JP4036819B2 - Cogeneration system - Google Patents

Cogeneration system Download PDF

Info

Publication number
JP4036819B2
JP4036819B2 JP2003390364A JP2003390364A JP4036819B2 JP 4036819 B2 JP4036819 B2 JP 4036819B2 JP 2003390364 A JP2003390364 A JP 2003390364A JP 2003390364 A JP2003390364 A JP 2003390364A JP 4036819 B2 JP4036819 B2 JP 4036819B2
Authority
JP
Japan
Prior art keywords
heat
hot water
time
heating
load
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003390364A
Other languages
Japanese (ja)
Other versions
JP2004264010A (en
Inventor
義孝 栢原
伸 岩田
桂嗣 滝本
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Osaka Gas Co Ltd
Original Assignee
Osaka Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to JP2003054649A priority Critical patent/JP4036774B2/en
Application filed by Osaka Gas Co Ltd filed Critical Osaka Gas Co Ltd
Priority to JP2003390364A priority patent/JP4036819B2/en
Publication of JP2004264010A publication Critical patent/JP2004264010A/en
Application granted granted Critical
Publication of JP4036819B2 publication Critical patent/JP4036819B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/14Combined heat and power generation [CHP]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02TCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
    • Y02T10/00Road transport of goods or passengers
    • Y02T10/10Internal combustion engine [ICE] based vehicles
    • Y02T10/12Improving ICE efficiencies

Landscapes

  • Heat-Pump Type And Storage Water Heaters (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Steam Or Hot-Water Central Heating Systems (AREA)

Description

本発明は、電力と熱を発生する熱電併給装置と、熱媒循環路を通して熱媒を熱消費端末に循環供給させる熱媒循環手段と、前記熱電併給装置にて発生する熱にて貯湯タンク内の湯水および前記熱媒循環路を通流する熱媒を加熱する排熱式加熱手段と、前記貯湯タンク内に湯水が貯湯されていないときに湯水を加熱するおよび前記熱媒循環路を通流する熱媒を加熱する補助加熱手段と、運転を制御する運転制御手段とが設けられ、
前記運転制御手段は、時系列的な電力負荷、時系列的な給湯熱負荷、および、前記熱消費端末における時系列的な端末熱負荷を管理して、その管理している情報に基づいて、前記熱電併給装置の運転により省エネルギーを実現可能な運転用時間帯を設定し、その運転用時間帯に前記熱電併給装置を運転させるように構成されているコージェネレーションシステムに関する。
The present invention includes a combined heat and power supply device that generates electric power and heat, a heating medium circulating means for circulating and supplying a heating medium to a heat consuming terminal through a heating medium circulation path, and a heat storage tank with heat generated by the combined heat and power supply device. Waste heat heating means for heating the hot water and the heating medium flowing through the heating medium circulation path, heating the hot water when hot water is not stored in the hot water storage tank, and flowing through the heating medium circulation path Auxiliary heating means for heating the heating medium to be operated, and operation control means for controlling the operation are provided,
The operation control means manages a time-series power load, a time-series hot water supply heat load, and a time-series terminal heat load in the heat consuming terminal, and based on the managed information, The present invention relates to a cogeneration system configured to set an operation time zone in which energy saving can be realized by operation of the cogeneration device, and to operate the cogeneration device during the operation time zone.

上記のようなコージェネレーションシステムは、熱電併給装置が、ガスエンジンと発電機とを組み合わせたものや燃料電池などから構成され、熱電併給装置を運転させるとともに、排熱式加熱手段を作動させることにより、熱電併給装置にて発生する熱を利用して、貯湯タンク内への湯水の貯湯や、床暖房装置や浴室暖房装置などの熱消費端末への熱媒の供給を行い、補助加熱手段を作動させることにより、貯湯タンク内への湯水の貯湯や熱消費端末への熱媒の供給を行うようにしているものである。   In the cogeneration system as described above, the combined heat and power unit is composed of a combination of a gas engine and a generator, a fuel cell, etc., and operates the combined heat and power unit and operates the exhaust heat type heating means. Using the heat generated by the combined heat and power supply device, hot water is stored in the hot water storage tank, and heat medium is supplied to heat consuming terminals such as floor heating devices and bathroom heating devices, and auxiliary heating means are activated. By doing so, hot water is stored in the hot water storage tank and a heat medium is supplied to the heat consuming terminal.

そして、従来では、例えば、1日を設定周期として、その設定周期内での時系列的な電力負荷、時系列的な給湯熱負荷、および、時系列的な端末熱負荷を管理して、その管理している情報に基づいて、熱電併給装置の運転により省エネルギーを実現可能な運転用時間帯を設定し、その運転用時間帯に熱電併給装置を運転させるようにしている(例えば、特許文献1参照。)。   And, conventionally, for example, by setting a day as a set cycle, managing a time-series power load, a time-series hot water supply heat load, and a time-series terminal heat load within the set cycle, Based on the managed information, the operation time zone in which energy saving can be realized by the operation of the combined heat and power supply apparatus is set, and the combined heat and power supply apparatus is operated during the operation time period (for example, Patent Document 1). reference.).

特開2002−138902号公報JP 2002-138902 A

上記従来のコージェネレーションシステムでは、運転制御手段が、省エネルギーを実現可能であると設定した運転用時間帯に熱電併給装置を運転させるので、熱電併給装置を運転させる時間帯および運転させない時間帯が予測により設定されている。
しかしながら、実際に使用者が熱電併給装置を運転させたい時間帯および運転させたくない時間帯と、予測により設定された熱電併給装置を運転させる時間帯および運転させない時間帯とは必ずしも一致するものではなく、異なる場合もある。
そして、実際に使用者が熱電併給装置を運転させたい時間帯および運転させたくない時間帯と、予測により設定された熱電併給装置を運転させる時間帯および運転させない時間帯とが異なると、使用者の意図に沿った状態で熱電併給装置を運転できない虞があった。
In the above-mentioned conventional cogeneration system, the operation control means operates the cogeneration device during the operation time zone where energy saving can be realized, so the time zone during which the cogeneration device is operated and the time zone during which the cogeneration device is not operated are predicted. It is set by.
However, the time zone in which the user actually wants to operate the cogeneration device and the time zone in which the user does not want to operate the time zone in which the cogeneration device is set to operate and the time zone in which the cogeneration device is set to operate are not necessarily the same. There may be different.
If the time zone in which the user actually wants to operate the cogeneration device and the time zone in which the user does not want to operate and the time zone in which the cogeneration device set by prediction and the time zone in which the cogeneration device is not operated are different, the user There is a possibility that the combined heat and power unit cannot be operated in a state in line with the intention.

例えば、深夜には騒音の問題が生じるので、使用者は深夜に熱電併給装置を運転させたくなくても、深夜に給湯や暖房の使用があると、深夜にも運転用時間帯が設定され、深夜に熱電併給装置を運転させることがある。
また、使用者が旅行などにより不在中であっても、運転用時間帯が設定されると、給湯や暖房の予定がないにもかかわらず、熱電併給装置にて熱を発生することになり、熱電併給装置を無駄に運転させてしまうことになる。
さらに、給湯や暖房の使用形態は、設定期間としての1日内でいつも同じというわけでなく、給湯や暖房をいつもよりも早い時間帯に終了すると、給湯や暖房の1日の使用が終了したあとに、運転用時間帯が設定され、給湯や暖房の予定がないにもかかわらず、熱電併給装置にて熱を発生することになり、熱電併給装置を無駄に運転させてしまうことになる。
For example, noise problems occur at midnight, so even if the user does not want to operate the combined heat and power unit at midnight, if hot water or heating is used at midnight, the operating time zone is set at midnight, The cogeneration unit may be operated at midnight.
In addition, even if the user is absent due to travel, etc., if the operating time zone is set, heat will be generated in the combined heat and power unit even though there is no plan for hot water supply or heating, The cogeneration apparatus will be made uselessly operated.
Furthermore, the usage pattern of hot water supply and heating is not always the same within a day as a set period. In addition, although the operation time zone is set and there is no plan for hot water supply or heating, heat is generated in the combined heat and power supply device, and the combined heat and power supply device is operated wastefully.

本発明は、かかる点に着目してなされたものであり、その目的は、使用者の意図に沿った状態で熱電併給装置を運転させることができるコージェネレーションシステムを提供する点にある。   This invention is made paying attention to this point, and the objective is to provide the cogeneration system which can drive a cogeneration apparatus in the state according to a user's intention.

本発明にかかるコージェネレーションシステムの第1特徴構成は、電力と熱を発生する熱電併給装置と、熱媒循環路を通して熱媒を熱消費端末に循環供給させる熱媒循環手段と、前記熱電併給装置にて発生する熱にて貯湯タンク内の湯水および前記熱媒循環路を通流する熱媒を加熱する排熱式加熱手段と、前記貯湯タンク内に湯水が貯湯されていないときに湯水を加熱するおよび前記熱媒循環路を通流する熱媒を加熱する補助加熱手段と、運転を制御する運転制御手段とが設けられ、
前記運転制御手段は、時系列的な電力負荷、時系列的な給湯熱負荷、および、前記熱消費端末における時系列的な端末熱負荷を管理して、その管理している情報に基づいて、前記熱電併給装置の運転により省エネルギーを実現可能な運転用時間帯を設定し、その運転用時間帯に前記熱電併給装置を運転させるように構成されているコージェネレーションシステムにおいて、
設定期間内での運転終了を指令する運転終了指令手段が設けられ、
前記運転制御手段は、
前記設定期間内で前記運転用時間帯を設定するように構成され、かつ、前記運転終了指令手段にて運転終了が指令された場合には、前記運転用時間帯であっても、前記熱電併給装置の運転を停止させ、前記運転終了指令手段にて運転終了が指令されていない場合には、前記運転用時間帯に熱電併給装置を運転させるように構成され、さらに、
前記運転終了指令手段にて運転終了が指令された場合には、その指令から設定時間が経過する又は前記設定期間が終了すると、前記運転用時間帯に熱電併給装置を運転するように自動的に復帰するように構成されている点にある。
The first characteristic configuration of the cogeneration system according to the present invention is a combined heat and power supply device that generates electric power and heat, a heat medium circulation means that circulates and supplies a heat medium to a heat consuming terminal through a heat medium circulation path, and the heat and power supply device. Exhaust heat heating means for heating the hot water in the hot water storage tank and the heat medium flowing through the heating medium circulation path with the heat generated in, and heating the hot water when hot water is not stored in the hot water storage tank And an auxiliary heating means for heating the heat medium flowing through the heat medium circulation path, and an operation control means for controlling the operation,
The operation control means manages a time-series power load, a time-series hot water supply heat load, and a time-series terminal heat load in the heat consuming terminal, and based on the managed information, In a cogeneration system configured to set an operation time zone capable of realizing energy saving by operation of the cogeneration device, and to operate the cogeneration device in the operation time zone,
An operation end command means for commanding the end of operation within the set period is provided,
The operation control means includes
The operation time zone is set within the set period, and when the operation end command is instructed by the operation end command means, the combined heat and power supply even in the operation time zone The operation of the apparatus is stopped, and when the operation end commanding means is not instructed to end the operation, it is configured to operate the cogeneration device during the operation time zone, and
When the end of operation is commanded by the operation end command means, when the set time elapses from the command or when the set period ends, the combined heat and power supply device is automatically operated during the operation time zone. The point is that it is configured to return .

すなわち、例えば、設定期間を1日とすると、使用者は、電力、給湯、暖房の1日の使用が終了したことを運転終了指令手段にて指令できることになり、その使用者による設定によって、設定期間内では、今後、電力、給湯、暖房の使用の予定がないことを指令できることになる。
そして、運転制御手段は、運転終了指令手段にて運転終了が指令された場合には、運転用時間帯であっても、熱電併給装置の運転を停止させるので、今後、電力、給湯、暖房を使用する予定がない場合には、熱電併給装置の運転を停止させて、無駄に熱電併給装置を運転させることを阻止できることになる。
That is, for example, if the setting period is one day, the user can instruct the operation end command means that the use of power, hot water supply, and heating has been completed for one day. Within the period, it can be commanded that there is no plan to use electric power, hot water supply, or heating in the future.
When the operation end command is given by the operation end command means, the operation control means stops the operation of the cogeneration device even in the operation time zone. When there is no plan to use it, it is possible to stop the operation of the cogeneration apparatus by stopping the operation of the cogeneration apparatus.

また、運転制御手段は、運転終了指令手段にて運転終了が指令された場合には、その指令から設定時間が経過したのちや設定期間が終了することによって、運転終了の指令を自動的に解除するように構成することによって、運転終了指令手段にて運転終了が指令されたあとでも、自動的に運転用時間帯に熱電併給装置を運転させるように復帰させることができることになる。   In addition, the operation control means automatically cancels the operation end command after the set time has elapsed from the command or when the set period ends when the operation end command means instructs the operation end. With this configuration, even after the operation end command is issued by the operation end command means, it is possible to automatically return the cogeneration apparatus to operate in the operation time zone.

したがって、設定期間内での電力、給湯、暖房の使用が終了したことにより、設定期間内で電力、給湯、暖房を使用する予定がない場合には、熱電併給装置の運転を停止させることができることとなって、使用者の意図に沿った状態で熱電併給装置を運転させることができるコージェネレーションシステムを提供できるに至った。   Therefore, the operation of the combined heat and power supply device can be stopped when there is no plan to use electric power, hot water supply, or heating within the set period due to the end of use of electric power, hot water supply, or heating within the set period. As a result, it has become possible to provide a cogeneration system capable of operating the combined heat and power supply device in a state in line with the user's intention.

本発明にかかるコージェネレーションシステムについて図面に基づいて説明する。
〔第1実施形態〕
このコージェネレーションシステムは、図1および図2に示すように、ガスエンジン1によって発電装置2を駆動するように構成された熱電併給装置3と、その熱電併給装置3にて発生する熱を利用しながら、貯湯タンク4への貯湯および熱消費端末5への熱媒供給を行う貯湯ユニット6と、熱電併給装置3および貯湯ユニット6の運転を制御する運転制御手段としての運転制御部7などから構成されている。
A cogeneration system according to the present invention will be described with reference to the drawings.
[First Embodiment]
As shown in FIGS. 1 and 2, this cogeneration system uses a combined heat and power supply device 3 configured to drive a power generation device 2 by a gas engine 1 and heat generated in the combined heat and power supply device 3. However, it comprises a hot water storage unit 6 for storing hot water in the hot water storage tank 4 and supplying a heat medium to the heat consuming terminal 5, an operation control unit 7 as operation control means for controlling the operation of the combined heat and power unit 3 and the hot water storage unit 6, and the like. Has been.

前記熱電併給装置3は、定格出力にて電力と熱を発生するように構成され、発電装置2の出力側には、系統連係用のインバータ8が設けられ、そのインバータ8は、発電装置2の出力電力を商用系統9から供給される電力と同じ電圧および同じ周波数にするように構成されている。
前記商用系統9は、例えば、単相3線式100/200Vであり、商業用電力供給ライン10を介して、テレビ、冷蔵庫、洗濯機などの電力負荷11に電気的に接続されている。
また、インバータ8は、コージェネ用供給ライン12を介して商業用電力供給ライン10に電気的に接続され、発電装置2からの発電電力がインバータ8およびコージェネ用供給ライン12を介して電力負荷11に供給するように構成されている。
The cogeneration device 3 is configured to generate electric power and heat at a rated output, and an inverter 8 for system linkage is provided on the output side of the power generation device 2, and the inverter 8 is connected to the power generation device 2. The output power is configured to have the same voltage and the same frequency as the power supplied from the commercial system 9.
The commercial system 9 is, for example, a single-phase three-wire system 100/200 V, and is electrically connected to a power load 11 such as a television, a refrigerator, or a washing machine via a commercial power supply line 10.
The inverter 8 is electrically connected to the commercial power supply line 10 via the cogeneration supply line 12, and the generated power from the power generator 2 is supplied to the power load 11 via the inverter 8 and the cogeneration supply line 12. It is configured to supply.

前記商業用電力供給ライン10には、商用系統9からの電力を計測する電力負荷計測手段13が設けられ、運転制御部7は、電力負荷計測手段13による計測値とインバータ8の出力から電力負荷11の負荷電力を計測するように構成されている。
また、運転制御部7は、商業用電力供給ライン10を通して流れる電流に逆潮流が発生するか否かをも検出するように構成されている。
The commercial power supply line 10 is provided with power load measuring means 13 for measuring the power from the commercial system 9, and the operation control unit 7 determines the power load from the measured value by the power load measuring means 13 and the output of the inverter 8. 11 load power is measured.
The operation control unit 7 is also configured to detect whether or not a reverse power flow occurs in the current flowing through the commercial power supply line 10.

電気ヒータ14は、複数の電気ヒータから構成され、冷却水循環ポンプ17の作動により冷却水循環路15を通流するガスエンジン1の冷却水を加熱するように設けられ、インバータ8の出力側に接続された作動スイッチ16によりON/OFFが切り換えられている。
また、作動スイッチ16は、余剰電力の大きさが大きくなるほど、電気ヒータ14の消費電力が大きくなるように、余剰電力の大きさに応じて電気ヒータ14の消費電力を調整するように構成されている。
The electric heater 14 is composed of a plurality of electric heaters, and is provided so as to heat the cooling water of the gas engine 1 flowing through the cooling water circulation path 15 by the operation of the cooling water circulation pump 17, and is connected to the output side of the inverter 8. The operation switch 16 is turned on and off.
The operation switch 16 is configured to adjust the power consumption of the electric heater 14 according to the amount of surplus power so that the power consumption of the electric heater 14 increases as the amount of surplus power increases. Yes.

前記貯湯ユニット6は、温度成層を形成する状態で湯水を貯湯する貯湯タンク4、湯水循環路18を通して貯湯タンク4内の湯水などを循環させる湯水循環ポンプ19、熱媒循環路20を通して熱媒を熱消費端末5に循環供給させる熱媒循環手段としての熱媒循環ポンプ21、湯水循環路18を通流する湯水を加熱させる排熱式熱交換器22、熱媒循環路20を通流する熱媒を加熱させる熱媒加熱用熱交換器23、ファン24を作動させた状態でのバーナ25の燃焼により湯水循環路18を通流する湯水を加熱させる補助加熱用熱交換器26などを備えて構成されている。   The hot water storage unit 6 has a hot water storage tank 4 for storing hot water in a state where temperature stratification is formed, a hot water circulation pump 19 for circulating hot water in the hot water storage tank 4 through the hot water circulation path 18, and a heat medium circulation path 20 through the heat medium circulation path 20. Heat medium circulating pump 21 serving as a heat medium circulating means for circulating supply to the heat consuming terminal 5, exhaust heat heat exchanger 22 for heating hot water flowing through the hot water circulation path 18, and heat flowing through the heat medium circulation path 20 A heat exchanger 23 for heating the medium, and a heat exchanger 26 for auxiliary heating for heating the hot water flowing through the hot water circulation path 18 by the combustion of the burner 25 in a state where the fan 24 is operated. It is configured.

前記排熱式熱交換器22においては、熱電併給装置3にて発生する熱を回収した冷却水循環路15の冷却水を通流させることにより、湯水循環路18を通流する湯水を加熱させるように構成されている。
そして、排熱式加熱手段Nが、排熱式熱交換器22により構成され、補助加熱手段Mが、ファン24、バーナ25、補助加熱用熱交換器26により構成されている。
ちなみに、補助加熱手段Mは、バーナ25の燃焼量を調整することにより、湯水の温度が貯湯設定温度や熱媒加熱用熱交換器23に供給するための熱媒加熱用設定温度になるように加熱させるように構成されている。
In the exhaust heat heat exchanger 22, the hot water flowing through the hot water circulation path 18 is heated by passing the cooling water of the cooling water circulation path 15 that has recovered the heat generated in the combined heat and power supply device 3. It is configured.
The exhaust heat type heating means N is constituted by the exhaust heat type heat exchanger 22, and the auxiliary heating means M is constituted by the fan 24, the burner 25, and the auxiliary heating heat exchanger 26.
Incidentally, the auxiliary heating means M adjusts the combustion amount of the burner 25 so that the temperature of the hot water becomes the set temperature for heating medium heating to be supplied to the stored hot water temperature or the heat exchanger 23 for heating the heating medium. It is configured to be heated.

前記熱媒加熱用熱交換器23においては、排熱式熱交換器22や補助加熱用熱交換器26にて加熱された熱源用湯水を通流させることにより、熱媒循環路20を通流する熱媒を加熱させるように構成されている。
前記熱消費端末5は、床暖房装置や浴室暖房装置などの暖房端末にて構成されている。
In the heat exchanger for heat medium heating 23, the hot water for the heat source heated by the exhaust heat heat exchanger 22 or the auxiliary heat exchanger 26 is allowed to flow, thereby allowing the heat medium circulation path 20 to flow. The heating medium is configured to be heated.
The said heat consumption terminal 5 is comprised by heating terminals, such as a floor heating apparatus and a bathroom heating apparatus.

前記湯水循環路18には、貯湯タンク4の下部と連通する取り出し路27と貯湯タンク4の上部と連通する貯湯路28が接続され、貯湯路28には、貯湯弁29が設けられている。
そして、湯水循環路18には、取り出し路27との接続箇所から湯水の循環方向の順に、排熱式熱交換器22、湯水循環ポンプ19、補助加熱用熱交換器26、湯水の通流を断続する断続弁30、熱媒加熱用熱交換器23が設けられている。
The hot water circulation path 18 is connected to a take-out path 27 communicating with the lower part of the hot water storage tank 4 and a hot water storage path 28 communicating with the upper part of the hot water storage tank 4, and a hot water storage valve 29 is provided in the hot water storage path 28.
The hot water circulation path 18 is connected with the exhaust heat heat exchanger 22, the hot water circulation pump 19, the auxiliary heating heat exchanger 26, and the hot water flow in the order of the hot water circulation direction from the connection point with the extraction path 27. An intermittent valve 30 for intermittent connection and a heat exchanger for heat medium heating 23 are provided.

また、貯湯タンク4から取り出した湯水を給湯するときの給湯熱負荷を計測する給湯負荷計測手段31が設けられ、熱消費端末5での端末熱負荷を計測する端末熱負荷計測手段32も設けられている。   Further, a hot water supply load measuring means 31 for measuring the hot water supply heat load when hot water taken out from the hot water storage tank 4 is supplied, and a terminal thermal load measuring means 32 for measuring the terminal heat load at the heat consuming terminal 5 are also provided. ing.

前記運転制御部7に各種の指令を与えるリモコンRが設けられ、そのリモコンRには、自動運転を行う自動運転モードと手動運転を行う手動運転モードとを選択するモード選択スイッチ33、手動運転モードにおいて、熱電併給装置3の運転の開始および停止を指令する発電スイッチ34などが設けられている。
ちなみに、リモコンRにおけるモード選択スイッチ33、発電スイッチ34は、照光式のスイッチであり、使用者は、点灯か消灯かによって、現在の状態を認識できるように構成されている。
A remote controller R for giving various commands to the operation control unit 7 is provided. The remote controller R includes a mode selection switch 33 for selecting an automatic operation mode for performing an automatic operation and a manual operation mode for performing a manual operation, and a manual operation mode. , A power generation switch 34 for instructing start and stop of the operation of the combined heat and power supply device 3 is provided.
Incidentally, the mode selection switch 33 and the power generation switch 34 in the remote controller R are illuminated switches, and are configured so that the user can recognize the current state depending on whether it is turned on or off.

そして、リモコンRは、熱電併給装置3の運転を禁止させる禁止時間帯を設定可能に構成され、発電スイッチ34によって、不在であることを指令したり、設定期間内での運転終了を指令可能に構成されている。
説明を加えると、発電スイッチ34を設定時間(例えば、3秒間)継続して押し操作することにより、不在であることを指令するように構成され、自動運転モード中に、発電スイッチ34にて熱電併給装置3の運転停止を指令することにより、例えば、設定期間としての1日での運転終了を指令するように構成されている。
そして、禁止時間帯設定手段が、リモコンRにて構成され、不在指令手段が、発電スイッチ34にて構成され、運転終了指令手段も、発電スイッチ34にて兼用するように構成されている。
また、発電スイッチ34にて不在であることが指令されている場合に、発電スイッチ34が押し操作されるなど、リモコンRに何らかの操作が行われると、不在であることの指令を解除するようにしている。
The remote controller R is configured to be able to set a prohibition time zone for prohibiting the operation of the combined heat and power supply device 3, and can be instructed to be absent by the power generation switch 34 or can be instructed to end the operation within the set period. It is configured.
In other words, the power generation switch 34 is configured to instruct absence by pressing the power generation switch 34 continuously for a set time (for example, 3 seconds). By commanding the operation stop of the co-feeder 3, for example, the operation end in one day as a set period is commanded.
The prohibited time zone setting means is configured by the remote controller R, the absence command means is configured by the power generation switch 34, and the operation end command means is also configured to be shared by the power generation switch 34.
Further, when the power generation switch 34 is instructed to be absent, if the remote control R is operated in some way, such as when the power generation switch 34 is pressed, the absence command is canceled. ing.

そして、運転制御部7は、熱電併給装置3の運転中には冷却水循環ポンプ17を作動させる状態で、熱電併給装置3の運転および冷却水循環ポンプ17の作動状態を制御するとともに、湯水循環ポンプ19、熱用循環ポンプ21の作動状態を制御することによって、貯湯タンク4内に湯水を貯湯する貯湯運転や、図外の暖房スイッチの指令により熱消費端末5に熱媒を供給する熱媒供給運転を行うように構成されている。 The operation control unit 7 controls the operation of the combined heat and power supply device 3 and the operating state of the cooling water circulation pump 17 in a state where the cooling water circulation pump 17 is operated during the operation of the combined heat and power supply device 3. By controlling the operating state of the circulation pump 21 for the heat medium , the heat medium for storing the hot water in the hot water tank 4 and the heat medium for supplying the heat medium to the heat consuming terminal 5 by the command of the heating switch (not shown) It is comprised so that supply operation may be performed.

ちなみに、給湯するときには、貯湯タンク4内に貯湯用設定温度の湯水が貯湯されていれば、その湯水を給湯し、貯湯タンク4内に貯湯用設定温度の湯水が貯湯されていなければ、補助加熱手段Mを作動させて、その補助加熱手段Mにて加熱された湯水を給湯するように構成されている。   By the way, when hot water is supplied, if hot water at the set temperature for hot water storage is stored in the hot water storage tank 4, the hot water is supplied, and if hot water at the set temperature for hot water storage is not stored in the hot water storage tank 4, auxiliary heating is performed. The means M is operated to supply hot water heated by the auxiliary heating means M.

まず、自動運転における運転制御部7による熱電併給装置3の運転の制御について説明を加える。
前記運転制御部7は、実際の使用状況に基づいて、時系列的な電力負荷、時系列的な給湯熱負荷、および、熱消費端末5における時系列的な端末熱負荷を管理して、それに併せて、現在要求されている現電力負荷、予測給湯熱負荷から求められる現在要求されている現給湯熱負荷、および、現在要求されている現端末熱負荷を管理するように構成されている。
前記運転制御部7は、設定期間としての1日分の時系列的な過去負荷データを曜日と対応付ける状態で更新して記憶するデータ更新処理を行い、日付が変わるごとに、記憶されている1日分の時系列的な過去負荷データから、その日1日分の時系列的な予測負荷データを求める予測負荷演算処理を行うように構成されている。
そして、運転制御部7は、その日1日分の時系列的な予測負荷データを求めた状態で、例えば、数秒間隔で、時系列的な予測負荷データから、熱電併給装置3を運転させるか否かの基準となる省エネ度基準値を求める省エネ度基準値演算処理を行うとともに、その省エネ度基準値演算処理にて求められた省エネ度基準値よりも現時点での実省エネ度が上回っているか否かによって、熱電併給装置3の運転の可否を判別する運転可否判別処理を行うように構成されている。
First, description is added about control of the driving | operation of the cogeneration apparatus 3 by the operation control part 7 in automatic operation.
The operation control unit 7 manages a time-series power load, a time-series hot water supply heat load, and a time-series terminal heat load in the heat consuming terminal 5 based on an actual use situation, In addition, it is configured to manage the currently requested current power load, the currently requested current hot water heat load obtained from the predicted hot water supply heat load, and the currently requested current terminal heat load.
The operation control unit 7 performs a data update process of updating and storing time-series past load data for one day as a set period in a state of being associated with the day of the week, and is stored every time the date changes. Predictive load calculation processing is performed for obtaining time-series predicted load data for one day of the day from time-series past load data for the day.
And the operation control part 7 is the state which calculated | required the time series prediction load data for the 1st of the day, for example, it is operated at several second intervals from the time series prediction load data, whether the cogeneration apparatus 3 is operated. The energy conservation level reference value calculation process for obtaining the standard value for energy conservation level is performed, and whether or not the current energy conservation level exceeds the energy conservation level reference value determined in the energy conservation level reference value calculation process. Thus, the operation availability determination process for determining whether the operation of the combined heat and power supply device 3 is performed is performed.

このようにして、運転制御部7は、運転可否判別処理において、熱電併給装置3の運転が可と判別されると、現時点から、例えば、1時間先までを運転用時間帯と設定して、その運転用時間帯に熱電併給装置3を運転させ、熱電併給装置3の運転が不可と判別されると、熱電併給装置3の運転を停止させるように構成されている。   Thus, when it is determined that the operation of the combined heat and power supply device 3 is possible in the operation availability determination process, the operation control unit 7 sets, for example, one hour ahead as the operation time zone from the present time, It is configured to operate the combined heat and power supply device 3 during the operation time period and stop the operation of the combined heat and power supply device 3 when it is determined that the combined operation of the combined heat and power supply device 3 is not possible.

前記運転制御部7は、上述の如く、基本的には、運転用時間帯に熱電併給装置3を運転させるようにしているが、使用者の操作によって、運転用時間帯であっても、熱電併給装置3を運転させない場合もあるので、その場合について説明を加える。
前記運転制御部7は、発電スイッチ34にて不在であることが指令されている場合には、熱電併給装置3を運転停止状態に維持し、発電スイッチ34にて不在であることが指令されていない場合には、運転用時間帯に熱電併給装置3を運転させるように構成されている。
また、運転制御部7は、運転用時間帯であっても、リモコンRにて設定された禁止時間帯内であると、熱電併給装置3の運転を禁止させるように構成されている。
さらに、運転制御部7は、発電スイッチ34にて1日の運転終了が指令された場合には、運転用時間帯であっても、熱電併給装置3の運転を停止させ、発電スイッチ34にて1日の運転終了がまだ指令されていない場合には、運転用時間帯に熱電併給装置3を運転させるように構成されている。
As described above, the operation control unit 7 basically operates the combined heat and power supply device 3 during the operation time zone. However, even if the operation time zone is operated by the user, Since there is a case where the co-feeder 3 is not operated, a description will be added about that case.
When the operation control unit 7 is instructed to be absent by the power generation switch 34, the operation control unit 7 is instructed to maintain the cogeneration apparatus 3 in the operation stop state and to be absent by the power generation switch 34. If not, the combined heat and power supply device 3 is operated during the operation time zone.
Further, the operation control unit 7 is configured to prohibit the operation of the combined heat and power supply device 3 within the prohibition time zone set by the remote controller R even in the operation time zone.
Furthermore, when the operation switch 7 is instructed to end the operation of the day by the power generation switch 34, the operation control unit 7 stops the operation of the combined heat and power supply device 3 even in the operation time zone, and the power generation switch 34 When the end of the operation for one day has not been instructed yet, the combined heat and power supply device 3 is operated during the operation time zone.

前記データ更新処理について説明を加えると、1日のうちのどの時間帯にどれだけの電力負荷、熱負荷としての給湯熱負荷と端末熱負荷があったかの1日分の時系列的な過去負荷データを曜日と対応付ける状態で更新して記憶するように構成されている。   When the data update process is further described, time series historical load data for one day indicating how much power load, hot water supply heat load as a thermal load, and terminal heat load existed in which time zone of the day. Is updated and stored in a state where it is associated with the day of the week.

まず、時系列的な過去負荷データについて説明すると、時系列的な過去負荷データは、時系列的な電力負荷データ、時系列的な給湯熱負荷データ、時系列的な端末熱負荷データの3種類の時系列的な負荷データからなり、図3に示すように、1日分の時系列的な過去負荷データが日曜日から土曜日までの曜日ごとに区分けした状態で記憶するように構成されている。
そして、1日分の時系列的な過去負荷データは、24時間のうち1時間を単位時間として、単位時間当たりの電力負荷データの24個、単位時間当たりの給湯熱負荷データの24個、および、単位時間当たりの端末熱負荷データの24個から構成されている。
First, time-series past load data will be described. Time-series past load data includes three types of time-series power load data, time-series hot water supply heat load data, and time-series terminal heat load data. As shown in FIG. 3, the time-series past load data for one day is stored in a state divided for each day of the week from Sunday to Saturday.
And the time-series past load data for one day includes 24 pieces of power load data per unit time, 24 pieces of hot water supply heat load data per unit time, and 1 hour out of 24 hours, and , It is composed of 24 pieces of terminal thermal load data per unit time.

上述のような過去負荷データを更新する構成について説明を加えると、実際の使用状況から、単位時間当たりの実電力負荷、実給湯熱負荷、および、実端末熱負荷の夫々を、電力負荷計測手段13、給湯熱負荷計測手段31、および、端末熱負荷計測手段32にて計測し、その計測した実電力負荷、実給湯熱負荷、および、実端末熱負荷を記憶する状態で1日分の時系列的な実負荷データを曜日と対応付けて記憶させる。
そして、1日分の時系列的な実負荷データが1週間分記憶されると、曜日ごとに、時系列的な過去負荷データと時系列的な実負荷データとを所定の割合で足し合わせることにより、新しい時系列的な過去負荷データを求めて、その求めた新しい時系列的な過去負荷データを記憶して、時系列的な過去負荷データを更新するように構成されている。
The configuration for updating the past load data as described above will be described. From the actual usage situation, the actual power load per unit time, the actual hot water supply thermal load, and the actual terminal thermal load are determined as the power load measuring means. 13. Measured by hot water supply thermal load measurement means 31 and terminal thermal load measurement means 32, and when the measured actual power load, actual hot water supply thermal load, and actual terminal thermal load are stored for one day The sequential actual load data is stored in association with the day of the week.
When one day of time-series actual load data is stored for one week, the time-series past load data and the time-series actual load data are added at a predetermined ratio for each day of the week. Thus, the new time-series past load data is obtained, the obtained new time-series past load data is stored, and the time-series past load data is updated.

日曜日を例に挙げて具体的に説明すると、図3に示すように、時系列的な過去負荷データのうち日曜日に対応する時系列的な過去負荷データD1mと、時系列的な実負荷データのうち日曜日に対応する時系列的な実負荷データA1とから、下記の〔数1〕により、日曜日に対応する新しい時系列的な過去負荷データD1(m+1)が求められ、その求められた時系列的な過去負荷データD1(m+1)を記憶する。
なお、下記の〔数1〕において、D1mを、日曜日に対応する時系列的な過去負荷データとし、A1を、日曜日に対応する時系列的な実負荷データとし、Kは、0.75の定数であり、D1(m+1)を、新しい時系列的な過去負荷データとする。
More specifically, taking Sunday as an example, as shown in FIG. 3, time-series past load data D1m corresponding to Sunday among time-series past load data and time-series actual load data Among them, new time-series past load data D1 (m + 1) corresponding to Sunday is obtained from the time-series actual load data A1 corresponding to Sunday by the following [Equation 1], and the obtained time-series Historical past load data D1 (m + 1) is stored.
In the following [Equation 1], D1m is time-series past load data corresponding to Sunday, A1 is time-series actual load data corresponding to Sunday, and K is a constant of 0.75. D1 (m + 1) is new time-series past load data.

〔数1〕
D1(m+1)=(D1m×K)+{A1×(1−K)}
[Equation 1]
D1 (m + 1) = (D1m × K) + {A1 × (1-K)}

ちなみに、発電スイッチ34にて不在であることが指令されている場合には、電力、給湯、暖房が行われないので、発電スイッチ34にて不在が指令されている場合には、時系列的な実電力負荷、時系列的な給湯熱負荷、時系列的な端末熱負荷を計測せずに、その実負荷データをデータ更新処理の対象から除外するようにしている。
また、不在であることの指令が解除された日については、その1日分の実負荷データを得られないので、この不在であることの指令が解除された日の実負荷データもデータ更新処理の対象から除外するようにしている。
By the way, when it is instructed to be absent by the power generation switch 34, power, hot water supply, and heating are not performed. The actual load data is excluded from the data update process without measuring the actual power load, the time-series hot water supply heat load, and the time-series terminal thermal load.
Further, since the actual load data for the day cannot be obtained for the day when the absence command is canceled, the actual load data for the day when the absence command is canceled is also updated. Are excluded from the target.

前記予測負荷演算処理について説明を加えると、0時になるなど日付が変わるごとに実行され、その日のどの時間帯にどれだけの電力負荷、給湯熱負荷、端末熱負荷が予測されているかの1日分の時系列的な予測負荷データを求めるように構成されている。
すなわち、曜日ごとの7つの過去負荷データのうち、その日の曜日に対応する過去負荷データと前日の実負荷データとを所定の割合で足し合わせることにより、どの時間帯にどれだけの電力負荷、給湯熱負荷、端末熱負荷が予測されているかのその日1日分の時系列的な予測負荷データを求めるように構成されている。
When the predicted load calculation process is described, it is executed every time the date changes, such as 0 o'clock, and one day of how much power load, hot water supply heat load, and terminal heat load are predicted in which time zone of the day. It is configured to obtain minute time-series predicted load data.
That is, out of the seven past load data for each day of the week, the past load data corresponding to the day of the day and the actual load data of the previous day are added together at a predetermined ratio to determine how much power load and hot water supply in which time zone. It is configured so as to obtain time-series predicted load data for one day on whether the thermal load and the terminal thermal load are predicted.

月曜日1日分の予測負荷データを求める場合を例に挙げて具体的に説明すると、図3に示すように、曜日ごとの7つの過去負荷データD1m〜D7mと曜日ごとの7つの実負荷データA1〜A7とが記憶されているので、月曜日に対応する過去負荷データD2mと、前日の日曜日に対応する実負荷データA1とから、下記の〔数2〕により、月曜日の1日分の時系列的な予測負荷データBを求める。
そして、1日分の予測負荷データBは、図4に示すように、1日分の時系列的な予測電力負荷データ、1日分の時系列的な予測給湯熱負荷データ、1日分の時系列的な予測端末熱負荷データからなり、図4の(イ)は、1日分の時系列的な予測電力負荷を示しており、図4の()は、1日分の時系列的な予測給湯熱負荷を示しており、図4の()は、1日分の時系列的な予測端末熱負荷を示している。
Specifically, the case of obtaining the predicted load data for one day on Monday will be described as an example. As shown in FIG. 3, seven past load data D1m to D7m for each day of the week and seven actual load data A1 for each day of the week are shown. ~ A7 are stored, so the past load data D2m corresponding to Monday and the actual load data A1 corresponding to Sunday of the previous day are used to calculate the time series for one day on Monday by the following [Equation 2]. Predictive load data B is obtained.
As shown in FIG. 4, the predicted load data B for one day includes time-series predicted power load data for one day, time-series predicted hot water supply heat load data for one day, and data for one day. 4 includes time-series predicted terminal thermal load data, (a) in FIG. 4 shows a time-series predicted power load for one day, and ( c ) in FIG. 4 represents a time-series for one day. 4 shows a typical predicted hot water supply heat load, and ( b ) in FIG. 4 shows a time series predicted terminal heat load for one day.

〔数2〕
B=(D2m×Q)+{A1×(1−Q)}
[Equation 2]
B = (D2m × Q) + {A1 × (1-Q)}

前記省エネ度基準値演算処理について説明を加えると、時系列的な予測給湯熱負荷データを用いて、現時点から基準値用時間先までの間に必要となる貯湯必要量を賄えるように熱電併給装置3を運転させた場合に、熱電併給装置3を運転させることによって省エネルギー化を実現できる省エネ度基準値を求めるように構成されている。   When the energy-saving standard value calculation processing is described, a combined heat and power supply device can cover the required hot water storage amount from the present time to the reference value time using the time-series predicted hot water supply thermal load data When the operation unit 3 is operated, the energy-saving standard value capable of realizing energy saving by operating the combined heat and power supply device 3 is obtained.

例えば、単位時間を1時間とし、基準値用時間を12時間として説明を加えると、まず、時系列的な予測負荷データによる予測電力負荷、予測給湯熱負荷、および、予測端末熱負荷から、下記の〔数3〕により、図5に示すように、熱電併給装置3を運転させた場合の予測省エネ度を1時間ごとに12時間先までの12個分を求めるとともに、熱電併給装置3を運転させた場合に貯湯タンク3に貯湯することができる予測貯湯量を1時間ごとに12時間先までの12個分を求める。   For example, assuming that the unit time is 1 hour and the reference value time is 12 hours, first, from the predicted power load, predicted hot water supply thermal load, and predicted terminal thermal load based on time-series predicted load data, From [Equation 3], as shown in FIG. 5, the predicted energy-saving degree when the combined heat and power supply device 3 is operated is obtained for 12 hours every 12 hours, and the combined heat and power supply device 3 is operated. In this case, the predicted hot water storage amount that can be stored in the hot water storage tank 3 is obtained for 12 hours every 12 hours.

具体的に説明を加えると、現時点が0時であると、0時から1時まで熱電併給装置3を運転させた場合の予測省エネ度については、0時から1時までの予測電力負荷、予測給湯熱負荷、および、予測端末熱負荷から、下記の〔数3〕により求められ、0時から1時まで熱電併給装置3を運転させた場合の予測貯湯量についても、0時から1時までの予測電力負荷、予測給湯熱負荷、および、予測端末熱負荷から求められる。
このようにして、現時点が0時である場合には、1時間ごとの予測省エネ度と予測貯湯量とを12時までの12個分求めるようにしている。
Specifically, if the current time is 0 o'clock, the predicted energy saving when the combined heat and power supply device 3 is operated from 0 o'clock to 1 o'clock is predicted as the predicted power load from 0 o'clock to 1 o'clock From the hot water supply heat load and the predicted terminal heat load, it is obtained by the following [Equation 3], and the predicted hot water storage amount when the combined heat and power supply device 3 is operated from 0 o'clock to 1 o'clock is also from 0 o'clock to 1 o'clock. The predicted power load, the predicted hot water supply heat load, and the predicted terminal heat load.
In this way, when the current time is 0:00, the predicted energy saving degree and the predicted hot water storage amount for every hour are obtained for 12 pieces up to 12:00.

〔数3〕
省エネ度P={(EK1+EK2+EK3)/熱電併給装置3の必要エネルギー}×100
[Equation 3]
Energy saving level P = {(EK1 + EK2 + EK3) / required energy of cogeneration apparatus 3} × 100

ただし、EK1は、有効発電出力E1を変数とする関数であり、EK2は、E2を変数とする関数であり、EK3は、E3を変数とする関数であり、
EK1=有効発電出力E1の発電所一次エネルギー換算値
=f1(有効発電出力E1,発電所での必要エネルギー)
EK2=有効暖房熱出力E2の従来給湯器でのエネルギー換算値
=f2(有効暖房熱出力E2,バーナ効率(暖房時))
EK3=有効貯湯熱出力E3の従来給湯器でのエネルギー換算値
=f3(有効貯湯熱出力E3,バーナ効率(給湯時))
熱電併給装置3の必要エネルギー:5.5kW
(熱電併給装置3を1時間稼動させたときに必要な都市ガス使用量を0.433m3とする)
単位電力発電必要エネルギー:2.8kW
バーナ効率(暖房時):0.8
バーナ効率(給湯時):0.9
However, EK1 is a function with the effective power generation output E1 as a variable, EK2 is a function with E2 as a variable, EK3 is a function with E3 as a variable,
EK1 = Effective power generation output E1 power plant primary energy conversion value = f1 (Effective power generation output E1, required energy at the power plant)
EK2 = energy conversion value of conventional heating water heater with effective heating heat output E2 = f2 (effective heating heat output E2, burner efficiency (during heating))
EK3 = Effective hot water storage heat output E3 energy conversion value in conventional water heater = f3 (Effective hot water storage heat output E3, burner efficiency (during hot water supply))
Necessary energy of the combined heat and power supply device 3: 5.5 kW
(The amount of city gas required when the cogeneration unit 3 is operated for 1 hour is 0.433 m 3)
Unit power generation required energy: 2.8kW
Burner efficiency (heating): 0.8
Burner efficiency (with hot water supply): 0.9

また、有効発電出力E1、有効暖房熱出力E2、有効貯湯熱出力E3の夫々は、下記の〔数4〕〜〔数6〕により求められる。   Moreover, each of the effective power generation output E1, the effective heating heat output E2, and the effective hot water storage heat output E3 is obtained by the following [Equation 4] to [Equation 6].

〔数4〕
E1=電力負荷11での消費電力=熱電併給装置3の発電電力−(電気ヒータ14の消費電力+各種補機の消費電力)
ちなみに、各種補機とは、このコージェネレーションシステムで固有に補助的に用いられる装置や機械であり、冷却水循環ポンプ17や湯水循環ポンプ19などがこれに該当する。
[Equation 4]
E1 = Power consumption at the power load 11 = Power generated by the combined heat and power supply device 3− (Power consumption of the electric heater 14 + Power consumption of various auxiliary machines)
Incidentally, the various auxiliary machines are devices and machines that are inherently and supplementarily used in this cogeneration system, such as the cooling water circulation pump 17 and the hot water circulation pump 19.

〔数5〕
E2=熱消費端末5での消費熱量
[Equation 5]
E2 = Amount of heat consumed by the heat-consuming terminal 5

〔数6〕
E3=(熱電併給装置3にて発生する熱量+電気ヒータ14の回収熱量−有効暖房熱出力E2)−放熱ロス
ただし、電気ヒータ14の回収熱量=電気ヒータ14の消費電力×ヒータの熱効率とする。
[Equation 6]
E3 = (amount of heat generated in the combined heat and power supply device 3 + amount of heat recovered by the electric heater 14−an effective heating heat output E2) −a heat dissipation loss However, the amount of heat recovered by the electric heater 14 = the power consumption of the electric heater 14 × the heat efficiency of the heater. .

そして、図5に示すように、1時間ごとの予測省エネ度および予測貯湯量を12個分求めた状態において、まず、時系列的な予測給湯熱負荷データから12時間先までに必要とされている予測必要貯湯量を求め、その予測必要貯湯量から現時点での貯湯タンク4内の貯湯量を引いて、12時間先までの間に必要となる必要貯湯量を求める。
例えば、予測給湯熱負荷データから12時間後に9.8kWの給湯熱負荷が予測されていて、現時点での貯湯タンク4内の貯湯量が2.5kWである場合には、12時間先までの間に必要となる必要貯湯量は7.3kWとなる。
And in the state which calculated | required the prediction energy saving degree and prediction hot water storage amount for every 12 hours as shown in FIG. 5, it is first required from the time-sequential prediction hot water supply thermal load data to 12 hours ahead. The required amount of stored hot water is obtained, and the amount of hot water stored in the hot water storage tank 4 at the present time is subtracted from the required amount of stored hot water to obtain the necessary amount of stored hot water until 12 hours ahead.
For example, if a hot water supply heat load of 9.8 kW is predicted 12 hours later from the predicted hot water supply heat load data and the hot water storage amount in the hot water storage tank 4 is 2.5 kW at the present time, the time until 12 hours ahead The necessary hot water storage required for 7.3 kW is 7.3 kW.

そして、単位時間の予測貯湯量を足し合わせる状態で、その足し合わせた予測貯湯量が必要貯湯量に達するまで、12個分の単位時間のうち、予測省エネ度の数値が高いものから選択していくようにしている。   And in the state where the predicted hot water storage amount of the unit time is added, until the total predicted hot water storage amount reaches the required hot water storage amount, select from among the unit time for 12 units that has the highest predicted energy saving level I am going to go.

説明を加えると、例えば、上述の如く、必要貯湯量が7.3kWである場合には、図5に示すように、まず、予測省エネ度の一番高い7時間先から8時間先までの単位時間を選択し、その単位時間における予測貯湯量を足し合わせる。
次に予測省エネ度の高い6時間先から7時間先までの単位時間を選択し、その単位時間における予測貯湯量を足し合わせて、そのときの足し合わせた予測貯湯量が1.1kWとなる。
また次に予測省エネ度の高い5時間先から6時間先までの単位時間を選択し、その単位時間における予測貯湯量を足し合わせて、そのときの足し合わせた予測貯湯量が4.0kWとなる。
For example, when the required hot water storage amount is 7.3 kW as described above, first, as shown in FIG. 5, first, the unit from 7 hours to 8 hours ahead with the highest predicted energy saving degree is shown. Select the time, and add the predicted hot water storage amount per unit time.
Next, a unit time from 6 hours ahead to 7 hours ahead with a high predicted energy saving degree is selected, and the predicted hot water storage amount in the unit time is added, and the predicted hot water storage amount at that time is 1.1 kW.
Moreover, the unit time from 5 hours ahead to 6 hours ahead with the highest predicted energy saving degree is selected, and the predicted hot water storage amount in the unit time is added, and the predicted hot water storage amount at that time is 4.0 kW. .

このようにして、予測省エネ度の数値が高いものからの単位時間の選択と予測貯湯量の足し合わせを繰り返していくと、図5に示すように、8時間先から9時間先までの単位時間を選択したときに、足し合わせた予測貯湯量が7.3kWに達する。
そうすると、8時間先から9時間先までの単位時間の省エネ度を省エネ度基準値として設定し、図5に示すものでは、省エネ度基準値が106となる。
In this way, when the selection of the unit time from the one with the high predicted energy saving value and the addition of the predicted hot water storage amount are repeated, the unit time from 8 hours to 9 hours ahead as shown in FIG. When is selected, the combined predicted hot water storage amount reaches 7.3 kW.
If it does so, the energy-saving degree of the unit time from 8 hours ahead to 9 hours ahead will be set as an energy-saving degree reference value, and in the thing shown in FIG.

この省エネ基準値演算処理では、現時点から基準値用時間先までの間に、リモコンRにて設定された禁止時間帯を含まない場合と含む場合とでは、省エネ度基準値の求める構成が多少異なるので、その点について説明を加える。   In this energy saving reference value calculation process, the configuration for obtaining the energy saving reference value is slightly different between the case where the prohibited time zone set by the remote controller R is not included and the case where it is included between the current time and the reference value time. So, I will explain about that point.

現時点から基準値用時間先までの間に、リモコンRにて設定された禁止時間帯を含まない場合には、禁止時間帯以外用の省エネ度基準値演算処理を行うように構成されている。
すなわち、禁止時間帯以外用の省エネ度基準値演算処理では、現時点から基準値用時間先までの間のどの単位時間でも、熱電併給装置3を運転させることは可能である。
したがって、予測省エネ度の数値が高いものからの単位時間の選択と予測貯湯量の足し合わせを繰り返していく場合に、現時点から基準値用時間先までの間、どの単位時間でも選択することができるので、図5において、上述の説明の如く、予測省エネ度の数値が高いものからの単位時間の選択と予測貯湯量の足し合わせを繰り返して、省エネ度基準値を106と求める。
When the prohibition time zone set by the remote controller R is not included between the current time and the reference value time, the energy saving standard value calculation processing for other than the prohibition time zone is performed.
That is, in the energy saving standard value calculation processing for other than the prohibited time zone, the combined heat and power supply device 3 can be operated in any unit time from the current time to the reference value time destination.
Therefore, when repeating the selection of the unit time from the one with the high predicted energy saving value and the addition of the predicted hot water storage amount, any unit time can be selected from the current time to the reference time. Therefore, in FIG. 5, as described above, the selection of the unit time from the one with the highest predicted energy saving degree and the addition of the predicted hot water storage amount are repeated to obtain the energy saving reference value of 106.

現時点から基準値用時間先までの間に、リモコンRにて設定された禁止時間帯を含む場合には、禁止時間帯用の省エネ度基準値演算処理を行うように構成されている。
すなわち、禁止時間帯用の省エネ度基準値演算処理では、禁止時間帯に熱電併給装置3の運転を禁止させるので、禁止時間帯を除外した状態で省エネ度基準値を求めるようにしている。
説明を加えると、予測省エネ度の数値が高いものからの単位時間の選択と予測貯湯量の足し合わせを繰り返していく場合に、禁止時間帯に相当する単位時間を除外した状態で、予測省エネ度の数値が高いものからの単位時間の選択と予測貯湯量の足し合わせを繰り返して、省エネ度基準値を求める。
When the prohibition time zone set by the remote controller R is included between the current time and the reference value time ahead, the energy saving degree reference value calculation process for the prohibition time zone is performed.
That is, in the energy saving level reference value calculation process for the prohibited time zone, the operation of the combined heat and power supply device 3 is prohibited during the prohibited time zone, and thus the energy saving level reference value is obtained without the prohibited time zone.
In other words, when repeating the selection of unit time from the one with the highest predicted energy saving value and the addition of the predicted hot water storage amount, the predicted energy saving level is excluded while excluding the unit time corresponding to the prohibited time zone. Repeat the selection of the unit time from the one with the highest value and the predicted hot water storage amount to obtain the energy conservation standard value.

例えば、現時点が12時であり、禁止時間帯が21時〜24時に設定されている場合を例に挙げて説明すると、図5において、禁止時間帯に相当する単位時間が、9時間先〜12時間先までの3つの単位時間となる。
したがって、9時間先〜12時間先以外で、単位時間の予測貯湯量を足し合わせる状態で、その足し合わせた予測貯湯量が必要貯湯量に達するまで、12個分の単位時間のうち、予測省エネ度の数値が高いものから選択していくようにしている。
そして、図5に示すものでは、3時間先から4時間先までの単位時間を選択したときに、足し合わせた予測貯湯量が7.3kWに達するので、3時間先から4時間先までの単位時間の予測省エネ度を省エネ度基準値として設定し、省エネ度基準値が102となる。
For example, a case where the current time is 12:00 and the prohibited time zone is set from 21:00 to 24:00 will be described as an example. In FIG. 5, the unit time corresponding to the prohibited time zone is 9 hours ahead to 12 hours. It becomes three unit times until the time ahead.
Therefore, in the state where the predicted hot water storage amount of unit time is added other than 9 hours ahead to 12 hours ahead, the predicted energy saving of the unit time for 12 units until the combined predicted hot water storage amount reaches the required hot water storage amount. I choose from the ones with the highest numerical values.
In the case shown in FIG. 5, when the unit time from 3 hours ahead to 4 hours ahead is selected, the combined hot water storage amount reaches 7.3 kW, so the unit from 3 hours ahead to 4 hours ahead is selected. The predicted energy saving level of time is set as the energy saving level reference value, and the energy saving level reference value is 102.

前記運転可否判別処理について説明を加えると、現在要求されている現電力負荷、予測給湯熱負荷から求められる現在要求されている現給湯熱負荷、および、現在要求されている現端末熱負荷から、上記の〔数3〕により、現省エネ度を求めて、その現省エネ度が省エネ度基準値よりも上回ると、熱電併給装置3の運転が可と判別し、現省エネ度が省エネ度基準値以下であると、熱電併給装置3の運転が不可と判別するようにしている。   In addition to the description of the operation availability determination process, from the current power load currently requested, the current hot water heat load currently requested obtained from the predicted hot water supply heat load, and the current terminal heat load currently requested, When the current energy saving level is obtained by the above [Equation 3] and the current energy saving level exceeds the energy saving level reference value, it is determined that the cogeneration device 3 can be operated, and the current energy saving level is less than the energy saving level reference value. If so, it is determined that the operation of the combined heat and power supply device 3 is impossible.

次に、手動運転における運転制御部7による熱電併給装置3の運転の制御について説明を加える。
前記運転制御部7は、発電スイッチ34にて運転開始が指令されると、熱電併給装置3を運転させ、発電スイッチ34にて運転停止が指令されると、熱電併給装置3の運転を停止させるように構成されている。
Next, description is added about control of the operation of the combined heat and power supply device 3 by the operation control unit 7 in manual operation.
When the operation start is commanded by the power generation switch 34, the operation control unit 7 operates the cogeneration device 3, and when the power generation switch 34 is commanded to stop operation, the operation control unit 7 stops the operation of the cogeneration device 3. It is configured as follows.

前記運転制御部7による貯湯運転および熱媒供給運転の動作について説明を加える。
前記貯湯運転は、熱電併給装置3の運転中で冷却水循環ポンプ17の作動により、排熱式熱交換器22において、冷却水循環路15を通流する冷却水にて湯水循環路18を通流する湯水を加熱させることができる状態で行われる。
そして、湯水循環ポンプ19を作動させて、貯湯タンク4の下部から湯水を湯水循環路18に取出し、その湯水を排熱式熱交換器22を通過させて加熱したのち、貯湯タンク4の上部に戻して、貯湯タンク4内に貯湯用設定温度の湯水を貯湯するようにしている。
また、排熱式熱交換器22を通過した湯水の温度が貯湯設定温度になるように、貯湯弁29と断続弁30の開度を調整するように構成されている。
The operation of the hot water storage operation and the heat medium supply operation by the operation control unit 7 will be described.
In the hot water storage operation, the operation of the cooling water circulation pump 17 during the operation of the combined heat and power supply device 3 causes the hot water circulation path 18 to flow with the cooling water flowing through the cooling water circulation path 15 in the exhaust heat heat exchanger 22. It is performed in a state where hot water can be heated.
Then, the hot water circulation pump 19 is operated, hot water is taken out from the lower part of the hot water storage tank 4 to the hot water circulation path 18, and the hot water is heated by passing through the exhaust heat heat exchanger 22. The hot water is stored in the hot water storage tank 4 at a set temperature for hot water storage.
Moreover, it is comprised so that the opening degree of the hot water storage valve 29 and the intermittent valve 30 may be adjusted so that the temperature of the hot water which passed the exhaust heat type heat exchanger 22 may become hot water storage preset temperature.

前記熱媒供給運転は、図外の暖房スイッチによる熱消費端末5の運転開始および運転停止の指令に基づいて行われ、湯水循環ポンプ19を作動させることにより、排熱式熱交換器22と補助加熱用熱交換器26との少なくとも一方にて湯水循環路18を通流する湯水を加熱させて、その加熱された湯水を熱媒加熱用熱交換器23を通過する状態で循環させ、熱媒加熱用熱交換器23において湯水により加熱される熱媒を熱消費端末5に循環供給するようにしている。
そして、例えば、補助加熱用熱交換器26を通過した湯水の温度が65〜70℃になるように、貯湯弁27と断続弁34の開度を調整するようにしている。
The heat medium supply operation is performed based on the operation start and operation stop command of the heat consuming terminal 5 by a heating switch (not shown), and the hot water circulation pump 19 is operated to assist the exhaust heat heat exchanger 22 and the auxiliary heat exchanger 22. The hot water flowing through the hot water circulation path 18 is heated in at least one of the heating heat exchanger 26, and the heated hot water is circulated in a state of passing through the heat medium heating heat exchanger 23. A heating medium heated by hot water in the heating heat exchanger 23 is circulated and supplied to the heat consuming terminal 5.
Then, for example, hot water temperature which has passed through the auxiliary heating heat exchanger 26 is to be 65 to 70 ° C., and to adjust the opening of the intermittent valve 34 and savings hot water valve 27.

前記湯水循環路18を通流する湯水の加熱については、熱電併給装置3の運転中である場合には、冷却水循環ポンプ17の作動により、排熱式熱交換器22において湯水を加熱させるように構成されている。
そして、排熱式用熱交換器22における加熱量よりも熱消費端末5で現在要求されている現端末熱負荷の方が小さい場合には、熱消費端末5で現在要求されている現端末熱負荷を賄いながら、貯湯タンク4内への貯湯を行うように、貯湯弁29の開度を調整するように構成されている。
Regarding the heating of the hot water flowing through the hot water circulation path 18, when the combined heat and power supply device 3 is in operation, the hot water is heated in the exhaust heat heat exchanger 22 by the operation of the cooling water circulation pump 17. It is configured.
If the current terminal heat load currently requested by the heat consuming terminal 5 is smaller than the heating amount in the exhaust heat heat exchanger 22, the current terminal heat currently requested by the heat consuming terminal 5 is used. The opening of the hot water storage valve 29 is adjusted so that hot water is stored in the hot water storage tank 4 while covering the load.

また、熱電併給装置3にて発生する熱だけでは熱消費端末5で現在要求されている現端末熱負荷を賄えない場合や、熱電併給装置3の非運転中の場合には、補助加熱手段Mを作動させることにより、補助加熱用熱交換器26において湯水を加熱させるように構成されている。   In addition, when only the heat generated in the combined heat and power supply device 3 cannot cover the current terminal heat load currently required by the heat consuming terminal 5, or when the combined heat and power supply device 3 is not in operation, the auxiliary heating means By operating M, the auxiliary heating heat exchanger 26 is configured to heat hot water.

前記運転制御部7の制御動作について、図6のフローチャートに基づいて説明を加える。
まず、発電スイッチ34にて不在であることが指令されていれば、熱電併給装置3を運転停止状態に維持する(ステップ1,2)。
発電スイッチ34にて不在であることが指令されていなければ、モード選択スイッチ33にて手動運転モードが指令されると、手動運転を行い、モード選択スイッチ33にて自動運転モードが指令されると、自動運転を行う(ステップ3〜5)。
The control operation of the operation control unit 7 will be described based on the flowchart of FIG.
First, if it is commanded that the power generation switch 34 is absent, the combined heat and power supply device 3 is maintained in the operation stop state (steps 1 and 2).
If it is not instructed that the power generation switch 34 is absent, when the manual operation mode is instructed by the mode selection switch 33, the manual operation is performed, and when the automatic operation mode is instructed by the mode selection switch 33. Then, automatic operation is performed (steps 3 to 5).

そして、自動運転中に、発電スイッチ34にて1日の運転終了が指令されると、熱電併給装置3および補助加熱手段Mの運転を強制停止させ、その強制停止させた状態から自動復帰用設定時間(例えば、1時間)が経過するまで、熱電併給装置3および補助加熱手段Mの運転を強制停止させる(ステップ6〜8)。
また、熱電併給装置3および補助加熱手段Mの運転を強制停止させた状態から自動復帰用設定時間(例えば、1時間)が経過すると、自動運転を復帰させるように構成されている。
Then, during the automatic operation, when the power generation switch 34 instructs the end of the operation of the day, the operation of the combined heat and power supply device 3 and the auxiliary heating means M is forcibly stopped, and the setting for automatic return is performed from the state where the forced stop is performed. Until the time (for example, 1 hour) elapses, the operation of the combined heat and power supply device 3 and the auxiliary heating means M is forcibly stopped (steps 6 to 8).
Further, the automatic operation is resumed when a set time for automatic return (for example, 1 hour) elapses from the state where the operations of the combined heat and power supply device 3 and the auxiliary heating means M are forcibly stopped.

ちなみに、手動運転中に、モード選択スイッチ33にて手動運転モードが指令されると、割り込み処理として、手動運転を停止して、自動運転を行い、逆に、自動運転中に、モード選択スイッチ33にて自動運転モードが指令されると、割り込み処理として、自動運転を停止して、手動運転を行うように構成されている。   Incidentally, when the manual operation mode is instructed by the mode selection switch 33 during the manual operation, the manual operation is stopped and the automatic operation is performed as an interruption process. Conversely, the mode selection switch 33 is operated during the automatic operation. When the automatic operation mode is commanded at, the automatic operation is stopped and the manual operation is performed as an interruption process.

前記自動運転での運転制御部7の制御動作について、データ更新処理および予測負荷演算処理を行っている状態で、図7のフローチャートに基づいて説明を加える。   The control operation of the operation control unit 7 in the automatic operation will be described based on the flowchart of FIG. 7 in a state where the data update process and the predicted load calculation process are performed.

まず、現時点から基準値用時間先までの間に、リモコンRにて設定された禁止時間帯が含まれない場合には、禁止時間帯以外用の省エネ度基準値演算処理を行い、現時点から基準値用時間先までの間に、リモコンRにて設定された禁止時間帯が含まれる場合には、禁止時間帯用の省エネ度基準値演算処理を行う(ステップ11〜13)。
そして、現時点が禁止時間帯であれば、熱電併給装置3の運転を停止させた状態に維持する(ステップ14〜15)。
First, if the prohibited time zone set by the remote controller R is not included between the current time and the reference value time, the energy-saving standard value calculation processing for other than the prohibited time zone is performed, and the reference from the current time If the prohibited time zone set by the remote controller R is included before the time for the value, energy-saving standard value calculation processing for the prohibited time zone is performed (steps 11 to 13).
And if a present time is a prohibition time slot | zone, it will maintain in the state which stopped the driving | operation of the combined heat and power supply apparatus 3 (steps 14-15).

現時点が禁止時間帯でなければ、運転可否判別処理を行い、運転可否判別処理において熱電併給装置3の運転が可と判別されると、熱電併給装置3を運転させる(ステップ14,16,17,18)。   If the current time is not the prohibited time zone, an operation availability determination process is performed. If it is determined in the operation availability determination process that the operation of the cogeneration apparatus 3 is possible, the cogeneration apparatus 3 is operated (steps 14, 16, 17, 18).

〔別実施形態〕
)上記第1実施形態では、発電スイッチ34にて不在指令手段と運転終了指令手段とを兼用するようにしているが、不在であることを指令する人為操作式のスイッチと設定期間内での運転終了を指令する人為操作式のスイッチとを設けて実施することも可能である。
[Another embodiment]
( 1 ) In the first embodiment, the power generation switch 34 serves as both the absence instruction means and the operation end instruction means. However, within the set period and the manually operated switch that commands the absence It is also possible to provide an artificially operated switch for commanding the end of the operation.

)上記第1実施形態では、自動運転モードと手動運転モードとを備えているが、自動運転モードのみまたは手動運転モードのみを備えて実施することも可能である。 (2) In the first implementation embodiment, although an automatic operation mode and manual operation mode, it is also possible to carry out include only automatic operation mode only or manual operation mode.

)上記第1実施形態では、運転制御部7が、運転用時間帯において、運転継続時間が設定時間未満である場合には、運転継続時間が設定時間以上となるまで熱電併給装置3の運転を継続させるように構成されているが、運転用時間帯において、運転継続時間が設定時間未満であっても、貯湯タンク4内の貯湯量が満杯となると、熱電併給装置3の運転を停止させるように構成して実施することも可能である。 (3) In the first implementation embodiment, the operation control section 7, in a driving time period, when the continuous operation time is less than the set time, cogeneration unit 3 until the operation continuation time beyond the predetermined period of time However, if the amount of hot water stored in the hot water storage tank 4 is full even if the operation continuation time is less than the set time in the operation time zone, the operation of the combined heat and power supply device 3 is performed. It can also be configured to be stopped.

)上記第1実施形態では、運転制御部7が、データ更新処理、予測負荷演算処理、省エネ度基準値演算処理、運転可否判別処理を行うことにより、予測電力負荷および予測熱負荷に基づいて、運転用時間帯を設定するようにしているが、運転用時間帯を設定する構成については適宜変更が可能である。
また、省エネ度を求める際に用いられる式については、上記〔数3〕に代えて、下記〔数7〕を用いて省エネ度を求めてもよく、適宜変更が可能である。
(4) In the first implementation embodiment, the operation control section 7, a data updating process, the predicted load processing, energy saving of the reference value calculation process, by performing the operation permission determining process, the predicted power loads and predicted heat load Based on this, the operation time zone is set, but the configuration for setting the operation time zone can be changed as appropriate.
Moreover, about the formula used when calculating | requiring an energy saving degree, it may replace with the said [Equation 3], may obtain | require an energy saving degree using the following [Equation 7], and can change suitably.

〔数7〕
省エネ度P=GΔt/{(GΔt×μE/μCP)+GΔt×μH×(1−HLoss)}
[Equation 7]
Energy saving level P = GΔt / {(GΔt × μE / μCP) + GΔt × μH × (1-HLoss)}

ただし、Gは、負荷の負荷量であり、Δtは、熱電併給装置3を運転させる時間であり、μEは、発電効率であり、μCPは、火力発電所など、電力供給会社から供給を受ける場合の発電効率であり、μHは、排熱率であり、HLossは、貯湯タンク4に溜めた熱が利用されるまでの放熱ロスである。
ちなみに、μEの発電効率については、熱電併給装置3の余剰電力を電気ヒータ14にて熱に変換する場合は、余剰電力を引いた実質の発電効率とし、μHの排熱率については、熱電併給装置3の余剰電力を電気ヒータ14にて熱に変換する場合は、余剰電力分を加えた実質の排熱率とする。
However, G is the load amount of the load, Δt is the time for which the cogeneration apparatus 3 is operated, μE is the power generation efficiency, and μCP is supplied from a power supply company such as a thermal power plant ΜH is an exhaust heat rate, and HLoss is a heat dissipation loss until the heat stored in the hot water storage tank 4 is used.
Incidentally, regarding the power generation efficiency of μE, when the surplus power of the combined heat and power supply device 3 is converted into heat by the electric heater 14, the power generation efficiency is obtained by subtracting the surplus power, and the exhaust heat rate of μH is combined with the heat and power supply. When the surplus electric power of the apparatus 3 is converted into heat by the electric heater 14, the substantial exhaust heat rate is obtained by adding the surplus electric power.

)上記第1実施形態では、電気ヒータ14がガスエンジン1の冷却水を加熱するように構成されているが、電気ヒータ14にて貯湯タンク4内の湯水を加熱するように構成して実施することも可能である。 (5) In the first implementation embodiment, the electric heater 14 is configured to heat the cooling water of the gas engine 1, configured to heat the hot water of the hot water storage tank 4 by an electric heater 14 It is also possible to implement.

)上記第1実施形態では、熱電併給装置3として、ガスエンジン1によって発電装置2を駆動するものを例示したが、例えば、熱電併給装置として燃料電池を適応することも可能である。 In (6) the first implementation embodiment, a combined heat and power unit 3, has been illustrated drives a power generator 2 by the gas engine 1, for example, it is also possible to adapt the fuel cell as the cogeneration unit.

コージェネレーションシステムの概略構成図Schematic configuration diagram of cogeneration system コージェネレーションシステムにおける制御ブロック図Control block diagram for cogeneration system データ更新処理における説明図Explanatory drawing in data update processing 1日分の時系列的な予測負荷を示すグラフGraph showing time-series forecast load for one day 第1実施形態における省エネ度基準値演算処理の説明図Explanatory drawing of the energy-saving standard value calculation process in 1st Embodiment 制御動作を示すフローチャートFlow chart showing control operation 自動運転モードにおける制御動作を示すフローチャート Flow chart illustrating the control operation in the automatic driving mode

符号の説明Explanation of symbols

3 熱電併給装置
4 貯湯タンク
5 熱消費端末
7 運転制御手段
20 熱媒循環路
21 熱媒循環手段
34 運転終了手
排熱式加熱手段
M 補助加熱手段
3 cogeneration apparatus 4 hot water storage tank 5 heat dissipation terminal 7 operation controlling means 20 heat medium circulation passage 21 heat medium circulation means 34 operation end hand stage
N exhaust heat heating means M auxiliary heating means

Claims (1)

電力と熱を発生する熱電併給装置と、熱媒循環路を通して熱媒を熱消費端末に循環供給させる熱媒循環手段と、前記熱電併給装置にて発生する熱にて貯湯タンク内の湯水および前記熱媒循環路を通流する熱媒を加熱する排熱式加熱手段と、前記貯湯タンク内に湯水が貯湯されていないときに湯水を加熱するおよび前記熱媒循環路を通流する熱媒を加熱する補助加熱手段と、運転を制御する運転制御手段とが設けられ、
前記運転制御手段は、時系列的な電力負荷、時系列的な給湯熱負荷、および、前記熱消費端末における時系列的な端末熱負荷を管理して、その管理している情報に基づいて、前記熱電併給装置の運転により省エネルギーを実現可能な運転用時間帯を設定し、その運転用時間帯に前記熱電併給装置を運転させるように構成されているコージェネレーションシステムであって、
設定期間内での運転終了を指令する運転終了指令手段が設けられ、
前記運転制御手段は、
前記設定期間内で前記運転用時間帯を設定するように構成され、かつ、前記運転終了指令手段にて運転終了が指令された場合には、前記運転用時間帯であっても、前記熱電併給装置の運転を停止させ、前記運転終了指令手段にて運転終了が指令されていない場合には、前記運転用時間帯に熱電併給装置を運転させるように構成され、さらに、
前記運転終了指令手段にて運転終了が指令された場合には、その指令から設定時間が経過する又は前記設定期間が終了すると、前記運転用時間帯に熱電併給装置を運転するように自動的に復帰するように構成されているコージェネレーションシステム。
A combined heat and power supply device for generating electric power and heat; a heating medium circulating means for circulating and supplying the heating medium to a heat consuming terminal through a heating medium circulation path; hot water in a hot water storage tank by heat generated by the combined heat and power supply device; Exhaust heat type heating means for heating the heat medium flowing through the heat medium circulation path, and heating medium for heating the hot water when hot water is not stored in the hot water storage tank and flowing through the heat medium circulation path An auxiliary heating means for heating and an operation control means for controlling the operation are provided,
The operation control means manages a time-series power load, a time-series hot water supply heat load, and a time-series terminal heat load in the heat consuming terminal, and based on the managed information, A cogeneration system configured to set an operation time zone capable of realizing energy saving by operation of the cogeneration device, and to operate the cogeneration device during the operation time zone,
An operation end command means for commanding the end of the operation within the set period is provided,
The operation control means includes
The operation time zone is set within the set period, and when the operation end command is instructed by the operation end command means, the combined heat and power supply even in the operation time zone The operation of the apparatus is stopped, and when the operation end commanding means is not instructed to end the operation, it is configured to operate the cogeneration device during the operation time zone, and
When the end of operation is commanded by the operation end command means, when the set time elapses from the command or when the set period ends, the combined heat and power supply device is automatically operated during the operation time zone. A cogeneration system that is configured to return .
JP2003390364A 2003-02-28 2003-11-20 Cogeneration system Expired - Fee Related JP4036819B2 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP2003054649A JP4036774B2 (en) 2003-02-28 2003-02-28 Cogeneration system
JP2003390364A JP4036819B2 (en) 2003-02-28 2003-11-20 Cogeneration system

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2003054649A JP4036774B2 (en) 2003-02-28 2003-02-28 Cogeneration system
JP2003390364A JP4036819B2 (en) 2003-02-28 2003-11-20 Cogeneration system

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003054649A Division JP4036774B2 (en) 2003-02-28 2003-02-28 Cogeneration system

Publications (2)

Publication Number Publication Date
JP2004264010A JP2004264010A (en) 2004-09-24
JP4036819B2 true JP4036819B2 (en) 2008-01-23

Family

ID=50023964

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2003054649A Expired - Fee Related JP4036774B2 (en) 2003-02-28 2003-02-28 Cogeneration system
JP2003390364A Expired - Fee Related JP4036819B2 (en) 2003-02-28 2003-11-20 Cogeneration system

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP2003054649A Expired - Fee Related JP4036774B2 (en) 2003-02-28 2003-02-28 Cogeneration system

Country Status (1)

Country Link
JP (2) JP4036774B2 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4654844B2 (en) * 2005-09-05 2011-03-23 パナソニック株式会社 Hot water storage water heater
JP2008311084A (en) * 2007-06-14 2008-12-25 Toshiba Fuel Cell Power Systems Corp Household fuel cell system
JP5268443B2 (en) * 2008-06-18 2013-08-21 東芝燃料電池システム株式会社 Fuel cell power generation system and control method thereof
JP5899482B2 (en) * 2012-02-21 2016-04-06 パナソニックIpマネジメント株式会社 Heating device control method and control device
JP2013217587A (en) * 2012-04-10 2013-10-24 Panasonic Corp Power generation system
JP5444442B2 (en) * 2012-11-26 2014-03-19 東芝燃料電池システム株式会社 Fuel cell power generation system and control method thereof
JP2020067248A (en) * 2018-10-25 2020-04-30 株式会社ノーリツ Heat storage type water heater and program

Also Published As

Publication number Publication date
JP2004264010A (en) 2004-09-24
JP4036774B2 (en) 2008-01-23
JP2004263620A (en) 2004-09-24

Similar Documents

Publication Publication Date Title
JP4875387B2 (en) Cogeneration system
JP4036819B2 (en) Cogeneration system
JP2005287132A (en) Cogeneration system
JP4614824B2 (en) Cogeneration system
JP4163977B2 (en) Heat source system
JP4208802B2 (en) Heat source system
JP4290206B2 (en) Cogeneration system
JP4916197B2 (en) Cogeneration system
JP4176028B2 (en) Energy system
JP4101082B2 (en) Cogeneration system
JP3970238B2 (en) Cogeneration system
JP4297700B2 (en) Cogeneration system
JP3970239B2 (en) Cogeneration system energy saving degree calculation method
JP4229866B2 (en) Energy supply system
JP5064856B2 (en) Cogeneration system
JP2005226969A (en) Energy system
JP4614809B2 (en) Energy supply system
JP2007333289A (en) Cogeneration system
JP4549234B2 (en) Cogeneration system
JP2004263622A (en) Cogeneration system
JP4649182B2 (en) Energy load data creation device and cogeneration system for energy generator
JP2006118748A (en) Cogeneration system
JP2005291562A (en) Cogeneration system
JP2005300102A (en) Heat source system
JP2009243851A (en) Cogeneration system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060203

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070112

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070118

AA91 Notification of revocation by ex officio

Free format text: JAPANESE INTERMEDIATE CODE: A971091

Effective date: 20070313

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070327

A256 Written notification of co-pending application filed on the same date by different applicants

Free format text: JAPANESE INTERMEDIATE CODE: A2516

Effective date: 20070327

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070522

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070628

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070827

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20071018

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20071030

R150 Certificate of patent or registration of utility model

Ref document number: 4036819

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101109

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131109

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees