JP2000290968A - Method for placing dam concrete and placing plant for use therein - Google Patents

Method for placing dam concrete and placing plant for use therein

Info

Publication number
JP2000290968A
JP2000290968A JP11103262A JP10326299A JP2000290968A JP 2000290968 A JP2000290968 A JP 2000290968A JP 11103262 A JP11103262 A JP 11103262A JP 10326299 A JP10326299 A JP 10326299A JP 2000290968 A JP2000290968 A JP 2000290968A
Authority
JP
Japan
Prior art keywords
mortar
ready
concrete
mixed concrete
placing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP11103262A
Other languages
Japanese (ja)
Other versions
JP4022572B2 (en
Inventor
Ryoji Fukamitsu
良治 深光
Masahiro Jokyo
正弘 乘京
Tetsuya Tsurumi
哲也 鶴見
Ryuzo Yamada
隆三 山田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SEIA KK
Tobishima Corp
Original Assignee
SEIA KK
Tobishima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SEIA KK, Tobishima Corp filed Critical SEIA KK
Priority to JP10326299A priority Critical patent/JP4022572B2/en
Publication of JP2000290968A publication Critical patent/JP2000290968A/en
Application granted granted Critical
Publication of JP4022572B2 publication Critical patent/JP4022572B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Air Transport Of Granular Materials (AREA)

Abstract

PROBLEM TO BE SOLVED: To efficiently transport both ready-mixed concrete and mortar on a belt conveyor, to effectively prevent the mortar from clinging to the belt conveyor, and to efficiently manufacture ready-mixed concrete in a ready-mixed concrete production facility. SOLUTION: This method for placing dam concrete transports ready-mixed concrete manufactured in a ready-mixed concrete production facility 1 to a dam concrete placement site from the ready-mixed concrete production facility 1 on a belt conveyor 2. The method for placing the dam concrete uses the belt conveyor 2 for transporting the ready-mixed concrete and transports mortar material from a storage site to the dam concrete placing site without adding water to the mortar material. The mortar material transported is placed in a placing part at the dam concrete placing site with water added to the mortar material for kneading.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明はダムコンクリートを
打設する方法と、この方法に使用する打設プラントに関
する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of casting dam concrete and a casting plant used in the method.

【0002】[0002]

【従来の技術】ダムコンクリートは、モルタルを打設し
てその上に生コンクリートを打設する。モルタルは、先
に打設したコンクリートと、その上に打設されるコンク
リートとを一体的に結合する。ダムを構築するコンクリ
ートは、極めて広い面積に生コンクリートを打設する。
このため、全面に一緒に生コンクリートを打設できな
い。広い面積を複数の領域に区分し、区分された領域
に、次々と生コンクリートを打設して構築される。生コ
ンクリートを打設する領域には、先にモルタルを打設す
る。打設されたモルタルは、約1時間経過すると凝結を
起こし、硬化した状態での強度が低下し、品質上問題と
なる。このため、生コンクリートを打設する区分された
領域には、生コンクリートを打設する前に、厚さ2cm
で1回当り約3m程度の量のモルタルを、1時間間隔
で打設している。このように、ダムコンクリートは、モ
ルタル打設と生コンクリート打設とを繰り返しながら、
広い面積のコンクリートを構築している。
2. Description of the Related Art For dam concrete, mortar is cast and raw concrete is cast thereon. The mortar unites the concrete cast first and the concrete cast thereon. The concrete used to construct the dam is to be poured over a very large area.
For this reason, ready-mixed concrete cannot be poured over the entire surface. The large area is divided into a plurality of areas, and ready-mixed concrete is poured into the divided areas one after another. Mortar is cast first in the area where the ready-mixed concrete is cast. The cast mortar sets after about one hour, and the strength in a hardened state is reduced, which is a problem in quality. For this reason, in the area where the ready-mixed concrete is to be cast, a thickness of 2 cm is set before placing the ready-mixed concrete.
Mortar in an amount of about 3 m 3 per time is cast at hourly intervals. In this way, dam concrete repeats mortar casting and fresh concrete casting,
We are building a large area of concrete.

【0003】さらに、生コンクリートは、1回に打設で
きる厚さが約1.5m以下に制限される。これよりも厚
くすると、硬化するときの熱でコンクリートが加熱され
て、硬化状態における強度が低下し、あるいはクラック
が発生する原因となるからである。このため、生コンク
リートは、1回に例えば約75cmの厚さに打設され
る。ダムコンクリートは、1回に75cmの厚さで、複
数の領域に区分して生コンクリートを打設するので、頻
繁にモルタル打設と生コンクリート打設とを繰り返して
構築することになる。
Further, the thickness of ready-mixed concrete that can be cast at one time is limited to about 1.5 m or less. If the thickness is greater than this, the concrete is heated by the heat at the time of hardening, which causes the strength in the hardened state to decrease or causes cracks to occur. For this reason, the ready-mixed concrete is cast at a time, for example, to a thickness of about 75 cm. Dam concrete is 75 cm in thickness at a time, and is divided into a plurality of areas, and fresh concrete is cast. Therefore, mortar casting and fresh concrete casting are frequently repeated.

【0004】ダムコンクリートに打設する生コンクリー
トとモルタルは、生コン生産設備で製造される。生コン
生産設備は大がかりなプラントであるために、ダムコン
クリートの打設場所から離れて設置される。生コン生産
設備で製造された生コンクリートとモルタルは、ベルト
コンベアを使用して、打設場所に輸送される。
[0004] Ready-mixed concrete and mortar to be poured into dam concrete are manufactured by ready-mixed concrete production equipment. Because the ready-mixed concrete production equipment is a large-scale plant, it is installed away from the place where dam concrete is poured. The ready-mixed concrete and mortar produced in the ready-mixed concrete production facility are transported to the casting site using a belt conveyor.

【0005】[0005]

【発明が解決しようとする課題】ベルトコンベアで、生
コンクリートとモルタルの両方を輸送するプラントは、
生コンクリートとモルタルを切り換えて交互に輸送す
る。このプラントは、生コンクリートを輸送するベルト
コンベアをモルタルの輸送に併用する。ベルトコンベア
は、生コンクリートの輸送を一時的に中断して、モルタ
ルを輸送する。ダムコンクリートの打設において、たと
えば、モルタルは1時間に1回の割合で輸送される。こ
のため、モルタルの運搬及び打設による待ち時間の発生
によって、生コンクリートの打設能力が低下しているの
が実状である。
A plant that transports both ready-mixed concrete and mortar on a belt conveyor is:
Switch between ready-mixed concrete and mortar and transport them alternately. This plant uses a belt conveyor that transports ready-mixed concrete together with mortar. The belt conveyor temporarily suspends the transportation of ready-mixed concrete and transports the mortar. In pouring dam concrete, for example, mortar is transported once an hour. For this reason, the actual situation is that the capacity for placing ready-mixed concrete is reduced due to the occurrence of waiting time due to the transportation and placement of the mortar.

【0006】さらに、このプラントは、モルタルを速や
かに運搬するのが難しい。それは、モルタルを生コンク
リートと同じ速度で輸送すると、モルタルがベルトコン
ベアから漏れやすいからである。とくに、モルタルは輸
送路が曲がっている部分で、ベルトコンベアから漏れや
すい。それは、モルタルが生コンクリートに比較して流
動しやすいからである。モルタルは、通常の生コンクリ
ートは言うに及ばず、ダムコンクリートに使用される超
硬練りの生コンクリートに比較すると、極めて流動しや
すく、ベルトコンベアから漏れやすい欠点がある。この
ため、モルタルと生コンクリートの両方を輸送するベル
トコンベアは、速度を相当に遅くする必要があり、生コ
ンクリートとモルタルの両方を能率よく輸送できなくな
る欠点がある。
[0006] Furthermore, this plant has difficulty in transporting mortar quickly. This is because if the mortar is transported at the same speed as the ready-mixed concrete, the mortar is likely to leak from the belt conveyor. In particular, mortar is likely to leak from the belt conveyor where the transport path is bent. This is because mortar is easier to flow than ready-mixed concrete. The mortar has the drawback that it is extremely easy to flow and leaks easily from the belt conveyor as compared with the super-hardened ready-mixed concrete used for dam concrete, not to mention ordinary ready-mixed concrete. For this reason, the speed of the belt conveyor for transporting both mortar and ready-mixed concrete needs to be considerably reduced, and there is a disadvantage that both the ready-mixed concrete and mortar cannot be transported efficiently.

【0007】さらに、生コンクリートを輸送するベルト
コンベアでモルタルを輸送すると、ベルトやローラーに
モルタルが付着する弊害もある。付着したモルタルは硬
化して、簡単に除去できず、清掃に極めて手間がかかる
欠点もある。
Further, when mortar is transported by a belt conveyor for transporting ready-mixed concrete, there is a problem that mortar adheres to belts and rollers. The adhered mortar hardens, cannot be easily removed, and has a disadvantage that cleaning is extremely troublesome.

【0008】さらにまた、生コンクリートとモルタルの
両方を製造する生コン生産設備は、モルタルと生コンク
リートとを交互に混練して製造するので、水や骨材の混
合比を切り換えるときに、水や骨材の混合率を正確に設
計値とするのが難しい欠点もある。また、生コンクリー
トとモルタルとを切り換えて製造するために、切り換え
に時間がかかって、全体の製造能率が低下する欠点もあ
る。
Furthermore, a ready-mixed concrete production facility for manufacturing both ready-mixed concrete and mortar alternately kneads and manufactures mortar and ready-mixed concrete. There is also a disadvantage that it is difficult to accurately set the mixing ratio of the materials to the design value. In addition, there is a disadvantage that since the production is performed by switching between the ready-mixed concrete and the mortar, the switching takes a long time, and the overall production efficiency is reduced.

【0009】本発明は、このような欠点を解決すること
を目的に開発されたものである。本発明の重要な目的
は、生コンクリートとモルタルの両方をベルトコンベア
で能率よく輸送できると共に、モルタルがベルトコンベ
アに付着するのを有効に防止でき、さらに生コン生産設
備で能率よく生コンクリートを製造できるダムコンクリ
ートの打設方法とこの打設方法に使用する打設プラント
を提供することにある。
[0009] The present invention has been developed for the purpose of solving such a drawback. An important object of the present invention is that both ready-mixed concrete and mortar can be efficiently transported by a belt conveyor, mortar can be effectively prevented from adhering to the belt conveyor, and ready-mixed concrete can be efficiently produced by ready-mixed concrete production equipment. An object of the present invention is to provide a method of placing dam concrete and a casting plant used for the method.

【0010】[0010]

【課題を解決するための手段】本発明のダムコンクリー
トの打設方法は、生コン生産設備1で製造された生コン
クリートを、ベルトコンベア2でもって、生コン生産設
備1からダムコンクリートを打設する場所まで輸送す
る。さらに、ダムコンクリートの打設方法は、生コンク
リートを輸送するベルトコンベア2を使用して、モルタ
ル材料を水を添加しない状態として、貯溜場所からダム
コンクリートの打設場所まで輸送する。水を添加しない
状態のモルタル材料とは、完全に水分を含まない状態の
みでなく、骨材に含有される水分によって、打設場所に
輸送されてから、モルタルとして混練するまでに硬化し
ない状態を含む広い意味に使用する。砂等の細骨材は、
多少の水分を含んでいるが、水分含有量が少ないと、含
有水分によってセメントが硬化することはない。
According to the present invention, there is provided a method of placing dam concrete, wherein the ready-mixed concrete produced in the ready-mixed concrete production facility 1 is placed on the belt conveyor 2 where the concrete is poured from the ready-mixed concrete production facility 1. To transport. Further, in the dam concrete placing method, the mortar material is transported from the storage location to the dam concrete placing location without using water by using the belt conveyor 2 for transporting the ready-mixed concrete. The mortar material to which water is not added means not only a state that does not completely contain water, but also a state that does not harden until it is transported to the casting place by the water contained in the aggregate and kneaded as mortar. Use in a broad sense, including: Fine aggregate such as sand
Although it contains some water, if the water content is low, the cement does not harden due to the water content.

【0011】水を添加しないモルタル材料は、骨材とセ
メントを混合した状態、あるいは混合しないで別々に打
設場所に輸送する。ダムコンクリートの打設場所に輸送
されたモルタル材料は、ここで水を添加して混練して打
設部分に打設する。
[0011] The mortar material to which water is not added is transported to a casting site separately with or without mixing the aggregate and the cement. The mortar material transported to the dam concrete placement site is added with water and kneaded to be poured into the placement site.

【0012】本発明の請求項2のダムコンクリートの打
設方法は、ベルトコンベア2でダムコンクリートの打設
場所に移送された水を添加しないモルタル材料を、打設
場所に設けた貯溜タンク7に蓄える。水を添加しないモ
ルタル材料は、骨材とセメントを混合した状態、あるい
は混合しない状態で貯溜タンク7に蓄える。モルタルを
使用するときに、モルタル材料を貯溜タンク7から取り
出して水を添加して混練して打設する。
According to a second aspect of the present invention, there is provided a dam concrete placing method, wherein the water-free mortar material transferred to the dam concrete placing place by the belt conveyor 2 is stored in the storage tank 7 provided at the placing place. store. The mortar material to which water is not added is stored in the storage tank 7 in a state where the aggregate and the cement are mixed or not mixed. When using the mortar, the mortar material is taken out of the storage tank 7, water is added, kneaded and poured.

【0013】本発明の請求項3のダムコンクリートの打
設方法は、水を添加しないモルタル材料を、空練り状態
で貯溜場所から打設場所まで移送している。空練り状態
とは、モルタル材料である細骨材とセメントを、水を添
加することなく混合した状態である。細骨材とセメント
は、あらかじめ計量して所定の混合比に空練りされて移
送される。移送された空練り状態のモルタル材料は、打
設場所で水を添加して混練して打設する。
According to a third aspect of the present invention, a mortar material to which water is not added is transferred from a storage location to a placement location in an empty kneaded state. The dry kneading state is a state in which fine aggregate and mortar material and cement are mixed without adding water. The fine aggregate and the cement are measured in advance, kneaded at a predetermined mixing ratio, and transferred. The transferred mortar material in the empty kneaded state is kneaded by adding water at the casting site and then poured.

【0014】本発明のダムコンクリートの打設プラント
は、生コン生産設備1で製造された生コンクリートをダ
ムコンクリートの打設場所まで輸送するベルトコンベア
2を備える。さらに、ダムコンクリートの打設プラント
は、生コンクリートを輸送するベルトコンベア2を、モ
ルタル材料を水を添加しない状態で貯溜場所からダムコ
ンクリートの打設場所まで輸送する搬送手段に併用す
る。また、ダムコンクリートの打設場所には、水を添加
していないモルタル材料に水を添加して混練するモルタ
ル生産設備3を設けている。このモルタル生産設備3を
使用して、ベルトコンベア2で輸送されたモルタル材料
に水を添加してモルタルを製造して打設する。
The dam concrete casting plant of the present invention is provided with a belt conveyor 2 for transporting ready-mixed concrete produced by the ready-mixed concrete production facility 1 to a dam concrete placement site. Further, the dam concrete placing plant uses the belt conveyor 2 for transporting the ready-mixed concrete together with a transport means for transporting the mortar material from the storage location to the dam concrete placing location without adding water. In addition, a mortar production facility 3 for adding water to a mortar material to which water is not added and kneading the mortar material is provided at the dam concrete placement site. Using this mortar production equipment 3, water is added to the mortar material transported by the belt conveyor 2 to produce mortar and place it.

【0015】本発明の請求項5のダムコンクリートの打
設プラントは、モルタル生産設備3を、貯溜タンク7と
モルタルミキサー8とを搭載する自動車としている。
In the dam concrete casting plant according to a fifth aspect of the present invention, the mortar production facility 3 is an automobile equipped with a storage tank 7 and a mortar mixer 8.

【0016】本発明の請求項6のダムコンクリートの打
設プラントは、水を添加しないモルタル材料を、空練り
状態で貯溜場所から打設場所まで移送している。細骨材
とセメントは、所定の混合比に空練りされてベルトコン
ベア2で移送される。移送された空練り状態のモルタル
材料は、打設場所で水を添加して混練して打設する。
In the dam concrete casting plant according to claim 6 of the present invention, the mortar material to which water is not added is transferred from the storage location to the casting location in an empty kneaded state. The fine aggregate and the cement are kneaded at a predetermined mixing ratio and transferred by the belt conveyor 2. The transferred mortar material in the empty kneaded state is kneaded by adding water at the casting site and then poured.

【0017】本発明の請求項7のダムコンクリートの打
設プラントは、モルタル生産設備3が、セメントと細骨
材とを別々に貯溜する貯溜タンク7を備える。ベルトコ
ンベア2は、細骨材とセメントとを別々に輸送する。細
骨材とセメントとを別々に打設場所に輸送して、別々の
貯溜タンク7に蓄えるプラントは、水分含有量の多い細
骨材を打設場所に輸送して貯蔵できる。生コンクリート
を生産するまで、細骨材がセメントに混合されないから
である。
In the dam concrete casting plant according to a seventh aspect of the present invention, the mortar production facility 3 includes a storage tank 7 for storing cement and fine aggregate separately. The belt conveyor 2 transports fine aggregate and cement separately. A plant that separately transports fine aggregate and cement to a casting site and stores them in separate storage tanks 7 can transport and store fine aggregate having a high water content to the casting site. This is because fine aggregate is not mixed with cement until ready-mixed concrete is produced.

【0018】[0018]

【発明の実施の形態】以下、本発明の実施例を図面に基
づいて説明する。ただし、以下に示す実施例は、本発明
の技術思想を具体化するためのダムコンクリートの打設
方法と打設プラントを例示するものであって、本発明は
ダムコンクリートの打設方法と打設プラントを下記のも
のに特定しない。
Embodiments of the present invention will be described below with reference to the drawings. However, the following examples illustrate a dam concrete placing method and a casting plant for embodying the technical idea of the present invention, and the present invention relates to a dam concrete placing method and a placing method. Do not specify the plant as:

【0019】さらに、この明細書は、特許請求の範囲を
理解し易いように、実施例に示される部材に対応する番
号を、「特許請求の範囲の欄」、および「課題を解決す
るための手段の欄」に示される部材に付記している。た
だ、特許請求の範囲に示される部材を、実施例の部材に
特定するものでは決してない。
Further, in this specification, in order to make it easier to understand the claims, the numbers corresponding to the members shown in the embodiments will be referred to as “claims” and “ In the column of “means”. However, the members described in the claims are not limited to the members of the embodiments.

【0020】図1に示すダムコンクリートの打設プラン
トは、生コン生産設備1で生産された生コンクリートを
打設場所に輸送するベルトコンベア2と、打設場所に設
けられるモルタル生産設備3とを備える。
The dam concrete casting plant shown in FIG. 1 includes a belt conveyor 2 for transporting ready-mixed concrete produced by the ready-mixed concrete production facility 1 to a casting location, and a mortar production facility 3 provided at the casting location. .

【0021】生コン生産設備1は、セメントと骨材に水
を添加して混練して生コンクリートを生産する。生コン
生産設備1は、生コンクリートの打設場所から離れた場
所に設置される。生コン生産設備1は、大がかりな設備
であるので、ダムコンクリートの打設場所には設置され
ず、打設場所から離れた場所に設置して、ここで生産さ
れた生コンクリートを打設場所に輸送する。
The ready-mixed concrete production facility 1 produces ready-mixed concrete by adding and kneading water to cement and aggregate. The ready-mixed concrete production equipment 1 is installed at a location away from the place where the ready-mixed concrete is poured. Since the ready-mixed concrete production equipment 1 is a large-scale facility, the ready-mixed concrete production equipment 1 is not installed at the dam concrete placement site, but is installed at a location away from the placement site, and the ready-mixed concrete produced here is transported to the placement site. I do.

【0022】生コン生産設備1は、骨材とセメントの貯
蔵タンク4と、貯蔵タンク4から取り出した骨材とセメ
ントを計量する計量器5と、計量器5で計量された骨材
とセメントに、定量の水を添加して混練するミキサー6
とを備えている。貯蔵タンク4は、生コンクリート用の
骨材と、モルタル用の細骨材とを別々に蓄えている。
The ready-mixed concrete production equipment 1 includes a storage tank 4 for aggregate and cement, a measuring device 5 for measuring the aggregate and cement taken out from the storage tank 4, an aggregate and cement measured by the measuring device 5, Mixer 6 to which a certain amount of water is added and kneaded
And The storage tank 4 separately stores aggregate for ready-mixed concrete and fine aggregate for mortar.

【0023】図1に示す生コン生産設備1は、骨材とセ
メントの貯蔵タンク4を備えているが、骨材の貯蔵タン
クは、生コン生産設備とは別の場所に設置することもで
きる。骨材の貯蔵タンクを別の場所に設置するプラント
は、骨材をベルトコンベアで生コン生産設備に輸送す
る。
Although the ready-mixed concrete production equipment 1 shown in FIG. 1 has a storage tank 4 for aggregate and cement, the storage tank for aggregates can be installed in a different place from the ready-mixed concrete production equipment. Plants that install aggregate storage tanks in other locations transport the aggregates to ready-mix production facilities on a belt conveyor.

【0024】さらに、生コン生産設備1は、貯蔵タンク
4に蓄えている骨材やセメントを計量器5に輸送するた
めのコンベア(図示せず)を備えている。コンベアは、
生コンクリートを生産するときに、骨材とセメントを貯
蔵タンク4から計量器5に輸送する。モルタル材料を打
設場所に輸送するとき、コンベアは、細骨材とセメント
を、ミキサー6に供給することなくベルトコンベア2に
供給する。ただし、細骨材とセメントを混合した空練り
状態のモルタル材料として、打設場所に輸送するプラン
トは、貯蔵タンク4の細骨材とセメントを、ミキサー6
に輸送する。
Further, the ready-mixed concrete production facility 1 is provided with a conveyor (not shown) for transporting aggregate and cement stored in the storage tank 4 to the measuring device 5. The conveyor is
When producing ready-mixed concrete, aggregate and cement are transported from the storage tank 4 to the measuring device 5. When transporting the mortar material to the casting site, the conveyor supplies the fine aggregate and the cement to the belt conveyor 2 without supplying them to the mixer 6. However, the plant that transports the fine aggregate and cement in the storage tank 4 to the casting site as an empty kneaded mortar material in which the fine aggregate and cement are mixed is mixed with the mixer 6.
Transport to

【0025】ベルトコンベア2は、生コン生産設備1で
生産された生コンクリートと、貯蔵タンク4に蓄えてい
る細骨材及びセメントを、別々に切り換えて、ダムコン
クリートの打設場所に輸送する。生コンクリートを輸送
するときは、細骨材およびセメントは輸送せず、細骨材
及びセメントを輸送するときは、生コンクリートを輸送
しない。ベルトコンベア2は、生コン生産設備1から打
設場所まで延長して設置される。貯蔵タンク4を生コン
生産設備1とは別の場所に設置するプラントは、生コン
生産設備1から打設場所に延長されるベルトコンベア2
に、貯蔵タンク4に連結しているベルトコンベア2を連
結する。
The belt conveyor 2 transports the ready-mixed concrete produced by the ready-mixed concrete production facility 1 and the fine aggregate and cement stored in the storage tank 4 separately to a dam concrete placing site. When transporting ready-mixed concrete, fine aggregate and cement are not transported, and when transporting fine aggregate and cement, fresh concrete is not transported. The belt conveyor 2 is installed so as to extend from the ready-mixed concrete production facility 1 to a casting place. The plant in which the storage tank 4 is installed at a place different from the ready-mixed concrete production facility 1 is a belt conveyor 2 that is extended from the ready-mixed concrete production facility 1 to a casting place.
Then, the belt conveyor 2 connected to the storage tank 4 is connected.

【0026】ベルトコンベア2は、先端部を打設場所ま
で延長している。ベルトコンベア2で打設場所に輸送さ
れた生コンクリートは、直接に打設部分に供給され、あ
るいは、打設場所を走行する生コン車に供給される。生
コン車は、供給された生コンクリートを打設する正確な
位置に輸送する。ベルトコンベア2の先端に移動できる
ベルトコンベア2を連結して、生コンクリートを打設場
所の正確な位置に供給することもできる。
The belt conveyor 2 has a leading end extending to a casting location. The ready-mixed concrete transported to the placing site by the belt conveyor 2 is directly supplied to the placing portion, or supplied to a ready-mixed vehicle traveling in the placing site. The ready-mixed truck transports the supplied ready-mixed concrete to the exact location where it will be cast. It is also possible to connect the movable belt conveyor 2 to the tip of the belt conveyor 2 and supply the ready-mixed concrete to an accurate position of the casting place.

【0027】さらに、ベルトコンベア2で輸送された水
を添加しないモルタル材料は、モルタル生産設備3に供
給される。図2に示すモルタル生産設備3は、細骨材お
よびセメントを蓄える貯溜タンク7と、細骨材およびセ
メントに水を添加して混練するモルタルミキサー8とを
搭載する自動車である。この図のモルタル生産設備3
は、細骨材とセメントとを別々に蓄える貯溜タンク7を
備えており、さらに、細骨材とセメントを計量してモル
タルミキサー8に供給するために、計量器9も搭載して
いる。この図のモルタル生産設備3は、ベルトコンベア
2で細骨材とセメントを別々に輸送して、貯溜タンク7
に蓄える。貯溜タンク7に細骨材とセメントを供給する
とき、モルタル生産設備3はベルトコンベア2の端部に
移動する。いいかえると、ベルトコンベア2から供給さ
れる細骨材とセメントが、貯溜タンク7に供給される位
置まで移動する。
Further, the mortar material to which water is not added, which is transported by the belt conveyor 2, is supplied to the mortar production equipment 3. The mortar production facility 3 shown in FIG. 2 is an automobile equipped with a storage tank 7 for storing fine aggregate and cement, and a mortar mixer 8 for adding and kneading water to fine aggregate and cement. Mortar production equipment 3 in this figure
Has a storage tank 7 for separately storing fine aggregate and cement, and further has a measuring device 9 for measuring the fine aggregate and cement and supplying them to the mortar mixer 8. The mortar production equipment 3 of this figure transports fine aggregate and cement separately by the belt conveyor 2 and
To store. When supplying fine aggregate and cement to the storage tank 7, the mortar production equipment 3 moves to the end of the belt conveyor 2. In other words, the fine aggregate and the cement supplied from the belt conveyor 2 move to a position where they are supplied to the storage tank 7.

【0028】図3に示すモルタル生産設備3は、細骨材
とセメントとを混合した状態で蓄える貯溜タンク7を備
えている。このモルタル生産設備3は、水を添加しない
空練り状態で混合された細骨材とセメントであって、ベ
ルトコンベア2でもって輸送されたモルタル材料を貯溜
タンク7に蓄える。貯溜タンク7に蓄えられる細骨材と
セメントは、生コン生産設備1であらかじめ計量して決
められた混合比に混合している。したがって、貯溜タン
ク7に蓄える細骨材およびセメントは、計量器で計量す
ることなく、モルタルミキサー8に供給してモルタルを
生産できる。
The mortar production facility 3 shown in FIG. 3 includes a storage tank 7 for storing fine aggregate and cement in a mixed state. The mortar production equipment 3 stores the mortar material, which is the fine aggregate and cement mixed in an empty kneaded state without adding water, and which is transported by the belt conveyor 2, in the storage tank 7. The fine aggregate and the cement stored in the storage tank 7 are mixed at a mixing ratio determined in advance by the ready-mixed concrete production facility 1. Therefore, the fine aggregate and cement stored in the storage tank 7 can be supplied to the mortar mixer 8 to produce mortar without being measured by a measuring instrument.

【0029】さらに、図示しないが、モルタル生産設備
は、貯溜タンクとモルタルミキサーを、別々に分離した
構造とすることもできる。このモルタル生産設備は、好
ましくは、モルタルミキサーを自動車に搭載して、貯溜
タンクを自走しない構造とする。ただし、この構造のモ
ルタル生産設備は、貯溜タンクとモルタルミキサーの両
方を自走しない構造とし、あるいはまた、貯溜タンクと
モルタルミキサーの両方を自走する構造とすることもで
きる。
Further, although not shown, the mortar production equipment may have a structure in which the storage tank and the mortar mixer are separately separated. This mortar production facility preferably has a structure in which a mortar mixer is mounted on an automobile and the storage tank does not run by itself. However, the mortar production equipment having this structure may be configured so that both the storage tank and the mortar mixer do not run by themselves, or alternatively, may be configured to run both the storage tank and the mortar mixer.

【0030】この構造の打設プラントは、以下の工程
で、ダムコンクリートの打設場所に生コンクリートとモ
ルタル材料とを輸送して、モルタルと生コンクリートと
を打設する。 [水を添加しないモルタル材料を輸送する工程]ベルト
コンベア2が生コンクリートを輸送しない空き時間を利
用して、生コンクリートを輸送するベルトコンベア2
で、水を添加しない細骨材とセメントからなるモルタル
材料を打設場所に輸送する。モルタル材料は、打設場所
から離れた場所に設置している生コン生産設備1から打
設場所に輸送する。また、モルタル材料は、生コン生産
設備の近傍に設けた貯溜タンクから打設場所に輸送する
こともある。モルタル材料である細骨材とセメントは、
決められた割合で混合した状態で輸送し、あるいは、混
合することなく別々に輸送する。
In the casting plant having this structure, the ready-mixed concrete and the mortar material are transported to the dam concrete placement site and the mortar and the ready-mixed concrete are cast in the following steps. [Step of transporting mortar material to which water is not added] Belt conveyor 2 that transports ready-mixed concrete using the free time when belt conveyor 2 does not transport ready-mixed concrete
Then, the mortar material composed of fine aggregate and cement to which water is not added is transported to the casting site. The mortar material is transported from the ready-mixed concrete production facility 1 installed at a location remote from the casting location to the casting location. Further, the mortar material may be transported from a storage tank provided near the ready-mixed concrete production facility to a casting place. Fine aggregate and cement, which are mortar materials,
They can be transported mixed in a fixed ratio or transported separately without mixing.

【0031】[モルタル材料を打設場所に打設する工
程]モルタル材料は、ベルトコンベア2からモルタル生
産設備3に供給される。モルタル生産設備3は、モルタ
ル材料に決められた量の水を添加してモルタルミキサー
8で混練してモルタルを生産する。このモルタルは、生
コンクリートを打設する直前に打設される。いいかえる
と、生コンクリートの下層としてモルタルを打設し、こ
のモルタルが硬化しないときに、モルタルの上に生コン
クリートを打設する。モルタルは、たとえば1〜3c
m、好ましくは約2cmの厚さに打設される。モルタル
を打設して、その上に生コンクリートを打設する時間
は、長くても1時間以内とする。
[Step of Casting Mortar Material to Casting Place] The mortar material is supplied from the belt conveyor 2 to the mortar production facility 3. The mortar production equipment 3 produces a mortar by adding a predetermined amount of water to the mortar material and kneading with a mortar mixer 8. This mortar is cast immediately before casting the ready-mixed concrete. In other words, mortar is cast as a lower layer of ready-mixed concrete, and when the mortar does not harden, ready-mixed concrete is cast on the mortar. Mortar is, for example, 1-3c
m, preferably about 2 cm thick. The time for placing the mortar and placing the ready-mixed concrete on it is within one hour at most.

【0032】モルタル生産設備3は、モルタル材料を貯
溜タンク7に蓄え、モルタルを使用するときにモルタル
ミキサー8で混練することもできる。この方法は、複数
回に打設する量のモルタル材料を、ベルトコンベア2で
輸送する。このため、ベルトコンベア2が生コンクリー
トを輸送しない空き時間をより有効に利用して、モルタ
ル材料を打設場所に輸送できる。それは、ベルトコンベ
ア2の空き時間が長いときは、多量のモルタル材料を打
設場所のモルタル生産設備3に輸送し、空き時間が短い
ときには、少量のモルタル材料を輸送して、ベルトコン
ベア2を、生コンクリートとモルタル材料の輸送に最も
有効に利用できるからである。
The mortar production equipment 3 can store the mortar material in the storage tank 7 and knead it with the mortar mixer 8 when using the mortar. In this method, an amount of mortar material to be cast a plurality of times is transported on the belt conveyor 2. For this reason, the mortar material can be transported to the casting place by effectively utilizing the idle time when the belt conveyor 2 does not transport the ready-mixed concrete. That is, when the idle time of the belt conveyor 2 is long, a large amount of mortar material is transported to the mortar production equipment 3 at the casting site, and when the idle time is short, a small amount of mortar material is transported, and the belt conveyor 2 is transported. This is because it can be used most effectively for transport of ready-mixed concrete and mortar material.

【0033】[生コンクリートを打設場所に輸送して打
設する工程]生コン生産設備1が、決められた割合で、
骨材とセメントと水を混練して、生コンクリートを生産
する。生コン生産設備1は、好ましくは、水の添加量を
少なくした超硬練りの生コンクリートを生産する。ただ
し、生コン生産設備1は必ずしも超硬練りの生コンクリ
ートを生産する必要はなく、ダムコンクリートとして使
用できる混合比の生コンクリートを生産することもでき
る。生産された生コンクリートは、ベルトコンベア2で
もって打設場所に輸送される。超硬練りの生コンクリー
トは、ベルトコンベア2で効率よく高速で輸送できる。
打設場所に送られた生コンクリートは、打設装置でもっ
て打設される。超硬練りの生コンクリートは、振動機等
を使用して隙間ができないように打設される。打設され
る生コンクリートの厚さは、50cm〜1mとする。生
コンクリートを厚く打設することは、打設する効率を良
くするが、硬化したコンクリートの特性を低下させる。
厚く打設された生コンクリート層は、硬化熱で割れやク
ラックが発生しやすくなるからである。したがって、生
コンクリートは、打設効率と硬化したダムコンクリート
の特性とを考慮して、前述の厚さに打設される。
[Process of transporting ready-cast concrete to a casting place and placing it] The ready-mixed concrete production facility 1
Mix concrete with aggregate and water to produce ready-mixed concrete. The ready-mixed concrete production facility 1 preferably produces ultra-hard kneaded ready-mixed concrete with a reduced amount of water. However, the ready-mixed concrete production equipment 1 does not necessarily need to produce super-hard-mixed ready-mixed concrete, but can also produce ready-mixed concrete having a mixing ratio that can be used as dam concrete. The produced ready-mixed concrete is transported by the belt conveyor 2 to the casting site. The super-hardened ready-mixed concrete can be efficiently transported at high speed by the belt conveyor 2.
The ready-mixed concrete sent to the casting site is cast by the casting device. The super-hardened ready-mixed concrete is poured using a vibrator or the like so that no gap is formed. The thickness of the ready-mixed concrete is 50 cm to 1 m. Casting thick green concrete increases casting efficiency but reduces the properties of hardened concrete.
This is because the thickly poured ready-mixed concrete layer is liable to generate cracks and cracks due to heat of hardening. Therefore, the ready-mixed concrete is cast to the above-mentioned thickness in consideration of the casting efficiency and the characteristics of the hardened dam concrete.

【0034】ダムコンクリートは、極めて広い面積に打
設される。したがって、複数の領域に区分して、順番に
前述の厚さに生コンクリートを打設する。生コンクリー
トを打設する前に、生コンクリートの下層として、モル
タルを打設する。たとえば、第1の領域にモルタルを打
設した後、このモルタル層の上に生コンクリートを打設
し、続いて第2の領域にモルタルを打設して、この上に
生コンクリートを打設し、第3、第4・・・の領域に次
々とモルタルと生コンクリートとを打設する。
The dam concrete is cast over a very large area. Accordingly, the concrete is divided into a plurality of regions and the ready-mixed concrete is cast in the aforementioned thickness in order. Before placing the ready-mixed concrete, mortar is placed as a lower layer of ready-mixed concrete. For example, after mortar is cast in the first area, ready-mixed concrete is cast on the mortar layer, then mortar is cast in the second area, and ready-mixed concrete is cast thereon. , Mortar and ready-mixed concrete are placed one after another in the third, fourth,... Areas.

【0035】モルタルは、生コンクリートを打設する前
に打設されるので、モルタル生産設備3は、生コンクリ
ートを打設する前に、モルタルを生産して打設する。そ
して、モルタル生産設備3には、ベルトコンベア2が生
コンクリートを輸送しない空き時間を利用して、モルタ
ル材料を輸送する。
Since the mortar is cast before placing the ready-mixed concrete, the mortar production equipment 3 produces and places the mortar before placing the ready-mixed concrete. Then, the mortar material is transported to the mortar production equipment 3 using the idle time when the belt conveyor 2 does not transport the ready-mixed concrete.

【0036】[0036]

【発明の効果】本発明のダムコンクリートの打設方法と
この打設方法に使用する打設プラントは、生コンクリー
トとモルタルの両方をベルトコンベアで能率よく輸送で
きると共に、モルタルがベルトコンベアに付着するのを
有効に防止できる特長がある。それは、本発明のダムコ
ンクリートの打設方法と打設プラントが、生コンクリー
トを輸送するベルトコンベアを使用して、モルタル材料
を水を添加しない状態で貯溜場所からダムコンクリート
の打設場所まで輸送しているからである。このように、
水を添加しない状態で輸送されるモルタル材料は、従来
のように輸送中に流動することがないので、ベルトコン
ベアの速度を遅くすることなく能率よく輸送できると共
に、モルタルがベルトコンベアのベルトやローラーに付
着するのを有効に防止できる特長がある。
According to the method of placing dam concrete of the present invention and the placing plant used in this method, both ready-mixed concrete and mortar can be efficiently transported by the belt conveyor, and the mortar adheres to the belt conveyor. Has the feature that it can be effectively prevented. That is, the dam concrete placing method and the placing plant of the present invention use a belt conveyor for transporting ready-mixed concrete to transport mortar material from a storage location to a dam concrete placing location without adding water. Because it is. in this way,
The mortar material that is transported without adding water does not flow during transportation as in the past, so it can be transported efficiently without reducing the speed of the belt conveyor, and the mortar can be transported by the belt or roller of the belt conveyor. It has the advantage that it can be effectively prevented from adhering to the surface.

【0037】さらに、本発明のダムコンクリートの打設
方法と打設プラントは、水を添加しない状態でモルタル
材料を輸送しているので、ベルトコンベアが生コンクリ
ートを輸送しない空き時間を有効に利用して能率よく輸
送できる特長もある。水を添加しない状態で輸送された
モルタル材料は、モルタルを打設するときに、打設場所
で水を添加して混練してモルタルとすることができる。
すなわち、モルタル材料は、モルタルを打設するタイミ
ングに関係なく輸送できる。したがって、ベルトコンベ
アを有効に利用して、生コンクリートとモルタルの両方
を能率よく輸送できる。
Further, since the dam concrete casting method and the casting plant of the present invention transport the mortar material without adding water, the belt conveyor can effectively utilize the idle time when the ready-mix concrete is not transported. There is also a feature that can be transported efficiently. The mortar material transported without adding water can be converted into mortar by adding water and kneading the mortar at the place where the mortar is to be poured.
That is, the mortar material can be transported irrespective of the timing at which the mortar is cast. Therefore, both the ready-mixed concrete and the mortar can be efficiently transported by effectively utilizing the belt conveyor.

【0038】さらに、本発明のダムコンクリートの打設
方法と打設プラントは、生コン生産設備で生コンクリー
トを混練して製造し、また、ダムコンクリートの打設場
所で、水を添加していないモルタル材料に水を添加して
混練してモルタルを製造しているので、従来のように、
生コン生産設備でこれ等を交互に切り換えて製造するこ
となく、能率よく、しかも、正確な混合比で生コンクリ
ートを製造できる特長もある。
Further, the method and the plant for dam concrete casting according to the present invention are characterized in that the ready-mixed concrete production equipment mixes and mixes the ready-mixed concrete, and the mortar to which the dam concrete is poured without water is added. Since mortar is manufactured by adding water to the material and kneading it, as in the past,
There is also a feature that ready-mixed concrete can be manufactured efficiently and with an accurate mixing ratio without manufacturing the ready-mixed concrete by alternately switching these components.

【0039】さらに、本発明の請求項2のダムコンクリ
ートの打設方法は、ベルトコンベアで打設場所に移送さ
れた水を添加しないモルタル材料を、打設場所に設けた
貯溜タンクに蓄え、使用するときにモルタル材料を貯溜
タンクから取り出して水を添加して混練して打設してい
るので、生コンクリートの打設を止めることなく、先行
してモルタルを打設して、ダムコンクリートを打設でき
る特長がある。この打設方法は、打設場所に設けた貯溜
タンクに蓄えたモルタル材料を、打設サイクルに合わせ
て混練して打設できるので、生コンクリートの打設能力
を低下させることなく極めて能率よくダムコンクリート
を打設できる特長がある。
Further, according to the method for placing dam concrete of the second aspect of the present invention, the mortar material to which the water is not added and transferred to the placement site by the belt conveyor is stored in the storage tank provided at the placement site and used. When the mortar material is taken out of the storage tank, water is added and kneaded, and the mortar is poured. There is a feature that can be set. According to this casting method, the mortar material stored in the storage tank provided at the casting site can be kneaded and poured in accordance with the casting cycle, so that the dam can be extremely efficiently used without lowering the ready-casting capacity of ready-mixed concrete. The feature is that concrete can be cast.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の実施例のダムコンクリートの打設プラ
ントの概略図
FIG. 1 is a schematic diagram of a dam concrete casting plant according to an embodiment of the present invention.

【図2】図1に示す打設プラントのモルタル生産設備の
一例を示す概略図
FIG. 2 is a schematic diagram showing an example of a mortar production facility of the casting plant shown in FIG.

【図3】モルタル生産設備の他の一例を示す概略図FIG. 3 is a schematic diagram showing another example of a mortar production facility.

【符号の説明】[Explanation of symbols]

1…生コン生産設備 2…ベルトコンベア 3…モルタル生産設備 4…貯蔵タンク 5…計量器 6…ミキサー 7…貯溜タンク 8…モルタルミキサー 9…計量器 DESCRIPTION OF SYMBOLS 1 ... Concrete production equipment 2 ... Belt conveyor 3 ... Mortar production equipment 4 ... Storage tank 5 ... Measuring device 6 ... Mixer 7 ... Storage tank 8 ... Mortar mixer 9 ... Measuring device

───────────────────────────────────────────────────── フロントページの続き (72)発明者 乘京 正弘 東京都千代田区三番町2番地 飛島建設株 式会社内 (72)発明者 鶴見 哲也 東京都千代田区三番町2番地 飛島建設株 式会社内 (72)発明者 山田 隆三 徳島県三好郡池田町白地井ノ久保450番地 の1 Fターム(参考) 2E172 BA03 BA27 CA00 DB11  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Masahiro Norikyo No.2, Sanbancho, Chiyoda-ku, Tokyo Tobishima Construction Co., Ltd. (72) Inventor Tetsuya Tsurumi No.2, Sanbancho, Chiyoda-ku, Tokyo Tobishima Construction Co., Ltd. In-company (72) Inventor Ryuzo Yamada 450F, Inokubo, Shirachi, Ikeda-cho, Miyoshi-gun, Tokushima Prefecture 1F term (reference) 2E172 BA03 BA27 CA00 DB11

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 生コン生産設備(1)で製造された生コン
クリートを、ベルトコンベア(2)でもって、生コン生産
設備(1)からダムコンクリートを打設する場所まで輸送
するダムコンクリートの打設方法において、 生コンクリートを輸送するベルトコンベア(2)を使用し
て、モルタル材料を水を添加しない状態で貯溜場所から
ダムコンクリートの打設場所まで輸送し、ダムコンクリ
ートの打設場所で、モルタル材料に水を添加して混練し
て打設部分に打設することを特徴とするダムコンクリー
トの打設方法。
1. A method for placing dam concrete by transporting ready-mixed concrete produced by ready-mixed concrete production equipment (1) from a ready-mixed concrete production equipment (1) to a place where dam concrete is to be poured by a belt conveyor (2). In, using a belt conveyor (2) for transporting ready-mixed concrete, mortar material is transported from the storage location to the dam concrete placement site without adding water, and the mortar material is transferred to the dam concrete placement site. A method of placing dam concrete, comprising adding water, kneading, and placing the mixture in a placement portion.
【請求項2】 ベルトコンベア(2)でダムコンクリート
の打設場所に移送された水を添加しないモルタル材料
を、打設場所に設けた貯溜タンク(7)に蓄え、使用する
ときに貯溜タンク(7)から取り出して水を添加して混練
して打設する請求項1に記載されるダムコンクリートの
打設方法。
2. A mortar material to which water is not added, which is transferred to a dam concrete placing site by a belt conveyor (2), is stored in a storage tank (7) provided at the casting site, and is stored when used. 7. The method for placing dam concrete according to claim 1, wherein the method is taken out from 7), added with water, kneaded and poured.
【請求項3】 水を添加していないモルタル材料を、空
練り状態で貯溜場所から打設場所まで移送することを特
徴とする請求項1に記載されるダムコンクリートの打設
方法。
3. The method according to claim 1, wherein the mortar material to which water has not been added is transferred from the storage location to the casting location in a kneaded state.
【請求項4】 生コン生産設備(1)で製造された生コン
クリートを、ベルトコンベア(2)でダムコンクリートの
打設場所まで輸送するダムコンクリートの打設プラント
において、生コンクリートを輸送するベルトコンベア
(2)を、モルタル材料を水を添加しない状態で貯溜場所
からダムコンクリートの打設場所まで輸送する搬送手段
に併用すると共に、 ダムコンクリートの打設場所に、水を添加しないモルタ
ル材料に水を添加して混練するモルタル生産設備(3)を
設け、モルタル生産設備(3)を使用して、ダムコンクリ
ートの打設場所において、水の添加されないモルタル材
料に水を添加してモルタルを製造して打設するように構
成してなるダムコンクリートの打設プラント。
4. A belt conveyor for transporting ready-mixed concrete in a dam concrete placing plant for transporting ready-mixed concrete produced by ready-mixed concrete production equipment (1) to a dam concrete placement site by a belt conveyor (2).
(2) is used together with the transport means for transporting the mortar material from the storage location to the dam concrete placement site without adding water, and water is added to the mortar material where water is not added to the dam concrete placement site. A mortar production facility (3) for adding and kneading is provided, and using the mortar production facility (3), water is added to the mortar material to which water is not added at the place where the dam concrete is poured to produce mortar. A dam concrete casting plant configured to be cast.
【請求項5】 モルタル生産設備(3)が、貯溜タンク(7)
とモルタルミキサー(8)とを搭載する自動車である請求
項4に記載されるダムコンクリートの打設プラント。
5. A mortar production facility (3) comprising a storage tank (7).
5. The dam concrete casting plant according to claim 4, which is an automobile equipped with a mortar mixer and a mortar mixer.
【請求項6】 水を添加していないモルタル材料を、空
練り状態で貯溜場所から打設場所まで移送することを特
徴とする請求項4に記載されるダムコンクリートの打設
プラント。
6. The dam concrete placing plant according to claim 4, wherein the mortar material to which water has not been added is transferred from the storage location to the casting location in an empty kneaded state.
【請求項7】 モルタル生産設備(3)が、セメントと細
骨材とを別々に貯溜する貯溜タンク(7)を備える請求項
4に記載されるダムコンクリートの打設プラント。
7. The dam concrete casting plant according to claim 4, wherein the mortar production equipment (3) includes a storage tank (7) for separately storing cement and fine aggregate.
JP10326299A 1999-04-09 1999-04-09 Method for placing dam concrete and plant for use in this method Expired - Lifetime JP4022572B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10326299A JP4022572B2 (en) 1999-04-09 1999-04-09 Method for placing dam concrete and plant for use in this method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10326299A JP4022572B2 (en) 1999-04-09 1999-04-09 Method for placing dam concrete and plant for use in this method

Publications (2)

Publication Number Publication Date
JP2000290968A true JP2000290968A (en) 2000-10-17
JP4022572B2 JP4022572B2 (en) 2007-12-19

Family

ID=14349531

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10326299A Expired - Lifetime JP4022572B2 (en) 1999-04-09 1999-04-09 Method for placing dam concrete and plant for use in this method

Country Status (1)

Country Link
JP (1) JP4022572B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009030375A (en) * 2007-07-27 2009-02-12 Okumura Corp Mortar-concrete carrying method to preparation site of dam bank body
CN108487921A (en) * 2018-04-28 2018-09-04 淮北矿业股份有限公司 One kind being used for underground coal mine large-section underground continuous concrete device and its casting method
CN113818403A (en) * 2021-09-09 2021-12-21 贵阳筑水水利产业发展有限公司 Construction method for constructing concrete hyperbolic arch dam by using excavation materials to replace stock ground

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009030375A (en) * 2007-07-27 2009-02-12 Okumura Corp Mortar-concrete carrying method to preparation site of dam bank body
JP4677622B2 (en) * 2007-07-27 2011-04-27 株式会社奥村組 Conveying method of mortar and concrete to the construction site of dam body
CN108487921A (en) * 2018-04-28 2018-09-04 淮北矿业股份有限公司 One kind being used for underground coal mine large-section underground continuous concrete device and its casting method
CN113818403A (en) * 2021-09-09 2021-12-21 贵阳筑水水利产业发展有限公司 Construction method for constructing concrete hyperbolic arch dam by using excavation materials to replace stock ground

Also Published As

Publication number Publication date
JP4022572B2 (en) 2007-12-19

Similar Documents

Publication Publication Date Title
KR100944970B1 (en) Cement mixing device and manufacturing remicon device using it
CN110424739A (en) A kind of construction method of casting of concrete in mass
JP2000290968A (en) Method for placing dam concrete and placing plant for use therein
KR101310334B1 (en) Batch type mobile mixer truck for concrete construction
JP3192621B2 (en) Method for producing ultralight concrete and ultralight concrete material used for the method
JP3161558U (en) Concrete mixer truck
JP3258141B2 (en) How to cast foam concrete by spraying
JPH10121730A (en) Reduction construction method for crack due to temperature of concrete
KR200337608Y1 (en) Device for manufacturing remicon using powder mixer
JP7295733B2 (en) Method for manufacturing lightweight concrete
JPH0399807A (en) Method and apparatus for processing ready-mixed concrete
JP2000006136A (en) Ready-mixed concrete manufacturing plant
JP2000327445A (en) Mixer pump for continuos production of foamed mortar and continuous production of foamed mortar using the same
JPH11229624A (en) Admixture pouring method for spraying concrete
JP2733719B2 (en) Embankment method
JPH02213599A (en) Frozen aggregate concrete spraying method
JPS63312106A (en) Manufacture of concrete
CN113684744A (en) Pouring and curing method for C100 concrete
KR20010017569A (en) Method for reducing temperature crack in concrete
JPS61102966A (en) Casting of hight weight aggragate material concrete having freeze-resistant melting property
KR20210075444A (en) The drum blade structure of the mixer truck to prevent the concrete separation and discharge
CN104842448B (en) Method for making inorganic compound type cement base plate, cable trough cover plate and sidewalk stepping plate
KR20040100817A (en) Method and device for manufacturing remicon using powder mixer
CN112265105A (en) Concrete pouring process suitable for offshore building construction
JPH05186281A (en) Method for concrete and apparatus therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060126

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20070606

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070612

A711 Notification of change in applicant

Free format text: JAPANESE INTERMEDIATE CODE: A711

Effective date: 20070621

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070621

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20070621

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101012

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101012

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111012

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121012

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131012

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131012

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141012

Year of fee payment: 7

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

EXPY Cancellation because of completion of term