JP3197874B2 - Construction method of PC pile - Google Patents

Construction method of PC pile

Info

Publication number
JP3197874B2
JP3197874B2 JP36839598A JP36839598A JP3197874B2 JP 3197874 B2 JP3197874 B2 JP 3197874B2 JP 36839598 A JP36839598 A JP 36839598A JP 36839598 A JP36839598 A JP 36839598A JP 3197874 B2 JP3197874 B2 JP 3197874B2
Authority
JP
Japan
Prior art keywords
pile
diaphragm
shaft hole
hole
head end
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP36839598A
Other languages
Japanese (ja)
Other versions
JP2000192459A (en
Inventor
和男 駒澤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIHON BASE CO.,LTD.
Original Assignee
NIHON BASE CO.,LTD.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIHON BASE CO.,LTD. filed Critical NIHON BASE CO.,LTD.
Priority to JP36839598A priority Critical patent/JP3197874B2/en
Publication of JP2000192459A publication Critical patent/JP2000192459A/en
Application granted granted Critical
Publication of JP3197874B2 publication Critical patent/JP3197874B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明はPCパイルの建込
施工方法に関し、特に杭を建て込む為に掘削した残土を
建て込んだPCパイルの軸孔内に投入することにより、
投棄すべき残土の及ぶ限りの減少を図り、環境破壊の原
因を除去したものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a PC pile, and more particularly to a method for constructing a pile by inserting surplus soil excavated into a pile of a PC pile.
The aim is to reduce as much as possible the amount of surplus soil to be dumped and eliminate the cause of environmental destruction.

【0002】[0002]

【従来の技術】PCパイルはプレキャストコンクリート
からなる杭体であって、一端部が閉じてコーンヘッドを
形成し、そのコーンヘッドから他端部まで所定長さの中
空の軸孔を有する細長の有底円筒体である。この軸孔は
PCパイルの重量を軽減することと、モルタル遠心成型
法による必然的な構成要素であるが、地中に建込時や建
込後に何等の便宜をも提供するものではない。すなわ
ち、軸孔内に液体や固体又は気体等の充てん物を投入す
るものではなく、従来より、ほとんど中空のまま埋め込
まれる。このPCパイルはアースオーガ等によって削設
された地中孔に挿入して建て込み、その頭端部に支持を
取って建築物の基礎などが形成される。
2. Description of the Related Art A PC pile is a pile made of precast concrete. One end is closed to form a cone head, and an elongated hole having a hollow shaft hole having a predetermined length from the cone head to the other end. It is a bottom cylinder. The shaft hole is an essential component for reducing the weight of the PC pile and for the mortar centrifugal molding method, but does not provide any convenience at the time of being built in the ground or after being built. That is, a filling material such as a liquid, a solid, or a gas is not charged into the shaft hole, and the filling is made almost hollow in the related art. This PC pile is inserted and built into an underground hole cut by an earth auger or the like, and its head end is supported to form a foundation of a building.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、杭建込
機等による建設現場の掘削土砂が残土として投棄せざる
を得ない場合、今やその投棄場所が限られて重大な環境
問題を提起しており、また、投棄場所まで運搬しなけれ
ばならないという経済的負担を強いられるのが現実であ
る。
However, when excavated soil at a construction site due to a pile construction machine or the like has to be dumped as surplus soil, the dumping place is now limited and raises serious environmental problems. In addition, the reality is that there is an economic burden of having to transport to the dump site.

【0004】そこで、この発明はPCパイルを建て込む
場合に、アースオーガ等にて掘削した土砂を、その建て
込んだPCパイルの軸孔内に投入して埋め戻すことによ
り、投棄すべき残土の及ぶ限りの減少を図ろうとするも
のである。
Therefore, according to the present invention, when a PC pile is built, earth and sand excavated by an earth auger or the like is put into a shaft hole of the built PC pile and back-filled, thereby removing residual soil to be dumped. The aim is to reduce as far as possible.

【0005】[0005]

【課題を解決するための手段】この発明にかかるPCパ
イルの建込施工方法は、請求項1に記載のように、削設
した地中孔にプレキャストコンクリートからなるPCパ
イルを建込んで地面に露出させたその頭端部から軸孔内
、前記PCパイルの内径よりも小さい巾寸法と起振性
の高い肉厚を有する所要長さの振動板を挿入し、該振動
板を起振させながらPCパイルの頭端部から軸孔内に残
土等を投入することを特徴とする。
According to a first aspect of the present invention, a method for constructing a PC pile according to the present invention is to lay a PC pile made of precast concrete in a ground hole that has been cut and install it on the ground. A width dimension smaller than the inner diameter of the PC pile and vibrating properties are set in the shaft hole from the exposed head end .
The method is characterized in that a diaphragm of a required length having a high wall thickness is inserted, and while the diaphragm is vibrated, residual soil or the like is poured into the shaft hole from the head end of the PC pile.

【0006】そして、請求項2に記載のように、前記振
動板がPCパイルに接触して該振動板にてPCパイルが
振動可能なことを特徴とするとともに、請求項3に記載
のように、前記残土等が前記PCパイルを建込むために
アースオーガ等にの掘削機にて穿設した土砂であること
を特徴とする。
According to a second aspect of the present invention, the vibration plate contacts the PC pile so that the PC pile can be vibrated by the vibration plate. The remaining soil and the like are earth and sand drilled by an excavator in an earth auger or the like in order to build the PC pile.

【0007】したがって、地中孔の穿設にて産出した残
土がPCパイルのい軸孔内に投入されて投棄すべき残土
量が減少して投棄に要する諸費用等の減少と環境破壊要
因の減少が可能となる。
[0007] Therefore, the residual soil produced by drilling the underground hole is thrown into the shaft hole of the PC pile to reduce the amount of residual soil to be dumped, thereby reducing various costs required for dumping and causing environmental destruction. Reduction is possible.

【0008】[0008]

【発明の実施の形態】以下この発明の実施の形態を図に
基づき説明する。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below with reference to the drawings.

【0009】PCパイルを建て込むための第1施工工程
として、図1に示すように、所要長さの地中孔10を地
面G.Lに穿設する。穿孔作業には、例えば、図示のよ
うなアースオーガ掘削機を用い、地上を走行可能なその
本体1に柱2を地上へ垂直に向けて立設し、該柱2に平
行して設けられたガイド柱3にガイドされて昇降可能な
減速機4を配設し、該減速機4は油圧モータ又は電動モ
ータ等の駆動機4にて駆動され、減速機4に接続したス
パイラルスクリュウからなるオーガ8が回転することに
より地中孔10が穿設される。穿設による残土11は排
出ガイド9等を介してなるべく地中孔10付近に載置し
ておく。
As a first construction step for laying a PC pile, as shown in FIG. Drill in L. For the drilling work, for example, an earth auger excavator as shown in the figure is used, and a pillar 2 is erected vertically on the main body 1 capable of traveling on the ground, and provided in parallel with the pillar 2. A speed reducer 4 that can be moved up and down by being guided by the guide pillar 3 is provided. The speed reducer 4 is driven by a drive device 4 such as a hydraulic motor or an electric motor, and is an auger 8 composed of a spiral screw connected to the speed reducer 4. The underground hole 10 is drilled by rotating. The excavated soil 11 is placed as close to the underground hole 10 as possible via the discharge guide 9 or the like.

【0010】所要長さの地中孔10が穿設された後、第
2施工工程として、その地中孔10内にPCパイルを建
て込む。この建て込み作業はどのような手段を採っても
よいが、例えば、図2に示すように、杭建込機としての
アースオーガ掘削機の本体1から駆動機5と一体の減速
機4をガイド柱3から取り外し、それらを吊り上げてい
る吊支索6にPCパイル12の頭端部を連結して吊り上
げ、コーンヘッドの先端部を地中孔12内に導いて建て
込むのがよい。
After the underground hole 10 having a required length is formed, a PC pile is erected in the underground hole 10 as a second construction step. This installation work may take any means. For example, as shown in FIG. 2, the reduction gear 4 integrated with the drive unit 5 is guided from the main body 1 of the earth auger excavator as a pile construction machine. It is preferable to remove the pillars 3, connect the head ends of the PC piles 12 to the suspension ropes 6 for lifting them, lift them up, guide the tip of the cone head into the underground holes 12, and build them.

【0011】PCパイル12が地中孔10内に建て込ま
れた後、第3施工工程として、地面G.Lから露出する
その頭端部から残土11を軸孔13内に投入する。残土
11の投入は、PCパイル12の内径が高々40cm程
度であるから、残土11を頭端部から直接投入しても内
部で団塊状となって目詰まりする可能性が高い。そこ
で、図3に示すように、PCパイル12の頭端部から振
動板15を内部に挿入し、該振動板15を起振機14に
接続する。起振機14は、例えば、図示のように、PC
パイル12を建て込んだ後のアースオーガ掘削機のガイ
ド柱3に係合し、吊支索6に吊支されて昇降可能に配設
するのがよい。
After the PC pile 12 is erected in the underground hole 10, the ground G. The residual soil 11 is put into the shaft hole 13 from the head end exposed from the L. Since the inside diameter of the PC pile 12 is at most about 40 cm when the residual soil 11 is charged, even if the residual soil 11 is directly introduced from the head end portion, there is a high possibility that the residual soil 11 becomes a nodule inside and is clogged. Therefore, as shown in FIG. 3, the diaphragm 15 is inserted into the inside of the PC pile 12 from the head end thereof, and the diaphragm 15 is connected to the vibrator 14. The exciter 14 is, for example, a PC
The pile 12 is preferably engaged with the guide pillar 3 of the earth auger excavator after the pile 12 is erected, suspended by the suspension rope 6 and arranged so as to be able to move up and down.

【0012】振動板15は、図4に実線にて示すよう
に、PCパイル12の内径Dよりも小さい巾寸法と起振
性の高い肉厚を有する所要長さの板体であって、通例、
鉄板からなる。したがって、振動板15はPCパイル1
2の軸孔内で自由に揺動し、かつ、振動することができ
る。また、図4に仮想線にて示すように、振動板15の
巾寸法を大きくしてPCパイル12の内周面に当接する
振動板16を配設することにより、振動板16はPCパ
イル12と一体的に振動することができるようにしても
よい。なお、軸孔13内に堆積する残土11の量に見合
い、振動板15は軸孔13から上方へ上昇させて最終的
には引き抜かれる。
As shown by a solid line in FIG. 4, the diaphragm 15 is a plate of a required length having a width dimension smaller than the inner diameter D of the PC pile 12 and a high vibrating thickness. ,
Made of iron plate. Therefore, the diaphragm 15 is the PC pile 1
It can freely swing and vibrate in the second shaft hole. Further, as shown by the phantom line in FIG. 4, by increasing the width of the diaphragm 15 and disposing the diaphragm 16 in contact with the inner peripheral surface of the PC pile 12, the diaphragm 16 is It may be possible to integrally vibrate. Note that the diaphragm 15 is lifted upward from the shaft hole 13 and finally pulled out in accordance with the amount of the residual soil 11 deposited in the shaft hole 13.

【0013】したがって、起振機14にて振動板15を
振動させながらPCパイル12の頭端部から軸孔内に残
土11を適宜の可搬機(ユンボ(登録商標)等)で投入
すると、振動板14又は振動板とPCパイルの両方が振
動して軸孔内の残土11は目詰まりを生じることなく、
孔内底部から頭端部まで密度高く投入され、地上G.L
に残る残土11の量のうち、少なくとも軸孔13の容積
に相当する量が処分されるため、投棄すべき残土11の
量が減少し、投棄するための諸費用等が減少する。
Therefore, when the residual soil 11 is put into the shaft hole from the head end of the PC pile 12 by a suitable portable machine (such as Yumbo (registered trademark)) while the diaphragm 15 is vibrated by the vibrator 14, The diaphragm 14 or both the diaphragm and the PC pile vibrate, and the residual soil 11 in the shaft hole does not clog,
It is injected with high density from the bottom of the hole to the head end. L
Since at least an amount corresponding to the volume of the shaft hole 13 is discarded out of the amount of the remaining soil 11, the amount of the remaining soil 11 to be dumped is reduced, and various costs for dumping are reduced.

【0014】[0014]

【発明の効果】以上説明したこの発明によれば、PCパ
イルを打ち込む為に穿設した地中孔から排出された残土
をPCパイルの軸孔内に埋め戻すこととしたので、投棄
すべき残土の産出量が減少してその投棄に要する諸費用
等の減少と環境破壊要因の削減を図ることができる。
According to the present invention described above, the residual soil discharged from the underground hole drilled for driving the PC pile is backfilled in the shaft hole of the PC pile, so that the residual soil to be discarded As a result, it is possible to reduce the costs required for dumping and reduce environmental destruction factors.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この発明の第1施工工程の概略図である。FIG. 1 is a schematic view of a first construction step of the present invention.

【図2】この発明の第2施工工程の概略図である。FIG. 2 is a schematic view of a second construction step of the present invention.

【図3】この発明の第3施工工程の概略図である。FIG. 3 is a schematic view of a third construction step of the present invention.

【図4】PCパイルに振動板を挿入した横断面図であ
る。
FIG. 4 is a cross-sectional view in which a diaphragm is inserted into a PC pile.

【符号の説明】 10…地中孔 11…残土 12…PCパイル 13…軸孔 14…起振機 15…振動板[Description of Signs] 10: Underground hole 11: Residual soil 12: PC pile 13: Shaft hole 14: Exciter 15: Vibration plate

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 削設した地中孔にプレキャストコンクリ
ートからなるPCパイルを建込んで地面に露出させたそ
の頭端部から軸孔内に、前記PCパイルの内径よりも小
さい巾寸法と起振性の高い肉厚を有する所要長さの板体
からなる振動板を挿入し、該振動板を起振させながらP
Cパイルの頭端部から軸孔内に残土等を投入することを
特徴とするPCパイルの建込施工方法。
To 1. A Kezu設the axial bore of the PC piles made of precast concrete in the ground hole from its head end to expose the ground crowded denominated smaller than the inner diameter of the PC pile
A diaphragm made of a plate of a required length having a width and a wall thickness with high vibrating properties is inserted, and P is applied while vibrating the diaphragm.
A method for constructing a PC pile, comprising charging remaining soil and the like into a shaft hole from a head end of a C pile.
【請求項2】 振動板がPCパイルに接触して該振動板
にてPCパイルが振動可能なことを特徴とする請求項1
記載のPCパイルの建込施工方法。
2. The PC pile is vibrated by the diaphragm in contact with the PC pile.
The construction method of PC pile described.
【請求項3】 残土等が前記PCパイルを建込むために
アースオーガ等の掘削機にて穿設した土砂であることを
特徴とする請求項1又は2記載のPCパイルの建込施工
方法。
3. The method according to claim 1, wherein the remaining soil is earth and sand pierced by an excavator such as an earth auger to lay the PC pile.
JP36839598A 1998-12-25 1998-12-25 Construction method of PC pile Expired - Fee Related JP3197874B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP36839598A JP3197874B2 (en) 1998-12-25 1998-12-25 Construction method of PC pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP36839598A JP3197874B2 (en) 1998-12-25 1998-12-25 Construction method of PC pile

Publications (2)

Publication Number Publication Date
JP2000192459A JP2000192459A (en) 2000-07-11
JP3197874B2 true JP3197874B2 (en) 2001-08-13

Family

ID=18491710

Family Applications (1)

Application Number Title Priority Date Filing Date
JP36839598A Expired - Fee Related JP3197874B2 (en) 1998-12-25 1998-12-25 Construction method of PC pile

Country Status (1)

Country Link
JP (1) JP3197874B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8100301B2 (en) 2009-05-06 2012-01-24 Babiarz Stacey A Sandbag filling apparatus

Also Published As

Publication number Publication date
JP2000192459A (en) 2000-07-11

Similar Documents

Publication Publication Date Title
JPH0711233B2 (en) Non-removing earth construction device for foundation piles and non-removing earth construction method for foundation piles
JP3197874B2 (en) Construction method of PC pile
GB2154630A (en) Construction method for foundation piling
JP2000170149A (en) Forming method for underground pile and equipment therefor
JP2673677B2 (en) Pile method
JPS62242011A (en) Method and apparatus for constructing shallow ground-improving pile
JP3144767B2 (en) Underground pile forming method and apparatus
JPH0280710A (en) Preparing cast-in-place concrete pile
GB2132667A (en) Method of installing precast concrete piles
JPH0711232B2 (en) Non-removing earth construction device for foundation piles and non-removing earth construction method for foundation piles
JP2001182047A (en) Construction method and device for static improvement of soft ground
JPS6235742Y2 (en)
JPH07901B2 (en) Non-removing earth construction device for foundation piles and non-removing earth construction method for foundation piles
JP2000345554A (en) Ground improvement method
JP2758129B2 (en) Installation method of ground improvement pile
JP2008248572A (en) Method of improving soil
JP2001323463A (en) Inner excavation, low-displacement, low-noise, low- vibration pile driver for friction pile and method of driving pile
JP2004150070A (en) Treatment method for removed soil, and removed soil-treated construction method for foundation pile
JP2008063916A (en) Ground improvement construction method and ground improvement device
JPS5941520A (en) Construction of foundation pile and excavator therefor
JPS63114719A (en) Foundation pile
JPH11336075A (en) Driving construction method of steel pipe pile and nose pile driving device therefor
JP2003003455A (en) Compaction method of ground
JPH02279820A (en) Method of laying pile
JPH04309617A (en) Method for improving foundation ground and device therefor

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees