structure of the periphery of the pressure switch unit with which the hydraulic-pressure operating device which concerns on 4th Embodiment is provided. 図10の圧力スイッチユニットを取り外した状態を示す断面図。Sectional drawing which shows the state which removed the pressure switch unit of FIG. 比較例の液圧操作装置の構成を示す断面図。Sectional drawing which shows the structure of the hydraulic operation apparatus of a comparative example.

以下、実施の形態を図面に基づき説明する。なお、図1〜図4及び図6〜図12では、移動可能な各部材の移動方向を把握しやすくするために、X1、X2、Y1、Y2方向を矢印でそれぞれ図示し、図示した移動方向を本文中の説明で引用する。また、図1〜図4及び図6〜図12では、液圧操作装置内の各部を流動する作動液が高圧であるか低圧であるかを把握しやすくするために、高圧になっているアキュムレータ内に文字“H”(High)を図示し、低圧になっている低圧タンク内に文字“L”(Low)を図示する。   Hereinafter, embodiments will be described with reference to the drawings. In FIGS. 1 to 4 and FIGS. 6 to 12, in order to make it easy to grasp the moving direction of each movable member, the X1, X2, Y1, and Y2 directions are respectively illustrated by arrows and illustrated. Is quoted in the explanation in the text. 1 to 4 and FIGS. 6 to 12, an accumulator that is at a high pressure is used in order to make it easy to grasp whether the hydraulic fluid flowing through each part in the hydraulic operating device is at a high pressure or a low pressure. The letter “H” (High) is shown in the figure, and the letter “L” (Low) is shown in the low-pressure tank that is at low pressure.

<第1の実施の形態>
図1〜図5に示すように、本実施形態の液圧操作装置10は、送電系統(電力系統)に設けられる遮断器を、開路動作及び閉路動作させるための駆動源として作動液(油などの作動流体)を適用する装置である。すなわち、液圧操作装置10は、液圧制御ユニット61及び電極駆動ユニット14を備えている。液圧制御ユニット61は、開路用電磁弁ユニット(開路用アクチュエータユニット)15と、閉路用電磁弁ユニット(閉路用アクチュエータユニット)16と、パイロット弁ユニット(切換弁ユニット)68と、主操作弁ユニット(給排液弁ユニット)9と、を有している。一方、電極駆動ユニット14は、圧力スイッチユニット(圧力監視ユニット)8を備えている。
<First Embodiment>
As shown in FIGS. 1 to 5, the hydraulic operating device 10 according to the present embodiment is a hydraulic fluid (oil or the like) as a drive source for opening and closing circuit breakers provided in a power transmission system (power system). A working fluid). That is, the hydraulic pressure operating device 10 includes a hydraulic pressure control unit 61 and an electrode driving unit 14. The hydraulic control unit 61 includes an opening solenoid valve unit (opening actuator unit) 15, a closing solenoid valve unit (closing actuator unit) 16, a pilot valve unit (switching valve unit) 68, and a main operation valve unit. (Supply / drainage valve unit) 9. On the other hand, the electrode drive unit 14 includes a pressure switch unit (pressure monitoring unit) 8.

ここで、上述した開路用電磁弁ユニット15と閉路用電磁弁ユニット16とパイロット弁ユニット68、さらに、パイロット弁ユニット68と主操作弁ユニット9、さらに、主操作弁ユニット9と電極駆動ユニット14(さらに、圧力スイッチユニット8と電極駆動ユニット14本体)は、図6及び図1に示すように、それぞれ、着脱自在(組み付け及び取り外し可能)に構成されている。また、電極駆動ユニット14は、低圧タンク17、液圧ポンプ18、アキュムレータ19及び電極移動機構12をさらに備えている。また、パイロット弁ユニット68は、インターロック機構64を備えている。   Here, the opening solenoid valve unit 15, the closing solenoid valve unit 16, the pilot valve unit 68, the pilot valve unit 68 and the main operation valve unit 9, and the main operation valve unit 9 and the electrode drive unit 14 ( Furthermore, the pressure switch unit 8 and the electrode drive unit 14 main body) are configured to be detachable (assembled and removable), as shown in FIGS. The electrode driving unit 14 further includes a low-pressure tank 17, a hydraulic pump 18, an accumulator 19, and an electrode moving mechanism 12. The pilot valve unit 68 includes an interlock mechanism 64.

電極移動機構12は、第1の制御ポート21を介して作動液が出入りする第1の液室31内の圧力に応じて、遮断器の可動電極3が、遮断器の固定電極2から離間する図1に示す第1の開路位置と固定電極2に接触する図3に示す第1の閉路位置との間で、可動電極3を矢印Y1−Y2方向に移動させる。より具体的には、可動電極3は、液圧操作装置10の開路動作の完了時に第1の開路位置に移動し、一方、閉路動作の完了時に第1の閉路位置に移動する。   In the electrode moving mechanism 12, the movable electrode 3 of the circuit breaker is separated from the fixed electrode 2 of the circuit breaker according to the pressure in the first liquid chamber 31 through which the working fluid enters and exits through the first control port 21. The movable electrode 3 is moved in the arrow Y1-Y2 direction between the first open position shown in FIG. 1 and the first closed position shown in FIG. More specifically, the movable electrode 3 moves to the first opening position when the opening operation of the hydraulic operating device 10 is completed, and moves to the first closing position when the closing operation is completed.

図1〜図4に示すように、電極移動機構12は、駆動シリンダ5、駆動ピストン6及び駆動ロッド7を備えている。駆動シリンダ5は、矢印Y1−Y2方向に移動可能な状態で駆動ピストン6を内部に収容している。駆動ロッド7は、一端部に可動電極3を支持していると共に、一端部と他端部との間に駆動ピストン6を保持している。   As shown in FIGS. 1 to 4, the electrode moving mechanism 12 includes a drive cylinder 5, a drive piston 6, and a drive rod 7. The drive cylinder 5 accommodates the drive piston 6 in a movable state in the arrow Y1-Y2 direction. The drive rod 7 supports the movable electrode 3 at one end and holds the drive piston 6 between the one end and the other end.

図2及び図4に示すように、駆動シリンダ5は、駆動ピストン6によって区画される他方の領域に第1の液室31を有し、駆動ピストン6によって区画される一方の領域に第6の液室36を有している。なお、駆動ピストン6の周縁部と駆動シリンダ5の内壁部分との間には、互いの境界部分をシールするシール部が設けられている。   As shown in FIG. 2 and FIG. 4, the drive cylinder 5 has a first liquid chamber 31 in the other region partitioned by the drive piston 6, and the sixth cylinder in one region partitioned by the drive piston 6. A liquid chamber 36 is provided. A seal portion is provided between the peripheral edge portion of the drive piston 6 and the inner wall portion of the drive cylinder 5 to seal the boundary portion between them.

ここで、駆動ピストン6及び駆動ロッド7が第1の液室31内で作動液と接触して圧力を受ける受圧面積は、駆動ピストン6及び駆動ロッド7が第6の液室36内で作動液と接触して圧力を受ける受圧面積よりも大きくなるように、駆動ピストン6及び駆動ロッド7が形成されている。つまり、パスカルの原理を応用するこのような構成により、第1の液室31内の圧力と第6の液室36内の圧力とが例えば互いに等しい場合、図3に示すように、駆動ピストン6及び駆動ロッド7と共に可動電極3は、固定電極2側(矢印Y2方向)に移動することになる。   Here, the pressure receiving area in which the drive piston 6 and the drive rod 7 are in contact with the hydraulic fluid in the first liquid chamber 31 and receives pressure is the hydraulic fluid in which the drive piston 6 and the drive rod 7 are in the sixth liquid chamber 36. The drive piston 6 and the drive rod 7 are formed so as to be larger than the pressure receiving area that receives pressure in contact with. That is, when the pressure in the first liquid chamber 31 and the pressure in the sixth liquid chamber 36 are equal to each other, for example, as shown in FIG. The movable electrode 3 together with the drive rod 7 moves to the fixed electrode 2 side (arrow Y2 direction).

なお、上述した電極移動機構は、可動電極を移動させて、可動電極と固定電極との各電極を接触又は離間させるものであるが、これに代えて、移動させる側を固定電極側にして各電極を接触又は離間させるようにしてもよいし、さらにこれに代えて、可動電極側と固定電極側との双方を移動させて、各電極を接触又は離間させるようにしてもよい。   The above-described electrode moving mechanism moves the movable electrode so that the movable electrode and the fixed electrode are brought into contact with or separated from each other. The electrodes may be brought into contact with or separated from each other. Alternatively, both the movable electrode side and the fixed electrode side may be moved to bring the electrodes into contact with or separated from each other.

低圧タンク17は、第1の排液ポート23を介して低圧の作動液を回収して貯留する。液圧ポンプ18は、低圧タンク17内に回収された作動液を昇圧してアキュムレータ19側に移送する。アキュムレータ19は、昇圧された作動液を高圧のまま蓄え、また、この昇圧された高圧の作動液を第1の給液ポート22側に向けて給液する。   The low-pressure tank 17 collects and stores the low-pressure hydraulic fluid via the first drain port 23. The hydraulic pump 18 increases the pressure of the hydraulic fluid collected in the low pressure tank 17 and transfers it to the accumulator 19 side. The accumulator 19 stores the pressurized hydraulic fluid at a high pressure and supplies the pressurized hydraulic fluid toward the first liquid supply port 22 side.

図1〜図4に示すように、アキュムレータ19と第1の給液ポート22との間は、高圧流路52で接続されている。つまり、アキュムレータ19は、高圧流路52を介して高圧の作動液を第1の給液ポート22側に向けて給液する。また、高圧流路52は、途中で分岐し、駆動シリンダ5の第6の液室36にも接続されている。   As shown in FIGS. 1 to 4, the accumulator 19 and the first liquid supply port 22 are connected by a high-pressure channel 52. That is, the accumulator 19 supplies high-pressure hydraulic fluid toward the first liquid supply port 22 through the high-pressure channel 52. Further, the high-pressure channel 52 is branched in the middle and is also connected to the sixth liquid chamber 36 of the drive cylinder 5.

図1〜図5に示すように、圧力スイッチユニット8は、アキュムレータ19内の高圧液の液圧(作動液の圧力)を監視する圧力監視部である。圧力スイッチユニット8は、圧力検出部8a、高圧閉止弁8b、安全弁8cを備えている。圧力検出部8aは、第1の給液ポート22から分岐した圧力スイッチ給液ポート(圧力検出用給液ポート)28に接続されており、圧力スイッチ給液ポート28における作動液の液圧を検出する。高圧閉止弁8bは、圧力スイッチ給液ポート28における作動液の液圧を放圧する。安全弁8cは、圧力スイッチ給液ポート28における作動液の液圧が所定の設定値(閾値)を超えたときに、高圧流路(第1の給液ポート22につながる圧力スイッチ給液ポート28)と低圧流路である圧力スイッチ排液ポート29(圧力スイッチ給液ポート28と低圧タンク17との間を接続するための圧力検出用排液ポート)とを連通させて高圧の作動液を高圧流路から前記低圧流路へと放出する。   As shown in FIGS. 1 to 5, the pressure switch unit 8 is a pressure monitoring unit that monitors the liquid pressure of the high-pressure liquid in the accumulator 19 (pressure of the working liquid). The pressure switch unit 8 includes a pressure detector 8a, a high-pressure close valve 8b, and a safety valve 8c. The pressure detection unit 8 a is connected to a pressure switch liquid supply port (pressure detection liquid supply port) 28 branched from the first liquid supply port 22, and detects the hydraulic pressure of the hydraulic fluid at the pressure switch liquid supply port 28. To do. The high-pressure shut-off valve 8b releases the hydraulic fluid pressure at the pressure switch liquid supply port 28. The safety valve 8c has a high-pressure flow path (pressure switch liquid supply port 28 connected to the first liquid supply port 22) when the hydraulic pressure of the hydraulic fluid in the pressure switch liquid supply port 28 exceeds a predetermined set value (threshold). And a pressure switch drain port 29 (pressure detection drain port for connecting between the pressure switch feed port 28 and the low pressure tank 17) to communicate with the low pressure flow path. It discharges from a channel to the low-pressure channel.

