JP3999556B2 - Three-dimensional intersection construction method and three-dimensional intersection - Google Patents

Three-dimensional intersection construction method and three-dimensional intersection Download PDF

Info

Publication number
JP3999556B2
JP3999556B2 JP2002123447A JP2002123447A JP3999556B2 JP 3999556 B2 JP3999556 B2 JP 3999556B2 JP 2002123447 A JP2002123447 A JP 2002123447A JP 2002123447 A JP2002123447 A JP 2002123447A JP 3999556 B2 JP3999556 B2 JP 3999556B2
Authority
JP
Japan
Prior art keywords
segment
girder
road
dimensional intersection
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002123447A
Other languages
Japanese (ja)
Other versions
JP2003313825A (en
Inventor
信行 松井
正 吉川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2002123447A priority Critical patent/JP3999556B2/en
Publication of JP2003313825A publication Critical patent/JP2003313825A/en
Application granted granted Critical
Publication of JP3999556B2 publication Critical patent/JP3999556B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、立体交差施工方法および立体交差に関するものである。
【0002】
【従来の技術】
都市部における道路の平面交差は、交通渋滞の大きな原因となっている。交差部の通過交通と右折左折交通を立体化することにより、通過交通を減速あるいは停止させることなく通過させることが可能となる。都市部の幹線においては、これら立体交差をアンダーパスあるいはオーバーパスのどちらかの方法で施工している。
【0003】
従来、オーバーパスの方法で立体交差を施工するには、交通を遮断して施工ヤードとし、その場所で杭あるいはケーソンなどの基礎を構築した後、橋脚・桁を構築する方法がある。
【0004】
【発明が解決しようとする課題】
しかしながら、従来の方法では、施工開始から完成までに、数年の期間を要する。数年の施工期間中、車線規制によって交通を阻害するため、さらなる交通渋滞が発生する。
【0005】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、基礎および橋脚工事と桁製作を同時に行うことで工期を短縮できる立体交差施工方法および立体交差を提供することにある。
【0006】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、架設ガーダ脚部と道路上ガーダを設置する工程と、基準セグメントの下方に前記架設ガーダ脚部を挟み込むような形状の仮支持ピースを設置して、前記架設ガーダ脚部を貫通するように前記基準セグメントを設置する工程と、前記道路上ガーダを用いて、前記基準セグメントを基準として複数のセグメントを配置する工程と、を具備することを特徴とする立体交差施工方法である。
【0007】
架設ガーダ脚部は、橋脚設置予定位置に、計画道路の幅員内に収まるように設置される。道路上ガーダは、隣接する2ヶ所の架設ガーダ脚部の間に架け渡され、計画道路高さの上方に設置される。計画道路の構成部材である基準セグメントは、ガーダ脚部の計画道路高さに設置される。計画道路の構成部材である複数のセグメントは、基準セグメントを基準として配置される。このとき、複数のセグメントは、例えば、道路上ガーダに取り付けられた吊り治具で吊下げて並べられる。吊り治具は、例えば、セグメントを所定の位置に吊下げるセグメント吊りロッド、道路上ガーダに沿ってセグメントを移動させるセグメント吊装置等で構成される。
【0008】
第1の発明では、まず、架設ガーダ脚部と道路上ガーダを設置し、架設ガーダ脚部に基準セグメントを設置する。そして、道路上ガーダを用いて、基準セグメントを基準として複数のセグメントを並べる。
【0009】
第2の発明は、第1の発明の立体交差施工方法で施工されたことを特徴とする立体交差である。
【0010】
【発明の実施の形態】
以下、図面に基づいて、本発明の実施例を詳細に説明する。図1は、立体交差道路2の立面図を示す。図1に示すように、立体交差道路2は、桁35a、桁35b、桁35c、橋脚23等で構成される。
【0011】
図2は、架設ガーダ脚部5と道路上ガーダ7を構築する工程を示す図である。立体交差道路2を構築するには、まず、図2に示すように、橋脚23の計画予定位置に、路面1と垂直に架設ガーダ脚部5を設置する。架設ガーダ脚部5は、交通障害とならないよう、立体交差道路2の計画幅員内に収まるように立設される。架設ガーダ脚部5は、後述する道路上ガーダ7と、道路上ガーダ7に固定されるセグメント仮受け桁9、セグメント仮受け桁9に吊下げられるセグメント等の重量を支持できる材質、構造を有する。
【0012】
さらに、隣接する2ヶ所の架設ガーダ脚部5の間に、道路上ガーダ7を架け渡す。道路上ガーダ7は、桁35a、桁35b、桁35cの計画位置の上方に配置される。道路上ガーダ7は、例えば、複数の水平部材8と、水平部材8を連結するトラス部材10で構成される。
【0013】
図3は、セグメント仮受け桁9等を設置する工程を示す図である。道路上ガーダ7の上側の水平部材8上に、水平部材8と直交するように、複数のセグメント仮受け桁9を設置する。セグメント仮受け桁9は、例えば、長方形板状の部材である。セグメント仮受け桁9の両端部には、ナット12を用いて棒状のセグメント仮吊用ゲビンデ11が固定される。セグメント仮吊用ゲビンデ11は、セグメントの仮吊りに用いられる。
【0014】
セグメント仮受け桁9の両端部には、さらに落下防止材吊ロープ13が設けられる。落下防止材吊ロープ13は、セグメント仮吊用ゲビンデ11の外側に吊下げられる。落下防止材吊ロープ13の下端部には、板状の落下防止材15が固定される。
【0015】
落下防止材15は、セグメント吊下げ予定位置の下方に配置され、施工中の工具あるいはボルト、ナット等の材料の地上への落下を防止する。落下防止材吊ロープ13、落下防止材15は、工具等の落下時の衝撃に耐えられる強度を有する部材で構成される。
【0016】
道路上ガーダ7には、さらに、セグメント吊り装置17が設けられる。セグメント吊り装置17は、道路上ガーダ7に沿って水平方向に移動可能である。また、クラブトロリ25(図5)を用いて、上下方向に昇降可能である。
【0017】
図4は、セグメント21cを設置する工程を示す図である。図5は、セグメント21cの通過中の架設ガーダ脚部5の断面立面図である。図5は、図4のA−Aによる断面の立面図である。
【0018】
図4に示すように、架設ガーダ脚部5を貫通するように、基準セグメント19a、基準セグメント19b、基準セグメント19cを設置する。基準セグメント19a、基準セグメント19b、基準セグメント19cは、桁35a、桁35b、桁35cの設置予定位置の高さに配置される。
【0019】
図5に示すように、架設ガーダ脚部5は、基準セグメント19b(19a、19c)に設けられた穴(図示せず)を貫通する。基準セグメント19b(19a、19c)の下方には、架設ガーダ脚部5を挟み込むような形状の仮支持ピース30が設置され、基準セグメント19b(19a、19c)を仮支持する。
【0020】
基準セグメント19a、基準セグメント19b、基準セグメント19cを設置した後、基準セグメント19aに隣接するセグメント21aをセグメント仮吊用ゲビンデ11で吊下げて設置する。さらに、セグメント21b、セグメント21c…を、順次セグメント仮吊用ゲビンデ11で吊下げて設置していく。
【0021】
セグメント21cを仮吊用ゲビンデ11で吊下げて設置するには、図4に示すように、設置時の状態から90度回転させた状態で、セグメント21cをセグメント吊り装置17に吊下げる。そして、セグメント吊り装置17を用いて、セグメント21cの位置を移動させる。
【0022】
セグメント吊り装置17は、クラブトロリ25、セグメント旋回機構27、セグメント吊りフレーム29等で構成される。クラブトロリ25は、セグメント旋回機構27やセグメント吊りフレーム29等の上下方向の吊上げ・吊下げを行い、道路上ガーダ7を走行路としてセグメント吊り装置17を移動させる。セグメント吊りフレーム29は、カプラ33、セグメント吊りロッド31等を用いてセグメント21cを保持する。セグメント旋回機構27は、セグメント吊りフレーム29や、セグメント吊りフレーム29に保持されたセグメント21cを旋回させる。
【0023】
図4に示す状態から、クラブトロリ25を用いて、セグメント吊りフレーム29に保持されたセグメント21cを、基準セグメント19bより高い位置まで吊上げる。そして、図5に示すように、架設ガーダ脚部5の間を通過させる。
【0024】
図6は、セグメント21cを設置予定位置付近まで移動させる工程を示す図、図7は、図6のB−Bによる断面の立面図である。図8は、セグメント21cを旋回させた状態を示す図である。
【0025】
図4に示す位置から、クラブトロリ25を用いて、セグメント21cを図6に示す位置、すなわち設置位置の手前まで移動させる。そして、図5に示すセグメント旋回機構27を用いてセグメント吊りフレーム29とセグメント21cとを90度旋回させる。旋回は、セグメント21cの方向転回に支障のない位置および高さで行う。
【0026】
次に、セグメント21cとセグメント21bの上端部が滑らかに連続するように、クラブトロリ25を用いてセグメント21cの位置と高さを調整する。そして、図8に示すように、セグメント仮吊り用ゲビンデ11をカプラ33に挿入してセグメント仮吊り用ゲビンデ11とセグメント吊りロッド31を接続し、セグメント21cの荷重をクラブトロリ25からセグメント仮吊り用ゲビンデ11に受け替える。セグメント21cは、図6に示すセグメント21a、21bと同様に、セグメント仮吊り用ゲビンデ11とセグメント吊りロッド31を用いて、セグメント仮受け桁9に吊下げられる。
【0027】
図4から図8に示す工程を繰り返して、桁35a、桁35b、桁35cを構成する複数のセグメントをセグメント仮受け桁9に吊下げる。そして、道路上ガーダ7に吊下げて並べられたセグメント21a、セグメント21b、セグメント21c…や架設ガーダ脚部5に保持された基準セグメント19a、基準セグメント19b、基準セグメント19cの接合面に接着剤を塗布し、適切な位置に緊張材を配置した後、間詰め部コンクリートの打設と緊張材の緊張を行う。桁35a、桁35b、桁35cは、プレストレスを与えることにより、一体化される。
【0028】
桁35a、桁35b、桁35cの形成と並行して、図1から図3に示すように、路面1の下方の地盤4を掘削し、適切な位置に基礎3を形成する。基礎3は、例えば、橋脚23の計画位置の下方等に形成される。さらに、図4から図6に示すように、架設ガーダ脚部5の位置に橋脚23を構築する。橋脚23は、図5に示すように、基準セグメント19b等の基準セグメントの下方に設けられ、桁35a、桁35b、桁35cを支持する。
【0029】
図9は、セグメント仮受け桁9等を撤去した状態を示す図である。プレストレスを与えて連続する複数のセグメントを一体化し、桁35a、桁35b、桁35cを形成した後、図9に示すように、セグメント仮受け桁9、セグメント仮吊用ゲビンデ11、セグメント吊り装置17等を撤去する。
【0030】
図10は、架設ガーダ脚部5等を撤去した状態を示す図である。図9に示す様態から、さらに架設ガーダ脚部5、道路上ガーダ7を撤去する。なお、図2から図10では、桁35bと桁35cの一方と桁35aのみを図示したが、残りの桁35b、桁35cも同様の方法で形成する。形成は、例えば、図2から図10に示した桁35bと桁35cの一方と桁35aの形成と並行して行う。最後に、橋面工や仕上げ工を施し、立体交差道路1を完成する。
【0031】
このように、本実施の形態では、基礎3および橋脚23を構築しつつ、架設ガーダ脚部5や道路上ガーダ7を用いて桁35a、桁35b、桁35cを形成する。基礎や橋脚の施工と桁製作を同時に行うことで、工期を短縮できる。架設ガーダ脚部5を立体交差道路2の計画幅員内に配置するため、交通の障害にならない。
なお、立体交差道路1を構成する桁や橋脚等の部材数は、図1に示す限りではない。
【0032】
【発明の効果】
以上、詳細に説明したように、本発明によれば、基礎および橋脚工事と桁製作を同時に行うことで工期を短縮できる立体交差施工方法および立体交差を提供できる。
【図面の簡単な説明】
【図1】立体交差道路2の立面図
【図2】架設ガーダ脚部5と道路上ガーダ7を構築する工程を示す図
【図3】セグメント仮受け桁9等を設置する工程を示す図
【図4】セグメント21cを設置する工程を示す図
【図5】セグメント21cの通過中の架設ガーダ脚部5の断面立面図
【図6】セグメント21cを設置予定位置付近まで移動させる工程を示す図
【図7】図6のB−Bによる断面の立面図
【図8】セグメント21cを旋回させた状態を示す図
【図9】セグメント仮受け桁9等を撤去した状態を示す図
【図10】架設ガーダ脚部5等を撤去した状態を示す図
【符号の説明】
1………路面
2………立体交差道路
5………架設ガーダ脚部
7………道路上ガーダ
9………セグメント仮受け桁
11………セグメント仮吊用ゲビンデ
17………セグメント吊り装置
19a、19b、19c………基準セグメント
21a、21b、21c………セグメント
25………クラブトロリ
27………セグメント旋回機構
29………セグメント吊りフレーム
31………セグメント吊りロッド
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a three-dimensional intersection construction method and a three-dimensional intersection.
[0002]
[Prior art]
Road crossings in urban areas are a major cause of traffic congestion. By making the passing traffic at the intersection and the right turn and left turn traffic three-dimensional, it is possible to pass the passing traffic without decelerating or stopping. On urban trunk lines, these three-dimensional intersections are constructed by either underpass or overpass methods.
[0003]
Conventionally, in order to construct a three-dimensional intersection by the overpass method, there is a method in which a traffic yard is cut off to form a construction yard and a foundation such as a pile or a caisson is constructed at that location, and then a pier / girder is constructed.
[0004]
[Problems to be solved by the invention]
However, in the conventional method, a period of several years is required from the start of construction to completion. During the construction period of several years, traffic congestion will occur due to lane restrictions, resulting in further traffic congestion.
[0005]
The present invention has been made in view of such problems, and an object of the present invention is to provide a three-dimensional intersection construction method and a three-dimensional intersection that can shorten the work period by simultaneously performing foundation and pier construction and girder production. It is in.
[0006]
[Means for Solving the Problems]
According to a first aspect of the present invention for achieving the above object, there is provided a step of installing a construction girder leg and a road girder, and a temporary support piece having a shape sandwiching the construction girder leg under a reference segment. Te, characterized by comprising the steps of placing the reference segment to pass through the bridging girder legs, with the road on girder, and disposing a plurality of segments based on the reference segment It is a three-dimensional intersection construction method.
[0007]
The erection girder leg is installed at the planned pier installation position so as to be within the width of the planned road. The on-road girder is bridged between two adjacent girder legs and installed above the planned road height. The reference segment, which is a component of the planned road, is installed at the planned road height of the girder leg. A plurality of segments that are constituent members of the planned road are arranged with reference to the reference segment. At this time, the plurality of segments are arranged by being suspended by, for example, a suspension jig attached to a girder on the road. The hanging jig includes, for example, a segment suspension rod that suspends the segment to a predetermined position, a segment suspension device that moves the segment along the girder on the road, and the like.
[0008]
In the first invention, first, an installation girder leg and a road girder are installed, and a reference segment is installed on the installation girder leg. Then, a plurality of segments are arranged with reference to the reference segment using the girder on the road.
[0009]
The second invention is a three-dimensional intersection characterized by being constructed by the three-dimensional intersection construction method of the first invention.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings. FIG. 1 shows an elevation view of the multilevel intersection road 2. As shown in FIG. 1, the three-dimensional intersection road 2 is composed of a girder 35a, a girder 35b, a girder 35c, a bridge pier 23, and the like.
[0011]
FIG. 2 is a diagram illustrating a process of constructing the construction girder legs 5 and the road girder 7. In order to construct the three-dimensional intersection road 2, first, as shown in FIG. 2, the construction girder leg 5 is installed at the planned position of the pier 23 perpendicular to the road surface 1. The erection girder leg 5 is erected so as to be within the planned width of the three-dimensional intersection road 2 so as not to obstruct traffic. The construction girder leg portion 5 has a material and a structure capable of supporting the weight of a road girder 7 to be described later, a segment provisional girder 9 fixed to the road girder 7, a segment suspended from the segment provisional girder 9, and the like. .
[0012]
Further, the girder 7 on the road is bridged between the two adjacent girder legs 5. The on-road girder 7 is disposed above the planned positions of the girders 35a, 35b, and 35c. The on-road girder 7 includes, for example, a plurality of horizontal members 8 and a truss member 10 that connects the horizontal members 8.
[0013]
FIG. 3 is a diagram showing a process of installing the segment temporary support beam 9 and the like. On the horizontal member 8 on the upper side of the on-road girder 7, a plurality of segment provisional girders 9 are installed so as to be orthogonal to the horizontal member 8. The segment temporary support beam 9 is, for example, a rectangular plate member. A rod-shaped segment temporary suspension Gebinde 11 is fixed to both ends of the segment temporary support beam 9 using nuts 12. The segment temporary suspension Gevinde 11 is used for temporarily suspending a segment.
[0014]
Fall prevention material suspension ropes 13 are further provided at both ends of the segment temporary support beam 9. The fall prevention material suspension rope 13 is suspended outside the segment temporary suspension gebinde 11. A plate-shaped fall prevention material 15 is fixed to the lower end portion of the fall prevention material suspension rope 13.
[0015]
The fall prevention material 15 is disposed below the segment suspension planned position, and prevents a tool or a material such as a bolt or a nut under construction from dropping to the ground. The fall prevention material suspension rope 13 and the fall prevention material 15 are configured by members having a strength capable of withstanding an impact when a tool or the like is dropped.
[0016]
A segment suspension device 17 is further provided on the road girder 7. The segment suspension device 17 is movable in the horizontal direction along the girder 7 on the road. The club trolley 25 (FIG. 5) can be used to move up and down.
[0017]
FIG. 4 is a diagram illustrating a process of installing the segment 21c. FIG. 5 is a sectional elevation view of the erected girder leg 5 during passage of the segment 21c. FIG. 5 is an elevational view of a section according to AA of FIG.
[0018]
As shown in FIG. 4, the reference segment 19a, the reference segment 19b, and the reference segment 19c are installed so as to penetrate the installation girder leg 5. The reference segment 19a, the reference segment 19b, and the reference segment 19c are arranged at the height of the planned installation positions of the girders 35a, the girders 35b, and the girders 35c.
[0019]
As shown in FIG. 5, the erection girder leg 5 passes through a hole (not shown) provided in the reference segment 19 b (19 a, 19 c). Below the reference segment 19b (19a, 19c), a temporary support piece 30 shaped so as to sandwich the installation girder leg 5 is installed to temporarily support the reference segment 19b (19a, 19c).
[0020]
After the reference segment 19a, the reference segment 19b, and the reference segment 19c are installed, the segment 21a adjacent to the reference segment 19a is installed by being suspended by the segment temporary suspension Gebinde 11. Further, the segment 21b, the segment 21c,... Are sequentially suspended by the segment temporary suspension Gebinde 11.
[0021]
In order to suspend and install the segment 21c with the temporary suspension Gebinde 11, the segment 21c is suspended from the segment suspension device 17 in a state rotated 90 degrees from the state at the time of installation as shown in FIG. Then, the segment suspension device 17 is used to move the position of the segment 21c.
[0022]
The segment suspension device 17 includes a club trolley 25, a segment turning mechanism 27, a segment suspension frame 29, and the like. The club trolley 25 lifts and hangs the segment turning mechanism 27, the segment suspension frame 29, and the like in the vertical direction, and moves the segment suspension device 17 using the on-road girder 7 as a travel path. The segment suspension frame 29 holds the segment 21c using the coupler 33, the segment suspension rod 31, and the like. The segment turning mechanism 27 turns the segment suspension frame 29 and the segment 21c held by the segment suspension frame 29.
[0023]
From the state shown in FIG. 4, using the club trolley 25, the segment 21c held by the segment suspension frame 29 is suspended to a position higher than the reference segment 19b. And as shown in FIG. 5, it passes between the installation girder leg parts 5. FIG.
[0024]
6 is a diagram showing a process of moving the segment 21c to the vicinity of the planned installation position, and FIG. 7 is an elevation view of a cross section taken along line BB of FIG. FIG. 8 is a diagram showing a state in which the segment 21c is turned.
[0025]
Using the club trolley 25, the segment 21c is moved from the position shown in FIG. 4 to the position shown in FIG. Then, using the segment turning mechanism 27 shown in FIG. 5, the segment suspension frame 29 and the segment 21c are turned 90 degrees. The turning is performed at a position and height that does not hinder the direction turning of the segment 21c.
[0026]
Next, the position and height of the segment 21c are adjusted using the club trolley 25 so that the upper ends of the segment 21c and the segment 21b are smoothly continuous. Then, as shown in FIG. 8, the segment temporary suspension Gebinde 11 is inserted into the coupler 33 to connect the segment temporary suspension Gevinde 11 and the segment suspension rod 31, and the load of the segment 21 c is applied to the segment temporary suspension from the club trolley 25. Change to Gevinde 11. Similarly to the segments 21 a and 21 b shown in FIG. 6, the segment 21 c is suspended from the segment temporary support beam 9 using the segment temporary suspension Gebinde 11 and the segment suspension rod 31.
[0027]
The steps shown in FIGS. 4 to 8 are repeated to suspend the plurality of segments constituting the beam 35a, beam 35b, and beam 35c on the segment provisional beam 9. Then, an adhesive is applied to the joining surfaces of the segment 21a, the segment 21b, the segment 21c,... And the reference segment 19a, the reference segment 19b, and the reference segment 19c that are held on the installation girder leg 5 while being suspended on the road girder 7. After applying and placing the tendon at an appropriate position, placing the interstitial concrete and tensioning the tendon. The girder 35a, girder 35b, and girder 35c are integrated by applying prestress.
[0028]
In parallel with the formation of the girders 35a, girders 35b, and girders 35c, as shown in FIGS. 1 to 3, the ground 4 below the road surface 1 is excavated to form the foundation 3 at an appropriate position. The foundation 3 is formed below the planned position of the pier 23, for example. Further, as shown in FIGS. 4 to 6, the pier 23 is constructed at the position of the erection girder leg 5. As shown in FIG. 5, the pier 23 is provided below a reference segment such as the reference segment 19b, and supports the girders 35a, 35b, and 35c.
[0029]
FIG. 9 is a diagram showing a state in which the segment provisional digits 9 and the like are removed. After a plurality of continuous segments are integrated by applying prestress to form a girder 35a, a girder 35b, and a girder 35c, as shown in FIG. 9, a segment temporary receiving girder 9, a segment temporary hanger Gebinde 11, a segment hanger Remove 17 mag.
[0030]
FIG. 10 is a diagram illustrating a state in which the erected girder leg 5 and the like are removed. From the mode shown in FIG. 9, the construction girder leg 5 and the road girder 7 are further removed. In FIGS. 2 to 10, only one of the digits 35b and 35c and the digit 35a are shown, but the remaining digits 35b and 35c are formed in the same manner. The formation is performed in parallel with the formation of one of the girders 35b and 35c and the girders 35a shown in FIGS. Finally, bridge work and finishing work are performed to complete the three-dimensional intersection road 1.
[0031]
As described above, in the present embodiment, the girder 35a, the girder 35b, and the girder 35c are formed using the erection girder leg portion 5 and the road girder 7 while the foundation 3 and the pier 23 are constructed. The construction period can be shortened by carrying out construction of the foundation and piers and girder production at the same time. Since the erection girder leg 5 is disposed within the planned width of the three-dimensional intersection road 2, it does not obstruct traffic.
In addition, the number of members, such as a girder and a bridge pier which comprise the three-dimensional intersection road 1, is not necessarily shown in FIG.
[0032]
【The invention's effect】
As described above in detail, according to the present invention, it is possible to provide a three-dimensional intersection construction method and a three-dimensional intersection that can shorten the construction period by simultaneously performing foundation and pier construction and girder production.
[Brief description of the drawings]
FIG. 1 is an elevation view of a three-dimensional crossing road. FIG. 2 is a diagram showing a process of constructing a construction girder leg 5 and a road girder 7. FIG. 3 is a diagram showing a process of installing a segment temporary support girder 9 and the like. FIG. 4 is a diagram showing a process of installing the segment 21c. FIG. 5 is a sectional elevation view of the erected girder leg 5 while the segment 21c is passing. FIG. 6 is a process of moving the segment 21c to the vicinity of the planned installation position. FIG. 7 is an elevation view of a section taken along line BB in FIG. 6. FIG. 8 is a view showing a state in which a segment 21c is swung. FIG. 9 is a view showing a state in which a segment temporary support beam 9 is removed. 10] The figure which shows the state which removed the installation girder leg part 5 etc. [Explanation of numerals]
1 ......... Road surface 2 ... ... Multi-level crossing road 5 ... ... Installation girder leg 7 ... ... On-road girder 9 ... ... Segment temporary support girder 11 ... ... Segment temporary suspension Gebinde 17 ... ... Segment suspension Devices 19a, 19b, 19c ......... Reference segments 21a, 21b, 21c ......... Segment 25 ......... Club trolley 27 ......... Segment turning mechanism 29 ......... Segment suspension frame 31 ......... Segment suspension rod

Claims (6)

架設ガーダ脚部と道路上ガーダを設置する工程と、
基準セグメントの下方に前記架設ガーダ脚部を挟み込むような形状の仮支持ピースを設置して、前記架設ガーダ脚部を貫通するように前記基準セグメントを設置する工程と、
前記道路上ガーダを用いて、前記基準セグメントを基準として複数のセグメントを配置する工程と、
を具備することを特徴とする立体交差施工方法。
Installing a girder leg and a girder on the road;
Installing a temporary support piece shaped to sandwich the installation girder leg below the reference segment, and installing the reference segment so as to penetrate the installation girder leg;
Using the girder on the road, placing a plurality of segments based on the reference segment;
A three-dimensional intersection construction method characterized by comprising:
前記架設ガーダ脚部は、橋脚設置予定位置に、計画道路の幅員内に設置されることを特徴とする請求項1記載の立体交差施工方法。  The three-dimensional intersection construction method according to claim 1, wherein the installation girder leg is installed in a width of a planned road at a planned pier installation position. 前記道路上ガーダは、計画道路高さの上方に設置されることを特徴とする請求項1記載の立体交差施工方法。  The three-dimensional intersection construction method according to claim 1, wherein the girder on the road is installed above the planned road height. 前記道路上ガーダは、セグメント仮吊用ゲビンデと、前記セグメント仮吊用ゲビンデの外側に吊下げられ、下端部に落下防止材が固定された落下防止材吊りロープとが設けられたセグメント仮受け桁が設置され、前記セグメント仮吊用ゲビンデで前記複数のセグメントを吊下げることを特徴とする請求項記載の立体交差施工方法。The road girder is a segment temporary support girder provided with a segment temporary suspension gebinde and a fall prevention material suspension rope that is suspended outside the segment temporary suspension gebinde and has a fall prevention material fixed to a lower end portion thereof. There is provided, crossing the construction method according to claim 1, wherein the suspending the plurality of segments at the segment temporary hanging for Gebinde. 前記基準セグメントは、計画道路高さに設置されることを特徴とする請求項1記載の立体交差施工方法。  The three-dimensional intersection construction method according to claim 1, wherein the reference segment is installed at a planned road height. 請求項1から請求項5のいずれかに記載された立体交差施工方法で施工されたことを特徴とする立体交差。  A three-dimensional intersection constructed by the three-dimensional intersection construction method according to any one of claims 1 to 5.
JP2002123447A 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection Expired - Fee Related JP3999556B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002123447A JP3999556B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002123447A JP3999556B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Publications (2)

Publication Number Publication Date
JP2003313825A JP2003313825A (en) 2003-11-06
JP3999556B2 true JP3999556B2 (en) 2007-10-31

Family

ID=29538735

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002123447A Expired - Fee Related JP3999556B2 (en) 2002-04-25 2002-04-25 Three-dimensional intersection construction method and three-dimensional intersection

Country Status (1)

Country Link
JP (1) JP3999556B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4872940B2 (en) * 2008-02-12 2012-02-08 Jfeエンジニアリング株式会社 Bridge erection device, floor slab erection method, and bridge erection method
CN104727211A (en) * 2015-02-04 2015-06-24 河南工程学院 Two-way independent type city overhead bridge structure
CN104929049B (en) * 2015-06-15 2018-03-02 许昌学院 Road and bridge combined type construction method

Also Published As

Publication number Publication date
JP2003313825A (en) 2003-11-06

Similar Documents

Publication Publication Date Title
JP3885584B2 (en) Construction method of composite truss bridge
CN102121234B (en) Quick construction method of two-tower five-span steel truss girder cable-stayed bridge
KR102321338B1 (en) Segmental precast concrete ventilating slabs of structure and construction way in tunnel for rapid installation
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
JP3579897B1 (en) Construction method of split bridge type traffic route and split bridge type traffic route
JP2003253623A (en) Rebuilding construction method for bridge beam
CN114214920B (en) Large-span double-layer built-up steel truss arch bridge and construction method thereof
CN109371820A (en) A kind of rotator construction frame-type bridge pier and its construction method
JP3999556B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
JP2000045231A (en) Erection method for arch bridge
CN112878171A (en) Large-span steel structure arch bridge and construction method
JP4685341B2 (en) Viaduct construction method
JP7409952B2 (en) Viaduct construction method and viaduct construction equipment
JP3954905B2 (en) Three-dimensional crossing method of plane intersection and viaduct
CN114892813A (en) Large-span building main body supporting steel structure and construction method
JP2004324340A (en) Steel shell for footing foundation, structure of bridge, construction method of bridge, and construction method of grade separation viaduct
JP3852686B2 (en) Three-dimensional intersection construction method and three-dimensional intersection
JP2005090108A (en) Erection method of bridge
CN109930497B (en) Workpiece for line crossing construction of formwork suspension casting combined system and construction process
JP3682247B2 (en) Construction method of elevated traffic route
JP3779978B2 (en) Elevated traffic route
CN218540353U (en) Steel bridge
JPH0711620A (en) Construction method of artificial ground
CN108914717B (en) Method for in-situ overhead installation of auxiliary support by using reinforcing steel bars of integral ballast bed
CN211421937U (en) Column bearing type viewing platform

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050111

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070201

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20070417

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20070615

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070807

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070809

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100817

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100817

Year of fee payment: 3

R154 Certificate of patent or utility model (reissue)

Free format text: JAPANESE INTERMEDIATE CODE: R154

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130817

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees