JP2009221843A - Slide method for precast balcony, and roller and rail for sliding precast balcony - Google Patents

Slide method for precast balcony, and roller and rail for sliding precast balcony Download PDF

Info

Publication number
JP2009221843A
JP2009221843A JP2009161024A JP2009161024A JP2009221843A JP 2009221843 A JP2009221843 A JP 2009221843A JP 2009161024 A JP2009161024 A JP 2009161024A JP 2009161024 A JP2009161024 A JP 2009161024A JP 2009221843 A JP2009221843 A JP 2009221843A
Authority
JP
Japan
Prior art keywords
balcony
precast
roller
rail
precast balcony
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2009161024A
Other languages
Japanese (ja)
Other versions
JP4885259B2 (en
Inventor
Keiichi Tanaka
中 恵 一 田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NAKAJIMA TOOKEN KK
Hazama Ando Corp
Original Assignee
NAKAJIMA TOOKEN KK
Ando Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NAKAJIMA TOOKEN KK, Ando Corp filed Critical NAKAJIMA TOOKEN KK
Priority to JP2009161024A priority Critical patent/JP4885259B2/en
Publication of JP2009221843A publication Critical patent/JP2009221843A/en
Application granted granted Critical
Publication of JP4885259B2 publication Critical patent/JP4885259B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a slide method for a precast balcony which conveys and attaches a precast balcony even to a place to which a crane does not extend. <P>SOLUTION: The slide method for a precast balcony comprises a process of installing rails almost parallel to the exterior wall of a building, a process of mounting the precast balcony on the rails and installing rollers capable of sliding along the rails, a process of mounting the precast balcony on the rollers, and a process of sliding the precast balcony to convey it to a mounting position. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明はプレキャスト工法によって製造したバルコニーを建造物に取り付ける工法およびそれに使用する装置に関する。   The present invention relates to a method of attaching a balcony manufactured by a precast method to a building and an apparatus used therefor.

特に、本発明は、通常はクレーン等のみによってバルコニーの取付位置に搬送可能なプレキャスト製バルコニーを人力によっても搬送できるようにしたプレキャスト製バルコニーのスライド工法およびその搬送装置に関する。   In particular, the present invention relates to a slide method for a precast balcony that can be transported by human power, usually a precast balcony that can be transported to the mounting position of the balcony only by a crane or the like, and a transport apparatus therefor.

たとえば高層集合住宅のような建造物は、建造物の外壁に多数のバルコニーを取り付けることがよくある。   For example, a building such as a high-rise apartment often has a number of balconies attached to the outer wall of the building.

現在では工場で予めコンクリート打設成形したバルコニー(プレキャスト製バルコニー)を建築現場で建造物に取り付けることが広く行われている。   At present, it is widely practiced that a balcony (precast balcony) pre-cast with concrete in a factory is attached to a building at a construction site.

従来はプレキャスト製バルコニーは、工場で製造された後に建築現場に搬送され、クレーン等の起重機によって吊り上げられ、建造物の所定のバルコニー取付場所に搬送され、取付場所で細かく位置調整が行われた後に仮に固定されていた。   Conventionally, precast balconies are manufactured at the factory, then transported to the construction site, lifted by a crane or other hoist, transported to the specified balcony mounting location of the building, and finely adjusted at the mounting location. It was temporarily fixed.

所定の数のプレキャスト製バルコニーが仮固定されると、これらのプレキャスト製バルコニーの基端部は建造物の外壁の一部と一体的にコンクリート打ちされ、建造物と一体化された。   When a predetermined number of precast balconies were temporarily fixed, the base end portions of these precast balconies were concreted integrally with a part of the outer wall of the building and integrated with the building.

従来は通常は上述したように、クレーンによってプレキャスト製バルコニーを吊り上げるようにしていたが、特許第2877148号には、プレキャスト製バルコニーを対象とするものではないが建造物の外部にガイドレールを立設し、このガイドレールに沿って上下に昇降できるすべり架台を設け、架台上にレールを設け、前記レール上に台車を設けた高層建築建設現場内部への重量資材荷揚げ搬入装置が記載されている。   Conventionally, as described above, a precast balcony is usually lifted by a crane. However, in Japanese Patent No. 2877148, a guide rail is erected outside a building, although it is not intended for a precast balcony. In addition, there is described a heavy material unloading and carrying device into a high-rise building construction site in which a slide frame that can be moved up and down along this guide rail is provided, a rail is provided on the frame, and a carriage is provided on the rail.

特許第2877148号公報Japanese Patent No. 2877148

従来のプレキャスト製バルコニーの取り付け方法は上述したように、クレーンによってプレキャスト製バルコニーを取付場所に吊り上げ、仮固定した後に建造物と一体的にコンクリート打ちする。   As described above, the conventional method for attaching the precast balcony is to lift the precast balcony to the installation location by a crane, temporarily fix the balcony, and then place the concrete integrally with the building.

しかし、従来のプレキャスト製バルコニーの取り付け方法は、クレーンが届く範囲でなら取付が可能であったが、クレーンが届かない所のバルコニーはプレキャスト製バルコニーを取り付けることができなかった。   However, the conventional method of attaching a precast balcony can be installed within the reach of the crane, but the balcony where the crane cannot reach cannot be attached to the precast balcony.

図10に従来のプレキャスト製バルコニーの取り付け方法の問題を示す。   FIG. 10 shows a problem of the conventional method for attaching a precast balcony.

図10において、符号30はバルコニーを取り付けようとする新築の建造物を示している。   In FIG. 10, the code | symbol 30 has shown the newly built structure which is going to attach a balcony.

この建造物30の側面と背面には既設の建物31,32が存在するとする。また、建造物30と既設の建物31,32の間には細い路地しかないものとする。   It is assumed that existing buildings 31 and 32 exist on the side and the back of the building 30. Further, it is assumed that there is only a narrow alley between the building 30 and the existing buildings 31 and 32.

この場合に、クレーン33は建造物30の前面と側面の道路に設置する以外に設置することができないので、図9に示すように、バルコニーの取付場所に応じて移動させて設置する。   In this case, the crane 33 cannot be installed other than being installed on the front and side roads of the building 30, so as shown in FIG. 9, the crane 33 is moved and installed according to the location of the balcony.

しかし、それでも図に示すように、既設の建物との間の道路から遠い部分はクレーン33のブームが届かない。   However, as shown in the figure, the boom of the crane 33 does not reach the part far from the road between the existing buildings.

そのため、従来はこのようなクレーン33のブームが届かない場所のバルコニーは、プレキャスト製のバルコニーを使用できず、現場で型枠を新たに組んでコンクリート打ちしてバルコニーを建設していた。   For this reason, conventionally, a balcony in which the boom of the crane 33 does not reach cannot be used as a precast balcony, and a balcony is constructed by newly forming a formwork and placing concrete on the site.

そこで、本発明が解決しようとする課題は、クレーンが届かない場所にもプレキャスト製のバルコニーを搬送して取り付けられるようにした工法を提供することにある。   Therefore, the problem to be solved by the present invention is to provide a construction method in which a precast balcony can be transported and attached to a place where a crane cannot reach.

本発明のプレキャスト製バルコニーのスライド工法は、建造物外壁にほぼ平行にレールを設置する工程と、前記レール上に前記レールに沿って滑走可能なローラーを設置する工程と、前記ローラー上にプレキャスト製バルコニーを載置する工程と、前記プレキャスト製バルコニーをスライドさせて取り付け場所に搬送する工程と、を有することを特徴とするものである。   The slide method of the precast balcony of the present invention includes a step of installing a rail substantially parallel to a building outer wall, a step of installing a roller that can slide along the rail on the rail, and a precast product on the roller. It has the process of mounting a balcony, and the process of sliding the said precast balcony and conveying to an attachment place, It is characterized by the above-mentioned.

また、本発明のプレキャスト製バルコニーのスライド工法は、建造物外壁にほぼ平行に頂部にローラーを有するレールを設置する工程と、前記レール上にプレキャスト製バルコニーを載置する工程と、
前記プレキャスト製バルコニーをスライドさせて取り付け場所に搬送する工程と、有することを特徴とするものである。
In addition, the slide method of the precast balcony of the present invention includes a step of installing a rail having a roller at the top substantially parallel to the outer wall of the building, a step of placing the precast balcony on the rail,
And a step of sliding the precast balcony and transporting it to the mounting location.

本発明のプレキャスト製バルコニーのスライド工法は、第1方向のレールと第2方向のレールが互いに交差するコーナー部を設ける工程と、前記第1方向のレールに沿って前記プレキャスト製バルコニーを前記コーナー部に搬送する工程と、前記コーナー部において、前記プレキャスト製バルコニーを昇降手段によって上昇させて前記第1方向のレール上のローラーを取り外し、続いて前記プレキャスト製バルコニーを昇降手段によって下降させて前記第2方向のレール上に設置したローラ上に載置し換える工程をさらに有することができる。   The slide method for a precast balcony according to the present invention includes a step of providing a corner portion where a rail in a first direction and a rail in a second direction intersect each other, and the corner portion of the precast balcony along the rail in the first direction. And, at the corner portion, the precast balcony is lifted by lifting means to remove the roller on the rail in the first direction, and then the precast balcony is lowered by the lifting means. The method may further include a step of placing on a roller installed on a directional rail.

また、本発明のプレキャスト製バルコニーのスライド工法は、第1方向のレールと第2方向のレールが互いに交差するコーナー部を設ける工程と、前記第1方向のレールに沿って前記プレキャスト製バルコニーを前記コーナー部に搬送する工程と、前記コーナー部において、前記プレキャスト製バルコニーを昇降手段によって上昇させて前記第1方向のレールを取り外し、続いて前記プレキャスト製バルコニーを昇降手段によって下降させて前記第2方向のレール上に載置し換える工程をさらに有することができる。   The slide method of the precast balcony according to the present invention includes a step of providing a corner portion where the first direction rail and the second direction rail intersect each other, and the precast balcony along the first direction rail. A step of conveying to the corner portion, and in the corner portion, the precast balcony is lifted by lifting means to remove the rail in the first direction, and then the precast balcony is lowered by the lifting means to the second direction. The method may further include a step of placing on the rail.

また、本発明のプレキャスト製バルコニーのスライド工法は、前記ローラー上または前記頂部にローラーを有するレール上に前記プレキャスト製バルコニーを載置する工程において、プレキャスト製バルコニーは建造物の外壁からの設計された突出距離に合わせてほぼ正確に載置するようにすることができる。   Further, the slide method of the precast balcony of the present invention is the step of placing the precast balcony on the roller or on the rail having a roller on the top, and the precast balcony is designed from the outer wall of the building. It can be placed almost accurately according to the protruding distance.

また、本発明のプレキャスト製バルコニーのスライド工法は、第2方向のローラー上または第2方向のレール上に前記プレキャスト製バルコニーを載置し換える時に、プレキャスト製バルコニーは建造物の外壁からの設計された突出距離に合わせてほぼ正確に載置し換えるようにすることができる。   In the slide method of the precast balcony according to the present invention, when the precast balcony is placed on the roller in the second direction or on the rail in the second direction, the precast balcony is designed from the outer wall of the building. Therefore, it can be placed almost exactly according to the protruding distance.

また、本発明のプレキャスト製バルコニーのスライド工法は、前記プレキャスト製バルコニーを取付場所に搬送した後に昇降手段によって前記プレキャスト製バルコニーを昇降させて設計高さに設置する工程をさらに有することができる。   Moreover, the slide method of the precast balcony of this invention can further have the process of raising / lowering the said precast balcony by the raising / lowering means, and installing in the design height after conveying the said precast balcony to an attachment place.

本発明のプレキャスト製バルコニースライド用ローラーは、円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材と、前記枠材から前記各転がり部材の外周面に接する面を超えて突設させた少なくとも1対のガイド部材とを有することを特徴とするものである。   The roller for a slide slide made of precast of the present invention is capable of rotating a plurality of rolling members having a columnar portion, a rotating shaft protruding from both ends of each rolling member, and ends of both rotating shafts of each rolling member. It has a pair of frame members to support, and at least one pair of guide members projected from the frame material beyond the surface in contact with the outer peripheral surface of each rolling member.

本発明のプレキャスト製バルコニースライド用のレールは、円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材とを有するローラーと、前記ローラーの枠部材を保持する保持部材と、前記保持部材を支持する支持部材とを有することを特徴とするものである。   The rail for a precast balcony slide according to the present invention is capable of rotating a plurality of rolling members having a columnar portion, rotating shafts projecting from both ends of each rolling member, and ends of both rotating shafts of each rolling member. A roller having a pair of frame members to be supported, a holding member for holding the frame member of the roller, and a support member for supporting the holding member.

本発明によれば、建造物外壁にほぼ平行にレールを設置し、もっともクレーンが届きやすい場所を搬入領域としてプレキャスト製バルコニーをレール上に載置し、順次人間の力によってプレキャスト製バルコニーをスライドさせ、クレーンの届き難いバルコニーの取付場所にもプレキャスト製バルコニーを容易に搬送して取り付けることができる。   According to the present invention, rails are installed almost parallel to the outer wall of the building, and the precast balcony is placed on the rail with the place where the crane can easily reach as the loading area, and the precast balcony is sequentially slid by human force. The precast balcony can be easily transported and attached to the place where the crane is difficult to reach.

また、建造物の角を迂回するなど、バルコニー取付場所までのバルコニー搬送路がコーナー部を有する場合において、本発明によればコーナー部でレールを互いに交差させ、コーナー部にプレキャスト製バルコニーを搬送し、コーナー部おいてプレキャスト製バルコニーを最初に搬送したレールから他のレールに載置し換えることができ、これによってコーナー部で搬送方向を変えて、従来クレーンでは届かないバルコニー取付場所にプレキャスト製バルコニーを人力によって搬送して取り付けることができる。   Also, when the balcony transport path to the balcony mounting location has a corner portion, such as detouring the corner of the building, according to the present invention, the rails cross each other at the corner portion, and the precast balcony is transported to the corner portion. In the corner, the precast balcony can be transferred from the rail that was first transported to another rail, which changes the direction of transport in the corner and makes it possible to change the transport direction at the corner and place it in a balcony mounting location that cannot be reached by conventional cranes. Can be transported and attached by human power.

本発明のプレキャスト製バルコニーのスライド工法の一工程を示した立面図。The elevation which showed 1 process of the slide construction method of the precast balcony of this invention. 図1を側面から見た側面断面図。Side surface sectional drawing which looked at FIG. 1 from the side. 本発明のプレキャスト製バルコニーのスライド工法のための装置の詳細を示した立面図。The elevation which showed the detail of the apparatus for the slide construction method of the precast balcony of this invention. 本発明のプレキャスト製バルコニーのスライド工法の一工程を示した立面図。The elevation which showed 1 process of the slide construction method of the precast balcony of this invention. 本発明のプレキャスト製バルコニーのスライド工法のための装置の詳細を示した立面図。The elevation which showed the detail of the apparatus for the slide construction method of the precast balcony of this invention. 本発明のプレキャスト製バルコニーのスライド工法によるレールの敷設例を示した平面図。The top view which showed the laying example of the rail by the slide construction method of the precast balcony of this invention. コーナー部の構成を示した平面図。The top view which showed the structure of the corner part. 本発明のプレキャスト製バルコニースライド用ローラーの側面図。The side view of the roller for pre-cast balcony slides of this invention. 本発明のプレキャスト製バルコニースライド用ローラーの正面図。The front view of the roller for pre-cast balcony slides of this invention. 本発明のプレキャスト製バルコニースライド用レールの正面図。The front view of the rail for rails made from precast of the present invention. 従来の工法の課題を説明した平面図。The top view explaining the subject of the conventional construction method.

以下に本発明の実施形態について説明するが、本発明はこれに限定されるものではない。   Embodiments of the present invention will be described below, but the present invention is not limited thereto.

図1は、本発明の一実施形態によるプレキャスト製バルコニーのスライド工法の一工程を示している。   FIG. 1 shows one step of a slide method for a precast balcony according to an embodiment of the present invention.

図1において、符号1は建造物を示している。建造物1は、4層建ての建物であり、すでに2階部分と3階部分のバルコニーは取り付けを完了し、バルコニーが建造物と一体的にコンクリート打ちされた状態になっており、現在は4階部分のバルコニーを取り付けているところを示している。   In FIG. 1, the code | symbol 1 has shown the building. Building 1 is a four-story building, and the balconies on the 2nd and 3rd floors have already been installed, and the balconies are in a state of being concreted with the building. It shows a floor balcony installed.

図1に示すように、本実施形態の工法では、階下のバルコニー上に足場2を設け、足場2の両側に間隔をおいて支持部材3を立て、支持部材3の上部に建造物1の外壁と平行にレール4を設けている。そして、クレーン5がアクセスしやすい場所を搬入領域6とし、クレーン5によってプレキャストしたプレキャスト製バルコニー7を吊り上げ、搬入領域6のレール4上に載置する。   As shown in FIG. 1, in the construction method of the present embodiment, a scaffold 2 is provided on a downstairs balcony, support members 3 are set up at intervals on both sides of the scaffold 2, and the outer wall of the building 1 is placed above the support member 3. A rail 4 is provided in parallel with the rail. A place where the crane 5 is easily accessible is set as the carry-in area 6, and the precast balcony 7 precast by the crane 5 is lifted and placed on the rail 4 in the carry-in area 6.

レール4上に載置したプレキャスト製バルコニー7は順次人力によって図示する矢印の方向にレール4上をスライドさせ、各プレキャスト製バルコニー7を取り付けるべき取付場所に搬送した後に、そこでプレキャスト製バルコニー7を仮固定する。所定数のプレキャスト製バルコニー7を仮固定した後に、プレキャスト製バルコニー7の基端部と建造物1の柱の一部と外壁の一部とにコンクリートを打設し、プレキャスト製バルコニー7と建造物1とを一体化させる。   The precast balconies 7 placed on the rails 4 are sequentially slid on the rails 4 in the direction of the arrows shown in the figure by human power, and are transported to the mounting locations where the precast balconies 7 are to be attached. Fix it. After temporarily fixing a predetermined number of precast balconies 7, concrete is cast on the base end of the precast balcony 7, part of the pillars of the building 1 and part of the outer wall, and the precast balcony 7 and the building 1 is integrated.

図2は、図1の建造物1を側面から見たところを示している。   FIG. 2 shows the building 1 of FIG. 1 as viewed from the side.

図2に示すように、建造物1の2階、3階部分のバルコニーはすでに建造物1と一体的に取り付けられている。4階部分のバルコニーを取り付けるために、3階のバルコニーの上に足場2と支持部材3を設け、支持部材3上にレール4を敷設する。レール4は、断面が中空の矩形の鋼材とすることが好ましい。レール4の上にプレキャスト製バルコニー7を載置し、紙面に垂直の方向に人力によってスライドさせて搬送する。   As shown in FIG. 2, the balconies on the second and third floors of the building 1 are already attached integrally with the building 1. In order to attach the balcony on the fourth floor, the scaffold 2 and the support member 3 are provided on the balcony on the third floor, and the rail 4 is laid on the support member 3. The rail 4 is preferably a rectangular steel material having a hollow cross section. A precast balcony 7 is placed on the rail 4 and slid by a human power in a direction perpendicular to the paper surface.

なお、最初にプレキャスト製バルコニー7をレール4上に載置する位置は、設計された建造物1の外壁からのプレキャスト製バルコニー7の突出距離に合わせてほぼ正確に載置するのが好ましい。これにより、プレキャスト製バルコニー7をレール4に沿ってスライドさせてバルコニー取付場所に搬送したときに、そのままプレキャスト製バルコニー7を仮固定することができる。この場合には、バルコニー取付場所での時間がかかる位置調整の作業が省かれあるいは少なくとも大幅に簡略化され、工事の作業効率を著しく向上させることができる。   In addition, it is preferable that the position where the precast balcony 7 is first placed on the rail 4 is placed almost accurately according to the protruding distance of the precast balcony 7 from the outer wall of the designed building 1. Thereby, when the precast balcony 7 is slid along the rail 4 and conveyed to the balcony mounting location, the precast balcony 7 can be temporarily fixed as it is. In this case, time-consuming position adjustment work at the balcony mounting location is omitted or at least greatly simplified, and the work efficiency of the construction can be significantly improved.

なお、図2に示すように、プレキャストされたプレキャスト製バルコニー7は、最終的な完成状態より薄くなっており、基端部は建造物1の外壁より建物内側に入り込むようになっている。建造物1の柱や外壁はプレキャスト製バルコニー7の基端部とともにコンクリート打ちできるように建造物1の4階部分に示すように接合部が空隙になっている。当該4階の部分の点線で示す輪郭はコンクリート打ちをした後の形状を示している。なお一方、建造物1の2,3階部分は、すでにバルコニーと建造物が一体的にコンクリート打ちされた状態を示している。   As shown in FIG. 2, the precast balcony 7 made of precast is thinner than the final completed state, and the base end portion enters the inside of the building from the outer wall of the building 1. As shown in the fourth floor portion of the building 1, the joints are gaps so that the pillars and outer walls of the building 1 can be concreted together with the base end of the precast balcony 7. The outline indicated by the dotted line of the fourth floor portion shows the shape after the concrete is cast. On the other hand, the 2nd and 3rd floor parts of the building 1 already show a state in which the balcony and the building have been concreted integrally.

図1と図2から分かるように、本発明のプレキャスト製バルコニーのスライド工法は、各階のバルコニーに共通したクレーン5がアクセスしやすい場所を搬入領域6とし、下の方の階からバルコニーを取り付けるようにし、2階のバルコニーを取り付ける際は地面に足場2と支持部材3を立て、3階以上の階のバルコニーについては階下のすでに完成したバルコニー上に足場2と支持部材3を立て、さらに立設した支持部材3の上にレール4を敷設し、搬入領域6からプレキャスト製バルコニー7を搬入してはレール4上に載置しては人力によって順次プレキャスト製バルコニー7をレール4に沿ってスライドさせて、奥の方のバルコニー取付場所からプレキャスト製バルコニー7を順次仮固定し、一定の数のプレキャスト製バルコニー7が仮固定された後は、プレキャスト製バルコニー7と建造物1の柱や外壁と一体的にコンクリート打ちする。   As can be seen from FIGS. 1 and 2, in the slide method of the precast balcony of the present invention, the place where the crane 5 common to the balconies on each floor is easily accessible is the carry-in area 6 and the balconies are attached from the lower floor. When installing the balcony on the second floor, stand the scaffold 2 and the support member 3 on the ground. For the balcony on the third and higher floors, set the scaffold 2 and the support member 3 on the already completed balcony, and further upstand The rail 4 is laid on the support member 3, and the precast balcony 7 is carried from the carry-in area 6 and placed on the rail 4. The precast balcony 7 is sequentially slid along the rail 4 by human power. The precast balconies 7 are temporarily fixed in order from the rear balcony mounting location, and a certain number of precast balconies 7 are After being fixed, the pillars and the outer wall integral with the concrete beating of the building 1 and precast made balcony 7.

このようにすることにより、クレーン5がアクセスしやすい場所を搬入領域6と定め、下の方の階のバルコニーから順次プレキャスト製バルコニー7を搬入し、奥の方からプレキャスト製バルコニー7を取り付け、最終的には全階のバルコニーを取り付けることができる。   In this way, a place where the crane 5 is easily accessible is defined as a carry-in area 6, a precast balcony 7 is sequentially carried in from the balcony on the lower floor, a precast balcony 7 is attached from the back, and the final It is possible to install a balcony on all floors.

このように本発明はクレーン5がアクセスしやすい搬入領域6の一カ所から搬入して全階のバルコニー取付場所にプレキャスト製バルコニーを搬送して取り付けることができることは特筆すべきことである。   In this way, it is noteworthy that the present invention can carry the precast balcony from one place of the carry-in area 6 that is easily accessible by the crane 5 and transport and attach the precast balcony to all the balcony attachment places.

次に、本発明による工法の詳細について以下に説明する。   Next, the details of the construction method according to the present invention will be described below.

図3は本発明による工法・装置を詳細に示している。   FIG. 3 shows the construction method and apparatus according to the present invention in detail.

図3に示すように、本発明の工法によってプレキャスト製バルコニーを取り付けるときは、目的とする階の下の階のバルコニーに足場2と、支持部材3と、必要に応じて昇降手段支柱8とを立設する。支持部材3と昇降手段支柱8は連結部材9を介して足場2に連結して安定化させるのが好ましい。   As shown in FIG. 3, when a precast balcony is attached by the method of the present invention, the scaffold 2, the support member 3, and, if necessary, the lifting / lowering means column 8 are attached to the balcony below the target floor. Stand up. The support member 3 and the lifting means support column 8 are preferably connected to the scaffold 2 via the connecting member 9 and stabilized.

支持部材3の上部にはレール4が取り付けられる。レール4の上部にはレール4に沿って滑走可能なローラー10が配置されている。プレキャスト製バルコニー7は前記ローラー10上に載置される。   A rail 4 is attached to the upper part of the support member 3. A roller 10 that can slide along the rail 4 is disposed on the top of the rail 4. The precast balcony 7 is placed on the roller 10.

なお、昇降手段支柱8の上部には受板11が取り付けられており、受板11上に昇降手段の一例としてジャッキ12が設けられている。ここで、昇降手段はジャッキ12に限られず、任意の公知の起重装置あるいはネジとナットを組み合わせた昇降手段を使用してもよい。   A receiving plate 11 is attached to the upper portion of the lifting / lowering means support column 8, and a jack 12 is provided on the receiving plate 11 as an example of the lifting / lowering means. Here, the lifting means is not limited to the jack 12, and any known lifting device or lifting means combining screws and nuts may be used.

足場2は、適当な高さのところに作業員の通路となる天板13を設ける。天板13はレール4に沿って紙面の垂直方向に続いており、作業員はその上部を移動できるようになっている。   The scaffold 2 is provided with a top plate 13 serving as a passage for workers at an appropriate height. The top plate 13 continues along the rail 4 in the direction perpendicular to the paper surface, so that the operator can move the top.

図4に人力によってプレキャスト製バルコニー7をスライドさせて移動させるところを示す。   FIG. 4 shows how the precast balcony 7 is slid and moved by human power.

図4において、足場2は下の階のバルコニー上を建造物の外壁に沿って設けられている。レール4は、間隔をおいて立設された支持部材3の上部に、建造物の外壁に沿って平行に設けられている。レール4上にはレール4に沿って滑走可能なローラー10が配置されている。プレキャスト製バルコニー7は前記ローラー10の上に載置されている。   In FIG. 4, the scaffold 2 is provided on the balcony of the lower floor along the outer wall of the building. The rail 4 is provided in parallel with the outer wall of the building on the upper part of the support member 3 erected at intervals. A roller 10 that can slide along the rail 4 is disposed on the rail 4. The precast balcony 7 is placed on the roller 10.

天板13は、前述したように、足場2に沿って作業員が通行できる通路を形成している。   As described above, the top plate 13 forms a passage through which workers can pass along the scaffold 2.

本発明のプレキャスト製バルコニーのスライド工法によれば、プレキャスト製バルコニーの重さが700kgである場合、約22kg程度の水平方向の力によってプレキャスト製バルコニー7をローラー10の上に乗せたままレール4上をスライドさせられることが実証されている。   According to the slide method of a precast balcony of the present invention, when the weight of the precast balcony is 700 kg, the precast balcony 7 is placed on the roller 10 while being placed on the roller 10 by a horizontal force of about 22 kg. Has been demonstrated to be slid.

したがって、図4に示すように、本発明のプレキャスト製バルコニーのスライド工法によれば、いったんクレーン等によってプレキャスト製バルコニー7をローラー10の上に載置した後は、作業員がプレキャスト製バルコニー7を押しながら天板13上を移動することにより、プレキャスト製バルコニー7はレール4に沿ってスライドして搬送される。   Therefore, as shown in FIG. 4, according to the slide method of the precast balcony of the present invention, after the precast balcony 7 is once placed on the roller 10 by a crane or the like, the worker can remove the precast balcony 7. By moving on the top plate 13 while pushing, the precast balcony 7 slides along the rail 4 and is conveyed.

なお、図3のように足場2を使用する代わりに、図5のように足場2を省略して支持部材3や昇降手段支柱8に直接通路を形成することができる。なお、図5において、図3と同一部分については同一の符号を付している。この場合、図5に示すように、支持部材3や昇降手段支柱8に部材26を横に渡し、その上に足場板27をかけて作業員がプレキャスト製バルコニー7を押して移動する通路を形成する。   Instead of using the scaffold 2 as shown in FIG. 3, the scaffold 2 can be omitted as shown in FIG. 5, and a passage can be formed directly in the support member 3 and the lifting means column 8. In FIG. 5, the same parts as those in FIG. In this case, as shown in FIG. 5, a member 26 is handed over to the support member 3 and the lifting / lowering means support column 8, and a scaffolding plate 27 is placed thereon to form a passage through which the operator moves by pushing the precast balcony 7. .

図6にレール4の敷設の方法を示す。   FIG. 6 shows a method of laying the rail 4.

図6に例示した建造物1は、建物の表と裏にバルコニーを取り付けるようになっている。この場合に、建造物1の角のクレーンがアクセスしやすいところに搬入領域6を設け、建物の表側には直線な搬送路のレール4を設け、建物の側面と裏側にコーナー部を有する搬送路のレール4を設ける。このようにレール4を設けることにより、搬入領域6から順次プレキャスト製バルコニー7を搬入し、レール4に沿って人力でプレキャスト製バルコニー7を押し、建造物1の表側と裏側の双方において奥の方のバルコニー取付場所からプレキャスト製バルコニー7を取り付けることができる。   The building 1 illustrated in FIG. 6 has balconies attached to the front and back of the building. In this case, a carry-in area 6 is provided where the corner crane of the building 1 is easily accessible, a straight conveyance path rail 4 is provided on the front side of the building, and a conveyance path having corner portions on the side and back sides of the building. The rail 4 is provided. By providing the rails 4 in this way, the precast balconies 7 are successively carried in from the carry-in area 6 and the precast balconies 7 are pushed manually along the rails 4, and both the front side and the back side of the building 1 The precast balcony 7 can be mounted from the balcony mounting location.

建造物1の表側のプレキャスト製バルコニー7については、建造物1の表側の搬入領域6でローラー10上にプレキャスト製バルコニー7を載置する際に、プレキャスト製バルコニー7は建造物の外壁からの設計された突出距離に合わせてほぼ正確に載置するようにすれば、バルコニー取付場所に搬送したプレキャスト製バルコニー7をそのまま仮固定することができる。   As for the precast balcony 7 on the front side of the building 1, when the precast balcony 7 is placed on the roller 10 in the carry-in area 6 on the front side of the building 1, the precast balcony 7 is designed from the outer wall of the building. If it is placed almost accurately according to the projected distance, the precast balcony 7 conveyed to the balcony mounting location can be temporarily fixed as it is.

また、建造物1の裏側のプレキャスト製バルコニー7については、コーナー部でプレキャスト製バルコニー7を建造物側面のレール4から建造物裏面のレール4に載置し換える際に、建造物1の裏側の外壁から設計された突出距離に合わせてほぼ正確にプレキャスト製バルコニー7を載置し換えるようにすれば、建造物裏面においてもバルコニー取付場所に搬送したプレキャスト製バルコニー7をそのまま仮固定することができる。   Further, regarding the precast balcony 7 on the back side of the building 1, when the precast balcony 7 is placed on the corner 4 from the rail 4 on the side of the building to the rail 4 on the back of the building, If the precast balcony 7 is placed almost exactly in accordance with the projecting distance designed from the outer wall, the precast balcony 7 conveyed to the balcony mounting location can be temporarily fixed even on the back of the building. .

また、前述のジャッキ12等によってプレキャスト製バルコニー7をその取付場所に搬送した後に、適宜プレキャスト製バルコニー7を昇降させて設計高さに設置することもできる。   In addition, after the precast balcony 7 is transported to the mounting place by the jack 12 or the like, the precast balcony 7 can be appropriately lifted and installed at the design height.

図7は、レール4のコーナー部14を詳細に示している。   FIG. 7 shows the corner portion 14 of the rail 4 in detail.

以下の説明では、便宜上コーナー部14にプレキャスト製バルコニー7を搬入する側のレール4を第1方向のレール4と呼び、コーナー部14からプレキャスト製バルコニー7を搬出する側のレール4を第2方向のレール4と呼ぶ。   In the following description, for convenience, the rail 4 on the side where the precast balcony 7 is carried into the corner portion 14 is referred to as a rail 4 in the first direction, and the rail 4 on the side where the precast balcony 7 is carried out from the corner portion 14 is referred to as the second direction. This is referred to as rail 4.

コーナー部14では、第1方向のレール4と第2方向のレール4は互いに90°をなして交差している。なお、第1方向のレール4と第2方向のレール4の交差の角度は90°と異なる場合も以下の説明が同様に当てはまる。   In the corner portion 14, the rails 4 in the first direction and the rails 4 in the second direction intersect each other at 90 °. In addition, the following description applies similarly when the angle of intersection of the rail 4 in the first direction and the rail 4 in the second direction is different from 90 °.

レール4同士の交差部は、後述するようにローラー10のガイド部材の通過を妨げないようにレールの一部が途切れて間隙4aを有している。   As will be described later, a part of the rail is interrupted at the intersection of the rails 4 so as to prevent the passage of the guide member of the roller 10 and has a gap 4a.

また、コーナー部14の内部では、一時的にプレキャスト製バルコニー7を支承して昇降させる複数のジャッキ12等の昇降手段が設けられている。   Further, inside the corner portion 14, lifting means such as a plurality of jacks 12 that temporarily support and lift the precast balcony 7 are provided.

次に、図7を用いて、コーナー部14でのプレキャスト製バルコニー7の搬送方向の変更方法について説明する。   Next, a method of changing the transport direction of the precast balcony 7 at the corner portion 14 will be described with reference to FIG.

最初に、プレキャスト製バルコニー7を第1方向のレール4に沿ってコーナー部14に搬入する。そして、コーナー部14において、プレキャスト製バルコニー7をジャッキ12によって支承して上昇させて第1方向のレール上のローラー10を取り外す。続いてプレキャスト製バルコニー7の下方の第2方向のレール4の上にローラー10を挿入し、プレキャスト製バルコニー7をジャッキ12によって下降させて第2方向のレール4上に設置したローラ10上に載置し換える。   First, the precast balcony 7 is carried into the corner portion 14 along the rail 4 in the first direction. And in the corner part 14, the precast balcony 7 is supported and lifted with the jack 12, and the roller 10 on the rail of a 1st direction is removed. Subsequently, the roller 10 is inserted on the rail 4 in the second direction below the precast balcony 7, and the precast balcony 7 is lowered by the jack 12 and placed on the roller 10 installed on the rail 4 in the second direction. Replace.

以上の操作により、プレキャスト製バルコニー7は第2方向のレール4の上設置したローラー10に乗ったまま第2方向のレール4に沿って人力によってスライドして移動させられるようになる。   With the above operation, the precast balcony 7 can be slid and moved along the rail 4 in the second direction by human power while riding on the roller 10 installed on the rail 4 in the second direction.

図8(a),8(b)は、ローラー10の構成を詳細に示している。   8A and 8B show the configuration of the roller 10 in detail.

図8(a),8(b)に示すように、ローラー10は、円柱状部分を有する複数の転がり部材15と、各転がり部材15の両端から突出した回転軸16と、各回転軸16の両端部を回転可能に支持する一対の枠部材17と、枠材17から各転がり部材15の外周面に接する面を超えて突設させた少なくとも1対のガイド部材18とを有している。   As shown in FIGS. 8A and 8B, the roller 10 includes a plurality of rolling members 15 having a columnar portion, rotating shafts 16 protruding from both ends of each rolling member 15, and each rotating shaft 16. It has a pair of frame members 17 that rotatably support both ends, and at least one pair of guide members 18 that protrude from the frame member 17 beyond the surface that contacts the outer peripheral surface of each rolling member 15.

図8(b)はローラー10をレール4上に配置した状態を示している。前述のように、ガイド部材18は各転がり部材15の外周面に接する面を超えて突設されているので、ガイド部材18を図8(b)に示すように下方向にレール4の両側に突出するようにローラー10を配置することにより、ローラー10は、転がり部材15がレール4に当接してレール4上で転動し、ガイド部材18によってガイドされてレール4に沿って滑走することができるようになる。滑走においてガイド部材18によってローラー10はレール4から脱落することがない。   FIG. 8B shows a state in which the roller 10 is arranged on the rail 4. As described above, since the guide member 18 protrudes beyond the surface in contact with the outer peripheral surface of each rolling member 15, the guide member 18 is moved downward on both sides of the rail 4 as shown in FIG. By disposing the roller 10 so as to protrude, the roller 10 can slide on the rail 4 while the rolling member 15 abuts on the rail 4 and is guided by the guide member 18 to slide along the rail 4. become able to. The roller 10 does not fall off the rail 4 by the guide member 18 during sliding.

前述したコーナー部14においては、ガイド部材18がレール4の交差部を通過するときに間隙4aを通るので、ローラー10はプレキャスト製バルコニー7を乗せたままプレキャスト製バルコニー7をコーナー部14に搬入及び搬出することができる。   In the corner portion 14 described above, since the guide member 18 passes through the gap 4a when passing through the intersection of the rails 4, the roller 10 carries the precast balcony 7 into the corner portion 14 while the precast balcony 7 is placed on the corner portion 14. Can be carried out.

また、コーナー部14において、ジャッキ12等によってプレキャスト製バルコニー7を上昇させれば、第1方向のレール4のローラー10を容易に抜き去ることができ、代わりに第2方向のレール4のローラー10を挿入することもできる。   Further, if the precast balcony 7 is raised by the jack 12 or the like at the corner portion 14, the roller 10 of the rail 4 in the first direction can be easily removed, and instead the roller 10 of the rail 4 in the second direction. Can also be inserted.

図9は、本発明の他の実施形態によるプレキャスト製バルコニースライド用のレールを示している。   FIG. 9 shows a rail for a precast balcony slide according to another embodiment of the present invention.

このレール19は頂部にローラーを有するものである。   The rail 19 has a roller at the top.

図9に示すように、レール19は、円柱状部分を有する複数の転がり部材20と、各転がり部材20の両端から突出した回転軸21と、各転がり部材の両回転軸21の端部を回転可能に支持する一対の枠部材22とを有するローラー23と、ローラー23の枠部材22を支承する受部材24と、受部材24を支持する支持部材25とを有している。   As shown in FIG. 9, the rail 19 rotates a plurality of rolling members 20 having a columnar portion, a rotating shaft 21 protruding from both ends of each rolling member 20, and ends of both rotating shafts 21 of each rolling member. It has a roller 23 having a pair of frame members 22 that can be supported, a receiving member 24 that supports the frame member 22 of the roller 23, and a support member 25 that supports the receiving member 24.

本実施形態のレール19によれば、ローラー23はプレキャスト製バルコニーとともに移動はしない。レール19のローラー23の部分は受部材24から着脱可能であることが好ましい。この場合、搬送路にそって支持部材25と受部材24のみを間隔をおいて設置し、プレキャスト製バルコニー7が通過する部分のみにローラー23を設置してレール19を形成し、プレキャスト製バルコニーが通過した後にローラー23を取り外して、次にプレキャスト製バルコニーが通過する所の支持部材25と受部材24の上に設置することができる。   According to the rail 19 of this embodiment, the roller 23 does not move with the precast balcony. The part of the roller 23 of the rail 19 is preferably detachable from the receiving member 24. In this case, only the support member 25 and the receiving member 24 are installed at intervals along the conveyance path, the roller 23 is installed only in a portion through which the precast balcony 7 passes, and the rail 19 is formed. After passing, the roller 23 can be removed and placed on the support member 25 and the receiving member 24 where the precast balcony then passes.

また、コーナー部においては、ローラー23のみを取り外しおよび挿入することにより、第1方向のレールから第2方向のレールにプレキャスト製バルコニーを乗せ換えることができる。   Further, in the corner portion, by removing and inserting only the roller 23, the precast balcony can be changed from the rail in the first direction to the rail in the second direction.

1 建造物
2 足場
3 支持部材
4 レール
5 クレーン
6 搬入領域
7 プレキャスト製バルコニー
8 昇降手段支柱
9 連結部材
10 ローラー
11 受板
12 ジャッキ
13 天板
14 コーナー部
15 転がり部材
16 回転軸
17 枠部材
18 ガイド部材
19 レール
20 転がり部材
21 回転軸
22 枠部材
23 ローラー
24 受部材
25 支持部材
26 部材
27 足場板
DESCRIPTION OF SYMBOLS 1 Building 2 Scaffolding 3 Support member 4 Rail 5 Crane 6 Carry-in area 7 Precast balcony 8 Elevating means support column 9 Connecting member 10 Roller 11 Receiving plate 12 Jack 13 Top plate 14 Corner portion 15 Rolling member 16 Rotating shaft 17 Frame member 18 Guide Member 19 Rail 20 Rolling member 21 Rotating shaft 22 Frame member 23 Roller 24 Receiving member 25 Support member 26 Member 27 Scaffold plate

Claims (6)

建造物外壁にほぼ平行にレールを設置する工程と、
前記レール上に、円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材と、前記枠部材から前記各転がり部材の外周面に接する面を超えて下方向に前記レールの両側に突設させた少なくとも1対のガイド部材とを有し、プレキャスト製バルコニーを載置して前記レールに沿って滑走可能なローラーを設置する工程と、
前記ローラー上にプレキャスト製バルコニーを載置する工程と、
前記プレキャスト製バルコニーをスライドさせて取り付け場所に搬送する工程と、
を有することを特徴とするプレキャスト製バルコニーのスライド工法。
A process of installing rails almost parallel to the outer wall of the building;
A plurality of rolling members having a columnar portion on the rail, a rotating shaft projecting from both ends of each rolling member, and a pair of frame members that rotatably support the ends of both rotating shafts of each rolling member And at least one pair of guide members projecting on both sides of the rail in a downward direction beyond the surface contacting the outer peripheral surface of each rolling member from the frame member, and placing a precast balcony Installing a roller capable of sliding along the rail;
Placing a precast balcony on the roller;
Sliding the precast balcony and transporting it to the mounting location;
A slide method of a precast balcony characterized by comprising:
建造物外壁にほぼ平行に、円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材とを有するローラーと、前記ローラーの枠部材を支承する受部材と、前記受部材を支持する支持部材とを有し、前記ローラーは前記受部材から着脱可能に構成されているレールを設置する工程と、
前記ローラー上にプレキャスト製バルコニーを載置する工程と、
前記プレキャスト製バルコニーをスライドさせて取り付け場所に搬送する工程と、
を有することを特徴とするプレキャスト製バルコニーのスライド工法。
A pair of rolling members having a columnar portion substantially parallel to the outer wall of the building, a rotating shaft protruding from both ends of each rolling member, and a pair of rotatably supporting ends of both rotating shafts of each rolling member A roller having a frame member, a receiving member that supports the frame member of the roller, and a support member that supports the receiving member, wherein the roller is configured to be detachable from the receiving member. Installation process;
Placing a precast balcony on the roller;
Sliding the precast balcony and transporting it to the mounting location;
A slide method of a precast balcony characterized by comprising:
前記ローラー上に前記プレキャスト製バルコニーを載置する工程において、プレキャスト製バルコニーは建造物の外壁からの設計された突出距離に合わせてほぼ正確に載置するようにしたことを特徴とする請求項1または2に記載のプレキャスト製バルコニーのスライド工法。   2. The step of placing the precast balcony on the roller, wherein the precast balcony is placed almost accurately according to a designed protruding distance from an outer wall of a building. Or the slide construction method of the precast balcony of 2. 前記プレキャスト製バルコニーを取付場所に搬送した後に昇降手段によって前記プレキャスト製バルコニーを昇降させて設計高さに設置する工程をさらに有することを特徴とする請求項1〜3のいずれかに記載のプレキャスト製バルコニーのスライド工法。   The precast product according to any one of claims 1 to 3, further comprising a step of raising and lowering the precast balcony by an elevating means after the precast balcony is transported to an installation place and installing the precast balcony at a design height. Balcony slide method. 円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材と、前記枠部材から前記各転がり部材の外周面に接する面を超えて下方向にレールの両側に突設させた少なくとも1対のガイド部材とを有し、プレキャスト製バルコニーを載置して前記レールに沿って滑走可能に構成されていることを特徴とするプレキャスト製バルコニースライド用ローラー。   A plurality of rolling members having a cylindrical portion, a rotating shaft projecting from both ends of each rolling member, a pair of frame members rotatably supporting ends of both rotating shafts of each rolling member, and the frame member And at least one pair of guide members projecting downward on both sides of the rail in a downward direction beyond the surface in contact with the outer peripheral surface of each rolling member, and a precast balcony is placed and slides along the rail Precast balcony slide roller, characterized in that it can be configured. 円柱状部分を有する複数の転がり部材と、前記各転がり部材の両端から突出した回転軸と、前記各転がり部材の両回転軸の端部を回転可能に支持する一対の枠部材とを有するローラーと、前記ローラーの枠部材を支承する受部材と、前記受部材を支持する支持部材とを有し、前記ローラーは前記受部材から着脱可能に構成されていることを特徴とするプレキャスト製バルコニースライド用のレール。   A roller having a plurality of rolling members each having a columnar portion, a rotating shaft projecting from both ends of each rolling member, and a pair of frame members that rotatably supports end portions of both rotating shafts of each rolling member; A slide member made of a precast, comprising: a receiving member that supports the frame member of the roller; and a support member that supports the receiving member, wherein the roller is configured to be detachable from the receiving member. Rails.
JP2009161024A 2009-07-07 2009-07-07 Precast balcony slide method and precast balcony slide rollers and rails Expired - Lifetime JP4885259B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009161024A JP4885259B2 (en) 2009-07-07 2009-07-07 Precast balcony slide method and precast balcony slide rollers and rails

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009161024A JP4885259B2 (en) 2009-07-07 2009-07-07 Precast balcony slide method and precast balcony slide rollers and rails

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP2003375964A Division JP4368659B2 (en) 2003-11-05 2003-11-05 Slide method for precast balcony

Publications (2)

Publication Number Publication Date
JP2009221843A true JP2009221843A (en) 2009-10-01
JP4885259B2 JP4885259B2 (en) 2012-02-29

Family

ID=41238897

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009161024A Expired - Lifetime JP4885259B2 (en) 2009-07-07 2009-07-07 Precast balcony slide method and precast balcony slide rollers and rails

Country Status (1)

Country Link
JP (1) JP4885259B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101154386B1 (en) 2011-12-30 2012-06-15 주식회사 포스코에이앤씨건축사사무소 Assemblying structure of module unit and method for remodeling using that
JP2016078711A (en) * 2014-10-19 2016-05-16 上田技研産業株式会社 Carriage for rail construction and method for rail construction with use of the same
CN111764502A (en) * 2020-06-30 2020-10-13 首钢水城钢铁(集团)赛德建设有限公司 Bolt ball net rack and splicing method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101154386B1 (en) 2011-12-30 2012-06-15 주식회사 포스코에이앤씨건축사사무소 Assemblying structure of module unit and method for remodeling using that
JP2016078711A (en) * 2014-10-19 2016-05-16 上田技研産業株式会社 Carriage for rail construction and method for rail construction with use of the same
CN111764502A (en) * 2020-06-30 2020-10-13 首钢水城钢铁(集团)赛德建设有限公司 Bolt ball net rack and splicing method thereof

Also Published As

Publication number Publication date
JP4885259B2 (en) 2012-02-29

Similar Documents

Publication Publication Date Title
JP5051591B2 (en) Precast PC plate erection device for floor slab and its erection method
JP6483177B2 (en) Floor slab replacement device and installation method of floor slab replacement device
JP6503716B2 (en) Demolition system and demolition method
JP4885259B2 (en) Precast balcony slide method and precast balcony slide rollers and rails
KR102144434B1 (en) Installation of temporary apparatus for curtain wall and temporary apparatus for curtain wall
KR101180845B1 (en) Supporting System for Slab Form and Construction Method Using the Same
JP2019210109A (en) Lifting device of heavy load and lifting and conveying method
JP4368659B2 (en) Slide method for precast balcony
JP5940404B2 (en) Construction method of beam members
JP2011153479A (en) Method for repairing exterior wall
JP2005226295A (en) Dismantling method and dismantling device for cylindrical structure
JP2007126708A (en) Method for overhauling and constructing blast furnace
JP6886872B2 (en) Material transfer device, material transfer method
JP2017071488A (en) Device and method for stair lifting of heavy load
JP2015014161A (en) Structure reconstruction method and structure reconstruction system
JP2007083935A (en) Large concrete form moving truck
JP2008063873A (en) Transfer mechanism of ceiling and execution method
KR20200124422A (en) Module lifting system utilizing of a strand jack, and method for vertical transportation of a heavy module using of the same
JP6129130B2 (en) Jacking device and method for conveying heavy object using the same
JP6898161B2 (en) Temporary passage system and repair method for high-rise structures
JP4986029B2 (en) Stock equipment
KR101696155B1 (en) Apparatus for manufacturing double wall precast concrete
JP2008180016A (en) Self-climbing type overhead crane
JP6718392B2 (en) How to suspend and remove concrete slabs
JP2001322115A (en) Site factory facility

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20090728

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20111108

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20111207

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141216

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4885259

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313115

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term