JP2002242210A - Earth retaining wall and construction method therefor - Google Patents

Earth retaining wall and construction method therefor

Info

Publication number
JP2002242210A
JP2002242210A JP2001041538A JP2001041538A JP2002242210A JP 2002242210 A JP2002242210 A JP 2002242210A JP 2001041538 A JP2001041538 A JP 2001041538A JP 2001041538 A JP2001041538 A JP 2001041538A JP 2002242210 A JP2002242210 A JP 2002242210A
Authority
JP
Japan
Prior art keywords
concrete
steel sheet
sheet pile
retaining wall
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2001041538A
Other languages
Japanese (ja)
Other versions
JP4647113B2 (en
Inventor
Kiyoshi Sano
佐野  清
Keiichi Iwatsuri
敬一 岩釣
Kengo Hori
堀  謙吾
Yoshikatsu Akiyama
祥克 秋山
Hiroyuki Handa
博幸 半田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
INBAKKUSU KK
Nippon Steel Metal Products Co Ltd
Original Assignee
INBAKKUSU KK
Nippon Steel Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by INBAKKUSU KK, Nippon Steel Metal Products Co Ltd filed Critical INBAKKUSU KK
Priority to JP2001041538A priority Critical patent/JP4647113B2/en
Publication of JP2002242210A publication Critical patent/JP2002242210A/en
Application granted granted Critical
Publication of JP4647113B2 publication Critical patent/JP4647113B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Retaining Walls (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide an earth retaining retaining wall and a construction method therefor capable of shaping an external wall member easily, facilitating construction work, improving work efficiency, reducing cost, and providing sufficient strength for a concrete placing pressure. SOLUTION: A foundation beam for determining a lower end position of the external wall member of the earth retaining wall is arranged as an upward facing channel on foundation ground and is joined with a fixing member fixed to the foundation ground, and a lower end of the external wall member is inserted into a ditch of the foundation beam. The external wall member is timbered by a column member supported by a support member from an inner side, a wale member in the horizontal direction is joined with the external wall member, and an anchor member is attached to the wale member. Concrete is placed between the external wall member and a slope.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、地山の法面が崩
落するのを防ぐために構築される土留め擁壁及びその構
築工法の技術分野に属し、更に云えば、鋼矢板をコンク
リート型枠兼用の外壁材として用い、外壁材と法面との
間にコンクリートを打設した土留め擁壁及びその構築工
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention belongs to the technical field of earth retaining walls constructed to prevent the slopes of the ground from collapsing and the construction method thereof. The present invention relates to an earth retaining wall in which concrete is cast between an outer wall material and a slope, and a construction method thereof.

【0002】[0002]

【従来の技術】従来、鋼矢板をコンクリート型枠兼用の
外壁材として用い、前記外壁材と法面との間にコンクリ
ートを打設した土留め擁壁及びその構築工法は皆無に等
しい。類似する公知技術としては、特開平11−210
004号公報に記載の斜面補強擁壁工法で構築された土
留め擁壁が存在する。
2. Description of the Related Art Conventionally, there are almost no earth retaining retaining walls in which a steel sheet pile is used as an outer wall material that also serves as a concrete formwork, and concrete is cast between the outer wall material and the slope, and a construction method therefor. A similar known technique is disclosed in JP-A-11-210.
There is an earth retaining wall constructed by the slope reinforcing retaining wall method described in Japanese Patent Application Publication No. 004-004.

【0003】前記斜面補強擁壁工法は、図8に示すよう
に、地山1の法面2にアンカー材aの一方の端部を打設
し、他方の端部をコンクリートパネルbに接合して前記
地山1とコンクリートパネルbを連結する。同様に地山
1と連結したコンクリートパネルbを複数積み上げて構
築し、上下方向及び左右方向のコンクリートパネルb、
b相互を鉄筋cで連結し、更に前記アンカー材aと鉄筋
cとを一体化する。前記コンクリートパネルb…と地山
1の法面2との間にコンクリート6を打設して強度が発
現するまで養生する。上記工程を複数回繰り返し土留め
擁壁を完成する。
In the slope reinforcing retaining wall method, as shown in FIG. 8, one end of an anchor material a is cast on a slope 2 of a ground 1 and the other end is joined to a concrete panel b. To connect the ground 1 and the concrete panel b. Similarly, a plurality of concrete panels b connected to the ground 1 are piled up and constructed, and the concrete panels b in the vertical and horizontal directions,
b are connected to each other by a reinforcing bar c, and the anchor material a and the reinforcing bar c are further integrated. Concrete 6 is cast between the concrete panels b and the slope 2 of the ground 1 and cured until the strength is developed. The above process is repeated several times to complete the earth retaining wall.

【0004】[0004]

【本発明が解決しようとする課題】前記斜面補強擁壁工
法により構築された土留め擁壁は、アンカー材aを地山
1の法面2に打設する必要があり作業が煩雑である。
The earth retaining wall constructed by the above-mentioned slope reinforcing retaining wall construction method requires the anchor material a to be cast on the slope 2 of the ground 1 and the work is complicated.

【0005】また、前記コンクリートパネルb…は、ア
ンカー材aと鉄筋cとで定形化しているだけなので、コ
ンクリート6の打設圧により隣り合うコンクリートパネ
ルb、b間に間隔が生じて、打設コンクリート6が漏れ
出すおそれがある。
Further, since the concrete panels b are simply formed by the anchor material a and the reinforcing bar c, a gap is generated between the adjacent concrete panels b due to the casting pressure of the concrete 6, so that the concrete panels b are cast. Concrete 6 may leak out.

【0006】更に、前記コンクリートパネルb…の定形
化は、上下方向及び左右方向のコンクリートパネルb、
b相互を鉄筋cで連結(具体的には、コンクリートパネ
ルbに上下方向及び左右方向に貫通した孔を設け、前記
パネルb、b相互の孔に鉄筋cを貫通させて連結す
る。)して行うため、コンクリートパネルbの配置位置
が少しでもずれると、孔の位置がずれてしまい鉄筋cを
貫通させることが難しく、コンクリートパネルb…の定
形化が困難である。また配置位置がずれてもコンクリー
トパネルbは相当な重量があるため、位置を修正するこ
とが困難で構築作業が煩雑である。そのため、作業効率
が悪くコストが嵩む。
[0006] Further, the concrete panels b are formed into concrete panels b in vertical and horizontal directions.
b is connected to each other by a reinforcing bar c (specifically, a hole penetrating the concrete panel b in the up-down direction and the left-right direction is provided, and the reinforcing bar c is connected to the hole between the panels b and b so as to be connected). Therefore, even if the arrangement position of the concrete panel b is slightly shifted, the position of the hole is shifted and it is difficult to penetrate the reinforcing bar c, and it is difficult to form the concrete panels b. Even if the arrangement position is shifted, since the concrete panel b has a considerable weight, it is difficult to correct the position and the construction work is complicated. Therefore, the work efficiency is low and the cost increases.

【0007】従って、本発明の目的は、外壁材の定形化
を容易に行うことができ構築作業が簡易で、作業効率の
向上及びコストの削減に寄与し、しかもコンクリートの
打設圧に十分な強度を発揮することができる土留め擁壁
及びその構築工法を提供することである。
Accordingly, an object of the present invention is to make it possible to easily form the outer wall material, to simplify the construction work, to improve the work efficiency and to reduce the cost, and to provide a sufficient pressure for the concrete placing pressure. An object of the present invention is to provide an earth retaining wall capable of exhibiting strength and a construction method thereof.

【0008】[0008]

【課題を解決するための手段】上記従来技術の課題を解
決するための手段として、請求項1に記載した発明に係
る土留め擁壁は、地山の法面の土石等が崩落するのを防
ぐために構築される土留め擁壁において、土留め擁壁の
外壁材の下端位置を定める基礎梁が基礎地盤上に上向き
の溝形断面材として配置され、該基礎梁は基礎地盤に固
定された固定部材と接合されており、基礎梁の溝内へ外
壁材の下端が挿入されていること、前記外壁材は内側か
らサポート材で支持された柱材で支保されており、前記
外壁材に水平方向の腹起こし材が接合され、その腹起こ
し材にアンカー材が取り付けられていること、前記外壁
材と法面との間へコンクリートが打設されていることを
特徴とする。
Means for Solving the Problems As a means for solving the problems of the prior art, a retaining wall according to the first aspect of the present invention is designed to prevent debris and the like on the slope of the ground from collapsing. In the earth retaining wall constructed to prevent, a foundation beam that defines the lower end position of the outer wall material of the earth retaining wall is arranged as an upward groove-shaped section member on the foundation ground, and the foundation beam is fixed to the foundation ground. The lower end of the outer wall material is inserted into the groove of the foundation beam, and the outer wall material is supported by a column material supported by a support material from the inside, and is horizontally attached to the outer wall material. The ridges are joined to each other, an anchor is attached to the ridges, and concrete is cast between the outer wall material and the slope.

【0009】請求項2記載の発明は、請求項1に記載し
た発明に係る土留め擁壁において、前記外壁材は、鋼矢
板、若しくは軽量鋼矢板又はライナープレートのいずれ
かで構成されていることを特徴とする。
According to a second aspect of the present invention, in the earth retaining wall according to the first aspect of the present invention, the outer wall material is made of a steel sheet pile, or a lightweight steel sheet pile or a liner plate. It is characterized by.

【0010】請求項3記載の発明は、請求項2に記載し
た発明に係る土留め擁壁において、前記鋼矢板、若しく
は軽量鋼矢板又はライナープレートは、千鳥状配置に組
み立てられていることを特徴とする。
According to a third aspect of the present invention, in the earth retaining wall according to the second aspect, the steel sheet pile, the lightweight steel sheet pile or the liner plate is assembled in a staggered arrangement. And

【0011】請求項4記載の発明は、請求項1に記載し
た発明に係る土留め擁壁において、前記コンクリートの
骨材がクラッシャーランであることを特徴とする。
According to a fourth aspect of the present invention, in the earth retaining wall according to the first aspect, the aggregate of the concrete is a crusher run.

【0012】請求項5に記載した発明に係る土留め擁壁
の構築工法は、地山の法面の土石等が崩落するのを防ぐ
ために構築される土留め擁壁の構築工法において、土留
め擁壁の外壁材の下端位置を定める基礎梁を基礎地盤上
に上向きの溝形断面材として配置し、該基礎梁は基礎地
盤に固定された固定部材と接合し、この基礎梁の溝内へ
外壁材の下端を挿入する段階と、前記外壁材を、内側か
らサポート材で支持された柱材で支保し、前記外壁材に
水平方向の腹起こし材を接合する段階と、前記外壁材と
法面との間へ、同外壁材が自立する高さまでコンクリー
トを打設し、打設したコンクリートの上部を振動ローラ
ー等で転圧し、前記腹起こし材にアンカー材を取り付け
て、打設したコンクリートが強度を発現するまで養生す
る段階と、前記外壁材の組み立てと、コンクリートの打
設と転圧、及びアンカー材の取付け、並びにコンクリー
トの養生を行う工程を、当該土木構造物の高さまで繰り
返す段階とから成ることを特徴とする。
According to a fifth aspect of the present invention, there is provided a method for constructing an earth retaining wall, wherein the earth retaining wall is constructed so as to prevent debris or the like on a slope of the ground from collapsing. A foundation beam that determines the lower end position of the outer wall material of the retaining wall is arranged on the foundation ground as a groove-shaped section facing upward, and the foundation beam is joined to a fixing member fixed to the foundation ground, and is inserted into the groove of the foundation beam. Inserting the lower end of the outer wall material, supporting the outer wall material with a pillar material supported from the inside by a support material, and joining a horizontal bulging material to the outer wall material; Between the surface and the surface, the concrete is cast to a height at which the outer wall material is self-supporting, the upper part of the cast concrete is rolled with a vibrating roller or the like, the anchor material is attached to the belly-raising material, and the concrete is cast. Curing until strength is developed; And assembly of wood, pouring concrete and compaction, and the mounting of the anchor material, and a step of performing curing of the concrete, characterized in that it consists of a step repeated until the height of the civil engineering structures.

【0013】請求項6記載の発明は、請求項5に記載し
た発明に係る土留め擁壁の構築工法において、前記外壁
材の頂部には、堤冠材を設けることを特徴とする。
According to a sixth aspect of the present invention, in the construction method of the earth retaining wall according to the fifth aspect of the present invention, an embankment material is provided on the top of the outer wall material.

【0014】請求項7に記載した発明に係る土留め擁壁
の構築工法は、地山の法面の土砂等が崩落するのを防ぐ
ために構築される土留め擁壁の構築工法において、土留
め擁壁の外壁材を鋼矢板で構成し、その一段目の鋼矢板
の下端位置を定める基礎梁を基礎地盤上に上向きの溝形
断面材として配置し、該基礎梁は基礎地盤に固定された
固定部材と接合すること、前記基礎梁の上に、長手方向
に間隔を開けて、柱材を一定の内向き傾斜角度で立て、
各柱材は内側からサポート材により支持させる段階と、
前記柱材をガイドにしてその外側に、モジュール長さ及
び略1/2モジュール長さに加工した一段目の鋼矢板を
それぞれ互い違いの配置に接合し、それぞれの下端を前
記基礎梁の溝内へ挿入することによって各鋼矢板の継目
を上下方向に段違いの千鳥状配置に形成し、背が低い鋼
矢板の基礎梁近傍に腹起こし材をボルト接合し、前記背
が低い鋼矢板の上端部近傍まで第一段目のコンクリート
を打設し、打設したコンクリートの上部を振動ローラー
等で転圧し、強度が発現するまで養生する段階と、前記
一段目の背が低い鋼矢板の上方に二段目のモジュール長
さの鋼矢板を接合して立て、前記鋼矢板の中部に二段目
の腹起こし材をボルト接合し、前記一段目の背が高い鋼
矢板の上端部近傍まで第二段目のコンクリートを打設
し、打設したコンクリートの上部を振動ローラー等で転
圧し、前記二段目の腹起こし材にアンカー材を水平方向
に取り付けて前記打設コンクリートの天端へ置き、同コ
ンクリートが強度を発現するまで養生する段階と、以
下、モジュール長さの鋼矢板を接合して立て、腹起こし
材を取付け、コンクリートを打設して転圧し、アンカー
材を取付け、打設コンクリートが強度を発現するまで養
生する工程を当該土留め擁壁の高さまで繰り返す段階と
から成ることを特徴とする。
According to a seventh aspect of the present invention, there is provided a method for constructing an earth retaining wall, which is constructed to prevent earth and sand or the like on a slope of a ground from collapsing. The outer wall material of the retaining wall was composed of steel sheet piles, and a foundation beam for determining the lower end position of the first-stage steel sheet pile was arranged on the foundation ground as an upward groove-shaped section material, and the foundation beams were fixed to the foundation ground. Joining with the fixing member, on the foundation beam, spaced apart in the longitudinal direction, stand up the pillar at a constant inward inclination angle,
A stage where each pillar is supported by a support material from the inside,
Using the column material as a guide, a first-stage steel sheet pile processed into a module length and approximately 1/2 module length is joined to a staggered arrangement on the outside thereof, and each lower end is inserted into the groove of the foundation beam. By inserting, the seams of each steel sheet pile are formed in a staggered arrangement with a step difference in the up and down direction, a bellows material is bolted near the foundation beam of the short steel sheet pile, and near the upper end of the short steel sheet pile Casting the first stage concrete, rolling the upper part of the cast concrete with a vibrating roller or the like, and curing until the strength develops, and two stages above the first stage short steel sheet pile A steel sheet pile having a module length of the first stage is joined and erected, and a second-stage flared material is bolted to the middle of the steel sheet pile, and the second stage is raised to near the upper end of the first-stage tall sheet pile. Concrete is cast and concrete is cast Rolling the upper part of the sheet with a vibrating roller or the like, attaching the anchor material horizontally to the second-stage flaring material, placing it on the top of the cast concrete, and curing it until the concrete develops strength In the following, the process of joining steel sheet piles of module length, erecting, attaching a flaring material, casting concrete and rolling, attaching an anchor material, curing the cast concrete until the concrete develops strength, Repeating the process up to the height of the retaining wall.

【0015】請求項8記載の発明は、請求項5〜7のい
ずれか一に記載した発明に係る土留め擁壁の構築工法に
おいて、前記コンクリートの骨材がクラッシャーランで
あることを特徴とする。
According to an eighth aspect of the present invention, in the method for constructing a retaining wall according to any one of the fifth to seventh aspects, the aggregate of the concrete is a crusher run.

【0016】[0016]

【本発明の実施の形態、及び実施例】先ずは請求項7に
記載した発明に係る土留め擁壁の構築工法の実施形態
を、図1〜図7に基づいて説明する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS First, an embodiment of a method for constructing an earth retaining wall according to the present invention will be described with reference to FIGS.

【0017】前記構築工法は、地山1の法面2が崩落す
るのを防ぐために構築される土留め擁壁の構築工法とし
て好適に実施され、外壁材4としてモジュール寸法の鋼
矢板5を用い、外壁材4と法面2との間にコンクリート
6を打設して土留め擁壁を構築する。
The above-mentioned construction method is suitably implemented as a method of constructing a retaining wall for retaining the slope 2 of the ground 1 in order to prevent the slope 2 from collapsing, and using a steel sheet pile 5 having a module size as the outer wall material 4. Then, concrete 6 is cast between the outer wall material 4 and the slope 2 to construct an earth retaining wall.

【0018】図1に概略を示すように、前記土留め擁壁
の外壁材4の下端位置を定める基礎梁7を、予め土工に
より地固めを行って整地された基礎地盤3上に、上向き
の溝形断面材として配置し、該基礎梁7は基礎地盤3に
アンカー等の手段で固定された固定部材8と接合する。
As shown schematically in FIG. 1, a foundation beam 7 for determining the lower end position of the outer wall material 4 of the earth retaining wall is provided with an upwardly directed groove on the foundation ground 3 which has been previously solidified by earthworks. The foundation beam 7 is joined to a fixing member 8 fixed to the foundation ground 3 by means such as an anchor.

【0019】具体的に説明すると、前記外壁材4は、図
1〜図3等に示すように、隣り合う鋼矢板を相互に接合
できるように両端にジョイント部を有する公知の鋼矢板
5を使用し、構築作業に至便のモジュール長さ(例え
ば、1m程度)及び1/2モジュール長さに加工して用
い、もって各々の継目が互い違いに高低に変化する、所
謂段違いの千鳥状配置となるように組み立てる(請求項
2及び3記載の発明)。したがって、隣り合う鋼矢板
5、5相互を容易に、且つ緊密に接合することができ、
鋼矢板5…の定形化が容易で構築作業が簡易である。そ
のため、作業効率の向上が可能でコストの削減に寄与す
る。
More specifically, as shown in FIGS. 1 to 3 and the like, a known steel sheet pile 5 having joints at both ends is used for the outer wall material 4 so that adjacent steel sheet piles can be joined to each other. Then, it is used by processing into a module length (for example, about 1 m) and a half module length which are convenient for the construction work, so that each seam alternately changes in height, so-called staggered staggered arrangement. (The invention according to claims 2 and 3). Therefore, the adjacent steel sheet piles 5, 5 can be easily and tightly joined to each other,
The steel sheet piles 5 can be easily formed into a standard shape, and the construction work is simple. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0020】その一段目の鋼矢板5…の下端位置を定め
るのが、基礎地盤3上に設置した上向きの溝形断面をな
す基礎梁7である。前記基礎梁7は、外壁材4の長さ
(法面の長さ)に応じて複数本を接合プレート12とボ
ルト13とで長く連結して構成される(図3を参照)。
The lower end position of the first-stage steel sheet piles 5 is determined by a foundation beam 7 having an upward groove-shaped cross section and installed on the foundation ground 3. The foundation beam 7 is formed by connecting a plurality of long beams with the joining plate 12 and the bolts 13 according to the length (length of the slope) of the outer wall material 4 (see FIG. 3).

【0021】前記固定部材8は、基礎梁7の長手方向に
一定の間隔(2m程度)を開けて基礎地盤3に固定し、
その一方の端部は基礎梁7にボルトで接合している。
The fixing member 8 is fixed to the foundation ground 3 at a predetermined interval (about 2 m) in the longitudinal direction of the foundation beam 7,
One end thereof is bolted to the foundation beam 7.

【0022】前記基礎梁7の上には、長手方向に間隔を
開けて複数の柱材9を一定の内向き傾斜角度(約1.4
rad)で立て、各柱材9は基端を前記固定部材8へボル
ト止めしたサポート材10により支持させる。柱材9は
1m程度の高さを有する山形鋼で構成され、図2及び図
5に示すように、前記基礎梁7と固定部材8との接合部
位に、その下端を上記基礎梁7の溝7aの内へ挿入して
立て、上端部近傍をサポート材10とボルト止めして一
定の内向き傾斜角度に支持させている。
On the foundation beam 7, a plurality of column members 9 are spaced apart in the longitudinal direction and have a constant inward inclination angle (approximately 1.4).
The base member 9 is supported by a support member 10 bolted to the fixing member 8 at the base end. The column member 9 is made of angle iron having a height of about 1 m. As shown in FIGS. 2 and 5, the lower end of the column member 9 is provided at the joint between the foundation beam 7 and the fixing member 8, The support member 10 is bolted to the vicinity of the upper end portion to support it at a constant inward inclination angle.

【0023】前記柱材9をガイドにしてその外側に、上
記のモジュール長さ及び略1/2モジュール長さに加工
した一段目の鋼矢板5と5’を互い違いの配置に接合
し、その下端を前記基礎梁7の溝7aの内に挿入するこ
とによって、一段目の鋼矢板5及び5’を外壁材として
立てる(図3を参照)。したがって、一段目の鋼矢板5
及び5’の下端位置及び傾斜角度を容易に定めることが
でき、やはり鋼矢板5及び5’の定形化が容易で構築作
業が簡易である。そのため、作業効率の向上が可能でコ
ストの削減に寄与する。
Using the column material 9 as a guide, the first-stage steel sheet piles 5 and 5 ′ processed into the above-described module length and approximately モ ジ ュ ー ル module length are joined in an alternate arrangement outside the lower end thereof. Is inserted into the groove 7a of the foundation beam 7, whereby the first-stage steel sheet piles 5 and 5 'are erected as outer wall materials (see FIG. 3). Therefore, the first sheet pile 5
, 5 ′ can be easily determined, and the steel sheet piles 5 and 5 ′ can be easily formed into a standard shape and the construction work can be simplified. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0024】次に、図3及び図6に示すように、前記一
段目の鋼矢板5及び5’のうち背が低い鋼矢板5’の内
側面の中部、及び背が高い鋼矢板5の内側面の下部に共
通の腹起こし材11を配置し、内側面が腹起こし材11
と当たっている鋼矢板(本実施形態では背が低い鋼矢板
5’)と腹起こし材11とをボルト13で接合する。そ
の場合、腹起こし材11へ当たらない背が高い鋼矢板5
の内側面と腹起こし材11とは柱材9を挟み込み、鋼矢
板5…がコンクリート6を打設した際のコンクリート圧
により外側へ倒れない構造としている。
Next, as shown in FIGS. 3 and 6, the middle part of the inner surface of the short steel sheet pile 5 'and the inside of the tall steel sheet pile 5 among the first-stage steel sheet piles 5 and 5'. A common bulging material 11 is arranged at the lower part of the side surface, and
(In this embodiment, a short steel sheet pile 5 'in this embodiment) and the belly material 11 are joined by bolts 13. In that case, a tall steel sheet pile 5 that does not hit the belly material 11
Are sandwiched between the inner surface and the belly material 11 so that the steel sheet piles 5 do not fall outward due to the concrete pressure when the concrete 6 is cast.

【0025】その後、前記背が低い鋼矢板5’の上端部
近傍まで第一段目のコンクリート6を打設し、打設した
コンクリート6の上部を振動ローラ−等で転圧し、強度
を発現するまで養生する。したがって、前記第一段目の
コンクリート6を打設する工程では、基礎梁7、固定部
材8、柱材9、サポート材10、腹起こし材11のそれ
ぞれが、鋼矢板5及び5’を支持する働きをなし、更に
鋼矢板5及び5’自身の剛性、及び隣り合う鋼矢板5、
5’相互の接合力等が、コンクリート6を打設した際の
コンクリート圧に耐える強度を発揮する。したがって、
鋼矢板5…の変形(孕み)及び隣り合う鋼矢板5、5間
に隙間が生じることがなく打設コンクリート6が漏れ出
すことがない。なお、前記コンクリート6の骨材にはク
ラッシャーランを用いる(請求項8記載の発明)。前記
クラッシャーランは、道路の路盤材などに使用する道路
用砕石である。具体的には、破砕機で破砕した後、ふる
いにかけずにそのまま使用する砕石であって、全国どこ
でも安価に入手できる。そのため、材料調達が容易に行
うことができコストの削減と作業効率の向上が可能であ
る。
After that, the first-stage concrete 6 is poured into the vicinity of the upper end of the short steel sheet pile 5 ', and the upper part of the placed concrete 6 is rolled by a vibrating roller or the like to develop strength. Cure until. Accordingly, in the step of placing the first-stage concrete 6, the foundation beam 7, the fixing member 8, the column member 9, the support member 10, and the belly material 11 support the steel sheet piles 5 and 5 ′. Work, and furthermore, the rigidity of the steel sheet piles 5 and 5 'itself, and the adjacent steel sheet piles 5,
The 5 'mutual bonding strength and the like exhibit strength to withstand the concrete pressure when the concrete 6 is cast. Therefore,
There is no deformation (confusion) of the steel sheet piles 5 and no gap between the adjacent steel sheet piles 5, and the poured concrete 6 does not leak. A crusher run is used as the aggregate of the concrete 6 (the invention according to claim 8). The crusher run is crushed stone for roads used for roadbed materials of roads and the like. Specifically, it is crushed stone that is used without being sieved after being crushed by a crusher, and can be obtained at low cost anywhere in the country. Therefore, material procurement can be easily performed, and cost reduction and work efficiency can be improved.

【0026】つづいて、図4に示すように、前記一段目
の背が低い鋼矢板5’の上方へ二段目のモジュール長さ
の鋼矢板5を接合して立て、前記鋼矢板5の中部に二段
目の腹起こし材11をボルト13で接合する。その場
合、一段目の背が高い鋼矢板5の内側面と前記腹起こし
材11とで柱材9を挟み込む。その後、前記一段目の背
が高い鋼矢板5の上端部近傍まで第二段目のコンクリー
ト6を打設し、打設したコンクリート6の上部を振動ロ
ーラー等で転圧する。このコンクリート6が強度を発現
する以前に、二段目の腹起こし材11に予めあけておい
た孔へアンカー材14のフック部を挿入し、当該アンカ
ー材14は前記コンクリート6の天端へ置く(又は寝か
せる)形で略水平方向に取り付ける。そして、前記第二
段目のコンクリート6が強度を発現するまで養生する。
Next, as shown in FIG. 4, a second-stage module-length steel sheet pile 5 is joined and erected above the first-stage short steel sheet pile 5 ', and the middle part of the steel sheet pile 5 is erected. Then, the second-stage belly-raising material 11 is joined with bolts 13. In this case, the column member 9 is sandwiched between the inner surface of the first-stage tall steel sheet pile 5 and the belly-raising member 11. Thereafter, the second-stage concrete 6 is poured into the vicinity of the upper end of the first-stage tall steel sheet pile 5, and the upper portion of the placed concrete 6 is rolled by a vibrating roller or the like. Before the concrete 6 develops its strength, the hook portion of the anchor material 14 is inserted into a hole previously drilled in the second-stage belly-raising material 11, and the anchor material 14 is placed on the top end of the concrete 6. (Or lay it down) in a substantially horizontal direction. Then, the concrete is cured until the second-stage concrete 6 develops strength.

【0027】前記第二段目のコンクリート6を打設する
工程では、既に第一段目のコンクリート6が強度を発現
し一体化された各部材の強度と剛性、及び二段目の鋼矢
板5自身の剛性、並びに隣り合う鋼矢板5、5相互の接
合力等がコンクリート6の打設圧に十分に耐え得る強度
を発揮しており、何の問題もない。
In the step of placing the second-stage concrete 6, the strength and rigidity of each member in which the first-stage concrete 6 has already developed and integrated, and the second-stage steel sheet pile 5 The rigidity of the steel sheet itself and the joining force between the adjacent steel sheet piles 5, 5 and the like exhibit strength enough to withstand the driving pressure of the concrete 6, and there is no problem.

【0028】以下、鋼矢板5を接合して立て、腹起こし
材11を取付け、コンクリート6を打設して転圧し、腹
起こし材11にアンカー材14を取付け、打設したコン
クリート6が強度を発現するまで養生する工程を、擁壁
の高さまで繰り返す。
In the following, the steel sheet piles 5 are joined and erected, the uprights 11 are attached, the concrete 6 is cast and rolled, and the anchors 14 are attached to the uprights 11 and the cast concrete 6 increases the strength. The process of curing until expression occurs is repeated up to the height of the retaining wall.

【0029】従って、上記構築工法は外壁材としてモジ
ュール長さに加工して、ジョイント部を有する鋼矢板5
を用い、該鋼矢板5を千鳥状配置に形成するので、運搬
及び鋼矢板5…の定型化を容易に行うことができ構築作
業が簡易である。そのため、作業効率の向上が可能でコ
ストの削減に寄与する。
Therefore, in the above construction method, a steel sheet pile 5 having a joint portion is processed into a module length as an outer wall material.
, And the steel sheet piles 5 are formed in a staggered arrangement, so that the transportation and the standardization of the steel sheet piles 5 can be easily performed, and the construction work is simple. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0030】また、柱材9をガイドにしてその外側に、
鋼矢板5を配置して接合し、その下端を前記基礎梁7の
溝7aの内へ挿入することによって、前記鋼矢板5を外
壁材として立てるので、鋼矢板5の下端位置及び傾斜角
度等を容易に定めることができ、やはり鋼矢板5の定形
化が容易で構築作業が簡易である。そのため、作業効率
の向上が可能でコストの削減に寄与する。
Further, using the column material 9 as a guide,
The steel sheet pile 5 is placed and joined, and the lower end thereof is inserted into the groove 7a of the foundation beam 7, thereby setting the steel sheet pile 5 as an outer wall material. The steel sheet pile 5 can be easily determined, and the construction work is also simple. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0031】更に、コンクリート6の打設圧に対して、
前工程におけるコンクリート6の打設により既に一体化
された各部材の強度と剛性、鋼矢板5自身の剛性、並び
に隣り合う鋼矢板5、5相互の接合力等が十分耐え得る
強度を発揮するので、鋼矢板5、即ち外壁材4が変形
(孕み)及び隣り合う鋼矢板5、5間に隙間が生じるこ
とがなく、打設コンクリートが漏れ出すおそれがない。
Further, with respect to the casting pressure of the concrete 6,
Since the strength and rigidity of the members already integrated by the casting of the concrete 6 in the previous process, the rigidity of the steel sheet pile 5 itself, and the joint strength between the adjacent steel sheet piles 5 and 5, etc., are sufficiently high enough to exhibit strength. In addition, the steel sheet pile 5, that is, the outer wall material 4 is not deformed (impregnated), no gap is generated between the adjacent steel sheet piles 5, 5, and there is no possibility that the poured concrete leaks.

【0032】しかも前工程で打設され強度を発現したコ
ンクリート6を足場代わりにして、次工程の鋼矢板5の
組立てその他を行うことができ、外壁材4の内外に別途
足場を構築する必要がないから、構築作業の容易化に寄
与する。
Moreover, the concrete 6 that has been cast in the previous process and has developed strength can be used as a scaffold, and assembling of the steel sheet pile 5 in the next process can be performed, and it is necessary to construct a separate scaffold inside and outside the outer wall material 4. No, it contributes to ease of construction work.

【0033】最後に、図7に拡大して示したように、前
記所定の高さまで達した鋼矢板5の頂部に堤冠材15を
挿入し土留め擁壁を完成する(請求項6記載の発明)。
Finally, as shown in an enlarged view in FIG. 7, the embankment material 15 is inserted into the top of the steel sheet pile 5 reaching the predetermined height to complete the earth retaining wall. invention).

【0034】上述のようにして構築される土留め擁壁
は、モジュール長さの鋼矢板に限らないで、請求項5記
載の発明に係る構築工法によっても、全く同様に構築さ
れる。即ち、外壁材の下端位置を定める基礎梁を基礎地
盤上に上向きの溝形断面材として配置し、該基礎梁は基
礎地盤に固定された固定部材と接合し、この基礎梁の溝
内へ外壁材の下端を挿入する。外壁材は、サポート材で
支持された柱材で支保させる。前記外壁材に水平方向の
腹起こし材を接合し、その腹起こし材にアンカー材を取
り付ける。そして、前記外壁材の内側へ、外壁材が自立
する高さまでコンクリートを打設し、打設したコンクリ
ートの上部を振動ローラー等で転圧し、前記腹起こし材
にアンカー材を取り付けて、打設したコンクリートが強
度を発現するまで養生を行う。
The retaining wall constructed as described above is not limited to a steel sheet pile having a module length, but can be constructed in exactly the same manner by the construction method according to the fifth aspect of the present invention. That is, a foundation beam that determines the lower end position of the outer wall material is disposed on the foundation ground as an upward groove-shaped cross-section member, and the foundation beam is joined to a fixing member fixed to the foundation ground, and the outer wall is inserted into the groove of the foundation beam. Insert the lower end of the material. The outer wall material is supported by a column material supported by a support material. A horizontal flared material is joined to the outer wall material, and an anchor material is attached to the flared material. Then, concrete was poured into the outer wall material to a height at which the outer wall material became self-supporting, the upper part of the cast concrete was rolled with a vibrating roller or the like, and an anchor material was attached to the belly-raising material and poured. Curing is performed until concrete develops strength.

【0035】その後、外壁材の組み立てと、コンクリー
トの打設と転圧、及びアンカー材の取付け、並びに打設
したコンクリートの養生を行う工程を擁壁の高さまで繰
り返すと、請求項1記載の発明に係るような土留め擁壁
を構築できる。なお、前記擁壁のコンクリートも、クラ
ッシャーランが用いられる(請求項4記載の発明)。
Thereafter, the steps of assembling the outer wall material, placing and compacting concrete, attaching the anchor material, and curing the placed concrete are repeated up to the height of the retaining wall. An earth retaining wall as described in (1) can be constructed. A crusher run is also used for the concrete of the retaining wall (the invention according to claim 4).

【0036】なお、上記実施形態では、外壁材4として
鋼矢板5を用いているが、軽量鋼矢板及びライナープレ
ートでも同様に実施できる(請求項3記載の発明)。
In the above embodiment, the steel sheet pile 5 is used as the outer wall material 4. However, the present invention can be similarly applied to a lightweight steel sheet pile and a liner plate.

【0037】また、上記実施形態では、基礎地盤3上に
基礎梁7を配置しているが、この限りではない。即ち、
前記基礎梁7を基礎地盤3にアンカー等の手段により固
定しても良い。
In the above embodiment, the foundation beams 7 are arranged on the foundation ground 3, but this is not a limitation. That is,
The foundation beam 7 may be fixed to the foundation ground 3 by means such as an anchor.

【0038】[0038]

【本発明の奏する効果】請求項1〜8に記載した発明に
係る土留め擁壁及びその構築工法は、外壁材としてジョ
イント部を有する鋼矢板を用いるので、運搬及び鋼矢板
の定型化を容易に行うことができ、構築作業が簡易であ
る。そのため、作業効率の向上が可能でコストの削減に
寄与する。
In the earth retaining wall and the construction method according to the first to eighth aspects of the present invention, since a steel sheet pile having a joint portion is used as an outer wall material, transportation and standardization of the steel sheet pile are easy. And the construction work is simple. Therefore, work efficiency can be improved, which contributes to cost reduction.

【0039】また、柱材をガイドにしてその外側に、鋼
矢板を配置して接合し、その下端を基礎梁の溝内へ挿入
することによって、前記鋼矢板を外壁材として立てるの
で、外壁材(特に一段目の鋼矢板)の下端位置及び傾斜
角度等を容易に定めることができ、やはり外壁材の定形
化を容易に行うことができ作業効率の向上が可能でコス
トの削減に寄与する。
Further, a steel sheet pile is arranged and joined to the outside thereof by using the column material as a guide, and the lower end thereof is inserted into the groove of the foundation beam, so that the steel sheet pile is set as an outer wall material. The lower end position and the inclination angle of the (particularly the first steel sheet pile) can be easily determined, so that the outer wall material can be easily formed into a standard shape, so that the work efficiency can be improved and the cost can be reduced.

【0040】更に、コンクリートの打設圧に対して、前
工程におけるコンクリートの打設により既に一体化され
た各部材の強度と剛性、鋼矢板自身の剛性、並びに隣り
合う鋼矢板相互の接合力等が十分耐え得る強度を発揮す
るので、鋼矢板、即ち外壁材が変形(孕み)及び隣り合
う鋼矢板の間に隙間が生じることがなく、打設コンクリ
ートが漏れ出すおそれがない。
Furthermore, the strength and rigidity of each member already integrated by the concrete casting in the previous process, the rigidity of the steel sheet pile itself, and the joining force between the adjacent steel sheet piles with respect to the concrete casting pressure. The steel sheet pile, that is, the outer wall material, is not deformed (impregnated) and a gap is not formed between adjacent steel sheet piles, and there is no possibility that the poured concrete leaks.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明に係る土留め擁壁を概略的に示した斜視
図である。
FIG. 1 is a perspective view schematically showing an earth retaining wall according to the present invention.

【図2】外壁材の構造を示した斜視図である。FIG. 2 is a perspective view showing a structure of an outer wall material.

【図3】一段目の鋼矢板の接合、腹起こし材の取付け、
コンクリートの打設と転圧、及びアンカー材を取り付け
た工程を示した正面図である。
FIG. 3 shows the joining of the first-stage steel sheet pile, the attachment of the belly-raising material,
It is the front view which showed the process of placing and compacting concrete, and attaching an anchor material.

【図4】二段目の鋼矢板の接合、腹起こし材の取付け、
コンクリートの打設と転圧、及びアンカー材を取り付け
た工程を示した正面図である。
[Fig. 4] Bonding of second-stage steel sheet pile, installation of belly-raising material,
It is the front view which showed the process of placing and compacting concrete, and attaching an anchor material.

【図5】図4のA−A矢視断面図である。FIG. 5 is a sectional view taken along the line AA of FIG. 4;

【図6】図4のB−B矢視断面図である。FIG. 6 is a sectional view taken along the line BB of FIG. 4;

【図7】外壁材の頂部を示した拡大図である。FIG. 7 is an enlarged view showing the top of the outer wall material.

【図8】従来の構築工法により構築された土留め擁壁を
示した断面図である。
FIG. 8 is a cross-sectional view showing an earth retaining wall constructed by a conventional construction method.

【符号の説明】[Explanation of symbols]

1 地山 2 法面 3 基礎地盤 4 外壁材 5 鋼矢板 6 コンクリート 7 基礎梁 7a 溝 8 固定部材 9 柱材 10 サポート材 11 腹起こし材 12 接合プレート 13 ボルト 14 アンカー材 15 堤冠材 DESCRIPTION OF SYMBOLS 1 Ground 2 Slope 3 Foundation ground 4 Exterior wall material 5 Steel sheet pile 6 Concrete 7 Foundation beam 7a Groove 8 Fixing member 9 Column material 10 Support material 11 Belly material 12 Joint plate 13 Bolt 14 Anchor material 15 Embankment material

───────────────────────────────────────────────────── フロントページの続き (72)発明者 堀 謙吾 神奈川県川崎市川崎区出来野3−2−405 (72)発明者 秋山 祥克 埼玉県川越市脇田町33−1 株式会社イン バックス内 (72)発明者 半田 博幸 埼玉県東松山市松風台3−28 Fターム(参考) 2D044 CA10 2D048 AA82  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Kengo Hori 3-2-405 Takino, Kawasaki-ku, Kawasaki City, Kanagawa Prefecture ) Inventor Hiroyuki Handa 3-28 Matsukazedai, Higashimatsuyama-shi, Saitama F-term (reference) 2D044 CA10 2D048 AA82

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】地山の法面の土石等が崩落するのを防ぐた
めに構築される土留め擁壁において、 土留め擁壁の外壁材の下端位置を定める基礎梁が基礎地
盤上に上向きの溝形断面材として配置され、該基礎梁は
基礎地盤に固定された固定部材と接合されており、基礎
梁の溝内へ外壁材の下端が挿入されていること、 前記外壁材は内側からサポート材で支持された柱材で支
保されており、前記外壁材に水平方向の腹起こし材が接
合され、その腹起こし材にアンカー材が取り付けられて
いること、 前記外壁材と法面との間へコンクリートが打設されてい
ることを特徴とする、土留め擁壁。
In a retaining wall constructed to prevent the debris and the like on the slope of the ground from collapsing, a foundation beam for determining a lower end position of an outer wall material of the retaining wall faces upward on the foundation ground. It is arranged as a channel-shaped section material, the foundation beam is joined to a fixing member fixed to the foundation ground, the lower end of the outer wall material is inserted into the groove of the foundation beam, the outer wall material is supported from the inside Supported by a column material supported by a material, a horizontal flared material is joined to the outer wall material, and an anchor material is attached to the flared material, between the outer wall material and the slope. An earth retaining wall characterized by concrete being poured into it.
【請求項2】前記外壁材は、鋼矢板、若しくは軽量鋼矢
板又はライナープレートのいずれかで構成されているこ
とを特徴とする、請求項1に記載した土留め擁壁。
2. The earth retaining wall according to claim 1, wherein the outer wall material is made of a steel sheet pile, a lightweight steel sheet pile or a liner plate.
【請求項3】前記鋼矢板、若しくは軽量鋼矢板又はライ
ナープレートは、千鳥状配置に組み立てられていること
を特徴とする、請求項2に記載した土留め擁壁。
3. The retaining wall according to claim 2, wherein the steel sheet pile, the lightweight steel sheet pile or the liner plate is assembled in a staggered arrangement.
【請求項4】前記コンクリートの骨材がクラッシャーラ
ンであることを特徴とする、請求項1に記載した土留め
擁壁。
4. The retaining wall according to claim 1, wherein the concrete aggregate is a crusher run.
【請求項5】地山の法面の土石等が崩落するのを防ぐた
めに構築される土留め擁壁の構築工法において、 土留め擁壁の外壁材の下端位置を定める基礎梁を基礎地
盤上に上向きの溝形断面材として配置し、該基礎梁は基
礎地盤に固定された固定部材と接合し、この基 礎梁の溝内へ外壁材の下端を挿入する段階と、 前記外壁材を、内側からサポート材で支持された柱材で
支保し、前記外壁材に水平方向の腹起こし材を接合する
段階と、 前記外壁材と法面との間へ、同外壁材が自立する高さま
でコンクリートを打設し、打設したコンクリートの上部
を振動ローラー等で転圧し、前記腹起こし材にアンカー
材を取り付けて、打設したコンクリートが強度を発現す
るまで養生する段階と、 前記外壁材の組み立てと、コンクリートの打設と転圧、
及びアンカー材の取付け、並びにコンクリートの養生を
行う工程を、当該土木構造物の高さまで繰り返す段階と
から成ることを特徴とする、土留め擁壁の構築工法。
5. A method of constructing a retaining wall for preventing earth and stones on a slope of a ground from collapsing, wherein a foundation beam for determining a lower end position of an outer wall material of the retaining wall is provided on the foundation ground. , The foundation beam is joined to a fixing member fixed to the foundation ground, and the lower end of the exterior wall material is inserted into the groove of the foundation beam; and Supporting with a pillar material supported by a support material from the inside, and joining a horizontal flared material to the outer wall material; between the outer wall material and the slope, concrete to a height at which the outer wall material is free standing And rolling the upper part of the cast concrete with a vibrating roller or the like, attaching an anchor material to the belly-raising material, and curing the cast concrete until it develops strength, and assembling the outer wall material And concrete placement and compaction,
And repeating the steps of attaching the anchor material and curing the concrete up to the height of the civil engineering structure.
【請求項6】前記外壁材の頂部には、堤冠材を設けるこ
とを特徴とする、請求項5に記載した土留め擁壁の構築
工法。
6. The method of constructing an earth retaining wall according to claim 5, wherein an embankment material is provided on a top portion of the outer wall material.
【請求項7】地山の法面の土砂等が崩落するのを防ぐた
めに構築される土留め擁壁の構築工法において、 土留め擁壁の外壁材を鋼矢板で構成し、その一段目の鋼
矢板の下端位置を定める基礎梁を基礎地盤上に上向きの
溝形断面材として配置し、該基礎梁は基礎地盤に固定さ
れた固定部材と接合すること、 前記基礎梁の上に、長手方向に間隔を開けて、柱材を一
定の内向き傾斜角度で立て、各柱材は内側からサポート
材により支持させる段階と、 前記柱材をガイドにしてその外側に、モジュール長さ及
び略1/2モジュール長さに加工した一段目の鋼矢板を
それぞれ互い違いの配置に接合し、それぞれの下端を前
記基礎梁の溝内へ挿入することによって各鋼矢板の継目
を上下方向に段違いの千鳥状配置に形成し、背が低い鋼
矢板の基礎梁近傍に腹起こし材をボルト接合し、前記背
が低い鋼矢板の上端部近傍まで第一段目のコンクリート
を打設し、打設したコンクリートの上部を振動ローラー
等で転圧し、強度が発現するまで養生する段階と、 前記一段目の背が低い鋼矢板の上方に二段目のモジュー
ル長さの鋼矢板を接合して立て、前記鋼矢板の中部に二
段目の腹起こし材をボルト接合し、前記一段目の背が高
い鋼矢板の上端部近傍まで第二段目のコンクリートを打
設し、打設したコンクリートの上部を振動ローラー等で
転圧し、前記二段目の腹起こし材にアンカー材を水平方
向に取り付けて前記打設コンクリートの天端へ置き、同
コンクリートが強度を発現するまで養生する段階と、 以下、モジュール長さの鋼矢板を接合して立て、腹起こ
し材を取付け、コンクリートを打設して転圧し、アンカ
ー材を取付け、打設コンクリートが強度を発現するまで
養生する工程を当該土留め擁壁の高さまで繰り返す段階
とから成ることを特徴とする、土留め擁壁の構築工法。
7. A method of constructing an earth retaining wall to prevent earth and sand on a slope of a ground from collapsing, wherein an outer wall material of the earth retaining wall is made of steel sheet pile. A foundation beam that defines the lower end position of the steel sheet pile is arranged on the foundation ground as an upward channel-shaped cross-section member, and the foundation beam is joined to a fixing member fixed to the foundation ground. At a distance, the pillars are set up at a constant inward inclination angle, each pillar is supported by a support material from the inside, and the module length and approximately 1 / The first-stage steel sheet pile processed into a length of 2 modules is joined in a staggered arrangement, and the lower end of each is inserted into the groove of the foundation beam, so that the seams of the steel sheet piles are staggered in the vertical direction. Near the foundation beam of a short steel sheet pile Bolt-up material is bolted, the first-stage concrete is cast near the upper end of the short steel sheet pile, and the upper part of the cast concrete is rolled with a vibrating roller or the like, and cured until the strength is developed. And the step of joining a second-stage module-length steel sheet pile above the first-stage short steel sheet pile, standing up, and bolting a second-stage flared material to the middle of the steel sheet pile, The second-stage concrete is poured into the vicinity of the upper end of the first-stage tall steel sheet pile, and the upper portion of the poured concrete is rolled with a vibrating roller or the like, and an anchor material is attached to the second-stage belly-raising material. Attaching the steel sheet pile horizontally and placing it on the top of the cast concrete, curing the concrete until the concrete develops its strength. Cast and roll Repeating the steps of pressing, attaching anchor material, and curing the cast concrete until the concrete develops its strength up to the height of the retaining wall.
【請求項8】前記コンクリートの骨材がクラッシャーラ
ンであることを特徴とする、請求項5〜7のいずれか一
に記載した土留め擁壁の構築工法。
8. The method according to claim 5, wherein the concrete aggregate is a crusher run.
JP2001041538A 2001-02-19 2001-02-19 Earth retaining wall and its construction method Expired - Fee Related JP4647113B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001041538A JP4647113B2 (en) 2001-02-19 2001-02-19 Earth retaining wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001041538A JP4647113B2 (en) 2001-02-19 2001-02-19 Earth retaining wall and its construction method

Publications (2)

Publication Number Publication Date
JP2002242210A true JP2002242210A (en) 2002-08-28
JP4647113B2 JP4647113B2 (en) 2011-03-09

Family

ID=18903970

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001041538A Expired - Fee Related JP4647113B2 (en) 2001-02-19 2001-02-19 Earth retaining wall and its construction method

Country Status (1)

Country Link
JP (1) JP4647113B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004027645A (en) * 2002-06-26 2004-01-29 Kyosei Kiko Kk Steel formwork
JP2004176314A (en) * 2002-11-25 2004-06-24 Nippon Steel Metal Prod Co Ltd Civil-engineered structure equipped with planting sections, and method of constructing the same
JP2004332304A (en) * 2003-05-02 2004-11-25 Toyo Shoko:Kk Fixing method for steel sheet pile in protection fence, and fixing tool of steel sheet pile
JP2017031733A (en) * 2015-08-05 2017-02-09 アキレス株式会社 Lightweight banking structure
CN111411638A (en) * 2020-04-29 2020-07-14 石家庄铁道大学 Steel sheet pile cofferdam and construction method thereof
JP2020153088A (en) * 2019-03-18 2020-09-24 Jfe建材株式会社 Training dike

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104727325B (en) * 2015-02-12 2016-08-17 宁波高新区围海工程技术开发有限公司 A kind of method of construction of polder sea wall

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53143404A (en) * 1977-05-20 1978-12-13 Toyo Shigyo Kk Method of producing endless relief plate
JPS62137311A (en) * 1985-12-09 1987-06-20 Kyosei Gijutsu Kaihatsu Kiko Kk Construction of steel sheet pile segment double-wall structure
JPH051425A (en) * 1991-06-25 1993-01-08 Taisei Corp Construction method for structure on slope
JPH05202527A (en) * 1992-01-29 1993-08-10 Fujita Corp Method for constructing structure using oblique permanent anchor
JPH108443A (en) * 1996-06-20 1998-01-13 Sato Kogyo Co Ltd Form structure for structure and construction method for structure
JPH11156371A (en) * 1997-11-27 1999-06-15 Yorishige Oomine Active material and its production
JPH11303107A (en) * 1998-04-20 1999-11-02 Horiguchi Keiko Retaing wall building construction
JP4183389B2 (en) * 2001-01-19 2008-11-19 日鐵住金建材株式会社 Construction method for civil engineering structures using steel sheet piles

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS53143404A (en) * 1977-05-20 1978-12-13 Toyo Shigyo Kk Method of producing endless relief plate
JPS62137311A (en) * 1985-12-09 1987-06-20 Kyosei Gijutsu Kaihatsu Kiko Kk Construction of steel sheet pile segment double-wall structure
JPH051425A (en) * 1991-06-25 1993-01-08 Taisei Corp Construction method for structure on slope
JPH05202527A (en) * 1992-01-29 1993-08-10 Fujita Corp Method for constructing structure using oblique permanent anchor
JPH108443A (en) * 1996-06-20 1998-01-13 Sato Kogyo Co Ltd Form structure for structure and construction method for structure
JPH11156371A (en) * 1997-11-27 1999-06-15 Yorishige Oomine Active material and its production
JPH11303107A (en) * 1998-04-20 1999-11-02 Horiguchi Keiko Retaing wall building construction
JP4183389B2 (en) * 2001-01-19 2008-11-19 日鐵住金建材株式会社 Construction method for civil engineering structures using steel sheet piles

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004027645A (en) * 2002-06-26 2004-01-29 Kyosei Kiko Kk Steel formwork
JP2004176314A (en) * 2002-11-25 2004-06-24 Nippon Steel Metal Prod Co Ltd Civil-engineered structure equipped with planting sections, and method of constructing the same
JP2004332304A (en) * 2003-05-02 2004-11-25 Toyo Shoko:Kk Fixing method for steel sheet pile in protection fence, and fixing tool of steel sheet pile
JP2017031733A (en) * 2015-08-05 2017-02-09 アキレス株式会社 Lightweight banking structure
JP2020153088A (en) * 2019-03-18 2020-09-24 Jfe建材株式会社 Training dike
JP7214521B2 (en) 2019-03-18 2023-01-30 Jfe建材株式会社 Construction method of training dike for permanent measures and training dike for permanent measures
CN111411638A (en) * 2020-04-29 2020-07-14 石家庄铁道大学 Steel sheet pile cofferdam and construction method thereof
CN111411638B (en) * 2020-04-29 2024-04-26 石家庄铁道大学 Steel sheet pile cofferdam and construction method thereof

Also Published As

Publication number Publication date
JP4647113B2 (en) 2011-03-09

Similar Documents

Publication Publication Date Title
KR20090094971A (en) Under ground top-down method
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
JP2002242210A (en) Earth retaining wall and construction method therefor
KR100605514B1 (en) Bracket support type downward construction system and construction method using the same
KR101006411B1 (en) System and method for underground downward construction using concrete filled tube
JP4421124B2 (en) Civil engineering structures such as sabo dams, etc. using long materials such as steel sheet piles and thinned wood, and construction methods
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP3958319B2 (en) Prestressed temporary construction method
JP3760304B2 (en) Building foundation construction method
JPH11172710A (en) Method for constructing underground part of steel encased reinforced concrete building
JP4183389B2 (en) Construction method for civil engineering structures using steel sheet piles
JP5278849B2 (en) Underground system temporary frame
JP2002021096A (en) Building and constructing method therefor
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
JP3133598B2 (en) Construction method of small and medium-sized building with basement floor
JPH1143952A (en) Construction method for pile foundation
JP2769937B2 (en) Steel tube concrete column in underground reverse driving method
KR102490025B1 (en) Floor frame support system for flat slab in top-down method
JP2004176314A (en) Civil-engineered structure equipped with planting sections, and method of constructing the same
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JP3061934B2 (en) Retaining wall construction method
JPH116162A (en) Construction method for reinforced concrete underground external wall
JPH11193529A (en) Earth retaining method for underground work, and building method for underground structure
KR200322945Y1 (en) Device of Innovative Prestressed Scaffolding System for Improving Workability

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060929

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090128

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090203

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090406

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090804

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090910

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100831

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20100906

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100928

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20101001

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20101109

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20101208

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131217

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4647113

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees