JP5959045B2 - Pavement location and repaving method for pavement location - Google Patents

Pavement location and repaving method for pavement location Download PDF

Info

Publication number
JP5959045B2
JP5959045B2 JP2012049309A JP2012049309A JP5959045B2 JP 5959045 B2 JP5959045 B2 JP 5959045B2 JP 2012049309 A JP2012049309 A JP 2012049309A JP 2012049309 A JP2012049309 A JP 2012049309A JP 5959045 B2 JP5959045 B2 JP 5959045B2
Authority
JP
Japan
Prior art keywords
pavement
asphalt
pavement layer
layer
additive
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2012049309A
Other languages
Japanese (ja)
Other versions
JP2013185318A (en
Inventor
慶文 荒尾
慶文 荒尾
長谷川 淳也
淳也 長谷川
橋本 賢治
賢治 橋本
川村 修
修 川村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Road Co Ltd
Original Assignee
Nippon Road Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nippon Road Co Ltd filed Critical Nippon Road Co Ltd
Priority to JP2012049309A priority Critical patent/JP5959045B2/en
Publication of JP2013185318A publication Critical patent/JP2013185318A/en
Application granted granted Critical
Publication of JP5959045B2 publication Critical patent/JP5959045B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Description

本発明は、舗装箇所および舗装箇所の再舗装方法に係り、特に、除染を必要とする箇所に用いられるものに関する。   The present invention relates to a pavement location and a re-paving method of the pavement location, and particularly relates to a method used for a location requiring decontamination.

従来の舗装道路201は、図5で示すように、路床203の上に路盤205を設け、路盤205の上に舗装(舗装層)207を設けてある。なお、路床203の下は、図示しない路体になっている。   As shown in FIG. 5, the conventional paved road 201 is provided with a roadbed 205 on the roadbed 203 and a pavement (paved layer) 207 on the roadbed 205. Note that a road body (not shown) is provided under the road bed 203.

路体は、たとえば、土で構成されており、路床203は、たとえば、砂で構成されており、路盤205は、たとえば、砕石で構成されており、舗装層207は、たとえば、アスファルト混合物で構成されている。   The road body is made of, for example, soil, the road bed 203 is made of, for example, sand, the roadbed 205 is made of, for example, crushed stone, and the pavement layer 207 is made of, for example, an asphalt mixture. It is configured.

アスファルト混合物は、骨材(たとえば砂や砂利)とアスファルト(ストレートアスファルト)とフィラー等の混合物で構成されている。フィラーは、骨材の空隙に充填されるものであり、フィラーとして、たとえば、石灰石粉が採用されている。   The asphalt mixture is composed of a mixture of aggregate (for example, sand or gravel), asphalt (straight asphalt) and filler. The filler is filled in the voids of the aggregate, and for example, limestone powder is adopted as the filler.

路盤205の厚さは、20cm〜50cm程度になっており、舗装層207の厚さは、たとえば、3cm〜10cm程度になっている。路体、路床203、路盤205、舗装層207は、転圧等によって締め固められている。   The thickness of the roadbed 205 is about 20 cm to 50 cm, and the thickness of the pavement layer 207 is about 3 cm to 10 cm, for example. The road body, the road bed 203, the road bed 205, and the pavement layer 207 are compacted by rolling or the like.

また、路盤205が下層路盤と上層路盤とに別れており、舗装層207が、基層と表層とに分かれている場合もある。   Further, the roadbed 205 may be divided into a lower layer roadbed and an upper layer roadbed, and the pavement layer 207 may be divided into a base layer and a surface layer.

なお、従来の舗装を示している文献として、たとえば特許文献1を掲げることができる。   For example, Patent Document 1 can be cited as a document showing conventional pavement.

特開2008−156944号公報JP 2008-156944 A

ところで、原子炉で重大な事故が発生しセシウム137等の放射性物質が撒き散らされると、この撒き散らされた放射性物質が舗装道路201の表面に付着、さらには、吸着されてしまう。図5の参照符号209は、放射性物質が付着した舗装道路201の表面を示している。なお、本願の各図面では、図を見やすくするために、ハッチングを省略してある。   By the way, when a serious accident occurs in the nuclear reactor and radioactive materials such as cesium 137 are scattered, the scattered radioactive materials are attached to the surface of the paved road 201 and further adsorbed. Reference numeral 209 in FIG. 5 indicates the surface of the paved road 201 to which a radioactive substance is attached. In each drawing of the present application, hatching is omitted for easy understanding of the drawing.

半減期が長い(たとえば、30年)放射性物質が舗装道路201に付着した状態を放置しておくと、場合によっては、100年間もしくはそれ以上の間、舗装道路201の使用が不可能になってしまう。そこで、放射性物質が付着した舗装道路を除染する必要が生じてくる。   If the radioactive material with a long half-life (for example, 30 years) is left on the paved road 201, it may become impossible to use the paved road 201 for 100 years or longer. End up. Therefore, it becomes necessary to decontaminate the paved road to which radioactive substances are attached.

上記除染の方法として、舗装道路201の表面を洗浄することが考えられる。しかし、放射性物質が吸着等していると、洗浄だけで放射線量を許容値以下にすることは難しい。   As the decontamination method, it is conceivable to clean the surface of the paved road 201. However, if the radioactive substance is adsorbed or the like, it is difficult to make the radiation dose below the allowable value only by cleaning.

そこで、舗装をやり直すことが考えられる。すなわち、舗装層207を撤去し、この後、別の新しい舗装層を設けることが考えられる。   Therefore, it is conceivable to redo the pavement. That is, it is conceivable to remove the pavement layer 207 and then provide another new pavement layer.

しかしながら、舗装層207を撤去するとなると、撤去する部分の体積が大きく、多くの工数がかかってしまう。また、撤去する舗装層207の体積も大きいので、放射性物質を含んだ廃材(舗装層207)の保管にも大きな施設を有する。   However, if the pavement layer 207 is to be removed, the volume of the part to be removed is large, which requires a lot of man-hours. In addition, since the volume of the pavement layer 207 to be removed is large, it has a large facility for storing waste materials (pavement layer 207) containing radioactive substances.

すなわち、舗装層207を除去する方法では、放射性物質を除去することはできるが、工事に多くの工数がかかるとともに、工事により発生した廃材(放射性物質を含んだ廃材)の保管にも広い保管場所が必要になってしまうという問題がある。   In other words, the method of removing the pavement layer 207 can remove radioactive substances, but it takes a lot of man-hours for construction and also has a large storage place for storing waste materials (waste materials containing radioactive substances) generated by the construction. There is a problem that becomes necessary.

なお、上記問題は、道路以外の箇所について同様の工事をする場合にも発生する問題である。   In addition, the said problem is a problem which generate | occur | produces also when performing the same construction about parts other than a road.

本発明は、上記問題点に鑑みてなされたものであり、舗装箇所における放射線の発生を確実に無くすことができ、工事の工数を削減し、工事によって発生した廃材の量を極力少なくすることができる舗装箇所および舗装箇所の再舗装方法を提供することを目的とする。   The present invention has been made in view of the above problems, and can reliably eliminate the generation of radiation at the pavement, reduce the number of man-hours for construction, and reduce the amount of waste materials generated by construction as much as possible. An object of the present invention is to provide a pavement and a method for re-paving the pavement.

請求項1に記載の発明は、舗装層を除染するために、前記舗装層の表面を、洗浄剤を用いて洗浄し、前記舗装層の表面を洗浄した洗浄剤を回収槽に回収する洗浄工程と、前記舗装層を除染するために、前記洗浄工程の前または後に前記舗装層を所定の厚さ除去し、除去した舗装層を回収ボックスに回収する除去工程と、前記洗浄工程と前記除去工程との後、前記舗装層の上に新舗装層を設ける舗装工程とを有する舗装箇所の再舗装方法である。 In the first aspect of the present invention, in order to decontaminate the pavement layer, the surface of the pavement layer is cleaned using a cleaning agent, and the cleaning agent that has cleaned the surface of the pavement layer is recovered in a recovery tank. Removing a predetermined thickness of the pavement layer before or after the cleaning step, and collecting the removed pavement layer in a recovery box, in order to decontaminate the pavement layer, the cleaning step , It is the repaving method of the pavement location which has a pavement process which provides a new pavement layer on the said pavement layer after a removal process .

請求項に記載の発明は、請求項1に記載の舗装箇所の再舗装方法において、前記舗装工程は、アスファルト用添加物を含んだアスファルト舗装をする工程であり、前記アスファルト用添加物は、ストレートアスファルトに対して親和性を有する添加材と、疎水化処理された短繊維からなる綿状の繊維物とを含み、前記繊維物に前記添加材を含浸させて含浸混合物となし、該含浸混合物を合成樹脂製の包装袋内に収容し、該包装袋を加熱下の前記ストレートアスファルトに投入して用いるものである舗装箇所の再舗装方法である。 Invention of Claim 2 is the repaving method of the pavement location of Claim 1 , The said pavement process is a process of asphalt pavement containing the additive for asphalt, The said additive for asphalt is An additive having an affinity for straight asphalt and a cotton-like fiber product made of hydrophobized short fibers, and the fiber material is impregnated with the additive to form an impregnated mixture, the impregnated mixture Is placed in a synthetic resin packaging bag, and the packaging bag is put into the heated straight asphalt for repaving.

請求項に記載の発明は、請求項1に記載の舗装箇所の再舗装方法において、前記舗装工程は、アスファルト混合物を用いて新舗装層を設ける工程であり、前記アスファルト混合物は、アスファルト用添加材と、ストレートアスファルトと、骨材とを含み、前記骨材100重量部に対して前記ストレートアスファルトを6.5〜8.5重量部、前記アスファルト用添加材を0.2〜0.6重量部含有し、前記アスファルト用添加材は、該アスファルト用添加材の全重量に対してナフテン系オイルを44〜64重量%、スチレン系熱可塑性エラストマーを22〜42重量%、ポリプロピレンを4〜24重量%含有し、前記骨材の表面は前記ストレートアスファルトの層で覆われ、かつ、そのストレートアスファルトの層が更に前記アスファルト用添加材の層で覆われる2層構造を有する舗装箇所の再舗装方法である。 The invention according to claim 3, in resurfacing method of paving portion of claim 1, wherein the paving step is a step of providing a new pavement layer using asphalt mixture, wherein the asphalt mixture, adding asphalt Material, straight asphalt, and aggregate, and 6.5 to 8.5 parts by weight of the straight asphalt and 0.2 to 0.6 parts by weight of the additive for asphalt with respect to 100 parts by weight of the aggregate. The asphalt additive contains 44 to 64% by weight of naphthenic oil, 22 to 42% by weight of styrene thermoplastic elastomer, and 4 to 24% by weight of polypropylene based on the total weight of the asphalt additive. And the aggregate surface is covered with the straight asphalt layer, and the straight asphalt layer further comprises the asphalt. Is resurfaced method pavement portion having a two-layer structure is covered with a layer of additional material.

請求項に記載の発明は、路体を覆っている路床と、前記路床を覆っている路盤と、前記路盤を覆っている舗装層と、前記舗装層、前記路盤および前記路床を掘り起こして前記路床の高さまで埋め戻された部分路床と、前記路盤の高さまで埋め戻されて前記部分路床を覆っている部分路盤と、前記部分路盤を覆っている部分舗装層と、除染のために上面が切削されている前記舗装層と除染のために上面が切削されている前記部分舗装層を覆っている所定の厚さの新舗装層とを有する舗装箇所である。 The invention according to claim 4 includes a road bed covering a road body, a road bed covering the road bed, a pavement layer covering the road bed, the pavement layer, the road bed, and the road bed. A partial roadbed that has been dug up and backfilled to the height of the roadbed; a partial roadbed that is backfilled to the height of the roadbed and covers the partial roadbed; and a partial pavement layer that covers the partial roadbed; is paved parts having a new pavement layer having a predetermined thickness, which upper surface for decontamination upper surface for decontamination and the pavement layer being cut covers and the portion pavement layer being cut .

本発明によれば、舗装箇所における放射線の発生を確実に無くすことができ、工事の工数を削減し、工事によって発生した廃材の量を極力少なくすることができるという効果を奏する。   ADVANTAGE OF THE INVENTION According to this invention, generation | occurrence | production of the radiation in a pavement place can be eliminated reliably, there exists an effect that the number of construction work can be reduced and the quantity of the waste material generated by construction can be decreased as much as possible.

本発明の実施形態に係る舗装箇所の概略構成を示す断面図である。It is sectional drawing which shows schematic structure of the pavement location which concerns on embodiment of this invention. 本発明の実施形態に係る舗装箇所の再舗装方法における除去工程の概要を示す図である。It is a figure which shows the outline | summary of the removal process in the repaving method of the pavement location which concerns on embodiment of this invention. 本発明の実施形態に係る舗装箇所の再舗装方法における洗浄工程の概要を示す図である。It is a figure which shows the outline | summary of the washing | cleaning process in the repaving method of the pavement location which concerns on embodiment of this invention. 継ぎ目を有する舗装箇所の概略構成を示す断面図であり、(a)は平面図であり、(b)は(a)におけるIVB−IVB断面を示す図である。It is sectional drawing which shows schematic structure of the pavement location which has a joint, (a) is a top view, (b) is a figure which shows the IVB-IVB cross section in (a). 従来の舗装道路の概略構成を示す断面図である。It is sectional drawing which shows schematic structure of the conventional paved road.

図1で示すように、本発明の実施形態に係る舗装箇所(たとえば道路)1には、従来と同様に路体(図示せず)、路床3、路盤5、表層7が形成されている。   As shown in FIG. 1, a pavement (not shown), a roadbed 3, a roadbed 5, and a surface layer 7 are formed in a pavement location (for example, a road) 1 according to an embodiment of the present invention, as in the past. .

すなわち、舗装箇所(再舗装がなされた舗装箇所)1には、路体(図示せず)と、この路体の上で路体を覆っている所定の厚さの路床3と、路床3の上で路床3を覆っている所定の厚さの路盤5と、路盤5の上で路盤5を覆っている所定の厚さの旧舗装層7と、新舗装層9とを備えている。   That is, a pavement location (a re-paved pavement location) 1 includes a road body (not shown), a road bed 3 of a predetermined thickness covering the road body on the road body, and a road bed A roadbed 5 having a predetermined thickness covering the roadbed 3 on the upper surface 3, an old pavement layer 7 having a predetermined thickness covering the roadbed 5 on the roadbed 5, and a new pavement layer 9. Yes.

路体はたとえば土で構成されており、路床3はたとえば砂で構成されており、路盤5はたとえば砕石で構成されており、表層(旧舗装層)7は、アスファルト混合物で構成されている。そして、いずれのものも、転圧等によって締め固められている。   The road body is made of, for example, soil, the road bed 3 is made of, for example, sand, the roadbed 5 is made of, for example, crushed stone, and the surface layer (old pavement layer) 7 is made of an asphalt mixture. . And all of them are compacted by rolling or the like.

旧舗装層7は、上面が切削されている。すなわち、旧舗装層7の上面は、ダイヤモンドカッター等によって切削された切削面になっている(ダイヤモンドカッター等による切削跡が形成されている)。なお、切削面としてショットブラストによって形成された面も含むものとする。   The upper surface of the old pavement layer 7 is cut. That is, the upper surface of the old pavement layer 7 is a cutting surface cut by a diamond cutter or the like (a cutting trace by the diamond cutter or the like is formed). In addition, the surface formed by shot blasting is also included as a cutting surface.

旧舗装層7の上には、所定の厚さの新舗装層9が設けられている。新舗装層9は、旧舗装層7を覆っている。   A new pavement layer 9 having a predetermined thickness is provided on the old pavement layer 7. The new pavement layer 9 covers the old pavement layer 7.

新舗装層9の厚さは、15mm程度の所定の厚さになっているが、この厚さを、旧舗装層7の除去厚さ(詳しくは後述する)に応じて、10mm〜20mmの範囲内で適宜変更してもよいし、また、5mm〜30mmの範囲内で適宜変更してもよい。いずれにしても、旧舗装層7の除去(切削)がなされる前における旧舗装層7の上面高さに対して、新舗装層9の上面の高さが、0mm〜20mm(好ましくは10mm程度)高くなってことが望ましい。   The thickness of the new pavement layer 9 is a predetermined thickness of about 15 mm, and this thickness ranges from 10 mm to 20 mm depending on the removal thickness of the old pavement layer 7 (details will be described later). May be changed as appropriate within the range of 5 mm to 30 mm. In any case, the height of the upper surface of the new pavement layer 9 is 0 mm to 20 mm (preferably about 10 mm) with respect to the height of the upper surface of the old pavement layer 7 before the removal (cutting) of the old pavement layer 7 is performed. ) It is desirable to be higher.

なお、旧舗装7から下の部分が施工された時期は、旧舗装7の上面(切削面)が形成された時期および新舗装層9が施工された時期よりも、古い時期である。 Incidentally, the timing of the lower part of which is construction from the old pavement layer 7, than timing timing top (cutting surface) is formed and the new pavement layer 9 of the old pavement layer 7 is construction, the old time.

また、舗装箇所1として、通学路等の道路(歩道を含む)、公園等の公共施設の敷地等を掲げることができる。   In addition, as the pavement location 1, roads such as school roads (including sidewalks), public facilities such as parks, and the like can be listed.

旧舗装層7は、アスファルト(アスファルト合材;アスファルト混合物)の層で構成されているが、必ずしもアスファルトの層である必要はなく、コンクリートの層、ブロックの層等、他の層で構成されていてもよい。 Old pavement layer 7, asphalt; are constituted by a layer of (asphalt mixture asphalt mixture), not necessarily a layer of asphalt, a layer of concrete, the layer of blocks and the like, consists of other layers It may be.

次に、道路1の再舗装の施工方法(舗装箇所の再舗装方法)について説明する。   Next, a method for re-paving the road 1 (a method for re-paving a pavement portion) will be described.

まず、初期状態として、図5に示すような舗装道路201であって表面に放射性物質が付着等しているものがあるものとする。   First, as an initial state, it is assumed that there is a paved road 201 as shown in FIG.

この道路201に対して、図2で示すように、舗装層(旧舗装層)207の除去を行う。すなわち、舗装層207を所定の厚さ、平削り(ミーリング法)により除去する(除去工程)。これにより、上面が切削面になっている旧舗装層7が生成される。   As shown in FIG. 2, the pavement layer (old pavement layer) 207 is removed from the road 201. That is, the pavement layer 207 is removed by a predetermined thickness and planing (milling method) (removal step). Thereby, the old pavement layer 7 whose upper surface is a cutting surface is generated.

除去工程での除去は、セシウム137等の放射性物質が付着もしくは吸着等している舗装層207の上側部分を除去するために行うものである。この除去によって、舗装層207がこの表面から所定の厚さ除去される。具体的には、工事車両(図示せず)を導入して、ダイヤモンドカッター11を用いたドライ切削により舗装層207の一部を除去する。   The removal in the removal step is performed to remove the upper portion of the pavement layer 207 to which a radioactive substance such as cesium 137 is attached or adsorbed. By this removal, the pavement layer 207 is removed from the surface by a predetermined thickness. Specifically, a construction vehicle (not shown) is introduced, and a part of the pavement layer 207 is removed by dry cutting using the diamond cutter 11.

除去の厚さは、0.5mm〜10mmであるが、より好ましくは1mm〜5mm、さらに好ましくは1mm〜2mmまたは2mm〜4mmとする。舗装層207の表面が波打っている場合は、一番薄いところで、上記厚さになるような除去をする。なお、通常の舗装路の改修等では、3cm〜10cmの厚さで舗装層207の総てを除去するが、除去工程では、除去厚さが薄いのである。   The thickness of removal is 0.5 mm to 10 mm, more preferably 1 mm to 5 mm, and still more preferably 1 mm to 2 mm or 2 mm to 4 mm. When the surface of the pavement layer 207 is wavy, the removal is performed so that the thickness becomes the thinnest. Note that in the normal renovation of a pavement, etc., all of the pavement layer 207 is removed with a thickness of 3 cm to 10 cm. However, in the removal process, the removal thickness is thin.

切削により生じた切削屑は、放射性物質を含んでいるので、ダクト13で吸引する(すなわち、同時吸引式平削りする)。そして、切削屑を回収し回収ボックス内に溜め、放射性物質の飛散を防ぐ。   Since the cutting waste generated by cutting contains a radioactive substance, it is sucked by the duct 13 (that is, the simultaneous suction type planing). And cutting waste is collect | recovered and collected in a collection box, and scattering of a radioactive substance is prevented.

また、既に理解されるように、除去工程での舗装層207の除去は、舗装層207の総てを取り除くのではなく、除去後でも所定の厚さだけ舗装層207が残っている。この残った舗装層が旧舗装層7になる。なお、旧舗装層7の上面はほぼ平坦になっている。   Further, as already understood, the removal of the pavement layer 207 in the removal step does not remove all of the pavement layer 207, but the pavement layer 207 remains by a predetermined thickness even after the removal. This remaining pavement layer becomes the old pavement layer 7. Note that the upper surface of the old pavement layer 7 is substantially flat.

なお、上記除去工程での除去を、ショットブラストで行ってもよい。ショットブラストの投射材(粒体)は、たとえば球状の鋼で構成されており、磁石にくっつくようになっている。したがって、ショットブラストの投射材と、ショットブラストによって除去された舗装層207の除去屑(廃材)とを、磁石を用いて分離することができる。分離された除去屑は、回収されて回収ボックス内に溜められ、分離された投射材は再び使用される。また、ある程度の時間使用された投射材は洗浄されて再使用される。   Note that the removal in the removal step may be performed by shot blasting. The shot blasting material (particles) is made of, for example, spherical steel, and is attached to a magnet. Therefore, it is possible to separate the shot blasting projection material and the removal waste (waste material) of the pavement layer 207 removed by the shot blasting using a magnet. The separated removal waste is collected and stored in the collection box, and the separated projection material is used again. Further, the projection material that has been used for a certain period of time is washed and reused.

続いて、除去工程での除去の後、図3で示すように、舗装層(旧舗装層)7の表面(上面)を、洗浄剤を用いて洗浄する(洗浄工程)。この洗浄も、付着もしくは吸着等している放射性物質を取り除くためになされるか、もしくは、除去工程でこぼれた廃材(放射性物質を含む廃材)を取り除くためになされるものである。   Subsequently, after the removal in the removal step, as shown in FIG. 3, the surface (upper surface) of the pavement layer (old pavement layer) 7 is washed with a cleaning agent (cleaning step). This cleaning is also performed in order to remove radioactive substances adhering or adsorbing, or in order to remove waste materials spilled in the removal process (waste materials containing radioactive substances).

洗浄工程では、たとえば、ノズル15から噴射した超高圧洗浄水を舗装層7に吹き付けて舗装層7の表面に付着している放射性物質を洗浄し(SJ−V工法で洗浄し)、舗装層7の放射性物質を除染する。また、洗浄に使用され放射性物質を含んでいる洗浄水をダクト17で吸引(強力吸引)することで回収し回収槽に溜める。これにより、放射性物質の飛散を防ぐことができる。   In the cleaning process, for example, the high-pressure cleaning water sprayed from the nozzle 15 is sprayed on the pavement layer 7 to clean the radioactive material adhering to the surface of the pavement layer 7 (cleaning by the SJ-V method), and the pavement layer 7 Decontaminate radioactive materials. Further, the cleaning water used for cleaning and containing the radioactive substance is collected by suction (strong suction) through the duct 17 and collected in the collection tank. Thereby, scattering of a radioactive substance can be prevented.

洗浄は、たとえば、工事車両(洗浄吸引車)も用いて行われる。これにより、洗浄する箇所の面積にあわせて、機動的な対応が可能になる。たとえば、放射線量を測定しこの結果放射線量が大きい箇所のみ洗浄するようにしてもよい。   Cleaning is performed using, for example, a construction vehicle (cleaning suction vehicle). This makes it possible to respond flexibly in accordance with the area of the location to be cleaned. For example, the radiation dose may be measured, and as a result, only portions where the radiation dose is large may be cleaned.

続いて、洗浄工程で洗浄をした後、舗装層7の表面を覆う新たな舗装(たとえばアスファルト舗装)をして、舗装層7の上に新舗装層(薄層遮蔽舗装)9を設ける(舗装工程)。   Subsequently, after cleaning in the cleaning process, a new pavement (for example, asphalt pavement) covering the surface of the pavement layer 7 is provided, and a new pavement layer (thin layer shielding pavement) 9 is provided on the pavement layer 7 (pavement). Process).

これにより、図1で示すような、道路1が生成される。   Thereby, a road 1 as shown in FIG. 1 is generated.

なお、道路1の再舗装の施工方法において、除去工程と洗浄工程との順序を入れ替えてもよいし、除去工程、洗浄工程のいずれか一方を削除してもよい。   In addition, in the construction method of the repaving of the road 1, the order of a removal process and a washing | cleaning process may be replaced, and any one of a removal process and a washing | cleaning process may be deleted.

ところで、新舗装層9を設ける舗装工程において、特許第4473896号公報に記載のアスファルト用添加物やアスファルト混合物の製造方法を採用してもよい。   By the way, in the pavement process which provides the new pavement layer 9, you may employ | adopt the manufacturing method of the additive for asphalts and an asphalt mixture as described in patent 4473896.

すなわち、舗装工程を、アスファルト用添加物(特殊改質剤)を含んだアスファルト舗装をする(新舗装する)工程としてもよい。   That is, the pavement step may be a step of performing asphalt pavement (additional pavement) including an asphalt additive (special modifier).

なお、アスファルト用添加物は、ストレートアスファルトに対して親和性を有する添加材と、疎水化処理された短繊維からなる綿状の繊維物とを含み、前記繊維物に前記添加材を含浸させて含浸混合物となし、該含浸混合物を合成樹脂製の包装袋内に収容し、該包装袋を加熱下の前記ストレートアスファルトに投入して用いるものである。   The asphalt additive includes an additive having an affinity for straight asphalt and a cotton-like fiber made of short fibers subjected to hydrophobic treatment, and the fiber is impregnated with the additive. The impregnation mixture is used, and the impregnation mixture is accommodated in a synthetic resin packaging bag, and the packaging bag is put into the heated straight asphalt for use.

ここで、前記包装袋の厚みを、0.03〜0.06mmとなすことが望ましい。また、前記短繊維を、植物繊維からなるものとすることが望ましい。また、添加材を、該添加材の全重量に対してナフテン系オイルを40〜70重量部、スチレン系熱可塑性エラストマーを20〜45重量部、ポリプロピレンを2〜30重量部含有するようにすることが望ましい。さらに、前記舗装工程は、アスファルト混合物を用いてアスファルト舗装をする工程である。アスファルト混合物は、骨材と、ストレートアスファルトとが混合されたものであり、前記骨材と、前記ストレートアスファルトとを150〜180℃で混合した後に、前記アスファルト用添加物を添加し、さらに5〜60秒混合することで製造されたものである。   Here, it is desirable that the thickness of the packaging bag is 0.03 to 0.06 mm. Moreover, it is desirable that the short fibers are made of plant fibers. Further, the additive contains 40 to 70 parts by weight of naphthenic oil, 20 to 45 parts by weight of styrene thermoplastic elastomer, and 2 to 30 parts by weight of polypropylene with respect to the total weight of the additive. Is desirable. Further, the paving step is a step of paving asphalt using an asphalt mixture. The asphalt mixture is a mixture of aggregate and straight asphalt. After the aggregate and the straight asphalt are mixed at 150 to 180 ° C., the asphalt additive is added, and It was manufactured by mixing for 60 seconds.

また、新舗装層の耐クラック性を高めることができるのであれば、特殊改質剤として、上述した構成のもの以外のものを使用してもよい。   In addition, as long as the crack resistance of the new pavement layer can be improved, a special modifier other than the one described above may be used.

たとえば、新舗装層9を設ける舗装工程において、特許第3685497号公報に記載のアスファルト混合物を採用してもよい(アスファルト混合物により新舗装をしてもよい)。   For example, in the pavement process of providing the new pavement layer 9, an asphalt mixture described in Japanese Patent No. 3685497 may be adopted (new pavement may be performed with the asphalt mixture).

このアスファルト混合物は、アスファルト用添加材と、ストレートアスファルトと、骨材とを含み、前記骨材100重量部に対して前記ストレートアスファルトを6.5〜8.5重量部、前記アスファルト用添加材を0.2〜0.6重量部含有し、前記アスファルト用添加材は、該アスファルト用添加材の全重量に対してナフテン系オイルを44〜64重量%、スチレン系熱可塑性エラストマーを22〜42重量%、ポリプロピレンを4〜24重量%含有し、前記骨材の表面は前記ストレートアスファルトの層で覆われ、かつ、そのストレートアスファルトの層が更に前記アスファルト用添加材の層で覆われる2層構造を有している。   The asphalt mixture includes an asphalt additive, straight asphalt, and aggregate, and 6.5 to 8.5 parts by weight of the straight asphalt with respect to 100 parts by weight of the aggregate, and the asphalt additive. 0.2 to 0.6 parts by weight, and the asphalt additive is 44 to 64% by weight of naphthenic oil and 22 to 42% by weight of styrene thermoplastic elastomer with respect to the total weight of the asphalt additive. 2 to 4% by weight, and the aggregate surface is covered with the straight asphalt layer, and the straight asphalt layer is further covered with the asphalt additive layer. Have.

また、上記アスファルト混合物において、前記骨材が砕石、スクリーニングス、粗砂、石粉からなり、前記骨材の全重量に対する組成が、前記砕石22〜42重量%、前記スクリーニングス18〜38重量%、前記粗砂24〜44重量%、前記石粉2〜10重量%、になっていることが望ましい。   Further, in the asphalt mixture, the aggregate is made of crushed stone, screenings, coarse sand, stone powder, and the composition with respect to the total weight of the aggregate is 22 to 42% by weight of the crushed stone, 18 to 38% by weight of the screenings, The coarse sand is preferably 24 to 44% by weight and the stone powder is 2 to 10% by weight.

道路の再舗装方法によれば、舗装層7の表面を洗浄し、この後、舗装層7の上に新舗装層9を設けるので、すなわち、多段階式除染工法を組み合わせているので、道路1における放射線の発生を確実に無くすことができ、工事の工数を削減し、工事によって発生した廃材の量を極力少なくすることができる。 According to the re-paving method of the road 1 , since the surface of the pavement layer 7 is washed, and then a new pavement layer 9 is provided on the pavement layer 7, that is, a multistage decontamination method is combined. The generation of radiation on the road 1 can be reliably eliminated, the number of construction steps can be reduced, and the amount of waste materials generated by the construction can be reduced as much as possible.

また、道路の再舗装方法によれば、舗装層7を洗浄する前に、舗装層7を所定の厚さ除去するので、放射性物質の量が比較的多い場合や、洗浄だけでは放射性物質が多く残ってしまう場合や、放射性物質が所定の深さまで舗装層の内部に浸透している場合であっても、道路1に付着等している放射性物質を確実に除去し放射線を無くすことができる。 Moreover, according to the re-paving method of the road 1 , the pavement layer 7 is removed to a predetermined thickness before the pavement layer 7 is washed. Even when a large amount of radioactive material remains or when the radioactive material has penetrated into the pavement layer 7 to a predetermined depth, the radioactive material adhering to the road 1 can be reliably removed and radiation can be eliminated. it can.

また、除去する舗装層207の厚さが薄いので、放射性物質を含んだ廃材の発生量を少なくすることができる。   Further, since the thickness of the pavement layer 207 to be removed is thin, the amount of waste materials containing radioactive substances can be reduced.

さらに、道路の再舗装方法において、洗浄工程もしくは除去工程を無くせば、道路の再舗装方法の工程が簡素化され、放射性物質を含んだ洗浄水もしくは舗装層の切削屑が生成されないので、放射性物質を含んだ廃材が減少する。 Furthermore, in the re-paving method of the road 1 , if the cleaning step or the removing step is eliminated, the re-paving method step of the road 1 is simplified, and the cleaning water containing the radioactive material or the cutting waste of the pavement layer is not generated. Waste materials containing radioactive materials are reduced.

また、道路の再舗装方法によれば、アスファルト用添加物が、ストレートアスファルトに対して親和性を有する添加材と、疎水化処理された短繊維からなる綿状の繊維物とを含み、繊維物に添加材を含浸させて含浸混合物となし、該含浸混合物を合成樹脂製の包装袋内に収容し、該包装袋を加熱下のストレートアスファルトに投入して用いているので、含浸混合物は繊維間での滑りがよく塊になり難く分散性が良好であるため、繊維物の濃度が均一となり、新舗装層での、耐流動性、耐摩耗性及び耐クラック性の向上を図ることができる。 Further, according to the road 1 re-paving method, the asphalt additive includes an additive having an affinity for straight asphalt and a cotton-like fiber material made of hydrophobically treated short fibers. Since the impregnated mixture is impregnated with an additive to form an impregnated mixture, the impregnated mixture is contained in a synthetic resin packaging bag, and the packaging bag is put into a heated straight asphalt and used. Since the inter-slip is difficult to agglomerate and dispersibility is good, the concentration of the fibrous material becomes uniform, and the flow resistance, wear resistance and crack resistance of the new pavement layer can be improved. .

新舗装層にクラックが生じ難くなることで(新舗装層はクラック抑制型舗装なので)、旧舗装層に放射性物質がごく僅かに残っていても、この放射性物質が発する放射線が新舗装層によって遮られ、舗装箇所の表面に出てくることがほぼ無くなる。また、舗装箇所(道路)1の耐久性も向上する。   The new pavement layer is less prone to cracking (since the new pavement layer is a crack-inhibited pavement), so even if very little radioactive material remains in the old pavement layer, the radiation generated by this radioactive material is blocked by the new pavement layer. Almost never appears on the surface of the pavement. Moreover, the durability of the pavement location (road) 1 is also improved.

さらに、道路1の再舗装方法によれば、特殊な機械を必要とせず、従来の機械(工事車両)だけを用いて、工事をすることができ、また、新舗装層9が薄く施工後に早く固まるので、早期に交通を開通することができる。   Furthermore, according to the re-paving method of the road 1, it is possible to perform construction using only a conventional machine (construction vehicle) without requiring a special machine, and the new pavement layer 9 is thin and quickly after construction. Because it sets, traffic can be opened early.

また、道路1の再舗装方法によれば、舗装層207を所定の厚さ除去し、この除去後に新舗装層9を設けるので、旧舗装層7の除去がなされる前における舗装層207の上面高さに対して、新舗装層9の上面の高さが、僅かに高くなるだけである。したがって、道路1の構造物(ガードレール等)の段差修正工事が不要になる。   Further, according to the re-paving method of the road 1, the pavement layer 207 is removed to a predetermined thickness, and the new pavement layer 9 is provided after the removal, so that the upper surface of the pavement layer 207 before the old pavement layer 7 is removed. The height of the upper surface of the new pavement layer 9 is only slightly higher than the height. Therefore, the step correction work for the structure of the road 1 (guardrail, etc.) becomes unnecessary.

ところで、道路1において、図4で示すように、継ぎ目19が形成されている場合がある。   By the way, as shown in FIG. 4, a seam 19 may be formed on the road 1.

継ぎ目19は、旧舗装層7にのみ形成されており、新舗装層9には、継ぎ目が形成されていない。したがって、旧舗装層7の継ぎ目は、新舗装層9によって隠れている。   The seam 19 is formed only on the old pavement layer 7, and no seam is formed on the new pavement layer 9. Therefore, the joint of the old pavement layer 7 is hidden by the new pavement layer 9.

継ぎ目19は、たとえば、道路の下に埋設されている下水道管の補修のために、旧舗装7がなされていた道路一部を掘り、この後、掘った孔を埋めて再舗装したことによって生成されたものである。   The seam 19 is generated by, for example, excavating a part of the road where the old pavement 7 was made for repairing a sewer pipe buried under the road, and then re-paving by filling the hole dug. It has been done.

したがって、舗装層7は、第1の部位(当初の古い舗装層)7Aと第2の部位(掘り返しによる新しい舗装層)7Bとを備えており、第1の部位7Aと第2の部位7Bとの間に継ぎ目19が形成されている。さらに。路床3や路盤5にも継ぎ目が形成されているが、これは、舗装層7ものよりも、おそらく目立たないであろう。 Therefore, the pavement layer 7 includes a first part (original old pavement layer) 7A and a second part (new pavement layer by dug-up) 7B, and the first part 7A and the second part 7B A seam 19 is formed between the two. further. Although seams in road bed 3 or roadbed 5 is formed, which, than that of the pavement layer 7, would not likely noticeable.

また、道路1の側溝(図示せず)内に堆積した放射性物質を含む堆積物(泥土等)は、図で示す場合と同様にして、洗浄水を使った超高圧洗浄と、強力吸引とによって取り除かれる。 Moreover, deposits containing radioactive material deposited in the groove of the road 1 (not shown) (mud, etc.), as in the case shown in FIG. 3, and ultra-high-pressure cleaning using wash water, and a strong suction Removed by.

また、図では、洗浄工程で使用された洗浄水をただちに吸引することにしているが、この吸引で吸引されずに道路の側溝に流れた洗浄水も、超高圧洗浄と、強力吸引とによって取り除かれる。 Further, in FIG. 3 , the cleaning water used in the cleaning process is immediately sucked, but the cleaning water that has not been sucked by this suction and has flowed into the side groove of the road is also cleaned by ultra-high pressure cleaning and strong suction. Removed.

さらに、洗浄工程で使用された洗浄水をただちに吸引することを止めて、洗浄工程で使用された洗浄水を側溝に流し、この流れたものを、高圧洗浄と、強力吸引とによって取り除くようにしてもよい。   In addition, stop the suction of the cleaning water used in the cleaning process immediately, let the cleaning water used in the cleaning process flow into the side groove, and remove this flow by high pressure cleaning and strong suction. Also good.

1 道路(舗装箇所)
7 舗装層(旧舗装層)
9 新舗装層
207 舗装層(旧舗装層)
1 road (paved area)
7 pavement layer (old pavement layer)
9 New pavement layer 207 Pavement layer (old pavement layer)

Claims (4)

舗装層を除染するために、前記舗装層の表面を、洗浄剤を用いて洗浄し、前記舗装層の表面を洗浄した洗浄剤を回収槽に回収する洗浄工程と、
前記舗装層を除染するために、前記洗浄工程の前または後に前記舗装層を所定の厚さ除去し、除去した舗装層を回収ボックスに回収する除去工程と、
前記洗浄工程と前記除去工程との後、前記舗装層の上に新舗装層を設ける舗装工程と、
を有することを特徴とする舗装箇所の再舗装方法。
In order to decontaminate the pavement layer, a cleaning step of cleaning the surface of the pavement layer using a cleaning agent, and collecting the cleaning agent that cleaned the surface of the pavement layer in a recovery tank ;
In order to decontaminate the pavement layer, a removal step of removing the pavement layer by a predetermined thickness before or after the cleaning step, and collecting the removed pavement layer in a collection box;
After the washing step and the removing step, a pavement step of providing a new pavement layer on the pavement layer;
A method for re-paving a pavement, characterized by comprising:
請求項1に記載の舗装箇所の再舗装方法において、
前記舗装工程は、アスファルト用添加物を含んだアスファルト舗装をする工程であり、
前記アスファルト用添加物は、ストレートアスファルトに対して親和性を有する添加材と、疎水化処理された短繊維からなる綿状の繊維物とを含み、前記繊維物に前記添加材を含浸させて含浸混合物となし、該含浸混合物を合成樹脂製の包装袋内に収容し、該包装袋を加熱下の前記ストレートアスファルトに投入して用いるものであることを特徴とする舗装箇所の再舗装方法。
In the repaving method of the pavement location according to claim 1,
The paving step is a step of paving asphalt containing an additive for asphalt,
The additive for asphalt includes an additive having an affinity for straight asphalt and a cotton-like fiber made of short fibers subjected to hydrophobic treatment, and the fiber is impregnated with the additive. mixture and without houses the impregnating mixture in plastic packaging bag, resurfacing method of pavement portion, characterized in der Rukoto those used by introducing the straight asphalt under heat the packaging bag.
請求項1に記載の舗装箇所の再舗装方法において、
前記舗装工程は、アスファルト混合物を用いて新舗装層を設ける工程であり、
前記アスファルト混合物は、アスファルト用添加材と、ストレートアスファルトと、骨材とを含み、前記骨材100重量部に対して前記ストレートアスファルトを6.5〜8.5重量部、前記アスファルト用添加材を0.2〜0.6重量部含有し、前記アスファルト用添加材は、該アスファルト用添加材の全重量に対してナフテン系オイルを44〜64重量%、スチレン系熱可塑性エラストマーを22〜42重量%、ポリプロピレンを4〜24重量%含有し、前記骨材の表面は前記ストレートアスファルトの層で覆われ、かつ、そのストレートアスファルトの層が更に前記アスファルト用添加材の層で覆われる2層構造を有することを特徴とする舗装箇所の再舗装方法。
In the repaving method of the pavement location according to claim 1,
The pavement step is a step of providing a new pavement layer using an asphalt mixture,
The asphalt mixture includes an asphalt additive, straight asphalt, and aggregate, and 6.5 to 8.5 parts by weight of the straight asphalt with respect to 100 parts by weight of the aggregate, and the asphalt additive. 0.2 to 0.6 parts by weight, and the asphalt additive is 44 to 64% by weight of naphthenic oil and 22 to 42% by weight of styrene thermoplastic elastomer with respect to the total weight of the asphalt additive. 2 to 4% by weight, and the aggregate surface is covered with the straight asphalt layer, and the straight asphalt layer is further covered with the asphalt additive layer . A pavement re-paving method characterized by comprising:
路体を覆っている路床と、
前記路床を覆っている路盤と、
前記路盤を覆っている舗装層と、
前記舗装層、前記路盤および前記路床を掘り起こして前記路床の高さまで埋め戻された部分路床と、
前記路盤の高さまで埋め戻されて前記部分路床を覆っている部分路盤と、
前記部分路盤を覆っている部分舗装層と、
除染のために上面が切削されている前記舗装層と除染のために上面が切削されている前記部分舗装層とを覆っている所定の厚さの新舗装層と、
を有することを特徴とする舗装箇所。
A roadbed covering the road,
A roadbed covering the roadbed;
A pavement layer covering the roadbed;
A partial road bed that has been dug up to the height of the road bed by digging up the pavement layer, the road bed and the road bed;
A partial roadbed that is backfilled to the height of the roadbed and covers the partial roadbed;
A partial pavement layer covering the partial roadbed;
A new pavement layer of a predetermined thickness covering the pavement layer whose upper surface is cut for decontamination and the partial pavement layer whose upper surface is cut for decontamination;
Paving箇plants that characterized the Rukoto to have a.
JP2012049309A 2012-03-06 2012-03-06 Pavement location and repaving method for pavement location Active JP5959045B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012049309A JP5959045B2 (en) 2012-03-06 2012-03-06 Pavement location and repaving method for pavement location

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012049309A JP5959045B2 (en) 2012-03-06 2012-03-06 Pavement location and repaving method for pavement location

Publications (2)

Publication Number Publication Date
JP2013185318A JP2013185318A (en) 2013-09-19
JP5959045B2 true JP5959045B2 (en) 2016-08-02

Family

ID=49386993

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012049309A Active JP5959045B2 (en) 2012-03-06 2012-03-06 Pavement location and repaving method for pavement location

Country Status (1)

Country Link
JP (1) JP5959045B2 (en)

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5836681B2 (en) * 1978-06-30 1983-08-11 新神戸電機株式会社 Road surface repair equipment
JPH08184024A (en) * 1994-12-28 1996-07-16 Shimizu Corp Repair execution device for road surface and repair execution method using repair execution device
JP3953596B2 (en) * 1997-09-30 2007-08-08 ニチレキ株式会社 Cracked repair method and repair structure of pavement surface
JP3685497B1 (en) * 2004-06-01 2005-08-17 三野道路株式会社 Asphalt mixture and method for producing the same
JP2007113319A (en) * 2005-10-21 2007-05-10 Ibiken Kk Painted floor remodeling method
JP5308623B2 (en) * 2006-12-25 2013-10-09 日本道路株式会社 Road pavement structure
JP4473896B2 (en) * 2007-07-24 2010-06-02 三野道路株式会社 Asphalt additive and method for producing asphalt mixture
JP2014062735A (en) * 2011-10-25 2014-04-10 Suyama Kiyoshi Decontamination method for buildings, soil, or plants contaminated with radioactive materials
JP2013156208A (en) * 2012-01-31 2013-08-15 Central Research Institute Of Electric Power Industry Decontamination method of radioactive matter from asphalt paved surface
JP5785884B2 (en) * 2012-02-14 2015-09-30 大成ロテック株式会社 Repair method of heat trimming car and existing pavement

Also Published As

Publication number Publication date
JP2013185318A (en) 2013-09-19

Similar Documents

Publication Publication Date Title
JP6335569B2 (en) Ground preparation method and ground structure
BR102012019092B1 (en) Linear drive system from conversion ENVIRONMENTAL RECOVERY PROCESS OF MINING AREAS Circular motion combined with linear motion, EXTINCT OR EXHAUSTED APPLICATION to citrus juice extraction machines and other equipment
Zumrawi The impacts of poor drainage on road performance in Khartoum
CN105507102B (en) A kind of construction method reinforcing road bed with waste or used plastics woven bag
Zumrawi Pavement design for roads on expansive clay subgrades
JP5959045B2 (en) Pavement location and repaving method for pavement location
CN102330401B (en) Joint-expansion-free refilling process for cement concrete road slab joint
KR20240016110A (en) Manufacturing method of composite recycled aggregate using waste asphalt and composite recycled aggregate made by the manufacturing method
KR100966473B1 (en) Structure of invisible waterway and construction method thereof including punctured pipes
Zhou Feasibility Study of Lean Oil Sand as Base and Surface Material on Gravel Roads in Alberta
RU2301862C2 (en) Method to create cutoff curtain with filtering openings
Berwal et al. Use of recycled aggregates in granular sub base
Babashamsi et al. Recycling toward sustainable pavement development: End-of-life considerations in asphalt pavement
KR101169024B1 (en) Acceleration of settlemetnt in soft ground using water permeability of fly ashes
Banzibaganye Investigation into the use of waste tyre shreds in reinforcement of sandy soils in South Africa
Versolatto The use of construction and demolition solid wastes as a gabion filling material for hydraulic works
Dumitru et al. Progress towards achieving ecologically sustainable concrete and road pavements in Australia
CN210238176U (en) Road subgrade settlement treatment device
CN108149578A (en) A kind of processing method about bonding plane at ultra-thin wearing layer bituminous bridge expanssion joint
JP5380626B1 (en) Method of using the final landfill site as farmland and the final landfill site farmland structure
Karan Investigation of The Properties of Unbound Granular Basecourse Aggregate Using Laboratory Tests
Monyake Improving the design, construction, and maintenance of Permeable Interlocking Concrete Pavement (PICP) in South Africa
Van Vuuren Unsaturated flow through permeable pavements: An experimental study
LAGOS SOWEMIMO ADEYEMI DAVID
Tao et al. Evaluation of post flooding shoulder reconditioning

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150120

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20151013

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20151020

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20151214

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20160607

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20160617

R150 Certificate of patent or registration of utility model

Ref document number: 5959045

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250