JP4436536B2 - Building foundations and foundation units - Google Patents

Building foundations and foundation units Download PDF

Info

Publication number
JP4436536B2
JP4436536B2 JP2000138139A JP2000138139A JP4436536B2 JP 4436536 B2 JP4436536 B2 JP 4436536B2 JP 2000138139 A JP2000138139 A JP 2000138139A JP 2000138139 A JP2000138139 A JP 2000138139A JP 4436536 B2 JP4436536 B2 JP 4436536B2
Authority
JP
Japan
Prior art keywords
foundation
slab
steel
slabs
precast concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000138139A
Other languages
Japanese (ja)
Other versions
JP2001317067A (en
Inventor
康夫 河田
一晃 山内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2000138139A priority Critical patent/JP4436536B2/en
Publication of JP2001317067A publication Critical patent/JP2001317067A/en
Application granted granted Critical
Publication of JP4436536B2 publication Critical patent/JP4436536B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、例えば鉄骨造の簡易建物に好適な建築物の基礎と、その構築に使用する基礎ユニットに関する。
【0002】
【従来の技術】
プレキャストコンクリート製の基礎ユニットを使用して布基礎を構築することは、既に知られており、特許第2785063号によっても提案されている。これらは、基礎コンクリートを現場打ちする場合に比べると、現場作業を省力化できるとはいえ、何れも、個々の基礎ユニットを接合する際、基礎ユニット相互の力の伝達を前提としているため、力の伝達機構を成立させるための接合部の施工に手間がかかり、このことが工期短縮を妨げる要因となっている。
【0003】
また、プレキャストコンクリート製基礎ユニットにおけるベース部および立上り部の接合部にコンクリートを現場打ちしたり、特許第2785063号に記載されているように
、グラウト材を充填することは、力の伝達機構を成立させる上で有効であるが、基礎ユニット同士が固結物によって一体化されるため、解体撤去や再利用が困難である。
【0004】
尚、特開平9−60005号公報には、プレキャストコンクリート製の基礎ベースの上に鉄骨製の基礎梁をボルト連結して成る建築物の基礎が開示されているが、この基礎は、基礎ベースを現場打ちコンクリートによって形成することが他の実施例として記載されているところからみて、明らかに布基礎である。従って、プレキャストコンクリート製の基礎ベース同士の接合は、上述した特許第2785063号等の従来例と同じく、力の伝達を前提としており、力の伝達機構を成立させるための接合部の施工に手間がかかり且つ解体撤去や再利用が困難である点では、大同小異である。
【0005】
【発明が解決しようとする課題】
本発明は、上記の点に留意してなされたものであって、その目的とするところは、工期短縮が可能であり、しかも、解体撤去や再利用が容易な建築物の基礎と、その構築に好適な基礎ユニットを提供することにある。
【0006】
【課題を解決するための手段】
上記の課題を解決するために、本発明が講じた技術的手段は、次のとおりである。即ち、請求項1に記載の発明による建築物の基礎は、独立基礎として設計されたプレキャストコンクリート製の基礎スラブを互いに連結することなく敷き並べ、基礎スラブの上にボルト連結された鉄骨製の基礎梁により基礎相互間の力の伝達を行うように構成した建築物の基礎であって、プレキャストコンクリート製の基礎スラブの上に、当該基礎スラブに対応する長さに設定され、両端にボルト孔が形成された鉄骨製の基礎梁を、両端が基礎スラブの両端と一致した状態にボルト連結して構成された基礎ユニットを敷き並べ、基礎梁同士をボルト連結して構成したことを特徴としている。
【0007】
上記の基礎は、プレキャストコンクリート製の基礎スラブの上に、当該基礎スラブに対応する長さに設定され、両端にボルト孔が形成された鉄骨製の基礎梁を、両端が基礎スラブの両端と一致した状態にボルト連結して構成された基礎ユニットを用いて構成されるものであり、しかも、布基礎ではなく、言わば連続した独立基礎として設計を行い、基礎スラブ相互間の力の伝達は考慮せず、基礎相互間の力の伝達は基礎スラブ上に設置した鉄骨製の基礎梁で行うもので、基礎スラブと基礎梁の役割を各々に分割したことにより、基礎スラブ相互間は、力の伝達機構を考慮しないで済み、連結の必要がないため、工期の短縮が可能である。
【0008】
また、基礎スラブ相互が現場打ちコンクリートやグラウト材で連結されていないため、はつり作業が不要で、解体撤去や再利用が容易である。殊に、鉄骨製の基礎梁が基礎スラブの上にボルト連結されているので、基礎梁と基礎スラブを分離することができ、再利用に備えてストックしておくことが容易である。
【0009】
また、請求項2に記載の発明では、隣り合う基礎スラブ同士の端部に互いに嵌合する凹凸部が形成されているので、地面に基礎スラブを設置する際、凹凸部の嵌合により基礎スラブ同士が位置決めされることになり、施工が容易である。
【0010】
【0011】
請求項に記載の発明による基礎ユニットは、独立基礎として設計されたプレキャストコンクリート製の基礎スラブの上に、当該基礎スラブに対応する長さに設定され、両端にボルト孔が形成された鉄骨製の基礎梁を、両端が基礎スラブの両端と一致した状態にボルト連結して成る基礎ユニットであって、前記基礎スラブの一端に嵌合用の凸部が形成され、他端に前記凸部に対応する凹部が形成され、下面に複数の突起部が形成されていること
を特徴としている。この基礎ユニットを使用することによって、工期の短縮が可能であるばかりでなく、上述した建築物の基礎を容易に構築できる。即ち、基礎スラブの下面に複数の突起部が形成されているので、基礎ユニットを地面に設置する際、地面に多少の凹凸があっても、突起部をめり込ませることによって、容易に水平に且つレベルを揃えて設置することができ、しかも、隣り合う基礎スラブの凸部と凹部を互いに嵌合させることによって基礎ユニット同士が位置決めされるため、水糸を張らなくても、基礎ユニットを一直線に敷き並べることが可能であり、基礎スラブ上に設置されている鉄骨製の基礎梁同士を容易にボルト連結することができ、これらの結果として、上述した建築物の基礎を容易に構築できるのである。また、鉄骨製の基礎梁は、基礎スラブの上にボルト連結されているため、基礎梁と基礎スラブを分離することが可能であり、基礎スラブ同士を積み重ね、且つ、基礎梁同士を一纏めにして、コンパクトな状態で保管することができ、再利用に備えてストックしておくことが容易である。
【0012】
【発明の実施の形態】
図1〜図4は、例えば建築現場の作業事務所のように、解体撤去が予定されている鉄骨造の二階建て程度の簡易建物に好適な建築物の基礎を例示する。上記の基礎は、後述する基礎ユニット1A,1Bを用いて構築されたものであって、独立基礎として設計されたプレキャストコンクリート製の基礎スラブ2を互いに連結することなく敷き並べ、基礎スラブ2の上にボルト連結された鉄骨製の基礎梁3により基礎相互間の力の伝達を行うように構成したものである。GLは、基礎の構築完了後、基礎下部を所定レベルまで土砂で埋め戻した設計上のグランドラインである。
【0013】
図5と図6は、基礎直線部に用いられる基礎ユニット1Aを示し、図7と図8は、基礎コーナー部に用いられる基礎ユニット1Bを示す。これらの基礎ユニット1A,1Bは、独立基礎として設計された平板状をなすプレキャストコンクリート製の基礎スラブ2の上に、当該基礎スラブ2に対応する長さに設定され、両端にボルト孔4が形成された鉄骨製の基礎梁3を、図示の通り、両端が基礎スラブ2の両端と一致した状態にボルト5で連結して構成したものであって、前記基礎スラブ2の一端に嵌合用の凸部6が形成され、他端に前記凸部6に対応する凹部7が形成され、下面には複数(図示の例では、4個)の突起部8が形成されている。
【0014】
図示の凸部6は、上面が基礎スラブ2上面と面一で、両側面の間隔が先端側程狭まり、下面が先端側程上方に位置するように傾斜して、先尖りのテーパ状に形成されており、凹部7はこれと嵌合する形状に形成されている。図3、図4、図9、図10に示す9は、基礎スラブ2のコンクリートに埋設された補強鉄筋、10は、ボルト5と螺合する雌ネジ状のインサート金物である。図2、図3に示す11は、基礎梁3同士を連結するボルト、12は基礎梁3のウエブを挟持する当て板である。図2、図5、図7に示す13は、基礎梁3の上フランジ部に形成された柱鉄骨連結用のボルト孔である。
【0015】
尚、基礎直線部に用いられる基礎ユニット1Aと、基礎コーナー部に用いられる基礎ユニット1Bとは、前者1Aが基礎スラブ2、基礎梁3とも直線的な形状であるのに対し、後者1Bでは、基礎スラブ2および基礎梁3が直角に折れ曲がった形状である点でのみ相違し、他の構成は同じである。前記基礎梁3として、図示の例では、断面コ字状の型鋼を用いているが、I型鋼やH型鋼等を用いてもよい。また、基礎ユニット1A,1Bの寸法は、任意に設定できるが、図示の例では、両基礎ユニット1A,1Bとも、基礎スラブ2の厚さが20cm、短辺が60cmに設定されており、基礎ユニット1Aにおける基礎スラブ2の長辺は約1.8mに設定され、基礎ユニット1Bにおける基礎スラブ2の出隅から短辺までの長さは、基礎梁3上に立設される鉄骨柱のピッチが一定となる寸法に設定されている。
【0016】
上記の構成によれば、布基礎ではなく、言わば連続した独立基礎として設計を行い、基礎スラブ2相互間の力の伝達は考慮せず、基礎相互間の力の伝達は基礎スラブ2上に設置した鉄骨製の基礎梁3で行うもので、基礎スラブ2と基礎梁3の役割を各々に分割したことにより、基礎スラブ2相互間は、力の伝達機構を考慮しないで済み、連結の必要がないため、工期の短縮が可能である。
【0017】
殊に、基礎スラブ2の下面に複数の突起部8が形成されているので、基礎ユニット1A,1Bを地面に設置する際、地面に多少の凹凸があっても、突起部8をめり込ませることによって、容易に水平に且つレベルを揃えて設置することができ、しかも、隣り合う基礎スラブ2の凸部6と凹部7を互いに嵌合させることによって基礎ユニット1A,1B同士が水平方向および鉛直方向に位置決めされるため、水糸を張らなくても、基礎ユニット1A,1Bを一直線に敷き並べることが可能であり、基礎スラブ2上に設置されている鉄骨製の基礎梁3同士を容易にボルト11連結することができ、これらの結果として、上述した建築物の基礎を容易且つ短期間に構築できるのである。
【0018】
また、基礎スラブ2相互が現場打ちコンクリートやグラウト材で連結されていないため、はつり作業が不要で、解体撤去や再利用が容易である。しかも、鉄骨製の基礎梁3は、基礎スラブ2の上にボルト5連結されているため、基礎梁3と基礎スラブ2を分離することが可能であり、基礎スラブ2同士を積み重ね、且つ、基礎梁3同士を一纏めにして、コンパクトな状態で保管することができ、再利用に備えてストックしておくことが容易である。
【0019】
上記の例では、基礎スラブ2のコンクリートにインサート金物を埋設し、これにボルトをねじ込むようにしたが、図11に示すように、基礎スラブ2のコンクリートにボルト5をその上端側が突出した状態に埋設してもよい。この場合、ボルト5の突出長さを突起部8の高さ以下に設定しておけば、ボルト5が障害物にならないので、図示の通り、基礎スラブ2同士を積み重ねることができる
【0020】
【発明の効果】
本発明は、上述した構成よりなり、工期短縮が可能であり、解体撤去や再利用が容易である等の効果がある。
【図面の簡単な説明】
【図1】 建築物の基礎の斜視図である。
【図2】 要部の斜視図である。
【図3】 施工が完了した基礎の縦断側面図である。
【図4】 要部の縦断正面図である。
【図5】 基礎直線部に用いる基礎ユニットの分解斜視図である。
【図6】 基礎直線部に用いる基礎ユニットの側面図である。
【図7】 基礎コーナー部に用いる基礎ユニットの分解斜視図である。
【図8】 基礎コーナー部に用いる基礎ユニットの側面図である。
【図9】 基礎直線部に用いる基礎ユニットにおけるプレキャストコンクリート製基礎スラブの一部破断平面図である。
【図10】 基礎コーナー部に用いる基礎ユニットにおけるプレキャストコンクリート製基礎スラブの一部破断平面図である。
【図11】 他の実施の形態を説明する側面図である。
【符号の説明】
1A,1B…基礎ユニット、2…プレキャストコンクリート製の基礎スラブ、3…鉄骨製の基礎梁。
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a building foundation suitable for, for example, a steel structure simple building and a foundation unit used for the construction.
[0002]
[Prior art]
The construction of a fabric foundation using a foundation unit made of precast concrete is already known and has also been proposed by patent 2785063. Although these can save on-site work compared to the case where foundation concrete is cast on-site, each of them is based on the premise of transmission of force between the foundation units when joining individual foundation units. The construction of the joint for establishing the transmission mechanism is troublesome, and this is a factor that hinders the shortening of the construction period.
[0003]
In addition, concrete is cast on the joint between the base part and the rising part of the precast concrete foundation unit or filled with grout material as described in Japanese Patent No. 2785063, which establishes a force transmission mechanism. Although it is effective in making it possible to disassemble and recycle the basic units, they are difficult to dismantle and reuse.
[0004]
Japanese Laid-Open Patent Publication No. 9-60005 discloses a foundation of a building in which a steel foundation beam is bolted on a foundation base made of precast concrete. Forming with cast-in-place concrete is clearly a fabric foundation in view of what is described as another example. Therefore, the joint between the foundation bases made of precast concrete is premised on the transmission of force, as in the conventional example such as the above-mentioned Japanese Patent No. 2785063, and it takes time to construct the joint for establishing the force transmission mechanism. It is a big difference in that it is expensive and difficult to dismantle and reuse.
[0005]
[Problems to be solved by the invention]
The present invention has been made in consideration of the above points, and the purpose of the present invention is to shorten the construction period, and to construct and construct a building foundation that can be easily dismantled and reused. It is to provide a suitable basic unit.
[0006]
[Means for Solving the Problems]
In order to solve the above problems, the technical means taken by the present invention are as follows. That is, the foundation of the building according to the first aspect of the present invention is a steel foundation in which precast concrete foundation slabs designed as independent foundations are arranged without being connected to each other and bolted on the foundation slab. It is a foundation of a building configured to transmit force between foundations by beams, and is set on a foundation slab made of precast concrete to a length corresponding to the foundation slab, with bolt holes at both ends. It is characterized in that the formed steel foundation beams are arranged by laying foundation units constructed by bolt connection in a state where both ends coincide with both ends of the foundation slab, and the foundation beams are bolted together .
[0007]
The above foundation is a precast concrete foundation slab, set to a length corresponding to the foundation slab, and a steel foundation beam with bolt holes formed at both ends. Both ends coincide with both ends of the foundation slab. It is constructed using a foundation unit constructed by connecting bolts in a fixed state, and it is designed as a continuous independent foundation, not a cloth foundation , and considers the transmission of force between foundation slabs. First, the transmission of force between the foundations is performed by steel foundation beams installed on the foundation slabs. By dividing the roles of the foundation slabs and foundation beams into each other, force transmission between the foundation slabs is performed. It is not necessary to consider the mechanism and there is no need for connection, so the construction period can be shortened.
[0008]
In addition, since the foundation slabs are not connected to each other by cast-in-place concrete or grout material, no lifting work is required, and dismantling and reuse are easy. In particular, since the steel foundation beam is bolted on the foundation slab, the foundation beam and the foundation slab can be separated and easily stocked for reuse.
[0009]
Moreover, in the invention of Claim 2, since the uneven | corrugated | grooved part which mutually fits in the edge part of adjacent foundation slabs is formed, when installing a foundation slab on the ground, the foundation slab by fitting of the uneven | corrugated | grooved part They will be positioned, and construction is easy.
[0010]
[0011]
The foundation unit according to the invention of claim 3 is made of a steel frame in which a length corresponding to the foundation slab is set on a foundation slab made of precast concrete designed as an independent foundation, and bolt holes are formed at both ends. Is a foundation unit that is bolted so that both ends coincide with both ends of the foundation slab, and a fitting projection is formed at one end of the foundation slab, and the other end corresponds to the projection. A concave portion is formed, and a plurality of protrusions are formed on the lower surface. By using this foundation unit, it is possible not only to shorten the construction period but also to easily construct the foundation of the building described above. That is, since a plurality of protrusions are formed on the bottom surface of the foundation slab, when the foundation unit is installed on the ground, even if there are some irregularities on the ground, it is easy to level the protrusion by inserting the protrusions. In addition, since the base units are positioned by fitting the convex portions and concave portions of the adjacent basic slabs to each other, the basic units can be installed without stretching the water thread. It can be laid out in a straight line, and steel foundation beams installed on the foundation slab can be easily bolted together. As a result, the foundation of the building described above can be easily constructed. It is. In addition, since the steel foundation beams are bolted on the foundation slabs, it is possible to separate the foundation beams and foundation slabs, stacking the foundation slabs together, and bringing the foundation beams together. It can be stored in a compact state and is easily stocked for reuse.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
1 to 4 exemplify the foundation of a building suitable for a simple structure of a steel-framed two-story structure that is scheduled to be dismantled and removed, for example, as a work office at a construction site. The above-mentioned foundation is constructed using foundation units 1A and 1B, which will be described later. The foundation slabs 2 made of precast concrete designed as independent foundations are laid out without being connected to each other. It is configured to transmit force between the foundations by a steel foundation beam 3 bolted to the foundation. GL is a design ground line in which the foundation lower part is backfilled with earth and sand to a predetermined level after the foundation construction is completed.
[0013]
5 and 6 show a basic unit 1A used for the basic straight portion, and FIGS. 7 and 8 show a basic unit 1B used for the basic corner portion. These foundation units 1A and 1B are set to a length corresponding to the foundation slab 2 on the flat slab 2 made of precast concrete designed as an independent foundation, and bolt holes 4 are formed at both ends. As shown in the figure, the steel base beam 3 made by connecting both ends of the steel base beam 3 with bolts 5 so as to coincide with both ends of the base slab 2, A portion 6 is formed, a concave portion 7 corresponding to the convex portion 6 is formed at the other end, and a plurality (four in the illustrated example) of protruding portions 8 are formed on the lower surface.
[0014]
The convex portion 6 shown in the figure is tapered so that the upper surface is flush with the upper surface of the basic slab 2, the distance between both side surfaces is narrower toward the tip side, and the lower surface is located higher toward the tip side. The recess 7 is formed in a shape that fits into the recess 7. 3, 4, 9, and 10 are reinforcing reinforcing bars embedded in the concrete of the foundation slab 2, and 10 is a female screw-like insert metal fitting with the bolt 5. 2 and 3, 11 is a bolt for connecting the foundation beams 3, and 12 is a contact plate for sandwiching the web of the foundation beams 3. Reference numeral 13 shown in FIGS. 2, 5, and 7 is a bolt hole for connecting a column steel frame formed in the upper flange portion of the foundation beam 3.
[0015]
In addition, the foundation unit 1A used for the foundation straight part and the foundation unit 1B used for the foundation corner part have the former 1A having a straight shape with both the foundation slab 2 and the foundation beam 3, whereas in the latter 1B, The difference is only in that the foundation slab 2 and the foundation beam 3 are bent at a right angle, and the other configurations are the same. In the example shown in the drawing, a steel plate having a U-shaped cross section is used as the foundation beam 3, but I-shaped steel, H-shaped steel, or the like may be used. The dimensions of the foundation units 1A and 1B can be arbitrarily set. In the example shown in the figure, both the foundation units 1A and 1B have a foundation slab 2 having a thickness of 20 cm and a short side of 60 cm. The long side of the foundation slab 2 in the unit 1A is set to about 1.8 m, and the length from the corner of the foundation slab 2 to the short side in the foundation unit 1B is the pitch of the steel column erected on the foundation beam 3 Is set to a constant dimension.
