Joint structure between reinforced concrete columns and steel beams

Info

Publication number
JP2547977Y2
JP2547977Y2 JP5442992U JP5442992U JP2547977Y2 JP 2547977 Y2 JP2547977 Y2 JP 2547977Y2 JP 5442992 U JP5442992 U JP 5442992U JP 5442992 U JP5442992 U JP 5442992U JP 2547977 Y2 JP2547977 Y2 JP 2547977Y2
Authority
JP
Japan
Prior art keywords
reinforced concrete
steel beam
joint
joint structure
concrete column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP5442992U
Other languages
Japanese (ja)
Other versions
JPH0610402U (en
Inventor
賢二 吉松
強志 辻
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kumagai Gumi Co Ltd
Original Assignee
Kumagai Gumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kumagai Gumi Co Ltd filed Critical Kumagai Gumi Co Ltd
Priority to JP5442992U priority Critical patent/JP2547977Y2/en
Publication of JPH0610402U publication Critical patent/JPH0610402U/en
Application granted granted Critical
Publication of JP2547977Y2 publication Critical patent/JP2547977Y2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Description

【考案の詳細な説明】[Detailed description of the invention]

【0001】[0001]

【産業上の利用分野】本考案は鉄筋コンクリート柱と鉄
骨梁を有する複合構造物の柱・梁接合部の構造に関する
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a column-beam joint structure of a composite structure having a reinforced concrete column and a steel beam.

【0002】[0002]

【従来技術およびその問題点】事務所ビル、ショッピン
グセンター、倉庫等の建築物には、鉄筋コンクリート柱
と鉄骨梁とからなる構造形式が採用されている。この構
造形式はスパンを長くすることができ、また、施工の合
理化を図ることができる点で優れているが、鉄筋コンク
リートおよび鉄骨という異種構造部材を組み立てるもの
であるから、これらの部材の接合部における応力伝達が
重要な課題となっている。
2. Description of the Related Art Structural forms including reinforced concrete columns and steel beams are used in buildings such as office buildings, shopping centers, and warehouses. This type of structure is excellent in that the span can be lengthened and the construction can be rationalized.However, since it is to assemble heterogeneous structural members such as reinforced concrete and steel frame, the joint at these members Stress transmission is an important issue.

【0003】鉄骨梁が鉄筋コンクリート柱を貫通するタ
イプの接合構造は、鉄骨梁の上下フランジ部近傍のコン
クリートが支圧破壊を起こし易く、接合部の耐力と変形
能が低下する虞がある。そこで、柱・梁によって構成さ
れるパネルゾーン内外に、水平ダイアフラムを設けるこ
とも行われている。
[0003] In a joint structure in which a steel beam penetrates a reinforced concrete column, concrete near the upper and lower flanges of the steel beam is liable to cause bearing failure, and there is a possibility that the strength and deformability of the joint decrease. Therefore, horizontal diaphragms are also provided inside and outside the panel zone constituted by columns and beams.

【0004】例えば、特開平1−290844号公報に
は、鉄筋コンクリート柱と鉄骨梁とを十分な機械的強度
を保って接合するために、鉄筋コンクリート柱と鉄骨梁
の接合部を鋼板で覆い、この鋼板に鉄骨梁の上下フラン
ジにそれぞれ連結する十文字状の水平ダイアフラムを上
記鋼板から外方に突出して設け、更に、この水平ダイア
フラムにコンクリート充填用穴および柱鉄筋貫通用穴を
設けた接合構造が開示されている。
For example, Japanese Patent Application Laid-Open No. 1-290844 discloses that a joint between a reinforced concrete column and a steel beam is covered with a steel plate in order to join the reinforced concrete column and the steel beam while maintaining sufficient mechanical strength. A joint structure in which cross-shaped horizontal diaphragms respectively connected to the upper and lower flanges of a steel beam are provided so as to protrude outward from the steel plate, and furthermore, the horizontal diaphragm is provided with a hole for filling concrete and a hole for penetrating a steel bar is disclosed. ing.

【0005】この接合構造は接合部を鋼板で覆っている
ので、パネルゾーンにおけるコンクリートの拘束効果が
大きい点で優れているが、接合部を覆う鋼板から水平ダ
イアフラムを突設させるなど、鋼板の加工作業が煩雑と
なるという問題点を有している。また、力学的にも、パ
ネルゾーン内に突設する水平ダイアフラムが引張り降伏
を起こす虞がある。
[0005] This joint structure is excellent in that the joint portion is covered with a steel plate, so that the concrete has a large restraint effect in the panel zone. However, the steel plate processing such as projecting a horizontal diaphragm from the steel plate covering the joint portion. There is a problem that the operation becomes complicated. Also, mechanically, the horizontal diaphragm projecting into the panel zone may cause tensile yielding.

【0006】[0006]

【考案の目的】本考案の目的は、鉄骨梁が鉄筋コンクリ
ート柱を貫通するタイプの接合部において、鉄骨梁の上
下フランジ部近傍のコンクリートが支圧破壊を惹起する
ようなことのない、優れた接合構造を提供することにあ
る。
[Object of the invention] The object of the invention is to provide an excellent joint in which a steel beam penetrates a reinforced concrete column without causing concrete bearing near the upper and lower flanges of the steel beam to cause bearing failure. It is to provide a structure.

【0007】[0007]

【考案の構成】この考案は、鉄骨梁が鉄筋コンクリート
柱を貫通する鉄筋コンクリート柱と鉄骨梁の接合構造に
おいて、該鉄筋コンクリート柱の側面に沿って水平に、
前記鉄骨梁の上下フランジにアングル材またはチャンネ
ル材を固着してなることを特徴とするものである。
[Constitution of the invention] This invention is a joint structure of a reinforced concrete column and a steel beam in which a steel beam penetrates the reinforced concrete column.
An angle material or a channel material is fixed to upper and lower flanges of the steel beam.

【0008】[0008]

【作用】上記接合構造において、鉄骨梁の応力は直接、
鉄筋コンクリート柱に伝達される。このとき、パネルゾ
ーンにおいて、前記鉄骨梁のてこ反力に対してアングル
材またはチャンネル材が効果的に抵抗するので、接合部
コンクリートの支圧破壊を防止する。
In the above joint structure, the stress of the steel beam is directly
Transmitted to reinforced concrete columns. At this time, in the panel zone, the angle material or the channel material effectively resists the lever reaction force of the steel beam, thereby preventing the bearing concrete from breaking.

【0009】[0009]

【実施例】以下、本考案の好適な実施例を図面に基づき
説明する。図1は本考案に係る鉄筋コンクリート柱10
と鉄骨梁20の接合部30の縦断側面図であり、図2と
図3は、それぞれ図1のII−II線およびIII −III 線に
おける切断平面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below with reference to the drawings. FIG. 1 shows a reinforced concrete column 10 according to the present invention.
2 and FIG. 3 are cut-away plan views taken along lines II-II and III-III in FIG. 1, respectively.

【0010】接合部30において、鉄筋コンクリート柱
10をH形鋼からなる鉄骨梁20が十字形に貫通してい
る。鉄骨梁20の上下フランジ22、22には、鉄筋コ
ンクリート柱10の外周面に沿って、アングル材32が
水平に溶接されている。アングル材32の長さは鉄骨梁
20のフランジ幅と等しいか、または、それ以上とす
る。
At the joint 30, a steel beam 20 made of H-section steel penetrates the reinforced concrete column 10 in a cross shape. Angle members 32 are horizontally welded to the upper and lower flanges 22 of the steel beam 20 along the outer peripheral surface of the reinforced concrete column 10. The length of the angle member 32 is equal to or longer than the flange width of the steel beam 20.

【0011】アングル材32には、座屈を防止するため
に、複数のリブ34を垂直に補強するのがよい。また、
鉄筋コンクリート柱10の外周面、鉄骨梁20の上下フ
ランジ22、22間には、スチフナ24を設けて、接合
部30の力学的性状を向上させている。アングル材32
の代わりに、チャンネル材を用いることも可能である。
The angle member 32 preferably has a plurality of ribs 34 vertically reinforced to prevent buckling. Also,
A stiffener 24 is provided between the outer peripheral surface of the reinforced concrete column 10 and the upper and lower flanges 22 of the steel beam 20 to improve the mechanical properties of the joint 30. Angle material 32
Alternatively, a channel material can be used.

【0012】上記接合部30は、工場においてH形鋼を
十字形に溶接した後、アングル材32を上記所定位置に
溶接して製作する。この接合部30を現場に搬入し、柱
主筋12、フープ筋14および図示してない型枠を建て
込んだ後、当該接合部30を吊り降ろし、柱頭部にセッ
トした後、コンクリートを打設して、鉄筋コンクリート
柱10と接合部30を同時に完成させる。接合部30の
鉄骨梁20と、柱10、10間に横架される鉄骨梁(図
示せず。)とは、溶接またはボルトにて接合する。
The joint 30 is manufactured by welding an H-beam in a cross shape at a factory and then welding an angle member 32 to the predetermined position. After the joint 30 is carried into the site and the column main reinforcement 12, the hoop reinforcement 14, and the formwork (not shown) are built, the joint 30 is lowered and set on the column head, and then concrete is poured. Then, the reinforced concrete column 10 and the joint 30 are completed at the same time. The steel beam 20 of the joint 30 and the steel beam (not shown) that is bridged between the columns 10 and 10 are joined by welding or bolts.

【0013】上記接合構造において、鉄骨梁20の曲げ
モーメントにより生じる梁端部の引張り及び圧縮力は、
直接、鉄筋コンクリート柱10に伝達される。このと
き、パネルゾーンにおいて、鉄骨梁20のてこ反力に対
してアングル材32が効果的に抵抗するので、接合部コ
ンクリートの支圧破壊と、はらみ出しを防止する。な
お、上記実施例において、鉄筋コンクリート柱10はプ
レキャスト製としてもよい。
In the above joint structure, the tensile and compressive forces at the beam end caused by the bending moment of the steel beam 20 are:
It is transmitted directly to the reinforced concrete column 10. At this time, in the panel zone, the angle member 32 effectively resists the lever reaction force of the steel beam 20, so that the bearing concrete is prevented from being crushed and spilled out. In the above embodiment, the reinforced concrete columns 10 may be made of precast.

【0014】[0014]

【考案の効果】本考案は、鉄骨梁が鉄筋コンクリート柱
を貫通するタイプの接合部において、接合部コンクリー
トが支圧破壊やはらみ出しを惹起するようなことのな
い、優れた接合構造を提供することにより、鉄骨梁の応
力を確実に鉄筋コンクリート柱に伝達させることがで
き、接合部に所要の耐力を確保することができる。
[Effects of the Invention] The present invention provides an excellent joint structure in which a steel beam penetrates a reinforced concrete column without causing the bearing concrete to cause bearing failure or protrusion in a joint portion where a steel beam penetrates a reinforced concrete column. Thereby, the stress of the steel beam can be reliably transmitted to the reinforced concrete column, and the required strength can be secured at the joint.

【0015】また、本考案に係る接合構造は簡易な構成
を採用し、接合部の製作、運搬ならびに現場施工が容易
であるという顕著な効果を発揮するものである。
Further, the joining structure according to the present invention employs a simple structure, and has a remarkable effect that the production, transportation and on-site construction of the joining portion are easy.

【図面の簡単な説明】[Brief description of the drawings]

【図1】鉄筋コンクリート柱と鉄骨梁の接合部の縦断側
面図である。
FIG. 1 is a longitudinal side view of a joint between a reinforced concrete column and a steel beam.

【図2】図1のII−II線における切断平面図である。FIG. 2 is a sectional plan view taken along line II-II of FIG.

【図3】図1のIII −III 線における切断平面図であ
る。
FIG. 3 is a sectional plan view taken along line III-III in FIG. 1;

【符号の説明】[Explanation of symbols]

10 鉄筋コンクリート柱 20 鉄骨梁 22 フランジ 24 スチフナ 30 接合部 32 アングル 34 リブ DESCRIPTION OF SYMBOLS 10 Reinforced concrete column 20 Steel beam 22 Flange 24 Stiffener 30 Joint 32 Angle 34 Rib

Claims (1)

(57)【実用新案登録請求の範囲】(57) [Scope of request for utility model registration] 【請求項1】 鉄骨梁が鉄筋コンクリート柱を貫通する
鉄筋コンクリート柱と鉄骨梁の接合構造において、該鉄
筋コンクリート柱の側面に沿って水平に、前記鉄骨梁の
上下フランジにアングル材またはチャンネル材を固着し
てなることを特徴とする鉄筋コンクリート柱と鉄骨梁の
接合構造。
In a joint structure of a reinforced concrete column and a steel beam in which a steel beam penetrates a reinforced concrete column, an angle material or a channel material is fixed to upper and lower flanges of the steel beam horizontally along a side surface of the reinforced concrete column. A joint structure between reinforced concrete columns and steel beams.
JP5442992U 1992-07-13 1992-07-13 Joint structure between reinforced concrete columns and steel beams Expired - Fee Related JP2547977Y2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5442992U JP2547977Y2 (en) 1992-07-13 1992-07-13 Joint structure between reinforced concrete columns and steel beams

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5442992U JP2547977Y2 (en) 1992-07-13 1992-07-13 Joint structure between reinforced concrete columns and steel beams

Publications (2)

Publication Number Publication Date
JPH0610402U JPH0610402U (en) 1994-02-10
JP2547977Y2 true JP2547977Y2 (en) 1997-09-17

Family

ID=12970480

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5442992U Expired - Fee Related JP2547977Y2 (en) 1992-07-13 1992-07-13 Joint structure between reinforced concrete columns and steel beams

Country Status (1)

Country Link
JP (1) JP2547977Y2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6442314B2 (en) * 2015-02-06 2018-12-19 鹿島建設株式会社 Joint structure of reinforced concrete column and steel beam

Also Published As

Publication number Publication date
JPH0610402U (en) 1994-02-10

Similar Documents

Publication Publication Date Title
JP2547977Y2 (en) Joint structure between reinforced concrete columns and steel beams
JPH0723455Y2 (en) Steel pipe concrete pillar
JP2566701Y2 (en) Joint structure between reinforced concrete columns and steel beams
JP3327184B2 (en) Column-to-beam joints between steel pipe structure or filled steel pipe concrete structure column and SRC structure beam
JP2570974Y2 (en) Joint structure between reinforced concrete columns and steel beams
JP3804174B2 (en) Seismic retrofitting method for existing buildings with square frame structure
JP3043938B2 (en) Joint structure between reinforced concrete columns and steel beams
JP2000073448A (en) Connection method and structure for precast concrete beam and column
JPS6012003Y2 (en) architectural framework structure
JP2716510B2 (en) Column and beam joining method
JP2000291289A (en) Joining structure of earthquake resistant member
JPS6134404Y2 (en)
JP3520483B2 (en) Reinforcement structure of existing building
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JP2629503B2 (en) Joint structure of prestressed concrete beam and steel tube concrete column
JP2570977Y2 (en) Joint structure between reinforced concrete columns and steel beams
JP2749310B2 (en) Steel structure
JPH06316962A (en) Structure for joining column and beam
JPH0518981B2 (en)
JP3250760B2 (en) Joining method of precast concrete column with beam bracket and precast concrete shear wall with steel beam
JP3430326B2 (en) Column and beam joint structure
JPH02236328A (en) Construction method for super-highrice building
JP2570978Y2 (en) Joint structure between reinforced concrete columns and steel beams
JPH0762740A (en) Joint method for precast steel framed reinforced concrete construction pillar and beam
JPH0823148B2 (en) Drop-in steel column base

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19970401

LAPS Cancellation because of no payment of annual fees