JP2011012539A - Hybrid anchor and anchor method - Google Patents

Hybrid anchor and anchor method Download PDF

Info

Publication number
JP2011012539A
JP2011012539A JP2010127248A JP2010127248A JP2011012539A JP 2011012539 A JP2011012539 A JP 2011012539A JP 2010127248 A JP2010127248 A JP 2010127248A JP 2010127248 A JP2010127248 A JP 2010127248A JP 2011012539 A JP2011012539 A JP 2011012539A
Authority
JP
Japan
Prior art keywords
anchor
pipe body
hole
rock layer
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2010127248A
Other languages
Japanese (ja)
Other versions
JP5542529B2 (en
Inventor
Kazuhiro Koseki
和廣 小関
Kengo Yamaguchi
健悟 山口
Hiroshi Hashiguchi
寛史 橋口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tokyo Seiko Co Ltd
Original Assignee
Tokyo Seiko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Seiko Co Ltd filed Critical Tokyo Seiko Co Ltd
Priority to JP2010127248A priority Critical patent/JP5542529B2/en
Publication of JP2011012539A publication Critical patent/JP2011012539A/en
Application granted granted Critical
Publication of JP5542529B2 publication Critical patent/JP5542529B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an anchor of excellent workability, which maintains a stable proof-stress in a simple structure, and an anchor method therefor.SOLUTION: This anchor is installed to support a string represented by a rope on a normal face having a rock layer and a surface soil layer covering the rock layer, the anchor includes an anchor rod embedded into the rock layer, and a pipe body having a string attaching part in an upper part, and arranged in the surface soil layer, to make a lower end reach the rock layer, and the pipe body is connected inclination-movably to the anchor rod via a spherical washer.

Description

本発明は主として雪崩や落石などのおそれがある法面等に使用されるのに好適なハイブリッドアンカーおよびアンカー工法に関する。 The present invention relates to a hybrid anchor and an anchor method suitable for use mainly on slopes where there is a risk of avalanches or falling rocks.

雪崩や落石の防止施設として、雪崩や落石の恐れのある法面に柵体(金網張りしたものを含む)や三角錐状の枠体を設置し、これら柵体あるいは枠体を法面の上方部位に固定したアンカーから吊りロープ(ケーブル)によって吊持した施設や、雪崩や落石の恐れのある法面にポケットを形成するように張ったポケット式ロックネットのロープや覆式ロックネットのロープを、法面の上方部位に固定したアンカーで吊持した施設や、法面に沿って浮石押さえロープを敷設し、そのロープの上部をアンカーで吊持した施設などが知られている。 As a facility to prevent avalanches and falling rocks, fences (including wire mesh) and triangular pyramid frames are installed on slopes where avalanches and rockfalls may occur, and these fences or frames are located above the slopes. A facility that is suspended from an anchor fixed to the site by a suspension rope (cable), or a pocket-type lock net rope or a cover-type lock net rope that is stretched to form a pocket on a slope where there is a risk of avalanche or falling rock There are known facilities that are suspended by anchors fixed above the slope, and facilities in which a floating rock holding rope is laid along the slope and the top of the rope is suspended by anchors.

上記施設のアンカーには、地盤が粘土や土砂等の土質系の場合のものとして、長尺の鋼製パイプを土中に打設機で打ち込み、パイプの土圧に対する耐力で定着されるパイプアンカーがあるが、地盤が岩層の場合には、岩に直接掘削孔を形成し、この掘削孔にアンカーロッドを挿入するとともにモルタル、セメント等の凝固剤を流し込み、凝固剤を介して岩とアンカーロッドが一体化することで定着する岩用アンカーが用いられている。 As the anchor of the above facilities, a pipe anchor that is fixed with the resistance to the earth pressure of a long steel pipe is driven into the soil with a driving machine, assuming that the ground is a soil type such as clay or earth and sand However, when the ground is a rock formation, a drilling hole is directly formed in the rock, an anchor rod is inserted into the drilling hole, and a coagulant such as mortar and cement is poured into the rock. Rock anchors are used, which are fixed when they are integrated.

しかし、地盤の表層が土砂等の堆積物で覆われ、その表層の下が岩層である場合には、上記のような岩用アンカーではアンカーロッド径が小径のため表層土圧に対する耐力は小さく、そのためアンカーの上端に吊りロープの端末を支持させた状態で法面に略平行方向の引張り荷重が加わると、荷重によりアンカー頭部が荷重方向である谷側に岩層と表土層の境界を起点として傾き(曲がり)やすく、水平耐力の低下を招く問題があった。 However, when the surface layer of the ground is covered with sediments such as earth and sand, and under the surface layer is a rock layer, the rock anchor as described above has a small anchor rod diameter, so the resistance to surface soil pressure is small, For this reason, when a tensile load in a direction parallel to the slope is applied with the end of the suspension rope supported at the upper end of the anchor, the anchor head starts from the boundary between the rock layer and the topsoil layer on the valley side where the load direction is the load. There was a problem that it was easy to tilt (bend) and caused a decline in horizontal strength.

この対策として、アンカー箇所の岩層まで法面の表土を取り除き、岩に削孔機で穿孔し、掘削孔にアンカーロッドを挿入するとともにモルタル、セメント等の凝固剤を流し込み、モルタル、セメント等が凝固した後、鋼製シャフトに複数の羽根を固定した抵抗部体をアンカーロッドの上端部にスリーブを介して締結一体化したアンカー体とし、取り除いた表土を埋め戻す工程を採用したアンカーが提案されている。
これによれば、アンカーの上端に吊りロープの端末を支持させた状態で法面に略平行の引張り荷重が作用下ときに、抵抗部体の複数の羽根が埋め戻した表土の土圧抵抗となり、荷重方向である前面側への傾きを緩和することが可能であるとされている。
To prevent this, remove the topsoil from the slope to the rock layer at the anchor location, drill the rock with a drilling machine, insert the anchor rod into the drilling hole, and pour a coagulant such as mortar and cement into the mortar and cement. After that, a resistance part body in which a plurality of blades are fixed to a steel shaft is used as an anchor body that is fastened and integrated with an upper end portion of an anchor rod via a sleeve, and an anchor that employs a process of backfilling the removed top soil has been proposed. Yes.
According to this, when a tensile load substantially parallel to the slope is applied with the end of the suspension rope supported at the upper end of the anchor, the earth pressure resistance of the topsoil is filled with the plurality of blades of the resistance part. It is said that it is possible to alleviate the inclination toward the front side that is the load direction.

しかし、このアンカーでは、アンカー箇所の岩層まで法面の表土を取り除くので、落石等が発生するような斜面で除去した表土の撤去場所を確保することは非常な困難を伴う。
また、確実に耐力が期待できる岩層まで表土を除去し、埋め戻すことは施工にかなりの時間とコストが掛かり、かつ、除去した表土を埋め戻しするため表土の土圧は低下し、羽根の十分な土圧抵抗が期待できない等の問題がある。
さらに、岩層と表土層の境界を起点とした傾きは剪断破壊の起点となるなどの問題がある。
However, since this anchor removes the topsoil of the slope to the rock layer at the anchor point, it is very difficult to secure a place to remove the topsoil removed on the slope where rockfalls and the like occur.
In addition, removing and refilling the topsoil to the rock layer where the yield strength can be reliably expected takes a considerable amount of time and cost for the construction, and because the topsoil removed is backfilled, the earth pressure of the topsoil is reduced, and the blades are sufficient. There is a problem such as that the earth pressure resistance cannot be expected.
Furthermore, there is a problem that the slope starting from the boundary between the rock layer and topsoil layer becomes the starting point of shear failure.

特開2008−127956号公報JP 2008-127756 A

本発明は前記のような問題点を解消するためになされたもので、その第1の目的は、簡単な構造で安定した耐力を維持し、外力が作用した場合にアンカー本体に曲げ応力が伝達しないようにすることができるハイブリッドアンカーと、かかる特徴を有するアンカーを法面おいて比較的簡易に施工することができるアンカー工法を提供することにある。 The present invention has been made to solve the above-described problems. The first object of the present invention is to maintain a stable proof stress with a simple structure, and to transmit bending stress to the anchor body when an external force is applied. It is an object of the present invention to provide a hybrid anchor that can be avoided and an anchor method that can relatively easily construct an anchor having such characteristics on the slope.

また、本発明の第2の目的は、土質条件や設置状態のいかんを問わず、異常に大きな外力が作用したときに上記特徴を発揮することができるハイブリッドアンカーを提供することにある。 A second object of the present invention is to provide a hybrid anchor capable of exhibiting the above characteristics when an abnormally large external force is applied regardless of soil conditions or installation conditions.

上記第1の目的を達成するため本発明のハイブリッドアンカーは、岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体は前記アンカーロッドに球面座金を介して連結されていることを特徴としている。(請求項1) In order to achieve the first object, the hybrid anchor of the present invention is an anchor installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the upper part of the rock layer. An anchor includes an anchor rod embedded in the rock layer, and a pipe body disposed in the topsoil layer so that a lower end thereof reaches the rock layer, and the pipe body includes the anchor rod. Are connected to each other through a spherical washer. (Claim 1)

また、上記第1の目的を達成するため本発明のアンカー工法は、岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカー工法であって、アンカーとしてアンカーロッドとパイプ体を用い、法面にパイプ体を挿入する孔を岩層に一部が達するまで穿孔する工程と、前記孔に保孔管を挿入する工程と、アンカーロッドを挿入するためのアンカー用孔を前記保孔管を貫いて岩層に穿孔する工程と、保孔管を撤去しパイプ体を前記孔に挿入したうえで、パイプ体を通して前記アンカー用孔内に凝固剤を挿入する工程と、アンカーロッドをアンカー用孔に挿入する工程と、パイプ体内のアンカーロッド上端部に球面座金を挿通してパイプ体底の球面座に接触するようにナットで連結する工程とを有することを特徴としている。(請求項3) In order to achieve the first object, the anchor method of the present invention is an anchor method that is installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the top of the rock layer. And using an anchor rod and a pipe body as anchors, drilling a hole for inserting the pipe body on the slope until a part of the rock reaches the rock layer, inserting a retaining tube into the hole, and an anchor rod A hole for inserting an anchor hole through the retaining tube and drilling in the rock layer; removing the retaining tube and inserting the pipe body into the hole; then solidifying into the anchor hole through the pipe body A step of inserting an agent, a step of inserting an anchor rod into the anchor hole, a step of inserting a spherical washer through the upper end of the anchor rod in the pipe body, and connecting with a nut so as to contact the spherical seat on the bottom of the pipe body; Have It is characterized in Rukoto. (Claim 3)

第2の目的を達成するため本発明のハイブリッドアンカーは、岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが、前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し、下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体はアンカーロッドに球面座金を介して連結され、かつ前記パイプ体が進入している岩層凹入部表面とパイプ体底面との間にクッション材が介在されていることを特徴としている。(請求項4)前記クッション材はたとえば粒状物である。 In order to achieve the second object, the hybrid anchor of the present invention is an anchor installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the top of the rock layer. Includes an anchor rod embedded in the rock layer, and a pipe body that has an attachment portion of a striated body at an upper portion and is disposed in the topsoil layer so that a lower end portion reaches the rock layer, and the pipe body is an anchor rod. A cushioning material is interposed between the surface of the recessed portion of the rock layer into which the pipe body has entered and the bottom surface of the pipe body. (Claim 4) The cushion material is, for example, a granular material.

また、第2の目的を達成するため本発明のハイブリッドアンカーは、岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが、前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体はアンカーロッドに球面座金を介して傾動可能に連結され、かつ前記パイプ体の底面が進入している岩層凹入孔表面が、中心部を頂点として360度方向で外径に向かうほど低い椀状となっていることを特徴としている。 In order to achieve the second object, the hybrid anchor of the present invention is an anchor installed to support a striate represented by a rope on a slope having a rock layer and a topsoil layer covering the top of the rock layer. The anchor includes an anchor rod embedded in the rock layer, and a pipe body disposed in the topsoil layer so that a lower end portion reaches the rock layer with an attachment portion of a strip at an upper portion, and the pipe body is an anchor. The surface of the rock formation indentation hole connected to the rod through a spherical washer so as to be tiltable and into which the bottom surface of the pipe body enters has a bowl-like shape that becomes lower toward the outer diameter in the direction of 360 degrees with the center as the apex. It is characterized by having.

本発明に係るアンカー(請求項1)によれば、岩層にはアンカーロッドが埋められて凝固剤で固定され、表土層にはパイプ体が配置され、しかも前記パイプ体は下部が岩層にまで達して安置され、底部分にアンカーロッドが球面座金を介して連結されているので、アンカー上端部に法面と略平行の引張り荷重が加わった場合、パイプ体を土圧抵抗体として働かせることができる。また、外力でパイプ体が引張り方向に傾いた場合は球面座金の滑りによりアンカーロッドを曲げることなく、引張り力が引き抜き力に転換され、アンカーロッドの曲げ応力が緩和されるとともに剪断破壊等の問題が解消される。すなわちアンカー上部に変位が生じても下部のアンカーロッドには曲げ応力を伝達させないようにすることができる。 According to the anchor of the present invention (Claim 1), an anchor rod is buried in the rock layer and fixed with a solidifying agent, a pipe body is arranged in the topsoil layer, and the lower part of the pipe body reaches the rock layer. Since the anchor rod is connected to the bottom part via a spherical washer, the pipe body can be used as an earth pressure resistor when a tensile load substantially parallel to the slope is applied to the upper end of the anchor. . In addition, when the pipe body is tilted in the pulling direction due to external force, the tensile force is converted to the pulling force without bending the anchor rod due to the slippage of the spherical washer, and the bending stress of the anchor rod is relaxed and problems such as shear fracture occur. Is resolved. That is, it is possible to prevent bending stress from being transmitted to the lower anchor rod even when displacement occurs in the upper portion of the anchor.

さらに、パイプ体は細く、掘削機などで穴を掘って下端部が岩層に達するように表土層内に配置し、アンカーロッドと球面座金を介して連結するだけでよいので、表土の撤去も埋め戻しも必要なく、斜面を荒らすこともなく環境も維持できる。また、材料は汎用性のある部材が使用でき、しかも構造がシンプルなため、コスト低減を可能にし、現場作業の標準化も容易である。 Furthermore, the pipe body is thin, it is only necessary to dig a hole with an excavator and place it in the topsoil layer so that the lower end reaches the rock layer, and connect it via an anchor rod and a spherical washer. There is no need to return, and the environment can be maintained without roughening the slope. In addition, the material can be a versatile member, and the structure is simple, so that the cost can be reduced and the standardization of the field work is easy.

本発明に係るアンカー工法(請求項3)によれば、簡単な構造で安定した耐力を発揮できるアンカーを、表土の除去、埋め戻し作業を要さずに法面において簡単かつ精度よく施工することができる。 According to the anchor method according to the present invention (Claim 3), an anchor capable of exhibiting a stable proof stress with a simple structure can be constructed easily and accurately on the slope without removing topsoil and backfilling work. Can do.

本発明に係るアンカー(請求項4)によれば、パイプ体が進入している岩層凹入部表面とパイプ体底面との間にクッション材が介在され、あらかじめ沈み代が与えられているので、異常な外力が作用した場合、球面座金を中心として外力方向にパイプ体底部がクッション材を圧縮させて沈み、外力反対側が浮き上がる。このため、パイプ体の下部埋設深さが大きくても、あるいは岩層の強度が高くても、球面座金と球面座付き孔との関係でパイプ体が円滑に傾動し、アンカーロッドに曲げ応力を伝達させない。
前記クッション材としては可縮性があることが好ましく、砂、土、それらの混合物、ゴム粉、発泡スチロール粉などの粒状物が代表的であるが、スポンジや発泡スチロールなどの可縮性あるいは弾性を持つリング状の固体であってもよい。
According to the anchor according to the present invention (Claim 4), since the cushioning material is interposed between the rock layer recessed portion surface into which the pipe body has entered and the bottom surface of the pipe body, the allowance for sinking is given in advance. When a strong external force is applied, the bottom of the pipe body compresses and sinks in the direction of the external force around the spherical washer, and the opposite side of the external force rises. For this reason, even if the depth of the pipe body is large or the strength of the rock layer is high, the pipe body smoothly tilts due to the relationship between the spherical washer and the hole with the spherical seat, and the bending stress is not transmitted to the anchor rod. .
The cushioning material is preferably shrinkable, and is typically a granular material such as sand, earth, a mixture thereof, rubber powder, or expanded polystyrene powder, but has compressibility or elasticity such as sponge or expanded polystyrene. It may be a ring-shaped solid.

また、本発明に係るアンカー(請求項6)によれば、パイプ体の底面が進入している岩層凹入孔表面が、中心部を頂点として360度方向で外径に向かうほど低い椀状となっているので、沈み代があらかじめ形成され、異常な外力が作用した場合、球面座金を中心として外力方向にパイプ体底部が椀状面に沿って沈み、外力反対側が浮き上がる。このため、パイプ体の下部埋設深さが大きくても、あるいは岩層の強度が高くても、球面座金と球面座付き孔との関係でパイプ体が円滑に傾動し、アンカーロッドに曲げ応力を伝達させない。 In addition, according to the anchor according to the present invention (Claim 6), the rock formation concave hole surface into which the bottom surface of the pipe body has entered has a saddle shape that becomes lower toward the outer diameter in the direction of 360 degrees with the center at the top. Therefore, when a sink allowance is formed in advance and an abnormal external force is applied, the bottom of the pipe body sinks along the bowl-shaped surface in the direction of the external force around the spherical washer, and the opposite side of the external force is lifted. For this reason, even if the depth of the pipe body is large or the strength of the rock layer is high, the pipe body smoothly tilts due to the relationship between the spherical washer and the hole with the spherical seat, and the bending stress is not transmitted to the anchor rod. .

本発明のハイブリッドアンカーをロープネット工に適用した状態を示しており、(a)は正面図、(b)は側面図を示す。The state which applied the hybrid anchor of this invention to the rope net construction is shown, (a) shows a front view, (b) shows a side view. 本発明のアンカーの第1実施例を示しており、(a)は設計引張り荷重が加わった状況を示す正面図、(b)は設計荷重以上の負荷が加わった状況を示す正面図である。The 1st Example of the anchor of this invention is shown, (a) is a front view which shows the condition where the design tension load was added, (b) is a front view which shows the condition where the load more than a design load was added. (a)は本発明アンカーの第1実施例の要部を示す正面図、(b)は横断面図である。(A) is a front view which shows the principal part of 1st Example of this invention anchor, (b) is a cross-sectional view. 本発明によるロープ端末部アンカーを示しており、(a)は正面図、(b)は平面図を示す。The rope terminal part anchor by this invention is shown, (a) is a front view, (b) shows a top view. 本発明によるロープ交差部アンカーを示しており、(a)は正面図、(b)は平面図を示す。The rope crossing part anchor by this invention is shown, (a) is a front view, (b) shows a top view. 本発明を覆式ネット工に適用した実施例を示し、(a)は正面図、(b)は側面図を示す。The Example which applied this invention to the cover type | mold net construction is shown, (a) is a front view, (b) shows a side view. 本発明を吊式雪崩・落石予防柵に適用した実施例を示す側面図である。It is a side view which shows the Example which applied this invention to the suspension type avalanche and falling rock prevention fence. (a)〜(d)は本発明アンカー工法の途中までの工程を段階的に示す説明図である。(A)-(d) is explanatory drawing which shows the process to the middle of this invention anchor method in steps. 本発明を実施するために使用する保孔管を示し、(a)は正面図、(b)は平面図である。The hole-holding pipe | tube used in order to implement this invention is shown, (a) is a front view, (b) is a top view. 本発明アンカー工法の図8(d)以降の工程を示す説明図である。It is explanatory drawing which shows the process after FIG.8 (d) of this invention anchor construction method. 本発明アンカーの第2実施例の要部を示す正面図である。It is a front view which shows the principal part of 2nd Example of this invention anchor. (a)は第2実施例において設計引張り荷重が加わった状況を示す正面図、(b)は設計荷重以上の負荷が加わった状況を示す正面図である。(A) is a front view which shows the condition where the design tensile load was added in 2nd Example, (b) is a front view which shows the condition where the load more than a design load was added. (a)は第2実施例を用いたロープ端末部アンカーを示す正面図、(b)はロープ交差部アンカーを示す正面図である。(A) is a front view which shows the rope terminal part anchor using 2nd Example, (b) is a front view which shows a rope crossing part anchor. 第2実施例のアンカー工法の工程を段階的に示す説明図である。It is explanatory drawing which shows the process of the anchor construction method of 2nd Example in steps. (a)は本発明アンカーの第3実施例の要部を示す正面図、(b)は孔底の斜視図である。(A) is a front view which shows the principal part of 3rd Example of this invention anchor, (b) is a perspective view of a hole bottom. (a)は第3実施例において設計引張り荷重が加わった状況を示す正面図、(b)は設計荷重以上の負荷が加わった状況を示す正面図である。(A) is a front view which shows the condition where the design tensile load was added in 3rd Example, (b) is a front view which shows the condition where the load more than a design load was added. (a)は第3実施例を用いたロープ端末部アンカーを示す正面図、(b)はロープ交差部アンカーを示す正面図である。(A) is a front view which shows the rope terminal part anchor using 3rd Example, (b) is a front view which shows a rope crossing part anchor. 第3実施例のアンカー工法の工程を段階的に示す説明図である。It is explanatory drawing which shows the process of the anchor construction method of 3rd Example in steps.

好適には、パイプ体は底板にアンカーロッドの突出を許容する径の球面座付き穴を有し、アンカーロッドに外装した球面座金がアンカーロッドに螺合したナットにより球面座付き穴に面接触されている。
これによれば、パイプ体は360度方向で所要角度に自在に傾斜することができるので、どのような方向でアンカー上部に変位が生じても下部のアンカーロッドに曲げ応力を伝達させないようにすることができ、360度方向に同じ耐力を期待できる。また、アンカーロッド用孔とパイプ体配置用の孔の軸線が少しずれていても球面座金で誤差を吸収できるので、穿孔作業が楽になる。
Preferably, the pipe body has a spherical seated hole having a diameter allowing the protrusion of the anchor rod on the bottom plate, and a spherical washer externally mounted on the anchor rod is in surface contact with the spherical seated hole by a nut screwed into the anchor rod. .
According to this, the pipe body can be freely tilted to a required angle in the 360 degree direction, so that no bending stress is transmitted to the lower anchor rod regardless of the direction in which the anchor upper portion is displaced. The same proof stress can be expected in the direction of 360 degrees. Further, even if the axis of the anchor rod hole and the pipe body arranging hole are slightly deviated, the error can be absorbed by the spherical washer, so that the drilling work becomes easy.

以下添付図面を参照して本発明の実施例を説明する。
図1は本発明によるハイブリッドアンカーを落石防止装置に適用した使用例を示しており、図4はロープ端末の引き止め用アンカーに使用した例、図5はロープ交差部のアンカーに使用した例である。
Embodiments of the present invention will be described below with reference to the accompanying drawings.
FIG. 1 shows an example in which the hybrid anchor according to the present invention is applied to a rock fall prevention device, FIG. 4 shows an example in which the hybrid anchor is used as an anchor for retaining a rope end, and FIG. 5 shows an example in which the hybrid anchor is used as an anchor at an intersection of ropes. .

図1において、符号1は本発明によるハイブリッドアンカーであり、aは落石等が発生する危険のある斜面を指しており、該斜面aは岩層cを主体としてなっているが、表面は岩の強風化が進むなどによりたとえば100〜500mmの比較的薄い表土が覆った表土層bとなっている。
そうした落石等が発生する危険のある斜面aに多数の縦横ロープ11、12を地表に沿うように張設し、それぞれのロープ端末部と縦横ロープ11、12の交差部を本発明によるハイブリッドアンカー1の上端部に取付け金具9を介して係止している。縦横ロープ11、12間には縦横の補強ロープが配設されている。
In FIG. 1, reference numeral 1 denotes a hybrid anchor according to the present invention, wherein “a” indicates a slope where rockfall or the like is likely to occur, and the slope “a” is mainly composed of a rock layer “c”. As a result, the surface soil layer b is covered with a relatively thin surface soil of, for example, 100 to 500 mm.
A large number of vertical and horizontal ropes 11 and 12 are stretched along the ground surface on the slope a where there is a risk of such falling rocks, etc., and the hybrid anchor 1 according to the present invention is formed at the intersection of each rope end portion and the vertical and horizontal ropes 11 and 12. It is locked to the upper end portion of this through a mounting bracket 9. Vertical and horizontal reinforcing ropes are disposed between the vertical and horizontal ropes 11 and 12.

図2と図3はハイブリッドアンカー1を示しており、岩層cに埋設されたアンカーロッド4と、下端部が岩層cの表層に埋め込まれるように配され、上端部が表土層bから突出する鋼製のパイプ体5とからなっており、前記アンカーロッド4に対しパイプ体5は球面座金6を介して傾動可能に連結されている。   2 and 3 show the hybrid anchor 1, which is an anchor rod 4 embedded in the rock layer c and a steel that is arranged so that the lower end portion is embedded in the surface layer of the rock layer c and the upper end portion protrudes from the top soil layer b. The pipe body 5 is connected to the anchor rod 4 via a spherical washer 6 so as to be tiltable.

パイプ体5はたとえば直径114mm、長さ600mmの鋼製あるいはステンレス製の本体50からなっており、上端部には蓋が無く、別途キャップ54で塞がれるようになっている。
パイプ体5の下端部には溶接等により底板51が固着されている。底板51の厚さは球面座金6の厚さと同等かそれ以上が望ましく、中心にはアンカーロッド4の挿通を許容する径をもち、かつ球面座金6を着座しつつ傾転を許す球面座付き孔52が座ぐり加工により形成されている。パイプ体5の本体50の上端部はキャップ54を抜け止めするピンボルト91を通す横孔53が180度対称に設けられており、ピンボルト91は同時にロープ11,12の離脱を防止する役目を果たす。
The pipe body 5 comprises a main body 50 made of steel or stainless steel having a diameter of 114 mm and a length of 600 mm, for example, and has an upper end without a lid and is separately closed with a cap 54.
A bottom plate 51 is fixed to the lower end of the pipe body 5 by welding or the like. The thickness of the bottom plate 51 is preferably equal to or greater than the thickness of the spherical washer 6, and has a diameter that allows the anchor rod 4 to be inserted in the center, and a spherical seated hole 52 that allows tilting while seating the spherical washer 6. Is formed by spot facing. The upper end portion of the main body 50 of the pipe body 5 is provided with a lateral hole 53 through which the pin bolt 91 for preventing the cap 54 from coming off is provided 180 degrees symmetrically, and the pin bolt 91 simultaneously serves to prevent the ropes 11 and 12 from being detached.

アンカーロッド4はたとえば直径20〜25mm、長さ1200〜1500mmの鋼棒からなり、定着部の表面には凝固剤との摩擦力を高めるための凹凸40が付けられている。しかし、アンカーロッド4は高強度樹脂製であってもよい。
岩層cに形成されたアンカーロッド孔101には樹脂系あるいはセメント系の凝固剤103が充填されており、凝固剤が硬化することでアンカーロッド4は固定される。
表土層bから岩層cにかけてはパイプ体5を挿入して安置させるパイプ挿入用孔100が設けられており、そのパイプ挿入用孔100は、表土層bを貫く貫通孔1000と、前記貫通孔1000と同軸状をなし、岩層cの表面から凹入した岩層凹入部1001とからなっている。
The anchor rod 4 is made of, for example, a steel rod having a diameter of 20 to 25 mm and a length of 1200 to 1500 mm, and the surface of the fixing portion is provided with irregularities 40 for increasing the frictional force with the coagulant. However, the anchor rod 4 may be made of high strength resin.
The anchor rod hole 101 formed in the rock layer c is filled with a resin-based or cement-based coagulant 103, and the anchor rod 4 is fixed when the coagulant hardens.
From the topsoil layer b to the rock layer c, there is provided a pipe insertion hole 100 for inserting and placing the pipe body 5 therethrough. The pipe insertion hole 100 includes a through hole 1000 penetrating the topsoil layer b, and the through hole 1000. And a rock layer recessed portion 1001 recessed from the surface of the rock layer c.

アンカーロッド4は上部に球面座金6をナット7で固定するために定着部の直径より小径のネジ部42が設けられている。
パイプ体5の球面座付き孔52はアンカーロッド4のネジ部42の貫通を許容するので、球面座金6を突出しているネジ部42に挿通し、ナット7で締め付けることによりアンカーロッド4とパイプ体5が結合される。
The anchor rod 4 is provided with a screw portion 42 having a diameter smaller than the diameter of the fixing portion in order to fix the spherical washer 6 with the nut 7 on the upper portion.
The hole 52 with the spherical seat of the pipe body 5 allows the threaded portion 42 of the anchor rod 4 to pass therethrough, so that the spherical washer 6 is inserted into the projecting threaded portion 42 and tightened with the nut 7 to tighten the anchor rod 4 and the pipe body 5. Are combined.

パイプ体5は上端部にロープの取付け部9を有している。その取付け部9は、図4のロープ端末アンカーではピンボルト91からなり、ロープ11(12)がパイプ体5を経由して折り返され、グリップ93によりアイが形成されピンボルト91により上方への外れが阻止されている。
図5のロープ交差部アンカーでは、取付け部9としてパイプ体5の上部のキャップ54に、平面小判状をなし、内面に十字状に交差したロープ半嵌め溝を形成した上下2部材と締め付けボルトからなる十字グリップ92が装備され、その十字グリップ92に縦ロープ11と横ロープ12が交差状に圧締されている。
The pipe body 5 has a rope attachment portion 9 at its upper end. In the rope end anchor of FIG. 4, the attachment portion 9 is composed of a pin bolt 91, the rope 11 (12) is folded back through the pipe body 5, an eye is formed by the grip 93, and upward disengagement by the pin bolt 91 is prevented. Has been.
In the rope crossing anchor of FIG. 5, the cap 54 on the upper part of the pipe body 5 as the attachment part 9 is formed from a top and bottom two members and a fastening bolt formed with a rope half-fitting groove crossed in a cross shape on the inner surface. A cross grip 92 is provided, and the vertical rope 11 and the horizontal rope 12 are pressed against the cross grip 92 in a cross shape.

図2はハイブリッドアンカー1に引っ張り荷重が加わった場合の挙動を示しており、パイプ体5は、たとえば、上部100mm程度が法面aに露出し、その下が表土層bに挿入して埋められ、下端部たとえば底板から50〜150mm程度が前記岩層凹入部1001に装填されている。
図2(a)は矢印で示す引張り力が設計荷重内の場合である。パイプ体5の表土層bに対する土圧耐力と岩層凹入部1001に装填しているパイプ体下端部周辺の岩盤の抵抗によりハイブリッドアンカー1の変位(曲げ)は見られず、表土層bと岩層cとの境界でのパイプ体の変形も見られない。
図2(b)は引張り力が設計荷重を超えた場合を示す。設計値を超える引張り力が加わった場合、表土層bの土圧が耐えられず、パイプ体5のロープ取り付け部は引っ張り方向に変位する。しかし、表土層bと岩層cとの境界でパイプ体5が剪断負荷を吸収し、アンカーロッド4は球面座金6の滑りで引張り荷重が引き抜き荷重に転化され、アンカーロッド4に加わる剪断負荷が大幅に緩和される。
FIG. 2 shows the behavior when a tensile load is applied to the hybrid anchor 1. For example, the pipe body 5 has an upper part of about 100 mm exposed on the slope a, and the lower part is inserted and buried in the topsoil layer b. The rock layer recessed portion 1001 is loaded with a lower end portion, for example, about 50 to 150 mm from the bottom plate.
FIG. 2A shows the case where the tensile force indicated by the arrow is within the design load. The displacement (bending) of the hybrid anchor 1 is not observed due to the earth pressure resistance of the pipe body 5 to the top soil layer b and the resistance of the rock around the lower end of the pipe body loaded in the rock formation recess 1001, and the top soil layer b and the rock layer c There is no deformation of the pipe body at the boundary.
FIG. 2B shows a case where the tensile force exceeds the design load. When a tensile force exceeding the design value is applied, the earth pressure of the surface soil layer b cannot be withstood, and the rope attachment portion of the pipe body 5 is displaced in the pulling direction. However, the pipe body 5 absorbs the shear load at the boundary between the topsoil layer b and the rock layer c, and the anchor rod 4 is converted into a pull-out load by the sliding of the spherical washer 6, and the shear load applied to the anchor rod 4 is greatly increased. To be relaxed.

パイプ体5は球面座金6と球面座つき孔52の関係により所要角度αたとえば15度程度で傾動可能なので、アンカーロッド4には曲げ応力が伝達されない。それゆえ、斜面単一引張り方向だけでなく、360度方位からの荷重に対応でき、しかも、引き抜き方向に対しても同等の耐力を期待できる。 Since the pipe body 5 can be tilted at a required angle α, for example, about 15 degrees due to the relationship between the spherical washer 6 and the spherical seated hole 52, no bending stress is transmitted to the anchor rod 4. Therefore, it is possible to cope with a load from a 360-degree azimuth as well as a single inclined surface pulling direction, and an equivalent proof stress can be expected in the drawing direction.

本発明のアンカーは、ロープネット工のほか種々のロープを使用した安全施設に適用される。 図6は本発明のハイブリッドアンカーを適用した複式ロックネットを示し、図7は同様に吊式雪崩予防柵に適用したものである。これらの適用は後述する第2、第3実施例でも同じである。   The anchor of the present invention is applied to a safety facility using various ropes in addition to a rope net work. FIG. 6 shows a double lock net to which the hybrid anchor of the present invention is applied, and FIG. 7 is also applied to a suspended avalanche prevention fence. These applications are the same in the second and third embodiments described later.

次に、本発明によるアンカー工法について説明すると、図1に示す落石防止ロープネットは図8ないし図10に示すような手順で施工される。
(1)斜面aに落石を防止すべき縦、横ロープ11、12の張設位置を決定する。
(2)縦、横ロープ11、12の端末箇所、交差箇所を決定する。
(3)ロープ端末箇所、交差箇所に、図8(a)に示すように、目盛の付いたピンアンカー110をハンマーなどで表土層bに打ち込み、ロープ端末箇所、交差箇所の表土層bの深さを測定することで土圧耐力のある岩層cまでの深さを正確に知ることができる。
Next, the anchor construction method according to the present invention will be described. The rock fall prevention rope net shown in FIG. 1 is constructed according to the procedure shown in FIGS.
(1) Determine the position where the vertical and horizontal ropes 11 and 12 should be prevented from falling on the slope a.
(2) The terminal location and intersection location of the vertical and horizontal ropes 11 and 12 are determined.
(3) As shown in FIG. 8 (a), a pin anchor 110 with a scale is driven into the topsoil layer b with a hammer or the like at a rope end point or intersection, and the depth of the rope end point or topsoil layer b at the intersection By measuring the depth, it is possible to accurately know the depth to the rock layer c having earth pressure resistance.

(4)図8(b)に示すように、回転ロッド130の先端に小径および大径の親子ビット131,132を有する削岩機90を法面に対し略垂直に配置し、大径のビット131が表土層bを貫く貫通孔1000を穿孔し、さらに岩圧をパイプ体表面で受ける面積を確保するため岩層cの表面から少なくとも50mm好適には150mm程度に達する凹入部1001が形成されるまで穿孔する。
大径ビット131はパイプ体5を埋め込む凹入部1001を穿孔する役割を果たし、したがってパイプ体5の本体50とほぼ同径たとえば直径115〜120mmにする。子ビット132はアンカーロッド4のパイロット穿孔の役割を果たすもので、たとえば直径28〜34mmであり、岩層bを前記深さまで掘削したところで削岩機13をいったん取り除く。これにより、表土層を貫く貫通孔1000と、端部が岩層cの所要深さに達する凹入部1001と、これの底1002からさらに深く伸びるパイロット穴101´が穿設され、全体としてパイプ挿入用孔100とされる。
(4) As shown in FIG. 8 (b), a rock drill 90 having small-diameter and large-diameter parent and child bits 131 and 132 at the tip of the rotating rod 130 is arranged substantially perpendicular to the slope, and a large-diameter bit is obtained. 131 pierces through-hole 1000 penetrating topsoil layer b, and further, until a recess 1001 is formed that reaches at least 50 mm, preferably about 150 mm from the surface of rock layer c in order to secure an area for receiving rock pressure on the surface of the pipe body. Perforate.
The large-diameter bit 131 plays a role of perforating the recessed portion 1001 in which the pipe body 5 is embedded, and therefore has a diameter substantially the same as that of the main body 50 of the pipe body 5, for example, a diameter of 115 to 120 mm. The child bit 132 plays a role of pilot drilling of the anchor rod 4 and has a diameter of, for example, 28 to 34 mm. When the rock layer b is excavated to the depth, the rock drill 13 is temporarily removed. As a result, a through-hole 1000 that penetrates the topsoil layer, a recessed portion 1001 whose end reaches the required depth of the rock layer c, and a pilot hole 101 ′ extending deeper from the bottom 1002 of the through-hole are drilled. The hole 100 is used.

(5)ついで、図8(c)のように、パイプ挿入用孔100に保孔管8を挿入する。保孔管80は、図9に示すようにパイプ挿入用孔100とほぼ同径の管体80たとえば直径114mm、長さ550mmの鋼管からなり、アンカーロッド孔101の芯出しを図るため、中心に内径がたとえば40mmのガイド管81が配置され、ガイド管81は中心に孔を持つ内鍔82、82で管体80の上下で固定されている。保孔管8の上部外側にはパイプ挿入用孔100が深い場合にも保孔管80が孔に落ち込まないようにするため外鍔83が取り付けられており、これが法面と面接触するため、保孔管8が安定させられる。なお、ガイド管81は管体80の上端にまで達しない長さであってもよい。 (5) Next, as shown in FIG. 8C, the hole holding tube 8 is inserted into the pipe insertion hole 100. As shown in FIG. 9, the hole-holding pipe 80 is formed of a pipe body 80 having substantially the same diameter as the pipe insertion hole 100, for example, a steel pipe having a diameter of 114 mm and a length of 550 mm. A guide tube 81 having an inner diameter of, for example, 40 mm is disposed. An outer collar 83 is attached to the outer side of the hole holding pipe 8 so that the hole holding pipe 80 does not fall into the hole even when the pipe insertion hole 100 is deep, and this is in surface contact with the slope. The hole holding tube 8 is stabilized. The guide tube 81 may have a length that does not reach the upper end of the tube body 80.

(6)ついで、図8(d)のように、削岩機90の継ぎ足しでたとえば1700mmの長さとしたロッド91の先端にたとえば直径28mmの小径ビット93を取付け、これを保孔管8のガイド管81に挿入し、パイロット穴101´を介して岩層cを穿孔していく。保孔管8を使用することで正確にパイプ対応孔100と同心にアンカーロッド用孔101を穿孔することができる。 (6) Next, as shown in FIG. 8D, a small-diameter bit 93 having a diameter of 28 mm, for example, is attached to the tip of a rod 91 having a length of 1700 mm, for example, by adding the rock drill 90, and this is attached to the guide of the hole-holding tube 8. It is inserted into the pipe 81 and the rock layer c is drilled through the pilot hole 101 '. By using the hole holding tube 8, the anchor rod hole 101 can be precisely drilled concentrically with the pipe corresponding hole 100.

(7)こうして所定の深さの穿孔が終ったならば、図10(a)のように削岩機13および保孔管8を撤去し、パイプ体5をパイプ挿入用孔100に挿入(装填)し、岩層cに形成された凹入部1001の底(表面)1002に底板51を着座させる。底板51の球面座孔52はアンカーロッド用孔101と連通している。
(8)ついで図10(b)のように、球面座孔52を通してアンカーロッド用孔101に凝固剤103を充填、撹拌し、アンカーロッド4を球面座孔52を通してアンカーロッド用孔101に挿入する。このときアンカーロッド4は上端部のねじ部42が球面座孔52を貫いて本体50内に突出するようにする。充填された凝固剤103はアンカーロッド4の凹凸に均等に付着し強固に固定される。
(7) When the drilling of the predetermined depth is completed in this way, the rock drill 13 and the hole holding pipe 8 are removed and the pipe body 5 is inserted (loaded) into the pipe insertion hole 100 as shown in FIG. The bottom plate 51 is seated on the bottom (surface) 1002 of the recessed portion 1001 formed in the rock layer c. The spherical seat hole 52 of the bottom plate 51 communicates with the anchor rod hole 101.
(8) Next, as shown in FIG. 10B, the anchor rod hole 101 is filled with the coagulant 103 through the spherical seat hole 52 and stirred, and the anchor rod 4 is inserted into the anchor rod hole 101 through the spherical seat hole 52. . At this time, the anchor rod 4 is configured such that the screw portion 42 at the upper end protrudes into the main body 50 through the spherical seat hole 52. The filled coagulant 103 adheres evenly to the unevenness of the anchor rod 4 and is firmly fixed.

凝固剤103は一般のモルタルやセメント等をポンプ等の手段で送り込んでもよいが、円柱形状をした水溶性の袋に早強セメントを充填充したセメントカプセルのほうが充填量の管理や斜面での持ち運びに優れている。なお、アンカーロッド4が高強度樹脂製である場合には、凝固剤は樹脂カプセルが用いられる。
アンカーロッド4の挿入は、エアインパクトといった回転治具を使用し、カプラーにより上端部のねじ部42を連結してアンカーロッド用孔101に押し込んでいけばよい。
For the coagulant 103, general mortar, cement, etc. may be fed by means of a pump or the like. However, a cement capsule in which a water-soluble bag with a cylindrical shape is filled with early-strength cement is used to control the amount of filling and carry it on a slope. Is excellent. When the anchor rod 4 is made of high strength resin, a resin capsule is used as the coagulant.
The anchor rod 4 may be inserted by using a rotating jig such as air impact, and connecting the screw portion 42 at the upper end with a coupler and pushing it into the anchor rod hole 101.

(9)凝固剤103が凝固しアンカーロッド4が固定したことが確認されたならば、球面座金6をアンカーロッド4のネジ部42に挿通し、パイプ体5の球面座孔52と球面座金6の球面部を面合わせし、ナット7をネジ部42に装着し、ボックスレンチ等の緊締用工具14でナット7を締め込み、球面座金6をアンカーロッド4に固定し、パイプ体5とアンカーロッド4を連結する。 (9) If it is confirmed that the coagulant 103 is solidified and the anchor rod 4 is fixed, the spherical washer 6 is inserted into the threaded portion 42 of the anchor rod 4, and the spherical washer 52 and the spherical washer 6 of the pipe body 5 are inserted. The nut 7 is mounted on the screw portion 42, the nut 7 is tightened with a tightening tool 14 such as a box wrench, and the spherical washer 6 is fixed to the anchor rod 4, and the pipe body 5 and the anchor rod are aligned. 4 are connected.

(10)あとは、図10(e)のように、表土層bから突出しているパイプ体5の上部の取り付け部9にロープを取り付けて完成する。
図4の端末部アンカーでは、縦、横ロープ11、12の端部はパイプ体5を巻くように折り返され、グリップ93あるいは巻きグリップで複数個所を固定される。固定後、パイプ体5の上端に雨水等の水進入防止のキャップ54を被せ、パイプ体の横孔90にピンボルト91を貫挿し、キャップ54の固定とロープ11、12の外れ防止とする。
図5に示すロープ交差部アンカーでは、縦、横ロープ11、12の交差部がキャップ54にボルトナットで取り付けられた十字グリップ92により締結される。
(10) After that, as shown in FIG. 10E, a rope is attached to the upper attachment portion 9 of the pipe body 5 protruding from the topsoil layer b, and the process is completed.
In the end anchor of FIG. 4, the ends of the vertical and horizontal ropes 11 and 12 are folded back so as to wind the pipe body 5, and a plurality of places are fixed by the grip 93 or the winding grip. After fixing, the cap 54 for preventing water intrusion such as rain water is put on the upper end of the pipe body 5, and pin bolts 91 are inserted into the horizontal holes 90 of the pipe body to fix the cap 54 and prevent the ropes 11 and 12 from coming off.
In the rope crossing portion anchor shown in FIG. 5, the crossing portions of the vertical and horizontal ropes 11 and 12 are fastened by a cross grip 92 attached to the cap 54 with a bolt and nut.

図11と図12は本発明にかかるハイブリッドアンカーの第2実施例を示している。図13は適用アンカー例を示している。
この第2実施例と後述する第3実施例は、パイプ挿入用孔100の穿孔時に意図的にあるいは誤って凹入部1001を深く形成し、パイプ体5の下端部がたとえば200〜300mmというように岩質の凹入部1001に深く挿入安置される場合や、凹入部1001が適度な深さでも底部下の岩質が緻密で非常に硬いなどの地質条件である場合などにおいてにも、球面座金6を的確に機能させて、アンカーロッド4の曲げ応力の回避を図ろうとするものである。
11 and 12 show a second embodiment of the hybrid anchor according to the present invention. FIG. 13 shows an example of an applied anchor.
In the second embodiment and the third embodiment to be described later, the recessed portion 1001 is formed deeply intentionally or mistakenly when the pipe insertion hole 100 is drilled, and the lower end portion of the pipe body 5 is, for example, 200 to 300 mm. The spherical washer 6 can be used even when it is inserted deeply into the rocky recessed portion 1001 or when the recessed portion 1001 has a moderate depth and the rock condition under the bottom is dense and very hard. Is intended to avoid the bending stress of the anchor rod 4.

第2実施例では、図11のごとくパイプ体5の底板51と凹入部1001の底1002との間に、外力作用時に球面座金を中心として外力側に底部が沈み、反外力側が浮き上がる挙動を生じさせるための可縮性のクッション材15を介在させている。 In the second embodiment, between the bottom plate 51 of the pipe body 5 and the bottom 1002 of the recessed portion 1001 as shown in FIG. 11, when the external force is applied, the bottom portion sinks to the external force side around the spherical washer, and the anti-external force side rises. A compressible cushion material 15 is interposed.

前記クッション材15はパイプ体5の径にもよるが、厚さは通常10〜50mmの範囲から選定される。
クッション材15は土砂、ゴム粉、発泡スチロール粉などの粒状物が代表的である。砂や土は穿孔時の排土砂であってもよい。また、クッション材15はスポンジや発泡スチロールなどの可縮性あるいは弾性を持つ固体であってもよい。前者の場合は凹入部1001の底1002に敷き詰めればよく、後者の場合にはパイプ体5の底板底面に貼り付けてもよい。
その他の構成はすべて第1実施例と同様であるからこれの説明を援用することとし、図面に同じ符号を付すにとどめる。
Although the said cushion material 15 is based also on the diameter of the pipe body 5, thickness is normally selected from the range of 10-50 mm.
The cushion material 15 is typically a granular material such as earth and sand, rubber powder, or polystyrene foam powder. The sand or soil may be sand discharged during drilling. Further, the cushion material 15 may be a solid having elasticity or elasticity such as sponge or polystyrene foam. In the former case, it may be spread on the bottom 1002 of the recessed portion 1001, and in the latter case, it may be attached to the bottom surface of the bottom plate of the pipe body 5.
Since all other configurations are the same as those of the first embodiment, the description thereof will be incorporated and only the same reference numerals are attached to the drawings.

この実施例の場合には、外力作用が通常のものである場合には、図12(a)のようにパイプ体5の表土層bに対する土圧耐力と岩層凹入部1001に嵌入しているパイプ体下端部周辺の岩盤の抵抗によりパイプ体5は鉛直状態を保ち、ハイブリッドアンカー1の変位(曲げ)は見られず、クッション材15は全体が同じ厚みで存し、表土層bと岩層cとの境界でのパイプ体の変形も見られない。 In the case of this embodiment, when the external force action is normal, as shown in FIG. 12 (a), the earth pressure proof strength against the top soil layer b of the pipe body 5 and the pipe fitted in the rock formation recess 1001 The pipe body 5 is maintained in a vertical state due to the resistance of the rock around the lower end of the body, and the displacement (bending) of the hybrid anchor 1 is not seen, and the cushion material 15 is entirely the same thickness, and the topsoil layer b and the rock layer c There is no deformation of the pipe body at the boundary.

引張り力が設計荷重を超えた場合、通常の場合では、パイプ体5の下端部が凹入部1001に嵌まり、パイプ体5の底面が良好な岩盤に安置されているため、パイプ体5とアンカーロッド4の連結部のナット7をしっかりと固定した場合、パイプ体が沈む現象は起こりづらく、従って球面座金の特徴であるアンカーロッド4に曲げを伝達させない機能を発揮できず、外力作用側のパイプ体5を支点としてアンカーロッド4に曲げ応力を伝達する恐れがある。
しかし、この第2実施例ではパイプ体5の底と岩層凹入部1001の表面との間に可縮性のクッション材15が介在しているので、岩層凹入部1001の深さが大きかったりしても、異常な外力が作用した場合に球面座金6が的確に機能する。すなわち、図12(b)のように、球面座金6を中心にパイプ体5の外力作用側はクッション部材15の厚さ減少により沈み込み、外力反対側は浮き上がろうとする。これによりパイプ体5は傾動し、アンカーロッド4には曲げ応力が作用せず、引抜荷重のみ伝達される。
図13は適用例を示しており、クッション材15の介在以外の構成は第1実施例と同様であるから説明は援用するものとする。
When the tensile force exceeds the design load, in the normal case, the lower end portion of the pipe body 5 is fitted into the recessed portion 1001, and the bottom surface of the pipe body 5 is placed in a good bedrock. When the nut 7 of the connecting portion of the rod 4 is firmly fixed, it is difficult for the pipe body to sink, so the function of not transmitting the bending to the anchor rod 4 which is a feature of the spherical washer cannot be exhibited, and the pipe on the external force acting side There is a risk of transmitting bending stress to the anchor rod 4 with the body 5 as a fulcrum.
However, in this second embodiment, since the compressible cushioning material 15 is interposed between the bottom of the pipe body 5 and the surface of the rock formation recess 1001, the depth of the rock formation recess 1001 may be large. However, the spherical washer 6 functions accurately when an abnormal external force is applied. That is, as shown in FIG. 12B, the external force acting side of the pipe body 5 sinks due to the thickness reduction of the cushion member 15 around the spherical washer 6, and the opposite side of the external force tends to float. As a result, the pipe body 5 tilts, no bending stress acts on the anchor rod 4, and only the pulling load is transmitted.
FIG. 13 shows an application example, and since the configuration other than the intervention of the cushion material 15 is the same as that of the first embodiment, the description is incorporated.

第2実施例のクッション材15の介在は、一般に、図8に示した工程が終わり、パイプ体5をパイプ対応孔100に装填する工程の際に行われる。図14(a)はこの状況を示しており、穿った岩層凹入部1001の孔底(表面)1002にクッション材15を所要厚さで敷き詰め、その状態でパイプ体5を装填するのである。なお、クッション材15がリング状の固体である場合には、あらかじめパイプ体5の底板51の下面に貼り付けておいてもよく、パイプ体5をパイプ挿入用孔100に装填するだけで敷き詰めも行われるので簡単である。
アンカー工法の他の工程は、前記第1実施例と同様であるから説明は援用するものとする。
The intervention of the cushion material 15 of the second embodiment is generally performed during the process of loading the pipe body 5 into the pipe corresponding hole 100 after the process shown in FIG. FIG. 14A shows this situation, in which the cushion material 15 is spread over the hole bottom (surface) 1002 of the drilled rock formation recess 1001 with a required thickness, and the pipe body 5 is loaded in this state. In addition, when the cushion material 15 is a ring-shaped solid, it may be affixed to the lower surface of the bottom plate 51 of the pipe body 5 in advance, and can be spread by simply loading the pipe body 5 into the pipe insertion hole 100. It is easy because it is done.
Since the other steps of the anchor method are the same as in the first embodiment, the description will be incorporated.

図15ないし図18は本発明にかかるハイブリッドアンカーとアンカー工法の第3実施例を示している。
この実施例においては、外力作用時に球面座金6を中心として外力側にパイプ体底部が沈み、反外力側が浮き上がる挙動を生じさせるために、パイプ体5の底板51が載置される凹入部1001の底を平坦面でなく、中心部を頂点として360度方向で外径に向かうほど低い椀状面1003としていることが特徴である。その他の構成はすべて第1実施例と同様であるからこれの説明を援用することとし、図面に同じ符号を付すにとどめる。
15 to 18 show a third embodiment of the hybrid anchor and the anchor method according to the present invention.
In this embodiment, when the external force is applied, the bottom of the pipe body sinks to the external force side around the spherical washer 6 and the anti-external force side is lifted, so that the recess 1001 on which the bottom plate 51 of the pipe body 5 is placed is provided. A feature is that the bottom is not a flat surface, but a bowl-like surface 1003 that is lower toward the outer diameter in the direction of 360 degrees with the center at the top. Since all other configurations are the same as those of the first embodiment, the description thereof will be incorporated and only the same reference numerals are attached to the drawings.

この実施例の場合には、外力作用が通常のものである場合には、図16(a)のようにパイプ体5の表土層bに対する土圧耐力と岩層凹入部1001に嵌入しているパイプ体下端部周辺の岩盤の抵抗によりパイプ体5は鉛直状態を保ち、ハイブリッドアンカー1の変位(曲げ)は見られない。 In the case of this embodiment, when the external force action is normal, as shown in FIG. 16A, the earth pressure proof strength against the top soil layer b of the pipe body 5 and the pipe fitted in the rock layer recess 1001 The pipe body 5 maintains a vertical state due to the resistance of the rock around the lower end of the body, and the displacement (bending) of the hybrid anchor 1 is not seen.

引張り力が設計荷重を超えた場合、この第3実施例ではパイプ体5の底が接している岩層凹入部1001の表面が下向き椀状となっているので、岩層凹入部1001の深さが大きかったりしても、異常な外力が作用した場合に球面座金6が的確に機能する。すなわち、図16(b)のように、球面座金6を中心にパイプ体5の外力作用側底面は椀状面1003の曲面に沿って沈み、外力反対側は椀状面1003から離間して浮き上がろうとする。これによりパイプ体5は傾動し、アンカーロッド4には曲げ応力が作用せず、引抜荷重のみ伝達されるのである。
図17は適用例を示しており、クッション材15の介在以外の構成は第1実施例と同様であるから説明は援用するものとする。
When the tensile force exceeds the design load, the depth of the rock formation recessed portion 1001 is large because the surface of the rock formation recessed portion 1001 that is in contact with the bottom of the pipe body 5 has a downward saddle shape in this third embodiment. Even when an abnormal external force is applied, the spherical washer 6 functions accurately. That is, as shown in FIG. 16B, the bottom face on the external force acting side of the pipe body 5 sinks along the curved surface of the bowl-like surface 1003 around the spherical washer 6, and the opposite side of the external force floats away from the bowl-like surface 1003. Try to go up. As a result, the pipe body 5 tilts, and no bending stress acts on the anchor rod 4, and only the pulling load is transmitted.
FIG. 17 shows an application example, and since the configuration other than the intervention of the cushion material 15 is the same as that of the first embodiment, the description is incorporated.

前記椀状面1003の加工は、パイプ体5をパイプ対応孔100に装填する前ならいつでもよいが、通常は、図18(b)のように岩層凹入部1001を削孔した後、同図(c)のように、削岩機13に椀状の凹型ビット133を装着し、岩層凹入部1001に挿入して、岩層凹入部の平らな表面1002の中心部を頂点とし360°方向均一で外周部に向かうほど深く切り込むR加工付穿孔を行うことで形成する。
それ以降の工程は第1実施例と同様であり、底板51が接している岩層凹入部の表面が平らであるが、これが椀状面1003になっている点を除いて図10の各工程と同じであるから説明は援用する。
The saddle-like surface 1003 may be processed at any time before the pipe body 5 is loaded into the pipe corresponding hole 100. Normally, however, after the rock formation recess 1001 is drilled as shown in FIG. As shown in c), the rock drill 13 is fitted with a bowl-shaped concave bit 133 and inserted into the rock formation recessed portion 1001. The outer periphery is uniformly 360 ° with the center of the flat surface 1002 of the rock formation recessed portion as the apex. It is formed by drilling with R machining that cuts deeper toward the part.
The subsequent steps are the same as in the first embodiment, and the surface of the rock formation recess where the bottom plate 51 is in contact is flat, except that this is a saddle-shaped surface 1003. Since it is the same, explanation is used.

なお、ハイブリッドアンカー1、縦横ロープ11、12、その他金具類は防食のため亜鉛めっきや亜鉛アルミ合金めっき等が施されている。また、景観を保つため有色樹脂塗装をすることもできる。樹脂塗装を施すことで耐食性能をさらに向上することができる。 The hybrid anchor 1, the vertical and horizontal ropes 11 and 12, and other metal fittings are galvanized or zinc aluminum alloy plated for corrosion protection. In addition, colored resin coating can be applied to maintain the landscape. Corrosion resistance can be further improved by applying resin coating.

a 法面
b 表土層
c 岩層
1 ハイブリッドアンカー
11 縦ロープ
12 横ロープ
4 アンカーロッド
5 パイプ体
6 球面座金
7 ナット
8 保孔管
15 クッション部材
52 球面座付き穴
100 パイプ挿入用孔
101 アンカー用孔
103 凝固剤
1001 岩層凹入部
1003 椀状面
a Slope b Topsoil layer c Rock layer 1 Hybrid anchor 11 Vertical rope 12 Horizontal rope 4 Anchor rod 5 Pipe body 6 Spherical washer 7 Nut 8 Hole retaining tube 15 Cushion member 52 Spherical seat hole 100 Pipe insertion hole 101 Anchor hole 103 Solidification Agent 1001 Rock layer recess 1003

Claims (6)

岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが、前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体は前記アンカーロッドに球面座金を介して連結されていることを特徴とするハイブリッドアンカー。 In an anchor installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the upper part of the rock layer, the anchor includes an anchor rod embedded in the rock layer and a strip in the upper part. And a pipe body disposed in the topsoil layer so that the lower end reaches the rock layer, and the pipe body is connected to the anchor rod via a spherical washer. Hybrid anchor. パイプ体は底板にアンカーロッドの突出を許容する径の球面座付き穴を有し、アンカーロッドに外装した球面座金がアンカーロッドに螺合したナットにより球面座付き穴に面接触されている請求項1に記載のハイブリッドアンカー。   The pipe body has a spherical seated hole having a diameter allowing the protrusion of the anchor rod on the bottom plate, and a spherical washer externally mounted on the anchor rod is in surface contact with the spherical seated hole by a nut screwed into the anchor rod. The described hybrid anchor. 岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカー工法であって、アンカーとしてアンカーロッドとパイプ体を用い、法面にパイプ体を挿入する孔を岩層に一部が達するまで穿孔する工程と、前記孔に保孔管を挿入する工程と、アンカーロッドを挿入するためのアンカー用孔を前記保孔管を貫いて岩層に穿孔する工程と、保孔管を撤去しパイプ体を前記孔に挿入したうえで、パイプ体を通して前記アンカー用孔内に凝固剤を挿入する工程と、アンカーロッドをアンカー用孔に挿入する工程と、パイプ体内のアンカーロッド上端部に球面座金を挿通してパイプ体底の球面座に接触するようにナットで連結する工程とを有することを特徴とするアンカー工法。 An anchor construction method installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the upper part of the rock layer, and using an anchor rod and a pipe body as an anchor, Drilling a hole for inserting a body until a part of the rock reaches the rock layer, inserting a hole-holding tube into the hole, and inserting an anchor hole for inserting an anchor rod into the rock layer through the hole-holding tube. A step of drilling, a step of removing a retaining tube and inserting a pipe body into the hole, a step of inserting a coagulant into the hole for anchor through the pipe body, and a step of inserting an anchor rod into the hole for anchor And a step of inserting a spherical washer through the upper end portion of the anchor rod in the pipe body and connecting with a nut so as to come into contact with the spherical seat on the bottom of the pipe body. 岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが、前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し、下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体はアンカーロッドに球面座金を介して傾動可能に連結され、かつ前記パイプ体が進入している岩層凹入部表面とパイプ体底面との間にクッション材が介在されていることを特徴とするハイブリッドアンカー。 In an anchor installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the upper part of the rock layer, the anchor includes an anchor rod embedded in the rock layer and a strip in the upper part. A pipe body disposed in the topsoil layer so that the lower end reaches the rock layer, the pipe body is tiltably connected to an anchor rod via a spherical washer, and the pipe A hybrid anchor characterized in that a cushioning material is interposed between the surface of a rock layer recess where a body enters and the bottom of a pipe body. クッション材が粒状物である請求項4に記載のハイブリッドアンカー。 The hybrid anchor according to claim 4, wherein the cushion material is a granular material. 岩層と該岩層の上部を覆う表土層とを有する法面にロープで代表される条体を支持するため設置されるアンカーにおいて、該アンカーが、前記岩層に埋設されたアンカーロッドと、上部に条体の取付け部を有し下端部が岩層に達するように表土層内に配置されたパイプ体とを備え、前記パイプ体はアンカーロッドに球面座金を介して傾動可能に連結され、かつ前記パイプ体の底面が進入している岩層凹入孔表面が、中心部を頂点として360度方向で外径に向かうほど低い椀状となっていることを特徴とするハイブリッドアンカー。   In an anchor installed to support a strip represented by a rope on a slope having a rock layer and a topsoil layer covering the upper part of the rock layer, the anchor includes an anchor rod embedded in the rock layer and a strip in the upper part. A pipe body disposed in the topsoil layer so that the lower end reaches the rock layer, the pipe body is tiltably connected to an anchor rod via a spherical washer, and the pipe body A hybrid anchor characterized in that a rock layer concave hole surface into which the bottom surface of the rock has entered has a saddle shape that becomes lower toward the outer diameter in the direction of 360 degrees with the center as a vertex.
JP2010127248A 2009-06-03 2010-06-02 Hybrid anchor and anchor method Active JP5542529B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010127248A JP5542529B2 (en) 2009-06-03 2010-06-02 Hybrid anchor and anchor method

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2009134537 2009-06-03
JP2009134537 2009-06-03
JP2010127248A JP5542529B2 (en) 2009-06-03 2010-06-02 Hybrid anchor and anchor method

Publications (2)

Publication Number Publication Date
JP2011012539A true JP2011012539A (en) 2011-01-20
JP5542529B2 JP5542529B2 (en) 2014-07-09

Family

ID=43591701

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010127248A Active JP5542529B2 (en) 2009-06-03 2010-06-02 Hybrid anchor and anchor method

Country Status (1)

Country Link
JP (1) JP5542529B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012225109A (en) * 2011-04-22 2012-11-15 Tokyo Seiko Co Ltd Anchor device
JP2013083084A (en) * 2011-10-11 2013-05-09 Tokyo Seiko Co Ltd Relocatable stone-fall protective net, and method of relocating stone-fall protective net
JP2014238000A (en) * 2014-07-17 2014-12-18 東京製綱株式会社 Anchor device
CN110158498A (en) * 2019-05-30 2019-08-23 中铁二院工程集团有限责任公司 A kind of elasticity passive protection net pillar construction and construction method
JP2021059889A (en) * 2019-10-07 2021-04-15 株式会社斜面対策研究所 Sloped face stabilization structure
CN113728843A (en) * 2021-09-01 2021-12-03 广州桃园建筑工程有限公司 Rock slope planting structure
JP2022063897A (en) * 2020-10-13 2022-04-25 株式会社ライテク Protective structure and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5668026U (en) * 1979-10-19 1981-06-05
JP2000136535A (en) * 1998-10-30 2000-05-16 Nippon Steel Metal Prod Co Ltd Slope stabilizing method and device thereof
JP2001172965A (en) * 1999-12-14 2001-06-26 Okabe Co Ltd Reinforcing method for rock bolt
JP2002038477A (en) * 2000-07-23 2002-02-06 Okabe Co Ltd Stabilizing method for slope face
JP2003253668A (en) * 2002-02-27 2003-09-10 Nisshoku Corp Member for tightening bar-like member
JP2006188839A (en) * 2004-12-30 2006-07-20 Nippon Kokyo Kikaku Kk Pipe type double compression anchoring method
JP2006194072A (en) * 2004-12-17 2006-07-27 Toko Techno Kk High strength anchor
JP2009084893A (en) * 2007-09-29 2009-04-23 Tokyo Seiko Co Ltd High-strength anchor

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5668026U (en) * 1979-10-19 1981-06-05
JP2000136535A (en) * 1998-10-30 2000-05-16 Nippon Steel Metal Prod Co Ltd Slope stabilizing method and device thereof
JP2001172965A (en) * 1999-12-14 2001-06-26 Okabe Co Ltd Reinforcing method for rock bolt
JP2002038477A (en) * 2000-07-23 2002-02-06 Okabe Co Ltd Stabilizing method for slope face
JP2003253668A (en) * 2002-02-27 2003-09-10 Nisshoku Corp Member for tightening bar-like member
JP2006194072A (en) * 2004-12-17 2006-07-27 Toko Techno Kk High strength anchor
JP2006188839A (en) * 2004-12-30 2006-07-20 Nippon Kokyo Kikaku Kk Pipe type double compression anchoring method
JP2009084893A (en) * 2007-09-29 2009-04-23 Tokyo Seiko Co Ltd High-strength anchor

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012225109A (en) * 2011-04-22 2012-11-15 Tokyo Seiko Co Ltd Anchor device
JP2013083084A (en) * 2011-10-11 2013-05-09 Tokyo Seiko Co Ltd Relocatable stone-fall protective net, and method of relocating stone-fall protective net
JP2014238000A (en) * 2014-07-17 2014-12-18 東京製綱株式会社 Anchor device
CN110158498A (en) * 2019-05-30 2019-08-23 中铁二院工程集团有限责任公司 A kind of elasticity passive protection net pillar construction and construction method
CN110158498B (en) * 2019-05-30 2024-01-23 中铁二院工程集团有限责任公司 Construction method of elastic passive protective net upright post structure
JP2021059889A (en) * 2019-10-07 2021-04-15 株式会社斜面対策研究所 Sloped face stabilization structure
JP7130252B2 (en) 2019-10-07 2022-09-05 株式会社斜面対策研究所 Slope stabilization structure
JP2022063897A (en) * 2020-10-13 2022-04-25 株式会社ライテク Protective structure and construction method thereof
JP7297263B2 (en) 2020-10-13 2023-06-26 株式会社ライテク Protective structure and construction method
CN113728843A (en) * 2021-09-01 2021-12-03 广州桃园建筑工程有限公司 Rock slope planting structure

Also Published As

Publication number Publication date
JP5542529B2 (en) 2014-07-09

Similar Documents

Publication Publication Date Title
JP5542529B2 (en) Hybrid anchor and anchor method
JP5882143B2 (en) Anti-floating pile for underground structures and anti-floating method for underground structures
JP5150596B2 (en) Anchor device and anchor construction method
JP4766996B2 (en) Rope anchor device for civil engineering facilities
JP3156537U (en) Anchor device
TWI771438B (en) Anchor mooring device
KR101016047B1 (en) Apparatus for reinforcing anchor and construction method thereof
JP5597590B2 (en) Anchor device
JP4583343B2 (en) Anchor structure and rope anchor guide member
JP4181192B2 (en) Ground anchor and ground anchor method
JP6249440B2 (en) Manhole levitation prevention method
JP2002047650A (en) Set anchor body and executing method therefor
JP2021188438A (en) Foundation foot protection structure, and foundation foot protection method
JP2023184036A (en) Anchor device, and construction method of anchor device
JP3863399B2 (en) High strength anchor device and installation method thereof
CN206204942U (en) A kind of tension type anchor pole for reinforcing cut slope
JP3813781B2 (en) Anchor device installation method
JP5743735B2 (en) Anchors and anchor methods for non-independent structures
JP6623393B2 (en) Mooring anchor device
JP5878596B2 (en) Anchor device installation method
JP2006183232A (en) High load bearing anchor
KR20140010487A (en) Supporting structure for marine structure and construction method thereof
CN113605934B (en) Reinforced structure for preventing tunnel uphill from slipping down and construction method thereof
JP2010255309A (en) Foundation structure for structure
CN110578332B (en) Supporting method of foundation pit supporting structure

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20110428

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20130423

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20131218

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20140107

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20140107

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20140203

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20140408

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20140507

R150 Certificate of patent or registration of utility model

Ref document number: 5542529

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250