JP3087093B2 - The structure of the vertical bridge in the railway viaduct - Google Patents

The structure of the vertical bridge in the railway viaduct

Info

Publication number
JP3087093B2
JP3087093B2 JP04234033A JP23403392A JP3087093B2 JP 3087093 B2 JP3087093 B2 JP 3087093B2 JP 04234033 A JP04234033 A JP 04234033A JP 23403392 A JP23403392 A JP 23403392A JP 3087093 B2 JP3087093 B2 JP 3087093B2
Authority
JP
Japan
Prior art keywords
vertical
fixed
track
height
railway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP04234033A
Other languages
Japanese (ja)
Other versions
JPH0633408A (en
Inventor
真一 玉井
惇 成行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyu Construction Co Ltd
Original Assignee
Tokyu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyu Construction Co Ltd filed Critical Tokyu Construction Co Ltd
Priority to JP04234033A priority Critical patent/JP3087093B2/en
Publication of JPH0633408A publication Critical patent/JPH0633408A/en
Application granted granted Critical
Publication of JP3087093B2 publication Critical patent/JP3087093B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、鉄道高架橋の縦粱の構
造に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a structure of a vertical bridge in a railway viaduct.

【0002】[0002]

【従来の技術】従来の鉄道高架橋の施工方法において
は、橋脚の上部にスラブを施工したらその上に砕石道
床、あるいはスラブ道床を搭載し、道床の上にまくらぎ
を敷設し、その上に軌条を敷設する構造であった。
2. Description of the Related Art In a conventional railway viaduct construction method, when a slab is constructed on an upper part of a pier, a crushed stone slab or a slab slab is mounted thereon, a sleeper is laid on the slab, and rails are laid thereon. Was laid.

【0003】[0003]

【発明が解決しようとする問題点】前記した従来の鉄道
高架橋の縦粱の構造にあっては、次のような問題点があ
る。 <イ>スラブの自重は1平方メートル当たり0.6t、
道床の自重は0.9t程度である。このように死荷重が
大きいため、それを支持する高架橋の各断面が大きくな
り不経済である。 <ロ>スラブコンクリートの打設のためにはその下部型
枠を支保工で支持しなければならない。そのために特に
使用中の鉄道の上にさらにスラブを設ける場合には、支
保工の高さだけスラブを高く設置しなければならない。
Problems to be Solved by the Invention The structure of the above-mentioned conventional vertical bridge of railway viaduct has the following problems. <I> The weight of the slab is 0.6t per square meter,
The weight of the track bed is about 0.9t. Since the dead load is large as described above, each section of the viaduct supporting the dead load becomes large, which is uneconomical. <B> In order to cast slab concrete, the lower formwork must be supported by shoring. Therefore, especially when further slabs are provided on the railway in use, the slabs must be installed high by the height of the shoring.

【0004】[0004]

【本発明の目的】本発明は上記のような従来の問題を改
善するためになされたもので、部材数が少なく、短い工
期において、鉄道の曲線部分を経済的に施工することの
できる鉄道高架橋の施工に使用する縦粱の構造を提供す
ることを目的とする。
SUMMARY OF THE INVENTION The object of the present invention is to solve the above-mentioned conventional problems. A railway viaduct capable of economically constructing a curved section of a railway with a small number of members and a short construction period. It is an object of the present invention to provide a structure of a vertical beam used for construction of a sword.

【0005】[0005]

【問題点を解決するための手段】 すなわち本発明は、
軌道の両側に橋脚を垂直に立設し、両側の橋脚間に、軌
道を横断する方向に横断梁を固定し、前記横断梁間に、
横断梁の上面と同じ高さに上面を合わせ、軌道と平行方
向に固定した縦梁であってプレストレスを導入した
コンクリートの梁と、前記縦梁の上面に搭載する高さ調
整用のスペーサブロックと、前記スペーサブロック上に
搭載する、軌条を固定した縦まくらぎとより構成した、
鉄道高架橋の縦梁の構造である。
[Means for Solving the Problems] That is, the present invention provides:
The piers are erected vertically on both sides of the track, and between the piers on both sides, cross beams are fixed in the direction crossing the track, and between the cross beams,
Align the upper surface at the same height as the upper surface of the transverse beam, a longitudinal beam secured to the track direction parallel to Prestressing
Concrete beams , a spacer block for height adjustment mounted on the upper surface of the vertical beam, and mounted on the spacer block, comprising a railroad-fixed vertical sleeper,
It is a vertical beam structure of a railway viaduct.

【0006】[0006]

【本発明の構成】以下図面を参照しながら本発明鉄道高
架橋の縦粱の構造について説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The structure of a vertical bridge of a railway viaduct of the present invention will be described below with reference to the drawings.

【0007】<イ>縦粱 本発明において、鉄道の軌道と平行方向に設置する粱を
縦粱1と称する。本発明の縦粱1は工場で製造したプレ
ストレスコンクリート製のプレキャスト部材である。し
たがって良好な品質管理の下に製造された部材を使用す
ることができる。この縦粱1の面には特に軌条などを取
り付けず、単なる長いブロック体として構成する。縦粱
1の平面形状は、図1では直線であるが、一般には設置
する位置のカーブに応じた円弧状に形成する。
<A> Vertical Beam In the present invention, a beam installed in a direction parallel to a railroad track is referred to as a vertical beam 1. The longitudinal beam 1 of the present invention is a precast member made of prestressed concrete manufactured at a factory. Therefore, components manufactured under good quality control can be used. No rails or the like are attached to the surface of the longitudinal beam 1 and it is configured as a simple long block. The planar shape of the longitudinal beam 1 is a straight line in FIG. 1, but is generally formed in an arc shape corresponding to a curve at the installation position.

【0008】<ロ>スペーサブロック この縦粱1の上面には高さ調整用のブロック4を搭載す
る。このブロック4は縦粱1の上面と同一の面積を有す
るコンクリート製の円弧状の長い部材であるが、特に計
算された高さに形成してある。鉄道車両は、左右の車輪
が車軸で一体に固定されているから、左右の車輪が同一
速度で回転しながら曲線を通過しなければならない。そ
のために車輪の踏面に勾配を形成するとともに、曲線部
分の軌条は間隔を広げ(スラック)、かつ左右の高さを
変化(カント)させる必要がある。このなかで、カント
を得る目的で縦粱1と軌条との間に介在させるのが、こ
のスペーサブロック4である。
<B> Spacer block A height adjusting block 4 is mounted on the upper surface of the vertical beam 1. The block 4 is a concrete arc-shaped long member having the same area as the upper surface of the vertical beam 1 and is formed at a height calculated especially. Since the left and right wheels of a railway vehicle are fixed integrally by an axle, the left and right wheels must pass through a curve while rotating at the same speed. For this purpose, it is necessary to form a gradient on the tread surface of the wheel, and to widen the interval (slack) and change the height of the right and left sides (cant) of the rail at the curved portion. Among them, the spacer block 4 is interposed between the longitudinal beam 1 and the rail for the purpose of obtaining a cant.

【0009】<ハ>縦まくらぎ 縦まくらぎ5は、縦粱1の平面形状とほぼ同一の平面形
状を有するコンクリート部材である。 このコンクリー
ト製の縦まくらぎ5の上面に、締結装置を使って軌条な
どを工場で一体に取り付ける。軌条などが縦まくらぎ5
と一体化しているから、縦まくらぎ5の運搬、架設作業
によって、軌条を同時に運搬し、架設することができ
る。曲線部においては円曲線の内側に軌間を広げて車輪
の踏面と軌条表面との接触位置を変化させる必要があ
る。そのために縦まくらぎ5に軌条を固定する場合に、
曲線内側の軌条は計算通り正確な位置に固定しなければ
ならない。この固定作業も、管理の良好な工場において
行うから、正確な位置に確実に固定することができる。
<C> Vertical sleeper The vertical sleeper 5 is a concrete member having a plane shape that is substantially the same as the plane shape of the vertical beam 1. Rails and the like are integrally attached to the upper surface of the concrete sleeper 5 at a factory using a fastening device. Rails and other sleepers 5
Since the rails are integrated, the rails can be simultaneously transported and erected by transporting and erection work of the vertical sleeper 5. In the curved portion, it is necessary to change the contact position between the tread surface of the wheel and the rail surface by extending the gauge inside the circular curve. Therefore, when fixing the rail to the vertical sleeper 5,
The rail inside the curve must be fixed in the correct position as calculated. Since this fixing work is also performed in a well-managed factory, it can be reliably fixed at an accurate position.

【0010】<ニ>その他の部材 本発明の縦粱1とともに使用する部材は、橋脚、横断粱
であり、すべて工場で製造したプレキャスト部材であ
る。したがって良好な品質管理の下に製造された部材を
使用することができる。さらに各コンクリート部材はプ
レストレスを導入したものを使用する。したがって、小
さい断面で軽量でありながら十分な強度を期待できる。
<D> Other members The members used with the longitudinal beam 1 of the present invention are piers and cross beams, all of which are precast members manufactured at a factory. Therefore, components manufactured under good quality control can be used. Furthermore, each concrete member uses a prestressed one. Therefore, sufficient strength can be expected while being lightweight with a small cross section.

【0011】[0011]

【施工方法】次に本発明の縦粱1を使用した施工方法に
ついて説明する。 <イ>橋脚の立設 現在使用中の軌道や道路の両側の地中には基礎を設置
し、その基礎の上には橋脚を立設する。この橋脚も工場
生産したプレストレスの部材であり、したがって現場で
コンクリートを打設して構築する方法に比較して施工は
きわめて迅速である。
[Construction method] Next, a construction method using the vertical beam 1 of the present invention will be described. <A> Erecting piers A foundation will be installed in the ground on both sides of the track or road currently in use, and piers will be erected on the foundation. This pier is also a pre-stressed member manufactured at the factory, and therefore its construction is extremely quick as compared with the method of casting and constructing concrete on site.

【0012】<ロ>横断粱の架設 軌道の両側に立設した橋脚の上部を連結する状態で、横
断粱を架設する。この横断粱は当然、橋脚の上端と一体
に固定しなければならない。そのためには交差する鉄筋
を場所打ちコンクリートで固定したり、横断粱と橋脚と
を貫通したPC鋼材を橋脚の外側から緊張したり、橋脚
の上部に横断粱を搭載して橋脚の上端から露出させたP
C鋼材で横断粱を緊張したり、その他各種の固定方法を
採用することができる。
<B> Installation of crossing beam A cross beam is installed while connecting the upper portions of the piers erected on both sides of the track. This crossbeam must, of course, be fixed integrally with the upper end of the pier. For this purpose, crossing steel bars are fixed with cast-in-place concrete, PC steel penetrating the cross beam and the pier is tensioned from the outside of the pier, or the cross beam is mounted on the top of the pier and exposed from the upper end of the pier. P
The transverse beam can be tensioned with C steel, and various other fixing methods can be adopted.

【0013】<ハ>縦粱1の架設 こうして橋脚の上端に固定した横断粱の上部に、本発明
の縦粱1を架設して固定する。縦粱1は前記したように
単なるコンクリート製の粱であり、直接横断粱に強固に
固定する。架設に際して、縦粱1は1本ごとに独立して
いるから、2本の縦粱1を横断粱上に平行に架設する。
<C> Installation of the vertical beam 1 The vertical beam 1 of the present invention is installed and fixed on the upper part of the cross beam fixed on the upper end of the pier. The longitudinal beam 1 is a simple concrete beam as described above, and is firmly fixed directly to the transverse beam. At the time of erection, since the vertical swords 1 are independent for each one, two vertical swords 1 are laid in parallel on the cross beam.

【0014】<ニ>スペーサブロック4の搭載 縦粱1の上面には前記した高さ調整用のスペーサブロッ
ク4を搭載する。このブロック4は計算によって、設置
する場所に必要な高さに応じて工場で製作されている。
したがって必要とするカントに応じた正確な高さのブロ
ック4を得ることができる。
<D> Mounting of Spacer Block 4 On the upper surface of the longitudinal beam 1, the spacer block 4 for height adjustment described above is mounted. This block 4 is manufactured in a factory by calculation according to the height required for the installation location.
Therefore, it is possible to obtain a block 4 having an accurate height according to a required cant.

【0015】<ホ>縦まくらぎ5の設置 スペーサブロック4の上には縦まくらぎ5を搭載する。
この縦まくらぎ5は、その上面に軌条を固定してあるか
ら、スペーサブロック4の傾斜に応じて軌条が傾斜する
ことになる。縦まくらぎ5を、スペーサブロック4を介
して縦粱1に固定することによって、高架橋の施工は完
了する。
<E> Installation of the vertical sleeper 5 The vertical sleeper 5 is mounted on the spacer block 4.
Since the rail is fixed to the upper surface of the vertical sleeper 5, the rail is inclined in accordance with the inclination of the spacer block 4. By fixing the vertical sleepers 5 to the longitudinal beams 1 via the spacer blocks 4, the construction of the viaduct is completed.

【0016】[0016]

【発明の効果】本発明の鉄道高架橋の縦粱1の構造は以
上説明したようになるから次のような効果を得ることが
できる。 <イ>縦粱1と軌条とによって軌道を構成する。そのた
めにスラブの施工が不要であり、さらにスラブの上に搭
載する多量の道床が不要となる。したがって死荷重を大
幅に減少することができ、その結果、地震時の水平慣性
力が小さくなるために、橋脚断面、基礎構造その他の構
造、断面を小さくすることができ、きわめて経済的であ
る。 <ロ>工場で製造した部材であり、これらを使用して組
み立てる。したがって現場で型枠を組んでコンクリート
を打設する方法に比較して部品、部材点数が少なく、工
期を大幅に短縮することができる。 <ハ>現場打ちのスラブを使用せず、軌条と固定した粱
を使用するから、スラブ型枠などを支持する支保工が不
要である。したがって使用中の鉄道の上部に施工する場
合にも支保工や型枠の高さだけ低くすることができ、経
済的な施工が可能である。 <ニ>本発明の縦粱1のみが空中に架設される。したが
って従来のスラブ構造のように雨や雪がたまることがな
くその処理が簡単である。 <ホ>縦粱1と軌条との間に、高さを調整するブロック
4を介在させた構造である。したがって曲線におけるカ
ントやスラックを正確に設置することができ、その後も
寸法の維持に特別なメンテナンスが不要であり、管理費
を低減することができる。
As described above, the structure of the vertical bridge 1 of the railway viaduct of the present invention has the following effects. <A> A trajectory is constituted by the longitudinal beam 1 and the rail. Therefore, construction of the slab is not required, and a large amount of roadbed mounted on the slab is not required. Therefore, the dead load can be greatly reduced, and as a result, the horizontal inertia force at the time of the earthquake is reduced, so that the cross section of the pier, the foundation structure and other structures and the cross section can be reduced, which is extremely economical. <B> Components manufactured at the factory and assembled using these. Therefore, the number of parts and members is smaller than that of a method in which concrete is cast by assembling a formwork on site, and the construction period can be greatly reduced. <C> Since a beam and a fixed beam are used without using a cast-in-place slab, there is no need to support a slab formwork or the like. Therefore, even when the construction is performed on the upper part of the railway in use, the height can be reduced by the height of the support and the formwork, and economic construction is possible. <D> Only the longitudinal beam 1 of the present invention is erected in the air. Therefore, unlike the conventional slab structure, rain and snow do not accumulate and the processing is simple. <E> A structure in which a block 4 for adjusting the height is interposed between the longitudinal beam 1 and the rail. Therefore, cants and slacks in the curve can be accurately set, and no special maintenance is required for maintaining the dimensions thereafter, and the management cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の縦粱1を使用した鉄道高架橋の施工方
法の例の説明図
FIG. 1 is an explanatory view of an example of a method for constructing a railway viaduct using a vertical beam 1 according to the present invention.

【図2】縦粱1の構造の説明図FIG. 2 is an explanatory view of a structure of a vertical liner 1.

【図3】縦粱1の構造の説明図FIG. 3 is an explanatory view of the structure of a vertical liner 1.

【図4】完成状態の説明図FIG. 4 is an explanatory view of a completed state.

フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E01B 37/00 Continuation of front page (58) Field surveyed (Int.Cl. 7 , DB name) E01B 37/00

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】軌道の両側に橋脚を垂直に立設し、 両側の橋脚間に、軌道を横断する方向に横断梁を固定
、 前記横断梁間に、横断梁の上面と同じ高さに上面を合わ
せ、軌道と平行方向に固定した縦梁であってプレストレスを導入したコンクリートの梁と 、 前記縦梁の上面に搭載する高さ調整用のスペーサブロッ
クと、 前記スペーサブロック上に搭載する、軌条を固定した縦
まくらぎとより構成した、 鉄道高架橋の縦梁の構造。
1. A pier is erected vertically on both sides of a track, and a cross beam is fixed between the piers on both sides in a direction crossing the track.
And, mounted on said transverse Harima, it fits a top at the same height as the upper surface of the transverse beam, a longitudinal beam fixed to the track and parallel to the direction, and beams of concrete introduced prestress, the upper surface of the longitudinal beam A vertical beam structure for a railway viaduct, comprising: a height-adjusting spacer block to be adjusted; and a railroad-fixed vertical sleeper mounted on the spacer block.
JP04234033A 1992-07-17 1992-07-17 The structure of the vertical bridge in the railway viaduct Expired - Lifetime JP3087093B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP04234033A JP3087093B2 (en) 1992-07-17 1992-07-17 The structure of the vertical bridge in the railway viaduct

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP04234033A JP3087093B2 (en) 1992-07-17 1992-07-17 The structure of the vertical bridge in the railway viaduct

Publications (2)

Publication Number Publication Date
JPH0633408A JPH0633408A (en) 1994-02-08
JP3087093B2 true JP3087093B2 (en) 2000-09-11

Family

ID=16964513

Family Applications (1)

Application Number Title Priority Date Filing Date
JP04234033A Expired - Lifetime JP3087093B2 (en) 1992-07-17 1992-07-17 The structure of the vertical bridge in the railway viaduct

Country Status (1)

Country Link
JP (1) JP3087093B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4665195B2 (en) * 2006-11-28 2011-04-06 みのる産業株式会社 Vacuum seeder
CN111041994B (en) * 2019-12-24 2021-02-12 中交隧道工程局有限公司 Pier stud wraps up in mould device
CN114108398B (en) * 2020-08-27 2023-01-06 比亚迪股份有限公司 Method for manufacturing track beam, track bridge and method for manufacturing track bridge
CN113389218A (en) * 2021-05-10 2021-09-14 中铁武汉勘察设计院有限公司 Retaining wall structure for entrance and exit of road bridge and construction method thereof

Also Published As

Publication number Publication date
JPH0633408A (en) 1994-02-08

Similar Documents

Publication Publication Date Title
JPH02248501A (en) Traveling way-supporting body for transportation system wherein rail is connected on magnetic track or the like
CA1336424C (en) Railroad roadway for high speed rail-mounted vehicles
KR100703134B1 (en) Prefabricated prestressed concrete beam bridge and its construction method
CN102653931B (en) Elastic supporting vibration isolation member ballast bed
CN1699692A (en) Superimposed rail beam for magnetic suspension traffic and method for manufacturing same
PL177215B1 (en) Gravelless track structure system for at least one railway track and method of forming such structure
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
JP4540632B2 (en) Erection girder
JP3087093B2 (en) The structure of the vertical bridge in the railway viaduct
KR102276570B1 (en) Lower part separating type mold for constructing embedded rail track
JP4162291B2 (en) Railway work girder cradle and rail work girder cradle construction method
DE4430769C2 (en) Railway superstructure with a track grating supported on a continuous support plate made of reinforced concrete
JP3028157B2 (en) Railroad viaduct structure
KR102501040B1 (en) Method For Constructing Embedded Rail Track
JP3028156B2 (en) Construction method of railway viaduct
JP4080652B2 (en) Railway viaduct girder
JP2002525457A (en) Track equipment for rail vehicles, especially sleeper frames for crushed stone superstructures
JP3028155B2 (en) Construction method of railway viaduct
JPS6227530Y2 (en)
CN114808556B (en) Prefabricated assembly frame formula track structure
JP3028159B2 (en) Construction method of railway viaduct
CN111118978B (en) Straddle type monorail stool type pillow and straddle type monorail traffic system
CN219653511U (en) Steel box girder cable-stayed bridge single-column inward-inclined steel tower embedded section fixing support
JP3695632B2 (en) Construction girders using PC sleepers as horizontal girders
KR200377108Y1 (en) Deep hunch composite girder bridge for railway bridge

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080714

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090714

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100714

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110714

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110714

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120714

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130714

Year of fee payment: 13

EXPY Cancellation because of completion of term
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130714

Year of fee payment: 13