Beam deformation control method and device

Info

Publication number
JP2635900B2
JP2635900B2 JP5011338A JP1133893A JP2635900B2 JP 2635900 B2 JP2635900 B2 JP 2635900B2 JP 5011338 A JP5011338 A JP 5011338A JP 1133893 A JP1133893 A JP 1133893A JP 2635900 B2 JP2635900 B2 JP 2635900B2
Authority
JP
Japan
Prior art keywords
cable
bracket
load
post
tension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP5011338A
Other languages
Japanese (ja)
Other versions
JPH062436A (en
Inventor
公彦 最上
正夫 宮口
攻 松井
輝夫 瀬川
政章 小島
正 山口
惺 谷口
幸荘 古川
克也 岡田
智久 奥野
公男 菊池
康夫 河田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP5011338A priority Critical patent/JP2635900B2/en
Publication of JPH062436A publication Critical patent/JPH062436A/en
Application granted granted Critical
Publication of JP2635900B2 publication Critical patent/JP2635900B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、多層の上部構造体の荷
重を大スパンの梁に支持させて下部に大空間を形成する
建築物の前記梁等を対象とする梁の変形制御技術に関す
る。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a beam deformation control technique for a beam having a multi-layered upper structure supported by a beam having a large span and forming a large space below the beam. .

【0002】[0002]

【従来の技術】上記のように下部に大空間を備えた建築
物では、上部構造体の大荷重で梁がたわまないようにす
ることが肝要である。そのため、一般には、梁として大
なる上部構造荷重に抗してたわまない高剛性の梁を用い
る手段と、支持すべき上部構造荷重によってたわむ量に
応じたむくりを梁に与えて、上部構造荷重の全部を支持
した状態で梁が水平等の所定の姿勢になるようにする手
段とのいずれかが採用される。ところが、前者手段によ
るときは、高剛性を得るために梁が大型化、大重量化
し、施工面およびコスト面で不利である。それに対し、
後者手段によるときは、梁を小型、軽量なものにできる
利点がある。そして、むくり付きの梁を用いるに、従来
では、このむくり付きの梁を柱にわたって架設したの
ち、そのむくり付きの梁に上部構造荷重を支持させるよ
うに上部構造体を構築していた。
2. Description of the Related Art In a building having a large space in the lower part as described above, it is important to prevent the beams from bending under the heavy load of the upper structure. Therefore, in general, a beam using a high-rigidity beam that does not bend against a large superstructure load as a beam, and giving the beam a flexure corresponding to the amount of deflection due to the superstructure load to be supported, Either of means for maintaining the beam in a predetermined posture such as horizontal while supporting all the structural loads is employed. However, when using the former means, the beam becomes large and heavy in order to obtain high rigidity, which is disadvantageous in terms of construction and cost. For it,
The latter means has the advantage that the beam can be made smaller and lighter. Conventionally, in order to use a stripped beam, after constructing the stripped beam over a column, the upper structure was constructed so that the stripped beam would support the superstructure load. .

【0003】[0003]

【発明が解決しようとする課題】ところが、前記従来手
段によるときは、上部構造体の構築に伴って上部構造荷
重が増加するにつれて梁がたわみ変形し、支持すべき上
部構造荷重の全部が梁に作用した時点で梁が水平等の所
定の姿勢になるものの、上部構造体の構築途中では、梁
が所定の姿勢とはならない。従って、多層の上部構造体
を複数層づつに分けて順に積上げ式に構築していく場
合、先に建込まれた下層部の柱や梁の姿勢がその後の上
層部の構築によって変化する。そのため、上部構造体に
取付けた外壁材や仕上げ材の姿勢調整を上部構造体の構
築と並行して行えずに、上部構造体の構築の完了を待っ
て行う必要があり、工期の長期化を招来していた。本発
明の目的は、上部構造体に取付けた外壁材や仕上げ材の
調整をその上部構造体の構築と並行して行えるように梁
の変形を制御できる梁の変形制御方法を提供する点にあ
る。
However, according to the conventional means, the beam is flexed and deformed as the superstructure load increases with the construction of the superstructure, and the entire superstructure load to be supported is applied to the beam. Although the beam assumes a predetermined posture such as horizontal at the time of acting, the beam does not assume the predetermined posture during the construction of the upper structure. Therefore, when a multi-layered upper structure is divided into a plurality of layers and sequentially constructed in a stacked manner, the posture of the lower pillars or beams previously built changes depending on the subsequent construction of the upper layer. Therefore, it is not possible to adjust the posture of the outer wall material and finishing material attached to the upper structure in parallel with the construction of the upper structure. Was calling. An object of the present invention is to provide a beam deformation control method capable of controlling the deformation of a beam so that adjustment of an outer wall material and a finishing material attached to an upper structure can be performed in parallel with construction of the upper structure. .

【0004】[0004]

【課題を解決するための手段】本発明による梁の変形制
御方法の特徴は、柱間にむくりを付与した梁を架設し、
その梁の長手方向の中間に立てたポストの上端部と、梁
の長手方向の延長上に位置する状態で前記柱よりも横側
外方に突出させたブラケットの突出端との間に斜材を架
設し、その斜材に張力を付与することにより、所定の姿
勢に前記梁をたわみ変形させ、その後、支持すべき上部
構造荷重の全部が梁に作用するまで、梁の所定の姿勢か
ら元の姿勢側への復元を阻止してその梁を所定の姿勢に
維持する点にある。
SUMMARY OF THE INVENTION The feature of the beam deformation control method according to the present invention is that a beam having a hollow between columns is erected.
A diagonal member is provided between the upper end of the post erected in the middle of the beam in the longitudinal direction and the protruding end of the bracket protruding laterally outward from the column in a state positioned on the longitudinal extension of the beam. The beam is flexed and deformed to a predetermined posture by applying tension to the diagonal member, and then the beam is returned from the predetermined posture until the entire upper structure load to be supported acts on the beam. Is prevented from restoring to the posture side, and the beam is maintained in a predetermined posture.

【0005】本発明による梁の変形制御装置の特徴は、
柱間に架設したむくりを付与した梁の長手方向の中間に
ポストを立て、梁の長手方向の延長上に位置する状態で
前記柱よりも横側外方にブラケットを突出させ、前記ポ
ストの上端部とブラケットの突出端との間に斜材を架設
し、その斜材に張力を付与する張力付与手段を設けてあ
る点にある。
The characteristics of the beam deformation control device according to the present invention are as follows.
A post is erected in the middle of the longitudinal direction of the beam provided with the peeling provided between the columns, and a bracket is protruded laterally outward from the column in a state of being positioned on the longitudinal extension of the beam, and The point is that a diagonal member is provided between the upper end portion and the protruding end of the bracket, and tension applying means for applying tension to the diagonal member is provided.

【0006】[0006]

【作用】上記の方法によれば、梁を所定の姿勢にたわみ
変形させた後、その上部構造荷重の全部が梁に作用する
までその梁の元の姿勢への復元を阻止して所定の姿勢に
維持するから、前記梁の所定の姿勢を、上部構造荷重の
全部が梁に作用した場合の姿勢又はそれに近い姿勢に設
定しておくことにより、上部構造体の構築に伴って梁に
作用する上部構造荷重が次第に増加するものの、その荷
重増加にかかわらず先に構築された上部構造体部分の変
形を防止して、構築完了時の姿勢に支持することができ
る。そして、前記梁を所定の姿勢にたわみ変形させる
に、梁に立てたポストの上端とブラケットの突出端との
間に架設した斜材に張力を付与するとにより、図12
に示すように、 《1》ポストからの下向き荷重F1 《2》梁上辺に沿った圧縮力F2 《3》ブラケットのうち斜材と連結する突出端がから
突出(に対して偏心)していることによる付加曲げモ
ーメントMの3つを梁に作用させ、これら3つの協同に
より、梁を所定の姿勢にわみ変形させるから、梁を所
定の姿勢にたわみ変形させるための操作が梁上方からの
操作となり、梁下側の空間をその梁の変形操作やそのた
めの装置類で占有することがなく、梁下側の空間を、他
の用途に使用可能なように開放維持することができるの
みならず、次の作用がある。すなわち、ポストと斜材と
を用いて梁を変形制御する手法としては、ポストの上端
と梁の両端やとの間に斜材を架設し、その斜材に張力
を付与する手法も考えられるが、この場合は、前述した
《1》《2》の2つが発生するものの、《3》が発生し
ない。従って、《1》《2》《3》の3つを発生させる
本発明の場合は、付与した張力を梁のたわみ変形に有効
に利用することができて、変形制御のために使用する油
圧ジャッキなどアクチエーターが小型のもので済む。も
ちろん、例えば梁にウェイト荷重をかけることにより、
梁をたわみ変形させる場合には、ウェイトとして梁の曲
げ剛性に見合った重さのものが必要で、ウェイトが大型
化して取扱い面で不便であるが、本発明では、斜材への
張力付与により梁をたわみ変形させるから、ポスト及び
斜材、斜材に張力を付与する油圧ジャッキ等の取扱い易
い装置で済む。
According to the above-described method, after the beam is flexed and deformed to a predetermined posture, the beam is prevented from restoring to the original posture until all of the superstructure load acts on the beam, and the predetermined posture is prevented. Therefore, by setting the predetermined posture of the beam to a posture in which all of the upper structure load acts on the beam or a posture close thereto, the beam acts on the beam with the construction of the upper structure. Although the superstructure load gradually increases, it is possible to prevent deformation of the previously constructed superstructure portion regardless of the increase in the load and to support the posture at the completion of the construction. Then, in order to flexibly deform the beam to a predetermined position by the this applying tension to the diagonal member which is installed between the projecting end of the upper end and the bracket post erected on the beam, FIG. 12
As shown in, "1" and downward load F1 "2" beam compression force F2 "3" along the upper side projecting projecting end for connecting the diagonal member of the bracket from the pillars of the post (eccentric to the column) is allowed to act on the beam of the three additional bending moment M by which, these by three cooperative, because to Wami deformation beams in a predetermined position, the operation for deforming bending of the beam to a predetermined posture beam Operation from above, without occupying the space under the beam with the deformation operation of the beam or the equipment for it, it is possible to keep the space under the beam open so that it can be used for other purposes. Not only can it do the following: That is, as a method of controlling the deformation of the beam using the post and the diagonal member, a method of laying a diagonal member between the upper end of the post and both ends of the beam or the column and applying tension to the diagonal member can be considered. However, in this case, although the above-described two of <1> and <2> occur, <3> does not occur. Therefore, in the case of the present invention in which three of <1>, <2> and <3> are generated, the applied tension can be effectively used for bending deformation of the beam, and the hydraulic jack used for deformation control is used. Actuators need only be small. Of course, for example, by applying a weight load to the beam,
When flexing and deforming a beam, it is necessary to use a weight corresponding to the bending stiffness of the beam as a weight, and the weight increases in size, which is inconvenient in terms of handling. Since the beam is bent and deformed, an easy-to-handle device such as a post, a diagonal member, and a hydraulic jack for applying tension to the diagonal member may be used.

【0007】特に、後述の実施例で示すように、梁を所
定の姿勢にたわみ変形させるためのポスト・ブラケット
・斜材を用いて前記梁の復元阻止を行う場合には、その
復元阻止のための装置を別途用意する必要がなく、コス
ト及び作業工数の低減を図れるとともに、梁を所定の姿
勢にたわみ変形させる場合と同様に、復元阻止にかかわ
らず、梁下側の空間を開放することができる。
[0007] In particular, as shown in an embodiment described later, when the beam is prevented from restoring using a post, a bracket , or a diagonal member for bending and deforming the beam to a predetermined posture, the restoration is prevented. It is not necessary to prepare a separate device, and it is possible to reduce costs and man-hours, and to open the space under the beam regardless of the prevention of restoration, as in the case of bending and deforming the beam to a predetermined posture. it can.

