JP2004076295A - Block for retaining wall and retaining wall construction method - Google Patents

Block for retaining wall and retaining wall construction method Download PDF

Info

Publication number
JP2004076295A
JP2004076295A JP2002234467A JP2002234467A JP2004076295A JP 2004076295 A JP2004076295 A JP 2004076295A JP 2002234467 A JP2002234467 A JP 2002234467A JP 2002234467 A JP2002234467 A JP 2002234467A JP 2004076295 A JP2004076295 A JP 2004076295A
Authority
JP
Japan
Prior art keywords
retaining wall
block
concrete
blocks
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2002234467A
Other languages
Japanese (ja)
Inventor
Yoji Sekiguchi
関口 陽二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kei KK
Original Assignee
Kei KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kei KK filed Critical Kei KK
Priority to JP2002234467A priority Critical patent/JP2004076295A/en
Publication of JP2004076295A publication Critical patent/JP2004076295A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Retaining Walls (AREA)
  • Revetment (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To construct a firm retaining wall including safety after construction and prevent occurrence of fluctuation of a construction period, in a concrete retaining wall block for constructing a retaining wall by piling up blocks in a slope face of a river , a road, or a reclaimed land. <P>SOLUTION: A concrete fixing hook 6 is integrally formed on the back face of a concrete rectangular parallelepiped block body 2. The fixing hook 6 is constituted of a fixing plate 6a and a leg 6b connecting the fixing plate 6a to the block body 2. The sectional area of the leg 6b of the fixing hook 6 is made smaller than the area of the fixing plate 6a. In this way, when many pieces of retaining wall blocks 1 are stuck, a clearance is generated at the periphery of the leg 6b of the fixing hook 6 of each retaining wall block 1 and these clearances are connected in all directions and a concrete filling space is formed in a lattice shape. <P>COPYRIGHT: (C)2004,JPO

Description

【0001】
【発明の属する技術分野】
本発明は、河川の法面や道路、造成地などに積み上げて擁壁を施工するためのコンクリート製の擁壁用ブロックと、この擁壁用ブロックを用いた擁壁施工方法に関するものである。
【0002】
【従来の技術】
この種の擁壁においては、十分な土留め機能を発揮しうるように、河川の法面などに対して強固に固定することが重要である。
【0003】
そのため、例えば特開平11−310913号公報に開示されているように、自然石に棒状部材と座金を取り付けた施工石を複数個用意し、これら施工石を河川の法面などに積み上げた後、これら施工石の棒状部材および座金を土砂で埋設することにより、この土砂との摩擦力で各施工石を固定するという手法が提案されている。
【0004】
【発明が解決しようとする課題】
しかし、この手法では次のような不都合があった。
【0005】
第1に、施工石を固定している土砂には流動性があるため、あまり強固な擁壁を施工することができないばかりか、地震や台風などの発生に伴って施工石が崩壊する恐れがあり、施工後の擁壁の安全性にも問題がある。
【0006】
第2に、施工石の積み上げ作業とそれ以降の作業がすべて現場で行われることになるので、擁壁の工期が現場の状況(天候など)や現場作業者の技量に左右されやすく、工期のバラツキを惹起する危険性が高い。
【0007】
本発明は、このような事情に鑑み、強固な擁壁を施工することができるとともに、施工後の安全性に問題がなく、しかも工期のバラツキの発生を抑制することが可能な擁壁用ブロックおよび擁壁施工方法を提供することを目的とする。
【0008】
【課題を解決するための手段】
すなわち、本発明のうち擁壁用ブロックの発明は、コンクリートからなる直方体状のブロック本体(2)を有し、このブロック本体の背面に、コンクリートからなる固定フック(6)を一体に形成した擁壁用ブロック(1)において、前記固定フックとして、係止板(6a)と、この係止板を前記ブロック本体に連結する脚部(6b)とからなる固定フックを用い、この固定フックの脚部の断面積を係止板の面積より小さくして構成される。ここで、固定フックの脚部は1本に限られず、2本以上の脚部を採用しても構わない。固定フックの脚部が2本以上ある場合は、これら脚部の総断面積が係止板の面積より小さくなるようにすればよい。
【0009】
こうした構成を採用することにより、多数個の擁壁用ブロックを積み上げたとき、各擁壁用ブロックの固定フックの脚部の周囲(上下左右)に空隙ができ、これら空隙が四方八方につながってコンクリート充填空間が格子状に形成されるように作用する。
【0010】
また、前記ブロック本体(2)に空胴部(3)を上下に貫通させて形成し、前記ブロック本体の前面に内外連通孔(10)を前記空胴部に連通させて形成して構成される。
【0011】
かかる構成により、空胴部をそのまま魚礁として利用できるようになるとともに、空胴部に植栽土を入れ、草木を植えることが可能となるように作用する。
【0012】
一方、本発明のうち擁壁施工方法は、上記擁壁用ブロック(1)を用いて擁壁(11)を施工する際に、複数個の擁壁用ブロックを組積して所定段数のブロック列(R1〜R6)を構築し、その後、これら擁壁用ブロックの固定フック(6)の周囲に胴込めコンクリート(17)を充填して硬化させるようにして構成される。
【0013】
かかる構成により、すべての擁壁用ブロックが同種材料の胴込めコンクリートで緊結固定されるように作用する。
【0014】
また、上記擁壁用ブロック(1)を用いて擁壁(11)を施工する際に、複数個の擁壁用ブロックを組積して所定段数のブロック列(R1〜R6)を構築し、その後、これら擁壁用ブロックの固定フック(6)の周囲に胴込めコンクリート(17)を充填して硬化させるとともに、これら擁壁用ブロックの空胴部(3)に植栽土(19)を入れるようにして構成される。
【0015】
かかる構成により、すべての擁壁用ブロックが同種材料の胴込めコンクリートで緊結固定されるとともに、空胴部の植栽土に草木を植えることが可能となるように作用する。
【0016】
さらに、上記擁壁用ブロック(1)をコンクリート充填空間(18)が格子状に形成されるように複数個組み合わせてユニット化したブロックユニット(20)を工場で必要個数だけ作製し、各ブロックユニットのコンクリート充填空間に胴込めコンクリート(17)を工場で充填して硬化させ、その後、これらブロックユニットを現場に搬入して接合するようにして構成される。
【0017】
かかる構成により、工場での作業が主体となるため、ブロックユニットの品質が向上し、かつ現場での作業効率がよくなるように作用する。
【0018】
なお、括弧内の符号は図面において対応する要素を表す便宜的なものであり、したがって、本発明は図面上の記載に限定拘束されるものではない。このことは「特許請求の範囲」の欄についても同様である。
【0019】
【発明の実施の形態】
以下、本発明の実施形態を図面に基づいて説明する。
【0020】
<第1の実施形態>
図1は本発明に係る擁壁用ブロックの一実施形態を示す図であり、(a)はその平面図、(b)はその右側面図、(c)はその正面図、
図2は図1に示す擁壁用ブロックを平積みして擁壁を施工した状態を示す図であり、(a)はその正面図、(b)は(a)のB−B線による断面図、(c)は(b)のC部分の拡大詳細図、(d)は(a)のD−D線による拡大断面図、
図3は図1に示す擁壁用ブロックを谷積みして擁壁を施工した状態の正面図である。
【0021】
この擁壁用ブロック1は、図1に示すように、コンクリートからなる直方体状のブロック本体2を有しており、ブロック本体2の背面にはコンクリートからなる固定フック6が一体に形成されている。この固定フック6は、ブロック本体2と同程度の面積を有する係止板6aと、この係止板6aをブロック本体2に連結する2本の脚部6bとから構成されており、図1(a)、(b)に示すように、これら脚部6bの総断面積は係止板6aの面積より小さくなっている。
【0022】
また、図1(a)に示すように、ブロック本体2の中央には空胴部3が上下に貫通して形成されており、ブロック本体2の左右両側にはそれぞれ溝部4、5が上下に貫通して形成されている。さらに、ブロック本体2の前面には、図1(c)に示すように、その上部中央に半円状の切欠部7が空胴部3に連通して形成されているとともに、その下部左右両端に1/4円状の切欠部8、9がそれぞれ溝部4、5に連通して形成されている。ここで、3個の切欠部7、8、9はすべて同一の曲率を有する円弧状となっている。なお、ブロック本体2の上面および下面にはそれぞれ係合凸部2aおよび係合凹部2bが形成されている。
【0023】
擁壁用ブロック1は以上のような構成を有するので、多数個の擁壁用ブロック1を河川の法面に平積みして擁壁11を施工する際には、図2(a)、(b)に示すように、河川の両側に基礎材12を敷設した後、この基礎材12の上側に基礎コンクリート13を打設して養生する。そして、この基礎コンクリート13が硬化したところで、所要個数の擁壁用ブロック1を現場(河川の法面の近く)に搬入し、以下に述べる手順に従い、これら擁壁用ブロック1を基礎コンクリート13の上側に平積みで6段に積み上げる。
【0024】
まず、基礎コンクリート13上に、複数個の擁壁用ブロック1を水平方向に組積して1段目(最下段)のブロック列R1を構築する。すると、図2(d)に示すように、互いに左右に隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。
【0025】
次に、1段目のブロック列R1の上側に、複数個の擁壁用ブロック1を当該擁壁用ブロック1の幅の半分だけ水平方向にずらして水平方向に組積することにより、2段目のブロック列R2を構築する。すると、この2段目のブロック列R2においても、互いに隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。この際、2段目のブロック列R2は1段目のブロック列R1に対して擁壁用ブロック1の幅の半分だけ水平方向にずれているので、1段目のブロック列R1の各空胴15の上側に2段目のブロック列R2の各擁壁用ブロック1の空胴部3が位置決めされると同時に、1段目のブロック列R1の各擁壁用ブロック1の空胴部3の上側に2段目のブロック列R2の各空胴15が位置決めされた状態となる。
【0026】
なお、図2(b)に示すように、2段目のブロック列R2は1段目のブロック列R1上に傾斜して載置されることになるが、図2(c)に示すように、2段目のブロック列R2にある擁壁用ブロック1のブロック本体2の係合凹部2bが1段目のブロック列R1にある擁壁用ブロック1のブロック本体2の係合凸部2aに係合するので、2段目のブロック列R2が自重で後方へ滑り落ちる恐れはない。このことは、後述する3〜6段目のブロック列R3〜R6についても同様である。
【0027】
次いで、2段目のブロック列R2の上側に、複数個の擁壁用ブロック1を当該擁壁用ブロック1の幅の半分だけ水平方向にずらして水平方向に組積することにより、3段目のブロック列R3を構築する。すると、この3段目のブロック列R3においても、互いに隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。この際、3段目のブロック列R3は2段目のブロック列R2に対して擁壁用ブロック1の幅の半分だけ水平方向にずれているので、2段目のブロック列R2の各空胴15の上側に3段目のブロック列R3の各擁壁用ブロック1の空胴部3が位置決めされると同時に、2段目のブロック列R2の各擁壁用ブロック1の空胴部3の上側に3段目のブロック列R3の各空胴15が位置決めされた状態となる。また、1段目から3段目までのブロック列R1〜R3にあるすべての擁壁用ブロック1の固定フック6が集まって、図2(d)に示すように、それらの脚部6bの周囲にコンクリート充填空間18が格子状に形成される。
【0028】
こうして1段目から3段目までのブロック列R1〜R3が構築されたところで、これらブロック列R1〜R3が後方へ倒壊しないように固定するため、図2(b)に示すように、河川の法面とブロック列R1〜R3との間に砂利や割栗石などの裏込め材16を充填した後、コンクリート充填空間18に胴込めコンクリート17を打設して養生する。すると、各擁壁用ブロック1の固定フック6の脚部6bの周囲に胴込めコンクリート17が充填された状態で硬化し、すべての擁壁用ブロック1は、当該擁壁用ブロック1と同種の材料である胴込めコンクリート17によって互いに強固に緊結されて河川の法面に固定される。
【0029】
その後、3段目のブロック列R3の上側に、複数個の擁壁用ブロック1を当該擁壁用ブロック1の幅の半分だけ水平方向にずらして水平方向に組積することにより、4段目のブロック列R4を構築する。すると、この4段目のブロック列R4においても、互いに隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。この際、4段目のブロック列R4は3段目のブロック列R3に対して擁壁用ブロック1の幅の半分だけ水平方向にずれているので、3段目のブロック列R3の各空胴15の上側に4段目のブロック列R4の各擁壁用ブロック1の空胴部3が位置決めされると同時に、3段目のブロック列R3の各擁壁用ブロック1の空胴部3の上側に4段目のブロック列R4の各空胴15が位置決めされた状態となる。
【0030】
次に、4段目のブロック列R4の上側に、複数個の擁壁用ブロック1を当該擁壁用ブロック1の幅の半分だけ水平方向にずらして水平方向に組積することにより、5段目のブロック列R5を構築する。すると、この5段目のブロック列R5においても、互いに隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。この際、5段目のブロック列R5は4段目のブロック列R4に対して擁壁用ブロック1の幅の半分だけ水平方向にずれているので、4段目のブロック列R4の各空胴15の上側に5段目のブロック列R5の各擁壁用ブロック1の空胴部3が位置決めされると同時に、4段目のブロック列R4の各擁壁用ブロック1の空胴部3の上側に5段目のブロック列R5の各空胴15が位置決めされた状態となる。
【0031】
最後に、5段目のブロック列R5の上側に、複数個の擁壁用ブロック1を当該擁壁用ブロック1の幅の半分だけ水平方向にずらして水平方向に組積することにより、6段目(最上段)のブロック列R6を構築する。すると、この6段目のブロック列R6においても、互いに隣接する擁壁用ブロック1の溝部4、5が対向して当接し、これら溝部4、5によって空胴15が上下に貫通する形で形成される。この際、6段目のブロック列R6は5段目のブロック列R5に対して擁壁用ブロック1の幅の半分だけ水平方向にずれているので、5段目のブロック列R5の各空胴15の上側に6段目のブロック列R6の各擁壁用ブロック1の空胴部3が位置決めされると同時に、5段目のブロック列R5の各擁壁用ブロック1の空胴部3の上側に6段目のブロック列R6の各空胴15が位置決めされた状態となる。また、4段目から6段目までのブロック列R4〜R6にあるすべての擁壁用ブロック1の固定フック6が集まって、それらの脚部6bの周囲にコンクリート充填空間18が格子状に形成される。
【0032】
こうして、さらに4段目から6段目までのブロック列R4〜R6が構築されたところで、これらブロック列R4〜R6が後方へ倒壊しないように固定するため、河川の法面とブロック列R4〜R6との間に裏込め材16を充填した後、コンクリート充填空間18に胴込めコンクリート17を打設して養生する。すると、各擁壁用ブロック1の固定フック6の脚部6bの周囲に胴込めコンクリート17が充填された状態で硬化し、すべての擁壁用ブロック1は、当該擁壁用ブロック1と同種の材料である胴込めコンクリート17によって互いに強固に緊結されて河川の法面に固定される。
【0033】
こうして、最下段から最上段までのすべてのブロック列R1〜R6の擁壁用ブロック1が河川の法面に固定されたところで、これら擁壁用ブロック1によって擁壁11が施工された状態となる。このとき、任意の上下二段のブロック列R1〜R6において、下段のブロック列の各空胴15の上側に上段のブロック列の各擁壁用ブロック1の空胴部3が位置決めされると同時に、下段のブロック列の各擁壁用ブロック1の空胴部3の上側に上段のブロック列の各空胴15が位置決めされた状態となる。そのため、図2(a)に示すように、最上段(6段目)のブロック列R6から最下段(1段目)のブロック列R1まで空胴15と空胴部3とが交互に上下方向に連通することになる。また、図2に示すように、互いに上下左右に隣接する擁壁用ブロックの切欠部7、8、9が協働して円形の内外連通孔10を形成し、この内外連通孔10を通じて擁壁用ブロック1の空胴部3または空胴15と前方空間Sとが連通する。
【0034】
そして、この擁壁11をこのまま利用すれば、水面下においては河川の水が内外連通孔10を通って擁壁用ブロック1の空胴部3および空胴15に流れ込み、魚などの水棲動物が擁壁用ブロック1の一部(水面下の部分)を魚礁として利用できるようになるので、水棲動物にとって生息しやすい河川となり、擁壁用ブロック1の環境保全性が向上する。
【0035】
また、河川の法面を緑化する場合には、最上段のブロック列R6にある各擁壁用ブロック1の空胴部3および各空胴15に植栽土19を投入する。すると、上述したとおり、最上段のブロック列R6から最下段のブロック列R1まで空胴15と空胴部3とが交互に上下方向に連通しているので、この植栽土19は順にブロック列R5、R4、R3、R2の擁壁用ブロック1の空胴部3または空胴15を通って最下段のブロック列R1に達し、その上に次々と溜まっていく。その結果、図2(b)、(c)に示すように、すべての擁壁用ブロック1の空胴部3および空胴15に植栽土19が充填され、さらに、すべての内外連通孔10から植栽土19が河川側に現れるため、そこに草木を植えて緑化することが可能となる。
【0036】
ところで、擁壁用ブロック1の積み方については、上述した平積み以外に谷積みも可能である。この谷積みを採用する場合は、図3に示すように、各擁壁用ブロック1を45°傾けつつ組積していく。このときも、すべての擁壁用ブロック1の固定フック6の脚部6bの周囲にコンクリート充填空間18が格子状に形成されるので、すべての擁壁用ブロック1は胴込めコンクリート17によって互いに強固に緊結される。また、最上段から最下段まで空胴15と空胴部3とが交互に上下方向に連通して稲妻形の経路が確保されるので、平積みの場合と同じく植栽土19の投入を円滑に実施することができる。
【0037】
なお、上述した第1の実施形態では、ブロック本体2の前面に円弧状(半円状、1/4円状)の切欠部7、8、9を設けることにより、積み上げたときに円形の内外連通孔10が形成されるようにした場合について説明した。しかし、これら切欠部7、8、9の形状については円弧状に限るわけではなく、例えば、矩形状の切欠部7、8、9を採用して長方形の内外連通孔10を形成することもできる。もちろん、擁壁用ブロック1の環境保全性を高める必要がない場合には、切欠部7、8、9を省略して擁壁用ブロック1の製造コストを下げることも可能である。
【0038】
また、上述した第1の実施形態では、擁壁用ブロック1を平積みで6段に積み上げて擁壁11を施工する場合について説明したが、この擁壁用ブロック1の段数は6段に限られないことは言及するまでもない。
【0039】
さらに、上述した第1の実施形態では、所定個数の擁壁用ブロック1を現場(河川の法面の近く)に搬入した後、これら擁壁用ブロック1を現場で組積して擁壁11を施工する場合について説明したが、この擁壁用ブロック1を何個か組み合わせた形状のブロックユニットを工場で予め作製し、このブロックユニットを現場に搬入して接合することにより、擁壁11を施工することも可能である。以下、第2の実施形態として、このブロックユニットを用いた擁壁施工方法について説明する。
【0040】
<第2の実施形態>
図4は図1に示す擁壁用ブロックを何個か組み合わせてユニット化したブロックユニットの一例を示す図であり、(a)はその正面図、(b)はその平面図、(c)はその左側面図、(d)はその右側面図、(e)は(a)のE−E線による断面図、(f)は(a)のF−F線による断面図、
図5は図4に示すブロックユニットを平積みして擁壁を施工した状態を示す図であり、(a)はその正面図、(b)は(a)のB−B線による断面図である。
【0041】
このブロックユニット20は、図4に示すように、上述した擁壁用ブロック1を何個か組み合わせた形状を有しており、その上面および左面には係合凸部21、22が形成されているとともに、その下面および右面には係合凹部23、24が形成されている。また、ブロックユニット20には、図4(b)、(f)に示すように、複数個の空胴部3および空胴15が左右に交互に並んで形成されており、これら空胴部3、空胴15の後方にはコンクリート充填空間18が格子状に形成されている。さらに、ブロックユニット20の前面には、図4(a)に示すように、複数個の円形の内外連通孔10が空胴部3または空胴15に連通して形成されている。そして、図4(e)、(f)に示すように、すべての空胴部3および空胴15には植栽土19が投入されているとともに、コンクリート充填空間18には胴込めコンクリート17が充填されて硬化した状態となっている。そのため、ブロックユニット20は胴込めコンクリート17によって補剛されて高い剛性を発現する。なお、ブロックユニット20の剛性をさらに向上させるため、コンクリート充填空間18に鉄筋を縦横2方向に配筋してもよい。
【0042】
ブロックユニット20は以上のような構成を有するので、複数枚のブロックユニット20を河川の法面に平積みして擁壁11を施工する際には、所要枚数のブロックユニット20を現場(河川の法面の近く)に搬入した後、図5に示すように、基礎コンクリート13の上側にブロックユニット20を3段に積み上げ、各ブロックユニット20をその係合凸部21、22と係合凹部23、24とを嵌合して接合する。
【0043】
この際、各ブロックユニット20は、すでに述べたとおり、高い剛性を有しているため、ハンドリング性に優れ、その接合作業を短時間で効率よく行うことができる。しかも、すべてのブロックユニット20は、工場で作製された高品質なものであるので、擁壁の工期が現場の状況や現場作業者の技量に左右される恐れはなく、予定どおりの工期で擁壁11の施工を完了することが可能となる。
【0044】
なお、上述した第2の実施形態では、ブロックユニット20を3段に積み上げて擁壁11を施工する場合について説明したが、このブロックユニット20の段数は3段に限られないことは言うまでもない。
【0045】
また、上述した第1および第2の実施形態においては、擁壁用ブロック1やブロックユニット20を用いて河川の法面に擁壁11を施工する場合について説明したが、道路または造成地などに擁壁11を施工する場合に本発明を適用することも可能である。
【0046】
【発明の効果】
以上説明したように、請求項1に記載の発明によれば、多数個の擁壁用ブロックを積み上げたとき、各擁壁用ブロックの固定フックの脚部の周囲(上下左右)に空隙ができ、これら空隙が四方八方につながってコンクリート充填空間が格子状に形成されることから、地震や台風などに耐え、施工後の安全性にも問題のない強固な擁壁を施工しうる擁壁用ブロックを提供することができる。
【0047】
また、請求項2に記載の発明によれば、空胴部をそのまま魚礁として利用できるようになるとともに、空胴部に植栽土を入れ、草木を植えることが可能となることから、上述した作用効果に加えて、水棲動物が生息しやすく、また緑化によって自然景観を維持することが可能な環境適応型の擁壁用ブロックを提供することができる。
【0048】
一方、請求項3に記載の発明によれば、すべての擁壁用ブロックが同種材料の胴込めコンクリートで緊結固定されるため、地震や台風などに耐え、施工後の安全性にも問題のない強固な擁壁を施工しうる擁壁施工方法を提供することができる。
【0049】
また、請求項4に記載の発明によれば、すべての擁壁用ブロックが同種材料の胴込めコンクリートで緊結固定されるとともに、空胴部の植栽土に草木を植えることが可能となるため、上述した作用効果に加えて、水棲動物が生息しやすく、また緑化によって自然景観を維持することが可能な環境適応型の擁壁施工方法を提供することができる。
【0050】
さらに、請求項5に記載の発明によれば、工場での作業が主体となるため、ブロックユニットの品質が向上し、かつ現場での作業効率がよくなることから、上述した作用効果に加えて、工期のバラツキの発生を抑制することが可能な擁壁施工方法を提供することができる。
【図面の簡単な説明】
【図1】本発明に係る擁壁用ブロックの一実施形態を示す図であり、(a)はその平面図、(b)はその右側面図、(c)はその正面図である。
【図2】図1に示す擁壁用ブロックを平積みして擁壁を施工した状態を示す図であり、(a)はその正面図、(b)は(a)のB−B線による断面図、(c)は(b)のC部分の拡大詳細図、(d)は(a)のD−D線による拡大断面図である。
【図3】図1に示す擁壁用ブロックを谷積みして擁壁を施工した状態の正面図である。
【図4】図1に示す擁壁用ブロックを何個か組み合わせてユニット化したブロックユニットの一例を示す図であり、(a)はその正面図、(b)はその平面図、(c)はその左側面図、(d)はその右側面図、(e)は(a)のE−E線による断面図、(f)は(a)のF−F線による断面図である。
【図5】図4に示すブロックユニットを平積みして擁壁を施工した状態を示す図であり、(a)はその正面図、(b)は(a)のB−B線による断面図である。
【符号の説明】
1……擁壁用ブロック
2……ブロック本体
3……空胴部
6……固定フック
6a……係止板
6b……脚部
10……内外連通孔
11……擁壁
17……胴込めコンクリート
18……コンクリート充填空間
19……植栽土
20……ブロックユニット
R1〜R6……ブロック列
[0001]
TECHNICAL FIELD OF THE INVENTION
TECHNICAL FIELD The present invention relates to a concrete retaining wall block for stacking a retaining wall on a slope of a river, a road, a lands, and the like, and a retaining wall construction method using the retaining wall block.
[0002]
[Prior art]
In this type of retaining wall, it is important that the retaining wall be firmly fixed to the slope of a river so as to exhibit a sufficient earth retaining function.
[0003]
Therefore, as disclosed in, for example, Japanese Patent Application Laid-Open No. H11-310913, a plurality of construction stones in which a bar-shaped member and a washer are attached to natural stone are prepared, and after these construction stones are stacked on a slope of a river, A method has been proposed in which a rod-like member and a washer of these construction stones are buried with earth and sand, and each construction stone is fixed by a frictional force with the earth and sand.
[0004]
[Problems to be solved by the invention]
However, this method has the following disadvantages.
[0005]
First, because the earth and sand that fix the construction stone has fluidity, it is not only possible to construct a very strong retaining wall, but also the construction stone may collapse due to the occurrence of an earthquake or typhoon. There is also a problem with the safety of the retaining wall after construction.
[0006]
Secondly, since the work of stacking construction stones and the work after that are all performed on site, the construction period of the retaining wall is easily affected by the site conditions (weather, etc.) and the skills of the site workers. There is a high risk of causing variations.
[0007]
In view of such circumstances, the present invention can construct a strong retaining wall, has no problem in safety after construction, and can suppress the occurrence of construction period variations. And a retaining wall construction method.
[0008]
[Means for Solving the Problems]
That is, the invention of the retaining wall block of the present invention has a rectangular parallelepiped block main body (2) made of concrete, and a fixed hook (6) made of concrete is integrally formed on the back surface of the block main body. In the wall block (1), a fixed hook including a locking plate (6a) and a leg (6b) connecting the locking plate to the block body is used as the fixed hook. The cross-sectional area of the portion is made smaller than the area of the locking plate. Here, the number of legs of the fixed hook is not limited to one, and two or more legs may be employed. If the fixed hook has two or more legs, the total cross-sectional area of these legs may be smaller than the area of the locking plate.
[0009]
By adopting such a configuration, when a large number of retaining wall blocks are stacked, voids are formed around the legs of the fixed hooks (up, down, left and right) of each retaining wall block, and these voids are connected in all directions. It works so that the concrete filling space is formed in a lattice shape.
[0010]
Also, the block body (2) is formed by vertically penetrating a cavity (3), and an inner / outer communication hole (10) is formed on the front surface of the block body by communicating with the cavity. You.
[0011]
With this configuration, the hollow portion can be used as a fish reef as it is, and the plant soil can be put in the hollow portion, so that plants can be planted.
[0012]
On the other hand, in the retaining wall construction method of the present invention, when constructing the retaining wall (11) using the retaining wall block (1), a plurality of retaining wall blocks are piled up and a predetermined number of blocks are stacked. Rows (R1 to R6) are constructed, and then the concrete around the fixed hooks (6) of these retaining wall blocks is filled with hardening concrete and hardened.
[0013]
With such a configuration, all the retaining wall blocks act so as to be tightly fixed by the stuffed concrete of the same material.
[0014]
Further, when constructing the retaining wall (11) using the retaining wall block (1), a plurality of retaining wall blocks are assembled to construct a predetermined number of block rows (R1 to R6), After that, around the fixing hooks (6) of the retaining wall blocks, the concrete (17) is filled and hardened, and the planting soil (19) is filled in the hollow portions (3) of the retaining wall blocks. It is configured to be inserted.
[0015]
With such a configuration, all the retaining wall blocks are tightly fixed with the stuffed concrete made of the same material, and the vegetation can be planted on the planting soil in the cavity.
[0016]
Furthermore, a required number of block units (20) are produced in a factory by combining a plurality of the retaining wall blocks (1) such that the concrete filling space (18) is formed in a lattice shape, and each block unit is manufactured. The concrete filling space (17) is filled with hardened concrete (17) at the factory and hardened, and then these block units are carried to the site and joined.
[0017]
With such a configuration, work in a factory is mainly performed, so that the quality of the block unit is improved and the work efficiency in the field is improved.
[0018]
It should be noted that reference numerals in parentheses are for convenience showing corresponding elements in the drawings, and therefore, the present invention is not limited to the description in the drawings. This is the same for the column of “Claims”.
[0019]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0020]
<First embodiment>
1A and 1B are diagrams showing an embodiment of a retaining wall block according to the present invention, wherein FIG. 1A is a plan view thereof, FIG. 1B is a right side view thereof, and FIG.
2A and 2B are diagrams showing a state in which the retaining wall blocks shown in FIG. 1 are piled up to form a retaining wall, wherein FIG. 2A is a front view thereof, and FIG. 2B is a cross-sectional view taken along line BB of FIG. FIG. 1C is an enlarged detailed view of a portion C of FIG. 2B, FIG. 2D is an enlarged sectional view taken along line DD of FIG.
FIG. 3 is a front view of a state in which the retaining wall blocks shown in FIG.
[0021]
As shown in FIG. 1, the retaining wall block 1 has a rectangular parallelepiped block main body 2 made of concrete, and a fixed hook 6 made of concrete is integrally formed on the back surface of the block main body 2. . The fixing hook 6 includes a locking plate 6a having an area approximately equal to that of the block main body 2 and two legs 6b connecting the locking plate 6a to the block main body 2 as shown in FIG. As shown in (a) and (b), the total cross-sectional area of these legs 6b is smaller than the area of the locking plate 6a.
[0022]
As shown in FIG. 1 (a), a cavity 3 is formed vertically through the center of the block body 2, and grooves 4 and 5 are vertically formed on both left and right sides of the block body 2, respectively. It is formed through. Further, on the front surface of the block body 2, as shown in FIG. 1 (c), a semicircular cutout 7 is formed at the center of the upper part so as to communicate with the cavity part 3, and the lower left and right ends thereof are formed. Are formed with cutouts 8 and 9 each having a quarter circle shape and communicating with the grooves 4 and 5, respectively. Here, the three cutouts 7, 8, and 9 are all arcs having the same curvature. Note that an engagement projection 2a and an engagement recess 2b are formed on the upper and lower surfaces of the block body 2, respectively.
[0023]
Since the retaining wall block 1 has the above-described configuration, when a large number of retaining wall blocks 1 are piled up on the slope of a river to construct the retaining wall 11, FIGS. As shown in b), after laying the base material 12 on both sides of the river, a base concrete 13 is poured over the base material 12 and cured. When the foundation concrete 13 has hardened, the required number of retaining wall blocks 1 are carried to the site (near the slope of the river), and these retaining wall blocks 1 are transferred to the foundation concrete 13 according to the procedure described below. Pile up six layers with flat top.
[0024]
First, a plurality of retaining wall blocks 1 are horizontally laid on the foundation concrete 13 to construct a first (lowest) block row R1. Then, as shown in FIG. 2 (d), the grooves 4, 5 of the retaining wall block 1, which are adjacent to each other on the left and right, are opposed to each other, and the cavity 15 is vertically penetrated by these grooves 4, 5. It is formed.
[0025]
Next, a plurality of retaining wall blocks 1 are horizontally shifted by half the width of the retaining wall block 1 in the horizontal direction above the first-stage block row R1, thereby forming a two-stage matrix. The eye block sequence R2 is constructed. Then, also in the second row of blocks R2, the grooves 4 and 5 of the retaining wall block 1 adjacent to each other face each other and come into contact with each other, and the cavity 15 is formed so as to penetrate vertically by the grooves 4 and 5. Is done. At this time, since the second-stage block row R2 is horizontally displaced from the first-stage block row R1 by half the width of the retaining wall block 1, each cavity of the first-stage block row R1 is displaced. The cavity 3 of each retaining wall block 1 of the second row of block rows R2 is positioned above the top 15 and at the same time the cavity 3 of each retaining wall block 1 of the first row of block rows R1. Each cavity 15 of the second row of blocks R2 is positioned on the upper side.
[0026]
In addition, as shown in FIG. 2B, the second-stage block row R2 is inclinedly placed on the first-stage block row R1, but as shown in FIG. 2C. The engaging concave portion 2b of the block body 2 of the retaining wall block 1 in the second row of block rows R2 is engaged with the engaging convex portion 2a of the block main body 2 of the retaining wall block 1 in the first block row R1. Since the second row of blocks R2 is engaged, there is no possibility that the second row of blocks R2 will slide rearward under its own weight. This is the same for the third to sixth-stage block rows R3 to R6 described later.
[0027]
Next, a plurality of retaining wall blocks 1 are horizontally shifted by half the width of the retaining wall block 1 in the horizontal direction above the second-stage block row R2, and the third retaining wall blocks 1 are stacked horizontally. Is constructed. Then, also in the third block row R3, the grooves 4 and 5 of the retaining wall block 1 adjacent to each other face each other and come into contact with each other, so that the cavity 15 is formed so as to penetrate vertically. Is done. At this time, since the third-stage block row R3 is horizontally displaced from the second-stage block row R2 by half the width of the retaining wall block 1, each cavity of the second-stage block row R2. At the same time, the cavity 3 of each retaining wall block 1 of the third row of blocks R3 is positioned above 15 and the cavity 3 of each retaining wall block 1 of the second row of blocks R2. Each cavity 15 of the third row of blocks R3 is positioned on the upper side. In addition, the fixing hooks 6 of all the retaining wall blocks 1 in the first to third block rows R1 to R3 are gathered and, as shown in FIG. 2 (d), around the legs 6b. The concrete filling space 18 is formed in a lattice shape.
[0028]
When the first to third block rows R1 to R3 are thus constructed, the block rows R1 to R3 are fixed so that they do not collapse backward, as shown in FIG. After filling the backfilling material 16 such as gravel or split stone between the slope and the block rows R1 to R3, the concrete filling 17 is poured into the concrete filling space 18 and cured. Then, the surrounding concrete around the legs 6b of the fixed hooks 6 of each retaining wall block 1 is hardened in a state where the concrete 17 is filled, and all the retaining wall blocks 1 are of the same type as the retaining wall block 1. It is firmly tied to each other by the stuffing concrete 17 which is a material and fixed to the slope of the river.
[0029]
Thereafter, a plurality of retaining wall blocks 1 are horizontally shifted by half the width of the retaining wall block 1 in the horizontal direction above the third row of block rows R3 to thereby form the fourth row. Is constructed. Then, also in the fourth block row R4, the grooves 4 and 5 of the retaining wall block 1 adjacent to each other face each other and abut against each other, and the cavity 15 is formed so as to penetrate vertically by the grooves 4 and 5. Is done. At this time, since the fourth block row R4 is horizontally displaced from the third block row R3 by half the width of the retaining wall block 1, each cavity of the third block row R3 is provided. At the same time, the cavity 3 of each retaining wall block 1 of the fourth row of blocks R4 is positioned above 15 and at the same time the cavity 3 of each retaining wall block 1 of the third row of blocks R3 is positioned. Each cavity 15 of the fourth row of blocks R4 is positioned above.
[0030]
Next, on the upper side of the fourth block row R4, a plurality of retaining wall blocks 1 are horizontally displaced by half the width of the retaining wall block 1 to be horizontally laid, thereby forming a five-step masonry. Construct an eye block sequence R5. Then, also in the fifth block row R5, the grooves 4 and 5 of the retaining wall block 1 adjacent to each other face each other and come into contact with each other, and the cavity 15 is formed so as to penetrate vertically by the grooves 4 and 5. Is done. At this time, since the fifth block row R5 is horizontally displaced from the fourth block row R4 by half the width of the retaining wall block 1, each cavity of the fourth block row R4 is displaced. The cavity 3 of each retaining wall block 1 of the fifth row of blocks R5 is positioned above the fifteenth row 15 at the same time as the cavity 3 of each retaining wall block 1 of the fourth row of blocks R4. Each cavity 15 of the fifth row of blocks R5 is positioned above.
[0031]
Finally, a plurality of retaining wall blocks 1 are horizontally shifted by half the width of the retaining wall block 1 horizontally above the fifth row of block rows R5, thereby forming a six-stage block. The block row R6 of the eye (top row) is constructed. Then, also in the sixth row of rows R6, the grooves 4 and 5 of the retaining wall block 1 adjacent to each other face each other and come into contact with each other, so that the cavity 15 is formed so as to penetrate vertically. Is done. At this time, since the sixth block row R6 is horizontally displaced from the fifth block row R5 by half the width of the retaining wall block 1, each cavity of the fifth block row R5 is displaced. The cavity 3 of each retaining wall block 1 of the sixth row of blocks R6 is positioned above the fifteenth row, and at the same time, the cavity 3 of each retaining wall block 1 of the fifth row of blocks R5 is positioned. Each cavity 15 of the sixth row of blocks R6 is positioned above. In addition, the fixed hooks 6 of all the retaining wall blocks 1 in the block rows R4 to R6 from the fourth to the sixth row gather, and a concrete filling space 18 is formed in a grid around the legs 6b. Is done.
[0032]
In this way, when the fourth to sixth block rows R4 to R6 have been constructed, the block rows R4 to R6 are fixed so that they do not collapse backward, so that the river slope and the block rows R4 to R6 are fixed. After filling the backfill material 16 between them, the filling concrete 17 is poured into the concrete filling space 18 and cured. Then, the surrounding concrete around the legs 6b of the fixed hooks 6 of each retaining wall block 1 is hardened in a state where the concrete 17 is filled, and all the retaining wall blocks 1 are of the same type as the retaining wall block 1. It is firmly tied to each other by the stuffing concrete 17 which is a material and fixed to the slope of the river.
[0033]
In this manner, when the retaining wall blocks 1 of all the block rows R1 to R6 from the bottom to the top are fixed to the slope of the river, the retaining wall 11 is constructed by these retaining wall blocks 1. . At this time, in any two upper and lower block rows R1 to R6, the cavity portion 3 of each retaining wall block 1 in the upper block row is positioned above each cavity 15 in the lower block row. Thus, the cavities 15 of the upper block row are positioned above the cavities 3 of the retaining wall blocks 1 of the lower block row. Therefore, as shown in FIG. 2A, the cavities 15 and the cavities 3 are alternately arranged in the vertical direction from the uppermost (sixth) block row R6 to the lowermost (first) block row R1. Will be in communication. As shown in FIG. 2, the notch portions 7, 8, and 9 of the retaining wall blocks vertically and horizontally adjacent to each other cooperate to form a circular inner / outer communication hole 10, and the retaining wall is formed through the inner / outer communication hole 10. The cavity 3 or cavity 15 of the application block 1 communicates with the front space S.
[0034]
If the retaining wall 11 is used as it is, under the surface of the water, the water of the river flows into the cavity 3 and the cavity 15 of the retaining wall block 1 through the inside / outside communication hole 10, and aquatic animals such as fish are circulated. Since a part of the retaining wall block 1 (the part below the water surface) can be used as a fish reef, the river becomes a river that is easy to inhabit for aquatic animals, and the environmental preservation of the retaining wall block 1 is improved.
[0035]
When the slope of the river is greened, planting soil 19 is put into the cavity 3 and the cavity 15 of each retaining wall block 1 in the uppermost block row R6. Then, as described above, the cavities 15 and the cavities 3 are alternately communicated in the vertical direction from the uppermost block row R6 to the lowermost block row R1. Through the cavity 3 or cavity 15 of the retaining wall block 1 of R5, R4, R3, R2, it reaches the lowermost block row R1 and accumulates on it one after another. As a result, as shown in FIGS. 2B and 2C, the planting soil 19 is filled in the cavity portions 3 and the cavities 15 of all the retaining wall blocks 1, and further, all the inside and outside communication holes 10 are formed. Since the planting soil 19 appears on the river side, it is possible to plant and plant greenery there.
[0036]
Incidentally, as for the method of stacking the retaining wall blocks 1, valley stacking is possible in addition to the flat stacking described above. When this valley is adopted, as shown in FIG. 3, the blocks 1 for retaining walls are piled while being inclined at 45 °. Also at this time, since the concrete filling space 18 is formed in a grid around the legs 6b of the fixed hooks 6 of all the retaining wall blocks 1, all the retaining wall blocks 1 are firmly connected to each other by the stuffing concrete 17. Be tied to. In addition, since the cavity 15 and the cavity 3 alternately communicate with each other in the vertical direction from the uppermost stage to the lowermost stage, a lightning-shaped path is secured, so that the planting soil 19 can be smoothly injected as in the case of flat stacking. Can be implemented.
[0037]
In the first embodiment described above, the arc-shaped (semicircular, quarter-circular) cutouts 7, 8, and 9 are provided on the front surface of the block main body 2, so that when the blocks are stacked, they are circular in and out. The case where the communication hole 10 is formed has been described. However, the shape of these cutouts 7, 8, 9 is not limited to an arc shape. For example, rectangular communication holes 10 can be formed by adopting rectangular cutouts 7, 8, 9. . Of course, when it is not necessary to enhance the environmental preservation of the retaining wall block 1, the notch portions 7, 8, and 9 can be omitted to reduce the manufacturing cost of the retaining wall block 1.
[0038]
Further, in the first embodiment described above, the case where the retaining wall blocks 1 are piled up in six levels and the retaining wall 11 is constructed is described. However, the number of the retaining wall blocks 1 is limited to six levels. It goes without saying that it cannot be done.
[0039]
Furthermore, in the first embodiment described above, after a predetermined number of retaining wall blocks 1 are carried into the site (near a river slope), these retaining wall blocks 1 are piled up at the site to form the retaining wall 11. Has been described, but a block unit having a shape in which some of the retaining wall blocks 1 are combined is prepared in advance in a factory, and the block unit is carried to the site and joined to form the retaining wall 11. Construction is also possible. Hereinafter, as a second embodiment, a retaining wall construction method using this block unit will be described.
[0040]
<Second embodiment>
FIGS. 4A and 4B are diagrams showing an example of a block unit in which some of the retaining wall blocks shown in FIG. 1 are combined to form a unit, where FIG. 4A is a front view, FIG. 4B is a plan view thereof, and FIG. (D) is a right side view thereof, (e) is a sectional view taken along line EE of (a), (f) is a sectional view taken along line FF of (a),
5: is a figure which shows the state which piled up the block unit shown in FIG. 4, and constructed the retaining wall, (a) is the front view, (b) is sectional drawing by the BB line of (a). is there.
[0041]
As shown in FIG. 4, the block unit 20 has a shape in which some of the above-described retaining wall blocks 1 are combined, and engagement protrusions 21 and 22 are formed on the upper surface and the left surface thereof. In addition, engagement recesses 23 and 24 are formed on the lower surface and the right surface. As shown in FIGS. 4B and 4F, the block unit 20 is formed with a plurality of cavities 3 and cavities 15 alternately arranged on the left and right. Behind the cavity 15, a concrete filling space 18 is formed in a lattice shape. Further, on the front surface of the block unit 20, a plurality of circular inner / outer communication holes 10 are formed so as to communicate with the cavity 3 or the cavity 15, as shown in FIG. Then, as shown in FIGS. 4E and 4F, planting soil 19 is put into all the cavities 3 and the cavities 15, and the concrete filling 17 is put into the concrete filling space 18. It is filled and cured. Therefore, the block unit 20 is stiffened by the stuffing concrete 17 and exhibits high rigidity. In order to further improve the rigidity of the block unit 20, reinforcing bars may be arranged in the concrete filling space 18 in two directions.
[0042]
Since the block units 20 have the above configuration, when the plurality of block units 20 are stacked on the slope of the river and the retaining wall 11 is constructed, the required number of block units 20 are placed on the site (of the river). 5), the block units 20 are stacked in three steps on the upper side of the foundation concrete 13, and each block unit 20 is provided with its engaging projections 21 and 22 and the engaging recess 23 as shown in FIG. , 24 are fitted and joined.
[0043]
At this time, since each block unit 20 has high rigidity as described above, it is excellent in handleability, and the joining operation can be performed efficiently in a short time. In addition, since all the block units 20 are of high quality manufactured in the factory, the construction period of the retaining wall does not depend on the situation of the site and the skills of the site workers, and the construction period is as scheduled. The construction of the wall 11 can be completed.
[0044]
In the above-described second embodiment, a case has been described in which the block units 20 are stacked in three stages to construct the retaining wall 11, but it is needless to say that the number of stages of the block units 20 is not limited to three.
[0045]
Further, in the first and second embodiments described above, the case where the retaining wall 11 is constructed on the slope of the river using the retaining wall block 1 and the block unit 20 has been described. The present invention can be applied to the case where the retaining wall 11 is constructed.
[0046]
【The invention's effect】
As described above, according to the first aspect of the invention, when a large number of retaining wall blocks are stacked, a gap is formed around the legs (up, down, left and right) of the fixing hook of each retaining wall block. Since these voids are connected in all directions and the concrete filling space is formed in a grid pattern, it can withstand earthquakes and typhoons, and can be used for retaining walls that can be used to build strong retaining walls without any problem in safety after construction Blocks can be provided.
[0047]
According to the second aspect of the present invention, the hollow portion can be used as a fish reef as it is, and planting soil can be put in the hollow portion and plants can be planted. In addition to the function and effect, it is possible to provide an environment-adaptive retaining wall block capable of easily inhabiting aquatic animals and maintaining a natural landscape by greening.
[0048]
On the other hand, according to the third aspect of the present invention, since all the retaining wall blocks are tightly fixed with the stuffed concrete of the same material, they withstand earthquakes, typhoons, etc., and there is no problem in safety after construction. It is possible to provide a retaining wall construction method capable of constructing a strong retaining wall.
[0049]
In addition, according to the invention described in claim 4, all the retaining wall blocks are tightly fixed by the stuffing concrete of the same material, and it becomes possible to plant plants on the planting soil in the cavity. In addition to the above-described effects, it is possible to provide an environment-adaptive retaining wall construction method capable of easily retaining aquatic animals and maintaining a natural landscape by greening.
[0050]
Furthermore, according to the invention as set forth in claim 5, since the work in the factory is mainly performed, the quality of the block unit is improved, and the work efficiency on the site is improved. It is possible to provide a retaining wall construction method capable of suppressing occurrence of construction period variations.
[Brief description of the drawings]
FIG. 1 is a view showing an embodiment of a retaining wall block according to the present invention, wherein (a) is a plan view thereof, (b) is a right side view thereof, and (c) is a front view thereof.
FIGS. 2A and 2B are diagrams showing a state in which the retaining wall blocks shown in FIG. 1 are piled up and a retaining wall is constructed, wherein FIG. 2A is a front view thereof, and FIG. FIG. 4C is an enlarged detailed view of a portion C in FIG. 4B, and FIG. 4D is an enlarged sectional view taken along line DD in FIG.
3 is a front view of a state where the retaining wall blocks illustrated in FIG. 1 are piled up to form a retaining wall.
4A and 4B are diagrams showing an example of a block unit in which some retaining wall blocks shown in FIG. 1 are combined to form a unit, wherein FIG. 4A is a front view, FIG. 4B is a plan view thereof, and FIG. Is a left side view thereof, (d) is a right side view thereof, (e) is a sectional view taken along line EE of (a), and (f) is a sectional view taken along line FF of (a).
5A and 5B are diagrams showing a state in which the block units shown in FIG. 4 are piled up to form a retaining wall, (a) is a front view thereof, and (b) is a cross-sectional view taken along line BB of (a). It is.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Retaining wall block 2 ... Block main body 3 ... Cavity part 6 ... Fixing hook 6a ... Locking plate 6b ... Leg part 10 ... Internal / external communication hole 11 ... Retaining wall 17 ... Packing Concrete 18 Concrete filling space 19 Planting soil 20 Block units R1 to R6 Block row

Claims (5)

コンクリートからなる直方体状のブロック本体(2)を有し、
このブロック本体の背面に、コンクリートからなる固定フック(6)を一体に形成した擁壁用ブロック(1)において、
前記固定フックとして、
係止板(6a)と、この係止板を前記ブロック本体に連結する脚部(6b)とからなる固定フックを用い、
この固定フックの脚部の断面積を係止板の面積より小さくしたことを特徴とする擁壁用ブロック。
It has a rectangular parallelepiped block body (2) made of concrete,
In the retaining wall block (1) integrally formed with a fixed hook (6) made of concrete on the back surface of the block body,
As the fixed hook,
A fixing hook comprising a locking plate (6a) and a leg (6b) connecting the locking plate to the block body is used.
A retaining wall block, wherein a cross-sectional area of a leg portion of the fixing hook is smaller than an area of a locking plate.
前記ブロック本体(2)に空胴部(3)を上下に貫通させて形成し、
前記ブロック本体の前面に内外連通孔(10)を前記空胴部に連通させて形成したことを特徴とする請求項1に記載の擁壁用ブロック。
A cavity portion (3) is formed by vertically penetrating the block body (2);
The retaining wall block according to claim 1, wherein an inside / outside communication hole (10) is formed in the front surface of the block body so as to communicate with the cavity.
請求項1に記載の擁壁用ブロック(1)を用いて擁壁(11)を施工する際に、
複数個の擁壁用ブロックを組積して所定段数のブロック列(R1〜R6)を構築し、
その後、これら擁壁用ブロックの固定フック(6)の周囲に胴込めコンクリート(17)を充填して硬化させるようにしたことを特徴とする擁壁施工方法。
When the retaining wall (11) is constructed using the retaining wall block (1) according to claim 1,
A plurality of retaining wall blocks are assembled to construct a predetermined number of block rows (R1 to R6),
After that, the concrete around the fixed hooks (6) of the retaining wall blocks is filled with hardening concrete (17) to be hardened.
請求項2に記載の擁壁用ブロック(1)を用いて擁壁(11)を施工する際に、
複数個の擁壁用ブロックを組積して所定段数のブロック列(R1〜R6)を構築し、
その後、これら擁壁用ブロックの固定フック(6)の周囲に胴込めコンクリート(17)を充填して硬化させるとともに、
これら擁壁用ブロックの空胴部(3)に植栽土(19)を入れるようにしたことを特徴とする擁壁施工方法。
When the retaining wall (11) is constructed using the retaining wall block (1) according to claim 2,
A plurality of retaining wall blocks are assembled to construct a predetermined number of block rows (R1 to R6),
After that, the concrete around the fixed hooks (6) of the retaining wall blocks is filled with hardening concrete (17) and hardened.
A method for constructing a retaining wall, wherein planting soil (19) is put in the cavity (3) of the retaining wall block.
請求項1または請求項2に記載の擁壁用ブロック(1)をコンクリート充填空間(18)が格子状に形成されるように複数個組み合わせてユニット化したブロックユニット(20)を工場で必要個数だけ作製し、
各ブロックユニットのコンクリート充填空間に胴込めコンクリート(17)を工場で充填して硬化させ、
その後、これらブロックユニットを現場に搬入して接合するようにしたことを特徴とする擁壁施工方法。
A required number of block units (20) obtained by combining a plurality of the retaining wall blocks (1) according to claim 1 or 2 so as to form a concrete-filled space (18) in a lattice shape and forming a unit. Just make,
The concrete filling space of each block unit is filled with concrete (17) at the factory and hardened,
After that, these block units are brought to the site and joined to each other, and a retaining wall construction method is provided.
JP2002234467A 2002-08-12 2002-08-12 Block for retaining wall and retaining wall construction method Pending JP2004076295A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002234467A JP2004076295A (en) 2002-08-12 2002-08-12 Block for retaining wall and retaining wall construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002234467A JP2004076295A (en) 2002-08-12 2002-08-12 Block for retaining wall and retaining wall construction method

Publications (1)

Publication Number Publication Date
JP2004076295A true JP2004076295A (en) 2004-03-11

Family

ID=32019273

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002234467A Pending JP2004076295A (en) 2002-08-12 2002-08-12 Block for retaining wall and retaining wall construction method

Country Status (1)

Country Link
JP (1) JP2004076295A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104328797A (en) * 2014-09-25 2015-02-04 陕西华山路桥工程有限公司 High-side-slope large-curve retaining wall building construction method
CN105256765A (en) * 2015-09-30 2016-01-20 黄文勇 Water retaining wall unit, water retaining wall and water retaining method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104328797A (en) * 2014-09-25 2015-02-04 陕西华山路桥工程有限公司 High-side-slope large-curve retaining wall building construction method
CN104328797B (en) * 2014-09-25 2015-12-09 陕西华山路桥工程有限公司 High slope large curvy wall building construction engineering method
CN105256765A (en) * 2015-09-30 2016-01-20 黄文勇 Water retaining wall unit, water retaining wall and water retaining method
CN105256765B (en) * 2015-09-30 2017-05-31 黄文勇 A kind of waterwall unit and waterwall and dash method

Similar Documents

Publication Publication Date Title
KR100402843B1 (en) Afforestation Retaining-Wall laying Concrete-block
JP2004076295A (en) Block for retaining wall and retaining wall construction method
KR100515136B1 (en) Vegetation block, and method for constructing vegetation retaining wall and bank protection using the block
KR100536304B1 (en) Vegetation revetment structures and method constructing blocktype revetment using the same
KR20160109206A (en) A gabion
KR100349863B1 (en) Revetment Block and Construction Method of Revetment for using thereof
JP2003119787A (en) Greening structure of construction
JP3446116B2 (en) Ecological conservation block and stacking method
KR100970457B1 (en) Block for wall and method for constructing wall using the same
KR200297571Y1 (en) Vegetation retaining wall structure
KR100994426B1 (en) Landscape block for reinforcing slope
KR100746128B1 (en) a block including planting space and construction method using the same
JP3266876B2 (en) Soil / cover soil block and construction method
KR200275387Y1 (en) Green Wall System
KR101129494B1 (en) Vegetation retaining wall structure and method forconstructing a retaining wall using the same
KR101539400B1 (en) A Soundproof Gabion Structure Having Solar Panel Installed thereon
JP3013406U (en) Multi-natural river revetment block
JP2004308244A (en) Retaining-wall block, partitioning board and method for constructing retaining wall
KR20110033479A (en) Log stone basket
CN214940257U (en) Grass planting brick for splicing and paving square grids
KR100720033B1 (en) A planting breast block and a breast wall
JP2001207468A (en) Block for environmental retaining wall
KR100948202B1 (en) Vegetation revetment block
KR100778066B1 (en) Construction structure making for breast wall
JP3294715B2 (en) Block structure for retaining wall and method for forming retaining wall