JP3533963B2 - Repair and construction method of waste disposal site - Google Patents

Repair and construction method of waste disposal site

Info

Publication number
JP3533963B2
JP3533963B2 JP34995498A JP34995498A JP3533963B2 JP 3533963 B2 JP3533963 B2 JP 3533963B2 JP 34995498 A JP34995498 A JP 34995498A JP 34995498 A JP34995498 A JP 34995498A JP 3533963 B2 JP3533963 B2 JP 3533963B2
Authority
JP
Japan
Prior art keywords
disposal site
waste disposal
tunnels
tunnel
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP34995498A
Other languages
Japanese (ja)
Other versions
JP2000170481A (en
Inventor
秀紀 河村
勝 納多
晶子 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP34995498A priority Critical patent/JP3533963B2/en
Publication of JP2000170481A publication Critical patent/JP2000170481A/en
Application granted granted Critical
Publication of JP3533963B2 publication Critical patent/JP3533963B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/30Landfill technologies aiming to mitigate methane emissions

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Processing Of Solid Wastes (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】この発明は、廃棄物処分場の補修施工法に
関し、特に、既設廃棄物の補修に適した工法に関するも
のである。
The present invention relates to a repair construction method for a waste disposal site.
Related to construction methods suitable for repairing existing waste.
Of.

【0002】[0002]

【従来の技術】原子力発電所,大学や企業の実験室,医
療施設などで使用した作業着や手袋などの低レベル放射
性廃棄物の処分方法として、先端が不透水地盤に到達す
る閉止した断面を有する遮水壁を構築し、この遮水壁の
内部を掘削して、低レベル放射性廃棄物を収納した鉄筋
コンクリート製や鋼板製の密閉容器を埋設する方法があ
る。
2. Description of the Related Art As a method of disposing of low-level radioactive waste such as work clothes and gloves used in nuclear power plants, laboratories of universities and companies, medical facilities, etc., a closed cross section whose tip reaches impermeable ground is used. There is a method of constructing an impermeable wall that has it, excavating the inside of this impermeable wall, and burying a closed container made of reinforced concrete or steel plate that stores low-level radioactive waste.

【0003】ところが、このような廃棄物処分場の構築
工法には、以下に説明する技術的な課題があった。
However, the construction method of such a waste disposal site has the following technical problems.

【0004】[0004]

【発明が解決しようとする課題】すなわち、放射性廃棄
物は、半減期が非常に長く、放射線が半減する期間中
に、鉄筋コンクリート製や鋼板製の密閉容器が劣化し
て、内部の汚染物が拡散する恐れがある。
That is, radioactive waste has a very long half-life, and during the period when the radiation is reduced to half, the sealed container made of reinforced concrete or steel plate deteriorates and the internal contaminants diffuse. There is a risk of

【0005】一方、この種の放射性廃棄物を収納する処
分場は、通常、不透水性の岩盤中に構築されるが、岩盤
構造は、非常に複雑であって、性状を広範囲に亙り正確
に把握することが難しく、亀裂などが存在している可能
性があり、このような亀裂から放射線が場外に漏出する
と、社会,環境に悪影響を与える。
On the other hand, the repository for storing this kind of radioactive waste is usually constructed in an impermeable bedrock, but the bedrock structure is very complicated and the properties are accurate over a wide range. It is difficult to grasp, and there is a possibility that cracks exist, and if radiation leaks out of such a crack, it will have a negative impact on society and the environment.

【0006】このような不都合が発生する恐れがある場
合には、一般的には、埋設されている廃棄物を掘り出し
て、他の処分場に移設することになるが、移設する際に
は、人手を介在させた掘削作業などが行われることにな
り、このような廃棄物処分場が、通常、放射線管理区域
内であるので、立ち入りに制約を受けて、移設作業に長
い時間がかかるという問題がある。
When such inconvenience may occur, the buried waste is generally dug out and transferred to another disposal site. Since excavation work is performed with human intervention, and such a waste disposal site is usually within a radiation control area, there is a restriction on entry and it takes a long time for relocation work. There is.

【0007】なお、このような問題は、低レベルの放射
性廃棄物の処分場だけのものでなく、例えば、重金属な
どの有害汚染物質を投棄した廃棄物処分場においても同
様な不都合が発生する恐れがあり、不都合を解消する際
には、低レベルの放射性廃棄物の処分場と同様な技術的
な課題があった。
Incidentally, such a problem may occur not only in the disposal site of low-level radioactive waste, but also in the waste disposal site in which harmful pollutants such as heavy metals are dumped. However, in solving the inconvenience, there was a technical problem similar to the disposal site of low-level radioactive waste.

【0008】本発明は、このような従来の問題点にかん
がみてなされたものであって、その目的とするところ
は、既設廃棄物処分場において汚染物の漏出ないしは漏
出可能性などの不都合がある場合に、迅速にその不都合
を解決することができる廃棄物処分場の補修施工法を提
供することにある。
The present invention has been made in view of the above-mentioned conventional problems, and the purpose thereof is to cause inconvenience such as leakage or possibility of leakage of contaminants at an existing waste disposal site. In this case, it is to provide a method for repairing and constructing a waste disposal site that can quickly solve the inconvenience.

【0009】上記目的を達成するために、本発明は、既
設廃棄物処分場の側面側の地盤中に、当該廃棄物処分場
の側面を覆うようにして、一対の止水性垂直壁を対向す
るように構築するとともに、前記既設廃棄物処分場の下
面側の地盤中に、当該廃棄物処分場の底面を覆うように
して、両端が前記止水性垂直壁に連結した水平遮水体を
構築する廃棄物処分場の補修施工法であって、前記水平
遮水体は、トンネルボーリングマシン,シールドマシン
などのトンネル掘進機により形成した複数のトンネルを
外周側で相互に連結することにより構築するようにし
た。このように構成した廃棄物処分場の補修施工法によ
れば、既設廃棄物処分場の側面側の地盤中に止水性垂直
壁を構築し、既設廃棄物処分場の下面側の地盤中に、当
該廃棄物処分場の底面を覆うようにして、両端が止水性
垂直壁に連結した水平遮水体を構築するので、既設廃棄
物処分場が止水性垂直壁と水平遮水体とで囲まれ、汚染
物の漏出ないしはその可能性を排除することができる。
この場合、本発明の補修施工法では、水平遮水体は、ト
ンネルボーリングマシン,シールドマシンなどのトンネ
ル掘進機により形成した複数のトンネルを外周側で相互
に連結することにより構築するので、既設廃棄物処分場
に投棄されている低レベル放射線廃棄物や有害物質を含
む廃棄物を別の場所に移設する必要がない。前記トンネ
ル掘進機は、前記既設廃棄物処分場の、前記止水生垂直
壁の構築されていない側の一方の地表または発進立坑か
ら発進させて、他方の地表または到達立坑に到達するよ
うに掘進させることができる。また、前記複数のトンネ
ルの連結は、外周の一部を相互にオーバーラップさせる
こと、あるいは、形成されたトンネル間に止水性連結壁
を構築するのいずれかににより行うことができる。前記
トンネル内には、コンクリートまたはベントナイトを充
填することができる。トンネル内にこのような物質を充
填すると、有害物質の漏出がより一層確実に防止され、
特に、低レベル放射線廃棄物を投棄する処分場において
は、ベントナイトを充填することが望ましい。
In order to achieve the above object, the present invention has a pair of vertical waterproof walls facing each other in the ground on the side of the existing waste disposal site so as to cover the side surface of the waste disposal site. In addition to the above construction, a horizontal water shield with both ends connected to the waterproof vertical wall is constructed in the ground on the lower surface side of the existing waste disposal site so as to cover the bottom surface of the waste disposal site. A method for repairing and disposing of a waste disposal site, wherein the horizontal water shield is constructed by interconnecting a plurality of tunnels formed by a tunnel excavator such as a tunnel boring machine or a shield machine on the outer peripheral side. According to the repair construction method of the waste disposal site constructed in this way
If this is the case, a waterproof vertical wall will be constructed in the ground on the side of the existing waste disposal site, and the bottom of the existing waste disposal site will be covered with the bottom of the existing waste disposal site. Since a horizontal water shield is connected to the water blocking vertical wall, the existing waste disposal site is surrounded by the water blocking vertical wall and the horizontal water shielding body, and the leakage or possibility of contaminants can be eliminated.
In this case, in the repair construction method of the present invention, the horizontal water shield is constructed by interconnecting a plurality of tunnels formed by a tunnel excavator such as a tunnel boring machine or a shield machine on the outer peripheral side. There is no need to relocate low-level radioactive waste and waste containing hazardous substances that have been dumped at the disposal site to another location. The tunnel
Leaving machine is located at the above-mentioned existing waste disposal site.
One of the unbuilt side of the wall, the surface or the starting shaft
From the other to reach the other surface or reach shaft.
Can be dug forward . Further, the plurality of tunnels can be connected to each other by partially overlapping the outer peripheries with each other or by constructing a water blocking connection wall between the formed tunnels. The tunnel may be filled with concrete or bentonite. Filling the tunnel with such substances will prevent leakage of harmful substances more reliably,
In particular, it is desirable to fill bentonite at the disposal site where low-level radioactive waste is dumped.

