JP6381090B1 - Forming method of flanged pipe material - Google Patents

Forming method of flanged pipe material Download PDF

Info

Publication number
JP6381090B1
JP6381090B1 JP2017200757A JP2017200757A JP6381090B1 JP 6381090 B1 JP6381090 B1 JP 6381090B1 JP 2017200757 A JP2017200757 A JP 2017200757A JP 2017200757 A JP2017200757 A JP 2017200757A JP 6381090 B1 JP6381090 B1 JP 6381090B1
Authority
JP
Japan
Prior art keywords
pipe material
mold
flange portion
plastic flow
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017200757A
Other languages
Japanese (ja)
Other versions
JP2019072741A (en
Inventor
小松 隆
隆 小松
Original Assignee
リンツリサーチエンジニアリング株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by リンツリサーチエンジニアリング株式会社 filed Critical リンツリサーチエンジニアリング株式会社
Priority to JP2017200757A priority Critical patent/JP6381090B1/en
Application granted granted Critical
Publication of JP6381090B1 publication Critical patent/JP6381090B1/en
Publication of JP2019072741A publication Critical patent/JP2019072741A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Shaping Metal By Deep-Drawing, Or The Like (AREA)

Abstract

【課題】パイプ材内側からの高圧のみに頼るのではなく、金型のプレスする力を利用してパイプ材を金型形状に沿わせることを可能とし、更にフランジ部を薄肉且つ高強度、高精度に成形できる成形方法を提供する。【解決手段】金型100によって、パイプ材120にパイプ材120の長手方向に沿ったフランジ部122を形成し且つ金型100で形成される第1のキャビティ(上型凹部102a、下型凹部104a)内でパイプ材120の本体部121を所望の形状に成形するフランジ付パイプ材の成形方法であって、金型100が接近する過程においてパイプ材120の一部を金型100によって押し潰して重ね合わせることによりフランジ部122を形成する押し潰し工程と、フランジ部122を更に圧縮することによりフランジ部122に塑性流動を引き起こさせ、当該流動の一部を第1のキャビティ(上型凹部102a、下型凹部104a)側に送り込む塑性流動工程とを経る。【選択図】図2[PROBLEMS] To make pipe material conform to the shape of a mold by utilizing the pressing force of a die, rather than relying only on the high pressure from the inside of the pipe material, and further to make the flange part thin and high in strength and high. A molding method capable of molding with high accuracy is provided. A flange portion 122 along a longitudinal direction of a pipe material 120 is formed on a pipe material 120 by a mold 100, and a first cavity (an upper mold concave portion 102a and a lower mold concave portion 104a is formed by the mold 100. ) Is a method for forming a flanged pipe material in which the main body 121 of the pipe material 120 is formed into a desired shape, and a part of the pipe material 120 is crushed by the mold 100 while the mold 100 approaches. A crushing step of forming the flange portion 122 by superimposing and causing the plastic flow in the flange portion 122 by further compressing the flange portion 122, and a part of the flow is transferred to the first cavity (the upper mold recess 102a, It passes through the plastic flow step of feeding to the lower mold recess 104a) side. [Selection] Figure 2

Description

本発明は、金型による型押しによって、パイプ材に当該パイプ材の長手方向に沿ったフランジを成形する技術に関する。   The present invention relates to a technique for forming a flange along a longitudinal direction of a pipe material on a pipe material by stamping with a mold.

従来から、パイプ材に当該パイプ材の長手方向に沿ったフランジを形成する技術は存在する。例えば、特許文献1においては、上下金型を有してなるブロー成形金型と、金属製パイプを所定の温度にまで加熱する加熱機構と、加熱された金属製パイプの両端をシールすると共に、当該金属製パイプ内に高圧ガスを吹き込むブロー機構と、を備え、ブロー成形金型は、ブロー成形時の金型位置により形成されるキャビティの一部にフランジ形成用サブキャビティを有し、ブロー成型金型をブロー成形時の金型位置よりも更に閉じると、サブキャビティが、当該サブキャビティ内にブロー成形された金属製パイプ14を押し潰してフランジ14aを形成するという技術である。   Conventionally, there is a technique for forming a flange along the longitudinal direction of the pipe material on the pipe material. For example, in Patent Document 1, a blow molding mold having upper and lower molds, a heating mechanism for heating a metal pipe to a predetermined temperature, and sealing both ends of the heated metal pipe, A blow mechanism for blowing high-pressure gas into the metal pipe, and the blow molding die has a flange forming subcavity in a part of the cavity formed by the die position at the time of blow molding, and blow molding This is a technique in which when the mold is further closed from the mold position at the time of blow molding, the subcavity crushes the metal pipe 14 blow-molded in the subcavity to form the flange 14a.

特開2012−654号公報JP 2012-654 A

しかしながら、特許文献1に記載の技術は、金属製パイプを金型に沿った所望の形状とするために、当該金属製パイプの内側から加える高い圧力のみに依存しているため、高圧を発生させるために必要となるコストが増大するという問題があった。 However, since the technique described in Patent Document 1 relies only on a high pressure applied from the inside of the metal pipe in order to make the metal pipe a desired shape along the mold, it generates a high pressure. Therefore, there is a problem that the cost required for the increase.

