JP4964346B1 - PC ground tank construction method - Google Patents

PC ground tank construction method Download PDF

Info

Publication number
JP4964346B1
JP4964346B1 JP2011168330A JP2011168330A JP4964346B1 JP 4964346 B1 JP4964346 B1 JP 4964346B1 JP 2011168330 A JP2011168330 A JP 2011168330A JP 2011168330 A JP2011168330 A JP 2011168330A JP 4964346 B1 JP4964346 B1 JP 4964346B1
Authority
JP
Japan
Prior art keywords
construction
wall
tank
opening
roof
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011168330A
Other languages
Japanese (ja)
Other versions
JP2013032170A (en
Inventor
宏彰 高木
渉 高次
智明 藤田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2011168330A priority Critical patent/JP4964346B1/en
Application granted granted Critical
Publication of JP4964346B1 publication Critical patent/JP4964346B1/en
Publication of JP2013032170A publication Critical patent/JP2013032170A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract


【課題】PC地上タンクの施工途中で施工開口を完全閉塞することによって多大な施工手間が生じ、かつ施工安全性が低下するといった課題を解消することのできるPC地上タンクの施工方法を提供すること。
【解決手段】コンクリート製の底版2の一部もしくは全部を施工し、施工開口K1を具備するPC壁3を底版2上に施工し、PC壁3の内側にこれと間隔を置いて側板4cを配し、側板4cの上に屋根6bを設置するステップ、施工開口K1のうち、一部の領域を施工開口K2として残して他の領域をコンクリートで閉塞し、PC壁3における鉛直方向のPC鋼材3cと周方向のPC鋼材3dの双方を緊張し、PC壁3の内側に冷熱抵抗緩和材4bの一部を配すステップ、一部の領域の施工開口K2を閉塞し、PC壁3の内側に冷熱抵抗緩和材4bの残部を配し、側板4cと冷熱抵抗緩和材4bの間に保冷材(粒状パーライト5)を配すステップからなる。
【選択図】図10

[PROBLEMS] To provide a construction method for a PC ground tank capable of solving the problems that a great deal of labor is caused by completely closing the construction opening during construction of the PC ground tank and that the construction safety is lowered. .
SOLUTION: A part or all of a concrete bottom slab 2 is constructed, a PC wall 3 having a construction opening K1 is constructed on the bottom slab 2, and a side plate 4c is placed inside the PC wall 3 with a gap therebetween. The step of installing the roof 6b on the side plate 4c, the part of the construction opening K1 is left as the construction opening K2, the other part is closed with concrete, and the PC steel material in the vertical direction on the PC wall 3 3c and the circumferential PC steel material 3d are tensioned, a part of the thermal resistance relaxation material 4b is disposed inside the PC wall 3, the construction opening K2 in a part of the region is closed, and the inside of the PC wall 3 The remaining portion of the cooling resistance reducing material 4b is disposed, and the cold insulating material (granular pearlite 5) is disposed between the side plate 4c and the cooling resistance relaxing material 4b.
[Selection] Figure 10

Description

本発明は、土木工事と機械(プラント)工事が混在するPC地上タンクの施工方法に関する。   The present invention relates to a construction method of a PC ground tank in which civil engineering work and mechanical (plant) work are mixed.

従来のLNGやLPG、工業用水等を貯蔵するためのPC地上タンクは一般に、RC構造(鉄筋コンクリート構造)もしくはPC構造(プレストレストコンクリート構造)の底版と、PC構造のPC壁と、から構成された防液堤(以下、PC防液堤)の内側に、金属製の内槽タンクが一体となった円筒形構造物から形成されている。通常時には内槽タンクで液を貯留し、地震等の際に液が内槽タンクから仮に漏れ出したとしても外周のPC防液堤で液密性が保証されており、液がタンク外へ漏れ出ないようになっている。なお、PC地上タンクの特にPC防液堤に関する構造や施工方法に関しては、これまで本出願人による多数の関連出願が公開されている(たとえば特許文献1〜5参照)。   Conventionally, a PC ground tank for storing LNG, LPG, industrial water, etc. is generally composed of a bottom plate of RC structure (reinforced concrete structure) or PC structure (prestressed concrete structure) and a PC wall of PC structure. It is formed from a cylindrical structure in which a metal inner tank is integrated inside a liquid bank (hereinafter referred to as PC liquid wall). Normally, the liquid is stored in the inner tank, and even if the liquid leaks from the inner tank in the event of an earthquake, etc., the liquid tightness is guaranteed by the outer PC liquid barrier, and the liquid leaks out of the tank. It is not going out. In addition, regarding the structure and construction method regarding the PC ground tank, especially the PC breakwater, many related applications by the present applicant have been published so far (see, for example, Patent Documents 1 to 5).

ところで、PC地上タンクの施工においては、主として土木工事と機械(プラント)工事の大きく2種類の工事が存在する。   By the way, in the construction of a PC ground tank, there are mainly two types of construction, civil engineering and machine (plant) construction.

より具体的には、土木工事では、PC防液堤工事、付帯設備工事などが主として存在しており、機械工事では、外槽工事、内槽工事、保冷工事や配管工事などが主として存在している。   More specifically, in civil engineering work, PC breakwater works and incidental equipment work mainly exist, and in mechanical work, outer tank work, inner tank work, cold insulation work, piping work, etc. mainly exist. Yes.

土木工事に関し、PC防液堤工事をより詳細に説明すると、その内訳は、基礎杭工事(地盤性状等に応じて必要ある場合)、掘削や埋戻しといった土工事、底版工事およびPC壁工事などがある。また、付帯設備工事には、底版ヒータ設備設置工事や昇降階段設置工事などがある。   Regarding civil engineering works, PC breakwater works will be explained in more detail. The breakdown includes foundation pile work (if necessary depending on the ground properties, etc.), earth work such as excavation and backfilling, bottom slab work and PC wall work. There is. In addition, incidental equipment construction includes bottom plate heater equipment installation work and elevating staircase installation work.

一方、機械工事に関し、外槽工事をより詳細に説明すると、その内訳は、外槽底板設置工事、外槽屋根設置工事および外槽ライナ(プレート)設置工事などがある。また、内槽工事には、内槽底板設置工事、内槽屋根設置工事および内槽側板設置工事などがある。さらに、保冷工事には、グラスウールの設置やパーライトの充填などがある。   On the other hand, regarding the mechanical work, the outer tank work will be described in more detail. The breakdown includes the outer tank bottom plate installation work, the outer tank roof installation work, and the outer tank liner (plate) installation work. The inner tank construction includes inner tank bottom plate installation work, inner tank roof installation work, and inner tank side plate installation work. In addition, cold insulation works include the installation of glass wool and the filling of perlite.

これら土木工事と機械工事によって一基のPC地上タンクが施工されることから、工種によっては双方の工事が錯綜したり、たとえば土木工事のある工種の終了によって機械工事のある工種が着手可能になるといった具合に、双方の工事が密に連携して施工フローやクリティカルパスが決定され、PC地上タンクの施工が進められることになる。   Since a single PC ground tank is constructed by these civil works and mechanical works, depending on the type of work, both works may be complicated, for example, a work type with mechanical work can be started by completing a certain type of civil engineering work. As such, the construction flow and critical path are determined through close cooperation between the two works, and the construction of the PC ground tank will proceed.

ここで、図15を参照してPC地上タンクの工程表の一例を紹介する。同図は、土木工事と機械工事の主たる工種のみを取り出して作成された工程表であり、説明の都合上、その他の工種、たとえば、仮設工事や掘削等の土工事等は省略している。   Here, an example of the process table of the PC ground tank will be introduced with reference to FIG. This figure is a process chart created by extracting only the main works of civil engineering and mechanical work. For convenience of explanation, other works such as temporary work and earth work such as excavation are omitted.

まず、現場ヤードにてPC防液堤のための基礎杭の施工がおこなわれ、次に底版施工に移行する。   First, foundation piles for PC breakwaters are constructed at the site yard, and then the base slab construction is started.

底版の施工においては、その途中でヒータ設備の設置がおこなわれる。底版内にヒータ設備を設けるのは、貯槽液がLNGの場合において該LNGの冷熱によって貯槽基礎版下が凍結するのを防止することを目的としたものである。   In the construction of the bottom plate, heater equipment is installed in the middle. The purpose of providing the heater in the bottom plate is to prevent the bottom of the storage tank from being frozen by the cold heat of the LNG when the storage tank liquid is LNG.

底版の施工が完了したら、土木工事はPC壁の施工に移行することになるが、これと同時に機械工事においては施工済みの底版上に外槽底板の設置工事がおこなわれる。   When the construction of the bottom plate is completed, the civil engineering work will shift to the construction of the PC wall. At the same time, in the mechanical work, the installation work of the outer tank bottom plate is performed on the already constructed bottom plate.

PC壁は、所定の高さごとにコンクリート打設ロットが設定され、PC壁外周の足場兼用階段の積み上げと同期する形で所定の高さまで鉛直方向および周方向のPC鋼材の設置とコンクリートの打設が交互におこなわれる。   A concrete placement lot is set for each PC wall at a predetermined height, and the vertical and circumferential PC steel materials are placed and the concrete is placed up to a predetermined height in synchronization with the build-up of scaffolding stairs around the PC wall. Setting is performed alternately.

そして、このPC壁の施工において極めて重要なことは、PC壁のたとえば対角線に位置する2箇所に所定規模の施工開口が設けられることである(施工開口の基数や位置は適宜設定される)。   And it is extremely important in the construction of this PC wall that construction openings of a predetermined scale are provided at two locations located on, for example, diagonal lines of the PC wall (the radix and position of the construction openings are appropriately set).

PC壁に設けられる施工開口は大きく以下2つの用途を有するものである。
(1)土木工事と機械工事が錯綜する工事において、大型〜小型の資機材のタンク内外への搬出入路としての用途。
(2)作業員のタンク内外へのアクセス路としての用途。
The construction opening provided in the PC wall has the following two uses.
(1) In the construction where civil engineering works and mechanical work are complicated, it is used as a loading / unloading path for large and small materials and equipment inside and outside the tank.
(2) Use as an access path for workers inside and outside the tank.

すなわち、PC壁に施工開口が設けられていることにより、足場兼用階段を利用することなく、各種の資機材(側板等の資材、資材搬送車両や足場等の機材など)を施工開口を経由してPC壁の内部や外部に作業員が搬出入することが可能となる。PC地上タンクの施工に当たり、PC壁に設けられる施工開口の存在は極めて重要である。なお、クレーン等で資機材をPC壁の上方から内部に吊り下ろす等の作業も当然におこなわれるが、この場合であっても、施工開口が完全閉塞されている場合には、作業員が足場兼用階段等の階段を使用してPC壁を乗り越え、タンクの内外を行き来しなければならないことに代わりはない。   In other words, because the construction opening is provided in the PC wall, various materials and equipment (materials such as side plates, materials transportation vehicles, and equipment such as scaffolds) can be routed through the construction opening without using a staircase that also serves as a scaffold. Thus, an operator can carry in and out the inside and outside of the PC wall. In the construction of the PC ground tank, the existence of a construction opening provided in the PC wall is extremely important. Of course, work such as suspending materials and equipment from above the PC wall with a crane or the like is also performed, but even in this case, if the construction opening is completely closed, workers will be scaffolding. There is no substitute for having to cross the PC wall using a staircase such as a dual-purpose staircase and go back and forth inside the tank.

土木工事におけるPC壁の施工が進行するのと並行して、機械工事においては、外槽底板の設置工事がおこなわれ、次いで、施工開口以外の領域において外槽ライナの設置工事がおこなわれ、内槽底版の設置工事、内槽側板の設置工事、内槽屋根の設置工事、さらには外槽屋根の設置工事と各種工事が進行することになり、土木工事と機械工事が同じエリアで錯綜することになる。   In parallel with the progress of the PC wall construction in civil engineering work, the installation work of the outer tank bottom plate was performed in the mechanical work, and then the outer tank liner was installed in the area other than the construction opening. The installation work of the tank bottom plate, the installation work of the inner tank side plate, the installation work of the inner tank roof, and further the installation work of the outer tank roof and the various works will proceed, and civil engineering work and mechanical work will be complicated in the same area become.

そして、これまでのPC地上タンクの施工においては、PC壁内のPC鋼材の緊張に先行して、上記する施工開口を完全に閉塞していた。この理由の一つは、PC壁の一部にある程度の大きさの施工開口が存在することによって、PC鋼材の歯抜け箇所が生じ、PC鋼材を緊張した際にこの歯抜け箇所やその近傍で不慮の偏荷重や内部応力が生じるのを回避するためである。また、後工程である保冷工事に先行して施工開口を完全に閉塞するという理由も当然にある。   And in the construction of the conventional PC ground tank, the construction opening described above has been completely closed prior to the tension of the PC steel material in the PC wall. One reason for this is that the presence of a certain size of opening in a part of the PC wall results in a missing portion of the PC steel material. This is to avoid the occurrence of unintentional uneven load and internal stress. In addition, there is of course a reason that the construction opening is completely closed prior to the cold insulation work which is a subsequent process.

PC壁の施工開口を完全に閉塞した後に、鉛直方向および周方向のPC鋼材を緊張し、次いで、機械工事においては完全閉塞された施工開口部に対応する領域の外槽ライナをPC壁の内側面に設置し、今度は、この外槽ライナの内側に土木工事としてPUF(ポリウレタンフォーム)からなる側部冷熱抵抗緩和材の設置がおこなわれる。   After completely closing the construction opening of the PC wall, the PC steel material in the vertical direction and the circumferential direction is tensioned. Then, in machine work, the outer tank liner in the region corresponding to the construction opening that is completely closed is placed inside the PC wall. Installed on the side, this time, a side thermal resistance mitigation material made of PUF (polyurethane foam) will be installed inside the outer tank liner as a civil engineering work.

PUFパネルを設置したら、最後に機械工事における保冷工事として、グラスウールを設置し、さらに、内槽側板とPUFパネルの間、および外槽屋根と内槽屋根の間のそれぞれの空間内に保冷材が充填されてPC地上タンクの施工が完了する。   Once the PUF panel is installed, glass wool is installed as a cold insulation work at the end of the machine work. Furthermore, there is a cold insulation material in each space between the inner tank side plate and the PUF panel, and between the outer tank roof and the inner tank roof. Filled to complete the construction of PC ground tank.

このように、PC鋼材の緊張に際して施工開口を完全に閉塞した後においても、土木工事と機械工事を合わせて多数の工事が残っている。   Thus, even after the construction opening is completely closed during the tension of the PC steel material, many works remain, including civil engineering work and mechanical work.

しかしながら、施工開口が完全に閉塞されることでPC地上タンクの内外の出入りはタンク外周の足場兼用階段等の階段を使用してたとえば20m以上の屋根(の開口、マンホール等)を経由し、タンク内の足場兼用階段を下って作業員が目的地へアクセスするといった多大の時間と労力を要する移動を余儀なくされる。そして、この際に作業員は、各種の機具や資材を持ち運びながら階段の昇降をおこなうことになるのである。   However, because the construction opening is completely closed, the inside and outside of the PC ground tank can enter and exit the tank via a roof (opening, manhole, etc.) of 20 m or more using a staircase or other staircase on the outer periphery of the tank. It is necessary to move a lot of time and labor, such as the worker going down the scaffolding staircase and accessing the destination. At this time, the worker goes up and down the stairs while carrying various equipment and materials.

そして、たとえば、施工開口閉塞後の土木工事であるPUFパネルの設置工事においては、作業員がタンク外周の階段を使用してタンクの屋根に渡り、屋根に設けられた開口(マンホール)を経由し、たとえば外槽ライナに取り付けられたステップ等を利用しながら、外槽ライナと内槽側板の間の極めて狭い空間(パーライトが充填される空間)を通ってPUFパネルを搬入することを余儀なくされるため、施工性が悪いことは勿論のこと、極めて安全性の低い施工となってしまう。   And, for example, in the PUF panel installation work, which is civil engineering work after the construction opening is closed, the worker crosses the tank roof using the stairs on the outer periphery of the tank and passes through the opening (manhole) provided on the roof. For example, while using the steps attached to the outer tank liner, it is necessary to carry the PUF panel through the extremely narrow space (space filled with pearlite) between the outer tank liner and the inner tank side plate. Of course, the workability is poor, and the construction is extremely low in safety.

そして、仮にこのような狭い空間で作業員が不慮の事故に見舞われた際には、たとえば負傷した作業員を吊り上げるための仮設担架を屋根から吊り下ろし、ここに作業員を載せて吊り上げるといった一連の救出作業が困難を極めることは必至である。   And, if a worker suffers an unexpected accident in such a narrow space, for example, a temporary stretcher for lifting an injured worker is hung from the roof, and the worker is placed on it and lifted up. It is inevitable that the rescue operation will be extremely difficult.

また、さらに、施工開口閉塞後にタンク内で火災等が発生した際に、タンク内の作業員は階段を利用してたとえば屋根を乗り越えてタンク外へ避難することを余儀なくされることから、避難にも多くの時間を要することになる。   In addition, when a fire or the like occurs in the tank after the construction opening is closed, workers in the tank are forced to evacuate outside the tank, for example, over the roof using the stairs. It will take a lot of time.

特開2009−041362号公報JP 2009-041362 A 特開2008−155999号公報JP 2008-155999 A 特開2006−083572号公報JP 2006-083572 A 特開2005−351045号公報JP-A-2005-351045 特開2005−350092号公報JP 2005-350092 A

以上をまとめると、これまでのPC地上タンクの施工方法では、PC壁に設けられた施工開口を施工途中で完全閉塞することにより、以後の施工において以下で列挙する課題を有するものとなっている。
(1)土木工事と機械工事が錯綜する工事において、大型〜小型の資機材のタンク内外への搬出入に使用される施工開口が施工途中で完全閉塞されることにより、資機材の搬出入の際に、作業員はタンク内外の階段を使用し、タンクの屋根を経由して昇降することを余儀なくされるため、施工開口が完全閉塞された後の土木工事と機械工事はいずれも多大な労力と時間を要するものとなっている。
(2)施工開口が施工途中で完全閉塞されることにより、作業員のタンク内外へのアクセス路は完全に遮断され、そのために、作業員はタンク内外の階段を使用してタンクの屋根を経由して昇降することを余儀なくされるために、タンク内外へのアクセスに際して多大な労力と時間を要するものとなっている。
(3)施工開口が施工途中で完全閉塞されることにより、外槽ライナと内槽側板の間の極めて狭い空間で作業をおこなう場合に施工性が極めて悪く、さらには施工安全性も極めて低くなっている。また、施工開口が完全閉塞された後にタンク内で火災等が発生した際に、タンク内の作業員が避難に多くの時間を要するものとなっている。
To summarize the above, in the conventional method for constructing a PC ground tank, the construction opening provided in the PC wall is completely closed during construction, thereby having the problems listed below in the subsequent construction. .
(1) In construction where civil engineering works and mechanical work are complicated, the construction opening used for carrying in and out large and small materials and equipment into and out of the tank is completely closed during construction. At the same time, workers are forced to use the stairs inside and outside the tank and go up and down via the tank roof, so both civil engineering and mechanical work after the construction opening is completely closed are labor intensive. And it takes time.
(2) When the construction opening is completely closed during construction, the worker's access path to the inside and outside of the tank is completely blocked. For this reason, the worker uses the stairs inside and outside the tank to go through the tank roof. In order to be forced to move up and down, much labor and time are required for accessing the inside and outside of the tank.
(3) When the construction opening is completely closed during construction, workability is extremely poor when working in an extremely narrow space between the outer tank liner and the inner tank side plate, and construction safety is also extremely low. Yes. In addition, when a fire or the like occurs in the tank after the construction opening is completely closed, a worker in the tank needs a lot of time to evacuate.

本発明は上記する問題に鑑みてなされたものであり、PC地上タンクの施工途中で施工開口を完全閉塞することによって生じ得る上記で列挙した種々の課題を全て解消することのできる、PC地上タンクの施工方法を提供することを目的としている。   The present invention has been made in view of the above-mentioned problems, and can solve all the various problems listed above that can be caused by completely closing the construction opening during construction of the PC ground tank. The purpose is to provide a construction method.

前記目的を達成すべく、本発明によるPC地上タンクの施工方法は、コンクリート製の底版の一部もしくは全部を施工し、施工開口を具備するPC壁を底版上に施工し、PC壁の内側に該PC壁と間隔を置いて側板を配し、側板の上に屋根を設置する第1のステップ、前記施工開口のうち、一部の領域を施工開口として残して他の領域をコンクリートで閉塞し、PC壁における鉛直方向のPC鋼材と周方向のPC鋼材の双方を緊張し、PC壁の内側に冷熱抵抗緩和材の一部を配す第2のステップ、前記一部の領域の施工開口を閉塞し、PC壁の内側に冷熱抵抗緩和材の残部を配し、前記側板と該冷熱抵抗緩和材の間に保冷材を配す第3のステップからなるものである。   In order to achieve the above object, a method for constructing a PC ground tank according to the present invention comprises constructing a part or all of a concrete bottom plate, constructing a PC wall having a construction opening on the bottom plate, and placing it inside the PC wall. A first step of placing a side plate at a distance from the PC wall and installing a roof on the side plate, of the construction openings, leaving some areas as construction openings and closing the other areas with concrete. The second step of tensioning both the PC steel material in the vertical direction and the PC steel material in the circumferential direction on the PC wall, and arranging a part of the thermal resistance relaxation material inside the PC wall, This is a third step of closing, placing the remainder of the thermal resistance relaxation material inside the PC wall, and arranging the cold insulation material between the side plate and the thermal resistance relaxation material.

本発明の施工方法は、PC地上タンクの施工途中で施工開口を完全に閉塞するのを廃し、その一部の領域を依然として施工開口として残して他の領域をコンクリートで閉塞し、その後の施工においては一部の領域の施工開口を作業員のPC地上タンク内外へのアクセス路、および、資機材の搬出入路として使用しながら施工をおこなうものである。   In the construction method of the present invention, the construction opening is completely obstructed during the construction of the PC ground tank, the other area is still left as the construction opening, and the other area is blocked with concrete. The construction is carried out while using the construction opening in a part of the area as an access path to the inside and outside of the PC ground tank of the worker and a loading / unloading path of materials and equipment.

施工開口の一部を閉塞するタイミングは、従来の施工方法における施工開口の完全閉塞のタイミングと同様に、たとえばPC鋼材を緊張する前段となる。   The timing for closing a part of the construction opening is, for example, a stage before the PC steel material is tensioned, similarly to the timing for completely closing the construction opening in the conventional construction method.

一方、閉塞されずに残った施工開口の閉塞のタイミングは、たとえば機械工事の最終工程である保冷材を設ける(たとえば粒状パーライトを充填する)前段となる。   On the other hand, the timing of closing of the construction opening remaining without being closed is, for example, the first stage of providing a cold insulating material (for example, filling granular pearlite), which is the final process of the mechanical work.

このように、施工開口を2段階に分けて閉塞することとし、1回目の閉塞で残った相対的に小寸法の施工開口をPC地上タンク内外への作業員のアクセス路、および、資機材の搬出入路とすることによって、1回目の閉塞以後の作業における作業効率が飛躍的に向上し、さらには、従来の施工方法のように足場兼用階段等の階段を昇降する場合に比してアクセスの際の作業員の安全性は格段に高められる。   In this way, the construction opening is closed in two stages, and the relatively small size construction opening remaining in the first closing is accessed by the worker access path to the inside and outside of the PC ground tank, and By using the carry-in / out route, the work efficiency in the work after the first blockage is dramatically improved, and moreover, it is accessed compared to the case of moving up and down stairs such as scaffolding stairs as in the conventional construction method. The safety of workers during this process is greatly improved.

本発明の施工方法では、まず、第1のステップとして、コンクリート製の底版の一部もしくは全部を施工し、施工開口を具備するPC壁を底版上に施工し、PC壁の内側に該PC壁と間隔を置いて側板を配し、側板の上に屋根を設置する。   In the construction method of the present invention, first, as a first step, a part or all of a concrete bottom plate is constructed, a PC wall having a construction opening is constructed on the bottom plate, and the PC wall is placed inside the PC wall. Arrange the side plates at intervals and install the roof on the side plates.

ここで、「底版の一部を施工する」とは、後工程で施工されるPC壁内の周方向のPC鋼材を緊張した際にPC壁の下端に過大な曲げモーメントが発生するのを回避するべく、底版をPC壁が直接固定される外周領域とその内側の領域で施工を2分割しておこなう方法の場合における外周領域の先行施工のことである。より具体的には、底版を一体施工した後にPC壁を底版と剛結合にて繋いだ状態でPC壁の周方向のPC鋼材を緊張すると、PC壁にはタンク内側へ曲げようとする力が作用し、この反力として底版と繋がるPC壁下端には過大な曲げモーメントが生じ得る。そこで、底版を外周リングとその内側の2つの領域に分割し、まず、第1のステップで底版の外周リングを施工してその上にPC壁を立上げ、底版の内側を施工する前に周方向のPC鋼材を緊張させることにより、PC壁をタンク内側へ曲げようとする力が作用した際に底版もリングの内側へ変位することができ(相対的に小径のリングに変形)、この底版の変位によってPC壁下端に生じ得る過大な曲げモーメントの発生を解消することが可能となるのである。したがって、周方向のPC鋼材を緊張した後に、底版の内側の領域の施工がおこなわれることとなる。   Here, “construct a part of the bottom slab” means that an excessive bending moment is not generated at the lower end of the PC wall when tension is applied to the PC steel in the circumferential direction in the PC wall to be constructed in the subsequent process. Therefore, it is a prior construction of the outer peripheral area in the method of performing the construction by dividing the bottom plate into the outer peripheral area where the PC wall is directly fixed and the inner area. More specifically, if the PC steel in the circumferential direction of the PC wall is tensioned after the bottom plate is integrally constructed and the PC wall is rigidly connected to the bottom plate, the PC wall has a force to bend toward the inside of the tank. As a reaction force, an excessive bending moment may be generated at the lower end of the PC wall connected to the bottom plate. Therefore, the bottom plate is divided into the outer ring and two areas inside it. First, in the first step, the outer ring of the bottom plate is constructed, the PC wall is raised on it, and before the inside of the bottom plate is constructed, By tensioning the PC steel material in the direction, the bottom plate can also be displaced to the inside of the ring when a force is applied to bend the PC wall to the inside of the tank (deforms into a relatively small diameter ring). It is possible to eliminate the occurrence of an excessive bending moment that can be generated at the lower end of the PC wall due to the displacement of. Therefore, after tensioning the PC steel material in the circumferential direction, the construction of the inner region of the bottom plate is performed.

この底版施工に先立ち、必要に応じて基礎杭の施工や地盤改良施工がおこなわれる。ここで、基礎杭には、たとえば場所打ちコンクリート杭やSC杭、PHC杭、鋼管杭などのいずれか一種が、工費や工期、地盤性状等を勘案して選定され、既製杭の施工においては打撃工法や中堀最終打撃工法などが適用される。   Prior to the bottom plate construction, foundation pile construction and ground improvement construction are performed as necessary. Here, for the foundation pile, for example, cast-in-place concrete pile, SC pile, PHC pile, steel pipe pile, etc. are selected in consideration of construction cost, construction period, ground properties, etc. The construction method and Nakabori final blow construction method are applied.

一方、地盤改良施工においては、サンドコンパクションパイル施工や薬液注入施工、セメント改良杭施工、表層地盤の置換施工などが液状化対策や圧密対策をはじめとする各種対策のためにおこなわれるものであり、基礎杭の施工と併用される場合には基礎杭の施工に先行して地盤改良施工がまず実施される。   On the other hand, in ground improvement construction, sand compaction pile construction, chemical solution injection construction, cement improvement pile construction, surface layer ground replacement construction, etc. are carried out for various measures including liquefaction measures and consolidation measures, When it is used in conjunction with foundation pile construction, ground improvement construction is first implemented prior to foundation pile construction.

底版の施工においては、既述するように、貯槽液がLNGの場合においては、LNGの冷熱によって貯槽基礎版下が凍結するのを防止するべく、底版内にヒータ設備を設けながらその施工がおこなわれる。なお、この底版のヒータ設備に関しては、ヒーティング方式がブライン循環方式の場合はメインヒータとサブヒータ双方の管路の設置などがあり、電熱線加熱方式の場合には電熱線の配設などがある。   In the construction of the bottom plate, as described above, when the storage tank liquid is LNG, in order to prevent the bottom of the storage tank base plate from freezing due to the cold heat of the LNG, the construction is performed while providing a heater facility in the bottom plate. It is. In addition, regarding the heater for the bottom plate, when the heating method is the brine circulation method, there are installation of both the main heater and the sub heater, and when the heating method is used, the heating wire is provided. .

底版施工においてはさらに、後工程で設置される内槽側板と底版を繋ぐアンカーストラップが底版内に定着され、PC壁を構成する鉛直方向のPC鋼材の下端が埋め込まれた態様で底版の施工が完了する。底版の施工が完了したら、土木工事はPC壁の施工に移行することになるが、これと同時に機械工事においては施工済みの底版上に外槽底板を設置する工事がおこなわれる。   In the bottom plate construction, the anchor strap connecting the inner tank side plate and the bottom plate installed in the subsequent process is fixed in the bottom plate, and the bottom plate construction is carried out in such a manner that the lower end of the vertical PC steel material constituting the PC wall is embedded. Complete. When the construction of the bottom plate is completed, the civil engineering work will shift to the construction of the PC wall. At the same time, in the mechanical work, a construction is performed in which the outer tank bottom plate is installed on the finished bottom plate.

PC壁は、たとえば2m〜4m程度の高さごとにコンクリート打設ロットが設定され、PC壁外周の足場兼用階段の積み上げと同期する形で所定の高さまで鉛直方向および周方向のPC鋼材の設置とコンクリートの打設が交互におこなわれる。   For PC walls, concrete placement lots are set for each height of about 2m to 4m, for example, and vertical and circumferential PC steel materials are installed up to a predetermined height in synchronization with the build-up of scaffolding staircases on the outer periphery of the PC wall. And concrete are placed alternately.

PC壁の施工をより詳細に説明すると、PC壁内には必要な縦鉄筋と周方向の鉄筋が配筋され、これらの鉄筋に鉛直方向のPC鋼材および周方向のPC鋼材それぞれのための鋼製シース管が固定され、このシース管内にPC鋼材(主としてPC鋼より線(もしくはPCケーブル)であり、鉛直方向のPC鋼材にはPC鋼棒が使用される場合もある)が配設される。   The construction of the PC wall will be explained in more detail. Necessary vertical bars and circumferential reinforcing bars are arranged in the PC wall, and steel for each of the vertical PC steel and the circumferential PC steel is arranged on these reinforcing bars. A sheath tube is fixed, and a PC steel material (mainly PC steel strand (or PC cable), and a PC steel rod may be used for the vertical PC steel material) is disposed in the sheath tube. .

そして、このPC壁の施工においては、所定寸法の施工開口がたとえば1箇所、もしくはPC壁の対角線上の2箇所に設けられた状態でPC壁の立上げがおこなわれ、この施工開口を、次の主たる用途、すなわち、(1)PC壁内外への作業員のアクセス路、(2)PC壁内外への大型〜小型の資機材の搬出入路、として使用しながら施工をおこなうものである。   In the construction of the PC wall, the PC wall is raised in a state in which the construction opening having a predetermined dimension is provided at, for example, one place or two places on the diagonal line of the PC wall. The construction is performed while being used as the main uses of (1) an access path for workers to and from the inside and outside of the PC wall, and (2) a carry-in / out path for large and small materials and equipment to and from the PC wall.

土木工事におけるPC壁の施工が進行するのと並行して、機械工事においては、外槽底板の設置工事がおこなわれ、次いで、施工開口以外の領域において外槽ライナの設置工事、内槽底板等の設置工事、内槽屋根や外槽屋根の設置工事と各種工事等が進行する。   In parallel with the progress of PC wall construction in civil engineering work, installation work for the outer tank bottom plate was carried out in the mechanical work, and then the outer tank liner installation work, inner tank bottom plate, etc. in areas other than the construction opening Installation work, installation work of inner tank roof and outer tank roof and various construction work.

次に、第2のステップとして、施工開口のうちの一部の領域を施工開口として残して他の領域をコンクリートで閉塞し、PC壁における鉛直方向のPC鋼材と周方向のPC鋼材の双方を緊張する。   Next, as a second step, a part of the construction opening is left as a construction opening and the other area is closed with concrete, and both the vertical PC steel and the circumferential PC steel on the PC wall are removed. get nervous.

当初開設されていた相対的に大きな寸法の施工開口に対して、一部が閉塞されて残った施工開口の大きさは、後工程でPC鋼材が緊張された際にPC鋼材の歯抜け箇所で偏荷重等が可及的に生じないような大きさで、かつ少なくとも作業員が出入り自在な大きさに調整される。   The size of the construction opening that was left partially closed compared to the construction opening of the relatively large size that was initially opened is the amount of missing part of the PC steel when the PC steel is tensioned in the subsequent process. The size is adjusted so that an unbalanced load or the like does not occur as much as possible, and at least allows the operator to enter and exit.

このように、施工開口の一部を残すことによって、後工程における作業員のアクセス路、および資機材の搬出入路が確保できることに加えて、これが緊急避難路としての役割も果たすこととなり、作業員が長い足場兼用階段等の階段を昇降する場合と比較して施工安全性が高くなることの他にも、タンク内火災等の際に迅速にタンク外へ避難できる避難路の確保という点でも施工安全性はより一層高くなるのである。また、さらに、外槽ライナと内槽側板の間の極めて狭い空間で作業をおこなう場合においても、施工開口の一部を利用して資機材を狭い空間に搬出入することができ、この狭い空間で作業員が負傷した場合でも施工開口の一部から迅速に作業員を運び出すことが可能となる。   Thus, by leaving a part of the construction opening, it is possible to secure an access path for workers in the post-process and a loading / unloading path for materials and equipment, and this also serves as an emergency evacuation path. In addition to the fact that construction safety is higher than when climbing up and down stairs such as long scaffolding stairs etc., it is also necessary to secure an evacuation route that can evacuate quickly outside the tank in the event of a fire in the tank, etc. Construction safety is even higher. Furthermore, even when working in an extremely narrow space between the outer tank liner and the inner tank side plate, materials and equipment can be carried in and out of the narrow space using a part of the construction opening. Even when the worker is injured, the worker can be quickly carried out from a part of the construction opening.

ここで、閉塞されずに残った施工開口の一部の大きさに関し、その横幅を鉛直方向のPC鋼材のピッチ間距離よりも小さく設定することができ、このような幅寸法とすることで、施工開口を残したことによる鉛直方向のPC鋼材の歯抜け箇所を生じないようにすることができる。   Here, regarding the size of a part of the construction opening that remains without being blocked, the lateral width can be set smaller than the pitch distance of the PC steel material in the vertical direction, and by setting such a width dimension, It is possible to prevent the occurrence of missing portions of the PC steel material in the vertical direction due to leaving the construction opening.

また、同様に、残った施工開口の縦幅(高さ寸法)も、周方向のPC鋼棒の高さ方向のピッチ間距離よりも小さく設定しておくのが好ましい。   Similarly, the vertical width (height dimension) of the remaining construction opening is preferably set smaller than the pitch-to-pitch distance in the height direction of the PC steel rod in the circumferential direction.

さらには、一部の領域の施工開口の周りが管体等で補強されているのが望ましい。
ここで、「管体」とは、たとえば鋼管や補強鋼材などを示称するものであり、一部の領域の施工開口の形状(円形、矩形(正方形)など)に応じて円管や角管を適用することができる。尤も、応力集中等が生じ得ない円形断面の施工開口とした方が望ましい。また、管体以外にも、施工開口周りに枠状に配筋され、コンクリートが打設されて形成される枠状のコンクリート補強体などであってもよい。
Furthermore, it is desirable that the periphery of the construction opening in a part of the region is reinforced with a pipe body or the like.
Here, the “tubular body” refers to, for example, a steel pipe or a reinforcing steel material, and a circular pipe or a square pipe is used depending on the shape of the construction opening (circular, rectangular (square), etc.) in a part of the region. Can be applied. However, it is desirable that the construction opening has a circular cross section where stress concentration or the like cannot occur. In addition to the pipe body, a frame-shaped concrete reinforcement body that is arranged in a frame shape around the construction opening and is formed by placing concrete may be used.

このように一部の領域の施工開口周りを高剛性の管体で補強しておくことにより、PC鋼材を緊張した際に当該施工開口周りでクラック等が生じるのを効果的に抑制することができるし、狭い施工開口を作業員が通過した際に搬出入される資機材が開口壁とぶつかって施工開口が破損するといった問題も解消できる。   Thus, by reinforcing the periphery of the construction opening in a part of the area with a highly rigid tube, it is possible to effectively suppress the occurrence of cracks and the like around the construction opening when the PC steel material is strained. In addition, it is possible to solve the problem that the construction opening is damaged because the equipment and materials carried in and out when the worker passes through the narrow construction opening collides with the opening wall.

PC鋼材に導入された緊張力(プレストレス力)がシース管に導入され、PC壁に圧縮力として作用することになる(ポストテンション方式)。   The tension force (pre-stress force) introduced into the PC steel material is introduced into the sheath tube and acts as a compressive force on the PC wall (post-tension method).

また、PC壁には、対角線上に位置する2箇所、もしくは対角線上に位置する2箇所を1組とした際にこれが複数組存在する態様で周方向のPC鋼材が緊張定着されるピラスターが設けられている。   In addition, the PC wall is provided with a pilaster on which two circumferentially-positioned PC steel materials are tension-fixed in such a manner that two sets located on the diagonal line or two sets located on the diagonal line exist as a set. It has been.

具体的には、PC壁における鉛直方向のPC鋼材と周方向のPC鋼材双方の緊張作業の後に、施工開口で一部閉塞された領域に対応する外槽ライナの設置工事が機械工事としておこなわれる。さらに、土木工事として、施工開口として残っている一部の施工開口以外の領域にPUF(ポリウレタンフォーム)からなる側部冷熱抵抗緩和材の設置がおこなわれる。なお、このPUFからなるパネルにはさらにその表面に液密性を向上させるためにガラスクロスを貼り付けたものなどもある。   Specifically, after the tension work of both the PC steel material in the vertical direction and the PC steel material in the circumferential direction on the PC wall, the installation work of the outer tank liner corresponding to the region partially blocked by the construction opening is performed as the mechanical work. . Furthermore, as a civil engineering work, a side cooling resistance reducing material made of PUF (polyurethane foam) is installed in a region other than a part of the construction openings remaining as construction openings. Some of these PUF panels have a glass cloth affixed to their surfaces to improve liquid tightness.

次に、第3のステップとして、一部の領域の施工開口を閉塞し、PC壁の内側に冷熱抵抗緩和材の残部を配し、前記側板と該冷熱抵抗緩和材の間に保冷材を配してPC地上タンクの施工が完了する。   Next, as a third step, the construction openings in some areas are closed, the remaining portion of the thermal resistance relaxation material is disposed inside the PC wall, and the cold insulation material is disposed between the side plate and the thermal resistance relaxation material. Then, the construction of the PC ground tank is completed.

このように、最後に閉塞された施工開口に対応する領域に土木工事として残りのPUFが設置され、同様に、この領域に対応する残りの外槽ライナが機械工事として設置される。   In this way, the remaining PUF is installed as a civil engineering work in the area corresponding to the construction opening that was closed last, and similarly, the remaining outer tank liner corresponding to this area is installed as a mechanical work.

保冷材は一般にグラスウールと粒状パーライトからなり、特に、この粒状パーライトを屋根の内外槽間の空間や内外槽側板間の空間に充填するに当たっては、施工開口を完全に閉塞する必要がある。   In general, the cold insulating material is made of glass wool and granular pearlite, and in particular, when the granular pearlite is filled in the space between the inner and outer tanks of the roof and the space between the inner and outer tank side plates, it is necessary to completely close the construction opening.

そこで、この最終工程である粒状パーライトの充填の前段で残りの施工開口が完全閉塞される。より具体的には、機械工事であるグラスウールの設置までは施工開口を残し、次いで土木工事にて残りの施工開口を閉塞した後に、再度機械工事として粒状パーライトの充填がおこなわれる。   Therefore, the remaining construction openings are completely closed before the granular pearlite filling, which is the final process. More specifically, the construction openings are left until the installation of glass wool, which is mechanical work, and then the remaining construction openings are closed by civil engineering work, and then the granular pearlite is filled again as the mechanical work.

なお、この粒状パーライトの充填は、作業員が足場兼用階段等の階段を利用して屋根上に移動し、屋根に設けられた屋根開口を介して屋根の内外槽間の空間や内外槽側板間の空間(双方は連通している)に充填するものである。   This granular pearlite is filled by the worker moving on the roof using stairs such as scaffolding stairs and the space between the inner and outer tanks of the roof and between the inner and outer tank side plates through the roof opening provided on the roof. The space (both are in communication) is filled.

以上の説明から理解できるように、本発明のPC地上タンクの施工方法によれば、PC壁に設けられた施工開口を施工途中で一度に完全閉塞することを廃し、二回に分けて閉塞するようにしたことで、一度目の閉塞〜二度目の閉塞までの施工の際にも、施工開口を以下の主たる用途、すなわち、(1)資機材のタンク内外への搬出入路、および、(2)作業員のタンク内外へのアクセス路、として利用しながら施工を進めることができ、もって施工性の向上と、最終工程までの緊急避難路の確保を含めた施工安全性の格段の向上を図ることができる。   As can be understood from the above description, according to the construction method of the PC ground tank of the present invention, it is abolished that the construction opening provided in the PC wall is completely closed at one time during the construction, and is closed in two times. As a result, even during the construction from the first blockage to the second blockage, the construction opening is used for the following main applications, that is, (1) loading and unloading paths of materials and equipment into and out of the tank, and ( 2) Construction can be carried out while using it as an access path to the inside and outside of the tank for workers, thereby improving workability and significantly improving construction safety, including securing emergency evacuation routes until the final process. Can be planned.

本発明の施工方法で施工されたPC地上タンクの一実施の形態を示した縦断面図である。It is the longitudinal cross-sectional view which showed one Embodiment of the PC ground tank constructed by the construction method of this invention. 図1のII部の拡大図である。It is an enlarged view of the II section of FIG. (a)、(b)はそれぞれ、図1のIIIa−IIIa矢視図、IIIb−IIIb矢視図であってPC地上タンクの横断面図である。(A), (b) is the IIIa-IIIa arrow directional view of FIG. 1, IIIb-IIIb arrow directional view, respectively, Comprising: It is a cross-sectional view of a PC ground tank. 図1のIV矢視図であって、PC地上タンクの正面図である。FIG. 4 is a front view of the PC ground tank, taken along the line IV in FIG. 1. 本発明の施工方法を説明した工程表である。It is a process chart explaining the construction method of the present invention. 本発明の施工方法の第1のステップを説明した図である。It is a figure explaining the 1st step of the construction method of the present invention. 図6に続いて第1のステップを説明した図である。FIG. 7 is a diagram illustrating a first step following FIG. 6. 図7に続いて第1のステップを説明した図である。FIG. 8 is a diagram illustrating a first step following FIG. 7. 図8に続いて第1のステップを説明した図である。FIG. 9 is a diagram illustrating a first step following FIG. 8. 本発明の施工方法の第2のステップを説明した図である。It is a figure explaining the 2nd step of the construction method of the present invention. 従来の施工方法を説明した図であって、施工開口が完全閉塞された後の作業員のタンク内へのアクセス路を説明した図である。It is a figure explaining the conventional construction method, Comprising: It is the figure explaining the access path to the inside of a tank of a worker after the construction opening was completely obstruct | occluded. 第2のステップで施工開口の一部が閉塞されたことを説明する模式図である。It is a schematic diagram explaining that a part of construction opening was obstruct | occluded by the 2nd step. 本発明の施工方法の第3のステップを説明した図である。It is a figure explaining the 3rd step of the construction method of the present invention. 第3のステップで残りの施工開口が閉塞されたことを説明する模式図である。It is a schematic diagram explaining that the remaining construction opening was obstruct | occluded at the 3rd step. 従来の施工方法を説明した工程表である。It is a process chart explaining the conventional construction method.

以下、図面を参照して本発明のPC地上タンクの施工方法の実施の形態を説明する。なお、図示するPC地上タンクはその側壁の下端に段部を具備しないものであるが、側壁の下端に1段もしくは2段以上(多段)の段部を具備する形態であってもよい。また、図示するPC地上タンクは杭基礎を適用するものであるが、地盤条件等によっては直接基礎のものや、逆に地盤改良が施されたものなどであってもよい。さらに、収容液体はLNGであるが、これ以外のLPGや工業用水などの任意の液体収容に供されるものであってもよい。   Hereinafter, an embodiment of a construction method of a PC ground tank according to the present invention will be described with reference to the drawings. The illustrated PC ground tank does not include a step at the lower end of the side wall, but may have a form including one or more steps (multi-stage) at the lower end of the side wall. Moreover, although the illustrated PC ground tank applies a pile foundation, depending on the ground conditions or the like, it may be a direct foundation or conversely a ground improvement. Furthermore, although the storage liquid is LNG, it may be used for storage of any liquid such as LPG or industrial water.

(PC地上タンク)
図1は本発明の施工方法で施工されたPC地上タンクの一実施の形態を示した縦断面図であり、図2は図1のII部の拡大図であり、図3a、図3bはそれぞれ、図1のIIIa−IIIa矢視図、IIIb−IIIb矢視図であってPC地上タンクの横断面図であり、図4は図1のIV矢視図であって、PC地上タンクの正面図である。
(PC ground tank)
FIG. 1 is a longitudinal sectional view showing an embodiment of a PC ground tank constructed by the construction method of the present invention, FIG. 2 is an enlarged view of a portion II in FIG. 1, and FIGS. Fig. 3 is a cross-sectional view of the PC ground tank as viewed from arrows IIIa-IIIa and IIIb-IIIb in Fig. 1, and Fig. 4 is a view of arrow IV in Fig. 1, a front view of the PC ground tank. It is.

図1で示すPC地上タンク100はLNGを貯蔵するためのタンクであり、PHC杭やSC杭等の基礎杭1と、基礎杭1で支持されたRC構造もしくはPC構造の底版2と、PC構造のPC壁3と、から構成されたPC防液堤10と、このPC防液堤10の内側に設けられた金属製の内槽タンクが一体となった円筒形構造物から大略構成されている。   A PC ground tank 100 shown in FIG. 1 is a tank for storing LNG, a foundation pile 1 such as a PHC pile or an SC pile, a bottom plate 2 of an RC structure or a PC structure supported by the foundation pile 1, and a PC structure. The PC wall 3 is generally composed of a cylindrical structure in which a PC liquid breakwater 10 constituted by a metal inner tank tank provided inside the PC liquid breakwater 10 is integrated. .

金属製の内槽タンクは、外槽ライナ4a、側部冷熱抵抗緩和材4b(PUFパネル)、内槽側板4cとこれらの間に充填された粒状のパーライト5からなる側壁保冷構造体4と、外槽底板ライナ7a、底部冷熱抵抗緩和材7b(PUFパネル)、内槽底板7cとこれらの間のパーライトコンクリートブロック7dからなる底版保冷構造体7と、外槽屋根6aと内槽屋根6bとこれらの間に充填された粒状のパーライト5からなる屋根6とから大略構成されている。   The inner tank made of metal includes an outer tank liner 4a, a side cooling resistance reducing material 4b (PUF panel), an inner tank side plate 4c, and a side wall cooling structure 4 composed of granular pearlite 5 filled therebetween, Outer tank bottom plate liner 7a, bottom cooling resistance reducing material 7b (PUF panel), inner tank bottom plate 7c and bottom slab insulation structure 7 composed of pearlite concrete block 7d therebetween, outer tank roof 6a and inner tank roof 6b and these And a roof 6 made of granular pearlite 5 filled in between.

PC防液堤10の外側には、基礎杭1で支持された昇降階段基礎8a上に昇降階段8bが立設しており、これが屋根6に通じていて、PC地上タンク100供用後には、屋根6に設けられた開閉自在の開口(メンテナンス開口)までアクセスできるようなっている。   On the outside of the PC breakwater 10, an ascending / descending step 8b is erected on an ascending / descending step foundation 8a supported by the foundation pile 1, which leads to the roof 6, and after the PC ground tank 100 is used, the roof 6 is openable to a freely openable / closable opening (maintenance opening).

PC防液堤10を構成する底版2には、貯槽液LであるLNGの冷熱によって貯槽基礎版下が凍結するのを防止するべく、底版2内にブライン循環方式のヒータ設備を構成するメインヒータとサブヒータ双方の管路2aが埋設されている。また、内槽側板4cと底版2は不図示のアンカーストラップで繋がれており、このアンカーストラップの一部は底版2内に定着されている。   The bottom plate 2 constituting the PC breakwater 10 has a main heater constituting a brine circulation type heater facility in the bottom plate 2 in order to prevent the storage tank base plate from being frozen by the cold heat of the LNG as the storage tank liquid L. And the sub-heater 2a are buried. The inner tank side plate 4c and the bottom plate 2 are connected by an anchor strap (not shown), and a part of the anchor strap is fixed in the bottom plate 2.

PC防液堤10を構成するPC壁3には、その断面中心において、周方向に所定のピッチで鉛直方向のPC鋼材3c(PC鋼より線)が配設されており、さらに、この鉛直方向のPC鋼材3cを包囲するように周方向のPC鋼材3d(PC鋼より線)がPC壁3の高さ方向に所定のピッチで配設されている。   The PC wall 3 constituting the PC breakwater 10 is provided with a vertical PC steel material 3c (PC steel strand) at a predetermined pitch in the circumferential direction at the center of the cross section. PC steel material 3d (PC steel strand) in the circumferential direction is arranged at a predetermined pitch in the height direction of the PC wall 3 so as to surround the PC steel material 3c.

図2,4で示すように、施工されたPC地上タンク100においては、PC防液堤10のPC壁3において、2つの閉塞跡m1、m2が存在しており、閉塞跡m1と閉塞跡m2の間にはコンクリートにて最初に閉塞された一度目の閉塞部3aがあり、閉塞跡m2の内側にはコンクリートにて閉塞された二度目の閉塞部3bがある。   As shown in FIGS. 2 and 4, in the constructed PC ground tank 100, there are two blockage marks m1 and m2 on the PC wall 3 of the PC breakwater 10, and the blockage mark m1 and the blockage mark m2 are present. Between them, there is a first closed portion 3a that is first closed with concrete, and inside the closed mark m2, there is a second closed portion 3b that is closed with concrete.

この閉塞跡m1、m2は、本発明の施工方法において、閉塞跡m1の形状および寸法の相対的に大きな施工開口が閉塞時期をずらして2度に亘って閉塞されたことを示すものである。   The blockage marks m1 and m2 indicate that in the construction method of the present invention, the construction opening having a relatively large shape and size of the blockage mark m1 is blocked twice with different closing times.

また、図3bで示すように、二度目の閉塞部3bの横幅t2は、その近傍の2本の鉛直方向のPC鋼材3c、3cのピッチ間距離t1よりも小さい幅に設定されており、このことにより、二度目の閉塞部3bが施工開口として残った際に、ここがPC鋼材の歯抜け部となることが解消されている。   Further, as shown in FIG. 3b, the lateral width t2 of the second blocking portion 3b is set to a width smaller than the inter-pitch distance t1 between the two vertical PC steel materials 3c and 3c in the vicinity thereof. Thus, when the second closed portion 3b remains as the construction opening, it is eliminated that this becomes a tooth missing portion of the PC steel material.

また、図3、図4で示すように、PC壁3には、対角線上に位置する2つのピラスター3’が設けてあり、このピラスター3’にて周方向のPC鋼材3dの緊張定着がおこなわれている。   As shown in FIGS. 3 and 4, the PC wall 3 is provided with two pilasters 3 ′ located on a diagonal line, and tension fixing of the PC steel material 3 d in the circumferential direction is performed by the pilasters 3 ′. It is.

このピラスター3’におけるPC鋼材3dの緊張固定に関しては、不図示のトランペットシース管がピラスター3’内に埋設されており、このトランペットシース管とここに配設されたアンカーディスクの円錐孔からPC鋼材3dを挿通させ、緊張姿勢で円錐孔にウェッジを嵌め込むことでPC鋼材3dを緊張固定することができる。PC鋼材3dが緊張されるとともにトランペットシース管内にはグラウトが充填され、この緊張力が支圧板を介してピラスター3’に反力となる圧縮力を付与した状態でPC鋼材3dの緊張定着が図られている。   Regarding the tension fixation of the PC steel material 3d in the pilaster 3 ′, a trumpet sheath tube (not shown) is embedded in the pilaster 3 ′, and the PC steel material is formed from the conical hole of the trumpet sheath tube and the anchor disk disposed therein. The PC steel material 3d can be tension-fixed by inserting 3d and inserting a wedge into the conical hole in a tension posture. The PC steel 3d is tensioned and the trumpet sheath tube is filled with grout, and the tension of the PC steel 3d is fixed in a state in which the compressive force is applied to the pilaster 3 'via the support plate. It has been.

(PC地上タンクの施工方法)
次に、図5〜図14(従来の施工方法を説明する図11を除く)を参照して、本発明のPC地上タンクの施工方法を説明する。ここで、図5は本発明の施工方法を説明した工程表の一例であり、図6〜図9は順に第1のステップ、図10は第2のステップ、図13は第3のステップをそれぞれ説明した模式図である。以下、図5の工程表と、対応する説明図を交互に参照しながら施工方法を説明する。
(PC ground tank construction method)
Next, the construction method of the PC ground tank of the present invention will be described with reference to FIGS. Here, FIG. 5 is an example of a process chart explaining the construction method of the present invention. FIGS. 6 to 9 show the first step, FIG. 10 shows the second step, and FIG. 13 shows the third step. It is the schematic diagram demonstrated. Hereinafter, the construction method will be described with reference to the process chart of FIG. 5 and the corresponding explanatory drawings alternately.

図5で示す工程表のうち、施工開口の一部閉塞の前までの工程は、図15を参照して説明した従来の施工方法の施工開口の完全閉塞の前までの工程と同様である。   In the process chart shown in FIG. 5, the process before the partial opening of the construction opening is the same as the process before the complete opening of the construction opening of the conventional construction method described with reference to FIG. 15.

まず、第1のステップとして、図6で示すように、所定本数の基礎杭1を施工し、ヒータ管路2aが埋設された底版2を施工し、不図示のアンカーストラップの据付けをおこなった後に、対角線上に位置する2箇所の施工開口K1を設けながらPC壁3をロットごとに施工していく。たとえば、1ロットあたり2m程度の高さに設定することができ、外側の足場兼用階段SをPC壁3の立上げに先行して組み付けながらPC壁3を順次立ち上げていく。なお、2箇所の施工開口K1は、作業員による機材や資材の搬入や搬出用のアクセス路として使用される(X方向)。   As a first step, as shown in FIG. 6, after a predetermined number of foundation piles 1 are constructed, a bottom plate 2 in which a heater pipe 2a is embedded is constructed, and an anchor strap (not shown) is installed. The PC wall 3 is constructed for each lot while providing two construction openings K1 located on the diagonal line. For example, the height can be set to about 2 m per lot, and the PC wall 3 is sequentially raised while assembling the external scaffolding staircase S prior to the rise of the PC wall 3. The two construction openings K1 are used as access paths for carrying in and carrying out equipment and materials by workers (X direction).

次に、図7で示すように、PC壁3を最上端まで施工するとともに、外側リング状の底版保冷構造体7eを底版2の上に設置し、この上に内槽側板4cを立て込み、不図示のアンカーストラップで立て込み姿勢を固定保持する。   Next, as shown in FIG. 7, while constructing the PC wall 3 to the uppermost end, the outer ring-shaped bottom plate cold insulation structure 7e is installed on the bottom plate 2, and the inner tank side plate 4c is stood on this, The standing posture is fixedly held by an anchor strap (not shown).

次に、図8で示すように、クレーンを利用して内槽屋根6bを内槽側板4cの上に据付け、PC壁3の上に外槽屋根6aを据付け、それぞれ溶接にて接続部の一体化を図る。さらに、底版2上であって、底版保冷構造体7eの内側には、外槽底板ライナ7a、底部冷熱抵抗緩和材7b(PUFパネル)、パーライトコンクリートブロック7dおよび内槽底板7cを設置する。   Next, as shown in FIG. 8, the inner tank roof 6b is installed on the inner tank side plate 4c by using a crane, the outer tank roof 6a is installed on the PC wall 3, and the connection parts are integrated by welding. Plan Further, on the bottom plate 2 and inside the bottom plate cold insulation structure 7e, an outer tank bottom plate liner 7a, a bottom cooling resistance reducing material 7b (PUF panel), a pearlite concrete block 7d, and an inner tank bottom plate 7c are installed.

次に、図9で示すように、PC壁3の内側のうち、施工開口K1以外の領域において外槽ライナ4aを設置し、さらに、昇降階段基礎8a上に昇降階段8bを組み付け、その上端で屋根6に設けられた開閉自在な開口(メンテナンス開口)にアクセス自在とする。   Next, as shown in FIG. 9, the outer tank liner 4a is installed in the area inside the PC wall 3 other than the construction opening K1, and the ascending / descending stairs 8b is assembled on the ascending / descending stairs foundation 8a, An openable / closable opening (maintenance opening) provided on the roof 6 is made accessible.

この第1のステップでは、比較的大きな寸法の施工開口K1を介して、作業員がPC壁3の内外を容易に出入りすることができる。なお、施工開口K1は、図示するように平面視が長方形であり、その平面寸法は、縦寸法を4〜5m程度、横寸法を5〜15m程度に設定することができる。   In this first step, an operator can easily go in and out of the PC wall 3 through the construction opening K1 having a relatively large size. The construction opening K1 has a rectangular shape in plan view as shown in the figure, and the planar dimension can be set to a vertical dimension of about 4 to 5 m and a horizontal dimension of about 5 to 15 m.

次に、第2のステップとして、施工開口K1の一部をコンクリートで閉塞して一度目の閉塞部3aを施工し、相対的に小寸法の施工開口K2を残した状態で、鉛直方向のPC鋼材3cと周方向のPC鋼材3dの緊張をおこなうことにより、施工途中のPC地上タンク100’が形成される(図5の工程表における「施工開口一部閉塞」および図10参照)。   Next, as a second step, a part of the construction opening K1 is closed with concrete, the first closing part 3a is constructed, and a relatively small size construction opening K2 is left, and the vertical PC By applying tension between the steel material 3c and the circumferential PC steel material 3d, a PC ground tank 100 'in the middle of construction is formed (see "Partial opening of construction opening" in the process chart of FIG. 5 and FIG. 10).

この第2のステップにおいても、施工開口K2が確保されていることにより、作業員のPC壁3の内外へのアクセス路、および、資機材の搬出入路が保証される(X方向)。   Also in this second step, the construction opening K2 is secured, so that the access path to the inside and outside of the PC wall 3 and the carry-in / out path of the equipment are guaranteed (X direction).

このように本発明の施工方法では、この段階で施工開口の一部を依然として残して以後の施工をおこなうものであるが、従来の施工方法では、図11で示すように施工開口が完全に閉塞されることになる(図11における完全閉塞部3a’)である。   Thus, in the construction method of the present invention, a part of the construction opening is still left at this stage and the subsequent construction is performed. However, in the conventional construction method, the construction opening is completely closed as shown in FIG. (Completely closed portion 3a ′ in FIG. 11).

この場合、同図で示すように、機械工事においては、昇降階段8bから外槽屋根6aと内槽屋根6bに設けられた不図示の施工開口(マンホール)を介し、タンク内に設けられた足場兼用階段Sを介して作業員がアクセスすることになり、かつ、このルートで資機材が搬入される(Z1方向)。   In this case, as shown in the figure, in the mechanical work, the scaffolding provided in the tank from the ascending / descending stairs 8b through the construction opening (manhole) (not shown) provided in the outer tank roof 6a and the inner tank roof 6b. Workers will access through the shared staircase S, and materials and equipment will be carried in this route (Z1 direction).

一方、施工開口が完全に閉塞された後の土木工事としてはPUFの設置工事があるが、作業員は、昇降階段8bから外槽屋根6aに設けられた不図示の施工開口(マンホール)を介し、外槽ライナ4aに設けられたステップ等を介して、外槽ライナ4aと内槽側板4cの間の極めて狭い空間を通って当該空間下方へアクセスすることになり、かつ、このルートでPUF等を搬入する(Z2方向)。   On the other hand, there is a PUF installation work as a civil engineering work after the construction opening is completely closed. However, the worker passes through the construction opening (manhole) (not shown) provided in the outer tank roof 6a from the ascending / descending stairs 8b. Through the steps provided in the outer tank liner 4a, the lower tank space is accessed through a very narrow space between the outer tank liner 4a and the inner tank side plate 4c. Is carried in (Z2 direction).

そのため、既述するように、外槽ライナ4aと内槽側板4cの間の極めて狭い空間で作業をおこなう場合に施工性が極めて悪く、さらには施工安全性も極めて低くなっており、また、施工開口が完全閉塞された後にタンク内で火災等が発生した際に、タンク内の作業員が避難に多くの時間を要するものとなっている。   Therefore, as described above, when working in an extremely narrow space between the outer tank liner 4a and the inner tank side plate 4c, the workability is extremely poor, and the construction safety is also extremely low. When a fire or the like occurs in the tank after the opening is completely closed, it takes a lot of time for the workers in the tank to evacuate.

しかしながら、本発明の施工方法では、この段階においても依然として施工開口の一部を残して以後の施工を進めるため、これらの問題が全て解消されることになる。   However, in the construction method according to the present invention, all of these problems are solved because the construction is continued while leaving a part of the construction opening even at this stage.

図12は、第2のステップで施工開口の一部が閉塞されたことを説明する模式図である。   FIG. 12 is a schematic diagram for explaining that a part of the construction opening is closed in the second step.

同図で示すように、一度目の閉塞部3aが施工されることによって、施工開口K1の閉塞跡m1が形成される。   As shown in the figure, the first blockage portion 3a is constructed to form a blockage mark m1 of the construction opening K1.

そして、既述するように、施工開口K2の横幅t2は鉛直方向のPC鋼材3cのピッチ間距離t1よりも小さく設定されており、したがって、施工開口K2を残したことによる鉛直方向のPC鋼材3cの歯抜け箇所の発生が抑止されている。   As described above, the width t2 of the construction opening K2 is set to be smaller than the pitch distance t1 of the PC steel material 3c in the vertical direction. Therefore, the PC steel material 3c in the vertical direction due to leaving the construction opening K2. Occurrence of missing tooth portions is suppressed.

また、施工開口K2の断面形状は、応力集中等が生じ得ない円形断面となっており、さらに、その外周には、鋼管や補強鋼材などからなる高剛性の管体3eが設置されて施工開口K2は補強されている。したがって、PC鋼材3c、3dを緊張した際に施工開口K2周りでクラック等が生じるのが効果的に抑制され、さらには、狭い施工開口K2を作業員が通過して開口壁とぶつかった際に施工開口K2が破損するといったことも抑制されている。   In addition, the cross-sectional shape of the construction opening K2 is a circular cross section where stress concentration or the like cannot occur, and a high-rigidity tube 3e made of a steel pipe or a reinforcing steel material is installed on the outer periphery of the construction opening K2. K2 is reinforced. Therefore, when the PC steel materials 3c and 3d are tensioned, the occurrence of cracks and the like around the construction opening K2 is effectively suppressed, and furthermore, when an operator passes through the narrow construction opening K2 and collides with the opening wall. It is also suppressed that the construction opening K2 is broken.

PC鋼材3c、3dが緊張されたら、機械工事において、施工開口の一部閉塞された領域に対応する外槽ライナ4aの取付けがおこなわれ、さらに、土木工事において、施工開口以外の領域における側部冷熱抵抗緩和材4b(PUF)の取付けがおこなわれ、さらに機械工事において、不図示のグラスウールの内槽側板4cの内側への取付けがおこなわれる。   When the PC steel materials 3c and 3d are strained, the outer tank liner 4a corresponding to the partially closed area of the construction opening is installed in the machine work, and further, in the civil engineering work, the side portion in the area other than the construction opening. The thermal resistance relaxation material 4b (PUF) is attached, and further, in the mechanical work, the glass wool (not shown) is attached to the inner side of the inner tank side plate 4c.

次に、第3のステップとして、図13で示すように、土木工事として、施工開口の残部の閉塞をおこなって二度目の閉塞部3bを施工し、次いで、閉塞された施工開口の残部の領域において側部冷熱抵抗緩和材4b(PUF)の残部の取付けがおこなわれ、次に、機械工事として、閉塞された施工開口の残部の領域における外槽ライナ4aの設置がおこなわれる。なお、図5の工程表でも示すように、施工開口の残部に対応する領域において、鉛直方向もしくは周方向のPC鋼材の緊張が必要な場合にはそのPC緊張がおこなわれる。   Next, as a third step, as shown in FIG. 13, as a civil engineering work, the remaining part of the construction opening is closed to construct the second closing part 3 b, and then the area of the remaining part of the closed construction opening Then, the remaining portion of the side cooling resistance reducing material 4b (PUF) is attached, and then the outer tank liner 4a is installed in the region of the remaining portion of the closed construction opening as mechanical work. In addition, as shown also in the process chart of FIG. 5, in the region corresponding to the remaining portion of the construction opening, when the tension of the PC steel material in the vertical direction or the circumferential direction is necessary, the PC tension is performed.

図13,14で示すように、二度目の閉塞部3bの施工によって施工開口が完全に閉塞されたら、最後に機械工事である粒状パーライト5を屋根6aに設けられた不図示の屋根開口から落とし込み、屋根の内外槽間の空間や内外槽側板間の空間に粒状パーライト5が充填されて金属製の内槽タンクが構築され、PC地上タンク100の施工が完了する。   As shown in FIGS. 13 and 14, when the construction opening is completely closed by the second construction of the closing portion 3b, the granular pearlite 5, which is mechanical work, is finally dropped from the roof opening (not shown) provided on the roof 6a. The space between the inner and outer tanks of the roof and the space between the inner and outer tank side plates are filled with the granular pearlite 5 to construct a metal inner tank, and the construction of the PC ground tank 100 is completed.

以上で説明するように、本発明の施工方法では施工開口を2段階に分けて閉塞することとし、1回目の閉塞で残った相対的に小寸法の施工開口K2をPC地上タンク100の内外への作業員のアクセス路とし、かつ、資機材の搬出入路とすることにより、1回目の閉塞以後の作業における作業効率が飛躍的に向上し、さらには、従来のように足場兼用階段を昇降する場合に比してアクセスの際の作業員の安全性は格段に高められる。   As described above, in the construction method of the present invention, the construction opening is closed in two stages, and the construction opening K2 having a relatively small size remaining in the first closing is moved into and out of the PC ground tank 100. As an access path for workers and a loading / unloading path for materials and equipment, the work efficiency in the work after the first blockage has been dramatically improved. Compared with the case, the safety of the worker at the time of access is greatly improved.

本発明者等の試算によれば、PC壁高さが20m程度のPC地上タンクの施工に際し、施工開口が完全閉塞した後の工程において作業員が足場兼用階段を昇降する際に要する時間は、午前、午後のそれぞれで40分ずつの計80分にも及んでいることが分かっている。   According to the estimation by the present inventors, when constructing a PC ground tank having a PC wall height of about 20 m, the time required for the worker to lift and lower the scaffolding stairs in the process after the construction opening is completely closed is as follows: It has been found that it takes 80 minutes, 40 minutes each in the morning and afternoon.

したがって、本施工方法を適用することにより、アクセスに要する時間はほとんど不要となり、上記80分程度の時間を他の作業に利用することが可能となり、施工効率の向上と工期の短縮に繋がる。   Therefore, by applying this construction method, the time required for access becomes almost unnecessary, and the time of about 80 minutes can be used for other work, leading to improvement of construction efficiency and shortening of the construction period.

以上、本発明の実施の形態を図面を用いて詳述してきたが、具体的な構成はこの実施形態に限定されるものではなく、本発明の要旨を逸脱しない範囲における設計変更等があっても、それらは本発明に含まれるものである。   The embodiment of the present invention has been described in detail with reference to the drawings. However, the specific configuration is not limited to this embodiment, and there are design changes and the like without departing from the gist of the present invention. They are also included in the present invention.

1…基礎杭、2…底版、3…PC壁、3a…一度目の閉塞部、3b…二度目の閉塞部、3c…鉛直方向のPC鋼材、3d…周方向のPC鋼材、3e…管体、4…側壁保冷構造体、4a…外槽ライナ、4b…側部冷熱抵抗緩和材、4c…内槽側板、5…粒状パーライト(保冷材)、6…屋根、6a…外槽屋根、6b…内槽屋根、7…底版保冷構造体、7a…外槽底板ライナ、7b…底部冷熱抵抗緩和材、7c…内槽底板、7d…パーライトコンクリートブロック(保冷材)、7e…外側リング状の底版保冷構造体、8a…昇降階段基礎、8b…昇降階段、10…PC防液堤、100…PC地上タンク、100’…施工途中のPC地上タンク、K1…施工開口、K2…一部が閉塞された後の施工開口、m1、m2…閉塞跡   DESCRIPTION OF SYMBOLS 1 ... Foundation pile, 2 ... Bottom plate, 3 ... PC wall, 3a ... 1st obstruction | occlusion part, 3b ... 2nd obstruction | occlusion part, 3c ... Vertical PC steel material, 3d ... Circumferential PC steel material, 3e ... Tubular body 4 ... Side wall cold insulation structure, 4a ... Outer tank liner, 4b ... Side cooling resistance reducing material, 4c ... Inner tank side plate, 5 ... Granular pearlite (cold insulation), 6 ... Roof, 6a ... Outer tank roof, 6b ... Inner tank roof, 7 ... Bottom plate cold insulation structure, 7a ... Outer tank bottom plate liner, 7b ... Bottom cooling resistance reducing material, 7c ... Inner tank bottom plate, 7d ... Perlite concrete block (cold insulation material), 7e ... Outer ring-shaped bottom plate cold insulation Structure, 8a ... Elevating staircase foundation, 8b ... Elevating staircase, 10 ... PC breakwater, 100 ... PC ground tank, 100 '... PC ground tank during construction, K1 ... Construction opening, K2 ... Partially blocked Rear construction opening, m1, m2 ... blockage mark

Claims (5)

コンクリート製の底版の一部もしくは全部を施工し、施工開口を具備するPC壁を底版上に施工し、PC壁の内側に該PC壁と間隔を置いて側板を配し、側板の上に屋根を設置する第1のステップ、
前記施工開口のうち、一部の領域を施工開口として残して他の領域をコンクリートで閉塞し、PC壁における鉛直方向のPC鋼材と周方向のPC鋼材の双方を緊張し、PC壁の内側に冷熱抵抗緩和材の一部を配す第2のステップ、
前記一部の領域の施工開口を閉塞し、PC壁の内側に冷熱抵抗緩和材の残部を配し、前記側板と該冷熱抵抗緩和材の間に保冷材を配す第3のステップからなるPC地上タンクの施工方法。
A part or all of the bottom plate made of concrete is constructed, a PC wall having a construction opening is constructed on the bottom plate, a side plate is placed inside the PC wall at a distance from the PC wall, and a roof is placed on the side plate. The first step of installing
Among the construction openings, a part of the construction openings are left as construction openings, and the other areas are closed with concrete, both the PC steel in the vertical direction and the PC steel in the circumferential direction on the PC wall are tensioned, and inside the PC wall. A second step of arranging a part of the thermal resistance relaxation material,
The PC comprising the third step of closing the construction opening in the partial area, placing the remainder of the thermal resistance relaxation material inside the PC wall, and arranging the cold insulation material between the side plate and the thermal resistance relaxation material Ground tank construction method.
前記一部の領域の施工開口が鉛直方向のPC鋼材のピッチ間に設けられている請求項1に記載のPC地上タンクの施工方法。   The construction method of the PC ground tank according to claim 1, wherein the construction openings in the partial area are provided between the pitches of the PC steel materials in the vertical direction. 前記一部の領域の施工開口の周りが管体で補強されている請求項1または2に記載のPC地上タンクの施工方法。   The construction method of the PC ground tank according to claim 1 or 2, wherein the periphery of the construction opening in the partial area is reinforced with a pipe body. 前記第1のステップで底版の一部が該底版の中央領域を残して先行施工され、前記第2のステップで少なくとも周方向のPC鋼材が緊張された後に前記中央領域が後施工される請求項1〜3のいずれかに記載のPC地上タンクの施工方法。   A part of the bottom plate is preliminarily applied leaving the central region of the bottom plate in the first step, and the central region is post-constructed after at least the circumferential PC steel is tensioned in the second step. The construction method of the PC ground tank in any one of 1-3. 前記側板が内槽側板であり、前記第1のステップでは、該内槽側板の上に内槽屋根を設置し、かつ、PC壁の上に屋根開口を具備する外槽屋根を設置し、施工開口以外の領域のPC壁の内側の面に外槽ライナを配するものであり、
前記第2のステップでは、PC鋼材の緊張をおこなった後に閉塞された施工開口の領域のPC壁の内側の面に外槽ライナを配し、一部の領域の施工開口以外の領域に冷熱抵抗緩和材の一部を配すものであり、
前記保冷材は粒状パーライトからなり、前記第3のステップでは、閉塞された一部の領域の施工開口に対応する領域に冷熱抵抗緩和材の残部と外槽ライナの残部を配し、前記屋根開口を介して冷熱抵抗緩和材と内槽側板の間の空間および外槽屋根と内槽屋根の間の空間に粒状パーライトを充填する請求項1〜4のいずれかに記載のPC地上タンクの施工方法。
The side plate is an inner tank side plate, and in the first step, an inner tank roof is installed on the inner tank side plate, and an outer tank roof having a roof opening is installed on the PC wall. An outer tank liner is arranged on the inner surface of the PC wall in a region other than the opening,
In the second step, an outer tank liner is disposed on the inner surface of the PC wall in the area of the construction opening that is closed after the tension of the PC steel material, and the thermal resistance is applied to the area other than the construction opening in a part of the area. A part of the relaxation material is arranged,
The cold insulating material is made of granular pearlite, and in the third step, the remaining portion of the cooling resistance reducing material and the remaining portion of the outer tub liner are arranged in a region corresponding to the construction opening of a part of the closed region, and the roof opening The construction method of the PC ground tank in any one of Claims 1-4 which fills the space between a thermal-resistance resistance relaxation material and an inner tank side plate, and the space between an outer tank roof and an inner tank roof through this.
JP2011168330A 2011-08-01 2011-08-01 PC ground tank construction method Active JP4964346B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011168330A JP4964346B1 (en) 2011-08-01 2011-08-01 PC ground tank construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011168330A JP4964346B1 (en) 2011-08-01 2011-08-01 PC ground tank construction method

Publications (2)

Publication Number Publication Date
JP4964346B1 true JP4964346B1 (en) 2012-06-27
JP2013032170A JP2013032170A (en) 2013-02-14

Family

ID=46506082

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011168330A Active JP4964346B1 (en) 2011-08-01 2011-08-01 PC ground tank construction method

Country Status (1)

Country Link
JP (1) JP4964346B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115038651A (en) * 2020-02-20 2022-09-09 三菱造船株式会社 Liquefied gas tank and ship

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6225479B2 (en) 2013-05-20 2017-11-08 株式会社Ihi Storage tank construction method
JP6751001B2 (en) * 2016-10-17 2020-09-02 大成建設株式会社 Construction method of thermal resistance material for PC ground tank
JP7319980B2 (en) * 2017-12-19 2023-08-02 プリロード クライオジェニックス、エルエルシー Precast and prestressed concrete tanks with temporary openings

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6244240Y2 (en) * 1981-05-21 1987-11-19
JP2010106501A (en) * 2008-10-29 2010-05-13 Takenaka Komuten Co Ltd Construction method of low-temperature storage tank
JP2010275796A (en) * 2009-05-29 2010-12-09 Ihi Corp Method for manufacturing storage tank
JP2011084960A (en) * 2009-10-16 2011-04-28 Ihi Corp Storage tank
JP3171076U (en) * 2011-08-01 2011-10-13 大成建設株式会社 PC ground tank during construction and PC ground tank when completed

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6244240Y2 (en) * 1981-05-21 1987-11-19
JP2010106501A (en) * 2008-10-29 2010-05-13 Takenaka Komuten Co Ltd Construction method of low-temperature storage tank
JP2010275796A (en) * 2009-05-29 2010-12-09 Ihi Corp Method for manufacturing storage tank
JP2011084960A (en) * 2009-10-16 2011-04-28 Ihi Corp Storage tank
JP3171076U (en) * 2011-08-01 2011-10-13 大成建設株式会社 PC ground tank during construction and PC ground tank when completed

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115038651A (en) * 2020-02-20 2022-09-09 三菱造船株式会社 Liquefied gas tank and ship
CN115038651B (en) * 2020-02-20 2024-01-05 三菱造船株式会社 Liquefied gas tank and ship

Also Published As

Publication number Publication date
JP2013032170A (en) 2013-02-14

Similar Documents

Publication Publication Date Title
JP4964346B1 (en) PC ground tank construction method
KR101221970B1 (en) Construction Method for Basement Structure without Temporary Structure
JP5348559B2 (en) Above-ground cryogenic tank and its construction method
KR102588684B1 (en) Method for constructing basement vertical member of top-down method constructed alternately
KR101165575B1 (en) Tunnel construction method
JP5937488B2 (en) Temporary support method for foundation
JP6755655B2 (en) Seismic reinforcement method for existing tubular walls made of reinforced concrete
JP3171076U (en) PC ground tank during construction and PC ground tank when completed
JP2000352296A (en) Method o constructing passage just under underground structure
JP5954835B2 (en) Retaining wall structure and retaining wall construction method
KR101105883B1 (en) Basic mat constructing method of high rise concrete structure
KR20110052360A (en) Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab
KR101534641B1 (en) The method for constructing the basement
JP6228836B2 (en) Reverse winding method
JP2004197373A (en) Earthquake resistant reinforcement method of existing concrete container structure and earthquake resistant reinforcement structure
KR100757710B1 (en) Dowel bar construction method for downward construction of underground structures
KR100973503B1 (en) Vertical RC structure construction method using prefabricated steel bar multi story unit
JP2016199957A (en) Floor preceding method
JP6710064B2 (en) Seismic isolation retrofit construction method and building construction
JP2010168806A (en) Method of constructing sidewall of underground tank structure
CN104631878B (en) Construction method of aluminum industry casting motor-pumped well
JP2005299387A (en) Construction method of foundation
KR200293048Y1 (en) shoring structure using prestressed retaining wall
JP6682173B1 (en) How to build a building
JP2019148108A (en) Bridge pier construction method

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120313

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120327

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4964346

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20180406

Year of fee payment: 6

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313114

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R371 Transfer withdrawn

Free format text: JAPANESE INTERMEDIATE CODE: R371

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250