【0010】以下、本発明の好適な実施の形態につい
て、添付図面に基づいて詳細に説明する。図1から図3
は、本発明にかかる廃棄物処分場の補修施工法の第1実
施例を示している。
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1 to 3
Shows a first embodiment of a method for repairing and constructing a waste disposal site according to the present invention.

【0011】同図に示した廃棄物処分場の補修施工法
は、図1に示すように、既設廃棄物処分場10側面の地
盤12中に、この既設廃棄物処分場10の側面を覆うよ
うにして、一対の止水性垂直壁14が対向するように構
築される。
According to the method for repairing and constructing the waste disposal site shown in FIG. 1, as shown in FIG. 1, the existing waste disposal site 10 is installed in the ground 12 on the side surface of the existing waste disposal site 10. A pair of vertical waterproof walls 14 are constructed so as to face each other so as to cover the side surfaces of the vertical walls 14.

【0012】既設廃棄物処分場10には、既に低レベル
放射性廃棄物や有害金属を含む廃棄物が投棄されてい
る。この止水性垂直壁14は、地中連続壁工法やグラウ
チング壁工法などにより形成される。
At the existing waste disposal site 10, low-level radioactive waste and waste containing harmful metals have already been dumped. This waterproof vertical wall 14 is formed by an underground continuous wall construction method, a grouting wall construction method, or the like.

【0013】止水性垂直壁14が形成されると、既設廃
棄物処分場10の下面側の地盤12中に、既設廃棄物処
分場10の底面を覆うようにして、両端が止水性垂直壁
14に連結された水平遮水体16が構築される。
When the waterproof vertical wall 14 is formed, both ends of the waterproof vertical wall 14 are covered with the bottom surface of the existing waste disposal site 10 so as to cover the bottom of the existing waste disposal site 10. The horizontal water shield 16 connected to is constructed.

【0014】この水平遮水体16は、複数のトンネル1
8を連結したものであって、このトンネル18の形成に
は、地盤12の性状に応じて、トンネルボーリングマシ
ン,シールドマシンなどのトンネル掘進機が選択され、
例えば、硬岩の場合には、トンネルボーリングマシン
が、また、軟岩,硬質土などの場合には、シールドマシ
ンが用いられ、この実施例の場合には、シールドマシン
を用いてトンネル18を形成する場合を例示している。
This horizontal water shield 16 comprises a plurality of tunnels 1.
In order to form the tunnel 18, a tunnel boring machine such as a tunnel boring machine or a shield machine is selected to form the tunnel 18,
For example, in the case of hard rock, a tunnel boring machine is used, and in the case of soft rock, hard soil, etc., a shield machine is used, and in the case of this embodiment, the shield machine is used to form the tunnel 18. The case is illustrated.

【0015】図2には、トンネル18の形成方法の一例
が示されている。図2に示した例では、既設廃棄物処分
場10の一端側(止水性垂直壁14が形成されていない
方向の端部)の地上部分に、反力架台20が設置され
る。
FIG. 2 shows an example of a method of forming the tunnel 18. In the example shown in FIG. 2, the reaction force pedestal 20 is installed on the ground portion on one end side (the end portion in the direction in which the water blocking vertical wall 14 is not formed) of the existing waste disposal site 10.

【0016】反力架台20の設置が終了すると、この架
台20に反力を採って、シールドマシンが発進される。
この時の発進方向は、既設廃棄物処分場10の他端側
(止水性垂直壁14が形成されていない方向の端部)で
あって、下り勾配は、例えば、10%程度に設定する。
When the installation of the reaction force pedestal 20 is completed, a reaction force is applied to the pedestal 20 to start the shield machine.
The starting direction at this time is the other end side of the existing waste disposal site 10 (the end in the direction in which the water blocking vertical wall 14 is not formed), and the downward gradient is set to about 10%, for example.

【0017】シールドマシンにより形成されるトンネル
18の支保工には、コンクリート製ないしは鋼製のセグ
メントが用いられ、セグメントは、通常のシールド工法
と同様に環状に組立てられる。
A concrete or steel segment is used for supporting the tunnel 18 formed by the shield machine, and the segment is assembled into an annular shape in the same manner as in the usual shield construction method.

【0018】トンネル18は、下り勾配の区間が既設廃
棄物処分場10の近傍まで掘削されると、その後は、既
設廃棄物処分場10下方を水平に通過して、上り勾配の
区間となって地表に到達する。
When the downward slope section of the tunnel 18 is excavated to the vicinity of the existing waste disposal site 10, thereafter, the tunnel 18 horizontally passes below the existing waste disposal site 10 to become an upward slope section. Reach the surface of the earth.

【0019】この時の上り勾配は、例えば、45%程度
とする。シールドマシンが地表に到達すると、マシンを
反力架台20側に送り返して、同様の工程を繰り返すこ
とにより、トンネル18が止水性垂直壁14の間に複数
形成され、所定のトンネル18の形成が終了すると反力
架台20は撤去される。
The upward slope at this time is, for example, about 45%. When the shield machine reaches the surface of the earth, the machine is sent back to the reaction force platform 20 side and the same process is repeated, whereby a plurality of tunnels 18 are formed between the water blocking vertical walls 14, and the formation of the predetermined tunnel 18 is completed. Then, the reaction force base 20 is removed.

【0020】このとき、水平遮水体16の両端側に位置
する一対のトンネル18は、止水性垂直壁14と連結す
るように形成される。この連結手段としては、例えば、
シールドマシンで掘進する際に、止水性垂直壁14の一
部を削り採るようにして掘削し、セグメントを設置した
後に、グラウト材をセグメントの背面側に裏込め注入す
ることにより、両者を一体化させる。
At this time, a pair of tunnels 18 located at both ends of the horizontal water shield 16 are formed so as to be connected to the vertical waterproof wall 14. As this connecting means, for example,
When excavating with a shield machine, a part of the waterproof vertical wall 14 is excavated so as to be excavated, the segment is installed, and then the grout material is back-filled and injected into the back side of the segment to integrate them. Let

【0021】一方、水平遮水体16の両端側以外の部分
に位置する複数のトンネル18は、外周側の一部同士が
相互に連結するように形成される。図3にこの連結手段
の一例を示している。
On the other hand, the plurality of tunnels 18 located on the portions other than both ends of the horizontal water shield 16 are formed such that the outer peripheral portions thereof are mutually connected. FIG. 3 shows an example of this connecting means.

【0022】同図に示した例では、トンネル18を所定
の間隔(トンネル18の断面外径よりも小さい長さ)隔
てて形成し、その後に一対のトンネル18間に、別のト
ンネル18をオーバーラップするように形成する。
In the example shown in the figure, the tunnels 18 are formed at a predetermined interval (a length smaller than the cross-sectional outer diameter of the tunnel 18), and then another tunnel 18 is overlaid between the pair of tunnels 18. Form to wrap.

【0023】すなわち、図3に示した例では、まず、
,,のトンネル18が所定の間隔を隔てて形成さ
れ、 その後に、,のトンネル18に跨るようにし
て、のトンネル18が形成され、さらにその後に、
,のトンネル18に跨るようにして、のトンネル
18が形成される。
That is, in the example shown in FIG.
,,, tunnels 18 are formed at a predetermined interval, and thereafter, tunnels 18 are formed so as to straddle the tunnels 18 ,, and further,
, The tunnel 18 is formed so as to extend over the tunnel 18.

【0024】このようにしてトンネル18を形成する
と、隣接するトンネル18同士を、外周の一部が相互に
オーバーラップさせた状態で連結形成することができ
る。このようにして形成されたトンネル18は、その一
部または全部を内部が中空な状態にしておいて、モニタ
リング装置などの設置に利用することもできるし、内部
にコンクリートやモルタルなどの硬化性物質ないしはベ
ントナイトなどの放射線バリア物質を充填することもで
きる。
When the tunnels 18 are formed in this way, the adjacent tunnels 18 can be connected to each other with their outer peripheries partially overlapping each other. The tunnel 18 formed in this way can be used for installing a monitoring device or the like with a part or all of the inside having a hollow interior, or a hardening substance such as concrete or mortar inside. Alternatively, a radiation barrier material such as bentonite may be filled.

【0025】そして、トンネル18を相互に連結した水
平遮水体16の形成が終了すると、既設廃棄物処分場1
0の補修が完了する。
When the formation of the horizontal water shield 16 connecting the tunnels 18 to each other is completed, the existing waste disposal site 1
The repair of 0 is completed.

【0026】さて、以上のように構成した廃棄物処分場
補修施工法によれば、既設廃棄物処分場10の側面側
の地盤12中に止水性垂直壁14を構築し、既設廃棄物
処分場10の下面側の地盤12中に、当該廃棄物処分場
10の底面を覆うようにして、両端が止水性垂直壁14
に連結した水平遮水体16を構築するので、既設廃棄物
処分場10をこの止水性垂直壁14と水平遮水体16と
で囲むことになり、汚染物の漏出ないしはその可能性を
排除することができる。
According to the construction method for repairing the waste disposal site constructed as described above, the waterproof vertical wall 14 is constructed in the ground 12 on the side surface of the existing waste disposal site 10 to dispose the existing waste disposal. The bottom surface of the waste disposal site 10 is covered in the ground 12 on the lower surface side of the site 10, and both ends of the vertical wall 14 are waterproof.
Since the horizontal water shield 16 connected to the above is constructed, the existing waste disposal site 10 will be surrounded by the water blocking vertical wall 14 and the horizontal water shield 16, and the leakage or possibility of contaminants can be eliminated. it can.

【0027】この場合、本発明の補修施工法では、水平
遮水体16は、シールドマシンにより形成した複数のト
ンネル18を外周側で相互に連結することにより構築す
るので、既設廃棄物処分場10に投棄されている低レベ
ル放射線廃棄物や有害物質を含む廃棄物を別の場所に移
設する必要がない。
In this case, in the repair construction method of the present invention, the horizontal water shield 16 is constructed by connecting a plurality of tunnels 18 formed by a shield machine to each other on the outer peripheral side, so that the existing waste disposal site 10 is constructed. There is no need to relocate dumped low-level radioactive waste and waste containing hazardous substances to another location.

【0028】また、水平遮水体16を複数のトンネル1
8を外周側で相互に連結することにより構築すると、放
射線物質の管理区域内や有害物質に汚染された区域内に
おける人間の作業を全く行うことなく処分場を構築する
ことができるので、施工能率も大幅に向上する。
Further, the horizontal water shield 16 is connected to the plurality of tunnels 1.
By constructing 8 by connecting them to each other on the outer circumference side, it is possible to construct a disposal site without any human work in the controlled area of radioactive materials and the area contaminated with harmful substances. Is also greatly improved.

【0029】さらに、本実施例のように、トンネル内1
8に、コンクリートまたはベントナイトを充填すると、
有害物質の漏出がより一層確実に防止され、特に、低レ
ベル放射性廃棄物を投棄する処分場においては、ベント
ナイトを充填することが望ましい。
Further, as in the present embodiment, in the tunnel 1
When 8 is filled with concrete or bentonite,
Leakage of harmful substances can be prevented more reliably, and it is desirable to fill bentonite, especially in the repository where low-level radioactive waste is dumped.

【0030】図4は、本発明にかかる廃棄物処分場の
修施工法の第2実施例を示しており、上記実施例と同一
もしくは相当する部分には、同一符号を付してその説明
を省略するとともに、以下にその特徴点についてのみ説
明する。
FIG. 4 shows the supplement of the waste disposal site according to the present invention.
The 2nd example of the repairing construction method is shown, the same numerals are given to the same or equivalent part as the above-mentioned example, the explanation is omitted, and only the feature is explained below.

【0031】同図に示した実施例は、トンネル18によ
り水平遮水体16を形成する際の変形例であって、この
例では、既設廃棄物処分場10の一端側(止水性垂直壁
14が形成されていない方向の端部)に、発進立坑22
が形成される。
The embodiment shown in the figure is a modification in which the horizontal water shield 16 is formed by the tunnel 18, and in this example, one end side of the existing waste disposal site 10 (the water blocking vertical wall 14 is At the end of the direction not formed), the starting shaft 22
Is formed.

【0032】シールドマシンは、この発進立坑22の下
端側からほぼ水平に発進され、既設廃棄物処分場10の
下方を水平に掘進した後に、上り勾配を経て地上に到達
する。
The shield machine is started substantially horizontally from the lower end side of the starting shaft 22 and horizontally excavates below the existing waste disposal site 10, and then reaches the ground through an upslope.

【0033】このような発進立坑22を形成すると、ト
ンネル18は、シールドマシンだけでなく、トンネルボ
ーリングマシンの掘進によっても形成することができ
る。なお、この場合、発進立坑22の対向位置に到達立
坑を形成することもでき、発進および到達立坑の双方を
形成すると、トンネル18を形成して到達した側の立坑
内でマシンの方向転換を行わせると、1台のマシンを効
率良く稼動させて、水平遮水体16を形成することがで
きる。
When the starting shaft 22 is formed, the tunnel 18 can be formed not only by the shield machine but also by the tunnel boring machine. In this case, a reaching shaft can be formed at a position opposite to the starting shaft 22. When both the starting shaft and the reaching shaft are formed, the direction of the machine is changed in the shaft on the side reached by forming the tunnel 18. Then, one machine can be operated efficiently and the horizontal water shield 16 can be formed.

【0034】このように構成した第2実施例でも第1実
施例と同等の作用効果が得られる。
In the second embodiment thus constructed, the same effect as that of the first embodiment can be obtained.

【0035】図5から図7は、本発明にかかる廃棄物処
分場の補修施工法の第3実施例を示しており、上記実施
例と同一もしくは相当する部分には、同一符号を付して
その説明を省略するとともに、以下にその特徴点につい
てのみ説明する。
5 to 7 show a third embodiment of a method for repairing and constructing a waste disposal site according to the present invention, and the same or corresponding parts as those in the above-mentioned embodiment are designated by the same reference numerals. The description will be omitted, and only the characteristic points will be described below.

【0036】これらの図に示した実施例では、水平遮水
体16aは、上記実施例と同様に、シールドマシンの掘
進により複数のトンネル18aを外周側で相互に連結す
ることにより形成する。
In the embodiments shown in these drawings, the horizontal water shield 16a is formed by connecting a plurality of tunnels 18a to each other on the outer peripheral side by excavation of a shield machine, as in the above embodiments.

【0037】本実施例の場合のトンネル18a間の連結
は、トンネル18aを所定の間隔を隔てて隣接形成し、
形成されたトンネル18a間に止水性連結壁24を形成
することにより行われる。
The connection between the tunnels 18a in the case of the present embodiment is performed by forming the tunnels 18a adjacent to each other with a predetermined gap,
This is performed by forming the water blocking connection wall 24 between the formed tunnels 18a.

【0038】この場合、本実施例では、止水性連結壁2
4は、端部に形成されたトンネル18aと、止水性垂直
壁14との間の連結にも採用されている。連結壁24
は、図6(A)に示すように、各トンネル18aの両端
から外方に突出形成して、端部同士を相互に連結させる
ことで形成することができる。
In this case, in this embodiment, the water blocking connecting wall 2
4 is also used for connection between the tunnel 18a formed at the end and the waterproof vertical wall 14. Connecting wall 24
Can be formed by projecting outward from both ends of each tunnel 18a and connecting the ends to each other, as shown in FIG. 6 (A).

【0039】また、図6(B)に示すように、連結壁2
4で一対のトンネル18aを結合した状態で、トンネル
18aを隣接形成し、トンネル18a間を、セグメント
の背面側に充填するモルタルなどの裏込め材で強固に連
結するようにしてもよい。
Further, as shown in FIG. 6B, the connecting wall 2
Alternatively, the tunnels 18a may be formed adjacent to each other in a state where the pair of tunnels 18a are joined at 4, and the tunnels 18a may be firmly connected to each other by a backfill material such as mortar filling the back side of the segment.

【0040】図7は、止水性連結壁24の形成方法の一
例を示している。同図に示した例では、隣接形成された
トンネル18aのセグメント内から、チェーン,トレン
チャー式の原位置攪拌掘削機26を突出させ、地盤12
を掘削しながらセメントミルクなどの固化材を注入す
る。
FIG. 7 shows an example of a method of forming the water blocking connection wall 24. In the example shown in the figure, the chain and trencher type in-situ stirring excavator 26 is projected from the inside of the adjacent segment of the tunnel 18a, and the ground 12
While excavating, inject solidifying material such as cement milk.

【0041】掘削機26は、周回駆動されるチェーン
と、チェーンに設けられた掘削ビットとを有していて、
チェーンを回転駆動させながら、トンネル18aのセグ
メント内からほぼ水平方向に突出させて、固化材を注入
する。
The excavator 26 has a chain that is orbitally driven and an excavation bit provided on the chain.
While rotating the chain, the solidifying material is injected by causing the chain to protrude substantially horizontally from the inside of the segment of the tunnel 18a.

【0042】注入された固化材が硬化すると、掘削機2
6の掘削幅に応じた厚みの止水性連結壁24が形成され
る。なお、この固化材は、掘削機26の後部側におい
て、別の手段により掘削地盤中に注入するようにしても
よい。
When the injected solidifying material hardens, the excavator 2
The water blocking connection wall 24 having a thickness corresponding to the excavation width 6 is formed. The solidified material may be injected into the excavated ground on the rear side of the excavator 26 by another means.

【0043】掘削機26は、トンネル18aを形成する
ためのシールドマシンやトンネルボーリングマシンの後
部側に設置し、これらのマシンに牽引させて移動させれ
ばよい。
The excavator 26 may be installed on the rear side of a shield machine or tunnel boring machine for forming the tunnel 18a, and may be pulled by these machines and moved.

【0044】以上のように構成した第3実施例によれ
ば、トンネル18を相互にオーバーラップさせて連結す
る場合よりも、トンネル18aの形成位置の精度を低く
しても連結することができる。
According to the third embodiment configured as described above, it is possible to connect the tunnels 18a with a lower precision of the formation position than the case where the tunnels 18 are overlapped with each other and connected.

【0045】[0045]

【発明の効果】以上、実施例で詳細に説明したように、
本発明にかかる廃棄物処分場の補修施工法によれば、既
設廃棄物処分場において汚染物の漏出ないしは漏出可能
性などの不都合がある場合に、迅速にその不都合を解決
することができる。
As described above in detail in the embodiments,
According to the method for repairing and constructing a waste disposal site according to the present invention, when there is a problem such as leakage or possibility of leakage of contaminants in an existing waste disposal site, the problem can be promptly resolved.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本発明にかかる廃棄物処分場の補修施工法
第1実施例を示す構築完了状態の断面説明図である。
FIG. 1 is a cross-sectional explanatory view of a construction completion state showing a first embodiment of a repair construction method for a waste disposal site according to the present invention.

【図2】 図1の廃棄物処分場でトンネルによる水平遮
水体を形成する際の説明図である。
FIG. 2 is an explanatory diagram when forming a horizontal water shield by a tunnel at the waste disposal site of FIG.

【図3】 図2のトンネルを相互に連結させる方法の説
明図である。
FIG. 3 is an explanatory view of a method of connecting the tunnels of FIG. 2 to each other.

【図4】 本発明にかかる廃棄物処分場の補修施工法
第2実施例を示す構築完了状態の断面説明図である。
FIG. 4 is a cross-sectional explanatory diagram showing a second embodiment of a method for repairing and disposing of a waste disposal site according to the present invention in a construction completed state.

【図5】 本発明にかかる廃棄物処分場の補修施工法
第3実施例を示す構築完了状態の断面説明図である。
FIG. 5 is an explanatory cross-sectional view of a construction completed state showing a third embodiment of the method of repairing a waste disposal site according to the present invention.

【図6】 図5の廃棄物処分場でトンネルを連結する際
の説明図である。
FIG. 6 is an explanatory diagram when connecting tunnels at the waste disposal site of FIG.

【図7】 図6のトンネル連結方法の具体例を示す説明
図である。
FIG. 7 is an explanatory diagram showing a specific example of the tunnel connection method of FIG.

フロントページの続き (56)参考文献 特開 平10−118603(JP,A) 特開 平4−62299(JP,A) (58)調査した分野(Int.Cl.7,DB名) E21D 9/06 B09B 1/00 Continuation of the front page (56) Reference JP-A-10-118603 (JP, A) JP-A-4-62299 (JP, A) (58) Fields investigated (Int.Cl. 7 , DB name) E21D 9 / 06 B09B 1/00

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 既設廃棄物処分場の側面側の地盤中に、
当該廃棄物処分場の側面を覆うようにして、一対の止水
性垂直壁を対向するように構築するとともに、 前記既設廃棄物処分場の下面側の地盤中に、当該廃棄物
処分場の底面を覆うようにして、両端が前記止水性垂直
壁に連結した水平遮水体を構築する廃棄物処分場の補修
施工法であって、 前記水平遮水体は、トンネルボーリングマシン,シール
ドマシンなどのトンネル掘進機により形成した複数のト
ンネルを外周側で相互に連結することにより構築するこ
とを特徴とする廃棄物処分場の補修施工法。
1. The ground on the side of the existing waste disposal site,
A pair of water-blocking vertical walls are constructed to face each other so as to cover the side surface of the waste disposal site, and the bottom surface of the waste disposal site is placed in the ground on the lower surface side of the existing waste disposal site. Repair of a waste disposal site that constructs a horizontal water shield with both ends connected to the vertical waterproof wall so as to cover it.
A construction method , wherein the horizontal water shield is constructed by interconnecting a plurality of tunnels formed by a tunnel boring machine such as a tunnel boring machine or a shield machine on the outer peripheral side. Repair construction method.
【請求項2】 前記トンネル掘進機は、前記既設廃棄物
処分場の、前記止水生垂直壁の構築されていない側の一
方の地表または発進立坑から発進させて、他方の地表ま
たは到達立坑に到達するように掘進させることを特徴と
する請求項1記載の廃棄物処分場の補修施工法。
2. The tunnel excavator is used for the existing waste.
One of the unbuilt sides of the static vertical wall of the landfill
Start from the surface of the other side or the starting shaft and move to the other surface.
Or digging to reach the reaching shaft
The method for repairing and constructing a waste disposal site according to claim 1.
【請求項3】 前記複数のトンネルの連結が、外周の一
部を相互にオーバーラップさせることにより行われるこ
とを特徴とする請求項1記載の廃棄物処分場の補修施工
法。
3. The connection of the plurality of tunnels is one of the outer circumferences.
This is done by overlapping the parts with each other.
Repair construction of the waste disposal site according to claim 1, characterized in that
Law.
【請求項4】 前記複数のトンネルの連結が、形成され4. A connection of the plurality of tunnels is formed.
たトンネル間に止水性連結壁を構築することにより行わBy constructing a water-blocking connection wall between the tunnels
れることを特徴とする請求項1記載の廃棄物処分場の補The supplement of the waste disposal site according to claim 1, characterized in that
修施工法。Repair construction method.
【請求項5】 前記トンネル内にコンクリートまたはベ5. The concrete or floor in the tunnel.
ントナイトを充填することを特徴とする請求項1から3Filling with tontonite, characterized in that
のいずれか1項記載の廃棄物処分場の補修施工法。The method for repairing and constructing a waste disposal site according to any one of 1.
JP34995498A 1998-12-09 1998-12-09 Repair and construction method of waste disposal site Expired - Fee Related JP3533963B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34995498A JP3533963B2 (en) 1998-12-09 1998-12-09 Repair and construction method of waste disposal site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34995498A JP3533963B2 (en) 1998-12-09 1998-12-09 Repair and construction method of waste disposal site

Publications (2)

Publication Number Publication Date
JP2000170481A JP2000170481A (en) 2000-06-20
JP3533963B2 true JP3533963B2 (en) 2004-06-07

Family

ID=18407235

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34995498A Expired - Fee Related JP3533963B2 (en) 1998-12-09 1998-12-09 Repair and construction method of waste disposal site

Country Status (1)

Country Link
JP (1) JP3533963B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838240A (en) * 2019-03-14 2019-06-04 中铁十八局集团有限公司 Cross the river tunnel ledge cover and cut construction method

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4525480B2 (en) * 2005-06-16 2010-08-18 株式会社大林組 Ground deformation prevention method
JP7070998B2 (en) * 2019-04-19 2022-05-18 東芝エネルギーシステムズ株式会社 Reactor building flooding equipment and reactor building flooding method
JP7071003B2 (en) * 2019-07-05 2022-05-18 東芝エネルギーシステムズ株式会社 Reactor building flooding equipment and reactor building flooding method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838240A (en) * 2019-03-14 2019-06-04 中铁十八局集团有限公司 Cross the river tunnel ledge cover and cut construction method

Also Published As

Publication number Publication date
JP2000170481A (en) 2000-06-20

Similar Documents

Publication Publication Date Title
CN110258549B (en) Repair structure and repair construction method for foundation pit supporting pile
JP3533963B2 (en) Repair and construction method of waste disposal site
EP0136355A1 (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP4356252B2 (en) Geological disposal facility and disposal tunnel segment
JPH06228947A (en) Construction of landslide protection wall in ground filled up with wastes
JP3803753B2 (en) Tunnel construction method
JP2943647B2 (en) Management method of contaminated water leaking from partition walls
JP3306527B2 (en) Open cut method of soft ground by deep mixing method
JPH0249896A (en) Open shield method and machine thereof
JP3663945B2 (en) Construction method of waste disposal site
JP2981165B2 (en) Underground impermeable wall and method of forming the same
JP2810957B2 (en) Pile foundation method
JP2008202344A (en) Support structure and support method of tunnel
JP2874906B2 (en) Shaft construction method
KR20030087288A (en) Executon method of wall for intercepting contamination zone of using steel sheet pile
JP2846248B2 (en) Earth retaining wall and construction method
JP5147616B2 (en) Construction method of underground wall
JP2007231641A (en) Collapse prevention construction method for dike
JPS62141260A (en) Construction method for sinking existing structure
JPH0631863B2 (en) Nuclear reactor abolition treatment method
JP3765047B2 (en) Construction method of steel pipe concrete pile
JP2023108461A (en) Nuclear reactor decommissioning method
JP3178357B2 (en) Construction method of large section tunnel
JPH02153110A (en) Constructing method for bottom enlarging and deepening pile
JPH06306887A (en) Chain type ditching machine and pipe embedding method therewith

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040217

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040301

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080319

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090319

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100319

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100319

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110319

Year of fee payment: 7

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110319

Year of fee payment: 7

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120319

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130319

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130319

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140319

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees