Water stoppage method using deck plate

Info

Publication number
JP2999896B2
JP2999896B2 JP35427292A JP35427292A JP2999896B2 JP 2999896 B2 JP2999896 B2 JP 2999896B2 JP 35427292 A JP35427292 A JP 35427292A JP 35427292 A JP35427292 A JP 35427292A JP 2999896 B2 JP2999896 B2 JP 2999896B2
Authority
JP
Japan
Prior art keywords
deck plate
steel frame
floor
deck
rainwater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP35427292A
Other languages
Japanese (ja)
Other versions
JPH06185155A (en
JPH073932A (en
Inventor
裕行 山本
和夫 深沢
照夫 佐々木
正仁 松川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP35427292A priority Critical patent/JP2999896B2/en
Publication of JPH06185155A publication Critical patent/JPH06185155A/ja
Publication of JPH073932A publication Critical patent/JPH073932A/en
Application granted granted Critical
Publication of JP2999896B2 publication Critical patent/JP2999896B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、雨水に対して遮断機能
を有する止水床をデッキプレートを用いて構築する技術
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a technique for constructing a waterproof floor having a function of blocking rainwater by using a deck plate.

【0002】[0002]

【従来の技術】一般に、床コンクリートの打込み型枠と
してデッキプレートを梁鉄骨上に敷き込んだ状態におい
て、デッキプレートによって形成された床面(型枠面)
が、コンクリートの流れ出しを阻止し得る程度の止水性
を有することは、型枠としての機能上、当然である。
2. Description of the Related Art Generally, a floor surface (form surface) formed by a deck plate in a state where a deck plate is laid on a beam steel frame as a concrete form for floor concrete.
However, it is a matter of course that the concrete has a water-stopping property that can prevent the concrete from flowing out, in terms of the function as a mold.

【0003】しかしながら、従来では、デッキプレート
によって形成された床面で雨水を遮断することは不可能
とされていた。その理由としては、例えば、次のような
事項が考えられる。 床コンクリートの打込み型枠としては、機能上、雨水
まで止める必要性がなく、デッキプレートによる降雨対
策は、発想もされていなかった。 敷き込まれたデッキプレートの凹凸の向きが区々であ
り、デッキプレートの上に降った雨水の排水まで考慮さ
れていなかった。因に、大梁鉄骨は、床コンクリートが
打設され、コンクリート重量が負荷された時点で水平と
なるように、上方へのキャンバー(ムクリ)を付けて柱
間に架設されるので、大梁鉄骨上にデッキプレートを敷
設すると、自然に排水勾配が得られることになるが、従
来では、デッキプレートによって雨水を遮蔽する発想そ
のものが存在しないため、デッキプレートの凹凸の向き
を揃えて一連の排水路を形成することまで、行われてい
なかった。 大梁鉄骨は、床コンクリートとの構造的一体化を達成
するためのスタッドジベル(シャーコネクター)を打設
する必要上、上面全体をデッキプレートで覆ってしまう
わけにはいかず、そのため、従来では、大梁鉄骨の両側
でデッキプレートを分離し、両側のデッキプレートの相
対向する端縁を、大梁鉄骨の上フランジの端部に、スタ
ッドジベルの打設に必要な間隙を隔てた状態に載置して
いた。そして、この状態で、各々のデッキプレートの端
縁を大梁鉄骨の上フランジに溶接して固定しているが、
大梁鉄骨に比してデッキプレートの板厚が極端に薄いた
め、溶接法としては点溶接が採用されることになり、デ
ッキプレートの端縁を全周シーム溶接するわけではない
ので、雨水を遮断し得るような高度な止水性能は得られ
なかった。
However, conventionally, it has been impossible to block rainwater on the floor formed by the deck plate. As the reason, for example, the following matters can be considered. There was no need to stop rainwater as a functional form for floor concrete driving, and no countermeasures against rainfall with deck plates were conceived. The direction of the unevenness of the deck plate laid was varied, and the drainage of rainwater falling on the deck plate was not considered. However, since the girder steel frame is installed between the pillars with a camber (mukuri) upward so that it becomes horizontal when the concrete is loaded and the concrete weight is applied, it is placed on the girder steel frame. When a deck plate is laid, a drainage gradient can be obtained naturally, but in the past, there was no idea of blocking rainwater by the deck plate, so a series of drainage channels was formed by aligning the unevenness of the deck plate Until that was not done. The girders have to be studd dowels (shear connectors) to achieve structural integration with the floor concrete, so it is not possible to cover the entire upper surface with a deck plate. The deck plate is separated on both sides of the steel frame, and the opposing edges of the deck plates on both sides are placed on the end of the upper flange of the girder steel beam with a gap required for placing the stud dowel. Was. And, in this state, the edge of each deck plate is fixed by welding to the upper flange of the girder steel frame,
Since the plate thickness of the deck plate is extremely thin compared to the girder steel frame, spot welding will be adopted as the welding method, and the edge of the deck plate will not be seam welded all around, so rainwater will be shut off A high water stopping performance as high as possible could not be obtained.

【0004】[0004]

【発明が解決しようとする課題】本発明は、上記の点に
留意してなされたものであって、その目的とするところ
は、デッキプレートを用いて、雨水に対して遮断機能が
ある止水床を構成できる工法を提供することにある。
SUMMARY OF THE INVENTION The present invention has been made in view of the above points, and an object of the present invention is to use a deck plate to prevent rainwater from blocking water. An object of the present invention is to provide a construction method capable of constructing a floor.

【0005】[0005]

【課題を解決するための手段】上記の目的を達成するた
めに本発明が講じた技術的手段は次のとおりである。即
ち、本発明によるデッキプレートを用いた止水床工法
は、デッキプレートを梁鉄骨上に凹凸の向きを揃えて敷
き込み、凹凸長手方向に隣接するデッキプレート同士の
接続部に止水テープを貼着し、大梁鉄骨と平行方向につ
いては、大梁鉄骨の上に梁幅に対応する幅狭デッキプレ
ートを着脱可能な状態に敷設しておいて、止水の必要が
なくなった時点で、当該幅狭デッキプレートを取り外
し、大梁鉄骨と直交方向については、止水の必要がなく
なった時点で、大梁鉄骨の上に位置するデッキプレート
を梁幅に対応する幅にわたって切除することを特徴とし
ている。
The technical measures taken by the present invention to achieve the above object are as follows. That is, in the waterproof floor construction method using the deck plate according to the present invention, the deck plate is laid on the beam steel frame with the irregularities aligned, and a waterproof tape is attached to a connection portion between deck plates adjacent in the longitudinal direction of the irregularities. In the direction parallel to the girder steel frame, a narrow deck plate corresponding to the beam width is laid in a detachable state on the girder steel frame. The deck plate is removed, and in the direction orthogonal to the girders steel frame, the deck plate located on the girders steel frame is cut off over a width corresponding to the beam width when the need for water stoppage is eliminated.

【0006】[0006]

【作用】上記の工法によれば、大梁鉄骨の上にも、デッ
キプレートが敷設されており、しかも、デッキプレート
の凹凸の向きが揃っていて、凹凸長手方向に隣接するデ
ッキプレート同士の接続部に止水テープが貼着されてい
るので、デッキプレート上に降った雨水は、凹凸に沿っ
て流下し、排水されることになる。大梁鉄骨の上面を覆
うデッキプレートは、そのままでは、後工程でデッキプ
レート上に打設される床コンクリートと大梁鉄骨との構
造的一体化を妨げることになるが、上記の工法によれ
ば、大梁鉄骨と平行方向については、大梁鉄骨の上に梁
幅に対応する幅狭のデッキプレートを着脱可能な状態に
敷設しておいて、止水の必要がなくなった時点で、当該
幅狭デッキプレートを取り外し、大梁鉄骨と直交方向に
ついては、止水の必要がなくなった時点で、大梁鉄骨の
上に位置するデッキプレートを梁幅に対応する幅にわた
って切除するため、大梁鉄骨に対するスタッドジベル
(シャーコネクター)の打設には支障がなく、床コンク
リートと大梁鉄骨との構造的一体化を妨げることがな
い。
According to the above-mentioned construction method, the deck plate is laid also on the steel girder, and the direction of the unevenness of the deck plate is uniform, and the connecting portion of the deck plates adjacent to each other in the longitudinal direction of the unevenness. Since the waterproof tape is stuck on the deck plate, the rainwater falling on the deck plate flows down along the unevenness and is drained. The deck plate that covers the upper surface of the girder steel frame, if left as it is, will hinder the structural integration of the floor concrete and the girder steel frame that will be cast on the deck plate in a later process. In the direction parallel to the steel frame, a narrow deck plate corresponding to the beam width is laid in a detachable state on the girder steel frame, and when the water stoppage is no longer necessary, the narrow deck plate is removed. Stud dowels (shear connectors) for the girders in order to remove the deck plate above the girders in the direction perpendicular to the girders when the water stop is no longer necessary. There is no hindrance to the casting, and there is no hindrance to the structural integration between the floor concrete and the girders.

【0007】[0007]

【実施例】図1は、鉄骨造多層建物の全天候施工法の概
要を示す。図において、1は柱鉄骨、2は柱鉄骨1や梁
鉄骨等の揚重に使用されるタワークレーンである。鉄骨
の建方は、一般的な積層工法により、複数階分(例え
ば、3層分)を1節として下から順に行われる。
FIG. 1 shows an outline of an all-weather construction method for a steel-framed multi-story building. In the figure, 1 is a column steel frame, and 2 is a tower crane used for lifting column steel frame 1 and beam steel frame. The steel frame is erected from the bottom by a general laminating method with a plurality of stories (for example, three stories) as one section.

【0008】Aは、鉄骨建方を行う都度、最上階に設け
られたデッキプレートによる止水床であり、当該止水床
Aにより各節屋根面が構成され、内部が降雨に対して遮
蔽される。Bは各節の鉄骨側面に取り付けられた風防パ
ネルであり、当該風防パネルBにより各節壁面が構成さ
れ、内部が横降り雨と風に対して遮蔽される。3は各節
壁面の四隅に設けられた幅狭の風通しネットである。風
通しネット3は、内部の換気を行って、溶接作業等を行
う際の作業環境を良好に維持する役目を果たすものであ
るが、各節壁面全体としての横降り雨や風の遮蔽機能を
損なわないように可及的に幅狭に形成される。風防パネ
ルBは横降り雨と風に対して遮蔽するための専用の仮設
材であってもよいが、図示の実施例では、塔屋外壁用の
パネルを、予め、下部地盤面(図示の実施例では、低層
部の屋上スラブ)Sでの組立て作業により大型ユニット
化し、これを風防パネルBとして使用している。
[0010] A is a water-stop floor provided by a deck plate provided on the top floor every time a steel frame is constructed. The water-stop floor A forms a nodal roof surface, and the inside is shielded from rain. You. B is a windshield panel attached to the side of the steel frame of each node, and the windshield panel B constitutes each node wall, and the inside is shielded from falling down and rain and wind. 3 is a narrow ventilation net provided at the four corners of each joint wall. The ventilation net 3 serves to maintain the working environment when performing welding work and the like by performing internal ventilation, but impairs the function of shielding rainfall and wind from falling down as the entire joint wall surface. It is formed as narrow as possible so as not to be present. The windshield panel B may be a temporary material dedicated for shielding against rainfall and wind, but in the illustrated embodiment, the panel for the outdoor wall of the tower is previously provided with a lower ground surface (the illustrated embodiment). In U.S. Pat. No. 5,867,849, the large-scale unit is assembled by the assembling work on the roof slab (S) of the low-rise part, and this is used as the windshield panel B.

【0009】Cは窓ガラスの嵌め込まれたアルミ製のカ
ーテンウォールである。カーテンウォールCは、予め、
下部地盤面(図示の実施例では、低層部の屋上スラブ)
Sでの組立て作業により大型ユニット化されており、鉄
骨建方の進行につれて、ウインチ又はタワークレーン2
で吊り上げられ、下方の節から順次、建て込まれる。D
は、風防パネル(塔屋外壁用のパネル大型ユニット)B
のスライドアップ後、カーテンウォールCが建て込まれ
るまで鉄骨側面に貼られる安全ネットである。
C is an aluminum curtain wall fitted with window glass. The curtain wall C is
Lower ground surface (lower roof slab in the illustrated embodiment)
S has been made into a large unit by the assembly work. As the steel frame construction progresses, the winch or tower crane 2
And are built in order from the lower section. D
Is windshield panel (panel large unit for tower outdoor wall) B
After the slide-up, the safety net is attached to the side of the steel frame until the curtain wall C is built.

【0010】鉄骨造多層建物の全天候施工法の工程を図
2に基づいて説明すると次の通りである。 図2の(イ)に示すように、1節の鉄骨建方を行い、
最上階のデッキプレートを水密状に敷き込んで止水床A
を構成する。止水床Aにより1節目の各節屋根面が構成
され、内部が降雨に対して遮蔽されることになる。しか
る後、風防パネル(塔屋外壁用のパネル大型ユニット)
Bを鉄骨の側面に取り付ける。これにより、1節目の各
節壁面が構成され、内部が横降り雨と風に対して遮蔽さ
れることになる。この状態で、内部(二点斜線で示す部
分)の現場溶接作業を行う。 図2の(ロ)に示すように、2節の鉄骨建方を行う。
1節の場合と同じように、最上階のデッキプレートを水
密状に敷き込んで止水床Aを構成し、当該止水床Aによ
り2節目の各節屋根面を構成する。しかる後、風防パネ
ル(塔屋外壁用のパネル大型ユニット)Bを上方へスラ
イドアップし、2節の鉄骨の側面に取り付けて、2節目
の各節壁面を構成する。 図2の(ハ)に示すように、2節の内部(二点斜線で
示す部分)の現場溶接作業を行う。次いで、大型ユニッ
ト化したカーテンウォールCを1節の鉄骨側面に建て込
み、鉄骨工事以降の全天候施工壁面を構成する。 上記の〜の工程を繰り返し、最後に、図2の
(ニ)に示すように、屋上の所定の位置に風防パネル
(塔屋外壁用のパネル大型ユニット)Bを建て込み、塔
屋の外壁3を構成する。
The steps of the all-weather construction method for a steel-framed multi-story building will be described below with reference to FIG. As shown in Fig. 2 (a), perform the steel frame construction of one section,
Waterproof floor A by laying the deck plate on the top floor in a watertight manner
Is configured. The water stop floor A constitutes each knot roof surface of the first knot, and the inside is shielded from rain. After a while, windshield panel (large panel unit for tower outdoor wall)
B is attached to the side of the steel frame. Thereby, each node wall of the first node is configured, and the inside is shielded from rain falling down and wind. In this state, an internal welding operation (indicated by a two-point hatched portion) is performed. As shown in FIG. 2 (b), a two-section steel frame is constructed.
As in the case of the first section, the deck plate on the top floor is laid in a water-tight manner to form the water stop floor A, and the water stop floor A forms each node roof surface of the second section. Thereafter, the windshield panel (panel large unit for tower outdoor wall) B is slid up and attached to the side of the two-section steel frame to configure the second-section node walls. As shown in (c) of FIG. 2, an on-site welding operation is performed on the inside of the second section (the portion indicated by the two-point hatching). Next, the curtain wall C, which is made into a large unit, is erected on the side of the steel frame of one section to constitute the all-weather construction wall surface after the steel frame construction. Steps (1) to (4) are repeated, and finally, as shown in FIG. 2 (D), a windshield panel (a large panel unit for an outdoor wall of a tower) B is erected at a predetermined position on the roof to form the outer wall 3 of the tower. I do.

【0011】前記止水床Aは、図3に示すように、梁鉄
骨上にデッキプレート4を水密状に敷き込んで構成した
ものであり、次のようにして施工されている。即ち、デ
ッキプレート4は、その凹部によって一連の排水路を形
成するように梁鉄骨上に凹凸の向きを揃えて敷き込まれ
ている。図3の破線は大梁鉄骨5を示す。図示の実施例
では、X−X線の位置が棟となって最も高くなるよう
に、大梁鉄骨5にキャンバー(ムクリ)をつけてある。
従って、デッキプレート4上の雨水は棟(X−X線)を
中心としてその両側へ排水されることになる。
As shown in FIG. 3, the water-stopping floor A is constructed by laying a deck plate 4 on a beam steel frame in a watertight manner, and is constructed as follows. That is, the deck plate 4 is laid on the beam steel frame so as to form a series of drainage channels by the concave portions, with the directions of the concave and convex aligned. The broken line in FIG. In the illustrated embodiment, the beam girder 5 is provided with a camber so that the position of the XX line becomes the highest as a ridge.
Therefore, the rainwater on the deck plate 4 is drained to both sides of the ridge (XX line).

【0012】図3のaは資材の搬入・搬出に使用する仮
設開口、bは階段室開口である。これらの開口a,bに
は着脱自在な蓋体(図示せず)を設けて、降雨時には蓋
体で開口a,bを閉塞するようにしてある。タワークレ
ーン2が止水床Aを貫通する位置に設けられる場合、例
えば、タワークレーン用開口cを貫通するタワークレー
ン2のマストに、図4に示すように、タワークレーン用
開口cよりも大きなスカート状の庇(雨よけ)dを設け
る等して、降雨時に雨水が入り込まないように雨仕舞い
を施すものとする。図4に示す6は、鉄骨建方の進行に
伴い、最上階の下階まで施工された本設雨水配管であ
る。
FIG. 3A shows a temporary opening used for loading and unloading materials, and FIG. 3B shows a staircase opening. Removable lids (not shown) are provided in these openings a and b, and the openings a and b are closed by the lids during rainfall. When the tower crane 2 is provided at a position penetrating the water stop floor A, for example, a mast of the tower crane 2 penetrating the tower crane opening c has a skirt larger than the tower crane opening c as shown in FIG. A rain eaves (rain guard) d is provided to perform rain closing so that rainwater does not enter during rainfall. Reference numeral 6 shown in FIG. 4 denotes a permanent rainwater pipe constructed to the lower floor of the top floor as the steel frame is being built.

【0013】凹凸長手方向に隣接するデッキプレート
4,4同士の接続部は、互いに端縁を突き合わせてあ
り、図5や図9に示すように、接続部の上面に、片面に
粘着剤の塗布された止水テープ7を貼着することによっ
て水漏れを防止している。図5中の破線矢印は、雨水の
排水方向を示している。
The connecting portions of the deck plates 4 and 4 which are adjacent to each other in the longitudinal direction of the concavo-convex face each other with their edges abutting each other. As shown in FIGS. Water leakage is prevented by attaching the waterproofing tape 7 that has been applied. The dashed arrow in FIG. 5 indicates the direction of drainage of rainwater.

【0014】大梁鉄骨5と平行方向については、デッキ
プレート4の割付けを事前に検討し、図6に示すよう
に、大梁鉄骨5の上に梁幅に対応する幅、つまり、スタ
ッドジベル(シャコネクター)の打設に必要な幅に設定
された1山タイプの幅狭デッキプレート4aを着脱可能
な状態に敷設してある。そして、止水の必要がなくなっ
た時点で、つまり、次の各節屋根面が形成された時点
で、当該幅狭デッキプレート4aを取り外し、大梁鉄骨
5の上面を露出させるように構成してある。従って、図
7に示すように、大梁鉄骨5の上面に直接、スタッドジ
ベル(シャコネクター)8を打設でき、大梁鉄骨5と床
コンクリート9との構造的一体化が達成されることにな
る。
In the direction parallel to the girder steel frame 5, the layout of the deck plate 4 is considered in advance, and as shown in FIG. 6, a width corresponding to the beam width, ie, a stud dowel (sha connector) ), A single deck type narrow deck plate 4a set to a width necessary for the casting is laid in a detachable state. Then, at the time when the water stoppage is no longer required, that is, at the time when the next knotted roof surface is formed, the narrow deck plate 4a is removed, and the upper surface of the girders steel frame 5 is exposed. . Therefore, as shown in FIG. 7, the stud dowel (sha connector) 8 can be cast directly on the upper surface of the girder steel frame 5, and the structural integration of the girder steel frame 5 and the floor concrete 9 is achieved.

【0015】尚、デッキプレート4の割付けの都合上、
1山タイプの幅狭デッキプレート4aが大梁鉄骨5の真
上からずれ、当該幅狭デッキプレート4aを取り外した
状態において、大梁鉄骨5と隣接するデッキプレート4
との間に床コンクリートの流れ出す程度の隙間が生じる
個所については、図8に示すように、1山タイプの幅狭
デッキプレート4aを取り外した後、大梁鉄骨5の上面
にフラッシングプレート10を点溶接して、上記の隙間を
閉塞するものとする。
Incidentally, due to the layout of the deck plate 4,
The single deck type narrow deck plate 4a is displaced from directly above the large beam steel frame 5, and in a state where the narrow deck plate 4a is removed, the deck plate 4 adjacent to the large beam steel frame 5 is removed.
As shown in FIG. 8, after removing the single-mount narrow deck plate 4a, the flashing plate 10 is spot-welded to the upper surface of the girder steel frame 5 at a location where a gap is generated to allow the floor concrete to flow. Then, the above gap is closed.

【0016】大梁鉄骨5と直交方向については、止水の
必要がなくなった時点(次の各節屋根面が形成された時
点)で、大梁鉄骨5の上に位置するデッキプレート4
を、図10に示すように、電気溶断器11等により、梁幅
に対応する幅(スタッドジベルの打設に必要な幅)にわ
たって切除して、大梁鉄骨5の上面を露出させるように
構成してある。図10の破線は、切断位置を示す。従っ
て、図11に示すように、直交方向の大梁鉄骨5の上面
にも直接、スタッドジベル(シャコネクター)8を打設
でき、大梁鉄骨5と床コンクリート9との構造的一体化
が達成されることになる。
In the direction orthogonal to the girder steel frame 5, the deck plate 4 positioned on the girder steel frame 5 at the time when the water stoppage is no longer necessary (at the time when the next joint roof surface is formed).
As shown in FIG. 10, is cut off by an electric fusible device 11 or the like over a width corresponding to the beam width (the width required for placing a stud dowel) to expose the upper surface of the steel girder 5. It is. The broken line in FIG. 10 indicates the cutting position. Therefore, as shown in FIG. 11, the stud dowel (sha connector) 8 can be directly cast on the upper surface of the girder steel frame 5 in the orthogonal direction, and the structural integration of the girder steel frame 5 and the floor concrete 9 is achieved. Will be.

【0017】尚、この実施例では、大梁鉄骨5の上に位
置するデッキプレート4を切断する際、大梁鉄骨5を損
傷することがないよう、図5、図9、図10に示すよう
に、大梁鉄骨5の上面中央部に10mm角程度の太さのゴ
ム製スペーサー12を粘着剤により貼着してある。このス
ペーサー12は床コンクリート9を打設する前に剥がし取
られるものである。
In this embodiment, as shown in FIGS. 5, 9 and 10, in order to prevent the steel beams 5 from being damaged when cutting the deck plate 4 located on the steel beams 5 as shown in FIG. A rubber spacer 12 having a thickness of about 10 mm square is attached to the center of the upper surface of the girder steel frame 5 with an adhesive. The spacer 12 is peeled off before the floor concrete 9 is cast.

【0018】また、この実施例では、図3に示すよう
に、階段室開口b,bの間に位置する大梁鉄骨5が平面
視で斜め方向に架設されており、図3、図4に示すよう
に、この部分に敷設されたデッキプレート4の凹凸長手
方向が他のデッキプレート4の凹凸長手方向に対して傾
斜しているので、この斜めになったデッキプレート4に
ついて次のような止水対策を講じてある。
In this embodiment, as shown in FIG. 3, a girder steel frame 5 located between the staircase openings b, b is erected in an oblique direction in plan view, as shown in FIGS. As described above, the longitudinal direction of the unevenness of the deck plate 4 laid in this portion is inclined with respect to the longitudinal direction of the unevenness of the other deck plates 4. Measures have been taken.

【0019】即ち、図3において、凹凸が上下方向から
斜め方向に変わる部位については、図12に示すよう
に、大梁鉄骨5の両側のデッキプレート4,4が、予
め、所定間隙を隔てた状態に設けられているが、端部の
凸部(山)の下面にコンクリート流れ止め13を設けると
共に、少なくとも凹部には止水テープ(図示せず)を貼
着し、図12に破線矢印で示すように、雨水が大梁鉄骨
5を越えて排水されるようにしてある。図示しないが、
図3における右側の階段室開口b近くの凹凸が上下方向
から斜め方向に変わる部位にも止水テープを貼着してあ
る。
That is, in FIG. 3, as for the portion where the unevenness changes from the vertical direction to the oblique direction, as shown in FIG. , A concrete flow stopper 13 is provided on the lower surface of the convex portion (mountain) at the end, and a waterproof tape (not shown) is attached to at least the concave portion, and is indicated by a broken line arrow in FIG. In this way, rainwater is drained beyond the girders 5. Although not shown,
A waterproof tape is also attached to a portion where the unevenness near the opening b of the right staircase in FIG. 3 changes from the vertical direction to the oblique direction.

【0020】図3において、左側の階段室開口b近くの
凹凸が斜め方向から上下方向に変わる部位については、
図5、図13に示すように、大梁鉄骨5を跨ぐ鋼板製の
止水カバー14を設けて、大梁鉄骨5の上を雨水が流れな
いようにしてある。
In FIG. 3, the portion where the unevenness near the left side staircase opening b changes from an oblique direction to a vertical direction is as follows.
As shown in FIGS. 5 and 13, a water stop cover 14 made of a steel plate is provided so as to straddle the girders 5 so that rainwater does not flow on the girders 5.

【0021】止水床Aを柱鉄骨1が貫通する部位につい
ては、次のような止水対策が講じられている。即ち、図
14〜図16に示すように、デッキプレート4の水下側
端縁と柱鉄骨1との当接部において、デッキプレート4
の水下側端縁の凸部(山)を押し潰して(所謂エンドク
ローズ止めを行って)、凹部(谷)の雨水が柱鉄骨1の
両側に位置するデッキプレート4の凹部へと排水される
ように構成してある。図14〜図16において、15は柱
鉄骨1の側面に溶接された平鋼板よりなるデッキプレー
ト受けである。デッキプレート受け15は、大梁鉄骨5の
上面と面一に設定されており、デッキプレート4の水下
側端縁と柱鉄骨1との当接部の微小な隙間から漏れ出た
雨水を受け止め、水下側に排水する役目を果たしてい
る。
The following waterproof measures are taken for the portion where the column steel frame 1 penetrates the waterproof floor A. That is, as shown in FIGS. 14 to 16, at the contact portion between the underwater edge of the deck plate 4 and the column steel frame 1, the deck plate 4
The ridges (mountains) at the lower edge of the underwater are crushed (so-called end-closing is stopped), and the rainwater in the recesses (valleys) is drained into the recesses of the deck plate 4 located on both sides of the columnar steel frame 1. It is configured so that: 14 to 16, reference numeral 15 denotes a deck plate receiver made of a flat steel plate welded to the side surface of the column steel frame 1. The deck plate receiver 15 is set flush with the upper surface of the girder steel frame 5, and receives rainwater leaking from a minute gap between the lower edge of the deck plate 4 and the column steel frame 1, It plays the role of draining down the water.

【0022】止水床Aの周囲に位置する外周部の大梁鉄
骨5の外側には、図3、図14〜図16に示すように、
薄鉄板製の横樋16が止水床Aの全周にわたって設けられ
ている。17は外周部の大梁鉄骨5に片持ちの小梁鉄骨18
を介して支持された小梁鉄骨であり、前記外周部の大梁
鉄骨5に沿って環状に配置されている。前記横樋16は、
図15、図16に示すように、前記小梁鉄骨18と前記外
周部の大梁鉄骨5との間に嵌め込まれた状態に設けられ
ている。19は小梁鉄骨18の外端部上面に溶接された断面
L字形の床コンクリートの端面せき板である。
As shown in FIG. 3 and FIGS. 14 to 16, on the outer side of the girder steel frame 5 in the outer peripheral portion located around the water stop floor A,
A gutter 16 made of a thin iron plate is provided over the entire circumference of the water stop floor A. 17 is a small cantilever steel frame 18 on the outer girders steel frame 5
And is arranged in an annular shape along the large beam 5 at the outer periphery. The gutter 16 is
As shown in FIGS. 15 and 16, it is provided so as to be fitted between the small beam steel frame 18 and the large beam steel frame 5 on the outer peripheral portion. Reference numeral 19 denotes an end weir plate made of floor concrete having an L-shaped cross section welded to the upper surface of the outer end of the small beam steel frame 18.

【0023】前記横樋16の所々には、図16に示すよう
に、網20付きの接続金物を介して、塩化ビニル製の仮設
縦樋21が接続されており、仮設縦樋21は蛇腹ホース等の
可撓管22を介して下階に施工された本設雨水配管6に接
続されている。従って、止水床A(デッキプレート4
上)を流れて来た雨水は、横樋16、仮設縦樋21、可撓管
22を経て、本設雨水配管6へと排水されることになる。
As shown in FIG. 16, a temporary downspout 21 made of vinyl chloride is connected to the downspout 16 via a connection hardware having a net 20, as shown in FIG. Is connected to the main rainwater pipe 6 constructed on the lower floor through a flexible pipe 22 of the present invention. Therefore, the water stop floor A (deck plate 4
The rainwater that has flowed through the upper part) is horizontal gutter 16, temporary downspout 21, flexible pipe
After 22, the water is drained to the rainwater piping 6.

【0024】尚、上記の通り、本設雨水配管6を鉄骨工
事と並行して施工し、鉄骨工事中から雨水を本設雨水配
管6に流すため、地中の雨水排水埋設管の作業は、鉄骨
建方に先立って早い時期に行っておくものとする。
As described above, the permanent rainwater pipe 6 is constructed in parallel with the steel frame work, and the rainwater flows into the main rainwater pipe 6 during the steel frame work. It shall be performed at an early stage prior to steel frame construction.

【0025】[0025]

【発明の効果】本発明は、上述した構成よりなり、大梁
鉄骨の上にも、デッキプレートを敷設し、しかも、デッ
キプレートの凹凸の向きを揃え、凹凸長手方向に隣接す
るデッキプレート同士の接続部に止水テープを貼着する
ので、デッキプレート上に降った雨水は、凹凸に沿って
流下し、排水されることになる。大梁鉄骨の上面を覆う
デッキプレートは、そのままでは、後工程でデッキプレ
ート上に打設される床コンクリートと大梁鉄骨との構造
的一体化を妨げることになるが、本発明によれば、大梁
鉄骨と平行方向については、大梁鉄骨の上に梁幅に対応
する幅狭のデッキプレートを着脱可能な状態に敷設して
おいて、止水の必要がなくなった時点で、当該幅狭デッ
キプレートを取り外し、大梁鉄骨と直交方向について
は、止水の必要がなくなった時点で、大梁鉄骨の上に位
置するデッキプレートを梁幅に対応する幅にわたって切
除するため、大梁鉄骨に対するスタッドジベル(シャー
コネクター)の打設には支障がなく、床コンクリートと
大梁鉄骨との構造的一体化を妨げることがない。従っ
て、デッキプレートを用いて、雨水に対して遮断機能が
ある止水床を構成できるのである。
According to the present invention, a deck plate is laid on a steel girder having the structure described above, and the direction of the unevenness of the deck plate is aligned, and the deck plates adjacent to each other in the longitudinal direction of the unevenness are connected. Since the waterproof tape is attached to the part, the rainwater that has fallen on the deck plate flows down along the unevenness and is drained. The deck plate covering the upper surface of the girder steel frame, as it is, will hinder the structural integration of the floor concrete and the girder steel frame that are cast on the deck plate in a later process. In the direction parallel to the above, a narrow deck plate corresponding to the beam width is laid in a detachable state on the girder steel frame, and when the water stoppage is no longer necessary, the narrow deck plate is removed. In the direction orthogonal to the girder steel, when the need for water stop is no longer required, the stud dowel (shear connector) for the girder steel is used to cut off the deck plate located above the girder steel over the width corresponding to the beam width. There is no hindrance to the casting, and it does not hinder the structural integration between the floor concrete and the girders. Therefore, it is possible to construct a water stoppage having a function of blocking rainwater using the deck plate.

【図面の簡単な説明】[Brief description of the drawings]

【図1】鉄骨造多層建物の全天候施工法を説明する斜視
図である。
FIG. 1 is a perspective view illustrating an all-weather construction method for a steel-framed multi-story building.

【図2】鉄骨造多層建物の全天候施工法の工程説明図で
ある。
FIG. 2 is a process explanatory view of an all-weather construction method for a steel-framed multi-story building.

【図3】鉄骨各節の最上階の止水床の概略平面図であ
る。
FIG. 3 is a schematic plan view of a waterproof floor on the top floor of each steel frame section.

【図4】要部の概略斜視図である。FIG. 4 is a schematic perspective view of a main part.

【図5】要部の斜視図である。FIG. 5 is a perspective view of a main part.

【図6】要部の縦断面図である。FIG. 6 is a longitudinal sectional view of a main part.

【図7】床コンクリートを打設した状態における要部の
縦断面図である。
FIG. 7 is a longitudinal sectional view of a main part in a state where floor concrete is cast.

【図8】要部の縦断面図である。FIG. 8 is a longitudinal sectional view of a main part.

【図9】要部の斜視図である。FIG. 9 is a perspective view of a main part.

【図10】要部の縦断面図である。FIG. 10 is a longitudinal sectional view of a main part.

【図11】床コンクリートを打設した状態における要部
の縦断面図である。
FIG. 11 is a longitudinal sectional view of a main part in a state where floor concrete is cast.

【図12】要部の縦断面図である。FIG. 12 is a longitudinal sectional view of a main part.

【図13】要部の縦断面図である。FIG. 13 is a longitudinal sectional view of a main part.

【図14】要部の平面図である。FIG. 14 is a plan view of a main part.

【図15】要部の縦断面図である。FIG. 15 is a longitudinal sectional view of a main part.

【図16】要部の一部切欠き斜視図である。FIG. 16 is a partially cutaway perspective view of a main part.

【符合の説明】[Description of sign]

A…止水床、4…デッキプレート、4a…幅狭デッキプ
レート、5…大梁鉄骨、7…止水テープ。
A: water-stop floor, 4: deck plate, 4a: narrow deck plate, 5: steel beam, 7: water-stop tape.

フロントページの続き (72)発明者 松川 正仁 大阪市中央区本町4丁目1番13号 株式 会社竹中工務店大阪本店内 (56)参考文献 特開 昭54−71823(JP,A) 特開 昭61−36441(JP,A) 特開 昭58−26157(JP,A) 実開 昭63−128797(JP,U) 実開 昭49−35530(JP,U) 実開 昭63−53420(JP,U) 実開 昭63−21427(JP,U) (58)調査した分野(Int.Cl.7,DB名) E04B 5/40 E04D 3/38 E04G 21/28 Continuation of front page (72) Inventor Masahito Matsukawa 4-1-1-13 Honcho, Chuo-ku, Osaka-shi Takenaka Corporation Osaka Main Store (56) References JP-A-54-71823 (JP, A) JP-A-61 JP-A-64441 (JP, A) JP-A-58-26157 (JP, A) JP-A-63-128797 (JP, U) JP-A-49-35530 (JP, U) JP-A-63-53420 (JP, U) (Japanese) Sho-63-21427 (JP, U) (58) Fields investigated (Int. Cl. 7 , DB name) E04B 5/40 E04D 3/38 E04G 21/28

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 デッキプレートを梁鉄骨上に凹凸の向き
を揃えて敷き込み、凹凸長手方向に隣接するデッキプレ
ート同士の接続部に止水テープを貼着し、大梁鉄骨と平
行方向については、大梁鉄骨の上に梁幅に対応する幅狭
デッキプレートを着脱可能な状態に敷設しておいて、止
水の必要がなくなった時点で、当該幅狭デッキプレート
を取り外し、大梁鉄骨と直交方向については、止水の必
要がなくなった時点で、大梁鉄骨の上に位置するデッキ
プレートを梁幅に対応する幅にわたって切除するように
したことを特徴とするデッキプレートを用いた止水床工
法。
Claims: 1. A deck plate is laid on a beam steel frame with the direction of unevenness aligned, and a waterproof tape is attached to a connection portion of deck plates adjacent to each other in a longitudinal direction of the unevenness. A narrow deck plate corresponding to the beam width is laid in a detachable state on the girder steel frame, and when it is no longer necessary to stop water, the narrow deck plate is removed, and the direction orthogonal to the girder steel frame is removed. Is a cut-off floor method using a deck plate, in which the deck plate located above the steel girders is cut off over a width corresponding to the beam width when the need for water stop is eliminated.
JP35427292A 1992-12-15 1992-12-15 Water stoppage method using deck plate Expired - Fee Related JP2999896B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP35427292A JP2999896B2 (en) 1992-12-15 1992-12-15 Water stoppage method using deck plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP35427292A JP2999896B2 (en) 1992-12-15 1992-12-15 Water stoppage method using deck plate

Publications (3)

Publication Number Publication Date
JPH06185155A JPH06185155A (en) 1994-07-05
JPH073932A JPH073932A (en) 1995-01-06
JP2999896B2 true JP2999896B2 (en) 2000-01-17

Family

ID=18436431

Family Applications (1)

Application Number Title Priority Date Filing Date
JP35427292A Expired - Fee Related JP2999896B2 (en) 1992-12-15 1992-12-15 Water stoppage method using deck plate

Country Status (1)

Country Link
JP (1) JP2999896B2 (en)

Also Published As

Publication number Publication date
JPH06185155A (en) 1994-07-05
JPH073932A (en) 1995-01-06

Similar Documents

Publication Publication Date Title
SK19395A3 (en) Element based foam and concrete modular wall construction and method and apparatus thereof
CN113309353A (en) Underground chamber roof post-cast strip advanced sealing structure and construction method
EP0537189A1 (en) A method of erecting a foundation structure for a building substructure.
JP2999896B2 (en) Water stoppage method using deck plate
JP2796301B2 (en) Concrete wall method
CN115075834A (en) Cross subdivision section structure of electric power tunnel and construction method
JP2788383B2 (en) Construction method of rooftop parapet of building
JP2994243B2 (en) External wall construction method and external wall structure for underground structures
JP4030717B2 (en) Corrosion-resistant treatment method for concrete frame surface
JP3605296B2 (en) Building and building construction methods
CN218092163U (en) Post-cast strip water retaining device
JP2002097760A (en) Terraced roof structure
JP2572272Y2 (en) Water impervious gantry and water impervious system using it for building construction sites
JP2871297B2 (en) Construction method of building roof
CN212506722U (en) Integral prefabricated balcony module adopting light ribbon board
CN217079458U (en) Floor support plate steel reinforced concrete combined stair
JPH06146311A (en) Construction method of underground work by completely automatic building construction system
JP2574095Y2 (en) Building gantry and rain curing system using the same
JP2742009B2 (en) Metal roofing structure
JPH0881964A (en) Body structure of building with underground section and execution method thereof
JP2618559B2 (en) Joint structure of unit with handrail wall
JPH0714482Y2 (en) Middle pillar mounting structure for balcony or terrace
JPH0714517Y2 (en) Waterproof structure for roof panel connections
JP2002061393A (en) Roof for raining countermeasure at time of construction of steel pipe concrete composite structure, and raining countermeasure method
JPH0649938A (en) Construction of building and rain water drainage structure in constructing

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees