JP3894893B2 - Construction method of foundation ground - Google Patents

Construction method of foundation ground Download PDF

Info

Publication number
JP3894893B2
JP3894893B2 JP2003025393A JP2003025393A JP3894893B2 JP 3894893 B2 JP3894893 B2 JP 3894893B2 JP 2003025393 A JP2003025393 A JP 2003025393A JP 2003025393 A JP2003025393 A JP 2003025393A JP 3894893 B2 JP3894893 B2 JP 3894893B2
Authority
JP
Japan
Prior art keywords
slag
construction method
foundation ground
frame
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003025393A
Other languages
Japanese (ja)
Other versions
JP2003293354A (en
Inventor
幸太郎 平尾
正樹 赤根
Original Assignee
株式会社ジオトップ
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社ジオトップ filed Critical 株式会社ジオトップ
Priority to JP2003025393A priority Critical patent/JP3894893B2/en
Publication of JP2003293354A publication Critical patent/JP2003293354A/en
Application granted granted Critical
Publication of JP3894893B2 publication Critical patent/JP3894893B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、基礎地盤の施工法に関し、特に、軟弱地盤の比較的浅い層を地盤改良して既製杭を施工することにより、建物などの構造物を安定して支持することができる基礎地盤の施工法に関するものである。
【0002】
【従来の技術】
建物などの構造物の基礎を直接支持できない地盤に構造物を建てる際には、浅層混合処理工法等の地盤改良が事前に実施される。
従来の浅層混合処理工法は、バックホウなどで掘削できる表層部の地盤改良であり、現地の掘削土と土質改良材を混合して、それを埋戻し転圧して改良地盤を造成している。
【0003】
【発明が解決しようとする課題】
ところで、上記従来の浅層混合処理工法においては、掘削土と土質改良材を均一に混合することは難しく、不均一な土質改良により地耐力にムラが生じ、不同沈下が起きる可能性がある。
また、軟弱な地盤では、浅層の地盤改良では地耐力が小さいので、軽い建物以外建てることが難しく、一方、杭基礎にすると、杭が長くなり費用がかかるうえ、地盤沈下が生じた場合に杭に負の摩擦力が加わったり、「杭の抜け上り現象」が生じたりする。
【0004】
本発明は、上記従来の浅層混合処理工法が有する問題点に鑑み、軟弱な地盤の比較的浅い層を地盤改良して比較的短い既製杭を施工することにより、建物などの構造物を安定して支持することができる基礎地盤の施工法を提供することを目的とする。
【0005】
【課題を解決するための手段】
上記目的を達成するため、本発明の基礎地盤の施工法は、基礎地盤を表層から上部構造物を支持できる地盤まで掘削し、該掘削部内にスラグを充填し転圧してスラグ層を形成する基礎地盤の施工法であって、前記スラグ層上に枠体を埋設するようにするとともに、各枠体内に既製杭を建て込み、杭周囲にスラグを充填し締め固めることを特徴とする。
【0006】
この基礎地盤の施工法は、掘削部内で転圧したスラグ層上に複数の枠体を埋設するとともに、各枠体内に既製杭を建て込み、杭周囲にスラグを充填し締め固めることから、枠体内のスラグと杭とを一体化することができ、これにより、杭に作用した荷重を周辺地盤とスラグ層に伝達することができる。
【0007】
この場合において、スラグには、膨張性及び固化性を有するスラグを用いることができる。
この膨張性及び固化性を有するスラグとしては、製鋼スラグ(転炉スラグ及び/又は電気炉スラグ(酸化スラグ及び/又は還元スラグ)をいい、ここでは、特に、エージング処理を行っていない製鋼スラグのほか、エージング処理を部分的に行うことにより膨張性を調整した製鋼スラグ等の膨張性を消失させていない製鋼スラグをいう。)、ゴミ焼却スラグ、汚泥スラグの1種若しくは2種以上の混合物を用いることができる。
さらに、膨張性及び固化性を有するスラグは、単独で用いるほか、これに、膨張性を消失した製鋼スラグ、高炉スラグ、フェロアロイスラグ、水砕スラグ、銅製錬スラグ、赤泥、フライアッシュ、ゴミ焼却灰、ガラス破砕物、廃石膏、コンクリート廃材等の産業廃棄物、石膏、生石灰、セメント、砕石、土砂、粘土等の建築用材料、人工材料、鉱物の1種若しくは2種以上を混合した、膨張性及び固化性を有するスラグの膨張性及び固化性を利用できるものを用いることができる。
【0008】
これにより、掘削部底面の地盤の緩みを一般の土砂よりも比重の重いスラグで圧密することにより防止することができ、また、施工後、充填した製鋼スラグ等の膨張性及び固化性を有するスラグが吸水し、膨張固化することによって、緩んだ掘削部底面の地盤を圧密にすることができ、強固な地盤を得ることができるものとなる。また、産業廃棄物である製鋼スラグ等の有効利用を図ることができ、循環型社会形成の促進に寄与することができる。
【0009】
また、枠体の内側に、エージング処理前の製鋼スラグ、特に好ましくは、還元スラグを主成分とする膨張性の強いスラグを充填し締め固めることができる。
【0010】
これにより、枠体内側のスラグの膨張によって既製杭が拘束され、既製杭と枠体とが一体となって、その鉛直支持力と水平耐力を増強することができる。
【0011】
また、枠体の外側に、エージング処理後の製鋼スラグを主成分とする高い固化性を有する材料及び/又はエージング処理後の製鋼スラグを主成分とする高い固化性を有する材料とを混合、撹拌したものを充填し締め固めることができる。
【0012】
これにより、枠体外側の材料の固化によって枠体が拘束され、枠体を介して既製杭の鉛直支持力と水平耐力を増強することができ、また、掘削した地盤層の土砂を用いることによって、残土の発生量を抑制することができる。
【0013】
また、前記枠体を円筒形状とすることができる。
【0014】
これにより、枠体に指向性をなくし、スラグの膨張圧を均一に枠体にかけ、水平耐力を均一にすることができる。
【0015】
また、前記枠体を有底部材で構成することができる。
【0016】
これにより、既製杭に作用する荷重を枠体の底蓋面積で受け持たせることができる。
【0017】
また、前記既製杭の長さを、設計上の引き抜き力に見合った長さとするとともに、既製杭の外周に半径外方向に突出する抵抗体を設けることができる。
【0018】
これにより、既製杭の引き抜き抵抗力を増大させることができる。
【0019】
さらに、基礎地盤を布状に掘削し、該掘削部内にスラグを充填し転圧してスラグ層を形成し、該スラグ層上に枠体を埋設するようにすることができる。
【0020】
これにより、必要な基礎地盤のみを掘削施工して、施工コストの低減を図ることができる。
【0021】
【発明の実施の形態】
以下、本発明の基礎地盤の施工法の実施の形態を図面に基づいて説明する。
【0022】
図1〜図5に、本発明の基礎地盤の施工法の一実施例を示す。
この基礎地盤の施工法は、上部構造物(図示省略)を建設する軟弱地盤3全体を、表層1から上部構造物を支持できる支持地盤2まで掘削し、該掘削部4内に、膨張及び固化性を有するスラグを、散水しながら転圧し、スラグ層5aを形成するようにする。
このスラグ層5aは、スラグ層5a上に設置される枠体7によるパンチング剪断を考慮して、枠体7の直径(四角筒の枠体7の場合は、枠体7の一辺の長さ)の1/2倍程度以上の層厚となるように敷設するようにする。
そして、このスラグ層5a上には、枠体7を設置するようにし、枠体7の外側を、適宜の充填材5b、好ましくは、固化性を有する材料を充填し転圧して締め固める。
さらに、各枠体7内に適宜の充填材5c、好ましくは、高い膨張及び固化性を有する材料を充填し締め固めるとともに、その中心位置に、比較的短い既製杭6を設置する。
この場合、掘削部4の深さは、軟弱地盤3の性状、上部構造物の大きさ、重量等によって、上部構造を支持できる地盤に設定することになるが、通常は、数m程度の深さに設定される。
【0023】
この場合において、スラグ層5a及び充填材5b、5cに用いるスラグとしては、適用箇所に応じた膨張及び固化特性を有するように、エージング処理前の製鋼スラグ及び/又はエージング処理後の製鋼スラグのスラグ単独、又はエージング処理前の製鋼スラグ及び/又はエージング処理後の製鋼スラグと、高炉スラグ、フェロアロイスラグ、水砕スラグ、銅製錬スラグ、赤泥、フライアッシュ、ゴミ焼却スラグ、ゴミ焼却灰、汚泥スラグ、ガラス破砕物、廃石膏、コンクリート廃材等の産業廃棄物、石膏、生石灰、セメント、砕石、土砂、粘土等の建築用材料、人工材料、鉱物の1種若しくは2種以上を混合したものを用いるようにする。
【0024】
また、スラグ等と置換する地盤層の土砂を、スラグ層5aや充填材5b、5cに、本願発明の目的を失しない範囲で用いることにより、残土の発生量を抑制して、施工コストを低減することができる。
【0025】
そして、より具体的には、スラグ層5aには、スラグの膨張性を利用しながら、併せて固化性も重要視するため、遊離CaOや遊離MgO等の膨張、固化成分を含有する膨張性及び固化性を有するスラグを用いるようにする。
この膨張性及び固化性を有するスラグとしては、製鋼スラグ(転炉スラグ及び/又は電気炉スラグ(酸化スラグ及び/又は還元スラグ)をいい、ここでは、特に、エージング処理(具体的には、特に限定されるものではないが、例えば、約100℃の蒸気中で100時間程度保持したり、長期間屋外に野積みすることによる安定化処理)を行っていない製鋼スラグのほか、エージング処理を部分的に行うことにより膨張性を調整した製鋼スラグ等の膨張性を消失させていない製鋼スラグをいう。)、ゴミ焼却スラグ、汚泥スラグの1種若しくは2種以上の混合物を用いることができる。
さらに、膨張性及び固化性を有するスラグは、単独で用いるほか、これに、膨張性を消失した製鋼スラグ、高炉スラグ、フェロアロイスラグ、水砕スラグ、銅製錬スラグ、赤泥、フライアッシュ、ゴミ焼却灰、ガラス破砕物、廃石膏、コンクリート廃材等の産業廃棄物、石膏、生石灰、セメント、砕石、土砂、粘土等の建築用材料、人工材料、鉱物の1種若しくは2種以上を混合した、膨張性及び固化性を有するスラグの膨張性及び固化性を利用できるものを用いることができ、特に、エージング処理前の製鋼スラグと、エージング処理後のスラグに強アルカリ物質を添加して用いることが好ましい。
また、充填材5bには、エージング処理後の製鋼スラグ等を主成分とする高い固化性を有する材料及び/又はエージング処理後の製鋼スラグ等を主成分とする高い固化性を有する材料と掘削した地盤層の土砂とを混合、撹拌したものを用い、さらに、充填材5cには、スラグ層5aと同様の高い膨張及び固化性を有する材料を用いることが望ましい。
これにより、充填材5bが早く固まり、スラグ層5aがそれに追従して膨張しながら固まるようにする。
スラグ層5aに掛かる上部の荷重を上載圧として、掘削底面地盤を回復させ、ゆるみをなくすことができる。
そして、特に、本実施例の基礎地盤の施工法では、枠体7の内側に充填する充填材5cに高い膨張及び固化性を有する材料、例えば、還元スラグを主成分とする膨張性の強いスラグを用いることにより、枠体7の内側の充填材5cの膨張によって既製杭6が拘束され、既製杭6と枠体7とが一体となって、その鉛直支持力と水平耐力を増強することができる。
【0026】
枠体7は、図1(a1)(a2)に示すように、円筒形状に形成することが好ましい。これにより、枠体に指向性をなくし、スラグの膨張圧を均一に枠体に掛けることにより水平耐力を均一にすることができる。
また、枠体7は、四角筒のものを並列に連結するなど、他の形状のものも採用することができる。
そして、枠体7の先端位置を既製杭6の杭先端位置よりも下方に位置するように設定することにより、既製杭6と枠体7との一体性がより高まり、既製杭6の拘束力を増大させることができる。
一方、図1(b1)(b2)に示すように、枠体7を底蓋71を有する有底の円筒形状の部材で構成することもできる。これにより、既製杭6の柱荷重を底蓋面積で受け持つことができ、鉛直支持力が大きくとれることになる。
また、底蓋71がある場合は、予め、別の場所で枠体7に充填材5cと既製杭6とを一体化したものを作り、この一体化した枠体7をスラグ層5a、5b中に設置することもできる。
【0027】
また、枠体7は、図2(a1)(a2)に示すように、底蓋のない状態で、その下端位置と既製杭6の杭先端位置とがほぼ同じとなるように設定することもでき、また、図2(b1)(b2)に示すように、既製杭6を、その杭先端位置が枠体7の下端位置より下方に位置するように長く設定することもできる。
【0028】
また、枠体7は、図2(c)に示すように、格子状に組むこともできる。この場合、充填材5cとしては、すべてに膨張性の強いスラグを使用することができる。
【0029】
なお、枠体7は、例えば、一種のドラム缶のように、周壁が縦に波打つような波形状のものが、周面支持力が大きくなるため好適である。また、枠体7の直径(四角筒の枠体7の場合、枠体7の一辺の長さ)は、杭径の2倍〜6倍程度が適当である。
【0030】
一方、既製杭6としては、例えば、鋼管杭やPHCコンクリート杭の直径が400mm程度以下のものを使用することができ、例えば、鋼管杭では、先端にスクリュー状体S等を設けて、回転圧入することにより建て込むことができる(図2(b1)参照)。
また、既製杭6は、ストレート形状のものよりも、図5(a)〜(d)に示すように、節杭61、62やコルゲート杭63、テーパー杭64等の方が、充填材5cとの付着性をよくしたり、杭周面の摩擦力を大きくするうえで好ましい。
そして、節杭は、各節下の支圧効果で支持力が増大し、また、上記既製杭は先端閉塞杭(図示省略)を圧入することにより、既製杭6を介して充填材5cの周辺地盤を一層締め固めることができる。なお、PHCコンクリート杭(節杭、テーパー杭、コルゲート杭等)は略同径のオーガードリルによってプレボーリングしてから圧入して設置する場合と、直接圧入する場合とがある。
