JP3744333B2 JP2000298972A JP2000298972A JP3744333B2 JP 3744333 B2 JP3744333 B2 JP 3744333B2 JP 2000298972 A JP2000298972 A JP 2000298972A JP 2000298972 A JP2000298972 A JP 2000298972A JP 3744333 B2 JP3744333 B2 JP 3744333B2
Authority
JP
Japan
Prior art keywords
time
equal
unit
vibration
seismic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000298972A
Other languages
Japanese (ja)
Other versions
JP2002107222A (en
Inventor
朋宏 片岡
尚子 川端
賢二 篠原
康司 下元
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Omron Corp
Original Assignee
Omron Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Omron Corp filed Critical Omron Corp
Priority to JP2000298972A priority Critical patent/JP3744333B2/en
Publication of JP2002107222A publication Critical patent/JP2002107222A/en
Application granted granted Critical
Publication of JP3744333B2 publication Critical patent/JP3744333B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Measurement Of Mechanical Vibrations Or Ultrasonic Waves (AREA)
  • Geophysics And Detection Of Objects (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は感震装置、特にガスメータに採用される感震器により地震を的確に検出できる感震装置に関するものである。
【0002】
【従来の技術】
従来、感震装置として、感震器からの信号のオン時間及びオフ時間の変動状態を監視し、その変動量の平均値が、規定値以上であれば地震による振動であり、規定値未満であれば衝撃による振動であると判別するものが公知である(特許第2699403号公報参照)。
【0003】
【発明が解決しようとする課題】
しかしながら、前記感震装置では誤動作が多い。すなわち、感震器は内部の硬球が振動してスイッチをオン・オフさせる構造となっている。このため、衝撃による振動の初期・中期・末期で硬球の振動状態が相違し、初期及び末期の出力が不規則となる。したがって、このような不規則な出力をも含めて平均値を算出すると、衝撃による振動であるにも拘わらず、地震であると誤判別され易くなる。
【0004】
また、前記感震装置ではアルゴリズムが複雑である。すなわち、感震器からの信号のオン時間及びオフ時間の変動量の平均値を算出するためのマイクロコンピュータの処理は複雑である。このため、高性能で高価なマイクロコンピュータが必要となる。特に、振動の初期及び末期の不規則な出力による悪影響を排除しようとすれば、益々処理が複雑となり、より一層高価なマイクロコンピュータが必要となる。
【0005】
さらに、感震器は並設した配管に取り付けられるガスメータ内に設置するのが一般的であり、配管の固定部からガスメータまでの距離が長い(例えば150cm以上である)と、ガスメータに衝撃力が作用した場合、感震器からの出力信号の周期が長くなる。このため、オン・オフ信号の出力状態が安定せず、振動が地震によるものであると誤判別されることがある。特に、衝撃力が作用する方向によっては、硬球の動作状態が安定しないことがあり、誤判別され易い。
【0006】
そこで、本発明は、検出された振動が地震によるものであるか否かを的確、簡単かつ安価に判別することのできる感震装置を提供することを課題とする。
【0007】
【課題を解決するための手段】
本発明は、前記課題を解決するための手段として、
振動によりオン・オフ信号を出力する感震器と、
該感震器から出力されるオン・オフ信号に基づいて地震による振動であるか否かを判別する判別手段とを備えた感震装置において、
前記判別手段は、
前記感震器から出力されるオン・オフ信号の周期を順次計時する計時部と、
該計時部で順次計時される周期が、設定時間以上となる回数を計数する計数部と、
前記感震器からの出力のうち、第2の設定オフ時間以上のオフ時間をそれぞれ間に持つ第2の設定オン時間以上のオン時間であるオン信号の回数を計数する第2の計数部と、
で構成し、
前記計数部での計数値が設定回数未満であると共に、前記第2の計数部での計数値が第2の設定回数以上である場合にのみ地震による振動であると判別する判別部とを備えた構成としたものである。
【0008】
この構成により、衝撃が原因の不規則な周期でオン・オフ信号が出力される場合であっても、周期が設定時間以上となる回数を計数することにより、地震による不規則な周期のオン・オフ信号とは区別して検出することができる。したがって、振動が地震によるものか衝撃によるものかを的確に判別することが可能となる。
【0009】
前記判別手段は、さらに、前記感震器からのオン信号の入力により判別処理を開始し、オフ信号の入力が所定時間以上となることにより判別処理を停止する判別時期決定部を備えてもよい。また、判別処理は、感震器からのオン信号の入力による判別処理の開始から一定時間だけ行うようにしてもよい。
【0011】
また、前記判別手段は、さらに、前記計時部で順次計時される周期が、第3の設定時間以上となる回数を計数する第3の計数部を備え、前記判別部は、前記計数部での計数値が設定回数未満であると共に、前記第3の計数部での計数値が第3の設定回数以上の場合にのみ地震による振動であると判別してもよい。
【0012】
このように、前記計数部での計数値だけでなく、第2又は第3の計数部での計数値をも考慮したので、地震による振動であるのか否かを、より一層正確に判別することが可能となる。
【0013】
前記感震器は、振動レベルの違いに応じて動作する2種類以上で構成すると、地震の強度の違いをも検出することが可能となる点で好ましい。
【0014】
【発明の実施の形態】
以下、本発明に係る実施形態を添付図面に従って説明する。
図1は、本実施形態に係る感震装置のブロック図である。この感震装置は、ガスメータ1内に設けられる2種類の感震器2a,2bと、各感震器2a,2bから出力されるオン・オフ信号に基づいて、検出された振動が地震によるものであるか否かを判別する判別ユニット3とで構成されている。
【0015】
感震器2a,2bは共に、振動によりケーシング内に収容した硬球が移動し、その上方に設けた蓋部を介してスイッチがオン・オフする従来周知の構造である。一方の感震器2aは、ガス漏れ等の危険度がかなり高い大型の地震による振動に基づく加速度が硬球に作用することによりオン・オフ信号を出力する。残る感震器2bは、前記感震器2aよりも小さな加速度が硬球に作用することによりオン・オフ信号を出力する。
【0016】
判別ユニット3は、計時部4、第1計数部5、第2計数部6、判別時期決定部7、及び判別部8を備える。ここでは、判別ユニット3には安価なカスタムICを使用している(マイクロコンピュータを使用することも可)。
【0017】
前記計時部4は、前記感震器2a,2bから出力されるオン・オフ信号の各周期の時間を計時する。すなわち、オン信号の立ち上りから次のオン信号の立ち上りまでの経過時間を測定する。
【0018】
前記第1計数部5は、計時部4で計時される周期が第1設定時間T1以上となる回数N1を計数する。
【0019】
前記第2計数部6は、感震器2a,2bからの信号のオフ時間TOFFが第2設定オフ時間T2OFF以上となるオフ信号をそれぞれ間に持つオン信号のオン時間TONが第2設定オン時間T2ON以上となる回数N2を計数する。
【0020】
前記判別時期決定部7は、判別処理の開始及び停止時期を決定する。すなわち、判別処理の開始時期を感震器2a,2bからのオン信号の入力があったか否かにより決定し、停止時期をオフ信号の入力が所定時間経過したか否かにより決定する。
【0021】
前記判別部8は、以下に詳述するように、第1計数部5で計数される第1設定時間T1以上となる周期tの回数N1が第1設定回数K1以上であると共に、第2計数部6で計数される回数N2が第2設定回数K2以上である場合にのみ地震による振動であると判別し、又、各感震器2a,2bからの出力に基づいて地震の強度を判別する。
【0022】
なお、第1設定時間T1、第2設定オン時間T2ON、第2設定オフ時間T2OF F、第1設定回数K1、及び第2設定回数K2は、予め実験等により地震と衝撃とを適切に判別可能な値を求めておく。
【0023】
次に、前記構成からなる感震装置の動作(振動判別処理)について、図4のフローチャートに従って説明する。
感震器2a,2bからオン信号の入力があれば(ステップS1)、計時部4により、感震器2a又は2bから出力されるオン・オフ信号の周期t、及び、オン信号又はオフ信号の時間(オン時間TON又はオフ時間TOFF)を計時する(ステップS2)。
【0024】
そして、計数部でオン・オフ信号の周期tが設定時間T1以上であるか否かを判断し(ステップS3)、第1設定時間T1以上となる場合にのみ、その回数N1を計数する(ステップS4)。
【0025】
続いて、第2計数部6により、感震器2a又は2bからの出力のうち、第2設定オフ時間T2OFF以上となるオフ信号(オフ時間TOFF)をそれぞれ間に持つオン信号(オン時間TON)が第2設定オン時間T2ON以上であるか否かを判断する(ステップS5)。そして、そのようなオン信号の時間(オフ時間TON)が第2設定オン時間T2ON以上である回数N2を計数する(ステップS6)。
【0026】
前記ステップS1〜S6までの処理は、感震器2a又は2bから出力されるオフ信号が所定時間経過して時間切れとなるまで、すなわち振動があるレベル以下に低下するまで繰り返す(ステップS7)。
【0027】
次いで、周期tが設定時間T1以上となる回数N1が第1設定回数K1以上であるか否かを判断する(ステップS8)。回数N1が第1設定回数K1以上であれば、衝撃による振動であると判断する(ステップS11)。一方、回数N1が第1設定回数K1未満であれば、前記ステップS6で計数した回数N2が第2設定回数K2以上であるか否かを判断する(ステップS9)。回数N2が第2設定回数K2以上であれば、地震であると判断する(ステップS10)。しかし、回数N2が第2設定回数K2未満であれば、たとえ回数N1が第1設定回数K1未満であったとしても、振動が衝撃によるものであると判断する(ステップS11)。
【0028】
このように、前記実施形態に係る振動判別処理によれば、第1設定時間T1以上となる周期tの回数N1が第1設定回数K1以上であるか否か、オン時間TONが第2設定オン時間T2ONを超えている回数N2が第2設定回数K2以上であるか否かの判断を行うだけでよいので、アルゴリズムが簡略化され、判別ユニット3にそれ程性能を要求されることもなく、安価なカスタムICを使用することが可能となる。また、衝撃による振動において感震器2a,2bの鋼球の慣性力や鋼球とケーシング等との摩擦力が原因で、オン時間TONが長くなった場合に、たとえオン時間TONが第2設定オン時間T2ON以上となったり、オフ時間TOFFが第2設定オフ時間T2OFF以上となったとしても、回数N1が第1設定回数K1未満となるので、誤判別を防止することができる。
【0029】
その後、各感震器2a,2bからの出力毎に、地震によるものであるのか、衝撃によるものであるのかが判断されれば、次表に従って最終的な判断を行う(ステップS12)。
【0030】
【表1】

Figure 0003744333
【0031】
これによれば、より小さな加速度で動作する感震器2aにより、地震に基づくものであるか否かを判別し、大きな加速度で動作する感震器2bにより、地震の強度を判別するようにしているので、感震器を1つだけ設ける場合に比べてより一層正確な判別が可能となる。また、さらに感度の異なる感震器を設けることで、震度階を検出させることも可能である。
【0032】
なお、前記実施形態では、第1計数部5及び第2計数部6での計数結果によって地震によるものか否かの判別を行うようにしたが、さらに第1計時部5で順次計時される周期の変動時間が第3設定時間以下となる連続回数が、第3設定回数以上となるか否かにより、振動が地震によるものか否かの判断を行うようにしてもよい。すなわち、ある1周期と、次の1周期との時間差の絶対値(変動時間)を算出し、この絶対値が連続して第3設定時間以下となる連続回数を計数する。衝撃による振動に基づいて出力されるオン・オフ信号であれば、振動初期には不規則であるが、振動中期に安定し、変動時間が連続的に第3設定時間以下となる。そこで、変動時間が第3設定時間以下となれば、その連続回数を計数し、第3設定時間を超えればクリアする。このようにして、連続回数が第3設定回数以上であるか否かを判断し、連続回数が第3設定回数以上であれば、振動が衝撃によるものであると判断する。
【0033】
これによれば、初期・中期・末期で硬球の振動状態が相違する衝撃による振動が発生し、初期及び末期の出力が不規則となる場合であっても、振動が衝撃により発生したことを適切に判別することができる。
【0034】
【発明の効果】
以上の説明から明らかなように、本発明によれば、オン・オフ信号の周期が設定時間以上となる回数が設定回数以上であれば、地震による振動であると判別するようにしたので、複雑な処理を必要とすることなく、的確に判別することができ、装置自体も省電力で安価な構成とすることが可能となる。
【図面の簡単な説明】
【図1】 本実施形態に係る感震装置のブロック図である。
【図2】 図1に示す感震装置の動作を示すフローチャートである。
【符号の説明】
1…ガスメータ 2…感震器
3…判別ユニット 4…計時部
5…第1計数部 6…第2計数部
7…判別時期決定部 8…判別部[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a seismic sensing device, and more particularly to a seismic sensing device capable of accurately detecting an earthquake with a seismic device employed in a gas meter.
[0002]
[Prior art]
Conventionally, as a seismic device, the fluctuation state of the on-time and off-time of the signal from the seismoscope is monitored, and if the average value of the fluctuation amount is greater than or equal to the specified value, the vibration is caused by an earthquake, If there is any, it is known that the vibration is caused by an impact (see Japanese Patent No. 2699403).
[0003]
[Problems to be solved by the invention]
However, there are many malfunctions in the seismic device. That is, the seismic sensor has a structure in which the internal hard ball vibrates to turn the switch on and off. For this reason, the vibration state of the hard sphere is different in the initial, middle, and final stages of vibration due to impact, and the initial and final outputs are irregular. Therefore, if the average value including such irregular output is calculated, it is easy to misclassify that it is an earthquake despite the vibration due to the impact.
[0004]
The seismic device has a complicated algorithm. In other words, the processing of the microcomputer for calculating the average value of the on-time and off-time fluctuation amounts of the signal from the seismoscope is complicated. For this reason, a high-performance and expensive microcomputer is required. In particular, if it is attempted to eliminate the adverse effects caused by the irregular output at the initial and final stages of the vibration, the processing becomes more complicated and a more expensive microcomputer is required.
[0005]
Furthermore, the seismic device is generally installed in a gas meter attached to a parallel pipe. If the distance from the fixed part of the pipe to the gas meter is long (for example, 150 cm or more), the gas meter has an impact force. When it acts, the period of the output signal from the seismoscope becomes longer. For this reason, the output state of the on / off signal is not stable, and it may be erroneously determined that the vibration is caused by an earthquake. In particular, depending on the direction in which the impact force is applied, the operating state of the hard sphere may not be stable, and is easily misidentified.
[0006]
Therefore, an object of the present invention is to provide a seismic sensing device that can accurately, easily and inexpensively determine whether or not the detected vibration is caused by an earthquake.
[0007]
[Means for Solving the Problems]
As a means for solving the above problems, the present invention provides:
A seismometer that outputs an on / off signal by vibration,
In a seismic sensing device comprising a discriminating means for discriminating whether or not the vibration is caused by an earthquake based on an on / off signal output from the seismic sensor,
The discrimination means includes
A timing unit that sequentially measures the period of the on / off signal output from the seismic sensor;
A counting unit that counts the number of times that the time sequentially counted by the time measuring unit is equal to or greater than a set time;
A second counter that counts the number of ON signals that are ON times that are equal to or greater than a second set ON time, with an OFF time that is equal to or greater than a second set OFF time among outputs from the seismic sensor; ,
Consisting of
A discriminating unit that discriminates that the vibration is caused by an earthquake only when the count value in the counting unit is less than the set number of times and the count value in the second counting unit is equal to or more than the second set number of times. This is a configuration.
[0008]
With this configuration, even when an on / off signal is output at an irregular cycle caused by an impact, counting the number of times that the cycle exceeds the set time allows the on / off of the irregular cycle due to the earthquake. It can be detected separately from the off signal. Therefore, it is possible to accurately determine whether the vibration is caused by an earthquake or an impact.
[0009]
The discriminating means may further include a discriminating time determination unit that starts discriminating processing when an ON signal is input from the seismic sensor, and stops the discriminating processing when an OFF signal is input for a predetermined time or more. . Further, the discrimination process may be performed for a certain time from the start of the discrimination process by inputting an ON signal from the seismoscope.
[0011]
The discriminating unit further includes a third counting unit that counts the number of times that the period sequentially counted by the timing unit is equal to or longer than a third set time, and the discriminating unit It may be determined that the vibration is caused by an earthquake only when the count value is less than the set number of times and the count value at the third counter is equal to or greater than the third set number of times.
[0012]
As described above, since not only the count value in the counting unit but also the count value in the second or third counting unit is considered, it is possible to more accurately determine whether the vibration is caused by an earthquake. Is possible.
[0013]
It is preferable that the seismoscope is composed of two or more types that operate according to the difference in vibration level because it is possible to detect the difference in the intensity of the earthquake.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Embodiments according to the present invention will be described below with reference to the accompanying drawings.
FIG. 1 is a block diagram of the seismic device according to the present embodiment. This seismic device is based on two types of seismic devices 2a and 2b provided in the gas meter 1 and on / off signals output from the respective seismic devices 2a and 2b. It is comprised with the discrimination | determination unit 3 which discriminate | determines whether it is.
[0015]
Both the seismographs 2a and 2b have a conventionally well-known structure in which a hard ball accommodated in a casing is moved by vibration, and a switch is turned on and off via a lid provided above the same. On the other hand, the seismic sensor 2a outputs an on / off signal when acceleration based on vibration caused by a large earthquake with a considerably high risk of gas leakage or the like acts on the hard ball. The remaining seismic device 2b outputs an on / off signal when an acceleration smaller than that of the seismic device 2a acts on the hard ball.
[0016]
The discrimination unit 3 includes a timer unit 4, a first counting unit 5, a second counting unit 6, a discrimination time determination unit 7, and a discrimination unit 8. Here, an inexpensive custom IC is used for the discrimination unit 3 (a microcomputer can also be used).
[0017]
The timer 4 measures the time of each cycle of the on / off signal output from the seismographs 2a and 2b. That is, the elapsed time from the rise of the on signal to the rise of the next on signal is measured.
[0018]
The first counting unit 5 counts the number of times N1 at which the cycle counted by the timing unit 4 is equal to or longer than the first set time T1.
[0019]
The second counting unit 6 has a second ON signal ON time T ON having an OFF signal between which the OFF time T OFF of the signals from the seismographs 2a and 2b is equal to or longer than the second set OFF time T2 OFF . The number of times N2 that is equal to or longer than the set ON time T2 ON is counted.
[0020]
The discrimination time determination unit 7 determines the start and stop times of the discrimination process. That is, the start time of the discrimination process is determined based on whether or not an on signal is input from the seismic devices 2a and 2b, and the stop time is determined based on whether or not a predetermined time has elapsed after the input of the off signal.
[0021]
As will be described in detail below, the discriminating unit 8 determines that the number N1 of the period t that is equal to or greater than the first set time T1 counted by the first counter 5 is equal to or greater than the first set number K1 and the second count. Only when the number of times N2 counted by the unit 6 is equal to or greater than the second set number of times K2, it is determined that the vibration is caused by an earthquake, and the intensity of the earthquake is determined based on the output from each of the seismic devices 2a and 2b. .
[0022]
The first set time T1, the second set on time T2 ON , the second set off time T2 OF F , the first set number of times K1, and the second set number of times K2 are appropriately determined based on an earthquake and an impact in advance through experiments or the like. Find a distinguishable value.
[0023]
Next, the operation (vibration discrimination processing) of the seismic device having the above-described configuration will be described with reference to the flowchart of FIG.
If there is an ON signal input from the seismographs 2a and 2b (step S1), the timing unit 4 outputs the cycle t of the ON / OFF signal output from the seismograph 2a or 2b and the ON signal or OFF signal. Time (ON time T ON or OFF time T OFF ) is measured (step S2).
[0024]
Then, the counting unit determines whether or not the cycle t of the on / off signal is equal to or longer than the set time T1 (step S3), and counts the number N1 only when it is equal to or longer than the first set time T1 (step S3). S4).
[0025]
Then, the second counting section 6, of the output from the seismic sensor 2a or 2b, the ON signal (on-time with off signal as a second set OFF time T2 OFF or more (OFF time T OFF) during each It is determined whether or not (T ON ) is equal to or longer than the second set on time T2 ON (step S5). Then, the number N2 of times that the ON signal time (OFF time T ON ) is equal to or longer than the second set ON time T2 ON is counted (step S6).
[0026]
The processes from Steps S1 to S6 are repeated until the OFF signal output from the seismic device 2a or 2b expires after a predetermined time, that is, until the vibration drops below a certain level (Step S7).
[0027]
Next, it is determined whether or not the number of times N1 at which the period t is equal to or greater than the set time T1 is equal to or greater than the first set number of times K1 (step S8). If the number of times N1 is equal to or greater than the first set number of times K1, it is determined that the vibration is caused by an impact (step S11). On the other hand, if the number N1 is less than the first set number K1, it is determined whether or not the number N2 counted in step S6 is equal to or greater than the second set number K2 (step S9). If the number of times N2 is greater than or equal to the second set number of times K2, it is determined that the event is an earthquake (step S10). However, if the number of times N2 is less than the second set number of times K2, it is determined that the vibration is due to an impact even if the number of times N1 is less than the first set number of times K1 (step S11).
[0028]
Thus, according to the vibration determination processing according to the embodiment, whether the number N1 of the period t of the first set time T1 or more is first set number K1 above, the ON time T ON second set Since it is only necessary to determine whether or not the number of times N2 exceeding the ON time T2 ON is equal to or greater than the second set number of times K2, the algorithm is simplified, and the performance of the discrimination unit 3 is not so required. It is possible to use an inexpensive custom IC. In addition, when the on-time T ON becomes longer due to the inertial force of the steel balls of the seismometers 2a and 2b or the frictional force between the steel balls and the casing in vibration due to impact, the on-time T ON is Even if the set ON time T2 is greater than or equal to ON or the OFF time T OFF is greater than or equal to the second set OFF time T2 OFF , the number of times N1 is less than the first set number of times K1, thus preventing erroneous determination. it can.
[0029]
Thereafter, if it is determined for each output from each of the seismic devices 2a and 2b whether it is due to an earthquake or an impact, a final determination is made according to the following table (step S12).
[0030]
[Table 1]
Figure 0003744333
[0031]
According to this, it is determined whether or not it is based on an earthquake by a seismic device 2a that operates at a smaller acceleration, and the intensity of the earthquake is determined by a seismic device 2b that operates at a higher acceleration. As a result, it is possible to make a more accurate discrimination than when only one seismoscope is provided. It is also possible to detect the seismic intensity scale by providing a seismic device with different sensitivity.
[0032]
In the above-described embodiment, it is determined whether or not it is caused by an earthquake based on the counting results of the first counting unit 5 and the second counting unit 6, but the period sequentially counted by the first timing unit 5 is further determined. It may be determined whether or not the vibration is caused by an earthquake depending on whether or not the continuous number of times that the fluctuation time is equal to or less than the third set time is equal to or greater than the third set number. That is, the absolute value (fluctuation time) of the time difference between one certain cycle and the next one cycle is calculated, and the number of consecutive times that this absolute value is continuously equal to or less than the third set time is counted. If it is an on / off signal that is output based on vibration due to an impact, it is irregular in the initial stage of vibration, but is stable in the middle stage of vibration, and the fluctuation time is continuously equal to or shorter than the third set time. Therefore, if the fluctuation time is equal to or shorter than the third set time, the number of consecutive times is counted, and if the fluctuation time exceeds the third set time, the number is cleared. In this way, it is determined whether or not the number of consecutive times is equal to or greater than the third set number of times. If the number of consecutive times is equal to or greater than the third set number of times, it is determined that the vibration is due to an impact.
[0033]
According to this, even if there is a vibration due to an impact in which the vibration state of the hard sphere is different in the initial, middle and final stages, even if the output at the initial and final stages is irregular, it is appropriate that the vibration is generated by the impact. Can be determined.
[0034]
【The invention's effect】
As is clear from the above description, according to the present invention, if the number of times that the cycle of the on / off signal is equal to or greater than the set time is equal to or greater than the set number, it is determined that the vibration is caused by an earthquake. Therefore, it is possible to make an accurate determination without requiring any processing, and the apparatus itself can be configured to save power and be inexpensive.
[Brief description of the drawings]
FIG. 1 is a block diagram of a seismic sensing device according to the present embodiment.
FIG. 2 is a flowchart showing the operation of the seismic sensing device shown in FIG.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Gas meter 2 ... Seismic device 3 ... Discrimination unit 4 ... Time measuring part 5 ... 1st counting part 6 ... 2nd counting part 7 ... Discrimination time determination part 8 ... Discrimination part

Claims (4)

振動によりオン・オフ信号を出力する感震器と、
該感震器から出力されるオン・オフ信号に基づいて地震による振動であるか否かを判別する判別手段とを備えた感震装置において、
前記判別手段は、
前記感震器から出力されるオン・オフ信号の周期を順次計時する計時部と、
該計時部で順次計時される周期が、設定時間以上となる回数を計数する計数部と、
前記感震器からの出力のうち、第2の設定オフ時間以上のオフ時間をそれぞれ間に持つ第2の設定オン時間以上のオン時間であるオン信号の回数を計数する第2の計数部と、
で構成し、
前記計数部での計数値が設定回数未満であると共に、前記第2の計数部での計数値が第2の設定回数以上である場合にのみ地震による振動であると判別する判別部とを備えたことを特徴とする感震装置。
A seismometer that outputs an on / off signal by vibration,
In a seismic sensing device comprising a discriminating means for discriminating whether or not the vibration is caused by an earthquake based on an on / off signal output from the seismic sensor,
The discrimination means includes
A timing unit that sequentially measures the period of the on / off signal output from the seismic sensor;
A counting unit that counts the number of times that the time sequentially counted by the time measuring unit is equal to or greater than a set time;
A second counter that counts the number of ON signals that are ON times that are equal to or greater than a second set ON time, with an OFF time that is equal to or greater than a second set OFF time among outputs from the seismic sensor; ,
Consisting of
A discriminating unit that discriminates that the vibration is caused by an earthquake only when the count value in the counting unit is less than the set number of times and the count value in the second counting unit is equal to or more than the second set number of times. A seismic device characterized by that.
前記判別手段は、さらに、前記感震器からのオン信号の入力により判別処理を開始し、オフ信号の入力が所定時間以上となることにより判別処理を停止する判別時期決定部を備えたことを特徴とする請求項1に記載の感震装置。  The discriminating means further comprises a discriminating time determining unit that starts discriminating processing by inputting an ON signal from the seismic sensor and stops the discriminating processing when an OFF signal is input for a predetermined time or more. The seismic device according to claim 1, wherein 前記判別手段は、さらに、前記計時部で順次計時される周期が、第3の設定時間以上となる回数を計数する第3の計数部を備え、前記判別部は、前記計数部での計数値が設定回数未満であると共に、前記第3の計数部での計数値が第3の設定回数以上の場合にのみ地震による振動であると判別することを特徴とする請求項1又は2に記載の感震装置。  The discriminating unit further includes a third counting unit that counts the number of times that the period sequentially counted by the clocking unit is equal to or longer than a third set time, and the discriminating unit includes a count value in the counting unit. 3 is less than the set number of times, and it is determined that the vibration is caused by an earthquake only when the count value in the third counter is equal to or greater than the third set number of times. Seismic device. 前記感震器は、振動レベルの違いに応じて動作する2種類以上で構成したことを特徴とする請求項1ないし3のいずれか1項に記載の感震装置。  The seismic device according to any one of claims 1 to 3, wherein the seismic device includes two or more types that operate according to a difference in vibration level.
JP2000298972A 2000-09-29 2000-09-29 Seismic device Expired - Fee Related JP3744333B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000298972A JP3744333B2 (en) 2000-09-29 2000-09-29 Seismic device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000298972A JP3744333B2 (en) 2000-09-29 2000-09-29 Seismic device

Publications (2)

Publication Number Publication Date
JP2002107222A JP2002107222A (en) 2002-04-10
JP3744333B2 true JP3744333B2 (en) 2006-02-08

Family

ID=18780847

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000298972A Expired - Fee Related JP3744333B2 (en) 2000-09-29 2000-09-29 Seismic device

Country Status (1)

Country Link
JP (1) JP3744333B2 (en)

Also Published As

Publication number Publication date
JP2002107222A (en) 2002-04-10

Similar Documents

Publication Publication Date Title
US5258707A (en) Method of noise rejection in a magnetostrictive position detector including determining a valid time range for propagation of sonic pulses over a reference distance
JP2001143048A (en) Pedometer
JP2004181982A (en) Invasion sensing device
JP3744333B2 (en) Seismic device
JP3744331B2 (en) Seismic device
JP3106965B2 (en) Seismic device
JP4427911B2 (en) Seismograph
JPH11142526A (en) Seismoscope
JP3404666B2 (en) Seismograph
JP3530948B2 (en) Detection signal processing method for rock fall prediction
JPH09280940A (en) Seismographic apparatus
JP2007130140A5 (en)
JP2697911B2 (en) Pedometer
JPH1090427A (en) Accelearation seismograph apparatus
JP2002368597A (en) Nearness sensor
SU1539810A1 (en) Device for determining parameters of article maintanence
JPH0135281B2 (en)
JP2627961B2 (en) Traffic information collection device
JP4208439B2 (en) Gas meter and earthquake judgment method
JPH07294323A (en) Output deciding device for seismoscope
JP3450063B2 (en) Anomaly location system for the subject
JPH08233842A (en) Speed detector and detection of abnormality thereof
JP2508364B2 (en) Waveform discriminator
KR880009323A (en) Coin selector
KR100602199B1 (en) Fault position estimation system and method of using the arrival time-difference of envelope signal

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040819

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050719

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050802

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050928

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051101

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051114

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091202

Year of fee payment: 4

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101202

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees