JP2700781B2 - Construction method of soil cement pile - Google Patents

Construction method of soil cement pile

Info

Publication number
JP2700781B2
JP2700781B2 JP7235223A JP23522395A JP2700781B2 JP 2700781 B2 JP2700781 B2 JP 2700781B2 JP 7235223 A JP7235223 A JP 7235223A JP 23522395 A JP23522395 A JP 23522395A JP 2700781 B2 JP2700781 B2 JP 2700781B2
Authority
JP
Japan
Prior art keywords
excavation
soil
cement
subsequent
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7235223A
Other languages
Japanese (ja)
Other versions
JPH0978571A (en
Inventor
秀隆 小野寺
Original Assignee
株式会社丸徳基業
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社丸徳基業 filed Critical 株式会社丸徳基業
Priority to JP7235223A priority Critical patent/JP2700781B2/en
Publication of JPH0978571A publication Critical patent/JPH0978571A/en
Application granted granted Critical
Publication of JP2700781B2 publication Critical patent/JP2700781B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、柱列杭によるソイ
ルセメント連続壁などのソイルセメント杭の施工法に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a soil cement pile such as a continuous soil cement wall using a columnar pile.

【0002】[0002]

【従来の技術】ソイルセメント連続地中壁は、アースオ
ーガによる掘削時に、掘削土とセメントミルク等の硬化
材とを攪拌してソイルセメントの杭体を地中に製作する
が、かかる杭体を重ね合わせた柱列杭壁を施工してなる
ものである。
2. Description of the Related Art A soil cement continuous underground wall is manufactured by excavating soil and a hardened material such as cement milk to excavate a soil cement pile underground when excavating with an earth auger. It is constructed by superimposing pillar row pile walls.

【0003】図3にかかるソイルセメント連続壁を施工
するための従来の掘削工法を示すと、図中1はオーガ
で、これは周知のごとく、油圧モータ等の駆動装置2に
より回転駆動されるスクリュー掘削軸3の先端を掘削ヘ
ッド4とし、この掘削軸3の内部を通過するセメントミ
ルク等の硬化材を掘削ヘッド4から注入できるようにし
ている。なお、図示は省略するが、駆動装置2はベース
マシンのリーダマストから昇降自在に吊り下げられ、ま
た、掘削軸3は適宜継ぎ足して長尺とすることができ
る。また、掘削軸3は不連続のものでもよい。
[0003] Fig. 3 shows a conventional excavation method for constructing a soil cement continuous wall. In the figure, reference numeral 1 denotes an auger, which is a well-known screw which is rotationally driven by a driving device 2 such as a hydraulic motor. The tip of the drilling shaft 3 is a drilling head 4, and a hardening material such as cement milk passing through the inside of the drilling shaft 3 can be injected from the drilling head 4. Although not shown, the driving device 2 is suspended from the leader mast of the base machine so as to be able to move up and down, and the excavating shaft 3 can be extended by being appropriately extended. Further, the excavating shaft 3 may be discontinuous.

【0004】オーガ1の位置決めを行い(A)、オーガ
1の掘削軸3の掘削ヘッド4を正転させ、削孔を開始す
る。その際、セメントミルク等の硬化材5とエアーを掘
削ヘッド4から出して孔内に注入する(B)。
The auger 1 is positioned (A), and the excavating head 4 of the excavating shaft 3 of the auger 1 is rotated forward to start drilling. At this time, hardening material 5 such as cement milk and air are taken out of the excavating head 4 and injected into the hole (B).

【0005】このように正転しながら所定深さまで注
入、削孔を継続したならば(C)(D)、引き上げを開
始し、その際も硬化材5を注入する。この引き上げは正
転と逆転を交互に繰り返す、正転・逆転による(E)。
[0005] If the injection and drilling are continued to a predetermined depth while rotating forward as described above, (C) and (D), the lifting is started, and the hardening material 5 is also injected at that time. This pulling is performed by normal rotation and reverse rotation, alternately repeating normal rotation and reverse rotation (E).