【0008】上記本発明の変形制御装置によれば、斜材
への張力付与により、梁を所定の姿勢にたわみ変形させ
ることができ、かつ、その後の上部構造体の構築に伴い
増大する上部構造荷重に応じた付与張力の調整などによ
り、上部構造体構築時における梁の元の姿勢への復元を
阻止することができ、しかも、張力を付与するための油
圧ジャッキなどアクチエーターが小型のもので済むとと
もに、ポスト・斜材。油圧ジャッキなど装置全体を取扱
い易いものにできる。
According to the deformation control device of the present invention, the beam can be flexed and deformed to a predetermined posture by applying tension to the diagonal member, and the upper structure increases with the construction of the upper structure thereafter. By adjusting the applied tension according to the load, etc., it is possible to prevent the beam from restoring to the original position when constructing the upper structure, and the actuators such as hydraulic jacks for applying tension are small. As well as post and diagonal. The entire device such as a hydraulic jack can be made easy to handle.

【0009】[0009]

【発明の効果】従って、本発明によれば、上部構造体の
構築中も、その構築に伴う上部構造荷重の増加にかかわ
らず、梁を所定の姿勢に保持して、上部構造体の構築と
並行して外壁材や仕上げ材の姿勢調整を行うことがで
き、しかも、梁を所定の姿勢に維持するための変形制御
を、取扱容易で安価な設備により行うことができる梁の
変形制御技術を提供できるようになった。
Therefore, according to the present invention, the beam is maintained in a predetermined posture even during the construction of the upper structure, regardless of the increase in the load of the upper structure accompanying the construction. At the same time, it is possible to adjust the posture of the outer wall material and the finishing material, and to control the deformation to maintain the beam in a predetermined posture by using easy-to-handle and inexpensive equipment. Now available.

【0010】[0010]

【実施例】本発明の実施例を次に示す。建物の架構は、
図2、図3に示すように、複数階分に相当する階高さの
大空間Aを形成する大スパンの下部架構1と、その上部
に構築した多層の上部構造体2と、建物の一辺を形成す
るコア部3とから成る。前記下部架構1は、建物の4つ
の隅夫々に配置した大スパンの鉄骨造りの柱4と、建物
の3辺に沿う姿勢で隣合う柱4にわたって架設した梁5
とから成る。前記梁5は、トラス梁であり、そのうち、
建物の長辺に沿う梁5は、図4(イ)に示すように、支
持すべき上部構造荷重によるたわみ量に相当するむくり
が付けられたものである。そして、このむくり付きの梁
5Aは、柱4にわたって架設されたのち、上部構造体2
の構築が完了して、支持すべき上部構造荷重の全部が作
用するまでの間、水平姿勢に保持するための変形制御を
受ける。前記上部構造体2は、複数層の単位に分けられ
て下方の構築単位F1 〜Fn から順に積上げ式に構築さ
れるものである。前記梁5Aの変形制御は次に示す手順
で行われる。 [1]図4(イ)に示すように、下部架構1上に最下位
の構築単位F1 を構築すると共に、抵抗付与装置を設置
する。前記抵抗付与装置は、図1、図3乃至図8に示す
ように、前記最下位の構築単位F1 における柱6のうち
梁長手方向の中央部に立設するものを梁変形制御用のポ
スト7として、そのポスト7の上端部に梁幅方向の両側
方に突出する2つの張出ブラケット7Aを固着し、前記
下部架構1のうち梁5Aの長手方向両端を支持する柱4
の夫々にブラケット8を固着し、それらブラケット8と
前記張出ブラケット7Aとにわたってポスト7の上下位
置を規制するケーブル(斜材の一例)9を複数本(図面
は8本を示す)づつ架設し、前記ケーブル9に張力を付
与するための油圧ジャッキ10と、ケーブル9の張力状
態を保持するための緊張保持手段とを設けて構成されて
いる。前記張出ブラケット7Aの夫々は、図5、図6に
示すように、一方のブラケット8とにわたって架設する
ケーブル9の端部を同数本づつ上下方向に並べて止着す
るためのケーブル受け7aと、他方のブラケット8とに
わたって架設するケーブル9の端部を同数本づつ上下方
向に並べて止着するためのケーブル受け7bとを突出端
部に突出方向に並べる状態で形成している。そして、各
ケーブル受け7a, 7bは、ケーブル9の端部に固着し
た取付けロッド9Aを、引張り方向で抜止めした状態に
挿通させることでケーブル9を取付けるものであって、
各ケーブル9夫々の張力を検出するためのロードセル利
用の荷重計11を備えている。前記ブラケット8は、図
7、図8に示すように、前記梁5Aとで柱4を挟む状態
で、かつ、梁5Aの上弦材5aの軸線X上に位置する状
態で柱4に固着した取付脚部8Aと、梁巾方向の両側方
に突出する状態で前記取付脚部8Aの先端に固着した張
出部8Bとから成る。そして、一方の張出ブラケット7
Aにおけるケーブル受け7a, 7bとにわたって架設す
るケーブル9の端部を止着するためのケーブル受け8a
を張出部8Bの一端部に備え、他方の張出ブラケット7
Aにおけるケーブル受け7a, 7bとにわたって架設す
るケーブル9の端部を止着するためのケーブル受け8a
を張出部8Bと他端部に備えている。これらブラケット
8のケーブル受け8aは、前記上弦材5aの軸線9を含
む水平面近くにケーブル9の端部を梁幅方向に並べて止
着するものであり、ケーブル9の端部に固着した取付け
ロッド9Bを引張っり方向で抜止め状態に挿通させるこ
とでケーブル9を取付けるものである。つまり、ケーブ
ル9の端部はブラケット8の突出端に止着されている。
つまり、ケーブル9を、梁5Aの梁幅方向両側脇に振分
け配置する状態でポスト7の上端部と柱4とにわたって
架設してあり、これによって梁5A上に立設した上部架
構F1 における柱6間に配置するPC壁等の壁工事を行
えるようにしてある。そして、張出ブラケット7Aのケ
ーブル受け7a, 7bを、ケーブル9の端部を上下方向
に並置して取付けるものとすることにより、張出ブラケ
ット7Aの突出量を小さくしてケーブル9の張りに伴な
って張出ブラケット7Aに作用するポスト7軸芯周りの
モーメントを小にすることができるようになっている。
かつ、ブラケット8のケーブル受け8aを、ケーブル9
の端部を梁幅方向に並置して取付けるものとすることに
より、ケーブル9の端部を上弦材5aの軸線aを含む水
平面近くに配置してケーブル9の張りに伴なう反力を梁
5Aに軸線方向で作用させる形式としながらも、ブラケ
ット8の突出量を小にすることができるようになってい
る。前記油圧ジャッキ10は、図8に示すように、前記
取付けロッド9A, 9Bのうちブラケット8側のもの9
Bに可動体10Aを抜止め装着し、ブラケット8のケー
ブル受け8aを反力台として可動体10Aを本体10B
に対してケーブル引張り方向に油圧で駆動することによ
りケーブル9に張力を付与するものである。前記緊張保
持手段は、前記取付けロッド9A, 9Bのうちブラケッ
ト8側のもの9Bをケーブル受け8aに対して抜止めす
るものを、取付けロッド9Bに螺合するナット12とす
る手段である。つまり、油圧ジャッキ10によりケーブ
ル9を引張ったのちナット12をケーブル受け8aに当
る位置に螺合移動させることで、ケーブル9の弛みを阻
止して緊張状態を保持するように構成されている。もっ
て、抵抗付与装置は、油圧ジャッキ10でケーブル9を
引張ることにより、ポスト7を下方に移動させて、梁5
Aに荷重をかけれるように構成されており、かつ、ナッ
ト12により、油圧ジャッキ10を取外した状態におい
てもケーブル9の張力を維持してポスト7の上下位置を
規制するように構成されている。なお、油圧ジャッキ1
0によるケーブル9への張力付与およびナット12によ
る張力保持は、全てのケーブル9について同時に行うの
ではなく、ケーブル9のうち、梁幅方向の一側に位置す
るものの1本と他側に位置するものの1本との2本を1
組として、1組づつ行う。もちろん、一方のブラケット
8とポスト7にわたるケーブル9の1組に対する張力付
与・保持と、他方のブラケット8とポスト7にわたるケ
ーブル9の1組に対する張力付与・保持とは同時に行
う。そして、付与する張力の管理は、前述した荷重計1
1と油圧ジャッキ10の油圧とを用いて行う。また、梁
5A上に立設する上部架構1の柱6のうち、ポスト7と
なる柱6は、梁5Aに最初から所定の接合強度で固着さ
れているが、残る柱6は、座14を介して梁5Aに固着
されている。前記残る柱6の下端部は、図9乃至図11
に示すように、鋼管6Aと、それの内部に固着した十字
形配置の補強板6Bと、その補強板6Bの下端に固着し
た取付板6Cとが構成されており、鋼管6Aには、事後
において蓋6aで塞がれる接続作業用の開口6bが形成
されている。前記座14は、梁5Aに固着した鋼管14
Aと、それの内部に固着した十字形配置の補強板14B
と、その補強板14Bの上端に固着した支持板14Cと
から構成されている。もって、柱6の梁5Aへの取付構
造は、図9の(イ)に示すように、柱6の取付板6Cを
座14の支持板14Cに載せ付け、その状態で取付板6
Cと支持板14Cとを図9の(ロ)に示すように、ボル
ト・ナット15で連結することにより、事後の梁5Aの
水平姿勢への変形に伴なう梁5Aに対する姿勢変化を許
容する強度で柱6を梁5Aに取付けた第1状態と、図1
0に示すように、蓋6aを固着するとともに、柱6の鋼
管6Aを座14の鋼管14Aとを溶接で連結することに
より、柱6を所定の強度で梁5Aに取付けた第2状態と
を現出するように構成されている。前記抵抗付与装置に
よる梁5Aに対するたわみ変形作用について説明する
と、図12に示すように、ケーブル9に張力を付与した
状態において、梁5Aには、ポスト7からの下向き荷重
(F1)と、梁上辺に沿った(つまり上弦材5aを圧縮
する)圧縮力(F2)と、ブラケット8のうちケーブル
9と連結する突出端が柱4から突出(柱4に対して偏
心)していることによる付加曲げモーメント(M)との
3つが、梁5Aを、むくり付きの姿勢から水平姿勢にた
わみ変形させる力として作用する。
Embodiments of the present invention will be described below. The frame of the building
As shown in FIGS. 2 and 3, a large span lower frame 1 forming a large space A having a floor height corresponding to a plurality of floors, a multi-layered upper structure 2 built thereon, and one side of the building And a core part 3 forming The lower frame 1 includes a large-span steel column 4 disposed at each of the four corners of the building, and a beam 5 erected over the adjacent column 4 in a posture along three sides of the building.
Consisting of The beam 5 is a truss beam, of which:
As shown in FIG. 4A, the beam 5 along the long side of the building is provided with a swell corresponding to the amount of deflection due to the superstructure load to be supported. Then, after this stripped beam 5A is erected over the column 4, the upper structure 2
Is completed, and is subjected to deformation control for maintaining the horizontal posture until all of the superstructure loads to be supported are applied. The upper structure 2 is divided into units of a plurality of layers, and is constructed in a stacked manner in order from the lower construction units F 1 to F n . The deformation control of the beam 5A is performed in the following procedure. [1] As shown in FIG. 4 (b), the building the building blocks F 1 of the lowest on the lower Frame 1, installing the resistance applying device. The resistance applying device, FIG. 1, as shown in FIGS. 3 to 8, wherein the lowermost construction beam longitudinal posts for beam deformation control those erected in the center of the posts 6 in a unit F 1 7, two overhanging brackets 7 </ b> A that protrude to both sides in the beam width direction are fixed to the upper end of the post 7, and columns 4 that support both longitudinal ends of the beam 5 </ b> A in the lower frame 1.
And a plurality of cables (an example of a diagonal member) 9 for regulating the vertical position of the post 7 are provided between the brackets 8 and the overhanging brackets 7A. A hydraulic jack 10 for applying tension to the cable 9 and a tension holding means for holding the tension state of the cable 9 are provided. As shown in FIGS. 5 and 6, each of the overhanging brackets 7A has a cable receiver 7a for vertically arranging and fixing the same number of ends of the cable 9 extending over one of the brackets 8 in a vertical direction. A cable receiver 7b for vertically arranging and fastening the same number of the ends of the cable 9 laid across the other bracket 8 and the same number is formed in a state of being arranged in the protruding end in the protruding direction. Each of the cable receivers 7a and 7b attaches the cable 9 by inserting the attachment rod 9A fixed to the end of the cable 9 in a state where the rod 9A is not pulled out in the pulling direction.
A load cell 11 using a load cell for detecting the tension of each cable 9 is provided. As shown in FIGS. 7 and 8, the bracket 8 is fixed to the column 4 in a state where the column 4 is sandwiched between the beam 5A and the axis 8 of the upper chord 5a of the beam 5A. It comprises a leg 8A and an overhang 8B fixed to the tip of the mounting leg 8A so as to protrude to both sides in the beam width direction. And one overhang bracket 7
A cable receiver 8a for fastening an end of the cable 9 laid across the cable receivers 7a and 7b in FIG.
Is provided at one end of the overhang portion 8B, and the other overhang bracket 7 is provided.
A cable receiver 8a for fastening an end of the cable 9 laid across the cable receivers 7a and 7b in FIG.
Is provided on the overhang 8B and the other end. The cable receivers 8a of the brackets 8 are arranged such that the ends of the cables 9 are arranged side by side in the beam width direction near a horizontal plane including the axis 9 of the upper chord member 5a, and are attached to the ends of the cables 9 by mounting rods 9B. The cable 9 is attached by inserting the cable 9 in the pulling direction in a retaining state. That is, the end of the cable 9 is fixed to the protruding end of the bracket 8.
In other words, the cable 9, Yes and bridged over the upper end and the bar 4 Doo posts 7 in a state of distribution disposed in the beam width direction on both sides beside the beam 5A, whereby the pillar in the upper Frames F 1 which is erected on the beam 5A Wall work such as a PC wall to be arranged between the six can be performed. Then, the cable receivers 7a and 7b of the overhang bracket 7A are attached with the ends of the cable 9 juxtaposed in the vertical direction, so that the amount of protrusion of the overhang bracket 7A is reduced, and the extension of the cable 9 is increased. As a result, the moment around the axis of the post 7 acting on the overhang bracket 7A can be reduced.
The cable receiver 8a of the bracket 8 is connected to the cable 9
Are arranged side by side in the beam width direction, so that the end of the cable 9 is arranged near a horizontal plane including the axis a of the upper chord material 5a, and the reaction force accompanying the tension of the cable 9 is The projection amount of the bracket 8 can be made small while having a form that acts on 5A in the axial direction. As shown in FIG. 8, the hydraulic jack 10 is configured such that the mounting rod 9A, 9B,
B, the movable body 10A is attached to the main body 10B using the cable receiver 8a of the bracket 8 as a reaction force base.
Is applied to the cable 9 by hydraulic pressure in the cable pulling direction. The tension holding means is a means for fixing a nut 9B of the mounting rods 9A, 9B, which locks the one 9B on the bracket 8 side, to the cable receiver 8a as a nut 12 screwed to the mounting rod 9B. In other words, after the cable 9 is pulled by the hydraulic jack 10, the nut 12 is screwed to a position where the nut 12 comes into contact with the cable receiver 8a, thereby preventing the cable 9 from being loosened and maintaining the tension state. Accordingly, the resistance applying device pulls the cable 9 with the hydraulic jack 10 to move the post 7 downward,
A is configured to apply a load, and the nut 12 maintains the tension of the cable 9 and regulates the vertical position of the post 7 even when the hydraulic jack 10 is removed. . The hydraulic jack 1
The tension application to the cable 9 by the 0 and the tension holding by the nut 12 are not performed simultaneously for all the cables 9, but one of the cables 9 located on one side in the beam width direction and the other on the other side. One of the two and one
Perform one set at a time. Of course, the tensioning and holding of one set of cables 9 over one bracket 8 and post 7 and the tensioning and holding of one set of cables 9 over the other bracket 8 and post 7 are performed simultaneously. The tension to be applied is managed by the load cell 1 described above.
1 and the hydraulic pressure of the hydraulic jack 10. Further, among the columns 6 of the upper frame 1 standing on the beam 5A, the column 6 to be the post 7 is fixed to the beam 5A from the beginning with a predetermined bonding strength, but the remaining column 6 It is fixed to the beam 5A through the intermediary. The lower ends of the remaining columns 6 are shown in FIGS.
As shown in FIG. 6, a steel pipe 6A, a reinforcing plate 6B fixed in a cross shape fixed inside thereof, and a mounting plate 6C fixed to the lower end of the reinforcing plate 6B are configured. An opening 6b for connection work closed by the lid 6a is formed. The seat 14 is a steel pipe 14 fixed to the beam 5A.
A and a cross-shaped reinforcing plate 14B fixed inside thereof
And a support plate 14C fixed to the upper end of the reinforcing plate 14B. Thus, as shown in FIG. 9A, the mounting structure of the column 6 on the beam 5A is such that the mounting plate 6C of the column 6 is placed on the support plate 14C of the seat 14, and the mounting plate 6
By connecting the C and the support plate 14C with bolts and nuts 15 as shown in FIG. 9B, a change in the attitude of the beam 5A due to the subsequent deformation of the beam 5A to the horizontal attitude is allowed. FIG. 1 shows a first state in which the column 6 is attached to the beam 5A with strength.
As shown in FIG. 0, by fixing the lid 6a and connecting the steel pipe 6A of the column 6 to the steel pipe 14A of the seat 14 by welding, the second state in which the column 6 is attached to the beam 5A with a predetermined strength is established. It is configured to appear. The flexural deformation effect on the beam 5A by the resistance applying device will be described. As shown in FIG. 12, when tension is applied to the cable 9, a downward load (F1) from the post 7 and an upper side of the beam are applied to the beam 5A. (That is, compressing the upper chord material 5a) and additional bending due to the protruding end of the bracket 8 connected to the cable 9 protruding from the column 4 (eccentric with respect to the column 4 ). The moment (M) acts as a force to bend and deform the beam 5A from a peeled posture to a horizontal posture.

【0011】[2]柱6の梁5Aへの取付けを第1状態
とし、抵抗付与装置を用いて梁5Aを水平姿勢にたわみ
変形させ、それを保持し、かつ、柱6を梁5Aに第2状
態で取付ける。
[2] The column 6 is attached to the beam 5A in the first state, and the beam 5A is bent and deformed to a horizontal position using a resistance applying device, and is held, and the column 6 is moved to the beam 5A. Install in two states.

【0012】[3]第2段目の構築単位F2 を構築し、
その後、ナット11を緩めて、その第2段目の構築単位
2 の構築によって梁5Aに作用した上部構造荷重分だ
け抵抗付与装置による梁5Aへの付与荷重を減らし、そ
の状態に固定する。なお、ケーブル9の伸び剛性が梁5
Aの曲げ剛性と同じ又は大きいのであれば、ナット11
を緩めての付与荷重を減す除荷を必要としないが、一般
に、ケーブル9の伸び剛性は梁5Aの曲げ剛性に比較し
て小さく、2段目の構築単位F2 の荷重が梁5Aに作用
しても、その作用した構築単位F2 の荷重分の張力がケ
ーブル9から抜けないため、前記の付与荷重を減す除荷
が必要となる。もちろん、ケーブル9の伸び剛性が梁5
Aの曲げ剛性と同じ又はそれ以上であれば、除荷は不要
である。
[3] Constructing a second-stage building unit F 2 ,
Then, by loosening the nut 11 to reduce the applied load to the beams 5A by the resistance applying unit only the superstructure load component acting on the beam 5A by construction of the building blocks F 2 its second stage, fixed in that state. The extension rigidity of the cable 9 is
If the bending stiffness of A is the same or greater, the nut 11
It does not require unloading lessen the grant load of Loosen, generally, elongation stiffness of the cable 9 is small compared to the bending stiffness of the beam 5A, the load of the building block F 2 of the second stage beam 5A also act, the tension of the load amount of the building blocks F 2 that its action because it does not come out of its cable 9, unloading lessen the grant load is required. Of course, the extension rigidity of the cable 9 is
If the bending stiffness of A is equal to or higher than that, no unloading is required.

【0013】[4]前記[3]と同様な作業を、第3段
目から最上段の構築の構築単位F3 〜Fn の夫々につい
て行う。
[4] The same operation as the above [3] is performed for each of the construction units F 3 to F n of the construction from the third stage to the top stage.

【0014】[5]上部構造体2の構築が完了したなら
ば、抵抗付与装置を撤去する。上記手順による変形制御
によれば、梁5Aを水平姿勢に変形させたのち、上部構
造体2の構築が完了して支持すべき上部構造荷重の全部
が梁5Aに作用するまでの間、梁5Aが水平姿勢に保持
される。つまり、梁5Aに荷重をかけて梁5Aを水平姿
勢にさせたのち、第2段目の構築単位F2 の構築を開始
するまでは、梁5Aの復元力よりも大なる下方からの突
き上げ荷重が作用しないかぎりケーブル9により上下位
置が規制された柱6による突っ張り(つまり下向き荷重
(F1))と、圧縮力(F2)と、付加曲げモーメント
(M)で、梁5Aの復元変形が阻止され、梁5Aは水平
姿勢に保持される。その後の第2段目の構築単位F2
構築においては、その構築によって梁5Aに作用する上
部構造荷重が増加し、その上部構造荷重が梁5Aの復元
変形の抵抗として作用し、梁5Aの復元変形に抵抗する
ための抵抗付与装置による負担が軽減される状態で梁5
Aが水平姿勢に保持される。そして、これは、第3段目
以降の構築単位F3 〜Fn についても同様である。ま
た、最初の構築単位F1 を梁5Aの設置作業の一部とし
て行い、最初の構築単位F1 を構築後に梁5Aの変形制
御を行うため、梁5Aの水平姿勢への変形により、構築
単位F1 の柱6がその梁5Aの変形に引き摺られて、柱
6が梁5Aに対して姿勢を変えようとする。ところが、
その梁5Aの変形時、第1状態で柱6を梁5Aに取付け
てあるため、その柱6の姿勢変化を抵抗少なくスムーズ
に行わせて、構築単位F1 による梁5Aの変形に対する
抵抗を小さくすることができるのである。13は上部構
造体2の梁である。
[5] When the construction of the upper structure 2 is completed, the resistance applying device is removed. According to the deformation control according to the above procedure, after the beam 5A is deformed to a horizontal posture, the beam 5A is maintained until the construction of the upper structure 2 is completed and all the upper structure loads to be supported act on the beam 5A. Is held in a horizontal position. In other words, mixture was allowed to beams 5A by applying a load to the beam 5A in the horizontal position, until the start building the second stage of the building block F 2, pushing up from below a large composed than the restoring force of the beam 5A load As long as the cable 9 does not act, the tension by the column 6 whose vertical position is regulated by the cable 9 (that is, the downward load)
(F1)), compressive force (F2), and additional bending moment
At (M) , restoring deformation of the beam 5A is prevented, and the beam 5A is held in a horizontal posture. In the subsequent second stage of construction of the building blocks F 2 of increased superstructure load acting on the beam 5A by its construction, its superstructure load acts as the resistance of the restoring deformation of the beam 5A, the beam 5A In the state where the load on the resistance applying device for resisting the restoration deformation is reduced, the beam 5
A is held in a horizontal position. And this also applies to the building unit F 3 to F n of the third stage and thereafter. Also, make the first building block F 1 as a part of the installation work of the beam 5A, for performing deformation control of the beam 5A after building the first building block F 1, by the deformation of the horizontal orientation of beams 5A, building block pillar 6 of the F 1 has been dragged by the deformation of the beams 5A, column 6 is trying to change the attitude with respect to the beam 5A. However,
Upon deformation of the beam 5A, since the pillar 6 is mounted on the beam 5A in a first state, a posture change of the pillar 6 to perform the resistance less smoothly, reducing the resistance to deformation of the beam 5A by building units F 1 You can do it. Reference numeral 13 denotes a beam of the upper structure 2.

【0015】〔別実施例〕 本発明の別実施例を以下に示す。 [1]上記実施例では、ケーブル9に張力を与えるに、
ケーブル9をブラケット8側で引張るようにしたが、そ
の張力を与える手段としては、図13に示すように、柱
6に前記ブラケット7Aを上下移動自在に装着し、前記
柱6に反力受け用のブラケットBを固着し、この反力受
け用のブラケットBと前記ブラケット7Aとの間に、ブ
ラケット7Aを上方に押す油圧ジャッキ10’を介装
し、ブラケット7Aを上方に押すことで柱6に下方への
力を作用させて梁5Aを下方に押圧するようにしても良
い。 [2]上記実施例では、変形制御対象の梁5Aとして、
トラス梁を示したが、梁5Aは、鉄骨造りのものや、鉄
筋コンクリート造りのもの、鉄骨鉄筋コンクリート造り
のもののいずれでも良い。 [3]上記実施例では、梁長手方向の中央部一点で梁5
Aに荷重を作用させ、かつ、上下位置を規制するように
したが、それらは、梁長手方向の複数点で分散して行っ
ても良い。 [4]上記実施例では、上記構造体2の柱6をポスト7
に利用して梁5Aに荷重を作用させ、上下位置を規制し
たが、それら用の柱を別途設けて実施しても良い。 [5]上記実施例では、ケーブル9を用いてポスト7を
引張ることにより、梁5Aに荷重を作用させ、かつ、上
下位置を規制するようにしたが、ポスト7を引張る斜材
9としては、鋼材でも良い。 [6]上記実施例では、抵抗付与装置により、梁5Aを
たわみ変形させるための荷重を梁5Aに作用させるよう
にしたが、荷重付与装置を別途設けて、荷重付与と抵抗
付与と独立して行ってもよい。
[Another Embodiment] Another embodiment of the present invention will be described below. [1] In the above embodiment, when tension is applied to the cable 9,
Although the cable 9 is pulled on the bracket 8 side, as means for applying the tension, as shown in FIG. Of the reaction force receiving bracket B and the bracket 7A, a hydraulic jack 10 'for pushing the bracket 7A upward is interposed, and the bracket 7A is pushed upward to attach to the column 6 The beam 5A may be pressed downward by applying a downward force. [2] In the above embodiment, as the beam 5A to be deformed,
Although the truss beam is shown, the beam 5A may be any of a steel frame, a reinforced concrete frame, and a steel reinforced concrete frame. [3] In the above embodiment, the beam 5 is formed at one point at the center in the beam longitudinal direction.
Although a load is applied to A and the vertical position is regulated, they may be dispersed at a plurality of points in the beam longitudinal direction. [4] In the above embodiment, the post 6 is
Although a load is applied to the beam 5A to regulate the vertical position, the columns may be separately provided and implemented. [5] In the above embodiment, the post 7 is pulled using the cable 9 to apply a load to the beam 5A and regulate the vertical position. However, as the diagonal member 9 for pulling the post 7, Steel may be used. [6] In the above embodiment, the load for bending and deforming the beam 5A is applied to the beam 5A by the resistance applying device. However, a load applying device is separately provided, and the load application and the resistance application are performed independently. May go.

【0016】尚、特許請求の範囲の項に図面との対照を
便利にするために符号を記すが、該記入により本発明は
添付図面の構成に限定されるものではない。
In the claims, reference numerals are provided for convenience of comparison with the drawings, but the present invention is not limited to the configuration shown in the attached drawings.

【図面の簡単な説明】[Brief description of the drawings]

【図1】要部の正面図FIG. 1 is a front view of a main part.

【図2】概略正面図FIG. 2 is a schematic front view.

【図3】要部の平面図FIG. 3 is a plan view of a main part.

【図4】制御手順を示す概略正面図FIG. 4 is a schematic front view showing a control procedure.

【図5】要部の一部切欠き正面図FIG. 5 is a partially cutaway front view of a main part.

【図6】要部の概略斜視図FIG. 6 is a schematic perspective view of a main part.

【図7】要部の平面図FIG. 7 is a plan view of a main part.

【図8】要部の一部切欠き正面図FIG. 8 is a partially cutaway front view of a main part.

【図9】柱の取付工程を示す縦断面図FIG. 9 is a longitudinal sectional view showing a mounting process of a pillar.

【図10】柱の取付工程を示す縦断面図FIG. 10 is a longitudinal sectional view showing a mounting process of a pillar.

【図11】柱の断面図FIG. 11 is a sectional view of a pillar.

【図12】斜材への張力付与に伴い梁に作用する荷重・
モーメントを示す概念図
FIG. 12 shows a load acting on a beam due to a tension applied to a diagonal member.
Conceptual diagram showing moment

【図13】別実施例を示す要部の正面図FIG. 13 is a front view of a main part showing another embodiment.

【符号の説明】[Explanation of symbols]

5A 梁 7 ポスト 4 ブラケット 9 斜材5A beam 7 post 4 pillar 8 bracket 9 diagonal

フロントページの続き (72)発明者 瀬川 輝夫 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (72)発明者 小島 政章 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (72)発明者 山口 正 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (72)発明者 谷口 惺 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (72)発明者 古川 幸荘 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内 (72)発明者 岡田 克也 東京都江東区南砂二丁目5番14号 株式 会社竹中工務店 技術研究所内 (72)発明者 奥野 智久 東京都中央区銀座八丁目21番1号 株式 会社竹中工務店 東京本店内 (72)発明者 菊池 公男 大阪府南河内郡美原町木材通3丁目1番 8号 株式会社竹中工務店 技術研究所 大阪支所内 (72)発明者 河田 康夫 大阪府大阪市中央区本町四丁目1番13号 株式会社竹中工務店 大阪本店内Continued on the front page (72) Inventor Teruo Segawa 4-1-1, Honcho, Chuo-ku, Osaka-shi, Osaka Inside Takenaka Corporation Co., Ltd. Osaka Main Store (72) Inventor Masaaki Kojima 4-chome, Honcho, Chuo-ku, Osaka-shi, Osaka No. 13 Takenaka Corporation, Osaka Main Store (72) Inventor Tadashi Yamaguchi 4-1-1, Honcho, Chuo-ku, Osaka City, Osaka Prefecture Inside Takenaka Corporation, Osaka Main Store (72) Inventor Satoshi Taniguchi Osaka City, Osaka Prefecture 4-1-1-13, Honcho, Chuo-ku, Osaka, Japan Takenaka Corporation (72) Inventor Koso Furukawa 4-1-1, Honmachi, Chuo-ku, Osaka-shi, Osaka Takenaka Corporation, Osaka Main Store (72) Inventor Katsuya Okada 2-5-14 Minamisuna, Koto-ku, Tokyo Inside the Technical Research Center, Takenaka Corporation (72) Inventor Tomohisa Okuno 8-2-1-1, Ginza, Chuo-ku, Tokyo Inside the Tokyo Main Office, Takenaka Corporation (72) Inventor Kimio Kikuchi 3-18, Mokudori, Mihara-cho, Minamikawachi-gun, Osaka Prefecture Bamboo Co., Ltd. (72) Inventor Yasuo Kawada 4-1-1-13 Honcho, Chuo-ku, Osaka-shi, Osaka Takenaka Corporation, Osaka Main Branch

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 柱(4)間にむくりを付与した梁(5
A)を架設し、その梁(5A)の長手方向の中間に立て
たポスト(7)の上端部と、梁(5A)の長手方向の延
長上に位置する状態で前記(4)よりも横側外方に突
出させたブラケット(8)の突出端との間に斜材(9)
を架設し、その斜材(9)に張力を付与することによ
り、所定の姿勢に前記梁(5A)をたわみ変形させ、そ
の後、支持すべき上部構造荷重の全部が梁(5A)に作
用するまで、梁(5A)の所定の姿勢から元の姿勢側へ
の復元を阻止してその梁(5A)を所定の姿勢に維持す
る梁の変形制御方法
A beam (5) having a hollow between columns (4).
Bridged to A), an upper end of the beam (the longitudinal direction of the intermediate vertical post of 5A) (7), than the beam (longitudinally said post in a state positioned on the extension of the 5A) (4) Diagonal material (9) between the protruding end of the bracket (8) protruding laterally outward
The beam (5A) is flexed and deformed to a predetermined posture by applying tension to the diagonal member (9), and thereafter all of the superstructure load to be supported acts on the beam (5A). Until the beam (5A) is restored from the predetermined posture to the original posture side and the beam (5A) is maintained in the predetermined posture.
【請求項2】 柱(4)間に架設したむくりを付与した
梁(5A)の長手方向の中間にポスト(7)を立て、梁
(5A)の長手方向の延長上に位置する状態で前記柱
(4)よりも横側外方にブラケット(8)を突出させ、
前記ポスト(7)の上端部とブラケット(8)の突出端
との間に斜材(9)を架設し、その斜材(9)に張力を
付与する張力付与手段を設けてある梁の変形制御装置。
2. A post (7) is erected in the middle of the longitudinal direction of the barbed beam (5A) provided between the columns (4), and is extended on the longitudinal extension of the beam (5A). In the position, the bracket (8) projects laterally outward from the column (4),
Deformation of a beam provided with a diagonal member (9) between the upper end of the post (7) and the protruding end of the bracket (8), and provided with tension applying means for applying tension to the diagonal member (9). Control device.
JP5011338A 1993-01-27 1993-01-27 Beam deformation control method and device Expired - Fee Related JP2635900B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5011338A JP2635900B2 (en) 1993-01-27 1993-01-27 Beam deformation control method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5011338A JP2635900B2 (en) 1993-01-27 1993-01-27 Beam deformation control method and device

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP1260939A Division JPH0726434B2 (en) 1989-10-05 1989-10-05 Beam deformation control method

Publications (2)

Publication Number Publication Date
JPH062436A JPH062436A (en) 1994-01-11
JP2635900B2 true JP2635900B2 (en) 1997-07-30

Family

ID=11775253

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5011338A Expired - Fee Related JP2635900B2 (en) 1993-01-27 1993-01-27 Beam deformation control method and device

Country Status (1)

Country Link
JP (1) JP2635900B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7041463B2 (en) * 2016-12-16 2022-03-24 大成建設株式会社 How to build a building

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03122333A (en) * 1989-10-05 1991-05-24 Takenaka Komuten Co Ltd Method of controlling deformation of beam

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03122333A (en) * 1989-10-05 1991-05-24 Takenaka Komuten Co Ltd Method of controlling deformation of beam

Also Published As

Publication number Publication date
JPH062436A (en) 1994-01-11

Similar Documents

Publication Publication Date Title
JP4034734B2 (en) An indirect prestressed concrete roof ceiling structure with a flat bottom plate
AU2007282232B2 (en) An engineered wood construction system for high performance structures
JP2635900B2 (en) Beam deformation control method and device
JP3049143B2 (en) Large span frame structure and construction method thereof
JP3059654B2 (en) Construction method of multi span continuous bridge
JP3261255B2 (en) Shell roof lift-up method
CN216973814U (en) Multilayer vibration-suppressing cantilever structure
JPH0460175B2 (en)
JPH0726434B2 (en) Beam deformation control method
JP2866545B2 (en) Portal structure
JP3897648B2 (en) Seismic control structure of reinforced concrete building
JP2974025B1 (en) Construction method of large span large beam upper frame
JP2671694B2 (en) Composite beam
JP3040095U (en) Reinforcement structure and reinforcement member used therefor
JPH04368528A (en) Frame construction using void beam
JP3079334B2 (en) Construction method of steel building with long projecting girders.
JPH0621474B2 (en) Truss frame and construction method
JP2760891B2 (en) Floor vibration control device
JPH03107048A (en) Beam and its installing method
JP2916587B2 (en) Construction method of building
JP2691278B2 (en) String form support method
JPH04237743A (en) Unit house
JP2545017B2 (en) Tension force Externally supported composite beam
RU2070257C1 (en) Exterior wall panel
JPH03100251A (en) Synthesized truss beam structure

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080425

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090425

Year of fee payment: 12

LAPS Cancellation because of no payment of annual fees