[0016]
According to the above configuration, it is designed not as a fabric foundation but as a continuous independent foundation, without considering the force transmission between the foundation slabs 2 and installing the force transmission between the foundations on the foundation slab 2 This is done with the steel foundation beam 3, and by dividing the roles of the foundation slab 2 and foundation beam 3 into each other, there is no need to consider the force transmission mechanism between the foundation slabs 2 and connection is necessary. Therefore, the construction period can be shortened.
[0017]
In particular, since a plurality of protrusions 8 are formed on the lower surface of the foundation slab 2, when the foundation units 1A and 1B are installed on the ground, the protrusions 8 are recessed even if there are some irregularities on the ground. Therefore, the base units 1A and 1B can be installed in the horizontal direction by fitting the convex portions 6 and the concave portions 7 of the adjacent basic slabs 2 to each other. Since it is positioned in the vertical direction, it is possible to lay the foundation units 1A and 1B in a straight line without stretching the water thread, and it is easy to connect the steel foundation beams 3 installed on the foundation slab 2 the bolt 11 can be coupled, as the results, it can be built between the easy and short the basis for building the above.
[0018]
In addition, since the foundation slabs 2 are not connected to each other by cast-in-place concrete or grout material, no lifting work is required, and dismantling and reuse are easy. Moreover, since the steel-made foundation beam 3 is connected to the foundation slab 2 by the bolt 5, the foundation beam 3 and the foundation slab 2 can be separated, and the foundation slabs 2 are stacked together, and the foundation The beams 3 can be gathered together and stored in a compact state, and can be easily stocked for reuse.
[0019]
In the above example, the insert metal is embedded in the concrete of the foundation slab 2 and the bolt is screwed into the concrete. However, as shown in FIG. 11, the bolt 5 is protruded from the concrete of the foundation slab 2 with its upper end side protruding. It may be buried. In this case, if the projecting length of the bolt 5 is set to be equal to or less than the height of the projecting portion 8, the bolt 5 does not become an obstacle, so that the basic slabs 2 can be stacked as illustrated .
[0020]
【The invention's effect】
The present invention has the above-described configuration, has an effect that the work period can be shortened, and dismantling and reuse are easy.
[Brief description of the drawings]
FIG. 1 is a perspective view of a foundation of a building.
FIG. 2 is a perspective view of a main part.
FIG. 3 is a longitudinal side view of a foundation on which construction has been completed.
FIG. 4 is a longitudinal front view of a main part.
FIG. 5 is an exploded perspective view of a foundation unit used for the foundation straight portion.
FIG. 6 is a side view of the foundation unit used for the foundation straight portion.
FIG. 7 is an exploded perspective view of a foundation unit used for a foundation corner portion.
FIG. 8 is a side view of a foundation unit used for a foundation corner portion.
FIG. 9 is a partially broken plan view of a precast concrete foundation slab in a foundation unit used for a foundation straight portion.
FIG. 10 is a partially broken plan view of a precast concrete foundation slab in a foundation unit used for a foundation corner.
FIG. 11 is a side view illustrating another embodiment.
[Explanation of symbols]
1A, 1B ... foundation unit, 2 ... foundation slab made of precast concrete, 3 ... foundation beam made of steel.

Claims (3)

独立基礎として設計されたプレキャストコンクリート製の基礎スラブを互いに連結することなく敷き並べ、基礎スラブの上にボルト連結された鉄骨製の基礎梁により基礎相互間の力の伝達を行うように構成した建築物の基礎であって、プレキャストコンクリート製の基礎スラブの上に、当該基礎スラブに対応する長さに設定され、両端にボルト孔が形成された鉄骨製の基礎梁を、両端が基礎スラブの両端と一致した状態にボルト連結して構成された基礎ユニットを敷き並べ、基礎梁同士をボルト連結して構成したことを特徴とする建築物の基礎。 Buildings constructed by laying precast concrete foundation slabs designed as independent foundations without connecting them to each other and transmitting the force between the foundations using steel foundation beams bolted onto the foundation slabs A steel foundation beam with a length corresponding to the foundation slab and a bolt hole formed at both ends on the foundation slab made of precast concrete on both sides of the foundation slab. The foundation of the building, which is constructed by laying foundation units constructed by bolting in a state consistent with the bolts, and bolting together the foundation beams . 隣り合う基礎スラブ同士の端部に互いに嵌合する凹凸部が形成されている請求項1に記載の建築物の基礎。  The foundation of a building according to claim 1, wherein uneven portions that are fitted to each other are formed at ends of adjacent foundation slabs. 独立基礎として設計されたプレキャストコンクリート製の基礎スラブの上に、当該基礎スラブに対応する長さに設定され、両端にボルト孔が形成された鉄骨製の基礎梁を、両端が基礎スラブの両端と一致した状態にボルト連結して成る基礎ユニットであって、前記基礎スラブの一端に嵌合用の凸部が形成され、他端に前記凸部に対応する凹部が形成され、下面に複数の突起部が形成されていることを特徴とする基礎ユニット On a foundation slab made of precast concrete designed as an independent foundation, a steel foundation beam set to a length corresponding to the foundation slab and having bolt holes formed at both ends is connected to both ends of the foundation slab. A base unit formed by bolt connection in a matched state, wherein a protrusion for fitting is formed at one end of the base slab, a recess corresponding to the protrusion is formed at the other end, and a plurality of protrusions on the lower surface A basic unit characterized in that is formed .
JP2000138139A 2000-05-11 2000-05-11 Building foundations and foundation units Expired - Fee Related JP4436536B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000138139A JP4436536B2 (en) 2000-05-11 2000-05-11 Building foundations and foundation units

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000138139A JP4436536B2 (en) 2000-05-11 2000-05-11 Building foundations and foundation units

Publications (2)

Publication Number Publication Date
JP2001317067A JP2001317067A (en) 2001-11-16
JP4436536B2 true JP4436536B2 (en) 2010-03-24

Family

ID=18645799

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000138139A Expired - Fee Related JP4436536B2 (en) 2000-05-11 2000-05-11 Building foundations and foundation units

Country Status (1)

Country Link
JP (1) JP4436536B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101317316B1 (en) * 2011-01-17 2013-10-14 신주영 Precast module footing and construction method therefwith
JP5964646B2 (en) * 2012-04-26 2016-08-03 住友林業株式会社 Building basic structure and its design program

Also Published As

Publication number Publication date
JP2001317067A (en) 2001-11-16

Similar Documents

Publication Publication Date Title
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
JP4436536B2 (en) Building foundations and foundation units
KR102118665B1 (en) Retaining wall and method for constructing the same
JP2000328586A (en) Retaining wall
JP3191951B2 (en) Foundation construction method
JP3643809B2 (en) Connection structure of precast concrete foundation blocks
JP2963613B2 (en) Foundation structure and construction method
JP2891931B2 (en) Formwork for building concrete structures
KR102479370B1 (en) Hybrid Composite Girder and Bridge Construction Method Using Thereof
JP2004084209A (en) Recyclable prefabricated continuous footing member and method of constructing foundation footing using it
JP2532797B2 (en) Support beam for foundation beams
JP5467935B2 (en) Mixed structure unit type building and construction method of mixed structure unit type building
KR20020025856A (en) Prevention of approach slab settlement by applying non-com paction abutment backfilling method
JP2512254B2 (en) Structure of artificial ground and structure of house
JP3143324B2 (en) Foundation structure and foundation construction method
JPS5914506Y2 (en) fence culvert
JP2915746B2 (en) Foundation formwork
JP3683419B2 (en) PC foundation beam member and concrete cloth foundation construction method
JP2880922B2 (en) Column members for underground structures
JP3108112B2 (en) Foundation structure
JP2877896B2 (en) Concrete basement basement
JPH0841899A (en) Construction method for foundation beam and pc plate for beam
JP2022190286A (en) Road structure and construction method of road structure
JPS6035638Y2 (en) panel foundation
KR200253362Y1 (en) Filling crushed stone type retainingwall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070329

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090807

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090901

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091030

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091222

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091228

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130108

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees