JP3158115B1 - Joint structure of steel pipe column and method of construction of the joint structure - Google Patents

Joint structure of steel pipe column and method of construction of the joint structure

Info

Publication number
JP3158115B1
JP3158115B1 JP2000192766A JP2000192766A JP3158115B1 JP 3158115 B1 JP3158115 B1 JP 3158115B1 JP 2000192766 A JP2000192766 A JP 2000192766A JP 2000192766 A JP2000192766 A JP 2000192766A JP 3158115 B1 JP3158115 B1 JP 3158115B1
Authority
JP
Japan
Prior art keywords
steel pipe
pipe column
hole
reinforcing member
column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000192766A
Other languages
Japanese (ja)
Other versions
JP2002004420A (en
Inventor
博信 黒田
Original Assignee
博信 黒田
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 博信 黒田 filed Critical 博信 黒田
Priority to JP2000192766A priority Critical patent/JP3158115B1/en
Application granted granted Critical
Publication of JP3158115B1 publication Critical patent/JP3158115B1/en
Publication of JP2002004420A publication Critical patent/JP2002004420A/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

【要約】 【課題】 鋼管柱の強度低下を招くことなく省力的かつ
正確に鋼管柱の接合作業を行うことができる鋼管柱の接
合構造物と、その合理的施工方法を提供する。 【解決手段】 止着孔を開設した鋼管柱1と;この鋼管
柱1の外側に被嵌可能な補強部材2と;鋼管柱1の止着
孔に挿着せる固定部材3と;この固定部材3のネジ孔に
螺合可能なボルト4とを包含して成り、鋼管柱1の外側
に補強部材2を被嵌させて前記止着孔と通孔とを合致さ
せて固定部材3によって鋼管柱1と補強部材2とを固定
すると共に、前記ボルト4により固定部材3のネジ孔に
当該補強部材2の外側から捻込んで鋼管柱1と鉄骨梁B
等を接合した。また、かゝる鋼管柱構造物を構築する際
に、パンダグラフ機構によって拡縮するワーク保持フレ
ームを備えた挿着治具を用いた。
An object of the present invention is to provide a joint structure of steel pipe columns capable of performing labor-saving and accurate joining work of steel pipe columns without reducing the strength of the steel pipe columns, and a rational construction method thereof. SOLUTION: A steel pipe column 1 having a fixing hole, a reinforcing member 2 that can be fitted to the outside of the steel pipe column 1, a fixing member 3 to be inserted into the fixing hole of the steel pipe column 1, and the fixing member 3 And a bolt 4 that can be screwed into the screw hole. The reinforcing member 2 is fitted to the outside of the steel pipe column 1 so that the fixing hole and the through hole are aligned with each other. And the reinforcing member 2 are fixed, and the steel pipe column 1 and the steel beam B are screwed into the screw holes of the fixing member 3 from outside of the reinforcing member 2 by the bolts 4.
Etc. were joined. When constructing such a steel pipe column structure, an insertion jig provided with a work holding frame that expands and contracts by a pandagraph mechanism was used.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鋼管柱における接
合構造物、およびその施工方法、より詳しくは、鋼管柱
と鉄骨梁との接合構造、鋼管柱同士の突合せ接合構造、
鋼管柱と柱脚部材との接合する合理的技術に関するもの
である。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a joint structure in a steel pipe column and a method of constructing the same, and more particularly, to a joint structure between a steel pipe column and a steel beam, a butt joint structure between steel pipe columns,
The present invention relates to a rational technique for joining a steel pipe column and a column base member.

【0002】[0002]

【従来の技術】従来、鋼管柱にH形鋼等の鉄骨梁を接合
する方法としては、鋼管柱の梁接合部に水平ダイヤフラ
ムを介在させ、この水平ダイヤフラムに鉄骨梁を溶接接
合するのが一般的である。しかし、この方法は、多くの
切断・溶接工程が必要で手間が掛かるうえに、作業者の
技量に負うところが大きく精度確保が困難である問題が
あった。
2. Description of the Related Art Conventionally, as a method of joining a steel beam such as an H-shaped steel beam to a steel tube column, a horizontal diaphragm is interposed at a beam joint of the steel tube column, and a steel beam is welded to the horizontal diaphragm. It is a target. However, this method has problems that many cutting / welding steps are required, which is troublesome, and that it depends on the skill of the operator and that it is difficult to ensure accuracy.

【0003】そこで、現在までに、溶接作業を必要とし
ない柱接合方法として、鋼管柱の梁接合部分に補強部材
を内装し、この補強部材を利用して鉄骨梁をボルト接合
する方法が提案されている(特開平5-263468号、特開平
11−324226号公報等参照)。しかしながら、この方法
は、鋼管柱内に補強部材を挿入し、そして、この補強部
材を梁接合部に確実に固定する作業に手間が掛かり、精
度の確保が困難であることに変わりはなく、しかも、こ
の補強部材に梁材をボルト接合する際に、鋼管柱の内側
の手の届かない場所においては、高価なワンサイドボル
トを使用せざるを得ず、また、通常の高力ボルトを使用
する場合には、鋼管柱の強度を犠牲にして鋼管柱に手を
差し入れるための開口部を設けなければならなかった。
[0003] To date, as a column joining method that does not require a welding operation, there has been proposed a method in which a reinforcing member is provided inside a beam joining portion of a steel pipe column and a steel beam is bolted using the reinforcing member. (Japanese Unexamined Patent Publication No. 5-263468,
11-324226, etc.). However, in this method, it takes time and effort to insert the reinforcing member into the steel pipe column and securely fix the reinforcing member to the beam joint, and it is still difficult to ensure accuracy. When bolting a beam to this reinforcing member, an expensive one-side bolt must be used and a normal high-strength bolt must be used in places that are not accessible inside the steel pipe column. In such a case, an opening for inserting a hand into the steel pipe column had to be provided at the expense of the strength of the steel pipe column.

【0004】[0004]

【発明が解決しようとする課題】本発明は、従来の鋼管
柱の接合構造に上記のような難点があったことに鑑みて
為されたもので、その目的とするところは、鋼管柱の強
度低下を招くことなしに省力的かつ正確に鋼管柱の接合
作業を行える鋼管柱の接合構造物、ならびにその合理的
な施工方法を提供することを技術的課題とするものであ
る。
SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned difficulties in the conventional joint structure of steel pipe columns. An object of the present invention is to provide a joint structure for steel pipe columns capable of labor-saving and accurate joining work of steel pipe columns without causing a reduction, and a rational construction method thereof.

【0005】[0005]

【課題を解決するための手段】本発明は、上記の技術的
課題を解決するために、鋼管柱1に鉄骨梁Bを接合する
鋼管柱の接合構造であって、鉄骨梁Bを接合すべき部位
に止着孔10が開設された鋼管柱1と;この鋼管柱1の外
側に被嵌され、当該鋼管柱1の止着孔10に対向する位置
に通孔20が開設された補強部材2と;軸心にネジ孔30を
備えた筒体であって、前記鋼管柱1の止着孔10に軸方向
へ進退可能に挿着され、この筒体の後端側には鋼管柱1
の内面に当接可能な鍔部31が形成されていると共に、筒
体の先端側には前記補強部材2の内面に当接可能な当接
部32が形成された固定部材3と;この固定部材3のネジ
孔30に螺合可能なボルト4と;から構成されており、前
記鋼管柱1の止着孔10に内側から挿着した固定部材3を
後退させた状態で、鋼管柱1の外側に補強部材2を被嵌
し、鋼管柱1の止着孔10と補強部材2の通孔20とを位置
合わせした後、固定部材3を前進させて当該固定部材3
の鍔部31を鋼管柱1の内面に当接させると共に当接部32
を補強部材2の内面に当接させることにより鋼管柱1の
梁接合部位に補強部材2を固定し、然る後、ボルト4を
固定部材3のネジ孔30に補強部材2の外側から螺合して
鋼管柱1と鉄骨梁Bとを接合するという技術的手段を採
用した。
SUMMARY OF THE INVENTION In order to solve the above-mentioned technical problem, the present invention relates to a joint structure of a steel tube column for joining a steel beam column B to a steel tube column 1, and the steel frame beam B is to be joined. A steel pipe column 1 having a fastening hole 10 formed at a portion thereof; a reinforcing member 2 fitted to the outside of the steel tube column 1 and having a through hole 20 formed at a position facing the fastening hole 10 of the steel pipe column 1. A cylindrical body having a screw hole 30 at the axis thereof, which is inserted into the fastening hole 10 of the steel pipe column 1 so as to be able to advance and retreat in the axial direction, and a steel pipe column 1 is provided at the rear end side of the cylindrical body.
A fixing member 3 having a contactable flange 32 formed on the inner surface of the reinforcing member 2 and a flange 31 that can be brought into contact with the inner surface of the reinforcing member 2. A bolt 4 which can be screwed into the screw hole 30 of the member 3. The fixing member 3 inserted from the inside into the fixing hole 10 of the steel tube column 1 is retracted, and After the reinforcing member 2 is fitted to the outside and the fastening hole 10 of the steel pipe column 1 and the through hole 20 of the reinforcing member 2 are aligned, the fixing member 3 is advanced and the fixing member 3 is moved forward.
Abutting the flange portion 31 of the steel tube column 1 against the inner surface thereof.
Is brought into contact with the inner surface of the reinforcing member 2 to fix the reinforcing member 2 to the beam joint portion of the steel pipe column 1. Thereafter, the bolt 4 is screwed into the screw hole 30 of the fixing member 3 from outside the reinforcing member 2. Then, the technical means of joining the steel pipe column 1 and the steel beam B was adopted.

【0006】また、本発明は、上記課題を解決するため
に、鋼管柱1と他の鋼管柱1′とを突合せ接合する鋼管
柱の接合構造であって、互いに突合せ接合すべき端部に
各々止着孔10が開設された鋼管柱1・1′と;これら鋼
管柱1・1′の外側に途中まで被嵌され、当該鋼管柱1
・1′の各止着孔10に対向する位置に通孔20が開設され
た補強部材2と;軸心にネジ孔30を備えた筒体であっ
て、前記鋼管柱1・1′の止着孔10に軸方向へ進退可能
に挿着され、この筒体の後端側には鋼管柱1・1′の内
面に当接可能な鍔部31が形成されていると共に、筒体の
先端側には前記補強部材2の通孔20に嵌合可能な嵌合突
起35を備え、かつ、この嵌合突起35の根本は前記補強部
材2の内面に当接可能な当接部32に形成された固定部材
3と;この固定部材3のネジ孔30に螺合可能なボルト4
と;から構成されており、前記鋼管柱1・1′の止着孔
10に内側から挿着した固定部材3を後退させた状態で、
鋼管柱1・1′の外側に補強部材2を途中まで被嵌し、
鋼管柱1・1′の止着孔10と補強部材2の通孔20とを位
置合わせした後、固定部材3を前進させて当該固定部材
3の鍔部31を鋼管柱1・1′の内面に当接させると共に
当接部32を補強部材2の内面に当接させることにより鋼
管柱1・1′の突合せ部位に補強部材2を固定し、然る
後、ボルト4を固定部材3のネジ孔30に補強部材2の外
側から螺合して鋼管柱1と他の鋼管柱1′とを突合せ接
合するという技術的手段を採用した。
In order to solve the above-mentioned problems, the present invention also relates to a joint structure of a steel pipe column in which a steel pipe column 1 and another steel tube column 1 'are butt-joined, wherein the steel tube column 1 and the other steel tube column 1' are respectively joined to ends to be butt-joined to each other. A steel pipe pillar 1.1 'having a fastening hole 10 therein; and a steel pipe pillar 1 which is fitted halfway to the outside of the steel pipe pillar 1.1'.
A reinforcing member 2 having a through hole 20 at a position facing each of the fixing holes 10 of 1 '; a cylindrical body having a screw hole 30 at the axis thereof, and a stopper for the steel pipe column 1.1'; A flange 31 is formed at the rear end side of the cylindrical body so as to be able to abut against the inner surface of the steel tube post 1, 1 ′. On the side, a fitting protrusion that can be fitted into the through hole 20 of the reinforcing member 2 is provided.
A fixing member 3 formed at a contact portion 32 capable of contacting the inner surface of the reinforcing member 2; and a threaded engagement with a screw hole 30 of the fixing member 3. Possible bolts 4
And a fixing hole of the steel pipe column 1.1 ′.
In a state where the fixing member 3 inserted from the inside to 10 is retracted,
Reinforcing member 2 is fitted halfway on the outside of steel pipe column 1.1 ',
After aligning the fastening holes 10 of the steel pipe columns 1 and 1 'with the through holes 20 of the reinforcing member 2, the fixing member 3 is advanced and the flange 31 of the fixing member 3 is moved to the inner surface of the steel pipe columns 1.1'. The reinforcing member 2 is fixed to the abutting portion of the steel pipe columns 1.1 'by contacting the contact portion 32 with the inner surface of the reinforcing member 2. Then, the bolt 4 is screwed into the fixing member 3. A technical means was employed in which the steel pipe column 1 and another steel pipe column 1 'were butt-joined by screwing into the hole 30 from outside the reinforcing member 2.

【0007】更にまた、本発明は、上記課題を解決する
ために、鋼管柱1の下端部に柱脚部材Cを接合する鋼管
柱の接合構造であって、下端部に止着孔10が開設された
鋼管柱1と;上部が鋼管柱1の外側に被嵌可能であると
共に鋼管柱1の止着孔10に対向する位置に通孔20が開設
されており、下部が柱脚部材Cに固定された補強部材2
と;軸心にネジ孔30を備えた筒体であって、前記鋼管柱
1の止着孔10に軸方向へ進退可能に挿着され、この筒体
の後端側には鋼管柱1の内面に当接可能な鍔部31が形成
されていると共に、筒体の先端側には前記補強部材2の
通孔20に嵌合可能な嵌合突起35を備え、かつ、この嵌合
突起35の根本は前記補強部材2の内面に当接可能な当接
部32に形成された固定部材3と;この固定部材3のネジ
孔30に螺合可能なボルト4と;から構成されており、前
記鋼管柱1の止着孔10に内側から挿着した固定部材3を
後退させた状態で、鋼管柱1の外側に補強部材2を被嵌
し、鋼管柱1の止着孔10と補強部材2の通孔20とを位置
合わせした後、固定部材3を前進させて当該固定部材3
の鍔部31を鋼管柱1の内面に当接させると共に当接部32
を補強部材2の内面に当接させることにより鋼管柱1の
柱脚接合部位に補強部材2を固定し、然る後、ボルト4
を固定部材3のネジ孔30に補強部材2の外側から螺合し
て鋼管柱1と柱脚部材Cとを接合するという技術的手段
を採用したのである。
Further, in order to solve the above-mentioned problems, the present invention relates to a joint structure of a steel tube column for joining a column base member C to a lower end portion of the steel tube column 1, wherein a fastening hole 10 is formed at a lower end portion. The upper end of the steel pipe column 1 can be fitted to the outside of the steel pipe column 1, and a through hole 20 is formed at a position facing the fastening hole 10 of the steel pipe column 1, and the lower part is formed in the column base member C. Fixed reinforcement member 2
A cylindrical body having a screw hole 30 at the axis thereof, which is inserted into the fixing hole 10 of the steel pipe column 1 so as to be able to advance and retreat in the axial direction, and the rear end side of the cylindrical body A flange 31 capable of contacting the inner surface is formed, and the reinforcing member 2
It is provided with a fitting projection 35 that can be fitted into the through hole 20, and this fitting
The root of the projection 35 is composed of a fixing member 3 formed on a contact portion 32 that can contact the inner surface of the reinforcing member 2; and a bolt 4 that can be screwed into the screw hole 30 of the fixing member 3. In a state where the fixing member 3 inserted from the inside into the fixing hole 10 of the steel pipe column 1 is retracted, the reinforcing member 2 is fitted to the outside of the steel pipe column 1, and the fixing hole 10 of the steel pipe column 1 is After the alignment with the through hole 20 of the reinforcing member 2, the fixing member 3 is advanced to move the fixing member 3.
Abutting the flange portion 31 of the steel tube column 1 against the inner surface thereof.
Abuts against the inner surface of the reinforcing member 2 to fix the reinforcing member 2 to the column-base joint portion of the steel pipe column 1.
Is screwed into the screw hole 30 of the fixing member 3 from outside of the reinforcing member 2 to join the steel pipe column 1 and the column base member C.

【0008】また更に、本発明は、上記課題を方法的に
解決するための手段として、鋼管柱1に鉄骨梁Bを接合
せしめるにあたって、鉄骨梁Bを接合すべき部位に止着
孔10を開設した鋼管柱1の外側に、前記止着孔10に対向
する位置に通孔20を開設した補強部材2を被嵌させて、
この補強部材2の通孔20と前記鋼管柱1の止着孔10とを
対向合致せしめる一方、前記鋼管柱1の止着孔10に挿入
進退させ得る筒体であって、内筒部はネジ孔30を形成
し、かつ、後端側には鋼管柱1の内面に当接可能な鍔部
31、および先端側には前記補強部材2の内面に当接可能
な当接部32を有する固定部材3・3・・・・を、パンダグラ
フ機構62・62によって対向的に拡縮動作可能な挿着治具
6のワーク保持フレーム63・63・・・・に保持させて前記鋼
管柱1の中に挿入し、対向合致状態にある前記止着孔10
と通孔20に前記各固定部材3を向い合わせ、前記パンダ
グラフ機構62・62の幅拡大動作を介してワーク保持フレ
ーム63・63を当該鋼管柱1の対向内壁面に向けて移動さ
せることによって固定部材3を挿入せしめ、前記各固定
部材3後端の鍔部31は当該鋼管柱1の内面に当接させ、
同固定部材3前端の当接部32は補強部材3の内面に当接
させてから、これら固定部材3のネジ孔30と前記鉄骨梁
Bのボルト孔bとを合致させ、ついで、高力ボルト4を
前記ネジ孔30に螺入することにより鋼管柱1と補強部材
2と鉄骨梁Bとを緊結状態に接合させるという作業手段
を採用した点に特徴がある。
Further, according to the present invention, as a means for solving the above-mentioned problem in a method, when a steel beam B is joined to a steel pipe column 1, a fastening hole 10 is opened at a portion where the steel beam B is to be joined. A reinforcing member 2 having a through hole 20 at a position facing the fastening hole 10 is fitted on the outside of the steel pipe column 1 thus formed,
The through-hole 20 of the reinforcing member 2 and the fastening hole 10 of the steel pipe column 1 are opposed to each other, and a cylindrical body that can be inserted into and retracted from the fastening hole 10 of the steel pipe column 1. A flange formed with a hole 30 and capable of contacting the inner surface of the steel tube column 1 at the rear end side
.. Having a contact portion 32 that can contact the inner surface of the reinforcing member 2 at the distal end side thereof. The holding jig 6 is held by the work holding frames 63, 63,.
By moving the work holding frames 63 toward the opposing inner wall surfaces of the steel pipe column 1 through the width-enlargement operation of the pandagraph mechanisms 62. The fixing members 3 are inserted, and the flange 31 at the rear end of each of the fixing members 3 is brought into contact with the inner surface of the steel pipe column 1.
After the contact portion 32 at the front end of the fixing member 3 is brought into contact with the inner surface of the reinforcing member 3, the screw hole 30 of the fixing member 3 and the bolt hole b of the steel beam B are aligned with each other. 4 is screwed into the screw hole 30 to join the steel pipe column 1, the reinforcing member 2 and the steel beam B in a tight state.

【0009】[0009]

【発明の実施の形態】以下、本発明を添付図面に示す第
一実施形態〜第四実施形態に基いて詳しく説明する。な
お、図1は本発明に係る第一実施形態の鋼管柱の接合構
造の部分縦断面図、図2は同接合構造の部分横断面図、
図3〜図8は同接合構造の組立工程図である。また、図
9は本発明に係る第二実施形態の鋼管柱の接合構造の部
分縦断面図、図10は同接合構造の部分横断面図、図11〜
図16は同接合構造の組立工程図である。また、図17は本
発明に係る第三実施形態の鋼管柱の接合構造の部分分解
縦断面図、図18は本発明に係る第四実施形態の鋼管柱の
接合構造の部分分解縦断面図、図19は本発明の第五実施
形態における挿着治具を用いて鋼管柱と補強部材とを固
定部材にて連結する過程を表わした説明図、図20は本発
明の第五実施形態を表わす部分拡大断面図である。
DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, the present invention will be described in detail based on first to fourth embodiments shown in the accompanying drawings. 1 is a partial longitudinal sectional view of a joint structure of a steel pipe column according to a first embodiment of the present invention, FIG. 2 is a partial transverse sectional view of the joint structure,
3 to 8 are assembly process diagrams of the joint structure. 9 is a partial longitudinal sectional view of a joint structure of a steel pipe column according to a second embodiment of the present invention, FIG. 10 is a partial transverse sectional view of the joint structure, FIGS.
FIG. 16 is an assembly process diagram of the joint structure. FIG. 17 is a partially exploded longitudinal sectional view of the joint structure of the steel pipe column according to the third embodiment of the present invention, and FIG. 18 is a partially exploded longitudinal sectional view of the joint structure of the steel pipe column according to the fourth embodiment of the present invention. FIG. 19 is an explanatory view showing a process of connecting a steel pipe column and a reinforcing member with a fixing member using an insertion jig according to a fifth embodiment of the present invention, and FIG. 20 shows a fifth embodiment of the present invention. It is a partial expanded sectional view.

【0010】『第一実施形態』 本実施形態の鋼管柱の接合構造は、図1〜図8に示すよ
うに、鋼管柱1とH形鋼製の鉄骨梁Bとを高力ボルト4
で接合するものである。
[First Embodiment] [0010] As shown in Figs. 1 to 8, a joint structure of a steel pipe column according to the present embodiment includes a steel pipe column 1 and a steel beam B made of H-section steel.
Are joined together.

【0011】図中、符号1で指示するものは角形鋼管か
ら成る鋼管柱であり、この鋼管柱1の管壁の鉄骨梁Bを
接合すべき部位には、図4に示すように、複数の止着孔
10・10…が開設されており、各止着孔10には左ねじの雌
ネジ11が刻設されている。
In the drawing, the reference numeral 1 designates a steel pipe column made of a square steel pipe. A plurality of steel pipe columns 1 are connected to the steel beam B on the pipe wall, as shown in FIG. Fastening hole
10... Are opened, and a female screw 11 of a left-hand thread is engraved in each fastening hole 10.

【0012】図中、符号2で指示するものは上記鋼管柱
1の外側に被嵌可能で、鋼管柱1の梁接合部位を補強す
るための補強部材であり、図5に示すように鋼管柱1の
止着孔10に対向する位置に通孔20が開設されている。即
ち、本実施形態の補強部材2は、図2に示すように角形
鋼管により形成されており、鋼管柱1の外側に被嵌した
とき、補強部材2の内周壁が鋼管柱1の外周壁に対面す
る。この補強部材2の内周壁に上記止着孔10・10…に対
応する複数の通孔20・20…が開設されている。
In the drawing, reference numeral 2 designates a reinforcing member which can be fitted on the outside of the steel pipe column 1 and reinforces a beam joint portion of the steel column 1 as shown in FIG. A through hole 20 is formed at a position facing the one fixing hole 10. That is, the reinforcing member 2 of the present embodiment is formed of a square steel pipe as shown in FIG. 2, and when the reinforcing member 2 is fitted on the outside of the steel pipe column 1, the inner peripheral wall of the reinforcing member 2 is attached to the outer peripheral wall of the steel pipe column 1. Face to face. A plurality of through holes 20 corresponding to the fastening holes 10 are formed in the inner peripheral wall of the reinforcing member 2.

【0013】図中、符号3で指示するものは上記鋼管柱
1の各止着孔10に進退可能に挿着され、鋼管柱1と補強
部材2とを固定するための固定部材であり、図3に示す
ように、軸心に右ねじのネジ孔30を備えた筒体を成して
おり、その後端側には鋼管柱1の内面に当接可能な鍔部
31が形成されていると共に、先端側には補強部材2の内
面に当接可能な当接部32が形成されている。なお、本実
施形態の固定部材3の鍔部31の外周には、後述の挿着治
具6のワーク保持フレーム63に螺着セットするための左
ねじの雄ネジ31aが刻設されている。
In the figure, reference numeral 3 designates a fixing member which is inserted into each of the fastening holes 10 of the steel pipe column 1 so as to be able to advance and retreat, and fixes the steel pipe column 1 and the reinforcing member 2. As shown in FIG. 3, a cylindrical body having a screw hole 30 with a right-hand thread at the axis thereof is formed, and a rear end of the cylindrical body is capable of abutting against the inner surface of the steel pipe column 1.
A contact portion 32 is formed on the distal end side of the reinforcing member 2 so as to contact the inner surface of the reinforcing member 2. In addition, on the outer periphery of the flange portion 31 of the fixing member 3 of the present embodiment, a left-handed male screw 31a for screwing and setting the work holding frame 63 of the insertion jig 6 described later is engraved.

【0014】また、本実施形態の固定部材3の外周に
は、図4に示すように、上記鋼管柱1の止着孔10の雌ネ
ジ11に螺合可能な左ねじの雄ネジ33が刻設されていると
共に、当接部32の先端部には、補強部材2の通孔20に嵌
合可能な嵌合突起35が設けられており、更にこの嵌合突
起35の先端にはナット部34が凹設されている。このナッ
ト部34に六角レンチを差し込んで固定部材3を回動させ
れば、止着孔10に挿着された固定部材3を軸方向へ進退
動させることが可能なのである。なお、図5中、符号36
で指示するものは、必要に応じて鍔部31と鋼管柱1との
間に介在させるスペーサである。
As shown in FIG. 4, on the outer periphery of the fixing member 3 of the present embodiment, a left-handed male screw 33 capable of being screwed into the female screw 11 of the fastening hole 10 of the steel pipe column 1 is formed. A fitting projection 35 is provided at the tip of the contact portion 32 so as to fit into the through hole 20 of the reinforcing member 2. 34 is recessed. If the fixing member 3 is rotated by inserting a hexagon wrench into the nut portion 34, the fixing member 3 inserted into the fastening hole 10 can be moved forward and backward in the axial direction. Note that, in FIG.
What is indicated by is a spacer interposed between the flange 31 and the steel pipe column 1 as necessary.

【0015】図中、符号4で指示するものは、上記固定
部材3のネジ孔30に対し固定部材3の外側から螺合可能
な右ねじの高力ボルトであり、符号40で指示するものは
ワッシャーである。
In the figure, what is indicated by reference numeral 4 is a right-handed high-strength bolt which can be screwed into the screw hole 30 of the fixing member 3 from the outside of the fixing member 3, and what is indicated by reference numeral 40 is Washer.

【0016】しかして、本実施形態の鋼管柱の接合構造
にあっては、まず、図3及び図4に示すように、固定部
材挿着治具6を使用して鋼管柱1の各止着孔10に内側か
ら固定部材3を挿着する。即ち、この挿着治具6は、車
輪64・64…を備えた上下一対のワーク保持フレーム63・
63と、このワーク保持フレーム63・63間に配設され、ハ
ンドル60でネジ軸61を回すことにより当該ワーク保持フ
レーム63・63の間隔を拡縮するパンダグラフ機構62・62
とから構成されており、このワーク保持フレーム63・63
の所定位置に、固定部材3がその雄ネジ31a部分で螺着
されている。図中、符号65で指示するものは、パンダグ
ラフ機構62・62によって間隔が同期的に拡縮する一対の
ガイドプレートであり、各ガイドプレート65にはガイド
ボール66・66…が配設されている。
In the joint structure of the steel pipe column according to the present embodiment, first, as shown in FIGS. 3 and 4, each fixing of the steel pipe column 1 using the fixing member insertion jig 6 is performed. The fixing member 3 is inserted into the hole 10 from the inside. That is, the insertion jig 6 includes a pair of upper and lower work holding frames 63.
A pandagraph mechanism 62 is provided between the work holding frames 63 and 63 and expands and contracts the intervals between the work holding frames 63 and 63 by turning the screw shaft 61 with the handle 60.
This work holding frame 63
The fixing member 3 is screwed at a predetermined position with a male screw 31a. In the figure, what is indicated by reference numeral 65 is a pair of guide plates whose intervals are synchronously enlarged and reduced by a pandagraph mechanism 62, and guide balls 66 are provided on each guide plate 65. .

【0017】図3に示すように、この挿着治具6を鋼管
柱1内へ挿入し、図4に示すように螺着した固定部材3
・3…と鋼管柱1の止着孔10とを位置合わせした後、ハ
ンドル60を回して上下のワーク保持フレーム63・63の間
隔を拡げ、そして、鋼管柱1の外側から各固定部材3の
ナット部34へ六角レンチを差し込んで回転させることに
より当該固定部材3を鋼管柱1の止着孔10に内側から挿
着するのである(図5参照)。なお、本実施形態では、
レンチで固定部材3を回転させたとき、ワーク保持フレ
ーム63から固定部材3が外れる前に、固定部材3の雄ネ
ジ33が鋼管柱1の止着孔10の雌ネジ11に螺合するように
構成されており、この固定部材の挿着作業時に各固定部
材3が脱落してしまうことはない。
As shown in FIG. 3, the fixing jig 6 is inserted into the steel pipe column 1 and screwed as shown in FIG.
After aligning 3 with the fastening hole 10 of the steel pipe post 1, turn the handle 60 to widen the space between the upper and lower work holding frames 63, 63, The fixing member 3 is inserted into the fixing hole 10 of the steel pipe column 1 from inside by rotating a hexagon wrench into the nut portion 34 (see FIG. 5). In the present embodiment,
When the fixing member 3 is rotated with a wrench, the male screw 33 of the fixing member 3 is screwed into the female screw 11 of the fastening hole 10 of the steel pipe column 1 before the fixing member 3 comes off from the work holding frame 63. The fixing members 3 do not fall off during the work of inserting the fixing members.

【0018】次に、図5に示すように、鋼管柱1の止着
孔10に内側から挿着した固定部材3を後退させておいた
状態で、鋼管柱1の外側に補強部材2を被嵌し、鋼管柱
1の止着孔10と補強部材2の通孔20とを位置合わせした
後、補強部材2の外側からレンチWを固定部材3のナッ
ト部34に差し込んで固定部材3を回転させ、固定部材3
を補強部材2へ向けて前進させる。そして、図6に示す
ように、固定部材3の鍔部31をスペーサ36を介して鋼管
柱1の内面に当接させると共に嵌合突起35を補強部材2
の通孔20内に嵌合させて当接部32を補強部材2の内面に
当接させることにより、補強部材2を鋼管柱1の梁接合
部位に固定する。なお、鋼管柱1における直交する他の
内面も、同様に固定するものとする。
Next, as shown in FIG. 5, with the fixing member 3 inserted from the inside into the fixing hole 10 of the steel pipe column 1 being retracted, the reinforcing member 2 is covered on the outside of the steel pipe column 1. After the fitting, the fixing hole 10 of the steel pipe column 1 and the through hole 20 of the reinforcing member 2 are aligned, a wrench W is inserted into the nut portion 34 of the fixing member 3 from outside the reinforcing member 2 to rotate the fixing member 3. And fixing member 3
Is advanced toward the reinforcing member 2. Then, as shown in FIG. 6, the flange 31 of the fixing member 3 is brought into contact with the inner surface of the steel pipe column 1 via the spacer 36, and the fitting projection 35 is connected to the reinforcing member 2
The reinforcing member 2 is fixed to the beam joint portion of the steel pipe column 1 by fitting the contact portion 32 into the inner surface of the reinforcing member 2 by fitting into the through hole 20. The other orthogonal inner surfaces of the steel pipe column 1 are also fixed similarly.

【0019】然る後、図7に示すように、補強部材2の
通孔20・20…に鉄骨梁Bの端部のエンドプレートのボル
ト孔bを合わせて、このエンドプレートの外側から高力
ボルト4を固定部材3のネジ孔30に螺合させ締結するこ
とによって、鋼管柱1と鉄骨梁Bとを確実にボルト接合
するのである(図8参照)。
Thereafter, as shown in FIG. 7, the through holes 20, 20... Of the reinforcing member 2 are aligned with the bolt holes b of the end plate at the end of the steel beam B, and a high force is applied from outside the end plate. By screwing the bolt 4 into the screw hole 30 of the fixing member 3 and fastening it, the steel pipe column 1 and the steel beam B are securely bolted (see FIG. 8).

【0020】このように、本実施形態の鋼管柱の接合構
造にあっては、補強部材2を鋼管柱1の外側に被嵌する
際、止着孔10に挿着した固定部材3を後退させておくこ
とができるので、頗る簡単に補強部材2を鋼管柱1に被
嵌し、所定の梁接合部位に位置させることができる。従
来のように、鋼管柱内に補強部材を圧入するなどの多大
な労力を要する作業を行なう必要がないのである。
As described above, in the joint structure of the steel pipe column of the present embodiment, when the reinforcing member 2 is fitted to the outside of the steel pipe column 1, the fixing member 3 inserted into the fastening hole 10 is retracted. Therefore, the reinforcing member 2 can be fitted on the steel pipe column 1 very easily and positioned at a predetermined beam joining portion. It is not necessary to perform an operation requiring a large amount of labor such as press-fitting a reinforcing member into a steel pipe column as in the related art.

【0021】しかも、本実施形態の鋼管柱の接合構造
は、補強部材2の外側から行なう回転操作だけで簡単に
止着孔10に挿着した固定部材3を前進させることがで
き、固定部材3の鍔部31及び当接部32の圧接、並びに嵌
合突起35の嵌合を利用して補強部材2を正確かつ確実に
鋼管柱1に固定することができるので、従来のように、
補強部材を固定するために溶接作業を行う必要もなく、
また、補強部材をボルト止めするために強度を犠牲にし
て鋼管柱に開口部を設ける必要もない。
Moreover, the joint structure of the steel pipe columns of the present embodiment allows the fixing member 3 inserted into the fastening hole 10 to be easily advanced only by the rotation operation performed from outside the reinforcing member 2. The reinforcing member 2 can be accurately and reliably fixed to the steel pipe column 1 by utilizing the press-contact of the flange portion 31 and the contact portion 32 and the fitting of the fitting protrusion 35.
There is no need to perform welding work to fix the reinforcing member,
Also, there is no need to provide an opening in the steel pipe column at the expense of strength for bolting the reinforcing member.

【0022】また、本実施形態の鋼管柱の接合構造は、
鋼管柱1の外側に固定した補強部材2を利用して鉄骨梁
Bを接合する際にも、補強部材2の外側から高力ボルト
4を固定部材3のネジ孔30に螺合させるだけで、頗る簡
単に鉄骨梁Bを接合することができるので、従来のよう
に、高価なワンサイドボルトを使用する必要もなく、ま
た、鋼管柱の内側でボルトを保持するための開口部を鋼
管柱に開設して強度の低下を招くこともない。
Further, the joint structure of the steel pipe column of this embodiment is as follows.
When the steel beam B is joined using the reinforcing member 2 fixed to the outside of the steel pipe column 1, only by screwing the high-strength bolt 4 into the screw hole 30 of the fixing member 3 from the outside of the reinforcing member 2, Since the steel beam B can be joined very easily, there is no need to use expensive one-side bolts as in the past, and the opening for holding the bolt inside the steel pipe column is made in the steel column. Opening does not cause a decrease in strength.

【0023】更にまた、本実施形態では、鋼管柱1の止
着孔10に固定部材3を挿着しておく際、固定部材挿着治
具6を利用しているので、省力的に且つ安全に固定部材
3の挿着作業を行うことができる。
Furthermore, in the present embodiment, when the fixing member 3 is inserted into the fixing hole 10 of the steel pipe column 1, the fixing member insertion jig 6 is used, so that labor is saved and safety is achieved. The fixing work of the fixing member 3 can be performed.

【0024】本発明の具体例である第一実施形態は概ね
上記のように構成されているが、本発明はこの実施形態
に限定されるものではなく「特許請求の範囲」の記載内
において種々の変更が可能である。例えば、上記実施形
態では、予め端部に接合金物としてエンドプレートが溶
接された鉄骨梁Bを鋼管柱1に接合しているが、決して
これに限定されるものではなく、予め端部にT形接合金
物がボルト接合された鉄骨梁Bを鋼管柱1に接合するこ
とも勿論可能である。
The first embodiment, which is a specific example of the present invention, is generally configured as described above. However, the present invention is not limited to this embodiment, and various modifications may be made within the description of the appended claims. Can be changed. For example, in the above-described embodiment, the steel beam B to which the end plate is welded in advance to the end portion as a metal fitting is joined to the steel pipe column 1, but the present invention is not limited to this. Of course, it is also possible to join the steel beam B to which the joining hardware is bolted to the steel pipe column 1.

【0025】『第二実施形態』 本実施形態の鋼管柱の接合構造は、図9〜図16に示すよ
うに鋼管柱1とH形鋼製の鉄骨梁Bとをトルシア型高力
ボルト5を利用して接合する点に特徴があり、補強部材
2及び固定部材3の構成は上述した第一実施形態とほぼ
同じである。
[Second Embodiment] The joint structure of a steel pipe column according to the present embodiment, as shown in FIG. 9 to FIG. It is characterized in that it is used and joined, and the configurations of the reinforcing member 2 and the fixing member 3 are almost the same as those in the first embodiment.

【0026】即ち、本実施形態では、鋼管柱1の止着孔
10には右ねじの雌ネジ11が刻設されており、固定部材3
の外周にこの雌ネジ11に螺合可能な右ねじの雄ネジ33が
刻設されていると共に、固定部材3の軸心には右ねじの
ネジ孔30が形成されている。そして、本実施形態のトル
シア型高力ボルト5は、図11に示すように、先端にナッ
ト部51が形成された破断ピンテール50を備えており、こ
のトルシア型高力ボルト5が予め、固定部材3の右ねじ
に刻設されたネジ孔30にその内側から螺着されている。
That is, in the present embodiment, the fastening hole of the steel pipe column 1
10 is provided with a female screw 11 of a right-hand thread.
A right-handed male screw 33 that can be screwed into the female screw 11 is engraved on the outer periphery of the fixed member 3, and a right-handed screw hole 30 is formed in the axis of the fixing member 3. As shown in FIG. 11, the torcia-type high-strength bolt 5 of the present embodiment includes a break pin tail 50 having a nut portion 51 formed at a tip thereof. 3 is screwed into the screw hole 30 formed in the right screw from the inside.

【0027】しかして、本実施形態の鋼管柱の接合構造
にあっては、上述した第一実施形態と同様に固定部材挿
着治具6を利用して鋼管柱1の止着孔10に内側から挿着
した固定部材3を後退させた状態で、図11に示すよう
に、鋼管柱1の外側に補強部材2を被嵌し、鋼管柱1の
止着孔10と補強部材2の通孔20とを位置合わせした後、
補強部材2の外側から六角レンチWを固定部材3のナッ
ト部34に差し込んで固定部材3を回転させ、固定部材3
を補強部材2へ向けて前進させる。そして、図12に示す
ように、固定部材3の鍔部31をスペーサ36を介して鋼管
柱1の内面に当接させると共に嵌合突起35を補強部材2
の通孔20内に嵌合させて当接部32を補強部材2の内面に
当接させることによって、補強部材2を鋼管柱1の梁接
合部位に固定する。
However, in the joint structure of the steel pipe column of the present embodiment, the fixing member insertion jig 6 is used to inwardly engage the fastening hole 10 of the steel pipe column 1 as in the first embodiment described above. 11, the reinforcing member 2 is fitted to the outside of the steel pipe column 1 as shown in FIG. 11, and the fixing hole 10 of the steel pipe column 1 and the through hole of the reinforcing member 2 are inserted as shown in FIG. After aligning with 20,
A hexagon wrench W is inserted into the nut portion 34 of the fixing member 3 from outside the reinforcing member 2 to rotate the fixing member 3, and the fixing member 3 is rotated.
Is advanced toward the reinforcing member 2. Then, as shown in FIG. 12, the flange 31 of the fixing member 3 is brought into contact with the inner surface of the steel pipe column 1 via the spacer 36, and the fitting projection 35 is connected to the reinforcing member 2
The reinforcing member 2 is fixed to the beam joint portion of the steel pipe column 1 by fitting the contact portion 32 into the inner surface of the reinforcing member 2 by fitting into the through hole 20.

【0028】次いで、図13に示すように、鉄骨梁Bをク
レーン等で吊り上げて補強部材2の通孔20と鉄骨梁Bの
端部のエンドプレートのボルト孔bとを位置合わせした
後、固定部材3のネジ孔30に螺着されているトルシア型
高力ボルト5の破断ピンテール50のナット部51に、鉄骨
梁Bのエンドプレートの外側から六角レンチXを差し込
んでトルシア型高力ボルト5を回転させることによっ
て、図14に示すように、トルシア型高力ボルト5を鉄骨
梁Bのエンドプレートの外側へ突出させる。すると、こ
のとき固定部材3のネジ孔30とトルシア型高力ボルト5
との掛合が外れて当該トルシア型高力ボルトは空回りす
ることになり、鉄骨梁Bから突出たボルトはバックしな
いようになる。
Next, as shown in FIG. 13, the steel beam B is lifted by a crane or the like, and the through hole 20 of the reinforcing member 2 is aligned with the bolt hole b of the end plate at the end of the steel beam B, and then fixed. A hexagon wrench X is inserted from the outside of the end plate of the steel beam B into the nut portion 51 of the break pin tail 50 of the torcia-type high-strength bolt 5 screwed into the screw hole 30 of the member 3 to insert the torcia-type high-strength bolt 5. By rotating, the torcia-type high-strength bolt 5 is projected outside the end plate of the steel beam B as shown in FIG. Then, at this time, the screw hole 30 of the fixing member 3 and the torcia-type high-strength bolt 5
And the torcia-type high-strength bolt turns idle, and the bolt protruding from the steel beam B does not back.

【0029】然る後、図15に示すように、トルシア型高
力ボルト5にワッシャー53及びナット52を螺合し、鉄骨
梁Bのエンドプレートの外側からトルシア型高力ボルト
専用レンチYのインナーソケットy1 で破断ピンテール
50を保持固定しながら、アウターソケットy2 でナット
52を回し、破断ピンテール50が破断するまで締め付ける
ことによって、鋼管柱1と鉄骨梁Bとを確実にボルト接
合するのである(図16参照)。
Thereafter, as shown in FIG. 15, a washer 53 and a nut 52 are screwed onto the torcia-type high-strength bolt 5, and the inner side of the wrench Y for torcia-type high-strength bolt is inserted from outside the end plate of the steel beam B. break in the socket y 1 pintail
While maintaining a fixed 50, nut outer socket y 2
The steel pipe column 1 and the steel beam B are securely bolted to each other by turning the screw 52 and tightening it until the break pin tail 50 breaks (see FIG. 16).

【0030】このように、本実施形態の鋼管柱の接合構
造にあっては、第一実施形態における高力ボルト4の代
わりに、所定の締付けトルクでピンテール50が破断する
トルシア型高力ボルト5を採用しているので、従来の高
力ボルトのように電動レンチのトルク調整や締付け後の
トルク検査を行う必要がなく、現場の施工管理が容易に
なり、鋼管柱1と鉄骨梁Bとの接合作業をより省力化で
きるのである。
As described above, in the joint structure of steel pipe columns according to the present embodiment, instead of the high-strength bolt 4 in the first embodiment, a torcia-type high-strength bolt 5 whose pin tail 50 is broken by a predetermined tightening torque is used. Since there is no need to adjust the torque of the electric wrench or perform a torque test after tightening unlike conventional high-strength bolts, the construction management on site becomes easy, and the steel pipe column 1 and steel beam B The joining work can be saved more.

【0031】『第三実施形態』 本実施形態の鋼管柱の接合構造は、図17に示すように、
鋼管柱1と他の鋼管柱1′とを高力ボルト4で突合せ接
合するものであり、補強部材2及び固定部材3の構成は
上述した第一実施形態と同様である。
[Third Embodiment] The joint structure of a steel pipe column of the present embodiment is as shown in FIG.
The steel pipe column 1 and another steel pipe column 1 ′ are butt-joined with high-strength bolts 4, and the configurations of the reinforcing member 2 and the fixing member 3 are the same as those in the above-described first embodiment.

【0032】即ち、本実施形態では、下側の鋼管柱1の
上部に複数の止着孔10・10…が開設されている一方、上
側の鋼管柱1′の下部にも複数の止着孔10・10…が開設
されており、補強部材2はこれら鋼管柱1・1′の外側
にそれぞれ半分ずつ被嵌されるのである。
That is, in the present embodiment, a plurality of fastening holes 10, 10... Are formed in the upper part of the lower steel pipe column 1, while a plurality of fastening holes are also formed in the lower part of the upper steel column 1 '. .., And the reinforcing member 2 is fitted in half each on the outside of the steel tube column 1.1 ′.

【0033】しかして、本実施形態の鋼管柱の接合構造
にあっては、予め工場内において、上述した固定部材挿
着治具により止着孔10に挿着された全ての固定部材3を
後退させた状態の下側の鋼管柱1の外側に補強部材2を
途中まで被嵌し、この下側の鋼管柱1の止着孔10と補強
部材2の下半分の通孔20とを位置合わせした後、補強部
材2の外側から六角レンチを用いて下半分の止着孔10の
固定部材3を回転させて前進させ、当該固定部材3の鍔
部31を鋼管柱1の内面に当接させると共に嵌合突起35を
補強部材2の通孔20内に嵌合させて当接部32を補強部材
2の内面に当接させ、そして、補強部材2の外側から高
力ボルト4・4…を固定部材3のネジ孔30に螺合させて
締結することにより、補強部材2を鋼管柱1の突合せ端
部に固定する。
In the joint structure of steel pipe columns according to the present embodiment, all the fixing members 3 previously inserted into the fixing holes 10 by the above-mentioned fixing member insertion jig are retracted in the factory. The reinforcing member 2 is fitted halfway to the outside of the lower steel pipe column 1 in a state where the lower steel pipe column 1 is in a state where the fastening hole 10 of the lower steel pipe column 1 is aligned with the through hole 20 of the lower half of the reinforcing member 2. After that, the fixing member 3 of the lower fixing hole 10 is rotated forward from the outside of the reinforcing member 2 using a hexagon wrench, and the flange 31 of the fixing member 3 is brought into contact with the inner surface of the steel pipe column 1. And the fitting projection 35 is fitted into the through hole 20 of the reinforcing member 2 to bring the contact portion 32 into contact with the inner surface of the reinforcing member 2, and the high-strength bolts 4. The reinforcing member 2 is fixed to the abutting end of the steel pipe column 1 by screwing and fastening to the screw hole 30 of the fixing member 3.

【0034】次いで、補強部材2を固定した鋼管柱1を
現場に建て込んだ後、この補強部材2の上部に、突合せ
接合すべき上側の鋼管柱1′を挿入し、この鋼管柱1′
の止着孔10と補強部材2の上半分の通孔20とを位置合わ
せした後、補強部材2の外側から六角レンチを用いて上
側の鋼管柱1′の止着孔10の固定部材3を回転させて前
進させ、当該固定部材3の鍔部31を鋼管柱1′の内面に
当接させると共に嵌合突起35を補強部材2の上側の通孔
20内に嵌合させて当接部32を補強部材2の内面に当接さ
せ、然る後、補強部材2の外側から高力ボルト4・4…
を固定部材3のネジ孔30に螺合させて締結することによ
り、補強部材2と上側の鋼管柱1′の突合せ端部とを固
定し、これら鋼管柱1・1′を確実に突合せ接合するの
である。
Next, after the steel column 1 to which the reinforcing member 2 is fixed is erected on the site, the upper steel column 1 'to be butt-joined is inserted into the upper part of the reinforcing member 2, and the steel column 1' is inserted.
After aligning the fixing hole 10 of the reinforcing member 2 with the through hole 20 of the upper half of the reinforcing member 2, the fixing member 3 of the fixing hole 10 of the upper steel pipe column 1 'is removed from the outside of the reinforcing member 2 using a hexagon wrench. By rotating and moving forward, the flange 31 of the fixed member 3 is brought into contact with the inner surface of the steel pipe column 1 ′, and the fitting projection 35 is inserted into the upper hole of the reinforcing member 2.
20 so that the abutting portion 32 abuts against the inner surface of the reinforcing member 2, and then the high-strength bolts 4.
Is screwed into the screw hole 30 of the fixing member 3 and fastened, thereby fixing the reinforcing member 2 and the butted end of the upper steel pipe column 1 ', and securely joining these steel pipe columns 1.1'. It is.

