JP2017004318A - Planning assistance system - Google Patents

Planning assistance system Download PDF

Info

Publication number
JP2017004318A
JP2017004318A JP2015118638A JP2015118638A JP2017004318A JP 2017004318 A JP2017004318 A JP 2017004318A JP 2015118638 A JP2015118638 A JP 2015118638A JP 2015118638 A JP2015118638 A JP 2015118638A JP 2017004318 A JP2017004318 A JP 2017004318A
Authority
JP
Japan
Prior art keywords
task
scenario
unit
tasks
small
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2015118638A
Other languages
Japanese (ja)
Other versions
JP6639115B2 (en
Inventor
信一 円谷
Shinichi Tsuburaya
信一 円谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP2015118638A priority Critical patent/JP6639115B2/en
Publication of JP2017004318A publication Critical patent/JP2017004318A/en
Application granted granted Critical
Publication of JP6639115B2 publication Critical patent/JP6639115B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

PROBLEM TO BE SOLVED: To appropriately assist in mapping out various activity plans in a planning assistance system, and thereby create activity plans easily without contradiction and improve work efficiency.SOLUTION: The planning assistance system comprises: a task input unit 41 for inputting a task; a rule input unit 42 for inputting a rule; a scenario input unit 43 for inputting a scenario; a scenario creation unit 23 for creating a plurality of large tasks for the task, rule, and scenario inputted from the input units 41, 42, 43 and a plurality of small task data arranged below the large tasks; a display unit 13 for displaying the large tasks along a time base on the basis of the scenario created by the scenario creation unit 23; a line boundary character check processing unit 24 for correcting the arrangement of the plurality of large tasks displayed on the display unit 13 along a time base in accordance with the connection state of the plurality of small task data; and an output unit 14 for outputting the scenario processed by the line boundary character check processing unit 24.SELECTED DRAWING: Figure 1

Description

本発明は、各種の行事や業務などの計画を立案するに当たり、その計画の立案を支援するための計画立案支援システムに関するものである。   The present invention relates to a planning support system for supporting the planning of various events and business plans.

例えば、自治体が防災訓練を実施するにあたり、担当者は、その防災訓練を円滑に実施する必要から、防災訓練の計画を立案しなければならない。この防災訓練は、本部の立ち上げ、市町村への連絡、被害状況の確認、交通機関の確保、支援物資の要請など、複数のタスクから構成されていることから、担当者は、各組織の担当者と連携を取って防災訓練の計画を立案する必要がある。そのため、担当者は、各組織の担当者を集めて防災訓練の計画を立案するための会議を開催し、各部署からの情報に基づいて、例えば、PERTなどの手法を用いて防災訓練の計画を立案している。   For example, when a local government conducts a disaster drill, the person in charge must make a plan for the disaster drill because it is necessary to smoothly implement the disaster drill. This disaster prevention training consists of multiple tasks, such as the start-up of the headquarters, contact with municipalities, confirmation of damage status, securing transportation facilities, and requesting support supplies. It is necessary to plan disaster prevention drills in cooperation with those who are involved. Therefore, the person in charge holds a meeting to gather the persons in charge of each organization and formulate a plan for disaster prevention training. Based on information from each department, for example, plans for disaster prevention training using a technique such as PERT We are planning.

なお、このような各種の行事や業務などの計画を立案するシステムとしては、例えば、下記特許文献に記載されたものがある。   In addition, as a system which makes a plan of such various events or business, there is one described in the following patent document, for example.

特許第3442131号公報Japanese Patent No. 3442131 特許第5119816号公報Japanese Patent No. 5119816 特開2008−221918号公報JP 2008-221918 A

ところで、防災訓練の計画を立案するとき、災害時の対応としては不確定な情報が多く、計画の変更が頻繁に発生することも予想される。しかし、前述したように、防災訓練には多くの組織が関与するため、計画の策定や更新が困難となる。一般的に、大規模な活動をする場合、事前の計画や調整が重要となるが、これを漏れなく実施することは困難である。これは、実行すべき事項が多いことに加え、様々な制約事項があることが要因の一つとなっている。例えば、被災者に飲料水を配布する場合、被災者が避難所に入室した後の方が望ましい。これを一般的なPERT法で考えると、被災者の入室というイベントと、飲料水の配布というイベントが直接的に接続される。しかし、本来、被災者の入室と飲料水の配布は別個な活動であり、これを直接的に接続することは不自然である。このように防災訓練などの大規模な活動を実行する場合、これを事前に計画することは重要であるが、これを矛盾なく作成することは非常に困難である。   By the way, when planning disaster prevention drills, there is a lot of information that is uncertain as a response to disasters, and it is expected that changes in the plan will occur frequently. However, as mentioned above, disaster prevention training involves many organizations, making it difficult to formulate and update plans. In general, prior planning and coordination are important for large-scale activities, but it is difficult to implement them without omissions. This is due to the fact that there are a lot of items to be executed and various restrictions. For example, when drinking water is distributed to victims, it is preferable that the victims enter the shelter. When this is considered by a general PERT method, an event of entering a disaster victim and an event of distribution of drinking water are directly connected. However, the entrance of the victims and the distribution of drinking water are separate activities, and it is unnatural to connect them directly. Thus, when carrying out large-scale activities such as disaster prevention drills, it is important to plan them in advance, but it is very difficult to create them without contradiction.

本発明は、上述した課題を解決するものであり、各種の活動の計画を立案することに対して適正に支援することで、活動計画を容易に矛盾なく作成して作業効率の向上を図る計画立案支援システムを提供することを目的とする。   The present invention solves the above-described problems, and plans to improve work efficiency by creating an activity plan easily and consistently by properly supporting various activity plans. The purpose is to provide a planning support system.

上記の目的を達成するための本発明の計画立案支援システムは、タスクを入力するタスク入力部と、ルールを入力するルール入力部と、シナリオを入力するシナリオ入力部と、前記タスク入力部から入力されたタスク及び前記ルール入力部から入力されたルール及び前記シナリオ入力部から入力されたシナリオに基づいて複数の大タスクを作成すると共に大タスクの下層に配置される複数の小タスクデータに基づいてシナリオを作成するシナリオ作成部と、前記シナリオ作成部が作成したシナリオに基づいて大タスクを時間軸に沿って表示する表示部と、複数の小タスクデータの接続状態に応じて前記表示部に表示された複数の大タスクの配置または小タスクの開始時間を時間軸に沿って修正する禁則処理部と、前記禁則処理部により処理されたシナリオを出力するシナリオ出力部と、を備えることを特徴とするものである。   In order to achieve the above object, a planning support system of the present invention includes a task input unit for inputting a task, a rule input unit for inputting a rule, a scenario input unit for inputting a scenario, and input from the task input unit A plurality of large tasks are created based on the entered task and the rule input from the rule input unit and the scenario input from the scenario input unit, and based on a plurality of small task data arranged below the large task A scenario creation unit that creates a scenario, a display unit that displays a large task along a time axis based on the scenario created by the scenario creation unit, and a display unit that displays a connection state of a plurality of small task data. A prohibition processing unit for correcting the arrangement of a plurality of large tasks or the start time of a small task along the time axis, and processing by the prohibition processing unit. And scenario output unit for outputting the scenario and is characterized in that it comprises.

従って、シナリオ作成部がタスクとルールとシナリオに基づいて複数の大タスクを作成すると共に複数の小タスクデータに基づいてシナリオを作成すると、この大タスクが表示部の時間軸に沿って表示され、禁則処理部が複数の小タスクデータの接続状態に応じて複数の大タスクの配置または小タスクの開始時間を時間軸に沿って修正する。そのため、複数の大タスクを異なる担当者が作成したとしても、この複数の大タスクを適正に且つ容易に接続して関連付けることができ、各種の活動の計画を立案することに対して適正に支援することで、活動計画を容易に矛盾なく作成して作業効率の向上を図ることができる。   Therefore, when the scenario creation unit creates a plurality of large tasks based on tasks, rules, and scenarios, and creates a scenario based on a plurality of small task data, this large task is displayed along the time axis of the display unit, The prohibition processing unit corrects the arrangement of the plurality of large tasks or the start time of the small tasks along the time axis according to the connection state of the plurality of small task data. Therefore, even if different persons create multiple large tasks, the multiple large tasks can be appropriately and easily connected and related to each other, and appropriate support is provided for planning various activities. By doing so, it is possible to easily create an activity plan without contradiction and improve work efficiency.

本発明の計画立案支援システムでは、前記シナリオ作成部は、第1の大タスクの下層の小タスクと第2の大タスクの下層の小タスクとを関連付けると、関連付けられた第1の大タスクと第2の大タスクの配置を時間軸に沿って修正して前記表示部に表示することを特徴としている。   In the planning support system of the present invention, when the scenario creating unit associates the small task below the first large task and the small task below the second large task, the associated first large task and The arrangement of the second large task is corrected along the time axis and displayed on the display unit.

従って、第1の大タスクと第2の大タスクとを容易に関連付けて各第タスクの配置を時間軸に沿って適正に配置することができる。   Therefore, the first large task and the second large task can be easily associated with each other and the arrangement of the first tasks can be appropriately arranged along the time axis.

本発明の計画立案支援システムでは、複数の大タスク及び大タスクの下層に位置する複数の小タスクが格納されるタスクデータ保存部と、複数の小タスクの開始時間及び終了時間を関連付ける複数のルールが格納されるルールデータ保存部とが設けられ、前記シナリオ入力部が前記タスクデータ保存部の大タスク及び小タスクを選択すると共に前記ルールデータ保存部のルールを選択することで、前記シナリオ作成部は、複数の大タスク及び複数の小タスクデータを作成することを特徴としている。   In the planning support system of the present invention, a plurality of rules that associate a plurality of large tasks and a plurality of small tasks located under the large tasks with a task data storage unit and start times and end times of the plurality of small tasks The scenario creation unit is configured such that the scenario input unit selects the large task and the small task of the task data storage unit and the rule of the rule data storage unit. Is characterized by creating a plurality of large tasks and a plurality of small task data.

従って、予め大タスク、小タスク、ルールを作成しておくことで、所望の大タスク、小タスク、ルールを選択することで、複数の大タスク及び複数の小タスクデータを容易に短時間で作成することができる。   Therefore, by creating large tasks, small tasks, and rules in advance, you can easily create multiple large tasks and multiple small task data in a short time by selecting the desired large tasks, small tasks, and rules. can do.

本発明の計画立案支援システムでは、前記表示部は、時間軸と、予め設定された選択可能な複数の大タスクを格納するタスク格納エリアと、選択された大タスクを時間軸に沿って表示するタスク表示エリアとを有することを特徴としている。   In the planning support system of the present invention, the display unit displays a time axis, a task storage area for storing a plurality of selectable large tasks set in advance, and the selected large task along the time axis. And a task display area.

従って、大タスクを効率良く表示することができる。   Therefore, large tasks can be displayed efficiently.

本発明の計画立案支援システムでは、前記表示部は、前記タスク表示エリアに表示された大タスクを選択すると、大タスクの下層の小タスクデータを表示することを特徴としている。   In the planning support system of the present invention, the display unit displays small task data below the large task when the large task displayed in the task display area is selected.

従って、大タスクを選択すると下層の小タスクデータが表示されることから、操作性を向上することができる。   Therefore, when a large task is selected, lower-level small task data is displayed, so that operability can be improved.

本発明の計画立案支援システムによれば、タスク及びルールに基づいて複数の大タスク及び大タスクの下層に配置される複数の小タスクデータを作成し、作成したシナリオに基づいて大タスクを時間軸に沿って表示し、複数の小タスクデータの接続状態に応じて複数の大タスクの配置を時間軸に沿って修正するので、各種の活動の計画を立案することに対して適正に支援することで、活動計画を容易に矛盾なく作成して作業効率の向上を図ることができる。   According to the planning support system of the present invention, a plurality of large tasks and a plurality of small task data arranged below the large tasks are created based on the tasks and rules, and the large tasks are arranged on the time axis based on the created scenarios. The layout of multiple large tasks is modified along the time axis according to the connection status of multiple small task data, so that appropriate support is provided for planning various activities. Therefore, it is possible to easily create an activity plan without contradiction and improve work efficiency.

図1は、本実施形態の計画立案支援システムを表す概略構成図である。FIG. 1 is a schematic configuration diagram showing a planning support system of this embodiment. 図2は、本実施形態の計画立案支援システムによる処理の流れを表すフローチャートである。FIG. 2 is a flowchart showing the flow of processing by the planning support system of this embodiment. 図3は、表示部における起動画面を表す概略図である。FIG. 3 is a schematic diagram showing a startup screen in the display unit. 図4は、表示部における大タスク配置画面を表す概略図である。FIG. 4 is a schematic diagram showing a large task arrangement screen on the display unit. 図5は、表示部における小大タスクデータ表示画面を表す概略図である。FIG. 5 is a schematic diagram showing a small and large task data display screen on the display unit. 図6は、表示部における小大タスクデータ編集画面を表す概略図である。FIG. 6 is a schematic diagram showing a small and large task data editing screen on the display unit. 図7は、表示部における大タスク修正画面を表す概略図である。FIG. 7 is a schematic diagram showing a large task correction screen on the display unit. 図8は、表示部における小タスクデータ表示画面を表す概略図である。FIG. 8 is a schematic diagram showing a small task data display screen on the display unit. 図9は、表示部における小タスクデータ接続画面を表す概略図である。FIG. 9 is a schematic diagram showing a small task data connection screen on the display unit. 図10は、表示部における大タスク確認画面を表す概略図である。FIG. 10 is a schematic diagram showing a large task confirmation screen on the display unit. 図11は、表示部における大タスク禁則処理画面を表す概略図である。FIG. 11 is a schematic diagram showing a large task prohibition processing screen on the display unit. 図12は、表示部におけるシナリオ出力画面を表す概略図である。FIG. 12 is a schematic diagram illustrating a scenario output screen on the display unit.

以下、添付図面を参照して、本発明に係る計画立案支援システムの好適な実施形態を詳細に説明する。なお、この実施形態により本発明が限定されるものではなく、また、実施形態が複数ある場合には、各実施形態を組み合わせて構成するものも含むものである。   DESCRIPTION OF EXEMPLARY EMBODIMENTS Hereinafter, exemplary embodiments of a planning support system according to the invention will be described in detail with reference to the accompanying drawings. In addition, this invention is not limited by this embodiment, and when there are two or more embodiments, what comprises combining each embodiment is also included.

図1は、本実施形態の計画立案支援システムを表す概略構成図である。   FIG. 1 is a schematic configuration diagram showing a planning support system of this embodiment.

本実施形態の計画立案支援システムは、図1に示すように、入力部11と、処理部12と、表示部13と、出力部14とから構成されている。   As shown in FIG. 1, the planning support system of this embodiment includes an input unit 11, a processing unit 12, a display unit 13, and an output unit 14.

入力部11は、タスク作成用データ及びルール作成用データ及びシナリオを入力するものであり、例えば、キーボードやマウスなどである。入力部11は、タスクを入力するタスク入力部41と、ルールを入力するルール入力部42と、シナリオを入力するシナリオ入力部と43とが設けられている。作業者は、タスク入力部41を用いて複数の大タスク作成用データやこの大タスクの下層にある複数の小タスク作成用データを入力する。また、作業者は、ルール入力部42を用いて複数の小タスクを関連付けるルール作成用データを入力する。更に、作業者は、シナリオ入力部43を用いて複数の大タスクと複数の小タスクを関連付けるシナリオを入力する。   The input unit 11 inputs task creation data, rule creation data, and scenarios, and is, for example, a keyboard or a mouse. The input unit 11 is provided with a task input unit 41 for inputting a task, a rule input unit 42 for inputting a rule, and a scenario input unit 43 for inputting a scenario. The worker uses the task input unit 41 to input a plurality of large task creation data and a plurality of small task creation data below the large task. In addition, the worker uses the rule input unit 42 to input rule creation data that associates a plurality of small tasks. Further, the worker inputs a scenario that associates a plurality of large tasks and a plurality of small tasks using the scenario input unit 43.

処理部12は、タスク作成部21と、ルール作成部22と、シナリオ作成部23と、禁則処理部24とを有している。また、処理部12は、タスクデータ保存部15とルールデータ保存部16が接続されている。   The processing unit 12 includes a task creation unit 21, a rule creation unit 22, a scenario creation unit 23, and a prohibition processing unit 24. The processing unit 12 is connected to a task data storage unit 15 and a rule data storage unit 16.

タスク作成部21は、タスク入力部41により入力された複数の大タスク作成用データや複数の小タスク作成用データに基づいて大タスク及び小タスクを作成する。ルール作成部22は、ルール入力部42により入力された複数の小タスク作成用ルールに基づいて複数の小タスクを関連付けるルールを作成する。   The task creation unit 21 creates a large task and a small task based on a plurality of large task creation data and a plurality of small task creation data input by the task input unit 41. The rule creation unit 22 creates a rule that associates a plurality of small tasks based on the plurality of small task creation rules input by the rule input unit 42.

シナリオ作成部23は、入力部11から入力されたタスクとルールとシナリオに基づいて複数の大タスク及びこの大タスクの下層に配置される複数の小タスクデータを作成するものである。即ち、シナリオ作成部23は、タスク作成部21が作成した大タスク及び小タスクと、ルール作成部22が作成したルールに基づいて複数の大タスクを作成すると共に、複数の小タスクデータに基づいてシナリオを作成する。ここで、小タスクデータは、作業の繋がりなどから大タスクを構成する小タスクの繋がりを定義したものであり、実施責任者(部署)、想定される実施時間、標準的な対応人数、小タスク完了後に実施される小タスクが定義されている。これらが定義されることで、各小タスクの実施時間や実施者等の情報が規定される。即ち、どのような複雑な活動であっても、小タスクデータ(小タスクの実行順序)とルールデータ(小タスクの優先実施順)の二つに分けて規定することで、簡易にシナリオの作成と管理ができる。   The scenario creation unit 23 creates a plurality of large tasks and a plurality of small task data arranged below the large tasks based on the tasks, rules, and scenarios input from the input unit 11. That is, the scenario creation unit 23 creates a plurality of large tasks based on the large task and the small task created by the task creation unit 21 and the rule created by the rule creation unit 22, and based on the plurality of small task data. Create a scenario. Here, the small task data defines the connection of small tasks that make up a large task from the connection of work, etc., and the person responsible for implementation (department), the estimated execution time, the standard number of responders, and the small tasks Small tasks to be performed after completion are defined. By defining these, information such as the execution time and implementer of each small task is defined. In other words, any complex activity can be created in two simple ways: small task data (small task execution order) and rule data (small task priority order). Can be managed.

なお、小タスクデータを作成するときに、ルールの矛盾が発生することがある。小タスクデータは、小タスクの実施順を直接的に規定するため、実施手順書(マニュアル)に近い。これに対して、ルールは、組織の活動に伴い蓄積される経験も含まれるため、ノウハウに近いと考えることができる。このため、ルールは、一時的に登録されるものではない可能性がある。即ち、ルールは、活動を実施する中で生じた課題や問題に対応するために追加されることが考えられる。このため、過去に登録したルールと新たに登録するルールとの間に矛盾が生じる可能性がある。   When creating small task data, rule conflicts may occur. The small task data is close to the execution procedure manual (manual) because it directly defines the execution order of the small tasks. On the other hand, since the rule includes experience accumulated with the activities of the organization, it can be considered that the rule is close to know-how. For this reason, the rule may not be temporarily registered. In other words, rules may be added to deal with issues and problems that arise during the implementation of activities. For this reason, there is a possibility that a contradiction occurs between a rule registered in the past and a newly registered rule.

例えば、過去に登録したルールとして、「AはBの実施後に実施される」と「BはCの実施後に実施される」があり、この場合の小タスクデータは、以下のものとなる。
C→B→A
しかし、新たに登録するルールとして、「CはAの実施後に実施される」があると、この場合の小タスクデータは、以下のものとなり、無限ループとして矛盾が発生する。
C→B→A→C
For example, the rules registered in the past include “A is implemented after execution of B” and “B is implemented after execution of C”, and the small task data in this case is as follows.
C → B → A
However, if there is a rule to be newly registered, “C is implemented after execution of A”, the small task data in this case is as follows, and a contradiction occurs as an infinite loop.
C → B → A → C

また、シナリオ作成部23は、例えば、第1の大タスクの下層の小タスクと第2の大タスクの下層の小タスクとを関連付けると、関連付けられた第1の大タスクと第2の大タスクの配置を時間軸に沿って修正して表示部13に表示する。第1の大タスクの下層の小タスクデータのうちの一つの小タスクと、第2の大タスクの下層の小タスクデータのうちの一つの小タスクとの実行順序や優先実施順が関連付けられると、小タスクデータ同士の関連が第1の大タスクと第2の大タスクの関連性にも影響を及ぼすことから、この第1の大タスクと第2の大タスクの配置を時間軸に沿って修正し、表示部13に表示する。   Further, for example, when the scenario creating unit 23 associates the small task in the lower layer of the first large task with the small task in the lower layer of the second large task, the associated first large task and the second large task Is corrected along the time axis and displayed on the display unit 13. When the execution order and priority execution order of one small task in the lower task data of the first large task and one small task in the lower task data of the second large task are associated with each other Since the relationship between the small task data also affects the relationship between the first large task and the second large task, the arrangement of the first large task and the second large task is arranged along the time axis. Correct and display on the display unit 13.

禁則処理部24は、複数の小タスクデータの接続状態に応じて表示部13に表示された複数の大タスクの配置と、小タスクの開始時間(大タスクの開始時間を変えずに、小タスクの開始時間だけを遅らせる調整を行う。)を時間軸に沿って修正するものである。即ち、複数の小タスクデータを接続することで、禁則処理部24は、複数の大タスクの実行順序や優先実施順に矛盾がないかどうかを確認する。ここで、複数の大タスクに矛盾が発生すると、この矛盾箇所が解消されるような禁則条件自動的に変更する。   The prohibition processing unit 24 arranges the plurality of large tasks displayed on the display unit 13 according to the connection state of the plurality of small task data and the start time of the small tasks (without changing the start time of the large task. Adjustment is made to delay only the start time of).) Is corrected along the time axis. That is, by connecting a plurality of small task data, the prohibition processing unit 24 checks whether there is a contradiction in the execution order or priority execution order of the plurality of large tasks. Here, when a contradiction occurs in a plurality of large tasks, the prohibition condition is automatically changed so that the contradiction portion is resolved.

表示部13は、シナリオ作成部23が作成し、禁則処理部24が修正したシナリオに基づいて大タスクを時間軸に沿って表示する。出力部14は、表示部13に表示されたシナリオまたは時間割を出力する。この出力部14は、例えば、プリンタやモニタなどである。また、所定の大タスクを選択すると、大タスクの下層にある小タスクデータを表示する。   The display unit 13 displays a large task along the time axis based on the scenario created by the scenario creation unit 23 and corrected by the prohibition processing unit 24. The output unit 14 outputs the scenario or timetable displayed on the display unit 13. The output unit 14 is, for example, a printer or a monitor. When a predetermined large task is selected, small task data below the large task is displayed.

また、表示部13は、図3に示すように、情報表示エリア(ハザード情報エリア)31と、タスク表示エリア32と、タスク格納エリア33とに区画され、タスク表示エリア32に時間軸34が上下方向に沿って表示されている。情報表示エリア31は、例えば、避難訓練を計画立案する場合、ハザード情報エリアとなる。タスク格納エリア33は、予め設定されて選択可能な複数の大タスクT(T1,T2,T3,T4,T5,T6,T7,T8,T9)を格納するものである。タスク表示エリア32は、タスク格納エリア33に格納されている複数の大タスクT(T1,T2,T3,T4,T5,T6,T7,T8,T9)から必要なタスクTを選択して時間軸34に沿って表示するものである。   Further, as shown in FIG. 3, the display unit 13 is divided into an information display area (hazard information area) 31, a task display area 32, and a task storage area 33, and the time axis 34 is moved up and down in the task display area 32. It is displayed along the direction. The information display area 31 is, for example, a hazard information area when planning an evacuation drill. The task storage area 33 stores a plurality of large tasks T (T1, T2, T3, T4, T5, T6, T7, T8, T9) that are preset and selectable. The task display area 32 selects a required task T from a plurality of large tasks T (T1, T2, T3, T4, T5, T6, T7, T8, T9) stored in the task storage area 33, and displays a time axis. 34 is displayed.

この場合、タスク表示エリア32やタスク格納エリア33にある各大タスクT1,T2,T3,T4,T5,T6,T7,T8,T9は、避難訓練の計画を立案する目的で予め作成されたものであり、各大タスクTの下層に複数の小タスクtが設定されている。表示部13は、入力部11によりタスク表示エリア32(または、タスク格納エリア33)に表示された大タスクTを選択すると、大タスクの下層の小タスクデータ(図5参照)を表示する。   In this case, the large tasks T1, T2, T3, T4, T5, T6, T7, T8, and T9 in the task display area 32 and the task storage area 33 are created in advance for the purpose of planning an evacuation drill. A plurality of small tasks t are set below each large task T. When the large task T displayed in the task display area 32 (or task storage area 33) is selected by the input unit 11, the display unit 13 displays small task data (see FIG. 5) below the large task.

また、表示部13は、編集ボタン35と接続ボタン36と禁則チェックボタン37が設けられている。入力部11により編集ボタン35を操作すると、各大タスクTや小タスクtやルールを変更することができる。入力部11により接続ボタン36を操作すると、小タスクデータの接続を変更することができる。入力部11により禁則チェックボタン37を操作すると、タスク表示エリア32にある各大タスクTの禁則処理を行うことができる。   The display unit 13 is provided with an edit button 35, a connection button 36, and a prohibition check button 37. When the edit button 35 is operated by the input unit 11, each large task T, small task t, and rule can be changed. When the connection button 36 is operated by the input unit 11, the connection of the small task data can be changed. When the prohibition check button 37 is operated by the input unit 11, prohibition processing of each large task T in the task display area 32 can be performed.

タスクデータ保存部15は、複数の大タスク及び複数の小タスクが格納されている。ルールデータ保存部16は、複数の小タスクの開始時間や終了時間を関連付ける複数のルール、つまり、前述した実施責任者(部署)、想定される実施時間、標準的な対応人数、小タスク完了後に実施される小タスクなどのルールが格納されている。そのため、入力部12によりタスクデータ保存部15の大タスク及び小タスクが選択されると共に、ルールデータ保存部16のルールが選択されることで、シナリオ作成部24は、複数の大タスク及び複数の小タスクデータを作成する。   The task data storage unit 15 stores a plurality of large tasks and a plurality of small tasks. The rule data storage unit 16 includes a plurality of rules that associate start times and end times of a plurality of small tasks, that is, the execution manager (department), the estimated execution time, the standard number of responders, and the completion of the small task. Stores rules such as small tasks to be executed. Therefore, by selecting the large task and the small task of the task data storage unit 15 by the input unit 12 and selecting the rule of the rule data storage unit 16, the scenario creation unit 24 has a plurality of large tasks and a plurality of tasks. Create small task data.

以下、本実施形態の計画立案支援システムによる発電プラントの避難訓練を計画立案する方法について説明する。   Hereinafter, a method for planning a power plant evacuation drill by the planning support system of the present embodiment will be described.

図2は、本実施形態の計画立案支援システムによる処理の流れを表すフローチャート、図3は、表示部における起動画面を表す概略図、図4は、表示部における大タスク配置画面を表す概略図、図5は、表示部における小大タスクデータ表示画面を表す概略図、図6は、表示部における小大タスクデータ編集画面を表す概略図、図7は、表示部における大タスク修正画面を表す概略図、図8は、表示部における小タスクデータ表示画面を表す概略図、図9は、表示部における小タスクデータ接続画面を表す概略図、図10は、表示部における大タスク確認画面を表す概略図、図11は、表示部における大タスク禁則処理画面を表す概略図、図12は、表示部におけるシナリオ出力画面を表す概略図である。   2 is a flowchart showing the flow of processing by the planning support system of the present embodiment, FIG. 3 is a schematic diagram showing a start screen on the display unit, and FIG. 4 is a schematic diagram showing a large task arrangement screen on the display unit, 5 is a schematic diagram showing a small and large task data display screen on the display unit, FIG. 6 is a schematic diagram showing a small and large task data editing screen on the display unit, and FIG. 7 is a schematic diagram showing a large task correction screen on the display unit. 8 is a schematic diagram showing a small task data display screen on the display unit, FIG. 9 is a schematic diagram showing a small task data connection screen on the display unit, and FIG. 10 is a schematic diagram showing a large task confirmation screen on the display unit. 11 is a schematic diagram showing a large task prohibition processing screen on the display unit, and FIG. 12 is a schematic diagram showing a scenario output screen on the display unit.

本実施形態の計画立案支援システムによる避難訓練を計画立案する方法において、図2に示すように、作業者は、ステップS11にて、編集ボタン35を操作した後、入力部11によりタスクを入力し、ステップS12にて、入力部11によりルールを入力すると、タスク作成部21は、大タスク及び小タスクを作成し、ルール作成部22は、複数の小タスクを関連付けるルールを作成する。ステップS13にて、作業者が禁則チェックボタン37を操作すると、禁則処理部24は、ルールに矛盾がないかどうかを判定する。   In the method for planning evacuation training by the planning support system of the present embodiment, as shown in FIG. 2, the operator inputs a task by the input unit 11 after operating the edit button 35 in step S11. In step S12, when a rule is input by the input unit 11, the task creation unit 21 creates a large task and a small task, and the rule creation unit 22 creates a rule that associates a plurality of small tasks. In step S13, when the operator operates the prohibition check button 37, the prohibition processing unit 24 determines whether there is a contradiction in the rules.

ここで、禁則処理部24によりルールに矛盾があると判定(Yes)されると、ステップS21にて、矛盾するルールを表示する。作業者は、ステップS22にて、ルールを修正する(Yes)のであれば、ステップS12に戻ってルールを変更することで矛盾を解消する。一方、作業者は、ステップS22にて、ルールを修正せず(No)に、ステップS23にて、タスクを修正する(Yes)のであれば、ステップS11に戻ってタスクを変更することで矛盾を解消する。そして、作業者は、ステップS23にて、ルールやタスクを修正しても矛盾が解消できない(No)と、ステップS24にて、エラーが表示される。   If the prohibition processing unit 24 determines that there is a contradiction in the rule (Yes), the contradicting rule is displayed in step S21. If the operator corrects the rule in step S22 (Yes), the operator returns to step S12 to change the rule and resolve the contradiction. On the other hand, if the operator does not correct the rule in step S22 (No) and corrects the task in step S23 (Yes), the operator returns to step S11 to change the task and make a contradiction. Eliminate. If the operator cannot correct the contradiction even if the rule or task is corrected in step S23 (No), an error is displayed in step S24.

ステップS13にて、禁則処理部24によりルールに矛盾がないと判定(No)されると、ステップS14にて、システムが起動され、表示部13に図3に示すような画面が表示される。なお、ステップS11からステップS13までの処理は、予め大タスク、小タスク、小タスクデータなどを作成しておくことで省略することができる。即ち、避難訓練は、複数の組織が対応するものであることから、事前に複数の組織を集めて会議をすることなく、主担当となる組織が各大タスクなど個々に作成しておくことが効率的である。本実施形態の場合、異なる組織の担当者が作成した複数の大タスクT1,T2,T3,T4,T5,T6,T7,T8,T9がタスク格納エリア33に表示される。   In step S13, if the prohibition processing unit 24 determines that there is no contradiction in the rules (No), the system is started in step S14, and a screen as shown in FIG. Note that the processing from step S11 to step S13 can be omitted by creating a large task, a small task, small task data, and the like in advance. In other words, since evacuation drills are handled by multiple organizations, the main organization can create each large task individually without gathering multiple organizations in advance and having a meeting. Efficient. In the present embodiment, a plurality of large tasks T1, T2, T3, T4, T5, T6, T7, T8, and T9 created by persons in charge in different organizations are displayed in the task storage area 33.

作業者は、ステップS15にて、シナリオを作成する。例えば、作業者は、図4に示すように、タスク格納エリア33に表示された複数の大タスクT1,T2,T3,T4,T5,T6,T7,T8,T9から、必要なタスクT1「要員参集」、T2「中山間部被害確認」、T3「沿岸部被害確認」、T4「郊外被害確認」、T5「社会インフラ被害確認」、T6「避難所開設状況確認」を選択してタスク表示エリア32に移動する。そして、選択した各タスクT1,T2,T3,T4,T5,T6を時間軸34に沿って配列する。すると、タスク表示エリア32にタスクT1「要員参集」、T2「中山間部被害確認」、T3「沿岸部被害確認」、T4「郊外被害確認」、T5「社会インフラ被害確認」、T6「避難所開設状況確認」が実施開始時間と共に表示される。   In step S15, the worker creates a scenario. For example, as shown in FIG. 4, the worker selects a necessary task T1 “personnel from a plurality of large tasks T1, T2, T3, T4, T5, T6, T7, T8, T9 displayed in the task storage area 33. Task display area by selecting "Gathering", T2 "Intermediate mountain damage confirmation", T3 "Coastal damage confirmation", T4 "Suburban damage confirmation", T5 "Social infrastructure damage confirmation", T6 "Evacuation site confirmation" Move to 32. Then, the selected tasks T1, T2, T3, T4, T5, and T6 are arranged along the time axis. Then, in the task display area 32, tasks T1 “personnel gathering”, T2 “intermediate damage check”, T3 “coastal damage check”, T4 “suburban damage check”, T5 “social infrastructure damage check”, T6 “evacuation shelter” “Open status confirmation” is displayed together with the implementation start time.

但し、ここでは、作業者は、他部署が作成した各大タスクT1,T2,T3,T4,T5,T6の内容の確認ができていないことから、各タスクT1,T2,T3,T4,T5,T6の下層にある小タスクデータの内容を確認する。例えば、T3「沿岸部被害確認」を選択することで、図5に示すように、小タスクデータを開き、小タスクt1,t2,t3,t4,t5,t6,t7,T8,T9の内容を確認すると共に、接続状態を確認する。ここで、小タスクt1,t2,t3,t4,t5,t6,t7,T8,T9の接続状態を変更する場合には、図6に示すように、小タスクt5の接続位置を小タスクt6から小タスクt7に変更する。同様に、その他の各大タスクT1,T2,T4,T5,T6の内容の確認を行う。   However, since the worker has not been able to confirm the contents of the large tasks T1, T2, T3, T4, T5, T6 created by other departments, the tasks T1, T2, T3, T4, T5 are here. , The contents of the small task data in the lower layer of T6 are confirmed. For example, by selecting T3 “Check coastal damage”, the small task data is opened and the contents of the small tasks t1, t2, t3, t4, t5, t6, t7, T8, T9 are displayed as shown in FIG. Confirm the connection status. Here, when the connection state of the small tasks t1, t2, t3, t4, t5, t6, t7, T8, and T9 is changed, the connection position of the small task t5 is changed from the small task t6 as shown in FIG. Change to small task t7. Similarly, the contents of the other major tasks T1, T2, T4, T5, and T6 are confirmed.

また、作業者は、他部署が作成した各タスクT1,T2,T3,T4,T5,T6同士を関連付けていないことから、各タスクT1,T2,T3,T4,T5,T6の下層にある小タスクデータ同士を関連付ける。例えば、図7に示すように、大タスクT4「郊外被害確認」とT5「社会インフラ被害確認」を選択することで、図8に示すように、各小タスクデータを開き、小タスクt11,t12,t13,t14,t15,t16,t17,t18,t19,t20,t21,t22,t23が接続された小タスクデータと、小タスクt31,t32,t33,t34,t35,t36・・・が接続された小タスクデータとを接続する。ここで、各小タスクデータを接続する場合には、図9に示すように、小タスクt21を小タスクt31に接続する。すると、図10に示すように、タスク表示エリア32にて、大タスクT4,T5の接続が設定される。なお、大タスクT4,T5同士を接続する接続線は、表示または非表示に設定できる。同様に、その他の各タスクT1,T2,T3,T4,T5,T6同士を接続する。   Further, since the worker does not associate the tasks T1, T2, T3, T4, T5, and T6 created by other departments with each other, the worker is located in a layer below each task T1, T2, T3, T4, T5, and T6. Associate task data with each other. For example, as shown in FIG. 7, by selecting a large task T4 “Confirm suburban damage” and T5 “Confirm social infrastructure damage”, each small task data is opened and small tasks t11, t12 as shown in FIG. , T13, t14, t15, t16, t17, t18, t19, t20, t21, t22, t23 and the small tasks t31, t32, t33, t34, t35, t36,. Connect to small task data. Here, when connecting each small task data, as shown in FIG. 9, the small task t21 is connected to the small task t31. Then, as shown in FIG. 10, the connection of the large tasks T4 and T5 is set in the task display area 32. The connection line connecting the large tasks T4 and T5 can be set to display or non-display. Similarly, the other tasks T1, T2, T3, T4, T5, and T6 are connected to each other.

図2に戻り、ステップS15にて、シナリオが作成されると、ステップS16にて、禁則条件の確認を行う。即ち、図11に示すように、作業者が禁則チェックボタン37を操作すると、禁則処理部24は、タスク表示エリア32に表示されている複数の大タスクにおける接続状態に矛盾がないかどうか、つまり、各小タスクデータ同士の接続に矛盾がないかどうかをチェックする。ここで、複数の大タスクに矛盾があると、この矛盾箇所が解消されるように大タスクの位置を時間軸34に沿って修正する。大タスクTを修正する場合、基本的には、各大タスクT1,T2,T3,T4,T5,T6,T7,T8,T9の開始時間(または、終了時間)を遅れる側に修正する。   Returning to FIG. 2, when a scenario is created in step S15, the prohibition condition is confirmed in step S16. That is, as shown in FIG. 11, when the operator operates the prohibition check button 37, the prohibition processing unit 24 checks whether there is a contradiction in the connection states of a plurality of large tasks displayed in the task display area 32. Check whether there is a contradiction in the connection between the small task data. Here, if there is a contradiction in a plurality of large tasks, the position of the large task is corrected along the time axis 34 so that the contradictory part is resolved. When the large task T is corrected, basically, the start time (or end time) of each large task T1, T2, T3, T4, T5, T6, T7, T8, and T9 is corrected to the delayed side.

図2に戻り、ステップS16にて、禁則条件の確認が終了すると、ステップS17にて、作成したシナリオを出力する。即ち、図12に示すように、作業者は、出力部14を用いて時刻及びプラント状態に対する各部署の対応を表したシナリオを出力する。   Returning to FIG. 2, when the confirmation of the prohibition condition is completed in step S16, the created scenario is output in step S17. That is, as shown in FIG. 12, the worker uses the output unit 14 to output a scenario representing the correspondence of each department to the time and the plant state.

このように本実施形態の計画立案支援システムにあっては、タスクを入力するタスク入力部41と、ルールを入力するルール入力部42と、シナリオを入力するシナリオ入力部43と、各入力部41,42,43から入力されたタスク及びルール及びシナリオに基づいて複数の大タスクを作成すると共に大タスクの下層に配置される複数の小タスクデータに基づいてシナリオを作成するシナリオ作成部23と、シナリオ作成部23が作成したシナリオに基づいて大タスクを時間軸に沿って表示する表示部13と、複数の小タスクデータの接続状態に応じて表示部13に表示された複数の大タスクの配置を時間軸に沿って修正する禁則処理部24と、禁則処理部24により処理されたシナリオを出力する出力部14とを設けている。   Thus, in the planning support system of the present embodiment, a task input unit 41 for inputting a task, a rule input unit 42 for inputting a rule, a scenario input unit 43 for inputting a scenario, and each input unit 41 , 42, 43, a scenario creation unit 23 that creates a plurality of large tasks based on the tasks, rules, and scenarios input from the scenarios, and creates a scenario based on a plurality of small task data arranged below the large tasks; A display unit 13 that displays a large task along the time axis based on a scenario created by the scenario creation unit 23, and an arrangement of a plurality of large tasks displayed on the display unit 13 according to the connection state of a plurality of small task data Are provided along with the time axis, and an output unit 14 that outputs a scenario processed by the prohibition processing unit 24 is provided.

従って、シナリオ作成部23がタスク及びルールに基づいて複数の大タスクと複数の小タスクデータに基づいてシナリオを作成すると、この大タスクが表示部の時間軸34に沿って表示され、禁則処理部24が複数の小タスクデータの接続状態に応じて複数の大タスクの配置及び小タスクの開始時間を時間軸34に沿って修正する。そのため、複数の大タスクを異なる担当者が作成したとしても、この複数の大タスクを適正に且つ容易に接続して関連付けることができ、各種の活動の計画を立案することに対して適正に支援することで、活動計画を容易に矛盾なく作成して作業効率の向上を図ることができる。   Therefore, when the scenario creation unit 23 creates a scenario based on a plurality of large tasks and a plurality of small task data based on the tasks and rules, the large task is displayed along the time axis 34 of the display unit, and the prohibition processing unit 24 corrects the arrangement of the plurality of large tasks and the start time of the small tasks along the time axis 34 according to the connection state of the plurality of small task data. Therefore, even if different persons create multiple large tasks, the multiple large tasks can be appropriately and easily connected and related to each other, and appropriate support is provided for planning various activities. By doing so, it is possible to easily create an activity plan without contradiction and improve work efficiency.

本実施形態の計画立案支援システムでは、シナリオ作成部23は、第1の大タスクの下層の小タスクと第2の大タスクの下層の小タスクとを関連付けると、関連付けられた第1の大タスクと第2の大タスクの配置を時間軸に沿って修正するか、または、小タスクの開始時間を変更して表示部13に表示する。従って、第1の大タスクと第2の大タスクとを容易に関連付けて各第タスクの配置を時間軸34に沿って適正に配置することができる。   In the planning support system of the present embodiment, when the scenario creation unit 23 associates the small task in the layer below the first large task and the small task in the layer below the second large task, the associated first large task And the arrangement of the second large task is corrected along the time axis, or the start time of the small task is changed and displayed on the display unit 13. Accordingly, the first large task and the second large task can be easily associated with each other and the arrangement of the first tasks can be appropriately arranged along the time axis 34.

本実施形態の計画立案支援システムでは、複数の大タスク及び大タスクの下層に位置する複数の小タスクが格納されるタスクデータ保存部15と、複数の小タスクの開始時間及び終了時間を関連付ける複数のルールが格納されるルールデータ保存部16とを設け、シナリオ入力部43がタスクデータ保存部15の大タスク及び小タスクを選択すると共にルールデータ保存部16のルールを選択することで、シナリオ作成部23は、複数の大タスク及び複数の小タスクデータを作成する。従って、予め大タスク、小タスク、ルールを作成しておくことで、所望の大タスク、小タスク、ルールを選択することで、複数の大タスク及び複数の小タスクデータを容易に短時間で作成することができる。   In the planning support system of this embodiment, the task data storage unit 15 in which a plurality of large tasks and a plurality of small tasks positioned below the large task are stored, and a plurality of associations between start times and end times of the plurality of small tasks. A rule data storage unit 16 for storing the rules, and the scenario input unit 43 selects a large task and a small task of the task data storage unit 15 and selects a rule of the rule data storage unit 16, thereby creating a scenario. The unit 23 creates a plurality of large tasks and a plurality of small task data. Therefore, by creating large tasks, small tasks, and rules in advance, you can easily create multiple large tasks and multiple small task data in a short time by selecting the desired large tasks, small tasks, and rules. can do.

本実施形態の計画立案支援システムでは、表示部13に、選択された大タスクを時間軸に沿って表示するタスク表示エリア32と、予め設定された選択可能な複数の大タスクを格納するタスク格納エリア33と、時間軸34とを設けている。従って、大タスクを効率良く表示することができる。   In the planning support system of this embodiment, the display unit 13 displays a task display area 32 that displays a selected large task along the time axis, and a task storage that stores a plurality of large tasks that can be selected in advance. An area 33 and a time axis 34 are provided. Therefore, large tasks can be displayed efficiently.

本実施形態の計画立案支援システムでは、表示部13のタスク表示エリア32に表示された大タスクを選択すると、大タスクの下層の小タスクデータを表示する。従って、大タスクを選択すると下層の小タスクデータが表示されることから、操作性を向上することができる。   In the planning support system of this embodiment, when a large task displayed in the task display area 32 of the display unit 13 is selected, small task data below the large task is displayed. Therefore, when a large task is selected, lower-level small task data is displayed, so that operability can be improved.

なお、上述した実施形態では、計画立案支援システムによりプラントの避難訓練の計画を立案するものに適用して説明したが、これに限定されるものではなく、各種の活動の計画を立案するものに適用することができる。   In the above-described embodiment, the description has been made by applying the plan evacuation training plan by the planning support system. However, the present invention is not limited to this, and the plan for various activities is planned. Can be applied.

11 入力部
12 処理部
13 表示部
14 出力部
15 タスクデータ保存部
16 ルールデータ保存部
21 タスク作成部
22 ルール作成部
23 シナリオ作成部
24 禁則処理部
31 情報表示エリア(ハザード情報エリア)
32 タスク表示エリア
33 タスク格納エリア
34 時間軸
35 編集ボタン
36 接続ボタン
37 禁則チェックボタン
41 タスク入力部
42 ルール入力部
43 シナリオ入力部
T 大タスク
t 小タスク
DESCRIPTION OF SYMBOLS 11 Input part 12 Processing part 13 Display part 14 Output part 15 Task data preservation | save part 16 Rule data preservation | save part 21 Task creation part 22 Rule creation part 23 Scenario creation part 24 Forbidden process part 31 Information display area (hazard information area)
32 task display area 33 task storage area 34 time axis 35 edit button 36 connect button 37 prohibition check button 41 task input section 42 rule input section 43 scenario input section T large task t small task

Claims (5)

タスクを入力するタスク入力部と、
ルールを入力するルール入力部と、
シナリオを入力するシナリオ入力部と、
前記タスク入力部から入力されたタスク及び前記ルール入力部から入力されたルール及び前記シナリオ入力部から入力されたシナリオに基づいて複数の大タスクを作成すると共に大タスクの下層に配置される複数の小タスクデータに基づいてシナリオを作成するシナリオ作成部と、
前記シナリオ作成部が作成したシナリオに基づいて大タスクを時間軸に沿って表示する表示部と、
複数の小タスクデータの接続状態に応じて前記表示部に表示された複数の大タスクの配置または小タスクの開始時間を時間軸に沿って修正する禁則処理部と、
前記禁則処理部により処理されたシナリオを出力するシナリオ出力部と、
を備えることを特徴とする計画立案支援システム。
A task input section for inputting a task;
A rule input section for inputting rules;
A scenario input section for inputting a scenario;
A plurality of large tasks are created based on a task input from the task input unit, a rule input from the rule input unit, and a scenario input from the scenario input unit, and a plurality of large tasks arranged below the large task A scenario creation unit that creates a scenario based on small task data;
A display unit for displaying a large task along the time axis based on the scenario created by the scenario creation unit;
A prohibition processing unit that corrects the arrangement of a plurality of large tasks displayed on the display unit or the start time of the small tasks according to a connection state of a plurality of small task data along the time axis,
A scenario output unit for outputting a scenario processed by the prohibition processing unit;
A planning support system characterized by comprising:
前記シナリオ作成部は、第1の大タスクの下層の小タスクと第2の大タスクの下層の小タスクとを関連付けると、関連付けられた第1の大タスクと第2の大タスクの配置を時間軸に沿って修正して前記表示部に表示することを特徴とする請求項1に記載の計画立案支援システム。   When the scenario creating unit associates the small task below the first large task with the small task below the second large task, the scenario creating unit arranges the associated first large task and the second large task in time. The planning support system according to claim 1, wherein the planning support system is corrected along an axis and displayed on the display unit. 複数の大タスク及び大タスクの下層に位置する複数の小タスクが格納されるタスクデータ保存部と、複数の小タスクの開始時間及び終了時間を関連付ける複数のルールが格納されるルールデータ保存部とが設けられ、前記シナリオ入力部が前記タスクデータ保存部の大タスク及び小タスクを選択すると共に前記ルールデータ保存部のルールを選択することで、前記シナリオ作成部は、複数の大タスク及び複数の小タスクデータを作成することを特徴とする請求項1または請求項2に記載の計画立案支援システム。   A task data storage unit that stores a plurality of large tasks and a plurality of small tasks that are positioned below the large task; and a rule data storage unit that stores a plurality of rules that associate start times and end times of the plurality of small tasks. And the scenario input unit selects a large task and a small task of the task data storage unit and selects a rule of the rule data storage unit, so that the scenario creation unit includes a plurality of large tasks and a plurality of tasks. 3. The planning support system according to claim 1 or 2, wherein small task data is created. 前記表示部は、時間軸と、予め設定された選択可能な複数の大タスクを格納するタスク格納エリアと、選択された大タスクを時間軸に沿って表示するタスク表示エリアとを有することを特徴とする請求項1から請求項3のいずれか一項に記載の計画立案支援システム。   The display unit has a time axis, a task storage area for storing a plurality of selectable large tasks set in advance, and a task display area for displaying the selected large tasks along the time axis. The planning support system according to any one of claims 1 to 3. 前記表示部は、前記タスク表示エリアに表示された大タスクを選択すると、大タスクの下層の小タスクデータを表示することを特徴とする請求項4に記載の計画立案支援システム。   5. The planning support system according to claim 4, wherein when the large task displayed in the task display area is selected, the display unit displays small task data below the large task.
JP2015118638A 2015-06-11 2015-06-11 Planning support system Active JP6639115B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2015118638A JP6639115B2 (en) 2015-06-11 2015-06-11 Planning support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2015118638A JP6639115B2 (en) 2015-06-11 2015-06-11 Planning support system

Publications (2)

Publication Number Publication Date
JP2017004318A true JP2017004318A (en) 2017-01-05
JP6639115B2 JP6639115B2 (en) 2020-02-05

Family

ID=57752786

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2015118638A Active JP6639115B2 (en) 2015-06-11 2015-06-11 Planning support system

Country Status (1)

Country Link
JP (1) JP6639115B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3348994A1 (en) 2017-01-13 2018-07-18 ARKRAY, Inc. Flow cell and measuring device

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005190241A (en) * 2003-12-26 2005-07-14 Kobe Steel Ltd Method for preparing schedule, schedule preparation system and program
JP2007164519A (en) * 2005-12-14 2007-06-28 Toshiba Corp Work plan creation device and work plan creation processing program
JP2011059770A (en) * 2009-09-07 2011-03-24 Canon Inc Process information management device and method, and storage medium recording process information management program
JP2011095918A (en) * 2009-10-28 2011-05-12 Being:Kk Project planning device
US20130297060A1 (en) * 2012-04-20 2013-11-07 Pipeline Software, Inc. Method and system for virtualized composite project work schedules
JP2015502620A (en) * 2011-12-21 2015-01-22 インターナショナル・ビジネス・マシーンズ・コーポレーションInternational Business Machines Corporation Detecting cases with conflicting rules

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005190241A (en) * 2003-12-26 2005-07-14 Kobe Steel Ltd Method for preparing schedule, schedule preparation system and program
JP2007164519A (en) * 2005-12-14 2007-06-28 Toshiba Corp Work plan creation device and work plan creation processing program
JP2011059770A (en) * 2009-09-07 2011-03-24 Canon Inc Process information management device and method, and storage medium recording process information management program
JP2011095918A (en) * 2009-10-28 2011-05-12 Being:Kk Project planning device
JP2015502620A (en) * 2011-12-21 2015-01-22 インターナショナル・ビジネス・マシーンズ・コーポレーションInternational Business Machines Corporation Detecting cases with conflicting rules
US20130297060A1 (en) * 2012-04-20 2013-11-07 Pipeline Software, Inc. Method and system for virtualized composite project work schedules

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP3348994A1 (en) 2017-01-13 2018-07-18 ARKRAY, Inc. Flow cell and measuring device

Also Published As

Publication number Publication date
JP6639115B2 (en) 2020-02-05

Similar Documents

Publication Publication Date Title
Tabrizi et al. Digital transformation is not about technology
US11615360B2 (en) System and method for identifying relevant information for an enterprise
US20180059910A1 (en) Collaborative network-based graphical progress management
US20060064335A1 (en) Method, system, and storage medium for performing business process modeling
US20220012671A1 (en) Systems and method for processing resource access requests
CN105447677A (en) Apparatus and scheduling method
CN105654243B (en) A kind of project information automated programming system based on trajectory diagram
CA3021514C (en) System and method for identifying relevant information for an enterprise
JP6639115B2 (en) Planning support system
Benyahya et al. Utilization of shopfloor management as a tool for communication and knowledge sharing in the framework of LEAN logistics–a case study
US20170278031A1 (en) System and Method for Crisis and Business Resiliency Management
Newsome ‘The Women Can Be Moved to Fill in the Gaps’: New Production Concepts, Gender and Suppliers
US20210312355A1 (en) Virtual agent system and method for modelling organization processes therefor
AU2019340053A1 (en) Method and system for completing and managing workflows
Sviridov et al. Approach to automatized formation of workplaces structure in configurable information systems
US20160162142A1 (en) User Interface Configuration Tool
JP2016006555A (en) Planning business support method and system
Jais et al. The role of women in nuclear-attracting public participation in regulatory decision-making process
Aripin et al. COVID-19 and disruptive technology in New Zealand
JP5367441B2 (en) Construction execution plan creation support system, construction execution plan creation support program, and computer-readable storage medium.
JP6463812B2 (en) System and method for identifying information relevant to a company
EP2849133A1 (en) Method and system for workflow objects to relate tasks and entities in support of processing, visualization and analytics
Nassief An Analogical JV Case Study on NUMMI
Galli The Role of Communication in Project Planning and Executing
JPH0496104A (en) Work plan generation processor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20180518

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20190419

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190507

A601 Written request for extension of time

Free format text: JAPANESE INTERMEDIATE CODE: A601

Effective date: 20190624

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20190807

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20190917

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20191114

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20191126

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20191224

R150 Certificate of patent or registration of utility model

Ref document number: 6639115

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150