JP2023136911A - Pile installation method - Google Patents

Pile installation method Download PDF

Info

Publication number
JP2023136911A
JP2023136911A JP2022042844A JP2022042844A JP2023136911A JP 2023136911 A JP2023136911 A JP 2023136911A JP 2022042844 A JP2022042844 A JP 2022042844A JP 2022042844 A JP2022042844 A JP 2022042844A JP 2023136911 A JP2023136911 A JP 2023136911A
Authority
JP
Japan
Prior art keywords
core material
pile
rotation mechanism
hole
core
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2022042844A
Other languages
Japanese (ja)
Inventor
啓知 井原
Hirotomo Ihara
孝 杉山
Takashi Sugiyama
浩二 恩田
Koji Onda
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KASUGA KISO KK
Kajima Corp
Original Assignee
KASUGA KISO KK
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KASUGA KISO KK, Kajima Corp filed Critical KASUGA KISO KK
Priority to JP2022042844A priority Critical patent/JP2023136911A/en
Publication of JP2023136911A publication Critical patent/JP2023136911A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

To provide a pile installation method reducing work load to construct an installation machine in a narrow side under a head space restriction.SOLUTION: A pile installation method comprises: a pile hole boring process forming a pile bore 15 by boring the ground as rotating an earth augur 11 with a rotation mechanism part 7 using a boring hole machine 1 provided with a leader 5 and the rotation mechanism part 7 lifting the leader 5; and a core member installation process installing core member units 21 in a bore hole 15 by inserting the core member units 21 attached on the rotation mechanism part 7 of the boring hole machine 1 by lifting motion of the rotation mechanism part 7 as extending the core member units without rotation in the pile hole 15.SELECTED DRAWING: Figure 4

Description

本発明は、杭打設方法に関するものである。 The present invention relates to a pile driving method.

従来、このような分野の技術として、下記特許文献1に記載の杭打設方法が知られている。この方法は、空頭制限がある場所において先に形成された掘削孔に杭の芯材が建込まれるものであり、空頭制限よりも短い分割芯材が順に連結されて掘削孔に吊り入れられる。この場合、最終的には分割芯材が複数連結されてなる芯材全体を吊る必要があり、これに対応する能力の大型のクレーンは空頭制限のある狭い現場に導入できない場合がある。従って、芯材全体を吊る能力をもつ専用の芯材建込装置が現場で構築される。 Conventionally, as a technique in this field, a pile driving method described in Patent Document 1 below is known. In this method, a pile core material is installed in a previously formed excavation hole in a place where there is a free head limit, and split core members shorter than the free head limit are successively connected and suspended into the drill hole. In this case, it is ultimately necessary to suspend the entire core material, which is made up of a plurality of connected core material segments, and a large crane with the capacity to handle this may not be able to be installed in a narrow site with limited free head capacity. Therefore, a dedicated core erecting device with the ability to suspend the entire core is constructed on site.

特開2021-021274号公報Japanese Patent Application Publication No. 2021-021274

しかしながら、上記のような芯材建込装置を用いる方法によれば、芯材建込装置を構築するための資機材を搬入し空頭制限下の狭い現場で組立てる、といった煩雑な作業が発生する。この課題に鑑み、本発明は、空頭制限下の狭い現場で建込装置を構築する手間を削減する杭打設方法を提供することを目的とする。 However, according to the method using the core material erecting device as described above, complicated work such as transporting the materials and equipment for constructing the core material erecting device and assembling the core material in a narrow site under air head restrictions occurs. In view of this problem, an object of the present invention is to provide a pile driving method that reduces the effort required to construct a construction device at a narrow site under free head restrictions.

本発明の杭打設方法は、リーダと、リーダ上を昇降する回転機構部と、を備える削孔機械を用いて回転機構部でアースオーガを回転させながら地盤を削孔し杭孔を形成する杭孔削孔工程と、芯材の一部をなし削孔機械の回転機構部に取付けられた芯材材料を継ぎ足しながら回転機構部の昇降動作により杭孔内に回転させずに挿入して芯材を杭孔内に建込む芯材建込み工程と、を備える。 The pile driving method of the present invention uses a drilling machine equipped with a leader and a rotating mechanism that moves up and down on the leader, and forms a pile hole by drilling a hole in the ground while rotating an earth auger in the rotating mechanism. During the pile hole drilling process, the core material, which forms part of the core material and is attached to the rotating mechanism of the drilling machine, is inserted into the pile hole without rotation by the lifting and lowering movement of the rotating mechanism while adding the core material, which forms part of the core and is attached to the rotating mechanism of the drilling machine. A core material erecting step of erecting the material into the pile hole.

上記の芯材がH鋼であってもよい。また、芯材建込み工程では、芯材材料の上端部が回転機構部に対して所定のアタッチメントを介して取付けられ、芯材材料の継ぎ足しは、芯材材料の端部に設けられたボルト穴を用いて添接板を介して芯材材料同士を接続して行なわれ、アタッチメントと芯材材料の上端部とが、当該上端部に位置するボルト穴を利用したボルト止めによって連結される、こととしてもよい。 The above core material may be H steel. In addition, in the core material installation process, the upper end of the core material is attached to the rotation mechanism section via a predetermined attachment, and the core material is added through the bolt hole provided at the end of the core material. This is done by connecting the core materials to each other via a splicing plate, and the attachment and the upper end of the core material are connected by bolting using the bolt hole located at the upper end. You can also use it as

また、芯材建込み工程では、芯材材料が杭孔で仮支持された状態で、芯材材料の上端部に新たな芯材材料が連結され継ぎ足される芯材連結工程と、芯材連結工程の後、芯材材料の上端部に回転機構部が取付けられ、芯材材料の仮支持が解除されて、回転機構部の昇降動作により芯材材料が杭孔内に挿入される芯材挿入工程と、芯材挿入工程で杭孔内に挿入された芯材材料が杭孔に仮支持される仮支持工程と、が繰返し実行される、こととしてもよい。 In addition, in the core material erection process, there is a core material connection process in which new core material is connected and added to the upper end of the core material while the core material is temporarily supported in the pile hole, and a core material connection process. After that, a rotation mechanism is attached to the upper end of the core material, the temporary support of the core material is released, and the core material is inserted into the pile hole by the vertical movement of the rotation mechanism, a core material insertion step. and a temporary support step in which the core material inserted into the pile hole in the core material insertion step is temporarily supported in the pile hole, may be repeatedly executed.

本発明によれば、空頭制限下の狭い現場で建込装置を構築する手間を削減する杭打設方法を提供することができる。 According to the present invention, it is possible to provide a pile driving method that reduces the effort required to construct a construction device at a narrow site under free head restrictions.

(a),(b)は、本実施形態の杭打設方法を順に示す施工現場の断面図である。(a) and (b) are sectional views of a construction site sequentially showing the pile driving method of this embodiment. H鋼同士の接続部を示す分解斜視図である。It is an exploded perspective view showing the connection part of H steel. (a),(b)は、図1に続いて、本実施形態の杭打設方法を順に示す施工現場の断面図である。(a) and (b) are sectional views of a construction site sequentially showing the pile driving method of this embodiment following FIG. 1. (a),(b)は、図3に続いて、本実施形態の杭打設方法を順に示す施工現場の断面図である。(a) and (b) are cross-sectional views of a construction site sequentially showing the pile driving method of this embodiment following FIG. 3. (a),(b)は、図4に続いて、本実施形態の杭打設方法を順に示す施工現場の断面図である。(a) and (b) are sectional views of a construction site sequentially showing the pile driving method of this embodiment following FIG. 4. 本実施形態の杭打設方法で使用されるアタッチメントと、このアタッチメントに取付けられるH鋼の上部と、を示す斜視図である。It is a perspective view showing the attachment used in the pile driving method of this embodiment, and the upper part of H steel attached to this attachment. (a)はアタッチメントの正面図であり、(b)はその側面図である。(a) is a front view of the attachment, and (b) is a side view thereof.

以下、図面を参照しながら本発明に係る杭打設方法の実施形態について詳細に説明する。同一又は同等の構成要素には図面で同一の符号を付して重複する説明を省略する。本実施形態の杭打設方法は、図1に示されるように、約4mの空頭制限がある現場101に、H鋼を芯材とする約17mの杭をプレボーリング工法によって打設するものである。この杭打設方法は、以下に説明する杭孔削孔工程と、芯材建込み工程と、を備えている。 DESCRIPTION OF EMBODIMENTS Hereinafter, embodiments of a pile driving method according to the present invention will be described in detail with reference to the drawings. Identical or equivalent components are denoted by the same reference numerals in the drawings, and redundant explanation will be omitted. As shown in FIG. 1, the pile driving method of this embodiment is to drive approximately 17 m long piles with H steel core material using the pre-boring method at a site 101 where there is a free head limit of approximately 4 m. be. This pile driving method includes a pile hole drilling process and a core material installation process, which will be described below.

〔杭孔削孔工程〕
図1(a)に示されるように、現場101には、自走式の削孔機械1と自走式の小型のバックホウ3とが導入される。削孔機械1は走行装置2とリーダ5と回転機構部7とを備えている。走行装置2は例えば履帯等を有し、削孔機械1は走行装置2によって自走可能である。リーダ5は削孔機械1の車両前部で鉛直方向に延びており、回転機構部7はリーダ5に取付けられるとともにリーダ5にガイドされて鉛直に昇降する。回転機構部7の下端部には鉛直軸周りに回転する回転軸部9が設けられており、回転軸部9にはアースオーガ11が取付けられる。回転機構部7は、例えば動力源や減速機等を内蔵し、回転軸部9を回転させて当該回転軸部9に取付けられたアースオーガ11を鉛直軸周りに回転させる。また、削孔機械1からは回転軸部9を通じてアースオーガ11の下端にモルタルが供給される。このような削孔機械1としては、例えば、プレボーリング工法を行うための公知の杭打機が用いられればよい。
[Pile hole drilling process]
As shown in FIG. 1(a), a self-propelled drilling machine 1 and a small self-propelled backhoe 3 are introduced to a site 101. The drilling machine 1 includes a traveling device 2, a leader 5, and a rotating mechanism section 7. The traveling device 2 has, for example, a crawler track, and the drilling machine 1 can be self-propelled by the traveling device 2. The leader 5 extends vertically at the front of the vehicle of the drilling machine 1, and the rotation mechanism 7 is attached to the leader 5 and is guided by the leader 5 to vertically move up and down. A rotating shaft section 9 that rotates around a vertical axis is provided at the lower end of the rotating mechanism section 7, and an earth auger 11 is attached to the rotating shaft section 9. The rotation mechanism section 7 includes, for example, a power source, a speed reducer, etc., and rotates the rotation shaft section 9 to rotate the earth auger 11 attached to the rotation shaft section 9 around a vertical axis. Further, mortar is supplied from the drilling machine 1 to the lower end of the earth auger 11 through the rotating shaft portion 9. As such a drilling machine 1, for example, a known pile driver for performing a pre-boring method may be used.

杭孔削孔工程では、地表面よりもやや低い位置に長さ約1.5mの口元管13が埋込まれる。削孔機械1に取付けられたアースオーガ11が先端からモルタルを噴出しながら、回転機構部7によって鉛直軸周りに回転されるとともに口元管13を通して下方に押込まれる。これにより、地盤が掘削され杭孔15が鉛直下方に延びていく。ここでは、空頭制限のために長いアースオーガ11は使用できず、杭孔15の掘削が例えば1.5mずつ進行する毎に、例えば1.5mの長さのアースオーガ11が継ぎ足される。このとき、継ぎ足される1.5mのアースオーガ11は、バックホウ3のアームを利用して回転軸部9の取付け位置に移動される。このようなアースオーガ11の継ぎ足し及び掘削を繰り返すことで、約17mの深さの杭孔15が形成される。杭孔15の直径は、例えば約80cmである。アースオーガ11が抜去され完成した杭孔15内にはモルタルが充填された状態であるが、各図面においてはこのモルタルの図示を省略する。 In the pile hole drilling process, a mouth pipe 13 with a length of about 1.5 m is buried at a position slightly lower than the ground surface. An earth auger 11 attached to a drilling machine 1 is rotated around a vertical axis by a rotation mechanism 7 and pushed downward through a mouth pipe 13 while spouting mortar from its tip. As a result, the ground is excavated and the pile hole 15 extends vertically downward. Here, a long earth auger 11 cannot be used due to the free head restriction, and each time the excavation of the pile hole 15 progresses by, for example, 1.5 m, an earth auger 11 with a length of, for example, 1.5 m is added. At this time, the 1.5 m long earth auger 11 to be added is moved to the attachment position of the rotating shaft portion 9 using the arm of the backhoe 3. By repeating such addition of the earth auger 11 and digging, a pile hole 15 with a depth of about 17 m is formed. The diameter of the pile hole 15 is, for example, about 80 cm. The pile hole 15 completed after the earth auger 11 has been removed is filled with mortar, but illustration of this mortar is omitted in each drawing.

〔芯材建込み工程〕
芯材建込み工程では、杭孔15内に充填されたモルタルにH鋼19を埋沈させるようにして、最終的には複数のH鋼19(芯材材料)が連結されてなる約17mの長さの芯材29(図5(b)参照)が杭孔15内に建込まれる。図1(b)に示されるように、芯材建込み工程では、最初に、自走式のクレーン17が現場101に導入される。このクレーン17によりH鋼19が吊られ杭孔15内に吊り入れられる。H鋼19の長さは、例えば1.5~2mであり、H鋼19の幅は例えば450mmx450mmである。このH鋼19が長手方向に連結され継ぎ足されながら杭孔15内に挿入されていく。互いに連結された複数のH鋼19からなるユニットを以下では「芯材ユニット21」という。新たなH鋼19を芯材ユニット21に連結する際には、芯材ユニット21(芯材材料)の上端部が仮支持具22(図3(a)参照)を介して口元管13上に仮支持される。仮支持具22は、例えば、口元管13の上端縁に架け渡されたアングル材(図示せず)と、当該アングル材を芯材ユニット21に固定するクランプ材(図示せず)と、で構成される。
[Core material installation process]
In the core material erection process, the H steel 19 is buried in the mortar filled in the pile hole 15, and finally the approximately 17 m long H steel 19 (core material) is connected. A length of core material 29 (see FIG. 5(b)) is built into the pile hole 15. As shown in FIG. 1(b), in the core material erection process, a self-propelled crane 17 is first introduced to the site 101. The H steel 19 is suspended by the crane 17 and placed into the pile hole 15. The length of the H steel 19 is, for example, 1.5 to 2 m, and the width of the H steel 19 is, for example, 450 mm x 450 mm. This H steel 19 is inserted into the pile hole 15 while being connected and spliced in the longitudinal direction. A unit consisting of a plurality of H steels 19 connected to each other will be referred to as a "core unit 21" below. When connecting a new H steel 19 to the core unit 21, the upper end of the core unit 21 (core material) is placed on the mouth tube 13 via the temporary support 22 (see FIG. 3(a)). Tentatively supported. The temporary support 22 includes, for example, an angle member (not shown) that spans the upper end edge of the mouth tube 13 and a clamp member (not shown) that fixes the angle member to the core unit 21. be done.

図1等においては、芯材ユニット21におけるH鋼19同士の連結部の詳細な描写が省略されているが、図2に示されるように、H鋼19の上端部及び下端部には連結用のボルト穴23が予め形成されている。そして、H鋼19同士は上記ボルト穴23を用いて添接板24を介して連結される。なお、図2では、H鋼19のウエブ同士を連結する添接板24のみが例として図示され、フランジ同士を連結する添接板の図示は省略されている。また、図2においては、連結に用いられるボルト及びナットの図示も省略されている。このような添接板によるH鋼同士の連結構造及び連結方法は公知であるので、更なる詳細な説明は省略する。 In FIG. 1 etc., the detailed depiction of the connecting portion between the H steels 19 in the core unit 21 is omitted, but as shown in FIG. 2, the upper and lower ends of the H steels 19 are A bolt hole 23 is formed in advance. Then, the H steels 19 are connected to each other via the splicing plate 24 using the bolt holes 23. In addition, in FIG. 2, only the splicing plate 24 that connects the webs of the H steel 19 is illustrated as an example, and the illustration of the splicing plate that connects the flanges is omitted. Further, in FIG. 2, illustrations of bolts and nuts used for connection are also omitted. Since the connection structure and connection method between H steels using such splicing plates are well known, further detailed explanation will be omitted.

その後、芯材ユニット21の長さが例えば6~7mに達したところで、芯材ユニット21の上端が仮支持具22を用いて口元管13上に仮支持された上で、図3(a)に示されるように、削孔機械1が再び現場101に導入される。また、クレーン17はそのまま削孔機械1の近傍に配置される。これ以降は芯材ユニット21の重量がクレーン17の吊り能力を超えるので、クレーン17に代えて削孔機械1によって芯材建込みが継続される。すなわち、削孔機械1は、クレーン17に比較してより大重量の芯材ユニット21を支持する能力を持つ。ここでは削孔機械1の回転機構部7の回転軸部9には、アースオーガ11に代えてアタッチメント25が取付けられている。アタッチメント25は、芯材ユニット21の上端部を回転軸部9に接続するためのものであり、アタッチメント25にはボルト穴23(図2)を利用して芯材ユニット21の上端部がボルト止めされる。アタッチメント25の詳細な構造については後述する。 After that, when the length of the core unit 21 reaches, for example, 6 to 7 m, the upper end of the core unit 21 is temporarily supported on the mouth tube 13 using the temporary support 22, and then the upper end of the core unit 21 is temporarily supported on the mouth tube 13, and then As shown in FIG. 1, the drilling machine 1 is again introduced to the site 101. Further, the crane 17 is directly placed in the vicinity of the drilling machine 1. After this, since the weight of the core unit 21 exceeds the lifting capacity of the crane 17, the core material erection is continued by the drilling machine 1 instead of the crane 17. That is, the drilling machine 1 has the ability to support a heavier core unit 21 than the crane 17. Here, an attachment 25 is attached to the rotating shaft portion 9 of the rotating mechanism portion 7 of the drilling machine 1 instead of the earth auger 11. The attachment 25 is for connecting the upper end of the core unit 21 to the rotating shaft 9, and the upper end of the core unit 21 is bolted to the attachment 25 using the bolt hole 23 (FIG. 2). be done. The detailed structure of the attachment 25 will be described later.

その後、クレーン17から削孔機械1に引き継がれた後の芯材建込み工程では、次に説明する芯材連結工程と、芯材挿入工程と、仮支持工程と、が繰返し実行される。 Thereafter, in the core material erection process after being taken over from the crane 17 to the drilling machine 1, a core material connection process, a core material insertion process, and a temporary support process, which will be described next, are repeatedly executed.

(芯材連結工程)
図3(a)に示されるように、芯材連結工程は、仮支持具22によって杭孔15の上端の口元管13上に芯材ユニット21が仮支持された状態で実行される。このとき、芯材ユニット21の上端部は、口元管13の上端よりもやや高い位置にある。この状態において、クレーン17が新たなH鋼19を芯材ユニット21の上方の位置に吊って移動させる。そして、芯材ユニット21の上端部にH鋼19が連結され継ぎ足される。このときの芯材ユニット21の上端部とH鋼19の下端部との連結は、図2で説明したように、添接板24を介したボルト止めで実行される。これにより、図3(b)に示されるように、芯材ユニット21が新たなH鋼19の長さ分だけ上方に延長される。
(core material connection process)
As shown in FIG. 3A, the core material connection step is performed in a state where the core material unit 21 is temporarily supported on the mouth pipe 13 at the upper end of the pile hole 15 by the temporary support 22. At this time, the upper end of the core unit 21 is located at a slightly higher position than the upper end of the mouth tube 13. In this state, the crane 17 suspends and moves the new H steel 19 to a position above the core unit 21. Then, the H steel 19 is connected and added to the upper end of the core unit 21. At this time, the upper end of the core unit 21 and the lower end of the H steel 19 are connected by bolting via the joining plate 24, as described with reference to FIG. As a result, the core unit 21 is extended upward by the length of the new H steel 19, as shown in FIG. 3(b).

(芯材挿入工程)
芯材連結工程の後、芯材挿入工程では、芯材ユニット21の上端部に削孔機械1の回転機構部7が取付けられる。具体的には、図4(a)に示されるように、アタッチメント25が芯材ユニット21の上端部に嵌まり込むまで回転機構部7が下降されアタッチメント25と芯材ユニット21の上端部とがボルト止めで連結される。詳細は後述するが、ここでアタッチメント25と芯材ユニット21の上端部とは、ボルト穴23(図2)を利用したボルト止めによって連結される。その後、芯材ユニット21から仮支持具22が取り外されることで芯材ユニット21の仮支持が解除され、芯材ユニット21は回転機構部7に支持された状態となる。
(core material insertion process)
After the core material connection step, in the core material insertion step, the rotation mechanism section 7 of the drilling machine 1 is attached to the upper end of the core material unit 21. Specifically, as shown in FIG. 4(a), the rotation mechanism section 7 is lowered until the attachment 25 fits into the upper end of the core unit 21, and the attachment 25 and the upper end of the core unit 21 are brought together. Connected with bolts. Although details will be described later, the attachment 25 and the upper end of the core unit 21 are connected by bolting using bolt holes 23 (FIG. 2). Thereafter, by removing the temporary support 22 from the core unit 21, the temporary support of the core unit 21 is released, and the core unit 21 is in a state of being supported by the rotation mechanism section 7.

この状態から、図4(b)に示されるように、削孔機械1の回転機構部7の下降動作により杭孔15内に下向きに芯材ユニット21が挿入される。ここでは、回転機構部7の上下可動範囲のほぼ下限位置まで当該回転機構部7が下降し、芯材ユニット21の上端部は、口元管13の上端部よりもやや高い位置まで移動する。なおここでは、下降中の芯材ユニット21が杭孔15内で引っ掛かった場合には、回転機構部7の上昇動作により芯材ユニット21を一旦上昇させて引っ掛かり状態を解除するといった措置も可能である。 From this state, as shown in FIG. 4(b), the core unit 21 is inserted downward into the pile hole 15 by the downward movement of the rotation mechanism section 7 of the drilling machine 1. Here, the rotation mechanism 7 descends to approximately the lower limit position of the vertical movable range of the rotation mechanism 7, and the upper end of the core unit 21 moves to a position slightly higher than the upper end of the mouth tube 13. Note that here, if the core unit 21 that is being lowered is caught in the pile hole 15, it is also possible to take measures such as lifting the core unit 21 once by the lifting operation of the rotating mechanism section 7 to release the stuck state. be.

削孔機械1は、回転機構部7をリーダ5上で上下移動させる上下駆動機能と、回転機構部7によって回転軸部9を鉛直軸周りに回転させる回転駆動機能と、を備えているが、芯材挿入工程では回転駆動機能は使用されず、上下駆動機能のみが使用される。従ってここでは、芯材ユニット21は、鉛直軸周りに回転せずに下降し、杭孔15内に挿入される。また、上記の上下駆動機能では、回転機構部7を下向きに押す動作が可能であるので、削孔機械1は、芯材ユニット21に下向きの力を付与し、杭孔15内に向けて芯材ユニット21を下向きに押込む動作が可能である。 The drilling machine 1 has a vertical drive function that moves the rotation mechanism section 7 up and down on the leader 5, and a rotation drive function that causes the rotation mechanism section 7 to rotate the rotation shaft section 9 around a vertical axis. In the core material insertion process, the rotational drive function is not used, but only the vertical drive function. Therefore, here, the core unit 21 descends without rotating around the vertical axis and is inserted into the pile hole 15. In addition, in the above-mentioned vertical drive function, since it is possible to push the rotation mechanism section 7 downward, the drilling machine 1 applies a downward force to the core unit 21 and pushes the core toward the inside of the pile hole 15. It is possible to push the material unit 21 downward.

なお、ここでは、上下駆動機能と回転駆動機能とを合わせて使用し芯材ユニット21を回転させながら芯材ユニット21を杭孔15内に挿入することも考えられる。しかしながら、モルタルが充填された杭孔15内で芯材ユニット21を回転させると、モルタルの粘性抵抗力により芯材ユニット21が変形したり、回転軸部9やアタッチメント25が破損したりする虞がある。従って、本実施形態における芯材挿入工程では、芯材ユニット21を回転させずに杭孔15内に挿入する。なお、下降中の芯材ユニット21が杭孔15内で引っ掛かった場合に引っ掛かり状態を解除するためには、回転駆動機能を用いて芯材ユニット21を僅かに回転させてもよい。 Note that here, it is also possible to insert the core unit 21 into the pile hole 15 while rotating the core unit 21 by using both the vertical drive function and the rotation drive function. However, when the core unit 21 is rotated in the pile hole 15 filled with mortar, there is a risk that the core unit 21 may be deformed due to the viscous resistance of the mortar, or the rotating shaft portion 9 or the attachment 25 may be damaged. be. Therefore, in the core material insertion step in this embodiment, the core material unit 21 is inserted into the pile hole 15 without rotating. In addition, in order to release the stuck state when the core material unit 21 which is descending is caught in the pile hole 15, the core material unit 21 may be slightly rotated using a rotation drive function.

(仮支持工程)
芯材挿入工程の後、仮支持工程では、芯材ユニット21が、杭孔15の上端である口元管13上に仮支持される。具体的には、芯材挿入工程で下降した芯材ユニット21の上端部に仮支持具22が取付けられる。前述したように、仮支持具22は、例えば、口元管13の上端縁に架け渡されるアングル材(図示せず)と、当該アングル材を芯材ユニット21に固定するクランプ材(図示せず)と、で構成される。そして、この仮支持具22が口元管13の上端縁に掛止されることで、芯材ユニット21が口元管13に支持された状態となる。その後、アタッチメント25と芯材ユニット21の上端部とのボルト止めが解除され、再び図3(a)に示されるように、回転機構部7の上昇動作により当該回転機構部7は芯材ユニット21から離れ、上下可動範囲のほぼ上限位置まで上昇する。この仮支持工程の後、前述の芯材連結工程が再び実行される。
(Temporary support process)
After the core material insertion step, in a temporary support step, the core material unit 21 is temporarily supported on the mouth pipe 13 which is the upper end of the pile hole 15. Specifically, the temporary support 22 is attached to the upper end of the core unit 21 that has been lowered in the core insertion process. As described above, the temporary support 22 includes, for example, an angle member (not shown) that spans the upper edge of the mouth tube 13 and a clamp member (not shown) that fixes the angle member to the core unit 21. It consists of and. Then, the temporary support 22 is hooked to the upper edge of the mouth tube 13, so that the core unit 21 is supported by the mouth tube 13. Thereafter, the bolting between the attachment 25 and the upper end of the core unit 21 is released, and as shown in FIG. , and rises to almost the upper limit of the vertical movable range. After this temporary support step, the above-mentioned core material connection step is performed again.

上述のような芯材連結工程と、芯材挿入工程と、仮支持工程と、が繰返し実行されることで、H鋼19を継ぎ足しながら回転機構部7の昇降動作により杭孔15内に回転させずに挿入して芯材ユニット21を杭孔15内に建込み、最終的な芯材29の建込みが完了する。その後、杭孔15内のモルタルが硬化することで、芯材29(図5(b)参照)を含む杭が完成する。 By repeatedly performing the core material connection process, core material insertion process, and temporary support process as described above, the H steel 19 is rotated into the pile hole 15 by the vertical movement of the rotation mechanism part 7 while adding the H steel 19. Then, the core unit 21 is inserted into the pile hole 15 and the final installation of the core unit 29 is completed. Thereafter, the mortar in the pile hole 15 hardens, thereby completing the pile including the core material 29 (see FIG. 5(b)).

なお、前述の芯材挿入工程では、回転機構部7が上下可動範囲のほぼ下限位置まで下降し、芯材ユニット21の上端部は口元管13の上端部よりもやや高い位置に移動される。そして、回転機構部7の上下可動範囲の制限により、芯材ユニット21を更に下方に移動することはできない。従って、完成後の芯材ユニット21の上端を口元管13の上端よりも低い位置にするためには、最後の芯材挿入工程において前述の芯材挿入工程とは異なる次のような工程が必要である。 In addition, in the above-mentioned core material insertion process, the rotation mechanism part 7 descends to almost the lower limit position of the vertical movable range, and the upper end part of the core material unit 21 is moved to a position slightly higher than the upper end part of the mouth tube 13. Further, due to the limited vertical movable range of the rotation mechanism section 7, the core unit 21 cannot be moved further downward. Therefore, in order to place the upper end of the completed core material unit 21 at a lower position than the upper end of the mouth tube 13, the following process, which is different from the above-mentioned core material insertion process, is required in the final core material insertion process. It is.

(最後の芯材挿入工程)
図5(a)に示されるように、最後の芯材挿入工程では、回転軸部9とアタッチメント25との間に介在するように延長軸部27が取付けられる。延長軸部27の長さは例えば約50cmである。この延長軸部27が使用されること以外は、前述の芯材挿入工程と同様であるので、重複する説明を省略する。このような最後の芯材挿入工程では、図5(b)に示されるように、回転機構部7が上下可動範囲のほぼ下限位置まで下降したときに、芯材ユニット21の上端が口元管13の上端よりも低い位置まで押込まれる。その後、アタッチメント25と芯材ユニット21の上端部とのボルト止めが解除され、回転機構部7が上方に退避することで、芯材29(芯材ユニット21)の建込みが完了する。
(Final core material insertion process)
As shown in FIG. 5(a), in the final core material insertion step, the extension shaft portion 27 is attached to be interposed between the rotating shaft portion 9 and the attachment 25. The length of the extended shaft portion 27 is, for example, about 50 cm. Since the process is the same as the core material insertion process described above except that this extended shaft part 27 is used, duplicate explanation will be omitted. In such a final core material insertion step, as shown in FIG. It is pushed to a position lower than the top of the . Thereafter, the bolting between the attachment 25 and the upper end of the core unit 21 is released, and the rotation mechanism section 7 is retracted upward, thereby completing the erection of the core 29 (core unit 21).

続いて、以上説明した芯材建込み工程で用いられるアタッチメント25の構成について、図6及び図7を参照しながら説明する。図6は、アタッチメント25と、このアタッチメント25に取付けられるH鋼19(または芯材ユニット21)の上部と、を示す斜視図である。図7(a)はアタッチメント25の正面図であり、図7(b)はその側面図である。回転機構部7(図3(a))に取付けられた状態のアタッチメント25は、図6及び図7に示されるように、水平な平板状をなす本体部31と、本体部31の上面中央から上方に延びる装着軸33と、本体部31の下面中央部から下方に延びる2枚の狭持板35と、を備えている。本体部31は、平面視でH鋼19の縦横幅とほぼ同等の縦横幅の長方形をなしている。装着軸33は、回転機構部7の回転軸部9(図3(a)参照)に嵌め込まれる部位である。この装着軸33が回転軸部9に着脱可能に嵌め込まれることにより、アタッチメント25は回転機構部7に対して着脱可能に取付けられる。なお、前述した最後の芯材挿入工程においては、装着軸33は延長軸部27の下端部に嵌め込まれる。 Next, the configuration of the attachment 25 used in the core material erection process described above will be described with reference to FIGS. 6 and 7. FIG. 6 is a perspective view showing the attachment 25 and the upper part of the H steel 19 (or core unit 21) attached to the attachment 25. FIG. 7(a) is a front view of the attachment 25, and FIG. 7(b) is a side view thereof. As shown in FIGS. 6 and 7, the attachment 25 attached to the rotation mechanism 7 (FIG. 3(a)) has a main body 31 in the form of a horizontal flat plate, and It includes a mounting shaft 33 extending upward, and two holding plates 35 extending downward from the center of the lower surface of the main body 31. The main body portion 31 has a rectangular shape with a length and breadth approximately equal to the length and breadth of the H steel 19 when viewed from above. The mounting shaft 33 is a portion that is fitted into the rotation shaft portion 9 (see FIG. 3(a)) of the rotation mechanism portion 7. By removably fitting the mounting shaft 33 into the rotating shaft portion 9, the attachment 25 is removably attached to the rotating mechanism portion 7. In addition, in the last core material insertion process mentioned above, the mounting shaft 33 is fitted into the lower end part of the extension shaft part 27.

狭持板35は、H鋼19のウエブ19wに対して平行に存在する平板状をなしている。狭持板35を補強するために、各狭持板35の外側の面と本体部31の下面との角部には三角形のリブ32が設けられている。2枚の狭持板35は隙間37をあけて平行であり、この隙間37はウエブ19wの厚さよりもやや広い。各狭持板35には、水平方向及び鉛直方向に並ぶ4つのボルト穴39が厚み方向に貫通するように形成されている。この4つのボルト穴39の水平ピッチ及び鉛直ピッチは、ウエブ19wに形成された添接板24用のボルト穴23のピッチの整数倍である。従って、ウエブ19wが隙間37に下から挿入されるとともに、一方の狭持板35のボルト穴39、ウエブ19wのボルト穴23、及び他方の狭持板35のボルト穴39を順に挿通する4本のボルトをもって、ウエブ19wを狭持板35,35に締結することができる。このようにウエブ19wが狭持板35,35に締結されることで、芯材ユニット21は、アタッチメント25に取付けられ、当該アタッチメント25を介して削孔機械1の回転機構部7に取付けられる。 The holding plate 35 has a flat plate shape that is parallel to the web 19w of the H steel 19. In order to reinforce the holding plates 35, triangular ribs 32 are provided at the corners between the outer surface of each holding plate 35 and the lower surface of the main body portion 31. The two holding plates 35 are parallel with a gap 37 between them, and this gap 37 is slightly wider than the thickness of the web 19w. Four bolt holes 39 aligned in the horizontal and vertical directions are formed in each holding plate 35 so as to penetrate in the thickness direction. The horizontal pitch and vertical pitch of the four bolt holes 39 are integral multiples of the pitch of the bolt holes 23 for the attachment plate 24 formed in the web 19w. Therefore, the web 19w is inserted into the gap 37 from below, and four bolts are inserted in order through the bolt hole 39 of one of the holding plates 35, the bolt hole 23 of the web 19w, and the bolt hole 39 of the other holding plate 35. The web 19w can be fastened to the holding plates 35, 35 with the bolts. By fastening the web 19w to the holding plates 35, 35 in this manner, the core unit 21 is attached to the attachment 25, and via the attachment 25, the core unit 21 is attached to the rotation mechanism section 7 of the drilling machine 1.

続いて、本実施形態の杭打設方法による作用効果について説明する。この杭打設方法によれば、杭孔削孔工程で用いられる削孔機械1を、芯材建込み工程においても共通して使用することができる。すなわち、杭孔削孔工程においては、回転機構部7にアースオーガ11が取付けられることで、削孔機械1は本来の使用方法に従って杭孔15を形成する。そして、芯材建込み工程では、回転機構部7に芯材ユニット21がアタッチメント25を介して取付けられ、削孔機械1は回転機構部7の上下駆動機能を用いて芯材ユニット21を杭孔15に挿入する。 Next, the effects of the pile driving method of this embodiment will be explained. According to this pile driving method, the drilling machine 1 used in the pile drilling process can also be used in the core material erection process. That is, in the pile hole drilling process, the earth auger 11 is attached to the rotating mechanism section 7, so that the drilling machine 1 forms the pile hole 15 according to the original usage method. In the core material installation process, the core material unit 21 is attached to the rotating mechanism section 7 via the attachment 25, and the drilling machine 1 uses the vertical drive function of the rotating mechanism section 7 to move the core material unit 21 into the pile hole. Insert into 15.

空頭制限がある狭い現場101では大型のクレーンは使用できず、現場101で使用可能なクレーン17では前述の通り能力不足により芯材29の建込みは不可能である。従って、従来であれは、芯材29を建込むために、前述の特許文献1で開示されるような芯材建込装置を現場101に構築する必要があった。これに対し、本実施形態の杭打設方法によれば、狭い現場101において例えば上記のような芯材建込装置を構築する手間が削減される。このように、使用される機械が共通化され、芯材建込装置の構築作業の手間が削減されることで、工期短縮やコスト削減を図ることができる。 A large crane cannot be used at the narrow site 101 due to headroom restrictions, and the crane 17 that can be used at the site 101 is unable to erect the core material 29 due to lack of capacity as described above. Therefore, conventionally, in order to erect the core material 29, it was necessary to construct a core material erecting device at the site 101 as disclosed in the above-mentioned Patent Document 1. On the other hand, according to the pile driving method of the present embodiment, the effort required to construct, for example, the core material erection device as described above in the narrow site 101 is reduced. In this way, the machines used are standardized and the time and effort required to construct the core material erecting device is reduced, making it possible to shorten the construction period and reduce costs.

本発明は、上述した実施形態を始めとして、当業者の知識に基づいて種々の変更、改良を施した様々な形態で実施することができる。また、上述した実施形態に記載されている技術的事項を利用して、実施例の変形例を構成することも可能である。各実施形態等の構成を適宜組み合わせて使用してもよい。 The present invention can be implemented in various forms including the embodiments described above, with various changes and improvements based on the knowledge of those skilled in the art. Further, it is also possible to configure a modified example of the embodiment by using the technical matters described in the embodiment described above. You may use the structure of each embodiment etc. in combination suitably.

例えば、上述の実施形態では、杭の芯材がH鋼19であるが、芯材は、他の型鋼でもよく、例えば円柱の鋼管であってもよい。 For example, in the above-described embodiment, the core material of the pile is H steel 19, but the core material may be another type of steel, for example, a cylindrical steel pipe.

1…削孔機械、5…リーダ、7…回転機構部、11…アースオーガ、15…杭孔、19…H鋼(芯材材料)、21…芯材ユニット(芯材材料)、23…ボルト穴、24…添接板、25…アタッチメント、29…芯材。 DESCRIPTION OF SYMBOLS 1...Drilling machine, 5...Leader, 7...Rotating mechanism section, 11...Earth auger, 15...Pile hole, 19...H steel (core material), 21...Core unit (core material), 23...Bolt Hole, 24... Connection plate, 25... Attachment, 29... Core material.

Claims (4)

リーダと、前記リーダ上を昇降する回転機構部と、を備える削孔機械を用いて前記回転機構部でアースオーガを回転させながら地盤を削孔し杭孔を形成する杭孔削孔工程と、
芯材の一部をなし前記削孔機械の前記回転機構部に取付けられた芯材材料を継ぎ足しながら前記回転機構部の昇降動作により前記杭孔内に回転させずに挿入して前記芯材を前記杭孔内に建込む芯材建込み工程と、を備える、杭打設方法。
A pile hole drilling step of drilling a hole in the ground and forming a pile hole while rotating an earth auger with the rotation mechanism using a drilling machine including a leader and a rotation mechanism that moves up and down on the leader;
While adding the core material, which forms part of the core material and is attached to the rotating mechanism section of the drilling machine, the core material is inserted into the pile hole without rotation by the lifting and lowering movement of the rotating mechanism section. A pile driving method comprising the step of erecting a core material into the pile hole.
前記芯材がH鋼である、請求項1に記載の杭打設方法。 The pile driving method according to claim 1, wherein the core material is H steel. 前記芯材建込み工程では、
前記芯材材料の上端部が前記回転機構部に対して所定のアタッチメントを介して取付けられ、
前記芯材材料の継ぎ足しは、前記芯材材料の端部に設けられたボルト穴を用いて添接板を介して前記芯材材料同士を接続して行なわれ、
前記アタッチメントと前記芯材材料の前記上端部とが、当該上端部に位置する前記ボルト穴を利用したボルト止めによって連結される、請求項1又は2に記載の杭打設方法。
In the core material installation process,
The upper end of the core material is attached to the rotation mechanism via a predetermined attachment,
The addition of the core material is performed by connecting the core materials to each other via a splicing plate using bolt holes provided at the ends of the core material,
The pile driving method according to claim 1 or 2, wherein the attachment and the upper end of the core material are connected by bolting using the bolt hole located in the upper end.
前記芯材建込み工程では、
前記芯材材料が前記杭孔で仮支持された状態で、前記芯材材料の上端部に新たな前記芯材材料が連結され継ぎ足される芯材連結工程と、
前記芯材連結工程の後、前記芯材材料の上端部に前記回転機構部が取付けられ、前記芯材材料の前記仮支持が解除されて、前記回転機構部の昇降動作により前記芯材材料が前記杭孔内に挿入される芯材挿入工程と、
前記芯材挿入工程で前記杭孔内に挿入された前記芯材材料が前記杭孔に仮支持される仮支持工程と、が繰返し実行される、請求項1~3の何れか1項に記載の杭打設方法。
In the core material installation process,
a core material connection step in which a new core material is connected and added to the upper end of the core material while the core material is temporarily supported in the pile hole;
After the core material connection step, the rotation mechanism is attached to the upper end of the core material, the temporary support of the core material is released, and the core material is moved up and down by the vertical movement of the rotation mechanism. a step of inserting a core material into the pile hole;
A temporary support step in which the core material inserted into the pile hole in the core material insertion step is temporarily supported in the pile hole, is repeatedly performed. pile driving method.
JP2022042844A 2022-03-17 2022-03-17 Pile installation method Pending JP2023136911A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2022042844A JP2023136911A (en) 2022-03-17 2022-03-17 Pile installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2022042844A JP2023136911A (en) 2022-03-17 2022-03-17 Pile installation method

Publications (1)

Publication Number Publication Date
JP2023136911A true JP2023136911A (en) 2023-09-29

Family

ID=88146302

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2022042844A Pending JP2023136911A (en) 2022-03-17 2022-03-17 Pile installation method

Country Status (1)

Country Link
JP (1) JP2023136911A (en)

Similar Documents

Publication Publication Date Title
US9371623B2 (en) Diaphragm wall apparatus and methods
JPH1046523A (en) Simple temporary bridge temporary pier building construction method
JP6681148B2 (en) Bridge construction method, pillars and guide means used in the bridge construction method
JP6416474B2 (en) Structure construction method and support device
JP2023136911A (en) Pile installation method
WO2023109014A1 (en) Construction apparatus and construction method for steel pipe pile in bare rock riverbed
JP4867488B2 (en) Construction method of underground space, underground space constructed by this method, and underground structure constructed by this method
JP2942779B1 (en) Underground wall construction method
CN109488341B (en) Supporting method and supporting structure of curtain frame type underground excavation system
JP2981164B2 (en) Drilling rig
JP2002030658A (en) Support for hammer drill
JP3263562B2 (en) Tunnel support leg reinforcement method
KR101756937B1 (en) The pile foundation construction method that can build bulb of various type
KR101599381B1 (en) Installation apparatus for steel pile and construction method using the same
JPH10252080A (en) Method for reinforcing foundation of pier for high level road
JP3076827B2 (en) Seismic support pile
WO2003038198A1 (en) A method and apparatus for forming foundations
JP2935633B2 (en) Drilling rig for steel sheet pile wall construction
KR20180093358A (en) Slot casing with spacer and a method of construction for retaining wall using slot casing
JPS61250229A (en) Method and apparatus for penetration of steel sheet pile
JP2023077243A (en) Installation method for core material
JP3325550B2 (en) Pile construction equipment and pile construction method
KR20130003341A (en) Apparatus for executing underground outer wall
JP2023176823A (en) Earth retaining method
JPH0473517B2 (en)