【0031】
次に、この基礎地盤の施工法の施工手順を、図3〜図4を参照して説明する。▲1▼ まず、図3(a)に示すように、上部構造物を支持できる地盤2まで軟弱地盤3を掘削する。この場合、掘削した土砂3aはすべて地上に排出する。
▲2▼ 次に、図3(b)に示すように、スラグ層5aを形成するスラグを一定量、掘削部4内に均一に投入し、締め固め機械等で転圧し、締め固める。
なお、散水によって、スラグ層5aの締め固め効果を高めるとともに、スラグ層5aの水和反応を助長して膨張、固化を早めることができる。
また、スラグ層5aのスラグとしては、粒度分布の悪いもの、具体的には、粒径が粗いものから細かいものまでが混合された締め固めに適した配合のものが好ましい。
▲3▼ 次に、図3(c)に示すように、スラグ層5aに枠体7を乗せて一部が埋まるように設置する。このとき、枠体7の根入れ深さは、枠体7の直径の20%以上が好ましい。
なお、ここでは、有底部材からなる枠体7を使用しており、枠体7の底蓋71には、通水口(透水口)72を設けている(図1参照)。これにより、枠体7の内部に位置する充填材5c及び有底下部の水和反応を妨げないようにすることができる。
▲4▼ そして、図3(d)に示すように、枠体7の周囲に充填材5bとして、エージング処理後の製鋼スラグ及び/又はエージング処理後の製鋼スラグと掘削した地盤層の土砂とを混合、撹拌した固化性を有する材料を投入し、締め固め機械等で転圧し、締め固める。
この場合、散水によって、充填材5bの締め固め効果を高めるとともに、充填材5bの水和反応を助長して膨張、固化を早めることができる。
▲5▼ さらに、図4(a)に示すように、枠体7の内部に充填材5cとして、エージング処理前の製鋼スラグを主成分とする高い膨張及び固化性を有する材料を投入し、締め固め機械等で転圧し、締め固める。
この場合、散水によって、充填材5cの締め固め効果を高めるとともに、充填材5cの水和反応を助長して膨張、固化を早めることができる。
なお、スラグを投入して充填材5cを形成する際に、同時に既製杭6を設置する場合もある。
▲6▼ そして、図4(b)に示すように、枠体7内部の充填材5cに既製杭6を、鋼管杭では回転圧入することにより、建て込むようにする。
最終的に、枠体7内の充填材5cの膨張を枠体7が拘束し、枠体7と充填材5cとが一体となり、これにより、既製杭6を強固に支持することができる。
【0032】
この場合、既製杭6の先端と枠体7の底蓋71は、図1(b)に示すように、接触させるようにする。これにより、杭6に作用した荷重は、枠体7の底蓋71で受け持つので、直接スラグ層5aに支持させることができ、鉛直支持力が大きくとれることになる。
【0033】
さらに、本発明の基礎地盤の施工法の他の実施例を説明する。
既製杭6の長さは、設計上の引き抜き力に見合った長さとするが、例えば、図6に示すように、既製杭を充填材5cを貫通して支持地盤2に建て込むこともできる。
また、既製杭6の外周に半径外方向に突出する抵抗体61を設けることも可能であり、この場合、抵抗体61を前記したようなスクリュー状体で構成することにより、既製杭6の引き抜き抵抗力を増大させるとともに、既製杭6を充填材5cや支持地盤8に建て込む際の推進力を得ることができる。
【0034】
また、図7に示すように、基礎地盤を布状に掘削し、この布状の掘削部4の充填材5bに複数の枠体7を埋設するとともに、各枠体7内に既製杭6を建て込み、杭周囲にスラグ5cを充填して締め固めることも可能である。
この場合、布状の掘削部4に囲まれた中央部と、この掘削部4の外側の部分とは、元の地盤のまま手を加えずに放置することができる。なお、この実施例では、枠体7の直径は、既製杭6の直径の約4倍の大きさとしている。
これにより、必要な基礎地盤のみを掘削施工して、地盤改良のコストの低減を図ることができる。
【0035】
かくして、この実施例の基礎地盤の施工法は、掘削部4内で締め固めたスラグ層5aに、複数の比較的短い既製杭6を建て込むことから、充填材5cと杭6とが一体化された強固な基礎杭を造成して、杭6の支持力とスラグ層5aの接地圧、さらには、枠体7と充填材5cと既製杭6とが一体となり、一般の土砂よりも充填材5cの内部摩擦抵抗が大きいことから、大きな水平抵抗力により建物等の上部構造物を安定して支持し、その不同沈下を抑制することができる。
また、各既製杭の周囲に、該既製杭を略中心として取り囲む枠体を配設することから、枠体が杭の周囲を拘束することができ、枠周囲の剪断強度が増大するとともに、既製杭の鉛直支持力と水平耐力を増強することができる。
【0036】
以上、本発明の基礎地盤の施工法を実施例に基づいて説明したが、例えば、枠体、既製杭の埋設順序は上記に限定するものではなく、本発明はその要旨を逸脱しない範囲において適宜に変更することが可能である。
【0037】
【発明の効果】
本発明の基礎地盤の施工法によれば、掘削部内で転圧したスラグ層上に複数の枠体を埋設するとともに、各枠体内に既製杭を建て込み、杭周囲にスラグを充填し締め固めることから、スラグ層と枠体を介して周辺地盤をさらに締め固めることができ、これにより、スラグ層と杭とが一体化された強固なスラグ層地盤を造成して、杭の支持力とスラグ層の接地圧、さらには、大きな水平抵抗力により建物等の上部構造物を安定して支持し、その不同沈下を抑制することができる。
また、各既製杭の周囲に、該既製杭を略中心として取り囲む枠体を埋設することから、枠体が杭の周囲を拘束することができ、枠周囲の剪断強度が増大するとともに、既製杭の鉛直支持力と水平耐力を増強することができる。
【0038】
また、スラグに、膨張性及び固化性を有するスラグを用いることにより、掘削部底面の地盤の緩みを一般の土砂よりも比重の重いスラグで圧密することにより防止することができ、また、施工後、充填した製鋼スラグ等の膨張性及び固化性を有するスラグが吸水し、膨張固化することによって、緩んだ掘削部底面の地盤を圧密にすることができ、強固な地盤を得ることができるものとなる。また、産業廃棄物である製鋼スラグ等の有効利用を図ることができ、循環型社会形成の促進に寄与することができる。
この膨張性及び固化性を有するスラグとしては、製鋼スラグ、ゴミ焼却スラグ、汚泥スラグの1種若しくは2種以上の混合物を用いることができ、さらに、膨張性及び固化性を有するスラグは、単独で用いるほか、これに、膨張性を消失した製鋼スラグ、高炉スラグ、フェロアロイスラグ、水砕スラグ、銅製錬スラグ、赤泥、フライアッシュ、ゴミ焼却灰、ガラス破砕物、廃石膏、コンクリート廃材等の産業廃棄物、石膏、生石灰、セメント、砕石、土砂、粘土等の建築用材料、人工材料、鉱物の1種若しくは2種以上を混合した、膨張性及び固化性を有するスラグの膨張性及び固化性を利用できるものを用いることができる。
【0039】
また、枠体の内側に、エージング処理前の製鋼スラグを主成分とする膨張性の強いスラグを充填し締め固めることにより、枠体内側のスラグの膨張によって既製杭が拘束され、既製杭と枠体とが一体となって、その鉛直支持力と水平耐力を増強することができる。
【0040】
また、枠体の外側に、エージング処理後の製鋼スラグを主成分とする高い固化性を有する材料及び/又はエージング処理後の製鋼スラグを主成分とする高い固化性を有する材料とを混合、撹拌したものを充填し締め固めることにより、枠体外側の材料の固化によって枠体が拘束され、枠体を介して既製杭の鉛直支持力と水平耐力を増強することができ、また、掘削した地盤層の土砂を用いることによって、残土の発生量を抑制することができる。
【0041】
また、前記枠体を円筒形状とすることにより、枠体に指向性をなくし、スラグの膨張圧を均一に枠体にかけ、水平耐力を均一にすることができる。
【0042】
また、前記枠体を有底部材で構成することにより、既製杭に作用する荷重を枠体の底蓋面積で受け持たせることができる。
【0043】
また、前記既製杭の長さを、設計上の引き抜き力に見合った長さとするとともに、既製杭の外周に半径外方向に突出する抵抗体を設けることにより、既製杭の引き抜き抵抗力を増大させることができる。
【0044】
さらに、基礎地盤を布状に掘削し、該掘削部内にスラグを充填し転圧してスラグ層を形成し、該スラグ層上に枠体を埋設するようにすることにより、必要な基礎地盤のみを掘削施工して、施工コストの低減を図ることができる。
【図面の簡単な説明】
【図1】本発明の基礎地盤の施工法の一実施例を示し、(a1)は枠体を長くした例の縦断面図、(a2)は同平面図、(b1)は枠体を有底部材で構成した例の縦断面図、(b2)は同平面図である。
【図2】同実施例の基礎地盤の施工法を示し、(a1)は枠体と杭を同じ長さとした例の縦断面図、(a2)は同平面図、(b1)は杭を枠体より長くした例の縦断面図、(b2)は同平面図、(c)は枠体を格子状とした例の平面図である。
【図3】同実施例の基礎地盤の施工法を示し、(a)は第1工程図、(b)は第2工程図、(c)は第3工程図、(d)は第4工程図である。
【図4】同実施例の基礎地盤の施工法を示し、(a)は第5工程図、(b)は第6工程図である。
【図5】同実施例の基礎地盤の施工法に使用する既製杭の例を示す断面図である。
【図6】本発明の他の施工法を示し、(a)は既製杭にスクリュー状体からなる抵抗体を設けた例を示す縦断面図、(b)は同平面図である。
【図7】本発明のさらに他の施工法を示す平面図である。
【符号の説明】
1 表層
2 支持地盤
3 軟弱地盤
3a 土砂
4 掘削部
5a スラグ層
5b 充填材
5c 充填材
6 既製杭
61 抵抗体
7 枠体
71 底蓋
72 通水口
8 支持地盤
S スクリュー状体
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a foundation ground construction method, and in particular, a foundation ground that can stably support a structure such as a building by improving the ground of a relatively shallow layer of soft ground and constructing a ready-made pile. It relates to the construction method.
[0002]
[Prior art]
When building a structure on the ground that cannot directly support the foundation of a structure such as a building, ground improvement such as a shallow mixed processing method is implemented in advance.
The conventional shallow mixing method is a ground improvement of the surface layer that can be excavated with a backhoe, etc., and local ground excavated soil and soil improvement material are mixed and backfilled and rolled to create an improved ground.
[0003]
[Problems to be solved by the invention]
By the way, in the conventional shallow layer mixing method, it is difficult to uniformly mix the excavated soil and the soil improvement material, and uneven soil resistance may occur due to uneven soil improvement, resulting in uneven settlement.
In addition, in soft ground, it is difficult to build anything other than light buildings because the ground strength is small in shallow ground improvement, but on the other hand, if it is a pile foundation, the pile will be longer and costly, and ground subsidence will occur A negative frictional force is applied to the pile, or a “pile pull-out phenomenon” occurs.
[0004]
In view of the problems of the conventional shallow layer mixed processing method, the present invention stabilizes a structure such as a building by improving the ground of a relatively shallow layer of a soft ground and constructing a relatively short ready-made pile. It aims at providing the construction method of the foundation ground which can be supported.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, the foundation ground construction method of the present invention excavates the foundation ground from the surface layer to the ground that can support the upper structure, fills the slag into the excavated portion, and rolls to form a slag layer. The ground construction method is characterized in that a frame body is embedded on the slag layer, a prefabricated pile is built in each frame body, slag is filled around the pile and compacted.
[0006]
This foundation ground construction method embeds multiple frames on the slag layer rolled in the excavation part, builds ready-made piles in each frame, fills the slag around the piles, and compacts them. The slag and the pile in the body can be integrated, whereby the load acting on the pile can be transmitted to the surrounding ground and the slag layer.
[0007]
In this case, slag having expandability and solidification property can be used as the slag.
As the slag having expandability and solidification, steelmaking slag (converter slag and / or electric furnace slag (oxidized slag and / or reduced slag) is referred to. In this case, in particular, a steelmaking slag not subjected to aging treatment is used. In addition, it refers to steelmaking slag that has not lost its expansibility, such as steelmaking slag whose expansibility is adjusted by partially performing an aging treatment.), One or a mixture of two or more kinds of waste incineration slag and sludge slag Can be used.
In addition, slag with expandability and solidification is used alone, and steel slag, blast furnace slag, ferroalloy slag, granulated slag, copper smelting slag, red mud, fly ash, and garbage incineration that have lost expansibility Industrial waste such as ash, crushed glass, waste gypsum, concrete waste, gypsum, quicklime, cement, crushed stone, earth and sand, clay, and other building materials, artificial materials, and one or more of minerals mixed to expand Can be used that can utilize the expansibility and solidification of the slag.
[0008]
As a result, loosening of the ground at the bottom of the excavation part can be prevented by compacting with slag having a specific gravity heavier than general earth and sand, and slag having expandability and solidification properties such as filled steelmaking slag after construction. By absorbing water and expanding and solidifying, the ground at the bottom of the loose excavated part can be consolidated and a solid ground can be obtained. In addition, it is possible to effectively use steelmaking slag, which is an industrial waste, and it is possible to contribute to promoting the formation of a recycling society.
[0009]
Further, the steelmaking slag before the aging treatment, particularly preferably, a highly expandable slag mainly composed of reduced slag can be filled and compacted inside the frame.
[0010]
Thereby, a ready-made pile is restrained by expansion | swelling of the slag inside a frame, a ready-made pile and a frame become united, and the vertical support force and horizontal proof stress can be strengthened.
[0011]
Also, mixing and stirring on the outside of the frame with a material having a high solidification property mainly composed of steelmaking slag after aging treatment and / or a material having a high solidification property mainly composed of steelmaking slag after aging treatment Can be filled and compacted.
[0012]
As a result, the frame body is constrained by the solidification of the material outside the frame body, and the vertical supporting force and horizontal proof stress of the ready-made pile can be enhanced via the frame body, and by using the earth and sand of the excavated ground layer In addition, the amount of residual soil generated can be suppressed.
[0013]
Moreover, the said frame can be made into a cylindrical shape.
[0014]
Thereby, directivity is lost to the frame, and the expansion pressure of the slag can be uniformly applied to the frame, and the horizontal proof stress can be made uniform.
[0015]
Moreover, the said frame can be comprised with a bottomed member.
[0016]
Thereby, the load which acts on a ready-made pile can be received by the bottom cover area of a frame.
[0017]
Moreover, while making the length of the said ready-made pile into the length corresponding to the design drawing-out force, the resistor which protrudes in a radial outward direction can be provided in the outer periphery of a ready-made pile.
[0018]
Thereby, the drawing-out resistance of a ready-made pile can be increased.
[0019]
Furthermore, the foundation ground can be excavated in a cloth shape, slag can be filled in the excavated portion and rolled to form a slag layer, and a frame body can be embedded on the slag layer.
[0020]
Thereby, only a necessary foundation ground is excavated and construction cost can be reduced.
[0021]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, an embodiment of the construction method of the foundation ground of the present invention will be described based on the drawings.
[0022]
1 to 5 show an embodiment of the foundation ground construction method of the present invention.
This foundation ground construction method involves excavating the entire soft ground 3 for constructing the upper structure (not shown) from the surface layer 1 to the supporting ground 2 that can support the upper structure, and expanding and solidifying in the excavated part 4 The slag having properties is rolled while watering to form the slag layer 5a.
The slag layer 5a has a diameter of the frame body 7 (in the case of the rectangular cylinder frame body 7, the length of one side of the frame body 7) in consideration of punching shear by the frame body 7 installed on the slag layer 5a. It is laid so that the layer thickness is about 1/2 times or more.
Then, the frame body 7 is installed on the slag layer 5a, and the outside of the frame body 7 is filled with an appropriate filler 5b, preferably a material having a solidifying property, and compacted by rolling and compacting.
Further, an appropriate filler 5c, preferably a material having a high expansion and solidification property, is filled in each frame body 7 and compacted, and a relatively short ready-made pile 6 is installed at the center position.
In this case, the depth of the excavation part 4 is set to a ground that can support the upper structure depending on the properties of the soft ground 3, the size of the upper structure, the weight, and the like. Is set.
[0023]
In this case, as the slag used for the slag layer 5a and the fillers 5b, 5c, the slag of the steelmaking slag before the aging treatment and / or the slag of the steelmaking slag after the aging treatment so as to have expansion and solidification characteristics according to the application location. Steelmaking slag alone or before aging treatment and / or steelmaking slag after aging treatment and blast furnace slag, ferroalloy slag, granulated slag, copper smelting slag, red mud, fly ash, garbage incineration slag, garbage incineration ash, sludge slag , Industrial waste such as crushed glass, waste gypsum, concrete waste, gypsum, quicklime, cement, crushed stone, earth and sand, clay and other building materials, artificial materials, or a mixture of minerals Like that.
[0024]
In addition, by using the soil of the ground layer that replaces slag, etc., in the slag layer 5a and fillers 5b and 5c within a range that does not lose the purpose of the present invention, the amount of generated residual soil is suppressed and the construction cost is reduced. can do.
[0025]
More specifically, in the slag layer 5a, while using the expandability of slag, the solidification property is also regarded as important, so the expansion of free CaO, free MgO and the like, the expandability containing a solidifying component, and Use solidifying slag.
As the slag having expandability and solidification property, steelmaking slag (converter slag and / or electric furnace slag (oxidized slag and / or reduced slag) is referred to, and in this case, in particular, an aging treatment (specifically, particularly Although not limited, for example, steelmaking slag that has not been maintained in steam at about 100 ° C for about 100 hours, or has not been subjected to stabilization treatment by leaving it outdoors for a long period of time, or part of the aging treatment Steelmaking slag that does not lose its expansibility, such as steelmaking slag whose expansibility has been adjusted by performing the same, or a mixture of two or more kinds of waste incineration slag and sludge slag can be used.
In addition, slag with expandability and solidification is used alone, and steel slag, blast furnace slag, ferroalloy slag, granulated slag, copper smelting slag, red mud, fly ash, and garbage incineration that have lost expansibility Industrial waste such as ash, crushed glass, waste gypsum, concrete waste, gypsum, quicklime, cement, crushed stone, earth and sand, clay, and other building materials, artificial materials, and one or more of minerals mixed to expand It is possible to use those that can utilize the expansibility and solidification of slag having properties and solidification, and in particular, it is preferable to use steelmaking slag before aging treatment and slag after aging treatment by adding a strong alkaline substance. .
Further, the filler 5b was excavated with a material having a high solidification property mainly composed of steelmaking slag after aging treatment and / or a material having a high solidification property mainly composed of steelmaking slag after aging treatment. It is desirable to use a material obtained by mixing and stirring the earth and sand of the ground layer, and to use a material having the same high expansion and solidification properties as the slag layer 5a for the filler 5c.
As a result, the filler 5b hardens quickly, and the slag layer 5a hardens while following the expansion.
The upper load applied to the slag layer 5a can be used as an overload pressure to recover the bottom surface of the excavated bottom and eliminate loosening.
And especially in the construction method of the foundation ground of a present Example, the material which has high expansion | swelling and solidification property in the filler 5c with which the inner side of the frame 7 is filled, for example, the slag with strong expansion | swelling which has a reduction slag as a main component Is used, the ready-made pile 6 is restrained by the expansion of the filler 5c inside the frame body 7, and the ready-made pile 6 and the frame body 7 are united to enhance the vertical support force and the horizontal strength. it can.
[0026]
As shown in FIGS. 1A1 and 1A2, the frame body 7 is preferably formed in a cylindrical shape. As a result, the frame body has no directivity, and the horizontal proof stress can be made uniform by uniformly applying the expansion pressure of the slag to the frame body.
Further, the frame body 7 may have another shape such as a rectangular tube connected in parallel.
And by setting the front-end | tip position of the frame 7 so that it may be located below the pile front-end position of the ready-made pile 6, the integrity of the ready-made pile 6 and the frame 7 increases more, and the restraint force of the ready-made pile 6 is increased. Can be increased.
On the other hand, as shown in FIGS. 1 (b 1) and (b 2), the frame body 7 can be formed of a bottomed cylindrical member having a bottom cover 71. As a result, the column load of the ready-made pile 6 can be handled by the bottom cover area, and the vertical support force can be increased.
In addition, when there is a bottom cover 71, the frame 7 is previously made by integrating the filler 5c and the ready-made pile 6 in another place, and the integrated frame 7 is placed in the slag layers 5a and 5b. It can also be installed.
[0027]
Moreover, as shown to FIG. 2 (a1) (a2), the frame 7 can also be set so that the lower end position and the pile front-end | position position of the ready-made pile 6 may become substantially the same in the state without a bottom cover. In addition, as shown in FIGS. 2 (b 1) and 2 (b 2), the ready-made pile 6 can be set long so that the tip position of the pile is positioned below the lower end position of the frame body 7.
[0028]
Moreover, the frame 7 can also be assembled in a lattice shape as shown in FIG. In this case, slag with strong expansibility can be used as the filler 5c.
[0029]
In addition, the frame 7 having a corrugated shape in which the peripheral wall is vertically undulated, for example, a kind of drum can, is preferable because the peripheral surface supporting force is increased. In addition, the diameter of the frame body 7 (in the case of the rectangular cylinder frame body 7, the length of one side of the frame body 7) is appropriately about 2 to 6 times the pile diameter.
[0030]
On the other hand, as the ready-made pile 6, for example, a steel pipe pile or a PHC concrete pile having a diameter of about 400 mm or less can be used. For example, in a steel pipe pile, a screw-like body S or the like is provided at the tip, and rotational press-fitting is performed. Can be built (see FIG. 2 (b1)).
Moreover, as for the ready-made pile 6, as shown in FIG. 5 (a)-(d), the direction of the nodal piles 61 and 62, the corrugated pile 63, the taper pile 64, etc. with the filler 5c rather than the straight-shaped thing. This is preferable for improving the adhesion of the pile and increasing the frictional force of the peripheral surface of the pile.
And the supporting force of the joint pile increases due to the bearing pressure effect under each joint, and the ready-made pile presses the closed end pile (not shown), so that the periphery of the filler 5c through the ready-made pile 6 The ground can be further compacted. Note that PHC concrete piles (node piles, tapered piles, corrugated piles, etc.) may be pre-bored and installed by auger drills having substantially the same diameter, or may be directly press-fitted.
[0031]
Next, the construction procedure of this foundation ground construction method will be described with reference to FIGS. (1) First, as shown in FIG. 3A, the soft ground 3 is excavated to the ground 2 that can support the upper structure. In this case, all the excavated earth and sand 3a is discharged to the ground.
(2) Next, as shown in FIG. 3 (b), a certain amount of slag forming the slag layer 5a is uniformly introduced into the excavation part 4, and is compacted by compaction with a compacting machine or the like.
By sprinkling water, the effect of compacting the slag layer 5a can be enhanced, and the hydration reaction of the slag layer 5a can be promoted to accelerate the expansion and solidification.
Moreover, as the slag of the slag layer 5a, a slag having a poor particle size distribution, specifically, a mixture suitable for compaction mixed with a coarse particle size to a fine particle size is preferable.
(3) Next, as shown in FIG. 3 (c), the frame body 7 is placed on the slag layer 5a so as to be partially buried. At this time, the penetration depth of the frame body 7 is preferably 20% or more of the diameter of the frame body 7.
Here, the frame body 7 made of a bottomed member is used, and a water passage (water-permeable opening) 72 is provided in the bottom lid 71 of the frame body 7 (see FIG. 1). Thereby, the hydration reaction of the filler 5c located inside the frame body 7 and the bottomed bottom can be prevented from being hindered.
(4) Then, as shown in FIG. 3 (d), the steelmaking slag after the aging treatment and / or the steelmaking slag after the aging treatment and the earth and sand of the excavated ground layer are used as the filler 5b around the frame body 7. A mixed and stirred material having solidification properties is charged, and compacted by compaction with a compacting machine or the like.
In this case, the watering can enhance the effect of compacting the filler 5b and promote the hydration reaction of the filler 5b to accelerate the expansion and solidification.
(5) Further, as shown in FIG. 4 (a), a material having high expansion and solidification properties mainly composed of steelmaking slag before aging treatment is introduced into the frame body 7 as a filler 5c and tightened. Compress and compact with a compacting machine.
In this case, the watering can enhance the compacting effect of the filler 5c and promote the hydration reaction of the filler 5c to accelerate the expansion and solidification.
In addition, when putting slag and forming the filler 5c, the ready-made pile 6 may be installed simultaneously.
{Circle over (6)} Then, as shown in FIG. 4 (b), the ready-made pile 6 is built into the filler 5 c inside the frame body 7 by rotational press-fitting in the steel pipe pile.
Finally, the frame body 7 restrains the expansion of the filler 5c in the frame body 7, and the frame body 7 and the filler material 5c are integrated, whereby the ready-made pile 6 can be firmly supported.
[0032]
In this case, the tip of the ready-made pile 6 and the bottom lid 71 of the frame body 7 are brought into contact as shown in FIG. Thereby, since the load which acted on the pile 6 is received by the bottom cover 71 of the frame 7, it can be directly supported by the slag layer 5a, and a large vertical support force can be obtained.
[0033]
Furthermore, the other Example of the construction method of the foundation ground of this invention is described.
The length of the ready-made pile 6 is set to a length corresponding to the design pull-out force. For example, as shown in FIG. 6, the ready-made pile can be built into the support ground 2 through the filler 5 c.
Moreover, it is also possible to provide the resistor 61 which protrudes in a radial outward direction on the outer periphery of the ready-made pile 6, and in this case, by pulling out the ready-made pile 6 by configuring the resistor 61 with the screw-like body as described above. While increasing resistance, the propulsive force at the time of building the ready-made pile 6 in the filler 5c and the support ground 8 can be obtained.
[0034]
In addition, as shown in FIG. 7, the foundation ground is excavated into a cloth shape, and a plurality of frames 7 are embedded in the filler 5 b of the cloth-shaped excavation part 4, and the ready-made piles 6 are embedded in the respective frame bodies 7. It is also possible to build up and fill the slag 5c around the pile and compact.
In this case, the central part surrounded by the cloth-like excavation part 4 and the outer part of the excavation part 4 can be left without changing the original ground. In this embodiment, the diameter of the frame body 7 is about four times the diameter of the ready-made pile 6.
Thereby, only the necessary foundation ground can be excavated and the cost for ground improvement can be reduced.
[0035]
Thus, in the construction method of the foundation ground of this embodiment, since a plurality of relatively short ready-made piles 6 are built in the slag layer 5a compacted in the excavation part 4, the filler 5c and the pile 6 are integrated. A solid foundation pile is formed, and the supporting force of the pile 6 and the contact pressure of the slag layer 5a, and the frame 7, the filler 5c, and the ready-made pile 6 are integrated, and the filler is more than ordinary earth and sand. Since the internal frictional resistance of 5c is large, it is possible to stably support an upper structure such as a building by a large horizontal resistance force and to suppress the uneven settlement.
Moreover, since the frame body surrounding the ready-made pile is arranged around each ready-made pile, the frame body can restrain the periphery of the pile, the shear strength around the frame is increased, and the ready-made pile is manufactured. The vertical bearing capacity and horizontal strength of the pile can be increased.
[0036]
As mentioned above, although the construction method of the foundation ground of this invention was demonstrated based on the Example, for example, the order of embedding a frame and a ready-made pile is not limited to the above, and this invention is suitably in the range which does not deviate from the summary. It is possible to change to
[0037]
【The invention's effect】
According to the foundation ground construction method of the present invention, a plurality of frames are embedded on the slag layer rolled in the excavation part, and prefabricated piles are built in each frame, and the slag is filled and compacted around the piles. Therefore, the surrounding ground can be further compacted through the slag layer and the frame, thereby creating a strong slag layer ground in which the slag layer and the pile are integrated, and the bearing capacity and slag of the pile It is possible to stably support an upper structure such as a building by a ground contact pressure of the layer and a large horizontal resistance force, and to suppress the uneven settlement.
Moreover, since the frame body surrounding the ready-made pile is embedded around each ready-made pile, the frame body can restrain the periphery of the pile, and the shear strength around the frame increases, and the ready-made pile It is possible to increase the vertical support force and horizontal proof stress.
[0038]
In addition, by using slag with expandability and solidification as the slag, loosening of the ground at the bottom of the excavated part can be prevented by compacting with slag having a higher specific gravity than general earth and sand. The slag having expandability and solidification, such as filled steelmaking slag, absorbs water and expands and solidifies, so that the ground on the bottom of the loose excavation part can be consolidated and a solid ground can be obtained. Become. In addition, it is possible to effectively use steelmaking slag, which is an industrial waste, and it is possible to contribute to promoting the formation of a recycling society.
As the slag having expandability and solidification, one or a mixture of steelmaking slag, waste incineration slag, sludge slag can be used, and further, the slag having expandability and solidification can be used alone. In addition to this, industries such as steelmaking slag, blast furnace slag, ferroalloy slag, granulated slag, copper smelting slag, red mud, fly ash, waste incineration ash, crushed glass, waste gypsum, concrete waste, etc. The expansibility and solidification of slag that has expansibility and solidification, mixed with one or more of building materials such as waste, gypsum, quicklime, cement, crushed stone, earth and sand, artificial materials and minerals What can be used can be used.
[0039]
Also, by filling the inside of the frame with highly inflatable slag mainly composed of steelmaking slag before aging treatment, the ready-made pile is restrained by the expansion of the slag inside the frame, and the ready-made pile and the frame The body and the body can be integrated to enhance its vertical support force and horizontal strength.
[0040]
Also, mixing and stirring on the outside of the frame with a material having a high solidification property mainly composed of steelmaking slag after aging treatment and / or a material having a high solidification property mainly composed of steelmaking slag after aging treatment By filling and compacting the material, the frame body is constrained by solidification of the material outside the frame body, and the vertical support force and horizontal strength of the ready-made piles can be enhanced via the frame body. By using the earth and sand of the layer, the amount of residual soil generated can be suppressed.
[0041]
Moreover, by making the said frame into a cylindrical shape, the directivity of the frame can be eliminated, the expansion pressure of the slag can be uniformly applied to the frame, and the horizontal proof stress can be made uniform.
[0042]
Moreover, the load which acts on a ready-made pile can be received by the bottom cover area of a frame by comprising the said frame with a bottomed member.
[0043]
In addition, the length of the ready-made pile is set to a length commensurate with the design pull-out force, and the pull-out resistance force of the ready-made pile is increased by providing a resistor projecting radially outward on the outer periphery of the ready-made pile. be able to.
[0044]
Furthermore, by excavating the foundation ground into a cloth shape, filling the excavated portion with slag and rolling it to form a slag layer, and embedding a frame on the slag layer, only the necessary foundation ground is obtained. Construction costs can be reduced by excavation.
[Brief description of the drawings]
FIG. 1 shows an embodiment of a foundation ground construction method according to the present invention, wherein (a1) is a longitudinal sectional view of an example in which a frame is elongated, (a2) is the same plan view, and (b1) is a frame having a frame. The longitudinal cross-sectional view of the example comprised by the bottom member, (b2) is the same top view.
FIG. 2 shows the construction method of the foundation ground of the embodiment, (a1) is a longitudinal sectional view of an example in which the frame body and the pile have the same length, (a2) is the same plan view, and (b1) is the frame of the pile. The longitudinal cross-sectional view of the example made longer than the body, (b2) is the same top view, (c) is the top view of the example which made the frame the grid | lattice form.
FIGS. 3A and 3B show a construction method of the foundation ground of the embodiment, wherein FIG. 3A is a first process diagram, FIG. 3B is a second process diagram, FIG. 3C is a third process diagram, and FIG. FIG.
4A and 4B show a construction method of the foundation ground according to the embodiment, where FIG. 4A is a fifth process diagram and FIG. 4B is a sixth process diagram.
FIG. 5 is a cross-sectional view showing an example of a ready-made pile used in the foundation ground construction method of the embodiment.
6A and 6B show another construction method of the present invention, wherein FIG. 6A is a longitudinal sectional view showing an example in which a resistor made of a screw-like body is provided on a ready-made pile, and FIG. 6B is a plan view of the same.
FIG. 7 is a plan view showing still another construction method of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 Surface layer 2 Support ground 3 Soft ground 3a Earth and sand 4 Excavation part 5a Slag layer 5b Filler 5c Filler 6 Ready-made pile 61 Resistor 7 Frame 71 Bottom cover 72 Water inlet 8 Support ground S Screw-like body

Claims (10)

基礎地盤を表層から上部構造物を支持できる地盤まで掘削し、該掘削部内にスラグを充填し転圧してスラグ層を形成する基礎地盤の施工法であって、前記スラグ層上に枠体を埋設するようにするとともに、各枠体内に既製杭を建て込み、杭周囲にスラグを充填し締め固めることを特徴とする基礎地盤の施工法。The foundation ground is excavated from the surface layer to the ground that can support the upper structure, the slag is filled into the excavated part, and the slag layer is formed by rolling and forming a slag layer, and a frame is embedded on the slag layer A construction method for the foundation ground, characterized in that prefabricated piles are built in each frame, and slag is filled and compacted around the piles. スラグに、膨張性及び固化性を有するスラグを用いることを特徴とする請求項1記載の基礎地盤の施工法。The foundation ground construction method according to claim 1, wherein slag having expandability and solidification is used for the slag. 膨張性及び固化性を有するスラグが、製鋼スラグ、ゴミ焼却スラグ、汚泥スラグの1種若しくは2種以上の混合物からなることを特徴とする請求項2記載の基礎地盤の施工法。3. The foundation ground construction method according to claim 2, wherein the slag having expandability and solidification properties comprises one or a mixture of steelmaking slag, garbage incineration slag and sludge slag. 膨張性及び固化性を有するスラグに、膨張性を消失した製鋼スラグ、高炉スラグ、フェロアロイスラグ、水砕スラグ、銅製錬スラグ、赤泥、フライアッシュ、ゴミ焼却灰、ガラス破砕物、廃石膏、コンクリート廃材等の産業廃棄物、石膏、生石灰、セメント、砕石、土砂、粘土等の建築用材料、人工材料、鉱物の1種若しくは2種以上を混合した、膨張性及び固化性を有するスラグの膨張性及び固化性を利用できるものであることを特徴とする請求項2又は3記載の基礎地盤の施工法。Steel slag, blast furnace slag, ferroalloy slag, granulated slag, copper smelting slag, red mud, fly ash, garbage incinerated ash, glass crushed material, waste plaster, concrete Industrial materials such as waste materials, gypsum, quicklime, cement, crushed stone, earth and sand, building materials such as clay, artificial materials, and one or more types of minerals are mixed, and inflatable and solidifying slag expandability The foundation ground construction method according to claim 2 or 3, wherein the solidification property can be utilized. 枠体の内側に、エージング処理前の製鋼スラグを主成分とする膨張性の強いスラグを充填し締め固めることを特徴とする請求項1、2、3又は4記載の基礎地盤の施工法。The foundation ground construction method according to claim 1, 2, 3, or 4, wherein the inside of the frame body is filled with a highly expandable slag mainly composed of steelmaking slag before aging treatment and then compacted. 枠体の外側に、エージング処理後の製鋼スラグを主成分とする高い固化性を有する材料及び/又はエージング処理後の製鋼スラグを主成分とする高い固化性を有する材料とを混合、撹拌したものを掘削した地盤層の土砂を充填し締め固めることを特徴とする請求項1、2、3、4又は5記載の基礎地盤の施工法。What was mixed and stirred on the outside of the frame with a material having a high solidification property mainly composed of steel slag after aging treatment and / or a material having a high solidification property mainly composed of steel slag after aging treatment 6. The foundation ground construction method according to claim 1, 2, 3, 4, or 5, wherein the earth and sand of the ground layer excavated is filled and compacted. 前記枠体を円筒形状としたことを特徴とする請求項1、2、3、4、5又は6記載の基礎地盤の施工法。7. The foundation ground construction method according to claim 1, wherein the frame body has a cylindrical shape. 前記枠体を有底部材で構成したことを特徴とする請求項1、2、3、4、5、6又は7記載の基礎地盤の施工法。8. The foundation ground construction method according to claim 1, wherein the frame body is formed of a bottomed member. 前記既製杭の長さを、設計上の引き抜き力に見合った長さとするとともに、既製杭の外周に半径外方向に突出する抵抗体を設けたことを特徴とする請求項1、2、3、4、5又は6記載の基礎地盤の施工法。The length of the ready-made pile is set to a length commensurate with the design pulling force, and a resistor projecting radially outward is provided on the outer periphery of the ready-made pile. The foundation ground construction method according to 4, 5 or 6. 基礎地盤を布状に掘削し、該掘削部内にスラグを充填し転圧してスラグ層を形成し、該スラグ層上に枠体を埋設するようにしたことを特徴とする請求項1、2、3、4、5、6又は7記載の基礎地盤の施工法。The foundation ground is excavated into a cloth shape, filled with slag in the excavated part and rolled to form a slag layer, and a frame is embedded on the slag layer. Construction method for foundation ground as described in 3, 4, 5, 6 or 7.
JP2003025393A 2002-02-04 2003-02-03 Construction method of foundation ground Expired - Fee Related JP3894893B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003025393A JP3894893B2 (en) 2002-02-04 2003-02-03 Construction method of foundation ground

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2002027150 2002-02-04
JP2002-27150 2002-02-04
JP2003025393A JP3894893B2 (en) 2002-02-04 2003-02-03 Construction method of foundation ground

Publications (2)

Publication Number Publication Date
JP2003293354A JP2003293354A (en) 2003-10-15
JP3894893B2 true JP3894893B2 (en) 2007-03-22

Family

ID=29253488

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003025393A Expired - Fee Related JP3894893B2 (en) 2002-02-04 2003-02-03 Construction method of foundation ground

Country Status (1)

Country Link
JP (1) JP3894893B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5791886B2 (en) * 2010-11-24 2015-10-07 株式会社竹中工務店 Pile construction method in contaminated soil
FR3084380B1 (en) * 2018-07-30 2020-10-23 Saipem Sa PROCESS FOR INSTALLING A TUBULAR METAL PILE IN ROCKY SOIL
WO2022255988A1 (en) * 2021-06-01 2022-12-08 Halliburton Energy Services, Inc. Expanding metal used in forming support structures

Also Published As

Publication number Publication date
JP2003293354A (en) 2003-10-15

Similar Documents

Publication Publication Date Title
EP2018454B1 (en) Ground engineering method
JP3894893B2 (en) Construction method of foundation ground
JP4010905B2 (en) Pile embedding method and equipment used therefor
JP4101724B2 (en) Steel pipe pile construction method
JP4223780B2 (en) Foundation pile structure and foundation pile construction method in soft ground
JP4057873B2 (en) Foundation pile structure on support ground and construction method of foundation pile
JP3380861B1 (en) Pile construction method
HU225407B1 (en) Procedure for augmentation physical parameters and bearing capacity of ground and for diminution time of consolidation and expected consolidation settlement of thereof
JP2003221828A (en) Burying method for prefabricated pile
JP2005146609A (en) Ground improving method
JP3996837B2 (en) Improvement method for soft ground
JP4145771B2 (en) Static press-fit method for steel pipe piles
JP3099040B2 (en) Embankment culvert
JP2003221825A (en) Work execution method for foundation ground
JP4118694B2 (en) Ground improvement method
CN207419448U (en) Novel composite foundation pile based on static pressure construction
JP4754121B2 (en) Improvement method for soft ground
JP4080305B2 (en) Construction method of foundation using slag having expansibility and solidification
JP4223781B2 (en) Ground improvement foundation method for soft ground.
JP2004169303A (en) Prefabricated pile and work execution method therefor
JP2004176466A (en) Foundation pile structure having expanded bottom part
JPS6070241A (en) Construction of sewage pipe culvert
JP3787536B2 (en) Foundation construction method
GB1577199A (en) Method of constructing underground gallery
JP2009068247A (en) Improved ground material and settlement prevention structure of dirt floor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041026

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061012

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20061114

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061212

R150 Certificate of patent or registration of utility model

Ref document number: 3894893

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091222

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 4

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101222

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111222

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121222

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121222

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131222

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R360 Written notification for declining of transfer of rights

Free format text: JAPANESE INTERMEDIATE CODE: R360

R370 Written measure of declining of transfer procedure

Free format text: JAPANESE INTERMEDIATE CODE: R370

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees