JP3831499B2 - Construction method of column head of PC cantilever bridge - Google Patents
Construction method of column head of PC cantilever bridge Download PDFInfo
- Publication number
- JP3831499B2 JP3831499B2 JP29699197A JP29699197A JP3831499B2 JP 3831499 B2 JP3831499 B2 JP 3831499B2 JP 29699197 A JP29699197 A JP 29699197A JP 29699197 A JP29699197 A JP 29699197A JP 3831499 B2 JP3831499 B2 JP 3831499B2
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- column head
- cantilever
- formwork
- cantilever bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、ポストテンション工法及び片持架設工法により構築されるプレストレストコンクリート橋(以下、PC片持架設橋という)の主桁のうち、橋脚の上方に位置する柱頭部の構築方法に関するもので、特に、底部コンクリートと頂部コンクリートとに分けてコンクリートを打設する場合における、PC片持架設橋の柱頭部の構築方法に関するものである。
【0002】
【従来の技術】
従来のこの種のPC片持架設橋における柱頭部の構築方法は、例えば、1日に打設できるコンクリート量は限られていることから、橋脚の上方に位置する箱桁たる柱頭部を底部及び頂部の2回に分けてコンクリートを打設し構築するというものであり、具体的には、橋脚の構築後に、橋脚の上側部に張り出したブラケット上に型枠支保工を設置して箱桁底部のコンクリートを打設し、養生後、更に箱桁内に型枠支保工を設置して箱桁頂部のコンクリートを打設し柱頭部を形成させた後、本設のPC鋼材によるプレストレスを導入し当該柱頭部の断面内に引張応力を発生させないようにした上で、箱桁内の型枠支保工及びブラケット上の型枠支保工を解体し撤去するというものである。
【0003】
従って、かかる柱頭部の構築方法により一旦柱頭部が構築されれば、当該柱頭部に型枠及び支保工が一体となった移動作業台車を据え付け、これを用いて柱頭部から両側に向かって片持部を張り出していくことができるから、片持部の張り出し完了後、直ちに側径間部及び中央部を施工することにより、PC片持架設橋の構築を円滑かつ迅速に完成させることが可能である。
【0004】
【発明が解決しようとする課題】
しかしながら、ブラケット上の型枠支保工としては、2回目の頂部のコンクリート打設後、本設のPC鋼材によるプレストレスを柱頭部に導入するまでの間、柱頭部の底部及び頂部を合わせた全コンクリート荷重を支え、しかも、橋脚の上側部から片持ちで張り出したブラケット式により当該荷重を支えるので、きわめて大がかりなものになり、このため施工が煩雑であり不経済であった(ブラケット式以外の支柱式や枠組式などの支保工もこれと同様に不都合があった)。
【0005】
そこで、本発明の目的は、ブラケット式や支柱式などによる柱頭部の型枠支保工を飛躍的に縮小することができ、よって、効率的かつ経済的に行い得るPC片持架設橋の柱頭部の構築方法を提供することにある。
【0006】
【課題を解決するための手段】
上記目的を達成するため、本発明に係るPC片持架設橋の柱頭部の構築方法は、従来のPC片持架設橋の柱頭部の構築方法において、柱頭部の底部コンクリートの打設をしてから当該柱頭部の頂部コンクリートに本設のプレストレスを導入するまでの間、底部コンクリートに仮設のプレストレスを導入する仮設プレストレス導入工程を有することを特徴とするものである。
【0007】
即ち、本発明は、柱頭部の底部コンクリートの打設をしてから当該柱頭部の頂部コンクリートに本設のプレストレスが導入されるまでの間、底部コンクリートに仮設のプレストレスを導入し、この底部コンクリートに頂部コンクリートの荷重を負担させることにより、従来、大がかりなものとなっていた柱頭部を支保するの型枠支保工を飛躍的に縮小させることができ、よって、効率的かつ経済的にPC片持架設橋の柱頭部の構築を行うことが可能になる。
【0008】
【発明の実施の形態】
以下、添付図面に示す実施の形態に基づいてこの発明を詳細に説明する。
【0009】
図1及び図2は本実施の形態に係るPC片持架設橋の柱頭部の構築方法を示す概略側面図であって、図1は縦側面図、図2は横側面図を示している。
【0010】
これらの図において、符号1は、このPC片持架設橋の箱桁(主桁)を橋の中間において支える橋脚、符号2は、橋脚1の構築が完成した後、まず最初に構築される箱桁の柱頭部、符号3は、橋脚1の上側部に固設されたブラケットユニットであって、鉛直部材3a、傾斜部材3b、水平部材3c、及び井桁部材3dで構成されている。
【0011】
また、符号4は、このブラケットユニット3上に設置され、柱頭部2を支保する底部型枠支保工、符号5は、前記ブラケットユニット3上であって柱頭部2の周囲に設置され、柱頭部2の外側部分の型枠の組立、解体などを行うビティー足場、符号6は、底部コンクリート2aの上でかつ箱桁の内部に設置され、頂部コンクリート2bの頂板部分の支保や、柱頭部2の内側部分の型枠の組立、解体などを行う桁内型枠支保工、符号7は、型枠及び支保工が一体となった移動作業台車たるトラベラー、を示している。
【0012】
更に、符号8は、底部コンクリート2aに仮設のプレストレスを導入するための仮設のPC鋼棒、符号9は、頂部コンクリート2bに本設のプレストレスを導入するための本設のカンチレバーケーブル、を示している。
【0013】
本実施の形態において、柱頭部2は、桁高の高い箱桁であるゆえ柱頭部2のコンクリート量がかなり多いのに対し、1日に打設できるコンクリート量は限られていることから、底部コンクリート2a及び頂部コンクリート2bの2回に分けて施工される。
【0014】
また、仮設のPC鋼棒8は、図3に示すように、上部PC鋼棒8a、中央部PC鋼棒8b、及び下部PC鋼棒8cからなり、かつ、シース11内に設置されるものであり、これにより、底部コンクリート2aの打設後直ちに仮設のプレストレスが導入される。
【0015】
次に、本実施の形態に係るPC片持架設橋の柱頭部の構築方法を図1乃至図3を用いて説明する。
【0016】
(a)底部コンクリートの施工
先ず、橋脚1の構築が完成した後、橋脚1の上側部にブラケットユニット3が架構され、このブラケットユニット3の井桁部材3d上に底部型枠支保工4及びビティー足場5が設置される。
【0017】
この底部型枠支保工4は、柱頭部2のすべてのコンクリート荷重を支える必要はなく、底部コンクリート2aの荷重のみを支えることが可能であれば足りるので、設置が容易かつ迅速に行うことが可能である。
【0018】
そして、この底部型枠支保工4の頂部の型枠板の上において鉄筋が組み立てられ、あらかじめPC鋼棒8を挿入すべきシース11が配置された後、コンクリートポンプ車(図示外)の利用により底部コンクリート2aが打設される。
【0019】
(b)仮設プレストレス導入、底部型枠支保工解体
次いで、この底部コンクリート2aの養生中に、前記シース11内にPC鋼棒8が挿入され、当該底部コンクリート2aが所定の強度に達したことを確認した上で、当該PC鋼棒8の端部に切られたねじの利用によりPC鋼棒8を緊張させ、これにより、底部コンクリート2aに所定の大きさの仮設のプレストレスが導入されるのである。
【0020】
そして、この仮設のプレストレスが導入された後、底部コンクリート2aを支えていたブラケットユニット3上の底部型枠支保工4が解体される。
【0021】
このとき、片持状態の底部コンクリート2aに自重が付与されるが、当該自重による引張応力が断面内に生じないように仮設のプレストレスが導入されているので、当該底部コンクリート2aに撓みやひび割れが発生することはない。
【0022】
(c)頂部コンクリートの施工
次に、箱桁の内部であって底部コンクリート2aの上に、頂部コンクリート2bを支保する桁内型枠支保工6が設置される。この桁内型枠支保工6は、頂部コンクリート2bの荷重のみを支えれば足りるので、設置が比較的容易である。
【0023】
そして、この桁内型枠支保工6の頂板の上において鉄筋が組み立てられ、あらかじめカンチレバーケーブル9を挿入すべきシース(図示外)が配置された後、コンクリートポンプ車(図示外)の利用により頂部コンクリート2bが打設される。
【0024】
このとき、桁内型枠支保工6の荷重、頂部コンクリート2bの荷重、及び底部コンクリート2aの自重が当該片持状態の底部コンクリート2aに付与されるが、当該荷重等による引張応力が断面内に生じないように仮設のプレストレスが導入されているので、当該底部コンクリート2aに撓みやひび割れが発生することはない。
【0025】
(d)本設プレストレス導入、仮設プレストレス解放
そして、この頂部コンクリート2bの養生中に、シース内にカンチレバーケーブル9が挿入され、当該底部コンクリート2aが所定の強度に達したことを確認した上で、当該カンチレバーケーブル9の端部に油圧ジヤッキ(図示外)を取り付け、この油圧ジヤッキの利用によりカンチレバーケーブル9を緊張させ、これにより、頂部コンクリート2bに所定の大きさの本設のプレストレスが導入されることになる。
【0026】
そして、この本設のプレストレスが導入された後、底部コンクリート2aに導入されていた仮設のプレストレスが解放され、これにより、柱頭部2の構築が完成する。尚、柱頭部2の構築が完成した後、当該柱頭部2に型枠及び支保工が一体となったトラベラー7が据え付けられ、円滑かつ迅速な片持部の施工が図られることになる。
【0027】
従って、本実施の形態に係るPC片持架設橋の柱頭部の構築方法によれば、柱頭部2の頂部コンクリート2bの施工前から頂部コンクリート2bの打設が完了して本設のプレストレスが導入されるまでの間、底部コンクリート2aに仮設のプレストレスを導入し、この底部コンクリート2aに、自重のほかに頂部コンクリート2bの張出し床版の荷重を除くすべての荷重を負担させることとしたので、従来、大がかりなものとなっていた底部型枠支保工4を飛躍的に縮小させることができ、その結果、効率的かつ経済的に当該構築を行うことが可能になる。
【0028】
【発明の効果】
以上説明したように、本発明に係るPC片持架設橋の柱頭部の構築方法によれば、従来のPC片持架設橋の柱頭部の構築方法において、柱頭部の底部コンクリートの打設をしてから当該柱頭部の頂部コンクリートに本設のプレストレスを導入するまでの間、底部コンクリートに仮設のプレストレスを導入する仮設プレストレス導入工程を有することとしたので、ブラケット式や支柱式などによる柱頭部の型枠支保工を飛躍的に縮小することができ、よって、効率的かつ経済的な当該構築方法が実現できる。
【図面の簡単な説明】
【図1】本発明の一実施の形態に係るPC片持架設橋の柱頭部の構築方法を示す概略縦側面図である。
【図2】本発明の一実施の形態に係るPC片持架設橋の柱頭部の構築方法を示す概略横側面図である。
【図3】本発明の一実施の形態に係るPC片持架設橋の柱頭部(仮設のPC鋼棒)を示す概略断面図である。
【符号の説明】
1…橋脚
2…柱頭部
2a…底部コンクリート
2b…頂部コンクリート
3…ブラケットユニット
3a…鉛直部材
3b…傾斜部材
3c…水平部材
3d…井桁部材
4…底部型枠支保工
5…ビティー足場
6…桁内型枠支保工
7…トラベラー
8…PC鋼棒
8a…上部PC鋼棒
8b…中央部PC鋼棒
8c…下部PC鋼棒
9…カンチレバーケーブル
11…シース[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a column head located above a bridge pier among main girder of a prestressed concrete bridge (hereinafter referred to as a PC cantilever bridge) constructed by a post-tension construction method and a cantilever construction method, In particular, the present invention relates to a method for constructing a column head of a PC cantilever bridge in the case of placing concrete separately into bottom concrete and top concrete.
[0002]
[Prior art]
In the conventional method for constructing a column head in a PC cantilever bridge of this type, for example, since the amount of concrete that can be cast per day is limited, the column head that is a box girder located above the pier is used as the bottom and Concrete is cast and constructed in two steps at the top. Specifically, after construction of the pier, a formwork support is installed on the bracket overhanging the upper part of the pier, and the bottom of the box girder After the concrete is placed and cured, a formwork support is installed in the box girder, the concrete at the top of the box girder is cast to form the column head, and pre-stress due to the PC steel material is introduced. Then, after preventing the tensile stress from being generated in the cross section of the column head, the formwork support in the box girder and the formwork support on the bracket are disassembled and removed.
[0003]
Therefore, once the column head is constructed by the method for constructing the column head, a movable work carriage in which the formwork and the support work are integrated is installed on the column head, and this is used to remove the piece from the column head toward both sides. Since the holding part can be extended, construction of the PC cantilever bridge can be completed smoothly and quickly by constructing the side span part and the central part immediately after the completion of the extension of the cantilever part. It is.
[0004]
[Problems to be solved by the invention]
However, as the formwork support work on the bracket, after the second top concrete placement, until the prestress due to the PC steel material is introduced to the pillar head, all the bottom and top of the pillar head are combined. The concrete load is supported and the load is supported by the bracket type that cantilevered from the upper part of the pier, so the construction becomes very large, and the construction is complicated and uneconomical (other than the bracket type). The support work such as the column type and the frame type was also inconvenient as well).
[0005]
Therefore, an object of the present invention is to dramatically reduce the column head support work by a bracket type or a column type, so that the column head of a PC cantilever bridge can be efficiently and economically performed. It is to provide a construction method.
[0006]
[Means for Solving the Problems]
In order to achieve the above object, a method for constructing a column head of a PC cantilever bridge according to the present invention is a method for constructing a column head of a conventional PC cantilever bridge in which the bottom concrete of the column head is placed. Until a temporary prestress is introduced into the bottom concrete until a permanent prestress is introduced into the top concrete of the column head.
[0007]
That is, the present invention introduces temporary prestress to the bottom concrete from the time when the bottom concrete of the column head is placed to the time when the prestress is introduced to the top concrete of the column head. By bearing the load of the top concrete on the bottom concrete, it is possible to dramatically reduce the formwork support work for supporting the pillar head, which has been a large scale in the past, and thus efficiently and economically. It becomes possible to construct the column head of a PC cantilever bridge.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described in detail based on embodiments shown in the accompanying drawings.
[0009]
FIG.1 and FIG.2 is a schematic side view which shows the construction method of the column head of the PC cantilever bridge according to this embodiment, FIG. 1 is a vertical side view, and FIG. 2 is a lateral side view.
[0010]
In these drawings, reference numeral 1 denotes a bridge pier that supports the box girder (main girder) of the PC cantilever bridge in the middle of the bridge, and
[0011]
Reference numeral 4 is installed on the
[0012]
Further,
[0013]
In the present embodiment, the
[0014]
Further, as shown in FIG. 3, the temporary
[0015]
Next, a method for constructing the column head of the PC cantilever bridge according to the present embodiment will be described with reference to FIGS.
[0016]
(A) Construction of the bottom concrete First, after the construction of the pier 1 is completed, the
[0017]
The bottom formwork support 4 does not need to support all the concrete load of the
[0018]
Then, after the reinforcing bars are assembled on the top formwork plate of the bottom formwork supporter 4 and the
[0019]
(B) Temporary pre-stress introduction, bottom formwork support dismantling dismantling Next, during the curing of the
[0020]
After the temporary prestress is introduced, the bottom formwork support 4 on the
[0021]
At this time, self-weight is imparted to the bottom concrete 2a in the cantilever state, but temporary pre-stress is introduced so that tensile stress due to the self-weight does not occur in the cross section. Therefore, the
[0022]
(C) Construction of top concrete Next, the in-
[0023]
Then, after reinforcing bars are assembled on the top plate of the in-
[0024]
At this time, the load of the in-
[0025]
(D) While confirming that the
[0026]
And after this pre-stress is introduced, the temporary pre-stress introduced into the
[0027]
Therefore, according to the construction method of the column head of the PC cantilever bridge according to the present embodiment, the placement of the top concrete 2b is completed before the construction of the top concrete 2b of the
[0028]
【The invention's effect】
As described above, according to the method of constructing a column head of a PC cantilever bridge according to the present invention, in the conventional method of constructing a column head of a PC cantilever bridge, the bottom concrete of the column head is placed. Until the pre-stress is introduced to the concrete at the top of the column head, and there is a temporary pre-stress introduction process for introducing temporary pre-stress into the bottom concrete. The formwork support work for the column head can be dramatically reduced, and thus the construction method can be realized efficiently and economically.
[Brief description of the drawings]
FIG. 1 is a schematic vertical side view showing a method for constructing a column head of a PC cantilever bridge according to an embodiment of the present invention.
FIG. 2 is a schematic lateral side view showing a method for constructing a column head portion of a PC cantilever bridge according to an embodiment of the present invention.
FIG. 3 is a schematic cross-sectional view showing a column head (temporary PC steel bar) of a PC cantilever bridge according to an embodiment of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ...
Claims (1)
柱頭部の底部コンクリートの打設をしてから当該柱頭部の頂部コンクリートに本設のプレストレスを導入するまでの間、底部コンクリートに仮設のプレストレスを導入する仮設プレストレス導入工程を有することを特徴とする、
PC片持架設橋の柱頭部の構築方法。In the construction method of the column head of the PC cantilever bridge,
It has a temporary pre-stress introduction step of introducing temporary pre-stress to the bottom concrete from the placement of the bottom concrete of the column head to the introduction of permanent pre-stress to the top concrete of the column head. Features
Construction method of column head of PC cantilever bridge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29699197A JP3831499B2 (en) | 1997-10-29 | 1997-10-29 | Construction method of column head of PC cantilever bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP29699197A JP3831499B2 (en) | 1997-10-29 | 1997-10-29 | Construction method of column head of PC cantilever bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH11131421A JPH11131421A (en) | 1999-05-18 |
JP3831499B2 true JP3831499B2 (en) | 2006-10-11 |
Family
ID=17840847
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP29699197A Expired - Fee Related JP3831499B2 (en) | 1997-10-29 | 1997-10-29 | Construction method of column head of PC cantilever bridge |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3831499B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4569878B2 (en) * | 2006-08-07 | 2010-10-27 | 清水建設株式会社 | Bridge girder construction method |
JP5711179B2 (en) * | 2012-04-17 | 2015-04-30 | 川田建設株式会社 | Construction method of superstructure in elevated structure |
-
1997
- 1997-10-29 JP JP29699197A patent/JP3831499B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH11131421A (en) | 1999-05-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100541965B1 (en) | Manufacturing apparatus for steel composite girder whose self weight is loaded on steel girder and manufacturing method thereof | |
JP3940211B2 (en) | Construction method of horizontal beams for concrete main tower. | |
KR101237000B1 (en) | Precast concrete panel construction technique | |
KR101585594B1 (en) | Dual-prestressing composite beam and the construction method therewith | |
JP2007092313A (en) | Construction method for precast concrete corrugated steel plate web box girder | |
KR100960508B1 (en) | Apparatus for supporting steel-concrete composite girder and method of manufacturing steel composite girder using thereof | |
JP4104910B2 (en) | How to build arch ribs for concrete arch bridges | |
CN111851317B (en) | Method for installing arch ring of arch bridge | |
JP3831499B2 (en) | Construction method of column head of PC cantilever bridge | |
JP3125652B2 (en) | Bridge girder erection equipment | |
JP2550846B2 (en) | Construction method of the pillar head of PC cable-stayed bridge | |
JP3342891B2 (en) | Construction method of horizontal beam erected on columnar structure | |
JP5033334B2 (en) | Tower crane support method | |
KR100540625B1 (en) | Constructing Method of Composite Beam Stiffened with In-Situ Concrete Panel Having Embedded Lower Flange | |
KR100982668B1 (en) | Method for manufacturing prestressed concrete girder | |
JPH05331808A (en) | Erection method for reversed langer arch bridge | |
JP2954523B2 (en) | Pretension type PC member and manufacturing method thereof | |
KR102329831B1 (en) | Manufacturing method of pre-flex introduction type casing composite girder using formwork weight | |
KR960011365B1 (en) | Construction method of steel-frame/steel concrete beam | |
JP3010355B1 (en) | Construction method of joint of prestressed concrete floor | |
CN215977348U (en) | Bearing platform setting assembly | |
KR100631031B1 (en) | Precasted concrete plate and bridge slab construction method using that | |
KR200357934Y1 (en) | Prestressed concrete double-t beam bridge & formwork applying incremental launching method | |
JP2962121B2 (en) | Sliding form method | |
JP2008150820A (en) | Wall concrete, and manufacturing method and construction method therefor |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040728 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060605 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20060705 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20060714 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100721 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110721 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110721 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120721 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130721 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130721 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140721 Year of fee payment: 8 |
|
LAPS | Cancellation because of no payment of annual fees |