JP2007217883A JP2006036820A JP2006036820A JP2007217883A JP 2007217883 A JP2007217883 A JP 2007217883A JP 2006036820 A JP2006036820 A JP 2006036820A JP 2006036820 A JP2006036820 A JP 2006036820A JP 2007217883 A JP2007217883 A JP 2007217883A
Authority
JP
Japan
Prior art keywords
steel material
floor slab
floor
void
jack mechanism
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2006036820A
Other languages
Japanese (ja)
Inventor
Koji Yamanobe
宏治 山野辺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2006036820A priority Critical patent/JP2007217883A/en
Publication of JP2007217883A publication Critical patent/JP2007217883A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a floor structure which dispenses with protection against external factors, secures wide effective space in a building, controls long-term deflection of a floor, and ensures a high-quality space. <P>SOLUTION: According to the floor structure, a prestressing steel 2 extending like a catenary curve, is arranged in a floor slab 1, and the prestressing steel 2 has tensioning force introduced thereto, to thereby apply prestress to the floor slab 1. Herein the prestressing steel 2 is inserted into a void space V1 secured in the floor slab 1, and jack mechanisms 6, 6 for moving part of the prestressing steel 2 in the vertical direction are set in the floor slab 1. <P>COPYRIGHT: (C)2007,JPO&INPIT

Description

本発明は、プレストレスを付与した床構造に関する。   The present invention relates to a floor structure to which prestress is applied.

一般に、コンクリート系の大スパン梁又は床の鉛直たわみを抑制するために、PC鋼材によるプレストレスによって鉛直たわみを抑制する技術が種々提供されている。この技術は、PC鋼材に引張力を導入して構造体に計画的に圧縮応力を与えて、たわみが生じる際の引張応力と相互に打ち消し合うように設計するものである(例えば、特許文献1参照。)。   In general, in order to suppress vertical deflection of a concrete-type large-span beam or floor, various techniques for suppressing vertical deflection by prestressing with PC steel are provided. This technique is designed so that a tensile force is introduced into a PC steel material and a compressive stress is applied to the structure in a planned manner so as to cancel each other with the tensile stress when the deflection occurs (for example, Patent Document 1). reference.).

上記した技術では、コンクリートのクリープや乾燥収縮による長期たわみの実情に合わせて、PC鋼材によるプレストレスを調整することは稀であるが、積載荷重の変動が大きい倉庫等の大スパン構造物では、梁に作用する荷重に応じてプレストレスを調整しなければ、梁のたわみを適切に制御することができない。そこで、従来、PC鋼材を、懸垂曲線状に延在させた状態(両端を固定して中央を下向きに弛ませた状態)で、梁の外側に配置するとともに、PC鋼材のライズを調整する調整装置を設置する技術が提供されている。この技術によれば、懸垂曲線状に延在するPC鋼材に緊張力(引張力)が導入されるため、梁に上向きのプレストレス(吊り上げ力)が付与されて梁のたわみが抑制されるとともに、調整装置によってPC鋼材のライズを調整することで、梁に付与されるプレストレスが調整されるため、梁のたわみが適正に制御される(例えば、特許文献2参照。)。
特開平5−106270号公報 特開平11−241507号公報
In the above technology, it is rare to adjust the prestress due to PC steel in accordance with the actual condition of long-term deflection due to creep or drying shrinkage of concrete, but in large-span structures such as warehouses with large load load fluctuations If the prestress is not adjusted according to the load acting on the beam, the deflection of the beam cannot be controlled appropriately. Therefore, conventionally, the PC steel material is placed outside the beam in a state of extending in a catenary curve shape (the state where both ends are fixed and the center is slackened downward), and adjustment for adjusting the rise of the PC steel material Techniques for installing the device are provided. According to this technique, since tensile force (tensile force) is introduced into the PC steel material extending in a suspended curve shape, upward prestress (lifting force) is applied to the beam to suppress the deflection of the beam. The prestress imparted to the beam is adjusted by adjusting the rise of the PC steel material by the adjusting device, so that the deflection of the beam is appropriately controlled (see, for example, Patent Document 2).
JP-A-5-106270 JP-A-11-241507

しかしながら、上記した従来の技術では、PC鋼材や調整装置が梁の外側に配置されているため、外的要因に対する保護が必要となる。さらに、PC鋼材や調整装置の分だけ、建物内部の有効空間が狭くなるという問題が存在する。また、大スパンの床は梁よりも長期たわみが大きくなる場合が多いため、梁のたわみを制御するだけでは品質の高い空間を保証することができないという問題がある。   However, in the above-described conventional technology, since the PC steel material and the adjusting device are arranged outside the beam, it is necessary to protect against external factors. In addition, there is a problem that the effective space inside the building is narrowed by the amount of PC steel and adjusting device. In addition, since a long span floor often has a longer-term deflection than a beam, there is a problem that a high-quality space cannot be guaranteed only by controlling the beam deflection.

本発明は、上記した従来の問題が考慮されたものであり、外的要因に対する保護を不要にすることができるとともに、建物内部の有効空間を広くとることができ、さらに、床の長期たわみの制御を可能にし、品質の高い空間を保証することができる床構造を提供することを目的としている。   The present invention takes the above-mentioned conventional problems into consideration, can eliminate the need for protection against external factors, can take a wide effective space inside the building, and can further prevent a long-term deflection of the floor. The object is to provide a floor structure that allows control and guarantees a high-quality space.

請求項1記載の発明は、床版に、懸垂曲線状に延在するPC鋼材が設置され、該PC鋼材に緊張力が導入されて床版にプレストレスが付与されている床構造において、PC鋼材が床版に形成されたボイド空間に挿通されており、PC鋼材の一部を上下方向に移動させるジャッキ機構が床版の内部に設置されていることを特徴としている。   The invention according to claim 1 is a floor structure in which a PC steel material extending in a hanging curve shape is installed on a floor slab, and a tensile force is introduced into the PC steel material so that prestress is applied to the floor slab. The steel material is inserted into a void space formed in the floor slab, and a jack mechanism for moving a part of the PC steel material in the vertical direction is installed inside the floor slab.

このような特徴により、PC鋼材やジャッキ機構は、床版の外に設置されず、床版内部に設置される。また、ジャッキ機構によってPC鋼材のライズや緊張力が調整され、床版に付与されるプレストレスが制御される。   Due to such characteristics, the PC steel material and the jack mechanism are not installed outside the floor slab, but are installed inside the floor slab. Moreover, the rise and tension of the PC steel material are adjusted by the jack mechanism, and the prestress applied to the floor slab is controlled.

請求項2記載の発明は、請求項1記載の床構造において、ボイド空間を形成するボイド部材にジャッキ機構が取り付けられ、少なくともジャッキ機構とボイド部材とがユニット化されていることを特徴としている。   The invention according to claim 2 is characterized in that, in the floor structure according to claim 1, a jack mechanism is attached to a void member forming a void space, and at least the jack mechanism and the void member are unitized.

このような特徴により、床構造を形成する際、ジャッキ機構とボイド部材とをユニット化したものを床版の所定位置に設置するだけでよい。   Due to such a feature, when the floor structure is formed, it is only necessary to install the jack mechanism and the void member as a unit at a predetermined position of the floor slab.

本発明に係る床構造によれば、PC鋼材やジャッキ機構が床版の内部にそれぞれ設置されるため、PC鋼材やジャッキ機構を外的要因から保護するケース等が不要であるとともに、建物内部の有効空間を広くとることができる。また、ジャッキ機構によって床版に付与するプレストレスが調整されるため、積載荷重に応じてジャッキ機構を調整することで、床の長期たわみの制御を行うことができ、品質の高い空間を保証することができる。   According to the floor structure according to the present invention, since the PC steel material and the jack mechanism are respectively installed inside the floor slab, a case for protecting the PC steel material and the jack mechanism from external factors is unnecessary, and the inside of the building The effective space can be widened. In addition, since the prestress applied to the floor slab is adjusted by the jack mechanism, it is possible to control the long-term deflection of the floor by adjusting the jack mechanism according to the loaded load, and to guarantee a high-quality space. be able to.

また、ジャッキ機構とボイド部材とをユニット化させることにより、床構造を形成する際、ユニット化されたものを床版の所定位置に設置するだけで、ボイド空間が形成されるとともにジャッキ機構が設置されるため、床構造の施工性(生産性)を向上させることができる。   In addition, when the floor structure is formed by unitizing the jack mechanism and the void member, the void space is formed and the jack mechanism is installed simply by installing the unitized structure at a predetermined position on the floor slab. Therefore, the workability (productivity) of the floor structure can be improved.

以下、本発明に係る床構造の実施の形態について、図面に基いて説明する。
なお、図1は本発明の実施の形態に係る床構造を表す断面図であり、図2は図1のA−A間の断面図であり、図3は図1のB−B間の断面図であり、図4は図1のC−C間の断面図である。
Hereinafter, embodiments of a floor structure according to the present invention will be described with reference to the drawings.
1 is a cross-sectional view showing a floor structure according to an embodiment of the present invention, FIG. 2 is a cross-sectional view taken along line AA in FIG. 1, and FIG. 3 is a cross-sectional view taken along line BB in FIG. FIG. 4 is a cross-sectional view taken along the line CC in FIG.

図1,図2,図3,図4に示すように、本実施の形態における床構造は、床版1に複数(図2〜図4では2本)のPC鋼材2,2が設置された構成からなる。   As shown in FIGS. 1, 2, 3, and 4, in the floor structure in the present embodiment, a plurality (two in FIGS. 2 to 4) of PC steel materials 2 and 2 are installed on the floor slab 1. Consists of configuration.

床版1は、予め工場等で製作されて現場で梁間等に設置されるプレキャスト鉄筋コンクリート造の構造体であり、その内部には、一方向に延在する複数(図2〜図4では5つ)のボイド空間V1,V2が形成されている。これら複数のボイド空間V1,V2は、床版1のコンクリートの中に埋設された筒状のボイド部材3…によってそれぞれ形成されている。また、複数のボイド空間V1,V2には、中央部V1aが両端部V1b,V1bから一段下がった状態になっている第1のボイド空間V1と、全長に亘って直線的に形成された第2のボイド空間V2とがある。   The floor slab 1 is a precast reinforced concrete structure that is manufactured in advance at a factory or the like and installed between beams at a site, and a plurality of (in FIG. 2 to FIG. 4, five in FIG. 2 to 4) extend in one direction. ) Void spaces V1 and V2 are formed. The plurality of void spaces V1 and V2 are respectively formed by cylindrical void members 3 embedded in the concrete of the floor slab 1. The plurality of void spaces V1 and V2 includes a first void space V1 in which the central portion V1a is lowered by one step from both end portions V1b and V1b, and a second void space formed linearly over the entire length. There is a void space V2.

図1,図2に示すように、第1のボイド空間V1の中央部V1aは、断面形状が横長の空洞であり、床版1の下面側寄りに形成されている。また、図1,図4に示すように、第1のボイド空間V1の両端部V1b,V1bは、断面形状が横長の空洞であり、床版1の上面側寄りにそれぞれ形成されている。また、図1,図3に示すように、第1のボイド空間V1の中央部V1aと端部V1b,V1bとの間の部分(以下、クランク部V1c,V1cと記す。)は、断面矩形の空洞であり、床版1の上面側から下面側に傾斜して形成されている。   As shown in FIGS. 1 and 2, the central portion V <b> 1 a of the first void space V <b> 1 has a horizontally long cross section and is formed closer to the lower surface side of the floor slab 1. As shown in FIGS. 1 and 4, both end portions V <b> 1 b and V <b> 1 b of the first void space V <b> 1 are cavities having a horizontally long cross-sectional shape and are formed closer to the upper surface side of the floor slab 1. As shown in FIGS. 1 and 3, a portion between the central portion V1a of the first void space V1 and the end portions V1b and V1b (hereinafter referred to as crank portions V1c and V1c) has a rectangular cross section. It is a cavity and is formed to be inclined from the upper surface side to the lower surface side of the floor slab 1.

第1のボイド空間V1の中には、第1のボイド空間V1に沿って懸垂曲線状に延在するPC鋼材2が挿通されている。PC鋼材2は、床版1に上向きのプレストレス(吊り上げ力)を付与するための緊張材であり、例えば、高張力鋼からなる鋼棒、鋼線、鋼より線、或いは鋼線や鋼より線を束ねたケーブル等である。このPC鋼材2には、プレテンション方式或いはポストテンション方式により所定の引張力(緊張力)が導入されており、また、PC鋼材2の両端は、床版1の端部に設けられた定着具4,4にそれぞれ取り付けられて定着されている。   A PC steel material 2 extending in a suspended curve shape along the first void space V1 is inserted into the first void space V1. The PC steel material 2 is a tension material for imparting upward prestress (lifting force) to the floor slab 1, for example, a steel bar made of high-strength steel, a steel wire, a steel strand, or a steel wire or steel. A cable bundled with wires. A predetermined tensile force (tensile force) is introduced into the PC steel material 2 by a pre-tension method or a post-tension method, and both ends of the PC steel material 2 are fixing devices provided at end portions of the floor slab 1. 4 and 4 are attached and fixed.

また、第1のボイド空間V1の内側面のうち、PC鋼材2が接触する角部分V1d…(第1のボイド空間V1の上下面にそれぞれ形成された出隅部)には、くの字状に屈曲した板状のガイドプレート5…が設けられている。PC鋼材2が引張られて軸方向に動くとき、このガイドプレート5上をPC鋼材2が摺動する。   Further, among the inner side surfaces of the first void space V1, the corner portions V1d (contact corners respectively formed on the upper and lower surfaces of the first void space V1) with which the PC steel material 2 comes into contact are formed in a dogleg shape. Are provided with plate-shaped guide plates 5. When the PC steel material 2 is pulled and moves in the axial direction, the PC steel material 2 slides on the guide plate 5.

第1のボイド空間V1のクランク部V1c,V1cには、懸垂曲線状に延在するPC鋼材2の一部を鉛直方向(上下方向)に移動させることでPC鋼材2の緊張力およびライズを調整するジャッキ機構6が設置されている。ジャッキ機構6は、床版1のコンクリート内に埋設されており、床版1の上面と面一に設けられている基板10と、基板10に垂設された2本平行のガイドアーム11,11と、2本のガイドアーム11,11に吊持された長ナット12と、長ナット12に螺合されたボルト13と、ボルト13の上端(先端)に水平方向(ボルト13の軸方向に直交する方向)に回転自在に付設された保持部材14とから構成されている。   Crank portions V1c and V1c of the first void space V1 adjust the tension and rise of the PC steel material 2 by moving a part of the PC steel material 2 extending in a hanging curve shape in the vertical direction (vertical direction). A jack mechanism 6 is installed. The jack mechanism 6 is embedded in the concrete of the floor slab 1, and includes a substrate 10 that is flush with the upper surface of the floor slab 1, and two parallel guide arms 11 and 11 that are suspended from the substrate 10. A long nut 12 suspended on the two guide arms 11, a bolt 13 screwed to the long nut 12, and an upper end (tip) of the bolt 13 in the horizontal direction (perpendicular to the axial direction of the bolt 13). The holding member 14 is provided so as to be freely rotatable in the direction in which it is rotated.

長ナット12は、鉛直方向に延在されており、その下端は、床版1の下面に形成された窪み部1aに開放されている。ボルト13は、長ナット12の下側から締め込まれており、床版1の窪み部1aのところで調整作業(ボルトを締め込んだり、緩めたりする作業)が行われる。   The long nut 12 extends in the vertical direction, and the lower end thereof is opened to a recess 1 a formed on the lower surface of the floor slab 1. The bolt 13 is tightened from the lower side of the long nut 12, and adjustment work (work for tightening or loosening the bolt) is performed at the recessed portion 1 a of the floor slab 1.

保持部材14は、第1のボイド空間V1内のPC鋼材2の一部を保持するものであり、第1のボイド空間V1の内部に配置されている。具体的には、保持部材14は、PC鋼材2を挿通させる筒状の部材であり、保持部材14に保持されたPC鋼材2は、その軸方向に移動自在になっている。また、第1のボイド空間V1のクランク部V1c,V1cでは、PC鋼材2は斜めに延在されているため、筒状の保持部材14の挿通孔は斜め延在されている。なお、保持部材14は、PC鋼材2を挿通させる筒状の部材でなくてもよく、例えば、断面C字形状の割スリーブ状の部材や半円筒形状の部材でもよく、或いは、PC鋼材2を挟持する部材でもよく、その他の構成からなる部材であってもよい。   The holding member 14 holds a part of the PC steel material 2 in the first void space V1, and is disposed in the first void space V1. Specifically, the holding member 14 is a cylindrical member through which the PC steel material 2 is inserted, and the PC steel material 2 held by the holding member 14 is movable in its axial direction. Further, in the crank portions V1c and V1c of the first void space V1, the PC steel material 2 extends obliquely, and therefore the insertion hole of the cylindrical holding member 14 extends obliquely. The holding member 14 may not be a cylindrical member through which the PC steel material 2 is inserted. For example, the holding member 14 may be a C-shaped section sleeve member or a semi-cylindrical member, or the PC steel material 2 may be It may be a member to be sandwiched or may be a member having another configuration.

また、保持部材14は、2本のガイドアーム11,11の間に挟まれた状態で配置されており、ボルト13を長ナット12に締め込むことで、保持部材14はガイドアーム11,11に沿って上方に移動し、ボルト13を弛めることで、保持部材14はガイドアーム11,11に沿って下方に移動する。   Further, the holding member 14 is arranged in a state of being sandwiched between the two guide arms 11, 11, and the holding member 14 is attached to the guide arms 11, 11 by tightening the bolt 13 into the long nut 12. The holding member 14 moves downward along the guide arms 11, 11 by moving upward along the line and loosening the bolt 13.

上記した構成からなるジャッキ機構6と、第1のボイド空間V1を形成するボイド部材3と、第1のボイド空間V1の中に挿通されるPC鋼材2と、PC鋼材2を摺動させるガイドプレート5…とは、ユニット化されている。具体的には、ボイド部材3の所定位置(クランク部V1c,V1cの位置)にジャッキ機構6が貫設されているとともに、ボイド部材3の所定位置(角部分V1d…)にガイドプレート5…が付設されており、さらに、保持部材14に保持(挿通)させた状態でPC鋼材2がボイド部材3の中に挿通されている。   The jack mechanism 6 having the above-described configuration, the void member 3 forming the first void space V1, the PC steel material 2 inserted into the first void space V1, and the guide plate for sliding the PC steel material 2 5 ... is unitized. Specifically, a jack mechanism 6 is provided through a predetermined position of the void member 3 (positions of the crank portions V1c and V1c), and a guide plate 5 is provided at a predetermined position (corner portion V1d ...) of the void member 3. Further, the PC steel material 2 is inserted into the void member 3 while being held (inserted) by the holding member 14.

なお、図2〜図4に示す符号20は鉄筋コンクリート造の床版1の主筋を示しており、符号21は鉄筋コンクリート造の床版1のせん断補強筋(配力筋)を示している。   2 to 4 indicate the main bars of the reinforced concrete floor slab 1, and reference numeral 21 indicates the shear reinforcing bars (distribution bars) of the reinforced concrete floor slab 1.

上記した構成からなる床構造によれば、床版1に懸垂曲線状に延在するPC鋼材2が設置されており、このPC鋼材2に引張力が導入されているため、床版1に上向きのプレストレスが付与され、このプレストレスが床版1に作用する荷重(下向きの力)と打ち消し合い、床版1のたわみが抑制される。   According to the floor structure having the above-described configuration, the PC steel material 2 extending in a suspended curve shape is installed on the floor slab 1, and a tensile force is introduced into the PC steel material 2. The prestress is applied, the prestress cancels out with the load (downward force) acting on the floor slab 1, and the deflection of the floor slab 1 is suppressed.

また、上記した構成からなる床構造によれば、ジャッキ機構6によって、PC鋼材2の一部を上下動させることができる。具体的には、ボルト13を長ナット12に締め込むことで、保持部材14が上方に移動し、保持部材14に保持されたPC鋼材2の一部が上方に移動する。一方、ボルト13を弛めることで、保持部材14が下方に移動し、保持部材14に保持されたPC鋼材2の一部が下方に移動する。このようにPC鋼材2の一部を上下動させると、PC鋼材2のライズや緊張力が変化する。したがって、床構造への積載荷重に応じてジャッキ機構6を調整することで、PC鋼材2のライズや緊張力が調整され、床版1に付与されるプレストレスが制御される。これによって、床構造の長期たわみの制御を行うことができ、品質の高い空間を保証することができる。   Moreover, according to the floor structure which consists of an above-described structure, the jack mechanism 6 can move a part of PC steel material 2 up and down. Specifically, by tightening the bolt 13 into the long nut 12, the holding member 14 moves upward, and a part of the PC steel material 2 held by the holding member 14 moves upward. On the other hand, by loosening the bolt 13, the holding member 14 moves downward, and a part of the PC steel material 2 held by the holding member 14 moves downward. Thus, if a part of PC steel material 2 is moved up and down, the rise and tension of PC steel material 2 will change. Therefore, by adjusting the jack mechanism 6 in accordance with the load on the floor structure, the rise and tension of the PC steel material 2 are adjusted, and the prestress applied to the floor slab 1 is controlled. As a result, the long-term deflection of the floor structure can be controlled, and a high-quality space can be guaranteed.

また、PC鋼材2やジャッキ機構6は、床版1の外に配置されずに内部に設置されているため、PC鋼材2やジャッキ機構6を外的要因から保護するケース等が不要となり、建物内部の有効空間を広くとることができる。   Further, since the PC steel material 2 and the jack mechanism 6 are installed inside the floor slab 1 without being disposed outside, a case for protecting the PC steel material 2 and the jack mechanism 6 from external factors is not required, and the building The internal effective space can be widened.

また、ジャッキ機構6とボイド部材3とPC鋼材2とガイドプレート5…とがユニット化されているため、プレキャストからなる床構造体を製作する際、ジャッキ機構6やボイド部材3をユニット化したものを、床版1の図示せぬ型枠内の所定位置にセットするとともに、床版1の主筋20…やせん断補強筋21をそれぞれ配筋し、その後、床版1のコンクリート打設を行うだけでよい。これによって、プレキャストからなる床構造体の生産性を向上させることができる。   In addition, since the jack mechanism 6, the void member 3, the PC steel 2, and the guide plate 5 are unitized, when the floor structure made of precast is manufactured, the jack mechanism 6 and the void member 3 are unitized. Is placed at a predetermined position in the formwork (not shown) of the floor slab 1, and the main reinforcing bars 20 and the shear reinforcing bars 21 of the floor slab 1 are respectively arranged, and then the concrete placement of the floor slab 1 is performed. It's okay. Thereby, the productivity of the floor structure made of precast can be improved.

以上、本発明に係る床構造の実施の形態について説明したが、本発明は上記した実施の形態に限定されるものではなく、その趣旨を逸脱しない範囲で適宜変更可能である。例えば、上記した実施の形態では、プレキャスト鉄筋コンクリート造からなる床構造について説明しているが、本発明は、在来工法によって形成される鉄筋コンクリート造の床構造であってもよく、或いは、鋼製デッキやプレキャスト版の上にコンクリートが打設された構成からなる床構造であってもよい。   As mentioned above, although embodiment of the floor structure concerning this invention was described, this invention is not limited to above-described embodiment, In the range which does not deviate from the meaning, it can change suitably. For example, in the above-described embodiment, a floor structure made of precast reinforced concrete is described. However, the present invention may be a reinforced concrete floor structure formed by a conventional construction method, or a steel deck. Alternatively, a floor structure composed of concrete cast on a precast plate may be used.

また、上記した実施の形態では、床版1に形成されたボイド空間V1,V2が一方向に延在しているが、本発明は、床版に二方向に延在するボイド空間が形成されていてもよい。
また、上記した実施の形態では、PC鋼材2を挿通させるための第1のボイド空間V1,V1のほかに、PC鋼材2が挿通されない第2のボイド空間V2…が床版1に形成されているが、本発明は、PC鋼材2が挿通されない第2のボイド空間V2…が形成されていなくてもよく、PC鋼材2を挿通させるためのボイド空間だけが形成されていてもよい。
In the above-described embodiment, the void spaces V1, V2 formed in the floor slab 1 extend in one direction. However, in the present invention, a void space extending in two directions is formed in the floor slab. It may be.
In the above-described embodiment, in addition to the first void spaces V1, V1 for inserting the PC steel material 2, the second void space V2,... In which the PC steel material 2 is not inserted is formed in the floor slab 1. However, in the present invention, the second void space V2 through which the PC steel material 2 is not inserted may not be formed, and only the void space for allowing the PC steel material 2 to be inserted may be formed.

また、上記した実施の形態では、基板10とガイドアーム11,11と長ナット12とボルト13と保持部材14とからなるネジ式のジャッキ機構6が用いられているが、本発明は、如何なる構成のジャッキ機構であってもよく、油圧シリンダーやエアシリンダーを用いて上下動させるジャッキ機構であってもよく、モータ等の駆動機構とラック・ピニオン機構とを組み合わせたジャッキ機構であってもよく、或いは、パンタグラフやその他の機構を用いたジャッキ機構であってもよい。   Further, in the above-described embodiment, the screw-type jack mechanism 6 including the substrate 10, the guide arms 11, 11, the long nut 12, the bolt 13, and the holding member 14 is used. May be a jack mechanism that moves up and down using a hydraulic cylinder or an air cylinder, or a jack mechanism that combines a drive mechanism such as a motor and a rack and pinion mechanism, Alternatively, a jack mechanism using a pantograph or other mechanism may be used.

また、上記した実施の形態では、ジャッキ機構6とボイド部材3とPC鋼材2とガイドプレート5…とがユニット化されているが、本発明は、PC鋼材2やガイドプレート5…が、ジャッキ機構6やボイド部材3とユニット化されていなくてもよく、また、PC鋼材2やガイドプレート5…以外の部材が、ジャッキ機構6やボイド部材3とユニット化されていてもよい。さらに、請求項1記載の発明は、ジャッキ機構6とボイド部材3とがユニット化されていなくてもよい。   In the embodiment described above, the jack mechanism 6, the void member 3, the PC steel material 2, and the guide plate 5 are unitized. However, in the present invention, the PC steel material 2 and the guide plate 5. 6 and the void member 3 may not be unitized, and members other than the PC steel material 2 and the guide plate 5 may be unitized with the jack mechanism 6 and the void member 3. Furthermore, in the invention described in claim 1, the jack mechanism 6 and the void member 3 may not be unitized.

本発明の実施の形態を説明するための床構造の断面図である。It is sectional drawing of the floor structure for demonstrating embodiment of this invention. 本発明の実施の形態を説明するための図1のA−A間を表す断面図である。It is sectional drawing showing the AA of FIG. 1 for demonstrating embodiment of this invention. 本発明の実施の形態を説明するための図1のB−B間を表す断面図である。It is sectional drawing showing between B-B of FIG. 1 for demonstrating embodiment of this invention. 本発明の実施の形態を説明するための図1のC−C間を表す断面図である。It is sectional drawing showing CC section of FIG. 1 for demonstrating embodiment of this invention.

符号の説明Explanation of symbols

1 床版
2 PC鋼材
3 ボイド部材
6 ジャッキ機構
V1 第1のボイド空間(ボイド空間)
DESCRIPTION OF SYMBOLS 1 Floor slab 2 PC steel material 3 Void member 6 Jack mechanism V1 1st void space (void space)

Claims (2)

床版に、懸垂曲線状に延在するPC鋼材が設置され、該PC鋼材に緊張力が導入されて床版にプレストレスが付与されている床構造において、
PC鋼材が床版に形成されたボイド空間に挿通されており、PC鋼材の一部を上下方向に移動させるジャッキ機構が床版の内部に設置されていることを特徴とする床構造。
In the floor structure in which a PC steel material extending in a suspended curve shape is installed on the floor slab, and tension is introduced into the PC steel material and prestress is applied to the floor slab,
A floor structure characterized in that a PC steel material is inserted into a void space formed in a floor slab, and a jack mechanism for moving a part of the PC steel material in the vertical direction is installed inside the floor slab.
請求項1記載の床構造において、
ボイド空間を形成するボイド部材にジャッキ機構が取り付けられ、少なくともジャッキ機構とボイド部材とがユニット化されていることを特徴とする床構造。
The floor structure according to claim 1, wherein
A floor structure characterized in that a jack mechanism is attached to a void member forming a void space, and at least the jack mechanism and the void member are unitized.
JP2006036820A 2006-02-14 2006-02-14 Floor structure Pending JP2007217883A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006036820A JP2007217883A (en) 2006-02-14 2006-02-14 Floor structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006036820A JP2007217883A (en) 2006-02-14 2006-02-14 Floor structure

Publications (1)

Publication Number Publication Date
JP2007217883A true JP2007217883A (en) 2007-08-30

Family

ID=38495462

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006036820A Pending JP2007217883A (en) 2006-02-14 2006-02-14 Floor structure

Country Status (1)

Country Link
JP (1) JP2007217883A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790577A (en) * 2015-04-20 2015-07-22 中国民航大学 Boundary beam solidification type large-bay prestressed concrete floor structure
CN112227725A (en) * 2020-11-11 2021-01-15 中交第四公路工程局有限公司 Grouting structure of long pore passage of prestressed concrete stiffening beam and construction method thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0462708U (en) * 1990-10-03 1992-05-28
JPH11210162A (en) * 1998-01-27 1999-08-03 Times Engineering:Kk Structure of installing rustproof pc steel
JPH11241507A (en) * 1998-02-24 1999-09-07 Takenaka Komuten Co Ltd Rise adjustable type outside pc steel material construction method to control deflection of beam and movable support for pc steel material used therefor

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0462708U (en) * 1990-10-03 1992-05-28
JPH11210162A (en) * 1998-01-27 1999-08-03 Times Engineering:Kk Structure of installing rustproof pc steel
JPH11241507A (en) * 1998-02-24 1999-09-07 Takenaka Komuten Co Ltd Rise adjustable type outside pc steel material construction method to control deflection of beam and movable support for pc steel material used therefor

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104790577A (en) * 2015-04-20 2015-07-22 中国民航大学 Boundary beam solidification type large-bay prestressed concrete floor structure
CN112227725A (en) * 2020-11-11 2021-01-15 中交第四公路工程局有限公司 Grouting structure of long pore passage of prestressed concrete stiffening beam and construction method thereof

Similar Documents

Publication Publication Date Title
US8375678B1 (en) Methods for construction of pre-fabricated modular reinforcement cages for concrete structures
JP5415204B2 (en) Bridge movement restraining device and movement restraining method
KR100719959B1 (en) Structure reinforcing apparatus and method using stressing apparatus for structure reinforcement
JP5367297B2 (en) Bridge with precast cross girder and precast girder and its construction method
WO2005066419A1 (en) Method of applying prestress and connecting means used therein and prestressed concrete beam therefrom
JP2008303702A (en) Bidirectional prestressing system and bent portion forming apparatus
KR100720996B1 (en) Continuous bridge construction method using precast slab
JPH07331618A (en) Method for reinforcing prestressed bridge by lower cable
JP4634537B1 (en) Bridge girder reinforcement structure
JP2008266910A (en) Projection structure of anchorage or deviator of tendon, and construction method therefor
JP2007217883A (en) Floor structure
KR101347038B1 (en) Structural strengthening method using fiber reinforcing fiber
KR20100057446A (en) Apparatus for preventing vertical structure from falling sideward
KR20130120096A (en) Girder bridge for pre-tention
JP2744955B2 (en) Reinforcement structure and reinforcement method of hinge part of gel bar bridge
JP4492422B2 (en) Structure near the intermediate fulcrum of continuous I-girder bridge
JP2010037833A (en) Bridge extrusion erection construction method
JP4493245B2 (en) Suspended floor slab bridge and method for reinforcing suspended floor slab
KR20030063071A (en) Prestressed concrete beam
US20150176276A1 (en) Post-tension concrete leave out splicing system and method
JP2006104863A (en) Steel pipe composite void slab capable of controlling stress/deformation, and its construction method
JP2006052573A (en) Method of overhangingly erecting bridge, and diagonal member anchoring structure for use therein
JP2020186516A (en) Method of constructing bridge railing
JP6359371B2 (en) Production method
JP3878096B2 (en) Reinforced concrete members

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080618

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100916

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100928

A02 Decision of refusal

Effective date: 20110208

Free format text: JAPANESE INTERMEDIATE CODE: A02