JP3066460B2 - How to build a tower - Google Patents

How to build a tower

Info

Publication number
JP3066460B2
JP3066460B2 JP8241567A JP24156796A JP3066460B2 JP 3066460 B2 JP3066460 B2 JP 3066460B2 JP 8241567 A JP8241567 A JP 8241567A JP 24156796 A JP24156796 A JP 24156796A JP 3066460 B2 JP3066460 B2 JP 3066460B2
Authority
JP
Japan
Prior art keywords
tower
building
steel
construction
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP8241567A
Other languages
Japanese (ja)
Other versions
JPH1088861A (en
Inventor
行正 荻原
洋 越田
象二 島村
壮年 高橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP8241567A priority Critical patent/JP3066460B2/en
Publication of JPH1088861A publication Critical patent/JPH1088861A/en
Application granted granted Critical
Publication of JP3066460B2 publication Critical patent/JP3066460B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、建物の屋上に設置
する鉄塔の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a tower installed on the roof of a building.

【0002】[0002]

【従来の技術】近年、無線通信の需要が増加しており、
市街地にも通信鉄塔を建設する必要が生じている。この
場合、敷地の確保、有効活用、鉄塔高さの確保などの観
点から市街地ではビルの屋上に通信鉄塔を建設するのが
有効である。
2. Description of the Related Art In recent years, the demand for wireless communication has been increasing.
There is also a need to build communication towers in urban areas. In this case, it is effective to construct a communication tower on the roof of a building in an urban area from the viewpoints of securing the site, making effective use of the tower, and securing the tower height.

【0003】このようにビル屋上に通信鉄塔を構築する
場合、従来は、鉄塔からの荷重を支持し、さらに地震時
や強風時に鉄塔から伝達される転倒モーメントを支える
手段として、ビル建物の完成後に、屋上に大型の梁(ウ
ォールガータ)をまず設置し、その後に鉄塔の構築工事
を開始していた。
[0003] When a communication tower is constructed on the roof of a building as described above, conventionally, as a means to support the load from the tower and to support the overturning moment transmitted from the tower during an earthquake or a strong wind, after the building is completed, First, a large beam (wall gata) was installed on the rooftop, and then the construction of the tower was started.

【0004】従来行われている鉄塔の構築には、一例と
して、鉄塔建設用のクレーンを屋上等に設置して、この
クレーンにより完成した部分の鉄塔の上部で部材を接合
しながら順次上方へとさらに組み上げていく方法があ
る。また、他の方法として、一定の単位(節)の部材を
屋上で組み立て、これを接合しながら油圧ジャッキや、
モータとギヤを使用して屋上から押し上げていくプッシ
ュアップ工法、またはステップロッドのような吊り材を
使用し、この吊り材によって引っ張り上げるリフトアッ
プ工法などによっている。
[0004] In the conventional construction of a steel tower, as an example, a crane for the construction of a steel tower is installed on a rooftop or the like, and members are joined at the upper portion of the steel tower in a portion completed by the crane and sequentially moved upward. There is a way to build it further. Also, as another method, a fixed unit (section) of members is assembled on the rooftop, and hydraulic jacks and
A push-up method in which a motor and gears are used to push up from the roof, or a lift-up method in which a suspending member such as a step rod is used and pulled by the suspending member is used.

【0005】[0005]

【発明が解決しようとする課題】前記クレーンにより組
み立てる方法は、高所作業が多くなり危険であり、資材
などの落下による第三者への障害発生を防止するための
養生も必要となる。
The method of assembling with a crane is dangerous because it requires a lot of work at high places, and also requires curing to prevent the occurrence of obstacles to third parties due to falling of materials and the like.

【0006】これに対して、プッシュアップ工法やリフ
トアップ工法の場合は、屋上の足場のよい場所で鉄塔部
材を節単位で組み立て、組み立ての完成した部分をジャ
ッキなどを使用して押し上げ、または引っ張り上げるも
のであることから、クレーンによる方法の場合における
ような高所での危険作業はないが、徐々に伸びていく鉄
塔を支えるために仮設(場合によっては本設)の支持フ
レームを設置する必要があり、工事が大掛かりなものと
なる。
On the other hand, in the case of the push-up method or the lift-up method, the steel tower members are assembled in knots at a good place on the rooftop, and the assembled part is pushed up or pulled using a jack or the like. There is no danger of working at heights as in the case of the crane method, but a temporary (or in some cases, permanent) support frame must be installed to support the gradually extending steel tower. There is a large amount of construction work.

【0007】また、従来行われているいずれの方法でも
鉄塔構築は、建物が完成し屋上に鉄塔を恒久的に支持す
るための大梁が完成した後でないと工事を開始できず、
さらに鉄塔完成後にアンテナ設置、配線工事を行うこと
になり、鉄塔が使用できるまで時間を要する。
[0007] In addition, in any of the conventional methods, the construction of a tower can only be started after the building has been completed and a girder for permanently supporting the tower on the roof has been completed.
Furthermore, after the tower is completed, antenna installation and wiring work will be performed, and it will take time until the tower can be used.

【0008】本発明の目的は前記従来例の不都合を解消
し、鉄塔組立のための高所での作業を無くし安全性を確
保し、鉄塔からの荷重を支持する構造大梁や支持フレー
ムが不要で仮設材料や本設材料の低減を図ることがで
き、さらに、建物の構築工事と同時進行で鉄塔の構築が
行えて工期短縮を図れる鉄塔の構築方法を提供すること
にある。
SUMMARY OF THE INVENTION An object of the present invention is to eliminate the disadvantages of the prior art, eliminate the work at high places for assembling the tower, ensure safety, and eliminate the need for structural beams or supporting frames for supporting loads from the tower. It is an object of the present invention to provide a method of constructing a steel tower that can reduce the amount of temporary materials and permanent materials, and can also perform the construction of a steel tower simultaneously with the construction work of a building, thereby shortening the construction period.

【0009】[0009]

【課題を解決するための手段】本発明は前記目的を達成
するため、建屋の屋上に設置する鉄塔の構築方法で、鉄
塔の設置位置の直下に位置させて組上がった建屋の躯体
内に鉄塔組立用の空間を設け、この空間内の上部に組立
作業場を設け、ここで1節ずつ組み立てた鉄塔フレーム
を組立が完了した鉄塔フレームの上部に継ぎ足しながら
前記空間内に吊り下げ、全長の完成後に鉄塔をジャッキ
などの引き上げ装置で屋上にスライドさせて引き上げ、
該鉄塔の下部を建屋の躯体内に差し込んだ状態で建屋に
固定することを要旨とするものである。
In order to achieve the above object, the present invention provides a method for constructing a steel tower installed on the roof of a building. A space for assembling is provided, an assembling work place is provided at the upper part of this space, and the tower frame assembled one by one is suspended in the space while being added to the upper part of the tower frame that has been assembled. Slide the tower on the roof with a jack or other lifting device and pull it up.
The gist is that the lower part of the tower is fixed to the building while being inserted into the building.

【0010】請求項1記載の本発明によれば、鉄塔の設
置位置の直下に位置させて設けた組上がった建屋の躯体
内の鉄塔組立用の空間の上部に設けた組立作業場で鉄塔
の構築工事を行うから、鉄塔の組立、仕上げ、塗装など
の作業を低所で行うことができ、安全であるとともに、
足場のよい場所で作業できるから品質を確保でき、ま
た、風雨などの影響を受けずに作業でき、建屋部から出
ていく鉄塔の部分は完成した部分であるから、落下物が
発生するおそれがなく、市街地で施工する場合も安全で
ある。
According to the first aspect of the present invention, the construction of the tower at the assembly work place provided above the space for assembling the tower in the frame of the assembled building provided immediately below the installation position of the tower. Since construction work is performed, work such as assembling, finishing, and painting steel towers can be performed in low places, and while being safe,
Since the work can be done in a place with good scaffolding, quality can be ensured, and work can be performed without being affected by wind and rain. No, it is safe to construct in urban areas.

【0011】さらに躯体は組上がっているものの、建設
工事全体の工程においては建設中の建屋内で鉄塔構築工
事を行うことにより、建屋の建設工事と同時進行で施工
でき、全体の工期短縮となる。
[0011] Further, although the skeleton is assembled, in the process of the entire construction work, by performing the steel tower construction work in the building under construction, the construction work can be performed simultaneously with the construction work of the building, thereby shortening the overall construction period. .

【0012】また、空間内で構築した完成後の鉄塔は屋
上にスライドさせて移動し該鉄塔の下部を建物躯体内に
差し込んだ状態で建物に固定しここで支持することで、
建屋との接合部分を多くとることができ、鉄塔からの軸
力、転倒モーメントなどの荷重を建屋内の本体架構の多
くの支持点で支持でき、屋上にウォールガータなどをの
大型の支持架構を設置する必要がない。
Also, the completed tower built in the space is slid to the roof and moved, and the lower part of the tower is inserted into the building frame and fixed to the building and supported there.
A large number of joints with the building can be taken, the load such as the axial force from the tower, the overturning moment, etc. can be supported at many support points of the main body frame in the building, and a large supporting frame such as a wall gutter on the roof No need to install.

【0013】[0013]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1から図4は本発明の鉄塔
の構築方法の実施形態の前提となる鉄塔の構築方法の一
般例を示す工程図で、その一例として建設中の建屋内で
鉄塔を完成させ、その後、完成した鉄塔を屋上に引き上
げる方法について説明する。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIGS. 1 to 4 are process diagrams showing a general example of a method of constructing a tower which is a premise of an embodiment of a method of constructing a tower according to the present invention. As an example, a tower is completed in a building under construction, and then completed. A method of lifting a tower that has been set up on the roof will be described.

【0014】図1は、建屋1の地下部分1aについて
は、逆打ち工法で地下1階を構築中であり、また、地上
部分1bについては5階までの躯体鉄骨17の組立が完了
している状態であり、図中、2は山留壁としての地中連
続壁、3は構真柱、4は現場造成杭を示す。なお、地下
部分1aの施工法は図示の逆打ち工法に限定されるもの
ではない。
FIG. 1 shows that the underground part 1a of the building 1 is under construction on the first basement floor by the reverse striking method, and that the underground part 1b of the building 1 has been assembled up to the fifth floor. In the drawing, reference numeral 2 denotes an underground continuous wall as a retaining wall, 3 denotes a straight pillar, and 4 denotes an on-site formation pile. In addition, the construction method of the underground part 1a is not limited to the reverse construction method shown in the figure.

【0015】構築途中の建屋1には、鉄塔の最終的な設
置位置の直下に位置させて建屋1の内部に鉄塔組立用の
空間5を設けておき、この空間5内で鉄塔の基礎部6と
なる部分を組み立てる。この基礎部6の組立は建屋1の
躯体鉄骨17の組立と同時進行で行い、建屋本体工事用の
大型タワークレーン7を使用して行う。
In the building 1 under construction, a space 5 for assembling the tower is provided inside the building 1 so as to be located immediately below the final installation position of the tower. Assemble the parts that will be. The assembling of the foundation 6 is carried out simultaneously with the assembling of the frame steel frame 17 of the building 1, and is carried out by using a large tower crane 7 for the construction of the building body.

【0016】この状態から図2に示すように建屋1の地
上部分1bの上層階の躯体鉄骨17をさらに組み上げてい
くが、このときも建屋1内に鉄塔組立用の空間5を確保
する。そして、建屋1の躯体鉄骨17の構築と同時進行で
建屋本体構築のために使用する大型タワークレーン7を
使用してこの空間5内の足場のよい場所で鉄塔8の上部
である本体鉄骨9を組み立てる。
From this state, as shown in FIG. 2, the frame steel frame 17 on the upper floor of the ground portion 1b of the building 1 is further assembled. At this time, a space 5 for assembling the tower is secured in the building 1. Then, using the large tower crane 7 used for building the building body at the same time as the building of the building frame 17 of the building 1, the main body steel frame 9, which is the upper part of the steel tower 8, is placed in a place with a good scaffold in this space 5. assemble.

【0017】鉄塔8の本体鉄骨9の組立は、溶接、接
合、塗装などの作業によるが、組み立てが完了した部分
の鉄塔8の頂部に全天候型の仮設の屋根10を設置するこ
とにより、天候による影響を排除し、安定した室内環境
状態での作業空間を確保できる。
The main body steel frame 9 of the tower 8 is assembled by welding, joining, painting or the like. However, by installing an all-weather temporary roof 10 on the top of the tower 8 where the assembly is completed, depending on the weather. The influence can be eliminated and a work space in a stable indoor environment can be secured.

【0018】また、かかる構築中の鉄塔8の荷重は建屋
1の本体架構で支持する。
The load of the steel tower 8 under construction is supported by the main frame of the building 1.

【0019】このとき、地下部分1aは前記のように逆
打ち工法により地下2階部分までの躯体構築が同時進行
で施工され、鉄骨組立が完了する。
At this time, in the underground part 1a, the frame construction up to the second basement part is simultaneously carried out by the reverse hitting method as described above, and the steel frame assembly is completed.

【0020】以上のようにして建屋1の躯体鉄骨17の構
築と同時進行で建屋1の内部に形成した鉄塔組立用の空
間5内で鉄塔8の本体鉄骨9を上方に順次組み上げてい
く。そして、図3に示すように所定長の鉄塔8の組立が
完了し、鉄塔8の頂部が建屋1の屋上から上方に突出し
た状態になれば、鉄塔8の頂部に付属物として通信アン
テナ11、パラボラアンテナ12、制震装置13を取り付け
る。
As described above, the steel frame 9 of the steel tower 8 is sequentially assembled upward in the steel tower assembling space 5 formed inside the building 1 simultaneously with the construction of the frame steel frame 17 of the building 1. Then, as shown in FIG. 3, when the assembling of the tower 8 of a predetermined length is completed and the top of the tower 8 projects upward from the roof of the building 1, the communication antenna 11 is attached to the top of the tower 8 as an accessory. The parabolic antenna 12 and the vibration control device 13 are attached.

【0021】制震装置13は例えば重錘駆動型のもので相
当の重量物を含むが、かかる付属物の取付も建屋1の本
体工事用の大型タワークレーン7を使用して行うから、
安全で簡単に行える。
The vibration damping device 13 is, for example, of a weight-driven type and includes a considerable weight. However, the attachment of such an accessory is performed by using a large tower crane 7 for the main body construction of the building 1.
Safe and easy to do.

【0022】また、この工程では組立が完成した鉄塔8
を屋上に引き上げるための装置としてセンターホール式
の鉛直ジャッキ14、ステップロッド15を鉄塔組立用の空
間5に臨ませて建屋1の躯体鉄骨17に設置する。
In this step, the assembled tower 8
A vertical jack 14 and a step rod 15 of a center hall type are installed on the frame 17 of the building 1 with the vertical jack 14 and the step rod 15 facing the space 5 for assembling the tower as a device for raising the roof to the roof.

【0023】図8、図9はセンターホール式の鉛直ジャ
ッキ14、ステップロッド15の取り付け構造を示し、躯体
鉄骨17の上部に梁受け架台18を介して仮設桁19を設け、
この仮設桁19でジヤッキ受梁20を介して鉛直ジヤッキ14
を支持する。また、躯体鉄骨17の鉄塔組立用の空間5に
面する側の鉄骨柱17aの側面に鉛直方向にガイドレール
21を設ける。
FIGS. 8 and 9 show a mounting structure of a vertical jack 14 and a step rod 15 of a center hole type. A temporary girder 19 is provided above a frame steel frame 17 via a beam receiving stand 18.
With this temporary girder 19, a vertical jack 14 is connected via a jack receiving beam 20.
I support. Also, guide rails are provided vertically on the side surface of the steel column 17a on the side of the frame steel frame 17 facing the space 5 for assembling the tower.
21 is provided.

【0024】他方、鉄塔8側には本体鉄骨9の柱9aの
側面で前記ガイドレール21と対向する側にブラケット22
を設け、該ブラケット22を滑り沓23を介してガイドレー
ル21にスライド自在に係合する。図中9bは本体鉄骨9
の梁を示す。
On the other hand, a bracket 22 is provided on the side of the column 9a of the main body steel frame 9 on the side of the tower 8 facing the guide rail 21.
The bracket 22 is slidably engaged with the guide rail 21 via the sliding shoe 23. 9b is a steel frame 9 in the figure.
Is shown.

【0025】そして,前記ステップロッド15の下部をブ
ラケット22に係合し、鉄塔8を引き上げるには、図4の
ように鉛直ジャッキ14を縮めステップロッド15を上昇さ
せることにより本体鉄骨9に設けたブラケット22を介し
鉄塔8を上方にさせる。このとき、ブラケット22は滑り
沓23を介してガイドレール21にそってスムーズに上方へ
とスライドする。
Then, in order to engage the lower part of the step rod 15 with the bracket 22 and pull up the steel tower 8, the vertical jack 14 is contracted and the step rod 15 is raised as shown in FIG. The tower 8 is moved upward through the bracket 22. At this time, the bracket 22 slides smoothly upward along the guide rail 21 via the sliding shoe 23.

【0026】鉛直ジャッキ14の1ストローク分だけ鉄塔
8を引き上げたならば、ステップロッド15を保持したま
ま鉛直ジャッキ14のストロークを縮め、次いで前記と同
様にしてステップロッド15を引き上げて鉄塔8を上方に
再度スライドさせる。これを繰り返し、尺取り虫のよう
にして鉄塔8を屋上の上方に引き上げる。鉄塔8の下部
には駄目工事用のホイストクレーン24を設けておく。
When the tower 8 is lifted by one stroke of the vertical jack 14, the stroke of the vertical jack 14 is reduced while holding the step rod 15, and then the step rod 15 is pulled up to raise the tower 8 in the same manner as described above. Slide again. This is repeated, and the tower 8 is pulled up to the rooftop like a scale insect. A hoist crane 24 for useless work is provided below the tower 8.

【0027】このようにして引き上げられる鉄塔8は、
建屋1から上方に出ていく部分は既に完成しているか
ら、落下物が発生するおそれはなく、市街地などで構築
する場合にも十分安全である。
The steel tower 8 thus lifted is
Since the part that goes upward from the building 1 has already been completed, there is no danger of falling objects, and it is sufficiently safe even when building in an urban area or the like.

【0028】鉄塔8を引き上げる期間は、図4に示した
ような例えば23階建て、高さ 106mの建屋1の内部で構
築した場合に、約2日間である。
The period during which the steel tower 8 is lifted is about two days when it is constructed inside the building 1 having a height of 106 m and a height of, for example, 23 as shown in FIG.

【0029】図10は鉛直ジャッキ14やステップロッド15
などの引き上げのための装置の配置と引き上げ階の建屋
の平面を示し、一例として鉄塔8の組立用の空間5に面
して対向位置に鉛直ジャッキ14をそれぞれ4基ずつ配設
し、鉛直ジャッキ14を配設しない側の空間5には建屋1
の鉄骨柱17aにガイドレール21を設けた。
FIG. 10 shows a vertical jack 14 and a step rod 15.
FIG. 3 shows the arrangement of devices for lifting, etc. and the plane of the building on the raising floor. As an example, four vertical jacks 14 are arranged at opposing positions facing the space 5 for assembling the steel tower 8, respectively. Building 1 is in space 5 on the side where 14 is not installed.
The guide rail 21 is provided on the steel column 17a.

【0030】図5は鉄塔8の引き上げが完了した状態で
あり、図6に示すように鉄塔8の基礎部6(図6におい
て破線で囲んだ部分)は建屋1の躯体鉄骨17の内部(図
6において一点鎖線で囲んだ部分)に差し込まれた状態
となり、鉄塔8からの荷重は鉄塔8の下部のフレームを
介して建屋1に伝搬される。
FIG. 5 shows a state in which the lifting of the tower 8 is completed. As shown in FIG. 6, the base part 6 of the tower 8 (portion surrounded by a broken line in FIG. 6) is inside the frame 17 of the building 1 (see FIG. 6). 6 and the load from the tower 8 is transmitted to the building 1 via the lower frame of the tower 8.

【0031】また、建屋1の頂部と鉄塔8の本体鉄骨9
との間には構造的に緊結しない部分が確保されるから、
この間に相対変位を利用して鉄塔8と建屋1に減衰力を
与えるよう機能する制震装置26を設置する。この制震装
置26は一例として建屋1の躯体鉄骨17と一体化させた超
耐久型のオイルダンパが地震や強風による振動を吸収す
るハイダンピングシステムを採用することが可能であ
る。
The top of the building 1 and the steel frame 9 of the tower 8
Because there is a portion that is structurally not tied between
In the meantime, a vibration control device 26 that functions to apply a damping force to the tower 8 and the building 1 using the relative displacement is installed. As an example, the vibration damping device 26 can employ a high damping system in which a super-durable oil damper integrated with the frame steel frame 17 of the building 1 absorbs vibration due to an earthquake or strong wind.

【0032】そして、図5に示した鉄塔8の基礎部6と
建屋1の上部の躯体鉄骨17との接合部は、柱が多く、ま
た梁も大きく突出しているため、一般的な居室としては
使用が困難であるが、鉄塔8の建設後に床を設けること
により、無線用導破管、ケーブル処理室、パイプスペー
ス、倉庫等に使用可能な空間となる。
The joint between the base 6 of the tower 8 and the steel frame 17 at the top of the building 1 shown in FIG. 5 has many pillars and large beams, so that it is used as a general living room. Although it is difficult to use, by providing a floor after the construction of the steel tower 8, it becomes a space that can be used for radio rupture tubes, cable processing rooms, pipe spaces, warehouses and the like.

【0033】鉄塔8の直下に位置する下部の空間5は、
鉄塔8の下部に設けておいた駄目工事用のホイストクレ
ーン24を使用して床25、壁、梁を設ける工事及び内装工
事を行い、パイプスペース、倉庫等の他に一般居室とし
ての使用の可能となる。なお、鉄塔8の直下に位置する
柱27は図示の例では設けたが、構造設計により所定の強
度を確保できれば不要とすることもできる。
The lower space 5 located immediately below the tower 8 is
Use the hoist crane 24 for useless work provided at the lower part of the tower 8 to install the floor 25, walls and beams, and to perform interior work, so that it can be used as a general living room in addition to pipe spaces, warehouses, etc. Becomes Although the column 27 located immediately below the tower 8 is provided in the illustrated example, it may be unnecessary if a predetermined strength can be secured by a structural design.

【0034】図11、図12は一般例の第2例を示し、鉄塔
8を引き上げる方法として躯体構築が完成した建屋1の
鉄塔8の最終固定位置にプッシュアップ装置を設置し、
鉄塔の建屋1内の上層階で組み立て、組立が完了した分
を継ぎ足しながら順次押し上げる方法である。
11 and 12 show a second example of the general example. As a method of pulling up the tower 8, a push-up device is installed at the final fixed position of the tower 8 of the building 1 in which the building has been completed.
It is a method of assembling on the upper floor in the tower 1 of the steel tower, and sequentially pushing up while adding the completed assembly.

【0035】構築した建屋1内で鉄塔8の最終固定位置
となる上層階に鉄塔8の押し上げ用の空間30を設け、こ
の空間30にプッシュアップ装置28を設置する。このプッ
シュアップ装置28としては、例えば油圧式の装置やAM
URAD工法で使用するモータとネジによる装置などが
考えられる。
A space 30 for pushing up the tower 8 is provided on the upper floor where the tower 8 is finally fixed in the constructed building 1, and a push-up device 28 is installed in this space 30. As the push-up device 28, for example, a hydraulic device or an AM
A device using a motor and a screw used in the URAD method can be considered.

【0036】プッシュアップ装置28の設置場所に連接し
て鉄塔1の組立場29を設け、ここで鉄塔8を1節分ずつ
組み立て、塗装し、完成した1節分を押し上げ用の空間
30に移動し、既に完成して押し上げ用の空間30内で仮置
き架台31で支持されている鉄塔8の下部に接合する。
An assembling site 29 for the tower 1 is provided in connection with the installation location of the push-up device 28, where the tower 8 is assembled and painted one section at a time, and the completed section is pushed up.
It moves to 30 and is joined to the lower part of the steel tower 8 already completed and supported by the temporary placing gantry 31 in the space 30 for lifting.

【0037】接合が完了し、既に完成している部分と一
体化されたならば鉄塔8の全体を1節分だけプッシュア
ップ装置28で押し上げる。押し上げが完了すれば、鉄塔
8の荷重を仮置き架台31で支持し、下部に継ぎ足す鉄塔
8の1節分を組み立て、組み立ての完了後、前記と同様
にして鉄塔8の下部に接合して再度1節分を押し上げ、
これを繰り返し、所定の高さに鉄塔を設置する。
When the joining is completed and integrated with the already completed part, the entire steel tower 8 is pushed up by one push-up device 28 by one node. When the lifting is completed, the load of the tower 8 is supported by the temporary placing stand 31, and one section of the tower 8 to be added to the lower part is assembled. After the assembly is completed, the tower 8 is joined to the lower part of the tower 8 in the same manner as described above and re-attached. Push up one clause,
This is repeated, and a steel tower is installed at a predetermined height.

【0038】鉄塔8の頂部に取り付けるパラボラアンテ
ナ12など、鉄塔8の平面からはみ出す付属物や制震装置
13は、鉄塔8の頂部が建屋1の屋上に突出した時点で、
建屋本体工事用の大型タワークレーン7を使用して取付
工事する。
Attachments and vibration control devices protruding from the plane of the tower 8, such as a parabolic antenna 12 attached to the top of the tower 8
13 is when the top of the tower 8 protrudes to the roof of the building 1,
The installation work is performed using a large tower crane 7 for the construction of the building body.

【0039】図中32は、鉄塔8の構築中に転倒モーメン
トを建屋1に伝達すると同時に、押し上げ時にガイドと
なるローラ、滑り支承などの部材を示す。また、図12に
おいて33は第1実施形態と同様の相対変位利用型の制震
装置を示す。
Numeral 32 in the figure indicates members such as rollers and sliding bearings which serve as a guide when pushing up while transmitting the overturning moment to the building 1 during construction of the steel tower 8. In FIG. 12, reference numeral 33 denotes a relative displacement-based vibration damping device similar to the first embodiment.

【0040】本発明の鉄塔の構築方法も、前記した一般
例の第2例と同様に、図13、図14に示すように、組み上
がった建屋1の躯体鉄骨17の内部に高さ方向に鉄塔8の
引き上げ用の空間35を設けるとともに、この空間35に連
接して上層階に鉄塔の組立場34を設けた。鉄塔8を引き
上げる装置は第1例と同様、センターホール式の鉛直ジ
ャッキ14、ステップロッド15などを使用する。
As shown in FIGS. 13 and 14, similarly to the second example of the above-mentioned general example, the method of constructing a steel tower according to the present invention, as shown in FIG. 13 and FIG. A space 35 for raising the tower 8 is provided, and an assembling site 34 for the tower is provided on the upper floor in connection with the space 35. As in the first embodiment, the apparatus for lifting the steel tower 8 uses a center-hole type vertical jack 14, a step rod 15, and the like.

【0041】この場合は、建屋1の上層階に設けた組立
場34で鉄塔8の基礎部6及び本体鉄骨9を1節分ずつ組
み立て、組み立てが完了した分から屋上に設置の天井ク
レーン36で引き上げ用の空間35に吊り下ろし、構築が終
了している分の鉄塔8の上部に接合する。
In this case, the base part 6 and the main body steel frame 9 of the tower 8 are assembled one section at a time at an assembly place 34 provided on the upper floor of the building 1, and after the assembly is completed, the tower 6 is lifted by an overhead crane 36 installed on the roof. In the space 35, and joined to the upper portion of the steel tower 8 for which construction has been completed.

【0042】接合終了後、鉄塔8を鉛直ジャッキ14、ス
テップロッド15を使用して1節分だけ空間35内で下降さ
せる。これを繰り返して所定長の鉄塔を空間35で組み立
てる。
After the joining, the steel tower 8 is lowered in the space 35 by one node using the vertical jack 14 and the step rod 15. By repeating this, a tower of a predetermined length is assembled in the space 35.

【0043】鉄塔8が所定長に達して頂部が建屋1の屋
上に突出したならば、前記一般例と同様にして建屋本体
工事用の大型タワークレーン7を使用してパラボラアン
テナ12、制震装置13などの付属物を鉄塔8の頂部に取り
付ける。
When the steel tower 8 reaches a predetermined length and the top protrudes to the roof of the building 1, the parabolic antenna 12, the vibration damping device and the large tower crane 7 for the construction of the building body are used in the same manner as in the general example. Attach an accessory such as 13 to the top of the tower 8.

【0044】図中10は第1例と同様の全天候型の仮設の
屋根、32は第2例と同様の鉄塔8の構築中に転倒モーメ
ントを建屋1に伝達すると同時に、押し上げ時にガイド
となるローラ、滑り支承などの部材を示す。
In the drawing, reference numeral 10 denotes a temporary roof of all weather type similar to the first example, and reference numeral 32 denotes a roller which transmits a turning moment to the building 1 during construction of the steel tower 8 similar to the second example, and serves as a guide when pushing up. , Slide bearings and the like.

【0045】鉄塔8の頂部への付属物の取付が終了した
ならば、第1例と同様にして鉛直ジャッキ14、ステップ
ロッド15を使用して所定の高さまで引き上げ設置する。
When the attachment of the accessory to the top of the tower 8 is completed, the vertical jack 14 and the step rod 15 are used to pull up and install the same as in the first example.

【0046】[0046]

【発明の効果】以上述べたように本発明の鉄塔の構築方
法は、鉄塔の設置位置の直下に位置させて設けた組上が
った建屋の躯体内の鉄塔組立用の空間の上部に設けた組
立作業場で鉄塔の構築工事を行うから、鉄塔の組立、仕
上げ、塗装などの作業を低所で行うことができ、安全で
あるとともに、足場のよい場所で作業できるから品質を
確保でき、また、風雨などの影響を受けずに作業でき、
建屋部から出ていく鉄塔の部分は完成した部分であるか
ら、落下物が発生するおそれがなく、市街地で施工する
場合も安全である。
As described above, the method for constructing a tower according to the present invention provides a method for assembling a tower provided in an upper part of a space for assembling the tower in a frame of an assembled building which is provided immediately below the installation position of the tower. Since the construction work of the tower is performed at the work place, the work such as assembling, finishing, and painting of the tower can be performed in low places, and it is safe. Work without being affected by
Since the part of the tower that goes out of the building is a completed part, there is no danger of falling objects and it is safe to construct in urban areas.

【0047】さらに躯体は組上がっているものの、建設
工事全体の工程においては建設中の建屋内で鉄塔構築工
事を行うことにより、建屋の建設工事と同時進行で施工
でき、全体の工期短縮となる。
Further, although the skeleton is assembled, in the entire construction work process, by performing the steel tower construction work in the building under construction, the construction work can be carried out simultaneously with the construction work of the building, thereby shortening the overall construction period. .

【0048】また、空間内で構築した完成後の鉄塔は屋
上にスライドさせて移動し該鉄塔の下部を建物躯体内に
差し込んだ状態で建物に固定しここで支持することで、
建屋との接合部分を多くとることができ、鉄塔からの軸
力、転倒モーメントなどの荷重を建屋内の本体架構の多
くの支持点で支持でき、屋上にウォールガータなどの大
型の支持架構を設置する必要がない。
Also, the completed steel tower constructed in the space is slid to the roof and moved, and the lower part of the steel tower is fixed to the building while being inserted into the building frame, and is supported here.
A large number of joints with the building can be taken, and loads such as the axial force and overturning moment from the tower can be supported at many support points of the main body frame inside the building, and a large support frame such as a wall gutter is installed on the roof No need to do.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の鉄塔の構築方法の一般例の第1例を示
す第1工程図である。
FIG. 1 is a first process diagram showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図2】本発明の鉄塔の構築方法の一般例の第1例を示
す第2工程図である。
FIG. 2 is a second process diagram showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図3】本発明の鉄塔の構築方法の一般例の第1例を示
す第3工程図である。
FIG. 3 is a third process diagram showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図4】本発明の鉄塔の構築方法の一般例の第1例を示
す第4工程図である。
FIG. 4 is a fourth process diagram showing a first example of a general example of the method for building a steel tower according to the present invention.

【図5】本発明の鉄塔の構築方法の一般例の第1例を示
す第5工程図である。
FIG. 5 is a fifth process diagram showing a first example of a general example of the method for building a steel tower according to the present invention.

【図6】本発明の鉄塔の構築方法の一般例の第1例を示
す鉄塔設置位置の建屋の平面図である。
FIG. 6 is a plan view of a building at a tower installation position, showing a first example of a general example of a tower construction method of the present invention.

【図7】本発明の鉄塔の構築方法の一般例の第1例を示
す鉄塔設置位置の下方部の建屋の平面図である。
FIG. 7 is a plan view showing a first example of a general example of a method for constructing a tower according to the present invention, showing a building below a tower installation position.

【図8】本発明の鉄塔の構築方法の一般例の第1例を示
す引き上げ装置の縦断正面図である。
FIG. 8 is a vertical sectional front view of a lifting apparatus showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図9】本発明の鉄塔の構築方法の一般例の第1例を示
す引き上げ装置の平面図である。
FIG. 9 is a plan view of a lifting apparatus showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図10】本発明の鉄塔の構築方法の一般例の第1例を
示す引き上げ装置の配置図である。
FIG. 10 is a layout diagram of a lifting device showing a first example of a general example of a method for constructing a steel tower according to the present invention.

【図11】本発明の鉄塔の構築方法の一般例の第2例を
示す鉄塔構築途中の説明図である。
FIG. 11 is an explanatory view showing a second example of the general method of constructing a tower according to the present invention, during the construction of the tower.

【図12】本発明の鉄塔の構築方法の一般例の第2例を
示す鉄塔構築完了状態の説明図である。
FIG. 12 is an explanatory view of a completed state of the tower construction, showing a second example of the general example of the tower construction method of the present invention.

【図13】本発明の鉄塔の構築方法の実施形態を示す鉄
塔構築途中の説明図である。
FIG. 13 is an explanatory view showing a method of constructing a steel tower according to an embodiment of the present invention during the construction of the steel tower.

【図14】本発明の鉄塔の構築方法の実施形態を示す鉄
塔引き上げ途中の説明図である。
FIG. 14 is an explanatory view showing a steel tower construction method according to an embodiment of the present invention while the steel tower is being lifted.

【符号の説明】[Explanation of symbols]

1…建屋 1a…地下部分 1b…地上部分 2…地中連続壁 3…構真柱 4…現場造成杭 5…空間 6…基礎部 7…大型タワークレーン 8…鉄塔 9…本体鉄骨 9a…柱 9b…梁 10…屋根 11…通信アンテナ 12…パラボラア
ンテナ 13…制震装置 14…鉛直ジャッ
キ 15…ステップロッド 17…躯体鉄骨 17a…鉄骨柱 18…梁受け架台 19…仮設桁 20…ジヤッキ受梁 21…ガイドレー
ル 22…ブラケット 23…滑り沓 24…ホイストクレーン 25…床 26…制震装置 27…柱 28…プッシュアップ装置 29…組立場 30…空間 31…仮置き架台 32…部材 33…制震装置 34…組立場 35…空間 36…天井クレーン
DESCRIPTION OF SYMBOLS 1 ... Building 1a ... Underground part 1b ... Above ground part 2 ... Underground continuous wall 3 ... Structural pillar 4 ... Site formation pile 5 ... Space 6 ... Foundation part 7 ... Large tower crane 8 ... Iron tower 9 ... Main body steel frame 9a ... Column 9b … Beams 10… roofs 11… communication antennas 12… parabolic antennas 13… vibration dampers 14… vertical jacks 15… step rods 17… framed steel frames 17a… steel columns 18… beam supports 19… temporary girders 20… jack receivers 21… Guide rails 22… Brackets 23… Sliding shoes 24… Hoist cranes 25… Floor 26… Seismic damping devices 27… Columns 28… Push-up devices 29… Assembly sites 30… Space 31… Temporary mounting bases 32… Members 33… Vibration damping devices 34 … Assembly site 35… Space 36… Overhead crane

───────────────────────────────────────────────────── フロントページの続き (72)発明者 高橋 壮年 東京都港区元赤坂一丁目2番7号 鹿島 建設株式会社内 (56)参考文献 特開 昭54−123231(JP,A) 特開 昭56−6876(JP,A) 特開 昭48−2849(JP,A) 特開 平6−300081(JP,A) 特開 平9−32249(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04H 12/00 - 12/34 ──────────────────────────────────────────────────続 き Continuation of the front page (72) Inventor Soutaka Takahashi Kashima Construction Co., Ltd. 1-2-7 Moto-Akasaka, Minato-ku, Tokyo (56) References JP-A-54-123231 (JP, A) JP-A Sho 56-6876 (JP, A) JP-A-48-2849 (JP, A) JP-A-6-300081 (JP, A) JP-A-9-32249 (JP, A) (58) Fields investigated (Int. Cl. 7 , DB name) E04H 12/00-12/34

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 建屋の屋上に設置する鉄塔の構築方法
で、鉄塔の設置位置の直下に位置させて組上がった建屋
の躯体内に鉄塔組立用の空間を設け、この空間内の上部
に組立作業場を設け、ここで1節ずつ組み立てた鉄塔フ
レームを組立が完了した鉄塔フレームの上部に継ぎ足し
ながら前記空間内に吊り下げ、全長の完成後に鉄塔をジ
ャッキなどの引き上げ装置で屋上にスライドさせて引き
上げ、該鉄塔の下部を建屋の躯体内に差し込んだ状態で
建屋に固定することを特徴とした鉄塔の構築方法。
1. A method for constructing a tower to be installed on the roof of a building, wherein a space for assembling the tower is provided in the frame of the building that is located immediately below the installation position of the tower, and assembled at the upper part of the space. A work place is provided, where the tower frame assembled one by one is suspended in the space while being added to the upper part of the assembled tower frame, and after the full length is completed, the tower is slid to the roof with a jack or other lifting device to lift it up A method for constructing a tower, wherein the lower part of the tower is inserted into a building body and fixed to the building.
JP8241567A 1996-09-12 1996-09-12 How to build a tower Expired - Fee Related JP3066460B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP8241567A JP3066460B2 (en) 1996-09-12 1996-09-12 How to build a tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8241567A JP3066460B2 (en) 1996-09-12 1996-09-12 How to build a tower

Publications (2)

Publication Number Publication Date
JPH1088861A JPH1088861A (en) 1998-04-07
JP3066460B2 true JP3066460B2 (en) 2000-07-17

Family

ID=17076264

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8241567A Expired - Fee Related JP3066460B2 (en) 1996-09-12 1996-09-12 How to build a tower

Country Status (1)

Country Link
JP (1) JP3066460B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101656067B1 (en) * 2014-09-19 2016-09-09 주식회사 모루유통 Pizza tray having power supply unit

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5374924B2 (en) * 2008-05-21 2013-12-25 株式会社大林組 Construction method of tower structure, tower structure
JP5470744B2 (en) * 2008-05-21 2014-04-16 株式会社大林組 Shake prevention structure, shake prevention method, tower construction method
CN111764730A (en) * 2020-06-30 2020-10-13 诚邦生态环境股份有限公司 Layered combined installation construction method for spiral truss type tower

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101656067B1 (en) * 2014-09-19 2016-09-09 주식회사 모루유통 Pizza tray having power supply unit

Also Published As

Publication number Publication date
JPH1088861A (en) 1998-04-07

Similar Documents

Publication Publication Date Title
EP0487516B1 (en) Construction apparatus and construction method
JP3066460B2 (en) How to build a tower
JPH0571225A (en) Temporarily set roof of complete weather type
JP2979039B2 (en) Large space building construction equipment
JPH05133016A (en) Peripheral supporting self-rising type building engineering method
JP2942879B2 (en) Temporary house for all-weather construction
JP2871468B2 (en) How to build a building
JP2793053B2 (en) Building construction method
JPH0791904B2 (en) Push-up device
JP3115942B2 (en) Building construction method
JP2704447B2 (en) Lift-up method using permanent columns
JP3074614B2 (en) Panel ceiling construction method in the panel construction method when there is an obstacle just above the building
JP3439545B2 (en) Construction method of multi-story parking lot
JP2793052B2 (en) Building construction method
JP2876991B2 (en) Steel frame method for high-rise buildings
JPH03235838A (en) Lift up method of construction using temporary pillar
KR200200363Y1 (en) Building construction apparatus
JP2834351B2 (en) All-weather temporary structure
JP2785112B2 (en) All-weather construction method for high-rise buildings
JP3416759B2 (en) Underground structure frame building equipment
JP3185069B2 (en) How to build structures using tower cranes
JPH0540492U (en) Automatic lifting work platform
JPH11125014A (en) Construction method of building
JPH04155034A (en) Execution method for small scale building
KR20100002768A (en) Wood building and construction method of this

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120519

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150519

Year of fee payment: 15

LAPS Cancellation because of no payment of annual fees