JP3678831B2 - Steel-concrete composite floor slab bridge and its construction method - Google Patents
Steel-concrete composite floor slab bridge and its construction method Download PDFInfo
- Publication number
- JP3678831B2 JP3678831B2 JP3172696A JP3172696A JP3678831B2 JP 3678831 B2 JP3678831 B2 JP 3678831B2 JP 3172696 A JP3172696 A JP 3172696A JP 3172696 A JP3172696 A JP 3172696A JP 3678831 B2 JP3678831 B2 JP 3678831B2
- Authority
- JP
- Japan
- Prior art keywords
- steel
- sheet pile
- concrete
- steel sheet
- bridge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、道路橋や鉄道橋などに用いられる鋼−コンクリート合成床版橋およびその施工方法に関する。
【0002】
【従来の技術】
都市内等の桁下空間の利用に制限を受ける道路橋や鉄道橋等においては、桁高さをできるだけ小さくする必要があることから、スラブ作用を主構造としての強度部材とする床版橋(スラブ橋)が用いられる。この床版橋には、従来、例えばRCスラブ橋やRCホロースラブ橋、PCスラブ橋等のコンクリート系の構造と、鉄筋やPC鋼材の代わりに鋼板や形鋼を用いた鋼−コンクリート合成床版橋の2種類の技術が用いられている。
【0003】
コンクリート系の床版橋は、例えば図4に示すように、全体がコンクリート1と鉄筋2とで構成されているため、必然的に自重(死荷重)が大きくなることから、桁高さ(床版厚さ)を制限した場合には鉄筋2の配置上の関係からその支間長(スパン)に制限があることや、コンクリート打設時に型枠や支保工が必要となり工事中の桁下空間の占有が一時的に必要となる。
【0004】
これに対し、鋼−コンクリート合成床版橋の場合は、例えば図5に示すように、鋼製底板3に鋼板を、鋼製主桁4にH形鋼あるいはCT形鋼をそれぞれ用い、両側端に側板5を取り付けてコンクリート6を打設する構造であるから、側板5はコンクリート打設時には型枠ならびに支保工となり、コンクリート硬化後は鉄筋に代わる強度部材として利用できるので、現地施工性にすぐれた経済的な構造であり、これまで鋼材部の構成を変えた種々の構造が提案され実用化されている。なお、図中の7は横桁である。
【0005】
しかし、このような従来技術による鋼−コンクリート合成床版橋では、鋼製底板3や鋼製主桁4の鋼材部に鋼板やH形鋼あるいはCT形鋼を組み合わせることにより、鋼材部のみで橋軸方向(主桁)ならびに橋軸直角方向(横桁)に剛性をもたせる必要があることから、工場で溶接等によって集成した構造部材が用いられており、その加工のための工数や現地での接合作業の必要性から、経済的にコンクリート系の床版橋に劣るという欠点がある。
【0006】
【発明が解決しようとする課題】
本発明は、上記のような鋼−コンクリート合成床版橋の従来技術が有するコスト面での課題を解決し、コンクリート系合成床版橋の経済性を兼ね備えた鋼−コンクリート合成床版橋およびその施工方法を提供することを目的とする。
【0007】
【課題を解決するための手段】
本発明は、鋼矢板(11)を底板とし、H形鋼またはCT形鋼を主桁部材(13)として両者を溶接またはボルト接合により一体化した橋軸方向部材(14)を複数順次爪部にて接合した鋼製パネル(21)と、半割りの鋼矢板(15)と側板(16)とを溶接またはボルト接合により一体化した枠体部材(17)とが前記爪部にて接合し、前記主桁部材(13)および側板(16)のウエブにPC鋼材(18)が貫通して装着され、前記底板の上方に場所打ちコンクリート(20)が打設されてなることを特徴とする鋼−コンクリート合成床版橋である。
【0008】
なお、前記鋼矢板(11)に直線形あるいはU形またはZ形の鋼矢板を用いてもよい。
また、本発明は、工場において底板とされる鋼矢板(11)のウエブに所定の剛性を有するH形鋼あるいはCT形鋼の主桁部材(13)を溶接またはボルト接合により一体化して橋軸方向部材(14)を、また半割りの鋼矢板(15)に側板(16)を溶接またはボルト接合によりL字状に一体化して枠体部材(17)をそれぞれ製作する工程と、現地において前記橋軸方向部材(14)を複数順次爪部にて接合して所要の幅員を有する鋼製パネル(21)を形成した後、その両側端に枠体部材(17)を結合する工程と、前記鋼製パネル(21)を橋軸直角方向に拡幅した後、側板(16)と主桁部材(13)のウエブ面にPC鋼材(18)を貫通して装着する工程と、場所打ちコンクリート(20)を打設する工程と、からなることを特徴とする鋼−コンクリート合成床版橋の施工方法である。
【0009】
なお、前記場所打ちコンクリート(20)を打設する工程の前に、前記側板(16)の間にコンクリート製の横桁(19)を挿入しプレキャストする工程を付加してもよい。
【0010】
【発明の実施の形態】
以下に、本発明の好適な実施の形態について、図面を参照して詳しく説明する。
図1は本発明の構成の一例を示す部分斜視図である。この図において、11は両端部に嵌合自在な爪部12を設けた直線形鋼矢板である。13はH形鋼あるいはCT形鋼の主桁部材であり、主桁部材13を直線形鋼矢板11のウエブに溶接またはボルト接合により一体化することにより設計上必要な剛性が発揮する橋軸方向部材14が構成される。15は半割りされた直線形鋼矢板、16は側板であり、側板16を直線形鋼矢板15のウエブに溶接またはボルト接合により一体化することにより枠体部材17が構成される。18はアンボンドのPC鋼材で、主桁部材13と側板16のウエブに所定の間隔で貫通して設けられる。19はプレキャストコンクリート製の横桁で、PC鋼材18を緊張させる効果を有する。20は場所打ちコンクリートである。
【0011】
つぎに、その組み立て工程について、図2を用いて説明する。
▲1▼まず工場において、図2(a) に示すように、直線形鋼矢板11のウエブに設計上必要な剛性を有するH形鋼あるいはCT形鋼の主桁部材13を溶接またはボルト接合により一体化して橋軸方向部材14を製作する。また、直線形鋼矢板15に側板16を溶接またはボルト接合により一体化して枠体部材17を製作する。なお、主桁部材13および側板16のそれぞれのウエブ面にはPC鋼材18を貫通する孔部を所定の間隔で例えば上下に2個開けておく。
▲2▼つぎに、これらの部材を現地に運搬し、現地において図2(b) に示すように、複数の橋軸方向部材14のそれぞれの爪部12を順次接合することにより必要な幅員を有する鋼製パネル21を形成する。
▲3▼図2(c) に示すように、鋼製パネル21の両側端面に枠体部材17の直線形鋼矢板15を接合する。これによって、場所打ちコンクリート打設時の漏れを止めることができる。
▲4▼引き続き、鋼製パネル21を爪部12の接合部の遊びが最大となるように橋軸直角方向に拡幅した後、図2(d) に示すように、側板16と主桁部材13のウエブ面の孔部にPC鋼材18を挿入し、横桁19をプレキャストする。
▲5▼図2(e) に示すように、場所打ちコンクリート20を打設する。
【0012】
なお、上記の拡幅作業は、PC鋼材18の緊張に際し底板である直線形鋼矢板11, 15に緊張力が入らず、場所打ちコンクリート20へのプレストレス導入の効率を上げるためである。これによって、場所打ちコンクリート20の硬化後PC鋼材18を緊張(横締め作業)し、橋軸直角方向の一体化と剛性を確保することができる。なお、上記の組み立て工程において、ステップ▲4▼でのプレキャストコンクリート製の横桁19のプレキャストを省略することも可能である。
【0013】
このような組み立て工程を用いることにより、横桁の製作ならびに現地接合の作業をなくすことができる。また、従来の合成床版橋の技術では底板に鋼板を用いるため、PC鋼材で横締めしても緊張力の大半が鋼材に導入され、場所打ちコンクリートへの緊張力の硬化が薄れるのであるが、これに対し本発明では、底板に用いる直線形鋼矢板の爪接合部に遊びがあるため、底板には緊張力が導入されずPC鋼材の緊張力のほとんどが場所打ちコンクリートに導入されプレストレスの効率が高く保持できるのである。
【0014】
さらに、本発明の合成床版橋の場合は、工場製作された大ブロックを運搬せざるを得ない従来例に対し、必要長さの直線形鋼矢板を運搬すればよいので、運搬コストの節減も可能である。
なお、上記の例では底板部に直線形鋼矢板11を用いるとして説明したが、本発明はこれに限るものではなく、例えばU形鋼矢板やZ形鋼矢板を用いても同様の作用効果を奏することが可能である。すなわち、図3(a) ,(b) は2種類のU形鋼矢板11A,11Bを組み合わせた例を示す斜視図であるが、これによって底板部に波板形状を与えることができるから、コンクリートの打設量を減らし死荷重の低減とコスト低減を図ることができる。なお、橋軸方向部材には、図3(a) に示すように、工場において予めU形鋼矢板11AにH形鋼の主桁部材13Aを溶接またはボルト接合にて取り付けて橋軸方向の剛性を高める橋軸方向部材14Aと、図3(b) に示すように、U形鋼矢板11BとCT形鋼の主桁部材13Bによる底板部機能のみを期待する橋軸方向部材14Bの2通りがあり、設計上の所要剛性に応じてその配置を決めるようにすればよい。
【0015】
【発明の効果】
以上説明したように、本発明によれば、直線形鋼矢板と主桁部材とによる橋軸方向部材と半割りの直線形鋼矢板と側板とによる枠体部材とを工場で予め組み立てた後、建設現場において直線形鋼矢板の爪部同士を接合して一体化し、その後PC鋼材を配置して場所打ちコンクリートを打設し、場所打ちコンクリートの硬化後においてPC鋼材に緊張力を与えて、橋軸直角方向の剛性を確保することが可能となるので、横桁の製作ならびに現地接合の作業をなくすことができ、また運搬コストの節減も可能である。
【図面の簡単な説明】
【図1】本発明の一実施例の構成を示す部分斜視図である。
【図2】 (a) 〜(e) は本発明の合成床版橋の組み立て工程の説明図である。
【図3】 (a) ,(b) は本発明の他の実施例を示す部分斜視図である。
【図4】コンクリート系床版橋の従来例を示す部分斜視図である。
【図5】鋼−コンクリート合成床版橋の従来例を示す斜視図である。
【符号の説明】
11 直線形鋼矢板(鋼矢板)
11A,11B U形鋼矢板
12 爪部
13,13A,13B 主桁部材
14,14A,14B 橋軸方向部材
15 直線形鋼矢板(鋼矢板)
15A U形鋼矢板
16 側板
17,17A 枠体部材
18 PC鋼材
19 横桁
20 場所打ちコンクリート
21 鋼製パネル[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a steel-concrete composite floor slab bridge used for road bridges, railway bridges, and the like, and a construction method thereof.
[0002]
[Prior art]
In road bridges and railway bridges that are restricted by the use of under-girder spaces in cities, etc., it is necessary to make the girder height as small as possible. Slab bridge) is used. Conventionally, for this floor slab bridge, for example, an RC slab bridge, an RC hollows slab bridge, a PC slab bridge, etc., a concrete structure, and a steel-concrete composite floor slab bridge using steel plates or section steel instead of reinforcing bars and PC steel materials are used. Two types of techniques are used.
[0003]
For example, as shown in FIG. 4, the concrete floor slab bridge is composed entirely of concrete 1 and
[0004]
On the other hand, in the case of a steel-concrete composite floor slab bridge, for example, as shown in FIG. 5, a steel plate is used for the steel bottom plate 3, and H-shaped steel or CT-shaped steel is used for the steel main girder 4, respectively. Since the
[0005]
However, in such a conventional steel-concrete composite floor slab bridge, a steel plate, an H-shaped steel, or a CT-shaped steel is combined with a steel material portion of the steel bottom plate 3 or the steel main girder 4 so that only the steel material portion is bridged. Since it is necessary to provide rigidity in the axial direction (main girder) and the direction perpendicular to the bridge axis (horizontal girder), structural members assembled by welding, etc. are used at the factory. Due to the necessity of joining work, there is a disadvantage that it is economically inferior to a concrete type slab bridge.
[0006]
[Problems to be solved by the invention]
The present invention solves the cost problems of the conventional technology of the steel-concrete composite floor slab bridge as described above, and combines the economical efficiency of the concrete-based composite floor slab bridge and its The purpose is to provide a construction method.
[0007]
[Means for Solving the Problems]
The present invention is a steel sheet pile (11) and a bottom plate, a plurality sequentially claw portions bridges axial member which is integrated by welding or bolting the two (14) of the H-shaped steel or CT shaped steel as main girder member (13) joining the contact combined steel panels (21) at the half-split steel sheet pile (15) and the side plate (16) frame members are integrated by welding or bolting and (17) of the claw portion at PC steel material (18) is mounted through the web of the main girder member (13) and side plate (16), and cast-in-place concrete (20) is placed above the bottom plate. It is a steel-concrete composite deck slab .
[0008]
The steel sheet pile (11) may be a linear, U-shaped or Z-shaped steel sheet pile.
Also, the present invention is integrated by welding or bolting the main girder member of H-shaped steel or CT section steel (13) having a predetermined stiffness to the web of the steel sheet pile (11) which is the bottom plate in a factory bridge The process of manufacturing the frame member (17) by integrating the axial member (14), the side plate (16) to the half steel sheet pile (15) by welding or bolt joining , after contact engaged by said bridge axial member (14) at a plurality sequentially claw portions to form a steel panel (21) having the required width, and bonding the frame member (17) at its both side ends The steel panel (21) is widened in the direction perpendicular to the bridge axis, and then the PC plate (18) is inserted through the web surface of the side plate (16) and the main girder member (13), and cast-in-place concrete And (20) a step of placing the steel-concrete composite deck slab bridge.
[0009]
Note that a step of inserting a concrete cross beam (19) between the side plates (16) and precasting may be added before the step of placing the cast-in-place concrete (20).
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.
FIG. 1 is a partial perspective view showing an example of the configuration of the present invention. In this figure,
[0011]
Next, the assembly process will be described with reference to FIG.
(1) First, at the factory, as shown in Fig. 2 (a), the
(2) Next, these members are transported to the site, and as shown in Fig. 2 (b), the necessary width is increased by sequentially joining the
(3) As shown in FIG. 2 (c), the straight
(4) Subsequently, after the
(5) Cast in
[0012]
The above-mentioned widening operation is for increasing the efficiency of introducing prestress into the cast-in-
[0013]
By using such an assembly process, it is possible to eliminate the production of cross beams and the work of on-site joining. In addition, since the conventional composite floor slab bridge technology uses a steel plate for the bottom plate, most of the tension force is introduced into the steel material even if it is laterally tightened with PC steel material, and the hardening of the tension force on cast-in-place concrete is diminished. On the other hand, in the present invention, since there is play in the claw joint portion of the linear steel sheet pile used for the bottom plate, no tension force is introduced into the bottom plate, and most of the tension force of the PC steel material is introduced into the cast-in-place concrete. It is possible to maintain high efficiency.
[0014]
Furthermore, in the case of the composite floor slab bridge of the present invention, it is only necessary to transport a linear steel sheet pile of the required length compared to the conventional example in which a large block manufactured at the factory has to be transported. Is also possible.
In the above example, the linear
[0015]
【The invention's effect】
As described above, according to the present invention, after pre-assembling the frame member by the bridge axial direction member by the linear steel sheet pile and the main girder member and the half linear steel sheet pile and the side plate at the factory, At the construction site, the claws of the straight steel sheet piles are joined and integrated, and then PC steel is placed and cast-in-place concrete is cast. After cast-in-place concrete is hardened, tension is applied to the PC steel, Since the rigidity in the direction perpendicular to the axis can be secured, it is possible to eliminate the production of cross beams and the work of on-site joining, and the transportation cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a partial perspective view showing a configuration of an embodiment of the present invention.
[Fig. 2] (a) to (e) are explanatory views of an assembly process of the composite floor slab bridge of the present invention.
3 (a) and 3 (b) are partial perspective views showing another embodiment of the present invention.
FIG. 4 is a partial perspective view showing a conventional example of a concrete floor slab bridge.
FIG. 5 is a perspective view showing a conventional example of a steel-concrete composite floor slab bridge.
[Explanation of symbols]
11 Straight steel sheet pile (steel sheet pile)
11A, 11B U-shaped steel sheet pile
12 Nail
13, 13A, 13B Main girder member
14, 14A, 14B Bridge axial member
15 Straight steel sheet pile (steel sheet pile)
15A U-shaped sheet pile
16 Side plate
17, 17A Frame member
18 PC steel
19 Horizontal girder
20 Cast-in-place concrete
21 Steel panel
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3172696A JP3678831B2 (en) | 1996-02-20 | 1996-02-20 | Steel-concrete composite floor slab bridge and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP3172696A JP3678831B2 (en) | 1996-02-20 | 1996-02-20 | Steel-concrete composite floor slab bridge and its construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH09221717A JPH09221717A (en) | 1997-08-26 |
JP3678831B2 true JP3678831B2 (en) | 2005-08-03 |
Family
ID=12339054
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP3172696A Expired - Fee Related JP3678831B2 (en) | 1996-02-20 | 1996-02-20 | Steel-concrete composite floor slab bridge and its construction method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3678831B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109537459A (en) * | 2018-11-29 | 2019-03-29 | 中铁四局集团第二工程有限公司 | A kind of cast-in-situ box girder skew web plate mould bases integral construction method |
Families Citing this family (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3708495B2 (en) | 2002-03-26 | 2005-10-19 | 朝日エンヂニヤリング株式会社 | Structure of floor slab bridge |
KR100685725B1 (en) * | 2003-09-05 | 2007-02-23 | 아사히 엔지니어링 가부시키가이샤 | Structure of floor slab bridge |
JP4519023B2 (en) * | 2005-07-21 | 2010-08-04 | Jfeエンジニアリング株式会社 | Steel / concrete composite rigid frame bridge and its construction method |
KR100693872B1 (en) * | 2005-10-17 | 2007-03-12 | 한국건설기술연구원 | Connection structure and construction method for steel and concrete composite deck with a blocked out |
KR100777432B1 (en) * | 2006-04-27 | 2007-11-21 | 주식회사 포스코 | Double Composite Bridge using Steel Composite Structure |
JP2008063803A (en) * | 2006-09-07 | 2008-03-21 | Jfe Engineering Kk | Composite floor slab formed of shape steel with inner rib, composite floor slab bridge, or composite girder bridge |
JP5214902B2 (en) * | 2007-04-06 | 2013-06-19 | 新日鐵住金株式会社 | Steel / concrete composite slabs and composite slab bridges using steel sheet piles |
KR100775936B1 (en) * | 2007-08-02 | 2007-11-15 | 주식회사 지구코퍼레이션 | Lining board and method manufacturing of the same |
JP5200825B2 (en) * | 2008-09-29 | 2013-06-05 | Jfeエンジニアリング株式会社 | Construction method of arch rib of concrete arch bridge |
KR101004617B1 (en) * | 2010-08-12 | 2011-01-03 | 이엔이건설주식회사 | Steel slab pannel and composited bridge construction method using temporary steel reinforcing rib and concrete reinforcing rib |
KR101004618B1 (en) * | 2010-08-12 | 2011-01-03 | 이엔이건설주식회사 | Composite girder bridge construction method using temporary steel lateral rib and permanent concrete lateral rib |
JP5260685B2 (en) * | 2011-01-07 | 2013-08-14 | 日本車輌製造株式会社 | Moving roof equipment for placing composite floor slab concrete |
CN108130852A (en) * | 2016-12-01 | 2018-06-08 | 上海浦东建筑设计研究院有限公司 | A kind of steel reinforced concrete combined board structure of Short/Medium Span Bridge |
CN106869032B (en) * | 2017-02-27 | 2018-12-07 | 中铁十九局集团有限公司 | A kind of bridge bearing platform constructing tie beam method |
CN109577191B (en) * | 2018-11-21 | 2020-11-10 | 许峰 | Prefabricated bridge plate based on corrugated steel plate |
CN109577190B (en) * | 2018-11-21 | 2020-11-10 | 许峰 | Prefabricated bridge plate |
CN109577192B (en) * | 2018-11-21 | 2020-11-10 | 许峰 | Prefabricated bridge plate with built-in steel reinforcement framework |
CN111794074B (en) * | 2020-07-07 | 2022-03-22 | 浙江华东工程咨询有限公司 | Arch bridge concrete beam and beam forming method thereof |
CN113417214A (en) * | 2021-06-29 | 2021-09-21 | 贵州路桥集团有限公司 | Steel-concrete composite beam connecting piece suitable for inclined plane bridge connection |
CN113481826B (en) * | 2021-07-21 | 2022-07-19 | 重庆大学 | Prefabricated assembled corrugated steel web plate combined box girder |
CN115491940B (en) * | 2022-08-22 | 2024-04-30 | 中交第一公路勘察设计研究院有限公司 | Highway steel-concrete combined structure roadbed in frozen soil area and construction method |
-
1996
- 1996-02-20 JP JP3172696A patent/JP3678831B2/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109537459A (en) * | 2018-11-29 | 2019-03-29 | 中铁四局集团第二工程有限公司 | A kind of cast-in-situ box girder skew web plate mould bases integral construction method |
Also Published As
Publication number | Publication date |
---|---|
JPH09221717A (en) | 1997-08-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3678831B2 (en) | Steel-concrete composite floor slab bridge and its construction method | |
JP4414834B2 (en) | Construction method of earthquake-resistant wall | |
JP2011512466A (en) | Prefabricated precast concrete lining and bridge structure | |
JP2007023714A (en) | Composite floor slab using shape steel, composite floor slab bridge or composite girder bridge and its construction method | |
KR20060046151A (en) | Precast composition i-beam with concrete panel and corrugated steel web girder | |
JP2000319816A (en) | Rigid connection structure of upper and lower composite members | |
KR101270733B1 (en) | Prestressed Concrete Box Girder Integrated with Steel Deck and Constructing Method of Bridge using Such Girder | |
JP2008063803A (en) | Composite floor slab formed of shape steel with inner rib, composite floor slab bridge, or composite girder bridge | |
JP2009079401A (en) | Girder structure using corrugated steel plate web | |
CA2023198C (en) | Composite girder construction and method of making same | |
JP2002188120A (en) | Joining structure of corrugated steel plate web beam | |
JP2005256341A (en) | Corrugated steel-plate web u component bridge | |
JP3410368B2 (en) | Connection method of corrugated steel web girder | |
JP2006009449A (en) | Truss panel girder and precast truss panel | |
JPH11148110A (en) | Continuous girder bridge | |
JP2750556B2 (en) | Manufacturing method of prestressed concrete girder | |
JPH11229329A (en) | Constructing method for steel-concrete composite floor board bridge | |
KR100622452B1 (en) | Multi-H section steel girder compounded part | |
JP2006183286A (en) | Connection structure of corrugated steel web for corrugated steel web u-shaped component bridge | |
JP2000064222A (en) | Elevated bridge | |
JP3682521B2 (en) | Structure of two-stage main girder composite floor slab bridge | |
JPH08302619A (en) | Joint structure for composite members | |
JPH11166292A (en) | Steel frame beam and floor execution using the beam | |
JP2002220812A (en) | Bridge girder | |
JP3950747B2 (en) | Bridge girder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20041209 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20041228 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20050224 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20050510 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20050511 |
|
R150 | Certificate of patent (=grant) or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090520 Year of fee payment: 4 |
|
S111 | Request for change of ownership or part of ownership |
Free format text: JAPANESE INTERMEDIATE CODE: R313111 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090520 Year of fee payment: 4 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090520 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100520 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110520 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110520 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120520 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130520 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140520 Year of fee payment: 9 |
|
LAPS | Cancellation because of no payment of annual fees |