JP2589936Y2 - Power switching device - Google Patents

Power switching device

Info

Publication number
JP2589936Y2
JP2589936Y2 JP1993045734U JP4573493U JP2589936Y2 JP 2589936 Y2 JP2589936 Y2 JP 2589936Y2 JP 1993045734 U JP1993045734 U JP 1993045734U JP 4573493 U JP4573493 U JP 4573493U JP 2589936 Y2 JP2589936 Y2 JP 2589936Y2
Authority
JP
Japan
Prior art keywords
power supply
breaker
thyristor
load
service
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP1993045734U
Other languages
Japanese (ja)
Other versions
JPH0716555U (en
Inventor
修治 植山
正利 前田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nissin Electric Co Ltd
Original Assignee
Nissin Electric Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nissin Electric Co Ltd filed Critical Nissin Electric Co Ltd
Priority to JP1993045734U priority Critical patent/JP2589936Y2/en
Publication of JPH0716555U publication Critical patent/JPH0716555U/en
Application granted granted Critical
Publication of JP2589936Y2 publication Critical patent/JP2589936Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Stand-By Power Supply Arrangements (AREA)

Description

【考案の詳細な説明】[Detailed description of the invention]

【0001】[0001]

【産業上の利用分野】この考案は、電力系統の常用受電
設備と予備受電設備の瞬時切替を行う静止型の電源切替
装置に関するものである。例えば、変電所等の常用−予
備所内切替回路の負荷側に自動化機器やコンピュータ等
の情報処理関連機器が接続されている場合、これらの機
器は、電源電圧変動には非常に敏感で瞬時停電や瞬時電
圧低下の影響を受けやすいので、瞬時切替が必要とな
り、このよう場合に電源切替装置が使用される。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a stationary power switching device for instantaneously switching between a regular power receiving facility and a standby power receiving facility in a power system. For example, when information processing-related devices such as automation devices and computers are connected to the load side of a switching circuit in a regular-standby station such as a substation, these devices are very sensitive to power supply voltage fluctuations, Since it is susceptible to an instantaneous voltage drop, instantaneous switching is required. In such a case, a power supply switching device is used.

【0002】[0002]

【従来の技術】図2に従来のこの種の電源切替装置の一
例の概略図を示す。この電源切替装置は、図2に示すよ
うに、常用電源(図示せず)に常用遮断器11の電源側
端子を接続し、予備電源(図示せず)に予備遮断器12
の電源側端子を接続し、常用遮断器11および予備遮断
器12の各負荷側端子を負荷(図示せず)に共通接続し
ている。常用遮断器11および予備遮断器12の投入・
遮断の制御は制御回路13により行う。
2. Description of the Related Art FIG. 2 is a schematic view showing an example of a conventional power supply switching device of this kind. As shown in FIG. 2, this power supply switching device connects a power supply side terminal of a service breaker 11 to a service power supply (not shown), and connects a protection circuit breaker 12 to a backup power supply (not shown).
Are connected, and the load side terminals of the service breaker 11 and the standby circuit breaker 12 are commonly connected to a load (not shown). Injection of service breaker 11 and backup breaker 12
The interruption is controlled by the control circuit 13.

【0003】この電源切替装置では、常用遮断器11を
投入し予備遮断器12を開放した状態では、常用電源よ
り負荷へ電力供給され、逆に予備遮断器12を投入し常
用遮断器11を開放した状態では、予備電源より負荷へ
電力供給される。図3に従来のこの種の電源切替装置の
他の例の概略図を示す。この電源切替装置は、図3に示
すように、常用電源(図示せず)に常時通電容量をもっ
た常用サイリスタ21の電源側端子を接続し、予備電源
(図示せず)に常時通電容量をもった予備サイリスタ2
2の電源側端子を接続し、常用サイリスタ21および予
備サイリスタ22の各負荷側端子を負荷(図示せず)に
共通接続している。常用遮断器21および予備遮断器2
2の投入・遮断の制御は制御回路23により行う。
In this power supply switching device, when the service breaker 11 is turned on and the spare circuit breaker 12 is opened, power is supplied from the service power supply to the load, and conversely, the service breaker 12 is turned on and the service breaker 11 is opened. In this state, power is supplied to the load from the standby power supply. FIG. 3 shows a schematic diagram of another example of this type of conventional power supply switching device. In this power supply switching device, as shown in FIG. 3, a power supply side terminal of a service thyristor 21 having a constant current supply capacity is connected to a service power supply (not shown), and a constant power supply capacity is connected to a standby power supply (not shown). Reserved thyristor 2
2 and the load side terminals of the service thyristor 21 and the spare thyristor 22 are commonly connected to a load (not shown). Service breaker 21 and spare circuit breaker 2
2 is controlled by the control circuit 23.

【0004】この電源切替装置では、常用サイリスタ2
1を導通させ予備サイリスタ22を遮断した状態では、
常用電源より負荷へ電力供給され、逆に予備サイリスタ
22を導通させ常用サイリスタ21を遮断した状態で
は、予備電源より負荷へ電力供給されることになる。
In this power supply switching device, a common thyristor 2
In the state where 1 is turned on and the spare thyristor 22 is cut off,
When power is supplied to the load from the service power supply, and conversely, when the protection thyristor 22 is turned on and the service thyristor 21 is shut off, power is supplied from the protection power supply to the load.

【0005】[0005]

【考案が解決しようとする課題】まず、図2に示した電
源切替装置では、常用電源より負荷へ電力供給する状態
から予備電源より負荷へ電力供給する状態へ切り替える
とき、あるいはその逆に切り替えるときに一時的に負荷
への電力供給が停止するという問題がある。また、図3
に示した電源切替装置は、常用電源より負荷へ電力供給
する状態から予備電源より負荷へ電力供給する状態へ切
り替えるとき、あるいはその逆に切り替えるときの一時
的な停電は回避することができ、瞬時切替が可能である
が、常用サイリスタ21および予備サイリスタ22は、
常時通電のため連続定格とする必要があり、大容量のも
のが必要である。また、通電時に常用サイリスタ21お
よび予備サイリスタ22が大きく発熱し、その発熱を抑
制するために、付帯設備として常用サイリスタ21およ
び予備サイリスタ22の冷却装置が必要となる。このた
め、設備構成がかなり大型化するとともに、コスト高と
なるという問題がある。
First, in the power supply switching device shown in FIG. 2, when switching from a state where power is supplied from a normal power supply to a load to a state where power is supplied from a standby power supply to a load, or vice versa. However, there is a problem that power supply to the load is temporarily stopped. FIG.
The power supply switching device described in (1) can avoid a temporary power failure when switching from a state in which power is supplied from a normal power supply to a load to a state in which power is supplied from a standby power supply to a load, or vice versa. Although switching is possible, the regular thyristor 21 and the spare thyristor 22
It is necessary to have a continuous rating for continuous energization, and a large capacity is required. In addition, the service thyristor 21 and the spare thyristor 22 generate a large amount of heat when energized, and a cooling device for the service thyristor 21 and the spare thyristor 22 is required as an additional facility in order to suppress the heat generation. For this reason, there is a problem that the equipment configuration becomes considerably large and the cost increases.

【0006】また、図2および図3の電源切替装置はと
もに、一度切替指令が与えられると、切替動作の途中で
負荷等に事故が発生して過大な事故電流が流れるような
ことがあっても、切替がそのまま行われることになり、
事故の拡大につながるという問題もあった。ここで、切
替動作の途中の事故について説明する。切替動作の途中
は、負荷側の短絡または地絡事故の発生が考えられる。
電源切替途中において、上記事故が発生した場合に切替
を停止せず、そのまま切替を行った場合、電源側より事
故拡大電源を供給することとなるため、遮断器が遮断す
るまで事故が継続し、負荷側機器の損傷にもつながる。
[0006] In both of the power supply switching devices of FIGS. 2 and 3, once a switching command is given, an accident may occur in a load or the like during the switching operation and an excessive accident current may flow. Will be switched as it is,
There was also a problem that it led to the spread of accidents. Here, an accident during the switching operation will be described. During the switching operation, a short circuit on the load side or a ground fault may occur.
In the middle of power switching, if the switching does not stop when the above-mentioned accident occurs, and if switching is performed as it is, the accident expanding power will be supplied from the power supply side, so the accident will continue until the circuit breaker is shut off, It also leads to damage to the load side equipment.

【0007】この考案の目的は、負荷への電力供給の一
時的な停止を生じることなく瞬時切替を行うことがで
き、しかも設備構成を小型化できるとともにコストを低
く抑えることができる電源切替装置を提供することであ
る。この考案の他の目的は、切替動作の途中で負荷等に
事故が発生して例えば過大な事故電流が流れるような場
合における事故の拡大を防止することができる電源切替
装置を提供することである。
An object of the present invention is to provide a power supply switching device capable of performing instantaneous switching without causing a temporary stop of power supply to a load, and capable of reducing the size of the equipment configuration and reducing the cost. To provide. Another object of the present invention is to provide a power supply switching device capable of preventing the occurrence of an accident when an accident occurs in a load or the like during a switching operation and an excessive accident current flows, for example. .

【0008】[0008]

【課題を解決するための手段】請求項1記載の電源切替
装置は、常用電源に常用遮断器の電源側端子を接続し、
予備電源に予備遮断器の電源側端子を接続し、常用遮断
器および予備遮断器の各負荷側端子を負荷に共通接続し
ている。また、常用遮断器および予備遮断器の各電源側
端子に切替スイッチの一対の切替端子を接続し、この切
替スイッチの共通端子と常用遮断器および予備遮断器の
各負荷側端子との間にサイリスタを接続している。さら
に、常用遮断器および予備遮断器の一方の開放信号に応
答してサイリスタを短時間導通状態とし、サイリスタの
短時間導通状態の間に常用遮断器および予備遮断器の他
方を投入する制御回路を設けている。
According to a first aspect of the present invention, there is provided a power supply switching device, wherein a power supply terminal of a service breaker is connected to a service power source.
The power supply side terminal of the standby circuit breaker is connected to the standby power source, and the load side terminals of the service breaker and the standby circuit breaker are commonly connected to the load. A pair of switching terminals of a changeover switch is connected to each power supply side terminal of the service breaker and the backup circuit breaker, and a thyristor is connected between a common terminal of the changeover switch and each load side terminal of the service breaker and the backup circuit breaker. Are connected. In addition, a control circuit is provided for turning on the thyristor for a short time in response to an open signal of one of the service breaker and the backup circuit breaker, and for turning on the other of the service breaker and the backup circuit breaker during the short-time conduction state of the thyristor. Provided.

【0009】請求項2記載の電源切替装置は、請求項1
の電源切替装置において、サイリスタに限流抵抗を直列
接続するとともにこのサイリスタに流れる負荷電流の波
形を分析する波形分析器を設け、この波形分析器が波形
の異常を検知したときは常用遮断器および予備遮断器の
他方の投入を禁止するようにしている。
According to a second aspect of the present invention, there is provided a power supply switching device.
In the power supply switching device, a current limiting resistor is connected in series to the thyristor, and a waveform analyzer for analyzing a waveform of a load current flowing through the thyristor is provided.When the waveform analyzer detects a waveform abnormality, a service breaker and The closing of the other of the spare circuit breakers is prohibited.

【0010】[0010]

【作用】請求項1記載の構成によれば、常用遮断器を開
放して予備遮断器を投入するとき、あるいは予備遮断器
を開放して常用遮断器を投入する場合において、切替の
過渡期にサイリスタが短時間導通状態となるので、負荷
への一時的な電力供給の停止を生じることなく、常用電
源より負荷へ電力供給する状態から予備電源より負荷へ
電力供給する状態へ切り替えることができ、あるいはそ
の逆の状態に切り替えることができる。また、サイリス
タは、常用遮断器および予備遮断器の一方が開放された
後常用遮断器および予備遮断器の他方が投入されるまで
の短時間だけ導通させればよいだけであるので、サイリ
スタは短時間定格の小容量ものでよく、サイリスタの発
熱はほとんどないと考えられ、冷却設備等も不要であ
る。
According to the first aspect of the invention, when the service breaker is opened and the spare circuit breaker is turned on, or when the service breaker is opened and the service breaker is turned on, the switching circuit is in a transition period. Since the thyristor is in a conducting state for a short time, it is possible to switch from a state in which power is supplied from the normal power supply to the load to a state in which power is supplied from the standby power supply to the load without causing a temporary stop of power supply to the load, Alternatively, the state can be switched to the opposite state. In addition, the thyristor need only be turned on for a short period of time after one of the service breaker and the backup circuit breaker is opened until the other of the service breaker and the backup circuit breaker is closed. A small capacity with a time rating may be sufficient, the thyristor is considered to generate little heat, and no cooling equipment is required.

【0011】請求項2記載の構成によれば、切替動作の
途中で例えば負荷等の事故が発生したときに、限流抵抗
により過大な事故電流を抑制することができる。また、
切替の途中において、波形分析器によってサイリスタに
流れる負荷電流の波形を分析し、波形分析器が波形の異
常を検知したときは常用遮断器および予備遮断器の他方
の投入を禁止することができる。
According to the configuration of the second aspect, when an accident such as a load occurs during the switching operation, an excessive accident current can be suppressed by the current limiting resistance. Also,
During the switching, the waveform of the load current flowing through the thyristor is analyzed by the waveform analyzer, and when the waveform analyzer detects an abnormality in the waveform, the closing of the other of the service breaker and the spare breaker can be prohibited.

【0012】[0012]

【実施例】この考案の一実施例を図1に基づいて説明す
る。この電源切替装置は、図1に示すように、常用電源
(図示せず)に常用遮断器1の電源側端子を接続し、予
備電源(図示せず)に予備遮断器2の電源側端子を接続
し、常用遮断器1および予備遮断器2の各負荷側端子を
負荷(図示せず)に共通接続している。また、常用遮断
器1および予備遮断器2の各電源側端子に切替スイッチ
3の一対の切替端子を接続し、この切替スイッチ3の共
通端子と常用遮断器1および予備遮断器2の各負荷側端
子との間に限流抵抗4およびサイリスタ5の直列回路を
接続している。さらに、常用遮断器1および予備遮断器
2の一方の開放信号に応答してサイリスタ5を短時間導
通状態とし、サイリスタ5の短時間導通状態の間に常用
遮断器1および予備遮断器2の他方を投入する制御回路
8を設けている。
An embodiment of the present invention will be described with reference to FIG. In this power supply switching device, as shown in FIG. 1, a power supply terminal of a service breaker 1 is connected to a power supply (not shown), and a power supply terminal of a protection circuit breaker 2 is connected to a backup power supply (not shown). The load-side terminals of the service breaker 1 and the backup circuit breaker 2 are commonly connected to a load (not shown). Further, a pair of switching terminals of a changeover switch 3 are connected to respective power supply side terminals of the service breaker 1 and the backup circuit breaker 2, and a common terminal of the changeover switch 3 and each load side of the service breaker 1 and the backup circuit breaker 2 are connected. A series circuit of the current limiting resistor 4 and the thyristor 5 is connected between the terminal and the terminal. Further, the thyristor 5 is turned on for a short time in response to an open signal of one of the service breaker 1 and the protection circuit breaker 2, and the other of the service breaker 1 and the protection circuit breaker 2 during the short-time state of the thyristor 5. Is provided with a control circuit 8 for inputting.

【0013】また、切替動作の途中においてサイリスタ
5に流れる負荷電流の波形を変流器6を通して検出しそ
れを分析する波形分析器7を設け、この波形分析器7が
波形の異常を検知したときは常用遮断器1および予備遮
断器2の他方の投入を禁止するようにしている。ここ
で、常用電源より負荷へ電力供給している状態から予備
電源より負荷へ電力供給する状態へ切り替えるときの動
作について説明する。
Further, a waveform analyzer 7 for detecting a waveform of a load current flowing through the thyristor 5 through the current transformer 6 and analyzing the load current during the switching operation is provided. When the waveform analyzer 7 detects a waveform abnormality, Is designed to prohibit the other one of the service breaker 1 and the spare breaker 2 from being turned on. Here, an operation when switching from a state in which power is supplied from the normal power supply to the load to a state in which power is supplied from the standby power supply to the load will be described.

【0014】まず、常用遮断器1にトリップ信号を与
え、常用遮断器1の開放信号をサイリスタ5のゲートに
送出すると、サイリスタ5は導通し、負荷へは無停電で
予備電源よりの電力供給に切り替わる。この際、負荷電
流が変流器6を介して波形分析器7に入力される。波形
分析器7は、入力電流を波形分析し、負荷側に短絡事故
等が発生しているか否かの診断を行う。もし、負荷側に
事故が発生していると、事故電流がサイリスタ5を通し
て流れるが、この電流は限流抵抗4によって抑制され、
過大な事故電流は流れず常用電源あるいは予備電源等の
電力系統や負荷等の損害が低減される。また、このと
き、波形分析器7は、波形異常の発生から負荷側の事故
の発生を検知したときは、制御回路8へ事故検知信号を
与える。この結果、制御回路8は、予備遮断器2への投
入信号の供給を停止し、予備遮断器2を投入せず、開放
状態を維持させ、サイリスタ5へのゲート信号を遮断し
てサイリスタ5を遮断させ、負荷への給電経路を完全に
遮断し、事故の拡大を防止する。
First, when a trip signal is given to the service breaker 1 and an open signal of the service breaker 1 is sent to the gate of the thyristor 5, the thyristor 5 conducts, and the load is uninterrupted and power is supplied from the standby power supply. Switch. At this time, the load current is input to the waveform analyzer 7 via the current transformer 6. The waveform analyzer 7 analyzes the waveform of the input current and diagnoses whether a short circuit accident or the like has occurred on the load side. If an accident has occurred on the load side, an accident current flows through the thyristor 5, but this current is suppressed by the current limiting resistor 4,
Excessive fault current does not flow, and damage to the power system, load, etc., such as a normal power supply or a standby power supply, is reduced. At this time, when the waveform analyzer 7 detects the occurrence of an accident on the load side from the occurrence of a waveform abnormality, the waveform analyzer 7 supplies an accident detection signal to the control circuit 8. As a result, the control circuit 8 stops supplying the closing signal to the spare circuit breaker 2, keeps the open state without turning on the spare circuit breaker 2, and shuts off the gate signal to the thyristor 5 to turn on the thyristor 5. Shut down and completely cut off the power supply path to the load, preventing the spread of accidents.

【0015】一方、負荷側に事故が発生していないとき
は、波形分析器7は波形異常を検出しないので、制御回
路8は、予備遮断器2に対して投入信号を供給して、予
備遮断器2を投入させる。さらに、この投入信号をサイ
リスタ5のゲートへ与え、つまり、サイリスタ5のゲー
ト信号を遮断し、サイリスタ5を遮断させる。その後、
切替スイッチ3の接点を反転させ、常用遮断器1の方へ
接続を切り替え、つぎの電源切替動作に備える。
On the other hand, when no accident has occurred on the load side, the waveform analyzer 7 does not detect a waveform abnormality. The container 2 is turned on. Further, this input signal is supplied to the gate of the thyristor 5, that is, the gate signal of the thyristor 5 is cut off, and the thyristor 5 is cut off. afterwards,
The contact of the changeover switch 3 is inverted to switch the connection to the service breaker 1 to prepare for the next power supply switching operation.

【0016】以上の動作により、常用電源より負荷へ電
力供給する状態から予備電源より負荷電力供給する状態
へ一時的な電力供給の停止を生じることなく切替を行う
ことができる。なお、予備電源より負荷へ電力供給する
状態から常用電源より負荷へ電力供給する状態へ切り替
える動作も、上記の切替動作と同様である。
With the above operation, switching from a state in which power is supplied from a normal power supply to a load to a state in which load power is supplied from a standby power supply can be performed without temporarily stopping power supply. The operation of switching from the state where power is supplied from the standby power supply to the load to the state where power is supplied from the regular power supply to the load is the same as the above-described switching operation.

【0017】このように構成すると、常用遮断器1を開
放して予備遮断器2を投入するとき、あるいは予備遮断
器2を開放して常用遮断器1を投入する場合において、
それらの切替の過渡期にサイリスタ5が短時間導通状態
となるため、負荷への一時的な電力供給停止を生じるこ
となく、常用電源より負荷へ電力供給する状態から予備
電源より負荷へ電力供給する状態へ切り替えることがで
き、またその逆の状態に切り替えることができる。
With this configuration, when the service breaker 1 is opened and the spare circuit breaker 2 is closed, or when the service breaker 2 is opened and the service breaker 1 is closed,
Since the thyristor 5 is in a conducting state for a short time in the transition period of the switching, the power supply from the normal power supply to the load is supplied to the load from the standby power supply without temporarily stopping the power supply to the load. State and vice versa.

【0018】また、常時の通電能力および事故時の短時
間短絡電流に対する熱容量は、常用遮断器1および予備
遮断器2に持たせてあり、サイリスタ5は、常用遮断器
1が開放された後予備遮断器2が投入されるまでの電源
切替の過渡期間に短時間導通させればよいだけであるの
で、サイリスタ5については連続通電定格容量は不要
で、短時間定格容量を備えるだけでよく、サイリスタ5
としては小型のものでよく、さらにサイリスタ5の発熱
はほとんどないと考えられ、冷却設備等も不要であり、
設備が小型化できるとともに低コスト化を達成できる。
The normal circuit breaker 1 and the spare circuit breaker 2 are provided with a normal current carrying capacity and a heat capacity for a short-circuit current in the event of an accident. The thyristor 5 operates after the service circuit breaker 1 is opened. It is only necessary to conduct for a short time during the transition period of the power supply switching before the circuit breaker 2 is turned on. 5
The thyristor 5 is considered to generate almost no heat, and no cooling equipment is required.
Equipment can be reduced in size and cost can be reduced.

【0019】また、切替動作の途中で例えば負荷等の事
故が発生したときには、限流抵抗4により過大な事故電
流を抑制することができる。また、切替動作の途中にお
いて、波形分析器7によってサイリスタ5に流れる負荷
電流の波形を分析し、波形分析器7が波形の異常を検知
したときは常用遮断器1および予備遮断器2の他方の投
入を禁止することにより、負荷への電力供給の切替動作
が停止し、事故の拡大を防止することができ、常用電源
あるいは予備電源等の電力系統や負荷の損害を少なくす
ることができる。
Further, when an accident such as a load occurs during the switching operation, an excessive accident current can be suppressed by the current limiting resistor 4. Also, during the switching operation, the waveform of the load current flowing through the thyristor 5 is analyzed by the waveform analyzer 7, and when the waveform analyzer 7 detects a waveform abnormality, the other of the service breaker 1 and the spare breaker 2 is detected. By prohibiting the power supply, the switching operation of the power supply to the load is stopped, the accident can be prevented from spreading, and the damage to the power system such as the normal power supply or the standby power supply and the load can be reduced.

【0020】[0020]

【考案の効果】請求項1記載の電源切替装置によれば、
常用遮断器および予備遮断器の一方を開放して常用遮断
器および予備遮断器の他方を投入するまでの過渡期間に
サイリスタを短時間導通させるので、負荷への電力供給
の一時的な停止を生じることなく瞬時切替を行うことが
でき、しかもサイリスタは短時間導通させるだけである
ので、短時間定格の小容量ものでよく、サイリスタの発
熱はほとんどないと考えられ、冷却設備等も不要であ
り、設備構成を小型化できるとともにコストを低く抑え
ることができる。
According to the power supply switching device of the first aspect,
Since the thyristor is turned on for a short time during the transition period between opening the service breaker and the backup circuit breaker and turning on the other of the service circuit breaker and the backup circuit breaker, the power supply to the load is temporarily stopped. Switching can be performed instantaneously, and the thyristor is only made to conduct for a short time.Thus, a small capacity with a short-time rating is sufficient, and it is considered that the thyristor generates almost no heat. The equipment configuration can be reduced in size and the cost can be kept low.

【0021】請求項2記載の電源切替装置によれば、サ
イリスタと直列に設けた限流抵抗で事故電流を制限する
とともに、波形分析器が波形異常を検知したときに常用
遮断器および予備遮断器の他方の投入を禁止するので、
切替動作の途中で負荷等に事故が発生して例えば過大な
事故電流が流れるような場合における事故の拡大を防止
することができる。
According to the power supply switching device of the present invention, the fault current is limited by the current limiting resistor provided in series with the thyristor, and the service breaker and the backup breaker are used when the waveform analyzer detects a waveform abnormality. Prohibits the input of the other,
In the case where an accident occurs in a load or the like during the switching operation and an excessive accident current flows, for example, it is possible to prevent the accident from spreading.

【図面の簡単な説明】[Brief description of the drawings]

【図1】この考案の一実施例の電源切替装置の構成を示
す概略図である。
FIG. 1 is a schematic diagram showing a configuration of a power supply switching device according to an embodiment of the present invention.

【図2】従来の電源切替装置の一例の構成を示す概略図
である。
FIG. 2 is a schematic diagram illustrating a configuration of an example of a conventional power supply switching device.

【図3】従来の電源切替装置の他の例の構成を示す概略
図である。
FIG. 3 is a schematic diagram showing the configuration of another example of a conventional power supply switching device.

【符号の説明】[Explanation of symbols]

1 常用遮断器 2 予備遮断器 3 切替スイッチ 4 限流抵抗 5 サイリスタ 6 変流器 7 波形分析器 8 制御回路 DESCRIPTION OF SYMBOLS 1 Working circuit breaker 2 Preliminary circuit breaker 3 Changeover switch 4 Current limiting resistor 5 Thyristor 6 Current transformer 7 Waveform analyzer 8 Control circuit

Claims (2)

(57)【実用新案登録請求の範囲】(57) [Scope of request for utility model registration] 【請求項1】 常用電源に電源側端子を接続した常用遮
断器および予備電源に電源側端子を接続した予備遮断器
の各負荷側端子を負荷に共通接続した電源切替装置にお
いて、 前記常用遮断器および前記予備遮断器の各電源側端子に
一対の切替端子を接続した切替スイッチと、この切替ス
イッチの共通端子と前記常用遮断器および前記予備遮断
器の各負荷側端子との間に接続したサイリスタとを備
え、 前記常用遮断器および前記予備遮断器の一方の開放信号
に応答して前記サイリスタを短時間導通状態とし、前記
サイリスタの短時間導通状態の間に前記常用遮断器およ
び前記予備遮断器の他方を投入する制御回路を設けたこ
とを特徴とする電源切替装置。
1. A power supply switching device, wherein each load side terminal of a service breaker having a power supply terminal connected to a service power supply and a load breaker having a power supply terminal connected to a standby power supply is commonly connected to a load. A changeover switch having a pair of changeover terminals connected to each power supply side terminal of the spare breaker; and a thyristor connected between a common terminal of the changeover switch and each load side terminal of the service breaker and the spare breaker. The thyristor is turned on for a short time in response to an open signal of one of the service breaker and the backup circuit breaker, and the service breaker and the backup circuit breaker are turned off during the short-time conductive state of the thyristor. A power supply switching device provided with a control circuit for inputting the other of the above.
【請求項2】 サイリスタに限流抵抗を直列接続すると
ともにこのサイリスタに流れる負荷電流の波形を分析す
る波形分析器を設け、この波形分析器が波形の異常を検
知したときは常用遮断器および予備遮断器の他方の投入
を禁止するようにした請求項1記載の電源切替装置。
2. A thyristor having a current limiting resistor connected in series and a waveform analyzer for analyzing a waveform of a load current flowing through the thyristor is provided. 2. The power supply switching device according to claim 1, wherein the closing of the other of the circuit breakers is prohibited.
JP1993045734U 1993-08-23 1993-08-23 Power switching device Expired - Fee Related JP2589936Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1993045734U JP2589936Y2 (en) 1993-08-23 1993-08-23 Power switching device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1993045734U JP2589936Y2 (en) 1993-08-23 1993-08-23 Power switching device

Publications (2)

Publication Number Publication Date
JPH0716555U JPH0716555U (en) 1995-03-17
JP2589936Y2 true JP2589936Y2 (en) 1999-02-03

Family

ID=12727556

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1993045734U Expired - Fee Related JP2589936Y2 (en) 1993-08-23 1993-08-23 Power switching device

Country Status (1)

Country Link
JP (1) JP2589936Y2 (en)

Also Published As

Publication number Publication date
JPH0716555U (en) 1995-03-17

Similar Documents

Publication Publication Date Title
CA2780946C (en) Device and method to break the current of a power transmission or distribution line and current limiting arrangement
US7545611B2 (en) Electric power circuit protecting apparatus using superconductor
JP2695941B2 (en) Uninterruptible power system
JP5567624B2 (en) Protection coordination system
JP3428242B2 (en) Uninterruptible power system
JP2589936Y2 (en) Power switching device
JP3101736B2 (en) Distribution line protection device
JP2726506B2 (en) Uninterruptible power supply system
JP3041449U (en) Power switch
JP3817921B2 (en) Grid interconnection device
JPH05236646A (en) Current limiter
KR20000025964A (en) Control method of auxiliary power device
JP2784142B2 (en) Circuit breakers and circuit breakers
JPS62117226A (en) Detector of disability of breaking of switch
JPH027831A (en) Protective circuit for inverter
JPH07107656A (en) Protecting device for electric power system
JPH07282691A (en) Commutation type dc circuit breaker
JP3564823B2 (en) Switchgear
JP2002093291A (en) Semiconductor switch and its control method
JPH09298885A (en) Protection of series inverter circuit
JP2001333537A (en) Power supply facility
JP2739022B2 (en) High-voltage three-phase distribution line phase switching device
JPS60141189A (en) Thyristor inverter operation protecting circuit
JPH05144350A (en) Thyristor switch
JPH04312330A (en) Uninterruptible power supply

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees