JP6257814B1 - Construction method of large section underground structure - Google Patents

Construction method of large section underground structure Download PDF

Info

Publication number
JP6257814B1
JP6257814B1 JP2017015016A JP2017015016A JP6257814B1 JP 6257814 B1 JP6257814 B1 JP 6257814B1 JP 2017015016 A JP2017015016 A JP 2017015016A JP 2017015016 A JP2017015016 A JP 2017015016A JP 6257814 B1 JP6257814 B1 JP 6257814B1
Authority
JP
Japan
Prior art keywords
tunnel
filling
succeeding
subsequent
tunnels
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2017015016A
Other languages
Japanese (ja)
Other versions
JP2018013024A (en
Inventor
尚 今石
尚 今石
中田 愼一
愼一 中田
努 豊田
努 豊田
俊幸 高橋
俊幸 高橋
憲一郎 長光
憲一郎 長光
佳文 服部
佳文 服部
直俊 日高
直俊 日高
哲也 布川
哲也 布川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2017015016A priority Critical patent/JP6257814B1/en
Application granted granted Critical
Publication of JP6257814B1 publication Critical patent/JP6257814B1/en
Publication of JP2018013024A publication Critical patent/JP2018013024A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

【課題】高水圧、軟弱地盤などの施工条件が厳しい場所でも安全に施工することができ、かつ、周辺環境への影響を最小限に抑え、なおかつ、容易に高品質な大断面地中構造物を構築することができる大断面地中構造物の構築方法を提案する。【解決手段】複数本の先行トンネル2,2を並設する先行トンネル施工工程と、各先行トンネル2内に先行鉄筋51を配筋する先行トンネル配筋工程と、各先行トンネル2内に先行中詰コンクリート41を充填する先行トンネル充填工程と、隣り合う先行トンネル2,2同士の間に後行トンネル3を構築する後行トンネル施工工程と、後行トンネル3内に後行鉄筋52を配筋する後行トンネル配筋工程とを備え、後行トンネル施工工程では隣接する先行トンネル2,2の断面の一部を切削するとともに後行トンネル3の外面が先行中詰コンクリート41に当接するように後行トンネル3を構築する。【選択図】図2An object of the present invention is to provide a large section underground structure that can be safely constructed even in places with severe construction conditions such as high water pressure, soft ground, etc., and minimizes the influence on the surrounding environment, and also has high quality easily. We propose a construction method of underground structure with large cross section. A preceding tunnel construction process in which a plurality of preceding tunnels 2 and 2 are arranged side by side, a preceding tunnel arranging process in which a preceding reinforcing bar 51 is arranged in each preceding tunnel 2, and a preceding tunnel in each preceding tunnel 2. The preceding tunnel filling process for filling the stuffed concrete 41, the succeeding tunnel construction process for constructing the succeeding tunnel 3 between the adjacent preceding tunnels 2 and 2, and the succeeding reinforcing bar 52 in the succeeding tunnel 3 A subsequent tunnel arrangement step, and in the subsequent tunnel construction step, a part of the cross section of the adjacent preceding tunnels 2 and 2 is cut and the outer surface of the subsequent tunnel 3 is in contact with the preceding filled concrete 41. The trailing tunnel 3 is constructed. [Selection] Figure 2

Description

本発明は、大断面地中構造物の構築方法に関する。   The present invention relates to a construction method for a large cross-section underground structure.

道路トンネルの合流部や鉄道トンネルの駅部分等を大断面地中構造物内に構築する場合がある。
大断面地中構造物の構築方法としては、複数本の小断面トンネルを筒状に並設して外殻(大断面覆工体)を形成し、この外殻の内部を掘削する方法がある。
In some cases, a junction of road tunnels, a station portion of a railway tunnel, or the like is built in a large section underground structure.
As a method of constructing a large section underground structure, there is a method in which a plurality of small section tunnels are juxtaposed in a cylindrical shape to form an outer shell (large section lining body) and the inside of the outer shell is excavated. .

例えば、特許文献1には、先行トンネルを間隔を空けて環状に複数構築する工程と、先行トンネルの一部を切削しながら後行トンネルを環状に複数構築する工程と、後行トンネルの一部を撤去して先行トンネルと後行トンネルとが連通する連通部を構築するとともに先行トンネルと後行トンネルとを連結する工程と、先行トンネルと後行トンネルとの外周に凍土を造成する工程とを備える施工方法が開示されている。
特許文献1の施工方法では、先行トンネル内に、後行トンネル施工時の切削部分よりも大きい範囲にエアモルタルを充填しておくとともに、エアモルタル同士の間に覆工体を形成しておく。後行トンネルの施工後、連通部を形成したら、後行トンネル内に先行トンネル内の覆工体に接続する覆工体を形成することで、環状に連続する大断面覆工体を形成する。
For example, Patent Document 1 discloses a step of constructing a plurality of preceding tunnels in a ring shape at intervals, a step of constructing a plurality of succeeding tunnels in a ring shape while cutting a part of the preceding tunnel, and a portion of the succeeding tunnel. And connecting the preceding and succeeding tunnels, and creating frozen soil on the outer periphery of the preceding and succeeding tunnels. A construction method is provided.
In the construction method of Patent Document 1, air mortar is filled in a range larger than the cutting portion at the time of construction of the subsequent tunnel in the preceding tunnel, and a lining body is formed between the air mortars. After the construction of the succeeding tunnel, if the communication portion is formed, a covering body connected to the covering body in the preceding tunnel is formed in the succeeding tunnel, thereby forming a large cross-section covering body that is continuous in an annular shape.

特開2016−094818号公報JP 2006-094818 A

特許文献1の施工方法では、後行トンネルと先行トンネル内の覆工体との間にエアモルタルが介設されている。先行トンネル内の覆工体と後行トンネルに形成する覆工体とを接続するために、このエアモルタルを撤去する必要があるため、地山側から後行トンネルに作用する土圧や地下水圧に対して、先行トンネル側から十分な反力を確保することができず、後行トンネルが変形するおそれがある。後行トンネルが変形すると、先行トンネルと後行トンネルとの外周囲の凍土に亀裂が生じ、もしくは、変形した後行トンネルと凍土が剥離して、出水するおそれがある。凍土において出水が生じると、凍土が溶解してしまう。
このような観点から、本発明は、地下水の出水や土砂の流入を防止することで安全性を確保し、かつ、周辺環境への影響(例えば、地盤沈下や地下水位の低下等)を最小限に抑えることを可能とし、なおかつ、効率よく止水性に優れた高品質な大断面地中構造物を構築することを可能とした、大断面地中構造物の構築方法を提案することを課題とする。
In the construction method of Patent Document 1, air mortar is interposed between the following tunnel and the lining body in the preceding tunnel. Since this air mortar needs to be removed to connect the lining body in the preceding tunnel and the lining body formed in the succeeding tunnel, the earth pressure and groundwater pressure acting on the succeeding tunnel from the natural ground side will be reduced. On the other hand, a sufficient reaction force cannot be secured from the preceding tunnel side, and the subsequent tunnel may be deformed. When the succeeding tunnel is deformed, there is a risk that cracks may occur in the frozen ground around the preceding tunnel and the succeeding tunnel, or the deformed succeeding tunnel and the frozen soil may be separated to cause water discharge. When flooding occurs in frozen soil, the frozen soil will melt.
From this point of view, the present invention ensures safety by preventing groundwater discharge and sediment inflow, and minimizes the impact on the surrounding environment (for example, land subsidence and lowering of the groundwater level). It is an object to propose a construction method of a large cross-section underground structure that makes it possible to build a high-quality large cross-section underground structure that is excellent in water-stopping efficiency. To do.

前記課題を解決するために、第一発明の大断面地中構造物の構築方法は、間隔をあけて複数本の先行トンネルを並設する先行トンネル施工工程と、前記各先行トンネル内に先行鉄筋を配筋する先行トンネル配筋工程と、前記各先行トンネル内に先行中詰コンクリートを充填する先行トンネル充填工程と、隣り合う前記先行トンネル同士の間に後行トンネルを構築する後行トンネル施工工程と、前記各後行トンネル内に後行鉄筋を配筋する後行トンネル配筋工程と、前記後行トンネル内に後行中詰コンクリートを充填する後行トンネル充填工程と、複数本の前記先行トンネルおよび複数本の前記後行トンネルにより囲まれた領域を掘削する掘削工程とを備えている。前記後行トンネル施工工程では、隣接する前記先行トンネルの断面の一部および前記先行中詰コンクリートの一部を切削するとともに前記先行中詰コンクリートに凹部を形成し、前記後行トンネルの外面が前記先行中詰コンクリートに当接するように当該後行トンネルを構築する。また、前記後行トンネル配筋工程では、前記凹部に露出した前記先行鉄筋の端部に前記後行鉄筋を接続するで、前記複数本の先行トンネルおよび前記複数本の後行トンネルを貫通する主筋を配筋する。   In order to solve the above-mentioned problems, a construction method of a large cross-section underground structure according to the first invention includes a preceding tunnel construction step in which a plurality of preceding tunnels are arranged side by side at intervals, and a preceding reinforcing bar in each preceding tunnel. A preceding tunnel arrangement step of arranging a preceding tunnel, a preceding tunnel filling step of filling each preceding tunnel with preceding filling concrete, and a subsequent tunnel construction step of constructing a trailing tunnel between the adjacent preceding tunnels A succeeding tunnel arranging step for arranging a succeeding reinforcing bar in each succeeding tunnel, a succeeding tunnel filling step for filling a succeeding intermediate concrete in the succeeding tunnel, and a plurality of the preceding precedents An excavation step of excavating a region surrounded by the tunnel and the plurality of succeeding tunnels. In the subsequent tunnel construction step, a part of a cross section of the adjacent preceding tunnel and a part of the preceding filling concrete are cut and a recess is formed in the preceding filling concrete, and an outer surface of the subsequent tunnel is the The following tunnel is constructed so as to contact the preceding filled concrete. Further, in the succeeding tunnel reinforcing step, the succeeding reinforcing bar is connected to the end of the preceding reinforcing bar exposed in the concave portion, so that the main reinforcing bar penetrates the plurality of preceding tunnels and the plurality of succeeding tunnels. Arrange the bars.

かかる大断面地中構造物の構築方法によれば、後行トンネルの外面が先行中詰コンクリートに当接しているため、後行トンネルに変形が生じることを防止あるいは最小限に抑えることができる。そのため、後行トンネルの切り開き部からの出水を防止し、施工時の安全性が向上する。なお、「後行トンネルの外面が先行中詰コンクリートに当接している」状態は、後行トンネルの覆工が先行中詰コンクリートに当接している場合の他、裏込め材やスペーサー等を介して当接している場合も含むものとする。
また、先行中詰コンクリートに形成した凹部を利用して先行鉄筋と後行鉄筋とを接合するため、一体性に優れた覆工体を簡易に構築することができる。
According to the construction method of such a large cross-section underground structure, since the outer surface of the succeeding tunnel is in contact with the preceding filling concrete, it is possible to prevent or minimize the deformation of the succeeding tunnel. Therefore, water is prevented from flowing out from the cut-off portion of the succeeding tunnel, and safety during construction is improved. The state where the outer surface of the trailing tunnel is in contact with the preceding filling concrete is not limited to the case where the lining of the trailing tunnel is in contact with the preceding filling concrete, or through a backfilling material or a spacer. This includes cases where they are in contact with each other.
Moreover, since the preceding reinforcing bar and the succeeding reinforcing bar are joined using the concave portion formed in the preceding middle-filled concrete, it is possible to easily construct a covering body excellent in unity.

また、前記先行トンネル充填工程では、前記先行鉄筋の端部に間詰材を設置した状態で前記先行中詰コンクリートを充填するのが望ましい。このようにすれば、後行トンネル施工工程において先行トンネルの一部を切削した際に間詰材を撤去することで容易に先行鉄筋の端部を露出させることが可能となる。
また、前記後行トンネル施工工程後に、前記先行トンネルおよび前記後行トンネルの集合体の外周側地山および内周側地山に対して止水対策を施す止水工程を備えていれば、止水性をより向上させることができる。
In the preceding tunnel filling step, it is desirable to fill the preceding middle-filled concrete in a state where a filling material is installed at an end of the preceding reinforcing bar. If it does in this way, it will become possible to expose the end part of a preceding reinforcing bar easily by removing a filling material, when a part of a preceding tunnel is cut in a succeeding tunnel construction process.
In addition, after the construction of the succeeding tunnel, if there is a water stopping process for taking measures against water on the outer and inner peripheral grounds of the assembly of the preceding tunnel and the subsequent tunnel, The aqueous property can be further improved.

本発明の大断面地中構造物の構築方法によれば、高水圧、軟弱地盤等の施工条件が厳しい場所でも、地下水の出水や土砂の流入を防止することで安全性を確保し、かつ、周辺環境への影響を最小限に抑えることを可能とし、なおかつ、効率よく止水性に優れた高品質な大断面地中構造物を構築することが可能となる。   According to the construction method of the large cross-section underground structure of the present invention, even in places where the construction conditions such as high water pressure and soft ground are severe, safety is ensured by preventing the discharge of groundwater and the inflow of earth and sand, and It is possible to minimize the influence on the surrounding environment, and it is possible to construct a high-quality large section underground structure with excellent water-stopping efficiency.

本発明の実施形態の大断面トンネルを示す横断図である。It is a sectional view showing a large section tunnel of an embodiment of the present invention. 大断面覆工体の一部を示す拡大断面図である。It is an expanded sectional view showing a part of large section lining body. 本実施形態の大断面地下構造物の構築方法の各工程を示す断面図であって、先行トンネル施工工程、(b)は(a)に続く先行トンネル施工工程、(c)は先行トンネル配筋工程、(d)は先行トンネル充填工程である。It is sectional drawing which shows each process of the construction method of the large section underground structure of this embodiment, Comprising: A preceding tunnel construction process, (b) is a preceding tunnel construction process following (a), (c) is a preceding tunnel arrangement. Step (d) is a preceding tunnel filling step. 図3に続く大断面地下構造物の構築方法の各工程を示す断面図であって、(a)は後行トンネル施工工程、(b)は止水工程、(c)は後行トンネル接続準備工程である。It is sectional drawing which shows each process of the construction method of the large-section underground structure following FIG. 3, (a) is a subsequent tunnel construction process, (b) is a water stop process, (c) is preparation for subsequent tunnel connection. It is a process. 図4(c)のA部分の拡大断面図である。It is an expanded sectional view of A part of Drawing 4 (c). 図4に続く大断面地下構造物の構築方法の各工程を示す断面図であって、(a)は後行トンネル配筋工程、(b)は後行トンネル充填工程である。It is sectional drawing which shows each process of the construction method of the large-section underground structure following FIG. 4, Comprising: (a) is a subsequent tunnel reinforcement process, (b) is a subsequent tunnel filling process.

本実施形態では、図1に示すように、道路トンネル(本線トンネル11および分岐トンネル12)の合流部の構築に必要な大断面地下空間を形成するための大断面トンネル1を例示する。大断面トンネル1は、本線トンネル11および分岐トンネル12を内包可能な大断面覆工体10により形成されている。
本実施形態の大断面覆工体10は、円筒状に並設された複数本のトンネル2,3と、各トンネル2,3内に充填された中詰コンクリートの硬化体4と、複数本のトンネル2,3に跨って配筋された主筋5とを備えている。なお、複数本のトンネル2,3は、必ずしも円筒状に並設されている必要はなく、例えば、角筒状や楕円筒状に並設されていてもよい。すなわち、大断面覆工体10の断面形状は円形に限定されるものではなく、例えば、矩形状や楕円形状等であってもよい。
In the present embodiment, as shown in FIG. 1, a large-section tunnel 1 for forming a large-section underground space necessary for constructing a junction of road tunnels (main tunnel 11 and branch tunnel 12) is illustrated. The large-section tunnel 1 is formed by a large-section lining body 10 that can include a main tunnel 11 and a branch tunnel 12.
The large cross-section lining body 10 of the present embodiment includes a plurality of tunnels 2 and 3 arranged side by side in a cylindrical shape, a hardened body 4 of filled concrete filled in each tunnel 2 and 3, and a plurality of tunnels. The main bar 5 is arranged across the tunnels 2 and 3. The plurality of tunnels 2 and 3 are not necessarily arranged in a cylindrical shape, and may be arranged in a rectangular tube shape or an elliptic tube shape, for example. That is, the cross-sectional shape of the large cross-section lining body 10 is not limited to a circular shape, and may be, for example, a rectangular shape or an elliptical shape.

大断面覆工体10は、複数本のトンネル2,3として、間隔をあけて形成された複数本の先行トンネル2,2,…と、隣り合う先行トンネル2,2同士の間に形成された後行トンネル3,3,…とを備えている。
本実施形態の先行トンネル2および後行トンネル3は、同じ外径の円筒状の覆工により形成されている。なお、先行トンネル2および後行トンネル3の断面形状は限定されるものではない。例えば、先行トンネル2と後行トンネル3とが、異なる外径を有していてもよい。
The large cross-section lining body 10 is formed as a plurality of tunnels 2, 3 between a plurality of preceding tunnels 2, 2. The following tunnels are provided.
The preceding tunnel 2 and the succeeding tunnel 3 of this embodiment are formed by a cylindrical lining with the same outer diameter. The cross-sectional shapes of the preceding tunnel 2 and the succeeding tunnel 3 are not limited. For example, the preceding tunnel 2 and the succeeding tunnel 3 may have different outer diameters.

隣り合う先行トンネル2と後行トンネル3は、図2に示すように、一部を重ねた状態(ラップさせた状態)で並設されている。
大断面覆工体10は、先行トンネル2と後行トンネル3との重ね合わせ厚さ(トンネルの覆工同士の地山側交点から内空側交点までの間隔)により構造上必要な覆工厚さを確保している。また、大断面覆工体10の内径は、先行トンネル2と後行トンネル3との重ね合わせ幅(一方のトンネルが他方のトンネルに入り込んでいる長さ)の大きさを変えることで変化させることができる。
As shown in FIG. 2, the adjacent preceding tunnel 2 and the succeeding tunnel 3 are juxtaposed in a state of being partially overlapped (wrapped state).
The large cross-section lining body 10 has a necessary lining thickness in terms of the structure due to the overlapping thickness of the preceding tunnel 2 and the succeeding tunnel 3 (the distance from the intersection of the tunnel lining to the intersection on the ground side). Is secured. Further, the inner diameter of the large cross-section lining body 10 can be changed by changing the size of the overlapping width of the preceding tunnel 2 and the succeeding tunnel 3 (the length of one tunnel entering the other tunnel). Can do.

先行トンネル2の覆工20は、無筋コンクリート製のセグメントを組み合わせることにより形成されている。
本実施形態の先行トンネル2の覆工20を構成するセグメントは鋼繊維補強コンクリートにより形成されているが、先行トンネル2の形成に必要な強度を有し、かつ、シールド掘削機により切削が可能であれば、セグメントを構成する材料は限定されない。例えば、切削可能な補強材(例えば、炭素繊維等)が埋め込まれたコンクリート製セグメントを使用してもよい。
本実施形態では、シールド掘削機により切削が可能な樹脂製ボルトを介してセグメント同士およびセグメントリング同士を接合する。なお、セグメント同士の接合構造およびセグメントリング同士の接合構造は、シールド掘削機により切削が可能であれば限定されない。
The lining 20 of the preceding tunnel 2 is formed by combining unreinforced concrete segments.
The segment constituting the lining 20 of the preceding tunnel 2 of this embodiment is formed of steel fiber reinforced concrete, but has the strength necessary for forming the preceding tunnel 2 and can be cut by a shield excavator. If so, the material constituting the segment is not limited. For example, a concrete segment in which a cuttable reinforcing material (for example, carbon fiber) is embedded may be used.
In the present embodiment, the segments and the segment rings are joined via a resin bolt that can be cut by a shield excavator. In addition, the joining structure between segments and the joining structure between segment rings will not be limited if cutting with a shield excavator is possible.

後行トンネル3の覆工30は、大断面覆工体10の外周側の地山に面するコンクリート中詰鋼製セグメント31と、その他の部分に配設された鋼製セグメント32とを組み合わせることにより形成されている。
コンクリート中詰鋼製セグメント31は、トンネル軸方向の両端に設けられた一対の主桁と、トンネル周方向の両端に設けられた一対の端板と、主桁および端板の外面を覆うスキンプレートとからなる鋼製セグメントにコンクリートが打設されることにより構成されている。コンクリート中詰鋼製セグメント31は、両隣りの先行トンネル2,2により挟まれた範囲に配設されている。
鋼製セグメント32は、トンネル軸方向の両端に設けられた一対の主桁と、トンネル周方向の両端に設けられた一対の端板と、外面を覆うスキンプレートとを備えて構成されている。鋼製セグメント32のうちの両隣りの先行トンネル2,2の内部に配設された部分では、スキンプレートが撤去されて、主桁および端板が残置されている。
The lining 30 of the trailing tunnel 3 is a combination of a concrete-filled steel segment 31 facing the ground on the outer peripheral side of the large cross-section lining body 10 and a steel segment 32 disposed in the other part. It is formed by.
The concrete-filled steel segment 31 includes a pair of main girders provided at both ends in the tunnel axial direction, a pair of end plates provided at both ends in the circumferential direction of the tunnel, and a skin plate that covers the outer surfaces of the main girders and the end plates Concrete is cast in a steel segment consisting of The concrete-filled steel segment 31 is disposed in a range sandwiched between the adjacent preceding tunnels 2 and 2.
The steel segment 32 includes a pair of main girders provided at both ends in the tunnel axial direction, a pair of end plates provided at both ends in the tunnel circumferential direction, and a skin plate that covers the outer surface. In the portion of the steel segment 32 disposed inside the adjacent adjacent tunnels 2 and 2, the skin plate is removed, and the main girder and the end plate are left.

先行トンネル2の内部の中詰コンクリートの硬化体4(先行中詰コンクリート41)には、凹部(箱抜き)6が形成されている。凹部6は、後行トンネル3に面する位置で、かつ、主筋5の通る位置(大断面覆工体10の外周側と内周側)に形成されている。後行トンネル3の中詰コンクリートの硬化体4(後行中詰コンクリート42)には、凹部6に係合された凸部7が形成されている。なお、本実施形態では、先行トンネル2の内部に充填する先行中詰コンクリート41と後行トンネル3の内部に充填する後行中詰コンクリート42として同じ配合のコンクリートを採用するが、先行中詰コンクリート41と後行中詰コンクリート42には、それぞれ異なる配合のコンクリートを充填してもよい。また、少なくとも先行中詰コンクリート41は、大断面覆工体10に作用する外力に対して十分な耐力を発現するとともに、シールド掘削機による切削が可能な材料であれば限定されるものではない。一方、後行中詰コンクリート42は、大断面覆工体10に作用する外力に対して十分な耐力を発現するものであればよい。   A recessed portion (box removal) 6 is formed in the hardened concrete 4 (previous filling concrete 41) inside the preceding tunnel 2. The recess 6 is formed at a position facing the follower tunnel 3 and at a position through which the main reinforcement 5 passes (an outer peripheral side and an inner peripheral side of the large cross-section covering body 10). A convex portion 7 engaged with the concave portion 6 is formed on the hardened material 4 (following middle-filled concrete 42) of the filling concrete in the trailing tunnel 3. In the present embodiment, the same filling concrete is adopted as the preceding filling concrete 41 filling the inside of the preceding tunnel 2 and the following filling concrete 42 filling the inside of the following tunnel 3, but the preceding filling concrete is used. 41 and post-filling concrete 42 may be filled with different blends of concrete. Further, at least the preceding filled concrete 41 is not limited as long as it is a material that exhibits sufficient proof strength against the external force acting on the large cross-section lining body 10 and can be cut by a shield excavator. On the other hand, the following filling concrete 42 only needs to exhibit sufficient proof strength against the external force acting on the large cross-section covering body 10.

主筋5は、大断面覆工体10の周方向に連続するように、内空側と地山側にそれぞれ配筋されている。主筋5は、並設されたトンネル2,3を周方向に貫通している。本実施形態では、主筋5と交差するようにせん断補強筋50が配筋されている。なお、せん断補強筋50は必要に応じて配筋すればよく、例えば、中詰コンクリートとして繊維補強コンクリートを採用した場合には省略してもよい。   The main reinforcing bars 5 are arranged on the inner sky side and the natural ground side so as to be continuous in the circumferential direction of the large cross-section lining body 10. The main reinforcement 5 penetrates the tunnels 2 and 3 arranged side by side in the circumferential direction. In the present embodiment, the shear reinforcement bars 50 are arranged so as to intersect the main bars 5. The shear reinforcing bars 50 may be arranged as necessary, and may be omitted, for example, when fiber reinforced concrete is used as the filling concrete.

次に、本実施形態の大断面トンネル1の構築方法について説明する。
大断面トンネル1の構築方法は、先行トンネル施工工程、先行トンネル配筋工程、先行トンネル充填工程、後行トンネル施工工程、止水工程、接続準備工程と、後行トンネル配筋工程、後行トンネル充填工程および掘削工程を備えている。
Next, a method for constructing the large-section tunnel 1 of the present embodiment will be described.
The construction method of the large section tunnel 1 includes the preceding tunnel construction process, the preceding tunnel arrangement process, the preceding tunnel filling process, the subsequent tunnel construction process, the water stop process, the connection preparation process, the subsequent tunnel arrangement process, and the subsequent tunnel. It has a filling process and a drilling process.

先行トンネル施工工程は、図3(a)に示すように、複数本の先行トンネル2,2を、間隔をあけて並設する工程である。
先行トンネル2の施工は、図示しないシールド掘削機により地山を切削するとともに、シールド掘削機の後部においてセグメントリング(覆工20)を形成し、このセグメントリングをシールド掘削機の後方に連設することにより行う。先行トンネル2同士の間隔は、トンネル2,3の断面形状、先行トンネル2と後行トンネル3とのラップ長(重ね合わせ幅)および大断面覆工体10の断面形状等に応じて適宜設定する。
本実施形態では、図3(b)に示すように、覆工20の内面に、トンネル軸方向に沿って、凍結管81を配管する。凍結管81は、大断面覆工体10の外周側と内周側にそれぞれ3本ずつ配管する。なお、凍結管81の本数および間隔は、先行トンネル2の断面形状や地山状況等に応じて適宜決定すればよい。凍結管81を配管したら、外周側の凍結管81の内空側に断熱材82を設置するとともに、防水材83を吹き付ける(図5参照)。なお、断熱材82および防水材83は、必要に応じて設置すればよく、省略してもよい。また、断熱材82および防水材83は、内周側の凍結管8に対しても設置してもよい。
As shown in FIG. 3A, the preceding tunnel construction process is a process in which a plurality of preceding tunnels 2 and 2 are arranged side by side at intervals.
The construction of the preceding tunnel 2 is performed by cutting a natural ground with a shield excavator (not shown), forming a segment ring (lining 20) at the rear of the shield excavator, and connecting this segment ring to the rear of the shield excavator. By doing. The interval between the preceding tunnels 2 is appropriately set according to the cross-sectional shape of the tunnels 2 and 3, the wrap length (overlapping width) between the preceding tunnel 2 and the succeeding tunnel 3, the cross-sectional shape of the large cross-section lining body 10, and the like. .
In the present embodiment, as shown in FIG. 3B, a freezing pipe 81 is piped on the inner surface of the lining 20 along the tunnel axis direction. Three freezing pipes 81 are provided on each of the outer peripheral side and the inner peripheral side of the large cross-section lining body 10. In addition, what is necessary is just to determine suitably the number and space | interval of the freezing pipe 81 according to the cross-sectional shape of the preceding tunnel 2, a natural ground condition, etc. FIG. When the freezing pipe 81 is piped, the heat insulating material 82 is installed on the inner side of the outer freezing pipe 81 and the waterproof material 83 is sprayed (see FIG. 5). The heat insulating material 82 and the waterproof material 83 may be installed as necessary and may be omitted. Further, the heat insulating material 82 and the waterproof material 83 may be installed on the inner peripheral side freezing pipe 8.

先行トンネル配筋工程は、図3(c)に示すように、先行トンネル2内に先行鉄筋51(主筋5)およびせん断補強筋50を配筋する工程である。
先行鉄筋51は、大断面覆工体10の外周側と内空側に、覆工20から所定の間隔を空けて配筋する。本実施形態では、先行鉄筋51の両端に予め機械式継手53を設置しておくとともに、機械式継手53の端部を覆う間詰材43を配置しておく。なお、間詰材43を構成する材料はこれに限定されるものではないが、例えば、先行中詰コンクリート41よりも低強度な材料からなる密実部材(例えば、硬質ウレタンフォーム材等)を使用すればよい。
The preceding tunnel reinforcement step is a step of arranging a preceding reinforcing bar 51 (main reinforcing bar 5) and a shear reinforcing bar 50 in the preceding tunnel 2 as shown in FIG.
The preceding reinforcing bars 51 are arranged at a predetermined interval from the lining 20 on the outer peripheral side and the inner space side of the large cross-section lining body 10. In the present embodiment, mechanical joints 53 are installed in advance at both ends of the preceding reinforcing bar 51, and a padding material 43 that covers the ends of the mechanical joints 53 is disposed. In addition, although the material which comprises the filling material 43 is not limited to this, For example, the solid member (for example, hard urethane foam material etc.) which consists of material lower in strength than the preceding filling concrete 41 is used. do it.

先行トンネル充填工程は、図3(d)に示すように、先行トンネル2内に先行中詰コンクリート41を充填する工程である。
先行トンネル2内への先行中詰コンクリート41の打設は、コンクリートポンプで圧送することにより、先行トンネル2の先端側から行う。先行中詰コンクリート41の打設は、先行鉄筋51およびせん断補強筋50の配筋が完了した先行トンネル2から順に実施する。なお、先行中詰コンクリート41の打設のタイミングは限定されるものではなく、例えば、全ての先行トンネル2,2,…の配筋作業が完了してから実施してもよい。また、先行中詰コンクリート41の打設方法も限定されるものではなく、例えば、先行トンネル2の中間部から打設してもよい。
The preceding tunnel filling step is a step of filling the preceding filling concrete 41 in the preceding tunnel 2 as shown in FIG.
The placement of the preceding filled concrete 41 into the preceding tunnel 2 is performed from the front end side of the preceding tunnel 2 by pumping with a concrete pump. The placement of the preceding filling concrete 41 is performed in order from the preceding tunnel 2 in which the placement of the preceding reinforcing bar 51 and the shear reinforcing bar 50 is completed. In addition, the timing of placement of the preceding filling concrete 41 is not limited. For example, it may be performed after the bar arrangement work of all the preceding tunnels 2, 2,. Further, the method for placing the preceding filling concrete 41 is not limited, and for example, it may be placed from an intermediate portion of the preceding tunnel 2.

後行トンネル施工工程は、図4(a)に示すように、隣り合う先行トンネル2,2同士の間に後行トンネル3を構築する工程である。
後行トンネル3の施工は、まず、シールド掘削機(図示せず)を利用して、隣接する先行トンネル2,2の断面の一部および先行トンネル2内に充填された先行中詰コンクリート41の硬化体4の一部を切削しながら掘削孔を形成する。後行トンネル3は、その周囲に充填された裏込め材を介して先行中詰コンクリート41の硬化体4に当接する。
シールド掘削機により所定延長掘進したら、シールド掘削機の後方でセグメントを組み立てて、覆工30を形成する。
The subsequent tunnel construction process is a process of constructing the subsequent tunnel 3 between the adjacent preceding tunnels 2 and 2 as shown in FIG.
The construction of the trailing tunnel 3 is carried out by first using a shield excavator (not shown) and a part of the cross section of the adjacent preceding tunnels 2, 2 and the preceding filling concrete 41 filled in the preceding tunnel 2. An excavation hole is formed while cutting a part of the cured body 4. The trailing tunnel 3 comes into contact with the hardened body 4 of the preceding filling concrete 41 through the backfilling material filled in the periphery thereof.
After a predetermined extended excavation by the shield excavator, the segments are assembled behind the shield excavator to form the lining 30.

後行トンネル3を施工するタイミングは、隣り合う2本の先行トンネル2,2が形成され、かつ、両先行トンネル2,2内の先行中詰コンクリートが充填された後であれば限定されるものではない。すなわち、後行トンネル3は、少なくとも2本の先行トンネル2,2が施工された後であれば、施工を開始してもよく、また、全ての先行トンネル2,2,…が完成した後から施工を開始してもよい。
次に、後行トンネル3の覆工30の内面に沿って、凍結管81を配管する。凍結管81は、大断面覆工体10の外周側と内周側にそれぞれ3本ずつ配管する。なお、凍結管81の本数および間隔は、先行トンネル2の断面形状や地山状況等に応じて適宜決定すればよい。凍結管81を配管したら、凍結管81の内空側に、断熱材82を設置するとともに、連続する防水材83を吹き付ける(図5参照)。なお、断熱材82および防水材83は、必要に応じて設置すればよく、省略してもよい。
The timing for constructing the succeeding tunnel 3 is limited as long as the two adjacent preceding tunnels 2 and 2 are formed and the preceding filling concrete in both the preceding tunnels 2 and 2 is filled. is not. That is, the construction of the succeeding tunnel 3 may be started after at least two preceding tunnels 2, 2 are constructed, and after all the preceding tunnels 2, 2,. Construction may begin.
Next, a freezing pipe 81 is piped along the inner surface of the lining 30 of the trailing tunnel 3. Three freezing pipes 81 are provided on each of the outer peripheral side and the inner peripheral side of the large cross-section lining body 10. In addition, what is necessary is just to determine suitably the number and space | interval of the freezing pipe 81 according to the cross-sectional shape of the preceding tunnel 2, a natural ground condition, etc. FIG. When the freezing pipe 81 is piped, a heat insulating material 82 is installed on the inner side of the freezing pipe 81 and a continuous waterproofing material 83 is sprayed (see FIG. 5). The heat insulating material 82 and the waterproof material 83 may be installed as necessary and may be omitted.

止水工程は、図4(b)に示すように、先行トンネル2,2および後行トンネル3の集合体の外周側地山および内周側地山に対して止水対策工を施す工程である。本実施形態では、地山を凍結することで、止水層(凍土)8を形成する凍結工法を採用する。地山の凍結作業は、凍結管81内に冷媒を通流させることにより、トンネル2,3の外側の地山を冷却することにより行う。
止水工程の実施は、少なくとも2本の先行トンネル2,2と、これらの先行トンネル2,2の間の後行トンネル3とが形成された後であれば限定されるものではない。すなわち、止水層8の施工は、全ての先行トンネル2,2,…および後行トンネル3,3,…が形成された後に実施してもよいし、先行トンネル2,2および後行トンネル3が部分的に形成された後に実施してもよい。これにより、全ての先行トンネル2、後行トンネル3の構築を待たなくても部分的に止水工程〜充填工程を実施できるため、工期短縮を図ることができる。また、長期間にわたって大きな範囲を止水する必要がないため、安全性も向上する。
As shown in FIG. 4 (b), the water stop process is a process in which water stop measures are applied to the outer and inner peripheral grounds of the assembly of the preceding tunnels 2 and 2 and the subsequent tunnel 3. is there. In the present embodiment, a freezing method is employed in which a still water layer (frozen soil) 8 is formed by freezing the natural ground. The freezing operation of the natural ground is performed by cooling the natural ground outside the tunnels 2 and 3 by passing the refrigerant through the freezing pipe 81.
The implementation of the water stop process is not limited as long as at least two preceding tunnels 2 and 2 and a succeeding tunnel 3 between these preceding tunnels 2 and 2 are formed. That is, the construction of the water blocking layer 8 may be performed after all the preceding tunnels 2, 2,... And the succeeding tunnels 3, 3,. May be carried out after partially forming. Thereby, even if it does not wait for construction of all the preceding tunnels 2 and the succeeding tunnel 3, it can implement a water stop process-a filling process partially, Therefore A construction period can be shortened. Moreover, since it is not necessary to stop a large range over a long period of time, safety is also improved.

接続準備工程は、図4(c)に示すように、後行トンネル3の覆工30のうち、先行中詰コンクリート41との当接部分に対応する鋼製セグメントのスキンプレートを撤去する工程である。本実施形態では、まず、先行トンネル2と後行トンネル3との接合部において、スキンプレート33の一部を撤去するとともに必要最小限の裏込め材を撤去し、さらに、図6(a)に示すように、鋼製セグメント32の主桁と先行中詰コンクリート41との間にくさび状のスペーサー9を介設する。この作業を繰り返すことにより必要な数のスペーサー9を介設したら、先行トンネル2と後行トンネル3との接合部に対応するスキンプレート33の残り部分と当該スキンプレート33の背面に充填された裏込め材34も撤去して、先行中詰コンクリート41の表面を露出させる(図2および図6(a)参照)。この結果、後行トンネル3は、スペーサー9を介して先行トンネル2の硬化体4に当接する。このように、本実施形態では、スペーサー9を介設する際に、スキンプレート33と裏込め材の撤去範囲を最小限に抑えることで、後行トンネル3の変形を最小限に抑える。本実施形態のスペーサー9は、金属製の部材により構成されている。なお、スペーサー9の形状および材質は限定されるものではない。
接続準備工程では、スキンプレート33と裏込め材34の撤去により露出した先行中詰コンクリート41の表面に対してチッピングを行い、当該表面に凹凸を形成する。また、凹部6内に入り込んだ裏込め材34も除去する。なお、チッピングは必要に応じて行えばよい。
As shown in FIG. 4C, the connection preparation step is a step of removing the skin plate of the steel segment corresponding to the contact portion with the preceding filling concrete 41 in the lining 30 of the subsequent tunnel 3. is there. In the present embodiment, first, a part of the skin plate 33 is removed at the joint portion between the preceding tunnel 2 and the succeeding tunnel 3, and the necessary minimum backfill material is removed, and further, as shown in FIG. As shown, a wedge-shaped spacer 9 is interposed between the main beam of the steel segment 32 and the preceding filling concrete 41. When the necessary number of spacers 9 are interposed by repeating this operation, the remaining portion of the skin plate 33 corresponding to the joint portion between the preceding tunnel 2 and the succeeding tunnel 3 and the back surface filled in the back surface of the skin plate 33 are filled. The filling material 34 is also removed to expose the surface of the preceding filled concrete 41 (see FIGS. 2 and 6A). As a result, the trailing tunnel 3 comes into contact with the cured body 4 of the preceding tunnel 2 via the spacer 9. Thus, in the present embodiment, when the spacer 9 is interposed, the deformation of the subsequent tunnel 3 is minimized by minimizing the removal range of the skin plate 33 and the backfill material. The spacer 9 of the present embodiment is constituted by a metal member. The shape and material of the spacer 9 are not limited.
In the connection preparation process, chipping is performed on the surface of the preceding middle-filled concrete 41 exposed by removing the skin plate 33 and the backfilling material 34, and irregularities are formed on the surface. Further, the backfill material 34 that has entered the recess 6 is also removed. Note that chipping may be performed as necessary.

スキンプレート33を撤去したら、間詰材43を撤去する。間詰材43を撤去すると、先行トンネル2の硬化体4(先行中詰コンクリート41)に、後行トンネル3側に開口する箱抜き(凹部6)が形成される。凹部6内では、先行鉄筋51(機械式継手53)の端部が露出している。
凹部6(箱抜き)が露出したら、図5に示すように、先行トンネル2と後行トンネル3との接合部において、先行トンネル2の端部(後行トンネル3に隣接する部分)に後行トンネル3側に突出する鋼板21を固定する。鋼板21は、後行トンネル3の裏込め材34の端面を覆うように配置し、コンクリートアンカー22を介して先行トンネル2の覆工20に固定する。すなわち、鋼板21は、先行トンネル2の覆工20と後行トンネル3の覆工30との間に横架されている。
また、先行トンネル2と後行トンネル3との接合部(後行トンネル3のコンクリート中詰鋼製セグメント31の端面)に対し、断熱材82および防水材83を設置する。
さらに、鋼製セグメント32の端部において、鋼製セグメント32の側面に防水材83を吹き付ける。なお、符号35は水膨張シール、符号36は後行トンネル3のセグメントリング間用シール、符号37はコーキング材である。
When the skin plate 33 is removed, the interstitial material 43 is removed. When the filling material 43 is removed, a box opening (concave portion 6) opened to the subsequent tunnel 3 side is formed in the cured body 4 (preceding intermediate concrete 41) of the preceding tunnel 2. In the recessed part 6, the edge part of the preceding reinforcement 51 (mechanical coupling 53) is exposed.
When the recess 6 (box removal) is exposed, as shown in FIG. 5, at the junction between the preceding tunnel 2 and the succeeding tunnel 3, the end of the preceding tunnel 2 (the part adjacent to the succeeding tunnel 3) is followed. The steel plate 21 protruding to the tunnel 3 side is fixed. The steel plate 21 is disposed so as to cover the end face of the backfill material 34 of the subsequent tunnel 3, and is fixed to the lining 20 of the preceding tunnel 2 via the concrete anchor 22. That is, the steel plate 21 is laid across the lining 20 of the preceding tunnel 2 and the lining 30 of the subsequent tunnel 3.
Further, a heat insulating material 82 and a waterproof material 83 are installed at the joint portion between the preceding tunnel 2 and the following tunnel 3 (the end surface of the concrete-filled steel segment 31 of the following tunnel 3).
Further, a waterproof material 83 is sprayed on the side surface of the steel segment 32 at the end of the steel segment 32. Reference numeral 35 denotes a water expansion seal, reference numeral 36 denotes a seal between segment rings of the trailing tunnel 3, and reference numeral 37 denotes a caulking material.

ここで、先行トンネル2と後行トンネル3との接合部の周辺では、後行トンネル3の裏込め材34として、高強度裏込め材を充填しておくことで、スキンプレート33とその背面の裏込め材34とを撤去した際に、後行トンネル3が変形することを防止する。すなわち、後行トンネル3の変形を抑制するためのスペーサー9を介設する際に、先行して最小限のスキンプレート33と裏込め材34を撤去するが、接合部周辺の高強度裏込め材によって、その時点での後行トンネル3の変形を抑制する。また、スキンプレート33および裏込め材34を撤去することによって後行トンネル3が変形しようとすると、支点となる先行トンネル2のセグメント(覆工30)に挟まれた裏込め材34が圧縮されて後行トンネル3の変形が促進されるが、この支点の周囲の裏込め材34を高強度裏込め材とすることで、裏込め材の変形を抑制し、ひいては、後行トンネル3の変位量を最小限に抑える。ここで、高強度裏込め材とは、通常の裏込め材34と同様に充填初期の可塑性を有し、かつ、硬化後に中詰コンクリート4と同様の強度を発現するものとする。なお、高強度裏込め材の強度は必要に応じて変更させればよい。また、高強度裏込め材は必要に応じて使用する。   Here, in the vicinity of the junction between the preceding tunnel 2 and the subsequent tunnel 3, a high-strength backfill material is filled as the backfill material 34 of the subsequent tunnel 3, so that The rear tunnel 3 is prevented from being deformed when the backfill material 34 is removed. That is, when the spacer 9 for suppressing the deformation of the trailing tunnel 3 is interposed, the minimum skin plate 33 and the backing material 34 are removed in advance, but the high-strength backing material around the joint is removed. Therefore, the deformation of the succeeding tunnel 3 at that time is suppressed. Further, when the succeeding tunnel 3 is to be deformed by removing the skin plate 33 and the backfilling material 34, the backfilling material 34 sandwiched between the segments (lining 30) of the preceding tunnel 2 serving as a fulcrum is compressed. Although the deformation of the following tunnel 3 is promoted, the back-filling material 34 around this fulcrum is made of high-strength back-filling material, so that the deformation of the back-filling material is suppressed. To minimize. Here, the high-strength backfilling material has plasticity at the initial stage of filling like the normal backfilling material 34, and expresses the same strength as the filled concrete 4 after curing. In addition, what is necessary is just to change the intensity | strength of a high intensity | strength backfilling material as needed. In addition, a high-strength backfill material is used as necessary.

後行トンネル配筋工程は、図6(a)に示すように、各後行トンネル3内に後行鉄筋52(主筋5)およびせん断補強筋50を配筋する工程である。
後行鉄筋52は、箱抜き(凹部6)内において、先行鉄筋51(機械式継手53)に接続する。
As shown in FIG. 6A, the succeeding tunnel reinforcing step is a step of arranging the succeeding reinforcing bar 52 (main reinforcing bar 5) and the shear reinforcing bar 50 in each succeeding tunnel 3.
The trailing reinforcing bar 52 is connected to the leading reinforcing bar 51 (mechanical joint 53) in the box opening (recess 6).

後行トンネル充填工程は、図6(b)に示すように、後行トンネル3内に後行中詰コンクリート42を充填する工程である。
後行トンネル3内への後行中詰コンクリート42の打設は、コンクリートポンプで圧送することにより、先行トンネル2の先端側から行う。後行中詰コンクリート42を打設すると、後行中詰コンクリート42の一部が凹部6に入り込むことで、凸部7が形成される。なお、後行トンネル3内への中詰コンクリート42の打設のタイミングは限定されるものではなく、例えば、全ての後行トンネル3の施工が完了してから実施してもよいし、施工が完了した後行トンネル3から順に実施してもよい。また、後行中詰コンクリート42の打設方法も限定されるものではない。中詰コンクリート4に所定の強度が発現したら、大断面覆工体10が完成する。
As shown in FIG. 6B, the subsequent tunnel filling step is a step of filling the subsequent intermediate filling concrete 42 into the subsequent tunnel 3.
The placement of the subsequent filling concrete 42 into the subsequent tunnel 3 is performed from the front end side of the preceding tunnel 2 by being pumped by a concrete pump. When the subsequent filling concrete 42 is placed, a part of the following filling concrete 42 enters the concave portion 6, so that the convex portion 7 is formed. The timing of placing the filled concrete 42 in the trailing tunnel 3 is not limited. For example, it may be performed after the construction of all the trailing tunnels 3 is completed. You may implement in order from the succeeding tunnel 3 after completion. Further, the method for placing the subsequent filling concrete 42 is not limited. When the predetermined strength is developed in the filled concrete 4, the large cross-section lining body 10 is completed.

掘削工程は、大断面覆工体10(先行トンネル2および後行トンネル3)により囲まれた領域を掘削して大断面トンネル1を形成する工程である(図1参照)。
本実施形態では、大断面覆工体10の頂部から掘削を行う。なお、大断面覆工体10の内部の掘削方法は限定されるものではなく、例えば、下部(路盤)から掘削してもよい。
The excavation process is a process of excavating a region surrounded by the large cross-section lining body 10 (the preceding tunnel 2 and the subsequent tunnel 3) to form the large cross-section tunnel 1 (see FIG. 1).
In the present embodiment, excavation is performed from the top of the large cross-section lining body 10. In addition, the excavation method inside the large cross-section lining body 10 is not limited, For example, you may excavate from the lower part (roadbed).

本実施形態の大断面覆工体10および大断面トンネルの施工方法によれば、後行トンネル施工工程においては後行トンネル3の外面が裏込め材を介して先行中詰コンクリート41に当接し、接続準備工程の後はスペーサー9を介して後行トンネル3の外面がスペーサー9を介して先行中詰コンクリート41に当接しているため、後行トンネル3に変形が生じることを防止あるいは最小限に抑えることができる。後行トンネル3の変位を抑制することで、止水層8に亀裂が生じることを防止し、かつ、後行トンネル3と止水層8とが剥離することを防止できるので、地下水の出水や土砂の流入を防止し、ひいては、安全性が向上し、かつ、周辺環境への影響を最小限に抑えることができ、なおかつ、高品質な覆工体を構築することができる。
なお、後行トンネル3の変位を抑制することを目的として後行トンネル3のセグメントの仕様を大きくすると、不経済であるとともに、セグメントの運搬および組立に手間がかかる。また同様に後行トンネル3に別途支保構造を構築すると、その作業自体に手間がかかるだけでなく、大断面覆工体10の施工時(後行鉄筋52の配筋および後行中詰コンクリート42の打設)においてそれらが作業の支障になり、かつそれらは残置され大断面覆工体10を貫通することになるため、大断面覆工体10の止水性が低下するとともに、費用が増大する。一方、本実施形態では、スペーサー9を利用して後行トンネル3の変位を抑制するため、セグメントの仕様を最小限に抑えることが可能となり、経済的であるとともに施工性および止水性に優れている。
According to the construction method of the large cross-section lining body 10 and the large cross-section tunnel of the present embodiment, in the subsequent tunnel construction process, the outer surface of the subsequent tunnel 3 comes into contact with the preceding filling concrete 41 via the backfilling material, After the connection preparation step, the outer surface of the succeeding tunnel 3 is in contact with the preceding filling concrete 41 via the spacer 9 via the spacer 9, so that deformation of the succeeding tunnel 3 is prevented or minimized. Can be suppressed. By suppressing the displacement of the trailing tunnel 3, it is possible to prevent cracks in the water blocking layer 8 and to prevent the trailing tunnel 3 and the water blocking layer 8 from peeling off. The inflow of earth and sand can be prevented, and as a result, the safety can be improved, the influence on the surrounding environment can be minimized, and a high-quality lining body can be constructed.
In addition, if the specification of the segment of the trailing tunnel 3 is increased for the purpose of suppressing the displacement of the trailing tunnel 3, it is uneconomical and it takes time to transport and assemble the segment. Similarly, if a separate support structure is constructed in the succeeding tunnel 3, not only the work itself takes time, but also during construction of the large cross-section lining body 10 (the reinforcement of the succeeding rebar 52 and the following filling concrete 42). Since they are obstructed in the operation, and they are left behind and penetrate the large cross-section lining body 10, the water stoppage of the large-section lining body 10 decreases and the cost increases. . On the other hand, in the present embodiment, since the displacement of the trailing tunnel 3 is suppressed using the spacer 9, it becomes possible to minimize the specification of the segment, and it is economical and has excellent workability and water stoppage. Yes.

また、先行中詰コンクリート41が充填された先行トンネル2を切削するため、先行トンネル2の覆工20を切削した際に先行トンネル2に破損が生じることが防止されており、安全な施工を可能としている。そのため、後行トンネル3を施工する際に、先行トンネル2内に支保構造を構築する必要がない。
また、先行中詰コンクリート41に形成した箱抜き(凹部6)を利用して先行鉄筋51と後行鉄筋52とを接合するため、一体性に優れた大断面覆工体10を簡易に構築することができる。
In addition, since the preceding tunnel 2 filled with the preceding filling concrete 41 is cut, the preceding tunnel 2 is prevented from being damaged when the lining 20 of the preceding tunnel 2 is cut, and safe construction is possible. It is said. Therefore, it is not necessary to construct a support structure in the preceding tunnel 2 when constructing the following tunnel 3.
In addition, since the preceding reinforcing bar 51 and the succeeding reinforcing bar 52 are joined using the box opening (recess 6) formed in the preceding filling concrete 41, the large cross-section lining body 10 excellent in unity is constructed. be able to.

また、スキンプレートの撤去により露出した先行中詰コンクリート41の表面にチッピングを行っているため、先行中詰コンクリート41と後行中詰コンクリート42との一体性が向上する。   Further, since chipping is performed on the surface of the preceding filling concrete 41 exposed by removing the skin plate, the integrity of the preceding filling concrete 41 and the following filling concrete 42 is improved.

以上、本発明の実施形態について説明したが本発明は、前述の実施形態に限られず、前記の各構成要素については、本発明の趣旨を逸脱しない範囲で、適宜変更が可能である。
前記実施形態では大断面トンネルを構築する場合について説明したが、大断面地下構造物はトンネルに限定されるものではない。
前記実施形態では、道路トンネルを構築する場合について説明したが、大断面トンネル1(大断面覆工体10)の用途は道路に限定されるものではなく、例えば鉄道等、その他のあらゆる地下構造物に適用することができる。
前記実施形態では、大断面覆工体10が、本線トンネル11と分岐トンネル12との2本のトンネルを巻き込む場合について説明したが、大断面覆工体10は、必ずしも2本のトンネルを巻き込んでいる必要はない。
トンネル2,3の形状寸法や本数等は、大断面トンネル1の形状寸法に応じて適宜決定すればよい。
Although the embodiments of the present invention have been described above, the present invention is not limited to the above-described embodiments, and the above-described constituent elements can be appropriately changed without departing from the spirit of the present invention.
Although the case where the large-section tunnel is constructed has been described in the above embodiment, the large-section underground structure is not limited to the tunnel.
In the above embodiment, the case where a road tunnel is constructed has been described. However, the use of the large section tunnel 1 (large section lining body 10) is not limited to a road, and for example, any other underground structure such as a railway. Can be applied to.
In the above-described embodiment, the case where the large cross-section lining body 10 involves two tunnels of the main tunnel 11 and the branch tunnel 12 has been described. However, the large cross-section lining body 10 does not necessarily involve two tunnels. There is no need to be.
The shape dimensions and number of the tunnels 2 and 3 may be appropriately determined according to the shape dimensions of the large-section tunnel 1.

前記実施形態では、先行中詰コンクリート41を打設する前に、先行鉄筋51の端部に間詰材43を設置しておく場合について説明したが、箱抜き(凹部6)の形成方法は限定されない。例えば、先行鉄筋51の端部周辺に先行中詰コンクリート41よりも低強度なコンクリートを打設しておき、後行トンネル施工工程において低強度なコンクリートを撤去することにより凹部6を形成してもよいし、先行鉄筋51の端部に箱抜き用の型枠を設置しておいてもよい。
止水層8の施工は必要に応じて行えばよい。例えば、湧水量の少ない地盤の場合には、止水工程は省略してもよい。また、前記実施形態では、止水層8を凍土により形成する場合について説明したが、止水層8の形成方法は限定されるものではなく、例えば、薬液注入により形成してもよい。また、止水層8は、地山状況に応じて凍結工法と薬液注入工法とを組み合わせてもよい。
In the above-described embodiment, the case where the filling material 43 is installed at the end of the preceding reinforcing bar 51 before placing the preceding filling concrete 41 has been described, but the method of forming the box (recess 6) is limited. Not. For example, even if the recessed portion 6 is formed by placing concrete having lower strength than the preceding filling concrete 41 around the end portion of the preceding reinforcing bar 51 and removing the low strength concrete in the subsequent tunnel construction process. Alternatively, a box forming mold may be installed at the end of the preceding reinforcing bar 51.
The construction of the water blocking layer 8 may be performed as necessary. For example, in the case of ground with a small amount of spring water, the water stop process may be omitted. Moreover, although the said embodiment demonstrated the case where the water stop layer 8 was formed with frozen soil, the formation method of the water stop layer 8 is not limited, For example, you may form by chemical | medical solution injection | pouring. Moreover, the water stop layer 8 may combine a freezing method and a chemical solution injection method according to the natural ground conditions.

1 大断面トンネル(大断面地下構造物)
10 大断面覆工体
11 本線トンネル
12 分岐トンネル
2 先行トンネル
20 覆工
3 後行トンネル
30 覆工
31 コンクリート中詰鋼製セグメント
32 鋼製セグメント
4 硬化体
41 先行中詰コンクリート
42 後行中詰コンクリート
5 主筋
51 先行鉄筋
52 後行鉄筋
6 凹部
7 凸部
8 止水層
9 スペーサー
1 Large section tunnel (large section underground structure)
DESCRIPTION OF SYMBOLS 10 Large section lining body 11 Main line tunnel 12 Branch tunnel 2 Leading tunnel 20 Covering 3 Trailing tunnel 30 Covering 31 Concrete filling steel segment 32 Steel segment 4 Hardened body 41 Leading filling concrete 42 Backing filling concrete 5 Reinforcing Bars 51 Leading Reinforcing Bars 52 Backing Reinforcing Bars 6 Concave portions 7 Convex Portions 8 Waterstops 9 Spacers

Claims (3)

間隔をあけて複数本の先行トンネルを並設する先行トンネル施工工程と、
前記各先行トンネル内に先行鉄筋を配筋する先行トンネル配筋工程と、
前記各先行トンネル内に先行中詰コンクリートを充填する先行トンネル充填工程と、
隣り合う前記先行トンネル同士の間に後行トンネルを構築する後行トンネル施工工程と、
前記後行トンネル内に後行鉄筋を配筋する後行トンネル配筋工程と、
前記後行トンネル内に後行中詰コンクリートを充填する後行トンネル充填工程と、
複数本の前記先行トンネルおよび複数本の前記後行トンネルにより囲まれた領域を掘削する掘削工程と、を備える大断面地中構造物の構築方法であって、
前記後行トンネル施工工程では、隣接する前記先行トンネルの断面の一部および前記先行中詰コンクリートの一部を切削するとともに前記先行中詰コンクリートに凹部を形成し、前記後行トンネルの外面が前記先行中詰コンクリートに当接するように当該後行トンネルを構築し、
前記後行トンネル配筋工程では、前記凹部に露出した前記先行鉄筋の端部に前記後行鉄筋を接続することで、前記複数本の先行トンネルおよび前記複数本の後行トンネルを貫通する主筋を配筋することを特徴とする、大断面地中構造物の構築方法。
A preceding tunnel construction process in which a plurality of preceding tunnels are arranged in parallel at intervals;
A preceding tunnel arrangement step of arranging a preceding reinforcing bar in each preceding tunnel;
A preceding tunnel filling step of filling the preceding filled concrete in each preceding tunnel;
A subsequent tunnel construction process for constructing a subsequent tunnel between the adjacent preceding tunnels;
A subsequent tunnel arrangement step of arranging a subsequent reinforcement in the subsequent tunnel;
A subsequent tunnel filling step of filling the subsequent tunnel with the filling intermediate concrete;
Excavation step of excavating a region surrounded by a plurality of preceding tunnels and a plurality of succeeding tunnels, and a construction method of a large cross-section underground structure comprising:
In the subsequent tunnel construction step, a part of a cross section of the adjacent preceding tunnel and a part of the preceding filling concrete are cut and a recess is formed in the preceding filling concrete, and an outer surface of the subsequent tunnel is the Construct the following tunnel so as to contact the preceding filling concrete,
In the succeeding tunnel reinforcement step, by connecting the succeeding reinforcing bar to an end portion of the preceding reinforcing bar exposed in the concave portion, main reinforcing bars penetrating the plurality of preceding tunnels and the plurality of succeeding tunnels are provided. A construction method of a large section underground structure characterized by arranging bars.
前記先行鉄筋の端部に間詰材を設置した状態で前記先行中詰コンクリートを充填することを特徴とする、請求項1に記載の大断面地中構造物の構築方法。   The method for constructing a large-section underground structure according to claim 1, wherein the preceding filling concrete is filled in a state in which a filling material is installed at an end portion of the preceding reinforcing bar. 前記後行トンネル施工工程後に、前記先行トンネルおよび前記後行トンネルの集合体の外周側地山および内周側地山に対して止水対策工を施す止水工程を備えていることを特徴とする、請求項1または請求項2に記載の大断面地中構造物の構築方法。   It is characterized by comprising a water stop process for applying a water stop countermeasure to the outer and inner peripheral grounds of the assembly of the preceding tunnel and the subsequent tunnel after the subsequent tunnel construction process. The construction method of the large cross-section underground structure according to claim 1 or 2.
JP2017015016A 2017-01-31 2017-01-31 Construction method of large section underground structure Active JP6257814B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017015016A JP6257814B1 (en) 2017-01-31 2017-01-31 Construction method of large section underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017015016A JP6257814B1 (en) 2017-01-31 2017-01-31 Construction method of large section underground structure

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2016208918A Division JP6127193B1 (en) 2016-10-25 2016-10-25 Construction method of large section underground structure

Publications (2)

Publication Number Publication Date
JP6257814B1 true JP6257814B1 (en) 2018-01-10
JP2018013024A JP2018013024A (en) 2018-01-25

Family

ID=60940230

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017015016A Active JP6257814B1 (en) 2017-01-31 2017-01-31 Construction method of large section underground structure

Country Status (1)

Country Link
JP (1) JP6257814B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958323A (en) * 2021-10-13 2022-01-21 中建三局第一建设工程有限责任公司 Large-section tunnel construction method and supporting structure
CN114135299A (en) * 2021-12-06 2022-03-04 中建三局第一建设工程有限责任公司 Combined tunnel construction method and supporting structure

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6756892B1 (en) * 2019-11-13 2020-09-16 鹿島建設株式会社 Underground skeleton and how to build an underground skeleton

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61122320A (en) * 1984-11-15 1986-06-10 Penta Ocean Constr Co Ltd Method of coupling continuous underground wall with underground structure
JP2869877B2 (en) * 1991-07-04 1999-03-10 清水建設株式会社 Tunnel merging method and branching method
JP4687986B2 (en) * 2006-10-03 2011-05-25 清水建設株式会社 Construction method of large section tunnel
JP4912839B2 (en) * 2006-11-15 2012-04-11 大成建設株式会社 Multiple arc-shaped tunnel construction method and tunnel-joint connection structure
JP6252842B2 (en) * 2013-11-29 2017-12-27 清水建設株式会社 Construction method of outer shield tunnel
JP6445341B2 (en) * 2015-02-13 2018-12-26 西松建設株式会社 Construction method of underground cavity

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113958323A (en) * 2021-10-13 2022-01-21 中建三局第一建设工程有限责任公司 Large-section tunnel construction method and supporting structure
CN113958323B (en) * 2021-10-13 2022-10-11 中建三局第一建设工程有限责任公司 Large-section tunnel construction method and supporting structure
WO2023061002A1 (en) * 2021-10-13 2023-04-20 中建三局第一建设工程有限责任公司 Large-section tunnel construction method and supporting structure
CN114135299A (en) * 2021-12-06 2022-03-04 中建三局第一建设工程有限责任公司 Combined tunnel construction method and supporting structure
CN114135299B (en) * 2021-12-06 2024-04-26 中建三局第一建设工程有限责任公司 Combined tunnel construction method and supporting structure

Also Published As

Publication number Publication date
JP2018013024A (en) 2018-01-25

Similar Documents

Publication Publication Date Title
JP6171052B2 (en) Construction method of underground widening part
JP4687986B2 (en) Construction method of large section tunnel
JP6252842B2 (en) Construction method of outer shield tunnel
JP6127193B1 (en) Construction method of large section underground structure
JP6257814B1 (en) Construction method of large section underground structure
JP6147818B2 (en) Large section tunnel construction method and large section lining body
JP2017172280A (en) Body lining wall and construction method thereof
JP6062098B1 (en) Construction method of large section underground structure
JP2019143376A (en) Underground structure and construction method of underground structure
JP5498295B2 (en) Construction method for underground structures
JP6636774B2 (en) Integrated structure of pipe roof material
JP6624441B2 (en) Construction method of the wall
JP7021419B2 (en) Construction method of underground widening part
JP3777549B2 (en) Synthetic underground wall, its construction method, and water expansion waterproofing material
JP6019690B2 (en) Tunnel widening method
JP6935640B2 (en) Construction method of underground widening part
JP6638907B2 (en) Waterproof structure and waterstop method
JP3900683B2 (en) Construction method of branch / merge part of main line tunnel and rampway
JP6092359B1 (en) Large section lining body and large section tunnel construction method
JP2849605B2 (en) Large section tunnel and its construction method
JP3900686B2 (en) Underground structure and its construction method
JPH0462299A (en) Larger section tunnel and construction method thereof
JP5715542B2 (en) Tunnel connection method and connection ring
JPH09328987A (en) Tunnel and its construction method
JP2020204187A (en) Outer shell shield wall and manufacturing method thereof

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20170131

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20171128

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171205

R150 Certificate of patent or registration of utility model

Ref document number: 6257814

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250