JP2001220906A - Building structure and its frame structure - Google Patents

Building structure and its frame structure

Info

Publication number
JP2001220906A
JP2001220906A JP2000029889A JP2000029889A JP2001220906A JP 2001220906 A JP2001220906 A JP 2001220906A JP 2000029889 A JP2000029889 A JP 2000029889A JP 2000029889 A JP2000029889 A JP 2000029889A JP 2001220906 A JP2001220906 A JP 2001220906A
Authority
JP
Japan
Prior art keywords
floor
equipment
space
inspection
building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2000029889A
Other languages
Japanese (ja)
Inventor
Shigeru Nakamura
茂 中村
Shinjiro Momo
真二郎 百々
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2000029889A priority Critical patent/JP2001220906A/en
Publication of JP2001220906A publication Critical patent/JP2001220906A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a building structure and its frame structure in consideration of an overall building so as to actuate various facilities of plumbing, etc., to support a whole say operating state without influencing upon operation and to freely perform maintenance and inspection without stopping operation. SOLUTION: A building structure 1 constitutes facility spaces 10, 10' constructed of truss frames 31-, 41- arranging an operation supporting facility on upper parts of operating floors 3, 4, makes a piping space of plumbing, etc., of an underfloor pit 2 excluding a foundation by directly connecting a pile 6 and a column 5 supporting the operating floors 3, 4 and the facility spaces 10, 10' to each other and arranges inspection footpaths 15, 15' in the facility space.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、建築構造物とその
架構構造に関し、特に、稼働階における一切の保守点検
を排除することで終日稼働を可能にした建築構造物とそ
の架構構造に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a building structure and a frame structure thereof, and more particularly, to a building structure and a frame structure thereof which can be operated all day long by eliminating any maintenance and inspection on an operating floor.

【0002】[0002]

【従来の技術】昨今、産業界におけるグローバル化の影
響や社会環境の変化で、24時間開店のコンビニエンス
ストアのように日夜の区別がない状態での日常生活が一
般化しようとしている。このような生活環境の変化は、
その需要が巨大化して行くにつれてそれぞれの店舗に消
費物質を供給する生産体制においても稼働状態の変化が
求められている。特に、食料品のように恒常的な需要が
見込まれていながら日持ちのしない生活必需品に関して
は、末端店舗に対して需要に見合った数量の供給が要求
されており、ご飯、惣菜等の製造部門においては年間を
通しての終日稼働を必須にしてきている。終日稼働の要
求は、保守点検のための稼働停止もあってはならないも
のであり、要求に対応するための体制作りのためには製
造工場等での諸設備を含めた稼働体制の再構築が必要に
なっている。
2. Description of the Related Art In recent years, due to the effects of globalization and changes in the social environment in the industrial world, daily life in which there is no distinction between day and night, as in convenience stores that are open 24 hours a day, is about to generalize. Such changes in the living environment
As the demand has become enormous, a change in the operating state is also required in a production system that supplies each store with consumable substances. In particular, with regard to daily necessities that are expected to have constant demand such as foodstuffs but do not last a long time, supply to the end stores is required in a quantity that matches the demand. Has become mandatory throughout the year. An all-day operation request must not cause an operation stop for maintenance and inspection, and in order to create a system to respond to the request, it is necessary to rebuild the operation system, including various facilities at manufacturing plants, etc. Is needed.

【0003】従来においても病院や研究所においては、
長時間の手術や連続してのデータ収集を必要とする研究
等において終日稼働の状態が発生している。このために
病院や研究所においては、これまでも、各居住階の間の
天井懐を拡大させて空調設備、給水給湯、排水等の設
備、配管のみを配置した設備階を付属的に配置して、作
業員が居住者の活動と無関係に入り込んで作業ができる
ようにすることが行われていた。
[0003] Conventionally, in hospitals and laboratories,
All-day operation has occurred in studies requiring long-term surgery or continuous data collection. For this reason, hospitals and research institutes have previously installed equipment floors with only air-conditioning equipment, hot and cold water supply, drainage, etc., and only pipes, by expanding the ceiling between each living floor. Therefore, it has been practiced to allow workers to work independently of residents' activities.

