JP2012025521A - Maintenance information management device and working machine - Google Patents

Maintenance information management device and working machine Download PDF

Info

Publication number
JP2012025521A
JP2012025521A JP2010164657A JP2010164657A JP2012025521A JP 2012025521 A JP2012025521 A JP 2012025521A JP 2010164657 A JP2010164657 A JP 2010164657A JP 2010164657 A JP2010164657 A JP 2010164657A JP 2012025521 A JP2012025521 A JP 2012025521A
Authority
JP
Japan
Prior art keywords
maintenance
unit
load
work
information
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010164657A
Other languages
Japanese (ja)
Other versions
JP5679529B2 (en
Inventor
Mamoru Konishi
守 小西
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Heavy Industries Construction Crane Co Ltd
Original Assignee
Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd filed Critical Hitachi Sumitomo Heavy Industries Construction Crane Co Ltd
Priority to JP2010164657A priority Critical patent/JP5679529B2/en
Publication of JP2012025521A publication Critical patent/JP2012025521A/en
Application granted granted Critical
Publication of JP5679529B2 publication Critical patent/JP5679529B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Operation Control Of Excavators (AREA)
  • Control And Safety Of Cranes (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a maintenance information management device that correctly computes information on maintenance time, and a working machine.SOLUTION: In the maintenance information management device, maintenance time is estimated based on information on energy of each unit, or information on energy transmitted by each unit. As compared with a case where information on the maintenance time of a consumable supply is derived based on a representative value representing the load of the consumable supply, the information on the maintenance time can be derived correctly. Accordingly, each unit can be maintained efficiently.

Description

本発明は、作業機械のメンテナンス情報の管理技術に関する。   The present invention relates to a maintenance information management technique for work machines.

作業機械の主要部品や消耗品のメンテナンスに関する情報を管理する装置が知られている。この装置では、特定の作業時に検出された、消耗品の負荷を代表させる代表値を累積して記憶し、記憶した代表値に基づいて、消耗品のメンテナンス時期に関する情報を導出している。この装置では、たとえば、クレーンにおける作業半径および吊り荷重の積であるモーメントと、作業時間とに基づくモーメント時間との累積値で、吊り作業またはブーム起伏作業によって負荷の掛かる油圧ホース類のメンテナンス時期に関する情報を提供する(特許文献1参照)。   Devices for managing information related to maintenance of main parts and consumables of work machines are known. In this apparatus, representative values representative of the load of consumables detected during a specific work are accumulated and stored, and information on the maintenance time of consumables is derived based on the stored representative values. In this device, for example, the cumulative value of the moment, which is the product of the work radius and the suspension load in the crane, and the moment time based on the operation time, the maintenance time of the hydraulic hoses that are loaded by the suspension operation or boom undulation operation Information is provided (see Patent Document 1).

特開2008−127129号公報JP 2008-127129 A

たとえば、上述した特許文献に記載の装置では、吊り荷がない場合には、負荷の代表値であるモーメントがゼロとなる。しかし、クレーンにはブームの自重があるので、ブームを起伏する圧油が流れる油圧ホース類には吊り荷がなくても圧力が作用している。そして、ブームの長さや重量がブーム毎に異なると、吊り荷がないときに当該油圧ホース類に作用する圧力が異なる。また、ブーム吊り荷の荷重および作業半径が同じであれば、負荷の代表値であるモーメントが同じ値となるが、ブームの重量が異なると、当該油圧ホース類に作用する圧力は、ブームの重量の差に起因して異なることとなる。したがって、消耗品の負荷を代表させる代表値に基づいて消耗品のメンテナンス時期に関する情報を導出すると、消耗品のメンテナンス時期に関する情報を正しく導出できないおそれがある。   For example, in the apparatus described in the above-described patent document, when there is no suspended load, the moment that is a representative value of the load becomes zero. However, since the crane has its own weight of the boom, pressure is applied to the hydraulic hoses through which the pressure oil for raising and lowering the boom flows even if there is no suspended load. And if the length and weight of a boom differ for every boom, when there is no suspended load, the pressure which acts on the said hydraulic hoses will differ. If the load of the boom load and the working radius are the same, the moment, which is a representative value of the load, will be the same value.However, if the weight of the boom is different, the pressure acting on the hydraulic hoses will be the weight of the boom. It will be different due to the difference. Therefore, if information on the maintenance time of consumables is derived based on the representative value that represents the load of the consumables, there is a possibility that information on the maintenance time of the consumables cannot be correctly derived.

(1) 請求項1の発明によるメンテナンス情報管理装置は、作業機械のメンテナンスに関する情報を管理する装置であって、作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての積算仕事量を演算する積算仕事量演算手段と、積算仕事量演算手段で演算した積算仕事量に基づいて、演算した積算仕事量に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とする。
(2) 請求項2の発明は、作業機械のメンテナンスに関する情報を管理する装置であって、作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての効率を演算する効率演算手段と、効率演算手段で演算した効率に基づいて、演算した効率に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とする。
(3) 請求項3の発明は、作業機械のメンテナンスに関する情報を管理する装置であって、作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての負荷の変動幅および負荷の印加回数を演算する負荷演算手段と、負荷演算手段で演算した負荷の変動幅および負荷の印加回数に基づいて、演算した負荷の変動幅および負荷の印加回数に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とする。
(4) 請求項4の発明による作業機械は、エンジンと、メインポンプと、油圧アクチュエータと、請求項1〜4のいずれか一項に記載のメンテナンス情報管理装置とを備えることを特徴とする。
(1) A maintenance information management device according to the invention of claim 1 is a device for managing information related to maintenance of a work machine, and is an integrated work for at least one device of an engine, a main pump, and a hydraulic actuator of the work machine. An integrated work amount calculating means for calculating the amount; and a calculating means for calculating information related to the maintenance time of the equipment related to the calculated integrated work amount based on the integrated work amount calculated by the integrated work amount calculating means. Features.
(2) The invention of claim 2 is an apparatus for managing information related to maintenance of a work machine, and is an efficiency calculation means for calculating the efficiency of at least one of the engine, main pump, and hydraulic actuator of the work machine. And calculating means for calculating information related to the maintenance timing of the equipment related to the calculated efficiency based on the efficiency calculated by the efficiency calculating means.
(3) The invention of claim 3 is an apparatus for managing information related to maintenance of a work machine, wherein the load fluctuation range and load load of at least one of the engine, main pump, and hydraulic actuator of the work machine are controlled. Based on the load calculation means for calculating the number of times of application, the load fluctuation range calculated by the load calculation means and the number of times of load application, information on the calculated load fluctuation range and the time of maintenance of the equipment related to the number of times of load application And calculating means for calculating.
(4) A work machine according to a fourth aspect of the invention includes an engine, a main pump, a hydraulic actuator, and the maintenance information management device according to any one of the first to fourth aspects.

本発明によれば、メンテナンスの時期に関する情報を正しく算出できる。   According to the present invention, it is possible to correctly calculate information relating to the time of maintenance.

本発明に係るメンテナンス情報管理装置が適用される作業機械の一例であるクレーンの外観側面図である。It is an appearance side view of a crane which is an example of a work machine to which a maintenance information management device concerning the present invention is applied. 巻上用油圧モータを駆動するための油圧回路を示す図である。It is a figure which shows the hydraulic circuit for driving the hoisting hydraulic motor. 本発明によるメンテナンス情報管理装置の構成を示す図である。It is a figure which shows the structure of the maintenance information management apparatus by this invention. クレーンの油圧システムでエネルギ変換がどのように行われているかを示す図である。It is a figure which shows how energy conversion is performed in the hydraulic system of a crane. メンテナンス情報の管理に関する処理の動作を示したフローチャートである。It is the flowchart which showed the operation | movement of the process regarding management of maintenance information. 第2の実施の形態のメンテナンス情報の管理に関する処理の動作を示したフローチャートである。It is the flowchart which showed the operation | movement of the process regarding management of the maintenance information of 2nd Embodiment. 第3の実施の形態のメンテナンス情報の管理に関する処理の動作を示したフローチャートである。It is the flowchart which showed the operation | movement of the process regarding management of the maintenance information of 3rd Embodiment.

−−−第1の実施の形態−−−
図1〜5を参照して、本発明によるメンテナンス情報管理装置および作業機械の第1の実施の形態を説明する。図1は、本実施の形態に係るメンテナンス情報管理装置が適用される作業機械の一例であるクレーンの外観側面図である。クレーンは、走行体1と、旋回輪2を介して走行体上に旋回可能に設けられた旋回体3と、旋回体3に回動可能に軸支されたブーム4とを有する。旋回体3には巻上ドラム5と起伏ドラム6が搭載されている。巻上ドラム5には巻上ロープ5aが巻回され、巻上ドラム5の駆動により巻上ロープ5aが巻き取りまたは繰り出され、フック7が昇降する。起伏ドラム6には起伏ロープ6aが巻回され、起伏ドラム6の駆動により起伏ロープ6aが巻き取りまたは繰り出され、ブーム4が起伏する。
--- First embodiment ---
A first embodiment of a maintenance information management device and a work machine according to the present invention will be described with reference to FIGS. FIG. 1 is an external side view of a crane that is an example of a work machine to which the maintenance information management device according to the present embodiment is applied. The crane includes a traveling body 1, a revolving body 3 that is turnably provided on the traveling body via a turning wheel 2, and a boom 4 that is pivotally supported by the revolving body 3. The revolving unit 3 is equipped with a hoisting drum 5 and a undulating drum 6. A hoisting rope 5 a is wound around the hoisting drum 5, and the hoisting rope 5 a is wound or fed out by driving of the hoisting drum 5, and the hook 7 moves up and down. A hoisting rope 6 a is wound around the hoisting drum 6, and the hoisting rope 6 a is wound or fed out by driving of the hoisting drum 6, and the boom 4 is raised and lowered.

巻上ドラム5は巻上用油圧モータにより駆動され、起伏ドラム6は起伏用油圧モータにより駆動される。これら油圧モータの回転は不図示のブレーキ装置によって制動可能である。巻上用油圧モータを駆動する油圧回路と、起伏用油圧モータを駆動する油圧回路とは構成が同様であるので、以下の説明では、巻上用油圧モータを駆動する油圧回路について説明し、起伏用油圧モータを駆動する油圧回路についての説明を省略する。図2は、巻上用油圧モータを駆動するための油圧回路を示す図である。   The hoisting drum 5 is driven by a hoisting hydraulic motor, and the hoisting drum 6 is driven by a hoisting hydraulic motor. The rotation of these hydraulic motors can be braked by a brake device (not shown). Since the hydraulic circuit that drives the hoisting hydraulic motor and the hydraulic circuit that drives the hoisting hydraulic motor have the same configuration, the following description will explain the hydraulic circuit that drives the hoisting hydraulic motor, A description of the hydraulic circuit that drives the hydraulic motor is omitted. FIG. 2 is a diagram showing a hydraulic circuit for driving the hoisting hydraulic motor.

図2に示すように、この油圧回路には、エンジン10で駆動されるメインポンプ11と、メインポンプ11から供給される圧油により回転する巻上用油圧モータ12と、この油圧モータ12で駆動される巻上ドラム5と、メインポンプ11から油圧モータ12への圧油の流れを制御する制御弁13と、巻き下げ時の戻り管路L1に設けられたカウンタバランス弁14とが設けられている。この油圧回路には、制御弁13を駆動するために操作される操作レバー15と、操作レバー15の操作量に応じたパイロット圧P16を発生させるパイロット弁16a,16bと、パイロット弁16a,16bに圧油を供給するパイロットポンプ17と、制御弁13の巻上側および巻下側パイロットポートへ供給されるパイロット圧P18,P19をそれぞれ制御する電磁比例弁18,19とが設けられている。   As shown in FIG. 2, the hydraulic circuit includes a main pump 11 driven by the engine 10, a hoisting hydraulic motor 12 that is rotated by pressure oil supplied from the main pump 11, and the hydraulic motor 12. A hoisting drum 5 to be driven, a control valve 13 for controlling the flow of pressure oil from the main pump 11 to the hydraulic motor 12, and a counter balance valve 14 provided in the return pipe L1 at the time of lowering. Yes. The hydraulic circuit includes an operation lever 15 that is operated to drive the control valve 13, a pilot valve 16a and 16b that generates a pilot pressure P16 corresponding to an operation amount of the operation lever 15, and a pilot valve 16a and 16b. A pilot pump 17 that supplies pressure oil and electromagnetic proportional valves 18 and 19 that respectively control pilot pressures P18 and P19 supplied to the upper and lower pilot ports of the control valve 13 are provided.

この油圧回路には、パイロット弁16aによって制御されるパイロット圧を検出する巻上リモコン圧力センサ31と、パイロット弁16bによって制御されるパイロット圧を検出する巻下リモコン圧力センサ32と、メインポンプ11の吐出圧力を検出するポンプ吐出圧力センサ33とが設けられている。また、この油圧回路には、巻き上げ時に油圧モータ12に供給される圧油の圧力検出する巻上圧力センサ(モータ保持圧力センサ)34と、巻き下げ時に油圧モータ12に供給される圧油の圧力検出する巻下圧力センサ35とが設けられている。なお、この油圧回路には、図2において図示しない各種センサが設けられているが、これらについては後述する。   The hydraulic circuit includes a hoisting remote control pressure sensor 31 that detects a pilot pressure controlled by the pilot valve 16 a, a lowering remote control pressure sensor 32 that detects a pilot pressure controlled by the pilot valve 16 b, and the main pump 11. A pump discharge pressure sensor 33 for detecting the discharge pressure is provided. The hydraulic circuit also includes a hoisting pressure sensor (motor holding pressure sensor) 34 that detects the pressure of the pressure oil supplied to the hydraulic motor 12 during winding, and the pressure of the pressure oil supplied to the hydraulic motor 12 during lowering. A lowering pressure sensor 35 for detection is provided. The hydraulic circuit is provided with various sensors (not shown in FIG. 2), which will be described later.

また、巻上ドラム5と油圧モータ12との間には図示しないウインチの減速機が設けられており、この油圧モータ12内部には、巻上ドラム5を停止させるための図示しないネガブレーキ装置が設けられている。ネガブレーキ装置は、ブレーキ解除のための圧油(ブレーキ解除圧油)が供給されてブレーキ解除圧が上昇するとブレーキを解除し、ブレーキ解除圧が低下するとブレーキを作動させる。ブレーキ解除圧油は、パイロットポンプ17から不図示のブレーキ解除電磁弁を介して供給される。   A winch speed reducer (not shown) is provided between the hoisting drum 5 and the hydraulic motor 12, and a negative brake device (not shown) for stopping the hoisting drum 5 is provided in the hydraulic motor 12. Is provided. The negative brake device releases the brake when pressure oil for releasing the brake (brake release pressure oil) is supplied and the brake release pressure increases, and operates the brake when the brake release pressure decreases. The brake release pressure oil is supplied from the pilot pump 17 via a brake release electromagnetic valve (not shown).

制御弁13は、巻上側および巻下側パイロットポートへ供給されるパイロット圧P18,P19に応じて切換量が制御される。パイロット圧P18,P19は、操作レバー15の操作量に応じたパイロット圧P16と、電磁比例弁18,19の減圧度とに応じて決定される。なお、詳細な説明は省略するが、電磁比例弁18,19の減圧度は、たとえば、巻上ドラム5(油圧モータ12)を緩停止させる際に、後述するコントローラ20からの制御信号によって制御される。   The switching amount of the control valve 13 is controlled according to the pilot pressures P18 and P19 supplied to the winding upper and lower pilot ports. The pilot pressures P18 and P19 are determined according to the pilot pressure P16 corresponding to the operation amount of the operation lever 15 and the degree of pressure reduction of the electromagnetic proportional valves 18 and 19. Although the detailed description is omitted, the degree of pressure reduction of the electromagnetic proportional valves 18 and 19 is controlled by a control signal from the controller 20 described later when, for example, the hoisting drum 5 (hydraulic motor 12) is gently stopped. The

図3は、本発明によるメンテナンス情報管理装置の構成を示す図である。コントローラ20は、クレーンの各部を制御する制御回路である。なお、図3では、メンテナンス情報管理装置に関する構成を図示し、その他のクレーン各部の制御に関する構成についての図示を省略する。コントローラ20には、巻上リモコン圧力センサ31と、巻下リモコン圧力センサ32と、ポンプ吐出圧力センサ33と、巻上圧力センサ34と、巻下圧力センサ35とが接続されている。また、コントローラ20には、メインポンプ11の吐出流量を検出するポンプ吐出流量センサ36と、油圧モータ12に流れる圧油の流量を検出するモータ流量センサ37とが接続されている。コントローラ20には、これら各センサからの信号が入力される。   FIG. 3 is a diagram showing the configuration of the maintenance information management apparatus according to the present invention. The controller 20 is a control circuit that controls each part of the crane. In addition, in FIG. 3, the structure regarding a maintenance information management apparatus is shown in figure, and illustration about the structure regarding control of the other parts of a crane is abbreviate | omitted. The controller 20 is connected to a hoisting remote control pressure sensor 31, a lowering remote control pressure sensor 32, a pump discharge pressure sensor 33, a hoisting pressure sensor 34, and a lowering pressure sensor 35. In addition, a pump discharge flow sensor 36 that detects the discharge flow rate of the main pump 11 and a motor flow sensor 37 that detects the flow rate of the pressure oil flowing through the hydraulic motor 12 are connected to the controller 20. The controller 20 receives signals from these sensors.

なお、クレーンには、エンジン10の制御を行う公知のECU27と、公知のモーメントリミッタ装置28とが設けられている。コントローラ20には、ECU27からのエンジン出力トルクおよびエンジン出力回転数の情報と、モーメントリミッタ装置28からのウインチ出力トルク、吊り荷重、および吊り荷移動速度の情報が入力される。   The crane is provided with a known ECU 27 for controlling the engine 10 and a known moment limiter device 28. Information on the engine output torque and engine output speed from the ECU 27 and information on the winch output torque, suspension load, and suspension load moving speed from the moment limiter device 28 are input to the controller 20.

コントローラ20は、電磁比例弁18,19、および不図示のブレーキ解除電磁弁に制御信号を出力して、これらの電磁弁を制御する。また、コントローラ20は、後述するように、メンテナンスに関する情報をオペレータに報知するよう、表示装置25にメンテナンス情報の表示を行わせるための制御信号を表示装置25に出力可能である。なお、表示装置25は、クレーンの各部の動作状態や、モーメントリミッタ装置の動作状態など各種情報を表示するための表示装置である。   The controller 20 outputs control signals to the electromagnetic proportional valves 18 and 19 and a brake release electromagnetic valve (not shown) to control these electromagnetic valves. Further, as will be described later, the controller 20 can output a control signal for causing the display device 25 to display maintenance information so as to notify the operator of information related to maintenance. The display device 25 is a display device for displaying various information such as the operation state of each part of the crane and the operation state of the moment limiter device.

このように構成されるクレーンでは、オペレータによって操作レバー15が巻き上げ方向に操作されると、巻上ドラム5が巻き上げ方向に回動されて、巻上ロープ5aが巻き取られ、フック7が上昇する。オペレータによって操作レバー15が巻き下げ方向に操作されると、巻上ドラム5が巻き下げ方向に回動されて、巻上ロープ5aが繰り出され、フック7が下降する。具体的には、クレーンの各部は次のように操作する。すなわち、オペレータによって操作レバー15が巻き上げ方向に操作されると、パイロット弁16aが操作レバー15の操作量に応じたパイロット圧P16でパイロット圧油を電磁比例弁18に供給する。このパイロット圧油は、電磁比例弁18を介して制御弁13の巻上側パイロットポートへ供給される。これにより、制御弁13のスプールが起動されて、油圧モータ12が巻上ドラム5を巻き上げ方向に回動させるように、メインポンプ11からの圧油が油圧モータ12へ供給される。   In the crane configured as described above, when the operation lever 15 is operated in the winding direction by the operator, the winding drum 5 is rotated in the winding direction, the winding rope 5a is wound, and the hook 7 is lifted. . When the operation lever 15 is operated in the lowering direction by the operator, the hoisting drum 5 is rotated in the lowering direction, the hoisting rope 5a is fed out, and the hook 7 is lowered. Specifically, each part of the crane is operated as follows. That is, when the operation lever 15 is operated in the winding direction by the operator, the pilot valve 16a supplies pilot pressure oil to the electromagnetic proportional valve 18 at a pilot pressure P16 corresponding to the operation amount of the operation lever 15. This pilot pressure oil is supplied to the hoisting pilot port of the control valve 13 via the electromagnetic proportional valve 18. As a result, the spool of the control valve 13 is activated, and the pressure oil from the main pump 11 is supplied to the hydraulic motor 12 so that the hydraulic motor 12 rotates the hoisting drum 5 in the winding direction.

これと略同期して、コントローラ20から不図示のブレーキ解除電磁弁へブレーキを解除するように制御信号が出力される。これにより、ブレーキ解除電磁弁を介してブレーキ解除圧油が不図示のネガブレーキ装置に供給され、ブレーキが解除される。このように、油圧モータ12の回動開始のタイミングに合わせてブレーキを解除することで、巻上ドラム5がスムーズに回転を始める。オペレータによって操作レバー15が巻き下げ方向に操作された場合も同様である。   A control signal is output so as to release the brake from the controller 20 to a brake release electromagnetic valve (not shown) substantially synchronously with this. As a result, the brake release pressure oil is supplied to the negative brake device (not shown) via the brake release electromagnetic valve, and the brake is released. Thus, the hoisting drum 5 starts to rotate smoothly by releasing the brake in accordance with the timing of starting the rotation of the hydraulic motor 12. The same applies when the operating lever 15 is operated in the lowering direction by the operator.

−−−本実施の形態の油圧システムにおけるエネルギ変換について−−−
図4は、クレーンの油圧システムでエネルギ変換がどのように行われているかを示す図である。エンジン10から出力される回転運動エネルギは、メインポンプ11で流体運動エネルギに変換される。メインポンプ11から出力される流体運動エネルギは、油圧モータ12で回転運動エネルギに変換される。油圧モータ12から出力される回転運動エネルギは、巻上ドラム5(ウインチ)で直線運動エネルギに変換される。巻上ドラム5(ウインチ)から出力される直線運動エネルギは、吊り荷の位置エネルギに変換される。
--- About energy conversion in the hydraulic system of this embodiment ---
FIG. 4 is a diagram showing how energy conversion is performed in the hydraulic system of the crane. The rotational kinetic energy output from the engine 10 is converted into fluid kinetic energy by the main pump 11. The fluid kinetic energy output from the main pump 11 is converted into rotational kinetic energy by the hydraulic motor 12. The rotational kinetic energy output from the hydraulic motor 12 is converted into linear kinetic energy by the hoisting drum 5 (winch). The linear kinetic energy output from the hoisting drum 5 (winch) is converted into the potential energy of the suspended load.

エンジン10から出力される回転運動エネルギの仕事率Leは、次式で表される。
Le=2×π×Te×ne/60000 [kW] ・・・(1)
ここで、Teはエンジン10の出力トルクであり、neはエンジン10の出力回転数である。
The work rate Le of the rotational kinetic energy output from the engine 10 is expressed by the following equation.
Le = 2 × π × Te × ne / 60000 [kW] (1)
Here, Te is the output torque of the engine 10, and ne is the output speed of the engine 10.

メインポンプ11から出力される流体運動エネルギの仕事率Lpは、次式で表される。
Lp=Pp×Qp/60 [kW] ・・・(2)
ここで、Ppはメインポンプ11の吐出圧力であり、Qpはメインポンプ11の吐出流量である。
The work rate Lp of the fluid kinetic energy output from the main pump 11 is expressed by the following equation.
Lp = Pp × Qp / 60 [kW] (2)
Here, Pp is the discharge pressure of the main pump 11, and Qp is the discharge flow rate of the main pump 11.

油圧モータ12に入力される流体運動エネルギの仕事率Lmは、次式で表される。
Lm=Pm×Qm/60 [kW] ・・・(3)
ここで、Pmは油圧モータ12の有効圧力であり、Qmは油圧モータ12の吸入流量である。
The work rate Lm of fluid kinetic energy input to the hydraulic motor 12 is expressed by the following equation.
Lm = Pm × Qm / 60 [kW] (3)
Here, Pm is the effective pressure of the hydraulic motor 12, and Qm is the suction flow rate of the hydraulic motor 12.

巻上ドラム5における回転運動エネルギの仕事率(ウインチの仕事率)Lwは、次式で表される。
Lw=2×π×Tw×nw/60000 [kW] ・・・(4)
ここで、Twはウインチの出力トルクであり、nwはウインチの出力回転数である。
The work rate of the rotational kinetic energy (winch work rate) Lw in the hoist drum 5 is expressed by the following equation.
Lw = 2 × π × Tw × nw / 60000 [kW] (4)
Here, Tw is the output torque of the winch, and nw is the output rotational speed of the winch.

吊り荷の移動に係る運動エネルギの仕事率Llは、次式で表される。
Ll=F×V [kW] ・・・(5)
ここで、Fは吊り荷重であり、Vは吊り荷の移動速度である。
The work rate Ll of the kinetic energy related to the movement of the suspended load is expressed by the following equation.
Ll = F × V [kW] (5)
Here, F is a suspended load, and V is a moving speed of the suspended load.

−−−メンテナンス情報の管理について−−−
従来技術による装置として、作業機械の主要部品や消耗品のメンテナンスに関する情報を管理する装置が知られている。この従来技術の装置では、特定の作業の作業時に検出された、消耗品の負荷を代表させる代表値を累積して記憶し、記憶した代表値に基づいて、消耗品のメンテナンス時期に関する情報を導出している。この装置では、たとえば、クレーンにおける作業半径および吊り荷重の積であるモーメントと、作業時間に基づくモーメント時間との累積値で、吊り作業またはブーム起伏作業によって負荷の掛かる油圧ホース類のメンテナンス時期に関する情報を提供する。
--- Maintenance information management ---
As an apparatus according to the prior art, an apparatus that manages information related to maintenance of main parts and consumables of work machines is known. In this prior art device, representative values representative of the load of consumables detected at the time of a specific work are accumulated and stored, and information on the maintenance time of consumables is derived based on the stored representative values. is doing. In this device, for example, information on the maintenance time of hydraulic hoses that are loaded by suspension work or boom undulation work, with the cumulative value of the moment that is the product of the work radius and suspension load in the crane and the moment time based on the work time I will provide a.

たとえば、上述した従来技術による装置では、吊り荷がない場合には、負荷の代表値であるモーメントがゼロとなる。しかし、クレーンにはブームの自重があるので、ブームを起伏する圧油が流れる油圧ホース類には吊り荷がなくても圧力が作用している。そして、ブームの長さや重量がブーム毎に異なることがあるため、吊り荷がないときに当該油圧ホース類に作用する圧力がブーム毎に異なることがある。また、ブーム吊り荷の荷重および作業半径が同じであれば、負荷の代表値であるモーメントが同じ値となるが、ブームの重量が異なると、当該油圧ホース類に作用する圧力は、ブームの重量の差に起因して異なることとなる。したがって、消耗品の負荷を代表させる代表値に基づいて消耗品のメンテナンス時期に関する情報を導出すると、消耗品のメンテナンス時期に関する情報を正しく導出できないおそれがある。   For example, in the above-described conventional device, when there is no suspended load, the moment that is a representative value of the load becomes zero. However, since the crane has its own weight of the boom, pressure is applied to the hydraulic hoses through which the pressure oil for raising and lowering the boom flows even if there is no suspended load. And since the length and weight of a boom may differ for every boom, when there is no suspended load, the pressure which acts on the said hydraulic hoses may differ for every boom. If the load of the boom load and the working radius are the same, the moment, which is a representative value of the load, will be the same value.However, if the weight of the boom is different, the pressure acting on the hydraulic hoses will be the weight of the boom. It will be different due to the difference. Therefore, if information on the maintenance time of consumables is derived based on the representative value that represents the load of the consumables, there is a possibility that information on the maintenance time of the consumables cannot be correctly derived.

クレーンを構成する各部(各機器、ユニット)は、作業に際してエネルギを伝達している。したがって、各ユニットが伝達するエネルギに関する情報に基づいてメンテナンス時期を推定することが考えられる。たとえば、各ユニットはエネルギを伝達すれば、エネルギの伝達分だけ仕事をしている。そのため、各ユニットは、伝達したエネルギに応じて消耗が進行しているものと考えられる。したがって、各ユニットで伝達したエネルギ(仕事量)を積算して管理すれば、各ユニットの消耗度合いを推定することができる。   Each part (each device and unit) constituting the crane transmits energy during work. Therefore, it is conceivable to estimate the maintenance time based on the information related to the energy transmitted by each unit. For example, if each unit transmits energy, the unit is working as much as energy is transmitted. Therefore, it is considered that each unit is exhausted according to the transmitted energy. Therefore, if the energy (work load) transmitted by each unit is integrated and managed, the degree of wear of each unit can be estimated.

