JP2024038318A - Preventive maintenance method for steel bridges and circulating blasting equipment used for this method - Google Patents

Preventive maintenance method for steel bridges and circulating blasting equipment used for this method Download PDF

Info

Publication number
JP2024038318A
JP2024038318A JP2024002197A JP2024002197A JP2024038318A JP 2024038318 A JP2024038318 A JP 2024038318A JP 2024002197 A JP2024002197 A JP 2024002197A JP 2024002197 A JP2024002197 A JP 2024002197A JP 2024038318 A JP2024038318 A JP 2024038318A
Authority
JP
Japan
Prior art keywords
shot
salt
preventive maintenance
grit
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2024002197A
Other languages
Japanese (ja)
Inventor
博文 山田
翔平 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
YAMADAINFRATECHNOS CO.,LTD
Original Assignee
YAMADAINFRATECHNOS CO.,LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by YAMADAINFRATECHNOS CO.,LTD filed Critical YAMADAINFRATECHNOS CO.,LTD
Priority to JP2024002197A priority Critical patent/JP2024038318A/en
Publication of JP2024038318A publication Critical patent/JP2024038318A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Laser Beam Processing (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

【課題】鋼橋の表面に付着した塩分を適切に除去できる鋼橋の予防保全工法及びこれに用いられる循環式ブラスト装置を提供する。【解決手段】グリットとショットとを噴射可能な循環式ブラスト装置を用いた予防保全工法であって、鋼橋に対してグリットを用いてブラスト処理を行い、ブラスト処理済部分に対してレーザー光を照射して塩分を除去した後に疲労強度向上のためにショットを用いてショットピーニング処理を行い、その後、ショットピーニング処理済部分に対して最終仕上げ塗装を施すようにした。【選択図】図1The present invention provides a preventive maintenance method for a steel bridge that can appropriately remove salt adhering to the surface of a steel bridge, and a circulating blasting device used therein. [Solution] This is a preventive maintenance method using a circulating blasting device that can inject grit and shot, in which a steel bridge is blasted using grit, and a laser beam is applied to the blasted part. After removing salt through irradiation, shot peening was performed using shot to improve fatigue strength, and then a final finish was applied to the shot peened areas. [Selection diagram] Figure 1

Description

本発明は、鋼橋における表面を塗装する予防保全工法、及びこれに用いられる循環式ブラスト装置に関する。 The present invention relates to a preventive maintenance method for painting the surface of a steel bridge, and a circulating blasting device used therein.

従来から、新設するものや既設のものに関わらず鋼橋はサビ等の発生を防ぐために、あるいは特に既存の鋼橋においては経年劣化によって腐食が進行した塗装の更新のために、予防保全が施されている。このように予防保全は、サビ等を取り除いたり、古い塗膜を取り除いたりする必要があるため、近年ではブラスト処理(1種ケレン)によってサビや塗膜を除去し、その後、新規の塗装を施すことが行われている。 Traditionally, preventive maintenance has been carried out on steel bridges, whether newly built or existing ones, to prevent the occurrence of rust, or especially for existing steel bridges, to renew coatings that have become corroded due to aging. has been done. In this way, preventive maintenance requires the removal of rust and old paint films, so in recent years it has become more common to remove rust and paint films by blasting (class 1 keren), and then apply a new coat of paint. things are being done.

また、例えば特許文献1においては、寒冷地の鋼橋表面の塗料には、凍結防止や錆防止等のために人為的に使用された凍結防止剤等の処理剤に含まれる塩分が一般的に付着していることが示唆されている。また、沿岸地帯に建設された鋼橋にも自然に塩分が付着することはよく知られている。 Furthermore, for example, in Patent Document 1, paints on the surfaces of steel bridges in cold regions generally contain salt contained in treatment agents such as antifreeze agents artificially used to prevent freezing and rust. It is suggested that it is attached. It is also well known that salt naturally adheres to steel bridges built in coastal areas.

特開2016-203313号公報Japanese Patent Application Publication No. 2016-203313

しかしながら、上述のような環境下にある鋼橋においては、付着した塩分によって鋼橋表面に腐食の発生を誘引するおそれがあるため、この問題を適切に解決することが求められる。ここで、ブラスト処理やショットピーニング処理をして表面塗膜等を剥離させることで、鋼橋に付着した塩分を除去することは可能であるが、鋼橋の表面において複雑に入組んだ箇所や狭小箇所等においては、剥離処理ができずに依然として塩分が残留する可能性があった。 However, in steel bridges under the above-mentioned environment, there is a risk that the attached salt may induce corrosion on the surface of the steel bridge, so it is required to appropriately solve this problem. Although it is possible to remove the salt adhering to the steel bridge by removing the surface coating through blasting or shot peening, it is possible to remove the salt adhering to the steel bridge, but it is possible to remove the salt adhering to the surface of the steel bridge. In narrow areas, etc., there was a possibility that the removal process could not be performed and salt remained.

そこで本発明は、鋼橋に付着した処理剤に含まれる塩分を適切に除去することができる鋼橋の予防保全工法、及びこれに用いられる循環式ブラスト装置を提供することを目的とする。 SUMMARY OF THE INVENTION Therefore, an object of the present invention is to provide a preventive maintenance method for a steel bridge that can appropriately remove salt contained in a treatment agent adhering to a steel bridge, and a circulating blasting device used therein.

本発明は、塩分が付着した鋼橋の予防保全工法であって、鋼橋に対して素地調整するために研削材としてのグリットを用いてブラスト処理を行う工程Aと、前記素地調整の対象となる部分に対して疲労強度向上のためにショットを用いてショットピーニング処理を行う工程Bと、少なくとも前記工程Aの後、又は少なくとも前記工程Bの後に、前記素地調整の対象となる部分に残留した前記塩分を除去する工程Cと、少なくとも前記工程Cを行った後に、前記素地調整の対象となる部分に対して最終仕上げ塗装を施す工程Dと、を含むことを特徴とする鋼橋の予防保全工法である。 The present invention is a preventive maintenance method for steel bridges with salt deposits, and includes a step A in which blasting is performed using grit as an abrasive to condition the steel bridge; A step B in which shot peening is performed using a shot to improve the fatigue strength of the part to be treated, and at least after the step A, or at least after the step B, the remaining part in the part to be subjected to the substrate preparation is Preventive maintenance of a steel bridge, characterized in that it includes a step C of removing the salt, and a step D of applying a final finish coating to the part to be subjected to surface preparation after at least the step C. It is a construction method.

かかる構成にあっては、鋼橋(新設の鋼橋でもよいし既設の鋼橋でもよい。)に対して、例えばブラスト処理からショットピーニング処理に移行するに際し、ブラスト処理されて形成された素地面に対してそのままショットピーニング処理を行うことができるため、別々に各工事を行う必要がなく、工期を効果的に短縮でき、コストも削減できる。さらに詳述すると、一般的に、ブラスト処理においては足場を組んだり、粉塵が外部へ漏出することを防止するために防塵シートを張設したりするが、本発明にあってはこのような周辺設備を撤去することなく連続してショットピーニング処理を行うことができるため、作業工程に無駄がない。なお、本発明は、工程Aの後に工程Bを行っても良いし、工程Bの後に工程Aを行ってもよい。 In such a configuration, when a steel bridge (a newly constructed steel bridge or an existing steel bridge may be used) is transferred from blasting treatment to shot peening treatment, for example, the base surface formed by blasting is Since the shot peening treatment can be performed directly on the steel, there is no need to perform each construction separately, which can effectively shorten the construction period and reduce costs. To explain in more detail, generally during blasting, scaffolding is erected and dustproof sheets are stretched to prevent dust from leaking outside, but in the present invention, such surroundings are Shot peening can be performed continuously without removing equipment, so there is no waste in the work process. Note that in the present invention, step B may be performed after step A, or step A may be performed after step B.

さらに、本発明は、前記素地調整の対象となる部分に付着した塩分を除去する工程Cを実行することを大きな特徴としている。かかる構成を採用することにより、例えば寒冷地において鋼橋表面に付着した凍結防止剤等の処理剤に含まれる塩分や、沿岸地帯において自然に付着した塩分を適切に除去することができる。 Furthermore, a major feature of the present invention is that a step C of removing salt adhering to the portion to be subjected to surface preparation is performed. By employing such a configuration, for example, salt contained in a treatment agent such as an antifreeze agent adhering to the surface of a steel bridge in a cold region, or salt naturally adhering in a coastal zone can be appropriately removed.

ここで、前記工程Cは、前記素地調整の対象となる部分に対して水蒸気を噴霧して前記塩分を除去することを含む構成が提案される。また、より望ましくは、前記工程Cは、前記素地調整の対象となる部分に対してレーザー光を照射して前記塩分を除去することを含む構成が提案される。 Here, a configuration is proposed in which the step C includes spraying water vapor onto the portion to be subjected to the surface preparation to remove the salt. More desirably, a configuration is proposed in which the step C includes irradiating the portion to be subjected to the surface preparation with a laser beam to remove the salt.

かかる構成にあっては、高温の水蒸気(スチーム)を噴霧することによって素地表面を適切に洗浄して残留物を除去することができる。なお、素地表面の洗浄を行う方法は他にも多数存在するが、噴霧される水蒸気すなわち水は、少量であり、単に水をかけて洗浄するよりも作業環境を悪化させずに済む利点がある。また、レーザー光を照射することで鋼橋表面に残留する塩分を溶融等して除去する構成は、乾式の手法であるため、鋼橋表面に錆の発生を招くおそれを飛躍的に低減できる利点がある。また、レーザー光を照射することにより、ピーニング効果も得られる。なお、工程Cを行った際には粉塵が発生する場合があるが、本発明においては、上述のように、ブラスト処理を行う工程Aと、ショットピーニング処理を行う工程Bとを共に含んでおり、共通の防塵シートで囲まれた同一環境下で行うことができるため、粉塵が外部に漏洩することを適切に防止することができる。なお、本発明における工程Cは、鋼橋に設定された全ての素地表面に対して行われるものではなく、工程A又は工程Bで塩分を適切に除去できない局所的な部分に対して工程Cを実行する構成となる。 With such a configuration, by spraying high temperature steam, the surface of the base material can be appropriately cleaned and residues can be removed. Although there are many other methods for cleaning the substrate surface, the amount of steam or water that is sprayed is small and has the advantage of not deteriorating the working environment more than simply spraying water on the surface. . In addition, the structure in which salt remaining on the steel bridge surface is melted and removed by laser beam irradiation is a dry method, which has the advantage of dramatically reducing the risk of rust forming on the steel bridge surface. There is. Moreover, a peening effect can also be obtained by irradiating with laser light. Although dust may be generated when performing step C, the present invention includes both step A, which performs blasting, and step B, which performs shot peening. This can be done in the same environment surrounded by a common dust-proof sheet, so it is possible to appropriately prevent dust from leaking to the outside. Note that step C in the present invention is not performed on all the base surfaces of the steel bridge, but is performed on localized areas where salt cannot be properly removed in step A or step B. This is the configuration to execute.

なお、ブラスト処理、グリット、及びショットは、JIS Z 03120:2004「素地調整用ブラスト処理方法通則」において、それぞれ定義されている。具体的には、ブラスト処理とは「処理する鋼材表面に大きな運動エネルギーをもつ研削材を衝突させ、鋼材表面を細かく切削及び打撃することによって、鋼材表面の酸化物又は付着物を除去して鋼材表面を清浄化及び粗面化すること。」である。グリットとは「使用前の状態で、りょう角(稜角)をもつ角張った形状であり、丸い部分がその粒子の1/2未満の粒子。」である。ショットとは「使用前の状態で、りょう角(稜角)、破砕面又は他の鋭い表面欠陥がなく、長径が短径の2倍以内の球形状の粒子。」である。また、ブラスト処理において「研削材」は上記した「研掃材」と同義である。また、JIS B 2711:2013「ばねのショットピーニング」において、ショットピーニングとは「ばねの表面層に球形に近い硬質粒子を高速度で打ち当てることによって、疲労強度及び耐応力腐食割れ性の向上を図る冷間加工法。表面に圧縮残留応力を与え、その表面を加工硬化させる。」ことである。 Note that blasting, grit, and shot are each defined in JIS Z 03120:2004 "General Rules for Blast Treatment Methods for Preparing Surfaces." Specifically, blasting is ``impacting an abrasive material with large kinetic energy on the surface of the steel material to be treated, cutting and hitting the surface of the steel material finely, thereby removing oxides or deposits on the surface of the steel material, and polishing the steel material. "Cleaning and roughening the surface." Grit is a particle that, before use, has an angular shape with ridge angles, and the rounded portion is less than half of the particle size. Shot is "a spherical particle with a major axis within twice the minor axis, without any angles, fractured surfaces, or other sharp surface defects before use." Further, in the blasting process, the "abrasive material" has the same meaning as the above-mentioned "abrasive material". Furthermore, in JIS B 2711:2013 "Shot peening of springs", shot peening is defined as "improving fatigue strength and stress corrosion cracking resistance by bombarding the surface layer of a spring with near-spherical hard particles at high speed. A cold working method that applies compressive residual stress to the surface and work hardens the surface.

ただし、ばね以外の金属材料に対して行うショットピーニングという表面処理方法は一般的であり、本発明における鋼橋に対するショットピーニングも同様の内容である。すなわち、本発明においてブラスト処理を行うために用いられる研削材にはグリットが対応すると共に、ショットピーニング処理を行うために用いられる硬質粒子にはショットが対応する。なお、グリットとして、いわゆるスチールカットワイヤーが採用されてもよい。また、ショットとしていわゆるラウンドカットワイヤーが採用されてもよい。 However, the surface treatment method of shot peening performed on metal materials other than springs is common, and the shot peening applied to steel bridges in the present invention has the same content. That is, in the present invention, grit corresponds to the abrasive material used for blasting, and shot corresponds to the hard particles used for shot peening. Note that a so-called steel cut wire may be employed as the grit. Moreover, a so-called round cut wire may be employed as the shot.

なお、ステンレス鋼製のグリットの形態等については、上述したようにJIS Z 0310:2004の規定に準ずる。ステンレス鋼としては、マルテンサイト系ステンレス鋼、フェライト系ステンレス鋼、オーステナイト系ステンレス鋼、オーステナイト・フェライト二相ステンレス鋼、析出硬化ステンレス鋼のいずれも適用可能である。また、ショットがステンレス鋼製である場合には、グリットと同様にJIS Z 0310:2004の規定に準ずるものとする。 Note that the shape of the stainless steel grit, etc. conforms to the regulations of JIS Z 0310:2004, as described above. As the stainless steel, any of martensitic stainless steel, ferritic stainless steel, austenitic stainless steel, austenitic/ferritic duplex stainless steel, and precipitation hardening stainless steel can be used. In addition, when the shot is made of stainless steel, it shall comply with the provisions of JIS Z 0310:2004 similarly to the grit.

かかる材料のグリット及び/又はショットを用いる構成にあっては、使用済みのものを洗浄して乾燥することによって、付着した塩分を除去することができる。したがって、本構成によれば、寒冷地や沿岸地帯で使用する場合にあっても再度使用することができる。 In configurations using grit and/or shot of such materials, the salt deposits can be removed by washing and drying the used material. Therefore, according to this configuration, it can be used again even when used in cold regions or coastal areas.

また、本発明は、塩分が付着した鋼橋の予防保全工法に用いられる循環式ブラスト装置であって、鋼橋に対して素地調整するブラスト処理を行う工程に使用される研削材としてのグリット、及び前記素地調整の対象となる部分に対して疲労強度向上のために行うショットピーニング処理に使用されるショットを噴射する噴射手段と、前記噴射手段に電力を供給する電力供給手段と、備え、さらに、前記素地調整の対象となる部分に対してレーザー光を照射して前記塩分を除去するレーザー光照射手段を備えており、前記電力供給手段は、前記レーザー光照射手段に電気的に接続されて、レーザー光を照射するための電力を供給することを特徴とする循環式ブラスト装置である。 The present invention also provides a circulating blasting device used in a preventive maintenance method for steel bridges with salt deposits, which includes grit as an abrasive used in the process of blasting to condition the steel bridge. and an injection means for injecting shot used in shot peening treatment performed to improve fatigue strength on the part to be subjected to substrate conditioning, and a power supply means for supplying electric power to the injection means, and further comprising: , comprising a laser light irradiation means for removing the salt by irradiating the portion to be subjected to surface preparation with a laser light, and the power supply means is electrically connected to the laser light irradiation means. , a circulating blasting device characterized by supplying power for irradiating laser light.

かかる構成にあっては、例えば1種ケレンに必要な噴射手段に用いる電力供給手段を、レーザー光を照射するレーザー光照射手段に電力を供給する電力供給手段として共用することが可能となり、装置全体の簡素化を図ることが可能となる。 In such a configuration, for example, the power supply means used for the injection means necessary for type 1 cleaning can be shared as the power supply means for supplying power to the laser light irradiation means for irradiating laser light, and the entire device This makes it possible to simplify the process.

本発明の鋼橋の予防保全工法は、腐食の発生を飛躍的に抑制できる優れた効果がある。 The preventive maintenance method for steel bridges of the present invention has an excellent effect of dramatically suppressing the occurrence of corrosion.

また、本発明の循環式ブラスト装置は、装置全体の簡素化を図ることができる優れた効果がある。 Further, the circulation blasting device of the present invention has an excellent effect of simplifying the entire device.

鋼橋の予防保全の手順を示すフロー図である。It is a flow diagram showing the procedure of preventive maintenance of a steel bridge. 循環式ブラスト装置を説明する概要説明図である。It is a schematic explanatory diagram explaining a circulating blasting device.

以下、本発明にかかる鋼橋の予防保全(特に再塗装)の工法、及びこれに用いられる循環式ブラスト装置を具体化した実施例を詳細に説明する。なお、本発明は、下記に示す実施例に限定されることはなく、適宜設計変更が可能である。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments embodying the method of preventive maintenance (particularly repainting) of steel bridges according to the present invention and the circulating blasting device used therein will be described in detail. Note that the present invention is not limited to the embodiments shown below, and design changes can be made as appropriate.

図1に示すように、既存の鋼橋(鋼構造物)の再塗装手順としては、まず予防保全の対象となる鋼橋に足場を仮設する。これと共に、外部に粉塵が漏出しないように防塵シートを張設し、非塗装部分の養生を行い、ブラスト処理及びショットピーニング処理を行うための装置を設置する事前準備(S101)を行う。 As shown in Figure 1, the procedure for repainting an existing steel bridge (steel structure) is to first temporarily install scaffolding on the steel bridge that is subject to preventive maintenance. At the same time, preliminary preparations are made (S101) such as installing a dustproof sheet to prevent dust from leaking to the outside, curing unpainted areas, and installing equipment for blasting and shot peening.

その後、前記鋼橋に塗布されている旧塗料の種類や厚さ、あるいは該鋼橋の状況等を調査(S102)する。そして、調査結果に基づき、使用するグリット及びショットの種類や噴射速度等を決定する。ここで、選定するグリット(非球形)及びショット(球形)は、共にJIS Z 0310:2004に規定されているが、特に耐食性に優れ、かつ洗浄が可能なステンレス鋼製が好ましい。 Thereafter, the type and thickness of the old paint applied to the steel bridge, the condition of the steel bridge, etc. are investigated (S102). Then, based on the survey results, the type of grit and shot to be used, the injection speed, etc. are determined. The selected grit (non-spherical) and shot (spherical) are both specified in JIS Z 0310:2004, and stainless steel is particularly preferred as it has excellent corrosion resistance and is washable.

そして前記S102において決定したグリットを用いて、まずブラスト処理を行う(S103)。具体的には、前記鋼橋における剥離対象の塗膜等の剥離と素地調整対象の部分の素地調整を行う。かかるブラスト処理により、本発明における工程Aが構成される。なお、該ブラスト処理によって剥離した塗膜やサビ等、及び使用済みグリットが粉塵として発生するが、前記S101において防塵シートを張設しているため、外部に粉塵が漏出することはなく、後述のように該粉塵は順次回収処理される。ところで、かかる工程Aを行うことにより、付着した塩分の大部分は、鋼橋表面から除去されることとなる。 Then, using the grit determined in S102, a blasting process is first performed (S103). Specifically, the coating film and the like to be peeled off in the steel bridge is removed and the surface condition of the portion to be surface conditioned is performed. Such blasting constitutes step A in the present invention. In addition, the peeled paint film, rust, etc. and used grit are generated as dust by the blasting process, but since a dustproof sheet is installed in S101, the dust does not leak outside, and as described below. The dust is sequentially collected and processed. By the way, by performing this step A, most of the attached salt will be removed from the surface of the steel bridge.

次いで、ブラスト処理を終えた鋼橋表面に対し、付着した塩分をさらに精緻に除去するべく、別途、塩分除去工程を実行する(S104)。具体的には、前記工程Aで除去しきれない箇所(複雑に入り組んだ箇所や狭小箇所等)に、レーザー光を局所的に照射する。これにより、局所部位に対して塩分を除去することが可能となる。なお、この塩分除去工程を行う際には、工程Aで使用した仮設の足場や防塵シートは撤去することなく継続して使用することができる。 Next, a separate salt removal process is performed on the blasted steel bridge surface in order to more precisely remove the adhering salt (S104). Specifically, a laser beam is locally irradiated to areas that cannot be completely removed in the step A (complicated areas, narrow areas, etc.). This makes it possible to remove salt from localized areas. In addition, when performing this salt removal process, the temporary scaffolding and dustproof sheet used in process A can be used continuously without being removed.

上述の構成にあって、レーザー光を照射することによって、素地表面に付着した塩分は溶融等することで素地表面から除去される。なお、S104において発生する粉塵等は少ないものの、前記S101において防塵シートを張設しているため、S103と同様に外部に粉塵が漏出してしまうことがない。また、レーザー光の照射時間は極めて短時間で済むため、後述する最終仕上げ塗装に至るまでの時間が長くなりすぎてサビが発生してしまう、ことを効果的に防止することができる。なお、本実施例の塩分除去工程により、本発明に係る工程Cが構成される。 In the above configuration, by irradiating the laser beam, salt adhering to the surface of the substrate is melted and removed from the surface of the substrate. It should be noted that although the amount of dust generated in S104 is small, since a dustproof sheet is provided in S101, the dust does not leak to the outside as in S103. In addition, since the laser beam irradiation time is extremely short, it is possible to effectively prevent rust from occurring due to an excessively long period of time until the final finishing coating, which will be described later, is applied. Note that the salt removal step of this example constitutes step C according to the present invention.

続いて、グリットを噴射したブラスト装置に対して、グリットに代えて前記S102によって決定したショットを装填して該ショットを噴射可能とする。かかる工程により、ショット入れ替え工程が構成される。ここで、仮設した足場や防塵シートは撤去することなく継続して使用する。 Subsequently, the shot determined in step S102 is loaded into the blasting device that has sprayed the grit, so that the shot can be sprayed. This process constitutes a shot replacement process. At this point, the temporary scaffolding and dustproof sheets will continue to be used without being removed.

そして、前記ブラスト処理によって形成された素地面からなるブラスト処理済部分(すなわち素地調整部分)に対して、前記ショットに入れ替えたブラスト装置を用いてショットピーニング処理を行う(S105)。かかる処理により、素地面の疲労強度及び耐応力腐食割れ性が向上する工程Bが構成される。ところで、該ショットピーニング処理は前記ブラスト処理を行った全ての素地面に対して行ってもよいし、溶接箇所周辺や強度に不安のある箇所等に対して適宜部分的に行ってもよい。 Then, shot peening treatment is performed on the blasted portion (namely, substrate adjustment portion) of the base surface formed by the blasting process using the blasting device replaced with the shot (S105). Such treatment constitutes step B in which the fatigue strength and stress corrosion cracking resistance of the base surface are improved. Incidentally, the shot peening treatment may be performed on all the base surfaces that have been subjected to the above-mentioned blasting treatment, or it may be performed on a portion of the base surface that has been subjected to the above-mentioned blasting treatment, as appropriate, such as around welded areas or areas where the strength is uncertain.

その後、前記ブラスト処理、塩分除去工程、及びショットピーニング処理を行った素地面の確認を行う(S106)。かかる確認は目視確認のみならず、例えばISO8501ブラスト写真帳による比較、あるいは表面粗さ測定器による粗さ確認等も含まれる。これによって未剥離の塗膜が残っていないか、あるいは素地面の粗さが規格内であるか、等の確認がなされ、不十分な箇所に対して的確な処理がなされることとなる。また、鋼橋表面に塩分が残留していないかも確認される。残留塩分の確認方法としては、電導度法、ガーゼ拭き取り法、あるいはブレッセル法等が提案される。 Thereafter, the base surface that has been subjected to the blasting process, the salt removal process, and the shot peening process is confirmed (S106). Such confirmation includes not only visual confirmation but also, for example, comparison using an ISO8501 blast photo book or roughness confirmation using a surface roughness measuring device. This allows it to be confirmed whether there is any unpeeled paint remaining or whether the roughness of the base surface is within the specifications, and appropriate treatment can be carried out on any insufficient areas. It will also be confirmed that no salt remains on the surface of the steel bridge. The conductivity method, the gauze wiping method, the Bressel method, etc. are proposed as methods for checking residual salt.

こうして素地面の確認が済んだ部分に対して最終塗膜を形成するための最終仕上げ塗装を行う(S107)。かかる塗装工程により、本発明にかかる工程Dが構成される。なお、かかる塗装は、例えば防錆塗装として下塗り塗装、該防錆塗装を保護する中塗り塗装、及び最終仕上げ塗装となる上塗り塗装のように複数回にわたって層状に塗装されることが一般的である。 A final finish coating is applied to the part where the base surface has been confirmed in this way to form a final coating film (S107). This coating process constitutes process D according to the present invention. In addition, such coatings are generally applied in multiple layers, such as an undercoat as a rust-preventive coating, an intermediate coat to protect the rust-preventive coating, and a topcoat as a final finishing coat. .

前記塗装が済むと、その確認(S108)が行われる。かかる確認は塗装が乾燥した後の膜厚確認だけでなく、例えば塗装作業中にウェットネスゲージを用いてウェット膜厚の確認等も含まれる。また、このような確認は前記最終仕上げ塗装となる上塗り塗装後のみならず、前記下塗り塗装、及び中塗り塗装時にも行われる。 After the painting is completed, confirmation thereof is performed (S108). Such confirmation includes not only checking the film thickness after the coating has dried, but also, for example, checking the wet film thickness using a wetness gauge during the painting operation. Further, such confirmation is performed not only after the top coat, which is the final finishing coat, but also during the undercoat and intermediate coat.

前記確認によって塗装作業が完了すると、現場の片付けを行う(S109)。具体的には、足場や防塵シート等の回収、及びブラスト-ショットピーニング噴射装置の撤収を行って予防保全の完了となる。 When the painting work is completed according to the above-mentioned confirmation, the site is cleaned up (S109). Specifically, the preventive maintenance will be completed by collecting the scaffolding, dustproof sheets, etc., and removing the blast-shot peening injection equipment.

また、上記のS103からS105までの手順と共に、粉塵の回収工程を実行する(S110)。具体的には、前記ブラスト処理(S103)で発生した使用済みグリット、前記ショットピーニング処理(S105)で発生した使用済みショット、及び、各工程で生じた剥離物やサビ等を含む粉塵を回収していく。 In addition to the steps from S103 to S105 described above, a dust collection process is executed (S110). Specifically, the used grit generated in the blasting process (S103), the used shot generated in the shot peening process (S105), and the dust containing flakes and rust generated in each process are collected. To go.

なお、回収した使用済みグリット、及び使用済みショットは、使用時に鋼橋と衝突してもアルマンダイトガーネットや製鉄スラグのように破砕することがなく、再利用可能である。なお、グリット及びショットは、JIS Z 0310:2004に規定する鉄製(金属系)研削材であってもよく、中でも高炭素鋳鋼のものは600回程度再利用することができ、非常に経済的である。 In addition, the collected used grit and used shot do not shatter like almandite garnet or steelmaking slag even if they collide with a steel bridge during use, and can be reused. The grit and shot may be iron (metallic) abrasives specified in JIS Z 0310:2004, and among them, high carbon cast steel can be reused about 600 times and is very economical. be.

次に、循環式ブラスト装置1を一例として説明する。具体的に循環式ブラスト装置1は、グリットとショットとを共通の装置で噴射することが可能であり、しかも使用済みグリット、使用済みショット、及び剥離した塗膜等を回収してそれぞれ分別することができる。 Next, the circulation type blasting device 1 will be explained as an example. Specifically, the circulating blasting device 1 is capable of ejecting grit and shot with a common device, and is also capable of collecting and separating used grit, used shot, peeled paint film, etc. Can be done.

図2に示すように、前記循環式ブラスト装置1は、作業対象となる鋼橋Kの作業現場αに隣接して設置される装置本体部2を備えている。 As shown in FIG. 2, the circulating blasting apparatus 1 includes an apparatus main body part 2 installed adjacent to a work site α of a steel bridge K to be worked.

さらに該装置本体部2は、圧送ホース4を具備し、該圧送ホース4の先端に噴射器3が接続されている。該噴射器3からはグリットやショットが噴射される。また、前記装置本体部2は、吸引ホース5を具備し、該吸引ホース5の先端が作業現場αに配置されている。これにより、該吸引ホース5を介して、作業現場αで発生した使用済みグリット、使用済みショット、及び剥離した塗膜やサビ等を含む異物Dからなる粉塵Xを吸引することができる。なお、粉塵Xが外部に漏出しないように、図示しない防塵シートが作業現場αには張設され、送風機や集塵装置等も適宜設置される。 Further, the device main body 2 includes a pressure hose 4, and an injector 3 is connected to the tip of the pressure hose 4. The injector 3 injects grit or shot. Further, the device main body 2 includes a suction hose 5, and the tip of the suction hose 5 is disposed at the work site α. Thereby, the dust X consisting of used grit, used shot, and foreign matter D including peeled paint films, rust, etc. generated at the work site α can be sucked through the suction hose 5. In order to prevent the dust X from leaking outside, a dustproof sheet (not shown) is stretched over the work site α, and blowers, dust collectors, etc. are also installed as appropriate.

また、前記循環式ブラスト装置1の装置本体部2には、グリットホッパータンク10とショットホッパータンク20とが互いに隣接して配設されている。さらに詳述すると、該グリットホッパータンク10は、グリット及び使用済みグリット(以下、これらの混合物をグリットという)を貯留しておく機能を有している。また、前記ショットホッパータンク20は、ショット及び使用済みショット(以下、これらの混合物をショットという)を貯留しておく機能を有している。 Further, in the device main body 2 of the circulating blasting device 1, a grit hopper tank 10 and a shot hopper tank 20 are arranged adjacent to each other. More specifically, the grit hopper tank 10 has the function of storing grit and used grit (hereinafter, a mixture thereof will be referred to as grit). Further, the shot hopper tank 20 has a function of storing shots and used shots (hereinafter, a mixture thereof will be referred to as shots).

さらに、グリットホッパータンク10には、グリットを作業現場αまで圧送するためのグリット加圧タンク11が接続されている。また、同様に、ショットホッパータンク120には、ショットを作業現場αまで圧送するためのショット加圧タンク21が接続されている。 Furthermore, a grit pressurizing tank 11 is connected to the grit hopper tank 10 for transporting grit under pressure to the work site α. Similarly, a shot pressurizing tank 21 is connected to the shot hopper tank 120 for pressure-feeding shot to the work site α.

さらに、前記グリット加圧タンク11及び前記ショット加圧タンク21には、乾燥圧縮空気配管31を介して乾燥圧縮空気供給手段30が接続されている。かかる乾燥圧縮空気供給手段30は、乾燥した圧縮空気を供給するためのエアコンプレッサーとエアドライヤーとで構成されている。 Further, a dry compressed air supply means 30 is connected to the grit pressurized tank 11 and the shot pressurized tank 21 via a dry compressed air pipe 31. The dry compressed air supply means 30 is composed of an air compressor and an air dryer for supplying dry compressed air.

また、前記乾燥圧縮空気配管31には切換弁32が備えられており、乾燥圧縮空気を前記グリット加圧タンク11又はショット加圧タンク21に選択的に送給可能とされ、グリットに代えてショットを噴射可能に装填自在としている。 Further, the dry compressed air piping 31 is equipped with a switching valve 32, which allows dry compressed air to be selectively fed to the grit pressurizing tank 11 or the shot pressurizing tank 21, and shot instead of grit. It can be loaded and sprayed at will.

また、前記グリット加圧タンク11及び前記ショット加圧タンク21には、前記圧送ホース4が接続されている。そして、かかる構成により、前記乾燥圧縮空気供給手段30から供給された乾燥圧縮空気による空気圧よってグリット又はショットが該圧送ホース4を介して噴射器3から噴射され、作業対象となる鋼橋Kにブラスト処理、あるいはショットピーニング処理が実行可能となっている。 Further, the pressure feeding hose 4 is connected to the grit pressure tank 11 and the shot pressure tank 21. With this configuration, grit or shot is injected from the injector 3 via the pressure hose 4 by the air pressure of the dry compressed air supplied from the dry compressed air supply means 30, and is blasted onto the steel bridge K to be worked. treatment or shot peening treatment can be performed.

また、作業現場αには、レーザー光を照射するレーザー光照射装置6が配設されている。レーザー光照射装置6は、ハンディ型のレーザー光照射部を備えており、作業員が容易に取り扱うことができる形状・寸法とされている。 Further, a laser light irradiation device 6 that irradiates laser light is provided at the work site α. The laser light irradiation device 6 includes a handy laser light irradiation unit, and has a shape and size that can be easily handled by a worker.

ここで、循環式ブラスト装置1に使用される機器に電力を供給する電力供給手段10は、レーザー光照射装置6にも電気的に接続されており、同一の電力供給手段10を用いて、レーザー光照射装置6からレーザー光が発振させる。なお、張設された防塵シートにより、レーザー光が外部に漏出しないため、安全性にも優れている。 Here, the power supply means 10 that supplies power to the devices used in the circulating blasting device 1 is also electrically connected to the laser light irradiation device 6, and the same power supply means 10 is used to supply power to the equipment used in the circulating blasting device 1. Laser light is oscillated from the light irradiation device 6. Additionally, the dustproof sheet installed prevents laser light from leaking outside, making it extremely safe.

前記作業現場αに堆積した使用済みグリット、使用済みショット、及び剥離した塗膜等の異物を含む粉塵Xは、前記吸引ホース5の一端からまとめて吸引される。そして、該吸引ホース5によって吸引された粉塵Xは、グリットホッパータンク10とショットホッパータンク20との上方に配された分別室40内に到達する。 Dust X containing foreign matter such as used grit, used shot, and peeled paint film deposited at the work site α is sucked all together from one end of the suction hose 5. The dust X sucked by the suction hose 5 reaches the separation chamber 40 arranged above the grit hopper tank 10 and the shot hopper tank 20.

また、前記分別室40には、ダストホース51が取り付けられており、該ダストホース51には、剥離塗膜回収部としてのダスト回収部50が接続されている。さらに、該ダスト回収部50には、粉塵吸引手段としての空気吸引装置60が接続されている。したがって、該空気吸引装置60の空気吸引力によって、前記粉塵Xが吸引可能となっている。 Further, a dust hose 51 is attached to the separation chamber 40, and a dust collection section 50 as a peelable coating film collection section is connected to the dust hose 51. Furthermore, an air suction device 60 as dust suction means is connected to the dust collection section 50. Therefore, the dust X can be sucked by the air suction force of the air suction device 60.

ここで、図3に示すように、前記分別室40は、上流側に使用済みグリット回収部45が配設され、該使用済みグリット回収部45の上流側に使用済みショット回収部46が配設されている。そして、分別室40は、ダストホース51に接続されていると共に、前記ダスト回収部50を介して前記空気吸引装置60に接続されている。 Here, as shown in FIG. 3, in the separation chamber 40, a used grit recovery section 45 is disposed on the upstream side, and a used shot recovery section 46 is disposed on the upstream side of the used grit recovery section 45. has been done. The separation chamber 40 is connected to a dust hose 51 and is also connected to the air suction device 60 via the dust collection section 50.

そして、分別室40から排出された異物は、ダストホース51を介してダスト回収部50に導入されてダスト回収部50内で堆積され、所望のタイミングで廃棄物袋52に排出されて産業廃棄物として処理される。 The foreign matter discharged from the separation chamber 40 is introduced into the dust collection section 50 via the dust hose 51, deposited therein, and discharged into the waste bag 52 at a desired timing to be disposed of as industrial waste. will be processed as

上記した構成は、適宜設計変更可能である。例えば、本発明の予防保全工法は、鋼橋の再塗装時のみならず新規に架設する鋼橋に対して適用してもよい。例えば、新設する鋼橋に対して、未だ塗装されていない表面に対してサビ等を除去すべく工程Aを実行した後に工程Cを実行し、その後、工程A実行時に使用した足場等の設備を撤去することなく工程Bを実行し、そして工程Dを実行するものである。かかる構成にあっても、防食性能を向上させることができると共に、工期を大幅に短縮でき、これによりコストも大幅に縮小することができる。 The design of the above configuration can be changed as appropriate. For example, the preventive maintenance method of the present invention may be applied not only to repainting a steel bridge but also to a newly constructed steel bridge. For example, for a newly constructed steel bridge, process A is performed to remove rust, etc. from the unpainted surface, and then process C is performed, and then the scaffolding and other equipment used during process A is removed. Process B is executed without removal, and then process D is executed. Even with such a configuration, it is possible to improve the anti-corrosion performance, and also to significantly shorten the construction period, thereby significantly reducing costs.

また、上述の工程Cは、例えば高温高圧の水蒸気(スチーム)を素地表面に噴霧するものであってもよいし、それ以外の方法で素地表面に付着した塩分を除去するものであってもよい。いずれの方法であっても、防塵シートが張設された作業現場α内で工程Cが実行されるため、外部に粉塵が漏出することはなく、安全に作業を行うことができる。 In addition, the above-mentioned step C may involve, for example, spraying high-temperature, high-pressure water vapor (steam) onto the surface of the substrate, or may remove salt adhering to the surface of the substrate using other methods. . In either method, since the process C is executed within the work site α covered with a dustproof sheet, the work can be carried out safely without any dust leaking outside.

工程A、工程B、及び工程Cの順番は上記実施例の順番に限定されるものではなく、例えば工程A、工程B、工程Cの順序でもよいし、それ以外の順番でも構わない。ただし、まず工程Aを実行して旧塗膜等を剥離させた後に工程Cを実行して局所的な部位の塩分を除去し、その後に工程Bを実行して疲労強度の向上を図り、最後に仕上げ塗装を実行する順序が最も望ましい。 The order of process A, process B, and process C is not limited to the order of the above-mentioned example, and may be, for example, the order of process A, process B, and process C, or any other order. However, first, process A is performed to peel off the old paint film, etc., then process C is performed to remove salt from localized areas, and then process B is performed to improve fatigue strength. The most desirable order is to perform the finishing coat.

1 循環式ブラスト装置
K 鋼橋(鋼構造物)

1 Circulating blasting device K Steel bridge (steel structure)

Claims (4)

塩分が付着した鋼橋の予防保全工法であって、
鋼橋に対して素地調整するために研削材としてのグリットを用いてブラスト処理を行う工程Aと、
前記素地調整の対象となる部分に対して疲労強度向上のためにショットを用いてショットピーニング処理を行う工程Bと、
少なくとも前記工程Aの後、又は少なくとも前記工程Bの後に、前記素地調整の対象となる部分に残留した前記塩分を除去する工程Cと、
少なくとも前記工程Cを行った後に、前記素地調整の対象となる部分に対して最終仕上げ塗装を施す工程Dと、
を含むことを特徴とする鋼橋の予防保全工法。
A preventive maintenance method for steel bridges with salt deposits,
Step A of performing a blasting process using grit as an abrasive material to condition the steel bridge;
Step B of performing shot peening treatment using a shot to improve fatigue strength on the part to be subjected to the substrate adjustment;
At least after the step A or at least after the step B, a step C of removing the salt remaining in the area to be subjected to the surface preparation;
After performing at least the step C, a step D of applying a final finish coating to the part to be subjected to the surface preparation;
A preventive maintenance method for steel bridges, characterized by comprising:
前記工程Cは、前記素地調整の対象となる部分に対して水蒸気を噴霧して前記塩分を除去することを含む
請求項1に記載の鋼橋の予防保全工法。
2. The preventive maintenance method for a steel bridge according to claim 1, wherein the step C includes removing the salt by spraying water vapor onto the portion to be subjected to the surface preparation.
前記工程Cは、前記素地調整の対象となる部分に対してレーザー光を照射して前記塩分を除去することを含む
請求項1又は請求項2に記載の鋼橋の予防保全工法。
3. The preventive maintenance method for a steel bridge according to claim 1, wherein the step C includes removing the salt by irradiating the portion to be subjected to surface preparation with a laser beam.
塩分が付着した鋼橋の予防保全工法に用いられる循環式ブラスト装置であって、
鋼橋に対して素地調整するブラスト処理を行う工程に使用される研削材としてのグリット、及び前記素地調整の対象となる部分に対して疲労強度向上のために行うショットピーニング処理に使用されるショットを噴射する噴射手段と、
前記噴射手段に電力を供給する電力供給手段と、
備え、
さらに、前記素地調整の対象となる部分に対してレーザー光を照射して前記塩分を除去するレーザー光照射手段を備えており、
前記電力供給手段は、前記レーザー光照射手段に電気的に接続されて、レーザー光を照射するための電力を供給する
ことを特徴とする循環式ブラスト装置。
A circulation blasting device used for preventive maintenance of steel bridges with salt deposits,
Grit as an abrasive used in the process of blasting to condition steel bridges, and shot used in shot peening to improve fatigue strength of the areas subject to surface conditioning. an injection means for injecting;
power supply means for supplying power to the injection means;
Prepare,
Furthermore, it is provided with a laser beam irradiation means for irradiating the portion to be subjected to the surface preparation with a laser beam to remove the salt;
The circulating blasting device is characterized in that the power supply means is electrically connected to the laser light irradiation means and supplies power for irradiating the laser light.
JP2024002197A 2019-05-13 2024-01-10 Preventive maintenance method for steel bridges and circulating blasting equipment used for this method Pending JP2024038318A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2024002197A JP2024038318A (en) 2019-05-13 2024-01-10 Preventive maintenance method for steel bridges and circulating blasting equipment used for this method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2019090839A JP2020186556A (en) 2019-05-13 2019-05-13 Preventive maintenance method of steel bridge and circulating blasting machine used for the same
JP2024002197A JP2024038318A (en) 2019-05-13 2024-01-10 Preventive maintenance method for steel bridges and circulating blasting equipment used for this method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2019090839A Division JP2020186556A (en) 2019-05-13 2019-05-13 Preventive maintenance method of steel bridge and circulating blasting machine used for the same

Publications (1)

Publication Number Publication Date
JP2024038318A true JP2024038318A (en) 2024-03-19

Family

ID=73222745

Family Applications (2)

Application Number Title Priority Date Filing Date
JP2019090839A Pending JP2020186556A (en) 2019-05-13 2019-05-13 Preventive maintenance method of steel bridge and circulating blasting machine used for the same
JP2024002197A Pending JP2024038318A (en) 2019-05-13 2024-01-10 Preventive maintenance method for steel bridges and circulating blasting equipment used for this method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
JP2019090839A Pending JP2020186556A (en) 2019-05-13 2019-05-13 Preventive maintenance method of steel bridge and circulating blasting machine used for the same

Country Status (1)

Country Link
JP (2) JP2020186556A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022110165A (en) * 2021-01-16 2022-07-29 株式会社Nttドコモ Surface treatment method and structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6304901B2 (en) * 2016-02-21 2018-04-04 ヤマダインフラテクノス株式会社 Preventive maintenance method for steel structure, and circulating blasting device used therefor

Also Published As

Publication number Publication date
JP2020186556A (en) 2020-11-19

Similar Documents

Publication Publication Date Title
JP6444232B2 (en) Maintenance painting method for steel structure and circulating blasting device
JP2024038318A (en) Preventive maintenance method for steel bridges and circulating blasting equipment used for this method
CN105817832B (en) Pressure vessel field repair is with remanufacturing technique
JP7359411B2 (en) Preventive maintenance method for steel bridges
JP6304901B2 (en) Preventive maintenance method for steel structure, and circulating blasting device used therefor
EP2606161A1 (en) Process for conditioning the surface of hardened sheet-steel components which are protected against corrosion
CN100542751C (en) Improve the glass cloudburst treatment art of anti-stress corrosion performance of welding joint of stainless steel
KR101760643B1 (en) Method for surface treatment of steel material
JP6924480B2 (en) Steel bridge maintenance method
US20130139852A1 (en) Method and device for removing a layer from a surface of a body
KR100714909B1 (en) Painting apparatus and painting method
JP6501718B2 (en) Preventive maintenance method of existing steel bridge
JP2024010583A (en) Preventive maintenance method for steel bridge
CN111195863B (en) Method for compacting anti-corrosive paint for turbine engine components
JP2020128572A (en) Metallic structure surface-conditioning method
CN106498381A (en) A kind of method of surface finish of steel construction
JP6885577B2 (en) Steel bridge maintenance method
JP2024017508A (en) Maintenance method for steel bridge
JP6674814B2 (en) Preventive maintenance method for steel structures
JP6949314B2 (en) Steel structure maintenance method and steel structure maintenance treatment system
JP6474306B2 (en) Steel bridge blasting method
US11959148B2 (en) Preventive maintenance construction method for steel bridge
Fauchais et al. Surface Preparation
CN113696103B (en) Long-service-life steel rail treatment method
JP7007722B2 (en) Vehicles for maintenance methods of steel structures and covering sheet sets

Legal Events

Date Code Title Description
A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20240205

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20240205

A871 Explanation of circumstances concerning accelerated examination

Free format text: JAPANESE INTERMEDIATE CODE: A871

Effective date: 20240205

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20240419