図1〜図4に示すように、主操作弁ユニット9は、主操作弁ケース43、ガイドケース43a、第2の液室33、給液弁45、排液弁46、給液弁用バネ47、排液弁用バネ48を主に備えている。主操作弁ケース43及びガイドケース43aは、給液弁45、排液弁46、給液弁用バネ47、排液弁用バネ48を内部に収容している。排液弁46は、有底円筒状に構成されている。給液弁45は、排液弁46に対して同軸的に配置される状態で排液弁46の内部に収容されている。   As shown in FIGS. 1 to 4, the main operation valve unit 9 includes a main operation valve case 43, a guide case 43 a, a second liquid chamber 33, a liquid supply valve 45, a liquid discharge valve 46, and a liquid supply valve spring 47. The drain valve spring 48 is mainly provided. The main operation valve case 43 and the guide case 43a accommodate a liquid supply valve 45, a liquid discharge valve 46, a liquid supply valve spring 47, and a liquid discharge valve spring 48 therein. The drainage valve 46 is configured in a bottomed cylindrical shape. The liquid supply valve 45 is accommodated inside the drainage valve 46 in a state of being coaxially disposed with respect to the drainage valve 46.

図1〜図4に示すように、第2の液室33は、主操作弁ケース43及びガイドケース43aの内壁と排液弁46の内壁と給液弁45の外形部分との間に包囲された空間によって構成されている。また、第2の液室33は、排液弁46に形成された開口部及び第2の制御ポート24を通じて第5の液室32と接続されている。   As shown in FIGS. 1 to 4, the second liquid chamber 33 is enclosed between the inner walls of the main operation valve case 43 and the guide case 43 a, the inner wall of the drain valve 46, and the outer portion of the liquid supply valve 45. It is composed of space. Further, the second liquid chamber 33 is connected to the fifth liquid chamber 32 through an opening formed in the drain valve 46 and the second control port 24.

給液弁45は、第2の制御ポート24を介して作動液が出入りする第2の液室33内の圧力に応じて、図1に示す第3の開路位置と図2に示す第3の閉路位置との間を矢印X1−X2方向(給液弁45自身の軸方向)に移動し、第3の開路位置に移動したときに、排液弁46に形成された開口部を通じて、第1の制御ポート21と第1の給液ポート22との間を接続する。   The liquid supply valve 45 has a third open position shown in FIG. 1 and a third open position shown in FIG. 2 according to the pressure in the second liquid chamber 33 through which the hydraulic fluid enters and exits via the second control port 24. When moving to the third open position by moving in the direction of arrows X1-X2 between the closed position and the axial direction of the liquid supply valve 45 itself, the first through the opening formed in the drain valve 46 The control port 21 and the first liquid supply port 22 are connected.

つまり、切換弁41の第2の閉路位置への移動により第2の制御ポート24と第2の給液ポート25とが接続されて第2の液室33内の圧力が高圧になっている状態では、給液弁45は、図2に示すように、第3の閉路位置に移動し、第1の制御ポート21と第1の給液ポート22との間を接続する。この場合、第1の給液ポート22から第1の制御ポート21を通じて高圧の作動液が第1の液室31内に導入され、この第1の液室31内が高圧となり、これにより、図3に示すように、可動電極3は、第1の閉路位置に移動し固定電極2と接触することになる。   That is, the state where the second control port 24 and the second liquid supply port 25 are connected by the movement of the switching valve 41 to the second closed position and the pressure in the second liquid chamber 33 is high. Then, as shown in FIG. 2, the liquid supply valve 45 moves to the third closed position, and connects between the first control port 21 and the first liquid supply port 22. In this case, high-pressure hydraulic fluid is introduced into the first liquid chamber 31 from the first liquid supply port 22 through the first control port 21, and the inside of the first liquid chamber 31 becomes high pressure. As shown in FIG. 3, the movable electrode 3 moves to the first closed position and comes into contact with the fixed electrode 2.

給液弁用バネ47は、給液弁45の一端部側に配置された圧縮コイルバネであり、給液弁45を第3の開路位置側(給液弁45を閉じる矢印X2方向)に付勢する。図1に示すように、第3の開路位置に移動した給液弁45は、排液弁46の内壁部分に形成されたシート部(弁座部分)49と接触して、第1の制御ポート21と第1の給液ポート22との間を閉鎖する。   The liquid supply valve spring 47 is a compression coil spring disposed on one end side of the liquid supply valve 45, and biases the liquid supply valve 45 toward the third open position (in the direction of the arrow X2 that closes the liquid supply valve 45). To do. As shown in FIG. 1, the liquid supply valve 45 moved to the third open position comes into contact with a seat portion (valve seat portion) 49 formed on the inner wall portion of the drainage valve 46 and the first control port. 21 and the first liquid supply port 22 are closed.

一方、排液弁46は、第2の液室33内の圧力に応じて、給液弁45と一体となって図4に示す第4の開路位置と図2に示す第4の閉路位置との間を矢印X1−X2方向(排液弁46自身の軸方向)に移動し、第4の開路位置に移動したときに、第1の制御ポート21と第1の排液ポート23との間を接続する。   On the other hand, the drain valve 46 is integrated with the liquid supply valve 45 in accordance with the pressure in the second liquid chamber 33, and the fourth open position shown in FIG. 4 and the fourth closed position shown in FIG. Between the first control port 21 and the first drainage port 23 when moved in the direction of the arrow X1-X2 (the axial direction of the drainage valve 46 itself) and moved to the fourth open position. Connect.

つまり、切換弁41の第2の開路位置への移動により第2の制御ポート24と第2の排液ポート26とが接続されて第2の液室33内の圧力が低圧になっている状態では、排液弁46は、図4に示すように、第4の開路位置に移動し、第1の制御ポート21と第1の排液ポート23との間を接続する。この場合、第1の液室31内から制御ポート21及び第1の排液ポート23を通じて作動液が低圧タンク17側に排出されて、第1の液室31内が低圧となり、これにより、図1に示すように、可動電極3は、第1の開路位置に移動し固定電極2側から大きく離間することになる。   That is, the state in which the second control port 24 and the second drainage port 26 are connected by the movement of the switching valve 41 to the second open position and the pressure in the second liquid chamber 33 is low. Then, as shown in FIG. 4, the drainage valve 46 moves to the fourth open position and connects between the first control port 21 and the first drainage port 23. In this case, the working fluid is discharged from the first liquid chamber 31 to the low-pressure tank 17 side through the control port 21 and the first drain port 23, and the pressure in the first liquid chamber 31 becomes low. As shown in FIG. 1, the movable electrode 3 moves to the first open circuit position and is largely separated from the fixed electrode 2 side.

排液弁用バネ48は、排液弁46の一端部側に配置された圧縮コイルバネであり、排液弁46を第4の開路位置側(排液弁46を閉じる矢印X1方向)に付勢する。図2に示すように、第4の開路位置に移動した排液弁46は、主操作弁ケース43の内壁部分に形成されたシート部(弁座部分)51と接触して、第1の制御ポート21と第1の排液ポート23との間を閉鎖する。   The drain valve spring 48 is a compression coil spring disposed on one end of the drain valve 46, and biases the drain valve 46 toward the fourth open position (in the direction of the arrow X1 that closes the drain valve 46). To do. As shown in FIG. 2, the drainage valve 46 moved to the fourth open position comes into contact with a seat portion (valve seat portion) 51 formed on the inner wall portion of the main operation valve case 43 to perform the first control. The space between the port 21 and the first drainage port 23 is closed.

図1〜図4に示すように、開路用電磁弁ユニット15は、開路用ソレノイド(開路用アクチュエータ)75、可動片75f、弁ケース15a、弁押圧シャフト75a、弁本体部75b、開路弁用バネ75c、シート部75d、リンクレバー75eを備えている。閉路用電磁弁ユニット16は、閉路用ソレノイド(閉路用アクチュエータ)76、可動片76f、弁ケース16a、弁押圧シャフト76a、弁本体部76b、閉路弁用バネ76c、シート部76d、リンクレバー76eを備えている。   As shown in FIGS. 1 to 4, the opening solenoid valve unit 15 includes an opening solenoid (opening actuator) 75, a movable piece 75f, a valve case 15a, a valve pressing shaft 75a, a valve main body 75b, and an opening valve spring. 75c, a sheet portion 75d, and a link lever 75e. The closing solenoid valve unit 16 includes a closing solenoid (closing actuator) 76, a movable piece 76f, a valve case 16a, a valve pressing shaft 76a, a valve main body portion 76b, a closing valve spring 76c, a seat portion 76d, and a link lever 76e. I have.

開路用ソレノイド75は、液圧操作装置10に与えられる(入力される)開路指令に応じて、液圧操作装置10(遮断器)の開路動作を始動させるための開路用アクチュエータである。一方、閉路用ソレノイド76は、液圧操作装置10に与えられる閉路指令に応じて、液圧操作装置10の閉路動作を始動させるための閉路用アクチュエータである。   The opening solenoid 75 is an opening actuator for starting the opening operation of the hydraulic operating device 10 (breaker) in response to an opening command given (input) to the hydraulic operating device 10. On the other hand, the closing solenoid 76 is a closing actuator for starting the closing operation of the hydraulic operating device 10 in response to a closing command given to the hydraulic operating device 10.

上記したインターロック機構64を含むパイロット弁ユニット68は、図1〜図4に示すように、弁ケース78、開路用ポート72、閉路用ポート74、分岐流路73、オリフィス79aを含む流路79、第2の排液ポート26、第4の液室35、第3の液室37、第5の液室32、第8の液室38、切換弁41、インターロック弁71、インターロック用バネ71b、を備えている。   As shown in FIGS. 1 to 4, the pilot valve unit 68 including the interlock mechanism 64 includes a valve case 78, a circuit opening port 72, a circuit closing port 74, a branch flow path 73, and a flow path 79 including an orifice 79a. , Second drain port 26, fourth liquid chamber 35, third liquid chamber 37, fifth liquid chamber 32, eighth liquid chamber 38, switching valve 41, interlock valve 71, interlock spring. 71b.

上述した各ポート及び各液室は、ブロック化された弁ケース78の内部に形成されている。インターロック用バネ71b、開路弁用バネ75c、閉路弁用バネ76cは、圧縮コイルバネである。また、第4の液室35は、閉路用ポート74と接続されており、この閉路用ポート74を介して作動液が出入りする。   Each port and each liquid chamber described above are formed inside a blocked valve case 78. The interlock spring 71b, the open valve spring 75c, and the close valve spring 76c are compression coil springs. The fourth liquid chamber 35 is connected to a closing port 74, and hydraulic fluid enters and exits through the closing port 74.

閉路用ソレノイド76は、分岐流路73を介して、第2の排液ポート26と閉路用ポート74との間を開閉する。つまり、閉路用ソレノイド76は、閉路指令に応じて励磁された場合、閉路弁用バネ76cの付勢力に抗しつつ、可動片76f、弁押圧シャフト76a、リンクレバー76eを介して、弁本体部76bを、シート部(弁座部分)76dから離間させて矢印X2方向に移動し、第2の排液ポート26と閉路用ポート74との間を開放する。   The closing solenoid 76 opens and closes between the second drainage port 26 and the closing port 74 via the branch flow path 73. That is, when the closing solenoid 76 is energized in response to the closing instruction, the valve main body portion is opposed to the urging force of the closing valve spring 76c via the movable piece 76f, the valve pressing shaft 76a, and the link lever 76e. 76b is moved away from the seat portion (valve seat portion) 76d in the direction of the arrow X2 to open the space between the second drain port 26 and the closing port 74.

また、図1〜図4に示すように、第3の液室37は、開路用ポート72と接続されており、この開路用ポート72を介して作動液が出入りする。開路用ソレノイド75は、第2の排液ポート26と開路用ポート72との間を開閉する。すなわち、開路用ソレノイド75は、開路指令に応じて励磁された場合、開路弁用バネ75cの付勢力に抗しつつ、可動片75f、弁押圧シャフト75a、リンクレバー75eを介して、弁本体部75bを、シート部(弁座部分)75dから離間させて矢印X1方向に移動し、第2の排液ポート26と開路用ポート72との間を開放する。   In addition, as shown in FIGS. 1 to 4, the third liquid chamber 37 is connected to an opening port 72, and the working fluid enters and exits through the opening port 72. The opening solenoid 75 opens and closes between the second drain port 26 and the opening port 72. That is, when the opening solenoid 75 is energized in response to the opening instruction, the valve body portion is opposed to the biasing force of the opening valve spring 75c via the movable piece 75f, the valve pressing shaft 75a, and the link lever 75e. 75b is moved away from the seat portion (valve seat portion) 75d and moved in the direction of the arrow X1, and the space between the second drainage port 26 and the opening port 72 is opened.

切換弁41は、第2の排液ポート26と第2の制御ポート24とを接続する図4に示す第2の開路位置と、第2の給液ポート25と第2の制御ポート24とを接続する図2に示す第2の閉路位置との間で、矢印X1−X2方向に移動する。詳述すると、切換弁41は、開路用ポート72を介して作動液が出入りする第3の液室37内の圧力と閉路用ポート74を介して作動液が出入りする第4の液室35内の圧力とに応じて、第2の開路位置と第2の閉路位置との間を移動する。   The switching valve 41 connects the second drainage port 26 and the second control port 24, the second open position shown in FIG. 4, the second liquid supply port 25, and the second control port 24. It moves in the direction of the arrow X1-X2 between the second closed position shown in FIG. More specifically, the switching valve 41 has a pressure in the third liquid chamber 37 through which the working fluid enters and exits through the opening port 72 and an inside of the fourth liquid chamber 35 in which the working fluid enters and exits through the closing port 74. And the second closed position according to the pressure.

ここで、切換弁41の一端部が第4の液室35内で作動液と接触して圧力を受ける受圧面積は、切換弁41の他端部が第3の液室37内で作動液と接触して圧力を受ける受圧面積よりも大きくなるように、当該切換弁41の形状が適宜構成されている。つまり、パスカルの原理を応用するこのような構成によって、第4の液室35内の圧力と第3の液室37内の圧力とが例えば互いに等しい場合、切換弁41は、矢印X2方向に押されて図1に示す第2の開路位置に移動することになる。また、切換弁41は、第4の液室35内の圧力が、第2の圧力(本実施形態では、第3の液室37内の圧力)よりも低いときに、図2に示す第2の閉路位置へ移動する。   Here, the pressure receiving area in which one end portion of the switching valve 41 contacts the hydraulic fluid in the fourth liquid chamber 35 and receives pressure is such that the other end portion of the switching valve 41 is in contact with the hydraulic fluid in the third liquid chamber 37. The shape of the switching valve 41 is appropriately configured so as to be larger than the pressure receiving area that contacts and receives pressure. That is, with such a configuration applying the Pascal principle, when the pressure in the fourth liquid chamber 35 and the pressure in the third liquid chamber 37 are equal to each other, for example, the switching valve 41 is pushed in the direction of the arrow X2. As a result, it moves to the second open position shown in FIG. Further, the switching valve 41 has a second valve shown in FIG. 2 when the pressure in the fourth liquid chamber 35 is lower than the second pressure (in this embodiment, the pressure in the third liquid chamber 37). Move to the closed position.

切換弁41の内部には、第2の給液ポート25と第3の液室37とを接続する流路41bと、第2の給液ポート25と第4の液室35とを接続する流路41cと、がそれぞれ形成されている。したがって、例えば、開路用ソレノイド75と閉路用ソレノイド76との双方が閉じられている場合、第3の液室37内及び第4の液室35内の圧力は、高圧の状態に維持される。   Inside the switching valve 41, a flow path 41b connecting the second liquid supply port 25 and the third liquid chamber 37 and a flow connecting the second liquid supply port 25 and the fourth liquid chamber 35 are provided. A path 41c is formed. Therefore, for example, when both the opening solenoid 75 and the closing solenoid 76 are closed, the pressures in the third liquid chamber 37 and the fourth liquid chamber 35 are maintained in a high pressure state.

つまり、この状態において、閉路用ソレノイド76が開いた場合、分岐流路73を介して、第2の排液ポート26と閉路用ポート74との間が開放され、第4の液室35内から作動液が閉路用ポート74、分岐流路73及び第2の排液ポート26を介して排出される。これにより、第4の液室35内の圧力が低下して、第4の液室35内が低圧となることから、切換弁41は、矢印X1方向に押されて図2に示す第2の閉路位置に移動する。   That is, in this state, when the closing solenoid 76 is opened, the space between the second drainage port 26 and the closing port 74 is opened via the branch flow path 73, and from the fourth liquid chamber 35. The hydraulic fluid is discharged through the closing port 74, the branch flow path 73 and the second drainage port 26. As a result, the pressure in the fourth liquid chamber 35 decreases and the pressure in the fourth liquid chamber 35 becomes low, so that the switching valve 41 is pushed in the direction of the arrow X1 and the second valve shown in FIG. Move to the closed position.

また、第3の液室37内及び第4の液室35内の圧力が高圧の状態において、開路用ソレノイド75が開いた場合、第2の排液ポート26と開路用ポート72との間が開放され、第3の液室37内から作動液が開路用ポート72及び第2の排液ポート26を介して排出される。これによって、第3の液室37内の圧力が低下して、第3の液室37内が低圧となることから、切換弁41は、矢印X2方向に押されて図1に示す第2の開路位置に移動する。   Further, when the opening solenoid 75 is opened in a state where the pressure in the third liquid chamber 37 and the fourth liquid chamber 35 is high, the gap between the second drain port 26 and the opening port 72 is increased. The hydraulic fluid is discharged from the third liquid chamber 37 through the opening port 72 and the second drainage port 26. As a result, the pressure in the third liquid chamber 37 decreases and the pressure in the third liquid chamber 37 becomes low, so that the switching valve 41 is pushed in the direction of the arrow X2 and the second valve shown in FIG. Move to the open circuit position.

なお、切換弁41の第2の開路位置への移動完了後、開路用ソレノイド75が閉じられると、第3の液室37内には、第2の給液ポート25及び切換弁41内の流路41bを介して作動液が供給され、第3の液室37内は、圧力が上昇する。ただし、上述したように、第4の液室35側にある切換弁41の一端部の受圧面積は、第3の液室37側にある切換弁41の他端部の受圧面積よりも大きいため、第4の液室35内の圧力と第3の液室37内の圧力とが例えば互いに等しい場合、切換弁41は、そのまま第2の開路位置に保持される。   After the movement of the switching valve 41 to the second opening position is completed, when the opening solenoid 75 is closed, the flow in the second liquid supply port 25 and the switching valve 41 is placed in the third liquid chamber 37. The hydraulic fluid is supplied through the path 41b, and the pressure in the third liquid chamber 37 increases. However, as described above, the pressure receiving area of one end of the switching valve 41 on the fourth liquid chamber 35 side is larger than the pressure receiving area of the other end of the switching valve 41 on the third liquid chamber 37 side. When the pressure in the fourth liquid chamber 35 and the pressure in the third liquid chamber 37 are equal to each other, for example, the switching valve 41 is held in the second open position as it is.

図1〜図4に示すように、インターロック機構64は、作動液が出入りする第5の液室32内の圧力が、閾値として定めた第1の圧力を超えるときに、切換弁41の第2の閉路位置への移動を、機械的に阻止する。インターロック機構64は、引き外し優先機能及びポンピング防止機能を実現する。具体的には、インターロック機構64は、図1〜図4に示すように、主に、上述した閉路用ポート74、第4の液室35、第5の液室32、第8の液室38、インターロック用バネ71b、インターロック弁71によって構成される。   As shown in FIGS. 1 to 4, the interlock mechanism 64 is configured such that when the pressure in the fifth fluid chamber 32 where the working fluid enters and exits exceeds the first pressure determined as the threshold, 2 is mechanically prevented from moving to the closed position. The interlock mechanism 64 realizes a trip priority function and a pumping prevention function. Specifically, as shown in FIGS. 1 to 4, the interlock mechanism 64 mainly includes the above-described closing port 74, the fourth liquid chamber 35, the fifth liquid chamber 32, and the eighth liquid chamber. 38, an interlock spring 71b, and an interlock valve 71.

インターロック弁71は、閉路用ポート74を閉じる図3に示す閉塞位置と閉路用ポート74を開放する図1に示す開放位置との間を移動可能であって、第5の液室32内の圧力が、第1の圧力を超えるときに(本実施形態では、閉路用ポート74内の圧力以上のときに)、図3に示す閉塞位置に移動する。インターロック用バネ71bは、インターロック弁71を、開放位置から閉塞位置へと移動させる方向(矢印X1方向)に付勢している。   The interlock valve 71 is movable between a closed position shown in FIG. 3 that closes the closing port 74 and an open position shown in FIG. 1 that opens the closing port 74, and is provided in the fifth liquid chamber 32. When the pressure exceeds the first pressure (in this embodiment, when the pressure is equal to or higher than the pressure in the closing port 74), the pressure moves to the closed position shown in FIG. The interlock spring 71b biases the interlock valve 71 in a direction (arrow X1 direction) that moves the interlock valve 71 from the open position to the closed position.

図1〜図4に示すように、インターロック弁71の内部には、第4の液室35及び流路41cを介して第2の給液ポート25につながっている閉路用ポート74と、第8の液室37と、を接続している流路41bが形成されている。したがって、図1に示すように、開路用ソレノイド75と閉路用ソレノイド76との双方が例えば閉じられている場合、第8の液室38内の圧力は、第4の液室35内及び閉路用ポート74内と共に、それぞれ高圧の状態に維持されている。   As shown in FIGS. 1 to 4, the interlock valve 71 includes a closing port 74 connected to the second liquid supply port 25 through the fourth liquid chamber 35 and the flow path 41 c, A flow path 41b connecting the eight liquid chambers 37 is formed. Therefore, as shown in FIG. 1, when both the opening solenoid 75 and the closing solenoid 76 are closed, for example, the pressure in the eighth liquid chamber 38 is the same as that in the fourth liquid chamber 35 and the closing solenoid. Along with the inside of the port 74, a high pressure state is maintained.

なお、上記したインターロック弁71、インターロック用バネ71bなどを含むインターロック機構64については、オリフィス79aなどと共にこれを削除し、第4の液室35に通じている閉路用ポート74を、閉路用電磁弁ユニット16の高圧導入側に直接接続する構成にしてもよい。   Note that the interlock mechanism 64 including the interlock valve 71 and the interlock spring 71b described above is deleted together with the orifice 79a and the like, and the closing port 74 communicating with the fourth liquid chamber 35 is closed. The electromagnetic valve unit 16 may be directly connected to the high pressure introduction side.

ここで、インターロック機構64により実現される引き外し優先機能及びポンピング防止機能について説明する。まず、引き外し優先機能は、例えば、閉路動作の完了後さらに閉路指令が継続されていて、閉路用ソレノイド76が開いたままになっている状況であっても、開路指令がさらに与えられて開路用ソレノイド75が開いた場合に、閉路状態から開路状態へと優先的に移行させることを可能とするものである。   Here, the trip priority function and the pumping prevention function realized by the interlock mechanism 64 will be described. First, the trip priority function is, for example, that even when the closing command is continued after the closing operation is completed and the closing solenoid 76 is kept open, the opening command is further provided to open the circuit. When the solenoid 75 is opened, it is possible to preferentially shift from the closed state to the open state.

つまり、第3の液室37内が低圧であると共に第4の液室35内が高圧である図1に示す開路状態において、図2に示すように、閉路指令に応じて閉路用ソレノイド76が開いた場合、分岐流路73と閉路用ポート74との間が開放され、第4の液室35内及び閉路用ポート74内の作動液が分岐流路73及び第2の排液ポート23を介して排出される。これにより、第4の液室35内及び閉路用ポート74内が低圧となることから、切換弁41は、矢印X1方向に押されて図2に示す第2の閉路位置に移動する。   That is, in the open circuit state shown in FIG. 1 in which the inside of the third liquid chamber 37 has a low pressure and the inside of the fourth liquid chamber 35 has a high pressure, as shown in FIG. When opened, the space between the branch flow path 73 and the closing port 74 is opened, and the working fluid in the fourth liquid chamber 35 and the closing port 74 passes through the branch flow path 73 and the second drainage port 23. Is discharged through. As a result, the pressure in the fourth liquid chamber 35 and the closing port 74 becomes low, and the switching valve 41 is pushed in the direction of the arrow X1 to move to the second closing position shown in FIG.

切換弁41が第2の閉路位置に移動したことで、これに伴い、給液弁45も、図2に示すように、第3の閉路位置に移動し、これにより、第1の給液ポート22と第2の給液ポート25と第2の制御ポート24とが接続される。この結果、第1、第2の給液ポート22、25及び第2の制御ポート24を介して高圧の作動液が第5の液室32内に導入され、第2の液室35内が高圧となることから、インターロック弁71は、矢印X1方向に押されて図3に示す閉塞位置に移動する。これによって、閉路用ポート74が閉じられる。   As the switching valve 41 is moved to the second closed position, the liquid supply valve 45 is also moved to the third closed position as shown in FIG. 2, thereby the first liquid supply port. 22, the second liquid supply port 25, and the second control port 24 are connected. As a result, high-pressure hydraulic fluid is introduced into the fifth liquid chamber 32 via the first and second liquid supply ports 22 and 25 and the second control port 24, and the second liquid chamber 35 has a high pressure. Therefore, the interlock valve 71 is pushed in the direction of the arrow X1 and moves to the closed position shown in FIG. As a result, the closing port 74 is closed.

図3に示すように、閉路動作が完了したこの状態において、さらに閉路指令が継続されていて、閉路用ソレノイド76が開いたままであっても、インターロック弁71によって閉路用ポート74が閉じられていることから、第4の液室35内は、低圧にはならず、この結果、切換弁41の第2の閉路位置への移動が阻止される。したがって、閉路動作が完了した後に閉路指令が継続されている場合に、閉路動作が再び実行されることを防止することができる。   As shown in FIG. 3, in this state where the closing operation is completed, the closing port 74 is closed by the interlock valve 71 even if the closing command is continued and the closing solenoid 76 remains open. Therefore, the inside of the fourth liquid chamber 35 does not become a low pressure, and as a result, the movement of the switching valve 41 to the second closed position is prevented. Therefore, when the closing command is continued after the closing operation is completed, the closing operation can be prevented from being executed again.

また、閉路指令が継続されているこの状況においても、開路指令をさらに与え、図4に示すように、開路用ソレノイド75を開くと、開路用ポート72と第2の排液ポート26との間が接続され、第3の液室37内から作動液が開路用ポート72及び第2の排液ポート26を介して排出される。これによって、第3の液室37内が低圧となることから、切換弁41が、矢印X2方向に押されて図4に示す第2の開路位置に移動し、開路動作が実行される。このようにして引き外し優先機能が実現される。   Further, even in this situation where the closing command is continued, when the opening command is further given and the opening solenoid 75 is opened as shown in FIG. 4, there is a gap between the opening port 72 and the second drainage port 26. Are connected, and the working fluid is discharged from the third fluid chamber 37 through the opening port 72 and the second drainage port 26. As a result, the pressure in the third liquid chamber 37 becomes low, so that the switching valve 41 is pushed in the direction of the arrow X2 to move to the second opening position shown in FIG. 4, and the opening operation is executed. In this way, the trip priority function is realized.

一方、ポンピング防止機能は、例えば、液圧操作装置10の閉路状態から開路状態への移行中に、閉路指令が継続的に与えられていた場合、開路動作完了後に続いて閉路動作が実行されてしまうことなどを防止する機能である。   On the other hand, in the pumping prevention function, for example, when the closing command is continuously given during the transition from the closed state to the opened state of the hydraulic pressure operating device 10, the closing operation is executed after the completion of the opening operation. This is a function to prevent such a situation.

つまり例えば、閉路動作完了後にさらに開路動作が完了した状況において、閉路指令が継続されている場合、インターロック弁71は閉塞位置にあり、閉路用ポート74は閉じられたままであることから、第4の液室35内を低圧にできない状況である。これによって、切換弁41の第2の閉路位置への動作が阻止されることから、閉路動作が再度実行されず、これによりポンピング動作の発生を防止することができる。このようにしてポンピング防止機能が実現される。   That is, for example, in the situation where the opening operation is further completed after the completion of the closing operation, when the closing command is continued, the interlock valve 71 is in the closed position and the closing port 74 remains closed. This is a situation where the pressure in the liquid chamber 35 cannot be reduced. As a result, the operation of the switching valve 41 to the second closed position is prevented, so that the closed action is not executed again, thereby preventing the occurrence of a pumping action. In this way, a pumping prevention function is realized.

なお、インターロック弁71を図4に示す開放位置に復帰させるには、第5の液室32内を低圧し、閉路用ポート74と流路79とにおけるオリフィス79aよりも上部側を高圧にすることである。つまり、継続されている閉路指令を解除して閉路用ソレノイド76を閉じると、第2の給液ポート25、切換弁41内の流路41c、オリフィス79aを含む流路79を介して、閉路用ポート74と流路79とにおけるオリフィス79aよりも上部側に高圧の作動液が導入されて当該閉路用ポート74の上部側が高圧になる。   In order to return the interlock valve 71 to the open position shown in FIG. 4, the pressure in the fifth liquid chamber 32 is reduced, and the upper side of the closing port 74 and the flow path 79 above the orifice 79 a is increased. That is. That is, when the closed closing command is released and the closing solenoid 76 is closed, the closing solenoid 76 is closed via the second liquid supply port 25, the flow path 41c in the switching valve 41, and the flow path 79 including the orifice 79a. High pressure hydraulic fluid is introduced into the port 74 and the flow path 79 above the orifice 79a, and the upper side of the closing port 74 becomes high pressure.

さらにこの状態で、開路動作が実行されると第5の液室32内が低圧となる。これにより、インターロック弁71は、インターロック用バネ71bの付勢力に抗しつつ、矢印X2方向に押されて開放位置に復帰する。インターロック弁71が開放位置に復帰したことで、閉路用ポート74が開き、さらに、開路動作が完了した後、閉路用ソレノイド76を開くことで、切換弁41が図2に示す第2の閉路位置に移動し、これにより閉路動作が実行される。   Further, in this state, when the opening operation is executed, the inside of the fifth liquid chamber 32 becomes a low pressure. As a result, the interlock valve 71 is pushed in the direction of the arrow X2 and returns to the open position while resisting the biasing force of the interlock spring 71b. When the interlock valve 71 is returned to the open position, the closing port 74 is opened. Further, after the opening operation is completed, the closing solenoid 76 is opened, so that the switching valve 41 has the second closing state shown in FIG. The position is moved to the position, and the closing operation is executed.

したがって、液圧操作装置10は、閉路動作よりも開路動作を優先的に実行させることができると共にポンピング動作の発生を防止することができる。また、液圧操作装置10は、図1〜図4に示すように、部品の設置スペースの有効な活用によって、装置本体の小型化を図ることができる。   Therefore, the hydraulic operating device 10 can preferentially execute the opening operation over the closing operation, and can prevent the occurrence of the pumping operation. In addition, as shown in FIGS. 1 to 4, the hydraulic operation device 10 can reduce the size of the device main body by effectively utilizing the installation space for components.

次に、本実施形態の液圧操作装置10における一連の動作を図1〜図4に基づき説明する。まず、液圧操作装置10が開路状態から閉路状態へ移行する際の動作について説明する。図1に示すように、液圧操作装置10の開路状態において、液圧操作装置10に与えられる閉路指令に応じて閉路用ソレノイド76が励磁される。図2に示すように、可動片76fが矢印Y2方向に移動すると、リンクレバー76e、弁押圧シャフト76aを介して弁本体部76bが矢印X2方向に移動する。この際、分岐流路73を介して閉路用ポート74と第2の排液ポート26とが接続されて、第4の液室35内が低圧になることから、図2に示すように、切換弁41は、矢印X1方向に押されて第2の閉路位置まで移動する。これにより、第2の制御ポート24と第2の給液ポート25とが接続される。   Next, a series of operations in the hydraulic pressure operating device 10 according to the present embodiment will be described with reference to FIGS. First, the operation when the hydraulic pressure operating device 10 transitions from the open state to the closed state will be described. As shown in FIG. 1, in the open circuit state of the hydraulic operating device 10, the closing solenoid 76 is excited in response to a closing command given to the hydraulic operating device 10. As shown in FIG. 2, when the movable piece 76f moves in the arrow Y2 direction, the valve body 76b moves in the arrow X2 direction via the link lever 76e and the valve pressing shaft 76a. At this time, the closing port 74 and the second drainage port 26 are connected via the branch flow path 73, and the pressure in the fourth liquid chamber 35 becomes low. Therefore, as shown in FIG. The valve 41 is pushed in the direction of the arrow X1 and moves to the second closed position. As a result, the second control port 24 and the second liquid supply port 25 are connected.

また、この際、アキュムレータ19からの高圧の作動液は、高圧流路52、第1の給液ポート22、第2の給液ポート25及び第2の制御ポート24を経て、第2の液室33内に給液され、第2の液室33内の圧力を上昇させる。このように第2の液室33内の圧力が高圧になっている状態では、給液弁45は、図2に示すように、給液弁用バネ47の付勢力に抗しつつ、矢印X1方向に押されて第3の閉路位置に移動し、第1の制御ポート21と第1の給液ポート22との間を接続する。   At this time, the high-pressure hydraulic fluid from the accumulator 19 passes through the high-pressure channel 52, the first liquid supply port 22, the second liquid supply port 25, and the second control port 24, and then the second liquid chamber. The liquid is supplied into the liquid 33 and the pressure in the second liquid chamber 33 is increased. Thus, in a state where the pressure in the second liquid chamber 33 is high, the liquid supply valve 45 resists the urging force of the liquid supply valve spring 47 as shown in FIG. The first control port 21 is pushed in the direction to move to the third closed position, and the first control port 21 and the first liquid supply port 22 are connected.

この場合、第1の給液ポート22から第1の制御ポート21を通じて高圧の作動液が第1の液室31内に導入され、第1の液室31内の圧力は上昇して高圧となる。この際、可動電極3は、図3に示すように、上記したパスカルの原理によって矢印Y2方向に押されて第1の閉路位置に移動し固定電極2と接触することになる。このようにして、液圧操作装置10は、閉路状態への移行を完了したことになる。   In this case, high-pressure hydraulic fluid is introduced into the first liquid chamber 31 from the first liquid supply port 22 through the first control port 21, and the pressure in the first liquid chamber 31 rises to become high pressure. . At this time, as shown in FIG. 3, the movable electrode 3 is pushed in the direction of the arrow Y2 by the Pascal principle described above, moves to the first closed position, and comes into contact with the fixed electrode 2. In this way, the hydraulic pressure operating device 10 has completed the transition to the closed state.

次に、液圧操作装置10が閉路状態から開路状態へ移行する際の一般的な動作について説明する。図3に示すように、液圧操作装置10の閉路状態において、液圧操作装置10への開路指令の入力に応じて開路用ソレノイド75が励磁される。図4に示すように、可動片75fが矢印Y2方向に移動すると、リンクレバー75e、弁押圧シャフト75aを介して弁本体部75bが矢印X1方向に移動する。この際、開路用ポート72と第2の排液ポート26とが接続されて、第3の液室37内が低圧になることから、図4に示すように、切換弁41は、矢印X2方向に押されて第2の開路位置まで移動する。これにより、第2の制御ポート24と第2の排液ポート26とが接続される。   Next, a general operation when the hydraulic pressure operating device 10 shifts from the closed state to the open state will be described. As shown in FIG. 3, in the closed state of the hydraulic operating device 10, the opening solenoid 75 is excited in response to an input of an opening command to the hydraulic operating device 10. As shown in FIG. 4, when the movable piece 75f moves in the arrow Y2 direction, the valve main body 75b moves in the arrow X1 direction via the link lever 75e and the valve pressing shaft 75a. At this time, since the circuit opening port 72 and the second drainage port 26 are connected and the inside of the third liquid chamber 37 becomes a low pressure, as shown in FIG. To move to the second open position. As a result, the second control port 24 and the second drainage port 26 are connected.

この際、第2の液室33内の作動液は、第2の制御ポート24及び第2の排液ポート26を経て、低圧タンク17内に回収される。これにより、第2の液室33内の圧力は低下する。このようにして第2の液室33内が低圧になっている状態では、排液弁46は、図4に示すように、排液弁用バネ48の付勢力に抗しつつ、給液弁45と一体となって矢印X2方向に押されて第4の開路位置に移動し、第1の制御ポート21と第1の排液ポート23との間を接続する。   At this time, the hydraulic fluid in the second liquid chamber 33 is collected in the low-pressure tank 17 through the second control port 24 and the second drainage port 26. Thereby, the pressure in the 2nd liquid chamber 33 falls. Thus, in a state where the inside of the second liquid chamber 33 is at a low pressure, the liquid discharge valve 46 resists the urging force of the liquid discharge valve spring 48 as shown in FIG. The first control port 21 and the first drainage port 23 are connected to each other by being pushed in the direction of the arrow X2 together with 45 and moved to the fourth open circuit position.

この場合、第1の制御ポート21及び第1の排液ポート23を通じて第1の液室31内の作動液は、低圧タンク17内に回収される。これにより、第1の液室31内の圧力が低下することになる。第1の液室31内の圧力が低下したことにより、図1に示すように、可動電極3は、矢印Y1方向に上昇して第1の開路位置に移動し固定電極2から離間することになる。このようにして、液圧操作装置10は、開路状態への移行を完了したことになる。   In this case, the working fluid in the first liquid chamber 31 is collected in the low-pressure tank 17 through the first control port 21 and the first drainage port 23. Thereby, the pressure in the 1st liquid chamber 31 falls. As the pressure in the first liquid chamber 31 decreases, the movable electrode 3 moves upward in the direction of the arrow Y1 and moves to the first open position as shown in FIG. Become. In this way, the hydraulic pressure operating device 10 has completed the transition to the open circuit state.

上記したように、本実施形態の液圧操作装置10は、主操作弁ユニット9の第1の制御ポート21の圧力を増減させることで、接続されている第1の液室31内の圧力を制御し、電極移動機構12の動作を制御している。この動作を繰り返すことで、可動電極3による開閉動作を連続的に行うことが可能である。なお、アキュムレータ19内の液圧は低下するが、一定の圧力を下回ると液圧ポンプ18が動作して圧力を再上昇させる。圧力検出部8aは、この変動する圧力を監視している。   As described above, the hydraulic pressure operating device 10 of the present embodiment increases or decreases the pressure in the first control port 21 of the main operating valve unit 9 to increase the pressure in the connected first liquid chamber 31. And the operation of the electrode moving mechanism 12 is controlled. By repeating this operation, the opening / closing operation by the movable electrode 3 can be continuously performed. In addition, although the hydraulic pressure in the accumulator 19 falls, if it falls below a fixed pressure, the hydraulic pump 18 will operate | move and will raise a pressure again. The pressure detector 8a monitors the fluctuating pressure.

また、本実施形態の液圧操作装置10は、第1の給液ポート22、第1の排液ポート23及び第1の制御ポート21を含むポート組と、第2の給液ポート25、第2の排液ポート26及び第2の制御ポート24を含むポート組と、のうちの少なくとも一方のポート組の各ポート上にそれぞれ設けられた後述する複数の閉止弁(第1の閉止弁)及び複数の第2の閉止弁を、ストップバルブ(Closed Nozzle Shutoff Valve)として備えている。   Further, the hydraulic pressure operating device 10 of the present embodiment includes a port set including the first liquid supply port 22, the first liquid discharge port 23, and the first control port 21, the second liquid supply port 25, the first liquid supply port 25, and the second liquid supply port 25. A port set including two drain ports 26 and a second control port 24, and a plurality of shut-off valves (first shut-off valves) to be described later provided on each port of at least one of the port sets; A plurality of second closing valves are provided as a closed valve (Closed Nozzle Shutoff Valve).

つまり、本実施形態では、上記した少なくとも一方のポート組の各ポートを前記閉止弁を用いて閉止する工程と、前記閉止弁による閉止状態で、電極駆動ユニット14とパイロット弁ユニット(切換弁ユニット)68と主操作弁ユニット(給排液弁ユニット)9とのうちの少なくとも一つのユニット内の損傷を検出する工程と、を有する液圧操作装置の検査方法が実行可能となる。   That is, in the present embodiment, the electrode driving unit 14 and the pilot valve unit (switching valve unit) are closed in the step of closing each port of the above-described at least one port set using the closing valve and in the closed state by the closing valve. 68 and a step of detecting damage in at least one of the main operation valve unit (supply / drainage liquid valve unit) 9 can be executed.

具体的には、液圧操作装置10は、パイロット弁ユニット68の弁ケース78の開路用ポート72上に設けられた開路ポート閉止弁81と、閉路用ポート74上に設けられた閉路ポート閉止弁82と、を第2の閉止弁として備えている。これらの閉止弁は、通常時は開放して使用するものの、外部から液圧操作装置10へ与えられる閉止指令などに応じて閉止させることで、図6に示すように、開路用ポート72と開路用電磁弁ユニット15、及び、閉路用ポート74と閉路用電磁弁ユニット16、をそれぞれ切り離すことが可能なように構成されている。   Specifically, the hydraulic operating device 10 includes an open port closing valve 81 provided on the opening port 72 of the valve case 78 of the pilot valve unit 68 and a closed port closing valve provided on the closing port 74. 82 as a second shut-off valve. These closing valves are normally opened and used, but are closed according to a closing command or the like given to the hydraulic pressure operating device 10 from the outside, thereby opening the opening port 72 and the opening circuit as shown in FIG. And the closing port 74 and the closing solenoid valve unit 16 can be separated from each other.

例えば、弁本体部75b、76b若しくはシート部75d、76dのいずれかが損傷し、開路用電磁弁ユニット15及び閉路用電磁弁ユニット16で高圧の作動液を保持できなくなった場合に、開路ポート閉止弁81、又は、閉路ポート閉止弁82を閉止することで、損傷部側がアキュムレータ19側から切り離されるため、高圧の作動液を保持することが可能となる。この場合、高圧の作動液のリーク箇所が、開路用電磁弁ユニット15、又は、閉路用電磁弁ユニット16にあると特定することができる。一方、開路ポート閉止弁81、又は、閉路ポート閉止弁82を閉止しても高圧の作動液を保持できない場合、リーク箇所は、開路用電磁弁ユニット15及び閉路用電磁弁ユニット16とは別の箇所にあると判断できる。   For example, when one of the valve main body portions 75b and 76b or the seat portions 75d and 76d is damaged and the high-pressure hydraulic fluid cannot be held by the open-circuit solenoid valve unit 15 and the close-circuit solenoid valve unit 16, the open-circuit port is closed. By closing the valve 81 or the closed port closing valve 82, the damaged portion side is separated from the accumulator 19 side, so that high-pressure hydraulic fluid can be held. In this case, it is possible to specify that the leak point of the high-pressure hydraulic fluid is in the opening solenoid valve unit 15 or the closing solenoid valve unit 16. On the other hand, if the high-pressure hydraulic fluid cannot be retained even if the open port closing valve 81 or the closed port closing valve 82 is closed, the leak location is different from the open solenoid valve unit 15 and the close solenoid valve unit 16. It can be judged that it exists

また、第2の排液ポート26上(閉止弁として後述する切換弁排液ポート閉止弁 の設置位置とは異なる第2の排液ポート26上の所定位置)には、電磁弁排液ポート閉止弁83が第2の閉止弁として設けられている。この電磁弁排液ポート閉止弁83は、通常時では開放して使用するものの、外部からの閉止指令などに応じて閉止することで、第2の排液ポート26と開路用電磁弁ユニット15及び閉路用電磁弁ユニット16とが、図6に示すように、低圧タンク17側から切り離されるため、低圧タンク17内に蓄えられている低圧の作動液の流出を防止することができる。以上により、開路用電磁弁ユニット15及び閉路用電磁弁ユニット16で作動液のリーク(漏洩)などがあった場合でも、高圧の作動液や、低圧タンク17内の低圧の作動液を残したままでも、開路用電磁弁ユニット15及び閉路用電磁弁ユニット16を取り外すことが可能となる。   On the second drainage port 26 (a predetermined position on the second drainage port 26 different from the installation position of the switching valve drainage port closing valve described later as a shutoff valve), the solenoid valve drainage port is closed. A valve 83 is provided as a second closing valve. The solenoid valve drain port closing valve 83 is normally opened and used. However, the solenoid valve drain port closing valve 83 is closed according to an external closing command or the like, so that the second drain port 26 and the opening solenoid valve unit 15 and Since the closing solenoid valve unit 16 is disconnected from the low-pressure tank 17 side as shown in FIG. 6, the low-pressure hydraulic fluid stored in the low-pressure tank 17 can be prevented from flowing out. As described above, even when there is a leakage (leakage) of the hydraulic fluid in the opening solenoid valve unit 15 and the closing solenoid valve unit 16, the high-pressure hydraulic fluid or the low-pressure hydraulic fluid in the low-pressure tank 17 remains. However, the opening solenoid valve unit 15 and the closing solenoid valve unit 16 can be removed.

同様に、主操作弁ユニット9の主操作弁ケース43、ガイドケース43a内において、第2の制御ポート24上と、第2の給液ポート25上と、第2の排液ポート26上と、にそれぞれ、切換弁制御ポート閉止弁84、切換弁給液ポート閉止弁85、切換弁排液ポート閉止弁86が閉止弁(第1の閉止弁)として設けられている。これらの閉止弁は、通常時では開放して使用するものの、外部からの閉止指令などに応じて閉止することで、主操作弁ユニット9内における第2の制御ポート24、第2の給液ポート25及び第2の排液ポート26と、パイロット弁ユニット68とを、図6に示すように、切り離すことを可能とする。   Similarly, in the main operation valve case 43 and the guide case 43a of the main operation valve unit 9, on the second control port 24, on the second liquid supply port 25, on the second drainage port 26, In addition, a switching valve control port closing valve 84, a switching valve supply port closing valve 85, and a switching valve drain port closing valve 86 are provided as closing valves (first closing valves), respectively. Although these shut-off valves are normally opened and used, they are closed in accordance with an external shut-off command or the like, whereby the second control port 24 and the second liquid supply port in the main operation valve unit 9 are used. 25 and the second drainage port 26 and the pilot valve unit 68 can be disconnected as shown in FIG.

例えば、切換弁41、若しくは、シート部42などで損傷が生じ、高圧の作動液が保持できなくなったときに、切換弁制御ポート閉止弁84、切換弁給液ポート閉止弁85を用いて、第2の制御ポート24、第2の給液ポート25を閉止することで、損傷部側とアキュムレータ19側とを切り離することが可能となるため、高圧の作動液を保持することができる。この場合、高圧の作動液のリーク箇所がパイロット弁ユニット68内にあるものとして特定できる。一方、第2の制御ポート24と第2の給液ポート25とを閉止しても高圧の作動液を保持できない場合、リーク箇所は、パイロット弁ユニット68と、高圧の作動液の流路が下流にある開路用電磁弁ユニット15や閉路用電磁弁ユニット16とは、別の箇所にあると判断できる。また、切換弁排液ポート閉止弁86を閉止することで、パイロット弁ユニット68と第2の排液ポート26が、低圧タンク17側から切り離されるため、低圧タンク17内に蓄えられている低圧の作動液の流出防止を図れる。以上により、パイロット弁ユニット68でリークがあった場合に高圧の作動液や、低圧タンク17内の低圧の作動液を残したままでも、パイロット弁ユニット68の取り外しが可能となる。   For example, when the switching valve 41 or the seat portion 42 is damaged and the high-pressure hydraulic fluid cannot be retained, the switching valve control port closing valve 84 and the switching valve liquid supply port closing valve 85 are used. By closing the second control port 24 and the second liquid supply port 25, it is possible to separate the damaged portion side from the accumulator 19 side, so that high-pressure hydraulic fluid can be held. In this case, it can be specified that the leak point of the high-pressure hydraulic fluid is in the pilot valve unit 68. On the other hand, if the high-pressure hydraulic fluid cannot be held even when the second control port 24 and the second liquid supply port 25 are closed, the leak point is that the pilot valve unit 68 and the high-pressure hydraulic fluid flow path are downstream. It can be determined that the opening solenoid valve unit 15 and the closing solenoid valve unit 16 are located at different locations. Further, by closing the switching valve drain port closing valve 86, the pilot valve unit 68 and the second drain port 26 are disconnected from the low pressure tank 17 side, so that the low pressure stored in the low pressure tank 17 is reduced. Prevents hydraulic fluid from flowing out. As described above, when there is a leak in the pilot valve unit 68, the pilot valve unit 68 can be removed even if the high-pressure hydraulic fluid or the low-pressure hydraulic fluid in the low-pressure tank 17 remains.

さらに、低圧タンク17に通じる第1の排液ポート23上、第1の制御ポート21上、第1の給液ポート22上、にはそれぞれ主操作弁排液ポート閉止弁87、主操作弁制御ポート閉止弁88、主操作弁給液ポート閉止弁89が設けられている。これらの閉止弁(第1の閉止弁)は、通常時では開放して使用するものの、外部からの閉止指令などに応じて閉止することで、第1の排液ポート23、第1の制御ポート21及び第1の給液ポート22と、主操作弁ユニット9と、を切り離すことが可能となるように構成されている。   Further, a main operation valve drain port closing valve 87 and a main operation valve control are respectively provided on the first drain port 23, the first control port 21, and the first feed port 22 that communicate with the low pressure tank 17. A port closing valve 88 and a main operation valve liquid supply port closing valve 89 are provided. Although these shut-off valves (first shut-off valves) are normally opened and used, they are closed according to a shut-off command from the outside, etc., so that the first drain port 23 and the first control port are used. 21 and the first liquid supply port 22 and the main operation valve unit 9 can be separated.

排液弁46やシート部51、若しくは給液弁45やシート部49にて損傷が生じ、高圧の作動液が保持できなくなったときに、主操作弁制御ポート閉止弁88、主操作弁給液ポート閉止弁89を閉止させることで、損傷部側がアキュムレータ19側から切り離されるため、高圧の作動液が保持されるようになる。この場合、高圧の作動液のリーク箇所が主操作弁ユニット9内にあると特定することができる。一方で、主操作弁制御ポート閉止弁88と主操作弁給液ポート閉止弁89を閉止しても、高圧の作動液が保持できない場合には、リーク箇所が、開路用電磁弁ユニット15、閉路用電磁弁ユニット16、パイロット弁ユニット68、主操作弁ユニット9とは別の箇所にあると判断できる。また、主操作弁排液ポート閉止弁87を閉止することで、主操作弁ユニット9が低圧タンク17側から切り離されるため、低圧タンク17内に蓄えられている低圧の作動液の流出防止を図ることができる。以上により、主操作弁ユニット9でリークがあった場合に高圧の作動液や、低圧タンク17内の作動液を維持したままでも、主操作弁ユニット9の取り外しが可能となる。   When the drainage valve 46 or the seat portion 51 or the liquid supply valve 45 or the seat portion 49 is damaged and the high-pressure hydraulic fluid cannot be retained, the main operation valve control port closing valve 88 and the main operation valve supply fluid By closing the port closing valve 89, the damaged portion side is separated from the accumulator 19 side, so that high-pressure hydraulic fluid is held. In this case, it is possible to specify that the leak point of the high-pressure hydraulic fluid is in the main operation valve unit 9. On the other hand, even if the main operation valve control port closing valve 88 and the main operation valve liquid supply port closing valve 89 are closed, if the high-pressure hydraulic fluid cannot be retained, the leak location is the opening solenoid valve unit 15, the closing circuit. It can be determined that the electromagnetic valve unit 16, the pilot valve unit 68, and the main operation valve unit 9 are in different locations. Moreover, since the main operation valve unit 9 is disconnected from the low pressure tank 17 side by closing the main operation valve drain port closing valve 87, it is intended to prevent the low pressure hydraulic fluid stored in the low pressure tank 17 from flowing out. be able to. As described above, when there is a leak in the main operation valve unit 9, the main operation valve unit 9 can be removed even while maintaining the high-pressure hydraulic fluid or the hydraulic fluid in the low-pressure tank 17.

したがって、各種の弁やシート部などの損傷によって高圧の作動液を保持できなくなった際に、上記した各閉止弁を用いてリーク箇所を特定することができる。さらに、アキュムレータ19内の高圧の作動液と低圧タンク17の低圧の作動液とをそれぞれ保持したまま、図6に示すように、開路用電磁弁ユニット15、閉路用電磁弁ユニット16、パイロット弁ユニット68、主操作弁ユニット9の取外しが可能となる。また、このような閉止弁は、上記した各ポート上に組み込むことができるので、閉止弁設置のために新たに流路を設ける必要がなく、液圧操作装置10の小型化などを可能とする。   Therefore, when the high-pressure hydraulic fluid cannot be held due to damage to various valves or seats, the leak location can be specified using each of the above-described stop valves. Further, as shown in FIG. 6, while holding the high pressure hydraulic fluid in the accumulator 19 and the low pressure hydraulic fluid in the low pressure tank 17, as shown in FIG. 6, the open solenoid valve unit 15, the close solenoid valve unit 16, the pilot valve unit. 68. The main operation valve unit 9 can be removed. In addition, since such a shut-off valve can be incorporated on each port described above, it is not necessary to provide a new flow path for installing the shut-off valve, and the hydraulic pressure operating device 10 can be downsized. .

また、これらの閉止弁は、流路を閉止する過程でそれぞれの流路を絞っていくことができるため、これを可動絞りとしての利用することも可能である。開路ポート閉止弁81及び閉路ポート閉止弁82を、可動絞りとして流路を絞ることで、切換弁41の動作する速度が遅くなるため、開路動作及び閉路動作のタイミング調整が可能である。さらに、主操作弁制御ポート閉止弁88及び主操作弁給液ポート閉止弁89を可動絞りとして流路を絞ることで、第1の液室31に供給される高圧の作動液の供給及び排出の際の損失が増加し、駆動ピストン6の速度の調整が可能になる。   Moreover, since these shut-off valves can narrow down each flow path in the process of closing the flow path, they can also be used as movable restrictors. By restricting the flow path by using the open port closing valve 81 and the closed port closing valve 82 as a movable restrictor, the operation speed of the switching valve 41 is reduced, and therefore the timing of the opening operation and the closing operation can be adjusted. Further, by restricting the flow path using the main operation valve control port closing valve 88 and the main operation valve liquid supply port closing valve 89 as a movable throttle, supply and discharge of the high-pressure hydraulic fluid supplied to the first liquid chamber 31 are reduced. Loss increases and the speed of the drive piston 6 can be adjusted.

既述したように、第1の実施形態によれば、保守性の向上及び小型化を図れる液圧操作装置10及びその検査方法を提供することができる。   As described above, according to the first embodiment, it is possible to provide the hydraulic operating device 10 and the inspection method thereof that can improve the maintainability and reduce the size.

<第2の実施の形態>
次に、第2の実施形態を図7に基づき説明する。なお、図7において、図6に示した第1の実施形態中の構成要素と同一の構成要素については、同一の符号を付与し重複する説明を省略する。
<Second Embodiment>
Next, a second embodiment will be described with reference to FIG. In FIG. 7, the same constituent elements as those in the first embodiment shown in FIG.

図7に示すように、第2の実施形態の液圧操作装置30は、第1の実施形態の液圧操作装置10が備えていた電磁弁排液ポート閉止弁83、切換弁排液ポート閉止弁86、主操作弁排液ポート閉止弁87に代えて、電磁弁排液ポート逆止弁83a、切換弁排液ポート逆止弁86a、主操作弁排液ポート逆止弁87aを、複数の第1の逆止弁(Check Valve/逆流防止弁)として備えている。低圧タンク17にそれぞれ接続された分岐流路73、第2の制御ポート24、第1の排液ポート23を流れる作動液の流れの方向は、常に低圧タンク17側へ向っている。   As shown in FIG. 7, the hydraulic operating device 30 of the second embodiment includes an electromagnetic valve drain port closing valve 83 and a switching valve drain port closing provided in the hydraulic operating device 10 of the first embodiment. Instead of the valve 86 and the main operation valve drainage port closing valve 87, a solenoid valve drainage port check valve 83a, a switching valve drainage port check valve 86a, and a main operation valve drainage port check valve 87a are provided. It is provided as a first check valve (Check Valve / check valve). The direction of the flow of hydraulic fluid flowing through the branch flow path 73, the second control port 24, and the first drainage port 23 respectively connected to the low pressure tank 17 is always directed to the low pressure tank 17 side.

したがって、第2の実施形態の液圧操作装置30によれば、図7に示すように、個々のユニットを取り外す際に、低圧タンク17内に蓄えられた低圧の作動液の流出防止を図ることができる。また、開放している閉止弁を閉止させるといった作業などが必要なく、さらには、復旧後に閉止弁を再度開放させるといった作業なども必要ないため、メンテナンス時の作業効率のさらなる向上を図れる。また、閉止弁の開放忘れなどよる動作不良を防止できるため、装置の信頼性の向上に寄与する。   Therefore, according to the hydraulic pressure operating device 30 of the second embodiment, as shown in FIG. 7, when removing individual units, it is possible to prevent the low-pressure hydraulic fluid stored in the low-pressure tank 17 from flowing out. Can do. Further, it is not necessary to perform an operation such as closing the opened stop valve, and further, it is not necessary to perform an operation such as opening the close valve again after the restoration, so that the work efficiency during maintenance can be further improved. In addition, since it is possible to prevent malfunction due to forgetting to open the shut-off valve, it contributes to improvement of the reliability of the apparatus.

<第3の実施の形態>
次に、第3の実施形態を図8、図9に基づき説明する。なお、図8、図9において、図1〜6に示した第1の実施形態中の構成要素と同一の構成要素については、同一の符号を付与し重複する説明を省略する。
<Third Embodiment>
Next, a third embodiment will be described with reference to FIGS. 8 and 9, the same components as those in the first embodiment shown in FIGS. 1 to 6 are given the same reference numerals and redundant description is omitted.

図8、図9に示すように、第3の実施形態の液圧操作装置では、圧力スイッチユニット8の周辺における圧力スイッチ給液ポート28上及び圧力スイッチ排液ポート29上に、圧力スイッチ給液ポート閉止弁91及び圧力スイッチ排液ポート閉止弁92を、第3の閉止弁としてそれぞれ備えている。圧力スイッチユニット8内で高圧の作動液を保持できないリークが発生した場合、図8に示すように、平常時には開放している圧力スイッチ給液ポート閉止弁91を、図9に示すように、閉止することで、損傷部側がアキュムレータ19側から切り離されるため、高圧の作動液が保持されるようになる。   As shown in FIGS. 8 and 9, in the hydraulic pressure operating device of the third embodiment, the pressure switch liquid supply is provided on the pressure switch liquid supply port 28 and the pressure switch drain port 29 around the pressure switch unit 8. A port closing valve 91 and a pressure switch drain port closing valve 92 are provided as third closing valves, respectively. When a leak that cannot hold the high-pressure hydraulic fluid occurs in the pressure switch unit 8, the pressure switch liquid supply port closing valve 91 that is normally open as shown in FIG. 8 is closed as shown in FIG. By doing so, the damaged portion side is separated from the accumulator 19 side, so that the high-pressure hydraulic fluid is held.

この場合、リーク箇所が圧力スイッチユニット8内にあると特定することができる。一方で、圧力スイッチ排液ポート閉止弁92を閉止しても高圧の作動液を保持できない場合には、リーク箇所が圧力スイッチユニット8とは別の箇所にあると判断できる。さらに、図9に示すように、圧力スイッチ排液ポート閉止弁92を閉止することで低圧タンク17内に蓄えられている低圧液の流出防止を図ることができる。   In this case, it can be specified that the leak location is in the pressure switch unit 8. On the other hand, if the high-pressure hydraulic fluid cannot be retained even when the pressure switch drain port closing valve 92 is closed, it can be determined that the leak location is at a location different from the pressure switch unit 8. Furthermore, as shown in FIG. 9, by closing the pressure switch drain port closing valve 92, it is possible to prevent the low pressure liquid stored in the low pressure tank 17 from flowing out.

このように、第3の実施形態の液圧操作装置によれば、圧力スイッチユニット8の内部で高圧の作動液の保持ができなくなった際に、上記閉止弁によりリーク箇所を特定でき、さらに、アキュムレータ19側の高圧の作動液と、低圧タンク17内の低圧の作動液を残したまま、図9に示すように、圧力スイッチユニット8の取外しが可能となる。また、このような閉止弁は、上記した各ポート上に組み込むことができるので、閉止弁設置のために新たに流路を設ける必要がなく、液圧操作装置10の小型化などが可能となる。   As described above, according to the hydraulic pressure operating device of the third embodiment, when the high-pressure hydraulic fluid cannot be held inside the pressure switch unit 8, the leak point can be specified by the shut-off valve. As shown in FIG. 9, the pressure switch unit 8 can be removed while leaving the high pressure hydraulic fluid on the accumulator 19 side and the low pressure hydraulic fluid in the low pressure tank 17. In addition, since such a shut-off valve can be incorporated on each port described above, it is not necessary to provide a new flow path for installing the shut-off valve, and the hydraulic pressure operating device 10 can be downsized. .

<第4の実施の形態>
次に、第4の実施形態を図10、図11に基づき説明する。なお、図10、図11において、図8、図9に示した第3の実施形態中の構成要素と同一の構成要素については、同一の符号を付与し重複する説明を省略する。
<Fourth embodiment>
Next, a fourth embodiment will be described with reference to FIGS. 10 and 11, the same components as those in the third embodiment shown in FIGS. 8 and 9 are given the same reference numerals, and redundant description is omitted.

図10、図11に示すように、第4の実施形態の液圧操作装置は、第3の実施形態の圧力スイッチ排液ポート閉止弁92に代えて、圧力スイッチ排液ポート逆止弁92aを第3の逆止弁として備えている。低圧タンク17に接続された圧力スイッチ排液ポート29を流れる作動液の流れの方向は、常に低圧タンク17側へ向っている。   As shown in FIGS. 10 and 11, the hydraulic pressure operating device of the fourth embodiment has a pressure switch drainage port check valve 92a instead of the pressure switch drainage port closing valve 92 of the third embodiment. It is provided as a third check valve. The direction of the flow of the hydraulic fluid flowing through the pressure switch drain port 29 connected to the low pressure tank 17 is always directed to the low pressure tank 17 side.

したがって、第4の実施形態の液圧操作装置によれば、図11に示すように、圧力スイッチユニット8を取り外す際に、低圧タンク17内に蓄えられた低圧の作動液の流出を抑制することができる。また、開放している閉止弁を閉止させるといった作業などが必要なく、さらには、復旧後に閉止弁を再度開放させるといった作業なども必要ないため、メンテナンス時の作業効率を向上させることができる。また、閉止弁の開放忘れなどよる動作不良を防止できるため、装置の信頼性を高めることが可能となる。   Therefore, according to the hydraulic pressure operating device of the fourth embodiment, as shown in FIG. 11, when the pressure switch unit 8 is removed, the outflow of the low-pressure hydraulic fluid stored in the low-pressure tank 17 is suppressed. Can do. Further, it is not necessary to perform an operation such as closing the opened stop valve, and further, it is not necessary to perform an operation such as opening the close valve again after the recovery, so that the work efficiency during maintenance can be improved. In addition, since it is possible to prevent malfunction due to forgetting to open the closing valve, it is possible to improve the reliability of the apparatus.

<比較例>
次に、図12に基づき比較例の液圧操作装置100について簡易的に説明する。比較例の液圧操作装置100は、小型化を実現するために電極駆動ユニット114の下部には、アキュムレータ119を備え、上部には、主操作弁ユニット109、パイロット弁ユニット168、低圧タンク117を備え、側部には、液圧ポンプ118を配置した構造としている。この構造では、各ユニットを集積化して小型化を図ると共に、排液ポート123、129の距離を短くできるため、大径で長尺な配管を設ける必要がなく、作動液の使用量も少なくなるため、製作コストの削減にもつなげることができる。
<Comparative example>
Next, the hydraulic operating device 100 of the comparative example will be briefly described with reference to FIG. The hydraulic pressure operating device 100 of the comparative example is provided with an accumulator 119 at the lower part of the electrode drive unit 114 in order to reduce the size, and a main operating valve unit 109, a pilot valve unit 168, and a low pressure tank 117 at the upper part. The hydraulic pump 118 is arranged on the side portion. In this structure, each unit is integrated to reduce the size, and the distance between the drain ports 123 and 129 can be shortened. Therefore, there is no need to provide a large-diameter and long pipe, and the amount of hydraulic fluid used is also reduced. Therefore, the manufacturing cost can be reduced.

しかしながら、個々の弁体は、高圧の作動液による力やばねの付勢力によってシート部に押し付けられることで高圧の作動液を保持できるものの、それぞれの弁体とシート部とが接触する際に、作動液内の異物を噛み込むなどして、弁体の表面やシート部に傷がつき、高圧の作動液の保持が不能になることがある。   However, although the individual valve bodies can hold the high-pressure hydraulic fluid by being pressed against the seat portion by the force of the high-pressure hydraulic fluid or the biasing force of the spring, when each valve body and the seat portion come into contact, When the foreign substance in the hydraulic fluid is bitten, the surface of the valve body and the seat portion may be damaged, and the high-pressure hydraulic fluid may not be retained.

この場合、傷が付きリークが発生している箇所の特定を行い、異常個所のみを交換し、復旧させることが保守費用の低減につながるが、小型化を図った比較例の液圧操作装置100においては、各部が集約されているために、例えば異常音の測定などによって外部からリーク箇所を検出することなどが困難となる。   In this case, it is possible to identify a spot where a flaw has occurred and a leak has occurred, and to replace and restore only the abnormal part, leading to a reduction in maintenance costs. In this case, since each part is integrated, it is difficult to detect a leak location from the outside by measuring abnormal sound, for example.

また、液圧制御ユニット161への空気の混入を防止するために低圧タンク117内の液面は、液圧制御ユニット161より高くなるため、交換のために液圧制御ユニット161や電磁弁ユニット175、176を取外す際には、低圧タンク117内の作動液をすべて排出する必要がある。以上より、多くの場合、異常を復旧させる際には、作動液を排出するポンプを用意するなど、大掛かりな作業が必要になるか、液圧操作装置100全体の交換が必要となる。   Further, since the liquid level in the low-pressure tank 117 is higher than the hydraulic pressure control unit 161 in order to prevent air from entering the hydraulic pressure control unit 161, the hydraulic pressure control unit 161 and the electromagnetic valve unit 175 are replaced for replacement. When removing 176, it is necessary to discharge all the hydraulic fluid in the low-pressure tank 117. As described above, in many cases, when recovering from an abnormality, a large-scale operation such as preparing a pump for discharging the hydraulic fluid is required, or the entire hydraulic operation device 100 needs to be replaced.

これに対して、第1〜第4の実施形態の液圧操作装置は、上記した各種のポート上に閉止弁や逆止弁を備えていることで、前述したように保守性の向上や小型化を図ることが可能となる。   On the other hand, the hydraulic pressure operating devices of the first to fourth embodiments are provided with a closing valve and a check valve on the above-described various ports, thereby improving the maintainability and reducing the size as described above. Can be achieved.

以上、本発明のいくつかの実施形態を説明したが、これらの実施形態は、例として提示したものであり、発明の範囲を限定することは意図していない。これら新規な実施形態は、その他の様々な形態で実施することが可能であり、発明の要旨を逸脱しない範囲で、種々の省略、置き換え、変更を行うことができる。これらの実施形態やその変形例は、発明の範囲や要旨に含まれると共に、特許請求の範囲に記載された発明とその均等の範囲に含まれる。   As mentioned above, although some embodiment of this invention was described, these embodiment is shown as an example and is not intending limiting the range of invention. These novel embodiments can be implemented in various other forms, and various omissions, replacements, and changes can be made without departing from the spirit of the invention. These embodiments and modifications thereof are included in the scope and gist of the invention, and are included in the invention described in the claims and the equivalents thereof.

2…固定電極、3…可動電極、8…圧力スイッチユニット、9…主操作弁ユニット、10,30…液圧操作装置、12…電極移動機構、14…電極駆動ユニット、15…開路用電磁弁ユニット、16…閉路用電磁弁ユニット、17…低圧タンク、19…アキュムレータ、21…第1の制御ポート、22…第1の給液ポート、23…第1の排液ポート、24…第2の制御ポート、25…第2の給液ポート、26…第2の排液ポート、31…第1の液室、32…第5の液室、33…第2の液室、35…第4の液室、37…第3の液室、41…切換弁、45…給液弁、46…排液弁、61…液圧制御ユニット、68…パイロット弁ユニット、72…開路用ポート、74…閉路用ポート、75…開路用ソレノイド、76…閉路用ソレノイド、81…開路ポート閉止弁、82…閉路ポート閉止弁、83…電磁弁排液ポート閉止弁、83a…電磁弁排液ポート逆止弁、84…切換弁制御ポート閉止弁、85…切換弁給液ポート閉止弁、86…切換弁排液ポート閉止弁、86a…切換弁排液ポート逆止弁、87…主操作弁排液ポート閉止弁、87a…主操作弁排液ポート逆止弁、88…主操作弁制御ポート閉止弁、88…制御ポート閉止弁、89…主操作弁給液ポート閉止弁、91…圧力スイッチ給液ポート閉止弁、92…圧力スイッチ排液ポート閉止弁、92a…圧力スイッチ排液ポート逆止弁。   DESCRIPTION OF SYMBOLS 2 ... Fixed electrode, 3 ... Movable electrode, 8 ... Pressure switch unit, 9 ... Main operation valve unit, 10, 30 ... Fluid pressure operation apparatus, 12 ... Electrode moving mechanism, 14 ... Electrode drive unit, 15 ... Electromagnetic valve for circuit opening Unit: 16 ... Solenoid valve unit for closing, 17 ... Low pressure tank, 19 ... Accumulator, 21 ... First control port, 22 ... First liquid supply port, 23 ... First drain port, 24 ... Second Control port 25 ... Second liquid supply port 26 ... Second drainage port 31 ... First liquid chamber 32 ... Fifth liquid chamber 33 ... Second liquid chamber 35 ... fourth Liquid chamber, 37 ... third liquid chamber, 41 ... switching valve, 45 ... liquid supply valve, 46 ... drain valve, 61 ... hydraulic pressure control unit, 68 ... pilot valve unit, 72 ... opening port, 74 ... closed circuit Port, 75 ... solenoid for opening, 76 ... solenoid for closing, 81 ... open Port closing valve, 82 ... Closed port closing valve, 83 ... Solenoid valve drainage port closing valve, 83a ... Solenoid valve drainage port check valve, 84 ... Switching valve control port closing valve, 85 ... Switching valve feed port closing valve 86 ... Switching valve drainage port closing valve, 86a ... Switching valve drainage port check valve, 87 ... Main operation valve drainage port closing valve, 87a ... Main operation valve drainage port check valve, 88 ... Main operation valve Control port closing valve, 88 ... Control port closing valve, 89 ... Main operation valve feed port closing valve, 91 ... Pressure switch feed port closing valve, 92 ... Pressure switch drain port closing valve, 92a ... Pressure switch drain port Check valve.

Claims (8)

昇圧された作動液を第1の給液ポート側に向けて給液するアキュムレータと、
第1の排液ポートを介して作動液を回収する低圧タンクと、
第1の制御ポートを介して作動液が出入りする第1の液室内の圧力に応じて、遮断器の可動電極が、前記遮断器の固定電極から離間する第1の開路位置と前記固定電極に接触する第1の閉路位置との間で、前記可動電極を移動させる電極移動機構を含む電極駆動ユニットと、
第2の排液ポートと第2の制御ポートとを接続する第2の開路位置と、前記第1の給液ポートにつながる第2の給液ポートと前記第2の制御ポートとを接続する第2の閉路位置と、の間で移動する切換弁を含む切換弁ユニットと、
前記第2の制御ポートを介して作動液が出入りする第2の液室内の圧力に応じて、第3の開路位置と第3の閉路位置との間を移動し、前記第3の閉路位置に移動したときに、前記第1の制御ポートと前記第1の給液ポートとの間を接続する給液弁と、前記第2の液室内の圧力に応じて、前記給液弁と一体となって第4の開路位置と第4の閉路位置との間を移動し、前記第4の開路位置に移動したときに、前記第1の制御ポートと前記第1の排液ポートとの間を接続する排液弁と、を含む給排液弁ユニットと、
前記第1の給液ポート、前記第1の排液ポート及び前記第1の制御ポートを含むポート組と、前記第2の給液ポート、前記第2の排液ポート及び前記第2の制御ポートを含むポート組と、のうちの少なくとも一方のポート組の各ポート上にそれぞれ設けられた閉止弁と、
を備える液圧操作装置。
An accumulator for supplying the pressurized hydraulic fluid toward the first liquid supply port;
A low-pressure tank that collects the hydraulic fluid via the first drainage port;
According to the pressure in the first liquid chamber through which the working fluid enters and exits through the first control port, the movable electrode of the circuit breaker is connected to the first open position and the fixed electrode separated from the fixed electrode of the circuit breaker. An electrode driving unit including an electrode moving mechanism for moving the movable electrode between the first closed position and the first closed position,
A second open position for connecting the second drainage port and the second control port, and a second connection position for connecting the second liquid supply port connected to the first liquid supply port and the second control port. A switching valve unit including a switching valve that moves between two closed positions;
According to the pressure in the second fluid chamber through which the working fluid enters and exits via the second control port, the fluid moves between a third open position and a third closed position, and reaches the third closed position. When moved, the liquid supply valve connecting the first control port and the first liquid supply port is integrated with the liquid supply valve in accordance with the pressure in the second liquid chamber. The first control port and the first drainage port are connected when moved between the fourth open position and the fourth closed position. A drainage valve unit comprising: a drainage valve unit comprising:
A port set including the first liquid supply port, the first liquid discharge port, and the first control port; the second liquid supply port; the second liquid discharge port; and the second control port. A port set including: a closing valve provided on each port of at least one of the port sets;
A hydraulic operation device comprising:
前記第1又は第2の排液ポート上には、前記閉止弁に代えて逆止弁が設けられる、
請求項1記載の液圧操作装置。
On the first or second drainage port, a check valve is provided instead of the stop valve.
The hydraulic operation device according to claim 1.
前記切換弁は、開路用ポートを介して作動液が出入りする第3の液室内の圧力と閉路用ポートを介して作動液が出入りする第4の液室内の圧力とに応じて、前記第2の開路位置と前記第2の閉路位置との間を移動し、
前記開路用ポートと前記第2の排液ポートとの間を開閉するための開路用アクチュエータを含む開路用アクチュエータユニットと、
前記閉路用ポートと前記第2の排液ポートとの間を開閉するための閉路用アクチュエータを含む閉路用アクチュエータユニットと、
前記開路用ポート上と、前記閉路用ポート上と、前記閉止弁の設置位置とは異なる前記第2の排液ポート上の所定位置と、にそれぞれ設けられた第2の閉止弁と、
をさらに備える請求項1又は2記載の液圧操作装置。
The switching valve is responsive to the pressure in the third liquid chamber through which hydraulic fluid enters and exits through the opening port and the pressure in the fourth liquid chamber through which hydraulic fluid enters and exits through the closing port. Moving between the open position of the second and the second closed position,
An opening actuator unit including an opening actuator for opening and closing between the opening port and the second drainage port;
A closing actuator unit including a closing actuator for opening and closing between the closing port and the second drainage port;
A second closing valve provided on each of the opening port, the closing port, and a predetermined position on the second drainage port different from the installation position of the closing valve;
The hydraulic operation device according to claim 1 or 2, further comprising:
前記第2の排液ポート上の所定位置には、前記第2の閉止弁に代えて第2の逆止弁が設けられている、
請求項3記載の液圧操作装置。
A second check valve is provided at a predetermined position on the second drainage port instead of the second stop valve.
The hydraulic operation device according to claim 3.
前記電極駆動ユニットと前記給排液弁ユニットと前記切換弁ユニットと前記開路用アクチュエータユニットと前記閉路用アクチュエータユニットとは、着脱可能に構成されている、
請求項3又は4記載の液圧操作装置。
The electrode driving unit, the supply / drainage valve unit, the switching valve unit, the opening actuator unit, and the closing actuator unit are configured to be detachable.
The hydraulic operation device according to claim 3 or 4.
前記電極駆動ユニットは、
前記第1の給液ポートから分岐した圧力検出用給液ポート内における前記作動液の圧力を検出する圧力検出部と、
前記圧力検出用給液ポートと前記低圧タンクとの間を接続する圧力検出用排液ポート上と、前記圧力検出用給液ポート上と、にそれぞれ設けられた第3の閉止弁と、
を含む圧力監視ユニットを備える、
請求項1ないし5のいずれか1項に記載の液圧操作装置。
The electrode driving unit is
A pressure detection unit for detecting the pressure of the working fluid in the pressure detection liquid supply port branched from the first liquid supply port;
A third shut-off valve provided on each of the pressure detection drainage port connecting the pressure detection liquid supply port and the low pressure tank; and on the pressure detection liquid supply port;
Including a pressure monitoring unit including
The hydraulic operating device according to any one of claims 1 to 5.
前記圧力検出用排液ポート上には、前記第3の閉止弁に代えて第3の逆止弁が設けられている、
請求項6記載の液圧操作装置。
A third check valve is provided on the pressure detection drain port instead of the third stop valve.
The hydraulic operation device according to claim 6.
昇圧された作動液を第1の給液ポート側に向けて給液するアキュムレータと、
第1の排液ポートを介して作動液を回収する低圧タンクと、
第1の制御ポートを介して作動液が出入りする第1の液室内の圧力に応じて、遮断器の可動電極が、前記遮断器の固定電極から離間する第1の開路位置と前記固定電極に接触する第1の閉路位置との間で、前記可動電極を移動させる電極移動機構を含む電極駆動ユニットと、
第2の排液ポートと第2の制御ポートとを接続する第2の開路位置と、前記第1の給液ポートにつながる第2の給液ポートと前記第2の制御ポートとを接続する第2の閉路位置と、の間で移動する切換弁を含む切換弁ユニットと、
前記第2の制御ポートを介して作動液が出入りする第2の液室内の圧力に応じて、第3の開路位置と第3の閉路位置との間を移動し、前記第3の閉路位置に移動したときに、前記第1の制御ポートと前記第1の給液ポートとの間を接続する給液弁と、前記第2の液室内の圧力に応じて、前記給液弁と一体となって第4の開路位置と第4の閉路位置との間を移動し、前記第4の開路位置に移動したときに、前記第1の制御ポートと前記第1の排液ポートとの間を接続する排液弁と、を含む給排液弁ユニットと、
前記第1の給液ポート、前記第1の排液ポート及び前記第1の制御ポートを含むポート組と、前記第2の給液ポート、前記第2の排液ポート及び前記第2の制御ポートを含むポート組と、のうちの少なくとも一方のポート組の各ポート上にそれぞれ設けられた閉止弁と、
を備える液圧操作装置を検査するための液圧操作装置の検査方法であって、
前記少なくとも一方のポート組の各ポートを前記閉止弁を用いて閉止する工程と、
前記閉止弁による閉止状態で、前記電極駆動ユニットと前記切換弁ユニットと前記給排液弁ユニットとのうちの少なくとも一つのユニット内の損傷を検出する工程と、
を有する液圧操作装置の検査方法。
An accumulator for supplying the pressurized hydraulic fluid toward the first liquid supply port;
A low-pressure tank that collects the hydraulic fluid via the first drainage port;
According to the pressure in the first liquid chamber through which the working fluid enters and exits through the first control port, the movable electrode of the circuit breaker is connected to the first open position and the fixed electrode separated from the fixed electrode of the circuit breaker. An electrode driving unit including an electrode moving mechanism for moving the movable electrode between the first closed position and the first closed position,
A second open position for connecting the second drainage port and the second control port, and a second connection position for connecting the second liquid supply port connected to the first liquid supply port and the second control port. A switching valve unit including a switching valve that moves between two closed positions;
According to the pressure in the second fluid chamber through which the working fluid enters and exits via the second control port, the fluid moves between a third open position and a third closed position, and reaches the third closed position. When moved, the liquid supply valve connecting the first control port and the first liquid supply port is integrated with the liquid supply valve in accordance with the pressure in the second liquid chamber. The first control port and the first drainage port are connected when moved between the fourth open position and the fourth closed position. A drainage valve unit comprising: a drainage valve unit comprising:
A port set including the first liquid supply port, the first liquid discharge port, and the first control port; the second liquid supply port; the second liquid discharge port; and the second control port. A port set including: a closing valve provided on each port of at least one of the port sets;
An inspection method for a hydraulic operating device for inspecting a hydraulic operating device comprising:
Closing each port of the at least one port set using the stop valve;
Detecting damage in at least one of the electrode drive unit, the switching valve unit, and the supply / drainage valve unit in a closed state by the stop valve;
Method for inspecting hydraulic operating device having
JP2015195367A 2015-09-30 2015-09-30 Hydraulic operating device and inspection method thereof Active JP6470159B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015195367A JP6470159B2 (en) 2015-09-30 2015-09-30 Hydraulic operating device and inspection method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015195367A JP6470159B2 (en) 2015-09-30 2015-09-30 Hydraulic operating device and inspection method thereof

Publications (2)

Publication Number Publication Date
JP2017069112A JP2017069112A (en) 2017-04-06
JP6470159B2 true JP6470159B2 (en) 2019-02-13

Family

ID=58492710

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015195367A Active JP6470159B2 (en) 2015-09-30 2015-09-30 Hydraulic operating device and inspection method thereof

Country Status (1)

Country Link
JP (1) JP6470159B2 (en)

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5654513Y2 (en) * 1976-07-02 1981-12-18
JP2001289201A (en) * 2000-04-05 2001-10-19 Hitachi Constr Mach Co Ltd Drain circuit for hydraulic motor
JP4322399B2 (en) * 2000-05-31 2009-08-26 株式会社東芝 Hydraulic operation device

Also Published As

Publication number Publication date
JP2017069112A (en) 2017-04-06

Similar Documents

Publication Publication Date Title
US7322270B2 (en) Safety circuit for media-operated consumers and process for its operation
CN104736858A (en) A hydraulic system with a dynamic seal
JP5588260B2 (en) Aircraft actuator control system
RU2080456C1 (en) Hydraulic protective and power oil system for control of steam supply to turbine
CN115929730A (en) System and method for controlling and monitoring an actuated valve
CN107965610B (en) Method and apparatus for evaluating testing of solenoid valves via a positioner
JP2018123732A (en) Steam turbine valve driving device
KR101470310B1 (en) Valve Operation System for preventing water hammer
JP6470159B2 (en) Hydraulic operating device and inspection method thereof
RU2722289C2 (en) Pneumatic emergency shutdown system for turbine, drive assembly for pneumatic emergency shutdown system and checking method of shutoff valve of pneumatic emergency shutdown system
JP5960582B2 (en) Machine tools and motor pump units
US20160215650A1 (en) System and device for over-speed protection of a turbo-machine
KR101195935B1 (en) Apparatus of Electrical trip solenoid valve isolation block
KR101444921B1 (en) APPARATUS AND METHOD FOR test of instant pressure rise detecting switch
CN202280482U (en) Quick closing valve for steam turbine
KR101085997B1 (en) Safety Valve Bypass Element Guard
JP5782483B2 (en) Hydraulic unit and hydraulic system
JP2018077198A (en) Control device and abnormality diagnostic method of high-pressure fluid control valve
KR100346091B1 (en) Apparatus for driving fluid pressure in breaker
JP6320193B2 (en) Hydraulic operation device
JP5512611B2 (en) Circuit breaker fluid pressure driving apparatus and driving method thereof
KR20060036452A (en) Pressure release device for application in pressurised systems in power stations
CN213116403U (en) Three-out-of-two protection device for steam turbine protection and steam turbine
KR20200112472A (en) Method for testing quick closing of actuator for power plant
KR100840604B1 (en) Pilot valve unit for actuator control

Legal Events

Date Code Title Description
A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A712

Effective date: 20171201

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20171201

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180312

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20181207

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20181218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20190117

R150 Certificate of patent or registration of utility model

Ref document number: 6470159

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150