JP2001048440A JP11225501A JP22550199A JP2001048440A JP 2001048440 A JP2001048440 A JP 2001048440A JP 11225501 A JP11225501 A JP 11225501A JP 22550199 A JP22550199 A JP 22550199A JP 2001048440 A JP2001048440 A JP 2001048440A
Authority
JP
Japan
Prior art keywords
guide rail
hoistway
hanging
elevator
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11225501A
Other languages
Japanese (ja)
Inventor
Takashi Morinaga
貴志 森永
Ryoetsu Kanayama
良悦 金山
Kazutaka Iwazawa
和孝 岩澤
Yoshito Mukoyama
芳人 向山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hitachi Building Systems Co Ltd
Original Assignee
Hitachi Building Systems Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hitachi Building Systems Co Ltd filed Critical Hitachi Building Systems Co Ltd
Priority to JP11225501A priority Critical patent/JP2001048440A/en
Publication of JP2001048440A publication Critical patent/JP2001048440A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B19/00Mining-hoist operation
    • B66B19/002Mining-hoist operation installing or exchanging guide rails

Landscapes

  • Load-Engaging Elements For Cranes (AREA)
  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

PROBLEM TO BE SOLVED: To cope with the size of various guide rails and also improve the efficiency of carry-in work and safety. SOLUTION: This device is provided with a winch 6 for hanging up a hang tool 11 through a hang rope 7 and an inclination adjust means which can adjust the hang angle of a guide rail 9. The hang tool 11 is composed of a hang tool piece contacted to one end of a joint plate 10 and the other hang tool piece engaged with this hang tool piece turnably in the longitudinal direction of the guide rail 9. Further, these hang tool pieces are arranged so as to pressingly hold the guide rail 9 with the sectional form of the maximum size and constituted so as to involve plural guide rails 9 arranged in a line.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、乗かごあるいはつ
り合いおもりを案内するエレベータ用ガイドレールの搬
入装置および搬入方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an elevator guide rail carrying device and a carrying method for guiding a car or a counterweight.

【0002】[0002]

【従来の技術】一般にエレベータは、昇降路内に順次立
設される複数本のガイドレールと、これらのガイドレー
ルのうち、上下方向に隣接するもの同士を連結する継ぎ
目板とを備えている。
2. Description of the Related Art Generally, an elevator is provided with a plurality of guide rails which are sequentially erected in a hoistway, and a joint plate which connects vertically adjacent ones of these guide rails.

【0003】従来、この種のエレベータにあっては、例
えば実開昭61−11676号公報に記載されているよ
うに、蝶番で連結された複数の吊り具片から構成したエ
レベータ用ガイドレールの搬入装置が提案されている。
この従来の搬入装置では、ガイドレールの上端部に継ぎ
目板を取り付けるとともに、吊り具片の開端をガイドレ
ールの下端側で閉塞してガイドレールを内包した状態で
揚重機で吊り上げて吊り具片の閉端を継ぎ目板に当接さ
せることにより、ガイドレールを昇降路内に搬入するよ
うになっている。
Conventionally, in an elevator of this type, as described in, for example, Japanese Utility Model Application Laid-Open No. 61-11676, a guide rail for an elevator composed of a plurality of hanging pieces connected by hinges is carried in. A device has been proposed.
In this conventional loading device, a seam plate is attached to the upper end of the guide rail, and the open end of the hanging piece is closed at the lower end side of the guide rail, and the lifting piece is lifted by a lifting machine in a state in which the guide rail is included. By bringing the closed end into contact with the seam plate, the guide rail is carried into the hoistway.

【0004】[0004]

【発明が解決しようとする課題】ところで、上述した従
来のエレベータ用ガイドレールの搬入装置では、ガイド
レールの上端部に取り付けられた継ぎ目板を確実に係合
させるため、ガイドレールの断面形状および大きさに対
応して、複数の吊り具片で構成した当該搬入装置の閉端
と開端との距離を設定する必要があり、各ガイドレール
のサイズ毎に当該搬入装置を準備する必要があった。
In the conventional elevator guide rail loading device described above, the cross-sectional shape and size of the guide rail are required in order to securely engage the seam plate attached to the upper end of the guide rail. Correspondingly, it is necessary to set the distance between the closed end and the open end of the loading device constituted by a plurality of hanging pieces, and it is necessary to prepare the loading device for each size of each guide rail.

【0005】また、このような搬入装置を用いたガイド
レールの搬入作業では、搬入装置の構成上、ガイドレー
ルを1本ずつしか搬入できないため、多くの作業時間を
要するという問題があった。特に、高階床のエレベータ
にあっては、上記の多くの作業時間を要するという問題
が顕著であった。
[0005] In addition, in the work of carrying in the guide rails using such a carrying-in device, there is a problem that much work time is required because only one guide rail can be carried in due to the structure of the carrying-in device. In particular, in the case of an elevator having a high floor, the above-described problem that a large amount of work time is required is remarkable.

【0006】また、ガイドレールを摺動しつつ、その上
端部に取り付けた継ぎ目板に係合してガイドレールを吊
り上げて昇降路内へ搬入するものであるため、搬入時の
ガイドレール上端部の案内作業を兼ねているが、搬入作
業時のガイドレール下端部の案内は、作業者自身が昇降
路近傍の搬入階開口部付近で人力で行なっており、特に
ガイドレールのサイズが大きい場合、作業者にかなりの
重量負担が掛かるため、搬入作業の安全上問題があっ
た。
In addition, since the guide rail is slid and engaged with the seam plate attached to the upper end thereof, the guide rail is lifted and carried into the hoistway. Guide work is also performed, but the guide at the lower end of the guide rails during loading work is manually performed by the worker himself near the entrance floor opening near the hoistway, especially when the size of the guide rail is large. There is a problem in the safety of carrying-in work because a heavy load is applied to the workers.

【0007】本発明は、このような従来技術における実
情に鑑みてなされたもので、その第1の目的は、種々の
ガイドレールのサイズに対応でき、ガイドレール搬入作
業に用いられる仮設材を少なくすることのできるエレベ
ータ用ガイドレールの搬入装置および搬入方法を提供す
ることにある。
The present invention has been made in view of such a situation in the prior art. A first object of the present invention is to cope with various sizes of guide rails and to reduce the number of temporary materials used for carrying in guide rails. It is an object of the present invention to provide an elevator guide rail loading device and a loading method which can be performed.

【0008】また、その第2の目的は、昇降路内へガイ
ドレールを搬入する際に作業の効率向上を図ることので
きるエレベータ用ガイドレールの搬入装置および搬入方
法を提供することにある。
It is a second object of the present invention to provide an elevator guide rail loading device and a loading method which can improve the work efficiency when loading the guide rail into the hoistway.

【0009】また、その第3の目的は、昇降路内へガイ
ドレールを搬入する際に作業者の負担を軽減し、作業の
安全性を向上させることのできるエレベータ用ガイドレ
ールの搬入装置および搬入方法を提供することにある。
A third object of the present invention is to provide an elevator guide rail loading device and loading device which can reduce the burden on the operator when loading the guide rail into the hoistway and improve the work safety. It is to provide a method.

【0010】[0010]

【課題を解決するための手段】上記第1の目的を達成す
るため、本発明の請求項1に係る発明は、昇降路内に順
次立設される複数本のガイドレールと、これらのガイド
レールのうち、上下方向に隣接するもの同士を連結する
継ぎ目板とを有するエレベータであって、前記ガイドレ
ールに摺動可能に係合する吊り具を備え、前記ガイドレ
ールの上端部の背面に前記継ぎ目板を取り付けた状態
で、前記ガイドレールを吊り上げて前記昇降路内に搬入
するエレベータ用ガイドレールの搬入装置において、前
記吊り具が、前記ガイドレールの背面側に設けられ、前
記継ぎ目板の一端に当接する第1の吊り具片と、前記ガ
イドレールの摺動部側に設けられ、前記第1の吊り具片
に対して前記ガイドレールの長手方向に回動可能に係合
する第2の吊り具片とを備えるとともに、これらの第1
の吊り具片および第2の吊り具片を、前記ガイドレール
の断面形状が最大寸法のものを挟圧可能に配置した構成
にしてある。
In order to achieve the first object, the invention according to claim 1 of the present invention provides a plurality of guide rails which are sequentially erected in a hoistway, and these guide rails are provided. An elevator having a seam plate connecting vertically adjacent ones of the guide rails, wherein the elevator includes a suspender slidably engaged with the guide rail, and the seam is provided on a back surface of an upper end of the guide rail. In an elevator guide rail loading device that lifts the guide rail and loads it into the hoistway with the plate attached, the lifting device is provided on the back side of the guide rail, and at one end of the joint plate. A first suspending piece that abuts and a second suspending part that is provided on the sliding portion side of the guide rail and engages with the first suspending piece so as to be rotatable in the longitudinal direction of the guide rail. Piece Provided with a, of the first
And the second suspending piece are arranged such that the guide rail having the largest cross-sectional shape can be pressed.

【0011】このように構成した本発明の請求項1に係
る発明では、ガイドレールを吊り具で内包した状態で吊
り具を吊り上げると、この吊り具がガイドレールを摺動
した後、ガイドレールの背面側に設けられる第1の吊り
具片が継ぎ目板の一端に当接するとともに、ガイドレー
ルの摺動部側に設けられる第2の吊り具片が第1の吊り
具片に対してガイドレールの長手方向に回動して、これ
らの第1の吊り具片および第2の吊り具片でガイドレー
ルを挟圧し、その結果、ガイドレールを吊り上げること
ができる。これにより、ガイドレールのサイズに合わせ
て第1の吊り具片および第2の吊り具片の位置関係を設
定する必要がなくて済み、種々のガイドレールのサイズ
に対応することができる。
According to the first aspect of the present invention having the above-described structure, when the lifting device is lifted in a state where the guide rail is included in the lifting device, the lifting device slides on the guide rail, and then the lifting device slides on the guide rail. A first hanging piece provided on the back side abuts one end of the seam plate, and a second hanging piece provided on the sliding portion side of the guide rail has a guide rail with respect to the first hanging piece. By rotating in the longitudinal direction, the guide rail is pinched by the first and second hanging pieces, and as a result, the guide rail can be lifted. Accordingly, it is not necessary to set the positional relationship between the first hanging piece and the second hanging piece according to the size of the guide rail, and it is possible to cope with various sizes of the guide rail.

【0012】また、上記第2の目的を達成するため、本
発明の請求項2に係る発明は、請求項1に係る発明にお
いて、前記第1の吊り具片および第2の吊り具片は、前
記ガイドレールの長手方向に対して直角な方向に所定の
長さを有し、かつ並列に配置した前記複数本のガイドレ
ールを内包可能な構成にしてある。
In order to achieve the second object, the invention according to claim 2 of the present invention is directed to the invention according to claim 1, wherein the first hanging piece and the second hanging piece are The guide rail has a predetermined length in a direction perpendicular to the longitudinal direction of the guide rail, and is configured to include the plurality of guide rails arranged in parallel.

【0013】このように構成した本発明の請求項2に係
る発明では、並列に配置した複数本のガイドレールを吊
り具により内包して昇降路内に一括して搬入するので、
全てのガイドレールを搬入する作業時間を短縮でき、こ
れにより、ガイドレール搬入作業の効率向上を図ること
ができる。
In the invention according to the second aspect of the present invention, a plurality of guide rails arranged in parallel are included in a hoist and collectively carried into the hoistway.
The work time for carrying in all the guide rails can be shortened, so that the efficiency of the guide rail carry-in work can be improved.

【0014】また、上記第2の目的を達成するため、本
発明の請求項3に係る発明は、請求項1に係る発明にお
いて、前記第1の吊り具片は、前記ガイドレールの背面
側に配置される平板部材と、この平板部材の長手方向の
両端部に配置され、その長手方向の間隔が調整可能な状
態で固定される一対の略L字型部材とから構成されてい
る。
According to a third aspect of the present invention, in order to achieve the second object, in the first aspect of the present invention, the first hanging piece is provided on a rear side of the guide rail. It is composed of a flat plate member to be arranged, and a pair of substantially L-shaped members which are arranged at both ends in the longitudinal direction of the flat plate member and are fixed in a state where the interval in the longitudinal direction is adjustable.

【0015】このように構成した本発明の請求項3に係
る発明では、一対の略L字型部材の間隔を任意に調整す
ることにより、内包するガイドレールの本数を変えるこ
とができるため、より多くのガイドレールを一括して搬
入でき、これにより、ガイドレール搬入作業の効率向上
をさらに図ることができる。
In the invention according to the third aspect of the present invention, the number of guide rails to be included can be changed by arbitrarily adjusting the interval between the pair of substantially L-shaped members. A large number of guide rails can be carried in at once, thereby further improving the efficiency of guide rail carrying work.

【0016】また、本発明の請求項4に係る発明は、請
求項1に係る発明において、第2の吊り具片は、前記ガ
イドレールの摺動部を保護する保護部材を備えた構成に
してある。
According to a fourth aspect of the present invention, in the first aspect of the invention, the second hanging piece is provided with a protection member for protecting a sliding portion of the guide rail. is there.

【0017】このように構成した本発明の請求項4に係
る発明では、第1の吊り具片および第2の吊り具片で挟
圧してガイドレールを吊り上げる際に、保護部材でガイ
ドレールの摺動部を保護するので、この摺動部の損傷を
防止でき、これにより、ガイドレール搬入作業を円滑に
行なえる。
According to the fourth aspect of the present invention, when the guide rail is lifted by being pressed between the first and second hanging pieces, the protection member slides the guide rail. Since the moving portion is protected, the sliding portion can be prevented from being damaged, and thus the guide rail carrying-in operation can be performed smoothly.

【0018】また、上記第1の目的および第3の目的を
達成するため、本発明の請求項5に係る発明は、昇降路
内に順次立設される複数本のガイドレールと、これらの
ガイドレールのうち、上下方向に隣接するもの同士を連
結する継ぎ目板とを有するエレベータであって、前記ガ
イドレールに摺動可能に係合する吊り具を備え、前記ガ
イドレールの上端部の背面に前記継ぎ目板を取り付けた
状態で、前記ガイドレールを吊り上げて前記昇降路内に
搬入するエレベータ用ガイドレールの搬入装置におい
て、前記昇降路およびその近傍の一方に配置され、前記
吊り具を吊りロープを介して吊り上げる揚重機と、前記
ガイドレールの下端部に取り付けられる連結具と、この
連結具と前記吊りロープの先端部との間に設けられ、前
記吊り具にて前記ガイドレールの上端部を吊り上げた
際、前記ガイドレールの吊り角度を調整可能な傾斜調整
手段とを備え、前記吊り具が、前記ガイドレールの背面
側に設けられ、前記継ぎ目板の一端に当接する第1の吊
り具片と、前記ガイドレールの摺動部側に設けられ、前
記第1の吊り具片に対して前記ガイドレールの長手方向
に回動可能に係合する第2の吊り具片とを備えるととも
に、これらの第1の吊り具片および第2の吊り具片を、
前記ガイドレールの断面形状が最大寸法のものを挟圧可
能に配置した構成にしてある。
In order to achieve the first and third objects, the invention according to claim 5 of the present invention provides a plurality of guide rails which are sequentially erected in a hoistway, and these guide rails are provided. An elevator having a seam plate for connecting vertically adjacent rails among the rails, comprising: a suspender slidably engaged with the guide rail; and a rear surface at an upper end portion of the guide rail. In an elevator guide rail loading device that lifts the guide rail and carries it into the hoistway with the seam plate attached, the elevator is disposed on one of the hoistway and the vicinity thereof, and the hanging tool is connected to the hoistway via a hanging rope. A lifting device, a connecting device attached to a lower end of the guide rail, and a connecting device provided between the connecting device and a tip of the suspension rope. When the upper end of the trail is lifted, the guide rail is provided with an inclination adjusting means capable of adjusting a hanging angle of the guide rail, and the hanging tool is provided on a rear side of the guide rail, and is in contact with one end of the joint plate. A first hanging piece and a second hanging piece provided on the sliding portion side of the guide rail and rotatably engaged with the first hanging piece in the longitudinal direction of the guide rail. And the first and second hanging piece pieces are
The guide rail having a maximum cross-sectional shape is arranged so as to be able to press.

【0019】このように構成した本発明の請求項5に係
る発明では、ガイドレールの上端部を吊り上げて昇降路
内に搬入する際、傾斜調整手段の作動でガイドレールの
吊り角度を調整することにより、ガイドレールの下端部
を誘導できるので、ガイドレール搬入作業時に作業者の
負担を軽減でき、作業の安全性を向上させることができ
る。また、上述したように第1の吊り具片および第2の
吊り具片でガイドレールを挟圧してガイドレールを吊り
上げることができるので、ガイドレールのサイズに合わ
せて第1の吊り具片および第2の吊り具片の位置関係を
設定する必要がなくて済み、種々のガイドレールのサイ
ズに対応可能である。
According to the fifth aspect of the present invention, when the upper end of the guide rail is lifted and carried into the hoistway, the suspension angle of the guide rail is adjusted by the operation of the inclination adjusting means. Thereby, the lower end of the guide rail can be guided, so that the burden on the operator can be reduced when the guide rail is carried in, and the safety of the work can be improved. Further, as described above, the guide rail can be lifted by pressing the guide rail between the first hanging member piece and the second hanging member piece. Therefore, the first hanging member piece and the second hanging member piece can be lifted according to the size of the guide rail. There is no need to set the positional relationship between the two hanging pieces, and it is possible to cope with various guide rail sizes.

【0020】また、上記第2の目的を達成するため、本
発明の請求項6に係る発明は、昇降路内に順次立設され
る複数本のガイドレールと、これらのガイドレールのう
ち、上下方向に隣接するもの同士を連結する継ぎ目板と
を有するエレベータであって、前記継ぎ目板を前記ガイ
ドレールの上端部に取り付けた状態で、前記ガイドレー
ルを吊り上げて前記昇降路内に搬入するエレベータ用ガ
イドレールの搬入方法において、前記昇降路の近傍の乗
り場床に、前記継ぎ目板を取り付けた前記複数本のガイ
ドレールの上端部側を前記昇降路に向けた状態で、これ
らのガイドレールを並列に配置して吊り具を摺動可能に
係合させるとともに、この吊り具で前記ガイドレールを
内包した後、前記昇降路およびその近傍の一方に配置し
た揚重機で前記吊り具を駆動することにより、この吊り
具で前記ガイドレールを挟圧するとともに、前記吊り具
を前記継ぎ目板の一端に当接させて、前記ガイドレール
を一括して吊り上げて前記昇降路内に搬入する構成にし
てある。
In order to achieve the second object, the invention according to claim 6 of the present invention is directed to a plurality of guide rails that are sequentially erected in a hoistway, and of these guide rails, An elevator having a seam plate connecting adjacent ones in a direction, wherein the seam plate is attached to an upper end portion of the guide rail, and the guide rail is lifted and carried into the hoistway. In the method of loading guide rails, on the landing floor near the hoistway, with the upper end sides of the plurality of guide rails attached with the seam plate facing the hoistway, these guide rails are arranged in parallel. The lifting device is slidably engaged with the lifting device, and the guide rail is included in the lifting device, and then the lifting device is placed on the hoistway and one of the vicinity thereof. By driving the tool, the guide rail is pressed by the hanging tool, and the hanging tool is brought into contact with one end of the seam plate, and the guide rail is lifted at a time and carried into the hoistway. It has a configuration.

【0021】このように構成した本発明の請求項6に係
る発明では、昇降路の近傍の乗り場床で複数本のガイド
レールを並列に配置し、これらのガイドレールを吊り具
により内包して昇降路内に一括して搬入するので、全て
のガイドレールを搬入する作業時間を短縮でき、これに
より、ガイドレール搬入作業の効率向上を図ることがで
きる。
In the invention according to the sixth aspect of the present invention, a plurality of guide rails are arranged in parallel on the landing floor near the hoistway, and these guide rails are included in the lifting device to ascend and descend. Since all the guide rails are loaded into the road at a time, the work time for loading all the guide rails can be shortened, thereby improving the efficiency of the guide rail loading work.

【0022】また、上記第3の目的を達成するため、本
発明の請求項7に係る発明は、昇降路内に順次立設され
る複数本のガイドレールと、これらのガイドレールのう
ち、上下方向に隣接するもの同士を連結する継ぎ目板と
を有するエレベータであって、前記継ぎ目板を前記ガイ
ドレールの上端部に取り付けた状態で、前記ガイドレー
ルを吊り上げて前記昇降路内に搬入するエレベータ用ガ
イドレールの搬入方法において、前記ガイドレールに吊
り具を摺動可能に係合させるとともに、この吊り具で前
記ガイドレールを内包した後、前記昇降路およびその近
傍の一方に配置した揚重機で前記吊り具を駆動すること
により、この吊り具で前記ガイドレールを挟圧するとと
もに、前記吊り具を前記継ぎ目板の一端に当接させて前
記ガイドレールの上端部を吊り上げるとともに、このガ
イドレールの下端部に取り付けられる連結具と前記揚重
機との間に角度調整手段を設けて、前記揚重機による前
記ガイドレールの上端部の吊り上げに同期して前記角度
調整手段で前記ガイドレールの吊り角度を調整しなが
ら、このガイドレールを鉛直な状態に配置して前記昇降
路内に搬入する構成にしてある。
In order to achieve the third object, the invention according to claim 7 of the present invention is directed to a plurality of guide rails which are sequentially erected in a hoistway, and of these guide rails, An elevator having a seam plate connecting adjacent ones in a direction, wherein the seam plate is attached to an upper end portion of the guide rail, and the guide rail is lifted and carried into the hoistway. In the method of loading a guide rail, a lifting device is slidably engaged with the guide rail, and the guide rail is included in the lifting device. By driving the suspender, the guide rail is pressed by the suspender, and the suspender is brought into contact with one end of the seam plate to allow the guide rail to move. While lifting the end portion, an angle adjusting means is provided between the connecting device attached to the lower end of the guide rail and the hoist, and the angle is synchronized with the lifting of the upper end of the guide rail by the hoist. While adjusting the hanging angle of the guide rail by adjusting means, the guide rail is arranged vertically and carried into the hoistway.

【0023】このように構成した本発明の請求項7に係
る発明では、ガイドレールの上端部を吊り上げて昇降路
内に搬入する際、傾斜調整手段の作動でガイドレールの
吊り角度を調整することにより、ガイドレールの下端部
を誘導できるので、ガイドレール搬入作業時に作業者の
負担を軽減でき、作業の安全性を向上させることができ
る。
In the invention according to the seventh aspect of the present invention, when the upper end of the guide rail is lifted and carried into the hoistway, the suspension angle of the guide rail is adjusted by the operation of the inclination adjusting means. Thereby, the lower end of the guide rail can be guided, so that the burden on the operator can be reduced when the guide rail is carried in, and the safety of the work can be improved.

【0024】[0024]

【発明の実施の形態】以下、本発明のエレベータ用ガイ
ドレールの搬入装置および搬入方法の実施の形態を図に
基づいて説明する。
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view of an elevator guide rail loading apparatus and method according to an embodiment of the present invention.

【0025】図1は本発明の第1の実施形態に係るエレ
ベータ用ガイドレールの搬入装置を説明する側面図、図
2は図1の搬入装置に設けられる吊り具の斜視図、図3
は図1の搬入装置に設けられる連結具を説明する斜視
図、図4は吊り具をガイドレールに装着した状態を示す
側面図、図5は吊り具を継ぎ目板の一端に当接させた状
態を示す側面図、図6はガイドレールの吊り角度を調整
する作業を説明する側面図、図7はガイドレールを昇降
路の底部に仮置きした状態を示す側面図、図8は本実施
形態に係る搬入方法によりエレベータ用ガイドレールを
搬入する際の作業手順を示すフローチャートである。
FIG. 1 is a side view illustrating an elevator guide rail loading device according to a first embodiment of the present invention. FIG. 2 is a perspective view of a hanging member provided in the loading device of FIG.
FIG. 4 is a perspective view illustrating a connector provided in the carrying-in device of FIG. 1, FIG. 4 is a side view showing a state in which the suspender is mounted on a guide rail, and FIG. , FIG. 6 is a side view illustrating the operation of adjusting the hanging angle of the guide rail, FIG. 7 is a side view illustrating a state where the guide rail is temporarily placed on the bottom of the hoistway, and FIG. It is a flowchart which shows the operation | work procedure at the time of carrying in an elevator guide rail by this carrying-in method.

【0026】図1に示すエレベータでは、昇降路1の最
上部および最下部のそれぞれに機械室2、ピット3が形
成されるとともに、図示しない乗場用部品が設置される
開口部4および乗り場床5が任意の位置に建築施工によ
り形成されており、昇降路1内に複数本のガイドレール
9を順次立設した後、上下方向に隣接する2本のガイド
レール9の端部を継ぎ目板10を介して連結するように
なっている。
In the elevator shown in FIG. 1, a machine room 2 and a pit 3 are formed at the uppermost portion and the lowermost portion of the hoistway 1, respectively, and an opening 4 and a landing floor 5 where landing parts (not shown) are installed. Is formed at an arbitrary position by construction, and after sequentially arranging a plurality of guide rails 9 in the hoistway 1, the ends of two guide rails 9 vertically adjacent to each other are connected to the seam plate 10. It is designed to be connected via

【0027】そして、本実施形態の搬入装置にあって
は、昇降路1の近傍、例えば乗り場床5に配置され、吊
りロープ7が巻掛けられる第1の揚重機6と、吊りロー
プ7を案内する滑車8a、8b、8cと、第1の揚重機
6により吊りロープ7を介して駆動され、複数本のガイ
ドレール9を挟圧して吊り上げる吊り具11と、この吊
り具11と吊りロープ7の先端部とを連結する連結ロー
プ12と、吊りロープ7の先端部に取り付けられる第2
の揚重機13と、ガイドレール9の下端部に取り付けら
れる連結具14とからなっている。
In the carrying-in device of the present embodiment, the first lifting machine 6 which is arranged near the hoistway 1, for example, on the landing floor 5 and around which the hanging rope 7 is wound, guides the hanging rope 7. Pulleys 8a, 8b, 8c, and a lifting tool 11 driven by a first lifting machine 6 via a lifting rope 7 to squeeze and lift a plurality of guide rails 9; A connecting rope 12 for connecting the leading end, and a second rope attached to the leading end of the hanging rope 7.
And a connecting member 14 attached to the lower end of the guide rail 9.

【0028】第1の滑車8aは昇降路1の側壁部に取り
付けられ、乗り場床5の反対側に位置し、第2の滑車8
bは機械室2の天井部の端部に取り付けられ、第1の滑
車8aの直上に位置し、第3の滑車8cは機械室2の天
井部の中央に取り付けられている。
The first pulley 8a is attached to the side wall of the hoistway 1, is located on the opposite side of the landing floor 5, and has the second pulley 8a.
b is attached to the end of the ceiling of the machine room 2 and is located immediately above the first pulley 8a, and the third pulley 8c is attached to the center of the ceiling of the machine room 2.

【0029】吊り具11は、図2に示すように、ガイド
レール9の背面9a側に設けられる第1の吊り具片11
aと、ガイドレール9の摺動部9b側に設けられる第2
の吊り具片11bとを備えるとともに、これらの第1の
吊り具片11aおよび第2の吊り具片11bを、ガイド
レール9の断面形状が最大寸法のものを挟圧可能に配置
してある。また、第1の吊り具片11aおよび第2の吊
り具片11bは、ガイドレール9の長手方向に対して直
角な方向に所定の長さを有し、かつ並列に配置した複数
本のガイドレール9を内包可能な構成である。
As shown in FIG. 2, the hanging member 11 is a first hanging member 11 provided on the back surface 9a side of the guide rail 9.
a and a second portion provided on the sliding portion 9b side of the guide rail 9.
And the first hanging piece 11a and the second hanging piece 11b are arranged so that the guide rail 9 having the largest cross-sectional shape can be pinched. The first hanging piece 11a and the second hanging piece 11b have a predetermined length in a direction perpendicular to the longitudinal direction of the guide rail 9, and a plurality of guide rails arranged in parallel. 9 can be included.

【0030】さらに、第1の吊り具片11aは、ガイド
レール9の背面9aに当接し、かつ継ぎ目板10の一端
に係合する平板部材11cと、この平板部材11cの長
手方向の両端部に配置され、平板部材11cに対して直
角に形成される一対の折曲部材11dとから構成されて
おり、この一対の折曲部材11dの側面にはそれぞれ外
方へ突出する突起11eが設けられている。第2の吊り
具片11bは、折曲部材11dの外側に当接し、前記の
突起11eが係合するL字型の溝部11gを有する一対
の平板11fと、この一対の平板11fの両方に挿通さ
れる連結棒11hからなっている。これらの平板11f
および連結棒11hは、前記の突起11eを回転軸とし
て一体的にガイドレール9の長手方向に回動可能な状態
で、第1の吊り具片11aに係合している。
Further, the first suspending piece 11a is in contact with the back surface 9a of the guide rail 9 and is engaged with one end of the seam plate 10, and is provided at both longitudinal ends of the flat member 11c. And a pair of bent members 11d formed at right angles to the flat plate member 11c. Projections 11e projecting outward are provided on the side surfaces of the pair of bent members 11d, respectively. I have. The second hanging piece 11b is in contact with the outside of the bending member 11d, and is inserted into both the pair of flat plates 11f having the L-shaped grooves 11g with which the protrusions 11e engage, and the pair of flat plates 11f. And a connecting rod 11h. These flat plates 11f
The connecting rod 11h is engaged with the first suspending piece 11a in a state in which the connecting rod 11h is rotatable in the longitudinal direction of the guide rail 9 integrally with the projection 11e as a rotation axis.

【0031】第2の揚重機13は、ガイドレール9の下
端に取り付けられる連結具14に先端が連結される索引
ロープ13aを有し、この第2の揚重機13を駆動する
ことによって吊りロープ7の先端部とガイドレール9の
下端部との距離を調整可能な構造になっており、これら
の第2の揚重機13および索引ロープ13aにより、吊
り具11にてガイドレール9の上端部を吊り上げた際、
ガイドレール9の吊り角度を調整可能な傾斜調整手段が
構成されている。
The second lifting machine 13 has an index rope 13a, the tip of which is connected to a connecting member 14 attached to the lower end of the guide rail 9; Of the guide rail 9 and the lower end of the guide rail 9 can be adjusted. The upper end of the guide rail 9 is lifted by the lifting device 11 by the second lifting machine 13 and the index rope 13a. When
Inclination adjusting means capable of adjusting the hanging angle of the guide rail 9 is configured.

【0032】連結具14は、図3に示すように、それぞ
れのガイドレール9の他端に設けられる短手方向の貫通
穴9cに通通されている。
As shown in FIG. 3, the connecting members 14 are passed through through holes 9c in the short direction provided at the other ends of the respective guide rails 9.

【0033】本実施形態の搬入方法にあっては、図8に
示す作業手順にしたがって、まず上述した搬入装置を昇
降路1およびその近傍に設置するようになっている。す
なわち手順S1として、あらかじめ昇降路1に近接する
場所、例えば乗り場床5上で図2に示すように4本のガ
イドレール9の上端部にそれぞれ継ぎ目板10をボルト
10aとナット10bにより固定し、各継ぎ目板10を
乗り場開口部4の方向に配置した状態で前記の4本のガ
イドレール9を並列に配置した後、これらのガイドレー
ル9の上端部近傍の背面9aに第1の吊り具片11aの
平板部材11cを当接させるとともに、4本のガイドレ
ール9を内包するように第1の吊り具片11aを配置す
る。
In the carrying-in method of the present embodiment, the carrying-in device described above is first installed in the hoistway 1 and its vicinity in accordance with the work procedure shown in FIG. That is, as a procedure S1, a seam plate 10 is fixed in advance to a location close to the hoistway 1, for example, on the landing floor 5 at the upper end portions of the four guide rails 9 with the bolts 10a and the nuts 10b as shown in FIG. After arranging the four guide rails 9 in parallel with each seam plate 10 arranged in the direction of the landing opening 4, a first hanging piece is attached to the back surface 9 a near the upper end of these guide rails 9. The first hanging piece 11a is arranged so that the flat plate member 11c of 11a abuts and the four guide rails 9 are included.

【0034】次いで、手順S2として、例えば乗り場床
5上で一対の平板11fおよび連結棒11hから第2の
吊り具片11bを予め組み立てておき、一対の平板11
fの溝部11gに第1の吊り具片11aの突起11eを
係合させた状態で、この第1の吊り具片11aに対して
第2の吊り具片11bを組み付ける。これにより、第1
の吊り具片11aおよび第2の吊り具片11bから構成
される吊り具11は、4本のガイドレール9を内包する
状態で、継ぎ目板10が取り付けられたガイドレール9
の上端部付近に配置される。
Next, as a step S2, for example, the second hanging piece 11b is previously assembled from the pair of flat plates 11f and the connecting rod 11h on the landing floor 5, and
With the projection 11e of the first hanging piece 11a engaged with the groove 11g of f, the second hanging piece 11b is assembled to the first hanging piece 11a. Thereby, the first
The hanging tool 11 composed of the hanging tool piece 11a and the second hanging tool piece 11b includes the four guide rails 9 and the guide rail 9 to which the seam plate 10 is attached.
Is arranged near the upper end.

【0035】次いで、手順S3として、乗り場床5上に
設置した第1の揚重機6の吊りロープ7を滑車8a〜8
cに順次掛け回すとともに、吊りロープ7の先端部に取
り付けた連結ロープ12の端部を第2の吊り具片11b
の連結棒11hに連結し、図3に示すように前記のガイ
ドレール9の下端部に設けられる貫通穴9cに連結具1
4を挿通するとともに、手順S4として、図1に示すよ
うに上述した吊りロープ7の先端部に第2の揚重機13
を取付け、牽引ロープ13aの先端部を連結具14に連
結する。
Next, in step S3, the suspension ropes 7 of the first hoist 6 installed on the landing floor 5 are pulled out of the pulleys 8a to 8a.
c, and the end of the connecting rope 12 attached to the tip of the hanging rope 7 is connected to the second hanging piece 11b.
3 is connected to a connecting rod 11h, and as shown in FIG.
4 and the second lifting machine 13 is attached to the distal end of the above-described hanging rope 7 as shown in FIG.
Is attached, and the distal end of the tow rope 13a is connected to the connecting tool 14.

【0036】このようにして搬入装置を昇降路1および
その近傍に設置した後、次のような手順でガイドレール
9を昇降路1内に搬入するようになっている。すなわ
ち、手順S5として、第1の揚重機6の駆動で吊りロー
プ7を若干巻取ることにより、この吊りロープ7の先端
部を昇降路1内で上昇させると、図4に示すように、連
結ロープ12を介して吊り具11が昇降路1の方向へ引
き寄せられるとともに、吊り具11がガイドレール9の
背面9aおよび摺動部9bを摺動し、ガイドレール9の
上端部に取り付けた継ぎ目板10の下端部に第1の吊り
具片11aの平板部材11cが当接するまで移動する。
次いで、図4に示す状態からさらに第1の揚重機6を駆
動することにより、図5に示すように、吊り具11が継
ぎ目板10の下端部に当接した状態で、この吊り具11
を介してガイドレール9の上端部を吊り上げながら昇降
路1の方向に引き込まれる。このとき、第2の吊り具片
11bは一対の平板11fの溝部11gに第1の吊り具
片11aの突起11eが係合しているので、この突起1
1eを回転軸として第2の吊り具片11bが昇降路1の
方向(図5の時計方向)に回転するとともに、第1の吊
り具片11aの平板部材11cと第2の吊り具片11b
の連結棒11hとで前記のガイドレール9を挟圧するた
め、これらの吊り具11および4本のガイドレール9は
一体的に係合した状態となる。
After the loading device is installed in the hoistway 1 and its vicinity, the guide rail 9 is loaded into the hoistway 1 in the following procedure. That is, as a step S5, by slightly winding the suspension rope 7 by driving the first lifting machine 6, the tip of the suspension rope 7 is raised in the hoistway 1, and as shown in FIG. The hanging member 11 is pulled toward the hoistway 1 via the rope 12, and the hanging member 11 slides on the rear surface 9 a and the sliding portion 9 b of the guide rail 9, and is attached to the upper end of the guide rail 9. The lower member 10 moves until the flat plate member 11c of the first hanging piece 11a comes into contact with the lower end portion.
Next, by further driving the first lifting machine 6 from the state shown in FIG. 4, as shown in FIG. 5, in a state where the hanging member 11 is in contact with the lower end portion of the seam plate 10,
Is pulled in the direction of the hoistway 1 while lifting the upper end portion of the guide rail 9 via. At this time, the projections 11e of the first hanging piece 11a are engaged with the grooves 11g of the pair of flat plates 11f.
The second hanging piece 11b rotates in the direction of the hoistway 1 (clockwise in FIG. 5) around the rotation axis 1e, and the flat member 11c of the first hanging piece 11a and the second hanging piece 11b.
Since the above-mentioned guide rail 9 is sandwiched by the connecting rod 11h, the hanging tool 11 and the four guide rails 9 are integrally engaged.

【0037】次いで、図5に示す状態からさらに第1の
揚重機6を駆動することにより、図1に示すように、吊
り具11および4本のガイドレール9は一体的に吊り上
げられながら昇降路1内に引き込まれる。その際、ガイ
ドレール9が乗り場開口部4を通過して昇降路1内に引
き込まれようとするとき、手順S6として、乗り場床5
にて第2の揚重機13を操作し、図6に示すように、牽
引ロープ13aを送り出して吊りロープ7の先端部とガ
イドレール9の下端部との距離を拡げることにより、こ
のガイドレール9の角度を調整してその下端部を昇降路
1内へ誘導し、ガイドレール9の全体が昇降路1内に入
った後、第2の揚重機13をさらに操作することによ
り、昇降路1内で鉛直状態になるまでガイドレール9を
誘導する。
Next, by further driving the first lifting machine 6 from the state shown in FIG. 5, the lifting tool 11 and the four guide rails 9 are lifted integrally while being lifted as shown in FIG. It is drawn into 1. At this time, when the guide rail 9 is going to be drawn into the hoistway 1 through the hall opening 4, as a step S6, the hall floor 5
As shown in FIG. 6, the second lifting machine 13 is operated to send out the tow rope 13a to increase the distance between the tip of the hanging rope 7 and the lower end of the guide rail 9. The lower end of the guide rail 9 is guided into the hoistway 1 and the entire guide rail 9 enters the hoistway 1. The guide rail 9 is guided until it becomes vertical.

【0038】このようにしてガイドレール9を昇降路1
内まで搬入した後、手順S7として、第1の揚重機6の
操作により昇降路1内でガイドレール9をピット3の所
定位置まで移動させて、第2の揚重機13から牽引ロー
プ13aを送り出すことにより、この牽引ロープ13a
の負荷をなくした状態にし、ガイドレール9の下端部の
貫通穴9cから連結具14を取り外す。手順S8とし
て、第1の揚重機6を駆動してガイドレール9の下端部
がピット3の底部に接するまで下降させて、図7に示す
ように、ガイドレール9をピット3内の所定位置に置い
てガイドレール9の上部を昇降路1の壁面に立て掛け
る。
In this way, the guide rail 9 is connected to the hoistway 1
Then, as step S7, the guide rail 9 is moved to a predetermined position of the pit 3 in the hoistway 1 by operating the first lifting machine 6, and the tow rope 13a is sent out from the second lifting machine 13. By this, this tow rope 13a
Is removed, and the connecting member 14 is removed from the through hole 9c at the lower end of the guide rail 9. In step S8, the first lifting machine 6 is driven and lowered until the lower end of the guide rail 9 contacts the bottom of the pit 3, and the guide rail 9 is moved to a predetermined position in the pit 3 as shown in FIG. Then, the upper part of the guide rail 9 is placed on the wall of the hoistway 1.

【0039】次いで、第1の揚重機6をさらに駆動して
吊りロープ7を送り出すと、この吊りロープ7に連結ロ
ープ12を介して連結された吊り具11がガイドレール
9を摺動しながら下降する。その後、ピット3にいる作
業者の高さ位置まで吊り具11が下降したとき、手順S
9として、吊り具片11a、11bの係合状態を解除し
て分割することにより、吊り具11をガイドレール9か
ら取り外す。
Next, when the first lifting machine 6 is further driven and the suspension rope 7 is sent out, the suspension 11 connected to the suspension rope 7 via the connection rope 12 descends while sliding on the guide rail 9. I do. After that, when the suspender 11 descends to the height position of the worker in the pit 3, the procedure S
As 9, the hanging pieces 11 a are removed from the guide rails 9 by releasing the engaging state of the hanging pieces 11 a and 11 b and dividing.

【0040】これによって、上述した4本のガイドレー
ル9の搬入作業が終了する。その後、同様の作業手順を
複数回繰り返すことにより昇降路1の全て行程にわたっ
て他のガイドレールの搬入作業を行なうようになってい
る。
Thus, the work of carrying in the four guide rails 9 described above is completed. Thereafter, the same work procedure is repeated a plurality of times, so that the work of loading another guide rail is performed over the entire travel of the hoistway 1.

【0041】このように構成された本実施形態では、4
本のガイドレール9を並列に配置した状態で一括して昇
降路1内へ搬入できるので、全てのガイドレールを搬入
する作業時間を短縮でき、この搬入作業の効率向上を図
ることができる。
In the present embodiment configured as above, 4
Since the guide rails 9 can be collectively loaded into the hoistway 1 with the guide rails 9 arranged in parallel, the work time for loading all the guide rails can be shortened, and the efficiency of the loading work can be improved.

【0042】また、本実施形態では、ガイドレール9を
吊り上げながら昇降路1内へ搬入させる際、第2の揚重
機13の作動によりガイドレール9の下端部を昇降路1
内へ誘導し、その際に人力を必要としないので、作業者
の負担を軽減できるとともに、作業の安全性を向上させ
ることができる。
In the present embodiment, when the guide rail 9 is carried into the hoistway 1 while being lifted, the lower end of the guide rail 9 is moved by the operation of the second lifting machine 13.
Since it is guided to the inside and no human power is required at that time, the burden on the worker can be reduced and the safety of work can be improved.

【0043】なお、この第1の実施形態では、4本のガ
イドレール9を一括して昇降路1内へ搬入する場合を例
示したが、本発明はこれに限らず、他の本数のガイドレ
ールを昇降路1内へ搬入することができる。また、図9
に示すように、1本のガイドレール9を昇降路1内へ搬
入することもできる。この図9に示す吊り具11は、第
1の吊り具片11aと第2の吊り具片11bとでガイド
レール9の断面形状が最大寸法のものを挟圧可能に構成
したので、種々のガイドレールのサイズに対応でき、当
該搬入作業に使用する仮設材を少なくすることができ
る。さらに、図2に示す吊り具11も同様であり、第1
の吊り具片11aと第2の吊り具片11bとでガイドレ
ール9の断面形状が最大寸法のものを挟圧可能に構成し
てある。
Although the first embodiment has exemplified the case where the four guide rails 9 are collectively carried into the hoistway 1, the present invention is not limited to this, and other guide rails may be used. Can be carried into the hoistway 1. FIG.
As shown in (1), one guide rail 9 can be carried into the hoistway 1. In the hanging device 11 shown in FIG. 9, the first hanging member piece 11 a and the second hanging member piece 11 b are configured such that the guide rail 9 having a maximum cross-sectional shape can be pressed. It is possible to correspond to the size of the rail, and it is possible to reduce the number of temporary materials used for the carrying-in work. Further, the hanging tool 11 shown in FIG.
The guide rail 9 having a maximum cross-sectional shape can be pinched by the hanging piece 11a and the second hanging piece 11b.

【0044】図10は本発明の第2の実施形態に設けら
れる吊り具の斜視図である。なお、図10において前述
した図1〜図9に示すものと同等のものには同一符号を
付してある。
FIG. 10 is a perspective view of a hanger provided in the second embodiment of the present invention. In FIG. 10, the same components as those shown in FIGS. 1 to 9 described above are denoted by the same reference numerals.

【0045】図10に示す本実施形態では、前述した図
1〜図9に示すものと比べて、第1の吊り具片15aの
構成が異なっており、その他の構成は基本的に同様であ
る。すなわち、本実施形態の吊り具片15aでは、平板
部材15bの両端に、この平板部材15bの長手方向に
沿ってそれぞれ一対の長穴15cが形成されており、こ
の一対の長穴15cにボルト15dを介して略L字型部
材15eが移動可能に取り付けられている。これによっ
て、略L字型部材15eは、長穴15cの範囲において
調整可能な構造となっている。また、略L字型部材15
eには、第2の吊り具片11bの溝部11gに係合する
突起15fが設けられており、上述した第1の実施形態
と同様に、突起15fを回転軸として第2の吊り具片1
1bがガイドレール9の長手方向に回転可能に係合して
いる。
In the present embodiment shown in FIG. 10, the configuration of the first hanging piece 15a is different from that shown in FIGS. 1 to 9 described above, and the other configuration is basically the same. . That is, in the hanging member piece 15a of this embodiment, a pair of long holes 15c are formed at both ends of the flat plate member 15b along the longitudinal direction of the flat plate member 15b. A substantially L-shaped member 15e is movably mounted via the. Thereby, the substantially L-shaped member 15e has a structure that can be adjusted in the range of the elongated hole 15c. Further, the substantially L-shaped member 15
e is provided with a projection 15f that engages with the groove 11g of the second hanging piece 11b. As in the first embodiment described above, the second hanging piece 1
1b is rotatably engaged with the guide rail 9 in the longitudinal direction.

【0046】このように構成した第2の実施形態にあっ
ても、上述した第1の実施形態と同様の効果を得ること
ができる。さらに、この第2の実施形態では、略L字型
部材15eが平板部材15bの長手方向へ調整可能な構
造となっているので、並列に配置した複数本のガイドレ
ール9の全幅寸法に合わせて一対の略L字型部材15e
の間隔を調整することにより、前記のガイドレール9に
吊り具15を確実に係合させることができる。
In the second embodiment configured as described above, the same effects as in the first embodiment can be obtained. Further, in the second embodiment, since the substantially L-shaped member 15e has a structure that can be adjusted in the longitudinal direction of the flat plate member 15b, the substantially L-shaped member 15e is adjusted to the entire width of the plurality of guide rails 9 arranged in parallel. A pair of substantially L-shaped members 15e
By adjusting the distance between the two, the hanging member 15 can be reliably engaged with the guide rail 9.

【0047】図11は本発明の第3の実施形態に設けら
れる吊り具の斜視図である。なお、図11において前述
した図1〜図10に示すものと同等のものには同一符号
を付してある。
FIG. 11 is a perspective view of a hanger provided in the third embodiment of the present invention. In FIG. 11, the same components as those shown in FIGS. 1 to 10 are denoted by the same reference numerals.

【0048】図11に示す本実施形態では、前述した図
10に示すものと比べて、第2の吊り具片11bの連結
棒11hに、各ガイドレール9の摺動部9bを保護する
複数の保護部材16が設けられたことが異なっており、
その他の構成は基本的に同様である。保護部材16は、
連結棒11hが挿通されるとともに、ガイドレール9の
摺動部9bを受け入れる溝部16aが形成されており、
この溝部16aの深さ寸法は、ガイドレール9の摺動部
9bの高さ寸法より大きく設定されている。
In the present embodiment shown in FIG. 11, the connecting rod 11h of the second hanging piece 11b is provided with a plurality of protecting members 9b for protecting the sliding portions 9b of the guide rails 9 as compared with the embodiment shown in FIG. The difference is that the protection member 16 is provided,
Other configurations are basically the same. The protection member 16
The connecting rod 11h is inserted therethrough, and a groove 16a for receiving the sliding part 9b of the guide rail 9 is formed.
The depth of the groove 16a is set larger than the height of the sliding portion 9b of the guide rail 9.

【0049】この第3の実施形態にあっては、突起15
fを回転軸として第2の吊り具片11bがガイドレール
9の長手方向に回転した際、保護部材16の溝部16a
がガイドレール9の摺動部9bの側面を摺動した後、保
護部材16の先端がガイドレール9の底部に当接するこ
とにより、第1の吊り具片11aおよび第2の吊り具片
11bによりガイドレール9を挟圧する。
In the third embodiment, the protrusion 15
When the second hanging member piece 11b rotates in the longitudinal direction of the guide rail 9 about the rotation axis f, the groove 16a of the protection member 16 is formed.
After sliding on the side surface of the sliding portion 9b of the guide rail 9, the tip of the protection member 16 abuts on the bottom of the guide rail 9, so that the first suspending piece 11a and the second suspending piece 11b The guide rail 9 is clamped.

【0050】このように構成した第3の実施形態にあっ
ても、上述した第1の実施形態と同様の効果を得ること
ができる。さらに、この第3の実施形態にあっては、保
護部材16の先端がガイドレール9の底部に当接するこ
とにより、第1の吊り具片11aおよび第2の吊り具片
11bによりガイドレール9を挟圧するので、第2の吊
り具片11bの連結棒11hが直接ガイドレール9の摺
動部9bに当接することなくて済み、この摺動部9bの
損傷を防止できる。
The third embodiment configured as described above can provide the same effects as those of the first embodiment. Further, in the third embodiment, the tip of the protection member 16 abuts against the bottom of the guide rail 9, so that the guide rail 9 is moved by the first hanging piece 11a and the second hanging piece 11b. Since the pinching is performed, the connecting rod 11h of the second hanging piece 11b does not need to directly contact the sliding portion 9b of the guide rail 9, and damage to the sliding portion 9b can be prevented.

【0051】[0051]

【発明の効果】以上のように構成したので、本発明の請
求項1に係る発明によれば、ガイドレールの背面側に設
けられる第1の吊り具片が継ぎ目板の一端に当接すると
ともに、第1の吊り具片および第2の吊り具片でガイド
レールを挟圧してガイドレールを吊り上げるので、ガイ
ドレールのサイズに合わせて第1の吊り具片および第2
の吊り具片の位置関係を設定する必要がなくて済み、種
々のガイドレールのサイズに対応することができ、した
がって、ガイドレール搬入作業に用いる仮設材を少なく
できるという効果がある。
As described above, according to the first aspect of the present invention, the first hanging piece provided on the back side of the guide rail abuts one end of the joint plate, Since the guide rail is lifted by pressing the guide rail with the first hanging piece and the second hanging piece, the first hanging piece and the second hanging piece are adapted to the size of the guide rail.
There is no need to set the positional relationship of the hanging pieces, and it is possible to cope with various sizes of guide rails, and therefore, it is possible to reduce the number of temporary materials used for the guide rail loading operation.

【0052】また、本発明の請求項2に係る発明によれ
ば、並列に配置した複数本のガイドレールを吊り具によ
り内包して昇降路内に一括して搬入するので、全てのガ
イドレールを搬入する作業時間を短縮でき、したがっ
て、ガイドレール搬入作業の効率向上を図れるという効
果がある。
According to the invention of claim 2 of the present invention, a plurality of guide rails arranged in parallel are included in the hoist and collectively carried into the hoistway, so that all the guide rails are used. There is an effect that the work time for carrying in can be shortened, and thus the efficiency of the work for carrying in the guide rail can be improved.

【0053】また、本発明の請求項3に係る発明によれ
ば、一対の略L字型部材の間隔を任意に調整することに
より内包するガイドレールの本数を変えることができる
ため、より多くのガイドレールを一括して搬入でき、し
たがって、ガイドレール搬入作業の効率向上をさらに図
れるという効果がある。
According to the third aspect of the present invention, the number of guide rails to be included can be changed by arbitrarily adjusting the interval between the pair of substantially L-shaped members. There is an effect that the guide rails can be carried in collectively, so that the efficiency of the guide rail carrying work can be further improved.

【0054】また、本発明の請求項4に係る発明によれ
ば、吊り具で挟圧してガイドレールを吊り上げる際に保
護部材によりガイドレールの摺動部を保護するので、こ
の摺動部の損傷を防止でき、したがって、ガイドレール
搬入作業を円滑に行なえるという効果がある。
Further, according to the invention of claim 4 of the present invention, when the guide rail is lifted by being pressed by the suspender, the sliding part of the guide rail is protected by the protection member, so that the sliding part is damaged. Therefore, there is an effect that the guide rail carrying-in work can be performed smoothly.

【0055】また、本発明の請求項5に係る発明によれ
ば、ガイドレールの上端部を吊り上げて昇降路内に搬入
する際、傾斜調整手段でガイドレールの下端部を誘導で
きるので、ガイドレール搬入作業時に作業者の負担を軽
減でき、したがって、ガイドレール搬入作業の安全性を
向上できるという効果がある。
According to the fifth aspect of the present invention, the lower end of the guide rail can be guided by the inclination adjusting means when the upper end of the guide rail is lifted and carried into the hoistway. There is an effect that the burden on the worker during the loading operation can be reduced, and thus the safety of the loading operation of the guide rail can be improved.

【0056】また、本発明の請求項6に係る発明によれ
ば、昇降路の近傍の乗り場床で複数本のガイドレールを
並列に配置し、これらのガイドレールを吊り具により内
包して昇降路内に一括して搬入するので、全てのガイド
レールを搬入する作業時間を短縮でき、したがって、ガ
イドレール搬入作業の効率向上を図れるという効果があ
る。
Further, according to the invention of claim 6 of the present invention, a plurality of guide rails are arranged in parallel on the landing floor near the hoistway, and these guide rails are included in the hoistway by hanging. Since all the guide rails are transported collectively, the operation time for loading all the guide rails can be shortened, and therefore, the efficiency of the guide rail loading operation can be improved.

【0057】また、本発明の請求項7に係る発明によれ
ば、ガイドレールの上端部を吊り上げて昇降路内に搬入
する際、傾斜調整手段でガイドレールの下端部を誘導で
きるので、ガイドレール搬入作業時に作業者の負担を軽
減でき、ガイドレール搬入作業の安全性を向上できると
いう効果がある。
According to the seventh aspect of the present invention, the lower end of the guide rail can be guided by the inclination adjusting means when the upper end of the guide rail is lifted and carried into the hoistway. There is an effect that the burden on the worker can be reduced during the carrying-in work, and the safety of the guide rail carrying-in work can be improved.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の第1の実施形態に係るエレベータ用ガ
イドレールの搬入装置を説明する側面図である。
FIG. 1 is a side view illustrating an elevator guide rail loading device according to a first embodiment of the present invention.

【図2】図1の搬入装置に設けられる吊り具の斜視図で
ある。
FIG. 2 is a perspective view of a hanger provided in the carrying-in device of FIG. 1;

【図3】図1の搬入装置に設けられる連結具を説明する
斜視図である。
FIG. 3 is a perspective view illustrating a connecting member provided in the carrying-in device of FIG. 1;

【図4】吊り具をガイドレールに装着した状態を示す側
面図である。
FIG. 4 is a side view showing a state in which the hanging tool is mounted on a guide rail.

【図5】吊り具を継ぎ目板の一端に当接させた状態を示
す側面図である。
FIG. 5 is a side view showing a state in which the hanging tool is in contact with one end of a seam plate.

【図6】ガイドレールの吊り角度を調整する作業を説明
する側面図である。
FIG. 6 is a side view illustrating an operation of adjusting a hanging angle of a guide rail.

【図7】ガイドレールを昇降路の底部に仮置きした状態
を示す側面図である。
FIG. 7 is a side view showing a state where the guide rail is temporarily placed on the bottom of the hoistway.

【図8】本実施形態に係る搬入方法によりエレベータ用
ガイドレールを搬入する際の作業手順を示すフローチャ
ートである。
FIG. 8 is a flowchart showing a work procedure when loading an elevator guide rail by the loading method according to the present embodiment.

【図9】吊り具の変形例を示す斜視図である。FIG. 9 is a perspective view showing a modification of the hanging device.

【図10】本発明の第2の実施形態に設けられる吊り具
の斜視図である。
FIG. 10 is a perspective view of a hanger provided in a second embodiment of the present invention.

【図11】本発明の第3の実施形態に設けられる吊り具
の斜視図である。
FIG. 11 is a perspective view of a hanger provided in a third embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 昇降路 6 第1の揚重機(揚重機) 7 吊りロープ 9 ガイドレール 9a 背面 9b 摺動部 10 継ぎ目板 11 吊り具 11a 第1の吊り具片 11b 第2の吊り具片 11c 平板部材 11d 折曲部材 11e 突起 11g 溝部 11f 平板 11h 連結棒 12 連結ロープ 13 第2の揚重機 13a 牽引ロープ 14 連結具 15 吊り具 15a 第1の吊り具片 15b 平板部材 15c 長穴 15d ボルト 15e 略L字型部材 15f 突起 16 保護部材 16a 溝部 DESCRIPTION OF SYMBOLS 1 Hoistway 6 1st lifting machine (lifting machine) 7 Hanging rope 9 Guide rail 9a Back surface 9b Sliding part 10 Seam board 11 Hanging tool 11a 1st hanging tool piece 11b 2nd hanging tool piece 11c Plate member 11d Folding Curved member 11e Projection 11g Groove 11f Flat plate 11h Connecting rod 12 Connecting rope 13 Second lifting machine 13a Traction rope 14 Connecting tool 15 Hanging tool 15a First hanging tool piece 15b Flat member 15c Slot 15d Bolt 15e Substantially L-shaped member 15f Projection 16 Protection member 16a Groove

───────────────────────────────────────────────────── フロントページの続き (72)発明者 岩澤 和孝 東京都千代田区神田錦町1丁目6番地 株 式会社日立ビルシステム内 (72)発明者 向山 芳人 東京都千代田区神田錦町1丁目6番地 株 式会社日立ビルシステム内 Fターム(参考) 3F004 AA08 AC01 AD01 AE03 EA07 3F305 BD01 DA13  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Kazutaka Iwasawa 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo, Japan Inside the Hitachi Building System Co., Ltd. (72) Inventor Yoshito Mukaiyama 1-6-6 Kandanishikicho, Chiyoda-ku, Tokyo, Japan F term in Hitachi Building Systems, Ltd. (reference) 3F004 AA08 AC01 AD01 AE03 EA07 3F305 BD01 DA13

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 昇降路内に順次立設される複数本のガイ
ドレールと、これらのガイドレールのうち、上下方向に
隣接するもの同士を連結する継ぎ目板とを有するエレベ
ータであって、前記ガイドレールに摺動可能に係合する
吊り具を備え、前記ガイドレールの上端部の背面に前記
継ぎ目板を取り付けた状態で、前記ガイドレールを吊り
上げて前記昇降路内に搬入するエレベータ用ガイドレー
ルの搬入装置において、 前記吊り具が、前記ガイドレールの背面側に設けられ、
前記継ぎ目板の一端に当接する第1の吊り具片と、前記
ガイドレールの摺動部側に設けられ、前記第1の吊り具
片に対して前記ガイドレールの長手方向に回動可能に係
合する第2の吊り具片とを備えるとともに、これらの第
1の吊り具片および第2の吊り具片を、前記ガイドレー
ルの断面形状が最大寸法のものを挟圧可能に配置したこ
とを特徴とするエレベータ用ガイドレールの搬入装置。
1. An elevator comprising: a plurality of guide rails which are sequentially erected in a hoistway; and a seam plate which connects vertically adjacent ones of the guide rails. An elevator guide rail for lifting the guide rail and carrying it into the hoistway with the seam plate attached to the back surface of the upper end of the guide rail, comprising a suspender slidably engaged with the rail. In the carrying-in device, the hanging device is provided on a back side of the guide rail,
A first suspending piece that abuts one end of the seam plate; a first suspending piece that is provided on a sliding portion side of the guide rail and that is rotatable in the longitudinal direction of the guide rail with respect to the first suspending piece. And a second suspending piece that fits, and the first suspending piece and the second suspending piece are arranged such that the guide rail having a maximum cross-sectional shape can be pressed. Characteristic equipment for loading guide rails for elevators.
【請求項2】 前記第1の吊り具片および第2の吊り具
片は、前記ガイドレールの長手方向に対して直角な方向
に所定の長さを有し、かつ並列に配置した前記複数本の
ガイドレールを内包可能な構成であることを特徴とする
請求項1記載のエレベータ用ガイドレールの搬入装置。
2. A method according to claim 1, wherein the first hanging piece and the second hanging piece have a predetermined length in a direction perpendicular to a longitudinal direction of the guide rail and are arranged in parallel. 2. The elevator guide rail loading device according to claim 1, wherein the guide rail is configured to include the guide rail.
【請求項3】 前記第1の吊り具片は、前記ガイドレー
ルの背面側に配置される平板部材と、この平板部材の長
手方向の両端部に配置され、その長手方向の間隔が調整
可能な状態で固定される一対の略L字型部材とから構成
されたことを特徴とする請求項1記載のエレベータ用ガ
イドレールの搬入装置。
3. The first hanging member piece is disposed on a flat plate member disposed on the back side of the guide rail, and is disposed at both ends in the longitudinal direction of the flat plate member, and the longitudinal interval is adjustable. 2. The elevator guide rail loading device according to claim 1, comprising a pair of substantially L-shaped members fixed in a state.
【請求項4】 前記第2の吊り具片は、前記ガイドレー
ルの摺動部を保護する保護部材を備えたことを特徴とす
る請求項1記載のエレベータ用ガイドレールの搬入装
置。
4. The elevator guide rail loading device according to claim 1, wherein the second hanging piece has a protection member for protecting a sliding portion of the guide rail.
【請求項5】 昇降路内に順次立設される複数本のガイ
ドレールと、これらのガイドレールのうち、上下方向に
隣接するもの同士を連結する継ぎ目板とを有するエレベ
ータであって、前記ガイドレールに摺動可能に係合する
吊り具を備え、前記ガイドレールの上端部の背面に前記
継ぎ目板を取り付けた状態で、前記ガイドレールを吊り
上げて前記昇降路内に搬入するエレベータ用ガイドレー
ルの搬入装置において、 前記昇降路およびその近傍の一方に配置され、前記吊り
具を吊りロープを介して吊り上げる揚重機と、前記ガイ
ドレールの下端部に取り付けられる連結具と、この連結
具と前記吊りロープの先端部との間に設けられ、前記吊
り具にて前記ガイドレールの上端部を吊り上げた際、前
記ガイドレールの吊り角度を調整可能な傾斜調整手段と
を備え、 前記吊り具が、前記ガイドレールの背面側に設けられ、
前記継ぎ目板の一端に当接する第1の吊り具片と、前記
ガイドレールの摺動部側に設けられ、前記第1の吊り具
片に対して前記ガイドレールの長手方向に回動可能に係
合する第2の吊り具片とを備えるとともに、これらの第
1の吊り具片および第2の吊り具片を、前記ガイドレー
ルの断面形状が最大寸法のものを挟圧可能に配置したこ
とを特徴とするエレベータ用ガイドレールの搬入装置。
5. An elevator, comprising: a plurality of guide rails which are sequentially erected in a hoistway; and a seam plate which connects vertically adjacent ones of the guide rails. An elevator guide rail for lifting the guide rail and carrying it into the hoistway with the seam plate attached to the back surface of the upper end of the guide rail, comprising a suspender slidably engaged with the rail. In the carry-in device, a hoisting machine that is arranged on the hoistway and one of the vicinity thereof and hoists the hanging tool through a hanging rope, a connecting tool attached to a lower end of the guide rail, the connecting tool, and the hanging rope Tilt adjustment provided between the end of the guide rail and the hanging angle of the guide rail when the upper end of the guide rail is lifted by the hanging tool. And a stage, wherein the hanging member is provided on the back side of the guide rail,
A first suspending piece that abuts one end of the seam plate; a first suspending piece that is provided on a sliding portion side of the guide rail and that is rotatable in the longitudinal direction of the guide rail with respect to the first suspending piece. And a second suspending piece that fits, and the first suspending piece and the second suspending piece are arranged such that the guide rail having a maximum cross-sectional shape can be pressed. Characteristic equipment for loading guide rails for elevators.
【請求項6】 昇降路内に順次立設される複数本のガイ
ドレールと、これらのガイドレールのうち、上下方向に
隣接するもの同士を連結する継ぎ目板とを有するエレベ
ータであって、前記継ぎ目板を前記ガイドレールの上端
部に取り付けた状態で、前記ガイドレールを吊り上げて
前記昇降路内に搬入するエレベータ用ガイドレールの搬
入方法において、 前記昇降路の近傍の乗り場床に、前記継ぎ目板を取り付
けた前記複数本のガイドレールの上端部側を前記昇降路
に向けた状態で、これらのガイドレールを並列に配置し
て吊り具を摺動可能に係合させるとともに、この吊り具
で前記ガイドレールを内包した後、前記昇降路およびそ
の近傍の一方に配置した揚重機で前記吊り具を駆動する
ことにより、この吊り具で前記ガイドレールを挟圧する
とともに、前記吊り具を前記継ぎ目板の一端に当接させ
て、前記ガイドレールを一括して吊り上げて前記昇降路
内に搬入することを特徴とするエレベータ用ガイドレー
ルの搬入方法。
6. An elevator, comprising: a plurality of guide rails that are sequentially erected in a hoistway; and a seam plate that connects vertically adjacent ones of the guide rails. In a method of loading an elevator guide rail, which lifts the guide rail and loads the guide rail into the hoistway with the plate attached to the upper end of the guide rail, the joint plate is mounted on a landing floor near the hoistway. With the upper end sides of the plurality of attached guide rails facing the hoistway, these guide rails are arranged in parallel, and a suspender is slidably engaged with the guide rail. After the rail is included, the hoist is driven by a hoisting machine arranged on one of the hoistway and the vicinity thereof, so that the guide rail is pressed by the hoist. Both the hanging member is brought into contact with one end of the seam plate, carrying the method of the elevator guide rails, characterized by carrying on the hoistway by lifting collectively the guide rail.
【請求項7】 昇降路内に順次立設される複数本のガイ
ドレールと、これらのガイドレールのうち、上下方向に
隣接するもの同士を連結する継ぎ目板とを有するエレベ
ータであって、前記継ぎ目板を前記ガイドレールの上端
部に取り付けた状態で、前記ガイドレールを吊り上げて
前記昇降路内に搬入するエレベータ用ガイドレールの搬
入方法において、 前記ガイドレールに吊り具を摺動可能に係合させるとと
もに、この吊り具で前記ガイドレールを内包した後、前
記昇降路およびその近傍の一方に配置した揚重機で前記
吊り具を駆動することにより、この吊り具で前記ガイド
レールを挟圧するとともに、前記吊り具を前記継ぎ目板
の一端に当接させて前記ガイドレールの上端部を吊り上
げるとともに、このガイドレールの下端部に取り付けら
れる連結具と前記揚重機との間に角度調整手段を設け
て、前記揚重機による前記ガイドレールの上端部の吊り
上げに同期して前記角度調整手段で前記ガイドレールの
吊り角度を調整しながら、このガイドレールを鉛直な状
態に配置して前記昇降路内に搬入することを特徴とする
エレベータ用ガイドレールの搬入方法。
7. An elevator comprising: a plurality of guide rails which are sequentially erected in a hoistway; and a seam plate for connecting vertically adjacent ones of the guide rails. In a method of loading an elevator guide rail for lifting a guide rail and loading the guide rail into a hoistway with a plate attached to an upper end of the guide rail, a lifting tool is slidably engaged with the guide rail. Along with including the guide rail with the hanging tool, the lifting tool is driven by a hoisting machine disposed on one of the hoistway and the vicinity thereof, and the guide rail is pressed by the hanging tool, and A lifting tool is brought into contact with one end of the seam plate to lift the upper end of the guide rail, and is attached to the lower end of the guide rail. Providing an angle adjusting means between the connecting tool and the hoist, and adjusting the hanging angle of the guide rail by the angle adjusting means in synchronization with the lifting of the upper end of the guide rail by the hoisting machine. A method for carrying in an elevator guide rail, comprising arranging the guide rail in a vertical state and carrying the guide rail into the hoistway.
JP11225501A 1999-08-09 1999-08-09 Carry-in device for and method of elevator guide rail Pending JP2001048440A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11225501A JP2001048440A (en) 1999-08-09 1999-08-09 Carry-in device for and method of elevator guide rail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11225501A JP2001048440A (en) 1999-08-09 1999-08-09 Carry-in device for and method of elevator guide rail

Publications (1)

Publication Number Publication Date
JP2001048440A true JP2001048440A (en) 2001-02-20

Family

ID=16830318

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11225501A Pending JP2001048440A (en) 1999-08-09 1999-08-09 Carry-in device for and method of elevator guide rail

Country Status (1)

Country Link
JP (1) JP2001048440A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003292265A (en) * 2002-03-29 2003-10-15 Toshiba Elevator Co Ltd Elevator installing scaffolding
EP2993153A1 (en) * 2014-09-03 2016-03-09 Kone Corporation Guide rail installation arrangement and a method for installing guide rails
CN105668408A (en) * 2014-12-08 2016-06-15 株式会社日立大厦*** Suspension clamp for elevator guide rail
KR101805425B1 (en) 2015-12-22 2017-12-07 현대엘리베이터 주식회사 Hook, mobile for a package of rail installation method

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003292265A (en) * 2002-03-29 2003-10-15 Toshiba Elevator Co Ltd Elevator installing scaffolding
EP2993153A1 (en) * 2014-09-03 2016-03-09 Kone Corporation Guide rail installation arrangement and a method for installing guide rails
US9592997B2 (en) 2014-09-03 2017-03-14 Kone Corporation Guide rail installation arrangement and a method for installing guide rails
CN105668408A (en) * 2014-12-08 2016-06-15 株式会社日立大厦*** Suspension clamp for elevator guide rail
JP2016108115A (en) * 2014-12-08 2016-06-20 株式会社日立ビルシステム Elevator guide rail suspension fixture
KR101805425B1 (en) 2015-12-22 2017-12-07 현대엘리베이터 주식회사 Hook, mobile for a package of rail installation method

Similar Documents

Publication Publication Date Title
EP0904247B1 (en) Procedure and apparatus for the installation of an elevator
CA2002158A1 (en) Elevator erection system using pit storage and roof hoist
CN109153539B (en) Elevator traction machine installation method
JP4828084B2 (en) How to install the hoist
JP2001048440A (en) Carry-in device for and method of elevator guide rail
CN1833981B (en) Elevator system
JP2000344445A (en) Method and device for loading elevator counterweight
JP3074373B2 (en) Clamping and lifting device
US3893219A (en) Apparatus and method for suspending elevator guide rails
JPH08245116A (en) Installation engineering of elevator
JP6382391B1 (en) Elevator counterweight frame reinforcement support device and elevator balance weight frame reinforcement mounting method
JPH08133636A (en) Temporary machine room for jump-up elevator
JP2809520B2 (en) Lifting device for elevator guide rails
JPH09278325A (en) Construction work elevator lifting method and construction work elevator device
JPH05319729A (en) Attaching work device of guide rail of elevator and attaching work method of guide rail using that device
JPH082850A (en) Work method in elevator shaft
CN112533857A (en) Counterweight block of elevator and moving method thereof
JPS6054231B2 (en) Elevator installation equipment
JP6882082B2 (en) Lifting support device in the hoistway of the elevator
JPH10218560A (en) Transportable lift
JP2862063B2 (en) How to extend the lift of a construction elevator
JPH0388685A (en) Method for vertically providing guide rail of elevator
JPH04121384A (en) Method for setting up elevator
JP2001316057A (en) Method and device for weight lifting in elevator
JP2023128271A (en) construction elevator