【0035】このように、本実施形態の鋼管柱の接合構
造にあっては、補強部材2を鋼管柱1・1′の外側に被
嵌する際、止着孔10に挿着した固定部材3を後退させて
おくことができるので、頗る簡単に補強部材2を鋼管柱
1・1′に被嵌して、突合せ接合部位に位置させること
ができ、しかも、補強部材2の外側から行う回転操作だ
けで簡単に固定部材3を前進させ、固定部材3の鍔部31
及び当接部32の圧接、並びに嵌合突起35の嵌合を利用し
て補強部材2を正確かつ確実に鋼管柱1・1′に固定す
ることができるので、従来のように補強部材を固定する
ために溶接作業を行なう必要もなく、また、補強部材を
ボルト止めするために鋼管強度を犠牲にして鋼管柱に開
口部を設ける必要もないのである。
As described above, when the reinforcing member 2 is fitted to the outside of the steel pipe columns 1 and 1 'in the joint structure of the steel pipe columns of the present embodiment, the fixing member 3 inserted into the fastening hole 10 is used. Can be retracted, so that the reinforcing member 2 can be very easily fitted on the steel pipe pillars 1 and 1 ′ and positioned at the butt joint portion, and furthermore, the rotation operation performed from the outside of the reinforcing member 2 can be performed. The fixing member 3 is easily moved forward only by the
The reinforcing member 2 can be accurately and reliably fixed to the steel pipe columns 1 and 1 'by utilizing the pressure contact of the contact portion 32 and the fitting of the fitting protrusion 35. Therefore, it is not necessary to perform a welding operation in order to perform the welding, and it is not necessary to provide an opening in the steel pipe column at the expense of steel pipe strength for bolting the reinforcing member.

【0036】また、この補強部材2を利用して鋼管柱1
・1′同士を突合せ接合する際にも補強部材2の外側か
ら高力ボルト4を固定部材3のネジ孔30に螺合させるだ
けで頗る簡単に接合することができるので、従来のよう
に、高価なワンサイドボルトを使用する必要もなく、ま
た、鋼管柱の内側でボルトを保持するための開口部を鋼
管柱に開設して強度の低下を招くこともないのである。
Further, the steel pipe column 1 is made utilizing this reinforcing member 2.
When joining the 1's by butt joining, the high strength bolts 4 can be joined very simply by screwing the high strength bolts 4 into the screw holes 30 of the fixing member 3 from the outside of the reinforcing member 2. There is no need to use expensive one-side bolts, and there is no opening in the steel tube post to hold the bolt inside the steel tube post, which does not reduce the strength.

【0037】本発明の具体例である第三実施形態は概ね
上記のように構成されているが、本発明はこの実施形態
に限定されるものではなく「特許請求の範囲」の記載内
において種々の変更が可能であり、例えば、上記実施形
態では、高力ボルト4を固定部材3のネジ孔30に螺合し
て突合せ接合しているが、上述した第二実施形態のよう
に、この高力ボルト4の代わりに、トルシア型高力ボル
トを採用して突合せ接合することも勿論可能である。
The third embodiment, which is a specific example of the present invention, is generally configured as described above. However, the present invention is not limited to this embodiment, and various modifications may be made within the scope of the claims. For example, in the above-described embodiment, the high-strength bolt 4 is screwed into the screw hole 30 of the fixing member 3 and butt-joined. Instead of the force bolt 4, it is of course possible to employ a torsion-type high-strength bolt and butt-join.

【0038】『第四実施形態』 本実施形態の鋼管柱の接合構造は、図18に示すように、
鋼管柱1の下端部に柱脚部材Cを高力ボルト4を利用し
て接合するものであり、固定部材3の構成は上述した第
一実施形態と同様である。
"Fourth Embodiment" The joint structure of a steel pipe column of the present embodiment, as shown in FIG.
The column base member C is joined to the lower end portion of the steel pipe column 1 by using a high-strength bolt 4, and the configuration of the fixing member 3 is the same as that of the above-described first embodiment.

【0039】即ち、本実施形態では、鋼管柱1の下端部
に複数の止着孔10・10…が開設されている一方、補強部
材2は、その上部が鋼管柱1の下端部に被嵌可能である
と共に鋼管柱1の止着孔10に対向する位置に通孔20が開
設されており、その下部が柱脚部材Cに固定されてい
る。本実施形態では、これら補強部材2と柱脚部材Cと
は一体に成形されている。
That is, in the present embodiment, a plurality of fastening holes 10 are formed at the lower end of the steel pipe column 1, while the upper portion of the reinforcing member 2 is fitted to the lower end of the steel pipe column 1. A through hole 20 is formed at a position opposite to the fastening hole 10 of the steel pipe column 1, and a lower portion thereof is fixed to the column base member C. In the present embodiment, the reinforcing member 2 and the column base member C are integrally formed.

【0040】しかして、本実施形態の鋼管柱の接合構造
にあっては、予め工場内において、上述した固定部材挿
着治具により止着孔10に挿着された固定部材3を後退さ
せた状態の鋼管柱1の外側に補強部材2を被嵌し、この
鋼管柱1の止着孔10と補強部材2の通孔20とを位置合わ
せした後、補強部材2の外側から六角レンチを用いて止
着孔10の固定部材3を回転させて前進させ、当該固定部
材3の鍔部31を鋼管柱1の内面に当接させると共に嵌合
突起35を補強部材2の通孔20内に嵌合させて当接部32を
補強部材2の内面に当接させることにより、補強部材2
を鋼管柱1の下端部に固定する。
In the joint structure of the steel pipe columns according to the present embodiment, the fixing member 3 previously inserted into the fixing hole 10 by the above-described fixing member insertion jig is retracted in the factory. The reinforcing member 2 is fitted to the outside of the steel pipe column 1 in the state, and the fixing hole 10 of the steel pipe column 1 and the through hole 20 of the reinforcing member 2 are aligned. Then, a hexagon wrench is used from the outside of the reinforcing member 2. The fixing member 3 of the fastening hole 10 is rotated and moved forward to bring the flange 31 of the fixing member 3 into contact with the inner surface of the steel pipe column 1 and the fitting projection 35 is fitted into the through hole 20 of the reinforcing member 2. By bringing the contact portion 32 into contact with the inner surface of the reinforcing member 2,
Is fixed to the lower end of the steel pipe column 1.

【0041】然る後、図18に示すように、補強部材2の
外側から高力ボルト4・4…を固定部材3のネジ孔30に
螺合させて締結することによって、鋼管柱1の下端部に
柱脚部材Cを確実に接合する。そして、現場でアンカー
Aにて柱脚部材Cを基礎に固定するのである。
After that, as shown in FIG. 18, the high-strength bolts 4 are screwed into the screw holes 30 of the fixing member 3 from the outside of the reinforcing member 2 and fastened. The column base member C is securely joined to the portion. Then, the column base member C is fixed to the foundation with the anchor A at the site.

【0042】このように、本実施形態の鋼管柱の接合構
造においても、補強部材2を鋼管柱1に被嵌する際、止
着孔10に挿着した固定部材3を後退させておくことがで
きるので、頗る簡単に補強部材2を鋼管柱1に被嵌する
ことができ、しかも、補強部材2の外側から行う回転操
作だけで簡単に固定部材3を前進させて固定部材3の鍔
部31及び当接部32の圧接、並びに嵌合突起35の嵌合を利
用して補強部材2を正確かつ確実に鋼管柱1に固定する
ことができるので、従来のように、補強部材を固定する
ために溶接作業を行う必要もなく、また、補強部材をボ
ルト止めするために鋼管強度を犠牲にして鋼管柱に開口
部を設ける必要もないのである。
As described above, also in the joint structure of steel pipe columns of the present embodiment, when the reinforcing member 2 is fitted to the steel pipe column 1, the fixing member 3 inserted into the fixing hole 10 may be retracted. Therefore, the reinforcing member 2 can be fitted to the steel pipe column 1 very easily, and the fixing member 3 can be easily advanced by the rotation operation performed from the outside of the reinforcing member 2 so that the flange 31 of the fixing member 3 can be formed. Since the reinforcing member 2 can be accurately and reliably fixed to the steel pipe column 1 by utilizing the pressure contact of the contact portion 32 and the fitting of the fitting protrusion 35, the reinforcing member is fixed as in the related art. In addition, there is no need to perform welding work, and it is not necessary to provide an opening in the steel pipe column at the expense of steel pipe strength for bolting the reinforcing member.

【0043】また、この補強部材2を利用して柱脚部材
Cと鋼管柱1とを接合する際にも、補強部材2の外側か
ら高力ボルト4を固定部材3のネジ孔30に螺合させるだ
けで頗る簡単に接合することができるので、従来のよう
に、高価なワンサイドボルトを使用する必要もなく、ま
た、鋼管柱の内側でボルトを保持するための開口部を鋼
管柱に開設して強度の低下を招くこともない。
Also, when joining the column base member C and the steel pipe column 1 using the reinforcing member 2, the high-strength bolt 4 is screwed into the screw hole 30 of the fixing member 3 from outside the reinforcing member 2. It is very easy to join just by making it unnecessary, so there is no need to use expensive one-side bolts as before, and an opening for holding the bolt inside the steel pipe column is opened in the steel pipe column Therefore, the strength does not decrease.

【0044】『第五実施形態』 本発明の第五実施形態は、図19と図20に示すように、鋼
管柱1に対し、端部に雄ネジsを形成した鉄筋Rを接合
する鋼管柱と鉄筋との接合構造として本発明を具現した
ものである。つまり、本実施形態の鋼管柱の接合構造
は、図19および20に示す如く、鋼管柱1と鉄筋コンクリ
ート梁の鉄筋Rとを接合するものであり、補強部材2お
よび固定部材3の更正は前述の第一実施形態と同じであ
る。
[Fifth Embodiment] In a fifth embodiment of the present invention, as shown in FIGS. 19 and 20, a steel pipe column 1 is joined to a steel pipe column 1 with a reinforcing bar R having an external thread s formed at an end. The present invention is embodied as a joint structure between a steel and a reinforcing bar. That is, as shown in FIGS. 19 and 20, the joint structure of the steel pipe column according to the present embodiment joins the steel pipe column 1 and the reinforcing steel R of the reinforced concrete beam. This is the same as the first embodiment.

【0045】即ち、本実施形態では、接合すべき主筋た
る鉄筋Rに雄ネジSが切ってあり、この雄ネジSを固定
部材3の雌ネジ30に螺合させて鋼管柱1の所定位置に直
接鉄筋Rが接合される。なお、図中の符号Tで指示する
ものは、鋼管柱1に主筋の鉄筋Rが接合された後、当該
鉄筋Rに巻回された帯筋である。また、符号Uで指示す
るものは鋼管柱1中に充填され、かつ、梁部を構成する
コンクリートである。なお、符号Nは固定ナット、符号
Jは鉄筋接続用カプラーである。
That is, in the present embodiment, a male screw S is cut in the reinforcing bar R which is the main bar to be joined, and this male screw S is screwed into the female screw 30 of the fixing member 3 so as to be positioned at a predetermined position of the steel pipe column 1. The rebar R is directly joined. In addition, what is indicated by the reference numeral T in the figure is a band reinforcing wire wound around the reinforcing steel bar R after the main reinforcing steel bar R is joined to the steel pipe column 1. Also, what is indicated by the reference numeral U is concrete that is filled in the steel pipe column 1 and that forms the beam. In addition, the code | symbol N is a fixing nut and the code | symbol J is a coupler for rebar connection.

【0046】しかして、本実施形態における鋼管柱の接
合構造にあっては、前述の第一実施形態と同様に予め鋼
管柱1の止着孔10に固定部材3を後退させた状態で仮嵌
めしておく一方、鋼管柱の外側に補強部材2を被嵌さ
せ、鋼管柱1の止着孔10と補強部材2の通孔20とを位置
合わせして、前記補強部材2の外側から六角レンチ等の
手段を用いて止着孔10の固定部材3を回転させて前進さ
せ、当該固定部材3の鍔部31を鋼管柱1の内面に当接さ
せると共に嵌合突起35を補強部材2の通孔20に嵌合さ
せ、当接部材32を補強部材2の内面に当接させることに
よって補強部材2を鋼管柱1の鉄筋接合位置に固定せし
める。
However, in the joint structure of the steel pipe column according to the present embodiment, the fixing member 3 is temporarily fitted to the fastening hole 10 of the steel pipe column 1 in advance in the same manner as in the first embodiment described above. On the other hand, the reinforcing member 2 is fitted to the outside of the steel pipe column, the fixing hole 10 of the steel pipe column 1 and the through hole 20 of the reinforcing member 2 are aligned, and a hexagon wrench is provided from outside the reinforcing member 2. The fixing member 3 of the fastening hole 10 is rotated and advanced by using such means as described above, and the flange 31 of the fixing member 3 is brought into contact with the inner surface of the steel pipe column 1 and the fitting protrusion 35 is inserted through the reinforcing member 2. The reinforcing member 2 is fixed to the steel pipe column 1 at the reinforcing bar joining position by fitting it into the hole 20 and bringing the contact member 32 into contact with the inner surface of the reinforcing member 2.

【0047】しかる後、図20に示すように、固定部材3
のネジ孔30に鉄筋Rの雄ネジSを螺合させることによっ
て、鋼管柱1と鉄筋Rとの接合が成されるのである。
Thereafter, as shown in FIG.
By screwing the male screw S of the reinforcing rod R into the screw hole 30 of the steel pipe R, the steel pipe column 1 and the reinforcing rod R are joined.

【0048】このように、本実施形態の鋼管柱の接合構
造においても、補強部材2を鋼管柱1に被嵌させる際に
挿着治具6を使用することによって、頗る簡単かつ迅速
に鋼管柱1の止着孔10に固定部材3を挿入することが可
能になる。しかも、補強部材2の外側から行う回転操作
だけで固定部材3を前進させて固定部材3の鍔部31およ
び当接部材32の圧接、並びに嵌合突起35を嵌合を利用し
て補強部材2を正確かつ確実に鋼管柱1に被嵌固定する
ことができるので、従来のごとく補強部材を固定するた
めの面倒な溶接作業も不要となり、また、補強部材をボ
ルト止めするために鋼管強度を犠牲にして開口部を空け
る必要もなくなるのである。
As described above, also in the joint structure of the steel pipe column of the present embodiment, by using the insertion jig 6 when the reinforcing member 2 is fitted to the steel pipe column 1, the steel pipe column can be very simply and quickly. The fixing member 3 can be inserted into the one fixing hole 10. Moreover, the fixing member 3 is advanced only by the rotation operation performed from the outside of the reinforcing member 2 to press the flange portion 31 and the contact member 32 of the fixing member 3 and to fit the fitting protrusion 35 to the reinforcing member 2. Can be accurately and reliably fitted to and fixed to the steel pipe column 1, so that a troublesome welding operation for fixing the reinforcing member as in the related art is unnecessary, and the strength of the steel pipe is sacrificed because the reinforcing member is bolted. There is no need to open the opening.

【0049】また、この補強部材2を利用して鉄筋Rを
接合する際にも、補強部材2の外側から鉄筋Rの雄ネジ
Sを固定部材3のネジ孔30に螺合させるだけで非常に簡
単に接合することが可能である。ちなみに、この場合に
おいて鉄筋Rは、図19の上端筋のように差し鉄筋態様で
あっても、また下端筋のように通し鉄筋態様の何れの形
態であってもよく、何れの態様であっても、鉄筋Rの雄
ネジSを固定部材3のネジ孔30に螺合させるだけで、極
めて簡単に接合することができるのである。
Also, when the reinforcing bar R is joined using the reinforcing member 2, it is very necessary to screw the male screw S of the reinforcing bar R into the screw hole 30 of the fixing member 3 from outside the reinforcing member 2. It is possible to easily join. Incidentally, in this case, the reinforcing bar R may be in the form of a reinforcing bar as shown in the upper end bar of FIG. 19, or may be in any form of the through-bar reinforcing bar as in the case of the lower end bar. Also, the connection can be made extremely easily only by screwing the male screw S of the reinforcing bar R into the screw hole 30 of the fixing member 3.

【0050】本発明の具体例である第一〜第五実施形態
は概ね上記のように構成されているが、本発明はこの実
施形態に限定されるものではなく「特許請求の範囲」の
記載内において種々の変更が可能であり、例えば、上記
実施形態では、高力ボルト4を固定部材3のネジ孔30に
螺合して突合せ接合しているが、上述した第二実施形態
のように、この高力ボルト4の代わりに、トルシア型高
力ボルトを採用して突合せ接合することも勿論可能であ
る。
Although the first to fifth embodiments, which are specific examples of the present invention, are generally configured as described above, the present invention is not limited to this embodiment, and is described in the claims. For example, in the above embodiment, the high-strength bolt 4 is screwed into the screw hole 30 of the fixing member 3 and butt-joined. However, as in the above-described second embodiment, Instead of the high-strength bolt 4, it is of course possible to employ a torsion-type high-strength bolt and butt-join.

【0051】[0051]

【発明の効果】以上実施形態を挙げて説明したとおり、
本発明の鋼管柱の接合構造物にあっては、鋼管柱の止着
孔に挿着した固定部材を後退させておくことができるの
で、頗る簡単に補強部材を鋼管柱の外側に被嵌すること
ができ、しかも、補強部材の外側から行う操作だけで簡
単に固定部材を前進させて補強部材を正確かつ確実に鋼
管柱に固定することができるので、従来のように、補強
部材を固定するために溶接作業を行う必要もなく、ま
た、補強部材をボルト止めするために鋼管強度を犠牲に
して鋼管柱に開口部を設ける必要もない。
As described above with reference to the embodiments,
In the joint structure of the steel pipe column of the present invention, since the fixing member inserted into the fixing hole of the steel pipe column can be retracted, the reinforcing member can be fitted on the outside of the steel pipe column very easily. The fixing member can be easily moved forward only by performing an operation from the outside of the reinforcing member, and the reinforcing member can be accurately and reliably fixed to the steel pipe column. Therefore, it is not necessary to perform a welding operation, and it is not necessary to provide an opening in the steel pipe column at the expense of steel pipe strength for bolting the reinforcing member.

【0052】また、本発明の鋼管柱の接合構造物は、鋼
管柱と補強部材とを固定部材によって直接固定すること
ができるので、鋼管柱の外側から固定ボルトの追加や仮
固定ボルトの取付けも必要でなく、また、従来のように
梁接合部に水平ダイヤフラムを介在させるべく鋼管柱を
各階毎に切断する必要もないので、鋼管柱の加工も最小
限で済み、切断加工や溶接による製品精度の低下を防ぐ
ことができると共に大幅なコスト削減を図ることができ
る。
Further, in the joint structure of steel pipe columns of the present invention, since the steel pipe columns and the reinforcing members can be directly fixed by the fixing members, addition of fixing bolts and attachment of temporary fixing bolts from outside of the steel pipe columns are also possible. It is not necessary, and since there is no need to cut the steel pipe columns for each floor to interpose a horizontal diaphragm at the beam joint as in the past, the processing of the steel pipe columns is minimized, and the product accuracy by cutting and welding Can be prevented from decreasing, and the cost can be significantly reduced.

【0053】また、本発明が提供する鋼管柱接合物の施
工方法は、操作の簡易な挿着治具を用いて鋼管柱の内部
に配した固定部材を、鋼管柱の止着孔と補強部材の通孔
と鉄骨梁のボルト孔に通して簡易かつ迅速に、しかも確
実に緊結接合させることができるから作業能率が高くて
仕上がりもよく極めて合理的である。
Further, the method for constructing a steel pipe column joint provided by the present invention is characterized in that a fixing member arranged inside the steel pipe column by using an easy-to-operate jig is used to fix a fixing hole and a reinforcing member of the steel pipe column. Can be easily and quickly and securely connected through the through hole of the steel beam and the bolt hole of the steel beam, so that the work efficiency is high, the finish is good, and it is extremely reasonable.

【0054】更にまた、本発明に係る鋼管柱の接合構造
物にあっては、補強部材及び固定部材を用いることによ
って、例えば、鋼管柱と鉄骨梁との接合、鋼管柱同士の
突合せ接合、鋼管柱と柱脚部材との接合等の殆ど全ての
鋼管柱の接合構造に適用できるので、その適用範囲が極
めて広く、また、従来のように大型の工作機械や特殊機
械等を用いる必要がないので、中小規模の工場での実施
も容易であり、産業上の利用価値は頗る高いものがあ
る。
Further, in the joint structure of steel pipe columns according to the present invention, by using a reinforcing member and a fixing member, for example, the joint between steel pipe columns and steel beams, the butt joint between steel pipe columns, the steel pipe It can be applied to almost all joint structures of steel pipe columns, such as joints between columns and column base members, so the applicable range is extremely wide, and there is no need to use large machine tools or special machines as in the past. It is easy to implement in small and medium-sized factories, and has very high industrial utility value.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る第一実施形態の鋼管柱の接合構造
の部分縦断面図である。
FIG. 1 is a partial longitudinal sectional view of a joint structure of steel pipe columns according to a first embodiment of the present invention.

【図2】同接合構造の部分横断面図である。FIG. 2 is a partial cross-sectional view of the joint structure.

【図3】同接合構造の組立工程図である。FIG. 3 is an assembly process diagram of the joint structure.

【図4】同接合構造の組立工程図である。FIG. 4 is an assembly process diagram of the joint structure.

【図5】同接合構造の組立工程図である。FIG. 5 is an assembly process diagram of the joint structure.

【図6】同接合構造の組立工程図である。FIG. 6 is an assembly process diagram of the joint structure.

【図7】同接合構造の組立工程図である。FIG. 7 is an assembly process diagram of the joint structure.

【図8】同接合構造の組立工程図である。FIG. 8 is an assembly process diagram of the joint structure.

【図9】本発明に係る第二実施形態の鋼管柱の接合構造
の部分縦断面図である。
FIG. 9 is a partial longitudinal sectional view of a joint structure of steel pipe columns according to a second embodiment of the present invention.

【図10】同接合構造の部分横断面図である。FIG. 10 is a partial cross-sectional view of the joint structure.

【図11】同接合構造の組立工程図である。FIG. 11 is an assembly process diagram of the joint structure.

【図12】同接合構造の組立工程図である。FIG. 12 is an assembly process drawing of the joint structure.

【図13】同接合構造の組立工程図である。FIG. 13 is an assembly process diagram of the joint structure.

【図14】同接合構造の組立工程図である。FIG. 14 is an assembly process diagram of the joint structure.

【図15】同接合構造の組立工程図である。FIG. 15 is an assembling process diagram of the joining structure.

【図16】同接合構造の組立工程図である。FIG. 16 is an assembly process diagram of the joint structure.

【図17】本発明に係る第三実施形態の鋼管柱の接合構
造の部分分解縦断面図である。
FIG. 17 is a partially exploded longitudinal sectional view of a joint structure of steel pipe columns according to a third embodiment of the present invention.

【図18】本発明に係る第四実施形態の鋼管柱の接合構
造の部分分解縦断面図である。
FIG. 18 is a partially exploded vertical sectional view of a joint structure of steel pipe columns according to a fourth embodiment of the present invention.

【図19】本発明の第五実施形態における挿入治具を用
いて鋼管柱と補強部材とを固定部材にて連結する過程を
表わした説明図である。
FIG. 19 is an explanatory diagram showing a process of connecting a steel pipe column and a reinforcing member with a fixing member using an insertion jig according to a fifth embodiment of the present invention.

【図20】本発明の第五実施形態を表わす部分拡大断面
図である。
FIG. 20 is a partially enlarged sectional view showing a fifth embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1・1′鋼管柱 10 止着孔 11 雌ネジ 2 補強部材 20 通孔 3 固定部材 30 ネジ孔 31 鍔部 32 当接部 33 雄ネジ 35 嵌合突起 4 ボルト 5 トルシア型高力ボルト 50 破断ピンテール 52 ナット 6 挿着治具 62 パンダグラフ機構 63 ワーク保持フレーム B 鉄骨梁 C 柱脚部材 R 鉄筋 s (鉄筋の)雄ネジ X 六角レンチ W レンチ 1.1 1 'steel pipe column 10 fastening hole 11 female screw 2 reinforcing member 20 through hole 3 fixing member 30 screw hole 31 flange 32 contact part 33 male screw 35 fitting projection 4 bolt 5 torcia type high strength bolt 50 break pin tail 52 Nut 6 Insertion jig 62 Panda graph mechanism 63 Work holding frame B Steel beam C Column base member R Reinforcing bar s (Rebar) male screw X Hex wrench W wrench

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.7 識別記号 FI E04B 1/58 508 E04B 1/58 508P 508S 511 511H E04G 21/16 E04G 21/16 (58)調査した分野(Int.Cl.7,DB名) E04B 1/24 E04B 1/30 E04B 1/58 E04G 21/14 - 21/22 ──────────────────────────────────────────────────続 き Continued on the front page (51) Int.Cl. 7 Identification symbol FI E04B 1/58 508 E04B 1/58 508P 508S 511 511H E04G 21/16 E04G 21/16 (58) Fields surveyed (Int.Cl. 7 , DB name) E04B 1/24 E04B 1/30 E04B 1/58 E04G 21/14-21/22

Claims (8)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 鋼管柱1に鉄骨梁Bを接合する鋼管柱の
接合構造であって、 鉄骨梁Bを接合すべき部位に止着孔10が開設された鋼管
柱1と; この鋼管柱1の外側に被嵌され、当該鋼管柱1の止着孔
10に対向する位置に通孔20が開設された補強部材2と; 軸心にネジ孔30を備えた筒体であって、前記鋼管柱1の
止着孔10に軸方向へ進退可能に挿着され、この筒体の後
端側には鋼管柱1の内面に当接可能な鍔部31が形成され
ていると共に、筒体の先端側には前記補強部材2の通孔
20に嵌合可能な嵌合突起35を備え、かつ、この嵌合突起
35の根本は前記補強部材2の内面に当接可能な当接部32
形成された固定部材3と; この固定部材3のネジ孔30に螺合可能なボルト4と;か
ら構成されており、 前記鋼管柱1の止着孔10に内側から挿着した固定部材3
を後退させた状態で、鋼管柱1の外側に補強部材2を被
嵌し、鋼管柱1の止着孔10と補強部材2の通孔20とを位
置合わせした後、固定部材3を前進させて先端側の嵌合
突起35を前記補強部材2の通孔20に嵌合させることによ
当該固定部材3の鍔部31を鋼管柱1の内面に当接させ
ると共に当接部32を補強部材2の内面に当接させ鋼管
柱1の梁接合部位に補強部材2を固定し、然る後、ボル
ト4を固定部材3のネジ孔30に補強部材2の外側から螺
合して鋼管柱1と鉄骨梁Bとを接合することを特徴とす
る鋼管柱の接合構造物。
1. A steel pipe column joining structure for joining a steel beam B to a steel tube column 1, the steel tube column 1 having a fastening hole 10 at a site where the steel beam B is to be joined; Fitting hole of the steel tube column 1
A reinforcing member 2 having a through hole 20 at a position opposite to 10; a cylindrical body having a screw hole 30 at an axial center thereof, which is inserted into the fastening hole 10 of the steel pipe column 1 so as to be able to advance and retreat in the axial direction. A flange 31 is formed on the rear end side of the tubular body so as to be able to contact the inner surface of the steel pipe column 1, and a through hole of the reinforcing member 2 is provided on the distal end side of the tubular body.
20 is provided with a fitting projection 35 that can be fitted to
The base of 35 is a contact portion 32 capable of contacting the inner surface of the reinforcing member 2.
And a bolt 4 that can be screwed into the screw hole 30 of the fixing member 3. The fixing member 3 inserted into the fastening hole 10 of the steel pipe column 1 from the inside.
In a state in which the steel pipe column 1 is retracted, the reinforcing member 2 is fitted on the outside of the steel pipe column 1, and the fixing hole 3 of the steel pipe column 1 is aligned with the through hole 20 of the reinforcing member 2, and then the fixing member 3 is advanced. On the tip side
By fitting the projection 35 into the through hole 20 of the reinforcing member 2,
The fixing member 3 of the flange portion 31 of the steel column reinforcing member 2 1 a is brought into contact with the inner surface and the contact portion 32 is abutted against the inner surface of the reinforcing member 2 to the beam joint portion of the steel pipe column 1 is fixed Ri, Thereafter, the bolt 4 is screwed into the screw hole 30 of the fixing member 3 from the outside of the reinforcing member 2 to join the steel pipe column 1 and the steel beam B to each other.
【請求項2】 鋼管柱1と他の鋼管柱1′とを突合せ接
合する鋼管柱の接合構造であって、 互いに突合せ接合すべき端部に各々止着孔10が開設され
た鋼管柱1・1′と; これら鋼管柱1・1′の外側に途中まで被嵌され、当該
鋼管柱1・1′の各止着孔10に対向する位置に通孔20が
開設された補強部材2と; 軸心にネジ孔30を備えた筒体であって、前記鋼管柱1・
1′の止着孔10に軸方向へ進退可能に挿着され、この筒
体の後端側には鋼管柱1・1′の内面に当接可能な鍔部
31が形成されていると共に、筒体の先端側には前記補強
部材2の通孔20 に嵌合可能な嵌合突起35を備え、かつ、
この嵌合突起35の根本は前記補強部材2の内面に当接可
能な当接部32形成された固定部材3と; この固定部材3のネジ孔30に螺合可能なボルト4と;か
ら構成されており、 前記鋼管柱1・1′の止着孔10に内側から挿着した固定
部材3を後退させた状態で、鋼管柱1・1′の外側に補
強部材2を途中まで被嵌し、鋼管柱1・1′の止着孔10
と補強部材2の通孔20とを位置合わせした後、固定部材
3を前進させて先端側の嵌合突起35を前記補強部材2の
通孔20に嵌合させることにより当該固定部材3の鍔部31
を鋼管柱1・1′の内面に当接させると共に当接部32を
補強部材2の内面に当接させ鋼管柱1・1′の突合せ
部位に補強部材2を固定し、然る後、ボルト4を固定部
材3のネジ孔30に補強部材2の外側から螺合して鋼管柱
1と他の鋼管柱1′とを突合せ接合することを特徴とす
る鋼管柱の接合構造物。
2. A joint structure for a steel pipe column in which a steel pipe column 1 and another steel pipe column 1 'are butt-joined, wherein a steel pipe column 1 having a fastening hole 10 at each end to be butt-joined to each other. A reinforcing member 2 fitted halfway to the outside of the steel pipe columns 1.1 'and having a through hole 20 at a position facing each of the fastening holes 10 of the steel pipe columns 1.1'; A cylindrical body having a screw hole 30 at an axial center thereof,
1 'is inserted into the fixing hole 10 so as to be able to advance and retreat in the axial direction, and a rear end side of this cylindrical body is a flange portion which can abut against the inner surface of the steel pipe column 1.1'.
31 is formed and the reinforcement
A fitting projection 35 capable of fitting into the through hole 20 of the member 2 ;
The root of the fitting projection 35 is formed from a fixing member 3 formed on a contact portion 32 that can contact the inner surface of the reinforcing member 2; and a bolt 4 that can be screwed into the screw hole 30 of the fixing member 3. In a state where the fixing member 3 inserted from the inside into the fixing hole 10 of the steel pipe column 1.1 ′ is retracted, the reinforcing member 2 is fitted halfway to the outside of the steel pipe column 1.1 ′. And the fixing hole 10 of the steel pipe column 1.1 '
After the positioning of the fixing member 3 with the through hole 20 of the reinforcing member 2, the fitting protrusion 35 on the distal end side
The flange 31 of the fixing member 3 is fitted to the through hole 20.
Is brought into contact with the inner surface of the steel pipe column 1.1 ′ and the contact portion 32 is brought into contact with the inner surface of the reinforcing member 2 to fix the reinforcing member 2 at the abutting portion of the steel pipe column 1.1 ′. A joint structure for a steel pipe column, wherein a bolt (4) is screwed into a screw hole (30) of a fixing member (3) from outside the reinforcing member (2) to butt-join the steel pipe column (1) and another steel pipe column (1 ').
【請求項3】 鋼管柱1の下端部に柱脚部材Cを接合す
る鋼管柱の接合構造であって、 下端部に止着孔10が開設された鋼管柱1と; 上部が鋼管柱1の外側に被嵌可能であると共に鋼管柱1
の止着孔10に対向する位置に通孔20が開設されており、
下部が柱脚部材Cに固定された補強部材2と; 軸心にネジ孔30を備えた筒体であって、前記鋼管柱1の
止着孔10に軸方向へ進退可能に挿着され、この筒体の後
端側には鋼管柱1の内面に当接可能な鍔部31が形成され
ていると共に、筒体の先端側には前記補強部材2の通孔
20に嵌合可能な嵌合突起35を備え、かつ、この嵌合突起
35の根本は前記補強部材2の内面に当接可能な当接部32
形成された固定部材3と; この固定部材3のネジ孔30に螺合可能なボルト4と;か
ら構成されており、 前記鋼管柱1の止着孔10に内側から挿着した固定部材3
を後退させた状態で、鋼管柱1の外側に補強部材2を被
嵌し、鋼管柱1の止着孔10と補強部材2の通孔20とを位
置合わせした後、固定部材3を前進させて先端側の嵌合
突起35を前記補強部材2の通孔20に嵌合させることによ
当該固定部材3の鍔部31を鋼管柱1の内面に当接させ
ると共に当接部32を補強部材2の内面に当接させ鋼管
柱1の柱脚接合部位に補強部材2を固定し、然る後、ボ
ルト4を固定部材3のネジ孔30に補強部材2の外側から
螺合して鋼管柱1と柱脚部材Cとを接合することを特徴
とする鋼管柱の接合構造物。
3. A steel pipe column joining structure in which a column base member C is joined to a lower end portion of the steel pipe column 1, the steel tube column 1 having a fastening hole 10 formed at a lower end portion; Steel pipe column 1 that can be fitted on the outside
A through hole 20 is opened at a position facing the fastening hole 10 of
A reinforcing member 2 having a lower portion fixed to the column base member C; a cylindrical body having a screw hole 30 at the axis thereof, which is inserted into the fastening hole 10 of the steel pipe column 1 so as to be able to advance and retreat in the axial direction; A flange 31 is formed on the rear end side of the cylindrical body so as to be able to contact the inner surface of the steel pipe column 1, and a through hole of the reinforcing member 2 is formed on the distal end side of the cylindrical body.
20 is provided with a fitting projection 35 that can be fitted to
The base of 35 is a contact portion 32 capable of contacting the inner surface of the reinforcing member 2.
And a bolt 4 that can be screwed into the screw hole 30 of the fixing member 3. The fixing member 3 inserted into the fastening hole 10 of the steel pipe column 1 from the inside.
In a state in which the steel pipe column 1 is retracted, the reinforcing member 2 is fitted on the outside of the steel pipe column 1, and the fixing hole 3 of the steel pipe column 1 is aligned with the through hole 20 of the reinforcing member 2, and then the fixing member 3 is advanced. On the tip side
By fitting the projection 35 into the through hole 20 of the reinforcing member 2,
The fixing member 3 of the flange portion 31 of the contact portion 32 of the reinforcing member 2 of the reinforcing member 2 in the column base junction of the steel pipe column 1 is brought into contact with the inner surface is brought into contact with the inner surface of the steel pipe column 1 and fixed Ri Thereafter, the bolt 4 is screwed into the screw hole 30 of the fixing member 3 from the outside of the reinforcing member 2 to join the steel pipe column 1 and the column base member C to each other.
【請求項4】 鋼管柱1に対し、端部に雄ネジsを形成
した鉄筋Rを接合する鋼管柱の接合構造であって、 鉄筋Rを接合すべき部位に止着孔10が開設された鋼管柱
1と; この鋼管柱1の外側に被挿され、当該鋼管柱1の止着孔
10に対向する位置に通孔20が開設された補強部材2と; 軸心にネジ孔30を有する筒体部材であって、前記鋼管柱
1の止着孔10に軸心方向へ進退自在に挿着され、かつ、
それ自身の後端側には前記鋼管柱1の内面に当接可能な
鍔部31、また、それ自身の先端部には前記補強部材2の
通孔20に嵌合可能な嵌合突起35を備え、かつ、この嵌合
突起35の根本は補強部材2の内面に当接可能な当接部32
を有する固定部材3と; から構成されており、 前記止着孔10と通孔20とが軸心を共通する状態に対向一
致する状態に補強部材2を鋼管柱1に被挿させ、鋼管柱
1の内側から固定部材3先端の嵌合突起35を止着孔10に
挿通して前記鍔部31は鋼管柱1の内面に当接し、また
合突起35の根本に位置する当接部32は補強部材2の内面
に当接した状態で鋼管柱1と補強部材2とを連結せし
め、さらに、この補強部材2の通孔20に連通するネジ孔
30には前記鉄筋Rの雄ネジsを螺入連結させたことを特
徴とする鋼管柱の接合構造物。
4. A joint structure of a steel pipe column for joining a steel rod R having an external thread s formed at an end to a steel pipe column 1, wherein a fastening hole 10 is formed at a position where the steel rod R is to be joined. A steel tube column 1; a fixing hole inserted into the outside of the steel tube column 1 to secure the steel tube column 1
A reinforcing member 2 having a through hole 20 at a position facing 10; a cylindrical member having a screw hole 30 at an axial center thereof, which is capable of moving forward and backward in the axial direction to the fastening hole 10 of the steel pipe column 1; Inserted and
The rear end side of itself has a flange portion 31 capable of contacting the inner surface of the steel pipe column 1, and the front end portion of the reinforcing member 2 has
It is provided with a fitting projection 35 that can be fitted into the through hole 20, and this fitting
The base of the projection 35 is a contact portion 32 that can contact the inner surface of the reinforcing member 2.
The reinforcing member 2 is inserted into the steel pipe column 1 in a state where the fastening hole 10 and the through hole 20 face and coincide with each other in a state where the axis is common, and the steel pipe column is formed. the flange portion 31 by inserting the fixing member 3 the tip fitting protrusion 35 of the fastening hole 10 from the first inner abuts the inner surface of the tubular columns 1, also fitted
The contact portion 32 located at the root of the joint projection 35 connects the steel pipe column 1 and the reinforcing member 2 in a state of contacting the inner surface of the reinforcing member 2, and further, a screw communicating with the through hole 20 of the reinforcing member 2. Hole
30 is a joint structure of steel pipe columns, wherein a male screw s of the reinforcing bar R is screwed and connected.
【請求項5】 ボルト4の代わりに、トルシア型高力ボ
ルト5を鋼管柱1の内側から固定部材3のネジ孔30に螺
着しておき、このトルシア型高力ボルト5にナット52を
補強部材2の外側から螺合させることによって鋼管柱1
に接合したことを特徴とする請求項1〜請求項3の何れ
か一つに記載の鋼管柱の接合構造物。
5. A torcia-type high-strength bolt 5 is screwed into the screw hole 30 of the fixing member 3 from the inside of the steel pipe column 1 instead of the bolt 4, and a nut 52 is reinforced with the torcia-type high-strength bolt 5. The steel pipe column 1 is screwed from the outside of the member 2
The steel tube column joint structure according to any one of claims 1 to 3, wherein the steel tube column is joined to the steel tube column.
【請求項6】 鋼管柱1の止着孔10に雌ネジ11が刻設さ
れている一方、固定部材3には当該雌ネジ11に対応する
雄ネジ33が刻設されており、当該固定部材3を回転させ
ることによって固定部材3を補強部材2へ向けて前進さ
せることを特徴とする請求項1〜請求項5の何れか一つ
に記載の鋼管柱の接合構造物。
6. A female screw 11 is engraved in the fixing hole 10 of the steel pipe column 1, while a male screw 33 corresponding to the female screw 11 is engraved in the fixing member 3. The joint structure for steel pipe columns according to any one of claims 1 to 5, wherein the fixing member (3) is advanced toward the reinforcing member (2) by rotating the fixing member (3).
【請求項7】 鋼管柱1に鉄骨梁Bを接合せしめるにあ
たり、 鉄骨梁Bを接合すべき部位に止着孔10を開設した鋼管柱
1の外側に、前記止着孔10に対向する位置に通孔20を開
設した補強部材2を被嵌させて、この補強部材2の通孔
20と前記鋼管柱1の止着孔10とを対向合致せしめる一
方、 前記鋼管柱1の止着孔10に挿入進退させ得る筒体であっ
て、内筒部はネジ孔30を形成し、かつ、後端側には鋼管
柱1の内面に当接可能な鍔部31、および先端側には前記
補強部材2の内面に当接可能な当接部32を有する固定部
材3・3・・・・を、パンダグラフ機構62・62によって対向
的に拡縮動作可能な挿着治具6のワーク保持フレーム63
・63に保持させて前記鋼管柱1の中に挿入し、対向合致
状態にある前記止着孔10と通孔20に前記各固定部材3を
向い合わせ、前記パンダグラフ機構62・62の幅拡大動作
を介してワーク保持フレーム63・63を当該鋼管柱1の対
向内壁面に向けて移動させることによって固定部材3を
挿入せしめ、前記各固定部材3後端の鍔部31は当該鋼管
柱1の内面に当接させ、同固定部材3前端の当接部32は
補強部材3の内面に当接させてから、これら固定部材3
のネジ孔30と前記鉄骨梁Bのボルト孔bとを合致させ、
ついで、高力ボルト4を前記ネジ孔30に螺入することに
より鋼管柱1と補強部材2と鉄骨梁Bとを緊結状態に接
合させることを特徴とした鋼管柱接合構造物の施工方
法。
7. At the time of joining the steel beam B to the steel pipe column 1, at the position facing the fixing hole 10 outside the steel pipe column 1 having a fastening hole 10 opened at a site where the steel beam B is to be joined. The reinforcing member 2 having the through hole 20 is fitted, and the through hole of the reinforcing member 2 is formed.
A cylindrical body which can be inserted into and retracted from the fitting hole 10 of the steel pipe column 1 while the fitting of the fitting 20 to the fitting hole 10 of the steel pipe column 1 is opposed, and the inner cylindrical portion forms a screw hole 30; , A fixing member 33 having a flange 31 on the rear end side capable of contacting the inner surface of the steel pipe column 1 and a contact portion 32 on the front end side capable of contacting the inner surface of the reinforcing member 2. The work holding frame 63 of the insertion jig 6 which can be oppositely expanded and contracted by the panda graph mechanisms 62
· Inserted into the steel pipe column 1 while holding it at 63, the fixing members 3 are opposed to the fastening holes 10 and the through holes 20 which are in a facing state, and the width of the pandagraph mechanism 62 is increased. The fixing members 3 are inserted by moving the work holding frames 63 and 63 toward the opposing inner wall surfaces of the steel pipe columns 1 through the operation, and the flange 31 at the rear end of each of the fixing members 3 is attached to the steel pipe columns 1. After the abutment portion 32 at the front end of the fixing member 3 is brought into contact with the inner surface of the reinforcing member 3,
The screw hole 30 of the steel beam B and the bolt hole b of the steel beam B,
Then, the steel pipe column 1, the reinforcing member 2, and the steel beam B are joined in a tight state by screwing the high-strength bolt 4 into the screw hole 30.
【請求項8】 固定部材3の外周面に雄ネジ33が形成さ
れており、これら各固定部材3を、パンダグラフ機構62
・62によって対向的に拡縮動作可能なワーク保持フレー
ム63・63・・・・に保持させて前記鋼管柱1の中に挿入し、
対向合致状態にある前記止着孔10と通孔20に前記各固定
部材3を向い合わせ、前記パンダグラフ機構62・62の幅
拡大動作を介してワーク保持フレーム63・63を当該鋼管
柱1の対向内壁面に向けて移動させてから、レンチWで
前記各固定部材3を螺進させることによって固定部材3
前端の当接部32は補強部材3の内面に当接せしめること
を特徴とした請求項7記載の鋼管柱接合構造物の施工方
法。
8. A male screw 33 is formed on the outer peripheral surface of the fixing member 3, and each of the fixing members 3 is connected to a pandagraph mechanism 62.
.. Inserted into the steel pipe column 1 while being held by work holding frames 63, 63...
Each of the fixing members 3 is opposed to the fastening hole 10 and the through hole 20 in the facing matching state, and the work holding frames 63, 63 are connected to the steel pipe column 1 through the width expanding operation of the pandagraph mechanisms 62, 62. After moving toward the opposing inner wall surface, each of the fixing members 3 is screwed forward with a wrench W so that the fixing members 3
The method according to claim 7, wherein the contact portion (32) at the front end is brought into contact with the inner surface of the reinforcing member (3).
JP2000192766A 2000-06-27 2000-06-27 Joint structure of steel pipe column and method of construction of the joint structure Expired - Fee Related JP3158115B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000192766A JP3158115B1 (en) 2000-06-27 2000-06-27 Joint structure of steel pipe column and method of construction of the joint structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000192766A JP3158115B1 (en) 2000-06-27 2000-06-27 Joint structure of steel pipe column and method of construction of the joint structure

Publications (2)

Publication Number Publication Date
JP3158115B1 true JP3158115B1 (en) 2001-04-23
JP2002004420A JP2002004420A (en) 2002-01-09

Family

ID=18691850

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000192766A Expired - Fee Related JP3158115B1 (en) 2000-06-27 2000-06-27 Joint structure of steel pipe column and method of construction of the joint structure

Country Status (1)

Country Link
JP (1) JP3158115B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797809A (en) * 2018-08-21 2018-11-13 长安大学 The connecting joint structure and construction method of core space heavier-duty circular steel tube concrete column and girder steel

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104863266B (en) * 2015-04-24 2019-06-18 清华大学 The prefabricated assembled high-ductility girder Column border node of box column-I-beam
JP2018145786A (en) * 2017-03-08 2018-09-20 積水化学工業株式会社 Pipe body connection structure and unit building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108797809A (en) * 2018-08-21 2018-11-13 长安大学 The connecting joint structure and construction method of core space heavier-duty circular steel tube concrete column and girder steel

Also Published As

Publication number Publication date
JP2002004420A (en) 2002-01-09

Similar Documents

Publication Publication Date Title
JP3237050B2 (en) Mortar-filled rebar joint
JP4858950B2 (en) Construction method of beam joint structure of square steel pipe column
JP2002242303A (en) Joint construction method for steel-pipe column
JP3158115B1 (en) Joint structure of steel pipe column and method of construction of the joint structure
JP3252961B2 (en) Fixed parts and bolt parts used for steel pipe column connection
JP3247815B2 (en) Column beam connection structure using one side bolt
JP3179073B1 (en) Steel tube column joint structure
JP2826269B2 (en) Column / beam joint structure using one side bolt
JP2004316426A (en) Joint structure for square steel pipe column
JPH07207769A (en) Joining structure for column to column
JPH08311989A (en) Joint structure of steel skeleton building construction
JPH07331749A (en) One-side bolt joint structure of steel pipe columns
JPH07127142A (en) Jointing structure for steel frame member with closed section and jointing method
JP3487311B2 (en) Alignment-free welding pin joint structure between square steel tubular column and H-shaped steel beam
JPH07331744A (en) Column-beam joint structure using one-side bolt
JP2000192550A (en) Joining metal fitting and joining part structure of framework member
JP2004107992A (en) Long-clamping high-strength bolt joint structure of steel-pipe column and joint metal, and long-clamping bolt
JP2840209B2 (en) Column-column joint structure of steel pipe columns of different diameter
JP2752905B2 (en) Column / beam joint structure using one side bolt
JP3859787B2 (en) Column / column joining method and its rough assembly jig
JPH0447049A (en) Column splicing method for steel pipe column
JPH0932111A (en) Column-beam joint metal for square-shaped steel-pipe column and manufacture thereof
JPH0435610Y2 (en)
JPH11152797A (en) Column-column joint metal and column body as well as execution method of column body
JPH019843Y2 (en)

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees