JP2000250975A - Progress schedule generation system - Google Patents

Progress schedule generation system

Info

Publication number
JP2000250975A
JP2000250975A JP17773499A JP17773499A JP2000250975A JP 2000250975 A JP2000250975 A JP 2000250975A JP 17773499 A JP17773499 A JP 17773499A JP 17773499 A JP17773499 A JP 17773499A JP 2000250975 A JP2000250975 A JP 2000250975A
Authority
JP
Japan
Prior art keywords
construction
work
budget
resource
schedule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP17773499A
Other languages
Japanese (ja)
Inventor
Keisuke Sakagami
敬介 阪上
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEING KK
Being Co Ltd
Original Assignee
BEING KK
Being Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEING KK, Being Co Ltd filed Critical BEING KK
Priority to JP17773499A priority Critical patent/JP2000250975A/en
Publication of JP2000250975A publication Critical patent/JP2000250975A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • General Factory Administration (AREA)

Abstract

PROBLEM TO BE SOLVED: To reduce construction cost in working budget by generating a progress schedule in which a machine, labor, etc., are optimized based on the working budget. SOLUTION: This progress schedule generation system is provided with a means 11 to generate the progress schedule showing construction period by every kind of construction from the working budget, a heaping means 13 to sum up kinds of construction and resources by every day based on the process list 12 and a correcting means 14 to change processes by adjusting the kind of construction or terms of the resources of the progress schedule. In this way, the progress schedule is rapidly and correctly generated by automatically converting working budget data. In addition, the progress schedule is easily corrected and the contents of correction is reflected on the working budget. Therefore, an optimal process is determined by optionally changing the processes as confirming amount of the working budget and distribution state of the resources to be required for construction and construction cost is reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、土木工事などの実
行予算案から工事に含まれる各工種の期間を定めた工程
表を作成するための工程表作成システムに関し、特に、
資源の平均化等が簡単に実行可能な工程表作成システム
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a process schedule creating system for creating a process schedule which defines a period of each type of work included in a construction from an execution budget plan for civil engineering and the like.
The present invention relates to a process chart creating system capable of easily averaging resources.

【0002】[0002]

【従来の技術】土木工事などの工事予算を立てる場合に
は、見積もりで作成した積算データである設計書と過去
の工事の実績データ等に基づいて実行予算を作成してい
た。「実行予算」とは、土木工事などの請負工事の各作
業をコスト面からみた具体的な実行計画であり、工事の
開始から終了に至るまでの全期間のコスト管理の目標値
となるものである。実行予算書においては、請け負った
工事を自社において実際いくらでできるかを算出する。
即ち、設計書は、例えば行政機関等によって定められて
いる一般的な材料、機械、単価等を使って作成される
が、実行予算では、自社で実際に使う材料、機械等の単
価を用いて計算することにより、自社のコストを予測す
る。
2. Description of the Related Art When setting up a construction budget for civil engineering work and the like, an execution budget is created based on a design document, which is integrated data created by estimation, and actual data of past construction work. The “execution budget” is a concrete execution plan from the viewpoint of cost for each work of contract work such as civil engineering work, and it is the target value of cost management for the entire period from the start to the end of the work. is there. In the execution budget, the amount of actual contracted work can be calculated by the company.
That is, the design document is created using, for example, general materials, machines, unit prices, and the like, which are determined by an administrative organization or the like. Predict your costs by calculating.

【0003】次に、実行予算を基に、工事に含まれる各
工種の期間を決定する。そして、各工種や資源の投入期
間を表した表が工程表である。従来の工程表作成システ
ムは、実行予算を参考にして工程表を作成するものであ
り、工種別、資源別に手作業で期間等を入力して工程表
を作成していた。
Next, the period of each type of work included in the construction is determined based on the execution budget. Then, a table showing the input period of each type of construction and resources is the process chart. The conventional process schedule creation system creates a process schedule by referring to the execution budget, and manually creates a process schedule by manually inputting a period and the like for each work type and resource.

【0004】[0004]

【発明が解決しようとする課題】上記したような従来の
工程表作成システムでは、実行予算の作成や工事の原価
管理処理と独立して、作成者の経験に基づいて、作業工
程や資源配分を決めて、手作業で工程表を作成していた
ので、手間と時間がかかるという問題があった。また、
工程の変更などの場合に、迅速に工程計画を作成し直す
ことができないという問題もあった。
In the above-described conventional process schedule creation system, the work process and resource allocation are performed based on the creator's experience independently of the execution budget creation and the cost management process of the construction. Decisions were made and the process schedule was created manually, which was troublesome and time-consuming. Also,
There is also a problem that it is not possible to quickly re-create a process plan when a process is changed.

【0005】本発明は、上記従来の問題を解決し、実行
予算を基に、機械、労務などを最適化した工程表を作成
し、人や機械の手待ちなどを最小限に押さえることによ
り、実行予算のコストダウンを図ることができる工程表
作成システムを提供することを目的とする。
[0005] The present invention solves the above-mentioned conventional problems, creates a process schedule in which machines and labor are optimized based on an execution budget, and minimizes the waiting time for humans and machines. An object of the present invention is to provide a process chart creation system that can reduce the cost of an execution budget.

【0006】[0006]

【課題を解決するための手段】上記の課題を解決するた
めに、本発明は、工程表作成システムにおいて、実行予
算から、工種毎の工事期間を示す工程表を作成する工程
表作成手段と、工程表に基づいて、工種および資源の日
毎の集計を行う山積み手段と、指示に応じて工程表の工
種あるいは資源の期日を調整して工程を変更する変更手
段と必要に応じて前記工程表作成手段および前記山積み
手段の出力情報を表示し、かつ工程を変更する前記指示
を入力する入出力手段とを具備することを特徴とする。
In order to solve the above-mentioned problems, the present invention provides a process chart creating system for creating a process chart showing a construction period for each type of work from an execution budget, in a process chart creating system, Based on the process chart, pile means for daily summation of work types and resources, change means for adjusting the work type or date of resources in the process chart according to instructions and changing the process, and creating the process chart as necessary And input / output means for displaying output information of the stacking means and inputting the instruction for changing a process.

【0007】本発明によれば、実行予算データを自動的
に変換して工程表を迅速かつ正確に作成できる。また、
工程表を容易に修正可能であり、修正内容は実行予算に
反映可能である。従って、実行予算の額や工事に必要と
なる資源の分布状況を確認しながら工程を任意に変更し
て最適なな工程を決定することができ、工事コストを削
減できる。
According to the present invention, it is possible to quickly and accurately create a process chart by automatically converting execution budget data. Also,
The process chart can be easily modified, and the details of the modification can be reflected in the execution budget. Therefore, it is possible to determine the optimal process by arbitrarily changing the process while checking the amount of the execution budget and the distribution state of the resources required for the work, and it is possible to reduce the construction cost.

【0008】[0008]

【発明の実施の形態】以下、本発明の実施の形態につい
て、図を参照しながら詳細に説明する。図1は、本発明
の実施の形態の工程表作成システムの構成を示す機能ブ
ロック図である。図1において、実行予算データは、工
事費の見積りを行って設計書を作成するシステムから出
力される設計書データを変換テーブル等を使用して実行
予算データに変換したものを使用するか、あるいは手動
で入力する。
Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is a functional block diagram showing a configuration of a process chart creation system according to an embodiment of the present invention. In FIG. 1, the execution budget data is obtained by converting design document data output from a system for estimating construction costs and creating a design document into execution budget data using a conversion table or the like, or Enter manually.

【0009】工程表作成手段11は、実行予算10に基
づいて工程表12を作成する手段である。山積み手段1
3は、工程表12に基づいて作業員、機械などの所要数
量を算出して、必要資源量を積算し、表示する手段であ
る。工程修正手段14は業界で「山均し」と呼ばれる処
理を行い、工程の期間や必要となる資源量を半自動的に
調整する手段である。工程修正手段14で、工事の必要
資源量を使用可能資源量に調整して、最適な工程表に更
新する。
The process chart creating means 11 is a means for creating a process chart 12 based on the execution budget 10. Piling means 1
Reference numeral 3 denotes a unit that calculates a required quantity of workers, machines, and the like based on the process chart 12, integrates the required resource amounts, and displays the total. The process correcting means 14 is a means for performing a process called "mountain leveling" in the industry and semi-automatically adjusting the process period and the required resource amount. The process modification means 14 adjusts the required amount of resources for the construction to the amount of usable resources and updates the schedule to an optimal schedule.

【0010】工程を修正した結果、実行予算も変化する
場合には、予算修正手段15によって実行予算データが
更新される。最適な工程表に基づいて資源工程表が作成
され、資源の手配計画と最終的な実行予算が出力され
る。なお、このようなシステムは、例えば周知の標準的
なハードウェアを備えたパソコンやワークステーション
において、上記した機能を有するプログラムを実行させ
ることにより実現することができる。
If the execution budget changes as a result of the process modification, the execution budget data is updated by the budget correction means 15. A resource schedule is created based on the optimal schedule, and a resource arrangement plan and a final execution budget are output. Note that such a system can be realized by, for example, executing a program having the above-described functions on a personal computer or a workstation including well-known standard hardware.

【0011】図2は、本発明の実施の形態の工程表作成
システムにおけるデータの関係を示す説明図である。ま
た、図3は、本発明の実施の形態の工程表作成システム
における処理の概要を示すフローチャートである。な
お、図2、図3においては、本発明に関する工程表作成
(原価管理)システム40と関連する積算システム20
および実行予算システム30についても図示している
が、これらのシステムは本発明の実施に必須のものでは
ない。
FIG. 2 is an explanatory diagram showing a data relationship in the process chart creating system according to the embodiment of the present invention. FIG. 3 is a flowchart showing an outline of processing in the process chart creating system according to the embodiment of the present invention. In FIGS. 2 and 3, an integration system 20 related to a process chart creation (cost management) system 40 according to the present invention is shown.
Also, the execution budget system 30 is illustrated, but these systems are not essential to the practice of the present invention.

【0012】積算システム20は、工事の仕様に基づ
き、設計単価DB21の内容を参照して、工事の見積書
あるいは設計書を作成する(S10)。なお、設計単価
DB21は、例えば行政機関などにおいて見積に使用さ
れる名称、単位、単価、単価コードが予め入力されてい
るDBである。積算システム20において作成された設
計書22は、設計書として印刷/出力されると共に、実
行予算作成システム30に入力される。なお、積算シス
テム20を使用しない場合には、例えば手動で設計書3
4を入力する。
The estimating system 20 creates an estimate or a design document for the construction based on the specifications of the construction and referring to the contents of the design unit price DB 21 (S10). The design unit price DB 21 is a DB in which, for example, a name, a unit, a unit price, and a unit price code used for estimation in an administrative organization or the like are input in advance. The design document 22 created in the accumulating system 20 is printed / output as a design document and is also input to the execution budget creation system 30. When the integrating system 20 is not used, for example, the design
Enter 4.

【0013】実行予算作成システム30においては、変
換テーブルDB31および実行単価DB32の内容に基
づき、設計書22に対応する変換テーブル33を生成す
る(S11、S12)。そして、この変換テーブル33
を使用して設計書22を実行予算データ(予算書)35
に変換する(S13)。なお、単価データとして設計単
価DB21あるいは実績単価DB41の内容も参照可能
である。
In the execution budget creation system 30, a conversion table 33 corresponding to the design document 22 is generated based on the contents of the conversion table DB 31 and the execution unit price DB 32 (S11, S12). Then, this conversion table 33
Executes design document 22 by using budget data (budget document) 35
(S13). The contents of the design unit price DB 21 or the actual unit price DB 41 can be referred to as the unit price data.

【0014】変換テーブルDB31に蓄積されるデータ
項目には、変換元単価コード、変換先単価コード、数量
率、単価率、選択方法(標準、更新日付、変換回数)が
ある。変換テーブルDB31には、予め標準的な変換項
目を登録しておく。実行単価DB32は、自社で工事を
行う場合に使用する資源の名称や予想される単価を入力
したDBである。蓄積されるデータ項目には、単価コー
ド、名称、単位、単価がある。実行単価DB32には、
まず代表的な工種毎の標準的な日当り施工数量データを
作成して、予め標準的な工種や自社資源を登録してお
く。変換テーブル33は必要により手動で編集され、変
更内容や変換実績等は変換テーブルDBあるいは実行単
価DB等に反映される。
The data items stored in the conversion table DB 31 include a source unit price code, a destination unit price code, a quantity rate, a unit rate, and a selection method (standard, update date, number of conversions). Standard conversion items are registered in the conversion table DB 31 in advance. The execution unit price DB 32 is a DB in which the names of resources to be used in the case of performing work by the company and expected unit prices are input. The stored data items include a unit price code, a name, a unit, and a unit price. In the execution unit price DB 32,
First, standard daily construction quantity data for each representative type of construction is created, and the standard type of construction and company resources are registered in advance. The conversion table 33 is manually edited as necessary, and the changed contents, the conversion results, and the like are reflected in the conversion table DB or the execution unit price DB.

【0015】実行予算データ(予算書)35は印刷/出
力されると共に、原価管理システム40に入力され、後
述するように、日当たり施工量DB45を参照して、予
算書41に基づいて実際の工事のスケジュールを示す工
程表42が作成され、資源が集中しているところを調整
する(S14〜S21)。即ち、まず工事の各工種の着
工順位を決め、山積みを行う。資源の配分が妥当であれ
ば終了し、そうでなければ、山均し作業を行う。その結
果に基づいて、予算書を表示し、予算が妥当であれば終
了し、そうでなければ山積みと山均しの処理を繰り返
す。そして、完成した工程表42に基づいて工事が実施
される。工事の毎日の進捗状況は日報として入力され、
該日報データに基づいて実績原価が計算される(S2
2)。そしてこの実績原価に基づく実績単価が実績単価
DB44に自動的に蓄積される(S23)。
The execution budget data (budget book) 35 is printed / output and input to the cost management system 40. As will be described later, referring to the daily work amount DB 45, the actual work is performed based on the budget book 41. A schedule 42 showing the schedule is created, and the places where resources are concentrated are adjusted (S14 to S21). That is, first, the start order of each type of construction is determined and piled up. If the allocation of resources is appropriate, the process ends. If not, a leveling operation is performed. Based on the result, a budget document is displayed. If the budget is appropriate, the process is terminated. Otherwise, the process of stacking and leveling is repeated. Then, the construction is performed based on the completed schedule 42. Daily progress of construction is entered as a daily report,
The actual cost is calculated based on the daily report data (S2
2). Then, the actual unit price based on the actual cost is automatically stored in the actual unit price DB 44 (S23).

【0016】図4は、図3のS14の工程表作成処理の
内容を示すフローチャートである。S30においては、
予算書から1項目を読み出す。S31においては、全項
目が読み出されたか否かが判定され、判定結果が肯定の
場合には処理を終了するが、否定の場合にはS32に移
行する。S32においては、読み出した項目が工種項目
か否(資源項目)かが判定され、判定結果が否定の場合
にはS30に戻るが、肯定の場合にはS33に移行す
る。
FIG. 4 is a flow chart showing the contents of the process chart creation process in S14 of FIG. In S30,
Read one item from the budget document. In S31, it is determined whether or not all the items have been read. If the determination result is affirmative, the process ends, but if the determination result is negative, the process proceeds to S32. In S32, it is determined whether the read item is a work item (resource item). If the determination result is negative, the process returns to S30, but if affirmative, the process proceeds to S33.

【0017】S33においては、読み出した工種項目が
日当たり施工量DB45に有るか否かが判定され、判定
結果が肯定の場合にはS34へ、否定の場合にはS35
へ移行する。S34においては、日当たり施工量DBか
ら該当する工種の日当たり施工量を読み出し、施工日数
=(工事のの施工量÷日当たり施工量)を計算して、施
工日数を得る。またS35においては、施工日数を10
日とする。S36においては、求めた施工日数を工種工
程表の対応する工種およびその下位の資源の項目の施工
日数欄に書き込む。施工開始日はすべて工期の最初の日
になる。
In S33, it is determined whether or not the read type of work item exists in the daily construction amount DB45. If the determination result is affirmative, the process proceeds to S34, and if the determination result is negative, S35.
Move to. In S34, the daily construction amount of the corresponding type of work is read out from the daily construction amount DB, and the construction days = (construction amount of construction / construction amount per day) is calculated to obtain the construction days. In S35, the number of construction days is 10
Days. In S36, the obtained construction days are written in the construction days column of the item of the corresponding work type and lower-order resources in the work type process chart. The construction start date is the first day of the construction period.

【0018】図5は、図3のS15の山積み表示処理の
内容を示すフローチャートである。S40においては、
工程表および工程表の基データである予算データを読み
出す。S41においては、各資源毎に予算データの資源
の数量を工程表の日数で割って日当たり資源量を求め
る。S42においては、同一単価項目(資源)の同一日
付の資源量を集計する。S43においては、予算データ
の全項目について処理が終了したか否かが判定され、判
定結果が否定の場合にはS40に戻るが、肯定の場合に
はS44に移行する。S44においては、表示するよう
に選択された資源について各工種の日当り数量の合計値
を例えば棒グラフ等によって表示する。
FIG. 5 is a flowchart showing the contents of the pile display process in S15 of FIG. In S40,
The process chart and the budget data which is the basic data of the process chart are read. In S41, the amount of resources per day is obtained by dividing the number of resources in the budget data for each resource by the number of days in the process chart. In S42, the resource amounts of the same unit price item (resource) on the same date are totaled. In S43, it is determined whether or not the processing has been completed for all items of the budget data. If the determination result is negative, the process returns to S40, but if affirmative, the process proceeds to S44. In S44, the total value of the daily quantity of each type of work for the resource selected to be displayed is displayed by, for example, a bar graph or the like.

【0019】山積み表示においては、資源一覧のカーソ
ルのある項目の山積みが表示され、カーソルを切り替え
ると、山積みも連動して切り替わる。山積みが最大値を
超えている項目は赤色表示され、山均しが必要なことを
示している。山積みは、各作業の資源数量を休日を除く
作業期間で割り、1日当りに必要となる量を工種毎に加
算したものである。山積みの対象となる作業は、作業指
定、業者指定により行う。これにより、作業員などが、
工事全体で何人必要かを見ることができる。他工事も合
わせた山積みを見るには、複数工事の抽出条件を作成す
る。工事の指定は山積みだけでなく工程表、資源工程に
対しても同じように機能する。
In the pile display, the pile of the item with the cursor in the resource list is displayed, and when the cursor is switched, the pile is also switched in conjunction. Items for which the pile exceeds the maximum value are displayed in red, indicating that leveling is required. The pile is obtained by dividing the resource quantity of each work by the work period excluding holidays and adding the amount required per day for each type of work. The work to be piled up is performed by work designation and contractor designation. This allows workers and others to
You can see how many people are needed throughout the construction. To see piles that include other works, create extraction conditions for multiple works. The designation of construction works not only for piles but also for schedules and resource processes.

【0020】次に、工程表の調整処理である山均しにつ
いて説明する。山積みした結果、資源が集中している箇
所については「山均し」を行い、工程を調整して、人、
機械などの資源が無駄に遊ぶことのないような工程を作
成する。また、機械、設備の使用期間を短くし、全体工
期を短くする。そして、その結果としてコストダウンを
図る。山均しにおいては、山積みと各資源の最大値よ
り、最大値を超えない範囲で作業開始日を早めることが
できる場合は開始日を早める。逆に山積みが最大値を超
えている場合は、例えば作業開始日を遅らせたり作業期
間を伸張することによって山積みが最大値内に収まるよ
うに調整する。
Next, a description will be given of mountain leveling which is an adjustment process of a process chart. As a result of piled up, for the place where resources are concentrated, "mountain leveling" is performed and the process is adjusted,
Create a process that does not waste resources such as machines. In addition, the period of use of machines and equipment is shortened, and the overall construction period is shortened. As a result, the cost is reduced. In mountain leveling, if the work start date can be advanced within a range not exceeding the maximum value from the maximum value of the pile and each resource, the start date is advanced. Conversely, if the pile exceeds the maximum value, the pile is adjusted to fall within the maximum value by, for example, delaying the work start date or extending the work period.

【0021】次に、工程の調整方法について説明する。
工程の調整には、まず工事期間の移動および工事期間の
長さの変更(伸張、短縮)がある。また、期間を変更し
た場合に資源の総数量を固定するか日当たり数量を固定
するかの選択操作も可能である。複数の工種が関連し、
他の工種が終わらないと次の工種が実行できない場合な
どには工種の接続を行う。複数の工種から、一つの工種
に接続することはできるが、一つの工種から複数の工種
に接続することはできない。基本的に接続された工種
は、以後の編集に於いてグループとして移動するが、特
定の作業の開始日のみを変更することもできる。ただ
し、接続された各工種は、作業期間を重複して持つこと
はできない。作業期間が重複する場合、以前又は以降の
工種も同時に移動することになる。
Next, a method of adjusting the steps will be described.
Process adjustments include moving the construction period and changing the length of the construction period (stretching, shortening). Further, when the period is changed, a selection operation of fixing the total amount of resources or fixing the daily amount is also possible. Multiple construction types are related,
If the next type cannot be executed unless another type is completed, the type is connected. A plurality of types can be connected to one type, but one type cannot be connected to a plurality of types. Basically, the connected works are moved as a group in the subsequent editing, but only the start date of a specific work can be changed. However, the connected works cannot have overlapping work periods. If the work periods overlap, the previous or subsequent works will also move at the same time.

【0022】工程表上の一つの工種を何回かに分けて行
う場合に、工種の分解を行う。分解数を設定すると、総
数量を均等に分割した数量がゲージに表示される。必要
に応じて各数量の調整を行い、分解を実行する。複数の
工種が接続している場合、一つ目の分割を設定する。従
属する他の工種は、第一工種の分割内容に合わせて分割
される。これにより、一つのサイクルを複数回繰り返す
設定を行うことができる。工種を分解した場合でも、総
数量を各工種が分担して持っているだけであり、基本的
に同じ工種となる。日当り施工数量は各分割数量の総数
量と総日数にて算出するので、分割を行っただけでは日
当り施工数量は変わらない。
When one process on the process chart is divided into several processes, the process is decomposed. When the number of decompositions is set, the gauge displays the quantity obtained by equally dividing the total quantity. Adjust each quantity as needed and perform disassembly. When a plurality of types are connected, the first division is set. Other subordinate works are divided according to the division contents of the first work. Thus, it is possible to perform a setting in which one cycle is repeated a plurality of times. Even when the construction type is disassembled, the total amount is merely shared by each construction type, and basically the same construction type. Since the daily construction quantity is calculated based on the total quantity and the total number of days of each division quantity, the division quantity alone does not change the daily construction quantity.

【0023】工程表に新たに工種を追加することができ
る。追加された工種は予算書にも内訳書として同時に追
加される。工種を追加しただけでは、中身は空であり、
金額は計上されないが、ここに材料などの資源を追加し
ていくことにより、金額を計上することができる。空の
工程表を先に作成し、後から必要な資源を計上していく
といった方法で予算書を作成することもできる。
A new work type can be added to the process chart. The added works will be added to the budget as a breakdown at the same time. The contents are empty only by adding the construction,
Although the amount is not calculated, the amount can be calculated by adding resources such as materials. It is also possible to create a budget by creating an empty schedule first and then accounting for the required resources later.

【0024】図6は、図3のS17の工種工程表調整処
理の内容を示すフローチャートである。S50において
は、表示されている工程表の各工種に対応するバーがマ
ウスによってどのように操作されたかを検出する。S5
1においては、操作されたバーが実作業のものか否かが
判定され、判定結果が否定の場合にはS53に移行する
が、肯定の場合にはS52に移行する。S52において
は、操作されたバーに対応する工種の下位にある資源の
工程(開始日、終了日)を更新(移動、変更)する。
FIG. 6 is a flowchart showing the contents of the process type process table adjustment process in S17 of FIG. In S50, it is detected how the bar corresponding to each process type in the displayed process chart is operated by the mouse. S5
In 1, it is determined whether or not the operated bar is for actual work. When the determination result is negative, the process proceeds to S53, but when the result is affirmative, the process proceeds to S52. In S52, the process (start date, end date) of the resource under the type of work corresponding to the operated bar is updated (moved, changed).

【0025】S53においては、工程表データから更新
された資源の内の1つの項目データを読み込む。S54
においては各項目毎に予め設定されている、資源の総数
量を固定するか日当たり数量を固定するかを示すフラグ
をチェックすBることにより、読み出した資源データは
日当たり数量が固定か否かを判定する。そして、判定結
果が否定の場合にはS55に移行するが、肯定の場合に
はS56に移行する。
In S53, one item data of the resources updated from the process chart data is read. S54
In the above, by checking a flag which is preset for each item and indicates whether the total amount of resources or the amount per day is fixed, the read resource data determines whether the amount per day is fixed or not. judge. Then, when the determination result is negative, the process proceeds to S55, and when the determination result is positive, the process proceeds to S56.

【0026】S55においては、総数量が固定であるの
で、日当たり数量=総数量÷変更後日数を計算すること
によって日当たり数量を算出し、工程表データの日当た
り数量を更新する。工事の材料費など総数量固定の場合
には工程を変更しても実行予算額は変化しない。S56
においては、日当たり資源量が固定であるので、総数量
=日当たり数量×変更後日数を計算することによって総
数量を算出し、工程表データの総数量を更新する。S5
7においては、実行予算データの対応する資源項目の総
数量を更新し、これに伴って予算額も更新する。S58
においては、バーが操作された工種内の全資源項目が更
新されたか否かが判定され、判定結果が否定の場合には
S52に戻るが、肯定の場合には処理を終了する。
In S55, since the total quantity is fixed, the daily quantity = the total quantity / the number of days after the change is calculated to calculate the daily quantity, and the daily quantity in the process chart data is updated. If the total amount is fixed, such as the cost of construction materials, the execution budget does not change even if the process is changed. S56
In (2), since the daily resource amount is fixed, the total amount is calculated by calculating the total amount = the daily amount × the number of days after the change, and the total amount of the process chart data is updated. S5
In step 7, the total amount of the corresponding resource items in the execution budget data is updated, and the budget amount is updated accordingly. S58
In, it is determined whether or not all the resource items in the type of operation for which the bar has been operated have been updated. If the determination result is negative, the process returns to S52, but if affirmative, the process ends.

【0027】次に、工程表の第2の調整方法である山積
み表調整処理について説明する。図7は、図3のS17
の工種工程表調整処理の第2の実施例を示すフローチャ
ートである。図6の調整方法は、工種毎の日付を修正す
ることによって全体の資源量を調整するものであった
が、第2の実施例においては、表示されている特定の資
源の山積み表において最大値をオーバーしている資源を
指定して、直接他の日付に移動させることによって山均
しを行う。
Next, a stacking table adjustment process which is a second adjustment method of the process chart will be described. FIG. 7 is a flowchart showing the operation of S17 in FIG.
It is a flowchart which shows the 2nd Example of the process type process table adjustment process of FIG. Although the adjustment method of FIG. 6 adjusts the total resource amount by correcting the date for each type of work, in the second embodiment, the maximum value is displayed in the stacking table of the specific resource displayed. Leveling is performed by specifying the resource that is over and directly moving it to another date.

【0028】S60においては、選択された資源項目の
山積み表を表示し、更に山均しする日付、資源量および
資源を移動する移動先の日付を入力する。S61におい
ては、複数の工種に同じ資源項目が存在しているか否か
が判定され、判定結果が否定の場合にはS65に移行す
るが、肯定の場合にはS62に移行する。S62におい
ては、使用者が設定可能な自動配分フラグをチェックす
ることにより資源量の自動配分を行うか否かが判定さ
れ、判定結果が否定の場合にはS64に移行するが、肯
定の場合にはS63に移行する。
In S60, a pile table of the selected resource item is displayed, and further, a date for leveling, a resource amount, and a destination date for moving the resource are input. In S61, it is determined whether or not the same resource item exists in a plurality of types of work. If the determination result is negative, the process proceeds to S65, but if the result is positive, the process proceeds to S62. In S62, it is determined whether or not to perform the automatic allocation of the resource amount by checking the automatic allocation flag that can be set by the user. If the determination result is negative, the process proceeds to S64. Shifts to S63.

【0029】S63においては、それぞれの工種の予算
額または施工量により、移動すべき資源量を自動的に配
分する。また、S64においては手動にてそれぞれの工
種に移動すべき資源量を配分する。S65においては、
対応する資源の工程(開始日、終了日)を更新(移動、
変更)する。S66〜S70の処理は図6のS53〜S
57の処理と同一であるので説明は省略する。なお、原
価管理(工程表作成)システムが図6の工程表調整機能
と図7の山積み表調整機能の双方を同時に備えていても
よい。
In S63, the amount of resources to be moved is automatically allocated according to the budget amount or construction amount of each type of construction. In S64, the amount of resources to be moved to each type of work is manually allocated. In S65,
Update the process (start date, end date) of the corresponding resource (move,
change. The processing in S66 to S70 is performed in S53 to S in FIG.
The description is omitted because it is the same as the process in step 57. Note that the cost management (process chart creation) system may have both the process chart adjustment function of FIG. 6 and the stacking chart adjustment function of FIG. 7 at the same time.

【0030】図8〜図14は、予算データから工程表を
作成する一連の処理例を示す説明図である。図8は、予
算データから施工日数を算出する処理を示す説明図であ
る。「予算DB」は例えば予算データベースから特定の
工事に関する予算項目を抽出し、表示したものである。
例えば、図示された工事には工種として「舗装工」、
「法面工」、「側溝工」があり、それの工種の下位「作
業員A」等の単価(資源)項目が存在する。
FIGS. 8 to 14 are explanatory diagrams showing a series of processing examples for creating a process chart from budget data. FIG. 8 is an explanatory diagram illustrating a process of calculating the number of construction days from budget data. The “budget DB” is, for example, one that extracts and displays budget items related to a specific construction from a budget database.
For example, in the construction shown in the illustration,
There are "Slope work" and "Gutter work", and there are unit price (resource) items such as "Worker A" under the work type.

【0031】例えば「舗装工」の施工日数を算出する場
合には、日当たり施工量マスタの同じ工種コードを検索
し、日当たり施工量200m2/日を得る。次に「舗装工」
の数量1200を200で割って、施工日数6日を得る。得ら
れた施工日数は工程DBの該当工種およびその下位の単
価項目の施工日数欄に書き込まれる。工程DBは、予算
DBと対応した工程表データを格納するDBであり、こ
の中から任意のデータを選択し表示可能である。
For example, when calculating the number of construction days for “paving work”, the same construction type code in the daily construction amount master is searched to obtain a daily construction amount of 200 m 2 / day. Next, "paving work"
Divide the quantity 1200 by 200 to get 6 days of construction. The obtained construction days are written in the construction days column of the pertinent work type and the unit price item below it in the process DB. The process DB is a DB that stores process chart data corresponding to the budget DB, and any data can be selected from the DB and displayed.

【0032】図9は、工程の開始日、終了日を決定する
処理例を示す説明図である。施工日数が求まると、次に
工種工程表を画面に表示する。工程表の工程名は予算D
Bから抽出する。工種工程表においては、各工種の工事
期間を工程バー(表右側のハッチングされた横棒)で表
し、初期状態では開始日は同じ日(当処理を行った日)
となっている。使用者は、工程表の工程バーを例えばマ
ウスによって操作することにより、期間の移動等を行
う。
FIG. 9 is an explanatory diagram showing an example of processing for determining a start date and an end date of a process. When the number of construction days is determined, a work schedule is displayed on the screen. The process name in the process chart is Budget D
Extract from B. In the construction process schedule, the construction period of each construction is indicated by a process bar (hatched horizontal bar on the right side of the table). In the initial state, the start date is the same day (the date when this process was performed).
It has become. The user moves the period, for example, by operating the process bar of the process chart with, for example, a mouse.

【0033】複数の作業が関連し、他の作業が終わらな
いと次の作業ができない場合などには、使用者は作業の
接続を行う。また、工程表上の一つの作業を何回かに分
けて行う場合には、作業の分解を行う。更に、工程表に
新たに作業を追加することができる。例えば使用者が図
9に図示するように工程バーを動かしたとすると、例え
ば最初の工種の開始日を当処理を行った日として各工種
の開始日および終了日が算出され、工程表および工程D
Bに書き込まれる。
When a plurality of works are related and the next work cannot be performed until the other work is completed, the user connects the works. In addition, when one operation on the process chart is to be performed several times, the operation is disassembled. Further, a new work can be added to the process chart. For example, assuming that the user moves the process bar as shown in FIG. 9, the start date and the end date of each type of work are calculated, for example, with the start date of the first type of work as the date when this process was performed, and the process table and the process D
B is written.

【0034】図10は、山積み表示処理を示す説明図で
ある。各工種の工事期間が決定/更新されると、各単価
(資源)項目の日当たり資源量を求める。例えば「舗装
工」の「作業員A」は数量が6人であり、施工日数が6
日であるので、日当たり資源量は1人/日となる。次に
同一資源、同一日付毎の資源量を合計する。ワークエリ
ア上で各資源の日付毎の資源量を書き出し、同一日付、
同一単価コードのものを集計する。例えば3月4日の単
価コードA0001(作業員A)の資源量は1+6=7人と
なる。
FIG. 10 is an explanatory diagram showing the pile display process. When the construction period of each construction type is determined / updated, the daily resource amount of each unit price (resource) item is obtained. For example, the number of “workers A” of “paving work” is six, and the number of construction days is six.
Since it is a day, the resource amount per day is 1 person / day. Next, the resource amounts for the same resource and the same date are totaled. Write out the resource amount of each resource on the work area by date,
Aggregate those with the same unit price code. For example, the resource amount of the unit price code A0001 (worker A) on March 4 is 1 + 6 = 7.

【0035】集計結果は、図10下方に図示されている
ように、資源一覧表のカーソルのある項目の山積みが表
示され、カーソルを切り替えると、山積みも連動して切
り替わる。これにより、作業員などが、工事全体で何人
必要かを見ることができる。また、山積みが予め設定さ
れている最大値を超えている項目は赤色表示され、山均
しが必要なことを示している。他工事も合わせた山積み
を見るには、複数工事の抽出条件を作成する。工事の指
定は山積みだけでなく工程表、資源工程に対しても同じ
ように機能する。
As shown in the lower part of FIG. 10, the tally result shows a pile of items with the cursor in the resource list, and when the cursor is switched, the pile is also switched. Thereby, it is possible to see how many workers and the like are required in the entire construction. Items for which the piles exceed the preset maximum value are displayed in red, indicating that leveling is required. To see piles that include other works, create extraction conditions for multiple works. The designation of construction works not only for piles but also for schedules and resource processes.

【0036】図11は、山均し処理を示す説明図であ
る。山積み表示をチェックした結果、例えば作業員の配
分を変更したい場合には、工種工程表の工程バーを操作
することによって、各工種の工事期間の移動/延長/短
縮を行う。山均し作業においては、工程DBおよび予算
DBのデータに基づき工種工程表を生成/表示させ、工
程バーを操作する。例えば図11において、法面工の工
程を前後に延ばして施工日数を8日から12日に延長し
た場合について説明すると、この場合、日当たり資源量
を固定する場合には図12へ、総資源量(数量)を固定
する場合には図13へ移行する。
FIG. 11 is an explanatory diagram showing the mountain leveling process. As a result of checking the pile display, for example, when it is desired to change the distribution of the workers, the operation period of each construction type is moved / extended / reduced by operating the process bar of the construction type schedule. In the mountain leveling work, a process schedule is generated / displayed based on the data of the process DB and the budget DB, and the process bar is operated. For example, referring to FIG. 11, a description will be given of a case where the number of days of construction is extended from 8 days to 12 days by extending the process of the slope work back and forth. In this case, when the daily resource amount is fixed, FIG. When (quantity) is fixed, the process proceeds to FIG.

【0037】図12は、日当たり資源量を固定する場合
の、山均し更新処理を示す説明図である。日当たり資源
量を固定する場合には、工程DBの日当たり資源量は変
更されずに、工種および単価項目の施工日数、開始日お
よび終了日が更新される。この結果は予算DBにも反映
する必要があるので、予算DBの法面工における作業員
Aの数量が12日×6人/日=72人に更新され、金額
も修正される。
FIG. 12 is an explanatory diagram showing a mountain leveling update process when the daily resource amount is fixed. When the daily resource amount is fixed, the number of construction days, the start date, and the end date of the work type and unit price item are updated without changing the daily resource amount of the process DB. Since this result needs to be reflected in the budget DB, the quantity of the worker A in the slope work of the budget DB is updated to 12 days × 6 persons / day = 72 persons, and the amount is also corrected.

【0038】図13は、総資源量を固定する場合の、山
均し更新処理を示す説明図である。総資源量を固定する
場合には、工程DBの工種および単価項目の施工日数、
開始日および終了日が更新されると共に、日当たり資源
量も更新される。例えば法面工における作業員Aの日当
たり資源量は6人/日であるが、更新後は48人÷12
日=4人/日となる。
FIG. 13 is an explanatory diagram showing a mountain leveling update process when the total resource amount is fixed. When the total resource amount is fixed, the number of construction days for the process type and unit price item in the process DB,
The start date and the end date are updated, and the daily resource amount is also updated. For example, the daily resource amount of worker A in the slope work is 6 / day, but after renewal, 48/12
Day = 4 people / day.

【0039】図14は、山均し更新結果の表示処理を示
す説明図である。この例においては、総数量を固定する
場合(図13の続き)について開示する。工程DBが更
新されると、図10における処理と同様の処理によって
山積み表示が行われる。また、必要に応じて予算書も表
示可能である。更に、必要に応じて特定の資源のみにつ
いて、工程を表示した資源工程表を表示させ、かつ修正
することも可能である。
FIG. 14 is an explanatory diagram showing a display process of the mountain leveling update result. This example discloses a case where the total amount is fixed (continuation of FIG. 13). When the process DB is updated, the pile display is performed by the same processing as the processing in FIG. A budget document can also be displayed as needed. Furthermore, it is also possible to display and correct a resource process chart in which processes are displayed only for specific resources as needed.

【0040】以下に、資源工程表の説明をする。資源工
程表は特定の資源についての工程を表示した表である。
工程計画においては、自社の資源をいかに有効に使うか
が重要となる。通常、複数の工事が同時に走る場合が多
く、現場の枠を超えた人員調整が必要となる。複数の工
事の工程、山積み、資源工程を同時に表示し、工程、人
員の調整を行うことができる。他工事も合わせた工程を
見るには、抽出条件の作成にて、現在の工事名表より工
事を選択する。
The resource schedule will be described below. The resource schedule is a table displaying the process for a specific resource.
In the process planning, it is important how to use the company's resources effectively. Usually, a plurality of works are performed at the same time in many cases, and it is necessary to adjust the personnel beyond the site. Multiple construction processes, piles, and resource processes can be displayed at the same time, and the processes and personnel can be adjusted. To view the process that includes other works, select the work from the current work name table when creating extraction conditions.

【0041】資源工程表では、各作業で使用されている
項目について、さらに詳細な計画を立てたり、実際の調
達計画に合わせて数量の調整を行う。調整は、必要とな
る項目に対してのみ行う。詳細計画を立てない場合は、
資源工程を調整する必要はない。資源工程表の最初の状
態は、項目別の山積みを平面化し、一覧表示したもので
ある。バーチャートは資源の所要期間、所要数量を示し
ている。最終的には、調整後の数量にて、月別のコスト
を算出する。
In the resource schedule, more detailed plans are made for the items used in each operation, and the quantities are adjusted in accordance with the actual procurement plan. Adjustments are made only for necessary items. If you do n’t have a detailed plan,
There is no need to adjust resource processes. The first state of the resource process chart is a list of piles for each item, which are flattened. The bar chart shows the required period of the resource and the required quantity. Finally, the monthly cost is calculated based on the adjusted quantity.

【0042】資源工程表の各項目のバーチャート内部に
は資源の所要数量が表示される。資源工程のバーチャー
トは、資源を使用する期間を示している。工程を作成し
た時点では、一つの作業の作業期間と資源の期間は一致
している。一つの作業でのみ使用されている項目は、背
景に作業期間が表示される。基本的には、この作業期間
内で、期間、数量の編集を行う。複数の作業で使われて
いる資源は他の色で表示され、内訳があることを示して
いる。内訳では、指定された資源がどの作業でどれだけ
使われているかが表示される。
The required quantity of resources is displayed inside the bar chart of each item of the resource schedule. The bar chart of the resource process shows a period in which the resource is used. When the process is created, the operation period of one operation and the period of the resource are the same. For the items used only in one operation, the operation period is displayed in the background. Basically, the period and quantity are edited within this work period. Resources used in multiple tasks are displayed in other colors, indicating that they have a breakdown. The breakdown shows how much and how much of the specified resource is used.

【0043】機械などを使う作業の場合、工程表の作業
期間と機械の稼動期間は必ずしも一致するとは限らな
い。特殊な機械を使う場合などには、機械を主体とした
工程を考える必要がある。資源工程では、作業バーのな
かでどれだけ機械を使用するかを計画できる。工程計画
を立てた時点では、資源は平均して必要となる数量が表
示されている。予測される数量に偏りがある場合、数量
の内訳を作成することができる。
In the case of an operation using a machine or the like, the operation period of the process chart does not always coincide with the operation period of the machine. When a special machine is used, it is necessary to consider a process mainly for the machine. In the resource process, you can plan how much machinery you will use in the work bar. At the time of making the process plan, the required quantity of resources is displayed on average. If there is a bias in the expected quantity, a breakdown of the quantity can be created.

【0044】資源工程の変更により、総数量が変わる揚
合は、変更後の数量が予算書に反映される。同じように
材料などを月毎にどれだけ投入するかといった計画を立
てることもできる。資源工程表では、各工事の期間別の
合計数量が表示される。各ケースの内訳を表示する場
合、工事名、作業名が表示される。各資源の調整は、単
一工事の場合と同じ様に各工事、各作業単位に行う。
When the total quantity changes due to a change in the resource process, the changed quantity is reflected in the budget. In the same way, it is possible to make a plan on how much material is to be put in each month. In the resource schedule, the total quantity of each construction period is displayed. When the breakdown of each case is displayed, the construction name and the work name are displayed. Coordination of each resource is performed for each work and each work unit as in the case of single work.

【0045】山積みや資源工程では工事単位でなく、会
社全体での計画を立てることができる。工事名表でのグ
ループ分けによって、監督ごとなど任意の表示が可能で
ある。実行予算システムでは、図示したように、予算書
と工程表は密接に連動する。工程表で編集した内容は、
予算書にも反映され、予算書で編集した内容は工程表に
も反映される。予算書・工程表データは、集計表、工程
表の双方から更新する。
In a pile or resource process, a plan can be made not for each construction but for the entire company. Arbitrary display such as for each director is possible by grouping in the construction name table. In the execution budget system, as shown in the figure, the budget document and the process chart are closely linked. The contents edited in the process chart
It is reflected in the budget document, and the contents edited in the budget document are also reflected in the process schedule. The budget and process schedule data is updated from both the summary table and process schedule.

【0046】次に、手配計画の説明をする。工程表がで
きると、これに基づき材料・労務・機械などを手配する
計画を作成する。手配計画は、山積みを見ながら納入予
定日を設定していく。設定された納入計画は山積み上に
プロットされ、山積みに対しての納入予定を確認でき
る。工事全体で必要となる量を把握し、事前に計画を立
てることにより、より有利な方法で資源を調達すること
ができる。山積みで選択された項目に対して、業者、数
量、納入予定日を設定する。納入予定日が点となって山
積み上に表示される。労務・機械の場合は線で表示され
る。立てられた手配計画は一覧表示される。また、業者
別、月別に集計することができる。
Next, the arrangement plan will be described. When the process schedule is completed, a plan for arranging materials, labor, machines, etc. is created based on this. In the arrangement plan, the delivery date is set while looking at the pile. The set delivery plan is plotted on the pile, and the delivery schedule for the pile can be confirmed. By grasping the amount required for the entire construction and planning in advance, resources can be procured in a more advantageous manner. Set the supplier, quantity, and expected delivery date for the items selected in the pile. The expected delivery date is displayed as a dot on the pile. In the case of labor / machinery, it is displayed as a line. The arranged arrangement plans are listed. In addition, data can be totaled by vendor and by month.

【0047】実行予算立案後は、立てられた実行予算が
工事管理の指針となり、工程の進捗、投入資源のフォロ
ーを行う。立案した実行予算とのずれが生じた場合、常
に変更、軌道修正を行う。変更した内容は、自社実績と
して蓄積され、今後の予算書立案にフイードバックされ
る。
After the execution budget is prepared, the executed execution budget serves as a guideline for construction management, and the progress of the process and the input resources are followed. When there is a deviation from the planned execution budget, change and trajectory correction are always performed. The changed contents will be accumulated as company results and will be fed back to future budget planning.

【0048】上記のように、本発明の実施の形態では、
工程表作成システムが実行予算用データから実行予算と
連動する工程表を作成し、工程表に基づいて山積みを行
い、山積みのデータを山均しにより調整して工程を変更
し、資源の配置を調整して実際のコストを算出し、材料
・労務・機械などを手配する計画を作成する構成とした
ので、工程を最適化することにより、コストダウンを図
ることができる。
As described above, in the embodiment of the present invention,
The operation schedule creation system creates an operation schedule linked to the execution budget from the execution budget data, stacks based on the operation schedule, adjusts the accumulation data by leveling, changes the process, and allocates resources. Since the actual costs are calculated by adjustment and a plan for arranging materials, labor, machines and the like is prepared, the cost can be reduced by optimizing the process.

【0049】[0049]

【発明の効果】以上のように、本発明では、工程表作成
システムを、実行予算と連動する工程表を作成する手段
と、工程表に基づいて山積みを行う手段と、山積みのデ
ータを山均しにより調整して工程を変更する手段とを具
備する構成としたので、予算書と連動する工程表を作成
し、実作業に基づいた無駄のない工程計画により、実行
予算のコストダウンが実現できるという効果が得られ
る。また、資源の配置を調整して実際のコストを算出す
る手段を設けたので、資源の配置が最適化され、機械、
労務などの投入計画により、実行予算のコストダウンが
実現できるという効果が得られる。
As described above, according to the present invention, the process chart creation system includes means for creating a process chart linked to the execution budget, means for stacking based on the process chart, and data for stacking. And a means for changing the process by adjusting the schedule, so that a process schedule linked to the budget can be created, and the cost reduction of the execution budget can be realized by a lean process plan based on actual work. The effect is obtained. In addition, the provision of means for adjusting the resource allocation and calculating the actual cost is provided, so that the resource allocation is optimized,
By inputting labor and the like, there is an effect that the cost of the execution budget can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の工程表作成システムの構成を示す機能
ブロック図である。
FIG. 1 is a functional block diagram showing a configuration of a process chart creation system of the present invention.

【図2】本発明の工程表作成システムにおけるデータの
関係を示す説明図である。
FIG. 2 is an explanatory diagram showing a data relationship in the process chart creation system of the present invention.

【図3】本発明の工程表作成システムにおける処理の概
要を示すフローチャートである。
FIG. 3 is a flowchart showing an outline of processing in a process chart creation system of the present invention.

【図4】図3のS14の工程表作成処理の内容を示すフ
ローチャートである。
FIG. 4 is a flowchart showing the contents of a process chart creation process in S14 of FIG. 3;

【図5】図3のS15の山積み表示処理の内容を示すフ
ローチャートである。
FIG. 5 is a flowchart showing the contents of a pile display process in S15 of FIG. 3;

【図6】図3のS17の工種工程表調整処理の内容を示
すフローチャートである。
FIG. 6 is a flowchart showing the details of a process type process table adjustment process in S17 of FIG. 3;

【図7】図3のS17の工種工程表調整処理の第2実施
例を示すフローチャートである。
FIG. 7 is a flowchart showing a second example of the process flow chart adjustment processing in S17 of FIG. 3;

【図8】予算データから施工日数を算出する処理を示す
説明図である。
FIG. 8 is an explanatory diagram showing a process of calculating the number of construction days from budget data.

【図9】工程の開始日、終了日を決定する処理例を示す
説明図である。
FIG. 9 is an explanatory diagram showing an example of processing for determining a start date and an end date of a process.

【図10】山積み表示処理を示す説明図である。FIG. 10 is an explanatory diagram showing a pile display process.

【図11】山均し処理を示す説明図である。FIG. 11 is an explanatory diagram showing a mountain leveling process.

【図12】日当たり資源量を固定する場合の、山均し更
新処理を示す説明図である。
FIG. 12 is an explanatory diagram showing a mountain leveling update process when the daily resource amount is fixed.

【図13】総資源量を固定する場合の、山均し更新処理
を示す説明図である。
FIG. 13 is an explanatory diagram showing a mountain leveling update process when the total resource amount is fixed.

【図14】山均し更新結果の表示処理を示す説明図であ
る。
FIG. 14 is an explanatory diagram showing display processing of a mountain leveling update result.

【符号の説明】 10…実行予算、11…工程表作成手段、12…工程
表、13…山積み手段、14…工程修正手段、15…予
算修正手段、20…積算システム、21…、設計単価D
B、22…設計書、30…実行予算システム、31…変
換テーブル、32…実行単価DB、33…変換テーブル
DB、35…実行予算データ、40…原価管理システ
ム、41…実行予算、42…工程表、43…実績原価、
44…実績単価DB、45…日当たり施工量DB
[Description of Signs] 10: execution budget, 11: process table creation means, 12: process table, 13: stacking means, 14: process correction means, 15: budget correction means, 20: integration system, 21 ..., design unit price D
B, 22: design document, 30: execution budget system, 31: conversion table, 32: execution unit price DB, 33: conversion table DB, 35: execution budget data, 40: cost management system, 41: execution budget, 42: process Table, 43… Actual cost,
44: Actual unit price DB, 45: Daily construction volume DB

Claims (3)

【特許請求の範囲】[Claims] 【請求項1】実行予算から工種毎の工事期間を示す工程
表を作成する工程表作成手段と、 工程表に基づいて、工種および資源の日毎の集計を行う
山積み手段と、 指示に応じて工程表の工種あるいは資源の期日を調整し
て工程を変更する変更手段と必要に応じて前記工程表作
成手段および前記山積み手段の出力情報を表示し、かつ
工程を変更する前記指示を入力する入出力手段とを具備
することを特徴とする工程表作成システム。
Claims: 1. A work schedule creating means for creating a work schedule indicating a construction period for each work type from an execution budget; a pile-up means for performing daily tallying of work types and resources based on a work schedule; Input / output for displaying output information of the process table creating means and the pile-up means as necessary, and inputting the instruction for changing the process, by changing means for adjusting the type of work in the table or the date of the resource and changing the process if necessary. And a means for preparing a process chart.
【請求項2】前期変更手段の出力に基づき、前記実行予
算を修正する予算修正手段を設けたことを特徴とする請
求項1記載の工程表作成システム。
2. The system according to claim 1, further comprising a budget correcting means for correcting said execution budget based on an output of said changing means.
【請求項3】前記入出力手段は、工種毎の工事期間を表
示した工程バーの操作によって、工事開始日あるいは工
事終了日を変更する情報を入力する手段を含むことを特
徴とする請求項2記載の工程表作成システム。
3. The system according to claim 2, wherein said input / output means includes means for inputting information for changing a construction start date or a construction end date by operating a process bar displaying a construction period for each construction type. Process schedule creation system described.
JP17773499A 1998-12-28 1999-06-24 Progress schedule generation system Pending JP2000250975A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP17773499A JP2000250975A (en) 1998-12-28 1999-06-24 Progress schedule generation system

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP37222998 1998-12-28
JP10-372229 1998-12-28
JP17773499A JP2000250975A (en) 1998-12-28 1999-06-24 Progress schedule generation system

Publications (1)

Publication Number Publication Date
JP2000250975A true JP2000250975A (en) 2000-09-14

Family

ID=26498175

Family Applications (1)

Application Number Title Priority Date Filing Date
JP17773499A Pending JP2000250975A (en) 1998-12-28 1999-06-24 Progress schedule generation system

Country Status (1)

Country Link
JP (1) JP2000250975A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002123577A (en) * 2000-10-17 2002-04-26 Sangikyou:Kk System and method for supporting construction
JP2002373013A (en) * 2001-06-14 2002-12-26 Asprova Corp Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
JP2004355526A (en) * 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
JP2007334673A (en) * 2006-06-15 2007-12-27 Takenaka Komuten Co Ltd Flowchart creation device, method, and program
JP2008522316A (en) * 2004-12-03 2008-06-26 ステート オブ オレゴン アクティング バイ アンド スルー ザ ステート ボード オブ ハイヤー エデュケーション オン ビハーフ オブ ザ ユニヴァーシティ オブ オレゴン System and process for job scheduling that minimizes construction costs
JP2017194274A (en) * 2016-04-18 2017-10-26 日立Geニュークリア・エナジー株式会社 Disposal process management device and disposal process management method
CN116128273A (en) * 2023-04-17 2023-05-16 清云小筑(北京)创新技术有限公司 Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002123577A (en) * 2000-10-17 2002-04-26 Sangikyou:Kk System and method for supporting construction
JP2002373013A (en) * 2001-06-14 2002-12-26 Asprova Corp Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
JP2004355526A (en) * 2003-05-30 2004-12-16 Toshiba Corp Job navigation system and its method
JP2008522316A (en) * 2004-12-03 2008-06-26 ステート オブ オレゴン アクティング バイ アンド スルー ザ ステート ボード オブ ハイヤー エデュケーション オン ビハーフ オブ ザ ユニヴァーシティ オブ オレゴン System and process for job scheduling that minimizes construction costs
JP2007334673A (en) * 2006-06-15 2007-12-27 Takenaka Komuten Co Ltd Flowchart creation device, method, and program
JP2017194274A (en) * 2016-04-18 2017-10-26 日立Geニュークリア・エナジー株式会社 Disposal process management device and disposal process management method
CN116128273A (en) * 2023-04-17 2023-05-16 清云小筑(北京)创新技术有限公司 Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint

Similar Documents

Publication Publication Date Title
US5016170A (en) Task management
JPH09268760A (en) Schedule control support system
US20090043635A1 (en) Scheduling chart creation system and program for the same
WO2019130712A1 (en) Manufacturing plan formulation assistance system
US20040039585A1 (en) Managerial decision support system and method
JP2011170496A (en) Device and method for supporting plant construction plan
JP2000250975A (en) Progress schedule generation system
KR19990088345A (en) Construction management system and construction management method
JP4966831B2 (en) Material requirements planning device, material requirements planning method, and material requirements planning program
JP2002373013A (en) Production scheduling method, program for computer to execute the same method and computer-readable recording medium with the program recorded thereon
US20080243269A1 (en) Method and System for Scheduling Reinforcing Bars for Use in Reinforced Products
JPWO2016129502A1 (en) Equipment plan support system, equipment plan support method and program
CN110968751A (en) Dynamic display method and device for engineering project capital curve
KR100945523B1 (en) On-line construction management method
JPH0793408A (en) Method and device for generating process planning
JP3262522B2 (en) Civil engineering cost control device
JP2017049863A (en) Gcm in-administration operation integral management technology
Fan et al. Cost-based scheduling method using object-oriented approach
JP2002123572A (en) Device and system for construction cost management
KR101171214B1 (en) Activity Process Management System
JP4831882B2 (en) Process management system using network
JPH02236359A (en) Work stage planning and construction schedule control system
JP7516851B2 (en) Process management support system, process management support method, and process management support program
JP4972720B2 (en) Construction cost management apparatus and method
JP2004234338A (en) Material procurement and construction plan integrated project management system

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060623

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090224

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090427

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20090723