JP2009197499A - Method for manufacturing precast rc column and rc column - Google Patents

Method for manufacturing precast rc column and rc column Download PDF

Info

Publication number
JP2009197499A
JP2009197499A JP2008041069A JP2008041069A JP2009197499A JP 2009197499 A JP2009197499 A JP 2009197499A JP 2008041069 A JP2008041069 A JP 2008041069A JP 2008041069 A JP2008041069 A JP 2008041069A JP 2009197499 A JP2009197499 A JP 2009197499A
Authority
JP
Japan
Prior art keywords
column
main
concrete
precast
tension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008041069A
Other languages
Japanese (ja)
Other versions
JP5185652B2 (en
Inventor
Takeyoshi Korenaga
健好 是永
Kazumasa Imai
和正 今井
Tsutomu Komuro
努 小室
Kazuhiro Kaneda
和浩 金田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2008041069A priority Critical patent/JP5185652B2/en
Publication of JP2009197499A publication Critical patent/JP2009197499A/en
Application granted granted Critical
Publication of JP5185652B2 publication Critical patent/JP5185652B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for manufacturing a precast RC column in which column main reinforcements effectively resist both compression and tension without yielding to a design-basis load even if high-strength reinforcements are not employed, and effectively prevents occurrence of hazardous cracking etc. caused by self shrinkage of concrete. <P>SOLUTION: According to the method for manufacturing the precast RC column, while first main reinforcements 11 to which tension is applied, and second main reinforcements 12 to which no stress is applied, are mixed to each other in a form, concrete is placed in the form, and thereafter the first main reinforcements 11 are released in an initial stage of the material age of the concrete, to thereby introduce prestressing to the concrete. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、高強度コンクリートを用いたプレキャストRC(鉄筋コンクリート)柱の製造方法および上記プレキャストRC柱を相互に接合してなるRC柱に関するものである。   The present invention relates to a method for producing a precast RC (reinforced concrete) column using high-strength concrete and an RC column formed by joining the precast RC columns to each other.

高層RC建物の低層階柱には、建物重量などによる大きな軸力が作用するため、一般に高強度コンクリートが用いられる(例えば特許文献1参照)。
図4は、地震時の柱における曲げモーメントと部材回転角との関係を模式的に示したもので、図中の×印は、部材端圧縮縁かぶりコンクリートが圧壊する時期を示している。この図から分かるように、使用するコンクリートが高強度になるほど、部材耐力および初期の剛性が高くなるとともに、上記かぶりコンクリートが圧壊する変形は小さくなる。
一般に、構造設計では、想定する地震に対して、柱に圧壊(設計終局限界)を生じさせない計画となっている。また、コンクリートの高強度化に伴い、柱に使用する鉄筋強度も大きくなる。これは、柱に生じる曲げモーメントが設計終局限界に達する以前に、圧縮側の主筋が降伏すると、上述した圧壊を誘発させる可能性があり、また中小地震で主筋が圧縮降伏すると、それ以降の長期的な柱の縮み(クリープ等による縮み)を増大させる懸念があるからである。このため、Fc100(設計基準強度が100N/mm2)以上のコンクリートを使用した柱では、主筋として高強度鉄筋USD685が用いられることが多い。
Since a high axial force due to the building weight or the like acts on a low-rise column of a high-rise RC building, high-strength concrete is generally used (see, for example, Patent Document 1).
FIG. 4 schematically shows the relationship between the bending moment in the column at the time of the earthquake and the member rotation angle, and the crosses in the figure indicate the time when the member end compression edge cover concrete collapses. As can be seen from this figure, the higher the strength of the concrete used, the higher the strength of the member and the initial rigidity, and the smaller the deformation that the cover concrete collapses.
In general, the structural design is designed to prevent the column from being crushed (the ultimate design limit) against an assumed earthquake. In addition, as the strength of concrete increases, the strength of the reinforcing bars used for the columns also increases. This is because if the main bar on the compression side yields before the bending moment generated in the column reaches the ultimate design limit, the above-mentioned collapse may be induced. This is because there is a concern of increasing the shrinkage of a typical column (shrinkage due to creep or the like). For this reason, in a column using concrete of Fc100 (design standard strength is 100 N / mm 2 ) or more, a high-strength reinforcing bar USD685 is often used as a main reinforcing bar.

図5は、Fc100超のコンクリートを用いた柱の主筋(USD685)について、地震時の応力履歴を模式的に示したものである。この図に見られるように、高強度鉄筋を主筋に用いているため、設計想定荷重の範囲では、主筋は圧縮降伏することなく弾性範囲内にある。一方、鉄筋の引張側に関しては、かなりの余力があり、鉄筋を圧縮・引張共、有効に使っていないことが分かる。   FIG. 5 schematically shows a stress history at the time of an earthquake for a main bar (USD685) of a column using concrete exceeding Fc100. As can be seen in this figure, since the high-strength reinforcing bar is used as the main reinforcing bar, the main reinforcing bar is in the elastic range without compressive yielding within the range of the assumed design load. On the other hand, on the tension side of the reinforcing bar, there is a considerable reserve, and it can be seen that the reinforcing bar is not used effectively for both compression and tension.

コンクリートの高強度化は、部材断面の縮小化などのメリットがあるが、コンクリートが高強度になるほど初期強度発現時の自己収縮が大きくなる。そのため、RC部材では、収縮低減対策を施さないと、主筋などの鉄筋による変形拘束により、柱製造時にひび割れ(材軸に直交するひび割れ)を生じることもある。収縮低減対策は幾つかあるが、過剰な収縮低減対策を施すと、コンクリートの強度発現を抑制して、コンクリートの超高強度化を阻害する要因にもなり得る。
特開2006−207281号公報
Increasing the strength of concrete has the advantage of reducing the cross section of the member, but the higher the strength of the concrete, the greater the self-shrinkage when the initial strength is developed. Therefore, in the RC member, cracks (cracks perpendicular to the material axis) may be generated during column manufacture due to deformation restraint by reinforcing bars such as main bars unless measures for shrinkage reduction are taken. There are several shrinkage reduction measures. However, if excessive shrinkage reduction measures are taken, it can be a factor that inhibits the development of the strength of the concrete by suppressing the concrete strength.
JP 2006-207281 A

本発明は、かかる事情に鑑みなされたもので、高強度鉄筋を敢えて使用しなくても、設計想定荷重に対して柱主筋を降伏させることなく、圧縮・引張共有効に抵抗させることができ、しかもコンクリートの自己収縮による有害なひび割れ等の発生を効果的に防止することができるプレキャストRC柱の製造方法およびRC柱を提供することを課題とする。   The present invention was made in view of such circumstances, and without using a high-strength reinforcing bar, it is possible to effectively resist compression and tension without yielding the column main reinforcing bar against the design assumed load, Moreover, it is an object of the present invention to provide a precast RC column manufacturing method and an RC column that can effectively prevent the occurrence of harmful cracks due to self-shrinkage of concrete.

請求項1に記載の発明は、プレキャストRC柱の製造方法であって、型枠内に、張力が付与された第1主筋と、無応力状態の第2主筋とを混在配置させた状態で、上記型枠内にコンクリートを打設した後、上記コンクリートの材齢初期段階で上記第1主筋を解放することにより、上記コンクリートにプレストレスを導入することを特徴とするものである。
ここで、上記コンクリートの材齢初期段階とは、材齢1日〜3日程度をいう。ただし、コンクリート強度が高い場合や、大きい緊張力を導入したい場合、またはクリープが懸念される場合には、養生期間を確保する意味で、1週間程度導入を遅らせることもある。
The invention according to claim 1 is a method for manufacturing a precast RC column, wherein the first main bar to which tension is applied and the second main bar in a stress-free state are mixedly arranged in the mold, After placing concrete in the formwork, prestress is introduced into the concrete by releasing the first main reinforcement at an early stage of age of the concrete.
Here, the initial stage of age of the concrete refers to about 1 to 3 days of age. However, when the concrete strength is high, when a large tension is to be introduced, or when there is a concern about creep, the introduction may be delayed for about one week in order to secure a curing period.

請求項2に記載の発明は、請求項1に記載のプレキャストRC柱の製造方法において、上記コンクリートのクリープ安定時期にほぼ無応力状態となるように、上記第1主筋に付与する上記張力を調整することを特徴とするものである。   According to a second aspect of the present invention, in the method for producing a precast RC column according to the first aspect, the tension applied to the first main bar is adjusted so that the concrete is almost free of stress during the creep stabilization time of the concrete. It is characterized by doing.

請求項3に記載の発明は、請求項1に記載のプレキャストRC柱の製造方法において、上記コンクリートのクリープ安定時期に引張応力状態となるように、上記第1主筋に付与する上記張力を調整することを特徴とするものである。   According to a third aspect of the present invention, in the method for producing a precast RC column according to the first aspect, the tension applied to the first main bar is adjusted so that a tensile stress state is obtained during the creep stabilization time of the concrete. It is characterized by this.

請求項4に記載の発明は、張力が付与された第1主筋と、無応力状態の第2主筋とが混在配置されたプレキャストRC柱が相互に接合されてなるRC柱であって、一方のプレキャストRC柱の第1主筋が他方のプレキャストRC柱の第2主筋と同軸上に配置されて両主筋が互いに接合されていることを特徴とするものである。ここで、上記プレキャストRC柱には、請求項1〜3の何れかに記載の製造方法により製造されたプレキャストRC柱が含まれる他、脱型後に第1主筋に張力を付与する、いわゆるポストテンション方式により製造されたプレキャストRC柱も含まれる。   The invention according to claim 4 is an RC column in which a precast RC column in which a first main bar to which tension is applied and a second main bar in a stress-free state are mixed is joined to each other. The first main bar of the precast RC column is disposed coaxially with the second main bar of the other precast RC column, and both main bars are joined to each other. Here, the precast RC column includes the precast RC column manufactured by the manufacturing method according to any one of claims 1 to 3, and so-called post tension that applies tension to the first main bar after demolding. Precast RC columns manufactured by the method are also included.

請求項5に記載の発明は、請求項4に記載のRC柱において、両プレキャストRC柱が階中間部で接合されていることを特徴とするものである。   The invention according to claim 5 is characterized in that, in the RC pillar according to claim 4, both precast RC pillars are joined at the middle part of the floor.

本発明によれば、第1主筋に予め張力を付与するようにしたので、建物竣工時またはその後のクリープ安定時期における第1主筋の応力状態を無応力状態に近付けることができる。したがって、高価なUSD685などの高強度鉄筋を使用しなくても、設計想定荷重に対して第1主筋を降伏させることなく、圧縮・引張共有効に抵抗させることができる。
また、コンクリート打設時に第2主筋を無応力状態としたので、建物竣工時またはその後のクリープ安定時期には第2主筋が圧縮応力状態となり、その結果、地震時には第2主筋が早期に降伏することとなる。このため、地震時には第2主筋が弾塑性変形して履歴減衰効果を発揮することによって、その履歴ループ内の面積に相当する地震エネルギーが減衰されることとなる。
According to the present invention, since the tension is applied to the first main bar in advance, the stress state of the first main bar at the time of building completion or the subsequent creep stabilization time can be brought close to the no-stress state. Therefore, even without using high-strength reinforcing bars such as expensive USD 685, it is possible to effectively resist both compression and tension without yielding the first main reinforcing bar with respect to the assumed design load.
In addition, since the second main bar is in an unstressed state when the concrete is placed, the second main bar is in a compressive stress state at the time of building completion or the subsequent creep stabilization period. As a result, the second main bar yields early during an earthquake. It will be. For this reason, during the earthquake, the second principal muscle is elastically plastically deformed to exhibit a hysteresis damping effect, so that the earthquake energy corresponding to the area in the hysteresis loop is attenuated.

また、コンクリートの材齢初期段階でプレストレスを導入するようにしたので、使用するコンクリートが、初期強度発現時における自己収縮の大きい超高強度のコンクリートであっても、主筋などの拘束による有害なひび割れ等の発生を効果的に防止することができる。したがって、前述したコンクリートの収縮低減対策を不要あるいは最小限とすることができ、それら対策に伴うコンクリートの強度低下を防止することができる。   In addition, since prestress was introduced at the early age of concrete, even if the concrete used is ultra-high-strength concrete with large self-shrinkage at the time of initial strength development, it is harmful due to restraint of the main bars, etc. Generation | occurrence | production of a crack etc. can be prevented effectively. Therefore, the above-described measures for reducing the shrinkage of the concrete can be made unnecessary or minimized, and the strength reduction of the concrete accompanying these measures can be prevented.

図1は、本発明に係る製造方法によって製造されたプレキャストRC柱の一実施形態を示すもので、図中符号1がプレキャストRC柱、符号2が梁である。
このプレキャストRC柱1は、コンクリート硬化体10と、プレテンション方式により予め張力(緊張力)が付与された第1主筋11、配筋時に無応力状態の第2主筋12、帯筋(図示省略)等により概略構成されている。
FIG. 1 shows an embodiment of a precast RC column manufactured by the manufacturing method according to the present invention, in which reference numeral 1 is a precast RC column and reference numeral 2 is a beam.
This precast RC column 1 includes a hardened concrete body 10, a first main bar 11 to which tension (tensile force) is applied in advance by a pre-tension method, a second main bar 12 in a stress-free state at the time of bar arrangement, and a band bar (not shown). Etc. are roughly configured.

第1主筋11および第2主筋12は、プレキャストRC柱1の外周部に沿ってほぼ等間隔に交互に配置され、図1(b)の例では、柱の各角部と、その中間位置に第2主筋12が、それら第2主筋12の間に第1主筋11がそれぞれ配置されている。なお、このプレキャストRC柱1の上端または下端に接合される上下のプレキャストRC柱においては、図1(c)に示すように、第1主筋11と第2主筋12の配置が逆となっている。   The 1st main reinforcement 11 and the 2nd main reinforcement 12 are alternately arrange | positioned at equal intervals along the outer peripheral part of the precast RC pillar 1, and in the example of FIG.1 (b), it exists in each corner | angular part of a pillar, and its intermediate position. The first main muscles 11 are arranged between the second main muscles 12 and the second main muscles 12 respectively. In addition, in the upper and lower precast RC columns joined to the upper end or the lower end of the precast RC column 1, as shown in FIG. 1 (c), the arrangement of the first main bars 11 and the second main bars 12 is reversed. .

第1主筋11は、上記張力が材軸方向に一様になるよう、その両端部に鉄筋貫通型の定着金物13を有している。この定着金物13には、既製のナットと定着版を組み合わせたものを使用することもできる。
一方、第2主筋12は、その両端部に鉄筋継手金物14を有している。この鉄筋継手金物14は管状に形成されて、その一方の開口から第2主筋12を挿入した状態で第2主筋12と一体化されている。鉄筋継手金物14の他方の開口からは、隣接するプレキャストRC柱の端面から突出する第1主筋11の先端部が挿入可能となっており、当該第1主筋11を挿入した状態で鉄筋継手金物14の内部にグラウトを注入することにより、当該第1主筋11が上記第2主筋12に接合されるようになっている。
The first main bar 11 has a reinforcing bar penetration type fixing metal 13 at both ends so that the tension is uniform in the material axis direction. As the fixing metal 13, a combination of a ready-made nut and a fixing plate can be used.
On the other hand, the 2nd main reinforcement 12 has the reinforcement joint metal fitting 14 in the both ends. The rebar joint hardware 14 is formed in a tubular shape, and is integrated with the second main bar 12 with the second main bar 12 inserted from one opening thereof. From the other opening of the reinforcing bar joint 14, the tip of the first main bar 11 protruding from the end face of the adjacent precast RC column can be inserted. With the first main bar 11 inserted, the reinforcing bar joint 14 The first main muscle 11 is joined to the second main muscle 12 by injecting grout into the inside.

第1主筋11、第2主筋12とも、使用する鉄筋の強度は、設計条件および設計応力に応じてSD345〜685を適宜選択することができる。また、本発明で使用するコンクリートの適用範囲は特に規定しないが、従来工法で高強度鉄筋を使用する可能性のあるFc60〜200が有効であり、強度増大に伴う自己収縮の影響を勘案すると、その強度が高いほど(例えばFc150以上)本発明による効果が大きいと考えられる。   For both the first main bar 11 and the second main bar 12, the strength of the reinforcing bar to be used can be appropriately selected from SD 345 to 685 depending on the design conditions and the design stress. In addition, although the application range of concrete used in the present invention is not particularly specified, Fc 60 to 200 that may use high-strength reinforcing bars in the conventional construction method is effective, and considering the influence of self-shrinkage accompanying the increase in strength, It is considered that the higher the strength (for example, Fc150 or more), the greater the effect of the present invention.

なお、本実施形態では、上記プレキャストRC柱1を、図1(a)に示すように、その上下に位置する他のプレキャストRC柱と、地震時応力の少ない各階中間部で接合することによりRC柱を構成している。このため、設計応力如何によっては、第1主筋11の定着金物13を省いて当該鉄筋の定着力で応力伝達する構成としたり、或いは第2主筋12の継手金物14を一部省略してメタルタッチにより接合することも可能である。   In this embodiment, as shown in FIG. 1A, the precast RC pillar 1 is joined to other precast RC pillars located above and below the middle part of each floor with low earthquake stress. It constitutes a pillar. Therefore, depending on the design stress, the fixing metal 13 of the first main reinforcing bar 11 may be omitted to transmit the stress by the fixing force of the reinforcing bar, or the metal fitting 14 may be partially omitted from the fitting 14 of the second main reinforcing bar 12. Can also be joined.

次に、上記構成からなるプレキャストRC柱1の製造方法について説明する。
先ず、図示省略の型枠内に、上述した第1主筋11および第2主筋12、帯筋等の鉄筋を配置する。この際に、第1主筋11が両端から引っ張られて張力が付与された状態、第2主筋12が無応力状態となるように各々を配置する(第1工程)。
次いで、上記型枠内にコンクリートを打設して(第2工程)、このコンクリートの材齢初期段階で、第1主筋11を解放して上記張力を解除することにより、コンクリートにプレストレスを導入する(第3工程)。その後、上記型枠を解体することにより(第4工程)、本実施形態のプレキャストRC柱1を得ることができる。
Next, the manufacturing method of the precast RC pillar 1 which consists of the said structure is demonstrated.
First, the reinforcing bars such as the first main bar 11 and the second main bar 12 and the band bars described above are placed in a formwork not shown. At this time, each of the first main muscles 11 is disposed so that the first main muscle 11 is pulled from both ends and tension is applied, and the second main muscle 12 is in an unstressed state (first step).
Next, concrete is placed in the formwork (second step), and prestress is introduced into the concrete by releasing the first main bar 11 and releasing the tension at the early stage of the concrete age. (Third step). Then, the precast RC pillar 1 of this embodiment can be obtained by disassembling the said formwork (4th process).

ここで、上記第1主筋11に付与する張力は、図2(a)に示すように、建物竣工時またはその後のクリープ安定時期にほぼ無応力状態となるように調整する。すなわち、プレストレスの導入から建物竣工時またはその後のクリープ安定時期に至るまでの間に、建物重量などによってプレキャストRC柱1が縮み、その縮み量に応じて第1主筋11の張力が減少することとなるので、その減少分に相当する強さの張力を予め第1主筋11に付与しておく。
その結果、クリープ安定時期には第1主筋11をほぼ無応力状態とすることができ、設計想定荷重に対して第1主筋11を圧縮・引張共有効に抵抗させることができる。例えば、第1主筋11の強度がSD390〜490程度であっても、図2(a)に示すように、設計想定地震ではこの第1主筋11の変形を弾性範囲内に抑えることができる。
Here, as shown in FIG. 2 (a), the tension applied to the first main bar 11 is adjusted so as to be in a substantially no-stress state at the time of building completion or at the subsequent creep stabilization time. That is, between the introduction of prestress and the completion of the building or the subsequent creep stabilization period, the precast RC column 1 contracts due to the weight of the building and the tension of the first main reinforcement 11 decreases according to the amount of contraction. Therefore, a tension having a strength corresponding to the decrease is applied to the first main muscle 11 in advance.
As a result, the first main bar 11 can be brought into a substantially no-stress state during the creep stabilization period, and the first main bar 11 can be effectively resisted against the assumed design load in both compression and tension. For example, even if the strength of the first main bar 11 is about SD390 to 490, as shown in FIG. 2A, the deformation of the first main bar 11 can be suppressed within the elastic range in the design assumed earthquake.

一方、第2主筋12に関しては、プレキャストRC柱1に縮みが生じることにより、図2(b)に示すように、建物竣工時またはその後のクリープ安定時期に圧縮応力状態となるため、地震時には早期に圧縮降伏することとなる。このため、地震時には第2主筋12が弾塑性変形して履歴減衰効果を発揮することによって、その履歴ループ内の面積に相当する地震エネルギーが減衰されることとなる。   On the other hand, as the second main reinforcement 12 is contracted in the precast RC column 1, as shown in FIG. 2 (b), it becomes a compressive stress state at the time of completion of the building or the subsequent creep stabilization time. Compression yields. For this reason, during the earthquake, the second main muscle 12 is elastically plastically deformed to exhibit a hysteresis damping effect, whereby the earthquake energy corresponding to the area in the hysteresis loop is attenuated.

なお、上記第3工程において、第1主筋11によりコンクリートに導入される圧縮応力(プレストレス)は、多くの場合、断面の平均応力で5N/mm2以下となるため、例えばFc60以上のコンクリートを対象とする場合には、コンクリートの強度発現過程の初期段階(材齢1〜3日)で導入可能である。この材齢初期段階でプレストレスを導入することにより、コンクリートの自己収縮に伴う有害なひび割れ等の発生を防止することができ、品質の高い安定したプレキャストRC柱1を製造することができる。 In the third step, the compressive stress (prestress) introduced into the concrete by the first main reinforcement 11 is often 5 N / mm 2 or less in terms of the average stress of the cross section. In the case of a target, it can be introduced at the initial stage of the concrete strength development process (age 1 to 3 days). By introducing prestress at this early stage of age, it is possible to prevent the occurrence of harmful cracks due to the self-shrinkage of the concrete, and to manufacture a high-quality and stable precast RC pillar 1.

以上のように、本実施形態によれば、プレテンション方式により予め張力が付与された第1主筋11と、配筋時無応力状態の第2主筋12(地震時にのみ抵抗する鉄筋)とを混在させるようにしたので、高価なUSD685などの高強度鉄筋を使用しなくても、設計想定荷重に対して第1主筋11を降伏させることなく、圧縮・引張共有効に抵抗させることができる。よって、プレキャストRC柱1の製造コストを低減することができる。   As described above, according to the present embodiment, the first main bar 11 to which tension is applied in advance by the pre-tension method and the second main bar 12 in the unstressed state during reinforcement (reinforcing bar that resists only during an earthquake) are mixed. Therefore, even without using high-strength reinforcing bars such as expensive USD685, it is possible to effectively resist compression and tension without yielding the first main reinforcing bars 11 with respect to the design assumed load. Therefore, the manufacturing cost of the precast RC pillar 1 can be reduced.

また、コンクリートの材齢初期段階でプレストレスを導入するようにしたので、使用するコンクリートが、初期強度発現時における自己収縮の大きい超高強度のコンクリートであっても、主筋などの拘束による有害なひび割れ等の発生を効果的に防止することができる。したがって、前述したコンクリートの収縮低減対策を不要あるいは最小限とすることができ、それら対策に伴うコンクリートの強度低下を防止することができる。   In addition, since prestress was introduced at the early age of concrete, even if the concrete used is ultra-high-strength concrete with large self-shrinkage at the time of initial strength development, it is harmful due to restraint of the main bars, etc. Generation | occurrence | production of a crack etc. can be prevented effectively. Therefore, the above-described measures for reducing the shrinkage of the concrete can be made unnecessary or minimized, and the strength reduction of the concrete accompanying these measures can be prevented.

さらに、プレキャストRC柱1の接合部を地震時応力の少ない各階中間部に設ける構成として、1つの接合部に必要となる継手金物を、上階柱下端部と下階柱上端部とに分けて配置したので、1箇所の柱端部あたりの継手金物が従来工法(全主筋接合)よりも少なくて済み、その結果、グラウト注入用ホースの設置(配筋との取り合い)が容易となる。
また、本実施形態では、互いに接合されるプレキャストRC柱の一方の第1主筋11と、他方の第2主筋12とを同軸上に配置して両主筋11、12を互いに接合する方式としたので、一方の第1主筋11の張力導入時に用いる突出部11a(図1参照)を、他方の第2主筋12の継手金物14内に挿入して互いを接合できる。
Furthermore, as a structure in which the joint part of the precast RC column 1 is provided in each middle part of the floor where the stress at the time of earthquake is low, the joint hardware necessary for one joint part is divided into the upper floor column lower end part and the lower floor pillar upper end part. Since it has been arranged, there is less joint hardware per column end than at the conventional method (all main reinforcement joints), and as a result, installation of the grout injection hose (combination with reinforcement) becomes easy.
Moreover, in this embodiment, since it was set as the system which arrange | positions the 1st main reinforcement 11 of the precast RC pillar mutually joined, and the other 2nd main reinforcement 12 on the same axis | shaft, and joins both main reinforcements 11 and 12 mutually. The protruding portion 11a (see FIG. 1) used at the time of introducing the tension of one of the first main bars 11 can be inserted into the joint hardware 14 of the other second main bar 12 to join each other.

なお、本実施形態では、第1主筋11と第2主筋12を同じ本数としているが、設計上は設計外力に対して柱の設計耐力などを勘案し、適時にその割合を変更するようにしてもよい。両主筋11、12の本数が異なる場合には、本発明に係るプレキャストRC柱1を、従来工法によるプレキャストRC柱と組み合わせて部分的に使用することも可能である。   In the present embodiment, the first main bars 11 and the second main bars 12 are the same number, but in terms of design, the design strength of the column is taken into consideration with respect to the design external force, and the ratio is changed in a timely manner. Also good. When the numbers of the main reinforcing bars 11 and 12 are different, the precast RC column 1 according to the present invention can be partially used in combination with a precast RC column by a conventional construction method.

また、本実施形態では、建物竣工時またはその後のクリープ安定時期にほぼ無応力状態となるように、第1主筋11に付与する張力を調整するようにしたが、本発明はこれに限定されるものではなく、例えば、建物竣工時またはその後のクリープ安定時期に引張応力状態となるように、第1主筋11に付与する張力を調整することも可能である。この場合、第1主筋11の引張降伏を促進させることが可能である。   Moreover, in this embodiment, although the tension | tensile_strength provided to the 1st main reinforcement 11 was adjusted so that it might be in a no-stress state at the time of completion of a building, or the subsequent creep stable period, this invention is limited to this. For example, it is also possible to adjust the tension to be applied to the first main bar 11 so that a tensile stress state is obtained when the building is completed or at the subsequent creep stabilization time. In this case, it is possible to promote the tensile yielding of the first main reinforcement 11.

このように、本発明においては、第1主筋11の張力や両主筋11、12の本数割合を設計条件によって調整することにより、より効率的且つ合理的なプレキャストRC柱の設計が可能である。柱の主筋量は、使用する鉄筋の本数だけではなく径によって調整することが断面配筋上有効である。また、地震時に高圧縮・高引張力が作用する建物隅柱などに本発明を適用する場合には、高強度鉄筋(SD490またはUSD685)を芯鉄筋として別途配筋する従来工法と組み合わせて適用することも可能である。   Thus, in the present invention, the precast RC column can be designed more efficiently and rationally by adjusting the tension of the first main muscle 11 and the ratio of the number of both main muscles 11 and 12 according to the design conditions. It is effective in terms of cross-section reinforcement to adjust the main bar amount of the column not only by the number of reinforcing bars to be used but also by the diameter. In addition, when the present invention is applied to a building corner column that is subjected to high compression and high tensile force during an earthquake, it is applied in combination with a conventional method in which a high-strength reinforcing bar (SD490 or USD685) is separately arranged as a core reinforcing bar. It is also possible.

また、本発明に係るプレキャストRC柱1では、その接合部に変形が集中することが懸念されるため、原則として接合部は層中間部に設けることが望ましいが、一般のプレキャスト複合工法のように、建物各層における部材端部で接合を行う場合には、第2主筋12として高強度鉄筋(SD490またはUSD685)を使用するようにしてもよい。また、本実施形態では、1層1節のプレキャストRC柱1(図1)を例示したが、本発明はこれに限られるものではなく、例えば、コンクリートの高強度化に伴い、柱断面を縮小する設計を採用した場合には、部材の軽量化により、図3に示すように、2層1節のプレキャストRC柱とすることも可能である。   Further, in the precast RC column 1 according to the present invention, since there is a concern that deformation concentrates on the joint, it is desirable to provide the joint in the middle part of the layer in principle, but like a general precast composite method When joining at the end of the member in each layer of the building, a high-strength reinforcing bar (SD490 or USD685) may be used as the second main reinforcing bar 12. In the present embodiment, the precast RC column 1 (FIG. 1) having one layer and one node is illustrated, but the present invention is not limited to this, and for example, the column cross-section is reduced as the strength of concrete increases. In the case of adopting such a design, it is possible to use a precast RC pillar having two layers and one joint as shown in FIG. 3 by reducing the weight of the member.

本発明に係る製造方法によって製造されたプレキャストRC柱の一実施形態を示すもので、(a)は縦断面図、(b)は(a)のA−A線に沿った断面図、(c)は(a)のB−B線に沿った断面図である。An embodiment of the precast RC pillar manufactured by the manufacturing method concerning the present invention is shown, (a) is a longitudinal section, (b) is a sectional view which met an AA line of (a), (c) ) Is a cross-sectional view taken along line BB in FIG. 図1のプレキャストRC柱の各主筋の応力履歴を模式的に示すもので、(a)は第1主筋の応力履歴、(b)は第2主筋の応力履歴である。The stress history of each main reinforcement of the precast RC pillar of Drawing 1 is shown typically, (a) is the stress history of the 1st main reinforcement, and (b) is the stress history of the 2nd main reinforcement. 図1のプレキャストRC柱の変形例を示すもので、(a)は縦断面図、(b)は(a)のA−A線に沿った断面図、(c)は(a)のB−B線に沿った断面図である。1A and 1B show a modification of the precast RC column in FIG. 1, wherein FIG. 1A is a longitudinal sectional view, FIG. 1B is a sectional view taken along line AA in FIG. 1A, and FIG. It is sectional drawing along a B line. 地震時の柱における曲げモーメントと部材回転角との関係を模式的に示したグラフである。It is the graph which showed typically the relation between the bending moment in a pillar at the time of an earthquake, and member rotation angle. 超高強度コンクリートを用いた従来のRC柱の高強度主筋(USD685)の応力履歴を模式的に示したグラフである。It is the graph which showed typically the stress history of the high-strength main reinforcement (USD685) of the conventional RC pillar using ultra-high-strength concrete.

符号の説明Explanation of symbols

1 プレキャストRC柱
11 第1主筋
12 第2主筋
1 Precast RC column 11 1st main bar 12 2nd main bar

Claims (5)

プレキャストRC柱の製造方法であって、型枠内に、張力が付与された第1主筋と、無応力状態の第2主筋とを混在配置させた状態で、上記型枠内にコンクリートを打設した後、上記コンクリートの材齢初期段階で上記第1主筋を解放することにより、上記コンクリートにプレストレスを導入することを特徴とするプレキャストRC柱の製造方法。   A method for manufacturing a precast RC column, in which concrete is placed in the formwork in a state in which the first main bar to which tension is applied and the second main bar in a stress-free state are mixedly arranged. Then, prestress is introduced into the concrete by releasing the first main bars in the early stage of age of the concrete. 上記コンクリートのクリープ安定時期にほぼ無応力状態となるように、上記第1主筋に付与する上記張力を調整することを特徴とする請求項1に記載のプレキャストRC柱の製造方法。   The method for producing a precast RC column according to claim 1, wherein the tension applied to the first main reinforcing bar is adjusted so that the concrete becomes substantially stress-free during the creep stabilization time of the concrete. 上記コンクリートのクリープ安定時期に引張応力状態となるように、上記第1主筋に付与する上記張力を調整することを特徴とする請求項1に記載のプレキャストRC柱の製造方法。   The method for producing a precast RC column according to claim 1, wherein the tension applied to the first main reinforcement is adjusted so that a tensile stress state is obtained during the creep stabilization time of the concrete. 張力が付与された第1主筋と、無応力状態の第2主筋とが混在配置されたプレキャストRC柱が相互に接合されてなるRC柱であって、一方のプレキャストRC柱の第1主筋が他方のプレキャストRC柱の第2主筋と同軸上に配置されて両主筋が互いに接合されていることを特徴とするRC柱。   A precast RC column in which a first main bar to which tension is applied and a second main bar in an unstressed state are mixedly mixed is an RC column, and the first main bar of one precast RC column is the other An RC column which is arranged coaxially with the second main bar of the precast RC column and is joined to each other. 両プレキャストRC柱が階中間部で接合されていることを特徴とする請求項4に記載のRC柱。   The RC pillar according to claim 4, wherein both precast RC pillars are joined at an intermediate part of the floor.
JP2008041069A 2008-02-22 2008-02-22 Precast RC pillar manufacturing method and RC pillar Expired - Fee Related JP5185652B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008041069A JP5185652B2 (en) 2008-02-22 2008-02-22 Precast RC pillar manufacturing method and RC pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008041069A JP5185652B2 (en) 2008-02-22 2008-02-22 Precast RC pillar manufacturing method and RC pillar

Publications (2)

Publication Number Publication Date
JP2009197499A true JP2009197499A (en) 2009-09-03
JP5185652B2 JP5185652B2 (en) 2013-04-17

Family

ID=41141300

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008041069A Expired - Fee Related JP5185652B2 (en) 2008-02-22 2008-02-22 Precast RC pillar manufacturing method and RC pillar

Country Status (1)

Country Link
JP (1) JP5185652B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013240921A (en) * 2012-05-21 2013-12-05 Kajima Corp Pretensioning type prestressed concrete member
JP2014114612A (en) * 2012-12-10 2014-06-26 Taisei Corp Crimp joint structure
JP2019011590A (en) * 2017-06-29 2019-01-24 株式会社フジタ Building structure
JP2020056165A (en) * 2018-09-28 2020-04-09 株式会社フジタ Construction method for building

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09105173A (en) * 1995-10-09 1997-04-22 Ando Corp Connecting section structure of precast prestressed reinforced-concrete frame

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09105173A (en) * 1995-10-09 1997-04-22 Ando Corp Connecting section structure of precast prestressed reinforced-concrete frame

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013240921A (en) * 2012-05-21 2013-12-05 Kajima Corp Pretensioning type prestressed concrete member
JP2014114612A (en) * 2012-12-10 2014-06-26 Taisei Corp Crimp joint structure
JP2019011590A (en) * 2017-06-29 2019-01-24 株式会社フジタ Building structure
JP2020056165A (en) * 2018-09-28 2020-04-09 株式会社フジタ Construction method for building
JP7220044B2 (en) 2018-09-28 2023-02-09 株式会社フジタ Building construction method

Also Published As

Publication number Publication date
JP5185652B2 (en) 2013-04-17

Similar Documents

Publication Publication Date Title
KR102571298B1 (en) Method of introducing prestress to beam-column joint in triaxial compression
KR102640461B1 (en) Method of introducing prestress to beam-column joint of pc structure in triaxial compression
JP5185652B2 (en) Precast RC pillar manufacturing method and RC pillar
KR101353266B1 (en) Coupling beam of shear wall with precast varlable-angle reinforcements using engineered cementitious composites
JP4826375B2 (en) Plastic hinge structure of concrete structure and manufacturing method of precast formwork
JP6227452B2 (en) Wall pillar structure
JP4819605B2 (en) Precast prestressed concrete beams using tendons with different strength at the end and center
JP2012057443A (en) Steel pipe reinforced concrete composite pile and manufacturing method for the same
JP5290097B2 (en) Brace type damping damper
JP2009215748A (en) Composite structure beam, and building structure having composite structure beam
JP6357357B2 (en) Concrete structure
JP2017020332A (en) Reinforcing structure
JP2005207016A (en) Buckling restraint brace member
JP5922993B2 (en) Structure and lining method using multiple fine crack type fiber reinforced cement composites
JP2011084900A (en) Mounting structure of buckling restraining brace and construction method of the same
JP5024617B2 (en) Prestressed concrete beam and its construction method
JP2007077628A (en) Joint structure of joint and its construction method
JP6012353B2 (en) Composite column structure and composite column construction method
JP3938718B2 (en) Reinforced concrete beam structure
JP2005155058A (en) Beam member of rc structure
JP2011202471A (en) Structural member
JPH0674620B2 (en) Reinforced concrete columns covered with steel pipes
JP2009121090A (en) Reinforced concrete column
JP7393816B2 (en) Structural base material, structural member, structure, and construction method of structural member
JP2762906B2 (en) RC frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20100315

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120410

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120516

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120904

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121017

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130115

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130118

R150 Certificate of patent or registration of utility model

Ref document number: 5185652

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20190125

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees