JP3756417B2 - Structure production management equipment - Google Patents

Structure production management equipment Download PDF

Info

Publication number
JP3756417B2
JP3756417B2 JP2001023157A JP2001023157A JP3756417B2 JP 3756417 B2 JP3756417 B2 JP 3756417B2 JP 2001023157 A JP2001023157 A JP 2001023157A JP 2001023157 A JP2001023157 A JP 2001023157A JP 3756417 B2 JP3756417 B2 JP 3756417B2
Authority
JP
Japan
Prior art keywords
processing
information
production management
process proceeds
name
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2001023157A
Other languages
Japanese (ja)
Other versions
JP2002229627A (en
Inventor
晴貞 東
清一郎 山切
成美 原田
紘一郎 若山
弘司 守屋
Original Assignee
Jfeシステムズ株式会社
川鉄橋梁鉄構株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jfeシステムズ株式会社, 川鉄橋梁鉄構株式会社 filed Critical Jfeシステムズ株式会社
Priority to JP2001023157A priority Critical patent/JP3756417B2/en
Publication of JP2002229627A publication Critical patent/JP2002229627A/en
Application granted granted Critical
Publication of JP3756417B2 publication Critical patent/JP3756417B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、橋梁、建築物、人口地盤、護岸設備等の大型構造物を製作する際の部品製作及び組立の各工程を管理する構造物の生産管理装置に関する。
【0002】
【従来の技術】
従来の構造物の生産管理装置は、たとえば構造物としての橋梁を構成する金属性箱状構造体の自動溶接を行う際の製造管理を行うものとして特開平10−277741号公報に記載されているものが知られている。
この従来例は、橋梁用箱桁等の鋼製セグメントを自動溶接装置で製造する際に、遅滞ない生産管理を行うために、CADシステムで作成した鋼製セグメントの製造諸元を工程管理システムに入力することにより、この工程管理システムで、構成セグメントの材料となる部材の種類と数を計算し、これらを発注或いは部材製造指示すると共に、CADシステムで作成した鋼製セグメントの設計諸元を設計コンピュータで設計し、この設計された鋼製セグメントの設計諸元に基づいて、鋼製セグメント自動溶接装置の動作パターン及び溶接条件をロボット・シミュレータにより選択し、選択された動作パターン及び溶接条件をロボット・シミュレータに記憶させて、ロボット・シミュレータに教示し、教示された動作パターン及び溶接条件をプロセス・コンピュータに伝達し、このプロセス・コンピュータから鋼製セグメントの自動溶接装置に指示して鋼製セグメントを製造するようにしている。
【0003】
【発明が解決しようとする課題】
しかしながら、上記従来例にあっては、橋梁用箱桁等の鋼製セグメントを自動溶接する際の製造管理方法が開示されているが、橋梁全体の生産管理については記載されておらず、部品点数が多いと共に、接合、組立等の多くの工数を必要とする橋梁全体についての生産管理を行うことはできないという未解決の課題がある。
【0004】
そこで、本発明は、上記従来例の未解決の課題に着目してなされたものであり、構造物全体の生産管理を容易且つ確実に行うことができる構造物の生産管理装置を提供することを目的としている。
【0005】
【課題を解決するための手段】
上記目的を達成するために、請求項1に係る構造物の生産管理装置は、構造物を製作する際の生産管理を行う構造物の生産管理装置において、前記構造物の設計完了時における構造情報に基づいて少なくとも前記構造物を構成する最小単位部材及び当該最小単位部材を組み合わせた組合せ部材の作成に必要とする部品情報を、少なくとも最小単位部材を格納する下位階層、この最小単位部材を組み合わせた組合せ部材を格納する中位階層、組合せ部材同士を組み合わせた上位階層を含む複数階層構造で格納した部品テーブルと、該部品テーブルに基づいて作成した当該部品テーブルに格納された各最小単位部材及び組合せ部材の処理工程及び加工量を前記複数階層構造に対応させて格納する処理工程テーブルと、該処理工程テーブルに基づいて作成した当該処理工程テーブルに格納された処理工程について各工程で処理する加工量をまとめて前記複数階層構造に対応させて格納するタスクテーブルとを有する生産管理データベースを備えていることを特徴としている。
【0006】
この請求項1に係る発明では、生産管理データベースが、部品テーブルとこの部品テーブルに基づいて作成された処理工程テーブルとこの処理工程テーブルに基づいて作成されたタスクテーブルとで構成され、タスクテーブルに、少なくとも最小単位部材を格納する下位階層、この最小単位部材を組み合わせた組合せ部材を格納する中位階層、組合せ部材同士を組み合わせた上位階層を含む複数階層構造に対応させて各処理工程で処理する加工量がまとめて格納されていることにより、このタスクテーブルを参照して、工数計算や工程管理を容易に行うことができると共に、作業指示の単位とすることができる。
【0007】
また、生産管理データベースを構成する各テーブルが最小単位部材を格納する下位階層からこれらを組み合わせる毎に階層が上がる複数階層構造とされているので、橋梁の製造過程に応じた階層構造となり、各階層毎に工程を管理することにより、正確な工程管理を行うことが可能となる。
【0008】
さらに、請求項に係る構造物の生産管理装置は、請求項に係る発明において、前記部品テーブルは、前記橋梁の設計完了時における構造情報が前記最小単位部材及びその組合せ部材との関係を表す部品展開属性を有する場合に、この部品展開属性に基づいて各階層の部品情報を格納することにより作成されていることを特徴としている。
【0009】
この請求項に係る発明では、部品テーブルを作成する際に、橋梁の設計完了時における構造情報が最小単位部材及びその組合せ部材との関係を表す部品展開属性を有する場合に、この部品展開属性に基づいて各階層の部品情報を格納することにより、容易に階層構造を形成することができる。
さらにまた、請求項に係る構造物の生産管理装置は、請求項に係る発明において、前記部品テーブルは、前記構造物の設計完了時における構造情報が部品展開属性を有さないが部品名称に規則性を有する場合に、最小単位部材に応じた下位階層から部品名称の規則性に基づいて順次中位階層及び上位階層を作成することにより構成されていることを特徴としている。
【0010】
この請求項に係る発明では、構造物の設計完了時における構造情報に部品展開属性がない場合に、部品名称の規則性に基づいて最小単位部材を格納する下位階層から部品名称の規則性に基づいて順次中位階層及び上位階層を自動的に作成することができる。
【0011】
【発明の実施の形態】
以下、本発明の実施の形態を図面に基づいて説明する。
図1は本発明を構造物としての橋梁の生産に適用した場合の一実施形態を示す橋梁製作工場を示す概略構成図であって、図中、1は橋梁の生産管理を行う生産管理システムや工場全体を管理する生産制御兼評価システム、原価管理システム、調達管理システム等の管理システムが配設された総合管理事務所、2は部材仕分ヤード、3は自動溶接機を有するフランジパネルラインFPLを備え、鋼製の箱桁橋を製作する箱桁製作ヤード、4は自動溶接機を有するウェブパネルラインWPL及びI桁製作ラインを備え、鋼製のI桁橋を製作するI桁製作ヤード、5はプレス機、H型鋼キャンバー矯正機、NCマーキング機、門型NC孔明機(SCOM)、テーブル型NC孔明機(BV)、NCプラズマ切断機等が配設された部材加工ヤード、6は屋外組立場である。
【0012】
この橋梁製作工場で、受注した複数の橋梁がその箱桁、鈑桁、鋼床版箱桁、鋼床版鈑桁等の橋種(構造物種)と、架設まで、塗装まで、輸送まで等の施工範囲とに応じて順次製作され、これら橋梁の製作時の工程管理及び受注の際に必要とする基本構造情報に基づく簡易物量計算を工程管理システムで実行する。
ここで、橋梁を生産する場合の概要を例えば箱桁鋼橋をステージ生産方式で生産する場合を例にとって説明する。このステージ生産方式は、図2に示すように、自動化ラインの個々の設備を、1つの管理区分としてのステージとし、非自動化工程についてもライン概念を導入し、生産工程の流れに沿って管理を行うようにした生産方式である。
【0013】
先ず、鋼板や型鋼の素材に対して仕分、外注切板、外注加工、1次加工の4つのステージで構成される切板加工作業を行うことにより、部材用切板や粗部材用切板等のピースを形成する。このピースは、素材を切板した状態で最小単位部材を表している。
そして、ピースに対して細巾板継ライン、広巾板継ライン、部材加工の3つのステージで構成される部材加工作業を行うことにより、フランジ、デッキプレート、ウェブ縦リブ、スティフナー、ガゼット、ソールプレート、スラブアンカー、スタッドジベル、対傾構部材、塗装金物、検査路金物、排水装置金物、添接板等の部材を形成する。この部材は、切板に加工をした状態又はピースとピースとを平面的に溶接した状態を表している。
【0014】
次いで、部材に対して小物組、I桁ライン(IBL)、ウェブパネルライン(WPL)及びフランジパネルライン(FPL)の4つのステージで構成される部材組立作業を行うことにより、I桁パネル、ウェブパネル、フランジパネル、横リブ、ダイヤフラム、横桁用仕口、縦桁用仕口、張出ブラケット用仕口、中床板用仕口、側床板用仕口、吊りピース等の組部材又はパネルを形成する。ここで、組部材とはピースとピース、ピースと部材、部材と部材を立体的に溶接した状態を表し、この組部材と部材とは形状により部材は組部材に、組部材は部材となることがある。
【0015】
そして、形成された組部材又はパネルに対してブロック組の1つのステージで構成されるブロック組立作業を行うことにより、主桁、横桁、縦桁、張出ブラケット、中床板、側床板、対傾構、横構、耐震連結、検査路、排水装置、伸縮装置、製作高欄等のブロックを形成し、形成されたブロックを仮組及び塗装の2つのステージで構成される仮組立作業を行うことにより、2つの箱桁を横桁で連接したグループ製品を製作し、製作されたグループ製品を出荷及び現地工事の2つのステージで構成される製品としての橋梁が完成する。なお、受注形態によっては、仮組立作業まで、塗装まで、出荷までで作業を打ち切ることがある。
【0016】
そして、ステージと作業指示工程との関係は、仕分ステージでは、受入、配材、次工程送の3つの作業指示工程が含まれ、外注切断ステージでは罫書、切断、糸面取、次工程送の4つの作業指示工程が含まれ、外注加工ステージでは曲げ、孔明、機械加工、鉄工加工、次工程送の5つの作業指示工程が含まれ、一次加工ステージでは、罫書、切断及び次工程送の3つの作業指示工程が含まれ、細巾板継ラインステージでは組立、溶接、歪取、ベーダー、孔明及び次工程送の6つの作業指示工程が含まれ、広巾板継ラインステージでは、組立、溶接、歪取、ベーダー及び次工程送の5つの作業指示工程が含まれ、部材加工ステージでは罫書機(MAM)、ベーダー、切断、孔明機(SCOM)、孔明機(BV)、ラジアル端面切削、曲げ、次工程送りの8つの作業指示工程が含まれている。
【0017】
また、小物組ステージ、I桁ラインステージ、ウェブパネルラインステージ、フランジパネルラインステージ及びブロック組ステージでは、夫々組立、溶接、歪取及び次工程送の4つの作業指示工程が含まれ、仮組ステージでは仮組立、解体及び次工程送の3つの作業指示工程が含まれ、塗装ステージでは塗装準備、塗装及び次工程送の3つの作業指示工程が含まれ、出荷ステージでは横持、保管、梱包及び発送の4つの作業指示工程が含まれている。
【0018】
このように、ステージ生産方式で箱桁鋼橋が生産されるのであるが、この間の生産管理を生産管理統括システムで行う。
この生産管理統括システムは、図3に示すように、設計が完了する以前に契約重量等の基本構造情報に基づいて予め橋種毎に主作成した簡易物量算出モデルに従って簡易物量計算を行い、部品及び加工量でなる物量を算出する簡易物量算出システム11と、生産計画を支援する生産管理システム12と、簡易物量算出システム11及び生産管理システム12から入力される工数計算パラメータに基づいて工数管理を行う工数管理システム13と、受注した橋梁の設計データを作成し、この設計データに基づく部品展開属性を有する第1の構造情報を生産管理システム12に出力するCADシステム14A及び部品展開属性を有さず、部品名称の規則性を有する第2構造情報及び原板情報を生産管理システム12に出力する加工情報生成システム14Bを有する自動原寸システム14と、生産管理システム12から出力される計画データ、工程手順、工程手順ネットワーク、部品情報を含む工程計画データに基づいてガントチャートを作成して工程スケジュールを確定し、これを生産管理システム12に出力する工程管理手段としての工程スケジューラ15と、各ヤード2〜5及び屋外組立場6での実際の工数実績情報を収集する生産制御兼評価システム16とを備えている。
【0019】
また、生産管理統括システムのハードウェア構成は、図4に示すように、簡易物量算出システム11、生産管理システム12及び工数管理システム13を構築する総合管理事務所1に配設された管理用サーバ21と、この管理用サーバ21に例えばイーサネットで構成されローカルエリアネットワークLANを介して接続された製作現場に配設された複数台のパーソナルコンピュータPCF及び総合管理事務所1に配設された複数台のパーソナルコンピュータPCOと、ローカルエリアネットワークLANに接続されたプリンタPRとで構成されている。
【0020】
管理用サーバ21には、例えば箱桁橋、鈑桁橋及び鋼床版箱桁橋でなる3つの橋種に応じて予め設定されたブロック物量算出モデル及び部材物量算出モデルを格納したモデルデータベースと、橋梁を生産する場合の管理を行う生産管理データベースとが形成されている。
モデルデータベースには、図5に示す橋種に応じた橋を構成する主桁、横桁等のブロック単位の物量を算出するブロック物量算出モデルと、図6に示す橋種に応じたブロックを構成する上フランジ、下フランジ、ウェブ等の部材単位の物量を算出する部材物量算出モデルとが格納されている。
【0021】
ここで、ブロック物量算出モデルは、図5に示すように、箱桁橋、鈑桁橋及び鋼床版箱桁橋の橋種毎に、主桁の1ブロック長を表すブロック長、橋長、支承間の長さを表す支間長、同一橋梁が重連する場合の重連数、契約重量に基づく総重量,鋼材重量,主構造重量,素材重量,切板重量でなる重量、主桁数に対応するライン数、主桁以外のライン数を表す列数、1主桁のジョイント間数を表す連数、主桁,横桁,対傾構等の主構造ブロック数、主構造ブロックに対応するジョイント数、支承,伸縮装置等の主要付属品数、ソールプレート,その補強リブ,落橋防止取付板等のブロック組、主桁,支承,伸縮装置等の仮組立、プライマー種類及び製品ブラストの有無を表す塗装等の各項目が基本情報としての契約重量に基づいて設定される。
【0022】
また、部材物量算出モデルは、図6に示すように、1ブロック当たりの橋種、ブロック名称、ブロックを形成するための部材名称毎に、幅及び長さを設定する寸法、部材数、タイプ、箇所、最大板厚等の板継作業、NC罫書による罫書作業、添接孔、添接板の孔明数、開先形状,開先加工等の溶接作業、外注,対傾構ライン,吊金具,塗装用手摺取付ピース等のブロック組作業について設定値が選定されている。
【0023】
また、生産管理データベースは、図7に示すように、自動原寸システム14から入力される構造情報としての原寸展開情報に基づいて作成される5つの階層を有するツリー構造に形成された部品テーブルと、この部品テーブルにおける各階層の部品を作成するために必要な処理工程と加工量とを格納した処理工程テーブルと、この処理工程テーブルの各階層における部品毎及び工程毎に加工量を集計して、作業指示の単位となるように作成されたタスクテーブルとで構成されている。
【0024】
部品テーブルは、橋梁を構成する各部品の加工、組立等の状態により、部品をピース、部材、パネル、ブロックの各構成要素に分け、各構成要素を図7に示すツリー構造に配置することにより、5つの構造階層を形成する。そして、第1の構造階層となる物件テーブルには物件の物件情報「○○橋」が登録され、第2の構造階層となるブロックテーブルには物件を構成する主桁、横桁等のブロックのブロック情報が登録され、第3の構造階層となるパネルテーブルにはブロックを構成する主桁上フランジ、主桁下フランジ、主桁ウェブ等のパネルのパネル情報が登録され、第4の構造階層となる部材テーブルにはパネルを構成する部材の部材情報が登録され、第5の構造階層となるピーステーブルには部材を構成する最小単位部材となるピースのピース情報が登録されている。
【0025】
ここで、物件情報としては、物件毎に設定される物件ID、契約番号、装置番号、物件名、橋種IDが設定されている。また、ブロック情報としては、物件ID、ブロックID、後述するマーク体系で定義されたブロックマーク、台数、代表ブロックID、ブロック種IDが設定されている。さらに、パネル情報としては、物件ID、パネルID、後述するマーク体系で定義されたパネルマーク、所属ブロックID、台数、代表パネルID、パネル種IDが設定されている。さらにまた、部材情報としては、物件ID、部材ID、後述するマーク体系で定義された部材マーク、所属ブロックID、所属パネルID、員数、代表部材IDが設定されている。なおさらに、ピース情報としては、物件ID、ピースID、後述するマーク体系で定義されたピースマーク、所属ブロックID、所属パネルID、所属部材ID、代表ピースID、所属素材IDが設定されている。
【0026】
そして、マーク体系としては、橋種が例えば箱桁橋であるときに、図8に示すように、予め設定した箱桁橋モデルに従って第5階層のピーステーブル、第4階層の部材テーブル、第3階層のパネルテーブル及び第2階層のブロックテーブルの夫々について階層、構造種ID、構造種名、部品マークが設定され、さらに部材テーブル、パネルテーブル及びブロックテーブルについてはリンクのみを行うか否かが設定されている。
【0027】
このマーク体系を使用して設計データを出力する自動原寸システムから例えば原板単位で入力される部品マーク及び員数に基づいてピーステーブル、部材テーブル、パネルテーブル、ブロックテーブル及び物件テーブルで構成される部品データベースを自動的に作成すると共に、作成した部品データベースに基づいて個々の部品を作成するために必要な処理工程を表す処理工程テーブルを作成し、且つ自動原寸システムからの原寸展開情報に基づいて孔数、罫書長、溶接長等の加工量を表す加工量テーブルを作成し、さらに作成した処理工程テーブルに基づいて部品データベースの各階層において、部品毎、工程毎に加工量を集計して、作業指示の単位となるタスクテーブルを作成し、なおさらに自動原寸システムから入力される材料情報に基づいて素材情報を設定した原板テーブルを作成し、素材情報をもとに部品テーブルのピースを検索してマッチした素材情報が登録されたピースとリンク付けを行う。原板テーブルに登録された素材情報とピーステーブルに登録された素材情報とが一致しない場合には、両者間のリンク付けを行うことなく開放原板となる。
【0028】
そして、上記部品テーブルは自動原寸システムからCADを使用した設計が完了した時点で出力される部品展開属性を有する原寸展開情報に基づいてピーステーブル、部材テーブル、パネルテーブル及びブロックテーブルを作成し、さらに、自動原寸システムから設計データに基づいて罫書機、切断機、孔明機、溶接機に対する加工情報を作成すると共に、手動原寸の板取を行って素材切断情報を含む原板情報を作成した時点で出力される部品名称による規則性を有する原寸展開情報に基づいてピーステーブル、部材テーブル、パネルテーブル及びブロックテーブルを作成し、これらと同時に処理工程テーブル及びタスクテーブルも作成する。
【0029】
すなわち、設計を完了した時点で出力される部品展開属性を有する原寸展開情報に基づいて部品テーブルを作成する場合には、図9に示すように、原寸展開情報に部材データ、ブロックデータ、加工種類データ、加工情報データ、加工代データ、加工方法データが含まれており、これら出力データを、モデルデータを管理しているテーブル管理アプリケーションをアクセス可能な出力形式に変換してから出力データ毎に、テーブル管理アプリケーションにアクセスして、これに登録されている部材レコード、ブロックレコード、加工種類レコード、加工情報レコード、加工代レコード及び加工方法レコードを参照して、部材データからピーステーブル、部材テーブル及びパネルテーブルを作成し、ブロックデータからブロックテーブル及び物件テーブルを作成し、加工種類データ、加工情報データ、加工代データ、加工方法データから処理工程テーブルを作成し、この処理工程テーブルからタスクテーブルを作成する。
【0030】
具体的には、生産管理システム12で、図10に示す部品テーブル形成処理を実行する。この部品テーブル形成処理は、先ず、ステップS101で、自動原寸システムから出力される原寸展開情報に含まれるピース名、部材名、パネル名及びブロック名の何れかを検索対象名として、これをもとにモデルデータを格納した抽出定義テーブルを検索し、次いでステップS102に移行して、検索対象名と同一の登録名が存在するか否かを判定し、検索対象名と同一の登録名が存在しない場合には、開放ピース又は開放部材であるものと判断して、ステップS103に移行して、原寸展開情報に基づいて開放ピース又は開放部材を登録し、これと同時に処理工程モデルテーブルを参照して処理工程テーブルを登録し、加工量も同時に登録してからステップS104に移行し、全ての原寸展開情報について登録処理を終了したか否かを判定し、全ての原寸展開情報について登録処理を完了した場合にはテーブル作成処理を終了し、未処理の原寸展開情報がある場合には前記ステップS101に戻る。
【0031】
一方、前記ステップS102の判定結果が検索対象名と同一の登録名が存在するものである場合には、ステップS105に移行して、登録名が存在する階層に応じてピーステーブル、部材テーブル及びパネルテーブルの何れかにピース名、部材名及びパネル名の何れかを登録すると共に、処理工程モデルテーブルを参照して処理工程テーブルを登録し、これと同時に加工量も登録してからステップS106に移行し、抽出定義テーブルを参照して親部品とのリンク付けを行ってから前記ステップS104に移行する。
【0032】
一方、加工情報及び原板情報が作成された時点で自動原寸システムから出力される原寸展開情報には、ピースマーク名が含まれていることから、このピースマーク名を使用してマーク体系を登録したマーク体系モデルテーブルを検索することにより、階層及びリンク情報を取得して、ピーステーブル、部材テーブル、パネルテーブル及びブロックテーブルを作成する。
【0033】
具体的には、図11に示すように、先ず、ステップS111で、ピースマーク名をもとにマーク体系モデルデータを格納したマーク定義テーブルを検索する。このマーク定義テーブルは、図12に示すように、行方向にピースマークの定義名が記載され、列方向にピース、部材、パネル及びブロックの階層が記載され、ピース階層には用途名及び部品名が併記され、部材、パネル及びブロックの各階層には用途名、部品名及びリンク関係表示欄が記載されている。ここで、定義名はi及びjは変数であり、残りの英文字は定数に設定されている。また、リンク関係表示欄は、空白である場合には該当テーブルに登録すると同時にリンクを行い、「/」が記入されている場合には、テーブルに登録することなくリンクのみを行うように設定されている。
【0034】
そして、ピースマーク名で検索する際には、定義名を大文字の定数優先にソートすることにより、「GA1」「Gai」「GFaiLj」「GFaiUj」「GFaiWj」「GaiU」「GaiUW」の順にソートしておき、ピースマーク名が「GFA2W43」である場合には、定義名の変換桁に合わせてピースマーク名の同じ桁を変換してマッチングするか否かを判定する。このとき、定義名の小文字の英数字の桁位置に合わせて、ピースマーク名の同じ桁を固定値i又はjに変換する。この結果、図13に示すように、定義名「GA1」に対しては変換できず、定義名「Gai」に対しては「GaA2W43」となり変換できず、定義名「GFaiLj」「GFaiUj」に対しては、「GFaiWj」「GFaiWj」となり変換できるがマッチングせず、「GFaiWj」に対しては「GFaiWj」と変換されることによりマッチングする。
【0035】
次いで、ステップS112に移行して、ピースマーク名とマッチする登録ピースマーク名が存在するか否かを判定し、ピースマーク名とマッチする登録ピースマーク名が存在しない場合には、ステップS113に移行して、開放ピース又は開放部材としてピーステーブル又は部材テーブルにピースマーク名を登録し、処理工程モデルテーブルを参照して処理工程を処理工程テーブルに登録し、同時に加工量も登録し、次いでステップS114に移行して、全てのピースマーク名に対して登録処理が完了したか否かを判定し、全てのピースマーク名に対して登録処理が完了したときにはテーブル作成処理を終了し、未登録のピースマーク名が存在するときには前記ステップS111に戻る。
【0036】
一方、ステップS112の判定結果が、ピースマーク名とマッチする登録ピースマーク名が存在する場合には、ステップS115に移行し、該当する登録ピースマーク名が登録されている階層に対応するピーステーブル又は部材テーブルにピースマーク名を登録し、処理工程モデルテーブルを参照して処理工程を処理工程テーブルに登録し、同時に加工量も登録してからステップS116に移行する。
【0037】
このステップS116では、マーク定義テーブルを参照して、該当ピースマーク名を部材テーブルに登録する必要があるか否かを判定し、部材テーブルに登録する必要があるときには、ステップS117に移行して、部材テーブルにピースマーク名を登録すると共に、子部材とのリンク付けを行い、且つ処理工程モデルテーブルを参照して処理工程を処理工程テーブルに登録し、これと同時に加工量も登録してからステップS122に移行する。
【0038】
また、ステップS116の判定結果が部材テーブルに登録する必要がないときには、ステップS118に移行して、マーク定義テーブルを参照して部材とのリンク付けを必要とするか否かを判定する。この判定は、マーク定義テーブルで部材にリンク付けするように設定されている場合でも、子部品と親部品との員数が1:1、n:1である正規の員数であるか否かを判定し、正規の員数であるときには子部品を親部品にリンクする必要があるものと判断してステップS119に移行し、部材とのリンク付けを行ってからステップS122に移行し、マーク定義テーブルでリンク付けが設定されていないとき又は正規の員数ではないn:m又は1:nであるときにはステップS120に移行して、マーク定義テーブルで部材とのリンク不要であるか否かを判定し、部材とのリンク不要に設定されているときにはステップS122に移行し、部材とのリンク付けが設定されているときにはステップS121に移行して、物件とのリンク付けを行ってから前記ステップS114に移行する。
【0039】
ステップS122では、マーク定義テーブルを参照して、該当ピースマーク名をパネルテーブルに登録する必要があるか否かを判定し、パネルテーブルに登録する必要があるときには、ステップS123に移行して、パネルテーブルにピースマーク名を登録すると共に、子部材とのリンク付けを行い、且つ処理工程モデルテーブルを参照して処理工程を処理工程テーブルに登録し、これと同時に加工量も登録してからステップS127に移行する。
【0040】
また、ステップS122の判定結果がパネルテーブルに登録する必要がないときには、ステップS124に移行して、マーク定義テーブルを参照してパネルとのリンク付けを必要とするか否かを判定する。この判定は、マーク定義テーブルでパネルにリンク付けするように設定されている場合でも、子部品と親部品との員数が1:1、n:1である正規の員数であるか否かを判定し、正規の員数であるときには子部品を親部品にリンクする必要があるものと判断してステップS125に移行し、パネルとのリンク付けを行ってからステップS127に移行し、マーク定義テーブルでリンク付けが設定されていないとき又は正規の員数ではないn:m又は1:nであるときにはステップS126に移行して、マーク定義テーブルでパネルとのリンク不要であるか否かを判定し、パネルとのリンク不要に設定されているときにはステップS127に移行し、パネルとのリンク付けが設定されているときには前記ステップS121に移行して、物件とのリンク付けを行ってから前記ステップS114に移行する。
【0041】
ステップS127では、マーク定義テーブルを参照して、該当ピースマーク名をブロックテーブルに登録する必要があるか否かを判定し、ブロックテーブルに登録する必要があるときには、ステップS128に移行して、ブロックテーブルにピースマーク名を登録すると共に、子部品とのリンク付けを行い、且つ処理工程モデルテーブルを参照して処理工程を処理工程テーブルに登録し、これと同時に加工量も登録してから前記ステップS114に移行する。
【0042】
また、ステップS127の判定結果がブロックテーブルに登録する必要がないときには、ステップS129に移行して、マーク定義テーブルを参照してブロックとのリンク付けを必要とするか否かを判定する。この判定は、マーク定義テーブルでブロックにリンク付けするように設定されている場合でも、子部品と親部品との員数が1:1、n:1である正規の員数であるか否かを判定し、正規の員数であるときには子部品を親部品にリンクする必要があるものと判断してステップS130に移行し、ブロックとのリンク付けを行ってから前記ステップS114に移行し、マーク定義テーブルでリンク付けが設定されていないとき又は正規の員数ではないn:m又は1:nであるときにはステップS131に移行して、マーク定義テーブルでブロックとのリンク不要であるか否かを判定し、ブロックとのリンク不要に設定されているときには前記ステップS114に移行し、ブロックとのリンク付けが設定されているときには前記ステップS121に移行して、物件とのリンク付けを行ってから前記ステップS114に移行する。
【0043】
また、管理用サーバ21には、工数管理システムが構築されている。この工数管理システムは、物件毎に生産管理データベースに格納されている簡易物量データ、設計完了時のCADシステム14Aの原寸展開情報に基づく物量データ、手動原寸の板取情報及びNC情報作成時の加工情報生成システム14Bの原寸展開情報に基づく物量データに基づいて工数計算を行う。
【0044】
この工数管理システムでは、鈑桁、箱桁、鋼床版箱桁等の橋種毎に工数計算モデルを登録しておく。この工数計算モデルの登録は、生産管理システムを起動することにより行う。
この生産管理システムは、起動されると、図14に示す処理を実行し、先ず、ステップS301で、図15に示す生産管理システム初期画面をディスプレイに表示する。この生産管理システム初期画面は、図15に示すように、物件管理ボタン81、実績情報ボタン82、進捗把握ボタン83、モデル登録ボタン84、マスタ登録ボタン85、計算モデルボタン86、工程計画ボタン87及び終了ボタン88が形成され、これらボタンをマウス又はキーボードで選択することにより、対応する処理が実行される。
【0045】
次いで、ステップS302に移行して、物件管理ボタン81が選択されたか否かを判定し、物件管理ボタン81が選択されたときにはステップS303に移行して、物件基本情報の作成、原板情報の登録、作業情報の登録及び工数計算等の作業を行う物件管理処理を行ってからステップS304に移行して、終了ボタン88が選択されたか否かを判定し、終了ボタン88が選択されていないときには前記ステップS301に戻り、終了ボタン88が選択されているときには生産管理システムを終了する。
【0046】
また、前記ステップS302の判定結果が、物件管理ボタン81が選択されていないときにはステップS305に移行して、実績情報ボタン82が選択されているか否かを判定し、実績情報ボタン82が選択されているときには、ステップS306に移行して、ピース納品情報の登録、出来高チェックシートの作成及び工数実績情報の登録等の作業を行う実績情報処理を行ってから前記ステップS304に移行し、実績情報ボタン82が選択されていないときにはステップS307に移行する。
【0047】
このステップS307では、進捗把握ボタン83が選択されているか否かを判定し、進捗把握ボタン83が選択されているときには、ステップS308に移行して、ピース調達状況確認、出来高進捗確認及び工数実績進捗率ファイル作成等を行う進捗把握処理を実行してから前記ステップS304に移行し、進捗把握ボタン83が選択されていないときにはステップS309に移行する。
【0048】
このステップS309では、モデル登録ボタン84が選択されているか否かを判定し、モデル登録ボタン84が選択されているときには、ステップS310に移行して、モデル関係の各テーブルの登録・更新を行うモデル登録処理を行ってから前記ステップS304に移行し、モデル登録ボタン84が選択されていないときにはステップS311に移行する。
【0049】
このステップS311では、マスタ登録ボタン85が選択されているか否かを判定し、マスタ登録ボタン85が選択されているときには、ステップS312に移行して、マスタ関係の各テーブルの登録・更新を行うマスタ登録処理を実行してから前記ステップS304に移行し、マスタ登録ボタン85が選択されていないときにはステップS313に移行する。
【0050】
このステップS313では、計算モデルボタン86が選択されているか否かを判定し、計算モデルボタン86が選択されているときにはステップS314に移行して、工数計算基本モデルの登録・更新を行う工数計算基本モデル処理を行ってから前記ステップS304に移行し、計算モデルボタン86が選択されていないときにはステップS315に移行する。
【0051】
このステップS315では、工程計画ボタン87が選択されているか否かを判定し、工程計画ボタン87が選択されているときにはステップS316に移行して、タスクテーブルに登録された組部材の各工程について工程順・工程間繋がりを登録して工程計画を行う工程計画処理を行ってから前記ステップS304に移行し、工程計画ボタン87が選択されていないときには直接前記ステップS304に移行する。
【0052】
ここで、ステップS314の工数計算基本モデル処理は、図16に示すように、先ず、ステップS321で、工数計算基本モデル名を工数計算モデルテーブルに登録する。この工数計算基本モデルテーブルの登録は、新規に作成してもよいし、既登録の基本モデルを選択して、これに登録されている組部材及び組部材の各物量パラメータを複写するようにしてもよい。
【0053】
次いで、ステップS322に移行して、工数計算モデルテーブルに登録されている工数計算モデルを選択し、次いでステップS323に移行して、図17に示すように、フランジ、主桁ウェブ等の組部材名を組番号と共に登録する。
次いで、ステップS324に移行して、各組部材についての工数計算パラメータを定義する。この工数計算パラメータの定義は、図18に示すように、各組部材についてパラメータ番号、例えば主構造鋼重、主構造部材数、総孔数等の組部材名で一意の物量パラメータ名、モデル内で一意の定義名、整数、実数、3択等の属性、単位、表示桁文字列、アドレス、自動計算するか否かを選択するチェックボックス、自動計算式を表形式で工数計算パラメータ定義テーブルに登録する。
【0054】
次いで、ステップS325に移行して、パラメータ定義に選択型項目が含まれているか否かを判定し、パラメータ定義に選択型項目がある場合には、ステップS326に移行して、選択型項目の項目名を選択型項目テーブルに登録してからステップS327に移行して、パラメータ定義に選択型項目がない場合には直接ステップS327に移行する。
【0055】
このステップS327では、図19に示すように、工数、数量、単位工数、段取時間、効率化係数及び段取効率化係数で構成される各タスク(工程)パラメータについて各々工数計算式を入力し、この工数計算式を工数計算式テーブルに登録する。各タスクパラメータとしては、箱桁の主桁ダイヤフラムである場合に、図20に示すように、ステージ名「5機械加工」で工程名「65NC切断」である場合に、数量は「=[ダイヤフラム枚数]」、単位工数は「=([フランジ幅]+[ウェブ高さ]/1000))*2*1.5*2*2)/12/60+(([ウェブ高さ]/1000/2+[フランジ幅]/2)*2*2)/2.5/60+([フランジ幅]+([ウェブ高さ]……」、段取時間は「=0.4*[ダイヤフラム枚数]」、効率化係数は「1.5」、段取効率化係数は「1.0」が登録される。
【0056】
このようにして工数計算基本モデルを予め工数計算モデルテーブルに登録しておくことにより、この工数計算基本モデルを使用して、前述したステップS303で実行する物件管理処理において工数計算を行うことができる。
この工数計算処理は、橋種に応じてステップS314の工数計算モデル処理で登録した工数計算モデルを選択し、選択された工数計算基本モデルと前記簡易物量算出処理で登録されたブロック物量データ及び部材物量データとに基づいて工数計算を行い、工数、数量、単位工数、段取時間を演算すると共に、効率化係数及び段取効率化係数を選定する。
【0057】
この工数計算処理は、具体的には、図21に示すように、先ず、ステップS331で、物件テーブルから対象物件を選択し、次いでステップS332に移行して、橋種に応じて前記ステップS314の工数計算モデル処理で登録した工数計算基本モデルを選択し、次いでステップS333に移行して、選択した工数計算基本モデルを複写することにより、物件専用の工数計算モデルを作成してからステップS334に移行する。
【0058】
このステップS334では、物件特有の組部材があるか否かを判定し、物件特有の組部材があるときにはステップS335に移行して、組部材の追加・削除を行い、次いでステップS336に移行して、追加した組部材があるか否かを判定し、追加した組部材があるときにはステップS337に移行して、追加した組部材の工程パラメータの計算式を値で入力してからステップS338に移行し、前記ステップS334の判定結果が物件特有の組部材がないとき及び前記ステップS336の判定結果が追加した組部材がないときには直接ステップS338に移行する。
【0059】
ステップS338では、前述した生産管理データベースに登録した物量算出データを例えば表計算アプリケーションのブックに形成した工数Prmシートに組部材番号*100+パラメータ番号を行アドレスとし、列アドレス“1”を定義名、列アドレス“2”を物量パラメータとして読込み、次いでステップS339に移行して、読込んだ物量算出データをもとに、設定された工数計算式に従って工数、数量、単位工数、段取時間を算出すると共に、効率化係数及び段取効率化係数の各工程パラメータを算出し、算出した各工程パラメータをタスクパラメータテーブルに登録してからステップS340に移行する。
【0060】
このステップS340では、工程パラメータの算出結果を修正するか否かを判定し、これを修正する場合にはステップS341に移行して、効率化係数及び段取効率化係数をこれらの夫々について修正係数を乗算して修正し、修正値に基づいて再度工程パラメータを算出し直す工程パラメータの修正を行ってからステップS342に移行し、工程パラメータの修正を行わないときにはそのままステップS342に移行する。
【0061】
このステップS342では、タスクテーブル物量データに基づいて物件物量表を出力すると共に、算出した工程パラメータを元に工数計画表を出力する。物件物量表としては、図22に示すように、組部材名を横軸方向に記載し、各組部材に対する数量等の物量パラメータを縦軸方向に記載した表形式に構成されている。また、工数計画表としては、図23に示すように、組部材名を横軸方向に記載し、各部材名の夫々に対して効率化係数、工数、単位工数及び数量の工程パラメータを横軸方向に記載し、ステージ名及び工程名を縦軸方向に記載した表形式に構成されている。
【0062】
このようにして工数計算が行われた後に、工程計画が行われる。この工程計画では、引き合い時に長期的な工程計画を作成するスケジュールを作成するために、橋種毎に登録してある基本モデルより工程情報を画面表示し、受注する物件の物量に合わせて工程情報を修正してから工程順・工程間繋がりを行い、その結果を標準工程スケジュールテーブルに登録する。
【0063】
この工程順・工程間繋がり登録は、生産管理システムを起動したときの図15に示す初期画面で、前述した工程計画ボタン87を選択することにより、図24に示す工程計画支援メニューが表示され、この工程計画支援メニューで、確定工程・工程間繋がり登録ボタンを選択することにより、図25に示す工程間繋がり登録処理が実行される。
【0064】
この工程間繋がり登録処理は、先ず、ステップS501で、図26に示す確定工程・工程間繋がり登録画面をディスプレイに表示し、物件名を入力するコンボボックス401で物件テーブルに登録された物件名を選択し、次いでステップS502に移行して、選択した物件が確定工程スケジュールテーブルに登録されているか否かを判定し、確定工程スケジュールテーブルに登録されているときにはステップS503に移行して、処理区分コンボボックス402に“修正”をセットしてからステップS505に移行し、確定工程スケジュールテーブルに登録されてないときにはステップS504に移行して、処理区分コンボボックスに“新規”をセットしてからステップS505に移行する。
【0065】
ステップS505では、図26の確定・工程間繋がり登録画面の処理区分を選択するコンボボックス402で修正又は新規を選択すると、ステップS506に移行して、選択された処理区分をコンボボックス402に表示し、次いでステップS507に移行して、処理区分で新規が選択されているか否かを判定し、新規が選択されているときにはステップS508に移行して、タスクテーブルから工程情報を読出し、これをテキストボックス404に表示してからステップS512に移行する。
【0066】
また、ステップS507の判定結果が処理区分で修正が選択されているものであるときには、ステップS509に移行して、確定工程スケジュールテーブルから工程情報を読込み、これをテキストボックス404に表示してからステップS510に移行し、工程の追加・削除があるか否かを判定し、工程の追加・削除があるときにはステップS512に移行し、工程の追加・削除がないときには項目修正入力を行ってから後述するステップS518に移行する。
【0067】
ステップS512では、図26の確定・工程間繋がり登録画面の通過順付与ボタン405を選択することにより、ステップS513に移行して、製作する部材の優先順位、作業工程の工程順により、製作部材毎に通過順位を編集したり、製作部材内で通過順の入れ替えを行う通過順編集処理を行ってからステップS514に移行する。
【0068】
ここで、通過順編集処理は、部品グループ番号を昇順にソートすると共に、工程順を昇順にソートし、ソートした順番に通過順を自動発番するが、このとき、同一部品グループ内でも部材加工曲げ、部材加工ベーダー、部材加工手切断の3つの工程があるときには自動発番を保留し、同一グループ内で、機械加工MAM、機械加工NC罫書、機械加工NC切断、機械加工SCOM、機械加工BV、機械加工手孔明、機械加工孔計測の各工程について全て通過順の自動発番が完了した時点で、保留した工程の通過順を部材加工曲げ、部材加工ベーダー、部材加工手切断の順で自動発番すると共に、通過順の入れ替え処理については同一部品グループ内で、図27に示すように、例えば通過順58のIPL歪取を通過順60に変更する。
【0069】
ステップS514では、図26の確定・工程間繋がり登録画面の工程連結ボタン406が選択されたときに、ステップS515に移行して、工程間繋がり編集処理を行う。
この工程間繋がり編集処理は、先ず、“設計”、“材料手配”、“原寸処理”、“切板加工”の工程通過順を求めると共に、部品グループ「共通」の“仕分受入”、“仕分配材”の工程通過順を求める事前処理を行う。次いで、前工程順セット処理を行う。この前工程順セット処理は、“設計”の前工程順にスペースをセットし、“材料手配”の前工程順に“設計”の工程通過順をセットし、“原寸処理”の前工程順に“材料手配”の工程通過順をセットし、さらに“切板加工”の前工程順に“原寸処理”の工程通過順をセットする。
【0070】
また、部品グループ「共通」の先頭工程の前工程順に“切板加工”の工程通過順をセットし、部品グループ「共通」以外の各部品グループの先頭工程の前工程順の編集を行う。この編集処理は、先頭工程が“仕分受入”であれば、“切板加工”の工程通過順をセットし、先頭工程が“仕分配材”であれば、“仕分受入”の工程通過順をセットし、先頭工程が“仕分受入”“仕分配材”以外であれば、前記事前処理における部品グループ「共通」の“仕分配材”の工程通過順をセットし、“仕分配材”の工程が無ければ、“仕分受入”の工程通過順をセットし、事前処理で“仕分受入”及び“仕分配材”の工程が無ければ、スペースをセットする。
【0071】
次いで、各部品グループ毎に2番目以降の工程の前工程順の編集を行う。この編集は、同一部品グループ内で一件前の工程の工程通過順をセットする。
次いで、前工程順の修正処理を行う。この修正処理は、部品グループ「共通」に“機械加工孔計測”の工程があれば前工程順をクリアし、部品グループ「共通」に“仮組立”の工程があれば前工程順をクリアし、各部品グループ毎で、“板継ライン組立”“板継オフライン組立”の2工程があれば、“板継ライン組立”の前工程順を“板継オフライン組立”の前工程順にセットする。
【0072】
次いで、前工程順をセットした工程の連結タイプ・ラグの編集を行い、連結タイプに“SS”をセットすると共に、ラグに“1”をセットする。
次いで、集約工程の工程通過順検索処理を行う。この検索処理は、“ブロック組立”“仮組立解体”“塗装準備”“出荷クレーンOP”の工程通過順を求める。これらの工程は、部品グループごとで複数件ある場合があるため、部品グループ番号の昇順で検索する。
【0073】
次いで、後工程順2編集処理を行う。この後工程順2編集処理は、各部品グループの最終工程のステージ名が“ブロック組”であれば、その最終工程の後工程順2に“仮組立解体”の工程通過順をセットし、各部品グループの最終工程のステージ名が“仮組立”であれば、その最終工程の後工程順2に“塗装準備”の工程通過順をセットし、各部品グループの最終工程のステージ名が“塗装”であれば、その最終工程の後工程2に“出荷クレーンOP”の工程通過順をセットする。また、後工程順2の修正処理としては、各部品グループ毎で“板継ライン溶接”“板継オフライン溶接”の2工程があれば、同一部品グループ内で、“板継オフライン溶接”の工程通過順を前工程順としている工程を検索して、その工程の工程通過順を“板継ライン溶接”の後工程順2にセットする。さらに、後工程順2をセットした工程の連結タイプ・ラグの編集を行い、連結タイプに同時スタートを表す“SS”をセットすると共に、ラグに“1”をセットする。
【0074】
次いで、後工程順1編集処理を行う。この後工程順1編集処理は、部品グループ間で同一工程があれば、部品グループ間の工程間繋がりを後工程順1に編集する。但し、“仕分受入”“仕分配材”以外の工程のみ。すなわち、工程順(昇順)、部品グループ番号(降順)でソートし、同一工程内で2番目以降の工程の後工程順1に1件前の工程の工程通過順をセットしてから、後工程順1をセットした工程の連結タイプ・ラグの編集を行い、連結タイプに終了後処理開始を表す“FS”をセットすると共に、ラグに“0”をセットする。
【0075】
次いで、図25の処理に戻って、ステップS516に移行して修正項目があるか否かを判定し、修正項目があるときにはステップS517に移行して、項目修正入力を行ってからステップS518に移行し、修正項目がないときには直接ステップS518に移行する。
ステップS518では、図26の確定工程・工程間繋がり登録画面における更新ボタン408が選択されたときにステップS519に移行して、作成された工程計画データを標準工程スケジュールテーブルに登録する登録処理を行ってから確定工程における工程順・工程間繋がり登録処理を終了する。
【0076】
このようにして、工程計画データが登録されると、この工程計画データをガントチャートを作成する工程管理スケジューラで取り扱い可能なCSVファイルとして作成する。このCSVファイルには、工程計画を行う物件の情報を作成する計画データ、スケジュール期間を決めるための物量・作業工数及び作業工程順番を部材、作業工程毎にアクティビティ情報として作成する工程手順、部材毎の作業工程の工程間繋がり、部材間での同一作業工程の工程間繋がり及び部材間での集約作業、個々のアクティビティの工程間繋がりを作成する工程手順ネットワーク、個々のアクティビティの部品情報が含まれている。この工程計画データを工程管理スケジューラ15に読み込ませることにより、この工程管理スケジューラ15でガントチャートを作成して工程スケジュールを確定する。次いで、確定した工程スケジュールを格納したCSVファイルを読込み、確定スケジュールデータに基づいて確定工程スケジュールテーブル及びタスクテーブルを更新する。
【0077】
以上のように、上記実施形態によると、生産管理データベースを最小単位部材に相当するピースを最下位の第5階層とし、これを組合わせた組合せ部材に相当する部材を第4階層、この部材を組み合わせたパネルを第3階層、パネルを組み合わせたブロックを第2階層、ブロックを組み合わせた製品を第1階層とするツリー構造に構成された部品テーブルと、この部品テーブルの各部品を生産するために必要な処理工程を部品毎に登録した処理工程テーブルと、この処理工程テーブルの登録データに基づき作業指示の単位となるように部品毎で且つ工程毎に加工量を集計して作成したタスクテーブルとで構成することにより、橋梁を製作する際の工程順に応じたデータベースとなり、実際の進捗状況との比較を容易に行うことができると共に、タスクテーブルに基づいて工数計算や工程計画を容易に作成することができる。
【0078】
しかも、生産管理データベースの部品テーブルを設計が完了した際のCADシステムから入力される部品展開属性を有する構造情報から各階層の部品データを容易に作成することができる共に、構造情報に含まれる加工情報から処理工程テーブル及びタスクテーブルを容易に作成することができる。
また、設計が完了した後に加工情報生成システム14Bから出力される部品展開属性を有しないが部品名称に規則性を有する第2の構造情報に基づいて、ピースを表す第5階層から順次上位階層の登録データを自動的に作成することができ、確定物量データを容易に作成することができる。
【0079】
なお、上記実施形態においては、橋種モデルが鈑桁、箱桁、鋼床版箱桁の3種類である場合について説明したが、これに限定されるものではなく、他の任意の橋種のモデルも形成するようにしてもよいことは言うまでもない。
また、上記実施形態においては、鋼橋について生産管理を行う場合について説明したが、これに限定されるものではなく、鋼橋とコンクリートとを組み合わせた合成橋にも本発明を適用することができる。
【0080】
さらに、上記実施形態においては、1台の管理用サーバ21に生産管理システムを設定した場合について説明したが、これに限定されるものではなく、複数台のサーバを使用して分散処理するようにしてもよい。
さらにまた、上記実施形態においては、橋梁の生産管理装置に本発明を適用した場合について説明したが、これに限定されるものではなく、橋梁以外の建築物、人口地盤、護岸設備等の大型構造物の生産についても本発明を適用することができる。
【0081】
【発明の効果】
以上説明したように、請求項1に係る発明によれば、生産管理データベースが、部品テーブルとこの部品テーブルに基づいて作成された処理工程テーブルとこの処理工程テーブルに基づいて作成されたタスクテーブルとで構成され、タスクテーブルに、最小単位部材を格納する下位階層、この最小単位部材を組み合わせた組合せ部材を格納する中位階層、組合せ部材同士を組み合わせた上位階層を含む複数階層構造に対応させて各処理工程で処理する加工量がまとめて格納されていることにより、このタスクテーブルを参照して、工数計算や工程管理を容易に行うことができると共に、作業指示の単位とすることができるという効果が得られる。
【0082】
また、生産管理データベースを構成する各テーブルが最小単位部材を格納する下位階層からこれらを組み合わせる毎に階層が上がる複数階層構造とされているので、橋梁の製造過程に応じた階層構造となり、各階層毎に工程を管理することにより、正確な工程管理を行うことが可能となるという効果が得られる。
【0083】
さらに、請求項に係る発明によれば、部品テーブルを作成する際に、橋梁の設計完了時における構造情報が最小単位部材及びその組合せ部材との関係を表す部品展開属性を有する場合に、この部品展開属性に基づいて各階層の部品情報を格納することにより、容易に階層構造を形成することができるという効果が得られる。
【0084】
さらにまた、請求項に係る発明によれば、橋梁の設計完了時における構造情報に部品展開属性がない場合に、部品名称の規則性に基づいて最小単位部材を格納する下位階層から部品名称の規則性に基づいて順次中位階層及び上位階層を自動的に作成することができるという効果が得られる。
【図面の簡単な説明】
【図1】本発明を適用し得る橋梁製作現場を示す概略構成図である。
【図2】ステージ方式を採用した橋梁の生産工程を示す説明図である。
【図3】生産管理システムの構成を示すシステム構成図である。
【図4】生産管理システムのハードウェアを示すブロック図である。
【図5】ブロック物量算出モデルを示す説明図である。
【図6】部材物量算出モデルを示す説明図である。
【図7】生産管理データベースを示す説明図である。
【図8】原寸展開情報に基づいて部品テーブルを形成する際におけるマーク体系の説明図である。
【図9】原寸システムの出力情報と生産管理システムテーブルとの間の情報の流れを示す説明図である。
【図10】部品テーブル形成処理手順の一例を示すフローチャートである。
【図11】加工情報及び厚板情報を作成した時点での原寸展開情報に基づいて部品テーブルを形成する処理手順の一例を示すフローチャートである。
【図12】マーク定義テーブルを示す説明図である。
【図13】定義名とピースマーク名とのマッチング処理を説明する説明図である。
【図14】生産管理システムの処理手順の一例を示すフローチャートである。
【図15】生産管理システム初期画面を示す説明図である。
【図16】工数計算基本モデルの作成処理手順の一例を示すフローチャートである。
【図17】組部材登録画面を示す説明図である。
【図18】工数計算パラメータ登録画面を示す説明図である。
【図19】工数計算式登録画面を示す説明図である。
【図20】工数パラメータの一例を示す説明図である。
【図21】工数パラメータ演算処理手順の一例を示すフローチャートである。
【図22】物量表の一例を示す説明図である。
【図23】工数計画表の一例を示す説明図である。
【図24】工程計画支援メニュー画面を示す説明図である。
【図25】工程間繋がり登録処理を示すフローチャートである。
【図26】確定工程・工程間繋がり登録画面を示す説明図である。
【図27】通過順の入れ替え処理を示す説明図である。
【符号の説明】
2 部材仕分ヤード
3 フランジパネルライン
4 ウェブパネルライン
5 部材加工ヤード
6 屋外組立場
11 簡易物量算出システム
12 生産管理システム
13 工数管理システム
14 自動原寸システム
15 工程スケジューラ
16 生産制御兼評価システム
21 管理用サーバ
LAN ローカルエリアネットワーク
PCF パーソナルコンピュータ
PCO パーソナルコンピュータ
PR プリンタ
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a structure production management apparatus that manages each process of manufacturing and assembling parts when manufacturing a large structure such as a bridge, a building, artificial ground, and a seawall.
[0002]
[Prior art]
A conventional structure production management apparatus is described in Japanese Patent Application Laid-Open No. 10-277741 as manufacturing management when, for example, automatic welding of a metallic box-like structure constituting a bridge as a structure is performed. Things are known.
In this conventional example, when manufacturing a steel segment such as a box girder for a bridge with an automatic welding device, the manufacturing specifications of the steel segment created by the CAD system are used as a process management system in order to perform production control without delay. By inputting this, the process management system calculates the type and number of members that will be the material of the constituent segments, orders them or instructs them to manufacture them, and designs the design parameters of the steel segments created by the CAD system. Designed by computer, based on the design specifications of the designed steel segment, the operation pattern and welding conditions of the steel segment automatic welding equipment are selected by a robot simulator, and the selected operation pattern and welding conditions are selected by the robot. -Store in the simulator, teach the robot simulator, and teach the motion pattern and welding conditions taught Transmitted to the scan computer, so that the production of steel segment instructs from the process computer in automatic welding apparatus of the steel segment.
[0003]
[Problems to be solved by the invention]
However, in the above conventional example, a manufacturing management method for automatically welding a steel segment such as a box girder for a bridge is disclosed, but the production management of the entire bridge is not described, and the number of parts is not described. In addition, there is an unsolved problem that production management cannot be performed for the entire bridge that requires many man-hours such as joining and assembly.
[0004]
Accordingly, the present invention has been made paying attention to the unsolved problems of the above-described conventional example, and provides a structure production management apparatus capable of easily and reliably performing production management of the entire structure. It is aimed.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, a structure production management apparatus according to claim 1 is a structure production management apparatus that performs production management at the time of manufacturing a structure. The component information necessary for creating at least the minimum unit member constituting the structure and the combination member combining the minimum unit member based on A multi-level structure including at least a lower hierarchy storing minimum unit members, a middle hierarchy storing combination members combining the minimum unit members, and an upper hierarchy combining combination members. The stored parts table, and Created based on the parts table The processing steps and processing amount of each minimum unit member and combination member stored in the parts table Corresponding to the multiple hierarchical structure Processing process table to be stored, and Created based on the process table Summarizes the amount of processing to be processed in each step for the processing steps stored in the processing step table And store in correspondence with the multiple hierarchical structure A production management database having a task table is provided.
[0006]
In the invention according to claim 1, the production management database includes a parts table and Created based on this parts table Processing process table and Created based on this process table Task table and the task table , Corresponding to a multi-hierarchy structure including at least a lower hierarchy storing minimum unit members, a middle hierarchy storing combination members combining the minimum unit members, and an upper hierarchy combining combination members Since the processing amounts to be processed in each processing step are stored together, man-hour calculation and process management can be easily performed with reference to this task table, and a unit of work instruction can be obtained.
[0007]
Also ,Living Each table that makes up the production management database has a multi-level structure in which the level increases every time they are combined from the lowest level that stores the minimum unit members, so it becomes a hierarchical structure according to the bridge manufacturing process. By managing the process, accurate process management can be performed.
[0008]
And claims 2 The structure production management device according to claim 1 In the invention according to the present invention, when the structural information at the time of completion of the design of the bridge has a part development attribute representing a relationship between the minimum unit member and a combination member thereof, each part table is based on the part development attribute. It is characterized by being created by storing the part information.
[0009]
This claim 2 In the invention according to the present invention, when the parts table is created, when the structural information at the time of completion of the bridge design has part development attributes indicating the relationship between the minimum unit member and the combination member, By storing hierarchical part information, a hierarchical structure can be easily formed.
Furthermore, the claims 3 The structure production management device according to claim 1 In the invention according to claim 1, the part table includes a part name from a lower hierarchy corresponding to the minimum unit member when the structural information at the completion of the design of the structure does not have a part development attribute but the part name has regularity. It is characterized in that it is configured by sequentially creating a middle hierarchy and an upper hierarchy based on the regularity.
[0010]
This claim 3 In the invention according to the present invention, when there is no part development attribute in the structure information at the time of completion of the design of the structure, the minimum unit member is stored based on the regularity of the part name. The rank hierarchy and the upper hierarchy can be automatically created.
[0011]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
FIG. 1 is a schematic configuration diagram showing a bridge manufacturing factory showing an embodiment when the present invention is applied to the production of a bridge as a structure. In the figure, reference numeral 1 denotes a production management system for managing production of bridges. General management office with management systems such as production control / evaluation system, cost management system, procurement management system, etc. for managing the whole factory, 2 is a material sorting yard, 3 is a flange panel line FPL with an automatic welder Box girder production yard for manufacturing steel box girder bridges, 4 includes an I-girder production yard for manufacturing steel I-girder bridges, including a web panel line WPL having an automatic welding machine and an I-girder production line, 5 Is a member processing yard where a press machine, H-shaped steel camber straightening machine, NC marking machine, portal NC drilling machine (SCOM), table type NC drilling machine (BV), NC plasma cutting machine, etc. An outer set position.
[0012]
At this bridge manufacturing plant, the orders received for multiple bridges are bridge types (structure types) such as box girder, girder, steel floor slab box girder, steel floor slab girder, etc. The process management system executes the process management at the time of manufacturing these bridges and the simple quantity calculation based on the basic structure information necessary for ordering.
Here, the outline in the case of producing a bridge will be described by taking as an example the case of producing a box girder steel bridge by a stage production method. In this stage production system, as shown in Fig. 2, each automated line equipment is set as a stage as one management division, and the line concept is introduced for non-automated processes, and management is performed along the flow of production processes. This is a production method that is performed.
[0013]
First of all, by performing cutting plate processing work consisting of four stages of sorting, subcontracting cutting, subcontracting processing, and primary processing on steel plate and die steel materials, cutting plates for members, cutting plates for rough members, etc. Form a piece. This piece represents the minimum unit member in a state where the material is cut.
And, by performing member processing work consisting of three stages of narrow plate joint line, wide plate joint line and member processing on the piece, flange, deck plate, web vertical rib, stiffener, gusset, sole plate , Slab anchors, stud gibbles, anti-tilt members, painted hardware, inspection road hardware, drainage hardware, attachment plates, etc. are formed. This member represents the state which processed the cut plate, or the state which welded the piece and the piece planarly.
[0014]
Next, by performing member assembly work consisting of four stages of small parts, I-girder line (IBL), web panel line (WPL) and flange panel line (FPL) on the member, I-girder panel, web Panels, flange panels, horizontal ribs, diaphragms, horizontal girder fittings, vertical girder fittings, overhang bracket fittings, mid-floor plate fittings, side floor plate fittings, hanging pieces, etc. Form. Here, the assembled member represents a state in which a piece and a piece, a piece and a member, and a member and a member are three-dimensionally welded. The assembled member and the member are formed into a combined member and the assembled member is a member depending on the shape. There is.
[0015]
Then, by performing block assembling work consisting of one stage of the block set on the formed assembly member or panel, the main girder, the cross girder, the vertical girder, the overhanging bracket, the intermediate floor board, the side floor board, By forming blocks such as tilting structures, horizontal structures, seismic connections, inspection paths, drainage devices, telescopic devices, manufacturing rails, etc., and performing the temporary assembly work that consists of two stages of temporary assembly and painting A group product in which two box girders are connected with a horizontal girder is manufactured, and a bridge as a product composed of two stages of shipping and field work is completed. Depending on the order form, the work may be terminated until the temporary assembly work, painting, and shipping.
[0016]
The relationship between the stage and the work instruction process includes three work instruction processes in the sorting stage: acceptance, distribution, and next process feeding, and in the outsourcing cutting stage, the rules, cutting, thread chamfering, and next process feeding are performed. Four work instruction steps are included, and the subcontracting stage includes five work instruction steps including bending, drilling, machining, ironworking, and next process sending. The primary processing stage includes ruled lines, cutting, and next process sending. There are six work instruction steps, and the narrow plate joint line stage includes six work instruction steps: assembly, welding, distortion removal, vader, drilling, and next process feeding. The wide plate joint line stage includes assembly, welding, It includes five work instruction steps, such as straightening, bader, and next-step feeding. At the member processing stage, a scoring machine (MAM), a bader, cutting, a drilling machine (SCOM), a drilling machine (BV), radial end face cutting, bending, Next work Eight work instruction step of feeding are included.
[0017]
The accessory assembly stage, I-girder line stage, web panel line stage, flange panel line stage, and block assembly stage each include four work instruction steps: assembly, welding, distortion removal, and next process delivery. Will include three work instruction steps: provisional assembly, disassembly, and next process delivery, and the painting stage will include three work instruction steps: painting preparation, painting, and next process delivery. Four work instruction steps for shipping are included.
[0018]
In this way, box girder steel bridges are produced by the stage production method, and production management during this period is performed by the production management system.
As shown in FIG. 3, this production management control system performs simple quantity calculation according to a simple quantity calculation model created mainly for each bridge type in advance based on basic structure information such as contract weight before the design is completed. And a simple quantity calculation system 11 for calculating the quantity composed of the machining quantity, a production management system 12 for supporting the production plan, and the manhour management based on the manhour calculation parameters input from the simple quantity calculation system 11 and the production management system 12. It has a man-hour management system 13 to be performed, a CAD system 14A that creates design data for the received bridge and outputs first structure information having a part development attribute based on this design data to the production management system 12 and a part development attribute. The machining information generation system that outputs the second structure information and the original plate information having the regularity of the part names to the production management system 12 A Gantt chart is created based on the process data including the automatic full-size system 14 having 14B and the plan data, process procedure, process procedure network, and parts information output from the production management system 12, and the process schedule is determined. And a production control / evaluation system 16 that collects actual man-hour performance information at each of the yards 2 to 5 and the outdoor assembly site 6.
[0019]
As shown in FIG. 4, the hardware configuration of the production management system is a management server disposed in the general management office 1 that constructs the simple quantity calculation system 11, the production management system 12, and the man-hour management system 13. 21 and a plurality of personal computers PCF installed in the production site connected to the management server 21 via, for example, Ethernet and connected via a local area network LAN, and a plurality of computers installed in the general management office 1 Personal computer PCO and a printer PR connected to a local area network LAN.
[0020]
In the management server 21, for example, a model database storing a block quantity calculation model and a member quantity calculation model preset according to three bridge types including a box girder bridge, a girder bridge, and a steel deck box girder bridge; A production management database is formed for performing management when producing bridges.
In the model database, a block quantity calculation model for calculating the quantity of block units such as main girders and horizontal girders constituting a bridge corresponding to the bridge type shown in FIG. 5 and blocks corresponding to the bridge type shown in FIG. A member quantity calculation model for calculating the quantity of each member such as an upper flange, a lower flange, and a web is stored.
[0021]
Here, as shown in Fig. 5, the block quantity calculation model is a block length, a bridge length, and a bearing that represent one block length of the main girder for each type of box girder bridge, girder bridge and steel-slab box girder bridge. Corresponding to the length of spans, the number of overlapping stations when the same bridge is linked, the total weight based on the contract weight, the weight of steel, the weight of the main structure, the weight of the material, the weight of the cutting board, and the number of main girders The number of lines to represent, the number of columns representing the number of lines other than the main girder, the number of stations representing the number of joints of the main girder, the number of main structural blocks such as the main girder, the horizontal girder, and the diagonal structure , Number of main accessories such as support and expansion device, sole plate, reinforcement ribs, block assembly such as fall prevention plate, temporary assembly of main girder, support, expansion device, etc., primer type and painting indicating presence or absence of product blasting, etc. Each item is set based on the contract weight as basic information.
[0022]
In addition, as shown in FIG. 6, the member quantity calculation model includes a bridge type per block, a block name, a dimension for setting a width and a length for each member name for forming a block, the number of members, a type, Joint work such as location, maximum plate thickness, crease work by NC crease, welding holes, number of holes in the fitting plate, groove shape, welding work such as groove processing, subcontracting, anti-tilt line, hanging bracket, painting A set value is selected for block assembly work such as a handrail mounting piece.
[0023]
In addition, as shown in FIG. 7, the production management database includes a part table formed in a tree structure having five hierarchies created based on full-size development information as structure information input from the automatic full-size system 14; The processing step table storing the processing steps and the processing amount necessary for creating the parts of each hierarchy in this parts table, and the processing amount for each part and each step in each hierarchy of this processing step table, It consists of a task table created to be a unit of work instructions.
[0024]
The parts table is divided into parts such as pieces, members, panels, and blocks according to the state of processing, assembly, etc. of each part constituting the bridge, and each component is arranged in the tree structure shown in FIG. Five structural hierarchies are formed. The property information “XX Bridge” is registered in the property table that is the first structural hierarchy, and the block table such as the main girder and the horizontal beam that constitute the property is registered in the block table that is the second structural hierarchy. Block information is registered, and panel information of panels such as the main girder upper flange, main girder lower flange, main girder web, etc. constituting the block is registered in the panel table which becomes the third structural hierarchy, and the fourth structural hierarchy In the member table, member information of members constituting the panel is registered, and piece information of a piece serving as a minimum unit member constituting the member is registered in a piece table serving as the fifth structural layer.
[0025]
Here, as property information, property ID, contract number, device number, property name, and bridge type ID set for each property are set. As the block information, a property ID, a block ID, a block mark defined by a mark system to be described later, the number of units, a representative block ID, and a block type ID are set. Further, as the panel information, a property ID, a panel ID, a panel mark defined by a mark system described later, a belonging block ID, the number of units, a representative panel ID, and a panel type ID are set. Furthermore, as the member information, a property ID, a member ID, a member mark defined by a mark system to be described later, a belonging block ID, a belonging panel ID, a number, and a representative member ID are set. Further, as the piece information, a property ID, a piece ID, a piece mark defined by a mark system to be described later, a belonging block ID, a belonging panel ID, a belonging member ID, a representative piece ID, and a belonging material ID are set.
[0026]
As the mark system, for example, when the bridge type is a box girder bridge, as shown in FIG. 8, according to a box girder bridge model set in advance, a fifth level piece table, a fourth level member table, a third level table, Hierarchy, structure type ID, structure type name, and part mark are set for each of the panel table of the hierarchy and the block table of the second hierarchy, and further, whether or not only the link is performed for the member table, the panel table, and the block table is set. Has been.
[0027]
A component database composed of a piece table, a member table, a panel table, a block table, and a property table based on, for example, a component mark and quantity input from an automatic original size system that outputs design data using this mark system. Is created automatically, and a process table representing the process steps required to create individual parts is created based on the created parts database, and the number of holes based on the actual size development information from the automatic actual size system. Create a processing amount table that represents processing amount such as ruled line length, welding length, etc., and further add up the processing amount for each part and process in each layer of the parts database based on the created processing process table, and give work instructions Create a task table that becomes the unit of the material, and further add to the material information input from the automatic full-size system Zui to create a master plate table set the material information, matched material information was to perform the piece and the link with that is registered by searching the piece of parts table on the basis of material information. When the material information registered in the original plate table and the material information registered in the piece table do not match, an open original plate is obtained without linking between the two.
[0028]
Then, the part table creates a piece table, a member table, a panel table, and a block table based on the original size development information having the part development attribute output when the design using the CAD is completed from the automatic full size system. It is output at the time when the original plate information including material cutting information is created by cutting the manual original size while creating processing information for the scoring machine, cutting machine, drilling machine and welding machine based on the design data from the automatic original size system A piece table, a member table, a panel table, and a block table are created based on the original size development information having regularity according to the part names to be created, and at the same time, a processing step table and a task table are created.
[0029]
That is, when creating a part table based on the full size development information having the part development attribute that is output when the design is completed, as shown in FIG. 9, the full size development information includes member data, block data, and processing type. Data, machining information data, machining allowance data, machining method data are included.For each output data, these output data are converted into an output format accessible to the table management application that manages the model data. Access to the table management application, refer to the member record, block record, processing type record, processing information record, processing allowance record and processing method record registered in this, and from the member data, piece table, member table and panel Create a table, block data from the block data Create a table, the processing type data, processing information data, machining allowance data, to create a process table from the processing method data, to create a task table from the process table.
[0030]
Specifically, the production management system 12 executes a part table forming process shown in FIG. In this part table forming process, first, in step S101, any one of a piece name, a member name, a panel name, and a block name included in the full-size development information output from the automatic full-size system is used as a search target name. The extraction definition table storing the model data is searched for, and then the process proceeds to step S102, where it is determined whether there is a registered name that is the same as the search target name, and there is no registered name that is the same as the search target name. In such a case, it is determined that it is an open piece or an open member, and the process proceeds to step S103, where the open piece or open member is registered based on the original size development information, and at the same time, the processing process model table is referred to. After registering the process table and registering the machining amount at the same time, the process proceeds to step S104, and it is determined whether or not the registration process has been completed for all the full-size development information. And, when completing the registration process for all the original size expansion information Exit table creation processing, if there is scale development information unprocessed returns to the step S101.
[0031]
On the other hand, if the determination result in step S102 is that the registered name identical to the search target name exists, the process proceeds to step S105, and the piece table, member table, and panel are moved according to the hierarchy in which the registered name exists. Register any of the piece name, member name, and panel name in any of the tables, register the processing process table with reference to the processing process model table, and register the processing amount at the same time, and then go to step S106 Then, referring to the extraction definition table and linking with the parent part, the process proceeds to step S104.
[0032]
On the other hand, since the piece mark name is included in the full size development information output from the automatic full size system when the processing information and the original plate information are created, the mark system is registered using this piece mark name. By searching the mark system model table, the hierarchy and link information are acquired, and a piece table, a member table, a panel table, and a block table are created.
[0033]
Specifically, as shown in FIG. 11, first, in step S111, a mark definition table storing mark system model data is searched based on the piece mark name. In this mark definition table, as shown in FIG. 12, the definition name of the piece mark is described in the row direction, the hierarchy of pieces, members, panels, and blocks is described in the column direction. Are also written, and a usage name, a part name, and a link relation display column are described in each layer of the member, the panel, and the block. Here, the definition names i and j are variables, and the remaining English characters are set to constants. In addition, if the link relation display column is blank, a link is made at the same time as registering in the corresponding table, and if “/” is entered, only the link is set without registering in the table. ing.
[0034]
Then, when searching by piece mark name, the definition names are sorted in order of uppercase constants, thereby sorting in the order of “GA1”, “Gai”, “GFaiLj”, “GFaiUj”, “GFaiWj”, “GaiU”, and “GaiUW”. If the piece mark name is “GFA2W43”, it is determined whether or not matching is performed by converting the same digit of the piece mark name in accordance with the conversion digit of the definition name. At this time, the same digit of the piece mark name is converted into a fixed value i or j in accordance with the lower case alphanumeric character position of the definition name. As a result, as shown in FIG. 13, the definition name “GA1” cannot be converted, the definition name “Gai” cannot be converted to “GaA2W43”, and the definition names “GFaiLj” and “GFaiUj” cannot be converted. Therefore, “GFaiWj” and “GFaiWj” can be converted but not matched, and “GFaiWj” is matched by being converted to “GFaiWj”.
[0035]
Next, the process proceeds to step S112, where it is determined whether there is a registered piece mark name that matches the piece mark name. If there is no registered piece mark name that matches the piece mark name, the process proceeds to step S113. The piece mark name is registered in the piece table or member table as an open piece or member, the processing step is registered in the processing step table with reference to the processing step model table, and the processing amount is also registered at the same time, and then step S114. To determine whether or not registration processing has been completed for all piece mark names. When registration processing has been completed for all piece mark names, the table creation processing is terminated and unregistered pieces are registered. When the mark name exists, the process returns to step S111.
[0036]
On the other hand, if there is a registered piece mark name that matches the piece mark name as a result of the determination in step S112, the process proceeds to step S115, where the piece table corresponding to the hierarchy in which the corresponding registered piece mark name is registered or The piece mark name is registered in the member table, the processing step is registered in the processing step table with reference to the processing step model table, and the processing amount is registered at the same time, and the process proceeds to step S116.
[0037]
In this step S116, referring to the mark definition table, it is determined whether or not the corresponding piece mark name needs to be registered in the member table. When it is necessary to register in the member table, the process proceeds to step S117, Registering the piece mark name in the member table, linking with the child member, registering the processing step in the processing step table with reference to the processing step model table, and simultaneously registering the processing amount at the same time The process proceeds to S122.
[0038]
If the determination result in step S116 does not need to be registered in the member table, the process proceeds to step S118, and it is determined whether or not linking with a member is required with reference to the mark definition table. This determination determines whether or not the number of child parts and parent parts is a normal number of 1: 1 and n: 1 even when the mark definition table is set to link to the member. If it is a regular number, it is determined that it is necessary to link the child part to the parent part, and the process proceeds to step S119. After linking with the member, the process proceeds to step S122, and the link is made in the mark definition table. When no attachment is set or when n: m or 1: n which is not a regular number, the process proceeds to step S120 to determine whether or not linking with a member is unnecessary in the mark definition table. If the link is set to be unnecessary, the process proceeds to step S122. If the link with the member is set, the process proceeds to step S121 to perform the link with the property. The process proceeds to the step S114 after.
[0039]
In step S122, it is determined whether or not the corresponding piece mark name needs to be registered in the panel table by referring to the mark definition table. If it is necessary to register the piece mark name in the panel table, the process proceeds to step S123. The piece mark name is registered in the table, linked to the child member, and the processing step is registered in the processing step table with reference to the processing step model table. Migrate to
[0040]
When the determination result in step S122 does not need to be registered in the panel table, the process proceeds to step S124, and it is determined whether or not it is necessary to link the panel with reference to the mark definition table. This determination is whether or not the number of child parts and parent parts is a normal number of 1: 1 and n: 1 even if the mark definition table is set to link to the panel. If it is a regular number, it is determined that the child part needs to be linked to the parent part, and the process proceeds to step S125. After linking with the panel, the process proceeds to step S127, and the link is made in the mark definition table. When no labeling is set or when n: m or 1: n which is not a regular number, the process proceeds to step S126 to determine whether or not a link with the panel is unnecessary in the mark definition table. If the link is not required, the process proceeds to step S127. If the link with the panel is set, the process proceeds to step S121, Transition from performing link with the step S114.
[0041]
In step S127, it is determined whether or not the corresponding piece mark name needs to be registered in the block table by referring to the mark definition table. If it is necessary to register the block mark name in the block table, the process proceeds to step S128. Registering the piece mark name in the table, linking with the child parts, referring to the process model table, registering the process in the process table, and simultaneously registering the machining amount, the step The process proceeds to S114.
[0042]
When the determination result in step S127 does not need to be registered in the block table, the process proceeds to step S129, and it is determined whether or not linking with the block is required with reference to the mark definition table. This determination is made whether or not the number of child parts and parent parts is a normal number of 1: 1 and n: 1 even if the mark definition table is set to link to the block. If it is a regular number, it is determined that the child part needs to be linked to the parent part, and the process proceeds to step S130. After linking with the block, the process proceeds to step S114, and the mark definition table When linking is not set or when n: m or 1: n which is not a regular number, the process proceeds to step S131 to determine whether or not linking with a block is unnecessary in the mark definition table. If the link is not required, the process proceeds to step S114. If the link with the block is set, the process proceeds to step S121. On the line, the transition from performing linking and properties to the step S114.
[0043]
Further, a man-hour management system is constructed in the management server 21. This man-hour management system consists of simple physical quantity data stored in the production management database for each property, physical quantity data based on the full-scale development information of the CAD system 14A when the design is completed, manual full-size planing information, and machining information when creating NC information. The man-hour calculation is performed based on the quantity data based on the actual size development information of the generation system 14B.
[0044]
In this man-hour management system, a man-hour calculation model is registered for each bridge type such as a girder, a box girder, and a steel deck box girder. This man-hour calculation model is registered by starting the production management system.
When this production management system is activated, the process shown in FIG. 14 is executed. First, in step S301, the production management system initial screen shown in FIG. 15 is displayed on the display. As shown in FIG. 15, the production management system initial screen includes a property management button 81, a result information button 82, a progress grasp button 83, a model registration button 84, a master registration button 85, a calculation model button 86, a process plan button 87, An end button 88 is formed, and a corresponding process is executed by selecting these buttons with a mouse or a keyboard.
[0045]
Next, the process proceeds to step S302, where it is determined whether or not the property management button 81 is selected. When the property management button 81 is selected, the process proceeds to step S303, where basic property information creation, original plate information registration, After performing property management processing for performing work such as work information registration and man-hour calculation, the process proceeds to step S304 to determine whether or not the end button 88 has been selected. Returning to S301, when the end button 88 is selected, the production management system is ended.
[0046]
If the determination result in step S302 indicates that the property management button 81 has not been selected, the process proceeds to step S305, where it is determined whether or not the result information button 82 has been selected, and the result information button 82 has been selected. If there is, the process proceeds to step S306, and after performing performance information processing for performing operations such as registration of piece delivery information, creation of a work volume check sheet, and registration of man-hour performance information, the process proceeds to step S304 and the performance information button 82 When is not selected, the process proceeds to step S307.
[0047]
In step S307, it is determined whether or not the progress grasp button 83 is selected. When the progress grasp button 83 is selected, the process proceeds to step S308, where the piece procurement status confirmation, the volume progress confirmation, and the man-hour performance progress are made. The process proceeds to step S304 after executing the progress grasping process for creating a rate file, etc. If the progress grasp button 83 is not selected, the process proceeds to step S309.
[0048]
In this step S309, it is determined whether or not the model registration button 84 is selected. When the model registration button 84 is selected, the process proceeds to step S310, and the model for registering / updating each table related to the model. After performing the registration process, the process proceeds to step S304. When the model registration button 84 is not selected, the process proceeds to step S311.
[0049]
In this step S311, it is determined whether or not the master registration button 85 has been selected. If the master registration button 85 has been selected, the process proceeds to step S312 to register / update the master-related tables. After executing the registration process, the process proceeds to step S304. When the master registration button 85 is not selected, the process proceeds to step S313.
[0050]
In this step S313, it is determined whether or not the calculation model button 86 has been selected. If the calculation model button 86 has been selected, the process proceeds to step S314, and the manhour calculation basic for registering / updating the manhour calculation basic model is performed. After performing the model processing, the process proceeds to step S304, and when the calculation model button 86 is not selected, the process proceeds to step S315.
[0051]
In step S315, it is determined whether or not the process plan button 87 is selected. If the process plan button 87 is selected, the process proceeds to step S316, and the process is performed for each process of the assembled member registered in the task table. After performing the process planning process for registering the sequence / process connection and performing the process planning, the process proceeds to step S304. When the process plan button 87 is not selected, the process proceeds directly to step S304.
[0052]
Here, in the man-hour calculation basic model process in step S314, as shown in FIG. 16, first, in step S321, the man-hour calculation basic model name is registered in the man-hour calculation model table. Registration of this man-hour calculation basic model table may be newly created, or an already registered basic model may be selected, and the assembly member registered in this and each quantity parameter of the assembly member may be copied. Also good.
[0053]
Next, the process proceeds to step S322, and the man-hour calculation model registered in the man-hour calculation model table is selected. Then, the process proceeds to step S323, and as shown in FIG. Is registered with the set number.
Next, the process proceeds to step S324, and manhour calculation parameters for each assembled member are defined. As shown in FIG. 18, the man-hour calculation parameter is defined by a parameter number for each assembled member, for example, a unique quantity parameter name by a group member name such as main structural steel weight, number of main structural members, total number of holes, etc. Unique definition name, integer, real number, 3 choice attributes, unit, display digit string, address, check box to select whether to calculate automatically, automatic calculation formula in tabular format parameter definition table sign up.
[0054]
Next, the process proceeds to step S325 to determine whether or not the selection type item is included in the parameter definition. If the selection type item is included in the parameter definition, the process proceeds to step S326 to select the item of the selection type item. After the name is registered in the selection type item table, the process proceeds to step S327, and when there is no selection type item in the parameter definition, the process proceeds directly to step S327.
[0055]
In this step S327, as shown in FIG. 19, a manhour calculation formula is input for each task (process) parameter composed of the manhour, quantity, unit manhour, setup time, efficiency factor, and setup efficiency factor. The man-hour calculation formula is registered in the man-hour calculation formula table. As each task parameter, when the main girder diaphragm is a box girder, as shown in FIG. 20, when the stage name is “5 machining” and the process name is “65 NC cutting”, the quantity is “= [number of diaphragms”. ], The unit man-hour is “= ([flange width] + [web height] / 1000)) * 2 * 1.5 * 2 * 2) / 12/60 + (([web height] / 1000/2 + [ Flange width] / 2) * 2 * 2) /2.5/60 + ([flange width] + ([web height] ... "), setup time is" = 0.4 * [number of diaphragms] ", efficiency The conversion factor is registered as “1.5” and the setup efficiency improvement factor as “1.0”.
[0056]
By previously registering the man-hour calculation basic model in the man-hour calculation model table in this way, man-hour calculation can be performed in the property management process executed in step S303 described above using the man-hour calculation basic model. .
In this man-hour calculation process, the man-hour calculation model registered in the man-hour calculation model process in step S314 is selected according to the bridge type, and the selected man-hour calculation basic model and the block physical quantity data and members registered in the simple physical quantity calculation process are selected. Man-hour calculation is performed based on the quantity data, and man-hours, quantities, unit man-hours and setup time are calculated, and an efficiency factor and a setup efficiency factor are selected.
[0057]
Specifically, in the man-hour calculation process, as shown in FIG. 21, first, in step S331, the target property is selected from the property table, and then the process proceeds to step S332, where the step S314 is performed according to the bridge type. Select the man-hour calculation basic model registered in the man-hour calculation model process, and then move to step S333 to create the man-hour calculation model dedicated to the property by copying the selected man-hour calculation basic model, and then move to step S334 To do.
[0058]
In this step S334, it is determined whether or not there is an assembly member specific to the property. If there is an assembly member specific to the property, the process proceeds to step S335 to add / delete the assembly member, and then to step S336. Then, it is determined whether or not there is an added assembled member. When there is an added assembled member, the process proceeds to step S337, and the formula for calculating the process parameter of the added assembled member is input as a value, and then the process proceeds to step S338. When the determination result of step S334 indicates that there is no property-specific assembly member and when the determination result of step S336 does not include the assembly member, the process directly proceeds to step S338.
[0059]
In step S338, the quantity calculation data registered in the production management database described above is, for example, the man-hour Prm sheet formed in the book of the spreadsheet application, the assembly member number * 100 + parameter number is the row address, the column address “1” is the definition name, The column address “2” is read as the quantity parameter, and then the process proceeds to step S339, and the man-hour, quantity, unit man-hour and setup time are calculated according to the set man-hour calculation formula based on the read quantity calculation data. At the same time, each process parameter of the efficiency coefficient and the setup efficiency coefficient is calculated, and each calculated process parameter is registered in the task parameter table, and the process proceeds to step S340.
[0060]
In this step S340, it is determined whether or not the calculation result of the process parameter is to be corrected. When this is corrected, the process proceeds to step S341, and the efficiency coefficient and the setup efficiency coefficient are corrected coefficient for each of them. And the process parameter is corrected again based on the correction value. Then, the process proceeds to step S342. When the process parameter is not corrected, the process proceeds to step S342.
[0061]
In step S342, the property quantity table is output based on the task table quantity data, and the man-hour plan table is output based on the calculated process parameters. As shown in FIG. 22, the property quantity table is configured in a table format in which the name of the assembly member is described in the horizontal axis direction, and the quantity parameter such as the quantity for each assembly member is described in the vertical axis direction. In addition, as shown in FIG. 23, the man-hour plan table describes assembly member names in the horizontal axis direction, and efficiency factors, man-hours, unit man-hours and numbers for each of the member names. Quantity The process parameters are described in the horizontal axis direction, and the stage name and the process name are configured in a table format described in the vertical axis direction.
[0062]
After man-hour calculation is performed in this way, a process plan is performed. In this process plan, in order to create a schedule for creating a long-term process plan at the time of inquiry, process information is displayed on the screen from the basic model registered for each bridge type, and process information according to the quantity of the property to be ordered After the process is corrected, the process order and the connection between processes are performed, and the result is registered in the standard process schedule table.
[0063]
In this process order / inter-process connection registration, the process plan support menu shown in FIG. 24 is displayed by selecting the process plan button 87 described above on the initial screen shown in FIG. 15 when the production management system is activated. By selecting the confirmation process / inter-process connection registration button in the process plan support menu, the inter-process connection registration process shown in FIG. 25 is executed.
[0064]
In this process connection registration process, first, in step S501, the confirmation process / process connection registration screen shown in FIG. Then, the process proceeds to step S502, where it is determined whether or not the selected property is registered in the confirmed process schedule table. After "correction" is set in the box 402, the process proceeds to step S505. When it is not registered in the fixed process schedule table, the process proceeds to step S504, and "new" is set in the process category combo box, and then to step S505. Transition.
[0065]
In step S505, when correction or new is selected in the combo box 402 for selecting the processing category on the confirmation / inter-process connection registration screen in FIG. 26, the process proceeds to step S506, and the selected processing category is displayed in the combo box 402. Then, the process proceeds to step S507, where it is determined whether or not new is selected in the processing category. If new is selected, the process proceeds to step S508 to read the process information from the task table and store it in the text box. After displaying in 404, the process proceeds to step S512.
[0066]
If the determination result in step S507 is that correction is selected in the process category, the process proceeds to step S509, the process information is read from the fixed process schedule table, and displayed in the text box 404 before the step. The process proceeds to S510, where it is determined whether or not there is a process addition / deletion. If there is a process addition / deletion, the process proceeds to step S512. The process proceeds to step S518.
[0067]
In step S512, by selecting the pass order assignment button 405 on the confirmation / inter-process connection registration screen in FIG. 26, the process proceeds to step S513, and each production member is determined according to the priority order of the members to be produced and the process order of the work process. After the passage order is edited or the passage order editing process for changing the passage order in the production member is performed, the process proceeds to step S514.
[0068]
Here, the passing order editing process sorts the part group numbers in ascending order, sorts the process order in ascending order, and automatically issues the passing order in the sorted order. Automatic numbering is suspended when there are three processes: bending, member processing Vader, and member processing manual cutting, and within the same group, machining MAM, machining NC rule, machining NC cutting, machining SCOM, machining BV When the automatic numbering of the passing order is complete for each process of machining manual drilling and machining hole measurement, the passing order of the suspended processes is automatically processed in the order of member processing bending, member processing vader, and member processing manual cutting. In addition to the numbering, the pass order changing process is performed by changing the IPL distortion in the pass order 58 to the pass order 60 as shown in FIG.
[0069]
In step S514, when the process connection button 406 on the confirmation / inter-process connection registration screen in FIG. 26 is selected, the process proceeds to step S515 to perform inter-process connection editing processing.
This inter-process connection editing process first obtains the order of passing through the processes of “design”, “material arrangement”, “original size processing”, “cutting plate processing”, and “sort acceptance”, “finishing” of the part group “common”. Pre-processing for obtaining the process passing order of the “distributor” is performed. Next, a pre-process order set process is performed. This pre-process order set processing sets the space in the order of the previous process of “design”, sets the process passing order of “design” in the order of the previous process of “material arrangement”, and arranges “material arrangement in the order of the previous process of“ original size processing ”. The process passing order of “process” is set, and the process passing order of “original size processing” is set in the order of the previous process of “cutting plate processing”.
[0070]
In addition, the process passing order of “cutting plate processing” is set in the order of the previous process of the first process of the part group “common”, and the order of the previous process of the first process of each part group other than the part group “common” is edited. This editing process sets the process passing order of “cutting plate processing” if the top process is “sort acceptance”, and sets the process passing order of “sort acceptance” if the top process is “distribution material”. If the first process is other than “Accept sorting” and “Distribution material”, set the process passing order of “Distribution material” in the part group “Common” in the pre-processing, and set the “Distribution material” If there is no process, the process passing order of “sort acceptance” is set, and if there is no “sort acceptance” and “distribution material” process in the pre-processing, a space is set.
[0071]
Next, editing in order of the previous process of the second and subsequent processes is performed for each part group. This editing sets the process passing order of the previous process within the same part group.
Next, correction processing in the order of the previous process is performed. This correction process clears the previous process order if the part group “common” has a “machined hole measurement” process, and clears the previous process order if the part group “common” has a “temporary assembly” process. If there are two processes of “plate joint line assembly” and “plate joint offline assembly” for each part group, the order of the previous process of “plate joint line assembly” is set in the order of the previous process of “plate joint offline assembly”.
[0072]
Next, the connection type / lag of the process in which the order of the previous process is set is edited, and “SS” is set to the connection type and “1” is set to the lug.
Next, a process passage order search process of the aggregation process is performed. This search process obtains the process passing order of “block assembly”, “temporary assembly disassembly”, “painting preparation”, and “shipping crane OP”. Since there may be a plurality of these processes for each part group, search is performed in ascending order of the part group number.
[0073]
Next, post-order 2 editing processing is performed. In this post-process order 2 editing process, if the stage name of the final process of each part group is “block set”, the process passing order of “temporary assembly / disassembly” is set in post-process order 2 of the final process. If the stage name of the final process of the part group is “temporary assembly”, the process passing order of “preparation for painting” is set in the second process order 2 of the final process, and the stage name of the final process of each part group is “painting” ", The process passing order of the" shipping crane OP "is set in the post-process 2 of the final process. In addition, if there are two processes of “plate joint line welding” and “plate joint offline welding” for each part group as the correction process in the post-process order 2, the process of “plate joint offline welding” within the same part group The process having the passing order as the previous process order is searched, and the process passing order of the process is set to the post-process order 2 of the “joint line welding”. Further, the connection type / lag of the process in which the post-process order 2 is set is edited, and “SS” indicating simultaneous start is set in the connection type, and “1” is set in the lug.
[0074]
Next, post-order 1 editing processing is performed. In this post-process order 1 editing process, if there is the same process between the part groups, the inter-process connection between the part groups is edited in the post-process order 1. However, only processes other than “Sorting receipt” and “Distributing material”. That is, sort by process order (ascending order) and part group number (descending order), and set the process passing order of the previous process to the post-process order 1 of the second and subsequent processes in the same process, and then the post-process Edit the connection type lag of the process in which the order 1 is set, and set “FS” indicating the start of post-end processing to the connection type and set “0” to the lag.
[0075]
Next, returning to the process of FIG. 25, the process proceeds to step S516 to determine whether or not there is a correction item. If there is a correction item, the process proceeds to step S517, and the item correction input is performed and then the process proceeds to step S518. If there is no correction item, the process directly proceeds to step S518.
In step S518, when the update button 408 on the confirmation process / inter-process connection registration screen in FIG. 26 is selected, the process proceeds to step S519, and a registration process for registering the created process plan data in the standard process schedule table is performed. After that, the process order / inter-process connection registration process in the finalized process is terminated.
[0076]
When the process plan data is registered in this way, the process plan data is created as a CSV file that can be handled by the process management scheduler that creates the Gantt chart. In this CSV file, plan data for creating property information for process planning, quantity / work man-hour and work process order for determining the schedule period are members, process procedures for creating activity information for each work process, for each member Included is a process sequence network for creating inter-process linkages between individual processes, creating inter-process linkages between parts in the same work process and aggregated work between parts, inter-process linkages for individual activities, and parts information for individual activities. ing. By reading this process plan data into the process management scheduler 15, the process management scheduler 15 creates a Gantt chart and finalizes the process schedule. Next, the CSV file storing the confirmed process schedule is read and based on the confirmed schedule data. Sure The regular process schedule table and task table are updated.
[0077]
As described above, according to the above-described embodiment, the piece corresponding to the minimum unit member in the production management database is the fifth lowest layer, the member corresponding to the combined member obtained by combining these pieces is the fourth layer, and this member is In order to produce a part table configured in a tree structure in which the combined panel is the third hierarchy, the block combining the panels is the second hierarchy, and the product combining the blocks is the first hierarchy, and each part of the part table is produced. A processing process table in which necessary processing processes are registered for each part, and a task table created by aggregating the machining amount for each part and for each process so as to be a unit of work instruction based on registration data of the processing process table; By constructing the database, the database according to the process sequence when manufacturing the bridge With Thus, comparison with the actual progress can be easily performed, and man-hour calculation and process plan can be easily created based on the task table.
[0078]
Moreover, it is possible to easily create part data of each layer from the structure information having the part development attribute inputted from the CAD system when the design of the parts table of the production management database is completed, and the processing included in the structure information A processing step table and a task table can be easily created from the information.
In addition, on the basis of the second structure information that does not have the part development attribute output from the machining information generation system 14B after the design is completed but has regularity in the part name, the order of the upper hierarchy from the fifth hierarchy representing the pieces is sequentially increased. Registration data can be created automatically, and definite quantity data can be created easily.
[0079]
In the above-described embodiment, the case where the bridge type models are three types of the girder, the box girder, and the steel deck box girder has been described. However, the present invention is not limited to this, and the model of any other bridge type is used. Needless to say, it may also be formed.
Moreover, in the said embodiment, although the case where production management was performed about a steel bridge was demonstrated, it is not limited to this, This invention is applicable also to the synthetic bridge which combined the steel bridge and concrete. .
[0080]
Furthermore, although the case where the production management system is set in one management server 21 has been described in the above embodiment, the present invention is not limited to this, and distributed processing is performed using a plurality of servers. May be.
Furthermore, in the above-described embodiment, the case where the present invention is applied to a production management device for bridges has been described. However, the present invention is not limited to this, and large structures such as buildings other than bridges, artificial ground, seawall facilities, etc. The present invention can also be applied to the production of goods.
[0081]
【The invention's effect】
As described above, according to the first aspect of the invention, the production management database includes the parts table and Created based on this parts table Processing process table and Created based on this process table Task table and the task table Corresponding to a multi-layer structure including a lower hierarchy storing minimum unit members, a middle hierarchy storing combination members combining the minimum unit members, and an upper hierarchy combining combination members Since the processing amount to be processed in each processing step is stored together, it is possible to easily perform manhour calculation and process management with reference to this task table and to be a unit of work instructions. An effect is obtained.
[0082]
Also ,Living Each table that makes up the production management database has a multi-level structure in which the level increases every time they are combined from the lowest level that stores the minimum unit members, so it becomes a hierarchical structure according to the bridge manufacturing process. By managing the process, it is possible to obtain an effect that accurate process management can be performed.
[0083]
And claims 2 According to the invention according to the present invention, when the parts table is created, when the structural information at the time of completion of the bridge design has a part development attribute that represents the relationship between the minimum unit member and the combination member, based on the part development attribute. By storing the component information of each hierarchy, an effect that a hierarchical structure can be easily formed is obtained.
[0084]
Furthermore, the claims 3 According to the invention according to the present invention, when there is no part development attribute in the structure information at the time of bridge design completion, the minimum unit member is stored based on the regularity of the part name, and sequentially based on the regularity of the part name. There is an effect that the middle hierarchy and the upper hierarchy can be automatically created.
[Brief description of the drawings]
FIG. 1 is a schematic configuration diagram showing a bridge manufacturing site to which the present invention can be applied.
FIG. 2 is an explanatory diagram showing a production process of a bridge adopting a stage method.
FIG. 3 is a system configuration diagram showing a configuration of a production management system.
FIG. 4 is a block diagram illustrating hardware of a production management system.
FIG. 5 is an explanatory diagram showing a block quantity calculation model.
FIG. 6 is an explanatory diagram showing a member quantity calculation model.
FIG. 7 is an explanatory diagram showing a production management database.
FIG. 8 is an explanatory diagram of a mark system when a parts table is formed based on original size development information.
FIG. 9 is an explanatory diagram showing a flow of information between output information of a full-size system and a production management system table.
FIG. 10 is a flowchart illustrating an example of a parts table formation processing procedure.
FIG. 11 is a flowchart showing an example of a processing procedure for forming a component table based on original size development information at the time when processing information and thick plate information are created.
FIG. 12 is an explanatory diagram showing a mark definition table.
FIG. 13 is an explanatory diagram illustrating a matching process between a definition name and a piece mark name.
FIG. 14 is a flowchart illustrating an example of a processing procedure of the production management system.
FIG. 15 is an explanatory diagram showing an initial screen of the production management system.
FIG. 16 is a flowchart illustrating an example of a procedure for creating a man-hour calculation basic model.
FIG. 17 is an explanatory view showing an assembly member registration screen.
FIG. 18 is an explanatory diagram showing a man-hour calculation parameter registration screen.
FIG. 19 is an explanatory diagram showing a man-hour calculation formula registration screen.
FIG. 20 is an explanatory diagram showing an example of a man-hour parameter.
FIG. 21 is a flowchart illustrating an example of a man-hour parameter calculation processing procedure;
FIG. 22 is an explanatory diagram showing an example of a quantity table.
FIG. 23 is an explanatory diagram showing an example of a man-hour plan table.
FIG. 24 is an explanatory diagram showing a process plan support menu screen.
FIG. 25 is a flowchart showing inter-process connection registration processing;
FIG. 26 is an explanatory diagram showing a confirmation process / inter-process connection registration screen;
FIG. 27 is an explanatory diagram showing a passing order switching process;
[Explanation of symbols]
2 Material sorting yard
3 Flange panel line
4 Web panel line
5 Material processing yard
6 outdoor assembly hall
11 Simple quantity calculation system
12 Production management system
13 Effort management system
14 Automatic full-scale system
15 Process scheduler
16 Production control and evaluation system
21 Management server
LAN local area network
PCF personal computer
PCO personal computer
PR printer

Claims (3)

構造物を製作する際の生産管理を行う構造物の生産管理装置において、前記構造物の設計完了時における構造情報に基づいて少なくとも前記構造物を構成する最小単位部材及び当該最小単位部材を組み合わせた組合せ部材の作成に必要とする部品情報を、少なくとも最小単位部材を格納する下位階層、この最小単位部材を組み合わせた組合せ部材を格納する中位階層、組合せ部材同士を組み合わせた上位階層を含む複数階層構造で格納した部品テーブルと、該部品テーブルに基づいて作成した当該部品テーブルに格納された各最小単位部材及び組合せ部材の処理工程及び加工量を前記複数階層構造に対応させて格納する処理工程テーブルと、該処理工程テーブルに基づいて作成した当該処理工程テーブルに格納された処理工程について各工程で処理する加工量をまとめて前記複数階層構造に対応させて格納するタスクテーブルとを有する生産管理データベースを備えていることを特徴とする構造物の生産管理装置。In a structure production management apparatus that performs production management at the time of manufacturing a structure, at least a minimum unit member constituting the structure and the minimum unit member are combined based on structure information at the time of completion of design of the structure Multiple layers including parts information required to create a combination member , at least a lower layer storing the minimum unit member, a middle layer storing the combination member combining the minimum unit member, and an upper layer combining the combination members and parts table storing in structure, the process of storing and processing steps and processing amount of each minimum unit members and combinations member stored in those said parts table created based on the component table in correspondence to said plurality hierarchy table and, the processing person the process for by processing steps stored in the table each step created on the basis of the process table Production control apparatus of the structure, characterized in that collectively processing amount to be processed and a production management database and a task table which stores in correspondence with the plurality hierarchy. 前記部品テーブルは、前記構造物の設計完了時における構造情報が前記最小単位部材及びその組合せ部材との関係を表す部品展開属性を有する場合に、この部品展開属性に基づいて各階層の部品情報を格納することにより作成されていることを特徴とする請求項記載の構造物の生産管理装置。When the structural information at the time of completion of the design of the structure has a component expansion attribute indicating the relationship between the minimum unit member and the combination member, the component table displays the component information of each layer based on the component expansion attribute. The structure production management apparatus according to claim 1 , wherein the structure production management apparatus is created by storing the structure. 前記部品テーブルは、前記構造物の設計完了時における構造情報が部品展開属性を有さないが部品名称に規則性を有する場合に、最小単位部材に応じた下位階層から部品名称の規則性に基づいて順次中位階層及び上位階層を作成することにより構成されていることを特徴とする請求項記載の構造物の生産管理装置。The part table is based on the regularity of the part name from the lower hierarchy corresponding to the minimum unit member when the structural information at the completion of the design of the structure does not have the part development attribute but the part name has regularity. The structure production management apparatus according to claim 1 , wherein the structure production management apparatus is configured by sequentially creating a middle hierarchy and an upper hierarchy.
JP2001023157A 2001-01-31 2001-01-31 Structure production management equipment Expired - Fee Related JP3756417B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001023157A JP3756417B2 (en) 2001-01-31 2001-01-31 Structure production management equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001023157A JP3756417B2 (en) 2001-01-31 2001-01-31 Structure production management equipment

Publications (2)

Publication Number Publication Date
JP2002229627A JP2002229627A (en) 2002-08-16
JP3756417B2 true JP3756417B2 (en) 2006-03-15

Family

ID=18888474

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001023157A Expired - Fee Related JP3756417B2 (en) 2001-01-31 2001-01-31 Structure production management equipment

Country Status (1)

Country Link
JP (1) JP3756417B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112001635A (en) * 2020-08-25 2020-11-27 上海汽车集团股份有限公司 Process flow determination method, device, server and storage medium
JP2023177506A (en) * 2022-06-02 2023-12-14 株式会社アマダ Work management device, work management system, work management method and work management program

Also Published As

Publication number Publication date
JP2002229627A (en) 2002-08-16

Similar Documents

Publication Publication Date Title
Eastman BIM handbook: A guide to building information modeling for owners, managers, designers, engineers and contractors
US7496487B2 (en) Computer-implemented building design and modeling and project cost estimation and scheduling system
CN108763710A (en) A kind of assembled architecture forward direction Deepen Design method based on BIM
Jensen et al. Product configuration in construction
CN104281729A (en) BIM (building information model) method for digital processing and manufacturing of steel structure buildings
CN109918860B (en) Intelligent design method for steel structure node
Wei et al. Automatic generation of assembly sequence for the planning of outfitting processes in shipbuilding
Firoz et al. Modelling concept of sustainable steel building by Tekla Software
Issa et al. Benefits of 3D and 4D models for facility managers and AEC service providers
US20100274374A1 (en) System and process for the detailed design and production of reinforcement for buildings
Sergei et al. An interactive construction project for method of statement based on BIM technologies for high-speed modular building
Ko et al. Making formwork design lean
JP5806013B2 (en) Design system
JP3756416B2 (en) Simple quantity setting method of structure, simple quantity setting device, and storage medium used therefor
JP3756417B2 (en) Structure production management equipment
Kontoudaki et al. HBIM library development for a doric temple column
Sacks Evaluation of economic impact of three-dimensional modeling in precast concrete engineering
JPH09166957A (en) Device for constructing three-dimensional model for design and construction of bridge
JP2005018673A (en) Method for supporting formation of process chart
Spitler et al. Constructible BIM Elements–A Root Cause Analysis of Work Plan Failures
JP3756415B2 (en) Structure production management method, production management apparatus, and storage medium used therefor
Popovas et al. Technique for computer aided evaluation of economic indicators of a construction project
Vasanthakumar et al. A Performance-Based Framework to Determine Built Form Guidelines
Horman et al. A lean approach to construction: an historical case study
JP2613016B2 (en) Construction method of 3D model for bridge design and fabrication

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050912

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050920

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20051121

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051213

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051221

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090106

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090106

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100106

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110106

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110106

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120106

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees