JP2551488B2 - Lifting method by crane and lifting jig - Google Patents

Lifting method by crane and lifting jig

Info

Publication number
JP2551488B2
JP2551488B2 JP2001396A JP139690A JP2551488B2 JP 2551488 B2 JP2551488 B2 JP 2551488B2 JP 2001396 A JP2001396 A JP 2001396A JP 139690 A JP139690 A JP 139690A JP 2551488 B2 JP2551488 B2 JP 2551488B2
Authority
JP
Japan
Prior art keywords
hoisting
crane
wire
winch
lifting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001396A
Other languages
Japanese (ja)
Other versions
JPH03205293A (en
Inventor
博光 矢野
稜朗 青木
健治 岡田
光延 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP2001396A priority Critical patent/JP2551488B2/en
Publication of JPH03205293A publication Critical patent/JPH03205293A/en
Application granted granted Critical
Publication of JP2551488B2 publication Critical patent/JP2551488B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、建築物の構築過程において、主架構の軸組
み後に、柱、梁または壁用のコンクリート型枠、鉄筋
等、大型の機材を、クレーンによって揚上操作する方法
に係り、とくに、クレーンの吊上げフック下と吊上げ作
業空間との間に、上階の先行梁に養生網が張設されてい
る場合の建設機材の吊上げ方法と、その方法に使用する
ためのクレーン用吊上げ治具に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Industrial field of application] The present invention relates to a large equipment such as a concrete formwork for a pillar, a beam or a wall, a reinforcing bar, etc. after a main frame is assembled in a building construction process. , A method of hoisting with a crane, in particular, a method of hoisting construction equipment when a curing net is stretched on the preceding beam on the upper floor between the hoisting space of the crane and the hoisting work space, The present invention relates to a crane lifting jig for use in the method.

[従来の技術] 最近の建築物構築用の機材は、労務費の削減や、工期
の短縮を目的として、大型の組立ユニットに構成される
ことが多くなっており、その施工位置への設置のために
は、クレーンを使用して移動させるようにしている。そ
して、建築物の施工が進行した階段では、その主なもの
は柱、梁または壁用のコンクリート型枠または床スラブ
用のデッキプレート等である。一方、建設中の建築物で
は、安全管理が重要であり、とくに、鉄骨工事が先行し
て上階に進行しているときには、架構済みの梁を利用し
て養生網を張設し、工具や材料の取り落しや、作業員の
墜落に対処することが不可欠である。そのような状況を
第5図によって示せば、1は鉄骨鉄筋コンクリート造の
建築物の全体を示し、2は柱、3は各階の梁、4はコン
クリート打設が終了した床スラブ、5は先行して架設さ
れた梁3に装備した吊り足場、6は吊り足場5の間に張
設された落下防止のための安全用の養生網、7は梁3の
鉄筋、8は梁3の梁型枠、9は小梁用の型枠である。
[Prior Art] Equipment for building construction these days is often configured into a large assembly unit for the purpose of reducing labor costs and shortening the construction period. In order to do so, I am using a crane to move it. In the stairs where the construction of the building has progressed, the main ones are concrete formwork for columns, beams or walls, or deck plates for floor slabs. On the other hand, in buildings under construction, safety management is important, and especially when steel frame construction is proceeding to the upper floors, a curing net is erected by using a framed beam and tools and It is essential to deal with material loss and worker crashes. If such a situation is shown in FIG. 5, 1 shows the whole structure of a steel-framed reinforced concrete structure, 2 is a pillar, 3 is a beam on each floor, 4 is a floor slab for which concrete placement has been completed, and 5 is a preceding one. Suspended scaffolding installed on the beam 3 erected, 6 is a safety net stretched between the suspended scaffolds 5 to prevent falling, 7 is a reinforcing bar of the beam 3, and 8 is a beam form of the beam 3. , 9 are molds for the beam.

一方、10は建築物1の構築のために装備された図示し
ないクレーンの主作業用のダブルの吊りワイヤロープで
あり、その下端には、吊りシーブ11を介してクレーンフ
ック12が昇降自在に設けてあり、床スラブ4上で地組み
した小梁型枠9には、台付ワイヤ13が取付けてあって、
この型枠9の揚上作業が本発明の対象になっている。
On the other hand, 10 is a double hanging wire rope for main work of a crane (not shown) equipped for building the building 1, and a crane hook 12 is provided at the lower end thereof via a hanging sheave 11 so as to be vertically movable. There is a wire 13 with a base attached to the beam girder formwork 9 that is grounded on the floor slab 4,
The lifting work of the mold 9 is the subject of the present invention.

しかしながら、上段の梁3には養生網6が張設してあ
り、吊りワイヤロープ10を操作しても、下端の吊りシー
ブ11と、クレーンフック12が、当然、養生網6の網目を
通過できないため、梁型枠9に取付けた台付ワイヤ13の
上端をクレーンフック12に係着することができない。
However, the curing net 6 is stretched on the upper beam 3, and even if the suspension wire rope 10 is operated, the suspension sheave 11 at the lower end and the crane hook 12 cannot pass through the mesh of the curing net 6 as a matter of course. Therefore, the upper end of the wire with base 13 attached to the beam form 9 cannot be attached to the crane hook 12.

[発明が解決しようとする課題] 従来のクレーンによる吊上げ方法では、上記のような
場合に、梁3の型枠8では、鉄骨の軸組に続いて早期に
揚上することができても、小梁の型枠9の設置には、地
組をしないで小型の部材のままクレーンによらずに運搬
したのち、梁3の型枠8に、梁底、梁側の順に組付ける
か、揚上の都度、養生網6を一時的に撤去してクレーン
を使用しなければならない。この間の掛け払いの作業
は、高所における広い領域での取扱いになり、作業員に
危険を伴うばかりでなく、作業そのものに長時間を要す
るものであり、地組の利点が活用できず、一方作業場に
おけるクレーンの利用効率が低下するものであって、こ
のような作業が多くなるに伴って、合理的な対策が要望
されていた。
[Problems to be Solved by the Invention] In the conventional hoisting method using a crane, in the case as described above, even if the frame 8 of the beam 3 can be quickly lifted after the steel frame is assembled, In order to install the beam form 9 of the beam, after carrying it as a small member without erection without using a crane, assemble the beam 8 of the beam 3 in the order of beam bottom and beam side, or lift. Each time, the curing net 6 must be temporarily removed and the crane must be used. The work of brushing over during this period requires handling in a wide area at a high place, which not only poses a danger to workers, but also takes a long time for the work itself, and the advantages of the ground structure cannot be utilized. The use efficiency of the crane in the workplace is reduced, and as such work increases, rational measures have been demanded.

[課題を解決するための手段] 本発明は、上記のような現状に鑑み、建築物の構築階
段で、クレーンの吊上げフック下と吊上げ作業空間との
間に上階の先行梁に養生網が張設されている場合に、ク
レーンフックの通過が不可能な養生網の存在に拘らず、
その網目を通過して建設機材を吊上げる方法を要旨とし
ている。そして、そのための技術的手段は、クレーンの
操作空間の上方に養生網が張設されている場合の建設機
材の吊上げ方法であって、クレーンの吊上げフックに小
型ウィンチを取付け、ウィンチワイヤの下端に長ナット
と案内重錘とからなる吊上げ治具を接続し、養生網の上
方でウィンチを巻出して案内重錘を養生網の網目を貫通
させたのち、案内重錘を取外し、ワイヤロープの下端部
分を折り返して長ナットを台付ワイヤに挿通すると共
に、ループを形成して固定し、台付ワイヤを下方の建設
機材に係着して前記ウィンチによって揚上することを特
徴としている。
[Means for Solving the Problems] In view of the above-mentioned current situation, the present invention provides a curing net on the preceding beam on the upper floor between the lifting hook of the crane and the lifting work space in the building staircase. Despite the existence of a curing net that is impossible to pass the crane hook when stretched,
The main point is to lift construction equipment through the mesh. And the technical means for that is a method of hoisting construction equipment when a curing net is stretched above the operating space of the crane, in which a small winch is attached to the hoisting hook of the crane and the lower end of the winch wire is attached. Connect a lifting jig consisting of a long nut and a guide weight, unwind a winch above the curing net to pass the guide weight through the mesh of the curing net, then remove the guide weight and lower the lower end of the wire rope. It is characterized in that the long nut is inserted into the wire with a stand and the loop is formed and fixed, and the wire with a stand is attached to the lower construction equipment and lifted by the winch.

これによって、本発明によれば、大型の建設機材の吊
上げ作業が合理化され、安全性を確保すると共に、プレ
ハブの利点を活かして労務費を軽減することができ、目
的に適する治具が得られたものである。
As a result, according to the present invention, hoisting work of large construction equipment is rationalized, safety is ensured, labor costs can be reduced by taking advantage of the prefab, and a jig suitable for the purpose can be obtained. It is a thing.

[実施例] 本発明のクレーンによる吊上げ方法および吊上げ治具
を実施例の図面に基づいて詳細に説明する。第1図は本
発明が適用される建築物の断面図で示す、クレーン操作
の説明図、第2図はクレーンのワイヤロープ下端部に小
型のウィンチと本発明の吊上げ治具を装着した概略側面
図、第3図はウィンチワイヤと吊上げ治具の詳細側面
図、第4図は吊上げ方法の一工程の説明図であって、第
5図の参照番号は該当部分について共通にしてある。図
において、1は鉄骨鉄筋コンクリート造の建築物であ
り、柱2と梁3を架設し、床スラブ4を構築する。この
階の床スラブ4上において、上階の梁3に架けわたす小
梁の型枠9を地組みし、これに台付ワイヤ13を取付け
る。
[Embodiment] A hoisting method and hoisting jig by a crane according to the present invention will be described in detail with reference to the drawings of the embodiment. FIG. 1 is a cross-sectional view of a building to which the present invention is applied, which is an explanatory view of crane operation, and FIG. 2 is a schematic side view in which a small winch and a lifting jig of the present invention are attached to a lower end of a wire rope of the crane. 3 and 4 are detailed side views of the winch wire and the hoisting jig, and FIG. 4 is an explanatory view of one step of the hoisting method. The reference numerals in FIG. 5 are common to the corresponding parts. In the figure, reference numeral 1 denotes a building made of steel-framed reinforced concrete, in which columns 2 and beams 3 are installed to construct a floor slab 4. On the floor slab 4 on this floor, a beam form 9 which extends over the beam 3 on the upper floor is grounded, and a wire 13 with a base is attached to this.

本発明にあっては、作業場に装備されたクレーンの吊
りシーブ11に取付けたフック12には、小型のウィンチ20
を吊り、このウィンチ20のウィンチワイヤ21の下端に、
本発明の吊上げ治具30を装着する。吊上げ治具30は、上
端をウィンチワイヤ21の下端に固着する長ナット31と、
その下半部に螺合によって接続された案内重錘32とから
なっている。案内重錘32はその下端をやや尖らせて養生
網6の網目をくぐり易くし、上端には、上方の養生網6
の下方の揚程に応じた長さに形成した連結杆33が固着し
てある。
In the present invention, the hook 12 attached to the hanging sheave 11 of the crane installed in the workplace has a small winch 20.
Hanging on the lower end of the winch wire 21 of this winch 20,
The lifting jig 30 of the present invention is attached. The lifting jig 30 includes a long nut 31 whose upper end is fixed to the lower end of the winch wire 21,
A guide weight 32 is connected to the lower half portion thereof by screwing. The guide weight 32 has its lower end slightly sharpened so as to easily pass through the mesh of the curing net 6, and the upper end thereof has an upper curing net 6 at its upper end.
A connecting rod 33 having a length corresponding to the lifting height below is fixedly attached.

本発明の対象となる建設機材は、上記の実施例の小梁
用型枠に限定されないことはもちろんであり、上階の先
行梁に養生網が張設されている場合の、柱または壁用の
コンクリート型枠、あるいはデッキプレート等の、大型
の機材を対象にすることができる。
Needless to say, the construction equipment to which the present invention is applied is not limited to the formwork for beam girders of the above-described embodiments, and is used for columns or walls when a curing net is stretched on the preceding beam on the upper floor. It can be used for large equipment such as concrete formwork or deck plate.

[作 用] 本発明のクレーンによる吊上げ方法と吊上げ用治具と
を前記実施例の建築物1の構築工程とその際の吊上げ治
具の使用方法に基づいて説明する。
[Operation] The hoisting method and hoisting jig by the crane of the present invention will be described based on the building process of the building 1 of the above-mentioned embodiment and the method of using the hoisting jig at that time.

第1図において、吊上げ治具30は、養生網6の上方に
おいてフック12に取付けた小型ウィンチ20のウィンチワ
イヤ21の下端に取付けられており、ウィンチ20を巻出
し、案内重錘32の下端から、つづいて長ナット31を養生
網6の網目をくぐらせる。案内重錘32は、ほぼ建築物1
の階高に対応する長さに対応した連結杆33を有し、床ス
ラブ4の面に到達した位置で、挿通案内の役目を終え、
長ナット31との螺合から取外す。
In FIG. 1, the hoisting jig 30 is attached to the lower end of the winch wire 21 of the small winch 20 attached to the hook 12 above the curing net 6, and unwinds the winch 20 from the lower end of the guide weight 32. Then, the long nut 31 is passed through the mesh of the curing net 6. The guide weight 32 is almost a building 1.
It has a connecting rod 33 corresponding to the length corresponding to the floor height of, and ends the role of insertion guide at the position where it reaches the surface of the floor slab 4,
Remove from screwing with long nut 31.

次に、長ナット31を付けたままのウィンチワイヤ21の
下端部分を台付ワイヤ13のループに挿通したのち、第4
図に示すように、ウィンチワイヤ21を折り返してループ
22を形成し、端部部分をクリップ23を使用して、確実に
ウィンチワイヤ21に固定する。次に、台付ワイヤ13を機
材に係着し、または予め係着しておくことによって、前
記ウィンチ20によって型枠9を揚上することができる。
もちろん、この間に作業はすべて養生網6の下方で行わ
れるから、ウィンチワイヤ21がその網目を通過している
だけで、一切の障害にならない。
Next, after inserting the lower end portion of the winch wire 21 with the long nut 31 attached, into the loop of the wire with base 13,
Fold the winch wire 21 back into the loop as shown
22 is formed and the end portion is securely fixed to the winch wire 21 by using the clip 23. Next, the platform wire 13 is attached to the equipment or previously attached, so that the winch 20 can lift the formwork 9.
Of course, during this time, all the work is performed below the curing net 6, so that the winch wire 21 simply passes through the net and does not cause any obstacle.

ここで作業員は親網81に安全用の命網を係着し、型枠
9は梁3の型枠8間に架設される。
Here, the worker attaches a safety life net to the main net 81, and the formwork 9 is installed between the formwork 8 of the beam 3.

[発明の効果] 本発明は上述のように、クレーンの吊上げフック下と
吊上げ作業空間との間に養生網が張設されている場合の
建設機材の吊上げ方法であって、クレーンの吊上げフッ
クに小型ウィンチを取付け、ウィンチワイヤの下端に長
ナットと案内重錘とからなる吊上げ治具を接続し、養生
網の上方でウィンチを巻出して案内重錘を養生網の網目
を貫通させたのち、案内重錘を取外し、ワイヤロープの
下端部分を折り返して長ナットを台付ワイヤに挿通する
と共に、ループを形成して固定し、台付ワイヤを下方の
建設機材に係着して前記ウィンチによって揚上するもの
であるから、まず、吊上げ治具の構成によって、養生網
を張設したまま、その網目をくぐらせて揚上ワイヤを建
設機材に係着し、養生網の上方での操作によって所定の
揚程を得ることができ、その結果、大型の建設機材をそ
のまま、または地組みすることができる利点があり、分
解した小型の部材をクレーンによらずに運搬したり、養
生網を揚上の都度、一時的に撤去してクレーンを使用し
なければならない等の不利益が回避できる。さらに、高
所における作業とその手間が不要で、かつ、作業員に危
険を伴わないばかりでなく、作業場におけるクレーンの
利用効率が低下することがないから、経済的な改善がも
たらされる。
[Effects of the Invention] As described above, the present invention is a method for hoisting construction equipment in which a curing net is stretched between the hoisting hook under the crane and the hoisting work space. Attach a small winch, connect a lifting jig consisting of a long nut and a guide weight to the lower end of the winch wire, unwind the winch above the curing net and let the guide weight penetrate the mesh of the curing net, Remove the guide weight, fold back the lower end of the wire rope and insert the long nut into the wire with base, fix it by forming a loop, and attach the base wire to the construction equipment below and lift it with the winch. First, by using the structure of the hoisting jig, the lifting wire is stretched, the lifting wire is passed through the mesh, and the lifting wire is attached to the construction equipment. Head of As a result, there is an advantage that large construction equipment can be used as it is or can be grounded, and it is possible to carry disassembled small members without using a crane or lift the curing net every time, The disadvantages such as having to temporarily remove and use a crane can be avoided. Further, not only the work at a high place and the labor thereof are unnecessary, and the worker is not in danger, but the utilization efficiency of the crane in the work place is not lowered, so that the economical improvement is brought about.

また、吊上げ治具には通常の材料を使用し、構造も簡
単であることによって、製作費用が低廉であり、使用に
際してはワイヤロープの取扱いだけでよく、小型のウィ
ンチの使用にも格別な技術を必要としないから、本発明
の吊上げ方法とその吊上げ治具とは、建築物の構築、こ
とに近代的な工法に貢献するところがきわめて大きい発
明ということができる。
Also, because the hoisting jig uses normal materials and the structure is simple, the manufacturing cost is low, and it is only necessary to handle the wire rope at the time of use, and a special technique for using a small winch. Therefore, it can be said that the hoisting method and hoisting jig of the present invention greatly contribute to the construction of buildings and especially to modern construction methods.

【図面の簡単な説明】[Brief description of drawings]

図面は本発明の実施例を示し、第1図は本発明が適用さ
れる建築物の断面図で示す、クレーン操作の説明図、第
2図はクレーンのワイヤロープ下端部の詳細図、第3図
は本発明の吊上げ治具の側面図、第4図は工程の一部の
説明図であり、第5図は従来技術を説明する第1図に対
応する建築物の断面図である。 1……建築物、2……柱、3……梁、4……床スラブ、
5……吊り足場、6……養生網、7……鉄筋、8……梁
型枠、9……小梁型枠、10……ワイヤロープ、11……吊
りシーブ、12……クレーンフック、13……台付ワイヤ、
20……ウィンチ、21……ウィンチワイヤ、22……ルー
プ、23……クリップ、30……吊上げ治具、31……長ナッ
ト、32……案内重錘、33……連結杆。
Drawing shows an embodiment of the present invention, Fig. 1 is a sectional view of a building to which the present invention is applied, an explanatory view of crane operation, Fig. 2 is a detailed view of a lower end portion of a wire rope of a crane, and Fig. 3 FIG. 4 is a side view of a hoisting jig of the present invention, FIG. 4 is an explanatory view of a part of the process, and FIG. 5 is a sectional view of a building corresponding to FIG. 1 for explaining a conventional technique. 1 ... Building, 2 ... Pillar, 3 ... Beam, 4 ... Floor slab,
5: Suspension scaffolding, 6 ... Curing net, 7 ... Reinforcing bar, 8 ... Beam form, 9 ... Small beam form, 10 ... Wire rope, 11 ... Hanging sheave, 12 ... Crane hook, 13 …… Wire with stand,
20 …… winch, 21 …… winch wire, 22 …… loop, 23 …… clip, 30 …… lifting jig, 31 …… long nut, 32 …… guide weight, 33 …… connecting rod.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】クレーンの吊上げフック下と吊上げ作業空
間との間に養生網が張設されている場合の建設機材の吊
上げ方法であって、クレーンの吊上げフックに小型ウィ
ンチを取付け、ウィンチワイヤの下端に長ナットと案内
重錘とからなる吊上げ治具を接続し、養生網の上方でウ
ィンチを巻出して案内重錘を養生網の網目を貫通させた
のち、案内重錘を取外し、ワイヤロープの下端部分を折
り返して長ナットを台付ワイヤに挿通すると共に、ルー
プを形成して固定し、台付ワイヤを下方の建設機材に係
着して前記ウィンチによって揚上することを特徴とする
クレーンによる吊上げ方法。
1. A method of hoisting construction equipment, wherein a curing net is stretched between a hoisting space under a hoisting hook of a crane, and a small winch is attached to the hoisting hook of the crane to secure a winch wire. Connect a lifting jig consisting of a long nut and a guide weight to the lower end, unwind the winch above the curing net to penetrate the net of the curing net, then remove the guide weight and remove the wire rope. A crane characterized in that the lower end of the base is folded back and a long nut is inserted into the wire with a base, a loop is formed and fixed, and the wire with a base is attached to the lower construction equipment and lifted by the winch. Lifting method.
【請求項2】クレーンの吊上げフック下と吊上げ作業空
間との間に養生網が張設されている場合の建設機材の吊
上げ方法に使用される吊上げ用治具であって、長ナット
と案内重錘とからなり、両者は養生網の網目を貫通する
太さに形成して、相互に螺合接続され、案内重錘は、上
方の養生網下の揚程に応じた長さに形成され、下端を尖
らせてあることを特徴とするクレーン用吊り上げ治具。
2. A hoisting jig used for hoisting construction equipment when a curing net is stretched between a hoisting hook of a crane and a hoisting work space, wherein a long nut and a guide weight are used. It consists of a weight, both of which are formed into a thickness that penetrates the net of the curing net and are screwed together, and the guide weight is formed with a length corresponding to the lifting height of the upper curing net and the lower end. A hoisting jig for cranes, which has a sharpened tip.
JP2001396A 1990-01-08 1990-01-08 Lifting method by crane and lifting jig Expired - Lifetime JP2551488B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001396A JP2551488B2 (en) 1990-01-08 1990-01-08 Lifting method by crane and lifting jig

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001396A JP2551488B2 (en) 1990-01-08 1990-01-08 Lifting method by crane and lifting jig

Publications (2)

Publication Number Publication Date
JPH03205293A JPH03205293A (en) 1991-09-06
JP2551488B2 true JP2551488B2 (en) 1996-11-06

Family

ID=11500332

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001396A Expired - Lifetime JP2551488B2 (en) 1990-01-08 1990-01-08 Lifting method by crane and lifting jig

Country Status (1)

Country Link
JP (1) JP2551488B2 (en)

Also Published As

Publication number Publication date
JPH03205293A (en) 1991-09-06

Similar Documents

Publication Publication Date Title
CN103635643B (en) The construction method of nigh-level synthesis steel bar concrete cylindrical shell
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN111255217A (en) Elevator shaft shaping operation platform and operation method thereof
CN113931313A (en) Super high-rise core tube horizontal structure construction method
JP3196043B2 (en) Construction method of stairs and staircase, construction method of stairs, and stair members
CN110735530A (en) external wall steel formwork and internal wall aluminum formwork combination system and operation method thereof
CN213836318U (en) Bridge floor wet joint hangs mould structure
CN112267692A (en) Assembly type building component hoisting comprehensive equipment and construction method thereof
JPH09317183A (en) Construction method of building
CN114508231B (en) Quick combination construction method for I-steel component
US3156071A (en) Building structure
JP2551488B2 (en) Lifting method by crane and lifting jig
CN211923466U (en) Elevator shaft regularization operation platform
CN211173029U (en) A liftable platform structure for chimney reinforcement construction
CN209742334U (en) Steel construction vestibule bottom curtain construction platform
CN113338537A (en) Construction method of ultrahigh large-section concrete frame column
JP4027170B2 (en) External scaffold device and construction method of external scaffold device
CN112627543A (en) Shaft inner lifting frame for mounting steel beams of core tube elevator shaft and steel beam construction method
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
US3295266A (en) Suspended floor system for a multi-level building
CN212671301U (en) Movable construction safety steel stair for assembly type building stairwell
CN216276830U (en) Super high-rise core tube formwork lowering construction device
CN110306784A (en) A kind of aluminum tunnel modular system and its operating method
CN215948934U (en) Construction elevator standard festival bearing support frame device
CN216840589U (en) Integral template structure for scaffold