そこで、本実施の形態では、クレーンを構成する各部(各機器、ユニット)毎に、各ユニットが行った仕事量の累積値(積算値)に基づいて、メンテナンスに関する情報を管理するようにしている。具体的には、コントローラ20が次の(1−1)〜(1−4)で述べるように、クレーンの各部のメンテナンスに関する情報を算出し、交換が必要な場合にはオペレータにその旨を報知するよう各部を制御する。コントローラ20は、次の(1−1)〜(1−4)で述べる処理を繰り返し実行する。なお、ここでユニットとは、たとえばエンジン10、メインポンプ11、油圧アクチュエータ(たとえば油圧モータ12)、巻上ドラム5や不図示の減速機を含むウインチ、巻き上げロープ5aやフック7といった吊り作業機などが挙げられる。   Therefore, in the present embodiment, for each part (each device, unit) constituting the crane, information related to maintenance is managed based on the accumulated value (integrated value) of the work performed by each unit. . Specifically, as described in (1-1) to (1-4) below, the controller 20 calculates information related to the maintenance of each part of the crane, and notifies the operator when replacement is necessary. Control each part to do. The controller 20 repeatedly executes the processes described in the following (1-1) to (1-4). Here, the units include, for example, the engine 10, the main pump 11, the hydraulic actuator (for example, the hydraulic motor 12), the winch including the hoisting drum 5 and a reduction gear (not shown), and the lifting work machine such as the hoisting rope 5a and the hook 7. Is mentioned.

(1−1) まず、コントローラ20は、各ユニットにおける仕事率を以下の(1−1−a)〜(1−1−e)のようにして算出する。
(1−1−a) エンジン10の仕事率は、上述した仕事率Leで表される。コントローラ20は、エンジン10の出力トルクTe、およびエンジン10の出力回転数neをECU27から取得して、上述した(1)式で仕事率Leを算出する。
(1-1) First, the controller 20 calculates the power in each unit as in the following (1-1-a) to (1-1-e).
(1-1-a) The power of the engine 10 is represented by the power Le described above. The controller 20 acquires the output torque Te of the engine 10 and the output rotational speed ne of the engine 10 from the ECU 27, and calculates the work rate Le by the above-described equation (1).

(1−1−b) メインポンプ11の仕事率は、上述した仕事率Lpで表される。コントローラ20は、メインポンプ11の吐出圧力Ppをポンプ吐出圧力センサ33から、メインポンプ11の吐出流量Qpをポンプ吐出流量センサ36からそれぞれ取得して、上述した(2)式で仕事率Lpを算出する。 (1-1-b) The power of the main pump 11 is represented by the power Lp described above. The controller 20 obtains the discharge pressure Pp of the main pump 11 from the pump discharge pressure sensor 33 and the discharge flow rate Qp of the main pump 11 from the pump discharge flow rate sensor 36, and calculates the work rate Lp by the above-described equation (2). To do.

(1−1−c) 油圧モータ12の仕事率は、上述した仕事率Lmで表される。コントローラ20は、油圧モータ12の上流および下流の圧力を巻上圧力センサ34および巻下圧力センサ35からそれぞれ取得し、その差圧を有効圧力Pmとして算出する。また、コントローラ20は、油圧モータ12の吸入流量Qmをモータ流量センサ37から取得して、上述した(3)式で仕事率Lmを算出する。 (1-1-c) The power of the hydraulic motor 12 is represented by the power Lm described above. The controller 20 acquires the upstream and downstream pressures of the hydraulic motor 12 from the hoisting pressure sensor 34 and the lowering pressure sensor 35, respectively, and calculates the differential pressure as the effective pressure Pm. Further, the controller 20 acquires the suction flow rate Qm of the hydraulic motor 12 from the motor flow rate sensor 37, and calculates the work rate Lm by the above-described equation (3).

(1−1−d) 巻上ドラム5の仕事率(ウインチの仕事率)は、上述した仕事率Lwで表される。コントローラ20は、ウインチの出力トルクTw、およびウインチの出力回転数neをモーメントリミッタ装置28から取得して、上述した(4)式で仕事率Lwを算出する。 (1-1-d) The work rate of the hoisting drum 5 (winch work rate) is represented by the above-described work rate Lw. The controller 20 acquires the output torque Tw of the winch and the output rotational speed ne of the winch from the moment limiter device 28, and calculates the work rate Lw by the above-described equation (4).

(1−1−e) 巻上ロープ5aやフック7の仕事率は、上述した仕事率Llで表される。コントローラ20は、吊り荷重F、および吊り荷の移動速度Vをモーメントリミッタ装置28から取得して、上述した(5)式で仕事率Llを算出する。 (1-1-e) The power of the hoisting rope 5a and the hook 7 is represented by the above-described power L1. The controller 20 acquires the suspension load F and the movement speed V of the suspension load from the moment limiter device 28, and calculates the power Ll by the above-described equation (5).

(1−2) 次に、コントローラ20は、上述のようにして算出した各仕事率に関してそれぞれ経過時間で積算して、各ユニットの仕事量を算出する。すなわち、コントローラ20は、上述した仕事率を、たとえば1秒毎に算出および積算することで仕事量(積算仕事量)[J]を算出して記憶する。 (1-2) Next, the controller 20 calculates the work amount of each unit by integrating the elapsed work time with respect to each work rate calculated as described above. That is, the controller 20 calculates and stores a work amount (integrated work amount) [J] by calculating and integrating the above-described work rate, for example, every second.

(1−3) コントローラ20では、各ユニットに設けられている、交換を促す基準となる仕事量である交換基準仕事量をあらかじめ記憶している。コントローラ20は、上述した(1−2)で算出した積算仕事量と、交換基準仕事量とを比較して、交換を促す必要があるか否かをユニット毎に判断する。 (1-3) The controller 20 stores in advance a replacement reference work amount, which is a work amount serving as a reference for prompting replacement, provided in each unit. The controller 20 compares the integrated work amount calculated in (1-2) described above with the replacement reference work amount, and determines for each unit whether or not it is necessary to prompt replacement.

(1−4) 上述した(1−3)において、交換を促す必要があると判断されたユニットについて、交換を促す旨の表示を表示装置25に表示させるよう、コントローラ20は各部を制御する。 (1-4) The controller 20 controls each unit so that the display device 25 displays a display for prompting replacement of the unit determined to be replaced in (1-3) described above.

−−−フローチャート−−−
図5は、上述したメンテナンス情報の管理に関する処理の動作を示したフローチャートである。本実施の形態のクレーンの不図示のイグニッションスイッチがオンされると、図5に示す処理を行うプログラムが起動され、コントローラ20で実行される。ステップS1において、上述した(1−1)で述べたように、各ユニットにおける仕事率を算出してステップS3へ進む。ステップS3において、ステップS1で算出した各ユニットの仕事率に基づいて、仕事量(積算仕事量)を算出して記憶し、ステップS5へ進む。
--- Flow chart ---
FIG. 5 is a flowchart showing the operation of the processing related to the management of maintenance information described above. When an ignition switch (not shown) of the crane of the present embodiment is turned on, a program for performing the processing shown in FIG. 5 is started and executed by the controller 20. In step S1, as described in (1-1) above, the power in each unit is calculated, and the process proceeds to step S3. In step S3, the work amount (integrated work amount) is calculated and stored based on the power of each unit calculated in step S1, and the process proceeds to step S5.

ステップS5において、ステップS3で算出した積算仕事量が、交換基準値、すなわちあらかじめ記憶している交換基準仕事量を超えたか否かを各ユニット毎に判断する。ステップS5が肯定判断されるとステップS7へ進み、ステップS3で算出した積算仕事量が、あらかじめ記憶している交換基準仕事量を超えたとステップS5で判断されたユニットに関して、メンテナンス情報として、交換を促す旨の表示を表示装置25に表示させてステップS9へ進む。   In step S5, it is determined for each unit whether or not the integrated work calculated in step S3 exceeds the exchange reference value, that is, the exchange reference work stored in advance. If an affirmative determination is made in step S5, the process proceeds to step S7, and replacement is performed as maintenance information for the unit determined in step S5 that the accumulated work calculated in step S3 exceeds the exchange reference work stored in advance. A display for prompting is displayed on the display device 25, and the process proceeds to step S9.

ステップS9において、メンテナンス情報の管理を終了するように指示されたか否かを判断する。具体的には、イグニッションスイッチがオフされるような場合である。   In step S9, it is determined whether or not an instruction to end management of maintenance information has been issued. Specifically, this is a case where the ignition switch is turned off.

ステップS9が否定判断されると、ステップS1へ戻る。ステップS9が肯定判断されると、本プログラムを終了する。ステップS5が否定判断されるとステップS9へ進む。   If a negative determination is made in step S9, the process returns to step S1. If a positive determination is made in step S9, the program is terminated. If a negative determination is made in step S5, the process proceeds to step S9.

第1の実施の形態のメンテナンス情報管理装置では、次の作用効果を奏する。
(1) 各ユニットのエネルギに関する情報、すなわち、各ユニットが伝達するエネルギに関する情報に基づいてメンテナンス時期を推定するように構成した。これにより、従来技術のように、消耗品の負荷を代表させる代表値に基づいて消耗品のメンテナンス時期に関する情報を導出する場合と比べて、メンテナンス時期に関する情報を正しく導出できるようになる。したがって、各ユニットのメンテナンスを効率的に行うことができるようになる。
The maintenance information management device according to the first embodiment has the following operational effects.
(1) The maintenance time is estimated based on information on energy of each unit, that is, information on energy transmitted by each unit. This makes it possible to correctly derive the information regarding the maintenance time as compared to the case where the information regarding the maintenance time of the consumable is derived based on the representative value representative of the load of the consumable as in the conventional technique. Therefore, maintenance of each unit can be performed efficiently.

(2) 各ユニットが伝達するエネルギに関する情報として、各ユニットが行った仕事量の積算値に基づいて、メンテナンスに関する情報を管理するように構成した。これにより、正確なメンテナンス時期に関する情報を容易に導出できる。 (2) As information about energy transmitted by each unit, information related to maintenance is managed based on an integrated value of the amount of work performed by each unit. Thereby, the information regarding the exact maintenance time can be derived easily.

−−−第2の実施の形態−−−
図6を参照して、本発明によるメンテナンス情報管理装置および作業機械の第2の実施の形態を説明する。以下の説明では、第1の実施の形態と同じ構成要素には同じ符号を付して相違点を主に説明する。特に説明しない点については、第1の実施の形態と同じである。本実施の形態では、主に、各ユニットが伝達するエネルギに関する情報として、各ユニットにおけるエネルギの伝達効率に基づいて、メンテナンスに関する情報を管理するように構成した点で、第1の実施の形態と異なる。
--- Second Embodiment ---
With reference to FIG. 6, a second embodiment of the maintenance information management apparatus and work machine according to the present invention will be described. In the following description, the same components as those in the first embodiment are denoted by the same reference numerals, and different points will be mainly described. Points that are not particularly described are the same as those in the first embodiment. In the present embodiment, the information regarding the maintenance is managed mainly based on the energy transmission efficiency in each unit as the information regarding the energy transmitted by each unit. Different.

各ユニットにおける入力側の仕事率と、出力側の仕事率との比を算出することで、各ユニットにおけるエネルギ伝達の効率(以下、単に伝達効率と呼ぶ)が求まる。各ユニットが仕事をすると、作動油の劣化や各部の摩耗等によって伝達効率が低下する。したがって、各ユニットの伝達効率を管理することで、メンテナンス時期を推定することが考えられる。   By calculating the ratio of the input-side power ratio and the output-side power ratio in each unit, the energy transmission efficiency (hereinafter simply referred to as transmission efficiency) in each unit can be obtained. When each unit works, transmission efficiency decreases due to deterioration of hydraulic oil, wear of each part, and the like. Therefore, it is conceivable to estimate the maintenance time by managing the transmission efficiency of each unit.

そこで、本実施の形態では、クレーンを構成する各部(ユニット)毎に、各ユニットの伝達効率に基づいて、メンテナンスに関する情報を管理するようにしている。具体的には、コントローラ20が次の(2−1)〜(2−4)で述べるように、クレーンの各部のメンテナンスに関する情報を算出し、交換が必要な場合にはオペレータにその旨を報知するよう各部を制御する。コントローラ20は、次の(2−1)〜(2−4)で述べる処理を繰り返し実行する。   Therefore, in the present embodiment, information related to maintenance is managed for each part (unit) constituting the crane based on the transmission efficiency of each unit. Specifically, as described in (2-1) to (2-4) below, the controller 20 calculates information related to maintenance of each part of the crane, and informs the operator when replacement is necessary. Control each part to do. The controller 20 repeatedly executes the processes described in the following (2-1) to (2-4).

(2−1) まず、コントローラ20は、各ユニットにおける仕事率を第1の実施の形態で述べた(1−1−a)〜(1−1−e)のようにして算出する。 (2-1) First, the controller 20 calculates the power in each unit as in (1-1-a) to (1-1-e) described in the first embodiment.

(2−2) 次に、コントローラ20は、上述のようにして算出した各仕事率に基づいて、各ユニットにおける伝達効率を以下の(2−2−a)〜(2−2−d)のようにして算出する。
(2−2−a) メインポンプ11の伝達効率ηpは、メインポンプ11の仕事率Lpをエンジン1の仕事率Leで除して求める。
ηp=Lp/Le ・・・(6)
(2-2) Next, the controller 20 determines the transmission efficiency in each unit based on each power calculated as described above in the following (2-2-a) to (2-2-d). Thus, the calculation is performed.
(2-2a) The transmission efficiency ηp of the main pump 11 is obtained by dividing the work rate Lp of the main pump 11 by the work rate Le of the engine 1.
ηp = Lp / Le (6)

(2−2−b) メインポンプ11から油圧モータ12までの配管における伝達効率ηhは、油圧モータ12に入力される流体運動エネルギの仕事率Lmをメインポンプ11の仕事率Lpで除して求める。
ηh=Lm/Lp ・・・(7)
(2-2b) The transmission efficiency ηh in the piping from the main pump 11 to the hydraulic motor 12 is obtained by dividing the work rate Lm of fluid kinetic energy input to the hydraulic motor 12 by the work rate Lp of the main pump 11. .
ηh = Lm / Lp (7)

(2−2−c) 油圧モータ12、減速機および巻上ドラム5における伝達効率(ウインチの伝達効率)ηwは、ウインチの仕事率Lwを油圧モータ12に入力される流体運動エネルギの仕事率Lmで除して求める。
ηw=Lw/Lm ・・・(8)
(2-2c) Transmission efficiency (winch transmission efficiency) ηw in the hydraulic motor 12, the speed reducer, and the hoisting drum 5 is a work rate Lm of fluid kinetic energy input to the hydraulic motor 12. Divide by to find.
ηw = Lw / Lm (8)

(2−2−d) 巻上ロープ5aやフック7における伝達効率(吊り作業機の伝達効率)ηlは、巻上ロープ5aやフック7の仕事率の仕事率(吊り荷の移動に係る運動エネルギの仕事率)Llをウインチの仕事率Lwで除して求める。
ηl=Ll/Lw ・・・(9)
(2-2d) The transmission efficiency of the hoisting rope 5a and the hook 7 (the transmission efficiency of the hoisting machine) ηl is the work rate of the hoisting rope 5a and the hook 7 (the kinetic energy related to the movement of the hoisting load) Obtained by dividing L1 by the work ratio Lw of the winch.
ηl = Ll / Lw (9)

(2−3) コントローラ20では、各ユニットに設けられている、交換を促す基準となる伝達効率である交換基準伝達効率をあらかじめ記憶している。コントローラ20は、上述した(2−2)で算出した伝達効率と、交換基準伝達効率とを比較して、交換を促す必要があるか否かをユニット毎に判断する。 (2-3) The controller 20 stores in advance exchange reference transmission efficiency that is provided in each unit and serves as a reference transmission efficiency for prompting replacement. The controller 20 compares the transmission efficiency calculated in the above (2-2) with the replacement reference transmission efficiency, and determines for each unit whether or not it is necessary to promote replacement.

(2−4) 上述した(2−3)において、交換を促す必要があると判断されたユニットについて、交換を促す旨の表示を表示装置25に表示させるよう、コントローラ20は各部を制御する。 (2-4) The controller 20 controls each unit so that the display device 25 displays a display for prompting replacement of the unit determined to be replaced in (2-3) described above.

−−−フローチャート−−−
図6は、上述した第2の実施の形態のメンテナンス情報の管理に関する処理の動作を示したフローチャートである。本実施の形態のクレーンの不図示のイグニッションスイッチがオンされると、図6に示す処理を行うプログラムが起動され、コントローラ20で実行される。ステップS1は、図5で説明した第1の実施の形態のフローチャートにおけるステップS1と同じである。ステップS1が実行されるとステップS13へ進む。ステップS13において、ステップS1で算出した各ユニットの仕事率に基づいて、各ユニットの伝達効率を算出して記憶し、ステップS15へ進む。
--- Flow chart ---
FIG. 6 is a flowchart showing an operation of processing related to management of maintenance information according to the second embodiment described above. When an ignition switch (not shown) of the crane of the present embodiment is turned on, a program for performing the processing shown in FIG. 6 is started and executed by the controller 20. Step S1 is the same as step S1 in the flowchart of the first embodiment described in FIG. When step S1 is executed, the process proceeds to step S13. In step S13, the transmission efficiency of each unit is calculated and stored based on the power of each unit calculated in step S1, and the process proceeds to step S15.

ステップS15において、ステップS13で算出した伝達効率が、交換基準値、すなわちあらかじめ記憶している交換基準伝達効率を下回ったか否かをユニット毎に判断する。ステップS15が肯定判断されるとステップS17へ進み、ステップS13で算出した伝達効率が、あらかじめ記憶している交換基準伝達効率を下回ったとステップS15で判断されたユニットに関して、メンテナンス情報として、交換を促す旨の表示を表示装置25に表示させてステップS9へ進む。   In step S15, it is determined for each unit whether or not the transmission efficiency calculated in step S13 is lower than the exchange reference value, that is, the exchange reference transmission efficiency stored in advance. If an affirmative determination is made in step S15, the process proceeds to step S17, and a replacement is urged as maintenance information for the unit determined in step S15 that the transmission efficiency calculated in step S13 is lower than the exchange reference transmission efficiency stored in advance. A display to that effect is displayed on the display device 25, and the process proceeds to step S9.

ステップS9は、図5で説明した第1の実施の形態のフローチャートにおけるステップS9と同じである。ステップS9が否定判断されると、ステップS1へ戻る。ステップS9が肯定判断されると、本プログラムを終了する。ステップS15が否定判断されるとステップS9へ進む。   Step S9 is the same as step S9 in the flowchart of the first embodiment described in FIG. If a negative determination is made in step S9, the process returns to step S1. If a positive determination is made in step S9, the program is terminated. If a negative determination is made in step S15, the process proceeds to step S9.

第2の実施の形態のメンテナンス情報管理装置では、第1の実施の形態の作用効果に加えて、次の作用効果を奏する。
(1) 各ユニットの現在の伝達効率を算出し、交換基準値と比較することによって、メンテナンスに関する情報を管理するように構成した。これにより、クレーンの各ユニットの実態(消耗度合い、伝達効率の低下)に基づいた正確なメンテナンス時期に関する情報を容易に導出できる。
The maintenance information management device according to the second embodiment has the following operational effects in addition to the operational effects of the first embodiment.
(1) The current transmission efficiency of each unit is calculated, and compared with the replacement reference value, information related to maintenance is managed. Thereby, the information regarding the exact maintenance time based on the actual condition (consumption level, reduction in transmission efficiency) of each unit of the crane can be easily derived.

−−−第3の実施の形態−−−
図7を参照して、本発明によるメンテナンス情報管理装置および作業機械の第3の実施の形態を説明する。以下の説明では、第1および第2の実施の形態と同じ構成要素には同じ符号を付して相違点を主に説明する。特に説明しない点については、第1または第2の実施の形態と同じである。本実施の形態では、主に、各ユニットが伝達するエネルギに関する情報として、各ユニットにおけるエネルギ負荷振幅およびエネルギ印加回数に基づいて、メンテナンスに関する情報を管理するように構成した点で、第1および第2の実施の形態と異なる。
--- Third embodiment ---
With reference to FIG. 7, a third embodiment of the maintenance information management apparatus and work machine according to the present invention will be described. In the following description, the same components as those in the first and second embodiments are denoted by the same reference numerals, and different points will be mainly described. Points that are not particularly described are the same as those in the first or second embodiment. In the present embodiment, the information on the maintenance is managed mainly based on the energy load amplitude and the number of times of energy application in each unit as the information on the energy transmitted by each unit. This is different from the second embodiment.

構造物の疲労による寿命推定方法として、負荷振幅と負荷回数の積から推定する方法が知られている。クレーンの各ユニットのように、エネルギを伝達する機器の場合、エネルギ負荷振幅と、エネルギを印加した回数とに基づいて、メンテナンス時期を推定することが考えられる。   As a method of estimating the life due to fatigue of a structure, a method of estimating from a product of a load amplitude and a load frequency is known. In the case of a device that transmits energy, such as each unit of a crane, it is conceivable to estimate the maintenance time based on the energy load amplitude and the number of times the energy is applied.

そこで、本実施の形態では、クレーンを構成する各部(ユニット)毎に、各ユニットにおけるエネルギ負荷振幅と、エネルギを印加した回数とに基づいて、メンテナンスに関する情報を管理するようにしている。具体的には、コントローラ20が次の(3−1)〜(3−6)で述べるように、クレーンの各部のメンテナンスに関する情報を算出し、交換が必要な場合にはオペレータにその旨を報知するよう各部を制御する。コントローラ20は、次の(3−1)〜(3−6)で述べる処理を繰り返し実行する。   Therefore, in the present embodiment, for each part (unit) constituting the crane, information related to maintenance is managed based on the energy load amplitude in each unit and the number of times energy is applied. Specifically, as described in (3-1) to (3-6) below, the controller 20 calculates information related to maintenance of each part of the crane, and informs the operator when replacement is necessary. Control each part to do. The controller 20 repeatedly executes the processes described in the following (3-1) to (3-6).

(3−1) まず、コントローラ20は、各ユニットにおける仕事率を第1の実施の形態で述べた(1−1−a)〜(1−1−e)のようにして算出する。
(3−2) コントローラ20は、巻上リモコン圧力センサ31、および巻下リモコン圧力センサ32で検出される圧力に基づいて、操作レバー15の操作状態を検出する。
(3-1) First, the controller 20 calculates the power in each unit as in (1-1-a) to (1-1-e) described in the first embodiment.
(3-2) The controller 20 detects the operation state of the operation lever 15 based on the pressure detected by the hoisting remote control pressure sensor 31 and the lowering remote control pressure sensor 32.

(3−3) コントローラ20は、上述した(3−1)、(3−2)の演算結果に基づいて、操作レバー15の操作の前後での各ユニットの仕事率の変化量、すなわちエネルギ負荷振幅を算出する。本実施の形態では、操作レバー15の操作の前の各ユニットの仕事率を、操作レバー15が操作されるたとえば1秒前の時点での仕事量とする。また、操作レバー15の操作の後の各ユニットの仕事率を、操作レバー15の操作完了のたとえば3秒後、すなわち、操作レバー15が操作されて、ある一定の操作量に略固定された状態からたとえば3秒後の時点での仕事量とする。 (3-3) The controller 20 determines the amount of change in the power of each unit before and after the operation of the operation lever 15 based on the calculation results of (3-1) and (3-2), that is, the energy load. Calculate the amplitude. In the present embodiment, the work rate of each unit before the operation of the operation lever 15 is set as the work amount at a time point, for example, one second before the operation lever 15 is operated. In addition, the power of each unit after the operation of the operation lever 15 is set to be approximately fixed to a certain operation amount, for example, 3 seconds after the operation of the operation lever 15 is completed, that is, the operation lever 15 is operated. For example, the amount of work at a time point after 3 seconds.

(3−4) コントローラ20は、操作レバー15の操作がなされる毎に、上述した(3−3)で算出したエネルギ負荷振幅を積算して記憶するとともに、操作回数、すなわち印加回数を1回加算して記憶する。 (3-4) Each time the operation lever 15 is operated, the controller 20 accumulates and stores the energy load amplitude calculated in (3-3) described above, and also sets the number of operations, that is, the number of applications once. Add and store.

(3−5) コントローラ20では、各ユニット毎に設けられている、交換を促す基準となる交換基準疲労閾値をあらかじめ記憶している。この交換基準疲労閾値は、積算(累積)したエネルギ負荷振幅と、エネルギを印加した回数との積である。コントローラ20は、上述した(3−4)で算出したエネルギ負荷振幅を積算した値および操作回数の合計値の積と、交換基準疲労閾値とを比較して、交換を促す必要があるか否かを各ユニット毎に判断する。 (3-5) The controller 20 stores in advance a replacement reference fatigue threshold that is provided for each unit and serves as a reference for prompting replacement. This replacement reference fatigue threshold is a product of the accumulated (accumulated) energy load amplitude and the number of times energy is applied. Whether or not the controller 20 needs to promote replacement by comparing the product of the value obtained by integrating the energy load amplitude calculated in (3-4) and the total number of operations with the replacement reference fatigue threshold. Is determined for each unit.

(3−6) 上述した(3−5)において、交換を促す必要があると判断されたユニットについて、交換を促す旨の表示を表示装置25に表示させるよう、コントローラ20は各部を制御する。 (3-6) The controller 20 controls each unit so that the display device 25 displays a display for prompting replacement of the unit determined to be replaced in (3-5) described above.

−−−フローチャート−−−
図7は、上述した第3の実施の形態のメンテナンス情報の管理に関する処理の動作を示したフローチャートである。本実施の形態のクレーンの不図示のイグニッションスイッチがオンされると、図7に示す処理を行うプログラムが起動され、コントローラ20で実行される。ステップS21において、上述した(3−1)で述べたように、各ユニットにおける仕事率を算出し、算出した仕事率を一時的に記憶してステップS23へ進む。ステップS23において、巻上リモコン圧力センサ31、および巻下リモコン圧力センサ32で検出される圧力に基づいて、操作レバー15が操作されたか否かを判断する。
--- Flow chart ---
FIG. 7 is a flowchart showing an operation of processing related to management of maintenance information according to the third embodiment described above. When an ignition switch (not shown) of the crane according to the present embodiment is turned on, a program for performing the process shown in FIG. 7 is started and executed by the controller 20. In step S21, as described in (3-1) above, the power in each unit is calculated, the calculated power is temporarily stored, and the process proceeds to step S23. In step S23, based on the pressure detected by the hoisting remote control pressure sensor 31 and the hoisting remote control pressure sensor 32, it is determined whether or not the operation lever 15 has been operated.

ステップS23が否定判断されると、ステップS21へ戻る。ステップS23が肯定判断されるとステップS25へ進み、巻上リモコン圧力センサ31、および巻下リモコン圧力センサ32で検出される圧力に基づいて、操作レバー15の操作が完了するまで、すなわち、操作レバー15が操作されて、ある一定の操作量に略固定されるまで待機する。ステップS25が肯定判断されるとステップS27へ進み、上述した(3−1)で述べたように、各ユニットにおける仕事率を算出してステップS29へ進む。ステップS29において、操作レバー15の操作が完了してから所定時間T(たとえば3秒)が経過したか否かを判断する。   If a negative determination is made in step S23, the process returns to step S21. If an affirmative determination is made in step S23, the process proceeds to step S25, and until the operation of the operation lever 15 is completed based on the pressure detected by the hoisting remote control pressure sensor 31 and the lowering remote control pressure sensor 32, that is, the operation lever It waits until 15 is operated and it is substantially fixed to a certain fixed operation amount. If an affirmative determination is made in step S25, the process proceeds to step S27, and as described in (3-1) above, the power in each unit is calculated, and the process proceeds to step S29. In step S29, it is determined whether or not a predetermined time T (for example, 3 seconds) has elapsed since the operation of the operation lever 15 was completed.

ステップS29が否定判断されるとステップS27へ戻る。ステップS29が肯定判断されるとステップS31へ進み、ステップS21で記憶している、操作レバー15が操作されるたとえば1秒前の時点での仕事量と、ステップS27で算出した、操作レバー15の操作が完了してから所定時間T(たとえば3秒)が経過後の仕事量との差をエネルギ負荷振幅として算出する。ステップS31が実行されるとステップS33へ進み、ステップS31で算出したエネルギ負荷振幅を積算して記憶するとともに、印加回数を1回加算して記憶してステップS35へ進む。   If a negative determination is made in step S29, the process returns to step S27. If an affirmative determination is made in step S29, the process proceeds to step S31. The work amount stored in step S21, for example, one second before the operation lever 15 is operated, and the operation lever 15 calculated in step S27. A difference from the work amount after a predetermined time T (for example, 3 seconds) has elapsed after the operation is completed is calculated as an energy load amplitude. When step S31 is executed, the process proceeds to step S33, and the energy load amplitude calculated in step S31 is accumulated and stored, and the number of times of application is added and stored, and the process proceeds to step S35.

ステップS35において、ステップS33で算出したエネルギ負荷振幅の積算値と印加回数とを乗じ、この値が交換基準疲労閾値を超えたか否かをユニット毎に判断する。ステップS35が肯定判断されるとステップS37へ進み、エネルギ負荷振幅の積算値と印加回数との積が、交換基準疲労閾値を超えたとステップS35で判断されたユニットに関して、メンテナンス情報として、交換を促す旨の表示を表示装置25に表示させてステップS9へ進む。   In step S35, the integrated value of the energy load amplitude calculated in step S33 is multiplied by the number of times of application, and it is determined for each unit whether this value exceeds the replacement reference fatigue threshold. If an affirmative determination is made in step S35, the process proceeds to step S37, and the unit determined in step S35 that the product of the integrated value of the energy load amplitude and the number of applications exceeds the replacement reference fatigue threshold is urged to be replaced as maintenance information. A display to that effect is displayed on the display device 25, and the process proceeds to step S9.

ステップS9は、図5で説明した第1の実施の形態のフローチャートにおけるステップS9と同じである。ステップS9が否定判断されると、ステップS21へ戻る。ステップS9が肯定判断されると、本プログラムを終了する。ステップS35が否定判断されるとステップS9へ進む。   Step S9 is the same as step S9 in the flowchart of the first embodiment described in FIG. If a negative determination is made in step S9, the process returns to step S21. If a positive determination is made in step S9, the program is terminated. If a negative determination is made in step S35, the process proceeds to step S9.

第3の実施の形態のメンテナンス情報管理装置では、第1および第2の実施の形態の作用効果に加えて、次の作用効果を奏する。
(1) 各ユニットにおけるエネルギ負荷振幅およびエネルギ印加回数に基づいて、メンテナンスに関する情報を管理するように構成した。これにより、クレーンの各ユニットのうち、疲労が問題となる部材や部位に関して、正確なメンテナンス時期に関する情報を容易に導出できる。
The maintenance information management device according to the third embodiment has the following operational effects in addition to the operational effects of the first and second embodiments.
(1) Information related to maintenance is managed based on the energy load amplitude and the number of times of energy application in each unit. Thereby, the information regarding the exact maintenance time can be derived | led-out easily regarding the member and site | part in which fatigue becomes a problem among each unit of a crane.

−−−変形例−−−
(1) 上述の説明では、メインポンプ11の吐出流量Qpをポンプ吐出流量センサ36で検出し、油圧モータ12の吸入流量Qmをモータ流量センサ37で検出するように構成したが、本発明はこれに限定されない。たとえば、メインポンプ11の吐出流量Qpや油圧モータ12の吸入流量Qmを、コントローラ20がメインポンプ11や油圧モータ12の傾転位置と回転数から算出するように構成してもよい。また、コントローラ20には、ECU27からのエンジン出力トルクおよびエンジン出力回転数の情報と、モーメントリミッタ装置28からのウインチ出力トルク、吊り荷重、および吊り荷移動速度の情報が入力されるように構成したが、本発明はこれに限定されない。たとえば、これらの情報を得るために設けられている各種センサ等からの検出素信号を直接コントローラ20で受信することで、これらの情報を得るように構成してもよい。
---- Modified example ---
(1) In the above description, the discharge flow rate Qp of the main pump 11 is detected by the pump discharge flow rate sensor 36, and the suction flow rate Qm of the hydraulic motor 12 is detected by the motor flow rate sensor 37. It is not limited to. For example, the controller 20 may be configured to calculate the discharge flow rate Qp of the main pump 11 and the suction flow rate Qm of the hydraulic motor 12 from the tilt position and the rotational speed of the main pump 11 or the hydraulic motor 12. Further, the controller 20 is configured to receive information on the engine output torque and engine output speed from the ECU 27 and information on the winch output torque, suspension load, and suspension load moving speed from the moment limiter device 28. However, the present invention is not limited to this. For example, the controller 20 may directly receive detection element signals from various sensors or the like provided for obtaining such information, thereby obtaining such information.

(2) 上述した第1の実施の形態では、各ユニットが行った仕事量の積算値として、各ユニットの出力した仕事量の積算値を用いているが、各ユニットへ入力された仕事量の積算値を用いてもよい。 (2) In the first embodiment described above, the integrated value of the work output from each unit is used as the integrated value of the work performed by each unit. An integrated value may be used.

(3) 上述した第2の実施の形態では、各ユニットの伝達効率を常時算出して、メンテナンスに関する情報を管理するように構成したが、本発明はこれに限定されない。たとえば、油圧回路が特定の状態となったときに各ユニットの伝達効率を算出するように構成してもよい。油圧回路の特定の状態として、たとえば、エンジン1の回転数が800rpmであり、かつ、メインポンプ11の吐出流量Qpが最大流量となり、かつ、油圧モータ12の傾転位置が最大傾転となったときとしてもよい。このように、油圧回路が特定の状態となったときに各ユニットの伝達効率を算出するように構成することで、各ユニットの伝達効率を常時算出しなくても済むので、コントローラ20の演算負荷を抑制できる。また、伝達効率を算出する際の油圧回路の条件が一定となるので、算出された伝達効率の精度、信頼性が向上し、メンテナンス時期に関する情報の信頼性が向上する。 (3) In the second embodiment described above, the transmission efficiency of each unit is always calculated and the information related to maintenance is managed. However, the present invention is not limited to this. For example, the transmission efficiency of each unit may be calculated when the hydraulic circuit is in a specific state. As a specific state of the hydraulic circuit, for example, the rotational speed of the engine 1 is 800 rpm, the discharge flow rate Qp of the main pump 11 is the maximum flow rate, and the tilt position of the hydraulic motor 12 is the maximum tilt. Sometimes it is good. As described above, the transmission efficiency of each unit is calculated when the hydraulic circuit is in a specific state, so that it is not necessary to always calculate the transmission efficiency of each unit. Can be suppressed. In addition, since the conditions of the hydraulic circuit when calculating the transmission efficiency are constant, the accuracy and reliability of the calculated transmission efficiency are improved, and the reliability of the information regarding the maintenance time is improved.

(4) 上述した第2の実施の形態において、1つのユニットに対する交換基準伝達効率を複数設けてもよい。たとえば、巻上ドラム5の巻き上げと巻き下げとで交換基準伝達効率を異なる値としてもよい。また、たとえば、作動油温度によって交換基準伝達効率が異なる値を採るようにしてもよい。このように、1つのユニットに対する交換基準伝達効率を複数設けることで、交換を促す必要があるか否かの判断精度が向上し、メンテナンス時期に関する情報の信頼性が向上する。 (4) In the second embodiment described above, a plurality of replacement reference transmission efficiencies for one unit may be provided. For example, the exchange reference transmission efficiency may be different depending on whether the hoisting drum 5 is wound or lowered. Further, for example, the exchange reference transmission efficiency may be different depending on the hydraulic oil temperature. In this way, by providing a plurality of replacement standard transmission efficiencies for one unit, the accuracy of determining whether or not it is necessary to promote replacement is improved, and the reliability of information regarding the maintenance time is improved.

(5) 上述した第2の実施の形態において、交換基準伝達効率として、各ユニットを事前にテストして得られた結果に基づく値を採用してもよく、あらかじめ計算によって求めた値を採用してもよい。 (5) In the second embodiment described above, as the exchange reference transmission efficiency, a value based on a result obtained by testing each unit in advance may be employed, or a value obtained by calculation in advance may be employed. May be.

(6) 上述した第3の実施の形態では、操作レバー15の操作の後の各ユニットの仕事率を、操作レバー15の操作完了のたとえば3秒後の時点での仕事量としたが、本発明はこれに限定されない。たとえば、操作レバー15の操作の後の各ユニットの仕事率を、操作レバー15の操作が完了してからたとえば3秒の間、すなわち、操作レバー15が操作されて、ある一定の操作量に略固定された状態となってからたとえば3秒の間の仕事量の最大値としてもよい。
(7) 上述した各実施の形態および変形例は、それぞれ組み合わせてもよい。
(6) In the above-described third embodiment, the work rate of each unit after the operation of the operation lever 15 is the work amount at the time of, for example, 3 seconds after the operation of the operation lever 15 is completed. The invention is not limited to this. For example, the power of each unit after the operation of the operation lever 15 is reduced to a certain amount of operation, for example, for 3 seconds after the operation of the operation lever 15 is completed, that is, when the operation lever 15 is operated. For example, it may be the maximum value of the work amount for 3 seconds after the state is fixed.
(7) You may combine each embodiment and modification which were mentioned above, respectively.

なお、本発明は、上述した実施の形態のものに何ら限定されず、作業機械のメンテナンスに関する情報を管理する装置であって、作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての積算仕事量を演算する積算仕事量演算手段と、積算仕事量演算手段で演算した積算仕事量に基づいて、演算した積算仕事量に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とする各種構造のメンテナンス情報管理装置、および、このメンテナンス情報管理装置を備える各種構造の作業機械を含むものである。   Note that the present invention is not limited to the above-described embodiment, and is an apparatus that manages information related to maintenance of the work machine, and is at least one device of an engine, a main pump, and a hydraulic actuator of the work machine. An integrated work amount calculating means for calculating the integrated work amount, and a calculating means for calculating information relating to the time of maintenance of the equipment related to the calculated integrated work amount based on the integrated work amount calculated by the integrated work amount calculating means; A maintenance information management device having various structures, and a work machine having various structures including the maintenance information management device.

5 巻上ドラム 6 起伏ドラム
7 フック 10 エンジン
11 メインポンプ 12 巻上用油圧モータ
20 コントローラ 25 表示装置
27 ECU 28 モーメントリミッタ装置
31 巻上リモコン圧力センサ 32 巻下リモコン圧力センサ
33 ポンプ吐出圧力センサ 34 巻上圧力センサ
35 巻下圧力センサ 36 ポンプ吐出流量センサ
37 モータ流量センサ
5 hoisting drum 6 hoisting drum 7 hook 10 engine 11 main pump 12 hoisting hydraulic motor 20 controller 25 display device 27 ECU 28 moment limiter device 31 hoisting remote control pressure sensor 32 lowering remote control pressure sensor 33 pump discharge pressure sensor 34 winding Upper pressure sensor 35 Lowering pressure sensor 36 Pump discharge flow sensor 37 Motor flow sensor

Claims (4)

作業機械のメンテナンスに関する情報を管理する装置であって、
前記作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての積算仕事量を演算する積算仕事量演算手段と、
前記積算仕事量演算手段で演算した積算仕事量に基づいて、演算した積算仕事量に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とするメンテナンス情報管理装置。
A device for managing information related to maintenance of a work machine,
An integrated work amount calculating means for calculating an integrated work amount for at least one of the engine, the main pump, and the hydraulic actuator of the work machine;
A maintenance information management apparatus comprising: a calculation unit that calculates information related to the maintenance time of the device related to the calculated integrated work amount based on the integrated work amount calculated by the integrated work amount calculating unit.
作業機械のメンテナンスに関する情報を管理する装置であって、
前記作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての効率を演算する効率演算手段と、
前記効率演算手段で演算した効率に基づいて、演算した効率に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とするメンテナンス情報管理装置。
A device for managing information related to maintenance of a work machine,
Efficiency calculation means for calculating the efficiency of at least one of the engine, main pump, and hydraulic actuator of the work machine;
A maintenance information management apparatus comprising: a calculation unit that calculates information related to the maintenance timing of the device related to the calculated efficiency based on the efficiency calculated by the efficiency calculation unit.
作業機械のメンテナンスに関する情報を管理する装置であって、
前記作業機械のエンジン、メインポンプ、油圧アクチュエータのうちの少なくとも1つの機器についての負荷の変動幅および負荷の印加回数を演算する負荷演算手段と、
前記負荷演算手段で演算した負荷の変動幅および負荷の印加回数に基づいて、演算した負荷の変動幅および負荷の印加回数に係る機器のメンテナンスの時期に関する情報を算出する算出手段とを備えることを特徴とするメンテナンス情報管理装置。
A device for managing information related to maintenance of a work machine,
Load calculation means for calculating a load fluctuation range and the number of times of application of the load for at least one of the engine, main pump, and hydraulic actuator of the work machine;
Calculation means for calculating information related to the time of maintenance of the equipment related to the calculated load fluctuation range and the load application frequency based on the load fluctuation range and the load application frequency calculated by the load calculation means. A featured maintenance information management device.
エンジンと、
メインポンプと、
油圧アクチュエータと、
請求項1〜4のいずれか一項に記載のメンテナンス情報管理装置とを備えることを特徴とする作業機械。
Engine,
The main pump,
A hydraulic actuator;
A work machine comprising: the maintenance information management device according to claim 1.
JP2010164657A 2010-07-22 2010-07-22 Maintenance information management device and work machine Active JP5679529B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010164657A JP5679529B2 (en) 2010-07-22 2010-07-22 Maintenance information management device and work machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010164657A JP5679529B2 (en) 2010-07-22 2010-07-22 Maintenance information management device and work machine

Publications (2)

Publication Number Publication Date
JP2012025521A true JP2012025521A (en) 2012-02-09
JP5679529B2 JP5679529B2 (en) 2015-03-04

Family

ID=45778945

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010164657A Active JP5679529B2 (en) 2010-07-22 2010-07-22 Maintenance information management device and work machine

Country Status (1)

Country Link
JP (1) JP5679529B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018144992A (en) * 2017-03-08 2018-09-20 三菱重工機械システム株式会社 Deck crane system
JP2019113140A (en) * 2017-12-25 2019-07-11 ナブテスコ株式会社 Actuator system
JP2020094416A (en) * 2018-12-13 2020-06-18 酒井重工業株式会社 Failure diagnostic device and failure diagnostic method of road surface cutting vehicle
US20210010581A1 (en) * 2018-03-20 2021-01-14 Isuzu Motors Limited Device for Estimating Degree of Fatigue of Motive Force Transmitting Component, and Method for Estimating Degree of Fatigue of Motive Force Transmitting Component

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01219222A (en) * 1988-02-25 1989-09-01 Komatsu Ltd Life selecting device for hydraulic excavator
JPH0449195A (en) * 1990-06-18 1992-02-18 Nkk Corp Device for diagnosing wire rope for crane
JPH04353131A (en) * 1991-05-30 1992-12-08 Komatsu Ltd Damage amount detecting device for hydraulic power shovel
JPH0610748A (en) * 1992-06-30 1994-01-18 Komatsu Ltd Engine life prediction system
JPH08333777A (en) * 1995-06-06 1996-12-17 Sumitomo Constr Mach Co Ltd Performance limit display device for hydraulic equipment in construction machine
JPH11324781A (en) * 1998-05-15 1999-11-26 Niigata Eng Co Ltd Method of determining part replacing time of prime mover, and prime mover equipment
JP2005009431A (en) * 2003-06-20 2005-01-13 Hitachi Constr Mach Co Ltd Hydraulic drive system of working machine
JP2008127129A (en) * 2006-11-17 2008-06-05 Kobelco Cranes Co Ltd Maintenance information management device for construction machine and method of managing maintenance information for construction machine

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01219222A (en) * 1988-02-25 1989-09-01 Komatsu Ltd Life selecting device for hydraulic excavator
JPH0449195A (en) * 1990-06-18 1992-02-18 Nkk Corp Device for diagnosing wire rope for crane
JPH04353131A (en) * 1991-05-30 1992-12-08 Komatsu Ltd Damage amount detecting device for hydraulic power shovel
JPH0610748A (en) * 1992-06-30 1994-01-18 Komatsu Ltd Engine life prediction system
JPH08333777A (en) * 1995-06-06 1996-12-17 Sumitomo Constr Mach Co Ltd Performance limit display device for hydraulic equipment in construction machine
JPH11324781A (en) * 1998-05-15 1999-11-26 Niigata Eng Co Ltd Method of determining part replacing time of prime mover, and prime mover equipment
JP2005009431A (en) * 2003-06-20 2005-01-13 Hitachi Constr Mach Co Ltd Hydraulic drive system of working machine
JP2008127129A (en) * 2006-11-17 2008-06-05 Kobelco Cranes Co Ltd Maintenance information management device for construction machine and method of managing maintenance information for construction machine

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2018144992A (en) * 2017-03-08 2018-09-20 三菱重工機械システム株式会社 Deck crane system
JP2019113140A (en) * 2017-12-25 2019-07-11 ナブテスコ株式会社 Actuator system
US20210010581A1 (en) * 2018-03-20 2021-01-14 Isuzu Motors Limited Device for Estimating Degree of Fatigue of Motive Force Transmitting Component, and Method for Estimating Degree of Fatigue of Motive Force Transmitting Component
JP2020094416A (en) * 2018-12-13 2020-06-18 酒井重工業株式会社 Failure diagnostic device and failure diagnostic method of road surface cutting vehicle
JP7074654B2 (en) 2018-12-13 2022-05-24 酒井重工業株式会社 Failure diagnosis device and failure diagnosis method for road cutting vehicles

Also Published As

Publication number Publication date
JP5679529B2 (en) 2015-03-04

Similar Documents

Publication Publication Date Title
JP5679529B2 (en) Maintenance information management device and work machine
JP5669264B2 (en) Hydraulic control device for work
JP7433100B2 (en) Hydraulic drive system for working machines
JP2009126613A (en) Piling machine
JP5722185B2 (en) Hydraulic device
JP2019055880A (en) Winch control device
JP2015078714A5 (en)
JP2013127309A (en) Electronic hill hold control of hydrostatic transmission
JP6246702B2 (en) Crane hydraulic circuit
JP2015078713A5 (en)
CN103508353B (en) The anti-fall control system of elevator secondary lifting and method
JP5511009B2 (en) Control device for variable displacement hydraulic motor
JP2012001304A (en) Rope speed control device, winch device and working machine
JP2009155022A (en) Control device for hydraulic winch
JP5156469B2 (en) Winch equipment
JP2005263470A (en) Winch speed control device, and winch speed control method
JP6753427B2 (en) Winch device and crane equipped with it
JPH11335086A (en) Hydraulic hoist device and work machine mounting the hydraulic host device
JP2008044700A (en) Abnormality detection device and abnormality detection method for winch circuit
JP6479572B2 (en) Swivel control device and work machine
JP7443120B2 (en) crane
JPH11278795A (en) Hydraulic winding device and working machine loaded with its hydraulic winding device
JPH0725591A (en) Drive control device of hydraulic winch
JP6067287B2 (en) Pile driver
JP2020147421A (en) Construction machine and control method of construction machine

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120913

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131002

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20131008

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20131209

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20140617

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140917

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20141029

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20141224

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20141229

R150 Certificate of patent or registration of utility model

Ref document number: 5679529

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350