JP2902635B1 - How to build a fence - Google Patents

How to build a fence

Info

Publication number
JP2902635B1
JP2902635B1 JP15798298A JP15798298A JP2902635B1 JP 2902635 B1 JP2902635 B1 JP 2902635B1 JP 15798298 A JP15798298 A JP 15798298A JP 15798298 A JP15798298 A JP 15798298A JP 2902635 B1 JP2902635 B1 JP 2902635B1
Authority
JP
Japan
Prior art keywords
mortar
connection unit
main body
fence
outer frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP15798298A
Other languages
Japanese (ja)
Other versions
JPH11350802A (en
Inventor
博 福永
Original Assignee
有限会社福永博建築研究所
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 有限会社福永博建築研究所 filed Critical 有限会社福永博建築研究所
Priority to JP15798298A priority Critical patent/JP2902635B1/en
Application granted granted Critical
Publication of JP2902635B1 publication Critical patent/JP2902635B1/en
Publication of JPH11350802A publication Critical patent/JPH11350802A/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Fencing (AREA)

Abstract

【要約】 【課題】 設置及び撤去の両方を簡便に行える塀の構築
方法を提供することを目的とする。 【解決手段】 複数のブロック1を塀本体5の構築ライ
ンに沿って配置する工程と、ブロックの縦目地1aにモ
ルタルを所定間隔毎に埋める工程と、モルタルに打ち込
まれるアンカーボルト6を備えた台部2と棚本体の外枠
下部5a、5bに密着できるように構成された第1連結
ユニット3とを剛結したものを、モルタルを埋めた縦目
地上に配置する工程と、ブロックの縦目地の寸法系に合
わせて組み立てられた塀本体の外枠下部を、第1連結ユ
ニットに連結する工程と、モルタルの乾燥後にアンカー
ボルトを締め込む工程とを含む。
An object of the present invention is to provide a method for constructing a fence that can be easily installed and removed. SOLUTION: A step of arranging a plurality of blocks 1 along a construction line of a wall main body 5, a step of burying mortar at predetermined intervals in vertical joints 1a of the blocks, and a table provided with anchor bolts 6 driven into the mortar. Arranging a rigidly connected part 2 and a first connecting unit 3 configured to be able to be in close contact with the outer frame lower parts 5a and 5b of the shelf main body on a vertical ground filled with mortar; Connecting the lower part of the outer frame of the wall main body assembled according to the dimensional system to the first connection unit, and tightening the anchor bolt after the mortar is dried.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、設置作業及び撤去
作業が容易な塀の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a fence that can be easily installed and removed.

【0002】[0002]

【従来の技術】従前より、屋外の空間を区画するため、
塀が広く使用されている。ところで、従来の塀では、単
に地面に打ち込むだけのものを除くと、地中に基礎を打
設し、この基礎から、塀本体とほぼ等しい高さを有する
一本の柱を垂直に立て、柱間に塀本体を固定していた。
2. Description of the Related Art Conventionally, in order to partition an outdoor space,
Fences are widely used. By the way, in conventional fences, except for those that are simply driven into the ground, a foundation is cast in the ground, and from this foundation, one pillar having a height approximately equal to the wall of the fence stands upright, The fence body was fixed between them.

【0003】[0003]

【発明が解決しようとする課題】ところが、このように
すると、塀本体とほぼ等しい高さの柱を、まるごと一本
使用せねばならず、材料の無駄が多い。
However, in this case, one pillar having almost the same height as the main body of the wall must be used as a whole, resulting in a large waste of material.

【0004】又、塀本体は、現場で組み立てるのではな
く、通常、工場などで既に組み立てられており、高い寸
法精度を有する。このため、上記柱にも同様の位置精度
が要求されることになり、柱の設置作業が難しくなりが
ちである。
[0004] The wall body is not assembled on site, but is usually assembled in a factory or the like, and has high dimensional accuracy. For this reason, the same positional accuracy is required also for the above-mentioned pillar, and the installation work of the pillar tends to be difficult.

【0005】加えて、塀を撤去する際には、柱を基礎ご
と引き抜かねばならず、撤去作業が大変である。
[0005] In addition, when removing the fence, the pillar must be pulled out together with the foundation, and the removal operation is difficult.

【0006】そこで本発明は、設置及び撤去の両方を簡
便に行える塀の構築方法を提供することを目的とする。
Accordingly, an object of the present invention is to provide a method of constructing a fence that can be easily installed and removed.

【0007】[0007]

【課題を解決するための手段】本発明の塀の構築方法で
は、複数のブロックを塀本体の構築ラインに沿って配置
する工程と、ブロックの縦目地にモルタルを所定間隔毎
に埋める工程と、モルタルに打ち込まれるアンカーボル
トを備えた台部と棚本体の外枠下部に密着できるように
構成された第1連結ユニットとを剛結したものを、モル
タルを埋めた縦目地上に配置する工程と、ブロックの縦
目地の寸法系に合わせて組み立てられた塀本体の外枠下
部を、第1連結ユニットに連結する工程と、モルタルの
乾燥後にアンカーボルトを締め込む工程とを含む。
According to the fence construction method of the present invention, a step of arranging a plurality of blocks along a construction line of a fence main body, and a step of burying mortar at predetermined intervals in vertical joints of the blocks; A step of arranging a base unit having an anchor bolt driven into the mortar and a first connection unit configured to be able to adhere to the lower part of the outer frame of the shelf main body on a vertical mesh surface filled with mortar; Connecting the lower part of the outer frame of the wall body assembled to the size system of the vertical joints of the block to the first connection unit, and tightening the anchor bolts after the mortar is dried.

【0008】この構成により、設置及び撤去の両方を簡
便に行える塀の構築方法を実現できる。
[0008] With this configuration, it is possible to realize a method of constructing a fence that can be easily installed and removed.

【0009】[0009]

【発明の実施の形態】請求項1記載の塀の構築方法で
は、複数のブロックを塀本体の構築ラインに沿って配置
する工程と、ブロックの縦目地にモルタルを所定間隔毎
に埋める工程と、モルタルに打ち込まれるアンカーボル
トを備えた台部と棚本体の外枠下部に密着できるように
構成された第1連結ユニットとを剛結したものを、モル
タルを埋めた縦目地上に配置する工程と、ブロックの縦
目地の寸法系に合わせて組み立てられた塀本体の外枠下
部を、第1連結ユニットに連結する工程と、モルタルの
乾燥後にアンカーボルトを締め込む工程とを含む。
In the method for constructing a fence according to the first aspect, a step of arranging a plurality of blocks along a construction line of a wall main body, and a step of burying mortar at predetermined intervals in vertical joints of the blocks; A step of arranging a base unit having an anchor bolt driven into the mortar and a first connection unit configured to be able to adhere to the lower part of the outer frame of the shelf main body on a vertical mesh surface filled with mortar; Connecting the lower part of the outer frame of the wall body assembled to the size system of the vertical joints of the block to the first connection unit, and tightening the anchor bolts after the mortar is dried.

【0010】以上の構成において、台部及びこれに剛結
された第1連結ユニットを、縦目地上に配置する際、こ
の配置の位置精度は、さほど高くなくて良い。ここで、
塀本体の寸法精度は高いので、本来、この配置の位置精
度も高くなくてはならないのであるが、アンカーボルト
が入り込むモルタルは、未だ非乾燥状態にあるので、ア
ンカーボルトはモルタル内で移動できる状態にある。
In the above arrangement, when the base and the first connection unit rigidly connected to the base are arranged on the ground, the positional accuracy of the arrangement does not need to be very high. here,
Since the dimensional accuracy of the fence body is high, the positional accuracy of this arrangement must also be high, but the mortar into which the anchor bolt enters is still in a non-dry state, so the anchor bolt can be moved within the mortar. It is in.

【0011】即ち、塀本体を、台部及び第1連結ユニッ
トに連結すると、台部及び第1連結ユニット側が、塀本
体側の位置にならって位置修正され、結果的に、台部及
び第1連結ユニットの位置精度が高くなる。
That is, when the wall main body is connected to the base and the first connecting unit, the base and the first connecting unit are corrected in position according to the position of the wall main body, and as a result, the base and the first connecting unit are adjusted. The positional accuracy of the connecting unit is increased.

【0012】以上の理由により、台部及び第1連結ユニ
ットの配置について、厳密な位置管理は不要であり、簡
便に配置できる。
For the above reasons, strict position management is not required for the arrangement of the base and the first connecting unit, and the arrangement can be performed easily.

【0013】又、第1連結ユニットは、塀本体の下部に
密着できれば十分であり、塀本体の高さとほぼ等しい柱
を用いていた従来技術に比べ、材料の無駄を少なくする
ことができる。
Further, it is sufficient that the first connecting unit can be in close contact with the lower part of the wall main body, and the waste of material can be reduced as compared with the prior art in which a column almost equal in height to the wall main body is used.

【0014】さらに、塀を撤去する際には、台部のアン
カーボルトを引き抜くだけでよく、容易に撤去作業を行
える。
Further, when removing the fence, it is only necessary to pull out the anchor bolts of the pedestal portion, and the removal operation can be easily performed.

【0015】請求項2記載の塀の構築方法では、塀本体
は、第1連結ユニットの真上に配置される第2連結ユニ
ットにも連結される。
[0015] In the wall construction method according to the second aspect, the wall main body is also connected to the second connection unit disposed directly above the first connection unit.

【0016】この構成により、隣接する塀本体同士を強
固に連結できる。また、このようにしても、柱をまるご
と一本使用する場合に比べると、材料の無駄が少ない。
With this configuration, the adjacent fence bodies can be strongly connected to each other. In addition, even in this case, waste of material is small as compared with a case where one pillar is used as a whole.

【0017】次に図面を参照しながら、本発明の実施の
形態について説明する。図1は、本発明の一実施の形態
における塀の斜視図、図2は同正面図、図3は図1A−
A断面図である。
Next, an embodiment of the present invention will be described with reference to the drawings. FIG. 1 is a perspective view of a wall according to an embodiment of the present invention, FIG. 2 is a front view of the same, and FIG.
It is A sectional drawing.

【0018】図1において、1は、基礎F(図2)上に
直線状に積まれるブロックであり、一定位置に縦目地1
aを有する。
In FIG. 1, reference numeral 1 denotes a block which is linearly stacked on a foundation F (FIG. 2), and a vertical joint 1 is fixed at a predetermined position.
a.

【0019】2は、この縦目地1a上に一定間隔毎に固
定される台部である。台部2には、略門型の第1連結ユ
ニット3が剛結されている。そして、台部2及び第1連
結ユニット3が配置される縦目地1aには、モルタルが
埋められる。
Reference numeral 2 denotes a base fixed on the vertical joint 1a at regular intervals. A substantially gate-shaped first connection unit 3 is rigidly connected to the base 2. The mortar is buried in the vertical joints 1a where the base 2 and the first connection unit 3 are arranged.

【0020】台部2は、図4(a),(b)に示すよう
に、凸状の縦断面を有し、左右が一段低い段差部2a、
2bとなっている。なお、図4では、関係をわかりやす
くするために、台部2と第1連結ユニット3とを分離し
て表示しているが、上述したように、台部2と第1連結
ユニット3とは、既に剛結され、これらは一体物となっ
ている。
As shown in FIGS. 4 (a) and 4 (b), the base portion 2 has a convex vertical cross section, and the step portion 2a on the left and right is one step lower.
2b. In FIG. 4, the base 2 and the first connection unit 3 are separately illustrated for easy understanding of the relationship. However, as described above, the base 2 and the first connection unit 3 , Already rigidly connected, and these are one.

【0021】そして、段差部2a、2bの外側には、上
方に突出するダボ8が打ってあり、塀本体5の外枠下部
5a、5bの下端部に掘られたダボ孔5cが、ダボ8と
係合することにより、塀本体5に対して、台部2及び第
1連結ユニット3の位置決めが行われる。ここで、モル
タルが非乾燥状態にある間、台部2を上下に貫通するア
ンカーボルト6は、モルタル内での移動を許される。即
ち、ダボ孔5cがダボ8に係合すると、台部2及び第1
連結ユニット3は、塀本体5の高い位置精度にならって
位置修正される。
A dowel 8 projecting upward is struck on the outside of the steps 2a and 2b, and a dowel hole 5c dug at the lower end of the outer frame lower part 5a and 5b of the fence body 5 is formed. The positioning of the base portion 2 and the first connection unit 3 with respect to the wall main body 5 is performed by engaging with the main body 5. Here, while the mortar is in a non-dry state, the anchor bolts 6 that penetrate the pedestal 2 up and down are allowed to move in the mortar. That is, when the dowel hole 5c engages with the dowel 8, the base 2 and the first
The position of the connecting unit 3 is corrected according to the high positional accuracy of the wall body 5.

【0022】又、図2に示すように、隣接する塀本体5
同士は、上述の第1連結ユニット3と、より上方の第2
連結ユニット4とにより、面状に連結される。
Also, as shown in FIG.
Are connected to the first connection unit 3 described above and the second upper unit
With the connection unit 4, they are connected in a planar manner.

【0023】第2ユニット4は、図2の一部拡大図に示
しているように、内部空間からその両側面まで貫通する
ボルト孔4aを有する。又、第1連結ユニット3も同様
のボルト孔を持つ。
As shown in a partially enlarged view of FIG. 2, the second unit 4 has a bolt hole 4a penetrating from the internal space to both side surfaces thereof. The first connection unit 3 also has a similar bolt hole.

【0024】そして、図4(a)に示しているように、
これらのボルト孔に連結ボルト7を通し、塀本体5の外
枠にねじ止めするものである。
Then, as shown in FIG.
The connection bolts 7 are passed through these bolt holes and screwed to the outer frame of the wall main body 5.

【0025】即ち、本形態の構築方法によれば、次の手
順で塀を構築する。
That is, according to the construction method of this embodiment, a fence is constructed in the following procedure.

【0026】まず、複数のブロック1を塀本体5の構築
ラインに沿って配置する。
First, a plurality of blocks 1 are arranged along the construction line of the wall main body 5.

【0027】次に、ブロック1の縦目地1aにモルタル
を所定間隔毎に埋める。
Next, mortar is buried in the vertical joints 1a of the block 1 at predetermined intervals.

【0028】そして、台部2と第1連結ユニット3を縦
目地1aに配置をするため、アンカーボルト6を、モル
タルに打ち込む。
Then, the anchor bolt 6 is driven into the mortar to arrange the base 2 and the first connection unit 3 on the vertical joint 1a.

【0029】次に、塀本体5の外枠下部5a、5bを、
第1連結ユニット3に連結する。また、塀本体5の上部
を、第1連結ユニット3の真上に配置される第2連結ユ
ニット4に連結する。
Next, the outer frame lower portions 5a and 5b of the wall main body 5 are
The first connection unit 3 is connected. In addition, the upper part of the wall main body 5 is connected to the second connection unit 4 disposed directly above the first connection unit 3.

【0030】そして、モルタルの乾燥後にアンカーボル
ト6を締め込む。これにより、棚本体5にならって位置
修正された台部2及び第1連結ユニット3は、修正され
た位置に拘束される。
After the mortar has dried, the anchor bolt 6 is tightened. As a result, the base 2 and the first connecting unit 3 whose positions have been corrected following the shelf body 5 are restrained at the corrected positions.

【0031】[0031]

【発明の効果】本発明は、以上のように構成したので、
柱をまるごと一本使用するよりも、材料の無駄が少な
い。また、台部などの設置は、厳密な位置管理を要せ
ず、簡便に行える。さらに、撤去は、アンカーボルトの
引き抜きのみで、容易である。
The present invention is configured as described above.
Less waste of material than using a single column. In addition, the installation of the pedestal or the like can be easily performed without requiring strict position management. Further, removal is easy only by pulling out the anchor bolt.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施の形態における塀の斜視図FIG. 1 is a perspective view of a wall according to an embodiment of the present invention.

【図2】同正面図FIG. 2 is a front view of the same.

【図3】図1A−A断面図FIG. 3 is a cross-sectional view of FIG. 1A-A.

【図4】(a)図1B部拡大図 (b)同台部の平面図4A is an enlarged view of FIG. 1B part, and FIG. 4B is a plan view of the base part.

【符号の説明】[Explanation of symbols]

1 ブロック 1a 縦目地 2 台部 3 第1連結ユニット 4 第2連結ユニット 5 塀本体 5a,5b 外枠下部 5c ダボ孔 6 アンカーボルト 7 連結ボルト 8 ダボ DESCRIPTION OF SYMBOLS 1 block 1a vertical joint 2 base part 3 1st connection unit 4 2nd connection unit 5 Fence main body 5a, 5b Lower part of outer frame 5c Dowel hole 6 Anchor bolt 7 Connection bolt 8 Dowel

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】複数のブロックを塀本体の構築ラインに沿
って配置する工程と、 前記ブロックの縦目地にモルタルを所定間隔毎に埋める
工程と、 前記モルタルに打ち込まれるアンカーボルトを備えた台
部と棚本体の外枠下部に密着できるように構成された第
1連結ユニットとを剛結したものを、前記モルタルを埋
めた前記縦目地上に配置する工程と、 前記ブロックの縦目地の寸法系に合わせて組み立てられ
た塀本体の外枠下部を、前記第1連結ユニットに連結す
る工程と、 前記モルタルの乾燥後に前記アンカーボルトを締め込む
工程とを含むことを特徴とする塀の構築方法。
1. A step of arranging a plurality of blocks along a construction line of a wall main body, a step of burying mortar at predetermined intervals in vertical joints of the blocks, and a base having an anchor bolt driven into the mortar. Arranging a rigid connection between the mortar and a first connection unit configured to be able to adhere to the lower part of the outer frame of the shelf main body on the vertical joint ground filled with the mortar; A method of constructing a fence, comprising: a step of connecting a lower portion of an outer frame of a wall body assembled according to the first connection unit to the first connection unit; and a step of tightening the anchor bolts after the mortar is dried.
【請求項2】前記塀本体は、前記第1連結ユニットの真
上に配置される第2連結ユニットにも連結されることを
特徴とする請求項1記載の塀の構築方法。
2. The method according to claim 1, wherein the wall body is also connected to a second connection unit disposed directly above the first connection unit.
JP15798298A 1998-06-05 1998-06-05 How to build a fence Expired - Fee Related JP2902635B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15798298A JP2902635B1 (en) 1998-06-05 1998-06-05 How to build a fence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15798298A JP2902635B1 (en) 1998-06-05 1998-06-05 How to build a fence

Publications (2)

Publication Number Publication Date
JP2902635B1 true JP2902635B1 (en) 1999-06-07
JPH11350802A JPH11350802A (en) 1999-12-21

Family

ID=15661668

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15798298A Expired - Fee Related JP2902635B1 (en) 1998-06-05 1998-06-05 How to build a fence

Country Status (1)

Country Link
JP (1) JP2902635B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106013954B (en) * 2016-07-07 2018-08-21 中建海峡建设发展有限公司 A kind of construction method of combination enclosing

Also Published As

Publication number Publication date
JPH11350802A (en) 1999-12-21

Similar Documents

Publication Publication Date Title
JP2902635B1 (en) How to build a fence
JP4628838B2 (en) Steel foundation structure
JP3084654B2 (en) Construction foundation, foundation structure using the same, and construction method thereof
JP2813605B2 (en) Construction foundation and construction method
JP3246321B2 (en) Column and pile joint structure
JPH077386Y2 (en) Foundation structure for building columns
JP2583058B2 (en) Basement method
JP3078236U (en) Gate pillar
JP2812925B2 (en) Box structure and its construction method
JP2611917B2 (en) Pillar formwork equipment
JP2577642B2 (en) How to build underground structures
KR100549849B1 (en) Shelf of charnel house
JP2004353254A (en) Foundation structure of building and its construction method
JP2709551B2 (en) Prefabricated foundation member and its construction method
JPH09217357A (en) Anchor frame
JPH0727790Y2 (en) Trough support pile
JP5341683B2 (en) Seismic reinforcement method for existing buildings
JP3018430U (en) Concrete gatepost
JP3261526B2 (en) Anchor frame for steel pier and footing using the same
JP2577385Y2 (en) Wall panel installation structure
JPH0797826A (en) Unit building and construction method therefor
JPH057314Y2 (en)
JPH06108705A (en) Constructing method for outer wall
JPH09112084A (en) Column foundation member and installing method of fence by using column foundation member thereof
JP2001197647A (en) Special area of common ducts for electric cable

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090319

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090319

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100319

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110319

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110319

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120319

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130319

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140319

Year of fee payment: 15

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees