JP3890118B2 - Scaffolding plate support device for concrete placement - Google Patents

Scaffolding plate support device for concrete placement Download PDF

Info

Publication number
JP3890118B2
JP3890118B2 JP23216297A JP23216297A JP3890118B2 JP 3890118 B2 JP3890118 B2 JP 3890118B2 JP 23216297 A JP23216297 A JP 23216297A JP 23216297 A JP23216297 A JP 23216297A JP 3890118 B2 JP3890118 B2 JP 3890118B2
Authority
JP
Japan
Prior art keywords
horizontal
concrete
beam member
scaffolding plate
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP23216297A
Other languages
Japanese (ja)
Other versions
JPH1171897A (en
Inventor
好宏 與那原
勝 金親
Original Assignee
ジャパン スチールス インターナショナル株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ジャパン スチールス インターナショナル株式会社 filed Critical ジャパン スチールス インターナショナル株式会社
Priority to JP23216297A priority Critical patent/JP3890118B2/en
Publication of JPH1171897A publication Critical patent/JPH1171897A/en
Application granted granted Critical
Publication of JP3890118B2 publication Critical patent/JP3890118B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は基礎構造物、橋脚、壁構造建物、地下壁、擁壁などのようにコンクリートを打ち込むことにより形成されるコンクリート構造物を構築する際に使用される足場板を支持するコンクリート足場板支持装置に関する。
【0002】
【従来の技術】
地下鉄、地下室、地下道などの地下構造物は、内部に鉄筋や鉄骨が組み込まれたコンクリート製の壁構造物や基礎構造物を構築することにより形成されており、ホテルやマンションなどの高層建築物も同様にコンクリート製の壁構造物や基礎構造物を構築することにより建築されている。さらに、崖などの土止めのための擁壁や橋脚なども、コンクリートにより形成されている。
【0003】
上述した種々のコンクリート構造物は、内部に鉄筋が配筋された鉄筋コンクリート構造のもの、鉄骨骨組のまわりに鉄筋が配筋されコンクリートで一体化した鉄骨鉄筋コンクリート構造のものなどがある。このような、コンクリート構造物を構築する際には、その構造物の内部に埋め込まれる鉄骨や鉄筋などを構築する鉄筋工事と、構造物の外表面を形成するための型枠を構築する型枠工事、および型枠内にコンクリートを打ち込むコンクリート工事などが施工される。
【0004】
型枠工事を行う際には、型枠材を固定するために垂直支持棒が基盤に取り付けられ、その垂直支持棒の外側にはそれぞれ水平方向に延びる水平固定棒材が上下方向に所定の間隔毎に取り付けられることになる。コンクリート工事にあっては、型枠の上方からコンクリートが打ち込まれることになるので、その作業を行うために型枠材の外側に足場板を配置することが必要となる。その足場板を支持するために、足場ブラケットあるいは型枠ブラケットとも言われるコンクリート打設用足場板支持装置を型枠材の外側に取り付けるようにしている。
【0005】
【発明が解決しようとする課題】
従来では、水平梁部材と垂直支柱部材とによりL字形状の足場ブラケットを形成し、水平梁部材の先端側と垂直支柱部材の下端側とを補強用の傾斜梁部材により連結するようにしている。そして、垂直支柱部材の上端部には型枠材の外側に設けられた上側の水平固定棒材に係合されるフックを設け、垂直支柱部材の下端部には下側の水平固定棒材に係合する受金具を設けており、その受金具をトグルピンにより上下方向に所定のピッチで固定し得るようにしている。
【0006】
しかしながら、このような従来の構造では、型枠材の外側にそれぞれ水平方向に延びて配置される複数本の水平固定棒材の上下方向の間隔を高い精度としなければ、確実にフックと受金具のそれぞれが水平固定棒材に所望の荷重を伝達することができなくなる。そのため、コンクリート構造物を構築するための、型枠工事にあっては、水平固定棒材の上下方向の間隔つまりピッチを高い精度としなければならず、その工事の能率を向上させることが困難であった。
【0007】
本発明の目的は、コンクリート構造物の構築を迅速かつ能率的に行い得るようにすることにある。
【0008】
本発明の前記ならびにその他の目的と新規な特徴は、本明細書の記述および添付図面から明らかになるであろう。
【0009】
【課題を解決するための手段】
本願において開示される発明のうち、代表的なものの概要を簡単に説明すれば、以下のとおりである。
【0010】
すなわち、本発明のコンクリート打設用足場板支持装置は、コンクリート構造物を構築する際に、コンクリートが打ち込まれる空間を形成する型枠材の外側にそれぞれ水平方向に延び上下方向に所定の間隔毎に固定された複数の水平固定棒材に配置され、かつ足場板を支持するコンクリート打設用足場板支持装置であって、上側の前記水平固定棒材に係合する上側係合部が一端部に設けられ、かつ手摺り用支柱が装着される支柱支持部材が他端部に設けられた水平梁部材と、前記水平梁部材に移動自在に取り付けられ、かつ任意の位置で前記水平梁部材に固定される移動部材と、上端部が前記移動部材にピン結合され、かつ下側の前記水平固定棒材に係合する下側係合部が下端部に設けられた傾斜梁部材とを有し、前記水平梁部材の上に足場板を配置して前記足場板の上において作業することにより前記コンクリート構造物を構築し得るようにしたことを特徴とする。
【0011】
また、本発明のコンクリート打設用足場板支持装置は、上側の前記水平固定棒材に前記水平梁部材を締結して前記水平固定棒材から外れるのを防止するクランプ部材を有することを特徴とする。
【0012】
本発明にあっては、上側係合部が係合される水平固定棒材と、下側係合部が形成される他の水平固定棒材との上下方向の間隔にずれが存在していても、そのずれを吸収してそれぞれの係合部は確実にそれぞれの水平固定棒材に密着した状態となる。
【0013】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて詳細に説明する。
【0014】
図1は地下室を構築するための地下構造物の一例を示す図であり、この地下構造物は、地盤面10を掘削することにより形成される凹所11内に構築されており、凹所11の垂直の地肌面に沿って構築される構内側壁部12、スラブ床部13、および基礎部ないし仕切り壁部14などを有している。
【0015】
図2は図1に示された仕切り壁部14の何れかを構築するための型枠工事を行っている状態を示す図であり、コンクリート構造物であり仕切り壁部14の内部に埋め込まれる鉄筋20が配筋された状態が示されている。図示する鉄筋20は、上下方向に延びる垂直鉄筋20aと、水平方向に延びる水平鉄筋20bとを有している。
【0016】
コンクリート構造物としての仕切り壁部の両側面に対応し、コンクリートが打ち込まれる空間を区画形成するための堰板つまり型枠材21が配置されており、型枠材21はこれの外側に位置する複数本の垂直固定棒材22により支持されている。垂直固定棒材22の外側には、それぞれ水平方向に延び、上下方向に所定の間隔となった複数の水平固定棒材23が取り付けられている。水平固定棒材23は2本を一対として、図2に示すように、型枠材21の高さ寸法に応じて複数対が取り付けられており、それぞれの対の水平固定棒材23は、左右の型枠材21の外側において上下方向の位置が相互に対応するようになっている。図示する場合には、垂直固定棒材22および水平固定棒材23は、それぞれ中空の丸パイプにより形成されている。ただし、それぞれの棒材22,23を断面四角形の中空の角パイプによって形成するようにしても良い。
【0017】
図2において左右両側の型枠材21相互の間隔を一定に保持するために、型枠材21の外側に上下位置が対応する一対の水平固定棒材23の間を貫通させてタイボルト24が設けられており、それぞれのタイボルト24の両端部にはリブ座金25が装着され、それぞれのリブ座金25はタイボルト24のねじ部にねじ結合するナット26により締結されている。
【0018】
図2に示すように型枠材21を固定することにより、内部にコンクリートが打ち込まれる空間14aを区画形成するための型枠が形成されることになる。左右それぞれの型枠材21の外側には、図3に示すように、作業者がコンクリートの打ち込みつまり打設作業を行うための足場板27が取り付けられる。
【0019】
図4は足場板27を支持するための本発明の一実施の形態であるコンクリート打設用足場板支持装置30を示す図であり、図5は図2に示された型枠の左右両側に図4の足場板支持装置30が取り付けられた状態を示す。なお、この足場板支持装置30は、型枠ブラケットあるいは足場ブラケットとも言われており、図3にあっては、左右両側の型枠材21のそれぞれに足場板支持装置30が取り付けられているが、左側の型枠材21の外側にのみ足場板27が取り付けられ、右側の型枠材21には、足場板27がまだ取り付けられていない状態が示されている。
【0020】
この足場板支持装置30は、横断面形状が正四角形となった中空金属製の角パイプにより形成された水平梁部材31を有し、その一端部には水平固定棒材23に係合する上側係合部32が設けられ、その他端部には手摺り用支柱28が装着されるサヤ管33が支柱支持部材として設けられている。このサヤ管33は断面形状が円形となった金属製の丸パイプにより形成されている。ただし、このサヤ管33を断面形状が四角形となった金属製の角パイプにより形成するようにしても良い。また、支柱支持部材としては、サヤ管33に代えてクランプ部材を用いるようにしても良い。
【0021】
水平梁部材31の外側には横断面形状が正四角形となった移動部材34が水平梁部材31に沿ってその長手方向に移動自在に取り付けられている。この移動部材34にはねじ部材35が設けられ、ねじ部材35を緩めると移動部材34を移動させることができ、締め付けると移動部材34をその位置で固定することができる。
【0022】
移動部材34には連結金具36が取り付けられており、移動部材34には連結金具36の部分で傾斜梁部材37の上端部がピン38によりこれを中心に揺動自在にピン結合されている。この傾斜梁部材37は水平梁部材31と同様に中空金属製の角パイプにより形成されている。この傾斜梁部材37の下端部には、前記上側係合部32が係合する水平固定棒材23よりも下側に位置する他の水平固定棒材23に係合する下側係合部39が設けられている。この下側係合部39は、金属製の板材をU字形状に折り曲げることにより形成されている。なお、水平梁部材31および傾斜梁部材37を断面円形の中空丸パイプにより形成するようにしても良い。
【0023】
このような構造の足場板支持装置30は、図3に示すように、同一高さの水平固定棒材23に、足場板27の長さに対応させて所定の間隔毎に取り付けられ、左右それぞれの型枠材21の外側に複数個配置されることになる。それぞれの足場板支持装置30を上側と下側のそれぞれの水平固定棒材23に係合させる際には、それぞれの水平固定棒材23相互間の距離に誤差ないしずれが発生していても、図6に示すように、移動部材34の位置を実線で示す位置や二点鎖線で示す位置などのように任意の位置に設定することによって、水平梁部材31を所定の水平度とすることができる。しかも、それぞれの係合部32,39は、水平固定棒材23に対して隙間なく確実に接触することになるので、足場板支持装置30の荷重は2本の水平固定棒材に対して分散して伝達される。
【0024】
上側係合部32は図4に示されるように水平梁部材31の両側面に固定される2つのクランプ部材32a,32bによって形成されている。
【0025】
図7は上側係合部32を形成する一方のクランプ部材32aの一部を拡大して示す図であり、クランプ部材32aは水平固定棒材23が入り込む凹部41を有し、クランプ部材32aには、凹部41内に入り込んだ水平固定棒材23から上側係合部32が外れないようにするためのクランプ片42が移動自在に取り付けられている。このように、上側係合部32にクランプ機能を持たせることによって、足場板支持装置30が振動などによって不用意に水平固定部材23から外れることを確実に防止することができる。
【0026】
クランプ部材32aには2つの支持ピン43,44が固定されており、クランプ片42にはそれぞれの支持ピン43,44が係合するカム溝45,46が形成されている。クランプ片42を図7において実線で示すクランプ位置に設定すると、クランプ片42が凹部41に出入口41aを水平固定棒材23の外径よりも狭くして上側係合部32が水平固定棒材23から外れることが防止される。一方、クランプ片42を二点鎖線で示す位置に設定すると、出入口41aの幅が広くなって、上側係合部32を水平固定棒材23から外すことができる。それぞれの支持ピン43,44はそれぞれのカム溝45,46の幅よりも大きい頭部を有し、クランプ片42がクランプ部材32aから外れないようになっている。なお、他のクランプ部材32bも同様の構造となっている。また、下側係合部39としては、上側係合部32と同様の構造としても良い。
【0027】
次に、上述した足場板支持装置を用いて型枠材21の外側に足場板27を取り付ける手順について説明する。
【0028】
コンクリート構造物の鉄筋工事が終了した状態のもとで、コンクリート構造物を構築するために、コンクリートが打ち込まれる空間を形成する型枠材21を取り付ける。図2に示すように、コンクリート構造物が図1に示される仕切り壁や基礎部14の場合には、その両面に対応させて型枠材21が取り付けられることになる。型枠材21は所定の高さと幅を有しており、複数枚が直線状などの所定の姿勢で配置され、それぞれの型枠材21が複数本の垂直固定棒材22と複数本の水平固定棒材23によって固定される。相互に対向する型枠材21は複数本のタイボルト24によって所定の間隔に保持される。
【0029】
垂直固定棒材22相互の間隔つまりピッチ、水平固定棒材23相互の間隔およびタイボルト24の間隔は、コンクリート構造物の厚みなどの条件によって設定される。このようにして、型枠材21が据え付けられた後に、図3に示すように、所定の高さの水平固定棒材23に図4に示す足場板支持装置30が相互に所定の間隔を置いて複数個取り付けられる。
【0030】
その取り付けに際しては、ねじ部材35を緩めて移動部材34が水平梁部材31に沿って移動し得る状態として、上側係合部32を所定の水平固定棒材23に、そして、その水平固定棒材23よりも下側に位置する水平固定棒材23に下側係合部39をそれぞれ係合させる。上側係合部32を上側の水平固定棒材23に係合する際には、図7に示すように、クランプ片42を二点鎖線に示す位置にずらしておき、係合終了後に実線で示す位置にずらして上側係合部32が水平固定棒材23から外れないようにしておく。
【0031】
図6において、符号23aは上側係合部32が係合される上側の水平固定棒材を示し、符号23bは下側係合部39が係合される下側の水平固定棒材を示しており、これらの上下方向の間隔が符号Lで示されている。この間隔Lが一定となるように、それぞれの水平固定棒材23の取り付けがなされるが、この間隔Lを高い精度で取り付けることはその作業性を低下させることになり、作業性を考慮すると、ある程度の誤差を持たせることになる。
【0032】
したがって、水平固定棒材23の取付作業性を考慮すると、間隔Lに誤差が発生することが不可避となるが、本発明の足場板支持装置にあっては、上側の水平固定棒材23aと下側の水平固定棒材23bとの間の間隔Lに誤差があっても、移動部材34を水平梁部材31に沿って移動させることにより上側係合部32と下側係合部39との間の垂直方向の間隔を無段階に調整することができる。これにより、上側係合部32と下側係合部39を係合させた状態で、水平梁部材31が所定の水平度となるように、上側係合部32を中心に揺動させると、移動部材34が水平梁部材31に沿って移動することになり、上下両方の水平固定棒材間の距離に誤差が存在していても、容易に水平梁部材31を所定の水平度とすることができる。所定の水平度となったら、ねじ部材35を締め付けることにより、移動部材34は水平梁部材31に締結固定される。
【0033】
このような手順によって、所定の数の足場板支持装置30を図3に示すように、型枠材21の外側に取り付けた後に、その上に足場板27を配置し、さらに、サヤ管33に手摺り用支柱28を取り付ける。手摺り用支柱28はねじ部材33aを締結することによりサヤ管33に固定され、この手摺り用支柱28には図3に示すように、手摺り29が取り付けられて作業者の安全が確保される。
【0034】
このようにして足場板27が配置された状態を示すと、図5の通りであり、作業者が足場板27の上に乗って、型枠材21によって区画形成された空間14a内にコンクリートの打ち込みつまり打設作業が行われる。
【0035】
このコンクリートの打ち込み作業が終了した後には、図5に示すそれぞれの型枠材21の上に、図示しない他の型枠材が積み上げられるとともに、複数の水平固定棒材が型枠材の外側に取り付けられ、さらに、所定の高さの位置に足場板支持装置が取り付けられて、同様なコンクリートの打ち込みが行われる。このようにして、所定の高さのコンクリート構造物が構築される。
【0036】
図8は本発明の他の実施の形態である足場板支持装置30を示す図であり、この図においては図4に示す足場板支持装置30を構成する部材と共通する部材には同一の符号が付されている。
【0037】
図8の足場板支持装置30にあっては、上側係合部32の構造が前述したものと相違しているが、他の構造は同様となっている。この場合の上側係合部32は、金属製の板材を断面U字形状に折り曲げた係合片47を有し、この係合片47内に入り込んだ水平固定棒材23から係合片47が外れるのを防止するために、クランプピン48が係合片47に着脱自在に嵌合されるようになっている。このクランプピン48はチェーンやワイヤ49によって水平梁部材31に結び付けられている。
【0038】
図9は上側係合部32の他の具体例を示す図であり、この上側係合部32は水平梁部材31の一端部に固定される第1係合アーム51と、これに対してピン53により開閉自在に連結された第2係合アーム52とを有し、第1係合アーム51の先端部にはピン54を中心に揺動自在にクランプボルト55が設けられている。第2係合アーム52の先端部にはクランプボルト55が入り込む溝56が形成されており、両方のアーム51,52の中に水平固定棒材23を入り込ませた状態で溝56の中にクランプボルト55を入り込ませてナット57を締め付けることにより、上側係合部32を水平固定棒材23にクランプすることができる。第1係合アーム51の水平梁部材31に対する取り付けは、第1係合アーム51が第2係合アーム52に対して図示するように下側となるようにしても良く、逆に第1係合アーム51が上側となるようにしても良い。
【0039】
図8およひ図9に示すタイプの上側係合部32を有する足場板支持装置にあっても、前述した場合と同様の手順によって足場板の取り付けが行われる。なお、図8に示した構造の上側係合部32を図4に示す下側係合部39として用いることも可能であり、図9に示すタイプの上側係合部を下側係合部として用いたり、支柱支持部材として用いるようにしも良い。
【0040】
図10は比較例として従来の足場板支持装置を示す図であり、この足場板支持装置は、水平梁部材61と垂直支柱部材62とによりL字形状に形成された足場ブラケット63を有し、水平梁部材61の先端側と垂直支柱部材62の下端側とが補強用の傾斜梁部材64により連結されている。垂直支柱部材62の上端部には型枠材の外側に設けられた上側の水平固定棒材に係合されるフック65が設けられ、垂直支柱部材62の下端部には下側の水平固定棒材に係合する受金具66が設けられており、その受金具66を垂直支柱部材62に沿って上下動させて所定のピッチ毎にトグルピン67により固定し得るようにしている。
【0041】
図10に示すような構造では、フック65と受金具66との間の上下方向の間隔を所定のピッチ毎にしか変化させることができないので、水平固定棒材の上下方向の間隔を高い精度としなければならず、この間隔に誤差が存在する場合には、受金具66と水平固定棒材との間に隙間が発生することになる。したがって、足場板支持装置の荷重の大部分を上側の水平固定棒材が受けることになる。しかも、受金具66の上下方向の位置を所定のピッチで変化させるためには、トグルピン67を抜き差ししなければならず、その作業性が良くない。
【0042】
これに対して、本発明の足場板支持装置30にあっては、ねじ部材35を緩めて水平梁部材31を上側係合部32を中心に揺動させることによって、上下両側の水平固定棒材相互間の誤差を吸収することができるので、足場板27からそれぞれの足場板支持装置30に加えられる荷重を上側係合部32と下側係合部39を介してそれぞれの水平固定棒材23に確実に分散して伝達することができる。したがって、水平固定棒材の変形を防止することができるとともに、その径が小さい部材を使用することができる。さらに、型枠工事にあっては、水平固定棒材の上下方向の間隔つまりピッチを高い精度とすることが不要となることから、その工事の作業能率を向上させることが可能となる。
【0043】
図2に示す型枠工事は、図1に示す地下構造物のうち仕切り壁部14を構築する場合を示しているが、これは型枠工事の一例であって、図1に示す構内側壁部12を構築する際にも、本発明の足場板支持装置30を使用することができる。その場合には、構内側壁部12の外側は地肌面に対向することになるので、足場板は構内側壁部12の外側には配置されることなく、構内側壁部12の内側面に対応して取り付けられる型枠材21の外側に足場板27を配置するために、足場板支持装置30が取り付けられることになる。また、その場合には、図2に示すタイボルト24とは相違し、地肌面側に配置される型枠材に基端部が固定され、先端部のみにねじ部を有するタイプのタイボルトが使用される。
【0044】
以上、本発明者によってなされた発明を実施の形態に基づき具体的に説明したが、本発明は前記の形態に限定されるものではなく、その要旨を逸脱しない範囲で種々変更可能であることはいうまでもない。
【0045】
たとえば、図1は地下構築物を示すが、それ以外に地上に建設されるマンションなどの中層建築物や高層建築物などを建築する際における壁体などのように、型枠材を使用して、所定の空間を形成しその中にコンクリートを打ち込むことにより形成されるコンクリート構造物であれば、橋脚や擁壁など種々の構造物を構築する際に本発明の足場板支持装置を使用することができる。また、図示する場合には、上側係合部32にクランプの機能を持たせているが、下側係合部39にのみ、あるいは両方の係合部32,39にクランプの機能を持たせるようにしても良い。
【0046】
【発明の効果】
本願において開示される発明のうち、代表的なものによって得られる効果を簡単に説明すれば、以下のとおりである。
【0047】
(1).型枠材の外側に取り付けられた水平固定棒材相互の上下方向の間隔に誤差が存在しても、その誤差を容易に吸収して上側係合部と下側係合部とを確実に水平固定棒材に密着させることができる。
【0048】
(2).水平固定棒材相互の上下方向の間隔の誤差を大きくすることができるので、その取り付けを高い精度とすることなく、迅速に行うことができ、コンクリート構造物の構築を迅速かつ能率的に行うことができる。
【図面の簡単な説明】
【図1】コンクリート構造物の一例としての地下構造物を示す断面図である。
【図2】コンクリート構造物を構築するために型枠材を取り付けた状態を示す断面図である。
【図3】図2に示した型枠材の外側に本発明の足場板支持装置を取り付けた状態を示す斜視図である。
【図4】(A)は本発明の一実施の形態である足場板支持装置を示す斜視図であり、(B)は同図(A)における4B−4B線に沿う断面図である。
【図5】足場板支持装置を型枠材の外側に取り付けた状態を示す断面図である。
【図6】図4の正面図である。
【図7】図4に示された上側係合部のクランプ部材を示す拡大正面図である。
【図8】本発明の他の実施の形態である足場板支持装置を示す斜視図である。
【図9】上側係合部の他の具体例を示す斜視図である。
【図10】従来の足場板支持装置を示す正面図である。
【符号の説明】
10 地盤面
12 構内側壁部
14 仕切り壁部
14a 空間
20 鉄筋
21 型枠材
22 垂直固定棒材
23 水平固定棒材
24 タイボルト
25 リブ座金
27 足場板
28 手摺り用支柱
29 手摺り
31 水平梁部材
32 上側係合部
32a クランプ部材
33 サヤ管
34 移動部材
35 ねじ部材
37 傾斜梁部材
38 ピン
39 下側係合部
42 クランプ片
43 支持ピン
[0001]
BACKGROUND OF THE INVENTION
The present invention is a concrete scaffolding plate support for supporting a scaffolding plate used in constructing a concrete structure formed by driving concrete such as a foundation structure, a bridge pier, a wall structure building, an underground wall, a retaining wall, etc. Relates to the device.
[0002]
[Prior art]
Underground structures such as subways, basements, and underground passages are formed by building concrete wall structures and foundation structures that have reinforcing bars and steel frames inside, and high-rise buildings such as hotels and apartments Similarly, it is constructed by building concrete wall structures and foundation structures. In addition, retaining walls and piers for earth retaining such as cliffs are also made of concrete.
[0003]
The various concrete structures described above include a reinforced concrete structure in which reinforcing bars are arranged inside, and a steel reinforced concrete structure in which reinforcing bars are arranged around a steel frame and integrated with concrete. When constructing such a concrete structure, formwork for constructing rebar construction for constructing steel frames, reinforcing bars, etc. embedded in the structure, and formwork for forming the outer surface of the structure Construction work, concrete work that puts concrete into the formwork, etc. will be performed.
[0004]
When performing the formwork, vertical support bars are attached to the base for fixing the formwork, and horizontal fixing bars extending in the horizontal direction are arranged at predetermined intervals in the vertical direction outside the vertical support bars. It will be attached every time. In concrete construction, since concrete is driven from above the formwork, it is necessary to arrange a scaffolding plate outside the formwork material in order to perform the work. In order to support the scaffold plate, a concrete placement scaffold plate support device, also referred to as a scaffold bracket or a formwork bracket, is attached to the outside of the formwork material.
[0005]
[Problems to be solved by the invention]
Conventionally, an L-shaped scaffold bracket is formed by a horizontal beam member and a vertical column member, and the leading end side of the horizontal beam member and the lower end side of the vertical column member are connected by an inclined beam member for reinforcement. . The upper end of the vertical support member is provided with a hook that engages with the upper horizontal fixing bar provided on the outer side of the formwork member, and the lower horizontal fixing bar is provided on the lower end of the vertical support member. An engaging bracket is provided, and the bracket can be fixed at a predetermined pitch in the vertical direction by a toggle pin.
[0006]
However, in such a conventional structure, if the vertical spacing of a plurality of horizontally fixed bars arranged extending in the horizontal direction on the outside of the mold material is not set with high accuracy, the hook and the bracket are surely secured. Each of these cannot transmit a desired load to the horizontal fixed bar. Therefore, in the formwork for constructing a concrete structure, it is necessary to make the vertical interval, that is, the pitch, of the horizontal fixed bars highly accurate, and it is difficult to improve the efficiency of the construction. there were.
[0007]
An object of the present invention is to enable a concrete structure to be constructed quickly and efficiently.
[0008]
The above and other objects and novel features of the present invention will be apparent from the description of this specification and the accompanying drawings.
[0009]
[Means for Solving the Problems]
Of the inventions disclosed in this application, the outline of typical ones will be briefly described as follows.
[0010]
That is, the concrete placement scaffolding plate support device of the present invention is configured such that when a concrete structure is constructed, it extends in the horizontal direction to the outside of the formwork material that forms the space into which the concrete is poured, and is vertically spaced at predetermined intervals. A concrete placement scaffolding plate support device that is disposed on a plurality of horizontal fixed bar members fixed to and supports the scaffolding plate, wherein the upper engagement portion that engages with the horizontal fixed bar member on the upper side is one end portion. And a horizontal beam member provided at the other end of the column support member to which the column for supporting the handrail is mounted, and the horizontal beam member is movably attached to the horizontal beam member, and can be attached to the horizontal beam member at an arbitrary position. A moving member to be fixed, and an inclined beam member having an upper end pin-coupled to the moving member and a lower engaging portion that engages with the lower horizontal fixing bar provided at the lower end portion. A scaffold on the horizontal beam member It characterized by being adapted to construct the concrete structure by working in on the arrangement to the scaffolding plate.
[0011]
In addition, the concrete placement scaffolding plate support device of the present invention has a clamp member that fastens the horizontal beam member to the upper horizontal fixing bar and prevents the horizontal beam member from coming off the horizontal fixing bar. To do.
[0012]
In the present invention, there is a deviation in the vertical interval between the horizontal fixed bar with which the upper engaging part is engaged and the other horizontal fixed bar with which the lower engaging part is formed. However, the displacement is absorbed, and the respective engaging portions are in close contact with the respective horizontal fixing rods.
[0013]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
[0014]
FIG. 1 is a diagram showing an example of an underground structure for constructing a basement. This underground structure is constructed in a recess 11 formed by excavating the ground surface 10. The side wall part 12, the slab floor part 13, and the foundation part or partition wall part 14 etc. which are constructed | assembled along the perpendicular | vertical ground surface are included.
[0015]
FIG. 2 is a view showing a state in which a formwork for constructing any of the partition wall portions 14 shown in FIG. 1 is being performed, and is a concrete structure that is a reinforcing bar embedded in the partition wall portion 14. A state in which 20 bars are arranged is shown. The illustrated reinforcing bar 20 has a vertical reinforcing bar 20a extending in the vertical direction and a horizontal reinforcing bar 20b extending in the horizontal direction.
[0016]
Corresponding to both side surfaces of the partition wall portion as a concrete structure, a dam plate, that is, a formwork material 21 for partitioning a space into which concrete is driven is arranged, and the formwork material 21 is located outside this. It is supported by a plurality of vertical fixing rods 22. A plurality of horizontal fixing rods 23 extending in the horizontal direction and having a predetermined interval in the vertical direction are attached to the outside of the vertical fixing rods 22. As shown in FIG. 2, a plurality of horizontal fixing rods 23 are attached in accordance with the height dimension of the formwork member 21, and the horizontal fixing rods 23 of each pair are left and right. The positions in the vertical direction correspond to each other on the outside of the mold material 21. In the illustrated case, the vertical fixed bar 22 and the horizontal fixed bar 23 are each formed by a hollow round pipe. However, each of the bars 22 and 23 may be formed by a hollow square pipe having a square cross section.
[0017]
In FIG. 2, tie bolts 24 are provided on the outside of the mold material 21 so as to penetrate between a pair of horizontal fixing rods 23 corresponding to the vertical positions in order to maintain a constant space between the left and right mold material 21. A rib washer 25 is attached to both ends of each tie bolt 24, and each rib washer 25 is fastened by a nut 26 that is screwed to a threaded portion of the tie bolt 24.
[0018]
As shown in FIG. 2, by fixing the formwork material 21, a formwork for partitioning the space 14 a into which concrete is poured is formed. As shown in FIG. 3, a scaffolding plate 27 for an operator to drive concrete, that is, to place a concrete, is attached to the outside of the left and right formwork members 21.
[0019]
FIG. 4 is a view showing a concrete placement scaffolding plate support device 30 according to an embodiment of the present invention for supporting the scaffolding plate 27, and FIG. 5 is shown on both left and right sides of the formwork shown in FIG. The state which attached the scaffold board | substrate support apparatus 30 of FIG. 4 is shown. The scaffold board support device 30 is also referred to as a formwork bracket or a scaffold bracket. In FIG. 3, the scaffold board support device 30 is attached to each of the left and right formwork materials 21. The scaffold plate 27 is attached only to the outside of the left mold member 21, and the right mold member 21 is shown with no scaffold plate 27 attached yet.
[0020]
This scaffolding plate support device 30 has a horizontal beam member 31 formed by a hollow metal square pipe having a square shape in cross section, and an upper side engaged with a horizontal fixing rod 23 at one end thereof. The engagement portion 32 is provided, and the other end portion is provided with a sheath tube 33 to which the handrail support 28 is attached as a support member. The sheath tube 33 is formed of a metal round pipe having a circular cross-sectional shape. However, the sheath tube 33 may be formed of a metal square pipe having a square cross-sectional shape. Further, as the support column support member, a clamp member may be used instead of the sheath tube 33.
[0021]
On the outside of the horizontal beam member 31, a moving member 34 having a regular square cross section is attached along the horizontal beam member 31 so as to be movable in the longitudinal direction. The moving member 34 is provided with a screw member 35. When the screw member 35 is loosened, the moving member 34 can be moved. When the screw member 35 is tightened, the moving member 34 can be fixed at the position.
[0022]
A connecting fitting 36 is attached to the moving member 34, and an upper end portion of the inclined beam member 37 is pin-coupled to the moving member 34 by a pin 38 so as to be swingable around the connecting fitting 36. Similar to the horizontal beam member 31, the inclined beam member 37 is formed of a hollow metal square pipe. At the lower end of the inclined beam member 37, a lower engaging portion 39 that engages with another horizontal fixing rod 23 positioned below the horizontal fixing rod 23 with which the upper engaging portion 32 engages. Is provided. The lower engaging portion 39 is formed by bending a metal plate material into a U shape. The horizontal beam member 31 and the inclined beam member 37 may be formed by a hollow round pipe having a circular cross section.
[0023]
As shown in FIG. 3, the scaffolding plate support device 30 having such a structure is attached to a horizontal fixed bar 23 having the same height at predetermined intervals corresponding to the length of the scaffolding plate 27. A plurality of the frame materials 21 are arranged outside. When the respective scaffolding plate support devices 30 are engaged with the respective upper and lower horizontal fixing rods 23, even if an error or deviation occurs in the distance between the respective horizontal fixing rods 23, As shown in FIG. 6, by setting the position of the moving member 34 to an arbitrary position such as a position indicated by a solid line or a position indicated by a two-dot chain line, the horizontal beam member 31 can be set to a predetermined level. it can. In addition, since each of the engaging portions 32 and 39 is surely in contact with the horizontal fixed bar 23 without a gap, the load of the scaffolding plate support device 30 is distributed to the two horizontal fixed bars. Is transmitted.
[0024]
As shown in FIG. 4, the upper engaging portion 32 is formed by two clamp members 32 a and 32 b that are fixed to both side surfaces of the horizontal beam member 31.
[0025]
FIG. 7 is an enlarged view of a part of one clamp member 32a forming the upper engaging portion 32. The clamp member 32a has a concave portion 41 into which the horizontal fixing rod 23 enters, and the clamp member 32a includes A clamp piece 42 for preventing the upper engaging portion 32 from being detached from the horizontal fixed bar 23 entering the recess 41 is movably attached. Thus, by providing the upper engagement portion 32 with a clamping function, it is possible to reliably prevent the scaffold plate support device 30 from being inadvertently detached from the horizontal fixing member 23 due to vibration or the like.
[0026]
Two support pins 43 and 44 are fixed to the clamp member 32a, and cam grooves 45 and 46 with which the support pins 43 and 44 engage are formed in the clamp piece 42, respectively. When the clamp piece 42 is set at the clamp position shown by the solid line in FIG. 7, the clamp piece 42 is in the recess 41 and the entrance 41 a is narrower than the outer diameter of the horizontal fixed bar 23, and the upper engaging portion 32 is in the horizontal fixed bar 23. It is prevented from coming off. On the other hand, when the clamp piece 42 is set at a position indicated by a two-dot chain line, the width of the entrance / exit 41a is widened, and the upper engaging portion 32 can be detached from the horizontal fixed bar 23. Each of the support pins 43 and 44 has a head that is larger than the width of each of the cam grooves 45 and 46 so that the clamp piece 42 does not come off from the clamp member 32a. The other clamp members 32b have the same structure. Further, the lower engaging portion 39 may have the same structure as the upper engaging portion 32.
[0027]
Next, a procedure for attaching the scaffold plate 27 to the outside of the formwork member 21 using the above-described scaffold plate support device will be described.
[0028]
In order to construct the concrete structure under the state where the rebar construction of the concrete structure is completed, a formwork material 21 that forms a space into which concrete is driven is attached. As shown in FIG. 2, when the concrete structure is the partition wall or the base portion 14 shown in FIG. 1, the formwork material 21 is attached so as to correspond to both surfaces thereof. The mold material 21 has a predetermined height and width, a plurality of sheets are arranged in a predetermined posture such as a straight line, and each mold material 21 includes a plurality of vertical fixing rods 22 and a plurality of horizontal. It is fixed by a fixed bar 23. The mold materials 21 facing each other are held at a predetermined interval by a plurality of tie bolts 24.
[0029]
The distance between vertical fixed bars 22, that is, the pitch, the distance between horizontal fixed bars 23, and the distance between tie bolts 24 are set according to conditions such as the thickness of the concrete structure. After the mold member 21 is installed in this way, as shown in FIG. 3, the scaffolding plate support device 30 shown in FIG. 4 is placed at a predetermined interval on the horizontal fixing rod 23 having a predetermined height. Can be attached.
[0030]
At the time of attachment, the screw member 35 is loosened so that the moving member 34 can move along the horizontal beam member 31, and the upper engaging portion 32 is placed on the predetermined horizontal fixing bar 23 and the horizontal fixing bar The lower engagement portions 39 are engaged with the horizontal fixing rods 23 positioned below the lower portions 23, respectively. When the upper engaging portion 32 is engaged with the upper horizontal fixing rod 23, the clamp piece 42 is shifted to the position indicated by the two-dot chain line as shown in FIG. The upper engaging portion 32 is shifted from the position so that it does not come off from the horizontal fixing rod 23.
[0031]
In FIG. 6, reference numeral 23 a indicates an upper horizontal fixed bar with which the upper engaging part 32 is engaged, and reference numeral 23 b indicates a lower horizontal fixed bar with which the lower engaging part 39 is engaged. These vertical intervals are indicated by the symbol L. The horizontal fixing rods 23 are attached so that the distance L is constant. However, attaching the distance L with high accuracy reduces the workability, and considering workability, It will have a certain amount of error.
[0032]
Therefore, considering the workability of attaching the horizontal fixing bar 23, it is inevitable that an error occurs in the interval L. However, in the scaffolding plate support device of the present invention, the upper horizontal fixing bar 23a and the lower Even if there is an error in the distance L between the horizontal fixing rod 23 b on the side, the moving member 34 is moved along the horizontal beam member 31 to move the upper engaging portion 32 and the lower engaging portion 39. Can be adjusted steplessly. Thus, when the upper engaging portion 32 and the lower engaging portion 39 are engaged, the horizontal beam member 31 is swung around the upper engaging portion 32 so as to have a predetermined level, The moving member 34 moves along the horizontal beam member 31, and the horizontal beam member 31 is easily set to a predetermined level even if there is an error in the distance between the upper and lower horizontal fixed bars. Can do. When the predetermined level is reached, the moving member 34 is fastened and fixed to the horizontal beam member 31 by tightening the screw member 35.
[0033]
According to such a procedure, as shown in FIG. 3, after a predetermined number of scaffolding plate support devices 30 are attached to the outside of the formwork member 21, the scaffolding plate 27 is disposed thereon, A handrail support 28 is attached. The handrail support 28 is fixed to the sheath tube 33 by fastening a screw member 33a, and a handrail 29 is attached to the handrail support 28 as shown in FIG. 3 to ensure the safety of the operator. The
[0034]
The state in which the scaffolding plate 27 is arranged in this manner is as shown in FIG. 5, where an operator rides on the scaffolding plate 27 and puts the concrete in the space 14 a defined by the formwork material 21. Driving or placing work is performed.
[0035]
After the concrete driving operation is completed, other mold materials (not shown) are stacked on the respective mold materials 21 shown in FIG. 5, and a plurality of horizontal fixing rods are placed outside the mold materials. In addition, a scaffolding plate support device is attached at a predetermined height, and the same concrete is driven. In this way, a concrete structure having a predetermined height is constructed.
[0036]
FIG. 8 is a view showing a scaffolding board support device 30 according to another embodiment of the present invention. In this figure, members common to the members constituting the scaffolding board support device 30 shown in FIG. Is attached.
[0037]
In the scaffold board support device 30 of FIG. 8, the structure of the upper engaging portion 32 is different from that described above, but the other structures are the same. The upper engagement portion 32 in this case has an engagement piece 47 obtained by bending a metal plate material into a U-shaped cross section, and the engagement piece 47 extends from the horizontal fixing rod 23 that has entered the engagement piece 47. In order to prevent detachment, the clamp pin 48 is detachably fitted to the engagement piece 47. The clamp pin 48 is connected to the horizontal beam member 31 by a chain or a wire 49.
[0038]
FIG. 9 is a view showing another specific example of the upper engaging portion 32. The upper engaging portion 32 has a first engaging arm 51 fixed to one end portion of the horizontal beam member 31, and a pin for the first engaging arm 51. A clamp bolt 55 is provided at the tip of the first engagement arm 51 so as to be swingable around a pin 54. A groove 56 into which the clamp bolt 55 enters is formed at the distal end of the second engagement arm 52, and clamped in the groove 56 with the horizontal fixing rod 23 being inserted into both arms 51, 52. The upper engaging portion 32 can be clamped to the horizontal fixing bar 23 by inserting the bolt 55 and tightening the nut 57. The first engagement arm 51 may be attached to the horizontal beam member 31 such that the first engagement arm 51 is positioned below the second engagement arm 52 as shown in the figure, and conversely The combined arm 51 may be on the upper side.
[0039]
Even in the scaffolding plate support apparatus having the upper engaging portion 32 of the type shown in FIGS. 8 and 9, the scaffolding plate is attached by the same procedure as described above. 8 can be used as the lower engaging portion 39 shown in FIG. 4, and the upper engaging portion of the type shown in FIG. 9 is used as the lower engaging portion. It may be used as a support member.
[0040]
FIG. 10 is a diagram showing a conventional scaffold board support device as a comparative example, and this scaffold board support device has a scaffold bracket 63 formed in an L shape by a horizontal beam member 61 and a vertical support member 62, The front end side of the horizontal beam member 61 and the lower end side of the vertical column member 62 are connected by an inclined beam member 64 for reinforcement. A hook 65 that is engaged with an upper horizontal fixing bar provided outside the formwork material is provided at the upper end of the vertical column member 62, and a lower horizontal fixing bar is provided at the lower end of the vertical column member 62. A receiving metal fitting 66 that engages with the material is provided. The receiving metal fitting 66 can be moved up and down along the vertical column member 62 and fixed by a toggle pin 67 at a predetermined pitch.
[0041]
In the structure as shown in FIG. 10, the vertical distance between the hook 65 and the metal fitting 66 can be changed only at a predetermined pitch. If there is an error in this distance, a gap will be generated between the metal fitting 66 and the horizontal fixing bar. Therefore, the upper horizontal fixed bar receives most of the load of the scaffolding plate support device. Moreover, in order to change the vertical position of the metal fitting 66 at a predetermined pitch, the toggle pin 67 must be inserted and removed, and the workability is not good.
[0042]
On the other hand, in the scaffolding plate support apparatus 30 of the present invention, the horizontal fixing bar on both the upper and lower sides is obtained by loosening the screw member 35 and swinging the horizontal beam member 31 around the upper engaging portion 32. Since errors between each other can be absorbed, a load applied from the scaffold plate 27 to the respective scaffold plate support devices 30 is applied to the respective horizontal fixing rods 23 via the upper engagement portion 32 and the lower engagement portion 39. Can be reliably distributed and transmitted. Therefore, deformation of the horizontal fixed bar can be prevented, and a member having a small diameter can be used. Further, in the form work, since it is not necessary to make the vertical interval, that is, the pitch of the horizontal fixed bar, highly accurate, the work efficiency of the work can be improved.
[0043]
The formwork shown in FIG. 2 shows a case where the partition wall part 14 is constructed in the underground structure shown in FIG. 1, but this is an example of the formwork and the side wall part on the premises shown in FIG. 1. The scaffolding plate support device 30 of the present invention can also be used when building 12. In that case, since the outer side of the campus side wall portion 12 faces the ground surface, the scaffolding plate is not disposed outside the campus side wall portion 12 and corresponds to the inner side surface of the campus side wall portion 12. In order to arrange the scaffolding plate 27 outside the formwork material 21 to be attached, the scaffolding plate support device 30 is attached. In this case, unlike the tie bolt 24 shown in FIG. 2, a tie bolt of a type in which the base end portion is fixed to the mold material disposed on the ground surface side and the thread portion is provided only at the tip portion is used. The
[0044]
As mentioned above, the invention made by the present inventor has been specifically described based on the embodiment. However, the present invention is not limited to the above-described embodiment, and various modifications can be made without departing from the scope of the invention. Needless to say.
[0045]
For example, FIG. 1 shows an underground structure, but other than that, using a formwork material such as a wall in building a medium-rise building or a high-rise building such as an apartment built on the ground, If it is a concrete structure formed by forming a predetermined space and driving concrete into it, the scaffold board support device of the present invention can be used when constructing various structures such as piers and retaining walls. it can. In the illustrated case, the upper engaging portion 32 has a clamping function, but only the lower engaging portion 39 or both engaging portions 32 and 39 have a clamping function. Anyway.
[0046]
【The invention's effect】
Of the inventions disclosed in the present application, effects obtained by typical ones will be briefly described as follows.
[0047]
(1) Even if there is an error in the vertical spacing between the horizontal fixed bars attached to the outside of the formwork, the error is easily absorbed and the upper and lower engagement parts Can be securely attached to the horizontal fixing rod.
[0048]
(2) Since the error in the vertical spacing between the horizontal fixed bars can be increased, the installation can be done quickly without high accuracy, and the construction of the concrete structure can be done quickly and efficiently. Can be done automatically.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing an underground structure as an example of a concrete structure.
FIG. 2 is a cross-sectional view showing a state where a formwork material is attached to construct a concrete structure.
FIG. 3 is a perspective view showing a state in which the scaffolding plate support device of the present invention is attached to the outside of the formwork shown in FIG. 2;
4A is a perspective view showing a scaffold board support device according to an embodiment of the present invention, and FIG. 4B is a cross-sectional view taken along line 4B-4B in FIG.
FIG. 5 is a cross-sectional view showing a state in which the scaffold board support device is attached to the outside of the formwork member.
6 is a front view of FIG. 4;
FIG. 7 is an enlarged front view showing a clamp member of the upper engagement portion shown in FIG.
FIG. 8 is a perspective view showing a scaffold board support device according to another embodiment of the present invention.
FIG. 9 is a perspective view showing another specific example of the upper engaging portion.
FIG. 10 is a front view showing a conventional scaffold board support device.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Ground surface 12 Side wall part 14 Partition wall part 14a Space 20 Reinforcement 21 Formwork material 22 Vertical fixed bar 23 Horizontal fixed bar 24 Tie bolt 25 Rib washer 27 Scaffold plate 28 Handrail support 29 Handrail 31 Horizontal beam member 32 Upper engagement portion 32a Clamp member 33 Saya tube 34 Moving member 35 Screw member 37 Inclined beam member 38 Pin 39 Lower engagement portion 42 Clamp piece 43 Support pin

Claims (2)

コンクリート構造物を構築する際に、コンクリートが打ち込まれる空間を形成する型枠材の外側にそれぞれ水平方向に延び上下方向に所定の間隔毎に固定された複数の水平固定棒材に配置され、かつ足場板を支持するコンクリート打設用足場板支持装置であって、
上側の前記水平固定棒材に係合する上側係合部が一端部に設けられ、かつ手摺り用支柱が装着される支柱支持部材が他端部に設けられた水平梁部材と、
前記水平梁部材に移動自在に取り付けられ、かつ任意の位置で前記水平梁部材に固定される移動部材と、
上端部が前記移動部材にピン結合され、かつ下側の前記水平固定棒材に係合する下側係合部が下端部に設けられた傾斜梁部材とを有し、
前記水平梁部材の上に足場板を配置して前記足場板の上において作業することにより前記コンクリート構造物を構築し得るようにしたことを特徴とするコンクリート打設用足場板支持装置。
When constructing a concrete structure, it is arranged on a plurality of horizontally fixed bars that extend in the horizontal direction and are fixed at predetermined intervals in the vertical direction on the outside of the formwork material that forms the space into which the concrete is driven, and A concrete placement scaffolding plate support device for supporting a scaffolding plate,
A horizontal beam member in which an upper engagement portion that engages with the upper horizontal fixing bar is provided at one end portion, and a column support member to which a handrail support column is mounted is provided at the other end portion;
A movable member that is movably attached to the horizontal beam member and is fixed to the horizontal beam member at an arbitrary position;
An upper end portion is pin-coupled to the moving member, and a lower engaging portion that engages with the lower horizontal fixing rod has an inclined beam member provided at the lower end portion,
A concrete placement platform support apparatus, wherein a concrete plate can be constructed by placing a scaffold board on the horizontal beam member and working on the scaffold board.
請求項1記載のコンクリート打設用足場板支持装置であって、前記上側係合部は上側の前記水平固定棒材に前記水平梁部材を締結して前記水平固定棒材から外れるのを防止するクランプ部材を有することを特徴とするコンクリート打設用足場板支持装置。2. The concrete placing scaffolding plate support device according to claim 1, wherein the upper engaging portion prevents the horizontal beam member from being detached from the horizontal fixed bar by fastening the horizontal beam member to the upper horizontal fixed bar. A scaffolding plate support device for placing concrete, comprising a clamp member.
JP23216297A 1997-08-28 1997-08-28 Scaffolding plate support device for concrete placement Expired - Lifetime JP3890118B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23216297A JP3890118B2 (en) 1997-08-28 1997-08-28 Scaffolding plate support device for concrete placement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23216297A JP3890118B2 (en) 1997-08-28 1997-08-28 Scaffolding plate support device for concrete placement

Publications (2)

Publication Number Publication Date
JPH1171897A JPH1171897A (en) 1999-03-16
JP3890118B2 true JP3890118B2 (en) 2007-03-07

Family

ID=16934976

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23216297A Expired - Lifetime JP3890118B2 (en) 1997-08-28 1997-08-28 Scaffolding plate support device for concrete placement

Country Status (1)

Country Link
JP (1) JP3890118B2 (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2360448B (en) * 2000-03-21 2004-04-28 John Dearlove A fold down mortar table attachable to poles with clamps
JP2006249800A (en) * 2005-03-11 2006-09-21 Yamada Gas Assetsu Kogyo:Kk Construction scaffold support tool and construction scaffold
GB2441766A (en) * 2006-09-14 2008-03-19 David Viles Spot board for attachment to a scaffold rail
CN104975707A (en) * 2014-04-04 2015-10-14 吴庆豪 Shed frame and triangular support frame body of shed frame
CN104088453B (en) * 2014-04-15 2016-07-06 中国建筑股份有限公司 A kind of scaffold edge support structure and using method thereof
JP6511671B2 (en) * 2015-02-23 2019-05-15 公益財団法人鉄道総合技術研究所 Construction method of coastal soil structure against huge tsunami by high-rigidity geosynthetic reinforced soil retaining wall with rigid integrated wall work
CN109518982A (en) * 2018-11-22 2019-03-26 蒿振侠 A kind of flat push type connects object net support construction and its application method
KR102113869B1 (en) * 2019-12-26 2020-05-21 박용진 Safety scaffolding installation structure
GB2592433A (en) * 2020-02-28 2021-09-01 J Mac Safety Systems Ltd Hop-up scaffold bracket
CN114482075B (en) * 2022-03-08 2023-06-23 福建省茂宏建设工程有限公司 Basement supporting structure and construction method thereof
CN114892939B (en) * 2022-07-01 2023-08-22 中国建筑第二工程局有限公司 Steel construction installation operation platform
CN115853314B (en) * 2022-12-09 2024-07-05 中国一冶集团有限公司 Parapet top overhanging component supporting device and construction method

Also Published As

Publication number Publication date
JPH1171897A (en) 1999-03-16

Similar Documents

Publication Publication Date Title
JP3890118B2 (en) Scaffolding plate support device for concrete placement
US2916245A (en) Adjustable scaffold bracket
KR100373783B1 (en) A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
WO1998036141A1 (en) Safety guardrail apparatus
KR102102214B1 (en) Safety handrail for beam table form
JP3839921B2 (en) Scaffolding plate support frame, method for attaching and removing the same, and method for constructing a reinforced concrete wall body using the same
KR20190106435A (en) Retainer for steel frame structure
KR200277918Y1 (en) supporter for establishing railings
KR200213539Y1 (en) Frame of safety workbench
KR100840279B1 (en) Suspension hanger for slab form
KR200294830Y1 (en) Supporting structure of scaffold for mold
KR100433700B1 (en) Mold system for slab concrete of bridge
KR200459397Y1 (en) Gang form support bracket for crash protection structures
KR102524591B1 (en) Temporary worktable
KR200285281Y1 (en) Supporting structure for concrete wall
CN217292740U (en) Cylinder design wood system template structure
KR200298097Y1 (en) Mold supporting structure
KR200497116Y1 (en) Safety guard fixing device
KR102370425B1 (en) The safety rail of the formwork
JP2611882B2 (en) Construction method of stairs
KR200245284Y1 (en) A temporary bracket for construction of precast concrete beam bridge
KR0134349Y1 (en) Spacers
KR100462355B1 (en) supporter for establishing railings
EP1651826B1 (en) Formwork fixing and method
KR200405440Y1 (en) Panel supporter for concrete slab

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040618

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20061121

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20061204

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101208

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111208

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121208

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131208

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term