JP3935716B2 JP2001366024A JP2001366024A JP3935716B2 JP 3935716 B2 JP3935716 B2 JP 3935716B2 JP 2001366024 A JP2001366024 A JP 2001366024A JP 2001366024 A JP2001366024 A JP 2001366024A JP 3935716 B2 JP3935716 B2 JP 3935716B2
Authority
JP
Japan
Prior art keywords
outdoor
unit
indoor
outdoor units
control device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001366024A
Other languages
Japanese (ja)
Other versions
JP2003166740A (en
Inventor
準治 松栄
善郎 後藤
和伸 大川
亮太 平田
亮一 助名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sanyo Electric Co Ltd
Original Assignee
Sanyo Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sanyo Electric Co Ltd filed Critical Sanyo Electric Co Ltd
Priority to JP2001366024A priority Critical patent/JP3935716B2/en
Publication of JP2003166740A publication Critical patent/JP2003166740A/en
Application granted granted Critical
Publication of JP3935716B2 publication Critical patent/JP3935716B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Air Conditioning Control Device (AREA)

Description

【0001】
【発明の属する技術分野】
複数台の室外ユニットを同一冷媒系統に接続し、空調運転を行う空気調和装置の点検予告に関する。
【0002】
【従来の技術】
これまで、複数台の室外ユニットを同一冷媒系統に接続して運転を行うマルチ型の空気調和装置において、前記複数台の室外ユニットのうち、いずれかの室外ユニットに何らかの故障が発生した時点で、通常は不具合箇所を判定して、それを報知することにより、使用者やサービス業者へ知らせ、故障した室外ユニットを停止させ、停止中の正常な室外ユニットを運転させて前記空気調和装置の運転を継続させていた。また、故障した室外ユニットが故障に至る前の不調状態での判定手段は、特に有しておらず、そのまま正常状態として運転を継続させていた。
【0003】
【発明が解決しようとする課題】
前記空気調和装置では、室外ユニットが復数台あるため、これら室外ユニットのうち、例えば、1台が故障しても上記の様に停止中の正常な室外ユニットを運転させることにより、運転の継続は可能であったが、夏季のピーク時には、能力が不足となり、空調性を損なう結果となってしまっていた。
【0004】
そこで、本発明の目的は、室外ユニットが故障に至る前の不調段階で判定する判定手段と、これを報知する報知手段を備えたことを特徴とする空気調和装置を提供することにある。
【0005】
【課題を解決するための手段】
請求項1に記載の発明は、室外制御装置を内蔵する複数台の室外ユニットと、室内制御装置を内蔵する少なくとも1台の室内ユニットとを同一の冷媒配管系統へ並列に接続し、前記室外ユニットと、前記室内ユニットと、集中制御装置とを通信配線で接続して、全室外ユニットの運転時間平準化のため、前記複数台の室外ユニットの積算運転時間を検出してこれら室外ユニットの積算運転時間が一定時間以内となるように各室外ユニットの運転を切り換えるローテーション運転を行い、停止信号による停止やサーモオフなどの正常停止以外の停止時には、その停止した室外ユニットの前記ローテーション運転の優先順位を、一旦、最下位の順位として運転を行なわせるようにした空気調和装置において、前記積算運転時間の推移から、前記複数台の室外ユニットの故障に至る前の不調状態を判定する判定手段を備え、この判定手段とは、前記複数台の室外ユニットのうち、不調と思われる室外ユニットの積算運転時間と、これ以外の正常と思われる室外ユニットの積算運転時間との時間差により判定するものであることを特徴とするものである。
【0006】
請求項2に記載の発明は、請求項1に記載のものにおいて、前記室外ユニットの室外制御装置と、前記室内ユニットの室内制御装置と、前記集中制御装置とのいずれかの制御装置に前記判定手段を備えたことを特徴とするものである。
【0007】
請求項3に記載の発明は、請求項1乃至2に記載のものにおいて、前記判定手段による判定結果を報知させることを特徴とするものである。
【0009】
【発明の実施形態】
以下、本発明の一実施形態について、図1から図2を示しながら説明する。
【0010】
まず、図1を参照して、図1は、ガスエンジン等の動力を利用して駆動する圧縮機を搭載した複数台の室外ユニットと複数台の室内ユニットとを同一の冷媒系統へ接続して構成した空気調和装置の概略図で、例えば、室外ユニット1a〜1cを、ユニット間配管3へ並列に接続し、そのユニット間配管3の延長した先には、室内ユニット2a〜2nが、並列に接続された空気調和装置として説明する。
【0011】
室外ユニット1aには、ガス等の燃料を燃焼させることにより動力を発生するエンジン10aと、その動力で駆動される圧縮機11aと、冷媒の循環方向を変更させる四方弁12aと、冷媒の流量を調節する室外電動弁13aと、圧縮機11aで圧縮された冷媒を屋外の外気と熱交換させる室外熱交換器14aとアキュームレータ15aとが、冷媒配管で接続されて内蔵され、この冷媒配管は、手動バルブ18aおよび19aを経由してユニット間配管3に接続されている。
【0012】
さらに、室外熱交換器14aへ送風を行う室外送風機16aが備えられ、エンジン10aと、四方弁12aと、室外電動弁13aと、室外送風機16aとのそれぞれのオンオフ等の制御を行う室外制御装置17aを有し、通信配線4を通じて室外ユニット1bおよび、1cと、通信配線5を通じて室内ユニット2a〜2nとの通信を行っている。
【0013】
この室外制御装置17aは、図示はしていないが、室外ユニット1aの制御を行う室外制御部と、室内ユニット2a〜2nからの通信を受信して、全体の空調負荷を算出し、この空調負荷に対応する室外ユニット1a〜1cの運転と、その運転能力とを算出して指示をしたり、室外ユニット1a〜1cのローテーション運転を行わせる中央制御部とにより構成されている。
【0014】
室外ユニット1bおよび1cは、上記室外ユニット1aと同様のため説明を省略する。ただ、室外ユニット1bおよび1cに内蔵されている室外制御装置17bおよび17cには、前記室外制御装置17aの中央制御部の機能は、備えられておらず、通信は、室外ユニット1aに搭載されている中央制御部との通信のみとなっている。
【0015】
他方の室内ユニット2aについては、室内熱交換器30aと、室内電動弁32aとが冷媒配管で接続されて内蔵され、ユニット間配管3へ接続されており、この室内熱交換器30aに送風を行う室内送風機31aと、空調負荷を検出する室内温度センサ33aとが備えられ、室内制御部34aにより、通信配線5を通じて、室外ユニット1aの中央制御部および集中制御装置6への通信と、リモコン配線7aを通じてリモコン35aへの通信と、室内送風機31aの風量調節と、室内電動弁32aの弁開度調節とが行われている。
【0016】
この室内ユニット2aは、リモコン35aの操作により、室内ユニット2aの運転停止および、運転モードや、設定温度が指示され、この設定温度と、室内温度センサ33aで検出された室内温度とにより、その空調負荷を算出している。
【0017】
室内ユニット2b〜2nも、上記室内ユニット2aと同様で有るため、説明は省略する。
【0018】
集中制御装置6は、前記リモコン35a〜35nと同様に、この1台で室内ユニット2a〜2nの運転停止や、運転モード、設定温度の操作を行うことができるとともに、室内ユニット2a〜2nに接続されたリモコン35a〜35nの表示部に表示される様々な警報内容の表示もそれの表示部で可能となっている。また、この集中制御装置6は、図示はしていないが、通信配線5以外に通信配線接続し、通信を行うことが可能となっている。
【0019】
そして、本発明による複数台の室外ユニットにおいて、それぞれの室外ユニットの積算運転時間の推移から不調な室外ユニットを検出し、点検予告を判定する判定手段と、これを報知する報知手段を、例えば、上記に概略を説明した室外ユニット1aに内蔵された室外制御装置17aの中央制御部に備えたとして、本実施形態で説明をすると、図2を参照して、図2は、この判定手段および、報知手段について概略を示したフローチャートで、まず、判定手段および、報知手段として、上記の全室外ユニット1a〜1cのそれぞれの積算運転時間を比較し(S1)、他の室外ユニットとの積算運転時間の差が、一定時間a以上の差となる室外ユニットが存在するか否かが判断される(S2)。
【0020】
これは、ローテーション運転によって、例えば、上記室外ユニット1a〜1cのうち、室外ユニット1aを運転させたとすると、この運転している室外ユニットが、一定時間b運転した場合、次の優先順位の室外ユニット1bを運転させ、また、一定時間後に室外ユニット1cへ運転を切り替えて運転させるため、全ての室外ユニット1a〜1cが正常であれば、積算運転時間の差は、前記一定時間b以内となるはずで、また、空調負荷の増加により、例えば、室外ユニット1aの運転能力では、空調負荷に対応出来ないため、室外ユニット1bの運転を開始させたとすると、なおさらこの積算運転時間の差は少なくなるはずである。このことから、ローテーション運転での各室外ユニット同士の運転時間の差は、この一定時間b以内に収まるとの判断が行われており、前記一定時間aと、一定時間bとは、a>bの関係にある数値で、全ての室外ユニットが正常であった場合、各室外ユニットの積算運転時間の差が、丁度、一定時間bとなる可能性があるため、この時間に余裕を持たせた時間aとして判断を行わせている。
【0021】
また、この複数台の室外ユニットのうちで、どの室外ユニットを運転させるかの優先順位の決定は、それぞれの室外ユニットの積算運転時間および、発停回数により決定されるが、これは、エンジンで圧縮機を運転していることから、そのエンジンのオイル交換時期やメンテナンス時期のばらつきを防ぐため、積算運転時間をなるべく平準化させる必要があり、また、運転開始時のスタータモータなどの負担を軽減させるため、発停回数も平準化させる必要があるからである。
【0022】
そして、ステップ2での判断において、他の室外ユニットとの積算運転時間の差が、一定時間a以上の差となる室外ユニットが存在しなければステップ4へ進み、一定時間a以上の差となる室外ユニットが存在すれば、この室外ユニットが不調であると判断して、点検する様、中央制御部から、通信配線5を通じて、室内ユニット2a〜2nに接続されたリモコン35a〜35nおよび、集中制御装置6へ点検予告を報知する(S3)。
【0023】
次に、上記判定に至るまでの過程となるが、本空気調和装置が運転中であるか否かが判断され(S4)、運転中で無ければ、運転信号の有無を確認し(S5)、運転信号が無ければ、ステップ1へ戻り、このフローチャートを繰り返し、運転信号があれば、各室外ユニットの優先順位に従い、空調負荷に応じた室外ユニットの台数を運転させ、ステップ1へ戻る。
【0024】
ステップ4で、本空気調和装置が運転中であれば、停止信号の有無の確認を行い(S7)、停止信号があれば、正常停止した室外ユニット内で、優先順位の更新を行い(S8)、ステップ1へ戻り、停止信号が無ければ、異常停止の室外ユニットの有無を確認する(S9)。
【0025】
ここで、異常停止とは、部品の故障などにより、運転が不可能となる通常の故障で停止した場合を含め、外来ノイズなど一時的な外乱を受けて室外ユニットが、一時的な異常状態となり、停止した場合を意味し、通常の故障であれば、後述の様に、停止させるとともに警報処理を行い、また、一時的な異常状態であった場合は、前記故障での停止とは異なり、警報処理は行わず、一旦停止させて故障へ至ることを防ぎ、停止時間を置いて、次回の運転には、正常な室外ユニットと同様に再度運転させている。これは、この一時的な異常状態も含め、警報処理を行い報知した方が、空気調和装置にとっては安全側の処理であるが、一時的な異常状態が頻繁に発生した場合、その度毎、空気調和装置を停止させて空調運転を中断し、使用者への迷惑および、混乱を与えることを回避するために行っているもので、例えば、連続して、あるいは、一定時間内に複数回この症状が発生した場合、初めて異常処理を行うこととし、運転を再開させても前記症状が発生しなければ、異常状態は無かったものとして、その後の運転を継続させる様にしている。
【0026】
ステップ9で、異常停止の室外ユニットが存在した場合、その異常停止が故障での停止であるか否かの判断を行い(S10)、故障での停止であると判断されると、この故障した室外ユニットの故障状態を報知して(S11)、停止中の正常な室外ユニットでの代替運転を行って(S12)、ステップ1へ戻り、ステップ10で、故障での停止では無いと判断されると、異常停止した室外ユニットの優先順位を最下位とし(S13)、上記ステップ12を経由して、ステップ1へ戻る。
【0027】
また、ステップ9で、異常停止の室外ユニットが存在しない場合、空調負荷に応じた室外ユニットの台数制御や、それぞれの室外ユニットの優先順位と運転時間などによるローテーション運転を行い(S14)、このローテーション運転や台数制御により、新たに停止した室外ユニットがあるか否かを判断し(S15)、新たに停止した室外ユニットが無ければ、ステップ1へ戻り、新たに停止した室外ユニットがあれば、全室外ユニットを対象として優先順位の更新を行い(S16)、ステップ1へ戻り、このフローチャートを繰り返す。
【0028】
このフローチャートのステップ9で、異常停止をした室外ユニットを検出し、ステップ13で、その室外ユニットの優先順位を最下位としているが、一旦異常停止を行った室外ユニットの優先順位を最下位のままとしておくと、当然ではあるが、優先順位が低いため、なかなか運転する機会に恵まれ無い、このままの状態では、積算運転時間の平準化や、発停回数の平準化が行われないどころか、一時的に異常状態とはなったが、正常な室外ユニットを停止させておく形となるため、異常停止をした時点で一旦は、優先順位を最下位とするが、その後の停止で正常停止した場合、室外ユニットの優先順位を見直し、ステップ8や、ステップ16で再度、優先順位を更新して、運転開始の機会を与えている。
【0029】
この様に、本来は正常で、一時的な異常状態となった室外ユニットであれば、次回の運転からは、正常な室外ユニットとして扱われ、また、一旦優先順位が下がったことにより、積算運転時間や発停回数も他の室外ユニットに比べ少なくなることから、優先順位も上がり、これまで正常に運転して来た他の室外ユニットの積算運転時間に近づく形となる。
【0030】
ところが、不調状態で運転を継続し、異常停止となる室外ユニットは、その優先順位が低くなることが多く、当然、運転する機会が出来ても、不調なため、すぐに異常停止してしまい、積算運転時間も伸びない傾向となるため、ステップ1から2の判定手段により不調状態の判定を行うことができ、ステップ3により報知することにより、前記室外ユニットが故障に至る前に対処することが可能となる。
【0031】
さらに、ステップ3で集中制御装置6の表示部でも、この不調状態にある室外ユニットの点検予告を報知しているが、上記の様にこの集中制御装置6は、他の機器への送信機能も有しているため、この集中制御装置6から遠隔監視システムや、ビル監視システムの端末へ接続することにより、より一層に利便性も良くなる。
【0032】
また、本実施形態では、この不調状態にある室外ユニットの検出を、室外ユニット1a内の室外制御装置17aが備えた判定手段および、報知手段として説明したが、特にこれに限定されるもので無く、他の室内制御装置2a〜2n、あるいは、集中制御装置6のいずれの制御装置へ、この判定手段および、報知手段を備えても可能である。
【0033】
【発明の効果】
以上の説明より、複数台の室外ユニットを同一冷媒配管で接続し、これらの積算運転時間などの平準化を行いながら運転を行っている空気調和装置のうち、いずれかの不調段階の室外ユニットを故障に至る前の時点でこれを検出して判定し、報知することが可能となる。
【図面の簡単な説明】
【図1】ガスエンジン等の動力を利用した圧縮機を搭載した室外ユニットと室内ユニットとを複数台づつ1冷媒系統に接続した空気調和装置の概略図である。
【図2】本発明による室外ユニットの点検予告を判定および報知する手段の概略を示したフローチャートである。
【符号の説明】
1a〜c 室外ユニット
2a〜c 室内ユニット
3 ユニット間配管
4 通信配線(室外ユニット間)
5 通信配線(室内外ユニット間)
6 集中制御装置
7a〜n リモコン配線
10a〜c エンジン
11a〜c 圧縮機
12a〜c 四方弁
13a〜c 室外電動弁
14a〜c 室外熱交換器
15a〜c アキュームレータ
16a〜c 室外送風機
17a〜c 室外制御装置
18a〜c 手動バルブ
19a〜c 手動バルブ
30a〜n 室内熱交換器
31a〜n 室内送風機
32a〜n 室内電動弁
33a〜n 室内温度センサ
34a〜n 室内制御装置
35a〜n リモコン
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an inspection notice of an air conditioner that performs air conditioning operation by connecting a plurality of outdoor units to the same refrigerant system.
[0002]
[Prior art]
So far, in a multi-type air conditioner that operates by connecting a plurality of outdoor units to the same refrigerant system, when any failure occurs in any one of the plurality of outdoor units, Normally, the malfunction location is determined and notified to the user or service provider, the malfunctioning outdoor unit is stopped, the stopped normal outdoor unit is operated, and the air conditioner is operated. It was continued. Further, there is no particular determination means in a malfunctioning state before the failed outdoor unit has failed, and the operation is continued as it is in a normal state.
[0003]
[Problems to be solved by the invention]
In the air conditioner, since there are a number of outdoor units, even if one of the outdoor units fails, for example, the normal outdoor unit that is stopped as described above is operated as described above to continue the operation. It was possible, but at the peak of the summer, the capacity was insufficient and air conditioning was impaired.
[0004]
SUMMARY OF THE INVENTION An object of the present invention is to provide an air conditioner comprising a determination unit that determines in a malfunctioning stage before an outdoor unit reaches a failure, and a notification unit that notifies the determination unit.
[0005]
[Means for Solving the Problems]
According to the first aspect of the present invention, a plurality of outdoor units incorporating an outdoor control device and at least one indoor unit incorporating an indoor control device are connected in parallel to the same refrigerant piping system, and the outdoor unit And the indoor unit and the centralized control device are connected by communication wiring, and in order to equalize the operation time of all outdoor units, the integrated operation time of the plurality of outdoor units is detected and the integrated operation of these outdoor units is detected. Rotation operation that switches the operation of each outdoor unit so that the time is within a certain time, and when stopping other than normal stop such as stop by a stop signal or thermo-off, the priority of the rotation operation of the stopped outdoor unit, In the air conditioner that has been operated once as the lowest order, the complex operation time is Determining means for determining a malfunctioning state before the failure of the outdoor unit of the stand, and the determining means includes, among the plurality of outdoor units, an accumulated operation time of the outdoor unit that seems to be malfunctioning; The determination is based on the time difference from the accumulated operation time of the outdoor unit that seems to be normal.
[0006]
According to a second aspect of the present invention, in the apparatus according to the first aspect, the determination is performed by any one of the outdoor control device for the outdoor unit, the indoor control device for the indoor unit, and the central control device. Means are provided.
[0007]
According to a third aspect of the present invention, in the first or second aspect of the present invention, the determination result by the determination means is notified.
[0009]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the present invention will be described with reference to FIGS.
[0010]
First, referring to FIG. 1, FIG. 1 is a diagram in which a plurality of outdoor units and a plurality of indoor units equipped with a compressor driven by using power such as a gas engine are connected to the same refrigerant system. In the schematic diagram of the air conditioner configured, for example, the outdoor units 1a to 1c are connected in parallel to the inter-unit piping 3, and the indoor units 2a to 2n are connected in parallel to the extended ends of the inter-unit piping 3. It demonstrates as a connected air conditioning apparatus.
[0011]
The outdoor unit 1a includes an engine 10a that generates power by burning fuel such as gas, a compressor 11a that is driven by the power, a four-way valve 12a that changes the circulation direction of the refrigerant, and a refrigerant flow rate. The outdoor motor-operated valve 13a to be adjusted, the outdoor heat exchanger 14a for exchanging heat of the refrigerant compressed by the compressor 11a with the outside air, and the accumulator 15a are connected by a refrigerant pipe, and are built in manually. It is connected to the inter-unit pipe 3 via the valves 18a and 19a.
[0012]
Further, an outdoor blower 16a that blows air to the outdoor heat exchanger 14a is provided, and an outdoor control device 17a that controls on / off of the engine 10a, the four-way valve 12a, the outdoor electric valve 13a, the outdoor blower 16a, and the like. And the outdoor units 1b and 1c through the communication wiring 4 and the indoor units 2a to 2n through the communication wiring 5.
[0013]
Although not shown, this outdoor control device 17a receives communication from the outdoor control unit that controls the outdoor unit 1a and the indoor units 2a to 2n, calculates the overall air conditioning load, and this air conditioning load It is comprised by the central control part which calculates the operation | movement of the outdoor unit 1a-1c corresponding to, and the instruction | indication by calculating the driving capability, or performs rotation operation of the outdoor unit 1a-1c.
[0014]
Since the outdoor units 1b and 1c are the same as the outdoor unit 1a, the description thereof is omitted. However, the outdoor control devices 17b and 17c built in the outdoor units 1b and 1c are not provided with the function of the central control unit of the outdoor control device 17a, and communication is mounted on the outdoor unit 1a. Communication is only with the central control unit.
[0015]
As for the other indoor unit 2a, the indoor heat exchanger 30a and the indoor motor-operated valve 32a are connected by a refrigerant pipe and connected to the inter-unit pipe 3, and air is blown to the indoor heat exchanger 30a. An indoor blower 31a and an indoor temperature sensor 33a for detecting an air conditioning load are provided. The indoor control unit 34a communicates with the central control unit 6 and the centralized control device 6 of the outdoor unit 1a through the communication wiring 5, and the remote control wiring 7a. The communication to the remote control 35a, the air volume adjustment of the indoor blower 31a, and the valve opening adjustment of the indoor electric valve 32a are performed.
[0016]
The indoor unit 2a is instructed to stop the operation of the indoor unit 2a, the operation mode, and the set temperature by operating the remote controller 35a, and the air conditioning is performed by the set temperature and the indoor temperature detected by the indoor temperature sensor 33a. The load is calculated.
[0017]
Since the indoor units 2b to 2n are the same as the indoor unit 2a, the description is omitted.
[0018]
As with the remote controls 35a to 35n, the centralized control device 6 can stop the operation of the indoor units 2a to 2n, operate the operation mode and set temperature, and connect to the indoor units 2a to 2n. It is also possible to display various alarm contents displayed on the display units of the remote controls 35a to 35n. Although not shown in the figure, this centralized control device 6 can be connected to a communication line other than the communication line 5 to perform communication.
[0019]
And in the plurality of outdoor units according to the present invention, a malfunctioning outdoor unit is detected from the transition of the accumulated operation time of each outdoor unit, a determination means for determining an inspection advance notice, and a notification means for informing this, for example, As described in the present embodiment, assuming that it is provided in the central control unit of the outdoor control device 17a built in the outdoor unit 1a outlined above, referring to FIG. 2, FIG. In the flowchart schematically showing the notification means, first, as the determination means and the notification means, the respective accumulated operation times of all the outdoor units 1a to 1c are compared (S1), and the accumulated operation time with other outdoor units is compared. It is determined whether or not there is an outdoor unit whose difference is equal to or longer than a predetermined time a (S2).
[0020]
This is because, for example, when the outdoor unit 1a among the outdoor units 1a to 1c is operated by rotation, the outdoor unit having the next priority order is operated when the outdoor unit operated for a certain period of time b. 1b is operated, and since the operation is switched to the outdoor unit 1c after a certain time, if all the outdoor units 1a to 1c are normal, the difference in the accumulated operation time should be within the certain time b. In addition, due to an increase in the air conditioning load, for example, the operating capacity of the outdoor unit 1a cannot cope with the air conditioning load. Therefore, if the operation of the outdoor unit 1b is started, the difference in the accumulated operation time should be further reduced. It is. From this, it is determined that the difference in the operation time between the outdoor units in the rotation operation is within this fixed time b, and the fixed time a and the fixed time b are a> b When all the outdoor units are normal, the difference in the accumulated operation time of each outdoor unit may be exactly a certain time b, so this time was given a margin. Judgment is made as time a.
[0021]
In addition, the priority order of which outdoor unit to operate among the plurality of outdoor units is determined by the accumulated operation time of each outdoor unit and the number of start / stop times. Since the compressor is in operation, the accumulated operation time must be leveled as much as possible in order to prevent variations in the oil change time and maintenance time of the engine, and the burden on the starter motor at the start of operation is reduced. This is because it is necessary to equalize the number of starts and stops.
[0022]
Then, in the determination in step 2, if there is no outdoor unit in which the difference in accumulated operation time with other outdoor units is a difference of a certain time a or more, the process proceeds to step 4 and a difference of a certain time a or more. If there is an outdoor unit, the remote control 35a to 35n connected to the indoor units 2a to 2n from the central control unit through the communication wiring 5 and centralized control are performed so that the outdoor unit is judged to be out of order and checked. An inspection notice is notified to the device 6 (S3).
[0023]
Next, the process until the above determination is made. It is determined whether or not the air conditioner is in operation (S4). If not, the presence or absence of an operation signal is confirmed (S5). If there is no operation signal, the process returns to step 1 and this flowchart is repeated. If there is an operation signal, the number of outdoor units corresponding to the air conditioning load is operated according to the priority of each outdoor unit, and the process returns to step 1.
[0024]
If it is determined in step 4 that the air conditioner is in operation, the presence / absence of a stop signal is confirmed (S7), and if there is a stop signal, the priority order is updated in the outdoor unit that has stopped normally (S8). Returning to step 1, if there is no stop signal, the presence or absence of an abnormally stopped outdoor unit is confirmed (S9).
[0025]
Here, the abnormal stop means that the outdoor unit becomes temporarily in an abnormal state due to a temporary disturbance such as external noise, including when it stops due to a normal failure that makes it impossible to operate due to a component failure, etc. In the case of a normal failure, as described below, it is stopped and alarm processing is performed as described below, and in the case of a temporary abnormal state, unlike the failure stop, The alarm processing is not performed, and it is temporarily stopped to prevent a failure, and after a stop time, the next operation is performed again like a normal outdoor unit. This is a process on the safe side for the air conditioner that performs warning processing, including this temporary abnormal condition, but if a temporary abnormal condition frequently occurs, each time, This is done to stop the air conditioner and interrupt the air-conditioning operation to avoid inconvenience and confusion to the user. For example, this is done continuously or several times within a certain time. When a symptom occurs, abnormality processing is performed for the first time, and if the symptom does not occur even when the operation is restarted, it is assumed that there is no abnormal state and the subsequent operation is continued.
[0026]
In step 9, when there is an abnormally stopped outdoor unit, it is determined whether or not the abnormal stop is a stop due to a failure (S10). The failure state of the outdoor unit is notified (S11), the substitute operation is performed with the normal outdoor unit that is stopped (S12), the process returns to step 1, and it is determined in step 10 that the stop is not a failure. Then, the priority order of the outdoor unit that has stopped abnormally is set to the lowest order (S13), and the process returns to step 1 via step 12 above.
[0027]
If there is no abnormally stopped outdoor unit in step 9, the number of outdoor units is controlled according to the air conditioning load, and the rotation operation is performed according to the priority order and operation time of each outdoor unit (S14). It is determined whether or not there is a newly stopped outdoor unit by operation or number control (S15). If there is no newly stopped outdoor unit, the process returns to Step 1, and if there is a newly stopped outdoor unit, all The priority order is updated for the outdoor unit (S16), the process returns to step 1 and this flowchart is repeated.
[0028]
In step 9 of this flowchart, the outdoor unit that has stopped abnormally is detected, and in step 13, the priority of the outdoor unit is set to the lowest, but the priority of the outdoor unit that has once stopped abnormally remains the lowest. As a matter of course, since the priority is low, there are not many opportunities to drive, and in this state, the accumulated operation time is not leveled, and the number of starts and stops is not leveled temporarily. However, when it stops abnormally, the priority is once the lowest, but if it stops normally after that stop, The priority order of the outdoor units is reviewed, and the priority order is updated again in step 8 and step 16 to give an opportunity to start operation.
[0029]
In this way, if the outdoor unit is normally normal and temporarily in an abnormal state, it will be treated as a normal outdoor unit from the next operation, and once the priority is lowered, the accumulated operation Since the time and the number of times of starting and stopping are less than those of other outdoor units, the priority is also raised, and the accumulated operating time of other outdoor units that have been operating normally so far is approached.
[0030]
However, outdoor units that continue to operate in a malfunctioning state and stop abnormally often have a lower priority, and naturally, even if there is an opportunity to drive, because it is malfunctioning, it immediately stops abnormally, Since the accumulated operation time does not tend to increase, the determination means in steps 1 and 2 can determine the malfunctioning state, and by notifying in step 3, it is possible to cope with the outdoor unit before it breaks down. It becomes possible.
[0031]
Further, in step 3, the display unit of the central control device 6 also notifies the inspection notice of the outdoor unit in the malfunctioning state. As described above, the central control device 6 also has a transmission function to other devices. Therefore, the convenience is further improved by connecting the central control device 6 to a remote monitoring system or a terminal of a building monitoring system.
[0032]
In the present embodiment, the detection of the outdoor unit in the malfunctioning state has been described as the determination unit and the notification unit provided in the outdoor control device 17a in the outdoor unit 1a. However, the present invention is not particularly limited to this. Any one of the other indoor control devices 2a to 2n or the central control device 6 may be provided with this determination means and notification means.
[0033]
【The invention's effect】
From the above explanation, one of the malfunctioning outdoor units of the air conditioner that operates while leveling the accumulated operation time, etc. by connecting a plurality of outdoor units with the same refrigerant pipe. This can be detected and determined at a point in time before failure, and can be notified.
[Brief description of the drawings]
FIG. 1 is a schematic view of an air conditioner in which a plurality of outdoor units and indoor units each equipped with a compressor using power such as a gas engine are connected to one refrigerant system.
FIG. 2 is a flowchart showing an outline of a means for determining and notifying an inspection notice of an outdoor unit according to the present invention.
[Explanation of symbols]
1a to c Outdoor units 2a to c Indoor unit 3 Inter-unit piping 4 Communication wiring (between outdoor units)
5 Communication wiring (between indoor and outdoor units)
6 Central control device 7a-n Remote control wiring 10a-c Engine 11a-c Compressor 12a-c Four-way valve 13a-c Outdoor electric valve 14a-c Outdoor heat exchanger 15a-c Accumulator 16a-c Outdoor blower 17a-c Outdoor control Apparatus 18a-c Manual valve 19a-c Manual valve 30a-n Indoor heat exchanger 31a-n Indoor blower 32a-n Indoor electric valve 33a-n Indoor temperature sensor 34a-n Indoor control apparatus 35a-n Remote control

Claims (3)

室外制御装置を内蔵する複数台の室外ユニットと、室内制御装置を内蔵する少なくとも1台の室内ユニットとを同一の冷媒配管系統へ並列に接続し、前記室外ユニットと、前記室内ユニットと、集中制御装置とを通信配線で接続して、全室外ユニットの運転時間平準化のため、前記複数台の室外ユニットの積算運転時間を検出してこれら室外ユニットの積算運転時間が一定時間以内となるように各室外ユニットの運転を切り換えるローテーション運転を行い、停止信号による停止やサーモオフなどの正常停止以外の停止時には、その停止した室外ユニットの前記ローテーション運転の優先順位を、一旦、最下位の順位として運転を行なわせるようにした空気調和装置において、前記積算運転時間の推移から、前記複数台の室外ユニットの故障に至る前の不調状態を判定する判定手段を備え、この判定手段とは、前記複数台の室外ユニットのうち、不調と思われる室外ユニットの積算運転時間と、これ以外の正常と思われる室外ユニットの積算運転時間との時間差により判定するものであることを特徴とする空気調和装置。A plurality of outdoor units incorporating the outdoor control device and at least one indoor unit incorporating the indoor control device are connected in parallel to the same refrigerant piping system, and the outdoor unit, the indoor unit, and centralized control Connect the equipment with communication wiring and level the operating time of all outdoor units so that the integrated operating time of the plurality of outdoor units is detected and the integrated operating time of these outdoor units is within a certain time. performs rotation operation for switching the operation of the outdoor units, when stopping other than the normal stopping or stopping and thermo-off by the stop signal, the priority of the rotation operation of the outdoor unit with its stop, temporarily, the operation as the lowest ranking In the air conditioner adapted to perform the failure of the plurality of outdoor units from the transition of the accumulated operation time Comprising a determining means for determining before sickened lead, and the determining means, among the plurality of outdoor units, the outdoor units seems the integrated operating time of the outdoor unit seems to upset, and normal non this An air conditioner characterized by being determined by a time difference from an accumulated operation time . 前記室外ユニットの室外制御装置と、前記室内ユニットの室内制御装置と、前記集中制御装置とのいずれかの制御装置に前記判定手段を備えたことを特徴とする請求項1に記載の空気調和装置。2. The air conditioner according to claim 1 , wherein the determination unit is provided in any one of the outdoor control device for the outdoor unit, the indoor control device for the indoor unit, and the central control device. . 前記判定手段による判定結果を報知させることを特徴とする請求項1乃至2に記載の空気調和装置。The air conditioning apparatus according to claim 1, wherein a determination result by the determination unit is notified.
JP2001366024A 2001-11-30 2001-11-30 Air conditioner Expired - Lifetime JP3935716B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001366024A JP3935716B2 (en) 2001-11-30 2001-11-30 Air conditioner

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001366024A JP3935716B2 (en) 2001-11-30 2001-11-30 Air conditioner

Publications (2)

Publication Number Publication Date
JP2003166740A JP2003166740A (en) 2003-06-13
JP3935716B2 true JP3935716B2 (en) 2007-06-27

Family

ID=19175982

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001366024A Expired - Lifetime JP3935716B2 (en) 2001-11-30 2001-11-30 Air conditioner

Country Status (1)

Country Link
JP (1) JP3935716B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4939799B2 (en) * 2005-11-07 2012-05-30 三洋電機株式会社 Air conditioner
KR101174054B1 (en) * 2005-12-21 2012-08-14 삼성전자주식회사 Multi type air conditioner system
JP4905939B2 (en) * 2006-08-30 2012-03-28 株式会社Nttファシリティーズ Operation control method for air conditioning system
JP5790738B2 (en) * 2013-10-31 2015-10-07 ダイキン工業株式会社 Air conditioning system
JP5900463B2 (en) * 2013-10-31 2016-04-06 ダイキン工業株式会社 Air conditioning system
WO2018096655A1 (en) 2016-11-25 2018-05-31 三菱電機株式会社 Refrigeration cycle device
JP7047305B2 (en) * 2017-09-26 2022-04-05 株式会社富士通ゼネラル Air conditioner
JP7438342B2 (en) * 2020-05-07 2024-02-26 三菱電機株式会社 air conditioner
WO2022059154A1 (en) * 2020-09-17 2022-03-24 東芝キヤリア株式会社 Air conditioner

Also Published As

Publication number Publication date
JP2003166740A (en) 2003-06-13

Similar Documents

Publication Publication Date Title
JP6731865B2 (en) Air conditioner outdoor unit, air conditioner, and air conditioning management method
JP3935716B2 (en) Air conditioner
JP4663483B2 (en) Air conditioner
EP3176516B1 (en) Air-conditioning apparatus
JP5222001B2 (en) Air conditioner control device
JP2014137161A (en) Air conditioner
JP3590499B2 (en) Air conditioner
JP2007212023A (en) Air conditioning system
JP3290251B2 (en) Air conditioner
KR20100069404A (en) Air conditioner and control method thereof
JP4183425B2 (en) Air conditioner and control method thereof
JP2715741B2 (en) Air conditioner
JP3960786B2 (en) Air conditioner
JP3302138B2 (en) Air conditioner
JPH0486444A (en) Air conditioner
JP3333000B2 (en) Air conditioner
JPH1183211A (en) High pressure protective controller for refrigerator
JPH05332647A (en) Air conditioner
KR102129927B1 (en) Air-conditioner
WO2001040716A1 (en) Multiple air conditioners
KR100575696B1 (en) Multi-air conditioner with emergency power supply part
KR100561538B1 (en) Multi type air conditioning system and method thereof
JPH0828982A (en) Air conditioner
JPH07120090A (en) Air conditioner
JPH0510574A (en) Air conditioner

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040702

RD01 Notification of change of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7421

Effective date: 20051227

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061017

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061204

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070220

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070320

R151 Written notification of patent or utility model registration

Ref document number: 3935716

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R151

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110330

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110330

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130330

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140330

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term