JP2014031623A - Preceding handrail for framework scaffold and method of constructing the same - Google Patents

Preceding handrail for framework scaffold and method of constructing the same Download PDF

Info

Publication number
JP2014031623A
JP2014031623A JP2012171371A JP2012171371A JP2014031623A JP 2014031623 A JP2014031623 A JP 2014031623A JP 2012171371 A JP2012171371 A JP 2012171371A JP 2012171371 A JP2012171371 A JP 2012171371A JP 2014031623 A JP2014031623 A JP 2014031623A
Authority
JP
Japan
Prior art keywords
frame
column
building frame
handrail
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2012171371A
Other languages
Japanese (ja)
Inventor
Masayuki Hamano
雅之 浜野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
STEP UP KK
Original Assignee
STEP UP KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by STEP UP KK filed Critical STEP UP KK
Priority to JP2012171371A priority Critical patent/JP2014031623A/en
Publication of JP2014031623A publication Critical patent/JP2014031623A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

PROBLEM TO BE SOLVED: To safely and easily construct a preceding handrail for a framework scaffold and to reduce construction costs.SOLUTION: A preceding handrail 1 for a framework scaffold includes vertically long columns 12 which are each provided detachably on one stringer 3a between a pair of stringers of each building frame 5, and detachable upper sash bars 13 which couple upper-end parts of both columns 12, Each column 12 is provided with a fastener 19 for fixing the column 12 to the stringer at upper and lower end parts, with an upper sash bar fixture for fitting an upper sash bar 13 at the upper end part, and with a lock tool capable of being locked to a brace fixture for fitting a brace 8 to the building frame 5 below the column 12 and above a fastener part 19 at the lower end part of the column 12.

Description

本発明は、先行手摺及びその施工方法に関し、特に、枠組足場用先行手摺及びその施工方法に関するものである。   The present invention relates to a leading handrail and its construction method, and more particularly to a preceding handrail for a frame scaffold and its construction method.

一般に、建設作業現場等で使用される仮設足場として、各部寸法が規定された門型の建枠を組み上げて形成される枠組足場が知られている。   In general, as a temporary scaffold used in a construction work site or the like, a frame scaffold formed by assembling a gate-shaped building frame with dimensions of each part is known.

このような枠組足場には、作業者の落下防止を図るため、安全設備としての手摺が設けられる。この手摺は、枠組足場の組み立て時には足場の最上段に当たる部分に先行して設置され、枠組足場の解体時には最上段の足場板を取り外すまでは残されるため、先行手摺と呼ばれている。   Such a frame scaffold is provided with a handrail as a safety facility in order to prevent the operator from falling. This handrail is called a leading handrail because it is installed in advance of the portion corresponding to the uppermost stage of the scaffold when assembling the frame scaffold, and remains until the uppermost scaffold plate is removed when the framework scaffold is disassembled.

従来のこの種の先行手摺としては、例えば、特許文献1に開示されているように、縦柱に固定される取付け装置を介して枠組足場に取り付けられる門型又は鳥居型の持ち上がり式先行手すり枠や、非特許文献1に開示されているように、専用金具を使用して支柱を枠組足場の建枠に取り付けた後、その支柱にさらに専用の手すり部材を取り付ける手すり先行足場などが知られている。   As this type of conventional handrail, for example, as disclosed in Patent Document 1, a gate-type or torii-type lift-type handrail that is attached to a frame scaffold via an attachment device fixed to a vertical column. Also, as disclosed in Non-Patent Document 1, there is known a handrail preceding scaffold for attaching a dedicated handrail member to the support after attaching the support to the building frame of the frame scaffold using a dedicated bracket. Yes.

特開2003−147953号公報Japanese Patent Laid-Open No. 2003-147953

ホリー株式会社の手すり先行足場「HORY UP TRIO SYSTEM」のカタログCatalog of "HOLY UP TRIO SYSTEM"

しかしながら、特許文献1の先行手摺では、専用の取付け装置や手すり枠が必要となり、しかも、取付け装置はかなり複雑な構造を有しているため、製造や組み立て等に手間が掛かり、施工コストの増大要因となるという問題がある。また、特許文献1の先行手摺は盛り替えるタイプであるため、施工に手間が掛かり、使い勝手が悪いという問題もある。   However, the prior handrail disclosed in Patent Document 1 requires a dedicated attachment device and a handrail frame, and the attachment device has a rather complicated structure, which requires time and labor for manufacturing and assembly, and increases construction costs. There is a problem that becomes a factor. Moreover, since the prior handrail of patent document 1 is a type which changes the order, construction also takes time and there also exists a problem that usability is bad.

また、非特許文献1の先行手摺では、枠組足場を組んだ上で先行手摺を取り付ける必要があるため、施工が面倒であるという問題がある。さらに、専用金具を使用する必要があると共に、手すり部材も専用の材料を使用する必要があるため、コストが掛かるという問題もある。   In addition, the prior handrail of Non-Patent Document 1 has a problem that the construction is troublesome because it is necessary to attach the prior handrail after the frame scaffold is assembled. Furthermore, since it is necessary to use a dedicated metal fitting and to use a dedicated material for the handrail member, there is a problem that costs are increased.

本発明は、上記した課題を解決すべくなされたものであり、安全且つ容易に施工することができ、施工コストの低減化を図ることのできる枠組足場用先行手摺及びその施工方法を提供することを目的とするものである。   The present invention has been made to solve the above-described problems, and provides a handrail for a frame scaffolding that can be safely and easily constructed and can reduce the construction cost, and a construction method thereof. It is intended.

上記した目的を達成するため、本発明は、2本一対の縦材と該両縦材の上端を結合する横材とにより門型に形成される建枠をお互いに対向するように起立させて該両建枠を筋交いで連結すると共に該両建枠の前記横材間に足場板を架設して形成される枠組足場において、新たに施工する最上段の足場の手摺として取り付けられる先行手摺であって、前記各建枠の2本一対の縦材のうちのそれぞれいずれか一方の縦材に着脱可能に設けられる上下方向に長い支柱と、該両支柱の上端部同士を連結する着脱可能な上桟と、を備え、前記支柱の上下端部には前記縦材に該支柱を固定するための締結具が設けられ、前記支柱の上端部には前記上桟を取り付けるための上桟取付具が設けられ、前記支柱の下部であって前記支柱の下端部の締結部の上方には、前記建枠に前記筋交いを取り付けるための筋交い取付具に掛止可能な掛止具が設けられていることを特徴とする。   In order to achieve the above-described object, the present invention allows a building frame formed in a gate shape to stand up against each other by a pair of vertical members and a horizontal member that joins the upper ends of the vertical members. In the frame scaffolding that is formed by linking the building frames in a brace and linking a scaffolding plate between the cross members of the building frames, it is a leading handrail attached as a handrail for the uppermost scaffold to be newly constructed. And a detachable upper for connecting the upper ends of the two columns to each other, and a column that is detachably provided on either one of the pair of vertical members of each building frame. And a fastener for fixing the column to the vertical member is provided at the upper and lower ends of the column, and an upper column attachment for attaching the upper beam to the upper end of the column. Provided at the bottom of the column and above the fastening portion at the lower end of the column. Characterized in that the latching possible locking device is provided in brace fitting for attaching said struts to said Kenwaku.

また、本発明に係る枠組み足場用先行手摺において、前記上桟より下方において前記両支柱同士を連結する着脱可能な中桟をさらに備え、前記支柱には、前記上桟取付具と前記掛止具との間に前記中桟を取り付けるための中桟取付具が設けられていることを特徴とする。   In addition, the advance scaffolding for a frame scaffold according to the present invention further includes a removable middle beam that connects the two columns below the upper beam, and the column includes the upper beam attachment tool and the hook. A middle rail attachment for attaching the middle rail is provided between the two.

また、本発明は、建枠の縦材に支柱を固定するための締結具が上下端部に設けられ、上桟を取り付けるための上桟取付具が上端部に設けられ、該上桟取付具の下方に中桟を取り付けるための中桟取付具が設けられ、下部であって前記下端部の締結部の上方に建枠の筋交い取付具に掛止可能な掛止具が設けられる先行手摺を枠組足場に施工する方法であって、前記建枠をお互いに対向するように起立させて該両建枠を筋交いで連結する工程と、一方の建枠の一方の縦材の前記筋交い取付具に前記掛止具を掛止すると共に該一方の建枠の一方の縦材に一方の支柱の下端部の前記締結具を固定して該一方の建枠の縦材に前記一方の支柱を固定する工程と、該一方の支柱の前記上桟取付具に前記上桟の一端部を取り付けると共に他方の支柱の前記上桟取付具に前記上桟の他端部を取り付けると共に、前記一方の支柱の前記中桟取付具に前記中桟の一端部を取り付けると共に前記他方の支柱の前記中桟取付具に前記中桟の他端部を取り付けた上で、他方の建枠の一方の縦材の前記筋交い取付具に前記掛止具を掛止すると共に該他方の建枠の一方の縦材に他方の支柱の下端部の前記締結具を固定して該他方の建枠の一方の縦材に前記他方の支柱を固定する工程と、前記両建枠間に足場板を架設する工程と、を備えていることを特徴とする。   The present invention also provides a fastener for fixing the column to the vertical member of the building frame at the upper and lower ends, and an upper beam attachment for attaching the upper beam at the upper end, the upper beam attachment An intermediate rail mounting tool for mounting the intermediate rail is provided below, and a leading handrail is provided at the lower portion and above the fastening portion of the lower end portion, and provided with a latch that can be hooked to the bracing attachment of the building frame. A method of constructing a frame scaffold, wherein the building frame is erected so as to face each other and the building frames are connected by bracing, and the bracing fixture of one vertical member of one building frame. The fastening member is latched and the fastening member at the lower end of one pillar is fixed to one vertical member of the one building frame, and the one pillar is fixed to the vertical member of the one building frame. A step of attaching one end of the upper beam to the upper beam fixture of the one column and the upper beam of the other column Attach the other end of the upper rail to the attachment, attach one end of the middle rail to the middle rail attachment of the one strut, and attach the other end of the middle rail to the middle rail attachment of the other strut After attaching the end portion, the hook is hooked to the bracing attachment of one vertical member of the other building frame and the lower end of the other column is attached to one vertical member of the other building frame. Fixing the fastener and fixing the other strut to one vertical member of the other building frame, and laying a scaffolding plate between the building frames. To do.

本発明によれば、安全且つ容易に施工することができ、施工コストの低減化を図ることができる等種々の優れた効果を得ることができる。   According to the present invention, various excellent effects such as safe and easy construction and reduction of construction cost can be obtained.

本発明の実施の形態に係る枠組足場用先行手摺を取り付けた枠組足場を示す正面図である。It is a front view which shows the frame scaffold which attached the front handrail for frame scaffolds concerning embodiment of this invention. 本発明の実施の形態に係る枠組足場用先行手摺を取り付けた枠組足場を示す側面図である。It is a side view which shows the frame scaffold which attached the advance handrail for frame scaffolds concerning embodiment of this invention. 本発明の実施の形態に係る枠組足場用先行手摺の支柱を背面側から示す斜視図である。It is a perspective view which shows the support | pillar of the preceding handrail for frame scaffolds concerning embodiment of this invention from the back side.

以下、図面を参照しつつ、本発明の実施の形態に係る枠組足場用先行手摺について説明する。ここで、図1は本発明の実施の形態に係る枠組足場用先行手摺を取り付けた枠組足場を示す正面図、図2は本発明の実施の形態に係る枠組足場用先行手摺を取り付けた枠組足場を示す側面図、図3は本発明の実施の形態に係る枠組足場用先行手摺の支柱を背面側から示す斜視図である。なお、以下の説明では、便宜上、前後の向きは本発明の実施の形態に係る枠組足場用先行手摺を取り付ける正面側を前側と定義して説明する。   Hereinafter, with reference to the drawings, description will be given of a handrail for a frame scaffold according to an embodiment of the present invention. Here, FIG. 1 is a front view showing a frame scaffold to which a handrail for a frame scaffold according to an embodiment of the present invention is attached, and FIG. 2 is a frame scaffold to which a handrail for a frame scaffold according to an embodiment of the present invention is attached. FIG. 3 is a perspective view showing the support rail of the advance scaffolding for the frame scaffold according to the embodiment of the present invention from the back side. In the following description, for the sake of convenience, the front-rear direction will be described by defining the front side to which the preceding handrail for frame scaffolding according to the embodiment of the present invention is attached as the front side.

本実施の形態に係る枠組足場用先行手摺1は、枠組足場2に取り付けられる。枠組足場2は、前後2本一対の縦材3a,3bと両縦材3a,3bの上端を結合する横材4とにより門型に形成される建枠5と、建枠5の各縦材3a,3bの下端に装着されるベース金具6と、各縦材3a,3bの下部に水平に締結される単管パイプから成る根がらみ7と、ベース金具6を介してお互いに対向するように地面に起立された両建枠5を連結する筋交い8と、両建枠5の横材4間に架設される足場板9と、足場板9上からの作業員の落下防止のために取り付けられる枠組足場用先行手摺1と、を備えて構成されている。   The preceding scaffold 1 for a framework scaffold according to the present embodiment is attached to a framework scaffold 2. The frame scaffold 2 includes a building frame 5 formed in a gate shape by a pair of longitudinal members 3a, 3b and a cross member 4 connecting the upper ends of both longitudinal members 3a, 3b, and each longitudinal member of the building frame 5. The base metal fitting 6 attached to the lower ends of 3a and 3b, the root stub 7 consisting of a single pipe pipe horizontally fastened to the lower part of each vertical member 3a and 3b, and the base metal fitting 6 are opposed to each other. A brace 8 connecting the two building frames 5 erected on the ground, a scaffolding plate 9 constructed between the cross members 4 of the two building frames 5, and attached to prevent the worker from falling from the scaffolding plate 9. And a framework handrail 1 for a scaffold.

建枠5の各縦材3a,3bには、お互いに対向する上下の位置に、取付ピン10,11がそれぞれ突設されている。取付ピン10,11にはそれぞれ筋交い8の両端部が掛止可能となっており、取付ピン10,11は筋交い8を取り付けるための筋交い取付具として機能する。   Mounting pins 10 and 11 project from the vertical members 3a and 3b of the building frame 5 at upper and lower positions facing each other. Both ends of the brace 8 can be hooked on the mounting pins 10 and 11, respectively, and the mounting pins 10 and 11 function as a brace fitting for attaching the brace 8.

枠組足場用先行手摺1は、各建枠5の2本一対の縦材3a,3bのうちのそれぞれ前側の対向する縦材3aに着脱可能に設けられる上下方向に長い支柱12と、両支柱12の上端部同士を連結する着脱可能な上桟13と、上桟13より下方において両支柱12同士を連結する着脱可能な中桟14と、を備えて構成されている。   The framed scaffolding handrail 1 includes a vertically long column 12 detachably provided on the opposite vertical member 3a on the front side of the pair of vertical members 3a, 3b of each building frame 5, and both columns 12 And a removable upper beam 13 for connecting the upper ends of the two columns, and a removable middle beam 14 for connecting the two columns 12 below the upper beam 13.

図3に良く示されているように、支柱12は、例えば金属製角パイプから成り、支柱12の鉛直な後面15の上下端部には、それぞれ短い平板16,17が片持ち梁状に水平に溶接されて固定されている。上下端部の平板16,17の前面側には、単管クランプ18,19がそれぞれ取り付けられており、単管クランプ18,19は縦材3aに支柱12を固定するための締結具として機能する。また、上端部の平板16の後面側には第1固定ピン20が突設されており、第1固定ピン20は上桟13を取り付けるための上桟取付具として機能する。   As shown well in FIG. 3, the support column 12 is made of, for example, a metal square pipe, and short flat plates 16 and 17 are horizontally arranged in a cantilever shape on the upper and lower ends of the vertical rear surface 15 of the support column 12, respectively. It is welded and fixed to. Single pipe clamps 18 and 19 are respectively attached to the front surfaces of the flat plates 16 and 17 at the upper and lower end portions, and the single pipe clamps 18 and 19 function as fasteners for fixing the column 12 to the vertical member 3a. . Further, a first fixing pin 20 protrudes from the rear surface side of the flat plate 16 at the upper end, and the first fixing pin 20 functions as an upper beam attaching tool for attaching the upper beam 13.

支柱12の下部であって支柱12の下端部の平板17の上方の側面には、L字板状の掛止具21が片持ち梁状に水平に溶接されて固定されている。掛止具21には円形孔22が穿設されており、円形孔22に縦材3a,3bの上側の取付ピン10が掛止可能となっている。   An L-shaped hook 21 is horizontally welded and fixed in a cantilevered manner to the lower side of the column 12 and the upper side surface of the flat plate 17 at the lower end of the column 12. A circular hole 22 is formed in the hook 21, and the mounting pin 10 on the upper side of the vertical members 3 a and 3 b can be hooked in the circular hole 22.

また、支柱12の後面15には、第1固定ピン20と掛止具21との間に、第2固定ピン22が突設されている。第2固定ピン22にはそれぞれ中桟14の両端部が掛止可能となっており、第2固定ピン22は中桟14を取り付けるための中桟取付具として機能する。   A second fixing pin 22 protrudes from the rear surface 15 of the support column 12 between the first fixing pin 20 and the latch 21. Both ends of the middle rail 14 can be hooked on the second fixing pins 22, respectively, and the second fixing pin 22 functions as a middle rail attachment for attaching the middle rail 14.

次に、図面を参照しつつ、本発明の実施の形態に係る枠組足場用先行手摺1を備えた枠組足場2の組み立て方法について説明する。   Next, a method for assembling the frame scaffold 2 including the frame scaffolding advance handrail 1 according to the embodiment of the present invention will be described with reference to the drawings.

先ず、図1及び図2に示すように、地面にベース金具6を介して複数(図示では3個)の建枠5をお互いに対向するように起立させ、各建枠5の後側の対向する縦材3bの取付ピン10,11に筋交い8の両端部をそれぞれ掛止させ、縦材3b間に筋交い8を取り付ける。また、各建枠5の縦材3a,3bの下側の取付ピン11より下方にそれぞれ根がらみ7を水平に締結する。   First, as shown in FIGS. 1 and 2, a plurality of (three in the figure) building frames 5 are erected on the ground via base metal fittings 6 so as to face each other. The both ends of the brace 8 are hooked on the mounting pins 10 and 11 of the longitudinal member 3b to be attached, and the brace 8 is attached between the longitudinal members 3b. Further, the root guards 7 are horizontally fastened below the mounting pins 11 on the lower side of the vertical members 3a and 3b of each building frame 5, respectively.

次いで、一方の建枠5の前側の縦材3aの取付ピン10に掛止具21を掛止すると共に一方の建枠5の前側の縦材3aに一方の支柱12の下端部の単管クランプ19を固定して、一方の建枠5の前側の縦材3aに一方の支柱12を固定する。   Next, the latch 21 is hooked on the mounting pin 10 of the vertical member 3a on the front side of one building frame 5, and the single tube clamp at the lower end portion of the one column 12 is attached to the vertical member 3a on the front side of one building frame 5. 19 is fixed, and one support column 12 is fixed to the longitudinal member 3a on the front side of one building frame 5.

次いで、一方の支柱12の第1固定ピン20に上桟13の一端部を取り付けると共に他方の支柱12の第1固定ピン20に上桟13の他端部を取り付け、また、一方の支柱12の第2固定ピン22に中桟14の一端部を取り付けると共に他方の支柱12の第2固定ピン22に中桟14の他端部を取り付けた上で、他方の建枠5の前側の縦材3aの取付ピン10に掛止具21を掛止すると共に他方の建枠5の前側の縦材3aに他方の支柱12の下端部の単管クランプ19を固定して、他方の建枠5の前側の縦材3aに他方の支柱12を固定する。   Next, one end portion of the upper rail 13 is attached to the first fixing pin 20 of one support column 12 and the other end portion of the upper beam 13 is attached to the first fixing pin 20 of the other support column 12. A vertical member 3a on the front side of the other building frame 5 after attaching one end portion of the intermediate beam 14 to the second fixed pin 22 and attaching the other end portion of the intermediate beam 14 to the second fixed pin 22 of the other support column 12. The fastening tool 21 is hooked on the mounting pin 10 and the single pipe clamp 19 at the lower end of the other support column 12 is fixed to the vertical member 3 a on the front side of the other building frame 5, and the front side of the other building frame 5 is fixed. The other support column 12 is fixed to the vertical member 3a.

そして、両建枠5の横材4間に足場板9を架設し、各建枠5の前側の対向する縦材3aの取付ピン10,11に筋交い8の両端部をそれぞれ掛止させ、縦材3a間に筋交い8を取り付ける。   And the scaffolding board 9 is constructed between the cross members 4 of both building frames 5, and the both ends of the brace 8 are respectively hooked on the mounting pins 10 and 11 of the opposing vertical members 3a on the front side of each building frame 5. A brace 8 is attached between the materials 3a.

以降、2段目より上段の足場についても同様に先行手摺1を組み立て、所定段数の枠組足場2を組み立てる。なお、2段目より上段の足場において、各建枠5の前側の縦材3a間には、先行手摺1が取り付けられているため、筋交い8を取り付ける必要がない。
また、枠組足場2を解体する場合には、上記した組み立て方法の逆の手順で行うことができるため、ここではその詳細な説明については省略する。
Thereafter, the preceding handrail 1 is similarly assembled to the scaffolds above the second stage, and the frame scaffold 2 having a predetermined number of stages is assembled. In addition, in the scaffolds above the second stage, since the leading handrail 1 is attached between the vertical members 3a on the front side of each building frame 5, it is not necessary to attach the brace 8.
Further, when the frame scaffold 2 is disassembled, it can be performed in the reverse order of the above-described assembly method, and thus detailed description thereof is omitted here.

このように上記した実施の形態に係る枠組足場用先行手摺1及びその施工方法によれば、市販の上桟13や中桟14を使用することができ、専用の部品は支柱12だけであり、しかも支柱12は極めて簡単な構造を有している。また、本実施の形態に係る枠組足場用先行手摺1は、筋交い8の代わりになるため、前側の縦材3a間の筋交い8を省略することができる。したがって、先行手摺1の製造や施工を容易に行うことができ、施工コストの低減化を図ることができる。また、先行手摺1を簡単な手順で確実に取り付けることができ、安全性の向上を図ることができる。   As described above, according to the framework scaffolding handrail 1 and its construction method according to the embodiment described above, the commercially available upper rail 13 and the middle rail 14 can be used, and the dedicated parts are only the pillars 12, Moreover, the support column 12 has a very simple structure. In addition, since the framework scaffolding handrail 1 according to the present embodiment is a substitute for the brace 8, the brace 8 between the longitudinal members 3a on the front side can be omitted. Therefore, manufacture and construction of the leading handrail 1 can be easily performed, and the construction cost can be reduced. In addition, the leading handrail 1 can be reliably attached by a simple procedure, and safety can be improved.

なお、上記した本発明の実施の形態の説明は、本発明に係る枠組足場用先行手摺及びその施工方法における好適な実施の形態を説明しているため、技術的に好ましい種々の限定を付している場合もあるが、本発明の技術範囲は、特に本発明を限定する記載がない限り、これらの態様に限定されるものではない。すなわち、上記した本発明の実施の形態における構成要素は適宜、既存の構成要素等との置き換えが可能であり、かつ、他の既存の構成要素との組合せを含む様々なバリエーションが可能であり、上記した本発明の実施の形態の記載をもって、特許請求の範囲に記載された発明の内容を限定するものではない。   In addition, since description of embodiment of this invention mentioned above demonstrates suitable embodiment in the advance handrail for frame scaffolds concerning the present invention, and its construction method, various technically preferable restrictions are attached. However, the technical scope of the present invention is not limited to these embodiments unless specifically described to limit the present invention. That is, the above-described components in the embodiment of the present invention can be appropriately replaced with existing components and the like, and various variations including combinations with other existing components are possible. The description of the embodiment of the present invention described above does not limit the contents of the invention described in the claims.

1 枠組足場用先行手摺
2 枠組足場
3a,3b 縦材
4 横材
5 建枠
8 筋交い
9 足場板
10,11 取付ピン(筋交い取付具)
12 支柱
13 上桟
14 中桟
18,19 直管クランプ(締結具)
20 第1固定ピン(上桟取付具)
21 掛止具
22 第2固定ピン(中桟取付具)
DESCRIPTION OF SYMBOLS 1 Leading handrail for frame scaffolds 2 Frame scaffolds 3a, 3b Vertical members 4 Horizontal members 5 Building frames 8 Bracing 9 Scaffolding plates 10, 11 Mounting pins (bracing attachments)
12 struts 13 upper beam 14 middle beam 18, 19 straight pipe clamp (fastener)
20 First fixing pin (upper frame mounting tool)
21 Latching tool 22 Second fixing pin (middle rail mounting tool)

Claims (3)

2本一対の縦材と該両縦材の上端を結合する横材とにより門型に形成される建枠をお互いに対向するように起立させて該両建枠を筋交いで連結すると共に該両建枠の前記横材間に足場板を架設して形成される枠組足場において、新たに施工する最上段の足場の手摺として取り付けられる先行手摺であって、
前記各建枠の2本一対の縦材のうちのそれぞれいずれか一方の縦材に着脱可能に設けられる上下方向に長い支柱と、
該両支柱の上端部同士を連結する着脱可能な上桟と、
を備え、前記支柱の上下端部には前記縦材に該支柱を固定するための締結具が設けられ、前記支柱の上端部には前記上桟を取り付けるための上桟取付具が設けられ、前記支柱の下部であって前記支柱の下端部の締結部の上方には、前記建枠に前記筋交いを取り付けるための筋交い取付具に掛止可能な掛止具が設けられていることを特徴とする枠組足場用先行手摺。
A building frame formed in a gate shape is erected so as to face each other by a pair of two vertical members and a cross member that joins the upper ends of the two vertical members, and the two building frames are connected to each other while straddling. In the frame scaffolding formed by laying a scaffolding plate between the cross members of the building frame, a preceding handrail attached as a handrail of the uppermost scaffold to be newly constructed,
A vertically long support column that is detachably provided on any one of the two vertical members of each of the building frames.
A detachable upper bar that connects the upper ends of the two columns;
The upper and lower ends of the support are provided with fasteners for fixing the support to the vertical member, and the upper support for attaching the upper support is provided at the upper end of the support, A hook that can be hooked to a brace fitting for attaching the brace to the building frame is provided below the brace and above the fastening portion at the lower end of the brace. Leading handrail for framework scaffolding.
前記上桟より下方において前記両支柱同士を連結する着脱可能な中桟をさらに備え、
前記支柱には、前記上桟取付具と前記掛止具との間に前記中桟を取り付けるための中桟取付具が設けられていることを特徴とする請求項1に記載の枠組足場用先行手摺。
A detachable middle beam that connects the two columns below the upper beam is further provided,
The frame scaffolding preceding structure according to claim 1, wherein the strut is provided with a middle beam attachment for attaching the middle beam between the upper beam attachment and the latch. handrail.
建枠の縦材に支柱を固定するための締結具が上下端部に設けられ、上桟を取り付けるための上桟取付具が上端部に設けられ、該上桟取付具の下方に中桟を取り付けるための中桟取付具が設けられ、下部であって前記下端部の締結部の上方に建枠の筋交い取付具に掛止可能な掛止具が設けられる先行手摺を枠組足場に施工する方法であって、
前記建枠をお互いに対向するように起立させて該両建枠を筋交いで連結する工程と、
一方の建枠の一方の縦材の前記筋交い取付具に前記掛止具を掛止すると共に該一方の建枠の一方の縦材に一方の支柱の下端部の前記締結具を固定して該一方の建枠の縦材に前記一方の支柱を固定する工程と、
該一方の支柱の前記上桟取付具に前記上桟の一端部を取り付けると共に他方の支柱の前記上桟取付具に前記上桟の他端部を取り付けると共に、前記一方の支柱の前記中桟取付具に前記中桟の一端部を取り付けると共に前記他方の支柱の前記中桟取付具に前記中桟の他端部を取り付けた上で、他方の建枠の一方の縦材の前記筋交い取付具に前記掛止具を掛止すると共に該他方の建枠の一方の縦材に他方の支柱の下端部の前記締結具を固定して該他方の建枠の一方の縦材に前記他方の支柱を固定する工程と、
前記両建枠間に足場板を架設する工程と、
を備えていることを特徴とする枠組足場用先行手摺の施工方法。

Fasteners for fixing the pillars to the vertical members of the building frame are provided at the upper and lower ends, upper rail attachments for attaching the upper rails are provided at the upper ends, and the middle rails are provided below the upper rail attachments. A method for constructing a front handrail on a frame scaffolding, in which a middle rail attachment for attachment is provided, and a lower part is provided above the fastening portion at the lower end, and a hook that can be hooked on a brace fitting of the building frame is provided Because
Standing the building frames so as to face each other and connecting the two building frames bracingly;
The fastener is hooked to the bracing attachment of one vertical member of one building frame, and the fastener at the lower end of one column is fixed to one vertical member of the one building frame. Fixing the one strut to the vertical member of one building frame;
One end of the upper beam is attached to the upper beam fixture of the one column, the other end of the upper beam is mounted to the upper beam bracket of the other column, and the middle beam is attached to the one column. Attach one end of the middle rail to the fixture and attach the other end of the middle rail to the middle rail fixture of the other column, and then to the bracing fixture of one vertical member of the other building frame The fastener is fastened to the vertical member of the other building frame, and the fastener of the lower end of the other column is fixed to the vertical member of the other building frame, and the other column is attached to the vertical member of the other building frame. Fixing, and
A step of constructing a scaffolding plate between the two building frames;
The construction method of the leading handrail for frame scaffolds characterized by comprising.

JP2012171371A 2012-08-01 2012-08-01 Preceding handrail for framework scaffold and method of constructing the same Pending JP2014031623A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2012171371A JP2014031623A (en) 2012-08-01 2012-08-01 Preceding handrail for framework scaffold and method of constructing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2012171371A JP2014031623A (en) 2012-08-01 2012-08-01 Preceding handrail for framework scaffold and method of constructing the same

Publications (1)

Publication Number Publication Date
JP2014031623A true JP2014031623A (en) 2014-02-20

Family

ID=50281664

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2012171371A Pending JP2014031623A (en) 2012-08-01 2012-08-01 Preceding handrail for framework scaffold and method of constructing the same

Country Status (1)

Country Link
JP (1) JP2014031623A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020192812A1 (en) * 2019-03-25 2020-10-01 Wilhelm Layher Verwaltungs-Gmbh Railing device, namely a leading railing for a scaffold

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0450352Y2 (en) * 1986-11-26 1992-11-27
JPH0581442U (en) * 1992-04-06 1993-11-05 アサヒ産業株式会社 Sliding brace handrail frame for temporary scaffolding
JPH06307072A (en) * 1993-04-21 1994-11-01 Asahi Sangyo Kk Brace handrail frame for temporary scaffold
JPH0715938U (en) * 1993-08-25 1995-03-17 アサヒ産業株式会社 Pipe mounting bracket for scaffolding frame
JP2002356989A (en) * 2001-05-31 2002-12-13 Tatsuo Ono Device for attaching handrail to prefabricated scaffold
JP2004316157A (en) * 2003-04-14 2004-11-11 Nikko Co Ltd Handrail for prefabricated scaffolding
JP2005188275A (en) * 2003-12-02 2005-07-14 Sugikou:Kk Preceding handrail for temporary scaffold
JP2007224574A (en) * 2006-02-23 2007-09-06 Kaltech Co Ltd Handrail for prefabricated scaffold

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0450352Y2 (en) * 1986-11-26 1992-11-27
JPH0581442U (en) * 1992-04-06 1993-11-05 アサヒ産業株式会社 Sliding brace handrail frame for temporary scaffolding
JPH06307072A (en) * 1993-04-21 1994-11-01 Asahi Sangyo Kk Brace handrail frame for temporary scaffold
JPH0715938U (en) * 1993-08-25 1995-03-17 アサヒ産業株式会社 Pipe mounting bracket for scaffolding frame
JP2002356989A (en) * 2001-05-31 2002-12-13 Tatsuo Ono Device for attaching handrail to prefabricated scaffold
JP2004316157A (en) * 2003-04-14 2004-11-11 Nikko Co Ltd Handrail for prefabricated scaffolding
JP2005188275A (en) * 2003-12-02 2005-07-14 Sugikou:Kk Preceding handrail for temporary scaffold
JP2007224574A (en) * 2006-02-23 2007-09-06 Kaltech Co Ltd Handrail for prefabricated scaffold

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020192812A1 (en) * 2019-03-25 2020-10-01 Wilhelm Layher Verwaltungs-Gmbh Railing device, namely a leading railing for a scaffold

Similar Documents

Publication Publication Date Title
JP2012132157A (en) Preceding balustrade
JP3851105B2 (en) Construction method of temporary structure and handrail braiding used for this
JP2018138717A (en) Mounting structure of beam frame and beam frame receiving member and beam frame laid-across member used in the same
JP2014009453A (en) Temporary scaffold assembly jig and assembling method
JP4996916B2 (en) Installation method of wire mesh panel and handrail
KR20130007502U (en) Apparatus for supporting forms for monowall construction and bracket for supporting foothold
JP2002356989A (en) Device for attaching handrail to prefabricated scaffold
JP2014031623A (en) Preceding handrail for framework scaffold and method of constructing the same
JP3996102B2 (en) Safety handrail
JP2013213373A (en) Preceding handrail for tube and coupler scaffolding and construction method of the same
JP5809955B2 (en) Temporary scaffold
JP2007309044A (en) Prefabricated scaffolding
JP2009027771A (en) Frame for distribution panel
JP2019094769A (en) Load receiving stage and mounting method thereof
JP4183654B2 (en) Handrail support bracket, preceding handrail assembly set, frame scaffold
JP2013129961A (en) Temporary fixation method for steel staircase and pipe support for supporting steel staircase
JP2001288883A (en) Precedent handrail for prefabricated scaffolding
JP5469360B2 (en) Leading handrail
JP3187838U (en) Temporary scaffolding H steel coupling fixture and temporary scaffolding equipped with the H steel coupling fixture
JP5996890B2 (en) Scaffolding equipment
JP2017014803A (en) Scaffold construction method, and scaffold
JP2009162044A (en) Temporary hut structure
JP3175924U (en) Skirting brackets and skirting board couplers
AU2014215948A1 (en) Cantilever bracket
JP5745898B2 (en) A cane-type connecting material with a handrail frame and a temporary scaffold

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20150204

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20151014

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20151104

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20160308