【0006】ある程度引き上げたならば、再度、正転・
逆転で掘削および攪拌を行い(F)、最後に逆転しなが
ら引き上げを行う(G)。
[0006] Once raised to some extent, the normal rotation
Excavation and agitation are performed by reversing (F), and finally lifting is performed while reversing (G).

【0007】このようにしてソイルセメントによる連続
地中壁を施工するには、オーガ1として単軸掘削機を使
用する場合は、図4に示すように一本置きの間隔を存し
て先行掘削を行い、その後にこの先行掘削間を後行掘削
する方法と、図5に示すように一本一本順次端から重ね
合わせながらつなげて行く方法とがあり、さらに、図6
に示すように多軸掘削機でも同様に一本(多軸の場合は
その軸数の連続した孔が形成される)置きの間隔を存し
て先行掘削を行い、その後にこの先行掘削間を後行掘削
する方法と、図示は省略するが一本一本順次端から重ね
合わせながらつなげて行く方法とがある。
[0007] In order to construct a continuous underground wall using soil cement in this way, when a single-screw excavator is used as the auger 1, preceding excavation is performed at every other interval as shown in FIG. 4. After that, there is a method in which the preceding excavation is performed in a backward excavation, and a method in which the excavations are sequentially connected one by one as shown in FIG.
As shown in the figure above, the multi-screw excavator also performs pre-drilling at intervals of one drill (in the case of multi-screw, continuous holes of the same number of shafts), and There is a method of excavation at a later time, and a method of connecting one by one one by one while sequentially omitting them, although not shown.

【0008】いずれにせよ、ソイルセメントの柱列杭に
よる連続地中壁工法は、原土に硬化材5としてのセメン
トミルク(セメント+ベントナイト+水)を改良土量m
2 ×60%位を注入し、攪拌して壁体を構築する工法であ
る。
[0008] In any case, the continuous underground wall construction method using the column piles of soil cement is performed by adding cement milk (cement + bentonite + water) as the hardening material 5 to the original soil with an improved soil volume m.
This is a method of injecting around 2 × 60% and stirring to build a wall.

【0009】例えば、巾50cm、深さ20m、長さ1mの1
ユニットの壁を築造するには、 0.5 × 2.0×1×0.5 =6m3 となり、約6m3 のセメントミルクの注入が必要とな
る。この6m3 のセメントミルクをオーガ1の掘削と同
時に注入し、所定深さまで注入しながら削孔し、かつ、
オーガ1の引き抜き時にも若干注入し、ターニング(正
転・逆転)を行いながら施工する。
For example, a 50 cm wide, 20 m deep, 1 m long 1
In order to build the wall of the unit, 0.5 × 2.0 × 1 × 0.5 = 6 m 3 , and about 6 m 3 of cement milk is required. Cement milk of 6 m 3 was injected at the same time as drilling auger 1, and drilling while injecting up to a predetermined depth, and,
Even when the auger 1 is pulled out, it is slightly injected, and the work is performed while turning (forward / reverse).

【0010】[0010]

【発明が解決しようとする課題】ところで、セメントミ
ルクの注入量以上分の(ソイルセメントと原土の混合し
た)産業廃棄物残土が発生する。ちなみに、前記図3の
従来工法では(A)〜(G)の全ての工程でかかる産業
廃棄物残土が発生する。そして、処分のために莫大な費
用が必要となる。一方、掘削土と硬化材とは必要以上の
量がオーガの正転・逆転により攪拌混合されるため、こ
のオーガに余分な負担がかかり効率的な作業を望むこと
はできない。
By the way, industrial waste remnants (mixture of soil cement and raw soil) are generated in excess of the amount of cement milk injected. Incidentally, in the conventional method shown in FIG. 3, such industrial waste residue is generated in all the steps (A) to (G). And enormous costs are required for disposal. On the other hand, an excessive amount of the excavated soil and the hardened material is agitated and mixed by the forward and reverse rotation of the auger, so that an extra load is imposed on the auger and efficient work cannot be desired.

【0011】本発明の目的は前記従来例の不都合を解消
し、ソイルセメント杭による連続地中壁を施工するため
の工法として、産業廃棄物残土をほとんど発生させずに
施工でき、工費も低廉ですみ、しかも工期の短縮化が図
れるソイルセメント杭の施工法を提供することにある。
An object of the present invention is to solve the above-mentioned disadvantages of the prior art, and as a construction method for constructing a continuous underground wall using a soil cement pile, the construction can be performed with almost no generation of residual soil of industrial waste, and the construction cost is low. Another object of the present invention is to provide a soil cement pile construction method capable of shortening the construction period.

【0012】[0012]

【課題を解決するための手段】本発明は前記目的を達成
するため、予め先行掘削としてセメントミルク等の硬化
材を注入する量に応じた量の掘削土を地上に排土し、そ
の後、この先行掘削による杭孔にこれと芯を同一にして
後行掘削を行い、かかる後行掘削と同時にセメントミル
ク等の硬化材を注入して、後行掘削での掘削土と硬化材
とを混合すること、または、この構成に加えて、先行掘
削は後行掘削とは別の掘削手段で行い、後行掘削はソイ
ルセメント杭造成機で行うこと、もしくは、先行掘削は
後行掘削と同一の掘削手段で、セメントミルク等の硬化
材を注入せずに行うことを要旨とするものである。
According to the present invention, in order to achieve the above object, an amount of excavated soil corresponding to an amount of a hardened material such as cement milk is previously discharged to the ground as advance excavation. The excavation is performed with the same core as the excavation, and a hardening material such as cement milk is injected at the same time as the latter excavation, and the excavated soil and hardened material in the latter excavation are mixed. In addition to this configuration, the preceding excavation shall be performed by a different excavation means than the subsequent excavation, and the subsequent excavation shall be performed by a soil cement pile builder, or the preceding excavation shall be the same as the subsequent excavation The gist of the invention is to perform the method without injecting a hardening material such as cement milk.

【0013】請求項1記載の本発明によれば、先行掘削
で地上に排土するのは原土としての一般残土であり、こ
れは産業廃棄物とせずに処分できる。そして、セメント
ミルク等の硬化材と掘削土との混合は、硬化材はこの排
土された部分に充填したものであり、掘削土は先行掘削
の後の後行掘削する際に発生するものを利用し、かかる
硬化材と掘削土との混合でソイルセメント杭体を構築す
るものであるから、産業廃棄物残土を発生させずに施工
できる。また、セメントミルク等の硬化材は排土ととも
に捨てられることがないので、無駄のない経済的な利用
となる。しかも、後行掘削は、先行掘削による杭孔を更
に芯を同一にして削孔するものであり、かかる後行掘削
での掘削土量が少なくてすむため工期を短縮することが
できる。とくに、後行掘削ではセメントミルク等の硬化
材を注入して、この硬化材と掘削土とを混合するため、
掘削土量が少ないことは大きなメリットとなる。
According to the first aspect of the present invention, what is discharged to the ground in the preceding excavation is the general remaining soil as the original soil, which can be disposed without being turned into industrial waste. The mixing of the hardened material such as cement milk and the excavated soil is based on the fact that the hardened material is filled into the excavated portion, and the excavated soil is generated when the subsequent excavation is performed after the preceding excavation. Since the soil cement pile is constructed by using such a hardened material and excavated soil, it can be constructed without generating industrial waste residual soil. Further, the hardened material such as cement milk is not discarded together with the earth removal, so that it is economical without waste. In addition, in the subsequent excavation, the pile hole formed by the preceding excavation is further drilled with the same core, and the amount of excavated soil in the subsequent excavation can be reduced, so that the construction period can be shortened. In particular, in subsequent excavation, inject hardened material such as cement milk and mix this hardened material with excavated soil,
The small amount of excavated soil is a great advantage.

【0014】請求項2記載の本発明によれば、前記作用
に加えて、先行掘削は後行掘削とは別の掘削手段で行う
ことで、確実に必要な分量の排土を先行して行うことが
できる。
According to the second aspect of the present invention, in addition to the above-described operation, the preceding excavation is performed by another excavation means different from the subsequent excavation, so that the necessary amount of unloading is reliably performed in advance. be able to.

【0015】請求項3記載の本発明によれば、先行掘削
は後行掘削とは同一の掘削手段で、セメントミルク等の
硬化材を注入せずに行うことにより、連続した工程で先
行掘削から後行掘削へと移行できる。
According to the third aspect of the present invention, the preceding excavation is carried out by the same excavation means as the subsequent excavation without injecting a hardened material such as cement milk or the like. It is possible to shift to subsequent excavation.

【0016】[0016]

【発明の実施の形態】以下、図面について本発明の実施
の形態を詳細に説明する。図1は本発明のソイルセメン
ト杭の施工法の1実施形態の各工程を示すものである。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 shows each step of an embodiment of a method for constructing a soil cement pile according to the present invention.

【0017】まず、第1工程としてA,Bに示すよう
に、先行掘削孔6を削孔するが、この掘削土はほとんど
地上に排土する。なお、この掘削土は 100%を排土する
ものでなくともよい。そして、この掘削土は一般残土で
あり、産業廃棄物としてではなく処理でき、再利用も可
能である。
First, as shown in A and B in the first step, the preceding excavation hole 6 is drilled, and this excavated soil is almost entirely discharged to the ground. The excavated soil does not have to be 100% excavated. And this excavated soil is general surplus soil, which can be treated not as industrial waste but can be reused.

【0018】また、先行掘削孔6を削孔する掘削機とし
ては、特に限定はないが、ハンマグラブ、回転バケット
等ソイルセメント杭造成機以外の掘削機7が好適であ
る。
The excavator for drilling the preceding excavation hole 6 is not particularly limited, but an excavator 7 other than a soil cement pile forming machine such as a hammer grab and a rotary bucket is suitable.

【0019】次いで、第2工程としてCに示すようにこ
の先行掘削孔6内にこの先行掘削孔6と孔の芯が一致す
るように削孔をする後行掘削のためのソイルセメント杭
造成機であるオーガ1を所定位置にセットし、以下、前
記従来例と同じく、オーガ1の掘削軸3の掘削ヘッド4
を正転させ、後行掘削による削孔を開始する。その際、
セメントミルク等の硬化材5とエアーを掘削ヘッド4か
ら出して孔内に注入する(D)。
Next, as shown in C, as a second step, a soil cement pile forming machine for subsequent excavation in which drilling is performed in the preceding drilling hole 6 so that the core of the drilling hole 6 matches the center of the hole. The auger 1 is set at a predetermined position, and the excavating head 4 of the excavating shaft 3 of the auger 1
Is rotated forward to start drilling by trailing excavation. that time,
A hardening material 5 such as cement milk and air are taken out of the excavating head 4 and injected into the hole (D).

【0020】このように正転しながら所定深さまで注
入、削孔を継続したならば(E)、引き上げを開始し、
その際も硬化材5を注入する。この引き上げは正転と逆
転を交互に繰り返す、正転・逆転による(F)。
If the injection and drilling are continued to a predetermined depth while rotating forward as described above (E), the lifting is started,
At this time, the hardening material 5 is also injected. This pulling is performed by normal rotation and reverse rotation, which alternately repeat normal rotation and reverse rotation (F).

【0021】ある程度引き上げたならば、再度、正転・
逆転で掘削および攪拌を行い(G)、最後に逆転しなが
ら引き上げを行う(H)。
After raising to some extent, the normal rotation
Excavation and agitation are performed by reversing (G), and finally lifting is performed while reversing (H).

【0022】このように一般残土を排出した所に硬化材
5を充填し、後行掘削する際の掘削土はすべてこの硬化
材5と混合してソイルセメントとして利用するものであ
るので、産業廃棄物残土をほとんど発生させずに施工で
きる。
As described above, the hardened material 5 is filled in the place where the general surplus soil has been discharged, and all the excavated soil during subsequent excavation is mixed with the hardened material 5 and used as soil cement. It can be constructed with almost no remaining soil.

【0023】また、前記実施形態としては先行掘削にソ
イルセメント杭造成機以外の掘削機を使用し、後行掘削
に単軸のオーガを使用する場合について説明したが、図
示は省略するが、他の実施形態として、先行掘削も後行
掘削もともに多軸のオーガを使用する場合や、先行掘削
にも単軸のオーガを使用する場合も考えられる。
In the above embodiment, a case was described in which an excavator other than a soil cement pile forming machine was used for preceding excavation and a single-axis auger was used for subsequent excavation. In both of the preceding excavation and the subsequent excavation, a multi-axis auger may be used, or a single-axis auger may be used for the preceding excavation.

【0024】さらに、応用例として、単軸のオーガを用
いて一本置きの間隔を存して先行掘削孔を削孔するが、
この掘削土はほとんど地上に排土する。次いで、多軸掘
削機により後行掘削を行い、隣接する先行掘削孔同士を
つなげると同時に、多軸掘削機からセメントミルク等の
硬化材を注入して掘削土と混合し、ソイルセメントを得
るようにしてもよい。
Further, as an application example, a preceding excavation hole is drilled at every other interval using a uniaxial auger.
Most of this excavated soil is discharged to the ground. Then, the trailing excavation is performed by a multi-axis excavator, and adjacent preceding excavation holes are connected to each other, and at the same time, a hardening material such as cement milk is injected from the multi-axis excavator and mixed with the excavated soil to obtain soil cement. It may be.

【0025】図2は本発明の第2実施形態を示すもの
で、まず、第1工程としてA,Bに示すように、ソイル
セメント杭造成機であるオーガ1をセットし、先行掘削
孔6を削孔するが、この掘削土はほとんど地上に排土す
る。そして、この掘削土は一般残土であり、産業廃棄物
としてではなく処理でき、再利用も可能である。さらに
Cに示すように所定深度まで前記先行掘削孔6と孔の芯
を一致させて削孔を続行する。なお、この掘削土は 100
%を排土するものでなくともよい。
FIG. 2 shows a second embodiment of the present invention. First, as shown in A and B, an auger 1 which is a soil cement pile forming machine is set as a first step, and a preceding excavation hole 6 is formed. The excavated soil is almost excavated above the ground. And this excavated soil is general surplus soil, which can be treated not as industrial waste but can be reused. Further, as shown in C, the preceding excavation hole 6 is aligned with the core of the hole up to a predetermined depth, and drilling is continued. The excavated soil is 100
% Does not have to be removed.

【0026】次いで、第2工程としてDに示すようにセ
メントミルク等の硬化材5を注入しながら正転にてオー
ガ1を引き上げ、Eに示すように掘削ヘッド4を地表近
くまで引き上げる。
Next, as shown in D, the auger 1 is pulled up by normal rotation while pouring a hardening material 5 such as cement milk as shown in D, and the excavating head 4 is pulled up to near the ground surface as shown in E.

【0027】第3工程としてF,Gに示すように正転に
て掘削を行い、掘削孔壁内の未排土土砂と硬化材5とを
攪拌する。Hの引き上げでは、正転と逆転とを交互に繰
り返して行う。
In the third step, excavation is performed in a normal rotation as indicated by F and G, and the undischarged earth and sand in the wall of the excavation hole and the hardened material 5 are stirred. In raising H, normal rotation and reverse rotation are alternately repeated.

【0028】このように硬化材5を未注入にて掘削し、
所定深度に到達した後に、硬化材5を注入し引き上げる
ため、その時点での排土土砂は産業廃棄物とならず、さ
らに、掘削孔壁内に残っている土砂と硬化材5を攪拌削
孔することで良品のソイル壁を造成できる。
As described above, the hardening material 5 is excavated without being injected.
After reaching the predetermined depth, the hardened material 5 is injected and pulled up, so that the excavated earth and soil at that time does not become industrial waste, and furthermore, the sand and hardened material 5 remaining in the excavation hole wall are stirred and drilled. By doing so, you can create a good quality soil wall.

【0029】[0029]

【発明の効果】以上述べたように本発明のソイルセメン
ト杭の施工法は、ソイルセメントによる連続地中壁等を
施工するための工法として、産業廃棄物残土をほとんど
発生させずに施工でき、残土処理の工費も低廉ですむも
のである。
As described above, the method for constructing a soil cement pile according to the present invention is a method for constructing a continuous underground wall or the like using soil cement, and can be constructed with almost no residual industrial waste soil. The construction cost of the remaining soil is low.

【0030】また、セメントミルク等の硬化材は排土と
ともに捨てられることがないので、無駄のない経済的な
利用となる。
Further, the hardened material such as cement milk is not discarded together with the earth removal, so that it is economical to use without waste.

【0031】しかも、後行掘削は、先行掘削による杭孔
を更に芯を同一にして削孔することで、かかる後行掘削
での掘削土量を少なくでき、これにより工期の短縮化を
図ることができるものである。
Further, in the subsequent excavation, the amount of excavated soil in the subsequent excavation can be reduced by drilling the pile hole of the preceding excavation with the same core, thereby shortening the construction period. Can be done.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明のソイルセメント杭の施工法の第1実施
形態を示す各工程の説明図である。
FIG. 1 is an explanatory diagram of each step showing a first embodiment of a method for constructing a soil cement pile according to the present invention.

【図2】本発明のソイルセメント杭の施工法の第2実施
形態を示す各工程の説明図である。
FIG. 2 is an explanatory view of each step showing a second embodiment of the method for constructing a soil cement pile according to the present invention.

【図3】従来例を示す説明図である。FIG. 3 is an explanatory diagram showing a conventional example.

【図4】地中壁の施工手順の一例を示す説明図である。FIG. 4 is an explanatory diagram showing an example of a construction procedure of an underground wall.

【図5】地中壁の施工手順の他例を示す説明図である。FIG. 5 is an explanatory view showing another example of a procedure for constructing an underground wall.

【図6】地中壁の施工手順のさらに他例を示す説明図で
ある。
FIG. 6 is an explanatory view showing still another example of a construction procedure of an underground wall.

【符号の説明】[Explanation of symbols]

1…オーガ 2…駆動装置 3…掘削軸 4…掘削ヘッド 5…硬化材 6…先行掘削孔 7…掘削機 DESCRIPTION OF SYMBOLS 1 ... Auger 2 ... Drive device 3 ... Drilling shaft 4 ... Drilling head 5 ... Hardened material 6 ... Advance drilling hole 7 ... Excavator

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 予め先行掘削としてセメントミルク等の
硬化材を注入する量に応じた量の掘削土を地上に排土
し、その後、この先行掘削による杭孔にこれと芯を同一
にして後行掘削を行い、かかる後行掘削と同時にセメン
トミルク等の硬化材を注入して、後行掘削での掘削土と
硬化材とを混合することを特徴としたソイルセメント杭
の施工法。
An excavated soil in an amount corresponding to an amount of a hardening material such as cement milk to be injected in advance as a preliminary excavation is discharged on the ground in advance, and thereafter, the core is made identical to the core in the pile hole formed by the preliminary excavation. A method for constructing a soil-cement pile, comprising performing a line excavation, injecting a hardened material such as cement milk at the same time as the subsequent excavation, and mixing the excavated soil and the hardened material in the subsequent excavation.
【請求項2】 先行掘削は後行掘削とは別の掘削手段で
行い、後行掘削はソイルセメント杭造成機で行う請求項
1記載のソイルセメント杭の施工法。
2. The soil cement pile construction method according to claim 1, wherein the preceding excavation is performed by a different excavation means than the subsequent excavation, and the subsequent excavation is performed by a soil cement pile forming machine.
【請求項3】 先行掘削は後行掘削と同一の掘削手段
で、セメントミルク等の硬化材を注入せずに行う請求項
1記載のソイルセメント杭の施工法。
3. The method for constructing a soil cement pile according to claim 1, wherein the preceding excavation is performed by the same excavation means as the subsequent excavation without injecting a hardening material such as cement milk.
JP7235223A 1995-09-13 1995-09-13 Construction method of soil cement pile Expired - Lifetime JP2700781B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7235223A JP2700781B2 (en) 1995-09-13 1995-09-13 Construction method of soil cement pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7235223A JP2700781B2 (en) 1995-09-13 1995-09-13 Construction method of soil cement pile

Publications (2)

Publication Number Publication Date
JPH0978571A JPH0978571A (en) 1997-03-25
JP2700781B2 true JP2700781B2 (en) 1998-01-21

Family

ID=16982912

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7235223A Expired - Lifetime JP2700781B2 (en) 1995-09-13 1995-09-13 Construction method of soil cement pile

Country Status (1)

Country Link
JP (1) JP2700781B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100447347C (en) * 2003-11-26 2008-12-31 株式会社丸德基业 Construction method of cement earth pile
JP5634036B2 (en) * 2009-06-03 2014-12-03 株式会社大林組 Method for constructing retaining wall, method for constructing pile, retaining wall, pile
JP5443928B2 (en) * 2009-09-30 2014-03-19 株式会社大林組 Method for constructing soil cement structure, soil cement structure
CN104912059B (en) * 2015-06-30 2016-12-14 重庆环德科技有限公司 Stir into a kind of usage of wall telephone
CN109403316A (en) * 2018-10-31 2019-03-01 中铁建工集团有限公司 A kind of manually digging hole combines the pile base construction method of realization with mechanical hole building

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2686445B2 (en) * 1989-09-11 1997-12-08 東急建設株式会社 Soil cement water blocking wall construction method and its equipment

Also Published As

Publication number Publication date
JPH0978571A (en) 1997-03-25

Similar Documents

Publication Publication Date Title
JPH10204876A (en) Soil improvement method by using pile
JP2700781B2 (en) Construction method of soil cement pile
JP2806217B2 (en) Underground excavator
JP4796197B2 (en) Ground improvement body construction apparatus and ground improvement body construction method
JP3158053U (en) Ground improvement body construction equipment
JP2700765B2 (en) Underground wall construction method
JP2589274B2 (en) Excavation method
JP3727017B2 (en) Construction method of soil cement pile
JP3706354B2 (en) Construction method of soil cement pile
JPH01219212A (en) Pile or continuous wall and its constructing method
JP2017057705A (en) Construction method of continuous soil cement underground wall
JPH09268554A (en) Construction method of basic pile and device thereof
JP3907538B2 (en) Pile construction method and pile head extension and rotation device used therefor
JP2886365B2 (en) Construction method of pile
JP2698768B2 (en) Method of forming underground continuous wall
JPH05239988A (en) Automatic excavating method for deep based pile and associated excavating machine
JP2004300847A (en) Construction method for columnar foundation improvement body using steel pipe pile
JP2000345546A (en) Improvement method for soft ground containing hard stratum
JP3099041B2 (en) Pile construction method
JP2899671B2 (en) Continuous drilling soil cement wall method and construction excavator
JP2836808B2 (en) Drill stirrer for soil cement pile method
JP2943675B2 (en) Construction method of retaining wall
JP2929981B2 (en) Excavation and stirrer for ground
JPS63197718A (en) Construction work of in-situ pile
JPH03140594A (en) Construction work of water-stopping shaft

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091003

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 14

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313113

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111003

Year of fee payment: 14

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121003

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121003

Year of fee payment: 15

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131003

Year of fee payment: 16

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term