【0004】しかし、上述した産業界の動向は、病院や
研究所のように特殊な部門における特定の状態でなく、
今後の動向として幅広くその対応が迫られている問題で
ある。しかるに、これらの業界需要に対応して製造供給
している建築構造物は、設備区域と稼働区域のように平
面方向に要求される機能の分担を考慮しているだけで、
建物全体を終日稼働を前提に検討を加えて、建物全体を
常に最善の稼働状態に維持できるように、建物における
必要空間の確保とそれを確立するための最適な架構につ
いて考慮されていないのが現在の状況である。
[0004] However, the trends in the industry described above are not specific conditions in special departments such as hospitals and research laboratories,
This is a problem that needs to be addressed widely as a future trend. However, building structures manufactured and supplied in response to these industry demands only consider the sharing of functions required in the horizontal direction, such as equipment areas and operation areas,
Considering that the entire building is expected to operate all day, the necessary space in the building and the optimal frame for establishing it are not considered so that the entire building can always be kept in the best operation state. This is the current situation.

【0005】[0005]

【発明が解決しようとする課題】本発明は、上記の状況
に鑑みて検討されたものであり、終日の効率的な稼働体
制を第一義として、その稼働状態を支援する給排水等の
諸設備に関しても、稼働に影響を与えることなく作動さ
せると共に、その保守点検においても稼働を停止させる
ことなく随意に実施できるように建物全体を考慮した建
築構造物とその架構構造を提供している。
DISCLOSURE OF THE INVENTION The present invention has been made in view of the above-mentioned circumstances, and has various aspects of facilities such as water supply and drainage for supporting the operating state, with an efficient operating system throughout the day being the primary purpose. The present invention also provides an architectural structure and its frame structure that take into account the entire building so that it can be operated without affecting operation and can be arbitrarily performed without stopping operation in maintenance and inspection.

【0006】[0006]

【課題を解決するための手段】本発明による建築構造物
は、稼働階の上部に稼働支援設備を配置する設備空間を
構成し、稼働階と設備空間を支持する杭と柱を直かに接
合して基礎を排除した床下を給排水等の配管空間とし、
上記設備空間に点検歩廊を配置することを特徴としてお
り、基礎や地中梁を無くして床下に広い空間を確保し
て、ガス、給排水等の導管を効率的に配置し、稼働階の
上部に設けた設備空間の点検歩廊を巡回することで、稼
働階の作業状況に何らの影響を与えることなく、支援設
備等の保守点検を可能にしている。
A building structure according to the present invention constitutes an equipment space in which operation support equipment is arranged above an operating floor, and a pile and a column supporting the operating floor and the equipment space are directly joined. The floor under the floor where the foundation has been removed is used as plumbing space for plumbing, etc.
It is characterized by placing an inspection corridor in the above equipment space, eliminating the foundation and underground beams, securing a wide space under the floor, efficiently locating gas, water supply and drainage pipes, etc. Inspection of the installed equipment space By patroling the corridor, maintenance and inspection of support equipment and the like are enabled without any influence on the working status of the operating floor.

【0007】又、本発明による建築構造物の架構構造
は、杭と柱を直に接続し床をフラットスラブで構築して
床下に形成した配管空間と、柱間の接合をトラス架構で
構築して稼働階の上部に形成した設備空間とで構成して
おり、床下における効率的な配管とその点検を容易に
し、設備空間のダクト配管スペースを広く確保して効率
的な配管と保守点検等を容易にしている。
Further, the frame structure of a building structure according to the present invention is constructed by connecting a pile and a column directly and constructing a floor with a flat slab to form a piping space formed under the floor and a joint between the columns with a truss frame. The equipment space formed above the working floor facilitates efficient piping and inspection under the floor, and secures a wide duct space in the equipment space for efficient piping and maintenance and inspection. Easy going.

【0008】[0008]

【発明の実施の形態】本発明による建築構造物は、稼働
階の上部に稼働支援設備を配置する設備空間を構成し、
稼働階と設備空間を支持する杭と柱を直かに接合して基
礎を排除した床下を給排水等の配管空間とし、上記設備
空間に点検歩廊を配置している。以下に、本発明の実施
の形態を図面に基づいて説明する。
BEST MODE FOR CARRYING OUT THE INVENTION A building structure according to the present invention constitutes an equipment space in which operation support equipment is arranged above an operation floor,
Piles and columns that support the working floor and the equipment space are directly connected to each other, and the underfloor with the foundation removed is the piping space for water supply and drainage, and the inspection corridor is located in the equipment space. Hereinafter, embodiments of the present invention will be described with reference to the drawings.

【0009】図1は、本発明による建築構造物の斜視断
面図である。惣菜工場1は、床下ピット2、一階の惣菜
を箱詰めして待機する搬出階3及び三階の惣菜を作る製
造階4を主体構造として構成されている。後で詳述する
ように、本発明による基礎構造では、柱5を基礎や地中
梁等を介さずに杭6に直接接合しているので、床下ピッ
ト2は、地中梁に分断されることなく均一な空間を構成
している。これによって、ガスや給排水の導管を自由に
配置できると共に点検スペースを均一に配分することが
可能になり、保守点検を十分に実施できる。
FIG. 1 is a perspective sectional view of a building structure according to the present invention. The side dish factory 1 is mainly composed of an underfloor pit 2, an unloading floor 3 for packing and waiting the first floor side dishes, and a manufacturing floor 4 for preparing the third floor side dishes. As will be described later in detail, in the foundation structure according to the present invention, since the pillar 5 is directly joined to the pile 6 without the interposition of the foundation or the underground beam, the underfloor pit 2 is divided into the underground beam. It forms a uniform space without any. As a result, the gas and water supply / drainage conduits can be freely arranged, and the inspection space can be evenly distributed, so that maintenance and inspection can be sufficiently performed.

【0010】搬出階3と製造階4とは、24時間フルに
作業することができる終日稼働が原則になっており、作
業に必要のない装置は一切排除されている。さらに、作
業を中断するような障害事態が発生しないように人の出
入りに関しても厳しく管理されており、稼働状態を支援
する設備の保守点検等も必要ないように考慮されてい
る。このために、搬出階3と製造階4との上部には、稼
働支援設備を配置する設備階10、10’が構築されて
おり、それぞれの階に必要な設備機器11、ダクト配管
12、ケーブルラック13等が設置されている。各設備
階には点検歩廊15、15’が必要位置に配置されてお
り、保守点検や設備の更新等に活用されている。
The unloading floor 3 and the manufacturing floor 4 are operated 24 hours a day so that they can be fully operated 24 hours a day, and any equipment unnecessary for the operation is eliminated. In addition, entry and exit of people are strictly controlled so as not to cause a trouble situation that interrupts the work, and it is considered that maintenance and inspection of equipment for supporting the operation state is not required. For this purpose, equipment floors 10 and 10 'for arranging operation support equipment are constructed above the unloading floor 3 and the manufacturing floor 4, and the necessary equipment 11, duct piping 12, cable A rack 13 and the like are provided. Inspection corridors 15 and 15 'are arranged at required positions on each facility floor, and are utilized for maintenance and inspections and for updating facilities.

【0011】以上のように構成することによって、搬出
階3と製造階4では終日稼働が確立することになり、そ
の稼働状態を支援している設備機器等は、搬出階3や製
造階4の生産ラインを止めたり、各階の室内に入ること
なく、天井裏と床下において随意に保守点検することを
可能にしており、機器類の更新も容易にしている。
[0011] With the above configuration, the operation is established all day between the unloading floor 3 and the manufacturing floor 4, and the equipment and the like supporting the operating state are the unloading floor 3 and the manufacturing floor 4. Without stopping the production line or entering the room on each floor, it is possible to perform maintenance and inspection at the ceiling and under the floor at will, and equipment can be easily updated.

【0012】本発明による建築構造物の架構構造は、杭
と柱を直に接続し床をフラットスラブで構築して床下に
配管空間を形成し、稼働階の上部における柱間の接合を
トラス架構で構築して設備空間を形成しており、点検等
に適した広いスペースの確保と上部荷重の低減を図って
いる。図2〜4は本発明による架構構造の実施の形態を
説明するための概要図である。
In the frame structure of a building structure according to the present invention, a pile and a column are directly connected, a floor is constructed with a flat slab, a piping space is formed under the floor, and a joint between the columns at the upper part of the working floor is connected to a truss frame. To secure a large space suitable for inspection, etc., and reduce the upper load. 2 to 4 are schematic views for explaining an embodiment of a frame structure according to the present invention.

【0013】図2は、1階の床と、杭と柱を直結させて
いる状態を詳細に示す断面図である。本実施の形態で
は、建物の周辺に位置する杭16を、大口径のPHC杭
を振動や騒音の少ない押込み工法で施工しており、高い
支持力を確保しながらその杭頭に鋼管柱17を直接結合
している。従って、床下には地中梁が存在しておらず、
外周部にだけ腰壁兼用の基礎梁18を設けている。又、
建物内部の基礎は、図示のようにPHC杭の杭頭部19
を補強する状態の鉄筋コンクリートで構成しており、そ
の上に構築される床20はフラットスラブであるから、
床下ピット2は突出部分のない広い空間として形成する
ことができる。
FIG. 2 is a sectional view showing in detail a state in which the floor of the first floor, the pile and the column are directly connected. In the present embodiment, the pile 16 located in the periphery of the building is constructed by using a large-diameter PHC pile by the indentation method with less vibration and noise, and the steel pipe column 17 is mounted on the pile head while securing a high supporting force. Directly coupled. Therefore, there is no underground beam under the floor,
A foundation beam 18 also serving as a waist wall is provided only on the outer peripheral portion. or,
The foundation inside the building is a PHC pile head 19 as shown in the figure.
Is made of reinforced concrete in a state of reinforcing, and the floor 20 built thereon is a flat slab,
The underfloor pit 2 can be formed as a wide space without any protruding portion.

【0014】以上のように、基礎の架構を杭に柱を直結
させることで地中梁等を不要にすることは、工事におけ
る搬出残土の低減を図るものであり、建物全体としての
コスト削減に寄与している。尚、杭に柱を直結させたこ
とによる耐震安全性についても、本発明の場合には、後
述するように上部架構の設備階をトラス架構によって構
成することで荷重の低減を図っており、さらに躯体とし
ても上部架構と杭とを連続性のあるモデルとして解析し
て問題が生じないことを確認している。
As described above, by eliminating the need for underground beams or the like by directly connecting the foundation frame to the piles to the pillars, the purpose is to reduce the unremoved soil during construction and to reduce the cost of the entire building. Has contributed. In addition, regarding the seismic safety by directly connecting the columns to the piles, in the case of the present invention, the load is reduced by configuring the equipment floor of the upper frame by a truss frame as described later. We analyzed the upper frame and the pile as a model with continuity as the frame, and confirmed that no problems occurred.

【0015】本実施の形態において、搬出階、製造階及
び設備空間を構成する上部架構は、壁面にブレースを設
けて耐震性を強めながら、設備階の構成をトラス架構中
心に構築することで、軽量化と上述した設備機器、ダク
ト配管、ケーブルラック等の支援設備機器を配置するた
めのスペースの拡大を図っている。図3は、搬出階3の
上部に構築された設備階10における点検歩廊の配置状
態を示す平面図である。トラス架構31〜34は、同形
状に構成されて等間隔で平行に配置されている。図で
は、トラス架構の設置と点検歩廊15の配置状態を主に
表現しており、トラス架構以外の部分やトラス架構間の
架構は、図示していないが、H鋼材等を用いて通常の形
態で構成されている。この設備階における点検歩廊15
は、支援設備機器の種類と配置に従って図示のように縦
横に配置されている。
In the present embodiment, the upper frame constituting the unloading floor, the manufacturing floor, and the equipment space is constructed by providing a brace on the wall surface to enhance the earthquake resistance, while constructing the structure of the equipment floor around the truss frame. The weight is reduced and the space for arranging the supporting equipment such as the above-described equipment, duct piping, and cable racks is increased. FIG. 3 is a plan view showing the arrangement of the inspection corridor on the equipment floor 10 constructed above the carry-out floor 3. The truss frames 31 to 34 are configured in the same shape and are arranged in parallel at equal intervals. In the figure, the installation of the truss frame and the arrangement of the inspection corridor 15 are mainly expressed, and the parts other than the truss frame and the frames between the truss frames are not shown, but are usually formed using H steel material or the like. It is composed of Inspection corridor 15 on this equipment floor
Are arranged vertically and horizontally as shown in the figure according to the type and arrangement of the support equipment.

【0016】図4は、製造階4の上部に構築された設備
階10’における点検歩廊の配置状態を示す平面図であ
る。本実施の形態におけるトラス架構41、42、45
〜47は、同形状に構成されて配置されており、空調機
室を構成しているトラス架構43、44は大きな成にな
っている。点検歩廊15’は、図示のように各トラス架
構に沿った状態で配置されており、両端部において点検
歩廊間を接続している。この場合も、トラス架構の設置
と点検歩廊15’の配置状態を主に表現しているが、ト
ラス架構以外の部分やトラス架構間の架構は、図示のよ
うにH鋼材等を用いて通常の形態で構成されている。
FIG. 4 is a plan view showing the arrangement of the inspection corridor on the equipment floor 10 ′ constructed above the manufacturing floor 4. Truss frames 41, 42, 45 in the present embodiment
47 are configured and arranged in the same shape, and the truss frames 43 and 44 constituting the air conditioner room are formed in a large size. The inspection corridor 15 'is arranged along each truss frame as shown, and connects the inspection corridors at both ends. In this case as well, the installation of the truss frame and the arrangement of the inspection corridor 15 'are mainly expressed. It is configured in the form.

【0017】図5は、ガスと給水管の引き込み及び排水
管の取り出し位置を示す基礎部分の平面図である。上述
のように基礎部分は、杭と柱を直接接合して地中梁を排
除してあるので、床下ピット2は均一な空間を形成して
おり、平面的にも柱が等間隔で整然とした点状態に配置
されている。従って、ガスと水の給排水配管は任意の位
置に自由度を持って配置することができると共に、保守
点検の場合にも図示の動線48が示すように前後左右に
直線上に移動することができるので、点検を確実に実施
することができる。。
FIG. 5 is a plan view of the basic portion showing the positions where the gas and water supply pipes are drawn in and the drainage pipes are taken out. As described above, since the underground beam is eliminated by directly joining the pile and the pillar to the foundation, the underfloor pit 2 forms a uniform space, and the pillars are also arranged at regular intervals in the plane. It is arranged in a point state. Therefore, the gas and water supply / drainage pipes can be arranged at an arbitrary position with a degree of freedom, and can be moved linearly forward, backward, left and right as indicated by the flow line 48 in the case of maintenance and inspection. As a result, the inspection can be reliably performed. .

【0018】以上、本発明を実施の形態に基づいて詳細
に説明してきたが、本発明による建築構造物とその架構
構造は、上記実施の形態に何ら限定されるものでなく、
トラス架構の構造や柱、杭等に関して本発明の趣旨を逸
脱しない範囲において種々の変更が可能であることは当
然のことである。
As described above, the present invention has been described in detail based on the embodiments. However, the building structure and the frame structure thereof according to the present invention are not limited to the above embodiments.
It is a matter of course that various changes can be made to the structure of the truss frame, columns, piles, etc. without departing from the spirit of the present invention.

【0019】[0019]

【発明の効果】本発明による建築構造物は、稼働階の上
部に稼働支援設備を配置する設備空間を構成し、稼働階
と設備空間を支持する杭と柱を直かに接合して基礎を排
除した床下を給排水等の配管空間とし、上記設備空間に
点検歩廊を配置することを特徴としているので、基礎や
地中梁を無くして床下に広い空間を確保して、ガス、給
排水等の配管を効率的に配置し、稼働階の上部に設けた
設備空間の点検歩廊を巡回することで、稼働階の作業状
況に何らの影響を与えることなく、支援設備等の保守点
検を可能にする効果を発揮している。
The building structure according to the present invention constitutes an equipment space for arranging operation support equipment at the upper part of the operating floor, and directly connects the piles and columns supporting the operating floor and the equipment space to form a foundation. The underfloor floor is a plumbing space for plumbing and drainage, etc., and the inspection corridor is located in the above equipment space.Therefore, a large space under the floor is secured by eliminating foundations and underground beams, and piping for gas, plumbing, etc. The effect of enabling efficient maintenance and inspection of support equipment without affecting the working status of the operating floor by patroling the stairs of the equipment space installed above the operating floor efficiently Has been demonstrated.

【0020】又、本発明による建築構造物の架構構造
は、杭と柱を直に接続し床をフラットスラブで構築して
床下に形成した配管空間と、柱間の接合をトラス架構で
構築して稼働階の上部に形成した設備空間とで構成して
いるので、床下における効率的な配管とその点検を容易
にし、設備空間のダクト配管スペースを広く確保して効
率的な配管と保守点検等を容易にする効果を発揮してい
る。
Further, the frame structure of the building structure according to the present invention is constructed by connecting a pile and a column directly, constructing a floor with a flat slab, and forming a pipe space formed under the floor and a joint between the columns with a truss frame. The equipment space formed above the operating floor facilitates efficient piping and inspection under the floor, and secures a wide duct space in the equipment space to ensure efficient piping and maintenance. It has the effect of making it easier.

【図面の簡単な説明】[Brief description of the drawings]

【 図1】本発明による建築構造物の斜視断面図FIG. 1 is a perspective sectional view of a building structure according to the present invention.

【 図2】本発明による建築構造物の床下構造を示す部
分断面図
FIG. 2 is a partial sectional view showing an underfloor structure of a building structure according to the present invention.

【 図3】本発明による設備階におけるトラス架構と点
検歩廊の平面配置図
FIG. 3 is a plan view of the truss frame and the inspection corridor on the equipment floor according to the present invention.

【 図4】本発明による他の設備階におけるトラス架構
と点検歩廊の平面配置図
FIG. 4 is a plan view of a truss frame and an inspection corridor at another facility floor according to the present invention.

【 図5】本発明による建築構造物の床下平面図FIG. 5 is a plan view under the floor of a building structure according to the present invention.

【符号の説明】[Explanation of symbols]

1 惣菜工場、 2 床下ピット、 3 搬出階、 4
製造階、 5 柱、6 杭、 10、10’ 設備
階、 11 設備機器、 12 ダクト配管、13 ケ
ーブルラック、 15、15’ 点検歩廊、 16 P
HC杭、17 鋼管柱、18 基礎梁、 19 杭頭
部、 20 フラットスラブ、31〜34 トラス架
構、 41〜47 トラス架構、48 点検動線、
1 side dish factory, 2 under floor pit, 3 unloading floor, 4
Manufacturing floor, 5 pillars, 6 piles, 10, 10 'equipment floor, 11 equipment, 12 duct piping, 13 cable rack, 15, 15' inspection corridor, 16P
HC pile, 17 steel pipe column, 18 foundation beam, 19 pile head, 20 flat slab, 31-34 truss frame, 41-47 truss frame, 48 inspection flow line,

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 稼働階の上部に稼働支援設備を配置する
設備空間を構成し、該稼働階と設備空間を支持する杭と
柱を直かに接合して基礎を排除した床下を給排水等の配
管空間とし、上記設備空間に点検歩廊を配置することを
特徴とする建築構造物。
1. An equipment space for arranging operation support equipment at the upper part of an operating floor, and a pile and a pillar for directly supporting the operating floor and the equipment space are directly connected to each other to remove water from a floor under a floor. An architectural structure characterized by a piping space and an inspection corridor arranged in the equipment space.
【請求項2】 杭と柱を直に接続し床をフラットスラブ
で構築して床下に形成した配管空間と、柱間の接合をト
ラス架構で構築して稼働階の上部に形成した設備空間と
で構成することを特徴とする建築構造物の架構構造。
2. A piping space formed directly below the floor by directly connecting the stakes and columns to form a floor with a flat slab, and a facility space formed above a working floor by connecting the columns with a truss frame. A frame structure of a building structure, characterized by comprising:
JP2000029889A 2000-02-08 2000-02-08 Building structure and its frame structure Pending JP2001220906A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000029889A JP2001220906A (en) 2000-02-08 2000-02-08 Building structure and its frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000029889A JP2001220906A (en) 2000-02-08 2000-02-08 Building structure and its frame structure

Publications (1)

Publication Number Publication Date
JP2001220906A true JP2001220906A (en) 2001-08-17

Family

ID=18554973

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000029889A Pending JP2001220906A (en) 2000-02-08 2000-02-08 Building structure and its frame structure

Country Status (1)

Country Link
JP (1) JP2001220906A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020105759A (en) * 2018-12-27 2020-07-09 Jsc株式会社 Ground reinforcement structure and reinforcement method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020105759A (en) * 2018-12-27 2020-07-09 Jsc株式会社 Ground reinforcement structure and reinforcement method

Similar Documents

Publication Publication Date Title
US10323428B2 (en) Sequence for constructing a building from prefabricated components
US20190040623A1 (en) Block construction of prefabricated buildings
ES2969483T3 (en) Building construction procedure
JP4316161B2 (en) Power plant construction method
KR100805732B1 (en) Building structure using modular unit
JP2001220906A (en) Building structure and its frame structure
RU169712U1 (en) Large-panel building
JP2577096B2 (en) 3D factory
JP5347557B2 (en) Column beam frame
RU2627436C1 (en) Large-panel building
JP3584979B2 (en) housing complex
CN220414519U (en) Assembled modularization box based on BIM
Ku et al. A case study of multi-trade near-site factory assembly
JPH0241239Y2 (en)
JP2005098079A (en) Unit construction building
JP2004076273A (en) Building
JP5030680B2 (en) Renovation skip floor structure
JP5255299B2 (en) Multipurpose building
JP6924689B2 (en) Suspended structure
JP3484232B2 (en) Unit building
JPH04368568A (en) Construction of multipurpose production system and building thereof
JP3041574B2 (en) Composite fire slab for multi-story apartment building
JP2512158B2 (en) 3D automatic factory
JPH0658002U (en) Structure of vertical prefabricated unit equipped with facilities for vertical function of housing in middle- and high-rise housing at factory
JPH08302823A (en) Unit building and building unit

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20040712

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20040929

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20041019

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20050301