そこで本発明は、この問題点を解決するべくなされたものであって、金属製パイプを金型に沿った所望の形状とするためにパイプ材の内側からの高圧のみに頼るのではなく、金型のプレスする力を利用してパイプ材を金型形状に沿わせることを可能とし、更にフランジ部を薄肉且つ高強度、高精度に成形できるフランジ付パイプ材の成形方法を提供する事をその課題としている。 Therefore, the present invention has been made to solve this problem, and does not rely only on the high pressure from the inside of the pipe material in order to make the metal pipe into a desired shape along the mold. It is possible to provide a method for forming a flanged pipe material that makes it possible to conform the pipe material to the mold shape by using the pressing force of the mold, and to form the flange portion thinly, with high strength and high accuracy. It is an issue.

上記課題を解決するべく、本願発明は、接近・離間する金型によって、パイプ材に当該パイプ材の長手方向に沿ったフランジ部を成形し且つ前記金型で形成される第1のキャビティ内で当該パイプ材の本体部を所望の形状に成形するフランジ付パイプ材の成形方法であって、前記金型が接近する過程において前記パイプ材の一部を前記金型によって押し潰して重ね合わせることによりフランジ部を成形する押し潰し工程と、当該フランジ部を更に圧縮することにより当該フランジ部に塑性流動を引き起こさせ、当該流動の一部を前記第1のキャビティ側に送り込む塑性流動工程と、を含むことを特徴とする。   In order to solve the above problems, the present invention forms a flange portion along the longitudinal direction of the pipe material with a mold that approaches and separates, and within the first cavity formed by the mold. A flanged pipe material molding method for molding the pipe body body into a desired shape, wherein a part of the pipe material is crushed and overlapped by the mold in the process of approaching the mold. A crushing step of forming the flange portion, and a plastic flow step of causing the flange portion to cause a plastic flow by further compressing the flange portion and feeding a part of the flow to the first cavity side. It is characterized by that.

このような方法により成形することにより、パイプ材の本体部を金型に沿わせることが可能となった。即ち、塑性流動が生じる程にフランジ部を押し潰すことにより、当該塑性流動が第1のキャビティ内に流れ込み、この流れ込みによってパイプ材の本体部が金型に沿うような動きをすることを発明者は知得したのである。特に、パイプ材の本体部の形状が角型断面形状となるような場合の角部への追従性を大きく改善することが可能となった。また、フランジ部に塑性流動が生じる程の圧力を印加しているので、フランジ部を薄肉に成形でき、他部材との結合において自由度が向上する。更に、フランジ部に塑性流動が生じる程の圧力を印加したことによって、互いに押しつけられた材料に材料同士の接合(圧接)が生じ、フランジ部全体の強度が向上することに加えて、例えばフランジ部の先端面を切り落とす等の加工を事後的に行った場合でも、フランジ部分から分割してしまうことがない。   By molding by such a method, the main body of the pipe material can be placed along the mold. In other words, the inventors invented that the plastic flow flows into the first cavity by crushing the flange portion to the extent that plastic flow occurs, and that the main body portion of the pipe material moves along the mold by this flow. Knew. In particular, it has become possible to greatly improve the followability to the corner when the shape of the main body of the pipe material has a square cross-sectional shape. In addition, since a pressure that causes plastic flow is applied to the flange portion, the flange portion can be formed thin, and the degree of freedom in connection with other members is improved. Further, by applying a pressure that causes plastic flow to the flange portion, the materials pressed against each other are joined (pressure contact), and the strength of the entire flange portion is improved. For example, the flange portion Even when the processing such as cutting off the tip end surface is performed afterwards, it is not divided from the flange portion.

また、前記押し潰し工程に先立ち、前記金型が前記パイプ材の一部を摘まみ出す摘まみ出し工程を有することを特徴とする。   Moreover, prior to the crushing step, the mold has a picking step for picking out a part of the pipe material.

このように、金型自体がパイプ材をキャビティ外に摘まみ出すという構成を採用しているため、必ずしもパイプ材の内側から圧力を加えなくともフランジ部を成形することができる。   Thus, since the mold itself employs a configuration in which the pipe material is picked out of the cavity, the flange portion can be formed without necessarily applying pressure from the inside of the pipe material.

なお、この摘まみ出し工程では、具体的には、前記金型における前記第1のキャビティと当該第1のキャビティ以外の部分を区画する段差部が前記パイプ材に接触して当該パイプ材を内側に屈曲させて進行する。   In this picking step, specifically, a step portion that divides the first cavity and the portion other than the first cavity in the mold comes into contact with the pipe material, and the pipe material is placed inside. Bend to progress.

また、前記フランジ部を更に圧縮する際、前記フランジ部の先端側には塑性流動を制限するための制限部材が配置されていることを特徴とする。   Further, when the flange portion is further compressed, a restricting member for restricting plastic flow is disposed on the distal end side of the flange portion.

このように構成したことによって、第1のキャビティ側への塑性流動量を増加させることができ、また、フランジ先端部の成型精度を向上させることができる。   With this configuration, the amount of plastic flow toward the first cavity can be increased, and the molding accuracy of the flange tip can be improved.

また、前記フランジ部を更に圧縮する際、圧縮前の前記フランジ部を形成する材料の体積が減少する程度にまで圧縮することを特徴とする。   Moreover, when the said flange part is further compressed, it compresses to such an extent that the volume of the material which forms the said flange part before compression reduces.

このように、フランジ部を形成する材料の体積が減少する程の圧力(鍛圧)を印加したことによって、例えばパイプ材が金属材料であるような場合は組織密度が向上し、フランジ部自体の強度が向上する。   Thus, by applying a pressure (forging pressure) that reduces the volume of the material forming the flange portion, for example, when the pipe material is a metal material, the tissue density is improved and the strength of the flange portion itself is increased. Will improve.

本発明を適用することで、金属製パイプを金型に沿った所望の形状とするためにパイプ材の内側からの高圧のみに頼るのではなく、金型のプレスする力を利用してパイプ材を金型形状に沿わせることを可能とし、更にフランジ部を薄肉且つ高強度、高精度に成形できるフランジ付パイプ材の成形方法を提供することができる。   By applying the present invention, in order to make a metal pipe into a desired shape along the mold, the pipe material is utilized not by relying only on the high pressure from the inside of the pipe material but by using the pressing force of the mold. It is possible to provide a method for forming a flanged pipe material in which the flange portion can be formed with a thin wall, high strength, and high accuracy.

金型と被加工材料となるパイプ材の状態を示した図であって、(a)は金型が離間している状態を示した概略構成図、(b)は金型が接近している状態を示した概略構成図である。It is the figure which showed the state of the metal mold | die and the pipe material used as a workpiece material, Comprising: (a) is a schematic block diagram which showed the state which the metal mold | die has separated, (b) is a metal mold | die approaching It is the schematic block diagram which showed the state. 金型がパイプ材を押し潰してフランジ付パイプ材を成形する過程を順に示した写真であって、(a)は型押し前の状態を示した写真、(b)は摘まみ出し工程を示した写真、(c)は押し潰し工程途中を示した写真、(d)は押し潰し工程完了後であって塑性流動工程前の状態を示した写真、(e)は塑性流動工程の状態を示した写真、(f)は型押しが完了した状態を示した写真である。It is the photograph which showed the process in which a metal mold crushes a pipe material, and formed the pipe material with a flange in order, (a) is the photograph which showed the state before mold pressing, and (b) shows the picking process. (C) is a photograph showing the middle of the crushing process, (d) is a photograph showing the state after the crushing process is completed and before the plastic flow process, and (e) is a state of the plastic flow process. (F) is a photograph showing a state where the embossing is completed. (a)は押し潰し工程完了時点でのパイプ材の断面写真、(b)は塑性流動工程を経たパイプ材の断面写真である。(A) is a cross-sectional photograph of the pipe material when the crushing process is completed, and (b) is a cross-sectional photograph of the pipe material that has undergone the plastic flow process. 塑性流動工程の前後における、フランジ部断面形状の比較写真である。It is a comparative photograph of the flange section sectional shape before and after the plastic flow process. フランジ部の先端面側に制限部材を配置した金型と被加工材料となるパイプ材の状態を示した図であって、(a)は金型が離間している状態を示した概略構成図、(b)は金型が接近している状態を示した概略構成図である。It is the figure which showed the state of the pipe material used as the workpiece and the metal mold | die which has arrange | positioned the limiting member in the front end surface side of a flange part, Comprising: (a) is a schematic block diagram which showed the state which the metal mold | die has separated | separated (B) is the schematic block diagram which showed the state which the metal mold | die is approaching. (a)は押し潰し工程完了時点でのパイプ材の断面写真、(b)は塑性流動工程を経たパイプ材の断面写真、(c)はフランジ部の先端面側に制限部材を配置した金型によって成形され且つ塑性流動工程を経たパイプ材の断面写真である。(A) is a cross-sectional photograph of the pipe material at the time of completion of the crushing process, (b) is a cross-sectional photograph of the pipe material that has undergone the plastic flow process, and (c) is a mold in which a limiting member is disposed on the front end side of the flange portion. It is the cross-sectional photograph of the pipe material shape | molded by this and passed through the plastic flow process.

以下、添付図面を参照しつつ、本発明の実施形態の一例であるにフランジ付パイプ材の成形方法ついて説明を加える。なお、図面理解容易の為、各部の大きさや寸法を誇張して表現している部分があり、実際の製品と必ずしも一致しない部分があることを付記しておく。また各図面は符号の向きに見るものとし、当該向きを基本に上下左右、手前、奥と表現する。   Hereinafter, a method for forming a flanged pipe material will be described as an example of an embodiment of the present invention with reference to the accompanying drawings. For easy understanding of the drawings, it should be noted that there are portions where the size and dimensions of each portion are exaggerated and there are portions that do not necessarily match the actual product. In addition, each drawing is viewed in the direction of the reference sign, and is expressed as upper, lower, left, right, near, and back based on the direction.

〈フランジ付パイプ材の成形方法の流れ〉
本発明の実施形態の一例として示すフランジ付パイプ材の成形方法は、図1に示した通り、接近・離間する金型100によって、被加工材となるパイプ材120を型押しすることにより行われる。なお、図面上は金型100とパイプ材120しか図示していないが、当然ながら、金型を作動させるための油圧装置等の周辺機構が備わっている。
<Flow of molding method for flanged pipe material>
The flanged pipe material forming method shown as an example of the embodiment of the present invention is performed by embossing a pipe material 120 to be processed by a mold 100 approaching / separating as shown in FIG. . Although only the mold 100 and the pipe material 120 are shown in the drawing, naturally, peripheral mechanisms such as a hydraulic device for operating the mold are provided.

金型100は、上型102と下型104とを有した構成とされ、それぞれに凹部102a、104aを有する。この2つの凹部102a、104aによって第1のキャビティが形成される。また、上型102における上型凹部102aと当該上型凹部102a以外の部分、即ち上型凹部102aと上型表面とを区画する部分は段差部102b、102cである。同様に、下型104における下型凹部104aと当該下型凹部104a以外の部分、即ち下型凹部104aと下型表面とを区画する部分は段差部104b、104cである。図1(a)では、パイプ材120にフランジ部は未だ成形されていないが、型押しを経て、図1(b)に示したようにパイプ材120の両側面にフランジ部122が成形される。なお、フランジ部122形成後における当該フランジ部122以外の部分を、パイプ材120の本体部(以下単に「本体部」という場合がある。)121と表現する。   The mold 100 is configured to have an upper mold 102 and a lower mold 104, and each has a recess 102a, 104a. A first cavity is formed by the two recesses 102a and 104a. Further, the portions other than the upper mold recess 102a and the upper mold recess 102a in the upper mold 102, that is, the portions that partition the upper mold recess 102a and the upper mold surface are stepped portions 102b and 102c. Similarly, the portions other than the lower mold recess 104a and the lower mold recess 104a in the lower mold 104, that is, the portions that partition the lower mold recess 104a and the lower mold surface are stepped portions 104b and 104c. In FIG. 1A, the flange portion is not yet formed on the pipe member 120, but the flange portion 122 is formed on both side surfaces of the pipe member 120 as shown in FIG. . A portion other than the flange portion 122 after the flange portion 122 is formed is expressed as a main body portion (hereinafter sometimes simply referred to as “main body portion”) 121 of the pipe material 120.

続いて、図2を参照しつつ、本発明の実施形態の一例として示すフランジ付パイプ材の成形方法の流れを説明する。   Next, a flow of a method for forming a flanged pipe material shown as an example of an embodiment of the present invention will be described with reference to FIG.

図2(a)に示しているように、金型100(上型102と下型104)間に、被加工品であるパイプ材120を載置する。必要に応じて、パイプ材120を加熱処理した上で載置してもよい。   As shown in FIG. 2A, a pipe material 120, which is a workpiece, is placed between the molds 100 (the upper mold 102 and the lower mold 104). If necessary, the pipe member 120 may be placed after being heat-treated.

次に、上型102と下型104が接近し、図2(b)に示しているように、パイプ材120の表面に、4つの段差部102b、102c、104b、104cが接触し、当該パイプ材120の両側面の一部を恰も摘まみ出しながら更に接近する(摘まみ出し工程)。この時、パイプ材120自体は、段差部102b、102c、104b、104cによって、内側に(谷折りに)折り曲げられるに変形すると同時に、上型102と下型104の間に挟み込まれるように(換言すると、第1のキャビティの外にはみ出すように)山折りに変形する。   Next, the upper mold 102 and the lower mold 104 approach each other, and as shown in FIG. 2B, the four step portions 102b, 102c, 104b, 104c come into contact with the surface of the pipe material 120, and the pipe It further approaches while picking up a part of both sides of the material 120 (plucking process). At this time, the pipe material 120 itself is deformed so as to be bent inward (valley-folded) by the step portions 102b, 102c, 104b, and 104c, and at the same time, sandwiched between the upper mold 102 and the lower mold 104 (in other words, Then, it is transformed into a mountain fold so that it protrudes out of the first cavity.

次に、上型102と下型104が更に接近すると、図2(c)乃至(d)に示しているように、上型102の表面と下型104の表面によって、上型102と下型104の間に挟み込まれるように(第1のキャビティの外にはみ出すように)変形した部分を、押し潰して重ね合わせが行われる(押し潰し工程)。この工程により、第一段階としてのフランジ部122が形成される。   Next, when the upper mold 102 and the lower mold 104 come closer, as shown in FIGS. 2C to 2D, the upper mold 102 and the lower mold 104 are formed by the surface of the upper mold 102 and the surface of the lower mold 104. The deformed portions are sandwiched between 104 (so as to protrude outside the first cavity) and are superposed to perform superposition (crushing step). By this process, the flange portion 122 as the first stage is formed.

本発明では、この段階で終了せず、更に上型102と下型104を接近させる。即ち、図2(e)乃至(f)に示しているように、パイプ材120が二重に重ね合わせられた第一段階のフランジ部120を、更に塑性流動が生じる程に押し潰すのである(塑性流動工程)。この時、塑性流動の一部が第1のキャビティ(上型凹部102a、下型凹部104a)側へと流れ込む作用によって、第1のキャビティ(上型凹部102a、下型凹部104a)内に位置する本体部121が、第1のキャビティの形状に沿うような動きをみせるのである。特に、第1のキャビティ(上型凹部102a、下型凹部104a)の四隅方向に沿うように変形しているのが把握できる。   In the present invention, the process does not end at this stage, and the upper mold 102 and the lower mold 104 are brought closer to each other. That is, as shown in FIGS. 2 (e) to 2 (f), the first-stage flange portion 120 in which the pipe materials 120 are overlapped is crushed so as to cause further plastic flow ( Plastic flow process). At this time, a part of the plastic flow is located in the first cavity (upper mold recess 102a, lower mold recess 104a) by the action of flowing into the first cavity (upper mold recess 102a, lower mold recess 104a). The main body 121 moves so as to follow the shape of the first cavity. In particular, it can be seen that the first cavity (the upper mold recess 102a and the lower mold recess 104a) is deformed along the four corner directions.

この、塑性流動工程の前後によって、被加工品であるパイプ材120(の特にフランジ部122周辺)がどのように変化したのかについて、図3及び図4を参照しつつ説明する。   It will be described with reference to FIGS. 3 and 4 how the pipe material 120 (particularly around the flange portion 122), which is a workpiece, has changed before and after the plastic flow process.

図3は(a)は押し潰し工程完了時点でのパイプ材120の断面写真、(b)は塑性流動工程を経たパイプ材120の断面写真である。一見して理解できる通り、塑性流動工程後のパイプ材120におけるフランジ部122は薄肉となっている。具体的には、押し潰し工程完了時点でのパイプ材120におけるフランジ部122の厚みT1は約6mmであるのに対して、塑性流動工程を経たパイプ材120におけるフランジ部122の厚みT2は約3mmとなっており、本体部121の厚みと略同じレベルに薄肉化されている。   3A is a cross-sectional photograph of the pipe material 120 at the time when the crushing process is completed, and FIG. 3B is a cross-sectional photograph of the pipe material 120 that has undergone the plastic flow process. As can be understood at a glance, the flange portion 122 of the pipe material 120 after the plastic flow process is thin. Specifically, the thickness T1 of the flange portion 122 in the pipe material 120 at the time of completion of the crushing process is about 6 mm, whereas the thickness T2 of the flange portion 122 in the pipe material 120 that has undergone the plastic flow process is about 3 mm. The thickness of the main body 121 is reduced to approximately the same level.

また、図4は、塑性流動工程の前後における、フランジ部122断面形状の比較写真である。上側に配置されている写真が押し潰し工程完了時点(即ち塑性流動工程の前)でのフランジ部122を中心とした断面形状を示しており、下側に配置されている写真が塑性流動工程後のフランジ部122を中心とした断面形状を示している。   FIG. 4 is a comparative photograph of the cross-sectional shape of the flange 122 before and after the plastic flow process. The photograph arranged on the upper side shows a cross-sectional shape centering on the flange 122 at the time when the crushing process is completed (that is, before the plastic flow process), and the photograph arranged on the lower side is after the plastic flow process. The cross-sectional shape centering on the flange part 122 is shown.

ここで、簡易的な方法であるが、それぞれの断面に対して同じ面積の仮想ブロック(縦横それぞれ3mmのブロック)を配置して、塑性流動工程の前後における断面積の変化を計測してみる。塑性流動工程前においては、フランジ部122に10個の仮想ブロックを配置でき、及び、本体部121(フランジ部122よりも上方且つパイプ材の中心までの部分)に11個の仮想ブロックを配置することができる。一方、塑性流動工程後においては、同様に計測すると、フランジ部122に7個の仮想ブロックを配置でき、相当する本体部121に12個の仮想ブロックを配置することができる。   Here, although it is a simple method, the virtual area (3 mm in length and breadth) of the same area is arrange | positioned with respect to each cross section, and the change of the cross-sectional area before and behind a plastic flow process will be measured. Prior to the plastic flow process, 10 virtual blocks can be arranged on the flange portion 122, and 11 virtual blocks are arranged on the main body 121 (a portion above the flange portion 122 and to the center of the pipe material). be able to. On the other hand, after the plastic flow process, when measured in the same manner, seven virtual blocks can be arranged in the flange portion 122 and twelve virtual blocks can be arranged in the corresponding main body portion 121.

上記計測の結果から、以下の2つの結果を導くことができる。1つは、塑性流動によって本体部121の断面形状が大きく変化していることに加えて、本体部121の断面積が、仮想ブロック11個分→12個分へと増加している。この増加した仮想ブロック1つ分は、フランジ部121からの塑性流動によって第1のキャビティ側に流動の一部が送り込まれたものであると判断できる。この送り込まれた仮想ブロック1つ分によって、本体部121の形状が第1のキャビティの形状に沿うように変化しているのである。   The following two results can be derived from the measurement results. One is that the cross-sectional shape of the main body 121 is greatly changed by plastic flow, and the cross-sectional area of the main body 121 is increased from 11 virtual blocks to 12 virtual blocks. It can be determined that this increased virtual block is a part of the flow fed to the first cavity side by the plastic flow from the flange portion 121. The shape of the main body 121 is changed so as to follow the shape of the first cavity by one virtual block sent in.

2つ目は、フランジ部122自体の仮想ブロックが、10個→7個に減少している。塑性流動によって第1のキャビティ側に送り込まれた分が本体部121の上下方向にそれぞれ仮想ブロック1つ分、計仮想ブロック2つ分としても、仮想ブロック1つ分足らないことになる。この仮想ブロック1つ分は、フランジ部122を形成する材料自体の体積が減少したと考える事ができ、それ程にまで圧縮(鍛圧)された結果であると推察できる。   Second, the number of virtual blocks of the flange portion 122 itself is reduced from 10 to 7. Even if the amount sent to the first cavity side by plastic flow is one virtual block and two total virtual blocks in the vertical direction of the main body 121, one virtual block is not enough. This one virtual block can be considered to be a result of the volume of the material itself forming the flange portion 122 being reduced, and it can be inferred that it is a result of being compressed (forging pressure) to that extent.

上記説明した通り、本願発明は、接近・離間する金型100によって、パイプ材120に当該パイプ材120の長手方向に沿ったフランジ部122を成形し且つ前記金型100で形成される第1のキャビティ(上型凹部102a、下型凹部104a)内で当該パイプ材120の本体部121を所望の形状に成形するフランジ付パイプ材の成形方法であって、前記金型100が接近する過程において前記パイプ材120の一部を前記金型100によって押し潰して重ね合わせることによりフランジ部122を成形する押し潰し工程と、当該フランジ部122を更に圧縮することにより当該フランジ部122に塑性流動を引き起こさせ、当該流動の一部を前記第1のキャビティ(上型凹部102a、下型凹部104a)側に送り込む塑性流動工程と、を含むことを特徴とする。   As described above, the present invention forms the flange portion 122 along the longitudinal direction of the pipe material 120 on the pipe material 120 by the mold 100 approaching / separating, and is formed by the mold 100. A flanged pipe material molding method for molding the main body portion 121 of the pipe material 120 into a desired shape within a cavity (upper mold recess 102a, lower mold recess 104a), and in the process in which the mold 100 approaches A crushing process for forming the flange portion 122 by crushing and overlapping a part of the pipe material 120 with the mold 100, and further compressing the flange portion 122 to cause the flange portion 122 to cause plastic flow. , A plastic flow step of feeding a part of the flow to the first cavity (the upper mold recess 102a and the lower mold recess 104a) side , Characterized in that it comprises a.

このような方法により成形することにより、パイプ材120の本体部121を金型100に沿わせることが可能となった。即ち、塑性流動が生じる程にフランジ部122を押し潰すことにより、当該塑性流動が第1のキャビティ(上型凹部102a、下型凹部104a)内に流れ込み、この流れ込みによってパイプ材120の本体部121が金型100に沿うような動きをするのである。特に、パイプ材120の本体部121の形状が角型断面形状となるような場合の角部への追従性を大きく改善することが可能となった。なお、金型に完全に沿わせる段階までには至らなくとも、近い段階まで沿わせることができることによって、その後の加工処理の負担が軽減されるため、十分な技術的意義を有するものである。また、フランジ部122に塑性流動が生じる程の圧力を印加しているので、フランジ部122を薄肉に成形でき、他部材との結合において自由度が向上する。更に、フランジ部122に塑性流動が生じる程の圧力を印加したことによって、互いに押しつけられた材料に材料同士の接合(圧接)が生じ、フランジ部122全体の強度が向上することに加えて、例えばフランジ部122の先端を切り落とす等の加工を事後的に行った場合でも、フランジ部122から分割してしまうこともない。   By molding by such a method, the main body 121 of the pipe material 120 can be fitted along the mold 100. That is, by crushing the flange portion 122 to the extent that plastic flow occurs, the plastic flow flows into the first cavity (the upper mold concave portion 102a and the lower mold concave portion 104a). Moves along the mold 100. In particular, it is possible to greatly improve the followability to the corner when the shape of the main body 121 of the pipe material 120 has a square cross-sectional shape. In addition, even if it does not reach the stage where it is completely along the mold, it is possible to follow it to a near stage, thereby reducing the burden of subsequent processing, and thus has sufficient technical significance. Moreover, since the pressure which produces the plastic flow in the flange part 122 is applied, the flange part 122 can be shape | molded thinly and a freedom degree improves in a coupling | bonding with another member. Furthermore, by applying a pressure that causes plastic flow to the flange portion 122, the materials pressed against each other are joined (pressure contact), and the strength of the entire flange portion 122 is improved. Even when processing such as cutting off the front end of the flange portion 122 is performed afterwards, the flange portion 122 is not divided.

また、押し潰し工程に先立ち、金型100がパイプ材120の一部を摘まみ出す摘まみ出し工程を有していた。   Further, prior to the crushing process, the mold 100 had a picking process in which a part of the pipe material 120 was picked up.

このように、金型100自体がパイプ材120をキャビティ(上型凹部102a、下型凹部104a)外に摘まみ出すという構成を採用しているため、必ずしもパイプ材120の内側から圧力を加えなくともフランジ部122を成形することができる。   In this way, the mold 100 itself employs a configuration in which the pipe material 120 is picked out of the cavity (the upper mold recess 102a and the lower mold recess 104a), and therefore pressure is not necessarily applied from the inside of the pipe material 120. In both cases, the flange portion 122 can be formed.

なお、この摘まみ出し工程では、具体的には、金型100における前記第1のキャビティ(上型凹部102a、下型凹部104a)と当該第1のキャビティ(上型凹部102a、下型凹部104a)以外の部分を区画する段差部102b、102c、104b、104cがパイプ材120に接触して当該パイプ材を内側に屈曲させて進行する。   In this picking step, specifically, the first cavity (upper mold recess 102a, lower mold recess 104a) and the first cavity (upper mold recess 102a, lower mold recess 104a) in the mold 100 are used. Steps 102b, 102c, 104b, and 104c that define portions other than () are in contact with the pipe member 120, and the pipe member is bent inward to advance.

また、フランジ部122を更に圧縮する際、圧縮前のフランジ部122を形成する材料の体積が減少する程度にまで圧縮することを特徴としていた。   Further, when the flange portion 122 is further compressed, the flange portion 122 is compressed to such an extent that the volume of the material forming the flange portion 122 before compression is reduced.

このように、フランジ部122を形成する材料の体積が減少する程の圧力(鍛圧)を印加したことによって、例えばパイプ材120が金属材料であるような場合は組織密度が向上し、フランジ部122自体の強度向上を図ることが可能となっている。   Thus, by applying a pressure (forging pressure) that reduces the volume of the material forming the flange portion 122, for example, when the pipe material 120 is a metal material, the tissue density is improved, and the flange portion 122 is increased. It is possible to improve the strength of itself.

〈その他の構成例〉
上記では、パイプ材120の両側面にフランジを成形する例として説明していたが、場合によっては片方側だけにフランジ部を成形してもよいし、その場合においても本発明を適用可能である。
<Other configuration examples>
In the above description, the flanges are formed on both side surfaces of the pipe material 120 as an example. However, in some cases, the flange portion may be formed only on one side, and the present invention is applicable also in that case. .

また、フランジ部122を更に圧縮する際、図5に示しているように、フランジ部122の先端側の位置に塑性流動を制限するための制限部材103を配置してもよい。   Further, when the flange portion 122 is further compressed, as shown in FIG. 5, a restricting member 103 for restricting plastic flow may be disposed at a position on the distal end side of the flange portion 122.

このように構成すれば、第1のキャビティ(上型凹部102a、下型凹部104a)側への塑性流動量を増加させることができ、また、フランジ122先端部の成型精度を向上させることができる。図6(a)は押し潰し工程完了時点でのパイプ材の断面写真、(b)は塑性流動工程を経たパイプ材の断面写真、(c)は制限部材103を配置した上での塑性流動工程を経たパイプ材の断面写真である。図6(b)と(c)を比べれば一目瞭然であるが、フランジ部122の先端側への塑性流動が制限されたことによって、フランジ部122の先端から先端までの長さ(矢視部分)は(c)の方が短くなっている。更にフランジ部122先端側への塑性流動が制限されたことによって、先端部分の断面が略直角になるように綺麗に且つ精度のよい仕上げとなっている点が見て取れる。   If comprised in this way, the amount of plastic flows to the 1st cavity (upper mold | type recessed part 102a, lower mold | type recessed part 104a) side can be increased, and the shaping | molding precision of the flange 122 front-end | tip part can be improved. . 6A is a cross-sectional photograph of the pipe material at the time when the crushing process is completed, FIG. 6B is a cross-sectional photograph of the pipe material that has undergone the plastic flow process, and FIG. 6C is a plastic flow process after the restricting member 103 is disposed. It is the cross-sectional photograph of the pipe material which passed through. 6B and 6C, it is obvious that the length of the flange 122 from the tip to the tip (arrow portion) is limited by the plastic flow to the tip of the flange 122 being restricted. (C) is shorter. Further, it can be seen that the plastic flow toward the distal end side of the flange portion 122 is restricted, so that the section of the distal end portion has a clean and accurate finish so as to have a substantially right angle.

また上記では、金属製のパイプ材を前提に説明をしているが、それ以外にも、例えばCFRPといった繊維強化樹脂性のパイプ材にも本発明を適用することが可能である。   In the above description, the pipe material made of metal is used as a premise. However, the present invention can be applied to a fiber reinforced resin pipe material such as CFRP.

100・・・金型
102・・・上型
102a・・・上型凹部
102b、102c・・・段差部
103・・・制限部材
104・・・下型
104a・・・下型凹部
104b、104d・・・段差部
120・・・パイプ材
121・・・本体部
122・・・フランジ
DESCRIPTION OF SYMBOLS 100 ... Mold 102 ... Upper mold 102a ... Upper mold recessed part 102b, 102c ... Step part 103 ... Limiting member 104 ... Lower mold 104a ... Lower mold recessed part 104b, 104d ..Step portion 120 ... pipe material 121 ... main body portion 122 ... flange

Claims (4)

接近・離間する金型によって、所定の厚みで形成されたパイプ材に当該パイプ材の長手方向に沿ったフランジ部を形成し且つ前記金型で形成される第1のキャビティ内で当該パイプ材の本体部を所望の形状に成形するフランジ付パイプ材の成形方法であって、
前記金型が接近する過程において前記パイプ材の一部を前記金型によって押し潰して重ね合わせることによりフランジ部を形成する押し潰し工程と、
当該フランジ部を更に少なくとも前記所定の厚み程度にまで圧縮することにより押し潰された前記フランジを構成する材料の一部が塑性流動によって前記第1のキャビティ側に流れ込み且つ前記本体部が前記第1のキャビティの形状に沿うように移動する程度の塑性流動を引き起こさせる塑性流動工程と、を含む
ことを特徴とするフランジ付パイプ材の成形方法。
A flange portion along the longitudinal direction of the pipe material is formed in the pipe material formed with a predetermined thickness by a mold that approaches and separates, and the pipe material is formed in the first cavity formed by the mold. A method for forming a flanged pipe material for forming a main body into a desired shape,
A crushing step of forming a flange portion by crushing and overlapping a part of the pipe material with the mold in the process of approaching the mold,
Part of the material constituting the flange, which is crushed by further compressing the flange portion to at least the predetermined thickness , flows into the first cavity side by plastic flow, and the body portion is the first portion. A plastic flow step of causing a plastic flow to move along the shape of the cavity of the pipe.
請求項1において、
前記塑性流動工程では、更に、前記フランジ部の重ね合わされた材料同士に接合が生じる程度にまで圧縮される
ことを特徴とするフランジ付パイプ材の成形方法。
In claim 1,
In the plastic flow process, the flanged pipe material is further compressed to such an extent that the overlapping materials of the flange portions are joined to each other.
請求項1または2において、
前記押し潰し工程に先立ち、前記金型が前記パイプ材の一部を摘まみ出す摘まみ出し工程を有する
ことを特徴とするフランジ付パイプ材の成形方法。
In claim 1 or 2,
Prior to the crushing step, the mold has a picking step for picking out a part of the pipe material. A method for forming a flanged pipe material.
請求項において、
前記摘まみ出し工程では、前記金型における前記第1のキャビティと当該第1のキャビティ以外の部分を区画する段差部が前記パイプ材に接触して当該パイプ材を内側に屈曲させて進行する
ことを特徴とするフランジ付パイプ材の成形方法。
In claim 3 ,
In the picking step, a stepped portion that separates the first cavity and the portion other than the first cavity in the mold is in contact with the pipe material, and the pipe material is bent inward to proceed. A method for forming a flanged pipe material.
JP2017200757A 2017-10-17 2017-10-17 Forming method of flanged pipe material Active JP6381090B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017200757A JP6381090B1 (en) 2017-10-17 2017-10-17 Forming method of flanged pipe material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017200757A JP6381090B1 (en) 2017-10-17 2017-10-17 Forming method of flanged pipe material

Publications (2)

Publication Number Publication Date
JP6381090B1 true JP6381090B1 (en) 2018-08-29
JP2019072741A JP2019072741A (en) 2019-05-16

Family

ID=63354711

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017200757A Active JP6381090B1 (en) 2017-10-17 2017-10-17 Forming method of flanged pipe material

Country Status (1)

Country Link
JP (1) JP6381090B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPWO2022034843A1 (en) * 2020-08-11 2022-02-17
CN117980086A (en) * 2021-11-25 2024-05-03 住友重机械工业株式会社 Forming device and forming method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001259754A (en) * 2000-01-14 2001-09-25 Sumitomo Metal Ind Ltd Forming method of hydraulically bulging part, die and hydraulically bulging part
JP2006061944A (en) * 2004-08-26 2006-03-09 Nissan Motor Co Ltd Hydrostatic bulging method, hydrostatically bulged product and hydrostatic bulging die
JP2016129891A (en) * 2015-01-13 2016-07-21 リンツリサーチエンジニアリング株式会社 Blow molding metal mold for manufacturing flanged aluminum pipe, flanged aluminum pipe device with the metal mold, and method for manufacturing flanged aluminum pipe

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001259754A (en) * 2000-01-14 2001-09-25 Sumitomo Metal Ind Ltd Forming method of hydraulically bulging part, die and hydraulically bulging part
JP2006061944A (en) * 2004-08-26 2006-03-09 Nissan Motor Co Ltd Hydrostatic bulging method, hydrostatically bulged product and hydrostatic bulging die
JP2016129891A (en) * 2015-01-13 2016-07-21 リンツリサーチエンジニアリング株式会社 Blow molding metal mold for manufacturing flanged aluminum pipe, flanged aluminum pipe device with the metal mold, and method for manufacturing flanged aluminum pipe

Also Published As

Publication number Publication date
JP2019072741A (en) 2019-05-16

Similar Documents

Publication Publication Date Title
JP6381090B1 (en) Forming method of flanged pipe material
KR101668715B1 (en) Method for manufacturing bent hollow pipe
JP6849212B2 (en) Manufacturing method of metal parts
JP2007054840A (en) Apparatus for forming hollow stepped shaft
CN104209444B (en) Oil pipe joint cold heading device and production technology thereof
KR102045208B1 (en) High speed blow molding method
JP2008149343A (en) Tube hydroforming method
JPH11320013A (en) Method for forming end deformed rod-shaped product and forging apparatus therefor
KR20180119672A (en) Press molding method
CN105834260A (en) Bending forming method for multi-segment bent pipe section
JPWO2005070582A1 (en) Deformed element pipe for hydraulic bulge processing, hydraulic bulge processing apparatus using the same, hydraulic bulge processing method, and hydraulic bulge processed product
JP6729011B2 (en) Method for manufacturing closed-section structural member and upper mold for O molding
JP2007050433A (en) Bulging method and die therefor
JP6031447B2 (en) Apparatus and method for forming deformed article from a plurality of sheet metal blanks
JP2001286944A (en) Forming method and machine for tube hydroforming
KR101720035B1 (en) Dies for cold forging
TWI763949B (en) Bending mold
JP4630759B2 (en) Bulge forming method
TWI778166B (en) Bending mold
KR100492747B1 (en) Manufacturing method of pipe joint
JP4319115B2 (en) Method for forming metal molded body
RU2336152C2 (en) Method of bimetal parts manufacture
JPH0929329A (en) Production of metal tube body
JP2005059047A (en) Hydraulic forming method and apparatus
JP5770016B2 (en) Tube forming machine for tube tire

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20171023

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20171023

A975 Report on accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A971005

Effective date: 20180112

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180123

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180314

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20180522

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20180706

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20180724

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20180727

R150 Certificate of patent or registration of utility model

Ref document number: 6381090

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150