JP5944970B2 - Open shield method - Google Patents
Open shield method Download PDFInfo
- Publication number
- JP5944970B2 JP5944970B2 JP2014211466A JP2014211466A JP5944970B2 JP 5944970 B2 JP5944970 B2 JP 5944970B2 JP 2014211466 A JP2014211466 A JP 2014211466A JP 2014211466 A JP2014211466 A JP 2014211466A JP 5944970 B2 JP5944970 B2 JP 5944970B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete box
- concrete
- box
- joint
- open shield
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 31
- 239000004567 concrete Substances 0.000 claims description 90
- 239000000463 material Substances 0.000 claims description 32
- 238000006243 chemical reaction Methods 0.000 claims description 11
- 239000007788 liquid Substances 0.000 claims description 4
- 239000002184 metal Substances 0.000 claims description 3
- 238000011900 installation process Methods 0.000 claims description 2
- 239000004576 sand Substances 0.000 claims description 2
- 238000007599 discharging Methods 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 11
- 238000010276 construction Methods 0.000 description 8
- 238000006073 displacement reaction Methods 0.000 description 8
- 238000004581 coalescence Methods 0.000 description 5
- 238000002347 injection Methods 0.000 description 5
- 239000007924 injection Substances 0.000 description 5
- 238000003780 insertion Methods 0.000 description 5
- 230000037431 insertion Effects 0.000 description 5
- 239000002689 soil Substances 0.000 description 5
- 229910000831 Steel Inorganic materials 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 239000003566 sealing material Substances 0.000 description 4
- 239000010959 steel Substances 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 230000002093 peripheral effect Effects 0.000 description 3
- 230000000694 effects Effects 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 239000003822 epoxy resin Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 229920000647 polyepoxide Polymers 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 239000013049 sediment Substances 0.000 description 1
- 239000010865 sewage Substances 0.000 description 1
- 229920002050 silicone resin Polymers 0.000 description 1
Images
Landscapes
- Sewage (AREA)
- Lining And Supports For Tunnels (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Description
本発明は、市街地に上下水道、地下道等の地下構造物を施工するオープンシールド工法に関する。 The present invention relates to an open shield method for constructing underground structures such as water and sewage systems and underground passages in an urban area.
オープンシールド工法は、開削工法(オープンカット工法)とシールド工法の長所を生かした合理性に富む工法で、上部開放型シールド機(オープンシールド機)を使用して推進させ土砂崩壊を防ぎながら、その内部で函体布設を行う工法である。 The open shield method is a rational method that makes use of the advantages of the open cut method (open cut method) and the shield method, and is promoted using an upper open type shield machine (open shield machine) while preventing sediment collapse. This is a method of laying a box inside.
図9、図10にその概略を示すと、図中1はオープンシールド機で、これは左右の側壁板とこれら側壁板に連結する底板とからなる前面、後面及び上面を開口したシールド機である。 9 and 10, the outline is shown in FIG. 9. In FIG. 9, reference numeral 1 denotes an open shield machine, which is a shield machine having left, right and left side walls and bottom plates connected to the side walls, with front, rear and top surfaces opened. .
該オープンシールド機1は、機体を前後方向で複数に分割し、フロント部1aとしての前方の機体の後端にテール部1bとしての後方の機体の前端が嵌入して、相互の嵌合部で中折れ部2を形成して屈曲可能としている。
The open shield machine 1 is divided into a plurality of bodies in the front-rear direction, and the front end of the rear body as the tail portion 1b is fitted into the rear end of the front body as the
フロント部1aは主として掘削を行うもので、前端と上面を開放面としてあり、機体内で後部に後方へ向けて中折ジャッキを左右によせて、また上下複数段に配設した。
The
これに対してテール部1bはコンクリート函体4の設置を行うもので、底板5を有し、機体内で前部に後方へ向けて推進ジャッキ(シールドジャッキ)3を左右によせて、また上下複数段に配設している。
On the other hand, the tail portion 1b is used to install the
図中6はフロント部1aの前端に設けたスライド土留板、8はプレスバー(押角)である。
In the figure, 6 is a slide earth retaining plate provided at the front end of the
次に、このようなオープンシールド機1を用いたオープンシールド工法について説明すると、図示は省略するが、発進立坑内にこのオープンシールド機1を設置して、オープンシールド機1の推進ジャッキ3を伸長して発進坑内の反力壁に反力をとってオープンシールド機1を前進させ、地下構造物を形成する第1番目のコンクリート函体4をクレーン等の揚重機14により上方から吊り降し、オープンシールド機1のテール1b部内で縮めた推進ジャッキ3の後方にセットする。
Next, an open shield construction method using such an open shield machine 1 will be described. Although illustration is omitted, the open shield machine 1 is installed in the start shaft and the
ショベル等の掘削機7でオープンシールド機1の前面又は上面から土砂を掘削しかつ排土する。この排土工程と同時またはその後に推進ジャッキ3を伸長してオープンシールド機1を前進させる。
The
そして前記第1番目のコンクリート函体4の前に第2番目のコンクリート函体4をオープンシールド機1のテール部1b内に吊り降す。以下、同様の排土工程、前進工程、コンクリート函体4のセット工程を適宜繰返して、順次コンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、さらにこのコンクリート函体4の上面に埋戻しを施す。
Then, the
なお、コンクリート函体4をオープンシールド機1のテール部1b内に吊り降す際には、コンクリートブロック等による高さ調整材をコンクリート函体4下に配設し、このテール部1b内でコンクリート函体4の左右および下部の空隙に瞬結性グラウト材を用いた裏込注入材9を充填して一次注入を行い、さらに、オープンシールド機1の前進後、二次注入として、コンクリート函体4の内側からグラウトホールにより、外側に裏込注入材9を注入する。
When the
このようにして、オープンシールド機1が到達坑まで達したならばこれを撤去して工事を完了する。 In this way, if the open shield machine 1 reaches the reaching mine, it is removed and the construction is completed.
ところで、地中に縦列に埋設されるコンクリート函体4は、既設のコンクリート函体4に対して新たなコンクリート函体4をオープンシールド機1のテール部1b内に吊り降した際に定着ボルトで締結していき、定着部10が形成される。
By the way, the
定着部10を形成するコンクリート函体4同士の接続は、図示は省略するがコーナー部に前後方向の貫通孔を設け、長ボルト等のPC鋼棒の緊結をもって縦列に並ぶものを接続していく。
The
また、カラーと称せられるリング状で断面T字形の継手を前後位置のコンクリート函体4,4の間に介装し、このカラーで前後のコンクリート函体4を接続することもある。
Further, a ring-shaped joint having a T-shaped cross section called a collar may be interposed between the
ところで、かかるコンクリート函体4による地中構造物では、地震等の耐震対策や軟弱地盤における地盤沈対策として、コンクリート函体4同士の接続を可撓継手とすることが要求される。
By the way, in the underground structure by such a
かかるコンクリート函体の可撓継手に関しては例えば、下記特許文献のようなものがある。
前記特許文献1は、中央に空間部を有する閉鎖断面のボックスカルバートを多数連結して設置することで、共同溝や下水道等を構築する時において、前記各ボックスカルバートの連結部に用いる可撓性連結構造であり、前記各ボックスカルバートの空間部周囲における各ボックスカルバートどうしの連結部には止水板が設けられていると共に、各ボックスカルバートの連結はPC鋼棒によって行われており、前記止水板は、設置地盤の軟弱化および地震等で生じる、前記各ボックスカルバートの設置位置の変位に対して、前記連結部の止水効果を維持しながら追従できるように構成されており、前記PC鋼棒は、前記止水板の設計変位量を越えた場合に、その変位を抑えて前記止水板の破損を防ぐことができると共に、自身の定着状態も前記止水板の設計変位に追従可能な定着部によって維持できるように構成されていることを特徴とするボックスカルバートにおける可撓性連結構造である。 Patent Document 1 discloses a flexible structure that is used for connecting portions of the box culverts when constructing joint grooves and sewers by connecting and installing a large number of closed cross-section box culverts having a space in the center. The box culvert is provided with a water stop plate at the connection portion between the box culverts around the space of the box culverts, and the box culverts are connected by a PC steel rod. The water plate is configured to follow the displacement of the installation position of each box culvert that occurs due to softening of the installation ground, earthquake, etc., while maintaining the water stop effect of the connecting portion, and the PC When the steel rod exceeds the design displacement amount of the water stop plate, the steel bar can suppress the displacement and prevent the water stop plate from being damaged. It is flexible coupling structure in box culvert, characterized in that is configured to be maintained by the fixing portion capable of following the design displacement water plate.
特許文献2は、一対のコンクリート函体と、このコンクリート函体の各接合端面同士を接続した接合部からなるプレキャストカルバートの可撓継手構造において、前記接合部は、前記各接合端面の内部に各端部が埋設された固体型可撓性連結部材と、前記各接合端面同士の隙間に充填された可撓性部材と、前記一対のコンクリート函体の接合部の外周面および/または内周面に形成された凹部に充填された、充填時に液状で硬化後にゴム弾性機能を持つ充填型可撓性部材とから構成されていることを特徴とするプレキャストカルバートの可撓継手構造である。
オープンシールド工法では、ショベル等の掘削機でオープンシールド機の前面又は上面から土砂を掘削しかつ排土し、この排土工程と同時またはその後に推進ジャッキを伸長してオープンシールド機を前進させるもので、コンクリート函体はジャッキ推力の反力を受けるため設置時にはしっかりとした締結が要求され、その後、コンクリート函体4同士の接続を可撓継手とすることが求められる。
In the open shield method, excavator such as excavator excavates and removes soil from the front or top surface of the open shield machine, and advances the open shield machine by extending the propulsion jack at the same time or after this earth removal process. Thus, since the concrete box receives a reaction force of the jack thrust, a firm fastening is required at the time of installation, and thereafter, the connection between the
本発明の目的はこのようなオープンシールド工法の特殊性を考慮して、オープンシールド工法の施工時(函体据付時)は函体と函体のずれ防止用に定着ボルトを締付定着でき、函体に反力が必要なくなったときにボルト定着部を緩めて可撓継手とすることができるとともに、止水性はいずれの場合でも確保できるオープンシールド工法を提供することにある。 The purpose of the present invention is to consider the special characteristics of the open shield method, and when fixing the open shield method (when installing the box), the fixing bolt can be fastened and fixed to prevent the box and box from slipping, It is an object of the present invention to provide an open shield method that can loosen a bolt fixing portion when a reaction force is no longer needed on a box to make a flexible joint and ensure water-stopping in any case.
前記目的を達成するため請求項1記載の本発明は、左右側壁板の内側に推進ジャッキを配設し、前面、後面及び上面を開口したオープンシールド機の前面又は上面開口より前方の土砂を掘削排土する工程と、推進ジャッキを伸長して左右側板と上床板と下床板とからなるコンクリート函体を反力にしてシールド機を前進させる工程と、シールド機のテール部内で縮めた推進ジャッキの後方に新たなコンクリート函体を上方から吊り降して既設コンクリート函体に接合する据え付け工程とを適宜繰り返して順次コンクリート函体を縦列に埋設するオープンシールド工法において、コンクリート函体は相互に接合する場合のインサートを設け、インサートから先はシース孔として形成され、その先に定着部が形成されるための箱抜き穴があり、既設のコンクリート函体に対して新たなコンクリート函体をオープンシールド機のテール部内に吊り降して接続する際に、コンクリート函体の内方端面に目地溝が形成され、また、コンクリート函体間にコンクリート函体の左側板、右側板の端面を上下に沿って覆うものとして、幅広の帯板であるゴム等のクッション材を介在させ、シース孔に抜け出し防止用金具として定着ボルトを挿通させ、定着部において定着部プレートを介在させてナットで締結し、コンクリート函体相互で形成する合体目地溝内に充填時に液状で硬化後弾性状となる目地材を充填するのに、合体目地溝の底部にはそれぞれのコンクリート函体の目地溝に跨らせてバックアップ材を配設し、目地材はそれぞれのコンクリート函体の目地溝の側面を中心に接着させることを要旨とするものである。 In order to achieve the above object, according to the present invention, a propulsion jack is disposed inside the right and left side wall plates, and excavated earth and sand ahead of the front or top opening of the open shield machine having the front, rear and top surfaces opened. The process of earth removal, the process of extending the propulsion jack and advancing the shield machine with the reaction of the concrete box consisting of the left and right side panels, the upper floor board and the lower floor board, and the propulsion jack shrunk in the tail part of the shield machine In the open shield construction method in which concrete boxes are buried in series in sequence by repeatedly repeating the installation process of hanging a new concrete box from above and joining to an existing concrete box, the concrete boxes are joined together. In the case, the tip of the insert is formed as a sheath hole, and there is a box opening hole for forming a fixing part at the tip. When a new concrete box is suspended from and connected to the tail part of an open shield machine, a joint groove is formed on the inner end face of the concrete box. Cushioning material such as rubber, which is a wide strip, is interposed between the left and right side plates of the concrete box, and the fixing bolt is inserted through the sheath hole as a metal fitting to prevent it from slipping out. the fixing plate is interposed and fastened with nuts in part, to fill the joint member to be cured after the elastic-like in liquid form at the time of filling in the coalescence th graben forming concrete box-body mutually, at the bottom of the coalescing th graben that is by straddle eyes graben each concrete box-body is disposed a backup member, joint material to adhere around the sides of the eyes graben each concrete box-body It is an effect.
本発明によれば、オープンシールド工法の施工時(函体据付時)は定着ボルトを締付定着することで、ジャッキ推力の反力を受けても函体と函体のずれ防止を行うことができ、しかも、コンクリート函体の接続部の止水に関しては、コンクリート函体相互で形成する合体目地溝内に充填した目地材で止水が確保できる。 According to the present invention, during the construction of the open shield method (when the box is installed), the fixing bolt is tightened and fixed, so that the box and box can be prevented from slipping even when the reaction force of the jack thrust is received. In addition, with respect to the water stoppage of the connecting portion of the concrete box, the water stoppage can be secured by the joint material filled in the joint joint groove formed between the concrete boxes.
一方、函体に反力が必要なくなったときにボルト定着部を緩めて、コンクリート函体の挙動に追従できる可撓継手とする場合に合体目地溝内に充填した目地材は硬化後ゴム弾性状となるものなのでコンクリート函体が変位しても伸展し、止水の確保は継続できる。 On the other hand, when the reaction force on the box is no longer needed, the bolt fixing part is loosened and the joint material filled in the joint joint groove is made into a rubber elastic after curing when making a flexible joint that can follow the behavior of the concrete box. Therefore, even if the concrete box is displaced, it will extend and the water stoppage can be secured.
さらに、目地材の接着面は合体目地溝のそれぞれのコンクリート函体の目地溝の面になるが、合体目地溝の底部を形成するそれぞれのコンクリート函体の目地溝の面にはバックアップ材を介在しているため接触せず、地震時の函体変位に追従しやすいものとなる。 Furthermore, the joint surface of the joint material becomes the joint groove surface of each concrete box of the united joint groove, but a backup material is interposed on the joint groove surface of each concrete box forming the bottom of the united joint groove. Therefore, it will not contact and will easily follow the box displacement during an earthquake.
以上述べたように本発明のオープンシールド工法は、オープンシールド工法の施工時(函体据付時)は函体と函体のずれ防止用に定着ボルトを締付定着でき、函体に反力が必要なくなったときにボルト定着部を緩めて可撓継手とすることができるとともに、止水性はいずれの場合でも確保できるものである。 As described above, the open shield method of the present invention can fix the fixing bolt to prevent the box from slipping when the open shield method is installed (when the box is installed). When it is no longer needed, the bolt fixing part can be loosened to make a flexible joint, and water-stopping can be ensured in any case.
以下、図面について本発明の実施の形態を詳細に説明する。図6は本発明のオープンシールド工法において使用するコンクリート函体を示すもので、コンクリート函体4は鉄筋コンクリート製またはPCコンクリート製のもので、左側板4a、右側板4bと上床板4cと下床板4dとからなるもので、前後面が開口として開放されている。
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 6 shows a concrete box used in the open shield method of the present invention. The
さらに、コンクリート函体4は相互に接合する場合のインサート(ボルト挿入孔)12を設けている。
Furthermore, the
このインサート(ボルト挿入孔)12から先は図7に示すようにシース孔16として形成され、その先に定着部10が形成されるための箱抜き穴がある。
The tip of the insert (bolt insertion hole) 12 is formed as a
また、コンクリート函体4は地下構造物として耐震性を持たせるため可撓継手とするもので、本発明は、コンクリート函体4間にゴム等のクッション材11を介在させ、かつ、ゴムパッキング等による帯状シール材13を配設している。
Moreover, the
クッション材11は、コンクリート函体4の左側板4a、右側板4bの端面を上下に沿って覆うものとして、幅広の帯板である。
The
シール材13は、コンクリート函体4の端面に形成する周方向に伸びる浅い溝に貼設する断面矩形(20mm×30mm)の帯状シール材で、弾性圧縮性がある。
The sealing
また、図1に示すようにコンクリート函体4の内方端面に目地溝20aを形成し、コンクリート函体4が相互に接続する際にはこれら目地溝20a同士で合体目地溝20が形成されるようにした。
Further, as shown in FIG. 1, a
目地溝20aはコンクリート函体4の接合面の内周縁に形成する凹溝であり、側壁面Aと底部面Bがある2面開放の溝である。
The
この目地溝20a同士が合わさって形成される合体目地溝20は一面のみが開放面となる断面コ字形の溝となる。
The
なお、オープンシールド工法の概要については、前記図9、図10で説明した通りであり、発進立坑内にこのオープンシールド機1を設置して、オープンシールド機1の推進ジャッキ3を伸長して発進坑内の反力壁に反力をとってオープンシールド機1を前進させ、地下構造物を形成する第1番目のコンクリート函体4をクレーン等の揚重機14により上方から吊り降し、オープンシールド機1のテール1b部内で縮めた推進ジャッキ3の後方にセットする。
The outline of the open shield construction method is as described with reference to FIGS. 9 and 10. The open shield machine 1 is installed in the start shaft, and the
ショベル等の掘削機7でオープンシールド機1の前面又は上面から土砂を掘削しかつ排土する。この排土工程と同時またはその後に推進ジャッキ3を伸長してオープンシールド機1を前進させる。
The
そして前記第1番目のコンクリート函体4の前に第2番目のコンクリート函体4をオープンシールド機1のテール部1b内に吊り降す。以下、同様の排土工程、前進工程、コンクリート函体4のセット工程を適宜繰返して、順次コンクリート函体4をオープンシールド機1の前進に伴い縦列に地中に残置し、さらにこのコンクリート函体4の上面に埋戻しを施す。
Then, the second
このようにして、オープンシールド機1が到達坑まで達したならばこれを撤去して工事を完了する。 In this way, if the open shield machine 1 reaches the reaching mine, it is removed and the construction is completed.
本発明のオープンシールド工法も新たなコンクリート函体4をオープンシールド機のテール部内に吊り降ろして、既設のコンクリート函体4に接続させるもので、位置決めとしてガイドピン挿入孔15にガイドピン(図示せず)を挿入する。
The open shield method of the present invention also suspends a new
また、シース孔16に抜け出し防止用金具として定着ボルトを挿通させ、定着部において定着部プレートを介在させてナットで締結する。
Further, a fixing bolt is inserted into the
さらに、コンクリート函体4の接続の際には、合体目地溝20内にバックアップ材23と弾性目地材24を充填してシールする。
Further, when the
弾性目地材24としては、例えば、伸縮性・耐久性を有する変成シリコーン樹脂とエポキシ樹脂の2液を混合させ、硬化後弾性状となり、目地の動きに追従し、かつ止水性を発揮できる目地材を使用するが、目地部への接着性と、充填後地震時のコンクリート函体の変位に追従性を有するものであれば、他の目地材でも良い。
As the elastic
弾性目地材24は一例としてセメダイン株式会社の商品名{PM700LM}が好適である。
As an example of the elastic
バックアップ材23は弾性目地材24の三面接着を防止するものであり、合体目地溝20の底部にそれぞれのコンクリート函体4の目地溝20aに跨らせて配設し、弾性目地材24はそれぞれのコンクリート函体4の目地溝20aの側面を中心に接着させる。
The
図2〜図4は、コンクリート函体4の内方端面に目地溝20aおよびコンクリート函体4が相互に接続する際の合体目地溝20の各種形状と、バックアップ材23の配置の各種例を示したものである。
2 to 4 show various shapes of the
掘進時としてナットを仮締めすると、既設のコンクリート函体4に貼り付けてあるクッション材11はコンクリート函体4同士で挟着される。
When the nut is temporarily tightened during excavation, the
掘進が終わりコンクリート函体4に反力が必要なくなった時に定着ボルトを緩め、可撓継手として形成する。
When the excavation is finished and the reaction force is no longer necessary for the
次に、地震時のコンクリート函体4の変位について説明すると、図8に示すように、コンクリート函体4の接続時およびその後に通常時に対して地震時は曲げ状態となってコンクリート函体4相互の継手に開きや圧縮が生じる場合や、抜け状態となって開きを生じる場合がある。
Next, the displacement of the
抜け状態の場合は、コンクリート函体4相互が目地が開くように挙動し、曲げ状態の場合もコンクリート函体4相互が目地が開くように挙動する。
In the detached state, the
弾性目地材24は硬化後ゴム弾性状となるものなので図5に示すように、コンクリート函体が変位し、目地間隔が広がった場合でも伸展して隙間に追従し、止水の確保は継続できる。
Since the elastic
1…オープンシールド機 1a…フロント部
1b…テール部 2…中折れ部
3…推進ジャッキ(シールドジャッキ)
4…コンクリート函体 4a…左側板
4b…右側板 4c…上床板
4d…下床板
5…底板 6…スライド土留板
7…掘削機 8…プレスバー(押角)
9…裏込注入材 10…定着部
11…クッション材 12…インサート(ボルト挿入孔)
13…シール材 14…揚重機
15…ガイドピン挿入孔 16…シース孔
17…定着ボルト 18…緩衝材
19…無収縮モルタル 20…合体目地溝
20a…目地溝
21…定着部プレート 22…ナット
23…バックアップ材 24…弾性目地材
DESCRIPTION OF SYMBOLS 1 ...
4 ...
9 ... Back
DESCRIPTION OF
Claims (1)
コンクリート函体は相互に接合する場合のインサートを設け、インサートから先はシース孔として形成され、その先に定着部が形成されるための箱抜き穴があり、
既設のコンクリート函体に対して新たなコンクリート函体をオープンシールド機のテール部内に吊り降して接続する際に、コンクリート函体の内方端面に目地溝が形成され、
また、コンクリート函体間にコンクリート函体の左側板、右側板の端面を上下に沿って覆うものとして、幅広の帯板であるゴム等のクッション材を介在させ、
シース孔に抜け出し防止用金具として定着ボルトを挿通させ、定着部において定着部プレートを介在させてナットで締結し、
コンクリート函体相互で形成する合体目地溝内に充填時に液状で硬化後弾性状となる目地材を充填するのに、
合体目地溝の底部にはそれぞれのコンクリート函体の目地溝に跨らせてバックアップ材を配設し、目地材はそれぞれのコンクリート函体の目地溝の側面を中心に接着させることを特徴としたオープンシールド工法。 Protrusion jacks are disposed inside the left and right side wall plates, and a step of excavating and discharging the earth and sand ahead of the front or upper surface opening of the open shield machine having the front, rear and upper surfaces opened, The process of advancing the shield machine with the reaction of the concrete box composed of the upper floor board and the lower floor board, and a new concrete box hung from the upper side behind the propulsion jack shrunk in the tail part of the shield machine. In the open shield method of burying concrete boxes in tandem in sequence by repeating the installation process of joining to the concrete box as appropriate,
The concrete box is provided with an insert for joining together, the tip from the insert is formed as a sheath hole, and there is a box opening hole for forming a fixing part at the tip,
When a new concrete box is hung in the tail part of an open shield machine and connected to an existing concrete box, a joint groove is formed on the inner end face of the concrete box,
In addition, as a cover that covers the end face of the left and right side plates of the concrete box along the top and bottom between the concrete boxes, a cushion material such as rubber that is a wide strip is interposed,
Insert a fixing bolt as a metal fitting to prevent the sheath hole from coming out, and fasten it with a nut with a fixing part plate interposed in the fixing part.
To fill the joint joint groove formed between the concrete boxes with a joint material that is liquid and elastic after hardening ,
A backup material is arranged at the bottom of the coalesced joint groove across the joint groove of each concrete box, and the joint material is bonded around the side of the joint groove of each concrete box . Open shield method.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2014211466A JP5944970B2 (en) | 2014-10-16 | 2014-10-16 | Open shield method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2014211466A JP5944970B2 (en) | 2014-10-16 | 2014-10-16 | Open shield method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2016079660A JP2016079660A (en) | 2016-05-16 |
JP5944970B2 true JP5944970B2 (en) | 2016-07-05 |
Family
ID=55957996
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2014211466A Active JP5944970B2 (en) | 2014-10-16 | 2014-10-16 | Open shield method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5944970B2 (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6290986B2 (en) * | 2016-07-21 | 2018-03-07 | 植村 誠 | Open shield method using concrete box with flexible joint |
JP6254657B1 (en) * | 2016-09-27 | 2017-12-27 | 植村 誠 | Flexible joint structure of concrete box |
JP6568897B2 (en) * | 2017-06-22 | 2019-08-28 | 植村 誠 | Open shield method and concrete box used for it |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3194192B2 (en) * | 1999-10-22 | 2001-07-30 | 誠 植村 | Open shield method |
JP3373469B2 (en) * | 1999-11-25 | 2003-02-04 | 誠 植村 | Joint structure of underground structure |
JP2004084372A (en) * | 2002-08-28 | 2004-03-18 | Makoto Uemura | Joint structure for underground structure |
JP4041412B2 (en) * | 2003-02-10 | 2008-01-30 | アイサワ工業株式会社 | Method and structure for joining concrete secondary products |
TWI512171B (en) * | 2011-11-21 | 2015-12-11 | Asahi Concrete Works | Joining method of concrete structure |
-
2014
- 2014-10-16 JP JP2014211466A patent/JP5944970B2/en active Active
Also Published As
Publication number | Publication date |
---|---|
JP2016079660A (en) | 2016-05-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6449040B2 (en) | Connection structure between submerged boxes, submarine tunnel construction method | |
JP5686693B2 (en) | Invert construction method and precast member | |
JP2009114643A (en) | Connecting structure of underground structure | |
JP5944970B2 (en) | Open shield method | |
JP6039734B1 (en) | Open shield method | |
JP5989718B2 (en) | Concrete box used for open shield method | |
JP6254657B1 (en) | Flexible joint structure of concrete box | |
EP2848739A1 (en) | Steel wall | |
JP4598731B2 (en) | Concrete box | |
JP6290986B2 (en) | Open shield method using concrete box with flexible joint | |
JP6548455B2 (en) | Water stop structure of continuous wall | |
KR101567742B1 (en) | PHC pile and construction method of underground structure using the same | |
JP6568897B2 (en) | Open shield method and concrete box used for it | |
JP6307135B2 (en) | Open shield method | |
JP6039735B1 (en) | Open shield method | |
JP6039736B1 (en) | Open shield method | |
JP6307136B2 (en) | Open shield method | |
JP6979417B2 (en) | Arrangement method of sealing material for flexible joint of concrete box for open shield method | |
JP6636989B2 (en) | Open shield method and concrete box used for it | |
JP6139631B2 (en) | Waterproof joint method for concrete box for open shield method | |
KR101204058B1 (en) | Steel Pipe for Underground Watertight Wall | |
JP6321710B2 (en) | Concrete box for open shield method | |
JP5705891B2 (en) | Method for forming flexible joint of concrete box | |
JP4460558B2 (en) | Joint structure of underground structure | |
JP5727863B2 (en) | Water stop member for manhole repair and manhole repair method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20160524 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20160526 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5944970 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |